[0:15] Hello. [0:16] Thank you. [0:16] We are pleased to present you [0:18] our project for Beaconsfield's new cultural centre. [0:21] I have to tell you that this project is particularly close to my heart. [0:24] I'm a Beaconsfield resident myself, [0:27] so I can tell you that I've often enjoyed the site, its [0:30] activities, its structures, its access to water as well. [0:35] It is already a unique and rather exceptional place. [0:39] So to add the marina site, as well as adding [0:43] cultural activities, make it a real opportunity [0:46] to make it an inspiring site that will become even more [0:48] a place of discovery and entertainment for citizens. [0:52] So, all along the West Island, the Lakeshore scenic parkway [0:56] is punctuated by slowdown points to [0:58] observe the attractions, including the Pointe-Claire village [1:01] and Beaurepaire village, a little to the West, in Beaconsfield. [1:05] Located between these two commercial hubs, the project becomes another of these places, [1:09] which, this time, comes to identify [1:11] and reinforce the civic core with its proximity to City Hall [1:14] and the surrounding sports facilities and green spaces. [1:20] So, on Beaconsfield [1:20] Boulevard, on the project, we can see a first pedestrian [1:23] crossing opposite City Lane. Then another crossing [1:29] opposite Heroes' Park which leads to the centre of the site. [1:32] And then to the East, the start of the civic core is marked by the axis leading [1:37] to the North of Beaconsfield, with its bike path, which is identified [1:41] here in red. So, with the project visible from the street, [1:45] and located in the centre of the site, it becomes a focal point [1:48] in a circulation loop where active transportation is encouraged [1:52] and leads users to discover the trails [1:55] and the new centre that is centrally placed. [1:59] So I'll leave you to it, Annie. [2:01] Good evening. [2:04] Like this? Yes. [2:05] So the new cultural centre project is [2:09] a real catalyst for the creation of a cultural landscape park in Beaconsfield. [2:14] Following the annexation of the existing park [2:18] to the marina site, we positioned the building [2:23] astride the water line that currently separates them [2:27] and roughly in the centre of the park. [2:31] The cultural centre and the park are designed [2:34] in interrelationship thanks to a detailed reading of the landscape [2:37] and an interpretation of the context and its history. [2:42] First of all, we identified and reinforced four landscape strips [2:45] that run parallel to the riverbank as far as Beaconsfield Boulevard, [2:51] and which in fact reveal [2:53] the landscape on a territorial scale and the natural topography of the site. [2:58] So these landscape waves each have [3:01] their own characteristics and purposes. [3:03] First of all, the shoreline strip. [3:14] ...(inaudible)... Pardon. [3:23] These landscape strips [3:24] each have their own characteristics and purposes. [3:26] First of all, the shoreline strip which is conducive to contemplation, [3:31] the grassy plain, [3:35] the grassy plain, [3:36] which is perfect for gatherings, the forest canopy [3:40] that allows discoveries, and the urban filter that welcomes citizens. [3:45] Human occupation [3:48] Human occupation and its history on the site is marked, [3:50] for its part, by tracings that are perpendicular to the street. [3:54] The tracings of three former [3:56] agricultural plots can still be seen in the lines of trees, [4:00] the paths leading to the lake and the docks entering the water. [4:03] A ditch that directs water away from the roadway... [4:06] ...(inaudible)... [4:09] the road to the lake [4:11] also forms part of these tracings. [4:14] In this way, we have identified and strengthened three landscape lots. [4:18] The historic lot on the left, which remains virtually intact. [4:22] The site of the former Centennial House, if it were to be demolished, [4:26] could be marked by the construction of a loose roof [4:29] that would become the park's gazebo and would provide a stage for gatherings. [4:34] In the centre, we have the wet lot which supports biodiversity. [4:39] It is characterized by a sequence of gardens [4:43] that extend to the [4:45] vegetated riverbank and replaces the existing ditch. [4:49] And finally, the community lot on the right-hand side, to the East [4:52] is characterized by the developing of a large open space [4:56] that descends from the boulevard to Lake Saint-Louis, [4:59] creating a sequence of open multipurpose spaces [5:03] for the community, known as the Heroes' Esplanade. [5:07] We also propose that [5:09] the new park chalet be integrated into this lot, in the forest canopy. [5:14] The waves and landscaped plots weave together a web [5:17] where nature, culture, landscape, [5:20] history and community come together. [5:24] On the longitudinal section [5:26] of the site, you can appreciate the natural topography [5:29] which descends from Beaconsfield Boulevard down to Lake Saint-Louis. [5:34] The centre is registered in the tree canopy. [5:38] We are proposing a single-level centre to encourage [5:42] conviviality and encounters, and also to create a public space that will ensure [5:48] the fluidity of community life between the interior spaces and the park. [5:53] Covered [5:54] by a large, welcoming, slightly sloping roof, [5:57] the cultural centre opens out onto the landscape. [6:02] The building's layout blends into the trees' canopy. [6:06] It unfolds organically, skirting around the existing trees [6:10] to preserve them, creating a configuration with several branches [6:14] that form together semi-open courtyards and an enclosed courtyard. [6:19] The branch that remains outside the forested area to the East [6:22] marks the building from Beaconsfield Boulevard. [6:26] This location provides a volumetric shape to the building [6:29] that is inviting and united with the landscape. [6:33] On the boulevard side, its arched shape