[0:00] Uh with that said, uh we should be at [0:02] the point of finally getting that one [0:04] closed out. We have notified them of [0:06] liquidated damages, uh which are in the [0:08] amount of $28,800. [0:10] So, it is our intent to collect on those [0:12] liquidated damages for failure to [0:14] failure to meet milestone completion [0:15] dates. And we really want to push it. [0:18] We're definitely well over the final [0:19] completion date, too. But, uh um [0:21] certainly the milestone completion date. [0:23] » Okay. And then in the future we will [0:25] probably not um entertain any of their [0:29] proposals. [0:30] » Yeah. That Yeah. So any any u any bids [0:34] coming from that contractor would um [0:36] likely be rejected. [0:38] » So So Chris, just for um just for their [0:41] sake, it mentions the 2026 project being [0:43] substantially complete, but they will [0:45] see lots of pipe sticking out of the [0:47] ground about every two weeks or about [0:48] every two blocks or a block or so. I [0:50] believe those are street lights, [0:51] correct? at this correct utilities. [0:53] » Yeah. So the work the work to be [0:55] performed by the uh by the project um [0:58] contractor is complete mostly complete [1:00] um new utilities is installing uh [1:03] lighting on the east side of the road [1:05] and they wanted to have our contractor [1:08] complete before they came through to [1:09] complete those that light installation. [1:10] So that's why it's happening um [1:13] sequentially instead of at the same [1:14] time. So [1:14] » Do you know a rough timeline on when [1:16] they plan to have those lights [1:18] installed? Uh, I thought they said two [1:19] to three weeks somewhere in that that [1:21] neighborhood if that sounds right. [1:22] » Two weeks. [1:23] » Two weeks. [1:24] » Yeah. [1:25] » Okay. [1:27] » And then there's some work on Highway [1:28] 19, but that's not related to our our [1:30] project. So that's something else. [1:32] » Oh, you mean with the [1:33] » With the gas going on? Yep. [1:35] » Because that's in what state [1:38] » There? It's in the state right away, but [1:40] private utility. [1:41] » Okay. Any other questions for Kurt or [1:45] Chris before we go on to the item B? [1:49] Okay. If not, we'll get into the First [1:51] Avenue Southeast uh turnback. [1:53] » Okay. Uh next item I have for you [1:55] tonight is related to the First Avenue [1:57] Southeast uh Lassour County Lassur Cas [2:00] 60 uh uh potential turnback project. Uh [2:04] so I believe it's back in June. We are [2:06] authorized to complete a uh complete a [2:09] preliminary engineering report um to uh [2:12] review the uh potential turnback of this [2:14] roadway from Lisser County ownership to [2:17] the city of New. Um we have been uh [2:20] looking at this potential turnback for [2:23] three years now probably at this point. [2:25] Um and uh just need to kind of nail down [2:28] a few things as far as what the cost [2:30] would be, what the cost shares would be [2:32] and what the potential improvements [2:33] would be. So, uh we did uh review the um [2:37] existing roadway um make um proposed uh [2:42] uh made recommendations for proposed [2:44] improvements um and uh some costs and [2:47] potential funding. Um the the roadway [2:50] itself we have split into four different [2:51] areas working from south to north. [2:53] [snorts] Um area one and area two are in [2:56] the worst condition. Area two is um from [2:59] about 11th Street uh circle southeast to [3:01] about fifth street. southeast. Um, so [3:05] that would take care of the south half [3:06] mile line. [3:13] » So, so we're good. Yeah. [3:16] » Okay. [3:16] » You woke me up. [laughter] [3:19] » So, that'd be the south half mile of the [3:20] roadway. Uh, the remaining half mile is [3:22] is considered areas three and four. Um, [3:25] areas one and two were uh improved. um [3:29] the middle area two was improved in 1986 [3:32] to show what show how old that roadway [3:34] was. Um area one was uh in the in the [3:38] 90s it was 1998 and then area three um [3:41] the north portion and uh area threes and [3:44] four uh were early 2000s and then I [3:46] guess with the more recent Main Street [3:48] paving project. So um so we have gone [3:51] through this. We have had a meeting with [3:53] Lassour County to review um the cost and [3:55] cost for the project, the potential [3:57] funding splits. Um and um we did have a [4:00] very positive meeting with them. [4:02] Everything seems to be in agreement with [4:03] what we show in the report as far as how [4:05] we would um likely go through a a [4:07] turnback. So, um, as far as the costs in [4:11] this project, we did, uh, largely match [4:15] what was performed on the Scott County [4:18] turnback projects more recently, 209 [4:21] and, uh, 2022. So, we're regarding uh, [4:25] Columbus Avenue, more most the most [4:27] recent one. Um, copied identically how [4:30] the cost share was done on those as far [4:32] as who paid for what, um, whether it's [4:34] street cost, sidewalk costs, utilities, [4:36] and and so forth. Um and uh that's what [4:40] was used as a guide for preparation of [4:42] this report. Um so with that said um as [4:45] I mentioned before working from south to [4:48] north um we do have costs for um area [4:52] one uh which we have estimated to be [4:54] about $850,000 $847,000 total project [4:58] cost. Um area two we have a total [5:02] project cost estimated $977,000. [5:04] that's including engineering and soft [5:06] costs and all the other associated [5:08] items. Um and then uh areas three and [5:11] four have been kind of lumped together [5:12] since they um would have similar [5:15] improvements at about $713,000. [5:18] So areas one and two we are proposing to [5:20] do a pavement reclamation which is to um [5:23] leave the curb in place but grind up the [5:25] black top with the gravel um repave the [5:27] roadway um remove the excess material [5:30] and then repave the roadway with six [5:31] inches of new black top. Um so the [5:33] roadway would be um same geometrics as [5:36] it is today just with new surfacing. Um [5:39] that would be for areas one and two. The [5:41] south half of 1 Avenue Southeast while [5:43] the north half is proposed for Melon [5:45] overlay um because it is in much better [5:47] condition and that uh um is currently [5:52] being proposed to uh potentially be a [5:54] future project whether it happens at the [5:56] same time or not because it is [5:58] [clears throat] in much better [5:59] condition. So there's seven inches of [6:00] black top on that portion of the roadway [6:02] which is probably the heaviest roadway [6:04] in the section in town I imagine with [6:06] that um section. [6:10] Uh I mentioned some timing on there. Um [6:15] the next step in this process uh we do [6:18] have the the report in front of you here [6:20] today would be to move into a memorandum [6:21] of understanding which is to outline the [6:24] expected cost participation by uh city [6:26] new and um lassur county. Um and then uh [6:31] moving after that it'd be moving towards [6:32] a uh turnback agreement. Um that'd be [6:36] the more formal process which would have [6:38] all the same findings um from the [6:41] memorandum of understanding but would [6:42] likely be uh take place uh concurrently [6:44] with with bidding of the project when [6:46] costs are a little more finalized. [6:49] There's a process to kind of follow [6:50] through that. Um the turnback process [6:53] itself wouldn't be initiated until um [6:56] likely March at the latest so that the [6:58] turn back of the roadway at the soonest [7:00] could happen in uh 2028. Doesn't mean [7:03] the improvements can't happen before [7:04] that, but that's when they officially uh [7:06] would change jurisdiction. [7:09] Um and that is uh just based on mind [7:12] cycles as far as when those when that [7:14] timing would happen. [7:16] So, uh, with that said, um, [7:22] I I don't have information on [7:24] assessments. That wasn't part of this [7:25] report. That would be something that'd [7:27] be completed afterwards if the project [7:28] does move forward. Um that is something [7:31] that uh we didn't want to include with [7:33] the u report uh beyond just saying city [7:36] share of costs because assessments are [7:38] would not be um something that the [7:41] county would participate in a cost for [7:43] determining since they are uh going to [7:45] be uh providing about 50% funding [7:47] towards this report that was put [7:49] together. So we as a city item we [7:51] decided to leave that one out. So the [7:54] next step would be a feasibility report [7:56] and uh if the project moves forward well [7:58] sorry the next step would be a [7:59] feasibility report for assessments and [8:01] then as a project moves forward all your [8:03] normal um normal improvement schedule [8:05] for prioritizing [clears throat] bidding [8:07] and construction all that stuff. [8:10] So [8:13] this is all broken down in areas. Is it [8:15] something that we're planning to do [8:17] everything next year? [8:19] » No. So, uh, section one and two [8:23] » Mhm. [8:23] » Are the ones that we were proposing that [8:25] I proposed to the county of last week [8:26] when we met that we would like to see [8:28] one and two done. That would be the 600 [8:31] block roughly to the south and then [8:33] anything north of that was done in 2002 [8:36] 2003ish. Um, that is the proposed just [8:39] to leave it and just pay the city lump a [8:41] lump sum payment and then we'll do that [8:43] down the road. In my opinion, we could [8:46] hopefully see another 10 years out of [8:48] that, maybe five years. Obviously depend [8:50] on Minnesota winner. Um but that that [8:53] road still has a lot of life in it [8:54] before we would do any maintenance to [8:55] it. So and the county was in in [8:57] agreeance. Um me, Chris, and Ken met [9:00] with the the county and it was a very [9:02] good meeting. They were agreeance on [9:04] pretty much everything we proposed. We [9:05] like Chris said, we just pretty much [9:07] everything the council approved in 2019 [9:09] and 2022 on the Scott County agreement. [9:12] That's what we proposed to them. So, [9:16] » And again, I just asked Chris to come um [9:18] since he was here today already to [9:20] present this. I know this has been a [9:21] major top topic for three, four years [9:24] with that First Avenue on the south side [9:25] deteriorating as fast as it has been. [9:27] So, um I thought it was good information [9:29] for you guys to see where we're at and [9:31] all the steps that we have been taking [9:32] already to get to this point. [9:37] » Um I got a few questions. In area three, [9:39] you talk about the last sentence on the [9:41] 2.2 2.3 area 3. Um, improvements to this [9:47] portion of 1 Avenue Southeast may not be [9:49] imminently needed, but would generally [9:51] be expected within 5 years. So, uh, [9:54] because of that, we are doing a Milan [9:57] overlay because it's going to be only [10:00] useful life of five years. Are we doing [10:02] a Millan overlay and that's only going [10:04] to last for five years? [10:05] » Yeah. So the the improvements that are [10:07] identified in um area three which is the [10:09] north half mile of the road. So there's [10:11] a north half I should just um put it [10:13] that way. Uh we've identified mill [10:15] overlay of the pavement surface and then [10:18] ADA improvements are probably the most [10:19] substantial part of the project on that [10:21] one. Um the uh sidewalks go through [10:24] driveways and a lot of those were done [10:25] the way they were done 20 years ago and [10:27] don't meet any current standards. But [10:30] there's nothing in there that's um [10:32] there's it doesn't