[0:02] Table, and we'll have everyone else do an [0:05] introduction. If you have any questions, go ahead [0:07] and throw that into the chat function or [0:09] do the raise the hand thing. That way, [0:12] we can make sure that we include you [0:15] into the dialogue here. So first, before we [0:17] go around, we'll start with Christy Christy Tidd, [0:21] Green County Department of Development. Vicky Sheets, Green [0:26] County Department of Development. Randy Gilbert, Sanitary Engineering [0:30] Department. DeAngelo Navratil, Greene County Regional Planning. Alright. [0:36] This is gonna be I don't know how [0:37] to to really it's kinda like herding cats [0:39] here, but if everyone who is logged on [0:41] and has the ability to access a mic, [0:44] if you just kinda introduce yourself real quick [0:46] and who you're with. But before we do [0:48] that, actually, is do we have anyone from [0:50] Greene County's IT Department on the call? Yes. [0:54] This is Mitch Fletcher, network admin. Awesome. Thank [0:58] you so much for coming. Mitch will be [1:00] our sort of point of contact for any [1:02] technical related questions that we might receive. Alright. [1:06] So if you can maybe start with the [1:08] Jacobs team and then we'll go with everyone [1:09] else. So Jacobs is our consulting agency that's [1:13] helping us build this RFP and a one [1:15] stop shop permitting solution. Yeah. I'll go first. [1:19] Oh, sorry. Janine, I think you're on mute. [1:32] Yeah. I got it now. Sorry about that. [1:34] Janine Dioriso, I'm one of the two key [1:37] main players helping pull this RFP together, and [1:41] we'll be walking through the scope of work [1:43] with you. Yep. I'm Eric Habermeyer with Jacobs. [1:47] I've been working with Janine just to kinda [1:49] help put this together. And then I think [1:51] for the rest, maybe just go alphabetically if [1:53] you can follow the no. I'll turn it [1:55] over to Ann. Albert, I think, is the [1:56] next on the list. Ann Albert, did you [2:01] there's a lot of echo. Not sure if [2:18] I'm next, but, this is Michael Bowen with, [2:21] three s g plus. Good morning, everyone. Eric [2:24] Sabato, MainStar. Brian Fatka, Maria Delisle, and Sandy [2:31] Hess, and we are all from the ICC [2:33] Community Development Solutions. Ben Smith with Tech Systems. [2:44] This is Ray Barker and Kara McFall with [2:46] Online Solutions Citizenserve. Eric and team, good morning. [2:56] This is Austin Kaiser with three s g [2:58] plus. A little out of order here, so [3:00] apologize for that one, but good to see [3:02] you guys. Hey. Good morning. This is Yeah. [3:07] Might be jumping as well, but Taylor Brodersen, [3:11] Helen Whiteco, and Savannah Harris all here with [3:14] Brightly Software SmartGov. Hey. Good morning. This is, [3:20] Harish Krishna with Tejas Gov together with, my [3:24] colleague, Nandan Naik from Atlanta, Georgia. This is [3:30] Gavira Corrido with Cityworks Trimble. Michael Romano, Cityworks [3:40] Trimble. Janelle Ennis, Cityworks Trimble. I'm not sure [3:49] if I'm in the right order here, but [3:50] I guess it makes the most sense for [3:52] us to introduce ourselves now. My name is [3:54] Matti Pujalt. I'm here with Tim Sharber. We [3:57] are both here with NV five Geospatial. Jason [4:06] Thompson, I'm here with Zipflo. Alright. Is that [4:21] everyone? The do we miss anyone here? This [4:24] is this is Shadrick Adams with Greene County [4:27] Public Health. I'm also responsible for the noise [4:30] at the beginning of the call, so I [4:32] apologize to everyone. My mic was on. It's [4:34] all good. Thanks, Shadrick. This is Chrisana Anderson [4:37] Lutz. I'm with Greene County Engineer. Thank you. [4:42] This is Al Kuzma, Greene County Building Regulation. [4:52] Right. I think that's everyone. Alright. So just [4:56] a minute, I'll hand things off to the [4:58] Jacobs team to kinda walk us through this [5:00] PowerPoint presentation. But before we get started, I'd [5:03] like to just make sure that we're all [5:05] tracking the same time frame here. So any [5:08] questions are due by January 30 by four [5:12] p. M. Eastern Standard Time. Our responses back [5:15] to you are due by February 6, '4 [5:17] p. M. And all proposals are due by [5:20] February 20. And that is eleven a. M. [5:23] Eastern Standard Time. So with that, I'm going [5:27] to hand things off to Janine and Jacob's [5:29] team and they'll walk us through their presentation [5:31] here. Yeah, thank you. So there's the agenda. [5:39] Let's hit the purpose of the RFP real [5:41] quick. Eric, if you can go to that. [5:44] So that's that schedule overview. Oh, sorry. Eric, [5:48] can you go back to the schedule overview? [5:52] Sorry about that. And this is what Eric, [5:55] Henry was just speaking to. This schedule overview [5:58] is included in the RFP, so you can [6:01] see those dates. There is a note underneath [6:04] that that indicates, you know, these dates could [6:06] change, but for the most part, this is [6:09] the solid schedule that Greene County is looking [6:12] to follow. Eric, you want you can go [6:16] to the next slide. So how we want [6:19] to conduct a meeting. So support consultant is [6:24] us, Jacob. Greene County, and we will present [6:29] the topics listed in the agenda. We wanna [6:31] leave thirty minutes at the end for your [6:34] questions and answers. So let us get through [6:37] the core content. If you have a question, [6:41] jot