welcomes residents. [6:38] On the park side, the courtyards bring the vegetation into the heart of the building [6:42] and open up views over the landscape. [6:47] The branch configuration also creates a welcoming heart [6:51] at the centre of the building, where the new paths [6:54] and the various public spaces in the park converge. [6:58] A real network of walkways linking the boulevard, [7:02] the cultural centre, the park and the lake, all created for the community. [7:10] The topography, which slopes down towards the lake, [7:12] creates a height difference between the main entrance, [7:15] on the boulevard side, and the courtyards facing south. [7:19] We even see the wooden platform courtyards with steps [7:22] integrated into the topography that link the interior level and that of the site, [7:26] which is also being reworked to soften the transition. [7:30] These courtyards are extensions of the cultural centre to the outside world, [7:34] but they are also welcoming for all park users. [7:39] This view from the riverside promenade shows how [7:42] the cultural centre opens generously [7:45] on the landscape with its inviting curves [7:48] which are partially covered by the overhangs of the large roof. [7:52] In the foreground, you can also see the play area, [7:55] which has been relocated close to the building. [8:00] For the [8:00] landscaping and immediate surroundings of the building, [8:05] they incorporate different areas of nature and uses of greenery. [8:10] On the main entrance side, in the urban filter, [8:13] a large forecourt has been laid out at the entrance to the esplanade. [8:18] It is paved with light-coloured cobblestones and includes planting islands. [8:23] It welcomes people arriving either by bike [8:26] or on foot from the boulevard or from the car parking, [8:30] and who are heading for the cultural centre or the park. [8:34] The forecourt can also be a gathering space [8:37] where various community events can be held. [8:40] It can become a market, for example: [8:41] public market, book market, outdoor expositions, [8:44] and other events can happen here too. [8:49] A green car parking has been created in continuity with the forecourt. [8:53] Its access and exit are separate from the access [8:57] and exit for vehicles going down to the marina. [9:03] In the [9:03] trees' canopy, so just on the left of forecourt, [9:06] on the image, the rain garden sequence [9:09] begins to descend towards the riverbank, skirting the building. [9:13] Then, on the park side, perennial gardens adorn the courtyards [9:18] and the interior spaces, including the library's reading areas. [9:21] These gardens create a welcoming area between the park and the cultural centre. [9:27] In continuity with the branch, [9:28] which asserts itself in the esplanade to the right, in the open space, [9:32] another gathering space is defined to the South. [9:38] So, in this view, from Beaconsfield Boulevard, [9:40] we can see the foreground's landscaping at the forefront [9:44] with its planted islands and integrated benches, and we can also see [9:48] the extension of the esplanade down to the water. [9:53] The new cultural centre, with its arched layout [9:57] and its wood cladding is warm and welcoming. [10:01] Its scale is both civic, [10:03] by extending into the landscape, and friendly, [10:06] with its template that is appropriate to the surrounding context. [10:10] Also visible in this image, in the corner of the building, [10:14] is the art studio that reveals some of the centre's activities. [10:19] The main entrance is marked [10:21] by a wide overhang on the large roof. [10:25] As we approach, we can see Lake Saint-Louis. [10:28] and adjacent to the entrance, [10:32] a large display case showing the artistic work created at the centre. [10:37] In terms of program organization, the branch configuration [10:41] provides a natural separation between the program zones. [10:47] The colour diagram on the left shows how they are organized. [10:51] In yellow is the reception area, which brings [10:54] together all the programmatic zones. It opens onto [10:59] the terrace of the bistro, which can be seen in the actionometry drawing on the right. [11:04] In red, [11:05] we have the animation branch which is installed in the branch, therefore outside the forested area. [11:11] In green, the library, which is housed in two other branches [11:15] and organized over three courtyards. And in orange, the administrative sector [11:21] which is in the branch that closes over the courtyard. [11:24] The cultural centre is accessible to all, from both [11:28] Boulevard Beaconsfield and the park. Inside the centre, [11:32] the central hall provides easy access [11:36] and quickly to all programmatic zones. [11:40] The main entrance opens onto the hall. [11:43] It's a welcoming, open and versatile space. [11:47] On the plan, we can see the light grey areas that identify the circulation routes [11:51] from the hall, which are fluid throughout the building. [11:55] The service counter is positioned close to the entrance. [11:58] It is welcoming to the public and allows the staff to [12:01] have an overview of all the centre's activities. [12:05] In the animation branch, [12:07] the branch on the right, are grouped together near the entrance to the meeting rooms, [12:12] the art studio and the computer laboratory. [12:16] The multipurpose hall is positioned at the other end of this branch, [12:20] so that when it is not in black box mode, it opens onto [12:25] the esplanade and offers a view of Lake Saint-Louis. [12:30] The bistro is adjacent to the multipurpose hall. [12:33] and is a continuation of the hall with its magazine corner and terrace. [12:38] A movable partition and an entrance from the terrace [12:42] allow the bistro to be open outside opening hours [12:45] of the centre. [12:47] The library's new releases displays are visible [12:50] and accessible from the hall, encouraging people to enter. [12:56] First of all, we