1 00:00:00,020 --> 00:00:10,260 All right, good afternoon, everyone. It's 130. I'd like to go ahead and get started. We have a lot of material to cover today. 2 00:00:11,040 --> 00:00:17,180 But first I just wanted to thank you all for taking the time out of your schedules to come and talk about project delivery, project development with us. 3 00:00:18,680 --> 00:00:29,140 First, well, just a little housekeeping. We are live streaming this this workshop. So there are folks at home. So if you have questions, please please let us know. 4 00:00:29,140 --> 00:00:34,060 So we can speak them back clearly into the microphone, so their folks can hear the question 5 00:00:34,060 --> 00:00:34,820 and the response. 6 00:00:35,540 --> 00:00:40,920 We also have been approved by the American Planning Association certification maintenance 7 00:00:40,920 --> 00:00:41,320 credits. 8 00:00:41,540 --> 00:00:48,180 So if you would like those, you can claim those credits after the workshop as well. 9 00:00:48,560 --> 00:00:54,160 We're going to have quite a few speakers today, so first up, I'll have Alan Clark, the director 10 00:00:54,160 --> 00:00:58,660 of Transportation here at the Houston Galveston Area Council, come and give you our formal 11 00:00:58,660 --> 00:01:00,320 welcome. Thank you. 12 00:01:03,100 --> 00:01:08,040 Thank you, Adam. I really just wanted to say thank you, you know, we do a lot of 13 00:01:08,040 --> 00:01:12,940 planning activities and get to work with all of you in different capacities as a council of 14 00:01:12,940 --> 00:01:19,160 governments, but it doesn't really mean much unless what we plan happens, right? And getting that 15 00:01:19,160 --> 00:01:25,900 project delivered in your community is what it's all about because without that we're not going to 16 00:01:25,900 --> 00:01:32,100 see the safety benefits, the mobility benefits, the economic development and your community. 17 00:01:32,880 --> 00:01:39,080 All the things that are important about the work we do only happen when you're able to 18 00:01:39,080 --> 00:01:45,020 work with your community with your, with, with, with important agencies like TechStot and 19 00:01:45,020 --> 00:01:50,960 others to bring that project to reality. So thank you so much for your time, for the work 20 00:01:50,960 --> 00:01:54,360 that you do, it's why our job is fun to do, 21 00:01:54,560 --> 00:01:56,620 because we get to see these great things happen. 22 00:01:57,360 --> 00:02:02,660 I was told that the simplified blow chart on the far wall 23 00:02:02,660 --> 00:02:03,900 will be on the quiz. 24 00:02:05,320 --> 00:02:11,720 So I hope you can read legibly and it's at 33rd box to the right. 25 00:02:11,960 --> 00:02:14,680 I'm going to give you a clue about one of the questions now. 26 00:02:15,400 --> 00:02:17,060 But thank you so much for being here today. 27 00:02:17,060 --> 00:02:18,680 I'm not going to take time. 28 00:02:18,680 --> 00:02:25,540 The Council of Governments is home to the Metropolitan Planning Organization for those of you who are not familiar with the Houston 29 00:02:25,540 --> 00:02:30,280 Galvestonary Council. And we try to work cooperatively with our local governments, our key 30 00:02:30,280 --> 00:02:38,760 Transportation Partners like Textot, to make sure our citizens are served as best we possibly can with the resources that we have. 31 00:02:39,100 --> 00:02:43,440 And that's certainly true in the Transportation Area. So thank you again for being here today. 32 00:02:49,200 --> 00:02:53,960 All right, to get us started, I wanted to introduce Katherine McCrape. 33 00:02:54,740 --> 00:03:00,900 She is with the text.heast in district office, believe Katherine has about 20 years experience 34 00:03:00,900 --> 00:03:02,140 in the project. 35 00:03:02,800 --> 00:03:10,720 Most of those with the district office, Katherine is going to talk to us today about, give us 36 00:03:10,720 --> 00:03:17,440 an overview of the project delivery process, process, and with that, I will turn it over 37 00:03:17,440 --> 00:03:17,940 to Katherine. 38 00:03:22,190 --> 00:03:24,710 Bring this down here because I'm a little short. 39 00:03:26,010 --> 00:03:33,730 Okay, so thank you for having me. Yes, my name is Catherine McRite and I'm a senior transportation planner with a Texas Department of Transportation. 40 00:03:34,270 --> 00:03:41,910 Today, I'm going to spend the bulk of the time talking to you about Texas process for project development and delivery. 41 00:03:41,910 --> 00:04:02,030 The reason this is important to you is that while you may be here because you received some funds through your MPO for to develop and deliver a project, the funds that you received actually came through the state. 42 00:04:02,030 --> 00:04:08,090 They are federal funds, and the federal highway administration has delegated responsibility 43 00:04:08,090 --> 00:04:11,630 for those funds to the Texas Department of Transportation. 44 00:04:12,410 --> 00:04:22,430 Our commission has suballocated certain funds of those federal funds to the MPO for a local 45 00:04:22,430 --> 00:04:31,570 project decision making, but just because the MPO has done projects selection, you still 46 00:04:31,570 --> 00:04:38,810 to come back to the state in order to develop and deliver your project. And so I think it's 47 00:04:38,810 --> 00:04:44,790 important that you understand kind of from a big picture our process and also I'm going to give 48 00:04:44,790 --> 00:04:52,910 you a peek into some of our new processes that we've implemented over the past couple of years. 49 00:04:54,810 --> 00:05:00,990 So I teach a class actually teach four classes across the state on a project development delivery 50 00:05:00,990 --> 00:05:09,410 text. And this is a condensed version. It's a 45-minute version of a four-hour class. So I'm going to go kind of fast. 51 00:05:10,990 --> 00:05:17,750 So today, some of the key learning objectives that you should realize, you should understand the many steps 52 00:05:17,750 --> 00:05:23,230 and their interdependencies to successfully develop and construct projects with text. That you should be able 53 00:05:23,230 --> 00:05:30,010 to define how projects are created and how they move through a funnel that's part of a portfolio that we 54 00:05:30,010 --> 00:05:32,470 manage at the district and at the state. 55 00:05:33,290 --> 00:05:36,850 You should have a good understanding of performance-based planning, 56 00:05:37,750 --> 00:05:39,990 understand our quarterly review process, 57 00:05:40,410 --> 00:05:45,350 and understand how understand our project delivery and governance process 58 00:05:45,350 --> 00:05:49,770 that ensures on time and on budget projects. 59 00:05:51,330 --> 00:05:54,170 So here's kind of a snapshot of where we're going. 60 00:05:55,710 --> 00:06:08,250 When I get to chapter two, I've eliminated this slide, this actual particular slide, and I'm just going to take you from two, three, four, five, and six kind of rapid fire. 61 00:06:10,030 --> 00:06:20,470 So, as Alan mentioned over here on the wall is kind of a layout of a, or it's a high level overview of the project development delivery process at text time. 62 00:06:20,470 --> 00:06:35,590 It is not exhaustive, and what you need to know about this is that there are a lot of processes where we can parallel process. 63 00:06:35,750 --> 00:06:40,990 And that's the important thing, the important message that I want to talk to you about today. 64 00:06:44,990 --> 00:06:48,610 So, project development delivery, our process is cyclical. 65 00:06:48,950 --> 00:06:53,870 We start with operation and maintenance, we're all maintaining our respective systems, 66 00:06:54,510 --> 00:07:00,430 and then we identify needs, and so, project selection has occurred within the far left 67 00:07:00,430 --> 00:07:06,810 part of that circle, that's where what you did with the MPO, when you went through the call 68 00:07:06,810 --> 00:07:13,690 for projects, and use the mid-idger project, and there was consideration by various committees and 69 00:07:13,690 --> 00:07:19,710 staff, and then it went through the TAC and TPC and your project was selected. 70 00:07:20,330 --> 00:07:27,250 We are in a process now where we are inserting your projects into the transportation improvement 71 00:07:27,250 --> 00:07:29,890 program, and I'll get into that in just a little bit. 72 00:07:30,230 --> 00:07:32,570 And we're going to begin the initiation process. 73 00:07:32,990 --> 00:07:40,030 We're going to take you through a process of initiation, engineering, PS&E, letting and construction. 74 00:07:40,690 --> 00:07:45,890 today you're going to be hearing from some subject matter experts in each one of these areas. 75 00:07:47,510 --> 00:07:47,590 So, 76 00:07:49,920 --> 00:07:51,700 we just take this for a second. 77 00:07:52,100 --> 00:07:53,120 I'll walk around with it. 78 00:07:53,540 --> 00:07:59,280 So, the interesting thing here is, from a federal perspective, 79 00:08:00,120 --> 00:08:02,780 the state starts out with a statewide long-range plan. 80 00:08:02,780 --> 00:08:11,140 It's a 24-year plan that lays out the framework for how the state is going to proceed over the next 24 years. 81 00:08:13,760 --> 00:08:20,160 It talks about technology, it talks about expected funding, what it does not have is a specific 82 00:08:20,160 --> 00:08:22,380 list of projects and specific funding. 83 00:08:22,560 --> 00:08:25,480 It just talks about what we think the trends are. 84 00:08:26,220 --> 00:08:31,880 If you read it today, we're introducing kind of some of these disruptive technologies, talking 85 00:08:31,880 --> 00:08:35,360 about how they're coming, CBAV, these kind of things. 86 00:08:35,360 --> 00:08:43,920 When you get down to the next document, the Metropolitan Transportation Plan or the RTP at Houston, 87 00:08:44,080 --> 00:08:50,540 Galveston Area Council, the Regional Transportation Plan, that is a 20-year document that identifies 88 00:08:50,540 --> 00:08:57,100 projects that are going to be undertaken by the region over the next 20 years and anticipated 89 00:08:57,100 --> 00:09:01,560 funding, reasonably available funding, not actual funding. 90 00:09:01,560 --> 00:09:09,600 Basically, the MPO takes the 10 year financial forecast in the UTP, the unified transportation program, 91 00:09:10,240 --> 00:09:21,920 and they run it out over the next 10 years to develop a reasonably anticipated funding that they can program projects against. 92 00:09:21,920 --> 00:09:27,680 The MTP, the UTP, the STIP, and the letting schedule are all 93 00:09:27,680 --> 00:09:29,280 physically constrained documents. 94 00:09:30,580 --> 00:09:33,880 The Unified Transportation Program is a state-required document. 95 00:09:33,880 --> 00:09:40,480 It is a 10-year programming document that identifies projects and the funding that will be used 96 00:09:40,480 --> 00:09:42,480 to implement that project. 97 00:09:43,380 --> 00:09:49,320 Then the statewide transportation improvement plan program, and you may hear it here as the 98 00:09:49,320 --> 00:09:57,080 the Transportation Improvement Program is a four-year federally-required document that generally is 99 00:09:57,080 --> 00:10:03,700 constructed authority. Those are guaranteed pretty much guaranteed funds to implement your project. 100 00:10:06,590 --> 00:10:12,630 And then of course, text dot does the two-year letting schedule. And so what you're doing is 101 00:10:12,630 --> 00:10:19,110 you can just kind of draw an arrow from the 24-year all the way down here, project development occurs 102 00:10:19,110 --> 00:10:23,630 throughout this process and we're working towards a letting schedule. 103 00:10:25,470 --> 00:10:26,070 Any questions? 104 00:10:37,480 --> 00:10:44,280 So, we're going to need processes fit into this letting schedule and these plans and programs. 105 00:10:48,360 --> 00:10:55,810 Text that over the past few years has implemented three new processes, the project delivery and governance for 106 00:10:55,810 --> 00:11:02,860 performance-based planning which is a response to state and federal requirements and the quarterly review process. 107 00:11:04,490 --> 00:11:15,430 Project development and governance, we document our current project development and delivery process and refine it to improve efficiency and facilitate improved staff training. 108 00:11:16,070 --> 00:11:21,890 We have a governance committee that manages the portfolio and makes adjustments as necessary. 109 00:11:21,890 --> 00:11:27,990 In performance-based planning, which is largely governed by our transportation planning and 110 00:11:27,990 --> 00:11:33,430 programming division in Austin, they help to define our planning process and develop scoring 111 00:11:33,430 --> 00:11:40,610 criteria and ranking methodology to ensure that we comply with the state requirements and 112 00:11:40,610 --> 00:11:43,250 federal requirements for performance-based planning. 113 00:11:43,950 --> 00:11:49,490 Probably, you've seen this process more here at the local level when you went through your 114 00:11:49,490 --> 00:11:54,010 for projects. If you were following it and you followed the tech and TPC and staff 115 00:11:54,010 --> 00:12:01,170 activities, you know that they went through many months worth of work to 116 00:12:01,170 --> 00:12:07,410 number one identify the funding that's available to look at the categories that 117 00:12:07,410 --> 00:12:13,370 they're going to fund like mobility, alt modes, planning projects, air quality 118 00:12:13,370 --> 00:12:18,590 projects, and then they came up with scoring criteria from there and then they 119 00:12:18,590 --> 00:12:25,870 release the call for projects, and you, as a project sponsor, probably submitted, you fill 120 00:12:25,870 --> 00:12:30,390 voucher application and submitted it and hoped for the best. If you're here, hopefully that 121 00:12:30,390 --> 00:12:37,550 means you were awarded some months. A very similar process goes on within text dot between the 122 00:12:37,550 --> 00:12:46,770 districts. And so we put together our list of projects and the state uses certain tools to rank 123 00:12:46,770 --> 00:12:52,090 evaluate and rank our projects internally as well to determine a portfolio or projects. 124 00:12:53,310 --> 00:12:59,550 The, and we'll talk a little bit later about which funds are suballocated to the, yeah, thank 125 00:12:59,550 --> 00:13:00,850 you. 126 00:13:02,230 --> 00:13:09,530 Which funds are suballocated to the MPO, but suffice to say that the MPO's selected projects 127 00:13:09,530 --> 00:13:15,700 just get inserted into our unified transportation program and the state carries them through 128 00:13:16,570 --> 00:13:23,870 towards completion. The quarterly review process was initiated a few years ago. It builds a 129 00:13:23,870 --> 00:13:28,630 structure into monitoring the progress of individual projects and the health of each district 130 00:13:28,630 --> 00:13:35,010 and the department's portfolio. And I'll talk a little bit more about that. All of these solutions 131 00:13:35,010 --> 00:13:45,270 are kind of tied into a modernization project called Text.Connect where we're taking all of 132 00:13:45,270 --> 00:13:52,670 our legacy systems. You may have heard of DCIS, Rois, if you've dealt with right away. We're 133 00:13:52,670 --> 00:13:59,370 taking all of the legacy systems that Text.us is and we're kind of rolling them all into this one 134 00:14:00,450 --> 00:14:06,970 program called Text.Connect. It's a slow process. They're rolling it out, module by module, 135 00:14:07,670 --> 00:14:15,230 the estimates, PS&E estimates, module just rolled out. And so the MPO does have access, at least 136 00:14:15,230 --> 00:14:21,630 to some of the information in Text.Connect, but eventually everything is going to be rolled into 137 00:14:21,630 --> 00:14:27,170 Text.Connect, and so we'll have a one-stop shop for managing the projects within our portfolio. 138 00:14:27,170 --> 00:14:28,370 And 139 00:14:30,550 --> 00:14:33,010 so where do these new processes fit? 140 00:14:35,490 --> 00:14:41,150 We integrate project development delivery in three areas, including plan, manage, and deliver. 141 00:14:41,830 --> 00:14:44,570 In plan, we look at performance-based planning. 142 00:14:45,210 --> 00:14:49,550 In manage, we use the quarterly review process and to deliver a project. 143 00:14:49,890 --> 00:14:53,350 We use the our project delivery in governance committee. 144 00:14:57,450 --> 00:14:58,450 Switch back over here. 145 00:14:58,450 --> 00:14:59,970 So this... 146 00:15:00,000 --> 00:15:04,980 This is just another way of looking at those planning and programming documents that I showed you earlier 147 00:15:04,980 --> 00:15:13,520 of the RTP, the statewide long-range plan, the UTP, the tip, and the two year-letting schedules. 148 00:15:14,060 --> 00:15:22,520 So what do we do? We have an estimate of funding and we have transportation strategic objectives that are given to us by our commission. 149 00:15:22,520 --> 00:15:30,660 We plan projects, we evaluate them against our strategic goals, and then we bring them 150 00:15:30,660 --> 00:15:31,560 through milestones. 151 00:15:31,820 --> 00:15:36,460 And they work through a funnel, they advance through a funnel to meet certain development milestones. 