it down, and when we open it [6:42] up, we'll certainly respond to those. And as [6:46] Eric said, the hand raise function is gonna [6:48] help us when we get to that point. [6:51] All questions we will be documenting any questions [6:54] that are raised here verbally, but you might [6:56] notice that in certain instances, we will say, [6:59] please submit that in writing, because we know [7:03] that that's gonna be information that, you know, [7:05] needs to be documented and and pushed back [7:07] out through, the response to questions. So just [7:11] be prepared for that. Okay. Eric, the next [7:15] slide. So purpose of the RFP, Eric Henry [7:18] gave a nice summary on that. And just [7:21] to really we're and we're not gonna read [7:23] all this text, but really focus on key [7:26] purposes. So technology solution, Greene County is looking, [7:31] for a permitting and plan review technology solution. [7:34] That could be one technology that encompasses all [7:37] the requirements and the things they're looking for, [7:40] or it could be a technology solution that [7:43] involves a couple of different technologies. It is [7:46] important to be mindful, and there's a technology [7:49] diagram included in the RFP, of the existing [7:53] technologies that they're working with. In certain instances, [7:56] a software such as stages that supports building [8:01] regulation, that's in that's staying. And so you'll [8:04] notice that there are some requirements around triggering [8:10] notifications between those two systems and and then [8:14] some. So take in mind that full suite [8:18] of software that they currently have in play. [8:21] There's a couple of mentions of software that [8:24] is optional. So this just indicates that Greene [8:27] County is thinking through a few things, about [8:30] their technology suite as it as it exists. [8:34] And when we're looking for costing of something [8:37] like an online phone system, I think is [8:39] referenced in there, it's labeled as optional. They're [8:43] considering that as part of the solution if [8:46] if that's going to improve things for them. [8:48] So take that in and be mindful of [8:51] those details when you're looking at them. Overall, [8:55] they are looking, as Eric said, this one [8:57] stop. This is this is a lot about [8:59] a key focus is on customer service and, [9:03] efficiency and processing permit applications and plan reviews. [9:08] And so ease of use on the customer [9:11] side, what what the end user has to [9:13] interact with simplicity, is a key objective in [9:17] what they're looking for. Also, you'll see reference [9:21] to smartly presented. So if I'm a customer, [9:24] I'm entering what I want to do, what [9:26] type of business I want to do at [9:28] Greene County. The system through entering of of [9:32] few keywords will help present to me the [9:35] process I need to follow, the permit applications [9:38] I'm I'm going to need to apply for, [9:41] the turnaround times that I can expect as [9:44] these applications go through internal review. So these [9:49] are key objectives that the county is looking [9:53] for. And then, of course, on the internal [9:55] side, having access to whose court is it [9:58] in now. I've reviewed it. I'm sanitary engineering. [10:01] I need to now have county engineer do [10:05] their thing. So, there are timings of push [10:08] notifications. So notifications and supporting that process is [10:12] another key objective. The staff are aware of [10:15] where things are at and and those turnaround [10:17] times and how they're performing in alignment. So [10:21] that's an expanded purpose and vision. Eric, you [10:24] can go to the next slide. So scoop [10:27] of work. So this is included in appendix [10:30] b as in boy. Eric, you can move [10:33] that past that slide. So boring text, I [10:37] know, but just to emphasize what the county [10:39] is looking for. So phase one on project [10:41] definition, you see a couple of key tasks. [10:45] So the scope of work when we lay [10:46] this out, we are asking you to present [10:49] a proposal that more or less follows what [10:52] is being asked for. You'll see a lot [10:54] of rigor, in the configuration stage around testing [10:58] and training. Those are critical elements because we're [11:01] really on cost client adoption, end user adoption, [11:06] and ease of use. In the project definition [11:09] phase, it's just, you know, setting out that [11:11] project management plan. What is your timeline? What [11:14] are the key, activities that will be going [11:17] on? And a key thing this informs is [11:19] you're working with busy people. Whoever selected will [11:22] be working with really busy people and they [11:25] need to know that schedule in advance of [11:27] when their time is going to be needed [11:28] so they can plan accordingly. And then, of [11:31] course, the kickoff meeting to explain how things [11:34] are going to move forward. On the next [11:37] slide, we're starting on phase two, which is [11:39] really the blueprinting. One thing I really want [11:42] to emphasize is Greene County staff, people around [11:46] the table that you're that are on this [11:48] call, and others did a lot of intense [11:51] work to envision what they wanted. And so, [11:55] you'll notice in the, right under the the [11:58] phase two blueprinting title, it says confirm business [12:02] processes. A big