[0:00] That's it. [0:01] Great. [0:03] All right. Okay, well, maybe I I guess [0:04] I'll I'll call to order and start the [0:07] meeting. Um [0:08] first order is roll call and I'll start [0:12] and then we can go around. John Tantum, [0:14] I volunteered to be chair of this [0:15] committee, a Cove Road resident. [0:18] Go ahead, Mr. Isaacson. Sitting in for [0:20] Larry Store. [0:22] Keith Fagan, a [0:24] town resident. Uh Peter Mark, city [0:26] council member. I'm going to excuse [0:28] myself and get a pen. This one doesn't [0:29] work good. [0:30] Okay. [0:34] Julian Poolweiler with Stetson [0:35] Engineers, uh design team for the Beach [0:37] Road stabilization project. [0:39] Adrian Formaini, both with the city [0:41] project management team. [0:43] Great. [0:44] Tony Boyd, public works director. [0:46] Um [0:48] and uh the others I I can chime in that [0:50] Robert's uh [0:52] excused himself from from being here. He [0:54] wasn't able to make it, but he is [0:55] joining us on Zoom. So, yeah, that's [0:58] city manager Robert Zadnik. [1:00] Robert, Robert, can you hear us? Are you [1:03] on audio? [1:05] Uh yeah, hi everyone. Can you hear me? [1:07] Yes. [1:08] Yeah, can you can you hear us okay, [1:10] Robert? [1:11] Yes. Yeah, you're coming through loud [1:13] and clear. Thanks. [1:14] Great. [1:17] And I'm Chris Berry, assistant engineer [1:18] with the city of Belvedere in the public [1:20] works department. [1:22] Peter, were you out when [1:24] when the [1:25] when the call came around to your your [1:27] seat? [1:27] » You know I said it, Peter. Okay, thanks. [1:30] Yeah, um [1:32] All right. Okay, well, the next item is [1:34] the approval of the minutes from our [1:36] prior meeting on February 26th, [1:39] uh which are in the packet here and were [1:42] distributed earlier. Are there any [1:43] comments? [1:46] on those? [1:47] Happy to make a motion to approve it. [1:50] I'll second that. [1:51] In favor? I. [1:54] Uh the minutes were approved from the [1:56] February 26th meeting. [1:59] Um [2:02] next is the the the matter at hand to [2:04] talk about the Beach Road stabilization [2:06] project and the bids and reviewing the [2:09] bids and [2:10] uh [2:11] discussing those and hopefully come out [2:13] come up with a recommendation for the [2:15] city council. [2:16] Great. So, maybe Tony, I'll let you take [2:18] it take over. Yep, thank you. Yeah, and [2:21] um thank you everybody for for being [2:23] here once again um [2:24] in your time. [2:26] And um [2:28] this uh this meeting is a follow-up from [2:32] our last meeting which really introduced [2:33] you all to the to the plans for the [2:35] project and uh the context for it. Um [2:39] this meeting is to uh present the [2:42] selection process [2:44] um [2:44] uh to you all and uh basically um [2:49] uh request a recommendation uh that the [2:53] city council approve uh the the contract [2:56] uh for the for the project and award the [2:57] contract uh to a contractor. Um [3:01] and so, what I'll be doing is I'll walk [3:03] you through the selection process um [3:06] and we are uh I think it's fairly [3:09] informal. We can, you know, discuss and [3:11] ask questions as we go. And um yeah, [3:14] happy to fill you in on on any of the of [3:17] the details. [3:20] All right. So, um [3:23] so, to start with I'd like to clarify in [3:25] my memo um [3:28] » [clears throat] [3:28] » Uh that because I didn't point this out [3:31] in the memo. Um this contract is for the [3:34] sheet pile installation portion of the [3:36] project, which is the main uh the sort [3:38] of the meat of the project. Uh there is [3:40] another um [3:42] segment which it which has to do with [3:44] the the private properties on Beach [3:45] Road, number 16 uh to number 28 Beach [3:48] Road, um where there are gangways and [3:52] utilities on on the properties there [3:54] that will need to be removed for the [3:55] installation of the pre of the of the [3:57] sheet piles. [3:59] And that's a project in itself. Um and [4:01] so, that will be a a separate contract. [4:03] Um [4:05] And there there's a little bit of [4:07] possible confusion with with uh with the [4:09] numbers that that amount was included in [4:11] the engineer's estimates um [4:13] uh [4:14] you know, and and that's not really I I [4:15] didn't really um clarify that or point [4:18] that out in the memo. [4:19] Um [4:21] and yeah, we we can we can look at it [4:24] more closely uh but uh exhibit C, the [4:26] engineer's estimate will will show [4:29] uh [4:30] that uh where that that line was [4:32] included in the total cost of of the [4:34] estimate versus the cost of this [4:37] proposal. [4:38] Um [4:40] and [4:42] yeah, if need be um I could also [4:46] it'll take me a few minutes, but at some [4:47] point I did [4:49] uh pull up uh some of these documents [4:51] onto the screen if it's helpful. [4:53] And Robert might find that [4:55] that useful. [4:56] Um okay. Um so, the RFP was posted on [5:00] February 20th. [5:02] There was a lot of interest um it seemed [5:04] to us with uh 58 downloads of uh of the [5:08] RFP materials. Um [5:11] uh it gives some indication, I guess, of [5:13] of uh all the contractors out there and [5:15] and who are kind of perusing the sites [5:16] and [5:17] uh [5:18] interested to see what what projects are [5:20] going on. [5:21] Um [5:22] that was followed by a mandatory site [5:24] meeting uh with with prospective [5:26] contractors. [5:27] Um so, any contractor who wanted to [5:30] submit a bid would have to be at the at [5:32] the site meeting. [5:33] Uh there were 14 companies represented [5:35] there. [5:36] Um and the deadline for questions [5:40] following that was March 9th. Um we [5:42] received four questions in writing [5:45] and responded to in in in an addendum. [5:49] Um there were two adden- addenda issued. [5:52] Uh the first addendum was um [5:55] a change to the insurance requirements [5:56] in the contract. [5:58] Um so, that uh yeah, basically uh [6:01] provided uh the details of that. [6:03] Um and then addendum two um [6:06] uh provided details on the on the uh [6:08] pre-bid meeting, um [6:10] the questions received, um the responses [6:13] to those questions, and also a [6:14] clarification of of some of the uh [6:16] contractor's responsibilities uh during [6:19] during the project um [6:21] related to workflow, their workflow, and [6:23] coordination. [6:26] The deadline was March the 19th um [6:29] and that was uh attended by four [6:32] different contractors' representatives [6:34] uh as well as a union representative [6:36] representative. Um A union from [6:39] local three. Operators. It's not [6:42] uncommon that they show up knowing about [6:44] this type of projects. Yeah, thank you. [6:48] Thanks, I wouldn't have known that. [6:50] Um [6:51] and then [6:53] uh yeah, so and it was fairly [6:55] straightforward. Each uh each envelope [6:58] each sealed envelope was opened and the [7:01] bids uh bid amount was was read out [7:03] loud. Um [7:05] uh people people, you know, took notes [7:07] and uh and then asked some questions. Um [7:11] most of the questions, I think all the [7:12] questions were [7:13] » So, they they they opened up their bids [7:15] amongst all the other competitors? [7:17] Yeah, so basically we received the bids [7:20] um at a table we had a little table [7:21] stationed next to the door there. As [7:22] they came in, uh they they uh handed in [7:25] their bid [7:26] um and then um at the designated time [7:29] which was 11:30 on that day, [7:31] um we declared that uh bids were now uh [7:35] closed and then uh and then we stood up [7:37] at a at a table and opened each bid [7:39] individually, pulled out the the [7:41] documents, and read out the number to [7:43] the to the uh the contractors. Is that [7:46] is that a requirement? So, is that a [7:48] requirement? It is the It's a law. I'm [7:50] sorry, I didn't mean to speak over you. [7:51] Yeah, that's right. Yeah, that was that [7:52] is the procedure for [7:53] uh public opening. And it sort of takes [7:55] away your ability to negotiate with [7:56] anybody. [7:58] It does and the law it's it's it's uh [8:03] it's a legal requirement for for public [8:05] agencies. Um [8:07] and and [8:08] the the possibility to negotiate um [8:12] is actually extremely limited. I mean, [8:13] the the the amount on the bid uh if the [8:17] city is to accept a bid, [8:19] um [8:20] it has to justify not accepting the [8:22] lowest bid, basically. Um if it's not [8:25] going to accept the the lowest bid, um [8:27] there there needs to be a reason in, you [8:30] know, um [8:31] uh that the city would would do that. I [8:34] mean, it's very seldom that that a city [8:36] would want to not [clears throat] accept [8:37] the lowest bid. But but is there is [8:39] there I'm sorry to meet you. [8:41] » No, no. [8:41] Just just [8:43] couple questions. So, you went from 58 [8:46] downloads, I guess, I know it's a it's a [8:48] gross number um [8:50] to 14 visits and four [8:52] made meeting the deadline. Did anybody [8:54] come in after the deadline? Um which I [8:56] know you you need to exclude, but I'm [8:58] saying anybody come in just for [9:00] information. [9:01] » No, no, nobody came in after the [9:02] deadline. [9:03] » Normal or why would you think you'd go [9:04] from 58 to 14? I I understand a 58 to [9:06] 14, but 14 to four seems a larger jump [9:09] than I would expect. I'll go over the [9:10] bats and then I'll and then I'll let [9:12] I'll let you Adrian chime in. He's [9:14] definitely um [9:16] kind of written a few more of these [9:17] rodeos than I have. Um but [9:19] um I think uh one of the main reasons [9:22] was there was this a specific piece of [9:24] equipment that was um specified in the [9:27] RFP and and uh and that was this uh [9:30] silent piler, this guy can machine. And [9:34] there are very few uh if [9:36] if any, I think, in Northern California [9:38] um [9:39] uh companies that that provide that. Um [9:42] so, [9:43] you know, that was another thing is that [9:45] all of them had the same subcontractor [9:47] uh to drive these piles in. [9:49] Um [9:50] and I think yeah, some of the comments [9:52] at the pre-bid meeting um [9:54] related to that. They they sort of said, [9:56] well, I mean, if we're all going to have [9:57] the same prime I mean, if we're all [9:59] going to have the same sub, [10:00] um [10:01] what difference does it make to you [10:02] guys? And so, I think a lot of people [10:04] felt that they wouldn't have a [10:06] competitive chance. So, you know, so [10:08] didn't didn't want to waste their time. [10:10] Um but yeah, Adrian Yeah. So, uh you [10:14] know, it was certainly a great turnout [10:17] at the pre-bid versus who pulled plans. [10:19] And who pulled plans could be a host of [10:21] individuals that may actually not even [10:23] have any [10:25] ultimate goal of bidding on the project. [10:27] However, they are very interested [10:28] whether it be a vendor. Uh there are [10:31] several [10:32] uh communication [10:35] uh companies that will track projects [10:37] and then, you know, post items. Um so, [10:40] you usually have a very broad spectrum [10:42] of individuals that will pull plans and [10:45] and anyone's allowed to do it. So, then [10:46] you get down to the pre-bid meeting, [10:48] which is certainly a more uh fine-tuned [10:51] group of individuals [10:53] that still may consist of additional [10:57] individuals outside of who will be [10:59] bidding on the project. Myself signed in [11:02] on the pre-bid sheet because I was an [11:04] attendee. [11:05] Um my project manager Kyle, you know, [11:07] Tony. So, there were [11:09] others at the pre-bid that necessarily [11:11] weren't going to be bidding on the [11:12] project including subcontractors [11:15] to potential primes. [11:17] So, one of the critical uh [11:20] subcontractors and at that point we [11:22] weren't sure if there was a [11:25] uh a prime or a subcontracting component [11:28] to the uh company that does retain [11:30] several of these Dyken silent pilers. [11:33] And they were, you know, there with [11:34] three individuals, you know, that are [11:36] all from Blue Iron. So, that's how your [11:37] list kind of kind of kind of [11:42] that we ended up with? Is that a [11:43] successful process or would we wish we'd [11:45] had more or what what how do we how do [11:47] you evaluate that? Exactly. Yes. So, [11:49] good question. So, because of the uh [11:52] selective equipment for installation, [11:55] these contractors all knew that Blue [11:58] Iron was going to be [12:00] involved with this contract. You can [12:02] only make the case Blue Iron's you know, [12:04] selected who they who they want to work [12:06] with. Correct. So, we do know based on [12:08] the bid results that Blue Iron so [12:10] provided numbers to several contractors [12:12] and that's great. And all of them were [12:14] very close on that one particular bid [12:16] item when we analyzed the results. [12:18] » But they're not though. But they're not [12:20] though. I mean, unless it's embedded in [12:21] these lines. I mean, there's there's [12:22] there's quite a big of variance in the, [12:24] you know, uh line five, six, seven, and [12:26] eight. [12:27] You would think you would think if it's [12:28] the same contractor between the same The [12:30] contractor is this the opinion of cost [12:32] for the [12:33] project? I'm just looking at the [12:34] line-by-line breakdown. Must be in the [12:36] bid [12:36] Okay. Yeah, so that's a computer too. [12:38] I'm sure it's in a more detailed [12:39] tabulation. But but you know, where you [12:42] would where you would expect to see [12:44] So, I'm I'm my bad. I'm sorry. I didn't [12:45] have a thought that was on the one Where [12:47] you would expect to see some consistency [12:49] among them all [12:51] would be alignment A, alignment A, [12:52] alignment B, alignment C, you know, [12:54] where this where where the the [12:55] structural steel um sheet piles are [12:57] being driven. You know, basically line [12:59] five, six, and seven. [13:00] Um [13:01] and part of I guess [13:05] Yeah. I don't know what I'm seeing right [13:06] now, but [13:07] To jump in, I'm I I I 100% see what [13:10] you're saying and it is a bit of a head [13:11] head scratcher about why Valentine [13:14] uh uh [13:15] have 2.3 million whereas the other [13:18] contractors I think are more [13:20] closely um converged at, you know, [13:24] between 1.6 [13:27] and and 1.8 million. Quick question. Are [13:30] uh are [13:31] are we we're in at this point we're not [13:32] even discussing Valentine's numbers or [13:34] do you want to discuss their I mean, [13:37] they're they're they're way high. No, [13:39] no, no, I know. I know. I know. I'm I'm [13:40] I mean, well, just just with four on the [13:42] page and I you may want to just mention [13:44] why you knocked out Corcus. [13:46] Yes. Yeah. Yeah, definitely. I was [13:48] coming to that. Yeah. [13:50] Yeah, so [13:50] they knocked out Corcus. They didn't [13:52] they didn't really follow the process. [13:53] Yeah, we can we can look at the [13:54] administrative oversight by Corcus and [13:56] they just forgot to sign something or [13:57] was it like a substantial [13:59] they didn't [14:00] complete something important? Uh it was [14:02] an it was I think [14:04] I if it was me, if it was my company, [14:07] I'd be very frustrated uh because um [14:10] it is it's it's a very minor [14:13] detail when you're filling out a form, [14:15] but [14:16] in in an RFP um it's it's significant [14:20] um and [14:22] uh it basically [14:25] um [14:26] The frustration for us too is that um we [14:29] we were aware that Corcus had downloaded [14:31] those those addenda [14:33] um and [14:35] so when they when they filled in their [14:37] form um saying that they had not they [14:39] they did not acknowledge uh the the [14:41] addenda basically. I mean, but but but [14:43] in the city's defense and our in our [14:45] broader legal defense of this is also [14:47] that when and if [14:49] they're they're not acknowledging those [14:50] two addenda which we we we can't verify [14:52] that it's in their their their budget [14:53] data and and they'll perform the work [14:54] according to the specs that you laid [14:56] out. Exactly. What's your real change? [14:58] Which is why you have to sort of [14:59] eliminate that. [15:00] There's no way to have them acknowledge [15:03] the addenda after the fact. It was too [15:06] late at that point after the envelopes [15:08] have been opened. Is that right? It you [15:10] know, it's [15:13] It would have been basically, yeah. I [15:14] think that would have resulted in [15:16] protest from from the other bidders um [15:19] basically that they didn't follow [15:20] procedures and then were being given an [15:22] allowance for [15:24] you know, to to correct items in their [15:26] in their bid. [15:27] Um [15:28] Yeah. And you know, I mean, I think [15:31] ultimately um [15:33] you know, the city attorney weighed in [15:34] on it and and uh [15:36] yeah, it it was quite clear that uh this [15:38] was the only option. [15:40] Yeah. Um [15:43] Luckily for us the the next the next [15:45] bidder was was a very close in price and [15:47] they, you know, for the total. [15:49] I mean, but on those my question was a [15:52] lot of those install sheet pile. Yeah, [15:54] you go from [15:56] even if you take out Valentine, you [15:57] know, there's a six there's a $300,000 [15:59] swing on line five. [16:03] Between between between Thompson and and [16:07] Gordon Gordon Mhm. And and Thompson [16:09] being the third. That's why they were in [16:10] third place. No, no, no, but I'm saying [16:12] but if if if the same subcontractor is [16:14] providing the service, maybe there's [16:15] more detail that that there that I'm not [16:16] seeing. Because they are carrying costs [16:18] of unforeseen to for covering a sub. So, [16:22] guaranteed Thompson is a more local [16:24] contractor from Nevada and they may or [16:27] may not have worked with um um Blue Iron [16:30] as much, but I do know that both Corcus [16:32] and Gordon Ball both [16:35] work with them quite often and that is [16:37] probably that is a reflection in Gordon [16:39] Ball's number is that they have a very [16:42] good understanding and operation for [16:44] their subcontractor which is carrying, [16:47] you know, 75% of this this project [16:50] weight here. [16:51] Um that is the way I see it. [16:54] What a really good question. Um what is [16:57] the ultimate nature of our agreement [16:59] with this contractor? Is it a guaranteed [17:00] max? What factors you you mentioned that [17:03] in your review of um [17:07] uh [17:08] references that one of the one of the [17:10] things you got back about Gordon Ball in [17:11] particular was that they were able to [17:13] finish the project on time and on [17:14] budget. [17:17] What [17:18] what are the opportunities or what are [17:19] the negative opportunities to be off [17:21] budget for us? I mean, [17:23] if is this a guaranteed max? Is this a [17:24] fixed price? What happens [17:27] um certainly I understand client driven [17:28] change orders or or or material driven [17:30] change orders, but is that what can can [17:32] can can drive this into an overage [17:33] situation? Yes. And and it's really and [17:36] and Adrian definitely please do chime in [17:38] here, but [17:39] um [17:40] my understanding is that [17:42] uh they based their [17:44] their their estimates of of costs or [17:46] their their price [17:50] on the If if other [17:52] you know, if they get out to the sites [17:54] and and um you know, they start digging [17:57] and there's something something else [17:59] down there than other than loose sand [18:00] and rock, for example, um that causes [18:03] delays and [18:05] you know, changes um then then costs can [18:08] change. Yeah. [18:12] Yeah. Most of them Yeah, and then some [18:13] of the units are are are stated you have [18:16] you do a square foot for the sheet pile, [18:18] but primarily they are either single [18:21] units or total and or, you know, lump [18:23] sum. So, each the only the square [18:26] footage is on the the sheet pile, which [18:28] is total. [18:29] And then it's a furnish and install, so [18:31] it's a completed system. I mean, Jason [18:34] repair that was completed a few years [18:35] ago. Were there many change orders [18:36] associated with that project? Not one. [18:40] And did it come in on budget? Uh well, [18:43] that one was a little There was there it [18:45] was not the same development of that [18:48] project based on the situation because [18:50] it was more of a observation that was [18:53] made with both and Miller Pacific during [18:55] and Stetson during the H and H study in [18:58] 2019 for the shoreline resiliency for [19:01] both shoreline and [19:03] Santa Paula and Beach. [19:04] Uh so, that