1 00:00:00,654 --> 00:00:02,674 [clears throat] 2 00:00:15,280 --> 00:00:23,480 So this meeting is live streamed um and is recorded. 3 00:00:20,160 --> 00:00:23,480 Is it recording? 4 00:00:36,960 --> 00:00:42,719 Good evening. We are now on the record. The purpose of the hearing is to receive 5 00:00:41,200 --> 00:00:45,840 comments and provide information specifically regarding to the pending 6 00:00:44,399 --> 00:00:50,879 permanent application for wetland impacts submitted by Waste Management of 7 00:00:48,160 --> 00:00:56,640 Wisconsin. Waste Management applied for a wetland individual permit to impact 11 8 00:00:53,440 --> 00:01:02,000 wetlands totaling approximately 7.66 acres of permanent wetland fill for a 9 00:00:59,359 --> 00:01:07,200 proposed landfill expansion. The project is located in the northern half of 10 00:01:03,760 --> 00:01:11,840 section 31, Township 5, range 21 east in the city of Franklin, Milwaukee County, 11 00:01:09,280 --> 00:01:17,119 Wisconsin. Thisformational hearing was requested by the city of Franklin 12 00:01:13,280 --> 00:01:21,600 pursuant to statutes 28136. The hearing today is non-adversarial in 13 00:01:19,200 --> 00:01:25,840 nature and is not intended as a Q&A session. It is designed to provide you 14 00:01:23,680 --> 00:01:30,080 an opportunity to submit your oral or written input and comments on the 15 00:01:27,680 --> 00:01:34,400 proposed project. Speakers will not be subject to cross-examination. 16 00:01:32,320 --> 00:01:39,520 This is not a contested case hearing as no decision has been rendered on the 17 00:01:36,320 --> 00:01:44,960 permit. This meeting is being recorded and all testimony is public record along 18 00:01:41,920 --> 00:01:48,560 with any written comments received. We will start with a brief presentation 19 00:01:46,799 --> 00:01:53,680 by the consultant representing the applicant who will describe the proposed 20 00:01:51,040 --> 00:01:57,520 project. Then DNR water management specialist Sonia Ponzi on behalf of 21 00:01:55,680 --> 00:02:01,200 Michelle Soderling will explain Wisconsin DNR's permit and review 22 00:01:59,439 --> 00:02:05,280 process along with the preliminary decision. I will then call upon those 23 00:02:03,680 --> 00:02:09,119 who have indicated on their appearance slips that they want to provide oral 24 00:02:07,280 --> 00:02:14,239 comments to come to the front of the room or the microphone 25 00:02:11,760 --> 00:02:19,120 for speaking. Please say your name and give your statement at that time. All 26 00:02:16,640 --> 00:02:22,560 comments will be recorded. If you have not submitted an appearance slip, but 27 00:02:21,040 --> 00:02:26,640 wish to make a statement before the hearing ends, you may also have that 28 00:02:25,040 --> 00:02:30,720 opportunity once you provide me with your appearance slip. I will need all 29 00:02:29,040 --> 00:02:35,360 slips prior to you leaving today so that we will have it as a matter of record. 30 00:02:33,040 --> 00:02:39,280 In addition to formal oral statements or written comment slips given at the 31 00:02:37,040 --> 00:02:50,160 hearing today, you can also submit written comments by email to travis t r 32 00:02:43,200 --> 00:02:53,160 a v i s period shrader s c h r o e disconsin.gov 33 00:02:54,080 --> 00:03:05,599 or by US mail to Travis Shrader, Wisconsin DNR, room 180, 34 00:03:01,920 --> 00:03:10,959 141 Northwest Barstow Street, Wauaaw, Wisconsin, and that's 53188. 35 00:03:09,360 --> 00:03:16,560 Any comments should be submitted no later than Friday, September 4th, 2026, 36 00:03:14,080 --> 00:03:20,640 close of business. You can also use an appearance slip to submit a written 37 00:03:18,239 --> 00:03:25,280 comment or your position on the proposed resource impacts of the project. Written 38 00:03:23,519 --> 00:03:29,680 comments receive the same weight and effect as all oral comments submitted 39 00:03:27,280 --> 00:03:33,840 into the record today. All comments will be summarized and 40 00:03:31,440 --> 00:03:39,120 taken into consideration in the review and decision on the permit application. 41 00:03:36,799 --> 00:03:43,920 The permit decision is appealable and the appeal procedure will be listed on 42 00:03:40,959 --> 00:03:47,920 the permit decision document. At this time, I will ask the applicant to give a 43 00:03:46,400 --> 00:03:50,920 brief background on the proposed project. 44 00:03:53,360 --> 00:03:58,000 » Thank you, Travis. Thank you everybody for coming. Um, introduced myself 45 00:03:56,640 --> 00:04:01,200 earlier. I'm Tyler Field. I'm accompanied by Betsy and Jeff. They'll 46 00:03:59,680 --> 00:04:06,560 be presenting the project here to you tonight. Um, just to give you a a 47 00:04:03,599 --> 00:04:09,760 project description and objective, the the main objective that WM wanted to 48 00:04:08,400 --> 00:04:14,159 achieve with this project was to continue to provide disposal services 49 00:04:11,840 --> 00:04:18,639 for the community. The landfill's been in the community providing a a 50 00:04:16,400 --> 00:04:24,479 beneficial disposal service for the community for up around 50 years. Um the 51 00:04:21,919 --> 00:04:28,800 proposed project includes constructing an expansion of that facility of 52 00:04:26,240 --> 00:04:35,199 approximately 72 acres to the north and to the east of the existing active fill 53 00:04:31,680 --> 00:04:41,120 area. Um this arrangement, this designed arrangement was consciously contemplated 54 00:04:37,280 --> 00:04:46,720 to maximize layover and re reduce the impacts to wetlands and the land use 55 00:04:44,160 --> 00:04:50,080 that that's there currently. So, we've we've really spent a lot of time laying 56 00:04:48,560 --> 00:04:53,600 out this landfill, laying out the expansion to maximize airspace to 57 00:04:51,919 --> 00:04:57,680 achieve the project goals, which is to provide a long-term ongoing disposal 58 00:04:55,919 --> 00:05:01,919 service for the community while minimizing the impacts to the land. 59 00:05:00,000 --> 00:05:05,680 Additionally, the area we selected has already been zoned and approved by the 60 00:05:03,600 --> 00:05:09,280 local community for landfilling activities. So, it fits well within the 61 00:05:07,680 --> 00:05:13,680 land use the community has already designated for this area. Um Betsy is 62 00:05:12,400 --> 00:05:17,759 going to talk a little bit more about how we uh went through the deciding the 63 00:05:16,320 --> 00:05:21,919 project's purpose and need and how we met the goals of the per purpose and 64 00:05:19,680 --> 00:05:24,919 need through our designed expansion process. 65 00:05:25,360 --> 00:05:34,000 » Thank you. So this project is in response to a real and documented need. 66 00:05:30,639 --> 00:05:41,360 Um, waste management serves over uh 1.5 million um people in the regional area 67 00:05:37,680 --> 00:05:46,639 and um they are required by uh statute to demonstrate that need as part of this 68 00:05:43,520 --> 00:05:52,000 process um for the landfill permitting and as a result of that evaluation 69 00:05:49,440 --> 00:05:55,840 uh the regional disposal capacity and the service area. So that includes waste 70 00:05:53,840 --> 00:06:00,320 disposal capacity from other landfills that accept waste from from this 71 00:05:57,600 --> 00:06:06,080 regional area is expected to be um depleted in 2033 and specifically at 72 00:06:03,680 --> 00:06:11,039 Metro by 2030. So there's a need for more disposal 73 00:06:08,800 --> 00:06:16,800 capacity in the service area with the estimated 14.7 million cubic yards of 74 00:06:14,319 --> 00:06:22,560 extra waste capacity that this expansion would provide. that would extend Metro 75 00:06:19,680 --> 00:06:28,479 site life by an estimated 11 and a half years, which is less than the maximum 76 00:06:25,520 --> 00:06:34,080 allowable 15 years um that is allowed for either an expansion or a new 77 00:06:30,400 --> 00:06:39,520 landfill in Wisconsin. Um, and the one of the keys to this is 78 00:06:36,560 --> 00:06:42,800 that it's uh it's taking advantage of continuing landfill operations on a 79 00:06:41,280 --> 00:06:47,440 property that currently has landfill operations and industrial uses at it 80 00:06:44,880 --> 00:06:50,639 rather than creating a new landfill on a a brand new property that doesn't 81 00:06:49,120 --> 00:06:54,639 currently have those types of activities occurring at it. So, there's three three 82 00:06:52,960 --> 00:07:00,160 primary objectives that this project will achieve. The first again is that it 83 00:06:57,600 --> 00:07:05,120 utilizes maximizes the efficiency at an existing site that has a landfill on it, 84 00:07:02,160 --> 00:07:08,720 has industrial uses. It allows the uh waste management to be able to take 85 00:07:07,440 --> 00:07:13,360 advantage of that existing infrastructure, site access, and the 86 00:07:11,440 --> 00:07:18,240 environmental controls and monitoring systems that are already at this site. 87 00:07:15,840 --> 