discover the pre-school section [12:59] which benefits from the natural light of the interior courtyard and of [13:03] a secure outdoor play area. [13:08] The adjacent youth [13:09] section is located in the central branch. [13:13] It opens onto the activity room, which is located a little lower down [13:18] thanks to the difference in ground levels, allowing the creation of tiered seating. [13:24] These two areas can also be separated by a movable partition. [13:28] A controlled access to the outside, near the youth section [13:32] which is visible from the reception desk, allows children to [13:36] to join the nearby playground. [13:40] The adult and [13:41] young adult sections occupy the West branch. [13:45] Their reading areas share a private outdoor terrace. [13:50] Their study rooms [13:51] are housed in a space that also includes a breastfeeding area [13:56] and family washrooms serving the adjacent pre-school area. [14:01] The library can also be closed off outside [14:03] opening hours thanks to a partition separating it from the hall. [14:08] And finally, the administrative sector; [14:11] it extends around the inner courtyard and creates a loop [14:15] with the library. [14:19] In this view, from the hall, [14:21] we can appreciate the natural light [14:25] which is filtered through the tree canopy and bathes the interior space. [14:29] You can also see the views towards the landscape. [14:33] It is also apparent the fluidity of the interior space [14:37] which is naturally subdivided by courtyards. [14:41] On the left is the terrace of the bistro [14:43] which is adjacent to the youth section, and further, [14:47] the adult and young adult section. [14:51] Skylights punctuate the circulation [14:53] throughout the different areas of the library. [14:57] The ceilings and soffits of the eaves [15:00] are both clad in wood paneling to ensure [15:03] the continuity, [15:04] especially the visual continuity, between the interior and exterior spaces. [15:09] We can also see the structure's slender, round columns [15:12] that accentuate the desired fluidity of the spaces. [15:17] So we can already mention that we opted for a steel structure, [15:21] which allows for greater ranges than a wooden structure. [15:23] Therefore, a greater versatility of space and a flexibility [15:27] that is actually even more sustainable. [15:29] This cross-section shows [15:33] the large sloping roof which forms protective soffits [15:36] on the entrance side and provides protection from the sun on the south side. [15:43] On the right is the hall, and on the left is the youth section [15:46] and the activity room in continuity, which is [15:49] lower down with its bleachers. [15:52] And we see here a view of the two spaces. [15:57] It should also be noted that coloured flexible floor coverings identify [16:01] the different areas of the library and that the acoustic quality [16:05] of the spaces is ensured by the treatment of the ceilings. [16:08] I'm going to hand over to Philippe, who is going to talk about the integration [16:11] of technical aspects and sustainable development strategies. [16:17] So I continue. Here, on the elevation. [16:19] So you can see the ...(inaudible)... sloping from [16:21] the roof which exposes the green roof. [16:24] On the facades, we notice the wood cladding, [16:26] which adds a warm, integrated feel to the park, [16:29] as well as being a local and renewable material. [16:32] The openings are more focused on the North side, [16:35] and then open up more on the south side, towards the park. [16:40] So, the technical cut [16:41] exposes that it is made up of fairly straightforward components [16:45] that make it easy to integrate systems. [16:48] It also illustrates well the continuity between inside and outside. [16:53] It can be seen that the natural level of the site [16:55] has been slightly altered, [16:58] which allows to be adapted to the interior, facing the terraces and the platforms. [17:03] The radius of the trees of 4.5 metres and over is therefore retained. [17:07] So we are further improving the condition around the trees [17:11] by making a straight excavation with foundation walls ...(inaudible)... that are insulated [17:16] to give the roots more room too. [17:19] The view from the terrace shows the bistro terrace with its courtyard [17:24] which is a covered area [17:25] also becomes the entrance accessible from the park side. [17:29] We can appreciate the openness, the protected areas, [17:32] the connection with nature, all to create inspiring and [17:35] inviting spaces. [17:37] In terms of the structure, [17:38] it is essentially a large inclined plane that accommodates [17:42] the different heights in terms of programmatic needs. [17:46] On one side, with the hall, with the administration, at a more modest height, [17:50] and a sunken roof to create a large drainage basin. [17:54] And one the other side, [17:55] the roof is raised to accommodate the multipurpose room [17:59] but also to accommodate a mezzanine mechanical [18:02] room above the technical areas. [18:06] So, in this mechanical room, we find the ventilation, which includes [18:10] heat recovery systems [18:11] via a thermal wheel with a ground-coupled heat exchanger. [18:15] The ventilation is connected to fan coil units [18:18] that use aerothermal energy for flexibility of use [18:20] to adapt to different locations. [18:23] And, especially, the fan coil units are installed in the ceiling space [18:26] enclosed spaces, [18:28] to allow for a greater architectural flexibility and [18:30] promote acoustics. [18:35] Then, in terms of sustainable development, [18:37] therefore, we are focusing on energy efficiency [18:39] as I've just described, but also on performance [18:42] of the tightly sealed envelope and a well-insulated envelope, [18:47] as well as a triple glazing on the north side and double glazing on the south side. [18:51] We are also focusing on several passive strategies, including solar control. [18:55] So, with the natural canopy of trees, with full daylight curtains, vertical [18:58] sunshades, roof overhangs, [19:00] and even the geometry creates shadows and also allows [19:04] the natural ventilation of each individual branch. [19:07] The focus is also on water management strategies [19:10] with ditch detour facing the rain gardens [19:14] which permits water filtration before it is discharged [19:17] into Lake Saint-Louis to improve water quality. [19:20] There are vegetated ...