152 00:15:37,160 --> 00:15:43,020 And as each project meets that milestone, it's working towards the ready to construct and let. 153 00:15:52,360 --> 00:15:56,480 So in performance-based planning, we define clear key performance measures. 154 00:15:56,480 --> 00:16:00,480 We develop planning targets for each district and MPO. 155 00:16:00,920 --> 00:16:07,560 We align those projects with the strategic objectives and support compliance with state legislative requirements. 156 00:16:10,080 --> 00:16:17,460 This helps us to ensure that we are consistent with state and federal rules and regulations. 157 00:16:18,220 --> 00:16:27,060 We align our planning activities with the strategic objectives, which enables us to improve project performance and tracking. 158 00:16:27,060 --> 00:16:28,080 So 159 00:16:32,680 --> 00:16:35,480 again, here are your 12 categories of funding. 160 00:16:35,700 --> 00:16:41,140 So I talked to you earlier about the fact that all of the federal funding that comes from 161 00:16:41,140 --> 00:16:48,400 federal highway administration, DOT, and open, really Congress, as well as the state funding 162 00:16:48,400 --> 00:16:54,740 comes into the text.coffers, and it's suballocated to 12 categories of funding. 163 00:16:55,180 --> 00:17:00,340 Each category has a specific purpose, for instance, category one is maintenance, category 164 00:17:00,340 --> 00:17:06,320 five is congestion mitigation air quality, category nine is your transportation alternative 165 00:17:06,320 --> 00:17:12,920 set aside program. The state, as I mentioned earlier, has sub-allocated four categories 166 00:17:12,920 --> 00:17:21,440 of funding to MPOs for a local project selection, categories two, five, seven, and nine. And so 167 00:17:21,440 --> 00:17:27,940 the MPO also develops a process that's consistent with state and federal criteria in evaluating 168 00:17:27,940 --> 00:17:37,360 your projects and ultimately selecting them for funding. So we identify projects. We evaluate 169 00:17:37,360 --> 00:17:45,780 them against the performance criteria and then we put them through a sieve basically that 170 00:17:45,780 --> 00:17:52,540 is determining the right source of funding for the project. Category 6 is Bridge Funding. 171 00:17:55,720 --> 00:17:56,720 Category 172 00:17:56,720 --> 00:18:07,850 So here are some examples of potential key performance measures that we look at safety, connectivity, preservation, and congestion. 173 00:18:08,250 --> 00:18:17,490 We also consider, as I mentioned on the previous slide, we also consider the economy and the environment because those are federal requirements. 174 00:18:17,490 --> 00:18:23,990 And so, but this is basically our commissions strategic objectives. 175 00:18:25,750 --> 00:18:33,290 And so, the stakeholders in this performance-based planning process, all of these entities around the UTP, 176 00:18:33,930 --> 00:18:37,690 and in the development of the UTP provide input to that. 177 00:18:37,930 --> 00:18:43,310 We have a quarterly review process leadership committee over on your right. 178 00:18:43,310 --> 00:18:46,690 You'll see that it's made up of our executives. 179 00:18:48,550 --> 00:18:53,470 Text that executives and everything from the chief engineer to the executive director. 180 00:18:54,370 --> 00:18:59,130 They meet on a quarterly basis to review the health of our portfolio. 181 00:19:02,230 --> 00:19:08,750 And so on the quarterly review process districts program a mix of projects to meet their key performance measures. 182 00:19:09,130 --> 00:19:13,330 We manage that portfolio to maintain the right volume and mix of projects. 183 00:19:13,330 --> 00:19:20,090 And we have defined we have quarterly meetings to review the district's portfolio. 184 00:19:20,730 --> 00:19:26,630 This is a time probably if you have a federally funded project that we might be contacting you and saying, 185 00:19:26,970 --> 00:19:29,210 Hey, we have concerns about your project. 186 00:19:29,590 --> 00:19:33,710 We have concerns about its ability to make the letting schedule. 187 00:19:34,170 --> 00:19:40,650 And this is usually what's triggering those concerns because we've internally we've met. 188 00:19:40,650 --> 00:19:50,070 And as part of the internal quarterly review process, our TPND, James Koch brings us into a 189 00:19:50,070 --> 00:19:55,690 conference room and we spend the day with him going line-by-line project by project, giving 190 00:19:55,690 --> 00:20:02,630 him a status and you're going to see a little snapshot of what that portfolio looks like later 191 00:20:02,630 --> 00:20:10,350 on, but we go line-by-line project by project, status by status, activity by activity, talking 192 00:20:10,350 --> 00:20:15,970 about where we are, what the problems are, what needs to be done to correct it and making adjustments 193 00:20:15,970 --> 00:20:21,990 as needed. And he usually wants to do this because, next the following month, he's heading 194 00:20:21,990 --> 00:20:28,590 up to Austin to tell the Quarterly Review Leadership Committee, line by line project by project 195 00:20:28,590 --> 00:20:34,710 what's going on. And so there's a lot of accountability within the organization to deliver 196 00:20:34,710 --> 00:20:36,870 projects on time and on budget. 197 00:20:38,490 --> 00:20:42,030 So what does the quarterly review process look like? 198 00:20:42,310 --> 00:20:45,270 Again, I just have to use a district portfolio review. 199 00:20:45,590 --> 00:20:48,950 And then from there, there is a pre-alignment meeting in Austin 200 00:20:48,950 --> 00:20:51,870 where the district meets with the central planning team, 201 00:20:52,110 --> 00:20:54,710 which is composed of several divisions, 202 00:20:55,450 --> 00:20:57,550 including our transportation planning and programming, 203 00:20:58,070 --> 00:21:01,370 finance, environmental, right of way in our professional 204 00:21:01,370 --> 00:21:08,210 engineering procurement services divisions. They review the portfolio, assess progress against 205 00:21:08,210 --> 00:21:14,690 the letting schedule. We look at the resources needed. If we're having trouble delivering a project, 206 00:21:14,730 --> 00:21:19,490 do we need some additional support? We might need to engage PAPS, the professional engineering 207 00:21:19,490 --> 00:21:24,210 procurement services, to get the job done. We may need right away division to give us 208 00:21:24,910 --> 00:21:29,510 some additional resources. That's the time that we sit and talk with our divisions about what 209 00:21:29,510 --> 00:21:34,710 support we need. We assess the projects against the letting schedule and then 210 00:21:34,710 --> 00:21:40,630 prioritize those projects based on anticipated letting and then following 211 00:21:40,630 --> 00:21:45,690 that there is a leadership committee meets with the central planning team and 212 00:21:45,690 --> 00:21:51,210 usually the district engineer for each district and the central planning team 213 00:21:51,210 --> 00:21:59,410 along with the leadership committee which I showed you right 214 00:22:04,940 --> 00:22:11,080 They will sit down, meet, they will review a consolidated portfolio, get district input and identify 215 00:22:11,080 --> 00:22:12,900 and take appropriate actions. 216 00:22:16,340 --> 00:22:20,580 Part of the concern is, you've heard it if you don't use it, you'll lose it. 217 00:22:21,040 --> 00:22:27,980 That's very much true for federal funds, and you're going to hear later on when Anna, 218 00:22:28,100 --> 00:22:33,300 Dr. Ramirez, talks about the TASA program, the Transportation Alternative Settiside Program. 219 00:22:33,300 --> 00:22:42,560 So, probably focusing on that program, but the truth is all federal funds expire three years after they've been apportioned. 220 00:22:43,020 --> 00:22:51,560 And so, we're always on time on budget is very important because we never want to send federal dollars back to Washington. 221 00:22:52,240 --> 00:23:01,240 the state also has certain requirements and the legislature is looking at us every two years seeing how well we spent the money they gave us. 222 00:23:01,540 --> 00:23:04,740 We want to show them that we need more, not less. 223 00:23:05,060 --> 00:23:07,960 And so it's very incumbent upon us to spend the money. 224 00:23:08,620 --> 00:23:16,660 And so many times we do want to make adjustments in your project and you may feel that you want to kind of leave it there because it's very important and we agree, 225 00:23:16,660 --> 00:23:23,980 but you also need to look at, we're also very much concerned about spending the money in drawing that down 226 00:23:23,980 --> 00:23:28,020 and not sending anything back either to Austin or to Washington. 227 00:23:33,360 --> 00:23:34,620 That is obligation. 228 00:23:36,620 --> 00:23:45,540 So, and what I mean by that is when you get projects, you will develop that project and go through 229 00:23:45,540 --> 00:23:50,580 process of schematics, environmental clearance, right away utility adjustments, all of that. 230 00:23:51,160 --> 00:23:58,420 Right before we let a project to construction, the month before that we pull, if you have 231 00:23:58,420 --> 00:24:04,440 federal funds, the month before that we pull what's called the FPAA Federal Project Authorization 232 00:24:04,440 --> 00:24:05,020 and Agreement. 233 00:24:05,500 --> 00:24:10,280 That is a one-page agreement between the State and Federal Highway Administration that 234 00:24:10,280 --> 00:24:15,520 says we're authorized for you to begin spending and drawing down your federal fund. 235 00:24:15,520 --> 00:24:22,940 That when we get that FPA, the project is considered obligated, meaning the federal government 236 00:24:22,940 --> 00:24:26,000 has an obligation to deliver those funds to you. 237 00:24:26,440 --> 00:24:31,280 They can't be rescinded or they shouldn't be rescinded unless there were extraordinary circumstances. 238 00:24:32,260 --> 00:24:35,180 And so they have an obligation to you at that time. 239 00:24:35,900 --> 00:24:40,960 And so that's once you get your FPA, the project's kind of off the books. 240 00:24:41,540 --> 00:24:42,960 That's what we're trying to get to. 241 00:24:42,960 --> 00:24:46,180 We're trying to get to letting and do that. 242 00:24:46,220 --> 00:24:49,160 But there's a lot of things you have to do in order to do that. 243 00:24:49,500 --> 00:24:53,580 And so the four desired outcomes for managing the portfolio 244 00:24:54,500 --> 00:24:57,380 programming, we want the right mix and volume of projects 245 00:24:57,380 --> 00:25:02,280 at each stage to ensure that projects can move through that funnel. 246 00:25:02,720 --> 00:25:05,880 We looked at and we can meet our planning targets. 247 00:25:06,120 --> 00:25:07,780 We're using the funding that we have, 248 00:25:07,860 --> 00:25:09,700 and we're not leaving anything on the table. 249 00:25:10,740 --> 00:25:18,200 FYI, moving your project a year, although sometimes with with TASA, and others can be problematic, 250 00:25:18,600 --> 00:25:24,860 but we would rather move it out, it's easier to accelerate and pull it back in than it is to push it out. 251 00:25:25,180 --> 00:25:32,020 And so when we ask you to delay your project, it doesn't mean that we're reducing its priority. 252 00:25:32,480 --> 00:25:38,380 It's still very much a priority for us, but we also, I talked earlier about the four documents, 253 00:25:38,380 --> 00:25:40,900 the fact that they're fiscally constrained. 254 00:25:43,000 --> 00:25:46,220 We have caps. We have budget caps in all four 255 00:25:46,220 --> 00:25:53,640 of those documents, the RTP that's up the UTP and the two year letting schedule. If your 256 00:25:53,640 --> 00:25:58,300 project is continuing to sit in there and isn't going to make it, it's consuming capacity 257 00:25:58,300 --> 00:26:03,400 that needs to be used by something else. And so we do want to move it out so that we can move 258 00:26:03,400 --> 00:26:06,300 something into that we can fully expand the funds. 259 00:26:07,220 --> 00:26:08,760 Anyway, we look at milestones. 260 00:26:09,180 --> 00:26:11,280 We monitor progress of letting projects 261 00:26:11,280 --> 00:26:13,940 to ensure that they're on time and on budget. 262 00:26:14,320 --> 00:26:15,780 We've hit all the milestones. 263 00:26:17,240 --> 00:26:19,880 We look at resources that are needed at the district 264 00:26:19,880 --> 00:26:23,060 and division, and we coordinate now stakeholders here 265 00:26:23,060 --> 00:26:26,240 is not about the public involvement process. 266 00:26:26,680 --> 00:26:29,160 stakeholders here is about the stakeholders 267 00:26:29,160 --> 00:26:38,300 internal to textile and the MPO to deliver the portfolio of projects and so the QRP enables 268 00:26:38,300 --> 00:26:42,640 the achievement of the four outcomes through regular coordination with all stakeholders. 269 00:26:46,100 --> 00:26:54,640 Here is kind of the process. Everything again feeds into the UTP. The ones with the gold circle around 270 00:26:54,640 --> 00:27:02,340 are the central planning team, they're the ones that coordinate the portfolio and the funding 271 00:27:02,340 --> 00:27:09,520 for it. The MPOs, of course, coordinate through the districts to move projects as an 272 00:27:09,520 --> 00:27:15,980 necessary. Some of the risks, if we don't actually manage that portfolio, we don't have 273 00:27:15,980 --> 00:27:20,380 the right-sized funnel and we don't have enough projects in the hopper to fully utilize the 274 00:27:20,380 --> 00:27:27,240 funding. We don't have timely and accurate data and we're in a hurry trying to get everything 275 00:27:27,240 --> 00:27:32,240 at the last minute so they make us do it quarterly and not some other time and we of course 276 00:27:32,240 --> 00:27:37,160 want to deliver with integrity. We don't want to prioritize short-term issues of the day 277 00:27:37,160 --> 00:27:39,060 over the big picture portfolio. 278 00:27:41,260 --> 00:27:44,680 Project delivery in governance is a standardized workflow. 279 00:27:48,060 --> 00:27:48,620 It 280 00:27:48,620 --> 00:27:54,220 These proactive collaboration and individual projects are delivered on time and on budget 281 00:27:54,220 --> 00:27:57,100 to minimize delays and cost overruns. 282 00:27:57,220 --> 00:27:58,720 What do they say time as money? 283 00:27:59,060 --> 00:27:59,840 It really is. 284 00:27:59,940 --> 00:28:03,140 If your project is delayed, the costs go up. 285 00:28:04,220 --> 00:28:09,400 The four guiding principles of the project development delivery and governance process 286 00:28:09,400 --> 00:28:10,560 is early involvement. 287 00:28:11,200 --> 00:28:13,620 Get all the stakeholders together against stakeholders. 288 00:28:13,820 --> 00:28:18,260 When I'm talking about stakeholders here, I'm not talking about a public involvement 289 00:28:18,260 --> 00:28:23,780 process. I'm talking about an internal process of making sure that environmental and 290 00:28:23,780 --> 00:28:29,260 right-of-way are talking to each other because right-of-way can be parallel processing 291 00:28:29,260 --> 00:28:35,460 while environmental clearance is happening. And so what can we begin doing? We can begin 292 00:28:35,460 --> 00:28:41,360 mapping our right-of-way. We can begin getting our our appraisals together. We just can't mail them. 293 00:28:41,360 --> 00:28:59,080 So if we put those kind of back to back the time would be much greater and so we want to make sure that we're parallel processing where we can and we're collaborating with each other internally to make sure that everybody understands where we are. 294 00:28:59,340 --> 00:29:09,480 If through the environmental process they identify the need for an individual permit, we need to understand what kind of hit to the time to the time table that's going to happen. 295 00:29:09,480 --> 00:29:15,940 individual permits can take up to a year. Certain agreements such as railroad agreements 296 00:29:15,940 --> 00:29:24,780 can easily take up to a year, we typically say 18 months. And so that's a railroad permit 297 00:29:24,780 --> 00:29:30,340 will delay a project by 18 months. And so we need to understand that because then we don't 298 00:29:30,340 --> 00:29:35,800 want to go out and begin doing the appraisals too soon, either. It's about the right time, 299 00:29:35,800 --> 00:29:41,600 you know it's about delivering work at the right time. So we want to parallel process and we want 300 00:29:41,600 --> 00:29:47,140 to be visible, making sure that all of the stakeholders internal and here at the MPO and the 301 00:29:47,140 --> 00:29:52,280 local governments that we're talking about what the challenges are. We're open about that so that we 302 00:29:52,280 --> 00:29:56,200 and begin phasing the work appropriately. 303 00:29:56,200 --> 00:29:56,400 deadly. 304 00:30:00,000 --> 00:30:06,120 This is just a glimpse that who all has part in the project delivery process. 305 00:30:06,800 --> 00:30:12,160 And so some of the risks, if we advance right away activities and right away title, work 306 00:30:12,160 --> 00:30:15,080 and appraisals aren't carried out in parallel to environmental. 