have potholes. [10:34] doesn't have a lot of surfacing surface [10:35] raveling or anything like that that's [10:36] creating a a condition where we need to [10:39] take care of it right now. Uh when I say [10:41] five years, it's just more of a and and [10:43] matches at 10 years. So something five [10:45] to 10 years somewhere in that range. The [10:47] expectation would be that the the [10:48] pavement would need a repair a mill [10:50] overlay um but not before five years. Uh [10:54] if it goes after 10 years, it probably [10:56] becomes something more substantial than [10:57] a mill overlay. But that's just as [10:59] » Okay. My mind is a turn around. One and [11:01] two would be done now. three and four be [11:03] done later. [11:04] » The the Yeah, that the expectation is [11:05] that areas one and two would be [11:07] completed um as soon as 2027 [11:11] and um the areas three and four would be [11:14] yeah the city has received receive the [11:16] funding now and take care of that [11:18] project when you're ready. [11:19] » Then if we when this happens, we would [11:22] sign an agreement to take it back with [11:25] the stipulations that they would still [11:27] share cost in area three and four. [11:32] » [clears throat] [11:32] » Usually in the past, Scott County had [11:34] paid like Scott County has paid us a [11:36] lump sum payment for objects that we [11:38] were looking at doing down the road. So [11:40] assume that's how we do the same thing [11:41] as [11:42] » So they would pay us and then we'd say [11:44] we just have that money in a [11:45] » That is correct. [11:45] » An account uh that [11:47] » A fund that we could use it when we're [11:49] ready to. [11:49] » That is correct. Yep. [11:52] » Uh talking about new sidewalks. Um it [11:55] references that the expectations that [11:57] we'll get traffic back up to what it was [11:59] and maybe I think it was cited as 2024 [12:01] or something like that. Okay. [12:03] » Uh in the report, [12:04] » Something like that. And then this is [12:06] more of a comment than really a question [12:08] I guess. [12:09] » But then you talking about the [12:11] sidewalks. [12:12] Um, [12:15] I think you say something about it be [12:16] preferable to have on both sides, but [12:20] I'm not sure if it's financial is the [12:22] main reason that it's just one side or [12:24] » And I apologize. I didn't I didn't go [12:25] into the sidewalks when I when I talked [12:27] about the project improvements. So, uh, [12:29] the north halfway, north half of the [12:30] project primarily has sidewalk on one or [12:32] both sides. Most of it, both sides. I [12:34] think the south block or so only has it [12:36] on one side, the east side of the [12:37] roadway. Uh we are proposing to extend [12:40] the sidewalk a six foot wide five or six [12:42] foot wide sidewalk further south all the [12:44] way to um highway 29 15th street [12:47] southeast. Um the uh sidewalk is only [12:50] proposed on one side of the roadway at [12:52] this time. Um topographically it'd be [12:55] difficult to put the sidewalk on the [12:56] west side due to steep driveways, [12:58] steeper areas, retaining walls, things [13:00] are kind of in the way. [13:01] » The west side is steeper. [13:02] » There's some steeper driveways. There's [13:04] some retaining walls too. So it it it [13:06] becomes one of those things that yes, [13:07] you can put it in there um but becomes a [13:09] much more extensive um type of [13:11] improvement when you've got some [13:12] driveways that are exceptionally steep. [13:15] So trying to put in a sidewalk [13:17] » Means we're probably taking out driveway [13:19] up to someone's garage practically in a [13:21] couple spots. So [13:21] » Yeah, I think of the east side as being [13:23] more steep. [13:23] » It's I think there's one driveway on the [13:25] east side that identified as being kind [13:27] of tough. Um but uh [13:29] » Yeah, I was referring to sidewalks, but [13:31] yeah. [13:32] » Yeah, sorry. Yeah. Well, the sidewalk [13:33] through the driveway is okay. Is what [13:35] I'd say. So, when the the steepness is [13:37] usually a bigger concern at driveways [13:38] because we're going to have a grade [13:39] break to put the sidewalk through there. [13:41] Um, and then you have to u remove [13:43] everything around it to make it work. [13:45] And that's why the north half of the [13:47] project does have so much sidewalk [13:48] replacement is because a lot of them go [13:50] through driveways and a lot of that [13:51] sidewalks directly behind the curb. Uh, [13:53] so it's preferable to have sidewalk on [13:55] both sides if we can take it all the way [13:57] to the south end. Um, I would say we do [13:59] have sidewalk allocated into the city [14:01] share. new sidewalk allocated to the [14:03] city share of the project. So, um if as [14:05] you move forward you had the um wanted [14:07] wanted to install a sidewalk on both [14:09] sides, you certainly can make that [14:10] decision. There just be of course a cost [14:12] associated with that. [14:14] » Yeah, I'm not advocating that we do [14:16] both, but I do when I think about the [14:18] geography in that area, [14:21] we do have kind of a geographic [14:23] bottleneck in that part of town. That is [14:26] our main exit for quite a ways. [14:30] I imagine when the Tokulski side on the [14:32] west side might get developed, there may [14:34] be other access to 29 coming off of [14:36] there maybe or something. [14:38] » But um and I'm not saying that we need [14:41] another pedestrian way there, but that [14:43] is the most that would be the most [14:46] widely used pedestrian [14:48] access to get out of there. But uh [14:52] unless there's really a community [14:55] the community really is wanting it or [14:57] screaming for it. I guess I would I just [15:00] wanted to ask about that I guess. [15:02] » Yeah. And we did try to include future [15:04] pedestrian improvements. So you know [15:05] hope at some point maybe there's a trail [15:07] on on 29 or something and we are trying [15:09] to account accommodate that but uh we [15:11] did accommodate for it with the 10th [15:12] Avenue improvements [15:14] » Or something to maybe happen later on [15:15] but uh at this point just accounting for [15:17] it not necessarily designing for it. the [15:20] east side where I I saw a sidewalk would [15:22] be going and the steepness there. I [15:24] think in the diagram you referenced that [15:26] the hill would be shaved down. I was [15:28] just curious [15:29] » Who was going to give us permission to [15:31] shave down the hill and is that cost in [15:33] the [15:34] » There's a cost associated with that and [15:35] we did have a conversation with the [15:36] property owner seemed able with it. Yes. [15:39] » Okay. [15:40] » So, and I should probably mention that. [15:42] So, um on the the east part of the prop [15:44] east side of 10th Avenue um north of uh [15:48] north of the county 29 that is um [15:52] private property the center line of the [15:54] road. So there is a rightway acquisition [15:55] that is needed before the turnback [15:56] agreement actually goes fully processed [15:59] because um the goal is with the turnback [16:01] um process is this is inherited as a [16:04] turnback a casad turnback onto your [16:06] state aid system. So you're able to [16:08] collect uh needs funding from it. Um if [16:11] you uh did not collect it that way or [16:13] not uh acquire that right away or the [16:16] county did not acquire that right away [16:17] um as part of the turnback process, then [16:19] you would not be able to collect needs [16:20] over the south [16:22] » Thousand feet of the road or whatever it [16:24] is. [16:24] » The uh intersection at 29 is is that [16:27] area going to be built up more? I mean [16:30] um on the east side because [16:33] roundabout or something there's it's [16:35] really low there. [16:36] » Yeah. [16:37] Nothing's proposed as far as what we're [16:39] talking about with the turnback at [16:40] least. Um I haven't had any [16:42] conversations with with uh Dave Tees [16:45] regarding any improvements at the [16:47] intersection there though. So [16:49] um not there there's nothing proposed at [16:51] the intersection um the far south end. [16:53] » Yeah. I don't know if it's you know more [16:55] than I do if that's something that [16:58] should be considered to build it up more [17:00] around the sides. But [17:02] » Will you look for volunteer flaggers if [17:04] you're interested? flaggers. [17:07] » Yeah, that that would be likely uh if [17:09] it's if that's something that was to [17:10] ever be to go through, there' probably [17:11] be extensive amount of work going in all [17:13] four legs of that intersection, make [17:15] something work. So, outside the scope of [17:17] a turnback, but certainly could be [17:19] something that uh maybe in the future. [17:22] » Yeah, I was just curious when I drive by [17:25] there, the 11th Street Circle, the U [17:28] that that just seems like it needs [17:31] attention. I don't know if that [17:32] » That's part of this project, but [17:33] » Oh, it is. Well, it's part of the [17:35] project, but not part of the turnback. [17:36] So, that's why we're not even discussing [17:38] 11th Avenue. That would be added on to [17:39] the project as that that needs a milling [17:41] overlay. That still coding failed [17:42] extremely bad. And it's um we were [17:44] waiting to get to First Avenue so we [17:46] could do 11th Street. [17:47] » Okay. Y sounds good. [17:50] » Okay. [17:52] » Any other questions? Uh so, what are the [17:53] steps we have? [17:55] » At this point, there's no action to [17:56] take. I did get a uh and I mentioned [17:58] these guys. Yep. I did get an example [18:00] memorandum of understanding from Lura [18:01] County. Um you just had one other [18:02] question through that. [18:04] » So I mean the next step would be the me [18:06] memorandum of understanding I guess [18:08] » The cost of the rightaways in the budget [18:12] » In this plan. [18:12] » It is not and I'm not sure if we talk [18:14] about that Ken or not if they're the [18:16] property owner. [18:16] » Yeah. [clears throat] [18:17] » So the property owner would be expected [18:18] to dedicate that rightway with the [18:21] development of their property [18:23] [clears throat] when we have met with I [18:24] met with the property owner a couple of [18:25] times and then most recently I think it [18:26] was Matt Chris myself uh met with the [18:29] property owner the family I should say. [18:31] And um I think they realize that whether [18:34] they develop or a future property owner [18:36] develops, it's going to be provided as [18:38] rightaway. I we have not talked cost to [18:41] acquire that because that would be a [18:42] requirement of obviously platting the [18:44] property. [18:45] » So in the map when you showed the I [18:47] thought it was the rightways with the [18:48] blue dotted line. Is that meaning [18:50] rightaways for all of property owners [18:52] all the way in section three? [18:54] It would just be the uh the only one [18:56] we're looking at needing right away from [18:58] is going to be the south two properties [19:00] on the east side. The farm field and [19:01] then the the um house at the corner. [19:05] » I misunderstood then. What's the dotted [19:07] sidewalk [19:09] » Sidewalk? [19:10] » Oh, okay. [19:11] » Yeah. [19:12] » Acquisition needed on parcels. [19:15] » Yeah. So, we'd be looking at I believe [19:16] 40T I think [snorts] is what we [19:18] identified from center line of the [19:19] roadway um onto the east side of the [19:21] road. [laughter] So we did stake that [19:24] last year just where we thought [snorts] [19:25] it would be for the property owner to [19:27] » That