difference, and this is, something [12:06] to take note of, we are not asking [12:08] you to start from scratch and and pull [12:11] these people through a bunch of, well, how [12:12] would you like it to be set up? [12:14] How would you like it to work? They [12:16] have done a lot of great work toward [12:18] that end already, and it's very detailed business [12:21] process diagrams in that appendix b. That is [12:25] their vision. It's also been couched that, you [12:28] know, this may be your vision. You may [12:30] not get a % of of how you [12:33] want this to work. It may be 90%. [12:36] That's what we're targeting. Right? It's not a [12:38] hundred. But nonetheless, that is their vision. So [12:41] I've they've gone through a lot of effort [12:43] to do this. So I really wanna emphasize [12:45] that you're not hitting the you know, from [12:47] ground zero, you're starting a leg up. And [12:51] what came out, the tech technical the functional [12:54] requirements that you see in that Excel spreadsheet [12:57] that was included in the proposal package, that [13:01] we're asking you to fill out, those functional [13:04] requirements are directly related to those business process [13:08] diagrams by business process listed, and they are [13:11] categorized by permit type or plan type that [13:14] is being reviewed. So there is a one [13:16] to one alignment there. So those diagrams really [13:19] help understand what the county's asking for, from [13:23] a vision standpoint, and those functional requirements were [13:26] asking you to say, can your technology solution [13:29] do this? Is it out of the box? [13:32] Is it something that would need to be [13:33] created? You know? So they have some sense [13:36] of what your solution how many of those [13:39] requirements it actually needs. So as part of [13:42] blueprinting, that system implementation plan, you know, is [13:47] a task creating the that more detailed technology [13:50] set of steps, going through the functional requirements, [13:54] the business process, and then working with their [13:56] IT designated person around to make sure there's [14:00] an understanding around data security, any hardware or [14:05] interfaces to existing software. So, is that blueprinting [14:10] phase, a lot of work, but there is [14:12] also a starting point. On the next slide, [14:16] we show an example of those detailed business [14:19] process diagrams. I know you can't read that [14:21] on the slide, but they are in the [14:23] RFP. Again, you know, you'll kind of notice [14:26] workflows, and I know technology people are used [14:29] to looking at these. And you'll see the [14:32] existing systems reference as well as a generic, [14:36] blue cylinder data box that is labeled One [14:39] Stop. That's the technology solution. And so, that, [14:43] we're seeing what do we want One Stop [14:45] to do at a particular step. Okay. Next [14:49] slide. Then, during phase three, that realization phase, [14:54] the the confirmation of the plan of action, [14:57] the what what what the team the proposal [15:00] team is going to be doing to build [15:01] out. Now you're starting to realize and set [15:04] up those configurations. Again, you'll you'll see a [15:07] lot of reference to and they're in the [15:09] scope of work in that appendix b. It [15:12] describes what each of those testing steps entail. [15:16] But for those of you who are technology, [15:18] it's pretty best practice. Right? But a lot [15:20] of emphasis on testing, making sure data's flowing [15:22] because we've got several systems at play here. [15:26] And then training too. We're not looking for [15:29] a very simple one day training. This is [15:32] how you do it. But know that there's [15:36] a lot of, people not only on the [15:39] customer side, but on the, internal side that [15:43] come from different groups. So, the training can't [15:47] just be this quick one day. There's there's [15:49] some kind of focused training that needs to [15:51] go on. Again, because the the long term [15:54] interest is that they've got a solid technology [15:57] solution that's accepted and used and loved by [16:02] staff. Okay. Next one down. And then go [16:10] live. Of course, being there when things go [16:13] live, be there for when, questions are being [16:17] asked. And, in particular, in the costing sheet, [16:20] you'll see, there's an interest in knowing the, [16:23] just up to five years, what those annual, [16:27] five years cost would be, to provide the [16:30] maintenance and support. Alright. Next one. We're getting [16:35] to questions, guys. Okay. Last section that I'm [16:38] gonna talk through, and then we'll toss it [16:40] back. Go ahead, Eric. So just, this is [16:43] in the RFP itself, but just, verbalizing is [16:47] there's the address for where the hard copy [16:50] proposal should be submitted along with the USB [16:53] flash drive. So you'll see they're looking for [16:55] five hard copies. That includes that separate Microsoft [16:59] Excel spreadsheet where you are responding yes, no, [17:03] maybe with configuration, those types of things to [17:06] each of those requirements, and then an electronic [17:09] copy. So both the proposal itself and that. [17:13] And then the cost proposal, they want in [17:15] a separate field envelope. Alright, Eric. So the [17:22] proposal requirements, you're used to seeing these categories. [17:28] There are indications