307 00:30:16,020 --> 00:30:21,480 The project could get delayed, accurate tracking of progress in milestones, lack of visibility, 308 00:30:23,160 --> 00:30:25,580 could complicate the timeline. 309 00:30:27,220 --> 00:30:29,700 We need to advance long lead time activities. 310 00:30:30,020 --> 00:30:32,960 We just talked about the individual permit and the railroad agreements. 311 00:30:33,380 --> 00:30:36,180 There are other things that may require some long lead times. 312 00:30:36,700 --> 00:30:40,440 We need to talk about and identify those early so that we can try to mitigate 313 00:30:40,440 --> 00:30:46,800 for them and also phase whatever other work we need that we can be doing. 314 00:30:47,000 --> 00:30:48,200 We need to be doing it. 315 00:30:48,200 --> 00:30:51,240 And then we need to just continue to collaborate. 316 00:30:51,980 --> 00:30:54,700 And so here I call this the long and winding road. 317 00:30:55,680 --> 00:30:59,920 This is kind of what it looks like to do a project at text time. 318 00:31:00,280 --> 00:31:03,560 From the beginning, we talked about the needs identification. 319 00:31:06,200 --> 00:31:09,760 So this would be the MPO data call for projects. 320 00:31:09,940 --> 00:31:13,940 And you know that there's a need in your local government. 321 00:31:13,940 --> 00:31:16,300 And so you've identified that need. 322 00:31:16,860 --> 00:31:19,000 At textile, we look for project authorization. 323 00:31:19,400 --> 00:31:21,800 Do we have authority to work on that project 324 00:31:21,800 --> 00:31:24,020 even if we don't have construction funding? 325 00:31:24,260 --> 00:31:26,080 We get something called developer authority. 326 00:31:26,680 --> 00:31:29,700 And that means we can start environmental engineering. 327 00:31:30,060 --> 00:31:32,160 Some of the other work that needs to be done 328 00:31:32,160 --> 00:31:36,040 in order to advance that project through project development, 329 00:31:36,520 --> 00:31:39,960 even before we have construction funding. 330 00:31:40,040 --> 00:31:42,380 We look at compliance with the planning documents. 331 00:31:42,380 --> 00:31:50,580 we talked about the long-range plan, the UTP, the STIP, and the two year-letting schedule, all of 332 00:31:50,580 --> 00:31:57,380 these documents need to be in sync with each other. Nine times out of 10, when we get a call from 333 00:31:57,380 --> 00:32:03,620 environmental, they're concerned because they can't get environmental clients because what we say, 334 00:32:03,840 --> 00:32:10,420 what we're trying to clear, is it consistent with the RTP in the STIP? And I'll give you a little, 335 00:32:11,220 --> 00:32:15,020 Let me give you an example real quick, and I'm going to throw them work under the bus. 336 00:32:17,940 --> 00:32:28,220 So, there was a project, and I will say which one it is, and we put the project in the RTP in this step, and everything was wonderful. 337 00:32:28,380 --> 00:32:31,060 We got a proof, said, great, good to go. 338 00:32:31,580 --> 00:32:34,800 Now, that project will just call it West time, or it wasn't. 339 00:32:34,800 --> 00:32:41,220 Um, we said that the original limits were the short little piece right over by the Galleria 340 00:32:41,220 --> 00:32:45,000 and then all the rest of it out to state highway six, right? 341 00:32:45,040 --> 00:32:49,320 So we had the small piece and we had this big long piece, but we were actually designing 342 00:32:49,320 --> 00:32:53,700 an implementing a widening on the whole facility, it's just different years. 343 00:32:55,000 --> 00:33:00,240 So it went through the environmental clearance process, it went through schematics, everything 344 00:33:00,240 --> 00:33:05,420 was fine, it's consistent with the, with the long range plan and the tip. Now when it 345 00:33:05,420 --> 00:33:12,500 gets to Mark to do PS&E, Mark is going to give it to consultants and very, very 346 00:33:12,500 --> 00:33:18,180 logically he says, why do I want to give one consultant this small little piece of 347 00:33:18,180 --> 00:33:23,960 here and give another consultant this big, huge piece over here? And he says, I'd 348 00:33:23,960 --> 00:33:31,080 to divide it in half and go from 610 to about 8 and then about 8 to highway 6 makes perfect 349 00:33:31,080 --> 00:33:36,800 sense, right? Very logical. He actually did the right thing and he took back into 350 00:33:36,800 --> 00:33:41,680 environmental and said, hey, if I change these limits, is that a problem? And they said, 351 00:33:41,820 --> 00:33:46,700 well, no, we cleared it from, you know, 610 all the way to highway 6, you're good to go. 352 00:33:46,760 --> 00:33:50,820 You can do anything as long as you deliver, you know, according to the environmental document. 353 00:33:51,600 --> 00:33:57,300 What he didn't do though is come back and tell us and planning what he had done. 354 00:33:58,080 --> 00:34:03,300 And so the project continues on through design and it gets towards letting and all of a sudden 355 00:34:03,300 --> 00:34:07,640 planning again is looking at the letting schedule and we said, whoa, whoa, what's this? 356 00:34:07,860 --> 00:34:10,080 What's going on? That's not what's approved. 357 00:34:10,940 --> 00:34:15,380 That's not going to give you an FPAA to obligate your project. 358 00:34:16,500 --> 00:34:18,460 You know, who changed the project limits? 359 00:34:18,460 --> 00:34:24,720 And everybody said, oh, well, so I'm so dead, oh, and work wanted to change it because of this perfectly good reason. 360 00:34:25,260 --> 00:34:33,200 But if he had just did back and told us, we could have made the change in the documents and he could have continued on with the process. 361 00:34:33,300 --> 00:34:36,220 That is the importance of concern. 362 00:34:36,540 --> 00:34:43,440 That is the importance of communicating and ensuring that we have compliance with the planning documents. 363 00:34:43,440 --> 00:34:50,580 we kind of make changes to your project, not only during the, sorry mark, not only during the 364 00:34:50,580 --> 00:34:55,100 contracting process and the MPO was done a really good job over the past few calls for 365 00:34:55,100 --> 00:35:01,950 projects publishing your applications. And so our contract specialist as Laura will talk about, 366 00:35:03,080 --> 00:35:07,740 look at the application and we developed your scopes using the budgets that you submitted and 367 00:35:07,740 --> 00:35:13,420 what was approved in the step because they pulled the step they want to ensure that we're compliant 368 00:35:13,420 --> 00:35:18,420 with what feds approved, but also if you want to make a change, many times we'll say, 369 00:35:18,640 --> 00:35:23,420 hey, you got to go back to the MPO, because we need a change here in this document. 370 00:35:28,790 --> 00:35:38,010 Okay, so a process, it depends. To do the MPO has a two meeting process for a tip amendment. 371 00:35:39,390 --> 00:35:45,670 The first month is a preview. The second month is approval. Now depending on the 372 00:35:45,670 --> 00:35:50,490 change that we're making it might require a step revision, meaning that it might require 373 00:35:50,490 --> 00:35:53,250 feds to have another look at that project. 374 00:35:53,910 --> 00:35:58,870 And if that happens, we revise the step on a quarterly basis. 375 00:35:58,870 --> 00:36:00,230 It's called a step revision. 376 00:36:00,770 --> 00:36:05,990 Now depending on when your project was approved by TPC, you may be three more months out. 377 00:36:08,220 --> 00:36:15,000 When a project goes through a step revision is a 30-day process for a 30-day public involvement 378 00:36:15,000 --> 00:36:22,260 process, and then once the 30 days in, we then transmit that to federal highway administration 379 00:36:22,260 --> 00:36:30,920 and our experience is feds take 60 to 90 days to approve a steep revision. So if we need 380 00:36:30,920 --> 00:36:37,960 an amendment and a steep revision is required, then we're, worst case, probably six months out. 381 00:36:38,560 --> 00:36:55,280 And so, that's again, that early collaborative activity, why it's so very important, and why many times we're pushing local governments to say we really want to move this project because we understand the time it's going to take even to move it. 382 00:36:55,460 --> 00:37:06,680 And if we don't move it, you run the risk of not being compliant with the planning documents and you can't get environmental approval and without environmental approval, you can't begin right away. 383 00:37:06,680 --> 00:37:19,440 And so there's this domino effect and so I just, you know, again, moving your project is not a huge problem unless you're trying to meet a milestone. 384 00:37:21,740 --> 00:37:34,280 And so we look at study requirements. We'll do agreements. We'll identify funding. This again is all in the planning process and so if you look over here at this chart, it's about 12 inches. 385 00:37:34,280 --> 00:37:40,520 The planning process is about 12 inches of that long work flow, 386 00:37:43,300 --> 00:37:45,120 and so now here we're moving 387 00:37:45,120 --> 00:37:50,220 into preliminary engineering. We hold the design concept conference. This is a formal 388 00:37:50,220 --> 00:37:56,440 form that we use to kind of identify the activities that are going to be required to deliver 389 00:37:56,440 --> 00:38:02,360 your project. And so we formalize that with our team. Get everybody in the same room. 390 00:38:02,360 --> 00:38:03,960 you'll be in the room at that time, 391 00:38:04,160 --> 00:38:06,260 where we can talk about your project. 392 00:38:07,060 --> 00:38:09,020 We'll do the data collection that's needed, 393 00:38:09,240 --> 00:38:11,240 begin schematic development and approval. 394 00:38:11,980 --> 00:38:15,780 We'll be looking at environmental, do we need right away, 395 00:38:16,040 --> 00:38:18,380 utility adjustments, and interstate access, 396 00:38:18,440 --> 00:38:19,800 justification request. 397 00:38:20,700 --> 00:38:26,380 Now, here for project requires a federal decision. 398 00:38:26,940 --> 00:38:29,840 It has got to be in the tip and long range plan. 399 00:38:29,840 --> 00:38:36,850 And so even we had a project once with the beaver, Becky's. 400 00:38:37,980 --> 00:38:44,120 Becky's was going to put the Katie Road, Becky's, maybe you guys know it. 401 00:38:45,320 --> 00:38:49,820 It was a 100% locally funded project, not regionally significant. 402 00:38:50,480 --> 00:38:54,180 So the determination was, we don't need to put it in the step. 403 00:38:54,900 --> 00:38:57,380 It doesn't meet any other requirements to begin there. 404 00:38:58,080 --> 00:39:08,740 Unfortunately, we found out later on, they wanted to move the ramp, and when you move the ramp, it required an IJR, an interstate access justification request. 405 00:39:09,260 --> 00:39:20,780 And when that happened, we ended up having to put it in the step in the project was delayed, and Mr. Beaver, Mr. Applin, he actually goes by the name Beaver, was not happy. 406 00:39:20,780 --> 00:39:27,180 And so, if you need a federal decision, you need to make sure that your project is in the 407 00:39:27,180 --> 00:39:30,500 step, and it's in the right timeframe in the step. 408 00:39:31,840 --> 00:39:35,740 We do public involvement and then in some projects we do value engineering. 409 00:39:36,080 --> 00:39:42,420 Value engineering is a federal requirement when the project is $50 million or more for a 410 00:39:42,420 --> 00:39:46,820 roadway project and $40 million or more for a bridge project. 411 00:39:46,820 --> 00:39:55,100 If you think your project is going to be somewhere near that, we all know that the early schematic 412 00:39:55,100 --> 00:39:59,380 level budgets, the cost always goes up on a project. 413 00:39:59,700 --> 00:40:05,600 And so if you're thinking you're going to be hitting that kind of budget, then you probably 414 00:40:05,600 --> 00:40:11,300 need to go ahead and ask for value engineering early on because it is a process and it does 415 00:40:11,300 --> 00:40:12,260 take time. 416 00:40:14,380 --> 00:40:21,100 Now, we're getting into Mark's area. Mark does the PS&E, the Plan Specifications and Estimates. 417 00:40:21,100 --> 00:40:22,800 These are your construction documents. 418 00:40:23,620 --> 00:40:27,580 What Mark is looking at is finalizing the alignment in the profiles. 419 00:40:28,240 --> 00:40:31,360 He's doing detailed design in the meantime, environmental. 420 00:40:32,460 --> 00:40:37,580 The engineers may be working on obtaining the IJR. 421 00:40:37,580 --> 00:40:42,840 Our right away is still furiously purchasing right away, we're adjusting those utilities and we're 422 00:40:42,840 --> 00:40:47,880 praying that we get railroad clearance because we have an imminent letting date. 423 00:40:48,540 --> 00:40:54,340 And so Mark is working very hard to put together the PS&E assembly and design review. 424 00:40:55,420 --> 00:41:03,480 Your design is due to the state, your PS&E is due to the state five months prior to letting. 425 00:41:04,640 --> 00:41:11,540 And so whatever your wet date is, back it up five months, we need a hundred percent perfectly 426 00:41:11,540 --> 00:41:20,560 reviewed text not approved plans. Five months prior to the letting date. And so work backwards 427 00:41:20,560 --> 00:41:26,540 from that schedule, build in that five months. Mark will probably talk to you about this, but 428 00:41:26,540 --> 00:41:30,260 but the state also likes to see 30, 60, 90 reviews. 429 00:41:30,640 --> 00:41:34,220 Until you need to make some build some time in for that. 430 00:41:40,150 --> 00:41:43,710 We, so if the state is letting your project, 431 00:41:44,170 --> 00:41:47,070 the five month review, we get your 100% plans. 432 00:41:47,510 --> 00:41:51,570 We review them, we certify them, we notify Austin. 433 00:41:52,430 --> 00:41:55,170 And there's kind of a chain reaction of activities 434 00:41:55,170 --> 00:41:58,410 that are going on during that time. 435 00:41:58,410 --> 00:42:07,150 Our finance division, 30 days prior to letting, goes to federal highway administration and pulls the FPA. 436 00:42:07,790 --> 00:42:14,970 If we don't get the FPA for some reason, like the project's not approved in the STIP, something like that, then the letting is pulled. 437 00:42:15,470 --> 00:42:16,830 It's automatically delayed. 438 00:42:17,730 --> 00:42:25,410 If we can't get the FPA shortly before that, we get that. 439 00:42:25,410 --> 00:42:27,350 of the financial clearances are done. 440 00:42:27,690 --> 00:42:32,090 We're going to be asking you for your final payment in there. 441 00:42:33,150 --> 00:42:35,210 And then the project is advertised. 442 00:42:35,350 --> 00:42:37,170 And let me keep going here. 443 00:42:37,850 --> 00:42:39,670 The project, so we get the letter of authority. 444 00:42:39,950 --> 00:42:41,190 That's the state letter of authority 445 00:42:41,190 --> 00:42:43,130 to make sure if it's state funds on there 446 00:42:43,130 --> 00:42:44,710 that those state funds are certified 447 00:42:44,710 --> 00:42:46,390 and that we've got them obligated, 448 00:42:46,390 --> 00:42:48,770 or we go to Feds and get the FPA. 449 00:42:50,030 --> 00:42:52,090 We advertise the project. 450 00:42:52,090 --> 00:42:58,730 Now, I'll text that recently in the last year or so, I think, has begun putting out 451 00:42:58,730 --> 00:43:04,810 mark as at a 50% for contractors to look at of our plans. 452 00:43:06,830 --> 00:43:15,190 On the big projects, we have started kind of publishing our plans at about 50% letting the contractors 453 00:43:15,190 --> 00:43:20,670 take a look at it. We hope that there's kind of a mutually beneficial activity there. 454 00:43:20,670 --> 00:43:25,410 maybe if they see some fatal flaws they can talk to us and if not it gives them a little glimpse. 455 00:43:25,590 --> 00:43:32,010 I think their complaint was that we give them less than 30 days to put a bit together but yet it took us 456 00:43:32,010 --> 00:43:37,170 a year or two to put the plans all the plans together depending on the size of the project. 457 00:43:37,530 --> 00:43:43,550 And so we've started giving them a little glimpse at that hopefully to facilitate a better bid during 458 00:43:43,550 --> 00:43:50,450 this bidding process. And so we advertise the project and 21 days later the bids are due. 459 00:43:50,450 --> 00:43:52,790 But it used to be in Austin, there was this room, 460 00:43:53,230 --> 00:43:56,510 and all of the bids would come in and it a certain time. 461 00:43:57,130 --> 00:43:58,610 All of the bids were opened, and of course, 462 00:43:58,750 --> 00:43:59,650 the low-bid wins. 463 00:43:59,690 --> 00:44:01,210 Now it's pretty much all electronic, 464 00:44:01,990 --> 00:44:03,750 but it's the same principle. 465 00:44:04,550 --> 00:44:06,590 And then the bids are reviewed. 466 00:44:07,350 --> 00:44:12,390 If they're over or above, how much percent? 467 00:44:16,740 --> 00:44:19,260 10%, 10%, if they're over or above 10%, 468 00:44:19,260 --> 00:44:22,680 maybe 15%, then the district is required 469 00:44:22,680 --> 00:44:29,120 to review the project and write an explanation of why the discrepancy, the difference. 470 00:44:30,640 --> 00:44:38,580 And so we'll go through that process and then all of the projects are sent to the Texas Transportation Commission, 471 00:44:39,600 --> 00:44:43,420 which is our governing body, and they award the project. 