acquisition label for those that [19:30] those two pages just goes to the farm [19:32] field through there and so they're just [19:34] signifying that we would need to have [19:35] that rightway dedicated along that last [19:39] section on the south part of it. [19:40] » Okay. Yeah, it wasn't delineated what it [19:43] was referring to I guess in the map. [19:46] [snorts] [19:47] » Thank you. [19:48] » Any other questions? [19:51] Then I guess the ne letter C the MS4 [19:56] proposal that uh is in front of us. [19:59] » Yes. So the next item I have in front of [20:01] you is uh in relation to the uh MS4 um [20:05] permit that the city is um now going to [20:08] be u required to complete. So you're [20:10] notified a couple years back um that uh [20:14] the city of New Prague would become an [20:16] MS4 community. Um, this is in relation [20:19] to [20:20] MS4 communities typically are of a [20:22] certain population. I believe it's [20:23] 10,000 or larger. Um, or you're within [20:26] uh a distance of an impaired water of [20:29] significance. Um, and in this case, Sand [20:33] Creek is is that waterway. Um and [20:36] because um that [clears throat] uh uh is [20:38] an impaired water um the city of New [20:40] Prague has been notified that you will [20:42] need to start uh um start preparation of [20:47] MS4 documentation. So uh this is a uh [20:51] technically you're into it now. Started [20:53] January 1, 2026. There's no [20:55] documentation needed the first year. So [20:57] you get a lot of little bit of leeway to [20:59] kind of start getting your bearings and [21:00] figure out what you need to do. um what [21:02] we have done is provided you a proposal [21:04] uh to um assist you with um assist you [21:09] with that documentation. So um on the [21:12] first [snorts] level we have a phase one [21:14] uh approach which is a um largely a [21:16] document uh information seeking type of [21:19] a proposal. So um a lot of the items [21:22] that you need to include with your MS4 [21:24] um permit um are things that you're [21:26] likely already doing. Um there's [21:28] probably a lot of things you still you [21:29] need to start doing. Um and we largely [21:33] don't know what that is yet. So this is [21:34] kind of an information gathering process [21:37] um meeting with city staff uh [snorts] [21:38] meeting with uh um uh council and and uh [21:43] going through some sort of a public [21:44] involvement uh stage here at the [21:46] beginning. So um the the the biggest [21:48] things right now uh we've identified for [21:51] for this information is what we kind of [21:53] identified in this um schedule at the [21:55] bottom here and we're we're some of [21:57] these will get pushed back. We're we're [21:58] reviewing it here today instead of [22:00] August 17th. But u we do have a a [22:02] questionnaire which is a documentation [22:04] we send out basically saying what are [22:06] you doing now so we can kind of start [22:08] adding that information. Um and then we [22:10] do have um a couple workshops and then [22:12] uh summary report and checklist. So [22:15] that's putting together uh basically [22:18] uh what are you doing, what do you need [22:20] to do and um this would all be used in [22:23] preparation of um like we have phase two [22:25] which is implementation um and that's [22:29] starting to to uh complete the the items [22:31] that you need to do for your for your uh [22:34] MS4 permit which I believe would be um [22:37] ultimately submitted in in May which is [22:40] I think it's May every year. So this is [22:42] kind of one of those things that um [22:45] it's going to be kind of a learning [22:47] process [22:48] um for not FCS has done many of these [22:51] but just learning what you are doing um [22:53] at the beginning here and uh kind of um [22:57] working with the city as far as um what [23:01] you need to do, what do you want to do, [23:02] what do you want us to do. And then [23:04] that's kind of what goes into the second [23:06] phase is u we do have the ability to [23:08] complete a lot of this documentation for [23:09] you but there's probably not much reason [23:10] for us to [snorts] to do that um at [23:14] least not uh you know forever because [23:16] this is something you'll be doing on a [23:18] annual basis. It doesn't mean you'll be [23:20] doing this proposal on annual basis but [23:22] once you start doing the the submitts [23:24] and documentation that you need to [23:25] prepare that is something you have to do [23:27] every year. Um there will be a um every [23:30] five years you should expect to be [23:32] audited from that information. Um so [23:34] there are certainly um certainly some [23:38] reasons to getting sure you get it I [23:39] guess the way you need to do it. So [23:41] you're probably doing a lot of the work [23:42] you need to [snorts] do pond inspections [23:43] and things like that um that get [23:45] implemented into it. Um you're going to [23:47] have a lot more stuff you need to do. [23:49] you're going to identify someone that's [23:51] doing um SWIP inspections, looking at [23:53] private developments, doing all sorts of [23:55] stuff you aren't necessarily doing now, [23:57] but uh so you will have some extra work [23:59] added to your [snorts] um to your staff, [24:02] but uh um that's basically what we need [24:05] to find out. What do you need to do [24:06] here? [24:08] » Okay. [24:09] » So, the proposal we have in front of you [24:11] here today is an hourly not to exceed uh [24:13] fee of $29,900. [24:16] Um this would be led by uh Jeremy [24:18] Walgrave who's in our water resources uh [24:20] group. Um Jeremy's met with uh city [24:23] staff here through a couple meetings now [24:25] already. I think maybe a year two years [24:26] ago I think we had the first time and [24:28] then um early this summer as well. So um [24:31] he's prepared these [snorts] [24:33] um he's assisted several cities with [24:35] preparation these documents and has has [24:38] a good background for that. [24:40] So, is this December 15th [24:43] date a firm date, which means I know [24:47] we're we're missing some of the earlier [24:48] dates, but [24:49] » Yeah. So, the [24:50] » Something that we can still achieve. [24:52] » Uh the December 15th date, I would [24:54] expect we'd still be able to to stick [24:56] with that. Um or [clears throat] [24:58] certainly before Christmas. There's [24:59] nothing in here that says you have to [25:00] get it done by 4, December 15th. This is [25:02] just trying to get us prepared so that [25:04] um we know what we need to do so we can [25:06] start working on that next step in [25:07] January is the general idea so that uh [25:10] then everything do need to get ready for [25:12] that first uh permit submittal um first [25:16] documentation is ready for that I think [25:17] it's I believe it's May has to be [25:19] submitted. So it's just uh yeah I think [25:22] a lot of stuff will probably be shifted [25:23] back a little bit but I don't see that [25:24] December 15th date changing a whole lot. [25:26] Maybe I would probably just say before [25:28] Christmas on that one. Okay. [25:31] » Besides uh inspections, do you uh [25:34] foresee us in the future needing to [25:36] either adjust zoning or ordinances or [25:39] how we uh allow developments to occur or [25:42] our permit process? [25:43] » Yeah, there will some of the items put [25:45] in there is are going to include [25:47] ordinance um updates and that's going to [25:49] be some of the things that whether it's [25:51] Ken and his staff work on it or [25:52] something that a CH helps out with. [25:54] there's some template um items that we [25:57] can provide and you just kind of orient [25:58] it towards how you want to work with it. [26:00] We can write them all directly and do [26:01] all that kind of stuff. So again goes [26:03] into our determination of what you need [26:04] to do. But yes, you will need to change [26:07] change things um that that are in your [26:10] um in your city code. [26:12] » Someone building a commercial building, [26:14] will they notice notice a difference [26:16] from yesterday to next year? [26:20] I'd say most uh most developers that are [26:22] coming in at this point, we're making [26:24] them aware of the changes and I think [26:26] the the items that we're referring to [26:27] right now are going to still follow [26:29] those guidelines that MS4 will have the [26:31] the storm water requirements. Um so we [26:34] are trying to get them oriented towards [26:35] that even though it's not officially [26:37] ordinance, [clears throat] but once you [26:38] have the permit, I mean you're you're [26:41] going to be you're going to be the [26:42] permit holder and people in your in your [26:44] city are going to have to be following [26:46] it as well. [26:49] Okay. [26:50] » One thing I want to point out, Chuck, um [26:52] or mayor, sorry. Been talking to you too [26:54] much lately outside of the council [26:55] meetings. Um [clears throat] so the cost [26:58] for this um study is 29,900 like you [27:01] said. So I pro I budgeted 15,000 for [27:04] this in the 2026 budget. We've had a [27:07] good uh budget this year for the storm. [27:09] Um I anticipate we'll have the [27:12] additional 15,000 to cover that [27:14] difference, but if we do not, we would [27:15] have to take out of the fund balance. Um [27:18] and we are sitting uh very well in the [27:21] storm budget so that would not be an [27:22] issue but this is a necessary step. It's [27:25] one audit and they miss we miss one [27:26] thing in our um paperwork and that fine [27:30] would exceed this. So this is a [27:31] necessary step but uh on top of that [27:33] we've talked about this for so many [27:34] years now that the city will become an [27:36] MS4 city. It's coming up. We've been [27:38] preparing for it. Um, we doing a lot. I [27:40] know we're doing 75% of the things that [27:42] we should be doing already to be an MS4 [27:43] city, but there are that 25% of stuff [27:46] that we could be missing that we need an [27:48] expert that's done this with other [27:50] cities to understand exactly what we're [27:51] missing. [27:53] » What triggers that, Matt, becoming an [27:56] MS4 city? [27:57] » Well, this one doesn't You would think [27:59] New Prairie hasn't changed much in five [28:00] years. How could this um how did we fall [28:04] into this lap now? Well, I know a lot of [28:06] the bordering cities, New Market, Bell [28:07] Plane, I think just recently landed in [28:09] at the same time we did. I think it's [28:11] because what who we dump into. Is that [28:13] correct? [28:14] » Yeah. So, if you're over 10,000 [28:16] population or if you are part of a [28:18] regional water significance or impaired [28:20] water, I should say. So, Sand Creek [28:22] wershed is is the reasoning for it. So, [28:23] once that got designated as an impaired [28:25] water um and I want to say it was within [28:28] I can't remember the the range of miles. [28:30] I think it might be within five miles. I [28:31] can't recall exactly, but um but because [28:34] of the proximity to Sand Creek um that's [28:37] why you got put on to it. So um yeah, [28:41] even though you're less than 10,000 [28:42] population, so a lot of the other that's [28:44] why the metro communities are included [28:45] in there, but uh you were not. [28:50] » Okay, any other questions? [28:53] If not, I guess I'll look for a motion [28:55] to approve this uh proposal, the MS4 [28:58] proposal. [28:59] » So move [29:01] And I will second. I got a motion by [29:03] Rick S, second by Chuck Nikolai. [29:06] There's no other questions. All in favor [29:08] say I. [29:09] » I. [29:09] » I. Any opposition? Okay. Passes 5-0. [29:12] Thanks, Chris. [29:12] » See you in two