(inaudible)... and then a bioretention basin for the parking lot [19:25] and also a green roof to reduce heat islands, [19:29] to absorb water [19:30] and for the irrigation of the building. [19:33] So the aim is to design biofilms that [19:36] enhances biodiversity while integrating the City's cultural ecosystem. [19:42] So, the [19:42] building itself is a catalyst for the park's development, [19:46] allowing the discovery of the site through new routes [19:49] where are introduced new opportunities for use. [19:52] These include, notably, sculpture gardens, relaxation areas [19:56] and edible gardens, but also more active areas [19:59] with play areas, walking and cross-country ski trails. [20:02] And then, finally, the front forecourt becomes a public gathering place. [20:07] Contrasting with the space in front, [20:10] the space behind becomes [20:13] so contrasted to ensure that the cultural centre [20:16] becomes, in a way, the keystone of the park [20:19] which, on one hand, welcomes citizens to cultural spaces, [20:23] and, on the other, shows its great openness to nature for all. Thank you. [20:42] OK, I'll start with a question [20:46] which is not architectural, but a question of estimation. [20:52] We turn to electromechanics. [20:55] So, in the estimates, item D-20, which is estimated at 108,000, [21:00] seems very low to include the scope of the work [21:03] plumbing appliances, domestic networks and domestic water, [21:07] sanitary drainage networks, rainwater drainage networks. [21:10] Therefore, we would ask you to please clarify the nature of this network, [21:13] according to the proposal, in order to justify the amounts submitted. In item 30-50, [21:19] you have an estimate of 477,000, which also seems [21:23] very low for the item that includes heat pumps. [21:26] So, refrigeration, boiler, heating, recovery system, [21:30] as we've just seen in your drawings. [21:32] Here again, you need to clarify your choice of systems [21:35] as well as the heating capacities in order to justify the amounts submitted. [21:40] Post 50-10, I'm sorry, it's not very... [21:43] This is not very interesting [21:45] but we will discuss more interesting things afterwards. The estimate of 219,000, [21:49] which also seems very low for the scope of the work [21:51] which includes underground connections for the supply transformer, [21:56] we ask you again to justify the amounts. [21:59] And, finally, the 50-30 position, [22:01] which has an estimate of just 69,000 for the scope of the work, [22:05] which includes intercom, wifi, general call systems, etc., etc. [22:11] So, to justify these amounts which seem low [22:14] and perhaps tell us how you plan to create the ground-coupled heat exchanger [22:17] while the level of the bedrock is in fact very high on the site. [22:22] In fact, I will begin, and then... So, indeed, [22:26] we recognize that there are discrepancies with the presentation. [22:29] First, [22:30] when we assessed the costs, there was not the same breakdown [22:33] and we had a slightly different breakdown [22:36] compared with this one. So our gaps were not [22:38] as substantial as what we saw in the report, [22:41] but we continued the analysis with this to see that, indeed, [22:46] there are certain gaps and there are certain amounts [22:48] that we recognize will have to be enhanced [22:51] before getting into the technical details. [22:52] So I'm just going to say that, in fact, we took a good look at the estimate in [22:57] an integrated and global manner and we have margins within [23:01] other places where we can accommodate [23:05] budget adjustments, where necessary, to electromechanical systems. [23:10] So, we've also made provision for the systems [23:13] as required by the program, tried-and-tested and fairly simple systems, [23:16] which allows for a budgetary rationality that works. [23:20] So, maybe, I can let you mention some points in the most [23:24] technical aspects, including the ground-couple heat exchanger and others... [23:29] In terms of the capacity of the VRF [23:33] systems, we calculated approximately 25 tonnes of air conditioning [23:38] which will be made with condensers, several condensers and several [23:41] systems, evaporators that will be decentralized in the building. [23:46] The ground-couple heat exchanger isn't very hollow, it just has to be under the ground. [23:52] to benefit from the cold of the ground, in fact, [23:55] to take advantage of [23:59] free air conditioning. [24:04] And if I [24:04] can maybe complete, since it's about the budgets. [24:07] We took a good look [24:09] at the budgetary envelope and we're very comfortable with it, [24:11] precisely with budget items where we know that [24:13] there were certain places where we had certain provisions [24:16] for the envelope, which were quite [24:18] generous, where we have room to adapt. [24:23] I do not know if you would want [24:24] precisions, because... there are certain areas... [24:28] Curtain walls, for example, which are almost, but not quite, double the price. [24:35] We overestimated them. So why? [24:37] Because curtains really are a big difference. [24:40] There's also the exterior layout, [24:43] we leave the minimum zone that was requested. [24:47] So we're getting out of the budget. What was mentioned [24:52] already in the presentation, [24:56] the presentation of the project, is the landscaping, [24:59] there is a budget allocated, but, depending on the project chosen, [25:04] there will be [25:06] possibility of seeing how it can be increased, [25:08] but there are ways of avoiding all these elements. [25:12] So there's money to be taken from there too. [25:14] Well, actually, balanced, because we realized that our architecture budget [25:18] was lower than the budget... [25:22] almost a million, I think. Yes. [25:25] So it's at site level. So some of the costs are lower. [25:28] There are a lot of things [25:29] that have been done more on the site, which will also have to be calibrated. [25:33] In the end, [25:35] probable deviation ...