472 00:44:52,120 --> 00:44:58,300 So during construction, we issue a notice to proceed to the contractor to a pre-construction conference, 473 00:44:58,300 --> 00:44:59,960 are area off. 474 00:45:00,000 --> 00:45:12,160 campuses, supervise and inspect the projects. We do contracted administration as needed. Quality assurance and testing, any change orders or process at that time. 475 00:45:12,660 --> 00:45:20,820 And then there is project acceptance and closed out. Probably the next time you'll hear from us. If we've left your project, is it closed out? 476 00:45:20,820 --> 00:45:24,120 I was just telling David Hortlow before this meeting. 477 00:45:24,700 --> 00:45:29,800 Our finance division, I talked about, we've kind of began modernizing. 478 00:45:30,560 --> 00:45:36,880 We about a couple of years ago, Austin also rolled out people's soft. 479 00:45:37,180 --> 00:45:43,080 And so all of our financial and other HR stuff is done through people's soft. 480 00:45:43,720 --> 00:45:47,000 Finance has automated the collection's process. 481 00:45:47,660 --> 00:45:50,700 And so what's really important for you to know about that? 482 00:45:50,700 --> 00:45:57,980 is that in article whatever article 14 or something like that of your contract, there is a 483 00:45:57,980 --> 00:46:04,900 contact name in there that says, for correspondence, who do you want to contact? We kind of default 484 00:46:04,900 --> 00:46:11,480 to the mayor. It's not a person, it's a title, and we usually default to the mayor, but in some 485 00:46:11,480 --> 00:46:16,900 larger local governments like the city of Houston sending something to the mayor instead of 486 00:46:16,900 --> 00:46:24,780 and that can actually deal with the collection letter is probably not the best idea. 487 00:46:25,120 --> 00:46:29,120 And so be sure, when you're doing your contract at the beginning of the project, 488 00:46:29,180 --> 00:46:35,860 determine who do we want notices to go to because our finance division now has an automated 489 00:46:35,860 --> 00:46:39,140 system for once project close out has happened. 490 00:46:39,580 --> 00:46:46,000 If you owe the state money, they will follow the state law and there's a highly prescribed process 491 00:46:46,000 --> 00:46:52,080 for collections. They'll send you a letter and tell you UOS money in within 30 days. 30 492 00:46:52,080 --> 00:46:57,140 days later, you'll get another letter from us and you'll get a final letter from us and then 493 00:46:57,140 --> 00:47:04,340 they will send it to the Attorney General for Collection. And that is now automated. Excuse 494 00:47:04,340 --> 00:47:07,960 me, it's not something that the district does anymore. 495 00:47:11,740 --> 00:47:14,500 And so with that, you should now understand 496 00:47:14,500 --> 00:47:20,920 many steps and interdependencies to successfully develop and construct projects. We go from project 497 00:47:20,920 --> 00:47:26,900 initiation and planning. We look at the planning and programming documents. There's a funnel that 498 00:47:26,900 --> 00:47:34,660 these projects go through. We do preliminary engineering, PS&E, letting and construction. Define 499 00:47:34,660 --> 00:47:40,080 how projects are created and move through a funnel. We talked about the 12 categories of funding 500 00:47:40,080 --> 00:47:52,560 in the funnel how they meet our strategic objectives and then we move them through a funnel to meet certain milestones trying to progress them through to construction. 501 00:47:54,600 --> 00:48:03,020 Here's the funding categories, categories 2, 5, 7 and 9 are suballocated to the MPO for 502 00:48:03,020 --> 00:48:09,640 a local project decision, included in that is the selection of those projects and how 503 00:48:09,640 --> 00:48:15,860 that occurs, other than that, the state has its own process for selecting projects. 504 00:48:18,300 --> 00:48:22,020 And then you should understand that we have a quarterly review process. 505 00:48:22,020 --> 00:48:50,640 The district looks at its portfolio and then certain district staff meet with the key team members and Austin to review the portfolio, assess progress against the letting schedule and to prioritize projects and then ultimately we have a consolidated portfolio that goes to our leadership committee made up of our executive leadership and they are trying to monitor the overall health of the project. 506 00:48:50,640 --> 00:48:57,720 to ensure that we let projects on time on budget and that we utilize the funds that we have available. 507 00:48:58,240 --> 00:49:00,980 We don't want to leave any funds on the table. 508 00:49:03,500 --> 00:49:06,880 You should now understand that we have a project delivery in governance process 509 00:49:07,300 --> 00:49:12,660 that involves that includes early involvement, collaboration, parallel processing, 510 00:49:13,280 --> 00:49:17,580 where we can, as I said, while you're waiting for you can't buy right away 511 00:49:17,580 --> 00:49:20,340 until you get environmental clearance with a few exceptions. 512 00:49:20,340 --> 00:49:27,380 But you can be doing some things in right of way like you're mapping in your appraisals while you're waiting on environmental. 513 00:49:28,040 --> 00:49:36,160 You want to be coordinating with environmental through that process because if there are certain things that are going to have long lead times, maybe you don't want to do that work. 514 00:49:36,680 --> 00:49:42,580 And so you'll want to continue to parallel process where you can and be visible. 515 00:49:42,580 --> 00:49:48,420 be open. If there's a problem, let's talk about it. Let's make some adjustments to that portfolio. 516 00:49:48,760 --> 00:49:54,700 It's not that your project is an important. It is. Your project is in this portfolio too. 517 00:49:54,780 --> 00:50:00,880 As I started out by saying, we've suballocated those funds, but the state still has responsibility for it. 518 00:50:00,880 --> 00:50:07,700 If your project is allocated, certain federal funds, it's in that portfolio and we want to deliver it. 519 00:50:07,700 --> 00:50:19,060 Every time we move a project even one month, we have to fill out a form and make a request and we have to specifically say why we're moving that project. 520 00:50:20,920 --> 00:50:24,640 Every time we move a project, our district engineer gets a ding. 521 00:50:25,260 --> 00:50:32,780 Okay, the district's report card, basically the district's performance report card is the district engineer's performance plan. 522 00:50:33,240 --> 00:50:37,680 Okay, district engineer, you know, will it rolls downhill, right? 523 00:50:37,700 --> 00:50:39,640 He wants to know, why are we moving projects? 524 00:50:39,820 --> 00:50:42,940 Why can't we let these projects, why aren't we scheduling them? 525 00:50:43,000 --> 00:50:47,720 You know, in a reasonable amount of time, not an optimistic amount of time. 526 00:50:47,740 --> 00:50:54,860 And so it's very important, as you look at, as you help us, with your project to look at the health of our portfolio, 527 00:50:55,380 --> 00:51:00,140 being realistic and not optimistic about when we can deliver that project. 528 00:51:02,260 --> 00:51:05,840 any questions? Yes sir. 529 00:51:12,230 --> 00:51:13,150 Say that again. 530 00:51:17,640 --> 00:51:21,760 Is there an approved? So the answer is yes. 531 00:51:22,060 --> 00:51:29,880 There is an approved bitter list for contractors. They get their pre-approved by the state or pre-qualified by the state. 532 00:51:29,880 --> 00:51:30,340 Right. 533 00:51:34,210 --> 00:51:36,850 Ooh, design build is a whole, another, yeah. 534 00:51:38,210 --> 00:51:40,850 Yeah, it's a, it's a, it's a whole mother, uh, Bologax. 535 00:51:45,070 --> 00:51:47,710 Any other questions about the process as a whole? 536 00:51:47,870 --> 00:51:55,270 You're going to be hearing, uh, from subject matter experts, uh, talking about the contracting process and what you can expect. 537 00:51:55,890 --> 00:51:57,650 Uh, you're going to get a glimpse into that portfolio. 538 00:51:57,990 --> 00:52:04,650 You're going to hear from our, uh, our environmental supervisor about, uh, what you can expect for environmental claims. 539 00:52:04,650 --> 00:52:10,490 you're going to be talking to Mark who not only does the PSNE, but he also does the local 540 00:52:10,490 --> 00:52:15,290 government coordination. So if you have a federal project that's federally funded, 541 00:52:15,770 --> 00:52:21,290 you're going to have to coordinate with him and his group. And then you're going to hear from 542 00:52:21,290 --> 00:52:21,990 right of way. 543 00:52:24,540 --> 00:52:25,320 Thank you guys. 544 00:52:33,300 --> 00:52:38,020 Thanks Katherine for that overview. It's now time in the schedule 545 00:52:38,020 --> 00:52:44,640 for a brief break. We have a 10 minute break before we come back and talk about the local 546 00:52:44,640 --> 00:52:46,640 government contracting and federal obligation. 547 00:52:47,600 --> 00:52:50,040 All right. It's been about 10 minutes. 548 00:52:50,580 --> 00:53:00,460 Breaks just over. Up next, we have our presentation by Lord Gimboa from text.com to discuss 549 00:53:00,460 --> 00:53:04,080 contracting and local government projects. 550 00:53:04,080 --> 00:53:04,800 So 551 00:53:11,160 --> 00:53:15,460 I'm Laura Gambo, I'll work with Catherine, I work in the planning section at text. 552 00:53:17,220 --> 00:53:21,780 And the person that, after you get the funds, if you need an advanced funding agreement, 553 00:53:22,160 --> 00:53:24,300 the person that you come to next. 554 00:53:25,620 --> 00:53:32,000 And so that's, I'm here to talk about kind of that process a bit, and come over here 555 00:53:32,000 --> 00:53:32,460 a little more. 556 00:53:34,160 --> 00:53:36,000 So this is just kind of a brief overview. 557 00:53:36,000 --> 00:53:39,820 How many of y'all have been through the AFA process before? 558 00:53:41,120 --> 00:53:42,320 All right, quite a few. 559 00:53:46,990 --> 00:53:47,470 There we go. 560 00:53:48,290 --> 00:53:50,070 Okay, you are already the project. 561 00:53:50,330 --> 00:53:51,190 What's next? 562 00:53:52,290 --> 00:53:57,570 So, we need a funding agreement if at least one phase of the project development is federally 563 00:53:57,570 --> 00:54:03,010 or state funded, managed by the local government being reimbursed by text 564 00:54:03,010 --> 00:54:06,490 or locally funded project on the state system. 565 00:54:09,080 --> 00:54:15,080 These are the various different types of projects that you may have had funded and that you do need a funding agreement for. 566 00:54:18,310 --> 00:54:22,610 And this just kind of gets into why we're even involved. 567 00:54:23,070 --> 00:54:26,950 You know, say there's no state money at all on it. It's not on the state system. 568 00:54:28,270 --> 00:54:33,450 Text that has through various different laws and statutes. 569 00:54:33,790 --> 00:54:36,170 We're sort of the governor of the federal money. 570 00:54:36,170 --> 00:54:41,250 And we'll sort of partner in that process. 571 00:54:43,210 --> 00:54:45,770 So, the event, funding agreement, is negotiated 572 00:54:45,770 --> 00:54:47,890 contract between textile and local government. 573 00:54:48,390 --> 00:54:51,490 It defines the scope of the project location and the budget. 574 00:54:52,390 --> 00:54:54,330 And who's going to be doing the various responsibilities 575 00:54:54,910 --> 00:54:57,150 and the state oversight fee? 576 00:54:57,270 --> 00:54:59,830 If we have a full reviewing your plans, 577 00:55:00,210 --> 00:55:02,890 and we need to recoup a cost for that, that sort of thing. 578 00:55:06,440 --> 00:55:06,620 No. 579 00:55:13,330 --> 00:55:18,290 I know a lot of people are wondering why we charge you on oversight fee and that's because 580 00:55:18,290 --> 00:55:26,070 state law says that it's against the law for us to spend state resources off system. 581 00:55:26,430 --> 00:55:30,510 Now state resources are not only our money, in other words we can't take our money and 582 00:55:30,510 --> 00:55:36,250 go improve your roads, but we also can't spend our time because our time is paid for by 583 00:55:36,250 --> 00:55:38,430 the state to therefore wear a state resource. 584 00:55:38,430 --> 00:55:49,670 If you're using federal funds, we have to oversee your project, but because it's off-system of the state highway system, we have to charge you for our time. 585 00:55:50,090 --> 00:56:00,570 The good news for you is that we can charge 80% of our most federal funds or 80-20, right? 80% federal, 20% your dollars. 586 00:56:00,570 --> 00:56:07,590 the good news for you is that we can charge 80% of our time to the federal government as well. 587 00:56:07,730 --> 00:56:11,690 So you're only paying $0.20 on the dollar for our expertise. 588 00:56:15,860 --> 00:56:21,560 I'm glad you address that, because we do frequently get people who have never been through the AFA process, 589 00:56:21,720 --> 00:56:26,120 and we send them the first draft, and they make the section at the bottom, and they're like, 590 00:56:26,220 --> 00:56:30,120 what are we indirect and direct costs? That's not part of what we've budgeted for construction, 591 00:56:30,120 --> 00:56:37,200 And that's where we recruit our costs for oversight, or if we're letting the project, it's all there on there. 592 00:56:37,420 --> 00:56:42,960 And those are costs of the projects that you need to think about when you submit your project. 593 00:56:43,140 --> 00:56:45,260 And you say, this is how much I think it's going to cost. 594 00:56:45,440 --> 00:56:47,200 You need to figure those in there. 595 00:56:50,140 --> 00:56:55,020 This kind of is a lot of lines and boxes, but he simply tells you the process. 596 00:56:55,800 --> 00:56:59,640 So to break it down, essentially, you're going to order the project. 597 00:57:00,980 --> 00:57:07,640 We watch the tip actions, so frequently I will contact you and say, okay, we're going to start 598 00:57:07,640 --> 00:57:13,660 the graph. Let's make sure of the details. If there's a change in a project, or if you haven't 599 00:57:13,660 --> 00:57:19,640 been contacted, and you believe we need an AFA, then I need you to contact me. And my contact 600 00:57:19,640 --> 00:57:25,380 information will be at the end of this presentation. But that's how we kind of initiate the process 601 00:57:25,380 --> 00:57:27,140 is one of those two ways. 602 00:57:27,860 --> 00:57:31,900 So once that happens, we draft, in our office, 603 00:57:32,060 --> 00:57:33,760 we'll draft the AFA. 604 00:57:34,020 --> 00:57:35,400 We send it to the local government. 605 00:57:35,920 --> 00:57:39,120 The local government at this point will view it. 606 00:57:39,300 --> 00:57:41,360 It gives us combines other comments 607 00:57:41,360 --> 00:57:43,200 and sends it back to us. 608 00:57:43,500 --> 00:57:46,040 Then we go back and forth to we agree on that draft. 609 00:57:46,700 --> 00:57:49,520 At that point, once I have an agreed upon draft, 610 00:57:50,140 --> 00:57:51,940 we send it for division reviews. 611 00:57:52,180 --> 00:57:54,680 So if it involves building a bridge, 612 00:57:54,680 --> 00:57:59,640 we're going to send it to our bridge division and our design division and maybe even traffic. 613 00:58:00,380 --> 00:58:06,360 We, those different divisions in Austin send us back in a review conference they may have. 614 00:58:06,780 --> 00:58:07,920 We address those. 615 00:58:08,380 --> 00:58:11,900 Then it goes to contract services in Austin. 616 00:58:13,160 --> 00:58:15,400 They do a complete review of the whole thing. 617 00:58:15,520 --> 00:58:19,960 They make sure it matches the still everything else. 618 00:58:20,440 --> 00:58:21,640 They send us back comments. 619 00:58:21,640 --> 00:58:32,580 If the comments are very volumeless or there's something that was really missed, then we'll come back to the local government and say, we need you to re-erate review and approve. 620 00:58:32,900 --> 00:58:36,420 So the process can become somewhat cyclical for all. 621 00:58:37,060 --> 00:58:47,260 If contract services doesn't have any major comments, then we usually just make those. They're usually kind of minor, like we want you to load this differently. 622 00:58:47,260 --> 00:58:50,900 this doesn't specifically match the scope description of the project. 623 00:58:52,220 --> 00:58:55,960 So if with the minor changes we don't come back to y'all with those usually, 624 00:58:56,280 --> 00:59:00,280 what they do is, once we're having a copy that's approved for partial execution, 625 00:59:00,820 --> 00:59:04,840 we'll send it to y'all for partial and they'll say, and we change this thing here, 626 00:59:05,060 --> 00:59:10,520 this there. It just speed this in process up a little more than going back and forth, 627 00:59:10,600 --> 00:59:15,440 because especially smaller local governments, if we send it back to you for some 628 00:59:16,120 --> 00:59:20,340 little tiny change that doesn't matter to anybody. A lot of small local 629 00:59:20,340 --> 00:59:23,260 governments, they'll be like, oh, I need my attorney to look the whole thing 630 00:59:23,260 --> 00:59:28,060 over again. If your attorney's being paid by the hour, he's going to hold on to it 631 00:59:28,060 --> 00:59:32,400 for a while and come back with some of it. So it's just that if it's not major, that's 632 00:59:32,400 --> 00:59:38,960 how we address those. So once we get a copy that's ready to be signed by the local 633 00:59:38,960 --> 00:59:43,800 we send that to you. And I'm going to talk about vacuum sign here in a second, but 634 00:59:43,800 --> 00:59:49,280 We really prefer, and it speeds the process up greatly, if I will get on the road with 635 00:59:49,840 --> 00:59:50,380 DocuSign. 