of page limits, so it [17:31] gives some sense of detail on what's being [17:34] looked for. Just clear writing, nailing the what [17:39] is being asked for and and providing that [17:41] exactly is a key. Right? Simplicity and clarity [17:46] is is is gonna be the key. You'll [17:49] notice on the e, item e, the proposed [17:52] technology solution, that's pretty short, two pages. It's [17:56] a basic statement of, okay, are the needs [17:58] that we have. What do you propose from [18:01] a technology? You may be teaming up with [18:03] another technology provider, or you may have the [18:07] whole enchilada in one suite. But the point [18:09] is is is that section is to say, [18:12] what is it? We're not looking for a [18:14] bunch of salesy material. We know sometimes people [18:17] will go their route of in a section [18:19] like that, you know, throwing in 10 brochures. [18:22] That's not what we're looking for. We're looking [18:24] for simplicity and clarity. Please state exactly what [18:27] you're proposing. And then it's in that item [18:29] f where we want you to detail out [18:32] the approach. And, again, the the key nugget [18:35] here is the approach is the scope of [18:37] work that's detailed out in appendix b as [18:40] in boy. So if you follow that scope [18:43] of work, obviously, you're professionals. There are variations [18:48] from that, which is fine and understandable. But [18:51] for the most part, you have the messaging [18:54] around intense testing, good training. Those are key [18:58] nuggets. Okay? Almost there. Okay. The cost proposal [19:04] sheet, which is appendix a, you'll notice just [19:08] out of the gate that in the table [19:10] itself, each of the, from the scope of [19:14] work, each of the numbered scope of work [19:16] items are listed there. The titles are listed [19:19] there, and that's where we're emphasizing, please follow [19:22] this approach. Right? How much would it cost [19:24] you to get through that, you know, the [19:26] estimate, any expense costs associated? On the expense [19:30] cost, you know, if there's a lot of [19:33] work you can do remotely and you're not [19:35] having to travel in, especially if you're not [19:37] local, that's gonna, you know, weigh well. So [19:40] you're balancing out that need of being in [19:42] person and the value of that versus work [19:45] you can be doing offline. And then on, [19:49] what's flashed up on the screen is the [19:50] second page of that. You'll see reference to [19:54] the interpieces, a potential for data migration if [19:59] the decision is to get rid of one [20:01] of their existing technologies, because this new technology [20:05] solution might place this. I say that with [20:08] the disclaimer. There has been no decision towards [20:10] that end. It's just a potential, and we're [20:13] leaving options open where where decisions still need [20:18] to be made. There are references in the [20:22] interfaces two to three non Greene County, so [20:27] statewide systems where different groups or divisions at [20:32] Greene County must interact with. You've got a [20:34] system like TOCAY. You've got the health department [20:38] uses HDIS. These are statewide systems. They are [20:41] not going away. So, you'll see referenced and [20:44] described in the RFP. And we've already had [20:47] conversations with those entities. But a a very [20:52] simple data exchange, whether that's a direct integration [20:56] or, a data export from those systems where [20:59] someone manually is bringing that into the new [21:02] technology system on the Greene County side, which [21:05] that latter is the more practical of what's [21:08] gonna happen based on what we know. Those [21:10] statewide systems don't want Greene County systems, you [21:14] know, feeding information in and out and exchanging. [21:16] So that data export process is is the, [21:20] route that is most likely. So but please [21:25] look at those costing things as, let's put [21:28] them in here as if it were an [21:30] integration on a couple of those data points [21:33] just for cost comparison and as prompted there. [21:38] I'm probably confused that just read what's written [21:40] there, which is please give us a cost [21:42] for an integration. But, again, for your back [21:44] pocket, most likely, will be a manual export [21:47] import. Okay. Almost done, Eric. Okay. The the, [21:54] functional and technical, requirements response work, which is [21:58] that Excel spreadsheet. Again, it supports the listing [22:03] of requirements as defined by Greene County staff. [22:07] We would like you to submit that, you [22:10] know, along with your proposal that's helping with [22:13] the evaluation that the voting members are gonna [22:15] be going through. It doesn't count on your [22:18] proposal page limit, and you can see the [22:21] number of different types listed there. So, functional, [22:24] how do we want it to behave? The [22:26] notification, routing, you know, display performance metrics against [22:32] processing time, those types of things. On the [22:35] technical requirements, that was heavily led by Greene [22:39] County IT, to help describe the technology environment, [22:44] any data and security requirements, those types of [22:46] things. And you'll see that categorization when you [22:49] look at that workbook. Again, there's two worksheets, [22:53] functional requirements, technical