[0:00] Hey, Jeremy. [0:09] » Okay, once it's 8:00, we'll go ahead and call [0:12] a special meeting for the Prospery Town Board to order for acceptance. [0:17] Um bids on the construction project. [0:22] Jared, do you want to take it over? >> Yeah, good. Several items here to review [0:26] and discuss. The first is would be uh leftover funds that the town has for [0:31] the Wastewater Treatment project. We have the phase two work, [0:36] uh which included two project areas that we had [0:41] eight bidders. So, it was well attended. Um and the low [0:48] um responsive responsible bidder for the project was Copper Ridge Contracting [0:54] with a total base bid of $254,970. [0:59] This is well below the engineer's estimates. Uh there are funds available [1:04] to complete the project through the IFA SRF project. So, engineer recommends [1:10] that town accept the low bidder of Copper Ridge Contracting. [1:16] » Now, I'll have a motion to accept it. >> Make a motion we accept the lower bid of [1:20] Copper Ridge Contracting. >> And I'll second that. All in favor? [1:25] » Aye. >> Any opposed? Hearing none. [1:34] » And we also have uh the the town is requesting additional funds using the [1:40] same IFA SRF program for two pieces of equipment here. Uh the [1:46] first of which is uh for [1:54] Uh this is the CCTV camera quotes. So, the low responsive responder was [2:00] Insight Vision at $11,128. [2:06] So, engineer recommends town proceed with Insight. [2:12] » Make a motion we accept the bid the given by Insight Vision for $11,128. [2:19] » I'll second that. All in favor? [2:22] » Aye. >> Any opposed? [2:25] Hearing none. >> What was that number again? [2:28] » $11,128. >> Oh. [2:30] » Mhm. [2:34] And then lastly, what the town has also has other piece of equipment which the [2:38] town will be installing themselves. Said equipment is [2:43] manhole insert dishes and didn't see three quotes for this as well. [2:50] The low responsive responder was Sealing Systems [2:55] Inc. with 80 inflow dishes at $50 a piece for [3:00] $4,000. So, engineer recommends town proceed with Sealing Systems Inc. [3:07] » Uh make a motion that we accept the bid given by Sealing Systems Inc. for four [3:11] grand for manhole insert dish dishes. >> I'll second that. All in favor? [3:17] » Aye. >> Any opposed? [3:20] Hearing none. [3:25] These documents here are doing the same thing. [3:29] » I want to hear that out in the [3:30] future. >> Yeah. [3:32] » Two certifications. >> Okay. [3:34] Okay. And then um [3:37] just give a quick update some other business here. So, the [3:41] we'll send these documents over to SRF for phase two and improvements. That [3:47] should proceed a little bit quicker than the equipment. Uh the equipment will [3:52] require a PER amendment and we have to submit a publisher's affidavit first [4:00] giving to note what the project entails what [4:03] the changes are and then once the publisher's affidavit is complete in the [4:07] paper then we'll submit the ER amendment request. Chris will have to sign on [4:12] that. So the the second task I have here I guess inside all this [4:19] equipment and bid acceptance is to give I recommend to give authorization to [4:25] Chris Anderson the town council president the ability to execute any [4:30] further SRF documents so you don't have to have any additional special meetings [4:35] to sign the documents necessary to keep the project moving forward. [4:42] » Uh make a motion to to allow Chris to uh conduct business uh [4:49] for the town clerk be uh based on Drew's recommendation there. [4:54] » I'll second that. >> All in favor say "Aye". [4:58] Any opposed? Hearing none. >> So once we get going here get [5:02] publisher's affidavit we'll work with T Kim on that to what we need to provide [5:05] in the paper and then I'll have some other further documents for you to sign [5:09] and then there will also be like the notice of award [5:13] uh notice to proceed we can certainly do that during uh town council meetings [5:18] we'll we'll do so but if we need to keep it moving forward we'll just send those [5:22] paperwork over to you. [5:26] I believe that's all uh John Ben Redman. [5:32] So with the Hurricane net project [5:37] So before you guys purchase we'll have to go through these couple of other BS [5:41] steps first. You got it. [5:53] » So, any other business I had was [5:58] uh we go ahead and fill in the BZA. That's that. [6:07] That's the one thing. >> What do you mean there's an opening? [6:09] » It's an opening. Just two. [6:18] Oh, that's advice. All right. So, we did fill up [6:22] two open spots on the BZA. Um [6:26] so, the first one was appointed [6:31] uh by council president. And then they also [6:35] had the planning commission member, so Fred McIntyre is taking that position. [6:40] And then the other open spot was uh just for citizen member appointed by council [6:46] president. Neighbor and he's going to take that spot. [6:51] So, we still do have an open spot on the advisory planning commission and we're [6:57] going to do that next. [7:00] » You said who's taking spot on which part of the start? [7:04] » BZA. >> BZA. [7:05] » As citizen member. >> Yes. [7:07] » And the other one is has the planning commission member. [7:15] Is there any other business that needs to be brought forth? [7:19] » I know we had an outstanding was it on the we did get the new pump stuck in the [7:24] uh return station and that's running fine. We have no problems. We generally [7:29] we'd like to go ahead and pull the second one out which we'd do as [7:31] maintenance but we had the one sitting there that came [7:35] in shop that we never made a motion on to do not to do and I felt like I'm [7:41] compelled to get them some It's like, "Hey, we're going to do [7:45] something with it. And if you want to wait till the next board meeting to [7:47] think about it, but it's the one that was going to cost us [7:50] about $4,700. So, basically 2/3 or, you know, [7:54] better than the uh replacement if you wanted to have one in storage. [8:00] But, um >> Cuz the new one was what? 61? [8:04] » Si- Yeah, 6,000 something. A little six is right. [8:08] » Yeah. And if you don't want to have it, then [8:12] that's fine. I just wanted to get it out of their shop if that's the [8:15] case. You know, >> Yeah. [8:17] I mean, I'm that close to the replacement. I almost feel like we'd [8:20] want to put the new one [8:22] » into Yeah, and >> our inventory type deal than that [8:25] rebuild that one. >> we feel that would be the gist of it. [8:27] Yes, we would do. But, I just wanted to counsel driven. [8:31] » So, Yeah, I mean, if you guys want to go ahead and get that back, and then cuz is [8:35] it the same as the other one that's the older one we have? [8:39] » We got two different ones in there right now from the what the original was. [8:44] Um the newest one is KBX. It's in Sand Ridge. [8:49] And then the other one, I forgot the name on it, but it's been in there a [8:52] little over a year, but it's due for pull, due maintenance, and [8:57] back in. So, we're just going to keep that rotation going. [9:01] » Yeah. [9:04] So, yeah, if you want to go ahead and get that one rebuilt or whatever, you [9:07] know what I mean, I'd go ahead and get that done. And then [9:10] uh maybe next year we'll look at getting a backup pump Yeah, to have. [9:17] » Look ahead and see. >> Yeah. [9:19] » Sorry, we're repairing the one, not replacing it with a new one. [9:23] » Well, no, and we won't repair it. We've already replaced it with a new one. [9:26] » Right. And then what are we doing with the old one then? [9:28] » We're just going to scrap it out. >> Okay. [9:31] » And then they're going to rebuild the one that's in service right now. [9:34] » Yeah, they'll go through doing an maintenance on it. Every uh 12 to 16 [9:39] months try to pull it and right here that's that's the thought and [9:43] we're we're going to go on there for the [9:47] » Sound good to you? >> Sound good to me. [9:49] » All right. I'll make a motion we close the meeting out then. [9:52] » Aaron, do you have anything else I'm sorry. [9:55] » That's all right. I was going to say I don't know they could possibly next [9:58] meeting they're trying to get a uh for the festival have a uh [10:04] parade this year. So in doing so the town about have to apply for the permit, [10:09] you know, and it it requires a requires a bond that we've got a bond waiver that [10:15] we can go through and a permit to to fill out for temporary closure the road [10:20] for that one day in October. Uh if the council agreeable on that I'd like to [10:25] get that signed this week which make sure we got all [10:30] little pieces and get signed and sent in. [10:34] » I'll make a motion. [10:35] » Make a motion that we allow the I guess permits. [10:38] » Yeah, permits for road closure. >> To [10:40] to continue forward getting that completed [10:44] for the parade fix. [10:47] » I'll second that. All in favor? >> Aye. [10:51] » Any opposed? Hearing none. [10:55] Is there any other business? [10:58] » I'll make a motion we close the meeting out. [11:00] » We can do that. >> I'll second. All in favor? [11:04] » Aye. >> All right. [11:07] We'll push the center. >> We'll push the center.