weeks. [29:14] » Okay, [29:17] next we have John, right? [29:20] » Yes. [29:20] » From Wald. [29:23] » Unless it's easier for me to do it. I [29:24] can either way. [29:26] » Either way. Plug in there. [29:32] » [snorts] [29:43] [snorts] [29:50] » There we go. [29:53] » Evening, [clears throat] mayor and [29:54] council. It's good to be back on a [29:56] different project this time. And this [29:58] one is is is the relocation of city hall [30:02] over to the uh building that uh the city [30:05] just recently purchased. Um we've met a [30:08] couple of times with city staff to kind [30:10] of go over some ideas on what we can do, [30:13] what we can defer in the building and um [30:16] are looking for some feedback tonight on [30:19] a couple of different ideas that um are [30:21] important as we look at this building. [30:23] not only from a building usage but also [30:26] from the side of public access. Um so [30:29] those of you that are looking at this, [30:31] we do have a public parking area on the [30:34] south side. It's noted on the drawings [30:36] here as there's 11 stalls there. Uh [30:38] there is a sizable parking lot behind [30:40] the building with 41 stalls in there. [30:43] And so while there isn't a lot of [30:45] traffic to city hall, there are [30:46] sometimes meetings in the council [30:48] chambers and whatnot that will involve [30:51] the potential of using uh the back lot [30:53] for public parking. So we wanted to make [30:55] sure to present some options that would [30:57] not only help with access to those [31:00] public spaces, but also uh enhance [31:03] security in the building as well, so [31:04] that we don't have people kind of [31:06] walking up back ways like what we do in [31:08] this building here. Um, so this is just [31:10] to illustrate that there are a number of [31:12] entries on the building that we'll need [31:14] some level of control over. And so we've [31:16] had a number of conversations related to [31:18] how we want to do that. And we'll kind [31:20] of talk through that uh as we go through [31:23] the presentation. [31:25] So for option number one is kind of a [31:28] more traditional um look at how we might [31:30] organize the building. Kind of the main [31:32] vestibule on kind of the southeast side [31:35] there at the angle. Um there's a very [31:37] large open rotunda in there, that [31:40] octagonal space uh that sets up nicely [31:43] for some sort of a service counter in [31:45] that area. And so what we would envision [31:47] is capturing probably about half of that [31:49] area uh for city staff to have a [31:53] singular uh service counter in that [31:55] building. So kind of combining those [31:57] into one location so that uh the public [31:59] coming in has kind of a one-stop shop [32:01] for city services. Um, a couple of [32:04] things to note in that lobby is there is [32:06] no security in that lobby from uh what [32:09] we're noting in this option as the [32:10] council chamber. So, we would add some [32:12] [snorts] [32:12] some doors in that area to allow uh for [32:16] the public to kind of be in that public [32:18] area and the staff spaces and the [32:21] council chambers uh would be secure and [32:24] only opened based on uh usage. Uh this [32:28] option here would add two handicap [32:30] accessible toilets. We have done a [32:32] preliminary occupancy count of the [32:35] council chambers and based on the usage [32:37] of that and the square footage of that [32:39] space it kind of dictates how many [32:40] restrooms we would need in that public [32:42] area and two are the number. So we are [32:45] proposing two uh unisex bathrooms in [32:48] that area non-gendered toilets. Uh we do [32:51] have um a service counter that we're [32:55] proposing to have um impact resistant [32:58] glass, not ballistic glass, but impact [33:00] resistant glass, kind of similar uh but [33:02] more uh designed into that space. Uh a [33:05] little public uh terminal in there. Um [33:07] and then a kind of a sub lobby area [33:09] leading into the council chambers. Uh [33:11] this option here envisions uh doing some [33:14] renovation in that corner by the council [33:16] chambers to not only add a toilet but to [33:18] add a a conference room in that area. So [33:21] not unlike the conference room that's [33:23] downstairs in this building. Something [33:24] that's in the more public area so that [33:27] uh we don't have uh to escort people [33:29] into the back area. We are showing a [33:32] council chambers as oriented to the [33:34] south. So the council would sit on the [33:36] south side against that southern part of [33:38] that octagon octagonal area there. We [33:41] are suggesting that that existing side [33:43] door would be a safe and secure way for [33:47] uh city staff and council to exit that [33:49] space should there be some emergency [33:51] that's necessary that so that we don't [33:53] have to go back through the public area. [33:55] Um and then from our conversations with [33:57] staff, we have added a um side area uh [34:00] to connect our uh staff positions to the [34:04] council uh DAS in there. The council [34:07] disated similar to what you have in [34:09] here. We are budgeting to add uh [34:12] ballistic protection to the council dis [34:15] uh safety reasons. It's a traditionally [34:18] the way that we do uh council chambers [34:20] uh today. And we do have a desk in there [34:24] for uh the media location um similar to [34:27] what you have here. Um during our [34:30] conversations, [snorts] it was noted [34:31] that we would likely relocate all of the [34:34] council equipment that's in here to the [34:36] new building. And so that would be [34:37] something that would need to be [34:38] coordinated uh during construction as to [34:41] how that IT stuff gets moved over there. [34:44] Uh the remainder the remaining part of [34:45] the building would pretty much stay as [34:47] is today. Maybe a little painting and [34:49] touchup here and there, but as if you've [34:52] toured through the building, it's in [34:53] good shape. So, we don't expect there to [34:55] be a lot of changes that are necessary, [34:57] but we would be adding a card access [34:59] system to the building. And through our [35:01] conversations with code official, we [35:03] would need to provide uh handicap [35:05] actuators to uh any location where we [35:08] would have the public coming and going [35:10] from the building. Um, in this option [35:13] here, we're leaving the existing [35:14] training room on the east side, uh, as [35:17] is. Um, and adding a door near where [35:21] those bathrooms are. So, as it's being [35:23] used as a polling location with two [35:25] separate polling areas in there, uh, [35:27] having access to public bathrooms would [35:29] be important. So, adding another point [35:32] of security in that area would allow the [35:34] public to use those restrooms um, if [35:37] there is a need for that. [35:40] When we go to option two, uh we had some [35:43] conversations related to um usage of the [35:48] east training room versus the um [35:51] octagonal space. And we had some [35:53] conversations related to the the parking [35:56] lot on the north side, having more [35:58] parking available there. Would it be uh [36:01] possible to put the council chambers in [36:04] that training room and have it [36:05] completely separated from the rest of [36:07] the building? uh we would still provide [36:09] access to those public restrooms. That [36:11] would solve uh the need to provide two [36:14] bathrooms off the main lobby. Uh in this [36:16] version, we would only need one unisex [36:18] bathroom off of the main lobby. It would [36:21] retain the octagonal space as a training [36:23] room in future growth for the city. Uh [36:26] and the rest of it would remain the [36:28] same. It's just a different way of [36:30] looking at it. And that's one of the key [36:32] components that we would like to um get [36:35] feedback from the council uh tonight. So [36:38] I'll pause there before we go through [36:40] the um the current estimate for the [36:44] project and u look for any questions [36:46] from the council we would like to get [36:49] some consensus on which option that we [36:51] want to go with so that we can advance [36:53] the drawings to the next stage. Is the [36:56] yellow meaning construction or does [36:59] yellow mean something in particular? [37:01] » It's where we're doing the most [37:02] renovation. Yes. [37:03] » Okay. [37:05] And I guess more question for Josh. I I [37:07] was just surprised when I looked at this [37:08] that there aren't that many offices. Are [37:11] we still having [37:14] do we have enough [37:16] space for the individual staff members? [37:19] » Yes. So, if you were to count current [37:21] city hall staff members today, we have [37:22] about 12 people that work out of city [37:24] hall full-time. So, when you look at the [37:27] various spaces, there's the what amounts [37:30] to four kind of office environments. If [37:33] you make that one a council uh a [37:35] conference room, you the one, two, three [37:38] kind of as they go around the curve. [37:39] There's a larger space that could work [37:41] as an office. Um, right now we're kind [37:44] of viewing it more as like a supply [37:45] closet, copers, all the noisy stuff that [37:49] we deal with, a kind of a work room with [37:50] maybe a desk in there. [37:52] » Then there's another a fourth office [37:54] kind of across that little hallway there [37:56] then. [37:56] » And then you end up having um [38:00] kind of going south there, you've got a [38:03] large enough space that you can put four [38:04] or five kind of workstations in there. [38:07] And then in that front lobby area, the [38:09] staff that would are the most direct [38:11] with the public all of the time, there's [38:13] enough space for three or four [38:14] workstations kind of right up front [38:16] there um for those people that deal with [38:18] the counter on a consistent basis. So [38:20] you end up dealing with I guess roughly [38:23] that gives you [38:25] uh off top my head [38:26] » 13 14 [38:29] » 13 spaces without really having to jam [38:31] people into spaces that don't make [38:33] sense. Um, like I said, then as you get [38:35] into it, I mean that that works that [38:37] work office space is large enough you [38:40] could fit desks in there in the future [38:41] if [clears throat] you have to. [38:42] » And then ultimately, as we kind of [38:44] talked through this whole process, um, [38:46] depending on which way you went, you [38:47] would have a space on one side that [38:50] would be able to be expanded into in the [38:53] future if you saw a staff staff [38:55] expansion, if that became something that [38:57] um, was a big need of the city at the [38:59] time. So when you walk in, are you [39:02] envision or am I to envision that [39:05] there's a person standing on that part [39:08] that's diagrammed as a wall [39:10] » Is as a service counter that would be [39:12] actually like a a built-in desk service [39:15] counter. [39:16] » But I Yeah. And I don't know at least we [39:18] talk it doesn't sound like there's [39:20] somebody working directly at the [39:21] counter. [39:22] » Yeah. To clarify we based on our [39:24] conversations we want the most [39:25] flexibility there. So staff would be [39:27] sitting at their workstation and then [39:28] whoever would walk up to the counter, [39:30] whether it's somebody to see the [39:32] building official, planning and zoning [39:34] question, a finance question, uh the [39:36] staff would come up to the counter to [39:38] service them. So it'd be more of a [39:39] standup work area uh on both sides. [39:42] » So it wouldn't be someone sitting there [39:44] then? [39:45] » No, not permanently. No. [39:46] » Okay. So otherwise the spacing didn't [39:48] seem to see seem right if you have four [39:51] three or four people behind a person [39:54] sitting at the front here. So those [39:56] those beige dashed things are intended [39:58] to be workstations for staff. [40:01] » Okay. [40:03] » So in my [clears throat] packet I see [40:06] the [40:08] um proposed budget for option one [40:12] » But not for option two and [40:14] [clears throat] the pages are [40:15] sequential. [40:16] » Correct. [40:17] » Um what would be the proposed budget for [40:21] option two? uh the because there is more [40:24] construction that's needed for option [40:26] two with adding a vestibule and um into [40:30] the council chambers and some of the [40:32] additional work that would be needed in [40:33] there. Uh our opinion is is that the [40:35] cost estimate is negligible between the [40:37] two of them. So council can make the [40:39] decision based on operationally what [40:40] works the best. [40:42] » I'm surprised by that because you're [40:44] eliminating a bathroom and that the [40:46] savings there is going to be eaten up by [40:48] the [40:50] » The training room. it's within, you [40:53] know, it's within5 to$10,000 between the [40:56] two of them. And we can certainly run a [40:57] detailed estimate on option two. Uh [41:00] tonight was to give you kind of an idea [41:01] where we're landing from, you know, kind [41:03] of the traditional putting the council [41:05] chambers in the octagonal space. Um and [41:08] once we kind of get that decision, we [41:11] can u finalize the details of what it's [41:13] going to take to do it and update it uh [41:16] at our next council update. [41:19] I guess in my opinion having the council [41:22] chambers in the octagonal [41:24] area makes more sense to me to keep that [41:30] training room open for expansion of [41:33] employees and perhaps more cubicles [41:36] um if needed in the future. [41:42] » I would agree with you Maggie. [41:45] [clears throat] That's a very large room [41:47] and it could have multiple uses. [41:49] » Correct. Yeah, it's a nice bit of [41:51] flexible space to have available. [41:52] » Yeah, [41:53] » I'm good with option one. [41:55] » Yeah, I also agree with Maggie's [41:57] statement, too. I think the the look [42:00] that that council chambers on option one [42:04] I think gives it [42:06] a unique look and I think that's [42:11] » We have access to the parking lot from [42:15] that public exit then [42:17] » Yeah if you look if you go back to the [42:19] site plan um there is a sidewalk that [42:22] leads to that side door so either coming [42:25] our thought was for council meeting [42:28] night, we would have the lobby, the main [42:30] lobby area be open, but also have the [42:32] ability to utilize the back parking [42:33] area. [42:35] » I Yeah, I mean, for all of this, I would [42:37] assume staff will always be parking up [42:39] in the north lot, kind of like we do [42:40] here now. Um, and then even if with you [42:44] guys with key cards to get in, whether [42:46] that's locked or not, you guys would [42:47] have access. So, if you wanted to park [42:49] them behind, too, you just have access [42:51] to that back door, leaving that front [42:53] lot open for any visitors. Is is there [42:56] one uh option that you feel provides [42:58] more value to the taxpayer than the [43:01] other? [43:02] » Initially [43:04] um there was some intrigue about the [43:06] training room because of its you know [43:08] location and that type of stuff but I [43:10] think from looking at kind of a more [43:12] traditional formal council venue. The [43:15] octagonal room kind of fits better for [43:17] that because as you can see you're [43:18] sitting at a desk with angles in it [43:20] already and so that room tends to to [43:23] lend itself to that. The only caveat is [43:26] it's got a lot of windows in it and so [43:28] um we just have to be able to control [43:30] daylighting and some of that type of [43:32] stuff in there. So, um if you want my [43:36] opinion on this, I think option one also [43:38] probably provides the best flexibility [43:40] in the future, but we wanted to at least [43:42] explore a couple of different ideas for [43:43] you. [43:45] » Yeah, I like option one. And um the [43:47] thing I don't like about it [43:49] » Is you're cornered in there. So there's [43:51] no escape [43:53] » Or [43:53] » If there was uh something going on with [43:55] the residents [43:56] » In option one. [43:57] » Yeah. [43:58] » Well, so there there is that staff exit. [44:00] And that's kind of why I know we talked [44:02] of where they're positioned and but how [44:05] you could potentially build that in a [44:07] way that that provides an exit if [44:09] needed. [44:10] » Yeah. That staff is there is that a [44:13] closet in in between [44:16] If you look to where the council would [44:17] be sitting, [44:19] » The the dark line, is that [snorts] just [44:20] like a half wall or? [44:22] » Yep, that's just a half wall. That's it [44:24] would be kind of like this ramp here, [44:25] but maybe with a more formal wall to [44:28] kind of blend it in. [44:32] » Uh, are most new buildings uh putting in [44:36] ballistic protection? Yes. [44:38] » Is that a pretty standard thing now? I [44:41] have since uh I don't know probably a [44:44] third of way my through my career uh [44:46] we've been putting ballistic material in [44:49] uh council desks to be able to give you [44:51] the ability to protect in place if [44:53] necessary [44:54] » And it's only in the desk then that this [44:56] would be in [44:57] » Y [44:57] » Nothing. [44:58] » We are proposing to put film on the [45:01] exterior windows to provide some level [45:03] of impact resistance to those existing [45:06] windows in there just because we have [45:08] such a large quantity of windows. Uh [45:10] certainly that's a budgetary decision [45:12] you can make, but it seemed prudent [45:14] based on how much glass is in there for [45:16] us to have some amount of impact [45:18] resistance to um council changes [45:21] » And that just and just for their sake [45:23] kind of talk there's different ways you [45:25] go about that. you could physically [45:27] replace the glass, [45:29] » Which was the much higher cost option. [45:31] And then similar to I'm assuming like [45:33] when you put the window tint on your [45:35] window, there's a film you can put over [45:37] it that just [45:38] » I guess probably like putting a [45:39] protector on your screen on your phone, [45:41] just provides a little bit more [45:42] resistance than what the glass provides. [45:44] » There's a lot of products that came [45:46] about with a lot of the school work that [45:48] we do that have transitioned into a lot [45:50] of our government projects as well, just [45:53] all the research that's been done out [45:55] there. So what we're trying to do is [45:56] just slow people down. [45:58] » Chief Applin, were you consulted in any [46:01] of this? [46:04] » Just at a high level, but I haven't been [46:05] a part of the conversations. [46:07] » No. [46:08] » Thank you. [46:13] » Is staff get ballistic material, too? [46:15] » Yes. [46:15] » Okay. [46:16] » Mhm. [46:19] » What are you saying? [46:20] » Just smile [laughter] at me. [46:21] » Just ask. [46:23] because I care about you. [46:25] [clears throat] Thank you. [46:26] » You'll be expected to wear a target on [46:29] yourself. [46:30] » So I I think Bruce, are you in thinking [46:32] option one is a better option? I I think [46:36] » The parking was the only concern I had [46:38] on that. But I think if you have access [46:40] to the back way, [46:41] » Yeah, [46:41] » That that's me. I [46:44] » So I assume that consensus is option [46:46] one. [46:47] » Yes, for me. Yes. [46:48] » Yes. [46:50] for me. But [46:51] » Yep, we will uh continue to build some [46:54] details around that. We would enjoy to [46:56] review with the council at a future date [46:58] the design of the dis and what that kind [47:00] of public facing piece would look like. [47:03] Um we should look at the budget a little [47:05] bit. Uh we did a little bit more [47:06] detailed budget uh on this based on um [47:09] our being on site and some of the design [47:12] work that we've done. Uh and right now [47:14] including a roughly about a $23,000 [47:18] estimated contingency, we're at roughly [47:20] about $480,000 in construction. Now, [47:23] this assumes that a general contractor [47:26] is doing all of the work. There has been [47:27] some conversation about using city [47:29] resources to do that. We have not taken [47:31] that into consideration at this point in [47:33] time because literally we're just at the [47:35] point of finalizing the design and we [47:37] would just need to make sure that that [47:38] doesn't have overburden uh your other [47:41] staff people. But our intent would be to [47:43] come back with a recommendation on uh [47:46] how we would split that work scope out. [47:48] A couple of other things to note in here [47:50] that still need some uh additional work, [47:54] which is the technology uh budget. We've [47:56] established roughly about 115,000 as a [47:59] set aside budget for technology just [48:01] based on conversations. Um obviously we [48:04] would like to reuse uh what we have at [48:06] city hall right now. Um and so that may [48:09] have some impact on that as well as uh [48:12] this does include uh an updated card [48:15] access system for the building. So this [48:17] includes modification of doors to [48:19] provide for card readers and all of that [48:22] stuff is included uh in the budget. Uh [48:24] there's some miscellaneous site stuff [48:26] that will likely be done by the city for [48:28] parking lot lights and the sign out [48:30] there and then an overall u project [48:33] contingency for unknown. So, at at the [48:36] schematic design level that we're at, [48:38] it's it's critical to have some uh [48:41] contingencies in there. And as we go [48:43] through the next phase of construction [48:45] documents, we'll be working on uh kind [48:48] of the final engineering, figuring out [48:50] what things we uh can save on and then [48:54] bringing back a final recommendation to [48:55] council at a future meeting. One thing I [48:58] would like to note guys is when you look [48:59] at that technology budget um one of the [49:01] things that we are having to adapt [49:04] around is I guess you could currently [49:06] call city hall the brains of our city [49:08] operations. We have connected all of our [49:09] buildings with fiber and a lot of the [49:12] brains of the city are located here. So [49:14] we have to move those brains somewhere. [49:16] Um and this building uh fiber is about a [49:19] block and a half away. And so, um, part [49:22] of that technology budget is just [49:24] acquiring fiber and then working through [49:26] our own utility that can do the work to [49:27] run that fiber, um, over to the new city [49:31] hall location. So that way we have the [49:33] new building connected to the rest of [49:34] the hub. But also then working with, um, [49:37] Bruce and staff and just trying to [49:39] figure out the is would this location be [49:41] the best place for a new brains or [49:43] center of the city or are we better off [49:45] putting it in like the power plant or [49:47] that sort of thing. um hopefully trying [49:50] to eliminate maybe a need if in 30 40 [49:52] years to have to move it again, but [49:54] that' just be conversations we have [49:56] internally. [49:59] » Well, Josh, when we walked through it [50:01] was going to be a couple of bathrooms [50:02] and we thought 200,000 and then it was [50:04] then we gave you a check for 650 and