00:07:22,080 The second one is that it adds that kind of long-term regional waste disposal 88 00:07:20,080 --> 00:07:27,599 capacity that we've just talked about as a demonstrated need. Um and then the 89 00:07:25,039 --> 00:07:32,960 third is that it does retain key wetland areas. There's five wetlands that will 90 00:07:29,840 --> 00:07:36,319 be um completely preserved. Um Jeff will talk more about those in just a moment 91 00:07:34,319 --> 00:07:41,039 here. Um but what what I would like to say about that is that um from the 92 00:07:38,560 --> 00:07:46,000 onset, Waste Management decided that they would um preserve those five 93 00:07:43,440 --> 00:07:51,440 wetlands in entirety. So there's a portion of them that just can't be 94 00:07:48,080 --> 00:07:55,520 impacted um because they are navigable. But there are portions of those wetlands 95 00:07:53,120 --> 00:08:00,720 that are also not navigable. So the waste management could have presented an 96 00:07:57,680 --> 00:08:05,039 option to um impact those non-navigable portions of those five wetlands, but 97 00:08:02,720 --> 00:08:08,879 from the onset chose not to made a conscious decision to maintain all of 98 00:08:07,440 --> 00:08:12,639 those and preserve all of those in their in their entirety, which reduced the 99 00:08:11,120 --> 00:08:16,879 overall capacity that they could have asked for right from the onset. This 100 00:08:15,120 --> 00:08:21,199 shows some meaningful avoidance that waste management took and those 101 00:08:18,879 --> 00:08:25,280 constraints um have an impact on the operational efficiency and the capacity 102 00:08:23,440 --> 00:08:28,080 that's provided by this but um waste management has accepted those 103 00:08:26,479 --> 00:08:33,839 constraints with the selected alternative. 104 00:08:30,560 --> 00:08:38,159 Um and then so this process requires us to look at several different footprints 105 00:08:35,919 --> 00:08:41,919 that could be considered for this um alternative 106 00:08:39,680 --> 00:08:46,080 um that would help to try to you know do document that uh achieving that waste 107 00:08:44,240 --> 00:08:51,360 disposal capacity that's needed for this region. Um and so there were like seven 108 00:08:49,440 --> 00:08:55,120 different alternatives that we evaluated and revisions to a couple of them. So 109 00:08:53,680 --> 00:08:59,519 you know even I could say like maybe like nine overall um alternative 110 00:08:57,680 --> 00:09:03,600 footprints that were looked at. One of them, the the single one that would mean 111 00:09:01,760 --> 00:09:09,680 that no wetlands on the site would be impacted, has a 3.6 million um cubic 112 00:09:07,360 --> 00:09:14,399 yard capacity, that's about a 75% reduction of the 14.7 million cubic 113 00:09:12,720 --> 00:09:19,519 yards that are provided by this selected alternative. Um and so that does not 114 00:09:16,959 --> 00:09:24,560 meet the the regional waste disposal capacity needed. Um so so I just want to 115 00:09:22,800 --> 00:09:28,720 point that out. So the 10.21 is what will be maintained. Those are those five 116 00:09:26,160 --> 00:09:33,600 that I've talked about. 7.66 66 will be directly impacted by this. More so more 117 00:09:31,440 --> 00:09:37,600 were um maintained than than are proposed to be impacted. And I think 118 00:09:35,839 --> 00:09:42,160 waste this this kind of selected alternative really provides that balance 119 00:09:40,080 --> 00:09:45,440 of providing meaningful avoidance while also meeting the project purpose and 120 00:09:43,920 --> 00:09:49,519 providing the waste disposal capacity needs for this region. Um so now Jeff 121 00:09:48,240 --> 00:09:53,920 will kind of talk more about the the wetlands themselves. 122 00:09:50,880 --> 00:09:59,040 » Thank you. Uh one of the first steps in the planning process for this project 123 00:09:55,920 --> 00:10:05,200 was to identify and assess sensitive resources and regulated resources. Um 124 00:10:02,240 --> 00:10:09,920 that includes wetlands. Um so wet the wetlands on the property were all 125 00:10:06,959 --> 00:10:14,160 assessed, mapped, and delineated um in the early planning stages so that 126 00:10:12,399 --> 00:10:20,399 we knew where where they were located, what their quality was um and how they 127 00:10:17,279 --> 00:10:26,399 affected the planning of the project. um uh detailed botanical surveys to 128 00:10:22,959 --> 00:10:31,680 understand the uh types of wetlands that are present and the diversity of those 129 00:10:28,399 --> 00:10:35,440 wetlands were completed. Uh we completed uh what are called functional value 130 00:10:33,440 --> 00:10:41,680 assessments of those wetlands proposed to be impacted. So that is a process 131 00:10:37,920 --> 00:10:46,000 where we look at um ecological, hydraological 132 00:10:43,360 --> 00:10:51,519 uh water quality, humid use uh functions of those wetlands. Um uh we evaluated uh 133 00:10:50,240 --> 00:10:56,720 the presence of threatened and endangered species within the project 134 00:10:53,360 --> 00:11:02,399 footprint. Uh we also evaluate just historical land use in this area and on 135 00:10:59,920 --> 00:11:08,399 the project area to understand past impacts and how they uh how those shaped 136 00:11:05,839 --> 00:11:13,040 the wetlands that are there today. uh we had coordination and consultation 137 00:11:10,720 --> 00:11:21,720 with the US Army Corps of Engineers to understand what federal regulations 138 00:11:14,880 --> 00:11:21,720 applied uh to the wetlands on site. Um 139 00:11:22,640 --> 00:11:29,920 as mentioned there uh 7.66 acres of wetlands proposed to be impacted. The 140 00:11:28,160 --> 00:11:34,959 wetlands that are are proposed for impacts are predominantly distur 141 00:11:32,240 --> 00:11:39,600 disturbed common wetland types. of wet meadow, shallow marsh, uh lots of 142 00:11:37,519 --> 00:11:44,480 invasive species that dominate these wetlands such as reed canary grass, 143 00:11:41,360 --> 00:11:49,680 cattails, and fragmitees. Um most of the wetland functions of of 144 00:11:47,120 --> 00:11:55,600 those proposed for impacts rated as low low functions. um water quality 145 00:11:53,600 --> 00:12:00,000 protection and storm water storage were typical moderate functions of these 146 00:11:57,920 --> 00:12:03,760 wetlands uh just based on landscape position and and no threatened or 147 00:12:02,160 --> 00:12:09,040 endangered species were identified within the project area. Um those 148 00:12:06,800 --> 00:12:14,000 wetlands uh that were avoided as Betsy mentioned uh those wetlands actually 149 00:12:10,959 --> 00:12:18,959 have some higher functioning resources associated with them. they have greater 150 00:12:16,240 --> 00:12:23,680 plant and habitat diversity and several of them have public water bodies 151 00:12:21,600 --> 00:12:30,560 associated with those wetlands that are being avoided. Um just uh briefly on the 152 00:12:27,680 --> 00:12:34,639 historic context of the site uh just looking at some of the older air photos 153 00:12:32,399 --> 00:12:39,920 before the the existing landfill was present. This property was an 154 00:12:35,920 --> 00:12:43,120 agricultural use. Um it was regularly rowcropped. There was drainage 155 00:12:41,360 --> 00:12:47,839 activities. um there really wasn't much for 156 00:12:45,200 --> 00:12:51,839 functioning vegetated wetlands present. Uh when the landfill became established 157 00:12:49,839 --> 00:12:56,079 on site, those land disturbance activities ceased and and these wetlands 158 00:12:53,920 --> 00:13:00,399 started to develop, redevelop and reveate on site. Um I think the 159 00:12:58,639 --> 00:13:06,639 important context from that is that these are not intact remnant wetland 160 00:13:03,760 --> 00:13:11,360 communities. These are uh highly historically disturbed wetlands that 161 00:13:08,560 --> 00:13:15,680 have had some amount of recovery uh since the landfill has been associated 162 00:13:13,519 --> 00:13:20,560 with the property. Um some of the uh protections that are 163 00:13:18,560 --> 00:13:25,600 uh in place for those wetlands that are not directly impacted. Uh we have 50 164 00:13:23,200 --> 00:13:31,600 foot setbacks from from wetlands in place to buffer uh those from the 165 00:13:28,079 --> 00:13:36,480 landfill. Um there are erosion and sediment controls and operational 166 00:13:33,600 --> 00:13:41,600 protections in place um to avoid secondary impacts. uh Waste Management 167 00:13:39,600 --> 00:13:47,360 submitted with their permit application a a long-term wetland monitoring and 168 00:13:44,399 --> 00:13:52,720 management plan that would be able to identify early potential unintentional 169 00:13:50,480 --> 00:14:00,320 secondary impacts and then has methods and means for uh ceasing those impacts 170 00:13:56,880 --> 00:14:04,880 and remediating those. Um the storm water management grading plans 171 00:14:02,399 --> 00:14:08,880 conveyance features are designed not only to control runoff and treat it from 172 00:14:07,199 --> 00:14:13,519 the landfill, but they're actually specifically designed to avoid 173 00:14:11,279 --> 00:14:19,760 hydraologic and sediment impacts to the wetlands that remain on site. 174 00:14:16,399 --> 00:14:24,399 Um and I guess lastly for the unavoidable wetland impacts that are 175 00:14:22,079 --> 00:14:29,440 proposed with this permit application compensator compensatory wetland 176 00:14:26,320 --> 00:14:34,480 mitigation was proposed and that is essentially offsetting each acre of 177 00:14:31,920 --> 00:14:38,959 wetland impacts with restoring wetlands at another location within the same 178 00:14:37,040 --> 00:14:43,440 watershed. Um so together these measures protect 179 00:14:41,279 --> 00:14:47,440 and retain wetlands and compensate for those unavoidable losses. 