was when it was prompted and [19:07] the wall was showing uh significant [19:09] signs of failure. So, that was what [19:11] prompted that project. So, it certainly [19:13] was in line with pricing [19:16] um and there was no additional inflated [19:19] costs due to a [19:20] you know, expedited, you know, time [19:22] frame. Blue Iron came in well under [19:24] because they had a unique perspective on [19:26] the installation of sheet with uh [19:29] um just cutting edge tech [19:32] you know, so [19:34] they were we were able to complete the [19:36] project faster than other companies. [19:38] So And can you confirm my understanding [19:41] as well that it's it it would go both [19:43] ways as well. So, if less materials are [19:45] used, for example, um [19:48] than than anticipated calculated the [19:50] square footage, um then [19:53] then uh that's what's that is what it's [19:56] built to the city as well as well [19:57] invoiced. Yeah, I mean they're they're [20:00] you know, this is what they were [20:01] expecting and they're going to they're [20:03] going to procure sheets like this is the [20:05] first thing that has to happen. So [20:07] » Right. So as far as the sheets go those [20:09] that would be a single kind of bulk [20:11] order I guess. [20:12] » Oh yeah, and they're going to jump on [20:13] that as soon as possible just because of [20:15] the lead time and getting into a roll [20:17] because these sheets very well may not [20:19] be on the brand yet. Okay. So it's yes [20:22] specific to sheets yeah. Okay. [20:25] I just know that I mean you know with [20:27] paving for example if um [20:29] you know for whatever reason it turns [20:31] out that it's a few tons less than than [20:33] expected. Absolutely [20:37] and that's what's important just for [20:38] keeping on track with you know that all [20:40] those all those things. But yeah we'll [20:42] certainly do that. And the good thing [20:43] that we have going for us is [20:45] the knowledge base of both Gordon and [20:47] Blue Iron is that they're [20:48] straightforward contracting that very [20:51] they work well together. So the mere [20:53] fact that they are a well-oiled machine [20:56] is going to have you know it's going to [20:58] just you know [21:00] assist tremendously versus you know [21:03] other subs that may or may not have that [21:05] well of a communication yeah you know [21:08] so. And then also yeah just to just to [21:11] add [21:13] if there is if there are complications [21:15] you know it's it's uh [21:18] the city you know through its through [21:20] its engineer engineering team would have [21:23] to [21:24] um [21:24] um [21:25] uh [21:26] basically approve any any changes like [21:28] that any changes to the to the scope. [21:32] So cost would be a part of that [21:34] decision. So if you know if there's a if [21:36] there's a huge change [21:38] it because of you know some [21:41] some unforeseen circumstance that that [21:44] results in a big change in cost [21:45] somewhere [21:47] that would be a decision that the city [21:48] would weigh [21:49] for in terms of the project as a whole. [21:52] What we do know is that we had very [21:54] little issues whatsoever with a [21:56] significant section of Beach Road [21:58] several years ago. We saw very [22:01] very bland questions from contractors. [22:04] The bids came in without carrying costs [22:07] of which we had no idea how this is [22:09] going to go down. [22:11] So that was those were all really good [22:12] signs of a well-designed bid package [22:15] from both the technical side as well as [22:17] the opinion of cost. It was it was very [22:20] it was right in line with what we you [22:22] know we were hoping to see. We're just [22:24] very excited we didn't see this as a [22:26] huge The lowest the lowest bid it's [22:28] Gordon Ball not Norman Ball right. I [22:31] think in your memo you Yeah right sorry [22:33] I for some reason I kept So I think a [22:36] little bit of Herman Ball I don't know [22:37] why it is wrong. See you the experience [22:39] they have but we have not worked with [22:41] Gordon Ball before as a city. They are a [22:44] large contractor so there's a very good [22:46] chance that they wouldn't have probably [22:48] been worked on any They are typically a [22:50] huge large scale commercial contractor [22:54] doing anything else than that. [22:56] But I I do know of that nature cuz they [22:58] they do a lot of municipal work. [23:00] » Okay. I don't know but I don't know the [23:01] company is that are public company or a [23:03] privately held company we have I'm not [23:05] sure and or if it's a member owned we [23:07] have to you know have to look into look [23:09] into that. One of them There was there [23:10] was a level of analysis required for [23:14] for this [23:16] review. But this is this is They they [23:18] are a large company that does many [23:19] projects that's not name I've never [23:22] heard of. No yeah. [23:23] um Yeah it's I have noted them either. [23:27] um [23:28] I don't know if they're nationwide I [23:30] don't know if they're that [23:31] » No they're not. I do know that they do a [23:32] lot of work with PG&E. They do a lot of [23:35] public utility work so they are they [23:38] understand the public process. And I do [23:41] know again that they work with Blue Iron [23:43] quite a bit with projects. And a lot of [23:45] times Gordon Ball is in prime for PG&E [23:47] projects where Blue Iron is their sub. [23:50] Yeah their their references were um [23:53] uh were I thought I thought very good [23:56] that the projects that they that they [23:58] highlighted [23:59] were very similar to this. [24:01] They all involved installing sheet pile [24:05] in in locations a lot of locations with [24:07] with water river banks and and boat [24:10] launches and and these kind of [24:12] situations and and one of the [24:14] one of the project managers that I spoke [24:16] to from I think it was the Santa Clara [24:18] Santa Clara [24:19] water district [24:21] said that they [24:23] um [24:24] that they were also in very close [24:25] proximity to homes and that they [24:28] uh you know they performed everything [24:30] that they needed to with you know [24:31] vibration monitoring and and that kind [24:33] of equipment so they they're definitely [24:35] familiar with with this this type of [24:38] work. They were they were nearby [24:40] projects here in the area in Northern [24:42] California. [24:42] » Yes yes yeah. [24:49] Yeah. [24:51] Right well so okay [24:56] where did I where was I? um [24:59] » [clears throat] [25:00] » Addenda yeah okay. So [25:05] The addenda were were required to be [25:07] acknowledged and and one contractor [25:09] didn't as we know [25:11] um [25:13] Is there [25:14] and I understand that the strict nature [25:16] of the [25:17] bid process [25:18] uh [25:22] We're not obligated to take anything [25:23] just just thing you guys have to get [25:25] right? Correct. [25:26] » Right we can say cuz you're [25:28] you're above what our expected cost will [25:29] be we're not obligated to take anything [25:31] on [25:31] » Yes. Yeah. Um it's still subject to city [25:34] approval [25:35] but you I mean there's there's there's a [25:37] number of line items you know [25:40] you know 10 12 and 15 for example where [25:43] they are higher than everybody else. [25:46] Uh and I know that just the it's the [25:48] discrepancies that you guys have the [25:50] uniqueness of that individual [25:51] contracting approach and their their [25:53] sensitivity to that particular line item [25:55] I can imagine. But you can't go back to [25:57] them and say you know we'd like to we'd [25:58] like these three items to be [26:00] reconsidered or looked at is does does [26:02] this municipal process allow for that or [26:03] not? [26:05] No um [26:06] yeah unfortunately not because of the [26:09] because of the RFP process um [26:12] you know everybody [26:14] uh everybody provide you know has the [26:16] same uses the same parameters for their [26:19] for their costing and and the the final [26:22] price [26:23] um [26:24] can't be changed before the before the [26:26] contract is awarded. After the contract [26:28] is awarded [26:30] then there can be some negotiation with [26:33] with the contractor. The contractor is [26:35] awarded at that price but change orders [26:37] can [26:39] be [26:41] generated by the city that change the [26:43] scope of work. So that's often in [26:46] negotiation. [26:47] » Be I mean I'm just saying cuz we have to [26:49] separate decision by the city as to [26:51] appropriate more money for this [26:53] right. So that's not insignificant. um [26:56] uh ask so it would be against this [26:59] process and perhaps municipal law I [27:02] don't know [27:03] that you can't go to them and say you [27:06] were the low bidder [27:07] after we excluded one you know full [27:10] transparency you're the low bidder [27:12] but you're still above our budget we [27:13] can't award the contract unless you were [27:15] to reconsider these three line items [27:16] which you're you're you're 10% above the [27:18] competitors. Would you consider to do [27:20] so? That's not you can't do that? [27:23] We do you Yes so [27:26] and and just so you know that we have [27:28] discussed [27:29] that [27:30] angle because in a public contract [27:32] that's kind of where you go next. You [27:34] look to VE or value engineer some of [27:37] your items [27:38] and where you do not take away or [27:42] we don't want to adjust and or go back [27:45] to the design team to say we need to [27:49] change the how we go about getting you [27:52] know this design completed. It is maybe [27:55] a reduction of overall footage and we [27:57] can't you know there's a very good [28:00] chance that the contractor is going to [28:01] be willing to negotiate cuz they want [28:03] this project that's for certain. But if [28:04] you [28:05] by your process you award the contract [28:07] at this price what reason do they have [28:09] to negotiate It's not as easy as looking [28:12] why are you well you're $80,000 more [28:14] than the competitor so why can't you do [28:16] it for their cost? Because there are so [28:17] many different moving mechanics we don't [28:20] know what the other contractor may or [28:22] may not have had or if they underbid [28:23] that. [28:24] But [28:25] at this point with them we don't care. [28:27] Realistically we don't care. I mean if [28:28] if if if we're if we're now one to one [28:30] with these folks [28:31] and we want to award it then we don't do [28:33] it. I I get where you're going with [28:34] this. I [28:35] I'm just I'm just saying that. [28:37] We haven't added obstacle here that [28:39] we've got to get this money from this [28:40] from the city and ultimately from our [28:41] residents. And [28:44] that's not a [28:46] you know [28:47] something the city council is going to [28:48] love to be vote on and be comfortable [28:50] with and the the way you propose to do [28:52] it is to put up other projects. [28:54] You know other lanes other maintenance [28:56] projects other other capital [28:57] improvements [28:58] or finding it in the this this this [29:00] broader budget whether it's contingency [29:01] or things like this which probably [29:03] possible but [29:05] depending on what you find out there. [29:07] Yeah [29:08] yeah no for sure. 300,000 for [29:10] Belvedere's is is a big [29:11] » Well let's let's let's shelve that [29:13] aspect over for now cuz if and when we [29:14] go there there's other things to talk [29:15] about certainly. Um [29:17] I would just say that it's a it's a [29:19] competitive public bidding process and [29:22] so you've provided all the parameters in [29:24] the contract documents and these [29:25] contractors have put their best foot [29:27] forward so to speak. This is this is [29:29] what they're proposing to do and I would [29:32] say you're not really one to one with [29:33] anybody until the contract is awarded. [29:36] But they also know your estimate going [29:38] in. [29:39] I mean it's it's it's not it's not a [29:41] it's a coming from the private you know [29:43] construction world that's just lunacy [29:45] lunacy to me. [29:46] But [29:47] Well I get it. If you if you if you're [29:49] attempting to negotiate with one [29:51] contractor before awarding a contract, [29:53] all the other ones say, "Well, how come [29:54] you didn't come to us? We We could We [29:56] could do it, too." And it just, you [29:58] know, it could sort of unravel the whole [29:59] process. I get it. I get it. [30:02] Yeah, and I I mean, to your point, you [30:04] lose all your leverage if if you've [30:06] already signed a contract with them. Um [30:08] but I think I mean, in my in my [30:10] experience, and and maybe you you guys [30:12] can chime in on this, um [30:15] you know, contractors are generally uh [30:18] willing to talk. You know, they they're [30:21] um [30:22] that [30:23] if you say, you know, "By the way, you [30:25] know, we We've got everything signed, [30:26] but [30:27] um [30:28] this is this uh you know, finances are [30:30] very tight for us, and we would like to [30:32] find ways to to reduce the costs. Um we [30:35] we may want to reduce the scope [30:37] somewhere. Um [30:38] but we did notice in your in your uh bid [30:41] that you know, these were much higher [30:43] than than other people's, and Okay. are [30:45] you able to, you know, you know, share [30:47] with us what the you Cuz we can always [30:49] say to them, "So, we're not going to [30:50] either uh [30:52] Ball, you reduce by this amount. And and [30:55] we'll award it to you, otherwise we will [30:56] award it to nobody, and we will we will [30:58] we won't go forward, and we'll do [31:00] another RFP, and we'll just [31:02] we'll rebid the whole thing, and let let [31:03] them it's a little bit of a [31:06] Put that on the table then. If they say [31:08] they won't, then we just put the RFP out [31:09] again, and start the process again. I [31:11] don't think you can Well, well, I don't [31:13] think you can do that. Well, why not? [31:14] Why Why What What Well, look, it's [31:16] public I mean, I'm not a I'm not a I'm [31:17] not a contractor. It changes the scope. [31:19] It changes the scope. I mean, obviously, [31:20] or the timing. No, no, because because [31:22] basically, if if if if if we choose not [31:24] to do this now, realistically at this [31:26] point in time, even with the same scope [31:27] in a rebid process, or modify this [31:29] slightly, we missed the '26 window. [31:31] Right. If you miss the '26 window, it's [31:33] not going to get any less expensive [31:35] knowing, you know, that [31:36] » That, for sure. And the re so the the [31:38] re-solicitation process, what we've done [31:40] is certainly has a a cost that isn't [31:43] going to necessarily, you know, be able [31:45] to be recouped as well in a lot of the [31:47] public, you know, process has, you know, [31:49] there's has to be, you know, completed [31:51] again. But but if we don't have the [31:52] money Yeah, no, I I they might say, [31:54] "Okay, well, we'll we'll help you with [31:56] that." So, I mean [31:58] they might say, "Okay." [32:00] And that's why I know that, you know, [32:01] again, internally within you know, with [32:03] James, I'll try to remember who else was [32:05] on that call, but Stetson, we talked [32:07] about at least areas identified that we [32:10] can discuss, um and it was confident We [32:12] don't have specifics, you know, but [32:14] there were certainly some areas uh to [32:16] look at that we started to discuss. You [32:18] know, [32:19] one of them would be, you know, just uh [32:21] essentially [32:23] I I think again, though in accordance [32:25] with the public contracting, you you [32:27] can't begin these negotiations until [32:29] after a contract is awarded to to one of [32:31] these. And so, I think that's probably [32:34] what the city is looking at. You You [32:35] either have to make the decision to [32:36] award a contract Could we go to all of [32:39] them and say, "This is This is our [32:40] budget. Would you like to Uh I think [32:42] that that that sort of involves [32:44] reopening up the bidding process. I [32:46] don't I can't I think once it's closed, [32:48] you can't reopen it. You would be [32:49] looking at a rebid. [32:51] The issue with the timing is that [32:53] there's an in-water work window, June [32:55] through October. [32:56] And so, to start the process over means [32:59] we wouldn't have enough time to issue a [33:01] rebid, open it all up, and receive bids [33:04] in order to construct this year. So, [33:05] re-bidding the project does mean you're [33:08] you're you're looking at next year, [33:09] 2027. [33:14] Let's be realistic. [33:15] Um [33:17] how confident are we that [33:19] with the ability to start this project? [33:21] First question. Second question is [33:23] um what I would be afraid would happen [33:26] is that there would be a delay, there [33:27] would be a uh uh [33:29] a backlog of this particular equipment [33:30] or something like that, and the [33:31] contractor gets started under this [33:33] price, and says we have to finish it [33:34] next year, and here's the here's the [33:35] cost to do so. [33:38] Well, I think they would be under [33:39] contract to um [33:41] uh you know, to to complete it by [33:43] October uh 15th, I think is what the [33:45] contract says. But just like but just [33:47] like finding a a a you know, Right. [33:49] immovable boulder under the ground, [33:51] there's a there's a there's a delay with [33:52] Blue Hill Stetson. I apologize. Blue [33:55] Iron. Blue Iron. That That can't deliver [33:56] it. It's out of their control, and [33:58] they're they're they're delayed a month, [33:59] and they and they That's I don't for I [34:01] mean, anything's possible, but I'm um [34:03] they're they're they have agreed to [34:06] perform this project by a certain date, [34:08] and if not, there are liquidated damages [34:10] daily that occur if they are not [34:13] complete by that time frame. [34:16] Do we Do we think we'll get this done in [34:17] this time frame? [34:19] I mean, can it be They need to go, yeah. [34:20] Permit I mean, we're you know, there's [34:22] Um there are there are a few factors um [34:25] that that are outstanding. Um [34:28] Yeah. What Like what? So, first of all, [34:31] uh permitting. Uh we're waiting for a [34:32] BCDC permit. Um [34:35] and they are in a review sort of stage. [34:39] Um they have a commission meeting where [34:41] it needs to be approved. Um and which I [34:45] believe it is April 29th, I think, 19th [34:48] or 29th, so it can only be after that. [34:51] Um [34:52] uh PG&E need to complete some uh some [34:56] work in on Beach Road to modify their uh [35:00] their lines, their um [35:02] utility lines, main lines through there. [35:04] » Before we get going. [35:05] Yes. Yeah. Given what we've heard from [35:07] PG&E, is that is that likely? [35:10] Uh they uh we we ask them We We meet [35:13] with them about every 2 weeks uh [35:15] to get progress and and update uh [35:17] updates from them. Um [35:19] they [35:21] assure us that um that that it's that [35:24] it's [35:25] doable to do before before June. Um [35:28] but we have no control over that or or [35:31] over their their work. So, if these [35:33] dependencies um if if Gordon and [35:36] Company, Gordon Ball, can't get started [35:39] to comfortably make the window [35:41] this contract's void then, right? We're [35:42] not, you know, cuz obviously, the prices [35:44] probably wouldn't be held for the next [35:45] year. [35:47] Well, I think there's probably room to [35:49] negotiate, and and if they would like to [35:51] keep the contract for next year um you [35:54] know, they may they may be some uh some [35:57] way to um [35:59] you know, to [36:00] to keep them on board um with some kind [36:03] of uh [36:04] you know, adjustment in price, you know, [36:06] related to inflation or something. There [36:09] There is some flexibility built into the [36:11] way this is structured. There's a [36:12] There's a The in-water work window is a [36:14] 5-month period, June through October, [36:16] but the actual construction period is [36:18] only 65 days. And so, even if they don't [36:21] necessarily have to start on June 1st, I [36:23] mean, that can slide backwards, and [36:25] there would there would still be room [36:26] for them to complete this project. And [36:28] in theory, the the out-of-water work can [36:30] continue outside that window. That's [36:31] correct. It is. Yeah. Yeah. [36:33] Um [36:35] And so, you know, that's [36:36] that's the reason we did try to put this [36:38] out to bid early, to get the bids early, [36:40] to have a contractor under contract [36:42] early so that these these scheduling and [36:46] um [36:47] the the coordination between