now [50:07] it's 760 and we're not even done yet. [50:09] » You didn't give me a check for anything. [50:10] Well, but we in our budget meeting you [50:12] asked for 650 [50:13] » And that was where we I I guess we [50:15] working with Matt, him and I kind of [50:17] walked the building and we made a very [50:18] general guess as to what we thought it [50:20] would be. And so um [50:23] » Yeah and like I said that that was with [50:26] staff doing some work and as as John [50:28] mentioned this is uh all contractor work [50:32] at this point, contingencies built in, [50:34] that sort of thing. So, as we get [50:36] through this process, my hope is that [50:37] this will get narrowed down a little bit [50:39] um to a more realistic number. So, [50:43] » I guess I was asking for clarification [50:45] on that, too, because the number seems [50:47] more than what we talked about. And when [50:50] we talked about a $400,000 construction [50:53] budget, I'm not sure maybe we the when [50:56] we use that word, it might mean [50:57] something different for different [50:59] people. So, I'm not sure if that was [51:00] meant to mean the construction budget or [51:03] the direct construction scope, but in my [51:06] mind, 400,000 meant the whole [51:08] construction part of it. [51:10] » So, I'm not sure. Are we thinking of [51:13] trying to get that back down to what we [51:15] thought around that 600,000 number or [51:17] » I I mean that that's our hope obviously [51:19] and I think working through some of this [51:20] a lot of it even comes down to what what [51:22] do we need to do now? What can we do [51:23] later? Um some of it comes down to um so [51:27] uh and we're certainly aware this is [51:29] higher than what was anticipated. Uh but [51:32] this this is the scope that we've talked [51:34] about. Our intent is to continue talking [51:36] about it and figuring out if there are [51:37] some ways to to save. We haven't even [51:40] had our mechanical engineers out to the [51:42] building yet to try to figure out what [51:44] we can reuse, what needs to be modified. [51:46] So we have placeholders in the budget [51:47] for what we would expect for restrooms [51:49] and that type of stuff and ventilation [51:51] systems. And so as we go through the [51:53] next stage of design, we're going to do [51:55] that field verification and make sure [51:56] that we are looking to reuse what we can [51:59] in the building. [52:02] » Okay. So obviously you understand which [52:06] direction the council would like to go. [52:08] Uh what's the timeline then of the next [52:11] step, Russ? [52:12] » So we're early September. I think uh we [52:15] had proposed to be pretty well done with [52:17] the schematic design here in September. [52:19] So, we're on track right now for where [52:21] we would hope to be. I think we had [52:22] allowed a couple of months to do final [52:24] design documents. And so, I'll work with [52:27] Josh and staff to kind of finalize the [52:29] details on that. And we'll look to come [52:31] back to council probably some midpoint [52:33] in the next phase of design. So, [52:35] probably sometime in October [52:37] » To uh review kind of the final design of [52:40] the council chambers and we'll have an [52:42] updated estimate at that time. and we [52:44] expect to be done with the bidding [52:46] documents probably in that November time [52:48] frame sometime. So, we're still on track [52:49] to what we had expected at this point in [52:51] time. [52:52] » Okay. Any other questions? [52:56] » All right. Well, looks good. Thank you [52:58] very much. [52:59] » Well, thank you. [53:00] » Thank you. [53:05] » Next on the agenda is [53:07] ordinance for introduction. Is this a [53:09] first reading uh Ken of ordinance number [53:11] 367? This would be the first reading. [53:14] So, I give you a little background. Um, [53:16] council will recall we did do some um [53:19] minor amendments to the unified [53:21] development code on July 6th that were [53:24] adopted. Um, those are some quick [53:26] changes we needed to make. Some [53:29] kind of more we'll say more important [53:31] and more critical amendments from when [53:33] we adopted that back in March that [53:36] [clears throat] [53:37] immediately. uh this next set of [53:40] amendments and we hope we've got uh most [53:42] of them subject to u one final item [53:46] we're bringing back to the planning [53:47] commission in September regarding solar [53:50] power but um planning commission did [53:52] review uh these changes in July and held [53:55] a public hearing at our August 26 [53:58] meeting. We did not have any um public [54:01] comment received at that meeting on [54:02] August 26, but just wanted to go over uh [54:05] in general terms the uh changes that are [54:09] proposed. So number one um in the [54:12] unified development code wanted to [54:14] specifically call out that shipping [54:16] containers and storage containers are [54:18] not allowed as structures or permanent [54:21] buildings. Uh there's a set of concerns [54:23] and then also concerns meeting building [54:26] code. That was something that um just by [54:29] [clears throat] the fact that it wasn't [54:30] listed specifically as being uh allowed [54:33] that they were prohibited but we want to [54:35] make that clearer because we did have [54:38] some inquiries about that. Um so the [54:41] language he put together surveyed number [54:43] of the cities in the area what they were [54:45] using for that clarifying language that [54:47] is included in that [clears throat] [54:49] uh clarifying again language regarding [54:52] uh the city requirement building permits [54:54] for all solar systems and explicitly not [54:56] allowing ground mounted solar um again [55:00] the city code or the uh UDC does not [55:03] specifically allow these at this point [55:06] but we're just clarifying the language [55:08] that one you need a permit if put solar [55:10] panels on the road. And then number two, [55:13] uh, specifically listing that ground [55:16] mounted solar are not allowed that [55:18] inquiries. Well, ordinance doesn't say [55:20] they're not allowed. It's like, well, by [55:24] state statute, if you don't allow it, it [55:27] is prohibited. So, we're just clarify. [55:30] Uh, third one regarding parking vehicles [55:33] in uh front yard or even back or [55:36] sideyard or residential properties. Uh, [55:39] put that language in there. So, you [55:40] can't just park on the grass. We had uh [55:43] again some questions of people saying, [55:45] "Well, I don't have a passenger vehicle. [55:48] I have a commercial vehicle." So, we're [55:51] uh suggesting making the change saying [55:53] that any vehicle parked in the grass in [55:55] your front yard, side yard, rear yard is [55:57] not allowed unless it's on a paved area. [56:00] So, that's another change. [56:04] Um we do allow them in certain cases to [56:06] be on gravel I should note but this is [56:09] saying yeah improved but um this is [56:12] being changed so that you can't make the [56:14] argument that it's some commercial [56:16] vehicle that um you get an exception for [56:20] just know we're clarifying that you [56:22] can't park. [56:24] Uh fourth one uh regarding that uh [56:28] commercial industrial building that are [56:30] accessory. Um previously to the UDC [56:33] being adopted we didn't require any [56:36] design requirement requirements for [56:38] them. PL commission had quite a bit of [56:40] discussion about this uh following the [56:42] public hearing uh at the meeting in [56:45] August and there's kind of a list of [56:47] different things that they have to meet [56:49] from uh using varying colors, varying [56:51] roof lines, windows, [56:54] accents to the the garage door. Um and [56:58] the way the code was written, they had [57:00] to pick two of these criteria which [57:01] applied to principal buildings. We've [57:04] never intended that to apply to [57:06] accessory buildings. So planning [57:07] commission determined that they should [57:09] pick at least one of these aesthetic [57:11] requirements um that are kind of a menu [57:14] of options that they can pick. So that [57:17] was what the planning commission [57:19] one of the design elements that have to [57:21] be incorporated into your commercial or [57:23] industrial accessory buildings like a [57:25] shed or a garage. [57:28] Uh fifth one regarding decks. This is [57:31] another kind of clarifying item. U we've [57:34] had more and more people wanting to put [57:35] decks around uh pools that are in their [57:38] backyards. And the way we had UDC [57:40] written and even going back before we [57:42] did the big adoption and change back in [57:44] March, it was just that you couldn't [57:46] have a deck less than 20 ft from your [57:49] rear lot line that was intended for [57:52] attached decks u and for fire uh [57:58] separation purposes and and that type of [58:00] thing. With these detached decks, they [58:03] really are like an accessory building [58:05] and pools are already allowed to be [58:06] within uh 10 ft of a rear side lot line [58:10] anyway. Um and this was limiting people [58:13] to not have detached deck above ground [58:17] pool is really what this would [58:20] play with. This is saying that as long [58:22] as they're not attached to the home, [58:24] they just accessory structure setbacks [58:27] of basically 10 ft instead of [58:30] um wasn't an issue that comes up a ton, [58:32] but didn't make sense that a detached [58:35] deck should have the same setback [58:37] requirements as an attached one because [58:39] it didn't have the fire connection uh to [58:42] the principal structure. Main reason why [58:45] we wanted [58:48] and then uh finally we said multiple [58:51] references to zoning ordinance in the [58:54] UDC and I should have said other [58:57] sections of the UDC [59:00] zoning ordinance. So that was really [59:02] just kind of a clean up item. So believe [59:05] we have uh all the major items again [59:07] planning commission is going to hold a a [59:09] hearing on the the topic of solar again [59:12] um at their meeting on September 16th um [59:14] that's coming up next week. Um so that [59:19] will be kind of item I think of this [59:21] batch coming out of the uh the new UDC [59:25] that again was was initially the major [59:28] adoption was handled back in so it's [59:31] been working well um so far but we just [59:33] believe that there's some good [59:35] clarifying uh items uh that the planning [59:38] commission wanted to review and did make [59:40] the motion to move in front of you for [59:42] introduction here uh tonight at the [59:44] council level [59:46] » And what [59:48] issues are coming before the planning [59:50] commission with regards to solar. [59:52] » Um solar specifically, I think the issue [59:56] was we're actually not I shouldn't just [59:58] say solar also regarding alternative [1:00:01] energy systems. So like um windmills [1:00:06] and I think specifically Sean brought up [1:00:08] at the meeting, correct me if I'm wrong [1:00:10] Sean? [1:00:10] » No, you're right. There was once uh [1:00:12] particularly a case that came up in Oro [1:00:15] with a housemounted um wind [1:00:18] » Turbine [1:00:18] » Turbine that was noisy unsightly [1:00:22] um and in state statute we can't out [1:00:25] prohibit them but we can severely limit [1:00:28] where they're allowed. So that's what [1:00:30] we're going to be looking at commission [1:00:32] hearings. And that was a the whole house [1:00:35] fan type of deal. [1:00:37] » Uh just a I was rough mounted um [1:00:40] windmill. [1:00:41] » We had a lot of them in the city. [1:00:43] » What's that? [1:00:44] » We did a lot of them in the city. [1:00:46] » Yeah. And we're not saying we prohibit [1:00:48] them. We just wanted to put some some [1:00:50] guard rails up. So we we have been and [1:00:52] are continuing through this week to do [1:00:54] research on what other cities have for [1:00:57] um regulations for them because right [1:00:58] now we don't have any. [1:01:02] And mine was not even housebased. I [1:01:04] think the orno case was it was out in [1:01:07] the backyard, but it was 30 feet high. [1:01:10] It was huge. So, [1:01:12] » In the farm, huh? [1:01:13] » Yeah. [1:01:14] » So, [1:01:15] » I'm surprised. Don't we have uh [1:01:17] residents with shipping containers being [1:01:19] used right now as structures to store [1:01:22] things? [1:01:23] » You know, um I hope we don't because [1:01:27] » By the ordinance, we we do not allow [1:01:29] them. So, they have not been allowed and [1:01:31] we've never had anybody ask to put one [1:01:32] in the yard. So, if there are any, [1:01:34] they're legally placed. [1:01:35] » They're next to the chickens. [1:01:36] » Would people ask the coupe? [1:01:39] » Um, I don't know that everybody would [1:01:40] ask, but if we if we have seen one and [1:01:42] we have not at this point, we would [1:01:44] definitely address it. [1:01:45] » Maybe we should drive through the alleys [1:01:46] again. [1:01:48] » We definitely can do that. And if you [1:01:50] know of an area where we should look, be [1:01:52] happy to to hear that. [1:01:53] » No, no, no, no, [laughter] [1:01:56] » No. I think it is uh [1:02:00] I I think that's that's an area that can [1:02:02] be u [1:02:04] there might be some people that have [1:02:06] arguments about that one but [1:02:09] » Contentious [1:02:10] » Some of the structures that people store [1:02:11] stuff in [1:02:13] don't look as good as the storage [1:02:15] containers. [1:02:19] [clears throat] [1:02:20] [snorts] [1:02:21] » So any other questions? [1:02:24] If not, I guess I'll make a motion for [1:02:27] the first reading of ordinance number [1:02:29] 367. [1:02:31] » I'll second. [1:02:32] » We got a second by Maggie Bass. There's [1:02:34] no other questions, comments. All in [1:02:36] favor say I. [1:02:37] » I. [1:02:37] » I. Any opposition? Okay. Passes. [1:02:40] » Thank you. [1:02:41] » We don't have any ordinance for [1:02:42] adoption. Next is a resolution dealing [1:02:45] with officially naming [1:02:48] the area where the pops [1:02:52] stage is being built. Is that correct? [1:02:55] » Correct. Um, so I think I'd given you an [1:02:58] update maybe a month and a half ago or [1:03:00] so. Um per the adopted policy for uh [1:03:05] park naming uh that we have uh council [1:03:08] adopted policy I should say had quite a [1:03:11] lengthy uh process that had to be [1:03:13] followed beginning with the um park [1:03:15] board and ultimately ending with the [1:03:17] park board [clears throat] uh to collect [1:03:19] names collect a public um comment period [1:03:22] and all the comments on the names that [1:03:24] we had solicited. So, we had six names [1:03:26] initially that were um solicited. [1:03:28] Milpond Commons, Central Park, D'vorox [1:03:31] Landing, Harmony Park, Milpond Park, and [1:03:35] I'm going to butcher this from Mavka [1:03:38] Park, which I believe is a park in the [1:03:40] Czech Republic um that were uh formally [1:03:43] submitted, and we had given the council [1:03:45] an update on those at that time. So, we [1:03:47] did have a public comment period that [1:03:49] had run for most of the summer, and that [1:03:52] wrapped up on August 10th. Uh the park [1:03:54] board did review uh the names and again [1:03:57] the comments that were on all the names. [1:03:59] I did include that information in the [1:04:01] packet here tonight for the city council [1:04:03] to consider. Uh but ultimately the the [1:04:06] park board did uh pass a recommendation [1:04:09] on to the council tonight to um utilize [1:04:12] the name of Mil Pond Commons for the [1:04:14] formal name of what we've uh temporarily [1:04:17] been calling city center where the pops [1:04:19] facility is located. So, I do have a [1:04:23] resolution in the packet tonight that [1:04:25] would uh establish the formal name of [1:04:28] Milon Commons for that property uh where [1:04:32] the [1:04:32] » Before you go into that part, can I ask [1:04:34] a question? [1:04:34] » Sure. [1:04:35] » Why did this come up? [1:04:37] » Why did it come up is because [1:04:39] » With the comments part at the end, it [1:04:40] almost sounds like there's an apartment [1:04:41] building right over there. So, that [1:04:43] actually did come up at the uh park [1:04:45] board meeting with Mil Pond Apartments. [1:04:49] And the common's idea was that it's not [1:04:51] just simply a uh park, but rather a park [1:04:56] with the surrounding development that [1:04:58] has not yet occurred on the north end of [1:04:59] the property with the council and the [1:05:01] concept plan and um all of that small [1:05:04] area planning that uh the park board and [1:05:06] the council did a few years back with [1:05:08] the comp plan that there could be future [1:05:10] development both north of Pops as well [1:05:13] as on the u adjacent to the railroad [1:05:16] tracks on the west side of u the gravel. [1:05:19] Third Avenue. [1:05:19] » Well, almost definitely the north north [1:05:22] end there is going to have to get [1:05:23] rebuilt up. Yep. [1:05:24] » I'm just saying that we could sell it [1:05:27] and everything like that and they could [1:05:28] put something anywhere they want there, [1:05:30] but [1:05:31] » We would be changing the name sooner or [1:05:34] later from Commons to something else. [1:05:37] » Yeah. And I I I think the the general [1:05:39] consensus and again with the public [1:05:41] comment was the Milon Commons. [1:05:43] Obviously, one of the other ones was [1:05:44] Milpond Park. So it wasn't a huge, [1:05:49] you know, outpouring of park versus [1:05:52] commons. Commons just had more comment [1:05:55] in the affirmative for that. And maybe [1:05:57] Maggie can shed some more light on [1:05:59] » It. Sounds like it was pretty common to [1:06:00] have a common. [1:06:01] » Yeah, Commons, I think, is is also known [1:06:04] as a gathering place. So, because I [1:06:07] think of the pops stadium, the storm [1:06:10] water pond, maybe a [1:06:12] a trail, and you know, some other [1:06:15] amenities. It's a place for people to [1:06:17] gather. So, it's just a a different use [1:06:20] of verbiage. [1:06:22] » I think you see it actually on you go [1:06:24] south of the border down to Mexico. When [1:06:25] you think like traditional [1:06:27] Mexican towns, a lot of have that common [1:06:29] square right in the middle, right? [1:06:31] Commons. Yeah. In this instance, I think [1:06:33] common is referring more to the public [1:06:35] gathering place open to everybody, [1:06:38] but [1:06:39] » I think park will kind of screw that [1:06:42] you're going to have park playground [1:06:45] equipment type there [1:06:46] » And I don't think [1:06:47] » There there may be but [1:06:48] » Maybe at some time but I don't think [1:06:51] that I mean growing up in New Prague [1:06:54] that was always the mill pond area [1:06:56] » Even when there was no pond but [1:07:00] I mean I'm you I think that's a a very [1:07:04] good option for a name. Um because we [1:07:07] are going to have kind some kind of a [1:07:08] pond, aren't we? A holding pond of some [1:07:10] sort on that end. [1:07:11] » We still hope that [1:07:15] » Are your buddies at deed having fun with [1:07:17] you or [1:07:18] » We're getting there. [1:07:18] » We're feel like we're this close. [1:07:21] » Yeah, we're this close in May. [1:07:23] » Isn't that the feeling Yeah. you had in [1:07:24] May? The same feeling. [1:07:26] » Every month we have [1:07:27] » We're not getting any farther away. [1:07:28] [laughter] We actually Yeah. [1:07:31] Well, now if we got a name, tell them, [1:07:32] "Hey, you got to put the pond there." [1:07:38] » Any other comments? [1:07:44] » Okay. If not, I guess I'll look for a [1:07:45] motion to approve resol resolution [1:07:49] CC-26-9-08-02. [1:07:53] » So moved. [1:07:54] » Officially naming mil pond comments. And [1:07:57] I got them [1:07:58] » A motion by Maggie Bass. [1:08:01] » I'll second it. [1:08:02] » Second by Rick Syler. If there's no [1:08:04] other comments, all in favor say I. [1:08:07] » I. [1:08:08] » Any opposition? All right, that's fair. [1:08:10] » I bet you we have to change that one of [1:08:12] these days. [1:08:13] » Well, go through the process again. [1:08:15] » There you go. Uh, there's no general [1:08:18] business. So, we're now at the [1:08:19] miscellaneous. Rick, do you have [1:08:20] anything? [1:08:21] » No. [1:08:22] » Bruce? [1:08:23] » No. [1:08:25] » Maggie? No. [1:08:26] » Sean. [1:08:27] » Um, just a question for Tim. Do we got [1:08:30] an open house date yet set? [1:08:34] » We are looking at [1:08:38] Give me one second. [1:08:42] October the 24th. [1:08:44] » Okay, great. [1:08:45] » So, we're doing our uh [1:08:48] we do our carving with the cops event. [1:08:50] » Oh. [1:08:51] » So, kind of jointly do that at the same [1:08:54] time. Perfect. Sounds great. Thank you. [1:08:56] » Yep. Well, we were just uh working on [1:08:59] the flyers today, so hopefully it'll be [1:09:01] out here by the end of the week. We can [1:09:03] start putting that out there. [1:09:04] » Okay, good. Thank you. That was it. [1:09:06] » No, that was it. [1:09:07] » Sean or Josh? [1:09:08] » Uh yes, real quick. Um, I had a talk [1:09:12] with the fire chief uh about their [1:09:15] pension fund and due to some wise [1:09:17] investments that fund has continued to [1:09:19] grow and so he wanted to sit down and [1:09:21] have a kind of a discussion to see if [1:09:23] there was possibility maybe of using [1:09:24] some of that funds. As you guys may [1:09:26] remember, the only way we can use that [1:09:28] funds is by disseminating it to [1:09:29] firefighters. So, I know in the past [1:09:32] generally the council has selected kind [1:09:34] of a subcommittee of two people and [1:09:35] myself to sit down um with the rural [1:09:38] board as well as um kind of the fire [1:09:40] board and kind of talk through that and [1:09:42] then bring back any sort of [1:09:43] recommendation to the council. And so [1:09:45] I'm just kind of wondering if the [1:09:46] council wants to go through that process [1:09:47] again. Um I think the last couple times [1:09:51] we've done it, it was the mayor and [1:09:54] Sean, wasn't it? And three of us. But um [1:09:56] just wanted to check with the council if [1:09:58] that's kind of process we wanted to go [1:09:59] through again. Um let me just uh trying [1:10:03] to understand how that works again. Is [1:10:04] that just transferring money into their [1:10:07] pension program? [1:10:08] » Yeah. So the way that works is cities do [1:10:10] it a few different ways. What we do is [1:10:12] we receive a fund. We receive basically [1:10:16] an amount from the state every year and [1:10:18] we as a city just act as a pass through [1:10:19] them to move that over into their [1:10:21] pension fund. And then when they leave [1:10:24] the uh service, whether it's like retire [1:10:27] or slightly early, I don't know the [1:10:28] exact payout schedules of it, they would [1:10:30] get a portion for serving within um the [1:10:34] fire department. And so a lot of times [1:10:36] when they retire with 20 years and their [1:10:38] full pension, they would then take a [1:10:40] lump sum of that. And so generally as we [1:10:43] um review this and part of it I think [1:10:45] they um we use uh [1:10:49] Shannon Brouso kind of looks over that [1:10:52] fund for them we make sure that that [1:10:55] fund can [snorts] hold or pay out [1:10:57] basically all of