636 00:59:50,860 --> 00:59:57,160 We have several open governments that do it in, from the time we send them a signable copy of the 637 00:59:57,160 --> 00:59:59,980 AFA to it being signed up. 638 01:00:00,000 --> 01:00:09,420 In Austin, can be 48 hours versus hard copy wet signatures that draws the whole process out about two weeks. 639 01:00:10,220 --> 01:00:13,060 That's how quick that speeds it up. 640 01:00:14,650 --> 01:00:22,750 Finally, a last sign that you send it back to us, we send it to Austin, our county and contract services signs that they send it back to us. 641 01:00:23,390 --> 01:00:31,410 Well, I'm back and forth, and if that person, we soon had a very executed copy, and if 642 01:00:31,410 --> 01:00:34,210 their funds do we send you a request for payment. 643 01:00:34,870 --> 01:00:39,290 That's that initial amount that's at the bottom of the budget, on the attachment. 644 01:00:40,930 --> 01:00:41,990 And it's the request for payment. 645 01:00:42,070 --> 01:00:46,910 Once you're all sent us payment, then we can proceed with a project. 646 01:00:46,910 --> 01:00:56,970 And tell that payments received, we can't have a kickoff meeting, no work can be done on the project that hasn't been authorized. 647 01:00:57,650 --> 01:01:00,710 We can't get the FPAA until we have payment. 648 01:01:06,920 --> 01:01:09,780 Okay, that goes into the FPAA that I just talked about. 649 01:01:12,960 --> 01:01:18,160 And we give y'all instructions when we send that, you know, this is how you send payment, this is how much it's due. 650 01:01:20,770 --> 01:01:22,010 Okay, thank you, sorry. 651 01:01:22,690 --> 01:01:25,670 It is so easy a caveman can do it. 652 01:01:27,840 --> 01:01:32,360 Okay, this is just going to send to Digital Signature what DocuSign is. 653 01:01:33,340 --> 01:01:35,580 The last house I bought was through DocuSign. 654 01:01:36,180 --> 01:01:39,700 I mean, it's used for everything, it's legal, it's binding. 655 01:01:41,400 --> 01:01:43,800 It's a very secure way of sending documents. 656 01:01:49,260 --> 01:01:51,320 It is so much faster. 657 01:01:51,760 --> 01:01:56,240 And TechSide is getting more and more into this and we're starting to 658 01:01:56,240 --> 01:02:00,720 use it for totally replace even storing paper documents. 659 01:02:01,540 --> 01:02:09,480 the digital copy initiates and is kept through this process and it's we can map it 660 01:02:09,480 --> 01:02:14,720 too. We get some local governments that get concerned because someone approves what we 661 01:02:14,720 --> 01:02:20,440 send, defer the sign or signs in it. And you can write it through all those people. If you 662 01:02:20,440 --> 01:02:25,380 tell me who you want to approve it, I'll just line them up in Dockey's sign and this person 663 01:02:25,380 --> 01:02:30,360 has to approve and then it'll write it to the next person to the next person and the next 664 01:02:30,360 --> 01:02:37,140 person. And the whole thing, you can do it from an iPhone, from an iPad, from a desktop computer. 665 01:02:37,840 --> 01:02:39,680 It is so quick and easy. 666 01:02:43,420 --> 01:02:46,660 All digital signatures legal and Texas, I get this from local 667 01:02:46,660 --> 01:02:52,440 governments a lot. They're like, were you not sure about that? Yes, they are legal. And here's 668 01:02:52,440 --> 01:02:57,120 all the codes. You can take a picture of that and take it back to your local government if they don't 669 01:02:57,120 --> 01:02:58,020 So 670 01:03:00,670 --> 01:03:09,210 you do not need to purchase any software to use like you sign touch that purchase the right to use it in this manner 671 01:03:09,210 --> 01:03:15,030 And we send it to you all and all you do is open it. It opens it in the DocuSign format 672 01:03:15,030 --> 01:03:18,970 I think there's an app you can download for your iPhone or iPad 673 01:03:18,970 --> 01:03:25,990 But we said a little easier to use but you don't need to buy your local government don't have to go out and buy all license or anything 674 01:03:28,050 --> 01:03:32,530 And this is just kind of basically what you'll get when it's sent to you in DocuSign. 675 01:03:32,630 --> 01:03:33,610 You get something like this. 676 01:03:33,710 --> 01:03:36,110 It says, hey, you need to take some action on this. 677 01:03:36,190 --> 01:03:39,530 Whether it's the review action or the signature action. 678 01:03:43,400 --> 01:03:46,620 And a guide you through the process tells you where to sign. 679 01:03:46,920 --> 01:03:49,440 You do your little chicken scrap signature with your finger, 680 01:03:49,720 --> 01:03:53,400 but resembles nothing but a looks like a doctor signing a prescription. 681 01:03:56,000 --> 01:03:58,560 And we hit finish and it wraps it back to us. 682 01:03:58,560 --> 01:04:00,460 It tells us you have signed it. 683 01:04:00,460 --> 01:04:04,180 It's ready to go on to our next person that signs it. 684 01:04:07,500 --> 01:04:10,520 And DocuSign also scores a copy of that. 685 01:04:10,780 --> 01:04:13,180 And you can access that copy at any point. 686 01:04:14,980 --> 01:04:16,680 And that's my contact information. 687 01:04:18,000 --> 01:04:20,120 If you have, if you need a lawyer for it, 688 01:04:20,200 --> 01:04:22,680 have problems with one need and a amendment, 689 01:04:23,200 --> 01:04:24,960 feel free to contact me. 690 01:04:25,460 --> 01:04:25,940 Any questions? 691 01:04:30,200 --> 01:04:30,360 No? 692 01:04:30,860 --> 01:04:32,460 I answered all your questions, point. 693 01:04:32,780 --> 01:04:33,260 Yes. 694 01:04:38,990 --> 01:04:43,390 Yes, the loss is a new type of modern agreement, yes. 695 01:04:44,110 --> 01:04:47,230 Any other other kinds where I use the term AFA, 696 01:04:48,210 --> 01:04:53,050 but there's non-federal AFAs, there's ones that are state-only money, 697 01:04:53,230 --> 01:04:55,310 there's donation agreements, volunteer agreements, 698 01:04:55,410 --> 01:04:57,050 and the loss is the new one. 699 01:04:57,470 --> 01:05:01,050 And it's purpose is more for smaller projects 700 01:05:01,050 --> 01:05:05,550 that we will have them to do a bunch of permits for overused 701 01:05:05,550 --> 01:05:07,770 to do permits for all of them ever came in AFA. 702 01:05:08,270 --> 01:05:12,930 So like, turn ones when you're joining our roadway 703 01:05:12,930 --> 01:05:15,570 in your project involves a turn line on our roadway 704 01:05:15,570 --> 01:05:18,010 or something like that. 705 01:05:19,030 --> 01:05:21,170 There's some restrictions on how it can be used, 706 01:05:21,490 --> 01:05:23,150 but it speeds up the process a lot 707 01:05:23,150 --> 01:05:25,230 at a board's a bunch of the review. 708 01:05:26,270 --> 01:05:29,270 And if it applies, that's another thing we have to tell you 709 01:05:29,270 --> 01:05:33,290 which found out in template applies, but if that one applies, 710 01:05:33,290 --> 01:05:37,210 that is my new favorite tool to use because it is so much quicker. 711 01:05:49,170 --> 01:05:49,290 Right. 712 01:05:53,880 --> 01:05:59,580 So, one of the one hiccup is some local governments that can't send us the Resolution 713 01:05:59,580 --> 01:06:02,580 beforehand because the Resolution is an attachment. 714 01:06:04,500 --> 01:06:13,300 So, it's workable that if we can get the Resolution beforehand, it gets lighted and 715 01:06:13,300 --> 01:06:17,540 DocuSign document doesn't have to be later all through to add that, which is a problem. 716 01:06:18,300 --> 01:06:20,180 It negates the signature, essentially. 717 01:06:22,360 --> 01:06:26,620 But what we do have this, it's similar to the documents, they have a whole copy 718 01:06:26,620 --> 01:06:32,920 per out of it, and the action that can't say or prove it, and then they docuSign it after 719 01:06:32,920 --> 01:06:38,720 accounts after that meeting, but not literally sit down silent in the meeting, although 720 01:06:38,720 --> 01:06:41,340 you could open up the DocuSign and sign it in the meeting. 721 01:06:41,340 --> 01:06:45,880 But they just take, but they do that to incorporate into their agenda. 722 01:06:51,890 --> 01:06:56,250 It's, I would need to get with you and see how we work that in, how yes process works. 723 01:06:56,930 --> 01:07:04,190 And so, I know some counties, they will get the resolution of proving the project like months before they approve the AFA. 724 01:07:04,650 --> 01:07:06,710 And then approving the AFA is a separate agenda. 725 01:07:06,710 --> 01:07:18,550 So, and that's another, let me touch on that while I keep your reservations general, don't put specific dollar amounts in them. 726 01:07:19,010 --> 01:07:27,970 Don't put very, very narrow project descriptions like we're proving five intersection improvements on these quarters of these intersections. 727 01:07:28,490 --> 01:07:35,370 Because when the project changes or we let the project in the process a little different, we need a new resolution. 728 01:07:35,370 --> 01:07:39,350 because you put a very specific dollar amount in there. 729 01:07:39,510 --> 01:07:41,550 So they only have to amend the whole agreement 730 01:07:41,550 --> 01:07:45,830 because your resolution doesn't approve how to project that. 731 01:07:47,390 --> 01:07:47,890 So, what do you want to answer? 732 01:07:49,310 --> 01:07:50,010 Anything else? 733 01:07:52,290 --> 01:07:55,610 Are we going to hand it off to one sentence? 734 01:08:15,540 --> 01:08:16,880 Hello, my name is Juan Fuentes. 735 01:08:17,220 --> 01:08:18,160 I work for 736 01:08:27,850 --> 01:08:31,670 deeply demonstrate the portfolio that we run. 737 01:08:32,490 --> 01:08:33,190 We do this. 738 01:08:33,190 --> 01:08:39,430 Like we have a quarterly review four times throughout the year, this is like Catherine was discussing 739 01:08:39,430 --> 01:08:45,830 earlier, all this information goes to Austin and we have a letting meeting once a month as 740 01:08:45,830 --> 01:08:46,170 well. 741 01:08:46,570 --> 01:08:52,110 All the information is gets pulled from the portfolio, it is just a sample of some projects that 742 01:08:52,110 --> 01:08:56,710 we're in there that are pulled, if you take a look, it gives you all the information on who's 743 01:08:56,710 --> 01:09:01,530 manager, who's the project manager, their environmental manager. 744 01:09:08,320 --> 01:09:09,560 It gives you the work programs 745 01:09:09,560 --> 01:09:16,440 with funding sources, federal percent, how much of it is 80 percent, 20 percent. It gives you 746 01:09:16,440 --> 01:09:21,080 all the main categories. So we know what funding categories we're using and it breaks down 747 01:09:21,080 --> 01:09:27,840 their cost per category. So we have, you can see at this project 27 million is a category 7. 748 01:09:27,840 --> 01:09:37,220 It tells you the project class, the PS&E percent, and the environmental date, the acquired date, 749 01:09:37,480 --> 01:09:40,340 when it's planning to be acquired, it goes right away needed. 750 01:09:41,160 --> 01:09:46,320 The right away acquisition date, all possibly, the future right away acquisition date, 751 01:09:46,520 --> 01:09:51,980 has the utility information, the utility of clearance date, the beneath of schematic. 752 01:09:52,300 --> 01:09:54,440 If there's a railroad, needs to be done. 753 01:09:54,440 --> 01:09:58,220 If there's a very quiet, like this project, there's a quiet area of faith. 754 01:09:58,920 --> 01:10:01,200 So it just keeps track of everything while the projects, 755 01:10:01,580 --> 01:10:05,160 and we sit down with the managers every three months, 756 01:10:05,460 --> 01:10:07,800 and we're going to line by line project by project, 757 01:10:08,060 --> 01:10:13,760 trying to fill in these dates, verify if it's going to make us 758 01:10:13,760 --> 01:10:18,560 letting data not, we also keep a middle system with comments. 759 01:10:18,960 --> 01:10:21,540 So I have to put all the comments in there and why is going to be delayed, 760 01:10:21,540 --> 01:10:28,600 Why is that on time and then we use this just to keep track of everything? 761 01:10:31,740 --> 01:10:32,460 One 762 01:10:34,860 --> 01:10:40,280 mentioned something else as well and that is that on a monthly basis we have a 763 01:10:40,280 --> 01:10:47,520 wedding meeting and so we talked about earlier the fact that your PSME 100% plans are due 764 01:10:47,520 --> 01:10:55,340 to text out five months prior to wedding. We have a wedding meeting which looks five months 765 01:10:55,340 --> 01:11:01,180 out we're looking ahead five months to say is this project going to make it? Do we have your 766 01:11:01,180 --> 01:11:07,320 100% plans? Is the local government environmentally cleared? You know, this is coming into it, 767 01:11:07,740 --> 01:11:12,740 but we're down to the nuts and bolts when we're taught number five months out. And so not only are we 768 01:11:12,740 --> 01:11:18,700 looking at our portfolio on a quarterly basis with the hope portfolio, but we also have monthly 769 01:11:18,700 --> 01:11:25,280 meeting and this is where we get really scared if the answer is no we don't have 770 01:11:25,280 --> 01:11:31,160 environmental clearance access we don't have 100% plans right away says well we 771 01:11:31,160 --> 01:11:37,520 still have a few parcels left I don't think we can make it and so again it's that 772 01:11:37,520 --> 01:11:40,800 realistic not optimistic letting schedule all 773 01:11:56,570 --> 01:12:04,450 right thanks Lord and one up next we have Mark 774 01:12:04,450 --> 01:12:07,810 us about engineering, federal and state-funded projects. 775 01:12:08,390 --> 01:12:08,490 Mark, 776 01:12:33,930 --> 01:12:34,890 I'm Mark Patterson. 777 01:12:35,290 --> 01:12:37,770 I'm the director of the consultant contract section with TechSod. 778 01:12:39,030 --> 01:12:43,830 And one of my responsibilities is to administer, there we go. 779 01:12:44,370 --> 01:12:48,270 We administer all local government projects, pretty much all local government projects. 780 01:12:48,950 --> 01:12:54,710 I also am responsible for hiring consultants to develop projects for TechSod. 781 01:12:55,650 --> 01:13:00,550 I don't know if you looked at that real closely at that spreadsheet that Juan had, looked 782 01:13:00,550 --> 01:13:06,810 like all the projects were assigned to me, he just, he had, he just sorted it, just 783 01:13:06,810 --> 01:13:10,850 those projects are assigned in, oh, I do have quite a few projects that are assigned 784 01:13:10,850 --> 01:13:14,810 to be for implementation and probably half of them are local government projects, which 785 01:13:14,810 --> 01:13:19,790 probably about 150 of them at any one time, so there's quite a few projects, okay, 786 01:13:19,790 --> 01:13:22,950 I'm going to walk you through some of the requirements 787 01:13:22,950 --> 01:13:24,270 if you get federal funds. 788 01:13:26,290 --> 01:13:28,670 And like all federal funds, there's a lot of strings attached 789 01:13:28,670 --> 01:13:30,070 to getting federal funds. 790 01:13:30,690 --> 01:13:34,770 And one of the first deals is, if you ask to get 791 01:13:34,770 --> 01:13:35,710 reimburse for engineering. 792 01:13:39,820 --> 01:13:42,680 So you've got a project selected with the MPO. 793 01:13:43,280 --> 01:13:46,420 You've asked for it to get reimburse for engineering. 794 01:13:46,980 --> 01:13:49,160 And let's involve with that. 795 01:13:49,160 --> 01:13:58,260 First of all, I think you got to ask yourself, how much am I going to get reimbursed, and if I walk you through what you need to do to get reimbursed, 796 01:13:58,880 --> 01:14:03,180 but is it worth my wild to get reimbursed with these federal funds? 797 01:14:04,980 --> 01:14:10,080 And if you're only going to get reimbursed like $10,000, I don't think it's worth going through all this trouble. 798 01:14:10,240 --> 01:14:11,560 You might as well just pay for yourself. 799 01:14:12,900 --> 01:14:13,800 That's my thought on it. 800 01:14:13,800 --> 01:14:16,320 But anyways, the general requirements are, 801 01:14:16,360 --> 01:14:18,940 you got to advertise in a paper of highest regional circulation, 802 01:14:19,260 --> 01:14:21,300 which in this area is usually the Houston Chronicle. 803 01:14:22,540 --> 01:14:24,900 It needs to be a qualification space selection. 804 01:14:26,240 --> 01:14:28,260 You need to have a DVE or hub requirement, 805 01:14:28,300 --> 01:14:30,220 depending on what kind of funds you're going to use. 806 01:14:30,540 --> 01:14:31,580 It's DVE for federal. 807 01:14:32,380 --> 01:14:33,680 It's hub for state. 808 01:14:34,940 --> 01:14:37,040 And there can't be no geographic preference 809 01:14:37,640 --> 01:14:38,700 for selecting a consultant. 