the city, [36:50] Hadley, PG&E, this can all kind of be [36:52] worked out over the next several months [36:54] until June, and when when the [36:55] construction would actually occur. Mhm. [36:58] » [clears throat] [37:00] » Yeah. Um [37:02] The other The other factor is uh [37:04] easements with uh temporary construction [37:06] easements with the property owners on on [37:08] Beach Road, because uh [37:10] the work that would need to take place [37:12] on their property um for this project to [37:15] to go ahead. I mean, the seawall [37:16] actually [37:17] enters their property at uh you know, [37:20] at at their property lines. Um [37:22] so, it's a couple of feet in from the [37:24] property line, so the the work and the [37:25] structures would would all be on their [37:27] on their land. [37:29] Um [37:30] and we've met we've met with them um [37:32] a few times, uh described the project, [37:35] and we've sent over the uh the easement [37:38] agreements. Um [37:40] So, at this point, we're waiting for [37:41] them to [37:42] um review those. Uh [37:46] And we're we're ready to go for the for [37:48] the April meeting for them uh to to have [37:51] those easements um [37:53] approved by City Council. Um [37:55] And yeah, but but we do have to wait for [37:57] their their signatures, basically, on [37:58] their side. [38:00] How many property owners are we talking [38:01] about again? Uh three property owners. [38:03] Um Yeah. Um [38:05] And one of them has indicated that um [38:09] he's is absolutely willing. Um he's just [38:12] out of the country right now. Um so, [38:14] he's uh seems seems like he's ready to [38:18] sign as soon as he gets back. Uh the [38:20] other two [38:21] uh are new uh new owners of of the [38:24] property. And um [38:26] I think it seems like they're wanting to [38:28] review the the language more carefully, [38:30] and um Was it a [38:32] It's three properties, but two owners, [38:34] right? Cuz there's Yeah. [38:36] Yes. [38:37] » Hadley owns one building, and the Spruce [38:39] Group owns the other two. Yes, yeah. And [38:41] those other two are are owned, I think, [38:43] on paper by two different LLCs, but it's [38:45] the same people. Okay, so that's okay. [38:47] Yeah. [38:49] Yeah. [38:51] So, from a financial perspective, I'm [38:53] looking at [38:54] this overall project budget relative to [38:56] appropriations funding at the top. Um [38:59] we're looking at that 3.475 [39:02] line [39:04] of which includes two $280,000 or so, [39:08] that's going to a separate contractor to [39:11] do the utility work. [39:13] Right? So, that's where we get the 300 [39:15] So, that the the we have a $315,000 [39:17] variance on that line if we take this [39:19] this this bid from Gordon and Ball, [39:21] right? [39:23] Uh yeah, it's it's [39:26] uh without knowing it, we don't have the [39:27] exact number for the contracts uh of the [39:30] other amounts. I would assume the 279 [39:33] that the way you got your 315 was the [39:34] 279 [39:36] um plus the 35 over [39:39] this number. Correct, yeah. With a with [39:41] a little bit of Yeah, yeah. flexibility [39:43] to in case that 279 is over. [39:45] » So, I'm just writing 315 in parentheses [39:47] next to the 3475, which means Right. on [39:50] this page we're 315 over budget on that [39:53] particular line. And you've [39:56] discussed this with Helga and her and [39:58] your recommendations with Robert as well [40:00] is to handle this either within this [40:04] $4.6 million [40:06] total project expenditures [40:08] budget, finding it somewhere, whether [40:10] it's coming out of your hide [40:13] I mean from a project manager [40:14] perspective or somewhere along this line [40:15] of our mass remediation, somewhere [40:17] somewhere through here you think you [40:19] might be able to find some [40:21] money. That that's option one, right? [40:23] Just confirming that's what that means. [40:24] » Yeah. And option two is in the broader [40:27] public works budget. [40:28] Um capital improvement projects, whether [40:30] it's paving or whether it's a retaining [40:32] wall or whether it's a lane improvement [40:34] or something like that, finding that [40:35] money in that over the next couple [40:37] years. Yeah, and and [40:38] and there are two components to that, [40:40] too. So, there are existing CIP funds [40:43] that [40:45] that that [40:46] overlap with [40:48] with with some of the work in this [40:50] project. So, paving for example, there's [40:52] a we have a we have a CIP fund for [40:53] paving. [40:55] And that that could cover the cost of [40:58] the the paving restoration [41:00] in instead of using this [41:02] this account for that for for those [41:04] costs. [41:05] » Use that account. [41:06] » Yeah, exactly. I get it. Um [41:12] Yeah, exactly. And the sidewalk, yeah, [41:13] exactly. [41:14] And and we have it in we have not [41:16] embedded the contingency on this budget. [41:20] Um [41:22] Well, with that [41:24] so [41:25] so with that over [41:29] I'm just saying on paper on paper right [41:31] now we're talking about that one line [41:32] item having a [41:34] a negative variance. [41:35] But that 383 arguably still exists if we [41:40] if we know we have 4.6 in our in our in [41:43] our fund at this point. [41:44] » Yes, right. Yes. So, so yeah, [41:46] sorry I I I [41:48] took me a minute there, but yeah, [41:49] basically that would restore that that [41:51] contingency amount. [41:52] » Yeah, yeah, absolutely. [41:53] So, [41:55] however we decide, [41:57] you may want to work with Helga. I would [41:58] suggest if this is to be recommended to [42:00] the city council, I wouldn't go in with [42:02] this to $315,000 over tier. [42:05] I would I would I would front it by [42:07] saying exactly what you've talked about [42:09] before, that we're going to approach [42:10] this if we award this contract with [42:14] diligent approach to value engineer to [42:16] to line item look at things to to [42:18] recognize this is over budget and see [42:20] where we can get some some some [42:21] potential savings out of this contract. [42:24] May yield nothing, but but that's an [42:25] approach and we certainly should do [42:26] that. I would also try to identify [42:28] specifically where you think this money [42:30] can come from. Meaning if you if you if [42:33] you have known expenditures that you [42:35] think are going to be less than what you [42:36] have up here anyway, [42:38] for example, if you know that [42:40] you know, the [42:42] the [42:43] environmental mitigation costs are not [42:45] $100,000, but they're going to be [42:46] $80,000 much like we had with the repair [42:48] over there on Beach Road. You know, [42:50] you that came in less than we thought we [42:52] were going to commit. So, I'm not saying [42:53] we take that money, but I'm saying if [42:55] you know already where we are, I [42:57] identify it. You could you could [42:59] probably say of that we know we've got [43:03] $35,000 in [43:05] city planning paving sorry, sidewalks [43:08] for the next 2026 2027 we have [43:12] $45,000 in in road paving for the 2026 [43:16] and 2027 budget that we can apply to [43:18] this. [43:20] And our assessment is that that won't [43:21] damage our overall [43:24] value of our infrastructure around the [43:26] city. So, we can apply that those small [43:27] amounts of those larger budgets. We can [43:29] also apply [43:31] $200,000 of contingency to that and [43:33] that's where we think we can make up [43:34] this money and still and still retain [43:36] the 4.630. [43:37] Right. [43:38] » Yeah, exactly. You need to present it in [43:40] a fashion like that. Right. Yeah, and [43:41] that's that's that is definitely what's [43:43] what we had planned was you know, be [43:46] able to be specific about you know, [43:48] about how you know, how this is [43:50] possible. [43:52] And and there would be council approval [43:55] for for some of those changes as well. [43:57] Well, they'll have [43:58] comments and they'll and they'll [43:59] probably stress you know, we really want [44:01] you to push the value engineering and [44:03] and really you know, sharpen your pencil [44:05] on the scope, you know, once you have [44:06] the contract selected to keep within the [44:08] the appropriate public bidding process [44:10] so that we can make sure we we make this [44:12] project as as tight and and not only [44:14] timely, but also it does our our our [44:17] base minimum needs for the for the for [44:18] the for the money we're spending so we [44:20] get as much value as we possibly can. [44:21] Right. Yeah. Yeah. [44:23] Yeah, I yeah, I I hear you and I think [44:27] um [44:28] I we all feel that way. We definitely I [44:30] know I I you know, and and and I [44:32] definitely know Robert does and [44:33] everybody does. [44:36] Yeah, I mean it's it's um it's [44:39] we we all want a want a project that's [44:41] delivered on time and under budget. [44:44] You know, some of this this [44:47] law that we have to [44:49] comply with [44:50] is is a little cumbersome and [44:52] frustrating, [44:54] but you know, from from the time that we [44:56] start meeting with the with the [44:59] contractor, [45:00] there will definitely be you know, a lot [45:02] of emphasis on on um [45:05] keeping costs you know, within budget. [45:08] Um and if I mean you know, I I [45:11] to be fair, I think I think the [45:13] contractors probably get that from from [45:14] everybody that they all the cities that [45:16] they work with. Um But yeah, and I mean [45:20] you know, some of the costs, you know, [45:21] and I can I can point to some in on here [45:23] that's um [45:24] we anticipate [45:26] not not having to pay for example, [45:29] environmental mitigation costs. [45:32] BCDC [45:33] uh [45:34] may ask us to you know, mitigate for [45:37] much more than than we are already. Um [45:40] but it seems like they're not [45:43] um [45:44] in in our discussions with them so far, [45:45] they haven't said that they that they [45:47] will that they will and they've accepted [45:49] our [45:50] submission with with the mitigation that [45:52] we've proposed. Um So, [45:55] uh you know, for example there, there's [45:56] potential for that full 100,000 to be [45:59] available to be to be moved into another [46:01] sort of road. Um [46:04] Yeah. Um [46:06] Yeah, and then [46:08] you know, land surveying and mapping for [46:09] example, that's another item that's we [46:11] haven't