requirements. Okay? You can't read [23:02] that. That's just an image of what it [23:04] is. So you have the requirements listed on [23:06] the left, the category that it falls into, [23:10] and you're filling out those four blue columns [23:12] with, and there's some acronyms there that that [23:15] indicate, yes, the my technology solution can wholly [23:18] meet this. No problem. Or it can't. Right? [23:22] So and we recognize that a % of [23:26] everything Greene County has envisioned may or may [23:29] not be possible. Alright? The proposal evaluation criteria, [23:37] this is directly from the RFP. So we're [23:40] quality of the proposal references. Where have you [23:43] done something similar? We know it may not [23:46] be exactly similar, but, those references are important. [23:51] Your just general qualifications and experience. Is this [23:55] your first time ever doing this, or have [23:57] you done this, you know, 5,000,000 times kind [24:00] of a thing? That ability to meet desired [24:03] functionality, again, that workbook that has the functional [24:06] and technical requirements, that's, you know, an important [24:12] extremely important consideration for the voting members. And [24:15] then we've got the cost listed out as [24:17] well. And I think that's probably the last [24:21] slide for me. Eric Henry, I'm gonna toss [24:26] it back to you if you've got someone [24:28] there who can do this last section on [24:30] the contract forms and then we can open [24:32] it up to q and a. I I [24:34] don't believe we have anyone from legal on [24:36] the call. All I'll say about this is [24:38] these are required documents for your submittal of [24:41] of your bid. If you have any questions, [24:44] I'd ask that you send those in writing [24:45] so we can have our legal team go [24:47] ahead and review them. Then I'll put out [24:50] some sort of FAQ available to all to [24:52] make sure that those answers are able to [24:55] be reviewed by everyone once spent. So that's [24:58] all I have to say about that section [25:00] time being. Respond, I mean, about that. I [25:09] don't know if Jeanine, you wanna go over [25:10] that or I feel like it's self explanatory, [25:14] but I'm happy to encourage questions, comments on [25:18] this. Okay. Alright. Well, let's since that's a [25:24] nice segue, let's go ahead and open it [25:26] up for questions. Think Eric, Hob Habermeer, if [25:30] you can, do that, we can open it [25:32] up. So that was a lot. It may [25:37] rest, where let's go ahead and and open [25:39] it up for questions. And as, Eric Henry [25:42] suggested, if you don't mind using your hand [25:44] raise, that'll give some sense of order to [25:46] any questions. Let's see. And Eric Habermeyer, you [25:57] can help me. Why am I not seeing [25:59] the hand raised? Okay. Who's that? Taylor Roderson? [26:05] Yeah. Thank you. Can you hear me okay? [26:08] Yep. Yes. We can hear you. Perfect. So [26:13] I'm looking at it's mentioned a couple of [26:15] times the interfaces that are required and optional, [26:21] and I'm specifically looking at page 18 where [26:24] it has them, labeled out in a table. [26:27] I was curious, and I can kinda ask [26:29] these questions one by one, but I was [26:31] hoping to get a better sense of exactly [26:35] what each of these systems is used for [26:38] today. And secondarily to that question would be [26:42] if the solution that we're bidding on could [26:46] help consolidate some of these other systems. Is [26:49] that something you'd like us to propose as [26:51] well, or is the county looking to definitely [26:55] keep all of those in place and just [26:57] integrate? So sorry. Long question. It's a great [27:02] question. One thing that popped into my mind, [27:05] Eric Henry, I'm stalling for time because I'm [27:07] gonna toss it to you as the official [27:08] kind of take the questions and farm it [27:12] out. But, Eric Coppermeyer, if you don't mind, [27:14] I think, having the RFP, maybe we could [27:16] even pull up that page 18 might be [27:19] helpful. Yep. I'm pulling it up right now. [27:24] Okay. And, Taylor, to oh, sorry. There is [27:28] a diagram that I think is helpful. I [27:30] think it's figure two one that shows the [27:34] different technologies in play, and there's some commentary [27:37] about what type of information is desired to [27:40] be shared. Is that all the details at [27:43] the moment? No. But it gives that high [27:45] level. So anyway, Eric Henry, did I spell [27:49] enough for you? So for the first part [27:51] of your question, I would leave that to [27:53] the individual departments to answer specifically. The second [27:58] part, I'm gonna give you kind of a [28:00] nuanced answer. It's just probably not super helpful, [28:03] but in a perfect world, consolidation would happen. [28:07] That being said, it feels like it's it's [28:10] so burdensome and so complicated that it's unattainable, [28:13] but I'd be happy to look at proposals [28:17] that have that function in there. But it's [28:19] not something that I'm requiring at this time, [28:21] if that makes sense. So if I'm hearing [28:26] that correctly, you know, being able to interface, [28:29] you would want us to outline but would [28:31] also be open to a recommendation where we [28:35] may be able to consolidate. Correct. Okay. Yeah. [28:40] That's helpful. And I do see the 2.1, [28:50] so that's really helpful as