810 01:14:39,360 --> 01:14:41,400 And that gets kind of back into why you need to advertise 811 01:14:42,280 --> 01:14:46,160 in a paper of high regional circulation, I get this all the time. 812 01:14:46,380 --> 01:14:51,140 Well, it's expensive to advertise in the chronicle, and it is. 813 01:14:51,960 --> 01:14:54,440 I want to just advertise in my local paper, so I like cheaper. 814 01:14:55,080 --> 01:14:57,480 Well, not everybody gets your, not always consultants. 815 01:14:57,780 --> 01:14:58,920 Look at your local paper. 816 01:15:00,000 --> 01:15:18,120 And so that gets back, you're trying to target consultants, local consultants. Well, now you need to target all consultants. Everybody, this is a federal, really funded deal, and you need to target all consultants. Everybody needs to have an opportunity to learn this project to send you a letter of interest. 817 01:15:19,700 --> 01:15:22,020 We have a very simple selection procedure. 818 01:15:22,540 --> 01:15:23,880 It's like a page and a half. 819 01:15:24,720 --> 01:15:25,740 It's not hard. 820 01:15:26,220 --> 01:15:29,380 It basically highlights these four or five things 821 01:15:29,380 --> 01:15:30,420 that I've outlined. 822 01:15:32,680 --> 01:15:35,360 We'll send you a sample for selection procedure. 823 01:15:35,780 --> 01:15:37,280 You need to put it in your own format. 824 01:15:38,040 --> 01:15:41,260 You know, maybe with a header of your agency on the top. 825 01:15:44,510 --> 01:15:45,710 You need to send it back to us. 826 01:15:45,710 --> 01:15:47,250 And we need to write your letter that says, 827 01:15:47,250 --> 01:15:50,130 Yes, we reviewed your selection procedure, it looks good. 828 01:15:50,430 --> 01:15:53,210 Need to do that before you start your selection. 829 01:15:55,170 --> 01:15:58,030 I think I want to add one other thing to the general requirements. 830 01:15:59,030 --> 01:16:02,370 You can't have any involvement in this process by elected officials. 831 01:16:03,770 --> 01:16:05,850 The selection needs to be done by the staff. 832 01:16:06,130 --> 01:16:08,310 If you have involvement by elected officials, 833 01:16:09,010 --> 01:16:12,590 then we're going to probably throw your selection out to start over again. 834 01:16:13,090 --> 01:16:14,090 That can be very time consuming. 835 01:16:15,970 --> 01:16:29,270 Okay, now you've gone through the process of selecting your consultant, but you're not finished with the federal requirements, because there's a lot of federal requirements that go along with your consultant contract. 836 01:16:31,290 --> 01:16:37,430 Textouts got to prove your contract between the local government and consultant prior to execution. 837 01:16:39,960 --> 01:16:45,980 We got to prove the scope, the contract format and the fee for all contracts we're going to reimburse you. 838 01:16:45,980 --> 01:16:50,580 Now, if you're not going to get reimbursed, we'd usually like to see the scope, so that we 839 01:16:50,580 --> 01:16:55,460 can make sure that what you're requiring of the consultant and what text out requiring of 840 01:16:55,460 --> 01:16:57,140 the consultant are the same thing. 841 01:16:57,740 --> 01:17:03,040 If not, we get a lot of complaints by the consultants that they're being asked to meet two different 842 01:17:03,960 --> 01:17:05,440 agendas by two different masters. 843 01:17:08,170 --> 01:17:13,230 Again, we've done this a lot, so we can send you a standard, the local government of samples, 844 01:17:13,230 --> 01:17:19,530 standard contract. The contract must be either lump sum or cost plus fixed fee. The local 845 01:17:19,530 --> 01:17:23,470 government and the consultant negotiate a contract and submit to text up for review. 846 01:17:24,990 --> 01:17:30,470 Text.reviews and approve the draft contract and we'll meet if necessary. A lot of times 847 01:17:30,470 --> 01:17:36,510 you could do it just reviewing stuff via email. The local government that consultant 848 01:17:36,510 --> 01:17:39,190 finalized negotiations and send the contract to text. 849 01:17:42,250 --> 01:17:44,310 Text. Here in the Houston district 850 01:17:44,310 --> 01:17:50,770 would submit, submit the contract to us and audit office review. 851 01:17:51,190 --> 01:17:53,730 What they're looking for there is text. 852 01:17:54,510 --> 01:17:56,770 Dot does a lot of contracting with consultants. 853 01:17:58,130 --> 01:18:03,350 So we have a list of, we have current contracts with consultants that maybe it's more 854 01:18:03,350 --> 01:18:05,490 likely we're using the same consultants you're using. 855 01:18:06,510 --> 01:18:09,970 And so we can make sure that you're going to get the best deal, that you're getting the overhead 856 01:18:09,970 --> 01:18:13,430 rate that we're getting, that you're getting the same hourly rates that we're getting. 857 01:18:13,430 --> 01:18:16,650 So we're going to help you in this process and it is a federal requirement. 858 01:18:19,110 --> 01:18:23,670 So we're going to help you, we need to submit that to the ROT office for you to make sure 859 01:18:23,670 --> 01:18:25,430 you're getting the best rates in overhead. 860 01:18:27,700 --> 01:18:33,400 If audit approves, text sets, submits for final approval and then we, we're offering running. 861 01:18:33,680 --> 01:18:36,780 The local government executes the contracts and we schedule a kickoff meeting. 862 01:18:38,480 --> 01:18:42,660 We do need a copy of the fully executed consultant contract because remember you're getting 863 01:18:43,220 --> 01:18:49,860 reverse. Also, female agreements to consultant contracts require prior approval. And the way 864 01:18:49,860 --> 01:18:56,240 it works with, with getting reimbursed is, this is a, yeah, it's a reimbursement. All of 865 01:18:56,240 --> 01:19:00,280 the stuff is a reimbursement deal. So you got to spend the money, then you get reimbursed. 866 01:19:00,940 --> 01:19:07,060 So, so if you hire a consultant, he sends a bill in. You get, you got to reimburse the 867 01:19:07,060 --> 01:19:11,780 consultant 100% of the bill, turn around and submit the bill back to us with the proof that 868 01:19:11,780 --> 01:19:16,700 paid the consultant and will reimburse you the 80%. But it's important to know that you've 869 01:19:16,700 --> 01:19:21,740 got to spend 100% before you get reimbursed. Kind of a texture cash flow. 870 01:19:24,480 --> 01:19:24,480 Okay. 871 01:19:26,560 --> 01:19:32,180 Let's get an engineering plan preparation. We'll have a design kick-up meeting. We'll assign 872 01:19:32,180 --> 01:19:38,080 it a project manager. We have 14 project managers that work on our section. They're all professional 873 01:19:38,080 --> 01:19:41,880 engineers and most of them are pretty experienced with doing these kind of projects. 874 01:19:42,660 --> 01:19:51,500 We typically have plan reviews at 30, 60, 90, 95, doesn't say it in the slide, and 100% completion. 875 01:19:52,080 --> 01:20:00,380 The 95% we, well, during all these interim submissions, 30, 60, 90, we have various sections that text out. 876 01:20:00,400 --> 01:20:06,720 We'll submit your plans over to our traffic people, our signing pavement marking people, our bridge section, 877 01:20:06,720 --> 01:20:09,880 They'll all review your plans at 30, 60, 90. 878 01:20:10,400 --> 01:20:12,140 We also have a plan review section. 879 01:20:13,340 --> 01:20:16,580 That's why you submit the 95% plans too. 880 01:20:16,980 --> 01:20:19,200 And they review, they review all the paperwork mainly. 881 01:20:20,060 --> 01:20:23,000 They look at, on any of these projects, 882 01:20:23,580 --> 01:20:28,360 you're required to, you're a whole raft of forms. 883 01:20:28,360 --> 01:20:30,180 You need to fill out for the final letting. 884 01:20:32,890 --> 01:20:34,370 We require, as Katherine mentioned, 885 01:20:34,450 --> 01:20:36,430 a five month review of the final plans 886 01:20:36,430 --> 01:20:39,230 that does include that the advertisement time. 887 01:20:39,710 --> 01:20:42,030 And so there's a required advertisement time, 888 01:20:42,210 --> 01:20:44,310 I can't remember what it is like, it's like 30A's 889 01:20:44,310 --> 01:20:46,910 or that that include that's included in this time, 890 01:20:47,010 --> 01:20:47,950 the five months. 891 01:20:50,480 --> 01:20:53,240 Plans will use text.specification and plan format 892 01:20:53,240 --> 01:20:56,860 for text.lettings, local specifications 893 01:20:56,860 --> 01:20:59,960 and plan format can be used for local leddings. 894 01:21:00,680 --> 01:21:03,160 Local leddings require text.par approval 895 01:21:03,160 --> 01:21:05,180 and adherence to local led guidelines. 896 01:21:06,020 --> 01:21:14,620 typically we do not let just everybody local letter project. We have a risk assessment process 897 01:21:15,260 --> 01:21:21,100 where we assess our risk, text, text, text risk of doing a project with a local government. 898 01:21:22,020 --> 01:21:25,560 And typically if you're a really small local government, you don't have a lot of resources. 899 01:21:26,040 --> 01:21:28,200 You don't have a big staff like the city of Houston. 900 01:21:29,380 --> 01:21:32,840 And all likelihood, you're going to have text.lager project. 901 01:21:33,600 --> 01:21:38,060 And the reason for that is, because the federal rules for this state, 902 01:21:38,320 --> 01:21:39,300 that nothing released text. 903 01:21:39,620 --> 01:21:42,080 Of our responsibility for these projects. 904 01:21:42,860 --> 01:21:45,860 And since if we're responsible for administering the project, 905 01:21:46,600 --> 01:21:50,680 then you have a very small staff, then yeah, we just don't want to take the risk. 906 01:21:52,660 --> 01:21:52,960 Yes, sir? 907 01:21:53,360 --> 01:21:53,740 Question. 908 01:21:58,670 --> 01:21:59,370 Excuse me? 909 01:22:06,820 --> 01:22:06,980 Okay. 910 01:22:11,890 --> 01:22:15,550 It kind of depends what you're doing, and it kind of gets back to what Laura was talking 911 01:22:15,550 --> 01:22:20,050 about with that specific, that new agreements she was telling us about, we have a lot 912 01:22:20,050 --> 01:22:24,590 of projects where people want to do something on our road, like the county wants to come in 913 01:22:24,590 --> 01:22:30,270 and put a right turn lane in, and they're not asking for any money from us, but we're going 914 01:22:30,270 --> 01:22:34,050 to end up with a right turn lane that textot's going to have to maintain when we're finished. 915 01:22:35,030 --> 01:22:42,730 Okay. So how do we do that? Well, typically we let the county do it if we're confident 916 01:22:42,730 --> 01:22:47,870 in their ability to execute. Now if you're a real small local government and we don't think 917 01:22:47,870 --> 01:22:53,270 you can execute it, we might say, hey look, we know that you want this done, you give us 918 01:22:53,270 --> 01:22:59,690 the money and we'll do it for you. It does require an agreement, but it doesn't, it's not 919 01:22:59,690 --> 01:23:03,770 what we call a local let. Local let is where you're getting federal or state funds for 920 01:23:03,770 --> 01:23:07,210 project. You're getting reimbursed. 921 01:23:07,590 --> 01:23:07,830 Sure, 922 01:23:11,660 --> 01:23:13,560 yes. Which one? 923 01:23:14,380 --> 01:23:15,960 Fondran, West Park, West Park. 924 01:23:26,200 --> 01:23:27,820 For local projects, for local 925 01:23:27,820 --> 01:23:30,860 projects, you can use your own format. And that's what we've 926 01:23:30,860 --> 01:23:33,960 typically done, you can. And that's what we've typically done 927 01:23:33,960 --> 01:23:37,520 with the city of Houston. So the question is can you use 928 01:23:37,520 --> 01:23:41,980 your own format? Well, a lot of local governments don't 929 01:23:41,980 --> 01:23:45,980 have a real set format. And if you don't, and you want to 930 01:23:45,980 --> 01:23:51,020 text us format, you can use that for local, for a local, for a local, for a local at 931 01:23:51,020 --> 01:23:57,800 project, if you so desire. No, no, no, I think it's in the agreement. It's in the 932 01:23:57,800 --> 01:24:01,800 agreement for West Park that you can, you can do that. That's part of our local 933 01:24:01,800 --> 01:24:05,540 letting deal. Have you been to the local government projects class? 934 01:24:07,140 --> 01:24:11,580 Okay. Well, they'll cover it in that class. And yeah, basically allow local 935 01:24:11,580 --> 01:24:13,360 governments to use their own specifications. 936 01:24:13,960 --> 01:24:17,360 Now, all your specifications have to meet federal requirements. 937 01:24:18,120 --> 01:24:22,260 And that's why we require you to produce a project manual for local projects. 938 01:24:24,040 --> 01:24:28,680 And in that project manual, you kind of demonstrate how, if you want to use any special 939 01:24:28,680 --> 01:24:34,160 specifications that are specific to your local government, how they meet the federal requirements. 940 01:24:39,300 --> 01:24:39,980 I'm doing it. 941 01:24:40,260 --> 01:24:40,600 I'm doing it. 942 01:24:40,600 --> 01:24:41,220 Another question. 943 01:24:41,480 --> 01:24:41,780 Yes, sir. 944 01:25:03,230 --> 01:25:07,370 Basically, we're not interested in your, we're not interested in how much you're paying them. 945 01:25:07,470 --> 01:25:09,730 We might be interested in the scope, the scope. 946 01:25:10,670 --> 01:25:13,510 Now, if you've already got a contract with them, we'll just work with you. 947 01:25:13,710 --> 01:25:19,350 But if you wanted to bring a contract before you started to us and have us get some joint input, 948 01:25:20,230 --> 01:25:20,830 that would be great. 949 01:25:21,250 --> 01:25:26,090 If you've already got, like for you guys with the City of Houston, you've got a project 950 01:25:26,090 --> 01:25:31,730 that you've already developed, you already have a consultant on board, and you're going 951 01:25:31,730 --> 01:25:34,450 to do yourself, and now you've got federal funds, 952 01:25:34,890 --> 01:25:36,270 we'll just work with you on those. 953 01:25:39,790 --> 01:25:40,490 Any other questions? 954 01:25:44,100 --> 01:25:45,600 Design standards and specification. 955 01:25:47,480 --> 01:25:49,220 The design must match the design criteria 956 01:25:49,220 --> 01:25:51,660 and text-outs operation and procedures manual 957 01:25:51,660 --> 01:25:53,140 and ashto guidelines. 958 01:25:53,560 --> 01:25:54,380 That's in the agreement. 959 01:25:55,460 --> 01:25:57,840 Deviation from Design criteria requires an exception 960 01:25:57,840 --> 01:26:00,280 slash waiver approved by text-outs. 961 01:26:01,120 --> 01:26:04,180 A desperate facility must meet ADA standards. 962 01:26:04,920 --> 01:26:08,160 Bicycle facilities must meet the Astro Bicycle guidelines. 963 01:26:14,660 --> 01:26:14,940 Construction. 964 01:26:17,400 --> 01:26:21,140 As we mentioned, projects may be let in managed by text.org or the local government. 965 01:26:22,440 --> 01:26:26,560 Local networks are reimbursed in a monthly basis, depending upon the percentage contract 966 01:26:26,560 --> 01:26:27,100 completion. 967 01:26:27,720 --> 01:26:32,480 And these work just like I mentioned with the consultant reimbursement. 968 01:26:32,800 --> 01:26:39,480 You've got to spend the money, you're a contractor, you know, you're a contractor, you 969 01:26:39,480 --> 01:26:44,900 pay it, you turn around and submit that bill to text sign you get reimbursed 80%. 970 01:26:47,040 --> 01:26:52,320 Statelets, if it's a statelet project, the local government's 20% match for the entire 971 01:26:52,320 --> 01:26:55,180 project is due 60 days prior to letting. 972 01:26:55,820 --> 01:27:01,480 In typical, we'll do this, I'll write you a letter, and we'll have a table line, it'll 973 01:27:01,480 --> 01:27:07,320 show all the costs for the project, it'll show the construction costs, the design costs, 974 01:27:07,320 --> 01:27:14,520 the review costs, any other costs, and have a break down of which costs may be 100% your 975 01:27:14,520 --> 01:27:16,500 cost and all the ones that we're splitting. 976 01:27:17,280 --> 01:27:20,960 There's certain costs in these projects that are not not eligible for reimbursement, 977 01:27:21,600 --> 01:27:26,000 like if you wanted to replace a water line or something as part of the project, we could 978 01:27:26,000 --> 01:27:28,560 do it as part of the project, but you would have to pay. 979 01:27:29,620 --> 01:27:30,320 This is a good question. 980 01:27:57,220 --> 01:28:02,480 Well, typically if we start the project from scratch, we can cover that in the end of 981 01:28:02,480 --> 01:28:07,980 project development. And a lot of the design criteria are fleshed out when we have a design 982 01:28:07,980 --> 01:28:13,240 concept conference, which is usually around 30%. Where we always have, where we typically 983 01:28:13,240 --> 01:28:17,760 have an issue is a project like Muhammad was talking about, where you guys have already started 984 01:28:17,760 --> 01:28:22,460 it. Well, then we have an issue. Can you, can you, or can you not meet our design criteria? 