we haven't had to Yeah, I you [46:14] know, I I I Yeah. You understand me. [46:17] Just as you prepare it, sharpen your [46:19] pencil in because you you know, come in [46:22] solution oriented to the council. [46:23] » Right. Right. Yeah. Yeah, okay. [46:26] Yeah, appreciate that. [46:31] Are you guys probably I mean [46:33] you've sat down with them. You've you've [46:35] you've you've met with them. Are you [46:37] comfortable with them being a partner in [46:39] in if not that it it doesn't sound like [46:41] it's a big job for them, but it's a big [46:42] job for us. [46:43] » Yeah, no, we haven't actually met with [46:44] them. [46:45] Yeah, we we wanted to but you know, I [46:47] actually I I spoke to [46:51] Gordon Ball yesterday on the phone. Um [46:54] And [46:56] um but we had wanted to have this [46:59] meeting before we you know, [47:01] provided any kind of official [47:03] communication to especially well, to the [47:06] other contractors. Um and it's obviously [47:08] not going to be an easy phone call with [47:10] Marcus, but um [47:12] yeah, that's So, Peter, I mean so [47:15] if we make a recommendation, we're [47:17] making a recommendation knowing it's [47:18] higher than the budget, although with [47:20] your mitigating [47:22] recommendations, it may be lower, but it [47:24] sounds like it's it's worth discussing [47:25] among the city council anyway. I mean [47:27] it's it's not so far out there. [47:28] » Absolutely. It's [47:30] it's achievable potentially. Well, I [47:32] mean [47:33] I mean I'm sure maybe Glenn you less so [47:34] than us, but we're [47:36] we're just all reacting to that like [47:38] public process is you know, I wouldn't [47:40] bid my house with that process. You [47:42] know, [47:42] and it's just a it's just a just a it's [47:44] sort of frustrating, but um [47:47] I think you need to present it that you [47:48] know, this is the process and and it's [47:51] not it's not unusual to have our [47:52] estimate be be a little bit short of the [47:54] of of the in fact, the dynamic of the of [47:57] the process to to to almost have that be [48:00] the the norm. [48:02] But there is an opportunity [48:04] and I and I do believe it's worth the [48:06] time because because we have a lot to do [48:07] between BCDC, PG&E and the easements um [48:11] which would at the end of the day if [48:12] those if those don't come through, [48:14] you know, this project's not going to go [48:15] ahead anyway. So, work aggressively with [48:18] with the selected contractor to and it's [48:21] not like we have much of a choice. We [48:22] have to choose [48:23] the non-eliminated low low bid, right? [48:26] Right. Yeah, and and I think [48:29] if if we're choosing if we're choosing [48:30] any, yeah. [48:31] Right, yeah, exactly. And and I I think [48:33] that you know, if if if there was [48:35] another close bid for example, and and [48:38] you know, there was a way to parse [48:39] through the qualifications, um then then [48:43] we might be having a different [48:44] conversation, but I think you know, we [48:46] have one apparently bidder. The the next [48:48] one is you know, [48:49] 500,000. I mean you know, higher. I [48:52] touched on this last meeting, too, and I [48:53] know this will come up in the city [48:54] council is [48:57] and it's hard it's hard to weigh this [48:59] against known risk failure there, but is [49:03] this is this something that you know, in [49:04] a year or two might be might be better [49:06] pricing? [49:07] I'm not saying non-inflationary pricing, [49:09] but just better pricing relative to the [49:11] war, the supply chain issues, steel [49:13] prices, gas petroleum prices. Good good [49:15] question. And currently so far, we [49:17] actually [49:19] do a lot of supply chain analysis for [49:21] our projects nationwide. [49:23] So, right now I do know that most of the [49:27] sheet pile is coming from US. So, no [49:31] tariffs. So, that has not been impacted. [49:34] Currently, the price of oil has not [49:37] impacted the sheet pile pricing. And [49:40] that was something that, you know, once [49:42] we started to see what was happening in [49:44] around and that's typically one of the [49:45] first triggers is the price of oil will [49:47] just start to impact everything for [49:49] production and [49:51] specifically sheet pile. So, at this [49:54] point we don't foresee [49:56] any changes and we're that close that it [49:59] would be not a major escalation. We may [50:02] have more impacts if we push the project [50:04] and [50:05] you know, without [50:07] you know, we're talking, you know, two [50:10] years down the road we're probably Even [50:12] these folks these folks gave these bids, [50:14] you know, these orders are good. The [50:16] price associations have been two or [50:17] three weeks, right? Two three and a half [50:18] weeks. [50:19] Um [50:20] would it could or would they come back [50:21] and say there's a 10% premium based on [50:24] recent events? [50:26] They I do know that there there is a [50:28] level of like they are entitled to that, [50:31] but I don't know the specifics [50:32] personally to what that is. [50:33] » They could do that. They could come back [50:34] with a I'm not sure to the specifics. [50:36] So, it all depends on I think on the [50:38] specifics of the contract. I'm just not [50:40] fully aware they are, you know, entitled [50:43] to that. [50:44] » [clears throat] [50:45] » All the good scenario I mean as far as [50:47] whether the contract [50:49] Yeah, yeah, two or three two or three [50:51] as as as they go lower their price they [50:52] can ask us to raise the price. No, this [50:55] is what the contract would be. Yeah. [50:57] And that's yeah, they're they're hanging [50:58] their hat on that and knowing that okay, [51:00] well, you know, we have to [51:02] we get a word once, you know, supposed [51:04] to that we you know, move specifically [51:06] on the sheets that would be the big [51:07] thing. So, I mean if it's if it's if [51:09] it's [51:11] legitimately now a cost of theirs big [51:13] it's [51:14] choose not to take the contract, right? [51:16] Or the or are they obligated to take [51:17] this contract? [51:19] Well, they're I think yeah, they have [51:21] you Julian can speak to this as well. [51:22] Again, are they obligated or that's [51:23] where they're yeah, that's where we have [51:25] a bond. Mhm. A bid bond. [51:29] Yeah. [51:31] » [clears throat] [51:32] » Well, so this committee we were going to [51:34] make a recommendation. It sounds like [51:36] the staff's recommendation is to to [51:38] recommend city council to accept the bid [51:41] of Gordon [51:42] Ball. [51:43] Um are we ready to decide on that with [51:46] the committee? I don't know how we what [51:48] do we further questions or discussion? [51:51] I would I would [51:54] edit that a bit in the sense that [51:57] it's not this committee's decision to go [51:59] ahead with the project. [52:00] Right? From a from a broader risk [52:02] perspective from a broader financing [52:04] perspective and from a broader um [52:06] operations perspective. But in in the [52:08] event the council is clearly said to us [52:09] at a retreat hence the formation of this [52:11] committee is um [52:14] we want this project to go forward. It [52:16] should it go forward we want you to do [52:18] the proper due diligence and proper [52:19] transparency to make sure that it's done [52:21] in a fair equitable manner and that [52:23] you're getting as much value for the [52:24] process as possible. [52:25] I think we should that's what we should [52:26] say is that given the process and given [52:28] the understanding of the project and the [52:29] scope, [52:31] this is the best contract for the job [52:32] and given the conditions that we talked [52:33] about a second ago that you're going to [52:35] post awarding of the contract value [52:36] engineer and look for look look for [52:39] potential values in the scope itself and [52:42] um [52:42] here are ways we can potentially [52:43] mitigate the cost in the existing [52:45] budgets or other budgets. Um that's the [52:48] recommendation to choose Gordon Ball. [52:51] What is it the [52:52] » Yeah, I think it should be yeah. We're [52:53] not saying the project should go ahead [52:54] with this. Ultimately, [52:56] you know, five people up there with [52:57] public comment are going to decide [52:59] whether this is this this, you know, [53:01] $4.6 million is something the city sees [53:03] a priority for the next, you know, year [53:05] and a half to [53:06] to mitigate this risk. Yeah. Yeah. [53:09] Um so it sounds like it it's um [53:13] on the understanding that there will be [53:15] you know, aggressive um [53:18] uh [53:21] what [53:22] I don't want to say reduction in cost [53:25] I mean, you know, you know the people up [53:27] there myself and and what I mean [53:30] they're going to say, you know, find a [53:31] place, you know, figure out the 315, [53:33] right? You know, we'd rather not have [53:34] that. We'd rather we'd rather you, you [53:36] know, get it out of the get it out of [53:38] the project one way or the other, you [53:39] know, either sharpen your pencil from a [53:40] scope perspective, value engineer it or [53:42] if you have to do exactly what what what [53:45] you guys talked about is is, you know, [53:47] take a portion that that's responsible [53:49] of a paving and a sidewalk budget or [53:51] other public works budgets and apply it [53:53] to this recognizing that you're you're [53:55] you're you're stealing from Peter to pay [53:56] Paul, but but be confident that you're [53:59] you're doing that in a in a in a in a [54:01] balanced way that you're not [54:03] jeopardizing Paul in that scenario. [54:05] They're going to want to see that [54:06] information. Right. Yeah. Yeah. [54:09] And and just just be confident that you [54:10] thought about it so that if you're not [54:12] able to lower the price [54:14] that we're not we don't have a, you [54:15] know, day one $315,000 [54:17] hit to this budget. You don't want to go [54:19] through a project day one with that kind [54:20] of, you know, budget deficit. [54:23] » For sure. [54:24] Um [54:25] Yeah, absolutely. I mean, I I [54:27] » Help you with the staff report too. I [54:28] mean, like I'm don't stress about that. [54:30] Between Robert, you and me and Helga we [54:31] can figure out how to Yeah. write that [54:33] up. Yeah, that that [54:35] I really