well. But if [28:52] any of the departments have any other detail [28:55] that would be helpful for us on the [28:56] different systems, definitely open to hearing that. I [29:02] don't put you on the spot. What do [29:04] you I I I don't. Okay. We'll start [29:08] with the media room that we have here, [29:09] then we'll open it up to the people [29:11] on the call. So go to Randy with [29:14] sanitary first. Yeah. With sanitary, we use the [29:17] Cityworks. CityWorks is our main AMS asset management [29:24] system. We have the add on for the [29:27] PLL for all of our permitting, and all [29:31] of our historical permits are listed or are [29:34] contained in that software. So that is a [29:37] very vital piece of, history for us. While [29:44] it is listed as an optional, someone's going [29:47] to have to make a very good case [29:49] to me to move away from it. I [29:55] that's not going to be a decision that's [29:57] made likely. I'll I'll just say that. We [30:00] spent too much time and effort getting where [30:02] we're at. It's gonna have to be a [30:05] very great solution to move me away from [30:07] it. So I do wanna make that comment. [30:11] Now Tokay is the other one that we [30:13] utilize that's on this list. That's our backflow [30:17] prevention system. We keep track of all the [30:21] backflow devices in our system. Again, that's a [30:28] software that we've just we spent a lot [30:29] of time getting up and running. If there's [30:32] another solution, I guess we'd be we'd entertain [30:35] it. But, again, it has it would have [30:38] to have all of the abilities that that [30:42] software has it that we're used to and [30:44] our plumbers are used to before we would [30:48] consider moving. Deandra? Sure. So for regional planning, [30:56] we don't directly work with any of these [30:58] interfaces aside from GIS, but we use that [31:01] more for research purposes and for zoning research [31:05] and helping our people who call us with [31:08] questions on that. The only thing that we [31:10] would be looking for directly is the online [31:14] payment system because right now, we don't have [31:16] anything. We only take cash and checks at [31:20] the moment, so that's something that other departments [31:22] have obviously modernized on, and that's something we're [31:26] really gonna need assistance with. Awesome. Thank you. [31:32] I'm trying to think off the top of [31:33] my head. So let's go with public health. [31:35] Chad. Chadwick? Yeah. Chadwick here. We utilize the [31:40] program known as HDIS. That's health district information [31:44] systems. It's a very old, archaic database program [31:51] that encompasses just about everything that happens at [31:54] a health district from environmental to community health, [31:58] billing, receiving, tracking time, and mileage, all sorts [32:03] of things. Despite its age, we are not [32:07] looking for a replacement within the scope of [32:11] this of this proposal. Because it is so [32:15] old and somewhat sensitive, we want an export [32:20] only function with HDIS. That is we send [32:24] out our plumbing information into the one stop [32:29] shop database that we're proposing here, but it [32:32] would not be two way. Yeah. Sorry. I'm [32:37] gonna chime in here. This is Janine. And [32:39] that's indicated in the RFP as you just [32:42] said. Right? And I'm saying this for all [32:44] the proposers. Tokay that was referenced by Randy [32:48] Gilbert, which is the backflow prevention, that is [32:52] not intended to go away. It's just the [32:54] export activity. HDIS is another system that's used [32:59] at the state level that's not going away, [33:02] as well as a system called SWPPP. You'll [33:07] see that reference. That's a statewide, you know, [33:11] system as well. So, again, with those three [33:13] in particular, there's no replacement of that functionality [33:17] desired. Thank you. Let's go with Prasanna, are [33:27] you there for the accounting engineer? Yeah. I [33:29] am. Yeah. I just like to reiterate what [33:31] Janine just said, which is that SwiftTrack is [33:34] definitely something that we cannot replace. We're not [33:37] looking to replace. It's integral to what we [33:41] do with our storm water, and it does [33:43] an excellent excellent job with that. So we're [33:45] gonna go ahead and keep that the way [33:47] that it is. Apia is newer for us [33:52] and we are really liking the way that [33:54] it works. So we don't need to have [33:57] it replaced. But Apia is something that we [34:04] would consider if necessary, if someone had something [34:07] better out there. But it's working right now. [34:13] So that's about it. Fantastic. And last, certainly [34:18] not least, Al of the building department. Yeah. [34:22] Sage is, we're committed to that program. It's [34:25] our permit tracking system, plan review, also keeps [34:31] track of all our inspections. So, we're well [34:35] invested in that. We like it, and we [34:39] wanna keep it. Although, I do wanna keep [34:43] it open mind just in case there's something [34:47] else out there. But, you know, that would [34:50] be pretty exceptional for us to give up [34:52] on stages. And if anybody has So let [34:56] me let me do a summary here for [34:59] people on the phone who are, like, wait. [35:01] What's going on? There's, like, existing plan review, [35:04] permitting systems at certain and this is in [35:07] the