its current debts and [1:10:59] if for some reason that drops below 90% [1:11:02] which I believe it's happened once [1:11:03] hasn't it Sean were you hearing that [1:11:04] happen the first time [1:11:05] » And Chuck there was one time [1:11:07] » Um the city basically has to come up [1:11:09] with funds to catch up to that now [1:11:13] last couple times that fund is hitting [1:11:15] around 115% of being covered and the [1:11:18] city said okay there's only one thing we [1:11:20] can do with this it's not like we can [1:11:21] recoup it for ourselves like it goes out [1:11:23] to pay out these funds and so we said [1:11:25] okay we're going to up the amount of [1:11:27] retirement for the annual years of [1:11:29] service [1:11:30] » So what they're asking is if they can [1:11:32] increase our pension benefits [1:11:34] » Yep so right now they're saying our our [1:11:36] current fund balance is sitting at [1:11:38] whatever it is I I don't know the exact [1:11:39] number is there something we could do to [1:11:41] look at increasing the pension fund [1:11:43] benefits to use some of that fund [1:11:45] balance. [1:11:45] » Okay. So then and I'm not trying to make [1:11:48] a statement here or anything but just so [1:11:50] I understand the financial part of it. [1:11:51] So if we do that increase their benefits [1:11:54] then there's a greater risk that we [1:11:55] might fall short in the future. [1:11:57] » That is correct. That risk exists. I [1:11:58] know was it a couple years ago we [1:12:00] started putting away a little bit of [1:12:01] money at the end of each year when we [1:12:03] had revenue surpluses just to kind of [1:12:05] hold as a just in case too for that. But [1:12:07] yes, obviously as their benefit [1:12:10] increases, it does increase that risk, [1:12:11] which is why we then look at it and say, [1:12:13] "Okay, where is it sitting? What would [1:12:16] the market have to adjust to potentially [1:12:18] put us into that default risk?" That's [1:12:20] » So there's no automatic increase in [1:12:22] benefits each year. [1:12:23] » Correct. [1:12:23] » Is nothing. [1:12:24] » That is correct. [1:12:26] » Okay. So [1:12:27] » Yeah. Yeah. They basically get a benefit [1:12:28] based off of years of service and what [1:12:30] we have set the annual benefit at. And [1:12:33] often it goes two or three years before [1:12:36] we ever changing [1:12:37] » Without anything changing. So [1:12:39] » When was the last time we changed it? [1:12:40] Was it two years ago? Probably. [1:12:41] » I was going to say I I thought two, but [1:12:44] uh it could be as soon as or maybe it [1:12:46] was last year. [1:12:46] » It wasn't like No, because I mean Chuck [1:12:48] wasn't here. It was back when was so I [1:12:51] think it was two years ago. [1:12:52] » Okay. [1:12:55] » Yeah. I'd be in favor of changing it. [1:12:57] » Yeah. and not doing it dramatically, but [1:13:00] » And I think that you usually we change [1:13:02] if we go from like 3,000 to 3,300 or [1:13:05] like I said, I know we last few years we [1:13:07] put that analysis into it of okay, if we [1:13:09] do this, where does that put our fund [1:13:11] balance and what are our liabilities and [1:13:13] what would that market likely have to [1:13:15] change to affect and really affect the [1:13:18] city because at this point the city [1:13:20] doesn't put anything into that [1:13:22] » Where I know some budgeted to put [1:13:25] something in it. We started a few years [1:13:26] ago when it was fluctuating quite a bit [1:13:29] that we just to cover so we didn't have [1:13:32] some un [1:13:32] » So do you have it in this budget? [1:13:35] » Uh no. So yes. Yeah. So we have an so [1:13:37] yeah we've taken we get to the end of [1:13:39] the year and say oh we've got these [1:13:40] excess revenues from the year like and [1:13:43] we talk to the auditors and they tell us [1:13:44] a little bit of fund balance like that's [1:13:46] where we we designate some of that fund [1:13:48] balance just to set aside kind of like [1:13:49] we've also done for the aquatic center [1:13:51] in case for some reason. [1:13:52] » Right. But I thought for a few years we [1:13:54] actually budgeted an expense [1:13:56] » Just so we wouldn't have some huge swing [1:13:58] just in case. [1:13:58] » We don't do that anymore. [1:13:59] » We don't do that anymore. [1:14:00] » Okay. [1:14:01] » Okay. [1:14:04] » I think that housing I think if I [1:14:06] remember right it was like 60some [1:14:08] thousand that the city had to come up [1:14:09] with one time before you and I were on. [1:14:12] » Yeah. [1:14:12] » But during like the housing crisis when [1:14:14] everything [1:14:15] » Right end of 2008 [1:14:17] » Or something. Yeah. There's only been [1:14:19] one year I think. [1:14:22] Yeah, I guess [1:14:23] » So. Oh, yeah. So, I guess would you [1:14:25] sorry the whole point of that [1:14:26] conversation, would you guys like to [1:14:27] kind of do that whole subcommittee thing [1:14:28] like we've done before? Like I said, I [1:14:30] know Sean sat on the last few ones at [1:14:32] least and has been the mayor, but if [1:14:34] you'd like a different makeup, we can [1:14:35] certainly do that, too. It's up to you [1:14:36] guys. [1:14:37] » I'd be happy to do it, but if somebody [1:14:39] else wants to do it, that's [1:14:40] » Happy to do it, too. If it's fine. [1:14:42] » It's just an hourlong meeting. [1:14:43] » I'd be happy for you guys to do it. [1:14:45] Well, then [laughter] [1:14:47] » And I I I guess if that's [1:14:48] » Second motion, [1:14:49] » If that's the case, I know some dates I [1:14:51] got kind of right off hand that would [1:14:53] work if kind of the 22nd, 24th, or 17th. [1:14:57] I guess I put those in the wrong order. [1:14:59] 17th, 22nd, or 24th work here this month [1:15:02] at like six o'clock. So, I think it's a [1:15:04] Thursday, Tuesday, Thursday. [1:15:07] Be next Thursday or after that, Tuesday [1:15:10] or Thursday? [1:15:11] » I think Thursday probably works a little [1:15:13] better for me. I don't have my I left my [1:15:15] phone in my car so I don't [1:15:16] » So if I call you tomorrow Yeah. [1:15:18] » Just kind of confirm that. [1:15:19] » Sure. Okay. [1:15:19] » Yeah, that's fine. [1:15:21] » Oh, wait. You have golf on Thursday. [1:15:23] » Uh [1:15:23] » I can do Tuesday. [1:15:25] » The 17th is our last golf meet. League [1:15:29] meet day. [1:15:30] » League? Not your last golf day? [1:15:32] » Well, no, but [1:15:34] » Okay. I'll I'll call you guys tomorrow [1:15:35] and see if I can confirm something on [1:15:36] that. [1:15:37] » Okay. Anything else? [1:15:38] » That's all I had. [1:15:39] » Ken, do you have anything? Robin, [1:15:42] Kim, [1:15:50] » I did want to share a little [1:15:51] information. Um, well, I feel like [1:15:53] there's so much [1:15:55] negative [1:15:57] stuff in the world, social media, [1:15:59] newspaper, everything. I wanted to share [1:16:01] a little bit of positive stuff about the [1:16:02] our community. Um, the last three weeks, [1:16:05] uh, hopefully I'm not stealing your [1:16:06] thunder, Chuck, but the last three [1:16:08] weeks, uh, New Prague held the state [1:16:10] amateur baseball tournament. Um, while I [1:16:13] made, uh, while I was there a lot, I [1:16:15] only made one game, but it I couldn't be [1:16:17] more impressed with this community. Um, [1:16:20] there is talking to Nick Shenker, he was [1:16:22] one of the one of the main guys that [1:16:24] helped get that tournament here, [1:16:26] including many. Uh Chuck was part of [1:16:27] that board and everything, but um [1:16:29] there's 29,000 people that attended uh [1:16:32] all the games through four uh four [1:16:34] venues, three main venues with the [1:16:36] fourth one. Uh New Prague had the [1:16:38] highest attendance at uh over 9,313 paid [1:16:42] attendance. Um [1:16:45] these events do not take place without [1:16:47] hundreds and hundreds of volunteers [1:16:49] throughout the three weeks. And I'm not [1:16:50] joking. It's hundreds and hundreds of [1:16:52] people that uh volunteer their time. Um, [1:16:56] city staff spends a lot of time on that [1:16:58] field. We are extremely proud of that [1:17:00] field. Uh, the big renovations that took [1:17:02] place 10 years ago. We were so excited [1:17:05] when we see all these people come into [1:17:06] our community to get to see our field. [1:17:08] Um, I heard nothing but great [1:17:10] compliments of how great the field [1:17:12] conditions were, how great this [1:17:14] community is, and how do you get so many [1:17:16] volunteers that are all happy just [1:17:19] willing to help and uh just make it a [1:17:22] better event. Um, I just I really cannot [1:17:26] express how excited I was. Someone [1:17:28] that's born and raised in New Prague, [1:17:30] New Prague means the world to me. Um, [1:17:32] just seeing everybody come together and [1:17:33] make this vent, this event, I would [1:17:36] argue one of the best events. Um, I [1:17:39] think a lot of the people I talked to [1:17:41] would say the same thing. So, one, I [1:17:43] want to thank all those people that did [1:17:44] that uh, volunteer their time. I want to [1:17:46] thank my staff for all the time they put [1:17:48] into that field. Um, [1:17:51] a lot of time, a lot of money has [1:17:53] obviously been put into that field. Uh, [1:17:55] a lot of money that, uh, this tournament [1:17:58] raises to put back into that field. Um, [1:18:01] really every dollar they make goes back [1:18:03] into that field and it gets lets us do a [1:18:05] lot of the projects we've done. So, I [1:18:08] really just want to thank everybody in [1:18:09] the community, staff. Um, it was an [1:18:12] amazing event. and uh coming down hole [1:18:16] 18 on Sunday when the class B tournament [1:18:18] was. I thought they were all cheering [1:18:19] for me, but then I realized they [1:18:20] weren't. Um but it was really [1:18:23] impressive. That's all I wanted to say. [1:18:24] Thank you uh to Chuck, everybody that [1:18:26] volunteered, if any of you guys did. Um [1:18:29] it was I know I'm rambling on, but it [1:18:31] was a very special event. So, I just [1:18:32] wanted to say that. [1:18:33] » And we all thank you guys because I [1:18:35] heard that you did a lot of work on this [1:18:37] too, Chuck. So, [1:18:38] » Yeah. No, I to reiterate that. I mean, I [1:18:41] think we had a lot of positive feedback [1:18:44] from people who've never heard of New [1:18:46] Prague, uh, because we had a lot of [1:18:49] class C games, which they came two or [1:18:51] three hours, they drove like a New York [1:18:54] Mills and and, uh, Buffington and all [1:18:57] this stuff and they come in and they [1:18:58] were not only impressed with the ball [1:19:01] field, but the community as a whole. And [1:19:04] uh I I think it really showcases that we [1:19:07] uh are doing the right things in this [1:19:10] community and uh we got great workers. [1:19:13] Matt, your people did a great job and [1:19:15] the board was impressed. I know we did [1:19:17] it in 2018, we broke a record also and [1:19:21] this record that we broke uh stood since [1:19:24] 1961. [1:19:26] So uh we got to be very proud of of what [1:19:28] we did. And you are right. Uh the [1:19:30] volunteers and there's people Johnny was [1:19:33] there two or three times and and other [1:19:35] people that you know they they would [1:19:37] look on sign up genius and they they [1:19:39] didn't care if they were there six [1:19:40] hours. They would sign up for different [1:19:42] shifts if there was gaps in it and we're [1:19:44] very fortunate to that. So [1:19:48] all right Mitch, you got anything? [1:19:51] Patrick? [1:19:54] I don't have anything. So I guess I'll [1:19:56] make a motion to adjurnn. [1:19:59] Second.