appreciate that. Um [54:38] Yeah, and and I think I think part of [54:40] the [54:41] um [54:42] you know, one of the questions that that [54:43] we'd have for you is is uh whether you [54:45] think, you know, where would be a more [54:48] appropriate um place to to look for um [54:51] savings uh and yeah, so [54:54] you know, see our existing CIP funds [54:56] versus scope of the projects and um [54:58] yeah, these kind of Well, that's kind of [55:00] a contract. I mean, I mean, yes [55:03] the the city can start with, you know, [55:06] what what what what um [55:08] parks and lanes what what what broader [55:10] public works infrastructure are you [55:11] doing that one you don't think you're [55:13] going to get to. Every year we don't get [55:15] to projects, right? That happens all the [55:16] time. So so so so [55:19] figure out which are the ones we don't [55:20] think we're going to get to [55:21] and roll that into '27 '28 or '26 '27 or [55:25] even '26 '27 '27 '28 and that's that's a [55:28] that's appropriate that potentially [55:30] could be used um for this recognizing [55:33] you're just kicking a can down the road. [55:34] It's not a savings, but [55:36] but it's a new public works budget next [55:38] year. Right. Yeah, exactly. And and if [55:41] through your personal or a professional [55:43] assessment [55:44] that [55:45] project can be deferred for that amount [55:47] of time. I mean, that's got to be part [55:49] of it as well. [55:50] Yes, exactly. And I think I actually [55:52] didn't get to that part of when I was [55:54] talking about the CIPs and the and the [55:55] paving um yeah, the It's got to be based [55:58] on some assessment [55:59] Well, exactly. Yeah, [56:01] I mean, because there are as you say [56:02] projects that roll over every year and [56:04] there are also, you know, sort of [56:07] forecast funds for [56:09] for for different projects that you [56:12] know, won't be used for one reason or [56:13] another and and can be pushed off to the [56:16] following year. Yeah. [56:18] And we'll just see if there are any I [56:19] see Patrick has joined. If there are [56:21] comments from Patrick or any I don't [56:22] know if there are any other Robert or [56:23] Rob or Glenn or anyone else who might [56:26] not have a chance to speak about this [56:27] and [56:30] Robert, Patrick, Glenn, any [56:35] Hey, [56:36] » [clears throat] [56:36] » I can go ahead and comment. I've just [56:38] been listening to this [56:40] well, to the whole conversation, but on [56:41] this last part we we did actually meet [56:44] Tony, myself and Helga and take a look [56:46] at our 20 our current budget in terms of [56:49] rollover and then what we're looking at [56:51] for next year in terms of projects that [56:53] have funds assigned, but not necessarily [56:55] a project earmarked for those funds. So, [56:58] I think there um you know, to Peter and [57:00] and Tony to your point there is enough [57:02] flexibility in the next, you know, this [57:04] current year and next year [57:06] we need to we we can find a way to pay [57:07] for this 315. Um but but the broader [57:10] point is let's let's work really hard [57:12] and try and bring the cost down, which [57:14] is of course what we'll present to city [57:15] council. [57:21] Yeah, [57:22] and so and this is just Robbie, you've [57:25] just reminded me of another thing that's [57:27] um [57:28] we would like to emphasize is that we [57:30] have no plans to request more funds from [57:34] from reserves [57:35] uh from general fund or critical [57:37] infrastructure reserves. [57:38] Um the you know, all the all the cost [57:41] savings would come from existing and [57:43] forecast funds and from the projects [57:46] itself. [57:47] Yeah. [57:49] That's a bit that's that's [57:50] sort of splitting hairs because it's [57:53] Well, [57:54] it's just going to be it really comes [57:55] from the city [57:56] » All all the same funds. So, it's a [57:57] matter of Right. [57:59] » Whether it's [58:00] in an existing appropriation or not. [58:02] Right. Yeah, yeah, no, absolutely. We [58:05] can't print money. So, it's it's at the [58:07] end of the day it's coming from [58:08] something or we're not doing something. [58:11] Oh, yeah, exactly. We're putting [58:12] deferring something or yeah. But I I I [58:14] think Robert said it exactly right and [58:17] Yeah. we can we can endeavor to to make [58:19] that presentation and I'll and I'll [58:20] certainly [58:21] be part of that and help explain it to [58:23] the council as we go forward. [58:25] Yeah, well, thank you. Yeah. [58:27] Okay, well, there's no further [58:29] discussion. It seems like we should try [58:31] and bring our our committee's [58:33] recommendation to our to a vote and [58:35] I think the movement is that the sub [58:38] committee [58:39] will vote to [58:41] um [58:42] I guess [58:44] that the vote along with the the staff [58:46] has made the proper recommendation to [58:49] the city council subject to the [58:51] adjustments and sort of [58:53] financing and payment. Um [58:57] and I I I guess we're not quite [58:58] endorsing that the the committee should [59:00] do this, but the committee supports the [59:01] staff's recommendation. I think you said [59:03] it exactly right that that that we we [59:05] support the recommendation of the of the [59:07] city staff that [59:09] Gordon Ball is the is is the contractor [59:11] to select and that [59:13] um [59:14] uh we encourage the the staff in the [59:16] presentation to city council to to focus [59:18] on [59:19] you know, value engineering and and and [59:21] scope considerations and then identify [59:24] where the [59:25] surplus $315,000 can come from within [59:27] existing budgets. [59:30] I was um [clears throat] may I move into [59:32] the vote on that? [59:34] Uh second that. [59:35] I can second that. And all all in favor, [59:38] I [59:40] I think it's just the three of us [59:42] Well, thank you. Yeah, and hopefully the [59:44] the speaker caught all of the [59:46] caught all of the language in there. [59:48] It's much better than the last one, I [59:49] know that. [59:50] Um so, the microphone of the speaker, [59:52] yeah. [59:53] And so, this may be the final time we'll [59:55] have to meet, I guess maybe subject to [59:57] Yeah, I don't know. [59:59] Robert, remind me, do we think it makes [1:00:01] sense to because because there's still [1:00:05] as you mentioned between BCDC, Genie, [1:00:07] and the [1:00:08] easements and the ultimate, you know, [1:00:11] issues of permits and getting going. Uh [1:00:14] and and after all, this committee [1:00:16] is designed to be the eyes and ears of [1:00:19] the community just just just just to [1:00:21] understand and, you know, either [1:00:22] anecdotally or or publicly make a [1:00:23] comment that, you know, we've been aware [1:00:25] of what's going on. I'd suggest another [1:00:27] in, you know, [1:00:29] if not one or two month at monthly [1:00:31] intervals, just to check in where you [1:00:32] are in this process [1:00:34] um so that the next month you presumably [1:00:36] would have received city council [1:00:37] approval, you presumably would have [1:00:39] engaged in a contract with Gordon Ball, [1:00:41] and have those initial discussions, and [1:00:43] have a tentative timeline for the [1:00:45] project. That would be So, in about a [1:00:47] month's time from now That's what I [1:00:48] think unless you think that's that's too [1:00:50] soon. [1:00:51] Um [1:00:52] No, I think I think there would be uh [1:00:56] quite a few there'd be a few updates in [1:00:58] a month's time. Um and we can [1:01:01] possibly, you know, change the date if [1:01:03] if we need to if we're waiting on for [1:01:04] some, you know, some [1:01:06] um decision or something. Robert, that's [1:01:08] not surpassing the the the um [1:01:12] charter or design of this subcommittee? [1:01:16] No, the the subcommittee is ad hoc. We [1:01:18] can't exist forever. Um but if we have a [1:01:20] clear ending point which may align [1:01:23] you know, with the duration of the [1:01:24] project and maybe at the close out uh [1:01:27] we'll have a final report that goes back [1:01:29] to council. I think that's still the [1:01:31] scope. Yeah, I would agree. I think it'd [1:01:33] be good to meet in another month. [1:01:35] And actually maybe throughout the until [1:01:36] the project is completed I absolutely We [1:01:38] discussed even having maybe one [1:01:39] committee member available for whether [1:01:42] it be every construction meeting, but at [1:01:44] least it's certainly up to speed whether [1:01:47] it's even also a follow-up after our [1:01:49] construction meeting with the [1:01:51] contractor. I'm under the impression [1:01:52] we'll be doing those weekly. Could be a [1:01:54] bi-weekly check-in or something of that [1:01:56] nature, but I think that it's very [1:01:58] important to keep you guys in the loop [1:02:00] throughout the process, too. You know, [1:02:02] we'll also have the have the contract [1:02:04] happening, [1:02:05] it sounds like. So, you'll you'll bring [1:02:07] this to council in April? [1:02:08] Yes. Yeah, that is the plan. Okay. Yeah. [1:02:13] Um [1:02:14] Yeah, so April 13th [1:02:16] um and [1:02:18] yeah, unfortunately, I'm going to be out [1:02:20] of town for a couple of weeks here, but [1:02:21] I have the the draft staff report and um [1:02:26] you know, uh I think the finance the [1:02:29] fiscal impact section is is the part we [1:02:31] need to um [1:02:33] drill down into. Yeah. [1:02:35] But uh [1:02:37] yeah, that and hopefully the [1:02:39] construction easements [1:02:40] and maybe even a contract for the other [1:02:43] portion of the work if that can all [1:02:44] happen in in in April, [1:02:46] uh that would be There's no bid [1:02:49] requirement for that? Is that the bid [1:02:51] threshold or something? They would [1:02:52] typically be, yes, [1:02:54] but there is in this case [1:02:57] what's called a sole source [1:02:58] justification [1:03:00] for for this for this contract [1:03:03] because they have specialized [1:03:06] knowledge of that company. [1:03:07] » Installed it. [1:03:08] Yes, exactly. Yeah. Yeah. [1:03:12] Yeah, and [1:03:14] but that's, you know, these are all [1:03:15] updates that can can come at the next [1:03:17] meeting for sure. Yeah. Okay, so we'll [1:03:19] plan on having a meeting probably late [1:03:21] April after the city council meeting and [1:03:23] after