RFP, but we're just verbalizing. You've got [35:09] building regulation. Al just spoke and he spoke [35:12] about stages, and that's indicated as something that [35:16] is not going away in the RFP. Stages [35:19] currently only handle plan, review and permitting tracking [35:24] for building regulation. The challenge is is that [35:27] other divisions who need communication and coordination and [35:32] and process flow to be supported as a [35:35] whole unit, is the county and these divisions [35:38] working together, a system like Sage's is not [35:42] currently supporting them. Similarly, when Randy Gilbert over [35:47] sanitary engineering was describing his use of Cityworks [35:50] for their asset management, that is not going [35:53] away. They're using, in to a a certain [35:58] degree, the PLL module of CityWorks. But, again, [36:01] it's just sanitary engineering. And you heard Randy [36:04] say, and it's labeled as optional. If the [36:07] new technology solution that we're asking for through [36:11] this RFP, does a with BAM job, right, [36:15] and could convince the Randy Gilbert and sanitary [36:18] engineering to release the CityWorks PLL component, then [36:22] that's what happens or vice versa. CityWorks PLL [36:25] is proposed to support larger divisions. I know [36:28] we got some CityWorks people. So you gotta [36:30] think of that, you know, it's the challenge [36:33] is it's being used, stages and both Cityworks [36:35] are being used by single group when it [36:38] needs to support all their groups or a [36:41] whole new technology solution is in play. So [36:47] that's kind of the big overview if you [36:49] hear people saying my plan in permitting review [36:53] software is not going away because it's already [36:57] supporting me. Did that confuse the matter or [37:03] bring clarity? I think that was really helpful. [37:08] I think all the feedback is helpful in [37:10] understanding where each department is. So thank you [37:15] very much. Looks like we have the next [37:21] question from Matthew. Yeah. Hey. Matthew here from [37:30] NV5 Geospatial. Out of curiosity, will Jacobs be, [37:35] providing a proposal to this RFP? No. We [37:41] are we we are not. We're a partner [37:45] with Greene County in getting the RFP ready [37:49] in alignment with their needs. Our role on, [37:56] the implementation phase of it is is TBD, [38:01] but but if there is a role there, [38:03] we would be helping to manage the implementation [38:06] and serve as a gatekeeper to answer questions, [38:09] those types of things. Okay. Great. Thank you. [38:27] Other questions? This is Taylor again, if it's [38:34] okay. I had one more. The RFP points [38:38] to 15 I think it was 15 unique [38:41] dashboards. Are there specific data points and dashboards [38:46] that the county is referencing for those 15 [38:49] or just looking for the ability to create [38:52] custom dashboards? Great question. So, yes. So think [38:59] of the end user that 15 number is [39:02] up to, I believe that's the language, but [39:06] that's the intent anyway. Think of the end [39:09] users within the county. So you have, you [39:11] know, executive leadership is interested in tracking metrics. [39:17] How are we doing? In particular, are we [39:19] being responsive to customers? We have stated out [39:23] there that, you know, once you submit an [39:25] application, it takes so many days to process. [39:29] How are we as an internal group performing [39:31] against that? So I'm making this up because [39:33] we haven't yet defined those dashboards. What would [39:35] they like on their dashboard if they could [39:37] pick, like, 10 things? But that's the idea. [39:40] So executive leadership, the the directors of each [39:44] of the divisions, Randy Gilbert, you know, etcetera, [39:49] Stephanie Gough, they will have specific for their [39:53] own group and their responsibilities, you know, kind [39:56] of keeping an eye on the ball and [39:58] making sure things are proceeding process wise and [40:00] they have a sufficient time. So those are [40:02] the types of metrics more aligned with performance [40:05] metrics, but still TBD. In the RFP itself, [40:08] I think we're requesting the cost associated with [40:11] if you were out of the gate to [40:13] build a dashboard for them, how much would [40:16] that level of effort be with the intent [40:18] that they would, through the training, would then [40:21] have the competency internal to create, you know, [40:25] random dashboards, ad hoc reports, should they need [40:28] to beyond that. So we're just looking for [40:31] the pricing of the dashboard piece actually creating [40:35] them. Okay. Thank you. Hey, everybody. This is [40:45] Michael Vaughn from DraftG Plus. I had a [40:48] question about the getting back to the two [40:51] way integrations with some of the various systems. [40:53] Are is it known at this time whether [40:55] systems like Tokay and Sages, do they have, [40:59] like, a an open API that that that [41:02] can be accessed and leveraged? Or is that [41:05] is the expect is the expectation that that [41:07] will be investigated and and and included in [41:10] the response? Great question. So we headed that [41:15] off. We did work with Greene County to [41:17] reach out to representatives from each of those [41:20] software vendors, to get clarity on that, you [41:23] know, would would you be open to a [41:26] a