180 00:14:46,079 --> 00:14:51,199 Thanks, Jeeoff. So, I'll bring it home. So, folks, as you can see, we we put a 181 00:14:49,519 --> 00:14:55,279 lot of thought and effort into the design and the layout of this expansion 182 00:14:53,279 --> 00:15:00,399 project. Um, I think you heard Betsy and Jeff, there's there wasn't a there was a 183 00:14:56,959 --> 00:15:04,880 conscious effort to understand what we have for wetland um, inventory out on 184 00:15:02,959 --> 00:15:09,680 our facility and on our available property to expand to understand the 185 00:15:07,839 --> 00:15:13,440 impacts that we have and how we can develop an expansion that minimizes the 186 00:15:11,839 --> 00:15:17,199 those direct impacts while protecting the secondary impacts for the remaining 187 00:15:15,120 --> 00:15:22,240 wetlands. that was included in our application. And the selected 188 00:15:20,079 --> 00:15:26,800 alternative that we've designed, we feel minimizes those direct impacts, controls 189 00:15:24,639 --> 00:15:32,399 the secondary impacts to those wetlands, and provides a service that that the 190 00:15:29,760 --> 00:15:35,680 community needs in a long-term disposal outlet that protects human health and 191 00:15:33,920 --> 00:15:38,320 environment. Appreciate you guys coming out tonight. I'll turn it back over to 192 00:15:37,120 --> 00:15:42,320 Travis. >> Thank you, Tyler. At this time, Sonia 193 00:15:40,880 --> 00:15:47,040 will now talk about the department's permit review process and preliminary 194 00:15:44,079 --> 00:15:47,040 decision. 195 00:15:52,240 --> 00:15:58,800 The Department of Natural Resources reviews permit applications for wildland 196 00:15:56,079 --> 00:16:02,480 impacts under section 281.36 of Wisconsin state statutes. The purpose of 197 00:16:01,279 --> 00:16:06,399 reviewing projects through an application and permitting process is to 198 00:16:04,480 --> 00:16:11,759 ensure projects are in compliance with statutory criteria for wetland impacts. 199 00:16:09,519 --> 00:16:15,360 State and federal regulations require that the project demonstrates that 200 00:16:13,519 --> 00:16:19,759 avoiding wetland impacts was the first step as the project is being designed. 201 00:16:17,839 --> 00:16:22,880 If the project cannot avoid wetland impacts, this is described and 202 00:16:21,360 --> 00:16:27,040 documented in the applicant's application materials. If it is 203 00:16:25,279 --> 00:16:30,880 adequately demonstrated that wetlands cannot be avoided, the applicant 204 00:16:29,040 --> 00:16:34,560 thoroughly reviews alternatives and the preferred alternative has to minimize 205 00:16:32,800 --> 00:16:38,800 wetland impacts to the greatest extent practicable. In this case, the applicant 206 00:16:37,120 --> 00:16:43,120 is also required to mitigate wetland impacts through the purchase of wetland 207 00:16:40,800 --> 00:16:47,600 mitigation credits. The department's preliminary decision is to tenatively 208 00:16:45,440 --> 00:16:50,600 deny the permit for the proposed wetland impacts. 209 00:16:50,880 --> 00:16:57,360 At this time, it is your opportunity to provide formal oral comment or statement 210 00:16:55,519 --> 00:17:01,199 regarding the wetland permit application under review. I will work through the 211 00:16:59,759 --> 00:17:05,439 list of hearing slips that have been submitted 212 00:17:02,800 --> 00:17:08,880 and I will call on you. When I call your name, please come up to the front of the 213 00:17:06,799 --> 00:17:15,319 room. State your name, address, who you represent or position if any, and the 214 00:17:10,720 --> 00:17:15,319 content of your comment or concern. 215 00:17:16,880 --> 00:17:24,240 » John Nelson, uh, Mayor Nelson, I'm sorry. 216 00:17:20,880 --> 00:17:28,240 » That's fine. Well, good evening and I thank everybody for coming out today 217 00:17:25,760 --> 00:17:32,960 because this is an extremely extremely important thing for our community. And 218 00:17:31,120 --> 00:17:39,120 looking back at the at the history on this, I see the former mayor Tom Taylor 219 00:17:36,799 --> 00:17:46,559 and the former alderman Ken Skaransky who authored this. And this was part of 220 00:17:43,520 --> 00:17:53,080 a Franklin undertaking an expansion with a very long-term goal and vision in 221 00:17:50,080 --> 00:17:53,080 mind. 222 00:17:53,440 --> 00:18:01,760 What we look at now as far as a fiscal impact 223 00:17:59,280 --> 00:18:06,160 in the city of Franklin, we've got five taxing entities that make up your tax 224 00:18:04,080 --> 00:18:10,240 bill. For the Franklin residents that are in here, there's five. So, you've 225 00:18:08,320 --> 00:18:15,600 got MMSD, Milwaukee County, 226 00:18:12,559 --> 00:18:20,880 okay? You've got MATC, schools, and the city of Franklin. So 227 00:18:18,720 --> 00:18:29,600 the city of Franklin portion of your tax bill makes up about 24% of the pie. 228 00:18:24,640 --> 00:18:38,000 Okay? Now that 24% 80% goes to staff. When you look at the fiscal impact of 229 00:18:33,600 --> 00:18:45,440 what the city of Franklin gets, for example, last year ending 2025, 230 00:18:43,039 --> 00:18:56,000 I'm glad you're all seated. $3.3 million we got for that year. 231 00:18:51,919 --> 00:19:05,320 This year projected 3.4. Next year estimated 3.6 million. We get 232 00:19:01,679 --> 00:19:05,320 notice the trend. 233 00:19:05,840 --> 00:19:13,520 What we're looking at so far, what we've collected is about $29.4 234 00:19:11,440 --> 00:19:17,039 million that came to the city of Franklin. 235 00:19:14,960 --> 00:19:22,080 That's what balances budgets. That's what makes things happen. That's what 236 00:19:18,720 --> 00:19:27,440 keeps our financial stability. So we can look at you taxpayers and say, you know 237 00:19:23,919 --> 00:19:32,000 what, we offer a top tier community A1 services, fire, police, DPW, and you 238 00:19:30,400 --> 00:19:37,120 know what? Your Franklin portion of your tax bill went up 2.8% last year on 239 00:19:34,480 --> 00:19:42,720 average. 2.8%. I can't speak to the other four 240 00:19:38,400 --> 00:19:48,160 entities, but 2.8%. This is huge for our city as we continue 241 00:19:46,000 --> 00:19:55,520 to plan our future and this is vital vital when we come to 242 00:19:52,400 --> 00:20:00,880 balancing our budgets, our expectations of our finances and to make sure we 243 00:19:58,240 --> 00:20:04,960 continue to provide top tier. I like saying that term top tier because it's 244 00:20:02,559 --> 00:20:13,760 true. We live in a booming community but a aside from that what makes it balance. 245 00:20:08,799 --> 00:20:19,039 This is vital to making it balance. Thank you. 246 00:20:15,679 --> 00:20:22,440 » All right. Thank you, [clears throat] >> Robert Whiti. 247 00:20:23,554 --> 00:20:25,574 [clears throat] 248 00:20:28,139 --> 00:20:30,159 [clears throat] 249 00:20:31,919 --> 00:20:35,159 » We came. 250 00:20:36,960 --> 00:20:44,440 » No. Uh, we'll take care of it. Thank you. 251 00:20:41,120 --> 00:20:44,440 » Thanks for coming. 252 00:20:49,760 --> 00:20:57,200 » Okay. Uh, my name is Bob Whitkkey. I am the state assembly representative for 253 00:20:55,039 --> 00:21:02,640 63rd assembly district which you are sitting in. The landfill is also in my 254 00:21:00,480 --> 00:21:10,400 district. I represent two host communities, the city of Franklin and um 255 00:21:06,480 --> 00:21:16,960 the village of Raymond as well. So, u I will also uh just to set a few facts 256 00:21:14,480 --> 00:21:21,280 straight, uh I have been out to the site. I have met with uh waste 257 00:21:19,520 --> 00:21:26,320 management and their people to talk about what they want to do, reviewed the 258 00:21:23,840 --> 00:21:32,320 site. Uh and I've also had a follow-up call with your department after that to 259 00:21:28,480 --> 00:21:37,039 gain more information on permit. So, I I appreciate the opportunity to 260 00:21:34,320 --> 00:21:42,320 provide testimony tonight um regarding this proposed expansion. Uh I want I 261 00:21:40,000 --> 00:21:47,520 want to make sure this is clear. I am here today to express my strong and 262 00:21:44,880 --> 00:21:51,760 undying support for the proposed expansion and to respectfully ask the 263 00:21:50,400 --> 00:21:57,200 Wisconsin Department of Natural Resources to reconsider its tenative 264 00:21:53,840 --> 00:22:02,000 determination to deny the wetland uh individual permit and I've got the 265 00:21:59,600 --> 00:22:05,120 number in case you want uh because that's the information we got. It's 266 00:22:03,520 --> 00:22:08,120 IPSSE 202441-03989. 