(inaudible)... [25:40] We understand that you are confident that you will be able to do ...(inaudible)... [25:44] That's because there's a budget. [25:46] We have noted that your envelope and superstructure are indeed [25:50] higher [25:50] but on the other hand, it's justified by the fact that you have curtain- [25:53] walls. No need to sacrifice curtain walls [25:56] with segments all the same. [26:00] No, that, that's not part of it. [26:02] In fact, during the development of the project, we explored the idea of [26:05] triple glass throughout and wooden curtain walls. [26:09] We have reduced some of these elements [26:11] which were not kept, [26:12] but the amounts have remained fairly high in curtain walls, for example. [26:15] There really is a lot of money in curtain walls. [26:20] [26:23] [26:26] I will have two questions [26:27] that are going to be about the captaincy, [26:30] the marina and their functions. [26:33] Can we have the site [26:35] plan, please? [26:39] Yes. Perfect, thank you. [26:40] I note that you have placed [26:41] the captaincy on the eastern side of the project, [26:46] with pedestrian access, [26:50] with the Esplanade of Heroes and, above all, the vehicle handling area. [26:56] I'd like you to explain... [26:59] I'd like you to explain the justification for a road on the east side, [27:04] considering there is a great deal of cross-fertilization between activities [27:09] in what could be called the Esplanade of Heroes [27:11] and the handling area. [27:16] What we have [27:16] positionned is the park chalet. I do not know if the park chalet and [27:19] and the captaincy are the same because... OK, it is the same thing. [27:23] Because there was also kayak renting with [27:26] perhaps a smaller shelter on the side that could be to the West, [27:31] but for the moment, [27:35] it's part of the mandate to be developed [27:37] because it really is an overall plan. [27:39] We've positioned it here, but it could move to the other side. [27:42] [27:43] [27:45] The yellow passage is also visible. The yellow passage, [27:49] actually, which is almost a pedestrian crossing of a narrower area. So you can see [27:53] that many of the activities will be located further south, towards the water. [27:58] On the other hand, the link with the new cultural centre would be much more... [28:04] much more [28:04] spaced out and activities would take place more to the South. [28:08] So there really is a central axis [28:10] through the park, through the axis here. [28:16] [28:19] [28:21] Thank you for your presentation. [28:23] I understand that, well actually, you've said that you're going to preserve the trees [28:30] around and near the building, including the terraces [28:35] and in the inner courtyard. [28:36] I would like to know if you have considered that [28:41] there is a possibility that the groundwater table will be changed [28:45] following the construction of the building, which would have an impact on [28:50] the ...(inaudible)... necessary to preserve the trees. [28:56] So, actually, [28:58] the site is mainly already [29:01] covered in grass, so it's already very, very used [29:05] to absorbing a lot of water. [29:08] So I don't think the intervention will have a significant impact, [29:12] then perhaps I'll let my colleagues in civic and landscape complete. [29:21] Hello. [29:23] As far as the building is concerned, quite simply the building, [29:26] it is... [29:27] a slab on grade that follows the profile of the lower natural ground. [29:31] So it's not something we're worried about on our side. As [29:36] Philippe said, of course, most of the site is grassed. So [29:39] the water seeps through, but the groundwater table remains high. We're close to the lake too, [29:43] so, I think the trees are mature and they're big precisely because of [29:47] the proximity of water to the building [29:51] and in the park. [29:51] Therefore, it is not a question [29:55] that is very problematic for us. [29:59] This will have no real impact on the groundwater table. [30:01] In terms of trees, the two elements that have an impact on the park are [30:04] if we were to clear around the trees or bury them. [30:08] And [30:08] this is why we're doing a lot of work on the perimeter of the building, [30:11] to have terraces that are above ground level. [30:14] And we try to preserve more of the natural soil [30:17] to avoid impact on the trees and preserve them. [30:19] There are also many trees that are already... Adjacent to these trees, [30:25] there are asphalted areas that are already impermeable. [30:28] So the roots are not necessarily... [30:32] don't necessarily go that way either. [30:33] So there's a kind of impermeability that already exists, [30:38] because they're parking lots. We really set up where there are [30:41] asphalt parking lots. [30:53] Thank you. Thank you for the start of this presentation. [30:55] I really like the fact that you're thinking about passive solar [30:59] power. So I understand that the soffits are going to be bigger, [31:03] are going to make use of the fact that you are going to put several linear feet of [31:10] soffits, [31:11] during the summer, to protect you from the sun. [31:15] Then, in winter, the sun is lower, so the sun will come in more quickly. [31:18] And it sounds well thought out. [31:24] ...