progress has been made. Um [1:03:25] and then we'll see [1:03:26] periodically after after that. Um would [1:03:29] you like to pencil in a date now that we [1:03:30] can [1:03:32] uh [1:03:32] or or uh [1:03:35] Would you Yeah. prefer to to wait and [1:03:38] have a a poll maybe further down the [1:03:40] line? If we if we sort of have a a [1:03:42] target date that we are, you know, can [1:03:44] then confirm, I think um [1:03:46] All right, for me that always seems to [1:03:48] work work better. [1:03:50] So, maybe the week of the 27th? [1:03:53] Okay. [1:03:55] I'm gone that whole week. [1:03:57] Are you there the week of the 20th? I'm [1:03:59] there the 20th. [1:04:02] I I'm here the week of the 20th. [1:04:05] When does city council act? Uh you said [1:04:08] it was the [1:04:09] 13th. 13th, yeah. So, that's great. [1:04:12] So, that's a week after the city council [1:04:13] meeting. But you might not have made [1:04:15] much progress with the contract. Yeah, [1:04:17] it might be a little soon. Might shoot [1:04:18] for beginning of May, like the week of [1:04:20] the 4th. Early May might be better. I'm [1:04:21] away the week of the 4th, so I can do [1:04:23] the Monday or Tuesday. [1:04:26] And there's always, you know, we can [1:04:28] there's no reason this for emailing [1:04:29] communication Personally, I could I [1:04:31] could join a Zoom call. [1:04:32] » Or even a remote call if that's Yeah. [1:04:34] Yeah, I know it works for you. I guess [1:04:35] it would do we if we're not voting on [1:04:37] things necessarily, we don't have to all [1:04:39] be present, correct? And [1:04:41] I don't know what the or can we not have [1:04:42] a meeting? It's not a Brown Act, I don't [1:04:43] believe. Right, Robert? [1:04:47] That is correct. I don't believe this is [1:04:49] a Brown Act. I don't believe [1:04:50] So, I mean If this same group is meeting [1:04:53] Sorry, sorry. If this same group is [1:04:55] meeting meeting the [1:04:57] you know, the the core group that we [1:04:58] have here today, then it is a Brown Act [1:05:00] meeting. If it's just one person [1:05:02] assigned to meet with staff and what's [1:05:04] not [1:05:06] Well, I I guess our question, Robert, is [1:05:08] if [1:05:09] we couldn't do this as a complete remote [1:05:11] meeting. [1:05:15] Right, we need to have a quorum. Then [1:05:16] then the majority a majority of the [1:05:18] members have to be in person. [1:05:20] It worked out today because only one [1:05:22] person [1:05:23] member of that sub of the subcommittee [1:05:25] was was connected remotely. [1:05:28] Do we want to shoot for say Wednesday [1:05:30] the 6th and [1:05:32] if John can't I did do it remotely, but [1:05:34] I'm happy to do that remotely. Yeah, [1:05:36] sure. Let's do that. Okay. Let's May the [1:05:39] 6th. [1:05:43] 2 2 p.m. Or sorry, 1 p.m. [1:05:47] Yeah, if that time works for everyone. [1:05:51] Keep it consistent, I guess. [1:05:55] Okay. [1:05:57] All right, I just need to raise one [1:05:59] point. [1:06:01] Yes, a design point. Yeah, uh go ahead. [1:06:03] Yeah, that's okay. [1:06:05] So, this is addressed to Stetson. [1:06:07] Uh has to do with the height of the [1:06:09] sheet piling. [1:06:11] Larry's question to you apparently was [1:06:13] misunderstood. [1:06:15] He's asking why not [1:06:18] maintain the level the [1:06:20] » [clears throat] [1:06:20] » Same as the existing sheet piling. [1:06:25] Oh, the 2019 sheet piling, the top of [1:06:27] it. [1:06:28] Um [1:06:29] » Maintaining that height. It was It was [1:06:32] primarily to save cost to to not have a [1:06:35] higher sheets and more concrete backfill [1:06:38] and any any fill you put along the wall [1:06:41] um requires a mitigation from the [1:06:45] jurisdiction. So, the wall where [1:06:47] existing sheet piling [1:06:49] is the new sheet piling. It's It's [1:06:52] approximately a foot lower. [1:06:55] You're cutting it off. [1:06:57] You're cutting off longer pieces anyway. [1:07:00] Maybe. I mean, it depends where they [1:07:02] where they drive it to. Well, [1:07:04] I could drive it in and drive it in [1:07:06] those. These aren't being driven. [1:07:09] These aren't being driven. Yeah, they're [1:07:10] being pressed. There's no driving. [1:07:13] There there will be a It's that We did [1:07:15] We did We did design it so there's a [1:07:17] It's a It's a It'll be a gradual [1:07:19] transition, so it's not going to be a an [1:07:21] abrupt, you know, [1:07:22] 90° change. It's There is going to be a [1:07:25] transition [1:07:27] over over a period of a horizontal [1:07:28] distance, so [1:07:29] » And and the 2019 [1:07:31] repair has one as well. There's a a [1:07:33] little slope down to two different [1:07:35] elevations. [1:07:37] Um but to add [1:07:38] Julian to the reason for keep reasons to [1:07:41] keep it keep it down, one is the [1:07:43] permitting [1:07:45] because permitting agencies um [1:07:47] were [1:07:49] happy to see that if that's the the all [1:07:52] the pile would be kept below the the [1:07:54] height of [1:07:55] where the sea sea lettuce reaches [1:07:58] because that would be colonized much [1:08:00] more quickly by sea lettuce and [1:08:02] barnacles and so on. So, the lower the [1:08:03] better for them [1:08:05] as far as habitat goes. [1:08:07] Um then also aesthetics. Um right now [1:08:10] from from the the homes along there or [1:08:13] from from the water [1:08:15] um [1:08:16] it's it's less visible [1:08:17] the the lower down it is. [1:08:19] Um so, [1:08:21] that along with the embedding the [1:08:23] uh the gravel into the top of the [1:08:25] concrete along there um [1:08:27] you know, sort of the the permitting and [1:08:29] and somewhat for aesthetics. So, we're [1:08:31] talking about a foot. [1:08:33] About a foot, yes. Yeah. Yeah. [1:08:36] Yeah, so I mean, and if you look at the [1:08:38] the 2019 piles, there's a point on the [1:08:40] piles where the barnacles stop. And then [1:08:42] above that is just the the metal, you [1:08:45] know. So, the idea here was that [1:08:47] the this would be completely below that [1:08:49] that level of [1:08:51] you know, habitat. Is Is there Is there [1:08:54] inherently a [1:08:55] you know, for the people viewing it from [1:08:57] the water side or from the [1:08:59] homes out there? Obviously, [1:09:01] um [1:09:01] I mean, there is every every aesthetic [1:09:03] appeal to having it consistent as as [1:09:05] much as consistent as as possible. Um [1:09:07] but you're saying there's there's [1:09:09] there's no structural need for it cuz [1:09:11] that the note we got today clearly said [1:09:14] that the the the structural requirements [1:09:16] are really down below as opposed to [1:09:17] above. No structural need for it. My my [1:09:19] biggest concern is is it would add [1:09:21] additional mitigation measures and [1:09:23] potentially hold up the BCDC permitting [1:09:25] process. Um you guys need to sort of [1:09:27] give us a thumbs up and thumbs down [1:09:29] this. I mean I see Larry's point that it [1:09:30] might look better if it was less It was [1:09:33] all the same. jig jaggy. [1:09:35] But not enough to delay or or the [1:09:38] project or to have a cost consideration [1:09:40] or have [1:09:42] you know, permitting issues with you [1:09:43] know, the lead agency there. Right. [1:09:45] Yeah. Or even if we can do it from an [1:09:47] environmental perspective whether [1:09:48] whether ours are are [1:09:51] review covered that scope. But then [1:09:53] again, we did we're we're we're we're [1:09:55] we're we're [1:09:56] we're we're I'm leaning on the broader [1:09:58] review, right? So that matter that [1:10:00] should matter. The environmental review [1:10:01] should matter, right? [1:10:03] No, so that it wouldn't I don't think [1:10:05] impact the EIR if it was you know, if if [1:10:09] what you're talking about is is the 2019 [1:10:11] sheet piles cuz I think that's [1:10:14] probably what was kind of envisioned as [1:10:17] the sort of a comparable Yeah, exactly. [1:10:20] Yeah, I don't know if Julian if you have [1:10:21] any thoughts on that. Well, it would [1:10:24] require going back to all the agencies. [1:10:26] It would be it would be more fill in the [1:10:28] jurisdictional waters. So we'd have to [1:10:29] restart or you know, renegotiate with [1:10:32] all the agencies and there would be a [1:10:34] cost increase. [1:10:36] Yeah. [1:10:38] Any answer? [1:10:39] » If I could chime in here too, from from [1:10:41] what we've talked about on this project [1:10:44] from the beginning we we always [1:10:45] envisioned I think this aesthetic [1:10:47] improvement that we're talking about [1:10:49] whether that be a cap or riprap or some [1:10:51] other kind of concealment method [1:10:53] for hiding that you know, the steel [1:10:55] sheet piles and the concrete. That would [1:10:57] always be coming as kind of a phase two. [1:11:00] And it's just a matter of when we can [1:11:01] get that done in terms of you know, [1:11:03] perhaps the larger project or when funds [1:11:05] are available. But you know, the [1:11:08] structural [clears throat] component [1:11:09] holding up the wall and you know, [1:11:11] keeping the cost down low was always our [1:11:13] primary target at least in the short [1:11:15] term. [1:11:17] Okay, I'll tell Larry. Thank you. [1:11:21] Yeah, he raised it last month also. And [1:11:22] I think [1:11:23] Yeah. You should I don't know if Larry [1:11:25] got that note you sent around today. Um [1:11:27] Um I I think he uh [1:11:30] with with the response from the state [1:11:31] and I think he must have because I think [1:11:33] that's what what you might be referring [1:11:35] to then for the [1:11:37] as far as the the misunderstanding. I [1:11:40] think that's maybe what what he was [1:11:41] referring He brought it up last week too [1:11:42] last month too. So he he may or may not [1:11:45] have it well. [1:11:48] » Right. Yeah, and I I mean I I [1:11:49] misunderstood it too actually cuz I [1:11:51] thought he was talking about having a [1:11:53] higher up [1:11:54] you know, [1:11:55] to support the wall. I think he just [1:11:57] wanted it to match what was there. Yeah, [1:11:59] I understand. And yes. [1:12:01] And so [1:12:03] Okay, I think we can adjourn unless [1:12:04] there's any further comments. Thank you [1:12:06] so much. So many thanks. Thanks. Yeah, [1:12:09] thank you all. Thank you all so much. [1:12:11] Thanks Robert. [1:12:11] » Thanks Robert. [1:12:16] What