267 00:22:08,720 --> 00:22:16,559 Um, Waste Management uh currently owns and operates the Northern Expansion West 268 00:22:14,640 --> 00:22:22,480 Landfill at the Metro Recycling and Disposal Facility. Metro RDF provides an 269 00:22:20,080 --> 00:22:27,120 important waste disposal resource for southeastern Wisconsin, receiving 270 00:22:25,120 --> 00:22:31,120 commercial, industrial, municipal, and permitted special waste from 271 00:22:29,200 --> 00:22:35,280 municipalities, businesses, and industries throughout 272 00:22:32,960 --> 00:22:40,559 the region, not simply serving one community. And I think that should be 273 00:22:37,280 --> 00:22:44,880 underscored as well because by denying this permit, denying this expansion in a 274 00:22:43,440 --> 00:22:51,440 time when everybody talks about affordability, you are potentially 275 00:22:48,000 --> 00:22:56,799 opening up residents from throughout Milwaukee County uh and in northern Rine 276 00:22:54,320 --> 00:23:03,039 County to additional costs. As John said, um trying to hold the line on 277 00:22:59,440 --> 00:23:07,679 property tax, uh if this would not be here, um that it would potentially lead 278 00:23:06,080 --> 00:23:11,120 to additional costs for each municipality. 279 00:23:09,360 --> 00:23:15,360 The proposed Oakwood expansion would provide additional capacity through both 280 00:23:12,799 --> 00:23:19,280 the horizontal and vertical expansion of the existing facility. The horizontal 281 00:23:17,360 --> 00:23:24,799 expansion would encompass approximately 72.25 additional acres. proposal would 282 00:23:22,799 --> 00:23:30,480 directly impact um and I think you saw that in the presentation. I have 11 283 00:23:26,960 --> 00:23:35,919 wetlands but I'll defer if I was too heavy on the investment involving 284 00:23:33,120 --> 00:23:43,280 approximately 7.66 acres of permanent wetland fill. 285 00:23:38,799 --> 00:23:48,640 I recognize um as uh representative of the state that Wisconsin has a pro 286 00:23:46,080 --> 00:23:54,240 responsibility to protect its wetlands and that any proposal in involving 287 00:23:50,799 --> 00:23:58,960 wetland impacts deserves careful scrutiny. Thi that responsibility is 288 00:23:57,039 --> 00:24:03,600 precisely why I believe the department should fully evaluate the public need 289 00:24:01,760 --> 00:24:08,720 for this project, the applicant's proposed measures to avoid and minimize 290 00:24:05,919 --> 00:24:13,679 impacts and any required mitigation before making a final decision. We 291 00:24:11,360 --> 00:24:18,960 should not lose sight of the larger public interest question before us. 292 00:24:16,960 --> 00:24:26,400 The state government should work for its constituents to minimize cost and to 293 00:24:22,799 --> 00:24:33,039 serve their interests instead of making determinations that are contrary to what 294 00:24:29,600 --> 00:24:37,200 the community wants. Metro RDF provides disposal capacity for municipalities and 295 00:24:35,039 --> 00:24:42,000 businesses across south uh eastern Wisconsin, Milwaukee, Wakaan, Rine 296 00:24:39,520 --> 00:24:46,880 counties uh generate substantial amounts of waste every day. that waste does not 297 00:24:44,880 --> 00:24:52,559 disappear simply because landfill capacity becomes more difficult to 298 00:24:48,720 --> 00:24:58,240 permit. If existing properly regulated facilities cannot expand to meet 299 00:24:55,200 --> 00:25:02,880 demonstrated regional needs, the waste must be transported somewhere else 300 00:25:00,720 --> 00:25:09,120 potentially increasing transportation distances, costs, traffic and place a 301 00:25:06,640 --> 00:25:15,600 burden on the communities involved. Fact of the matter and John mentioned this 302 00:25:11,840 --> 00:25:21,679 that well we have uh the overall impact is about 5 million in annual revenue and 303 00:25:18,080 --> 00:25:24,960 that's to uh all the host communities. Question before the department therefore 304 00:25:23,440 --> 00:25:29,679 should not be whether the wetlands are important. they are. The question is 305 00:25:27,679 --> 00:25:34,320 whether this expansion with appropriate environmental safeguards and mitigation 306 00:25:32,080 --> 00:25:39,760 can be permitted while balancing wetland protection with the very real need for 307 00:25:37,120 --> 00:25:44,880 reliable regional waste disposal capacity. I believe the balance is 308 00:25:42,400 --> 00:25:49,679 possible and as I said, I've been out to the site. I have talked to waste 309 00:25:46,799 --> 00:25:55,360 management. Um though I'm not an expert in landfill expansion, um I I know more 310 00:25:53,039 --> 00:26:00,240 than I probably should. The Oakwood expansion is an expansion of an existing 311 00:25:58,080 --> 00:26:06,080 established waste management facility rather than the creation of entirely new 312 00:26:02,960 --> 00:26:10,320 landfill in another location. That distinction matters. Existing 313 00:26:08,720 --> 00:26:15,600 infrastructure, established transportation routes and an existing 314 00:26:13,200 --> 00:26:20,480 operational framework can provide significant public benefits compared 315 00:26:17,679 --> 00:26:25,520 with for forcing future disposal capacity to be developed elsewhere. I 316 00:26:23,520 --> 00:26:30,240 also believe the department should consider the consequences of denying 317 00:26:27,440 --> 00:26:34,480 this application. Southeastern Wisconsin will continue to generate commercial, 318 00:26:32,480 --> 00:26:39,679 industrial, municipal, and permitted special waste. The need for responsible 319 00:26:37,200 --> 00:26:43,840 disposal will not disappear with a permit denial. Instead, the pressure 320 00:26:41,919 --> 00:26:48,880 will shift to other facilities and other communities. As the department conducts 321 00:26:46,559 --> 00:26:53,760 its review under Wisconsin statutes administrative code, I urge the DNR to 322 00:26:51,919 --> 00:26:58,720 consider the complete public interest picture, including the regional need for 323 00:26:56,159 --> 00:27:03,440 disposal capacity, the benefits to Franklin and Raymond and other host 324 00:27:01,039 --> 00:27:07,760 communities, the economic and practical needs of southeastern Wisconsin 325 00:27:05,279 --> 00:27:11,919 businesses and municipalities, and the applicant's ability to meet all 326 00:27:09,520 --> 00:27:16,960 applicable environmental requirements and mitigation standards. And I'll make 327 00:27:14,559 --> 00:27:21,760 a comment on the historical side that I was given when I was out at the 328 00:27:18,880 --> 00:27:26,480 property. It appears that uh Waste Management has been a good business 329 00:27:23,600 --> 00:27:31,120 partner with the communities with the constituents that reside here and I 330 00:27:29,440 --> 00:27:36,320 believe that that should be an overwhelming consideration as to how you 331 00:27:33,919 --> 00:27:40,159 work through this. I respectfully ask the Department of Natural Resources to 332 00:27:38,080 --> 00:27:45,039 reconsider its tenative determination to deny the wetland individual permit and 333 00:27:42,799 --> 00:27:50,559 give the Oakwood expansion a thorough and fair evaluation based on the full 334 00:27:48,640 --> 00:27:55,520 record, including the testimony information uh presented at this public 335 00:27:52,960 --> 00:27:59,039 information hearing tonight. Uh thank you for your consideration and I 336 00:27:57,520 --> 00:28:05,520 appreciate all those that came in support for this. Um, like I said, state 337 00:28:02,720 --> 00:28:11,080 government should be working for us, not putting roadblocks in between. Thank 338 00:28:08,080 --> 00:28:11,080 you. 339 00:28:11,229 --> 00:28:13,249 [applause] 340 00:28:15,200 --> 00:28:20,520 » Thank you, Bob. Danielle Kenny, 341 00:28:25,440 --> 00:28:32,880 thank you. Good evening. My name is Danielle Kenny 342 00:28:30,080 --> 00:28:38,240 and I serve as the district 6 alderwoman for the city of Franklin and I'm also a 343 00:28:35,760 --> 00:28:42,720 member of the finance committee and the waste manage management facility sits in 344 00:28:40,559 --> 00:28:48,000 my district and I rep where I represent and I actually live 1.2 miles away from 345 00:28:44,799 --> 00:28:51,679 it. Waste management has been a responsible business in our community 346 00:28:49,520 --> 00:28:55,279 for decades and as a neighbor I can vouch for the responsiveness 347 00:28:53,360 --> 00:28:59,520 responsiveness to issues as they arise. Anytime that I've called with a problem, 348 00:28:57,440 --> 