(inaudible)... [31:25] The use of the spaces, where you have [31:27] transparency from inside the building to the outside, [31:32] the orientation seems right, the use of the building to give [31:35] full view of the lake and lakeside green spaces, [31:39] are well organized. [31:44] I have a question, however, about the enclosed [31:46] space inside. There are mature trees inside that. [31:49] It's a great idea to keep this place and then create a protected area for... [31:56] I think you said it was a play area for 2-5-year-olds? 0-5 year olds? [31:59] However, in terms of operations, [32:02] in terms of maintenance, how do we manage this? [32:07] A play area requires a lot of infrastructure, to start. [32:09] So, sand, wood shavings, etc. [32:12] Maintenance of the structure itself, the lawn, the plants, etc. [32:16] And we can see that it's really fitted out inside [32:21] with the shelving [32:23] units and the meeting spaces and the sanitary blocks, etc. [32:30] So, there may be an operational purpose that is not [32:33] logical for me. [32:37] As far as maintenance is concerned, [32:42] it could... Actually. [32:44] [32:46] [32:49] Here, here is... [32:51] There is this space that is not in the public areas, [32:55] It's a traffic area that's quite wide, it measures about two metres. [32:58] There could also be double doors. [33:00] We've definitely got some doors here at the moment. A door there, [33:03] but all this can be opened up. [33:04] So, here, there's a way of getting around and entering with [33:10] There's nothing to move as such. [33:12] In terms of... [33:14] If there was any pruning to be done or anything to do with the trees, [33:16] It would not be difficult. [33:17] There's a lot of climbing to be done, or perhaps with a crane [33:21] to fetch dead wood, but in any case. It's... For me, [33:24] it's a big question, maybe with a question mark there. [33:28] It should also be noted that this is the lowest part of the building. [33:31] As Philippe mentioned, the roof comes down. [33:34] In fact, its lowest point is really here, and then it rises [33:38] like this, rises like this. [33:41] So that's the lowest point. [33:42] So the height of [33:46] the branches are really above the courtyard. [33:50] It could even be done from the roof. [33:55] I believe. [33:56] Then, I think that in terms of play facilities, yes, [33:58] I think that was more a reflection on a more detailed conception [34:01] that we can see. Making installations that require [34:04] less maintenance on this side, but also, [34:07] yes, as far as the trees are concerned, [34:08] there needs to be a path so that we can redo some of the maintenance. [34:11] Maybe, Mira, you could answer for the trees. Yes, that's it. [34:13] In fact, I can add ...(inaudible)... [34:17] ...(inaudible)... [34:18] ...(inaudible)... [34:22] ...(inaudible)... [34:26] ...(inaudible).... [34:29] ...(inaudible)... [34:30] The arrival of machinery ...(inaudible)... [34:33] ...(inaudible)..., but it's not necessary at this level, [34:37] for ...(inaudible)... [34:39] ...(inaudible)... as she was saying ...(inaudible)... [34:43] a pruning ...(inaudible)... trees that are tall enough. [34:45] ...(inaudible)... that grow on top of the building. Therefore, maintenance [34:49] pruning from the roof, that can be done from the roof. [34:51] And a programming... [34:54] ...(inaudible)... [35:01] ...(inaudible)... [35:05] It's clear [35:05] we have tree protection on the premises [35:08] around the trees will be necessary, but that's a detail for later. [35:11] My other question: in the area where the chalet is, the captaincy, [35:16] what is the purpose of this space? [35:18] It's also a little isolated because of the parking, which is [35:22] well thought out. [35:23] You have many islands of greenery in the car park, [35:25] then, after that, there's the green space overlooking the captaincy. [35:28] Is there a purpose here or is this a green, forested area? [35:32] Front or back? Between the captaincy [35:35] and the parking lot. [35:37] That, it is a picnic area. [35:39] Actually, we wanted to juxtapose two types of space. [35:42] So we talked about the grassy plain, which is an area that, [35:45] following the profile of the site, is higher up the marina. [35:49] And, at the moment, I think they have gatherings in this place, a bit further down. [35:54] And then the in-between space, [35:56] so we wanted to have picnic tables, a place to gather [35:59] which is close to the car parks, but benefits more from the trees' cover. [36:03] So, being able to enjoy the sun or the space more of as a gathering place. [36:07] This is where we really see that a more [36:10] community focus where people will be able to, first and foremost, [36:13] gather to then stroll around the park. [36:18] And the trees, [36:19] there are several trees added. [36:21] [36:22] enhanced [36:25] to make it a place where... [36:29] with more vegetation, more shade. [36:32] It's a big space. In fact, we imagined [36:35] in winter, we could perhaps make a small ice trail as well. [36:38] We're close to the captaincy. [36:40] So to try to make the most of the place during the winter as well. [36:44] Yes. It's like a plateau, there's the parking lot, then there's this plateau. [36:48] After that, there's another plateau further down. [36:50] Well, they're light, the plateaux, but they're like plateaux [36:53] at the moment. [36:56] Thank you. [36:59] Hello, [37:00] I had two questions about the accessibility of certain areas. [37:04] So the first area is the bistro section and the multi-purpose room. [37:09] So we can see that there are a lot of stairs. [37:11] How do you see the ramp that's actually going to the other end of the building? [37:16] The room... [37:19] Sorry, the room... [37:21] The bistro and the multi-purpose hall. In H-1. [37:26] How... [37:26] the acess [37:28] coming from the lake, from the park? [37:30] OK, we've actually fitted out the side here, the south side. [37:36] As we've explained, [37:37] there's a a difference in ground level but at the same time we are working the soil [37:42] that