985 01:28:23,060 --> 01:28:27,780 It's what you read on, because it's in our agreement, can you meet it or not? And then we'll 986 01:28:27,780 --> 01:28:31,840 let's just, well, we'll work with you to assess whether you can meet it or not. Typically, if you 987 01:28:31,840 --> 01:28:37,720 have right away, yeah, you have enough right away, you have enough room, we'd like you to 988 01:28:37,720 --> 01:28:43,080 meet at the middle of the Ash took design criteria. Preferably text-outs design criteria, 989 01:28:43,500 --> 01:28:44,880 but minimum Ash took, 990 01:28:50,470 --> 01:28:53,450 let's see, where do we leave this? Okay, field changes must be approved 991 01:28:53,450 --> 01:28:56,030 by text-outs, that's for local-let projects. 992 01:28:58,300 --> 01:29:00,020 Text-outs charges of construction management 993 01:29:00,020 --> 01:29:05,820 fee for text-out-let projects, as Catherine mentioned. We also charge an oversight fee for 994 01:29:05,820 --> 01:29:07,400 local, local, let projects. 995 01:29:08,320 --> 01:29:09,240 Now, why do we do that? 996 01:29:09,380 --> 01:29:11,820 Well, somebody's got to be out there from TechStot 997 01:29:11,820 --> 01:29:14,860 who monitors your project and make sure you get reimbursed. 998 01:29:15,240 --> 01:29:18,740 I mean, sorry, make sure that your contractor's doing the work 999 01:29:18,740 --> 01:29:21,540 and that we can reimbursed you. 1000 01:29:21,840 --> 01:29:23,020 So somebody's going to have a little oversight 1001 01:29:23,020 --> 01:29:25,260 from TechStot because you're going to send your build 1002 01:29:25,260 --> 01:29:27,300 to somebody and that somebody needs to, 1003 01:29:27,300 --> 01:29:29,260 it TechStot needs to make sure the work's been done. 1004 01:29:29,780 --> 01:29:31,440 So we charge you an oversight fee. 1005 01:29:32,080 --> 01:29:33,380 It's not as much, of course, 1006 01:29:33,380 --> 01:29:35,480 as if we were managing the project ourselves. 1007 01:29:37,540 --> 01:29:41,620 Uh, textot in the local government must agree on the final acceptance of the completed project. 1008 01:29:43,860 --> 01:29:47,640 Um, many federal requirements must be met for textot and local lip projects. 1009 01:29:49,820 --> 01:29:54,560 Like I said, there's a lot of strings attached with receiving, uh, state or federal funds for projects. 1010 01:29:55,460 --> 01:29:59,960 Finally, I'd encourage you all to go to this local government project procedures class that we, that we mentioned. 1011 01:30:00,000 --> 01:30:06,760 It's LGPP, they have it. If you get on our website, our text. website, there's a list of when the classes are held. 1012 01:30:08,200 --> 01:30:17,900 I think there's a big demand right now, so I think the classes here are not all more available, but there's lots of classes throughout the state if you're willing to travel someplace. 1013 01:30:20,510 --> 01:30:21,010 Any questions? 1014 01:30:29,680 --> 01:30:33,360 So the question is, context.letter project office system, yes, yes we can. 1015 01:30:43,790 --> 01:30:45,730 Okay. Yeah. 1016 01:30:53,750 --> 01:30:56,910 So the question is, what are the advantages of text out versus the local government 1017 01:30:56,910 --> 01:30:57,870 letting a project? 1018 01:31:00,000 --> 01:31:04,260 I get law kind of feedback from people from our construction people 1019 01:31:04,260 --> 01:31:10,380 and I get, yeah, about whether or not it's easier for a local government to do it or for us to do it. 1020 01:31:10,720 --> 01:31:14,780 I'd say if a project is kind of a lot of involvement with a local community, 1021 01:31:15,900 --> 01:31:21,240 it might be better for you guys to do it because you're more used to dealing with a local community. 1022 01:31:21,240 --> 01:31:27,000 So it's got a lot of community interests, like this project, well, we've got coming up 1023 01:31:27,000 --> 01:31:31,760 on Memorial Drive, yeah, that might be a good project for you guys to do. 1024 01:31:32,060 --> 01:31:34,960 Maybe for us, if you've got a big bridge project, 1025 01:31:37,240 --> 01:31:38,440 maybe that would be a better project 1026 01:31:38,440 --> 01:31:39,080 for textile. 1027 01:31:40,180 --> 01:31:45,060 But it's just, whatever you guys want to do, if you guys have already done the engineering 1028 01:31:45,060 --> 01:31:50,640 for a project and it's all in your format, yeah, you don't want it to go to the expense 1029 01:31:50,640 --> 01:31:55,960 of redoing the project and putting it into text us format, and we can't implement a project 1030 01:31:55,960 --> 01:31:59,160 that's done in your format, has to be done in text us format. 1031 01:32:00,820 --> 01:32:05,400 So, I don't know, any projects is just way the pros and cons. 1032 01:32:11,480 --> 01:32:13,540 It's usually pretty quick. 1033 01:32:15,260 --> 01:32:22,000 The issue I have more is getting your permission, so I've got a lot of projects where you 1034 01:32:22,000 --> 01:32:27,160 get complaints from our area offices. We sent the change where the local government, we've asked 1035 01:32:27,160 --> 01:32:32,460 them to approve it and we can't get the approval. And a lot of times on those projects if 1036 01:32:32,460 --> 01:32:39,480 it's a text out project, we may just proceed without your approval. We want to get your approval 1037 01:32:39,480 --> 01:32:44,400 because we're spending 20% of your funds in addition to our project, our funds rather, 1038 01:32:44,820 --> 01:32:49,840 or the state and federal funds. Some projects that we had an overrun, if we're overbudget, 1039 01:32:49,840 --> 01:32:55,280 But prior to letting, we may be spending 100% of your funds on a change order, so we really 1040 01:32:55,280 --> 01:32:59,120 want to get your buy-in, but we can't wait forever. 1041 01:33:04,960 --> 01:33:09,400 We just need it, you know, now you're back to the other deal, you're spending the federal 1042 01:33:09,400 --> 01:33:10,540 and state dollars, right? 1043 01:33:10,900 --> 01:33:14,060 So yeah, if you're going to spend those, then yeah, we need our approval. 1044 01:33:15,260 --> 01:33:21,080 We're looking the other day, and we've changed our agreements, and the agreements now say, 1045 01:33:21,080 --> 01:33:24,880 For local, it says exactly what we said on local government projects. 1046 01:33:25,240 --> 01:33:27,460 You need to submit the change order to us to approval. 1047 01:33:28,200 --> 01:33:30,380 It doesn't say the same thing for state projects. 1048 01:33:31,160 --> 01:33:34,920 I don't necessarily need your approval according to the new agreement format. 1049 01:33:35,340 --> 01:33:36,540 I used to say that. 1050 01:33:37,040 --> 01:33:39,080 We changed it. 1051 01:33:40,200 --> 01:33:40,660 The reason? 1052 01:33:40,880 --> 01:33:41,420 I don't know. 1053 01:33:41,560 --> 01:33:43,120 Maybe we're having trouble getting approvals. 1054 01:33:48,820 --> 01:33:49,260 I 1055 01:33:52,460 --> 01:33:53,640 didn't see it either. 1056 01:33:54,560 --> 01:33:58,600 I think we're going to continue as good state or practice to send you all the change order. 1057 01:33:58,600 --> 01:34:08,160 But then again, especially for federal projects, if there's a delay, federal funds don't participate in delays. 1058 01:34:09,120 --> 01:34:13,140 So for delayed implementing a change order, it delays the entire project. 1059 01:34:14,200 --> 01:34:19,360 Well, we're going to pass that cost on to you, the local government, because the feds aren't going to reimburse us either. 1060 01:34:22,380 --> 01:34:23,640 Does anybody have another question? 1061 01:34:35,910 --> 01:34:38,810 you can use the city piece and design criteria as long as they need 1062 01:34:38,810 --> 01:34:40,070 to ask to a design criteria. 1063 01:34:42,620 --> 01:34:43,940 That makes sense. 1064 01:34:46,000 --> 01:34:46,000 So, 1065 01:35:00,530 --> 01:35:02,250 the question is, when you can, 1066 01:35:02,250 --> 01:35:04,670 when can you use the city piece and design criteria. 1067 01:35:05,330 --> 01:35:06,790 Well, you can. 1068 01:35:07,550 --> 01:35:09,290 You didn't, we didn't agree that you could use the city 1069 01:35:09,290 --> 01:35:10,610 to use the design criteria. 1070 01:35:10,830 --> 01:35:13,150 We agreed that, you could use the askedo design criteria. 1071 01:35:13,550 --> 01:35:15,970 So, long as the city piece and design criteria meet 1072 01:35:15,970 --> 01:35:18,310 the askedo design criteria, we're good. 1073 01:35:18,770 --> 01:35:21,790 If they don't, do we need to have a conversation about it? 1074 01:35:22,090 --> 01:35:23,550 Why can't you meet the design criteria? 1075 01:35:23,830 --> 01:35:26,230 Are you constrained on the right away? 1076 01:35:26,850 --> 01:35:29,790 What's your reason why you can't meet the astro design criteria? 1077 01:35:30,350 --> 01:35:34,550 Remember, we have an agreement, and you agreed to use the ashto. 1078 01:35:39,470 --> 01:35:39,730 Yes. 1079 01:35:45,000 --> 01:35:45,140 Yes. 1080 01:35:45,140 --> 01:35:45,400 Yes, sir. 1081 01:36:03,430 --> 01:36:03,590 Okay. 1082 01:36:23,680 --> 01:36:28,240 It could be Mike, but then you need to have, you need to make sure that you can meet all the other 1083 01:36:28,240 --> 01:36:34,540 criteria. Can you meet the D.B. goals for a local at project? And I guess you, you know, 1084 01:36:34,640 --> 01:36:35,780 you've done these recently. 1085 01:36:38,580 --> 01:36:39,740 Can you meet all the other criteria? 1086 01:36:55,080 --> 01:36:55,700 I think that would be 1087 01:36:55,700 --> 01:37:00,260 better addressed by one of the subsequent speakers, but I've been thinking that, yes, you would 1088 01:37:00,660 --> 01:37:03,980 be. I think as soon as you get those federal funds, 1089 01:37:06,030 --> 01:37:07,110 you're subject to our scrutiny. 1090 01:37:09,230 --> 01:37:12,850 And if, so if you're still buying the right away after you receive the federal funds, 1091 01:37:15,220 --> 01:37:20,840 Now, if you've done it before, I don't know, you might, like I said, I might need to be addressed 1092 01:37:20,840 --> 01:37:24,960 by one of the subsequent speakers, but I'm thinking, yeah, I'll see another projects where, 1093 01:37:25,060 --> 01:37:30,300 yeah, they've asked how they acquired the right away for this project four years ago 1094 01:37:30,300 --> 01:37:35,220 before they could receive federal funds. Is that the new norm? I don't know. 1095 01:37:36,280 --> 01:37:37,100 But I have seen it happen. 1096 01:37:40,650 --> 01:37:42,470 It's something 1097 01:38:03,180 --> 01:38:05,780 that's going to cost additional funds. 1098 01:38:07,020 --> 01:38:08,860 Something that's going to cost additional funds. 1099 01:38:09,620 --> 01:38:13,620 It's just because you're moving a firehead or if the contractors are not going to 1100 01:38:13,620 --> 01:38:17,860 cost you more money, then I don't think we'd be that interested. 1101 01:38:18,200 --> 01:38:23,040 We're interested in stuff where it's going to cost additional funds and we're going to 1102 01:38:23,040 --> 01:38:24,520 have to reimburse for it. 1103 01:38:24,720 --> 01:38:25,660 That's what we're interested in. 1104 01:38:26,300 --> 01:38:28,120 And it's different from the contract. 1105 01:38:28,200 --> 01:38:30,120 It's outside the contract you have with your contract. 1106 01:38:37,500 --> 01:38:40,140 And then we're interested. 1107 01:38:43,840 --> 01:38:44,600 Anything else? 1108 01:38:46,180 --> 01:38:46,600 Thanks, everybody. 1109 01:38:55,420 --> 01:38:56,020 Thanks, Mark. 1110 01:38:57,180 --> 01:38:57,420 All right. 1111 01:38:57,720 --> 01:39:00,520 Up next, we have Anna Ramirez. 1112 01:39:01,480 --> 01:39:03,320 Here to talk about the transportation alternative 1113 01:39:03,320 --> 01:39:05,720 set of size or toss of program. 1114 01:39:28,150 --> 01:39:29,170 I think I'll say. 1115 01:39:29,810 --> 01:39:34,530 Well, I'm going to start with a story about pitfalls. 1116 01:39:35,490 --> 01:39:36,190 What not to do? 1117 01:39:37,850 --> 01:39:43,850 And this is a project that, believe it or not, started in 2012. 1118 01:39:45,310 --> 01:39:51,730 At that time, Tessa, or the PED-Bike funding project, was called Transportation Alternatives Program. 1119 01:39:52,170 --> 01:40:01,530 And I'm going to just walk it over here and say that this project right here, North, is kind of to the left. 1120 01:40:01,530 --> 01:40:04,470 was a project that seemed, you know, very promising. 1121 01:40:04,750 --> 01:40:07,810 It connected all those other shared use paths. 1122 01:40:09,550 --> 01:40:11,570 It was, when it says Cat 3, 1123 01:40:11,670 --> 01:40:16,730 I think it's really Cat 9, T-Tap, Tessa, Cat 9. 1124 01:40:17,110 --> 01:40:21,710 And so this project, the time when it was selected in 2012, 1125 01:40:21,930 --> 01:40:23,750 there was an amendment in 2013. 1126 01:40:24,530 --> 01:40:30,330 The AFA that Laura just talked about was in 2014. 1127 01:40:30,330 --> 01:40:37,130 to years after I got selected, we're hoping you would let and we would start construction 1128 01:40:37,130 --> 01:40:45,190 in 2018. That's six years right there. This is for maybe a World War Project. This is like 1129 01:40:45,190 --> 01:40:50,830 a think of a shared use path as a really wide sidewalk. A 10 feet. 1130 01:40:53,190 --> 01:40:54,190 So then happened. 1131 01:40:56,840 --> 01:40:57,400 Share this 1132 01:40:57,400 --> 01:40:58,040 project, 1133 01:41:00,260 --> 01:41:07,480 what happened here was a this project over here, used to go through the river 1134 01:41:08,220 --> 01:41:16,420 here, and it had to have a bridge. But in that area, which is in the clear lake area, 1135 01:41:16,820 --> 01:41:24,440 there basically have a lot of people that have cell boats go figure. And the clearance 1136 01:41:24,440 --> 01:41:30,600 to go through those bridge right here, this river was that we didn't have enough clearance 1137 01:41:30,600 --> 01:41:36,220 for all those cell boats to go through it. So the cell group community came out and said, 1138 01:41:36,420 --> 01:41:45,080 I know, I know how. And we could not move forward on this pipeline that we've been talking to 1139 01:41:45,080 --> 01:41:54,420 you about about getting into contract, the design review and all that good. So we could be 1140 01:41:54,420 --> 01:42:03,140 We had a script problem and it ended out that this project that was elected in 2012 lost the funding. 1141 01:42:04,080 --> 01:42:09,100 The funding was taken away because this project was not able to move forward. 1142 01:42:09,160 --> 01:42:11,440 It was an important gap for it. 1143 01:42:12,600 --> 01:42:16,540 But if you don't use it, like Catherine said, you lose it. 1144 01:42:16,780 --> 01:42:18,120 So they lost the funding. 1145 01:42:21,150 --> 01:42:22,490 So what happened next? 1146 01:42:23,900 --> 01:42:29,760 When your construction started, stay tuned because for this project, 1147 01:42:32,020 --> 01:42:39,140 so again, this is a river that we talked about, this river here, and so they couldn't get the bridge because of the server. 1148 01:42:40,700 --> 01:42:51,900 So they removed this segment and added this one here and they came back to the MPO in 2015 and said, we're ready to go. Let me will submit. 1149 01:42:53,080 --> 01:43:00,780 Well, going to have, there's people here that live in this house is right here said, 1150 01:43:01,200 --> 01:43:08,260 not in my backyard. I don't want to show you stuff behind my house. Who would think 1151 01:43:09,200 --> 01:43:15,180 that people who now want to have like a trail, like a buffalo by a trail? But for whatever reason, 1152 01:43:15,180 --> 01:43:24,020 These people had said, now in my backyard, and this segment here, was recently in April, 1153 01:43:24,640 --> 01:43:28,920 so made for an amendment, and it was changed. 1154 01:43:31,510 --> 01:43:32,870 So, still tuned, 1155 01:43:35,480 --> 01:43:37,040 where are our lessons learned? 1156 01:43:38,120 --> 01:43:45,460 For TASA, the transportation alternatives, say TASA, like I said before, it was TE, this project 1157 01:43:45,460 --> 01:43:48,900 that I just talked to you about was transportation enhancement 2012. 1158 01:43:49,580 --> 01:43:58,540 Then in 2015, the feds just to make it, you know, interesting, change the name of kind of the same kind of funds for paid like to tap. 1159 01:43:58,940 --> 01:44:01,200 Transportation alternatives program. 1160 01:44:01,820 --> 01:44:04,660 And then now that's called a transportation set aside. 1161 01:44:04,700 --> 01:44:10,680 And that's part of the surface transportation block grant that used to be called STP. 1162 01:44:10,680 --> 01:44:12,440 You just have to follow those things. 1163 01:44:14,440 --> 01:44:22,220 And basically, for the public funding, interestingly enough, there's not one but two 1164 01:44:22,220 --> 01:44:23,380 call for projects. 1165 01:44:25,860 --> 01:44:31,580 There's the agency's call for project, which is included in the tip, and then there's a 1166 01:44:31,580 --> 01:44:32,760 state call for projects. 1167 01:44:33,240 --> 01:44:34,200 And they're a little bit different. 1168 01:44:34,600 --> 01:44:41,040 From the state perspective, they find public infrastructure for nine urban communities 1169 01:44:41,040 --> 01:44:45,820 are you know, real small and smaller urban communities are less than 200,000. 