00:29:03,520 somebody calls me back immediately. And to me, that speaks volumes about 349 00:29:01,760 --> 00:29:07,760 whatever mitigation that they have planned and their follow through and the 350 00:29:05,440 --> 00:29:12,159 responsiveness to whatever it needs to be addressed. I wanted to begin by 351 00:29:10,559 --> 00:29:16,000 acknowledging something important. Wetlands have value. I don't believe 352 00:29:14,240 --> 00:29:19,919 Franklin's financial interests should simply override environmental 353 00:29:17,840 --> 00:29:24,000 protections. And I'm not asking the DNR to disregard the quality of these 354 00:29:21,360 --> 00:29:27,600 wetlands. I'm asking the the department to consider the full picture before 355 00:29:25,600 --> 00:29:32,480 denying the permit. This is an expansion of an existing 356 00:29:29,600 --> 00:29:37,679 regulated waste disposal facility that already serves a significant portion of 357 00:29:34,320 --> 00:29:41,520 southeastern Wisconsin. Like uh Bob Witkkey said, it doesn't disappear. It 358 00:29:39,840 --> 00:29:45,600 has to go somewhere. So, we're putting in money to move it somewhere else and 359 00:29:44,080 --> 00:29:52,880 have different environmental needs there. What I would like to know is um 360 00:29:50,399 --> 00:29:57,840 if the wetlands that are the problem are considered high quality, what does the 361 00:29:55,279 --> 00:30:02,799 the department account for these wetlands sitting at the base of the 362 00:29:59,679 --> 00:30:09,039 existing facility for decades and how how does that impact the quality of 363 00:30:05,679 --> 00:30:13,200 them? Also, the DNR previously allowed more than eight acres of wetland impact 364 00:30:11,120 --> 00:30:17,760 associated with an expansion of this same facility with compensatory 365 00:30:15,520 --> 00:30:23,200 mitigation in the past. And I'm wondering what's material materially 366 00:30:20,080 --> 00:30:28,240 different with these 7.66 acres that makes it unacceptable. Now, 367 00:30:26,399 --> 00:30:32,240 there's a substantial public interest component to this decision. Franklin 368 00:30:30,399 --> 00:30:36,720 receives, as you've heard, approximately 3 million annually in landfill sighting 369 00:30:34,480 --> 00:30:40,559 revenue. Losing it would create a significant funding gap that would 370 00:30:38,480 --> 00:30:44,480 ultimately mean additional borrowing, delayed infrastructure, 371 00:30:42,640 --> 00:30:48,559 reduced services, or an increased cost to taxpayers. 372 00:30:46,480 --> 00:30:52,640 Franklin has hosted this regional public necessity for decades. Our community 373 00:30:50,880 --> 00:30:56,960 accepts the trucks, environmental impacts, monitoring, and long-term 374 00:30:54,480 --> 00:31:01,840 responsibility that come with it. I respectfully ask the DNR to consider 375 00:30:59,279 --> 00:31:06,320 and the entire public interest, the actual quality and function of these 376 00:31:03,440 --> 00:31:09,600 wetlands, the feasibility of mitigation, regional waste disposal needs, the 377 00:31:08,000 --> 00:31:13,520 environmental consequences of sending that waste elsewhere, and the 378 00:31:11,440 --> 00:31:17,520 significant impact denial would have on the host community and the surrounding 379 00:31:15,360 --> 00:31:20,919 communities. Thank you. >> Thank you, Danielle. 380 00:31:22,799 --> 00:31:26,120 Ken Scoransky. 381 00:31:30,351 --> 00:31:32,371 » [laughter] 382 00:31:33,919 --> 00:31:37,559 » No, no, no, no, no. 383 00:31:38,399 --> 00:31:44,360 » Okay. >> Oh, no. 384 00:31:45,519 --> 00:31:48,840 » Please don't. 385 00:32:01,279 --> 00:32:06,432 No problem. >> Come back. [laughter] 386 00:32:06,880 --> 00:32:12,360 » All right. Somebody else. >> You're good. 387 00:32:12,880 --> 00:32:17,760 » Mr. Chairman, I can go in his place if I can give him some rest. 388 00:32:17,039 --> 00:32:20,640 » Okay. >> Yeah. Okay. All right. We can 389 00:32:19,440 --> 00:32:26,919 » Tom Taylor. >> All right. 390 00:32:22,720 --> 00:32:26,919 Okay, let me see if I can 391 00:32:27,120 --> 00:32:31,440 » Tom Taylor. >> Yeah, Tom. 392 00:32:29,600 --> 00:32:35,197 » Thank you very much. >> Happens to me, too. I lose the 393 00:32:32,960 --> 00:32:41,747 circulation in my legs these days. [snorts] Um uh I'm Tom Taylor. I'm the 394 00:32:38,159 --> 00:32:46,000 former mayor um city of Franklin. [snorts and clears throat] I've served 395 00:32:42,640 --> 00:32:49,279 as the um as a chairman of the IC elected by the mayors and village 396 00:32:47,440 --> 00:32:52,399 presidents of Milwaukee County and 19 municipalities. 397 00:32:51,120 --> 00:32:56,720 served as the director of human resources for Milwaukee County and I 398 00:32:55,120 --> 00:33:03,679 served as the vice president of Milwaukee District Council 48 ASME at 399 00:32:59,200 --> 00:33:09,360 one time. Um I also was alderman for approximately five years. 400 00:33:06,799 --> 00:33:15,120 I was intimately involved in the negotiations 401 00:33:11,200 --> 00:33:21,120 of the waste management contract met here and many other places with the uh 402 00:33:18,720 --> 00:33:25,200 other communities. Raymond, Norway, etc., etc., etc. I think when it was all 403 00:33:23,919 --> 00:33:30,240 said and done, it was something like nine years that went into the 404 00:33:28,159 --> 00:33:36,720 negotiations that led to the final contract. My recollection is Franklin 405 00:33:34,080 --> 00:33:44,960 did not want any expansion of the landfill at all. Um, but under state 406 00:33:40,720 --> 00:33:52,640 law, you must negotiate in good faith or you lose uh any negotiating ability that 407 00:33:48,320 --> 00:33:57,519 you have. So we did negotiate and we came up with a settlement offer. Well, I 408 00:33:55,519 --> 00:34:02,159 understand that waste management and Mike who used to be out there, we worked 409 00:33:59,440 --> 00:34:05,279 with him and he was pretty good with uh you know the uh the dump site and 410 00:34:03,760 --> 00:34:12,480 everything. Um well it's good we were not the city 411 00:34:09,359 --> 00:34:16,800 was not in favor of any expansion at all. So, we came up with this 412 00:34:14,399 --> 00:34:24,159 compromise. And the compromise basically is you got to stay in the box. You can't 413 00:34:20,399 --> 00:34:29,040 go uh past 112th. You can't go past 124th. You can't go past Oakwood Road. 414 00:34:26,560 --> 00:34:34,399 And you can't go past South County Line Highway. You have to stay in the box. 415 00:34:31,839 --> 00:34:39,679 But, Mr. Chairman, there's a flyer that has been distributed widely throughout 416 00:34:36,879 --> 00:34:45,599 the community. I've I've been told it's actually emanated coming from the dump 417 00:34:42,800 --> 00:34:50,480 site. It's being passed out by waste management. I I don't know if this is 418 00:34:47,280 --> 00:34:56,639 true or not, but in that document, it's basically saying that if they don't 419 00:34:53,200 --> 00:35:04,000 get the wetland expansion, then the tipping fees and the ability to 420 00:35:00,800 --> 00:35:07,920 dump at the site and all of the other things that were negotiated in the 421 00:35:05,440 --> 00:35:14,000 contract will basically disappear. And that's not the case at all. As I 422 00:35:10,400 --> 00:35:21,359 understand it, 77 acres you're not contesting for the expansion. What waste 423 00:35:17,280 --> 00:35:26,880 what the DNR is contesting is the 7 odd acres of wetland. 424 00:35:24,320 --> 00:35:30,400 And so that flyer that's out there, I think has misled many in the public that 425 00:35:29,200 --> 00:35:36,880 they won't be able to take their trailers like I do out there and dump uh 426 00:35:34,400 --> 00:35:42,800 or that the city is going to be restricted in getting the money that it 427 00:35:40,400 --> 00:35:47,920 has been gained that has it has gotten over the years and it's a substantial 428 00:35:45,359 --> 00:35:53,760 amount of money. But I I also have to tell you that when I was in there and 429 00:35:50,480 --> 00:36:00,000 Ken was an alderman, the money that w that came from the from the landfill, it 430 00:35:58,079 --> 00:36:05,599 was the policy decision that those monies be only used for capital 431 00:36:02,880 --> 00:36:12,000 projects. And the reason for that is when the landfill was finally 432 00:36:08,560 --> 00:36:17,200 uh filled in the box, I'll say, and it stopped and the money stopped pouring in 433 00:36:15,359 --> 00:36:22,640 that you would not have to raise the taxes in Franklin by 20 or 30%. you 434 00:36:20,800 --> 00:36:25,920 would just simply the capital projects you would have to go out maybe at a 435 00:36:24,160 --> 00:36:30,720 referendum maybe you'd have to go out for borrowing but the money was never 436 00:36:28,160 --> 00:36:34,560 intended to be used for the general fund to pay off let's say the police contract 437 00:36:32,560 --> 00:36:40,640 or the fire contract or anything like that and so I think it's it's important 438 00:36:37,359 --> 00:36:44,800 to note that well waste management I have to say very professional but it 439 00:36:43,040 --> 00:36:49,760 wasn't out of the kindness of their heart that they did all these things it 440 00:36:47,520 --> 00:36:55,440 came through really hard hard negotiations. And just so you know, this 441 00:36:52,800 --> 00:37:01,359 gentleman up here and I met with three county executives. We met with three 442 00:36:58,320 --> 00:37:05,520 secretaries of the DNR. I took the proposal along with Mr. Wesalowski to 443 00:37:03,839 --> 00:37:10,400 the mayors and village presidents, which at that time included Scott Walker and 444 00:37:08,400 --> 00:37:17,680 Tom Barrett, and to get their support to support us 445 00:37:13,440 --> 00:37:21,520 on keeping the expansion within the box. and we were eventually successful in 446 00:37:19,599 --> 00:37:26,960 that, but it was very, very hard negotiations. Almost fell apart a 447 00:37:23,920 --> 00:37:31,000 hundred times. So, with that, I thank you for allowing me to speak. 