goes up a little further, then we created a long... [37:45] gentle ramp leading up to the terrace. [37:50] Here. There will also be some that follow, actually, [37:54] that run alongside the building and provides access from [37:58] from the entrance, yes, from the forecourt. [38:02] If not, the multipurpose hall can be reached from here. [38:05] You can go up and down from there. [38:09] And, actually, you can see one of the black triangles there, which is the back [38:12] entrance of the library, here, which is close to the end of this ramp. [38:16] And we brought up all the floor levels. We worked on the ground level [38:19] to have ramps at accessible levels, [38:24] which are softer than that. [38:26] Perfect, my second question, [38:29] it's about the youth room [38:30] and the activity room. [38:32] We can see it a little here in the photo with the green steps. [38:36] Here we have a ramp that runs alongside the courtyard [38:42] and we also have one outside. [38:44] So we were able to bring it down the [38:48] the courtyard, inside or outside to access the activity room. [38:52] Perfect! [38:54] A quick question concerning the computer room. [38:58] So there are two places that have been added: [39:00] The H-5.1 and H-5.2. We were wondering about the purposes of these areas were. [39:05] In fact, these two rooms were part of the plan. [39:08] That's what we called them, but they were part of the H-5. [39:12] The H-5 surface area, it is all this, [39:14] but in one of the programs, the program we received, [39:18] there was - there was mention of developing [39:21] a photocopying area at the entrance which could be opened, even [39:25] if the room is occupied and can't be accessed. [39:28] And also a green screen for taking photos. [39:32] That was mentioned in the program. So we followed that. [39:35] Otherwise, if these parts are no longer required, [39:39] we can go back to the full size of this room. [39:54] Perfect, thank you. [39:54] Philippe and Annie, thank you very much. [39:56] It's very interesting, and tree conservation is very commendable. [40:01] and the way your building takes shape with the trees, in fact, [40:06] but I'm curious [40:08] rather about the urban part, what we call the reception, [40:12] the urban filter. That's your fourth zone at the top. Because you mentioned [40:16] the building's civic scale [40:20] and this also implies a civic [40:23] typology for the forecourt. [40:26] We know that the building [40:29] is relatively modest in terms of scales, but we can see that [40:34] you spoke of your desire to make a presence [40:37] on Beaconsfield Boulevard. [40:40] So my question... We have a whole series of plantation bubbles [40:45] in the forecourt, we have a single-story building. [40:49] This gives you a bit of a challenge to [40:52] create a real civic presence. [40:54] It's a civic amenity in the ...(inaudible)... [40:56] Can you explain a little bit your strategies in these two areas: [41:00] the civic presence of the building and the civic presence [41:05] the forecourt as a meeting place [41:08] and a gathering place? [41:11] Well. [41:12] As for the civic part of the building, [41:14] I think I was just mentioning that the building really extends itself. [41:19] The shape of the building, too, which is really like a kind of arch [41:23] is welcoming and its range, [41:26] I would say, on the site, [41:28] gives an impression of [41:32] grandeur, if you will, which is to scale for us. [41:38] From Beaconsfield Boulevard, [41:39] I think it's going to be quite visible. [41:41] Then, for the forecourt, maybe it's... the view [41:46] lacks perhaps a little furnishing, but the islands are really [41:50] positioned to create areas, a forecourt that will be shaded, [41:54] because this forecourt is quite large, and cleared [41:57] areas to allow for activities. [42:01] So it's a bit of an area that's included, at the same time, [42:05] that is inscribed in the park, but which opens up and really becomes like [42:11] a civic location [42:11] that is mineralized that invites events. [42:15] I don't know if I'm answering your question, but... I think the building [42:18] and the landscape [42:18] work together a bit. [42:19] That's it. The intention is to move the building back and make way for the forecourt. [42:23] And we're even very comfortable [42:25] with the car park a little more in the foreground to, precisely, provide a view, [42:29] and notice that there's a space, a building of some importance, [42:33] a place where people can come together. [42:35] I think that the City of Beaconsfield... [42:38] it remains a modest [42:39] building, but that encourages us to discover the place. [42:43] Once you appreciate the site, it's actually the cultural centre [42:47] and the site that become themselves a civic place. [42:52] This means that in this image, [42:53] here, we are in the old parking lot, [42:56] so we've planted the two mature trees here. [42:58] There are a few facing this way. [43:03] We would have to look at the plan because there are some existing ones. [43:06] It's quite alright that part of your perspective is 50 years from now, it doesn't matter, [43:10] But there is a tree... [43:11] But it's certain that along the car park in the planted islands, [43:14] there's going to be less mature trees. Yes. [43:20] Thank you very much. [43:25] So, yes, I appreciate the presentation. [43:28] I was wondering about something. [43:29] Two things, [43:30] actually. We talked about trees, the maintenance [43:32] of the inner courtyard, it's a technicality, [43:34] but nobody is talking about the snow. [43:36] [43:38] [43:41] [43:43] you could answer. [43:44] You've done several projects like this. [43:47] On the contrary, it's a way of bringing Winter indoors. [43:50] The four seasons within the interior space. [43:55] And the snow falls in the courtyard, but in the spring, [43:58] it melts and it's not a roof, so everything seeps into the ground. [44:04] It's also very