connection through an API or, you know, [41:29] or or do you have strict rules about [41:31] that? And absolutely, say no. All of them [41:35] indicated the preference was for that manual export. [41:39] So but they also referenced, potential for API [41:44] connection. So does it need to be further [41:48] discussed with them once they see the actual [41:50] data points of what we're looking for? And [41:52] we did kinda summarize that for them so [41:53] they saw that it's really about notifications of [41:57] when something is done. So when something is [41:59] done, for example, in SwiftTrack, which is a [42:02] statewide system, it works well. That the the [42:06] status of whatever's being done in SwiftTrack is [42:09] pushed into that one stop portal so the [42:11] customer truly has. Can the customer go to [42:14] SwiftTrack separately? Of course. But we wanna bring [42:17] it all together to them in one place. [42:19] So it's really primarily notification of where the [42:23] process is at within those other systems. So [42:26] that's the that's the the the type of [42:28] information, But, yes, definitely needs to be further [42:33] discussed with them. But those connections are made. [42:35] They're aware of the potential request coming. And [42:39] if we cost it what that API, just [42:42] simple notification of process integration is, then we [42:46] know that cost associated with that option if [42:48] those in entities say yes. Okay. Great. So [42:54] so I'm thinking about in thinking about the [42:56] proposal, you know, our our our our charge [42:59] is to investigate, well, a, the possibility of [43:01] whether or not that's that's that can happen. [43:04] But just the the cost associated with whatever [43:06] development work would be required, you know, from [43:11] the platform that we're proposing, the one stop [43:13] shop platform, if you will, and and what [43:15] that would take to to to essentially push [43:18] that data into into these these other platforms. [43:22] But in terms of the return data, the [43:24] things that are triggered in in the the [43:26] Sages and the ToeCase of the world, you [43:28] know, that would require a little bit further [43:30] exploration with those entities in order to in [43:33] order to get that return data, if you [43:34] will. Am am I understanding that correctly? Yeah. [43:38] No. And you raised a very valid point, [43:40] and I I I hear you. How about [43:44] this? Greene County will note this as a [43:47] question that we officially respond to, in writing. [43:52] And do you mind just submitting that making [43:55] sure you submit that question in writing, and [43:57] then the county will have a response because [43:59] you raised a valid point towards that end. [44:02] Yeah. Yeah. Absolutely. We'll we'll make sure we [44:04] get something submitted. Thank you, guys. Bye. Yep. [44:13] What else? Hi. Kara McFall, Citizenserv. Will you [44:18] be providing the copy of the recording of [44:21] this conference? Eric Henry? I'm okay with it. [44:31] Excellent. Thank you so much. Yeah. And it's [44:40] it's a big it's a big, RFP. I [44:44] think you probably all noted that, and in [44:48] particular, the, I forget the name of the [44:51] woman who brought it up. Taylor. Taylor. Thank [44:54] you. You know, that technology diagram in 2.1 [44:59] gives you that sense of, complexity, that they're [45:04] looking for with these different systems in play. [45:09] But at the same time, just that if [45:12] you keep that primary objective in mind, simplicity [45:15] on customer, I'm coming to I'm sitting at [45:19] home. I'm going I'm logging on. I'm typing [45:22] in a few keywords about what I wanna [45:24] do. And based on a search function, a [45:27] search engine, the system is communicating to me [45:32] the process I need to follow, the permits [45:36] I need to apply for, expected turnaround times, [45:41] right, processing times, and I'm able to follow [45:45] and see where my application is in at [45:49] the at any point in time. I also [45:52] know when I'm required to do something and [45:56] how long it's taken me. Right? And then [46:01] internally, again, the the same functionality is there [46:05] where internally they're able to see each other's [46:08] comments on plans. They're able to see tag [46:11] who's next because someone did just did something [46:14] in the field. So that vision really speaks [46:18] to efficiency and clarity of where I'm at [46:21] in the process. So those are the key [46:24] objectives. Even though there's a lot of existing [46:28] technologies at play here, If you kind of [46:31] think of it in that manner, it really [46:33] keeps that end goal in mind. Alright. I'm [46:39] very wordy. The county knows this, so I'll [46:41] stop. Eric, I'm gonna toss it back to [46:42] you. I have nothing to really add there. [46:50] Is there anything that we can clarify further [46:53] on or for anyone in the audience as [46:55] far as that last question goes? Any additional [47:04] questions? Well, not seeing any, so I guess [47:13] we can give you about an hour and [47:14] ten minutes back in your day there. If [47:18] you wouldn't mind submitting any follow on questions [47:21] in writing, that way we can make sure [47:23] we provide it as clear as a response [47:25] as possible. And, yeah, thank you for your [47:28] interest, and enjoy the rest of your day. [47:33] Thank you. Bye. Thank you.