448 00:37:31,440 --> 00:37:36,640 » Thank you, Tom. Doug White. Oh, Ken, are you 449 00:37:35,680 --> 00:37:39,359 » That's right. That's right. >> Ken, you got the microphone in your hand 450 00:37:38,000 --> 00:37:44,000 if you're Are you comfortable? >> Anybody else can speak? I got it. No, I 451 00:37:42,240 --> 00:37:47,920 should. Okay. Thank you very much and I apologize. my leg is getting better and 452 00:37:46,160 --> 00:37:55,440 fell asleep and everything everything else. So, uh I'm Ken Skansky. Uh I'm a 453 00:37:52,560 --> 00:38:01,040 resident. My residents when I first came to Franklin was part of the landfill 454 00:37:58,240 --> 00:38:05,280 that they own now. And since then, they have done a tremendous job. They've been 455 00:38:03,359 --> 00:38:11,839 very cooperative uh all the way along and then I became 456 00:38:08,320 --> 00:38:15,680 the alderman for the area and it never changed. They were always very 457 00:38:13,599 --> 00:38:20,560 cooperative. They got things done. They listened to the common council, the 458 00:38:17,520 --> 00:38:25,520 mayor, uh the citizens. They were here. Their heart was here. They get things 459 00:38:22,640 --> 00:38:29,599 done and get things done right. So, there's a lot of negotiations that 460 00:38:27,200 --> 00:38:37,520 nobody ever sees or does. Tom and the mayor, great job uh getting this things 461 00:38:33,040 --> 00:38:45,200 accomplished. And uh I'm for uh accepting the waste management's 462 00:38:40,320 --> 00:38:51,280 proposal. uh have the DNR uh help receive this and get it done. Uh I was 463 00:38:48,240 --> 00:38:56,400 there when a lot of that wetland wasn't there. So I don't know how it it it got 464 00:38:54,240 --> 00:39:00,640 a little extra land changes a little bit, but they've always been very 465 00:38:58,320 --> 00:39:07,520 professional in getting things done and I I admire them for it because it's is 466 00:39:04,079 --> 00:39:14,320 quite a task. So, I can I can't say anymore that the other uh people have 467 00:39:11,440 --> 00:39:17,200 said it's all been very good. Uh and I don't want to take up any more time or 468 00:39:15,680 --> 00:39:22,480 stumble around. My league is finally getting back awake. So, I thank you very 469 00:39:20,240 --> 00:39:30,720 much and thank the DNR for being here and Mayor Nelson and Mayor uh Taylor. Uh 470 00:39:26,560 --> 00:39:36,520 it's always been very good uh to serve the city of Franklin. Thank you. 471 00:39:33,119 --> 00:39:36,520 » Thank you, Ken. 472 00:39:44,800 --> 00:39:49,599 Doug, >> this Doug. 473 00:39:47,040 --> 00:39:52,839 » Yes. Okay. >> Doug, what 474 00:39:53,599 --> 00:39:59,947 I'm Doug White. I'm [clears throat] the president of the village of Raymond. Uh 475 00:39:57,839 --> 00:40:02,400 Raymond strongly supports responsible [clears throat] 476 00:40:00,560 --> 00:40:06,320 environmental stewardship and the protection of wetlands. 477 00:40:04,640 --> 00:40:09,839 But we also believe that environmental decisions should evaluate the full 478 00:40:08,079 --> 00:40:14,720 consequences of of the alternatives before us. 479 00:40:11,760 --> 00:40:17,839 This is not simply a Franklin landfill. DNR's own notice states that the 480 00:40:16,560 --> 00:40:23,200 majority of the waste received in the metro comes from Milwaukee, Walka, and 481 00:40:20,240 --> 00:40:27,520 Rine counties. Metro currently handles hundreds of thousands of tons of waste 482 00:40:24,960 --> 00:40:32,560 annually and reportedly only has 3 to 5 years remaining of capacity. If Metro 483 00:40:30,240 --> 00:40:37,040 closes, that waste does not disappear. It must be transported to other disposal 484 00:40:34,560 --> 00:40:40,880 facilities for Raymond. This has very very real consequences. 485 00:40:39,280 --> 00:40:44,400 Our village currently receives about $325,000 486 00:40:42,960 --> 00:40:48,480 uh annually associated with this facility. For a small community that 487 00:40:46,960 --> 00:40:52,920 represents a significant operating effect, that's 15% of our budget. 488 00:40:52,960 --> 00:41:00,560 But my concern goes beyond the revenue. In southeastern Wisconsin's waste must 489 00:40:58,400 --> 00:41:05,359 instead travel greater distances. Those additional truck miles have consequences 490 00:41:03,520 --> 00:41:10,480 and additional fuel consumption, emissions, traffic, and wear on the 491 00:41:07,040 --> 00:41:14,079 roads that those trucks use. Rural communities like Raymond ultimately bear 492 00:41:12,480 --> 00:41:17,920 part of the burden for that extra infrastructure. 493 00:41:16,000 --> 00:41:23,359 The proposal before the DNR involves approximately 7.66 acres of permanent 494 00:41:20,319 --> 00:41:27,680 wetland impact within a roughly 72 acre horizontal expansion. Wisconsin's 495 00:41:25,839 --> 00:41:33,040 permitting process provides mechanisms for avoidance, minimization, and 496 00:41:30,240 --> 00:41:37,760 compensatory mitigation. Therefore, I respectedly asked the DNR to consider 497 00:41:35,119 --> 00:41:41,839 the complete environmental equation. Has the DNR compared the environmental 498 00:41:39,440 --> 00:41:45,280 impact of mitigating these wetlands against the impact to the environment of 499 00:41:43,760 --> 00:41:50,400 transporting hundreds of thousands of tons of waste across southeast Wisconsin 500 00:41:48,079 --> 00:41:55,359 to another facility? Has the department exhausted reasonable opportunities to 501 00:41:52,800 --> 00:42:00,800 redesign, minimize, mitigate the wetland impacts before concluding the outright 502 00:41:57,040 --> 00:42:04,720 denial is is the appropriate result? Raymond is not asking the DNR to 503 00:42:02,480 --> 00:42:08,960 disregard Wisconsin's wetlands. We are asking the DNR to consider whether an 504 00:42:06,560 --> 00:42:12,800 environmentally responsible expansion with appropriate avoidance, 505 00:42:10,240 --> 00:42:16,640 minimization, mitigation may produce a better overall environmental and public 506 00:42:14,480 --> 00:42:23,640 outcome than simply moving the region's waste, truck traffic, and environmental 507 00:42:18,720 --> 00:42:23,640 impact. somewhere else. Thank you. 508 00:42:23,760 --> 00:42:27,379 » Thank you, Doug. [applause] 509 00:42:28,160 --> 00:42:33,800 » Vince Trippy. 510 00:42:30,160 --> 00:42:33,800 » Trippy. All right. 511 00:42:33,920 --> 00:42:41,280 » Thank you. Vince Trippy, 6910 South Lovers Lane Road, Franklin. I've lived 512 00:42:38,960 --> 00:42:44,640 in Franklin or Greenfield my whole life. I got my degrees from University of 513 00:42:42,960 --> 00:42:49,040 Wisconsin Milwaukee. Environmental scientist for a career. I worked for the 514 00:42:47,440 --> 00:42:52,240 Center for Great Lakes Studies for four years before I went into envir 515 00:42:50,560 --> 00:42:56,640 environmental engineering. I worked at the largest environmental engineering 516 00:42:54,000 --> 00:43:02,240 system in the world. I worked on dozens of landfills in the 42 states and Canada 517 00:42:59,440 --> 00:43:07,520 and Mexico. And it doesn't make sense to me to develop a new landfill when we 518 00:43:05,040 --> 00:43:12,560 have a functioning quality landfill in existence and working. The word 519 00:43:09,599 --> 00:43:19,520 mitigation means to make a deal to offset costs, benefits, and trade to 520 00:43:16,960 --> 00:43:25,839 make a a project go forward. It doesn't mean that it's a stop dead rationale to 521 00:43:23,200 --> 00:43:30,720 the project. So, I'm in in favor of moving forward with the the mitigation 522 00:43:28,240 --> 00:43:36,155 of the wetland to let the expansion go forward. Thank you. 523 00:43:32,400 --> 00:43:36,155 » Thank you, Vince. [applause] 524 00:43:37,920 --> 00:43:43,319 Joe Walter Spear Jr. 525 00:43:54,800 --> 00:44:01,599 » Uh, the card said, my name is Joe Spear. I am the landfill compliance officer for 526 00:44:00,000 --> 00:44:05,680 the city of Franklin and