bright in winter, with the snow, [44:08] so there really is a kind of reflection effect. Yes. [44:13] Regarding [44:14] the access to the marina, well, that's one aspect of the program... [44:19] maybe... I don't know if it was very well defined, [44:23] but there is a lot of overlap with the proximity of the building. [44:27] Had you considered a different radius of curvature [44:33] or a certain distancing from the buildings [44:36] and the activities taking place just behind it? [44:39] This is clearly shown on the site plan. [44:43] Yes, that. Exactly. [44:45] Maybe just explain? This here? [44:47] Well, yes, actually, [44:49] because the principle is to go to the marina until [44:52] the water. Yes, but in fact. [44:57] What's the question? [44:57] So it's in relation to dedicated access? Well, it's not direct, actually, [45:02] is that what you mean? [45:03] No, it's more... I don't know... [45:07] the intersection of uses. Because there's a sort of esplanade behind it [45:12] the building, which is going to be occupied, and then we bring people in [45:16] with their boats. [45:19] I was wondering if it were possible to think about a route [45:23] that's a bit far away or something like that? [45:28] In fact, I think... it's a discussion actually, [45:31] we don't know how much traffic there is either [45:34] to understand what the potential crossover is. [45:37] I think we wanted to make sure there was a dedicated entrance to ensure [45:41] that the regular use of the car park itself avoids crossovers. [45:47] Then it's downhill to the esplanade, [45:51] that is the place where there is [45:52] a management, mitigation needed. [45:54] I think there's a potential to see if [45:57] there are other ways, depending on traffic. [46:01] In fact, what was most important to us was to really [46:04] clear away; that [46:06] cars entering the parking lot [46:10] going at low speed, if you will, [46:13] but that the crossing [46:16] of boats with trailers is outside the entire access area [46:21] of the cultural centre. [46:26] I think there was also a desire to make sure that the marina [46:29] be a part of the show, which people in the library can also see. [46:34] So we didn't want to distance ourselves from this activity. [46:44] ...(inaudible)... [46:54] ...(inaudible)... [46:57] ...(inaudible)... [47:03] Landscape waves, [47:04] landscape lots in the other direction, [47:08] it creates a kind of grid, yes, [47:12] that we can see on this plan. [47:14] So, once we've established these lines of force, or these lines on the site, [47:18] how does that help you position the building? [47:21] It's not clear to me why the building [47:23] is there once we've mapped out these two sets [47:27] of horizontal and vertical lines. OK. [47:32] Well, in fact, the positioning of the building [47:34] is both linked to landscape work and the two are [47:39] influenced each other a little, if I may say so. [47:42] In fact, the... [47:43] So it's the building that defines the urban filter? [47:50] Actually, the urban filter, [47:50] for us, it already existed and then came to be defined by the building. [47:55] So, the urban filter, currently along the boulevard, [47:57] is fairly narrow and dense. [48:00] And what we wanted [48:00] to do, in terms of the building, is to widen it so that it becomes more of a filter which is [48:05] inviting rather than a barrier. [48:07] So that's why we came to expand it. [48:10] Then, for us, it was quite important, [48:12] as Annie mentioned, to have the building overlap the site's forested area [48:17] which is vacant and becomes a place [48:18] which is much more open and community-oriented. [48:21] So to do it in juxtaposition. These are elements that are very... [48:25] that are already existing. [48:26] So, the grassy plain is really, when you go to the site, [48:28] you can see how people converge on water, [48:32] and towards these spaces. So what we also want to do is [48:35] bring people back to the centre of the site, which is sometimes a little neglected. [48:39] To occupy it even more. [48:43] In fact, the building is pretty much... If we... [48:46] we cross... we make an X, it's roughly in the centre of the site. [48:50] At the same time, it is quite close to the boulevard. [48:54] in order to be visible from the boulevard, but also to have a full experience of the park. [48:58] It's idea of inserting, in fact, the building into the trees' canopy. [49:03] [49:05] there. And this idea of having to [49:08] keep a large open space for [49:13] the people who go all the way down to the marina. [49:15] And we turned it into a public space, so we thought we'd straddle the two, [49:18] it was quite an interesting experience and the animation branch, [49:22] which is much more, shall we say, lively with the multipurpose hall, [49:26] the art studios that you can see at the entrance, etc. [49:29] come to settle in this branch; while the library building and the [49:34] administration infiltrate the canopy. [49:38] And that's the idea behind the park chalet. [49:41] Maybe this will complete the answer. [49:42] The park chalet and the Centennial House, [49:46] let's say if we keep it, or if we ever demolish it, [49:49] what we were proposing was perhaps to build [49:51] a kind of large roof. A sort of park gazebo, [49:54] but which ultimately becomes the stage for gatherings. [49:58] They're all, like, in the canopy, [50:00] but with their gathering spaces, all three. [50:04] So it's this whole organization of the park [50:06] with the natural elements that helped us [50:10] to position both the building, with its green roof, also, which [50:15] makes it a part of the canopy and its position, [50:19] let's say, between the boulevard and the lake. [50:23] Then there's the 100-year line here, [50:26] so we got close, but not too close, that's to say [50:28] that we kept a safe distance. We thought [50:31] it would be a full experience for people in the building too. [50:35] And maybe I can just add...