have been for over 20 years. But I'm standing here to 527 00:44:03,680 --> 00:44:10,079 speak as a professional in the industry and everybody has covered so well how 528 00:44:08,240 --> 00:44:14,000 important it is that this landfill exists and others. So I'm going to ask 529 00:44:12,160 --> 00:44:18,720 the DNR to take a look at something that I've me mentioned before in swana 530 00:44:16,240 --> 00:44:23,760 conversations and so on. We are at a point now where we have not done our due 531 00:44:21,440 --> 00:44:26,880 diligence. We never reinstalled the bands for cardboard. We haven't done 532 00:44:25,280 --> 00:44:30,960 anything to reduce the waste going into our landfills. And now we're talking 533 00:44:28,800 --> 00:44:36,560 about not expanding. So, we now need to consider airspace as 534 00:44:34,000 --> 00:44:42,079 a natural resource. And we are running out of airspace. And this landfill, I 535 00:44:39,440 --> 00:44:47,280 always joke in Emerald Park, God said put it here. Here's a big plug of clay. 536 00:44:44,480 --> 00:44:51,440 Big plugs of clay have wetlands. You find a site without wetlands, you're 537 00:44:49,200 --> 00:44:56,079 going to have soil problem. And oh, I have one question. If I write 538 00:44:53,760 --> 00:45:03,119 the DNR, can I get a list of reasons why they're considering denial? It was a 539 00:44:58,319 --> 00:45:07,280 statement, not a not supported. >> So, we can you'll see in the decision 540 00:45:05,760 --> 00:45:11,119 all of those reasons. It'll be written out. We can get you a copy of the 541 00:45:08,800 --> 00:45:15,720 decision. Absolutely. >> Thank you, Joe. Joe, 542 00:45:15,920 --> 00:45:18,920 just 543 00:45:27,040 --> 00:45:30,520 Billy Faze. 544 00:45:39,760 --> 00:45:48,720 Okay, I kind of got sid sidetracked when uh 545 00:45:45,920 --> 00:45:57,760 Tyler made a comment about 50 years. So, I want to Tyler, I think you're a little 546 00:45:50,960 --> 00:46:03,440 bit off on that because the word has it old man Knight tried starting that 547 00:46:00,480 --> 00:46:09,520 landfill 1938. Okay, there's got to be somebody around 548 00:46:06,000 --> 00:46:15,321 here that knows Rolley, you >> Can you back me on that one? Roly, 549 00:46:13,301 --> 00:46:15,321 [laughter] 550 00:46:15,520 --> 00:46:27,040 » Harvey, you've been around too, but I do believe, if I remember right, 551 00:46:23,680 --> 00:46:30,880 Waybot Metro 1984, 552 00:46:28,640 --> 00:46:35,359 83ish. So, this landfill has been around a long 553 00:46:33,440 --> 00:46:41,839 time. I'm 60 years old 554 00:46:38,240 --> 00:46:49,200 and I'm trying to look to see I might be one of between Harvey Sitzer and I we're 555 00:46:46,800 --> 00:46:54,079 probably the closest to the landfill where we live. 556 00:46:51,440 --> 00:47:01,520 Been there for 60 years. My family been there. My uncle bought 557 00:46:58,560 --> 00:47:05,520 the farm in 1946 when he got home from World War II. 558 00:47:03,520 --> 00:47:10,960 Uh he made a comment 559 00:47:07,839 --> 00:47:16,160 one of the last times maybe 30 years, 25 years ago when we have to come to this 560 00:47:13,839 --> 00:47:20,160 to support the landfill. He said, 561 00:47:18,000 --> 00:47:25,839 "You know what? Everybody's arguing about that landfill. 562 00:47:23,920 --> 00:47:31,040 Everybody should be responsible about their own garbage. Maybe they should 563 00:47:28,000 --> 00:47:35,119 back or bury it in their backyard. And I'm thinking, boy, uncle, you're 564 00:47:33,280 --> 00:47:38,960 getting old that doesn't make sense. But you know what? It kind of does make 565 00:47:36,480 --> 00:47:44,160 sense. Everybody should be responsible their own garbage and bury it in their 566 00:47:40,960 --> 00:47:49,680 own backyard. Very easy for him to say. He had 80 acres behind his house. What 567 00:47:47,680 --> 00:47:56,000 do you do with the land? What What do you do when you live in the city? Where 568 00:47:52,079 --> 00:48:02,319 does the garbage have to go? So why don't we just leave it there? Let 569 00:48:00,400 --> 00:48:06,560 him expand because 570 00:48:04,079 --> 00:48:10,640 can I ask Tyler a question and can he answer it? 571 00:48:08,880 --> 00:48:16,960 » Tyler, [clears throat] >> if they if if they say you can't build 572 00:48:12,960 --> 00:48:21,040 no more, where do you go to find land? >> Do you look at a subdivision and go, 573 00:48:19,359 --> 00:48:26,400 we'll do it here. we're going to knock all these houses down or do you go to a 574 00:48:23,280 --> 00:48:32,640 farm and say we'll buy up your farm and we'll put the landfill here. 575 00:48:30,079 --> 00:48:35,920 Doesn't that mean how ridiculous is that? 576 00:48:34,319 --> 00:48:41,200 Now you can see all these data centers going 577 00:48:37,920 --> 00:48:46,480 up. They're taking up a lot of land farmland. 578 00:48:43,839 --> 00:48:51,839 We're going to run out of food to feed not just America but the world. 579 00:48:50,480 --> 00:48:55,359 They're already making meat in factories. 580 00:48:53,839 --> 00:49:00,240 Think about it. Next time you go to McDonald's, 581 00:48:57,280 --> 00:49:04,079 six billion hamburgers served a day. Now we're going to [sighs] get rid of a 582 00:49:02,559 --> 00:49:10,480 landfill to eat up more farmland. 583 00:49:07,200 --> 00:49:15,440 Well, I'm sorry, but I like to eat. You can see. 584 00:49:13,040 --> 00:49:21,440 Think about that. I bet you every one of you up there like to eat. I bet you 585 00:49:17,839 --> 00:49:27,280 everybody in this room likes to eat. Think about burning up more 586 00:49:25,280 --> 00:49:32,000 farmland when we got a night. The land's right 587 00:49:29,839 --> 00:49:37,520 there. Why? 588 00:49:34,079 --> 00:49:40,760 Let's just leave it. Leave it there. Thank you. 589 00:49:40,939 --> 00:49:49,000 [applause] Thank you, Billy. 590 00:49:45,119 --> 00:49:49,000 Kevin Lele. 591 00:49:56,160 --> 00:50:04,640 » Thank you. Uh my name is Kevin Lele. I am a resident in the village of Raymond. 592 00:50:01,040 --> 00:50:10,000 I um on purpose came here as a civilian. I didn't but um I'm also the assistant 593 00:50:07,359 --> 00:50:14,400 chief on the fire department. So came to assist uh this gentleman here as he fell 594 00:50:12,319 --> 00:50:20,000 on the floor. So was happy to get him back in this chair. So 595 00:50:17,200 --> 00:50:25,839 um a lot of people today waste management representative Whitkkey um 596 00:50:21,920 --> 00:50:29,440 the mayors my village president have said way more than what I have in my 597 00:50:27,440 --> 00:50:34,400 notes what I have in my notes and then more said I'm here in strong support. 598 00:50:32,079 --> 00:50:39,839 Um, the only thing I had to say for the DNR, they they're doing a good job of 599 00:50:36,800 --> 00:50:45,359 the wetlands management and that in fact the tile system in the area, you know, 600 00:50:42,720 --> 00:50:50,559 for the farmers that was put in over a 100 years ago is failing and the 601 00:50:46,960 --> 00:50:56,720 wetlands are in fact growing. um delin the lination where the make the mark the 602 00:50:53,040 --> 00:51:00,480 wetlands is growing and if the DNR took a look all the wetlands 603 00:50:58,880 --> 00:51:03,680 are growing and you know there's more of 604 00:51:02,000 --> 00:51:08,240 them and if the waste management is willing to 605 00:51:05,440 --> 00:51:13,119 help with that process and offset the the waste the wetlands that they're 606 00:51:10,160 --> 00:51:19,839 taking away I just believe that that's a a no-brainer for the DNR to use this 607 00:51:16,800 --> 00:51:23,599 existing property and expand it and kick that can down the road before we have to 608 00:51:21,359 --> 00:51:27,705 take away another farm. Thank you. My name's Kevin Lele. 609 00:51:24,640 --> 00:51:29,725 » Thank you, Kevin. [applause] 610 00:51:30,319 --> 00:51:35,559 » Uh, and I had one person that was undecided, Suzanne. 611 00:51:38,720 --> 00:51:46,319 I'm Suzanne Mayor. Uh, 9733 West Ryan Road, Franklin. So, I'm 2 miles from 612 00:51:44,720 --> 00:51:53,920 the, um, facility. Um, I was actually I'm 613 00:51:50,480 --> 00:52:00,640 here because I live close by and I'm always interested in the landfill. Um, 614 00:51:58,800 --> 00:52:06,160 I was actually very surprised at the fact that we learned that you're in 615 00:52:03,680 --> 00:52:11,359 you're considering denying the proposal. Um, 616 00:52:09,599 --> 00:52:16,960 surprises me because I kind of thought that it we were all here to discuss what 617 00:52:14,559 --> 00:52:24,240 the expansion was actually going to be. Um, this map wasn't gone over. I don't 618 00:52:20,800 --> 00:52:29,760 know why. Um, kind of seems like that showed maybe what the plan was supposed 619 00:52:26,240 --> 00:52:34,760 to be or is supposed to be. But I do want to just say um 620 00:52:36,319 --> 00:52:45,520 I would be in favor of the expansion with the understanding of what um Mayor 621 00:52:43,359 --> 00:52:53,640 Taylor had said that it doesn't go beyond those um parameters originally 622 00:52:49,280 --> 00:52:53,640 set in place. Um 623 00:52:54,800 --> 00:53:03,520 the only thing that I do have a question about is actually to the city of 624 00:53:00,240 --> 00:53:08,400 Franklin and that is to say why would we think that this is a vital 625 00:53:06,000 --> 00:53:14,960 part of our budget. This cannot be a vital part of our budget. This does come 626 00:53:10,640 --> 00:53:22,480 to an end at some point. um whether it's you know 3 to 5 years from now or what 627 00:53:18,079 --> 00:53:30,480 is it 11 or 15 years from now it that is scary to me as a resident. Um 628 00:53:27,359 --> 00:53:36,000 and I think that that is the biggest question that we need to that we need to 629 00:53:33,040 --> 00:53:42,880 solve. But I am definitely um not opposed to expan this expansion. Um I 630 00:53:39,440 --> 00:53:47,280 would be very curious to um Danielle's um question as to what the what's the 631 00:53:45,920 --> 00:53:53,599 difference between these wetlands and the wetlands from before that you know I 632 00:53:51,280 --> 00:53:59,200 have had experience with the DNR just blowing past wetlands when they want to 633 00:53:56,800 --> 00:54:04,880 and making a big deal out of them when um 634 00:54:01,599 --> 00:54:09,839 it's fits their purpose I guess. Um, this is within a dump. The the city of 635 00:54:07,920 --> 00:54:15,520 Franklin set this up. It's within a parameter. 636 00:54:13,520 --> 00:54:21,559 These are the wetlands that are in this um facility. And if they're not 637 00:54:22,400 --> 00:54:29,839 really great, I don't really know what the what the problem is. And there are 638 00:54:27,440 --> 00:54:36,000 already ones that are being set aside to protect. So just a lot of questions 639 00:54:33,520 --> 00:54:42,160 brought up because I did not know a lot coming into this meeting. Um now I know 640 00:54:39,760 --> 00:54:45,572 a lot. So thank you. >> Thank you Suzanne. [applause] 641 00:54:46,880 --> 00:54:53,720 » Is there anyone else wanting to change their mind and provide an oral comment 642 00:54:50,720 --> 00:54:53,720 today? 643 00:55:00,480 --> 00:55:03,559 All right. 644 00:55:03,760 --> 00:55:07,760 » If you've changed your mind, then >> Yeah. 645 00:55:06,800 --> 00:55:09,680 » You need my form. >> Did you fill out one? 646 00:55:09,200 --> 00:55:13,119 » Yeah. Okay. >> I walked in late and 647 00:55:10,960 --> 00:55:15,920 » Okay. If you have one, I'd love to get it just so I have your name so I can 648 00:55:14,480 --> 00:55:19,680 take notes on what you say. >> Okay. You need name, address. 649 00:55:18,559 --> 00:55:24,920 » Yeah. >> Can you give the form? 650 00:55:21,280 --> 00:55:24,920 » Can you give me the form? 651 00:55:30,400 --> 00:55:33,559 Thank you. 652 00:55:43,200 --> 00:55:46,200 Oh. 653 00:56:09,839 --> 00:56:16,520 No, the the slip just so we have a >> she's working on it. Yeah, 654 00:56:16,880 --> 00:56:24,119 » sorry. >> Yeah, it just helps me keep track of 655 00:56:20,559 --> 00:56:24,119 what you say and 656 00:56:24,799 --> 00:56:28,119 » that's all right. 657 00:56:30,160 --> 00:56:38,160 Hi, my name is Mera Cresvic. I am the district 4 alder. I also sit on the 658 00:56:36,079 --> 00:56:45,040 finance committee and I've lived in Franklin since 1971. 659 00:56:40,960 --> 00:56:52,319 Um, the landfill has been here and I do consider myself an environmentalist. 660 00:56:48,000 --> 00:56:59,040 I do believe that it makes more sense to expand the existing landfill than to 661 00:56:55,920 --> 00:57:03,040 create a new one elsewhere. The wetlands, as were discussed, I was 662 00:57:01,040 --> 00:57:07,680 listening on the way over. If I understood correctly, were previously 663 00:57:05,520 --> 00:57:13,599 farmed and we all know what chemicals do in 664 00:57:10,400 --> 00:57:19,520 farmland. You had stated there's a lot of invasive species there. You had 665 00:57:16,160 --> 00:57:25,280 stated that the are lowquality wetlands. So I failed to understand 666 00:57:22,559 --> 00:57:28,000 adequately why this would be denied. Thank you for your time and allowing me 667 00:57:26,799 --> 00:57:31,319 to speak. >> Thank you, Mera. 668 00:57:35,520 --> 00:57:41,640 Is there anyone else? Sir 669 00:57:49,599 --> 00:57:53,000 Thank you, sir. 670 00:57:54,160 --> 00:58:01,280 » Ron Dretzka, did I get it right? >> All right, good. 671 00:57:58,640 --> 00:58:06,079 » I had one question. I I did what didn't hear it mentioned, but I remember years 672 00:58:03,119 --> 00:58:12,720 ago that what they down there they had to uh eliminate houses that the water 673 00:58:09,599 --> 00:58:17,440 wells got poisoned. Is that a concern? Now, 674 00:58:15,200 --> 00:58:25,359 you know, you're expanding. Now, what happens when that expansion 675 00:58:21,520 --> 00:58:30,240 reaches wells that are still that people don't have city drinking 676 00:58:27,200 --> 00:58:36,960 water? They still got wells. I got a still got a well. What does that do to 677 00:58:33,359 --> 00:58:41,200 my well? Anything. I live on 94th and Ryan. 678 00:58:38,720 --> 00:58:45,359 How far does that go? because I know those houses had to be removed. People 679 00:58:43,119 --> 00:58:51,839 had to move from there to my neighborhood which is on 94th and Ryan. 680 00:58:49,440 --> 00:58:58,559 They had to be bought out. So, a lot of these older guys probably 681 00:58:54,240 --> 00:59:02,880 know that. They know this. So, so 682 00:59:00,480 --> 00:59:06,960 sorry guys you young guys. But yeah, I mean just 683 00:59:05,599 --> 00:59:13,119 something to consider and I haven't heard it in this meeting at all but 684 00:59:10,559 --> 00:59:17,680 Is that a consideration in your assessments? And when you check the 685 00:59:15,359 --> 00:59:21,119 ground and all that, how far does that travel? 686 00:59:19,359 --> 00:59:27,440 Because you're talking about toxics and whatever comes to the dump go leeches 687 00:59:23,520 --> 00:59:34,480 into the ground. How far does that go into the ground to other pe to people's 688 00:59:29,839 --> 00:59:39,680 wells or or uh places of where they live? I mean, is there some way to 689 00:59:37,280 --> 00:59:42,319 measure that? It's not really a part of >> this review. Y 690 00:59:41,280 --> 00:59:46,319 » isn't. Okay. I'm sorry. >> Appreciate Ron. No, I your comments well 691 00:59:44,799 --> 00:59:49,760 received. It's not part of the wetland process, but there is another part of 692 00:59:47,599 --> 00:59:53,599 our solid waste permitting process that will address your concerns. There's a 693 00:59:51,599 --> 00:59:58,720 extensive hydrogeeologic study that we have to perform as part of a different 694 00:59:56,079 --> 01:00:02,960 process than what Travis Travis is talking about tonight that looks at the 695 01:00:01,040 --> 01:00:07,280 groundwater flow patterns underneath our proposed expansion. We design a robust 696 01:00:05,359 --> 01:00:11,920 monitoring system and a robust liner system that goes through a DNR peritting 697 01:00:09,680 --> 01:00:16,000 solid waste permitting process, okay, to ensure that those protective measures 698 01:00:13,760 --> 01:00:22,000 get first put in place and then that there's a monitoring system beyond those 699 01:00:19,440 --> 01:00:26,079 that liner system to ensure that if there was a leak in that system, we 700 01:00:24,319 --> 01:00:30,640 would detect it prior to it meeting a downstream receptor like a private. So 701 01:00:28,559 --> 01:00:34,319 that that that process will >> okay 702 01:00:30,960 --> 01:00:38,480 » unfold if if part of if if we can get through this process which is we have to 703 01:00:36,720 --> 01:00:41,200 understand if the area we proposed for this expansion we can receive the 704 01:00:40,160 --> 01:00:43,839 wetland fill permit. >> Okay. 705 01:00:41,599 --> 01:00:46,319 » So good comment not related to what's being talked about tonight but it will 706 01:00:45,200 --> 01:00:50,559 be addressed. >> Um I assure you. 707 01:00:48,400 --> 01:00:55,760 » Okay. Thank you. >> All right. Thank you Ron. Is there 708 01:00:52,640 --> 01:00:59,040 anyone else? Thought I saw a hand. Just want to make sure. 709 01:01:06,079 --> 01:01:12,880 All right, with that I'll start the closing 710 01:01:09,920 --> 01:01:16,640 statement. Uh, I would again like to remind you that 711 01:01:14,640 --> 01:01:22,079 written comments may still be submitted to me, Travis Rder, no later than 712 01:01:19,119 --> 01:01:25,520 Friday, September 4th, 2026. and all written comments submitted will have the 713 01:01:23,920 --> 01:01:28,960 same weight and effect as the oral comments and statements given at the 714 01:01:26,880 --> 01:01:32,720 hearing today. If there are no further comments, I truly want to thank you on 715 01:01:31,119 --> 01:01:37,559 behalf of the Wisconsin DNR for your attendance here today. The hearing is 716 01:01:34,319 --> 01:01:37,559 now over.