1170 01:44:46,480 --> 01:44:52,660 For, you know, the NPR, obviously, you know, they do the urbanized area kind of a bit different 1171 01:44:52,660 --> 01:44:59,980 and the NPO in 2015, they include some transit for the state, is mostly pet. 1172 01:45:00,000 --> 01:45:11,760 But it is a competitive process and why am I calling highlighting that? I'm highlighting that it's a competitive process because you cannot just go up and change your scope of work. 1173 01:45:12,040 --> 01:45:18,300 Even if it's a slow sidewalk or a trail, you cannot just get creative and change your scope of work. 1174 01:45:21,150 --> 01:45:28,550 Now, from a faith-like perspective, the state, another difference is that the state pays 1175 01:45:28,550 --> 01:45:29,670 only for construction. 1176 01:45:29,910 --> 01:45:35,850 The only eligible activities construction only, except for this last cough cough 1177 01:45:35,850 --> 01:45:43,270 project that ended August 2015, they had safer to score funding that had remaining 1178 01:45:43,270 --> 01:45:48,830 safety movements that didn't include some engineering, but the state is construction only 1179 01:45:48,830 --> 01:45:56,530 A.J.C. is, you can have P.S. and E in right away another other basis of project development. 1180 01:45:57,330 --> 01:46:04,730 Now, the most important part is that TASA is really for this funding, the TASA funding is for transportation. 1181 01:46:05,690 --> 01:46:10,950 So, there is a transportation funds. So, I will understand that other amenities might be important, 1182 01:46:11,310 --> 01:46:14,850 or that other things might be needed to put in the sidewalk, or the shared use path. 1183 01:46:16,030 --> 01:46:23,010 The idea, both from the state and the MPO, is the most of it should go to increase the infrastructure for more-time-oral connections. 1184 01:46:24,530 --> 01:46:29,930 Meaning that from the state perspective, if you're in a small community and you need to re-grade your ditches, 1185 01:46:30,690 --> 01:46:32,910 because you have open ditch or you need to put a pipe. 1186 01:46:34,250 --> 01:46:40,330 Some drainage, you can only do 30% of that, because we know the drainage is a high cost ticket item. 1187 01:46:40,330 --> 01:46:44,930 And so that's going to take up all of the limited head-by-finding that is available. 1188 01:46:45,410 --> 01:46:53,230 From the NPO, in terms of advantages and last, if you think I think it's 15 percent, I believe, and it changes in each call for projects. 1189 01:46:55,150 --> 01:46:59,950 Now, those call for projects agree that you have to think about connectivity and access. 1190 01:46:59,950 --> 01:47:07,350 You want to connect with people who live to where they work, to where they shop, because it's for transportation and those, you know, short and long distance strips. 1191 01:47:07,350 --> 01:47:12,030 Obviously, there's an importance in connecting to transit. 1192 01:47:13,010 --> 01:47:17,670 Be it the first lesson to transit centers, park and rides, 1193 01:47:18,510 --> 01:47:20,470 thinking about continuity in the network, 1194 01:47:20,830 --> 01:47:23,150 thinking about gut fillers, and very importantly, 1195 01:47:23,410 --> 01:47:25,590 thinking about the logic terminology. 1196 01:47:27,350 --> 01:47:29,770 So let me go back to the funding. 1197 01:47:32,430 --> 01:47:36,390 So, Tessa, like Catherine was saying, is real restrictive. 1198 01:47:37,670 --> 01:47:44,230 The reason for it is, like we said, we have a three-year timeframe, but not only that. 1199 01:47:45,010 --> 01:47:51,170 It's not only the timeframe, but the fact that there's not enough projects. 1200 01:47:51,550 --> 01:47:54,810 So if there's a project that God delayed, what does that mean? 1201 01:47:55,170 --> 01:47:57,610 That means that we got to accelerate somebody else. 1202 01:47:58,430 --> 01:48:01,330 And is there somebody ready to go? 1203 01:48:01,990 --> 01:48:04,510 You know, sometimes that's just not the case. 1204 01:48:04,730 --> 01:48:09,030 And so it makes it a bit harder to find a substitute. 1205 01:48:10,710 --> 01:48:14,610 The other thing is sometimes for TASA, 1206 01:48:15,550 --> 01:48:16,930 they're going in and they look maybe, 1207 01:48:16,930 --> 01:48:19,030 can we do some sum back funding? 1208 01:48:19,310 --> 01:48:21,490 Can we, you know, transfer from category nine 1209 01:48:21,490 --> 01:48:23,190 and then move it at category five? 1210 01:48:23,790 --> 01:48:25,370 But category five, which is congestion, 1211 01:48:25,370 --> 01:48:28,990 communication or quality, you gotta think about admissions reductions. 1212 01:48:29,390 --> 01:48:33,490 So if you're really reconstructing a sidewalk, the feds are going to say, 1213 01:48:33,590 --> 01:48:36,610 well, how many admissions reduction is there for reconstruction? 1214 01:48:37,630 --> 01:48:42,370 There might be some associated with a new sidewalk, but to reconstruct, 1215 01:48:43,090 --> 01:48:44,130 maybe not so much. 1216 01:48:44,470 --> 01:48:48,370 So makes it harder on us to get that federal approval that is needed. 1217 01:48:48,950 --> 01:49:00,570 The person to think about with Tessa is that you think about this first time is that this is the funding that is available for Tessa. 1218 01:49:00,750 --> 01:49:03,610 It doesn't mean that your project is going to last. 1219 01:49:03,730 --> 01:49:08,830 It means that the funding that is available for the whole state or for an area where labs. 1220 01:49:09,250 --> 01:49:14,270 Which means that what we need is to hear from you earlier and say, you know what, I have delays. 1221 01:49:14,270 --> 01:49:19,470 I have the laser and that way we can reprogram your project. 1222 01:49:19,870 --> 01:49:23,590 We can make it, you know, delayed and try to accelerate somebody else. 1223 01:49:23,990 --> 01:49:31,990 You could have the laser because very commonly, sometimes the developers, especially local 1224 01:49:31,990 --> 01:49:36,210 governments, they already went in and pulled the sidewalk. 1225 01:49:36,770 --> 01:49:41,170 They already put the sidewalk in place, the developers, and then they come back to us and 1226 01:49:41,170 --> 01:49:46,430 have a new map and that doesn't look like the map that they submitted to a J.C. and the 1227 01:49:46,430 --> 01:49:50,730 car for projects. And there's a rule you know what the developer, the developer here 1228 01:49:50,730 --> 01:49:55,230 and there we already have those segments. So I'm just going to take my money and the money 1229 01:49:55,230 --> 01:50:00,130 that I got and I'm going to put the same linear feed somewhere else. But that's all fine 1230 01:50:00,130 --> 01:50:06,750 and then you got to come back to the J.C. and make sure they approve it. The other thing 1231 01:50:06,750 --> 01:50:13,270 think of our is outreach. You want to make sure that you reach out to the community because 1232 01:50:13,270 --> 01:50:20,270 you don't want to have that pitfall of having community really against your project. The other 1233 01:50:20,270 --> 01:50:26,470 thing that's important in terms of the change of scope is something that Mark touched upon. 1234 01:50:26,750 --> 01:50:35,330 If you decide to the local standards and you say, I'm project ready, I'm 95% complete. But remember, 1235 01:50:35,330 --> 01:50:38,750 one sense of federal funds for their life is a whole project. 1236 01:50:39,510 --> 01:50:42,310 Then that means you're not at 95% complete. 1237 01:50:43,210 --> 01:50:45,550 That means you have to go back and do it 1238 01:50:45,550 --> 01:50:46,990 to text that standards. 1239 01:50:47,990 --> 01:50:49,630 And that, you know, you have to go somewhere 1240 01:50:49,630 --> 01:50:53,230 without even something that you want to do it or not. 1241 01:50:53,450 --> 01:50:56,290 So, some of the things in terms of bike design standards, 1242 01:50:56,430 --> 01:50:57,570 we do up to Ashdo. 1243 01:50:58,070 --> 01:51:01,770 But some of you, on my think, will lack to is even better. 1244 01:51:01,770 --> 01:51:07,370 That may be the case, but your leaves have to be the minimum of ash, though. 1245 01:51:07,590 --> 01:51:15,990 You have to need whatever federal highways and, in terms of a proof control devices and anything 1246 01:51:15,990 --> 01:51:19,610 that's been approved in the METCV, in terms of pad bank. 1247 01:51:21,210 --> 01:51:27,270 One of the things that we have a lot of issues with is right away an easement for sidewalks. 1248 01:51:27,270 --> 01:51:32,170 Sometimes there is a corner club. You have a lot of utility there. You utility is there. Sometimes 1249 01:51:32,170 --> 01:51:37,910 is a fact that an easement can take about a year to resolve and that really delays projects. 1250 01:51:38,090 --> 01:51:43,990 Utility coordination, some of the utilities may be willing to move things for a roadway but not for a 1251 01:51:43,990 --> 01:51:53,890 sidewalk. So if you can avoid, if you can go around and go around them, if you don't have an 1252 01:51:54,730 --> 01:51:59,330 to make sure that you're up to par. 1253 01:52:00,010 --> 01:52:03,350 The idea here is that if your project is not ready, 1254 01:52:03,530 --> 01:52:04,850 we have to swap it. 1255 01:52:05,050 --> 01:52:07,690 We swap it in the district through the infield, 1256 01:52:07,890 --> 01:52:09,910 but then also they have to think about 1257 01:52:09,910 --> 01:52:12,670 so we don't have a lot in task-offending. 1258 01:52:13,090 --> 01:52:15,510 These are projects through the whole state. 1259 01:52:15,890 --> 01:52:17,390 But task-offending is limited, 1260 01:52:17,530 --> 01:52:21,150 so we don't have as many projects to pick and choose from. 1261 01:52:21,150 --> 01:52:27,690 So it's very important again to think about reaching to us earlier on to have a disability 1262 01:52:27,690 --> 01:52:35,350 and have those conversations with text on. Any questions? Go ahead. 1263 01:53:01,790 --> 01:53:03,610 Well, when you 1264 01:53:03,610 --> 01:53:09,470 think about the benefits, the benefit is the motion has been done differently here at HAC 1265 01:53:09,470 --> 01:53:15,730 than it has on at the state. At HAC it's really a process that they go that eventually gets approved 1266 01:53:16,310 --> 01:53:23,630 TPC. So, that would be more of an HAC policy question. I don't know if Adam, you want to answer that. 1267 01:53:32,980 --> 01:53:40,680 And those, you know, that has changed from 2015 to 2018 and that that HAC strives to work through those 1268 01:53:41,640 --> 01:53:46,860 eligibility and effectiveness and looking at federal house performance measures as well 1269 01:53:46,860 --> 01:53:49,000 when they think about the evaluation criteria. 1270 01:54:27,130 --> 01:54:28,730 Okay. So, let me see, 1271 01:54:28,730 --> 01:54:30,330 So I can see two scenarios. 1272 01:54:31,010 --> 01:54:37,350 One is why does a community reach to text that for a project? 1273 01:54:38,050 --> 01:54:40,170 One of the questions that is that, 1274 01:54:40,170 --> 01:54:44,930 what if, you know, some people that welcome back, 1275 01:54:45,690 --> 01:54:48,630 make them true, text that roadways, 1276 01:54:49,070 --> 01:54:50,290 to be a bit of a barrier. 1277 01:54:51,450 --> 01:54:51,990 And everybody, 1278 01:54:55,490 --> 01:54:56,970 so some people make them true, 1279 01:54:56,970 --> 01:54:59,730 it takes that roadways to be really wide, have a lot of volumes, 1280 01:54:59,730 --> 01:55:01,710 so I consider them to be a barrier. 1281 01:55:02,430 --> 01:55:05,950 But they want to cross them, because, you know, 1282 01:55:06,130 --> 01:55:09,050 as thick as the county, the citizens don't 1283 01:55:09,050 --> 01:55:12,190 and so many identified limits, because they're not, 1284 01:55:12,190 --> 01:55:13,230 you know, it's not like, you know, 1285 01:55:13,230 --> 01:55:15,730 I'm just right away here, I'm sitting in, you know, county road. 1286 01:55:16,310 --> 01:55:18,210 And so, since it's a, I right away, 1287 01:55:18,350 --> 01:55:19,490 they're going to come to us and say, 1288 01:55:19,990 --> 01:55:22,170 hey, we're really thinking it's in a foreign connection. 1289 01:55:22,630 --> 01:55:25,750 How can we work together to make it safer for the community? 1290 01:55:25,970 --> 01:55:28,950 And that happened this past last couple of projects. 1291 01:55:28,950 --> 01:55:33,990 We've got just regular community members reaching out to us and saying, I want a cross-ite 1292 01:55:33,990 --> 01:55:40,750 10 and I don't know how to do that. Can we do something safely? And in that way, we do collaborate with them. 1293 01:55:40,950 --> 01:55:48,870 There's other projects, two, seven days, which is in this area that basically, you know, on some projects, 1294 01:55:49,570 --> 01:55:55,750 we have an off-street facility because that's what the local government says they want, but then sometimes we have the cycling groups that say, 1295 01:55:55,750 --> 01:56:02,390 We wanted on straight because that's where we, I mean, you build that thing, but I'm not going to 1296 01:56:03,070 --> 01:56:08,270 write on it. And you're thinking, but it's off straight. You don't have to worry about the speed. 1297 01:56:08,410 --> 01:56:13,690 You don't have to worry about the volume. But in some areas, that's not context sensitive. 1298 01:56:13,710 --> 01:56:25,730 That's not what the users are want to do. And in some areas, they might say, you know, that I don't 1299 01:56:25,730 --> 01:56:31,650 over the right, so it just really varies and it's very context sensitive. The one thing to remember is, 1300 01:56:31,650 --> 01:56:37,410 and I think we're not going to touch on it a bit later, if you put a bike line, now that triggers 1301 01:56:37,410 --> 01:56:43,330 a public hearing, it's made a lower project. It's a public hearing. We have to have a judge clerk 1302 01:56:44,270 --> 01:56:53,230 a clerk and that would be about 60,000 just for the public hearing to put in the striping to do the 1303 01:56:59,340 --> 01:57:00,780 Thank you. 1304 01:57:09,810 --> 01:57:10,070 All right. 1305 01:57:10,090 --> 01:57:17,030 Now, it's time for a last short break before we come back and finish out the rest of the 1306 01:57:17,030 --> 01:57:17,550 presentations. 1307 01:57:18,530 --> 01:57:19,630 We'll be back in 10 minutes. 1308 01:57:20,610 --> 01:57:23,570 We have two more presentations left. 1309 01:57:25,050 --> 01:57:29,890 First up, we're going to have the presentation on environment, the environmental clearance 1310 01:57:29,890 --> 01:57:31,290 process. 1311 01:57:31,290 --> 01:57:34,430 And for that, I have a Mr. Nisha Robinson, 1312 01:57:42,320 --> 01:57:42,720 how you doing? 1313 01:57:43,540 --> 01:57:44,720 Just keep that microphone. 1314 01:57:45,620 --> 01:57:45,760 Let's see. 1315 01:57:46,720 --> 01:57:47,420 Yes, here. 1316 01:57:48,100 --> 01:57:49,100 That one's okay. 1317 01:57:49,640 --> 01:57:50,940 Good afternoon. 1318 01:57:51,600 --> 01:57:52,760 My name is Denise Robinson. 1319 01:57:53,040 --> 01:57:55,240 I'm the Environmental Manager for the Houston District. 1320 01:57:56,180 --> 01:57:58,560 And we're going to discuss a little bit about the environmental 1321 01:57:59,380 --> 01:58:01,600 clearance process for your projects. 1322 01:58:02,300 --> 01:58:05,960 This is a very, very important process. 1323 01:58:06,680 --> 01:58:15,960 A lot of times you guys kind of wait, and our strongest suggestion is as soon as you know, then you need to come and talk to us. 1324 01:58:17,260 --> 01:58:22,940 We have 15 staff that we work diligently with you to ensure that we're moving forward. 1325 01:58:23,700 --> 01:58:28,860 You never know until we get boots on the ground to determine exactly what we're dealing with. 1326 01:58:28,860 --> 01:58:48,840 And in fact, if it triggers one of these permanent processes, then we're looking at six months to 18 months in addition to so we're just going to step through just a little bit so you can see and when you have a project the best things to get with us and we'll step through our whole entire process this is just very general information. 1327 01:58:50,040 --> 01:58:53,760 So, the purpose is to talk about environmental, environmental clearance. 1328 01:58:55,020 --> 01:59:00,980 We have three, basically, classifications that we look at, the first is categorical exclusion. 1329 01:59:01,560 --> 01:59:07,900 This is an opportunity to do an analysis of a project that has very low impact. 1330 01:59:08,480 --> 01:59:15,300 The next is environmental assessment, the third is environmental impact statement, and we'll 1331 01:59:15,300 --> 01:59:17,380 go through these in general again, 1332 01:59:17,660 --> 01:59:19,740 but giving you more of the high points. 1333 01:59:20,680 --> 01:59:22,840 We do a lot of interagency coordination, 1334 01:59:23,360 --> 01:59:26,280 and this is critical for the success of your project. 1335 01:59:27,500 --> 01:59:31,860 So with that, if we have any idea that you're doing 1336 01:59:31,860 --> 01:59:35,020 something that may trigger Coast Guard 1337 01:59:35,020 --> 01:59:37,820 or working with the Corps, engineers, 1338 01:59:38,620 --> 01:59:42,120 then we need to try to start doing what we call 1339 01:59:42,120 --> 01:59:43,460 our pre-application process, 1340 01:59:43,460 --> 01:59:50,380 And that will then allow us to afford them with the potential of what your project will be. 1341 01:59:50,980 --> 01:59:59,980 And then allows them to start providing representatives from their areas to help us to navigate through the system. 1342 02:00:00,140 --> 02:00:11,300 And to reduce any lag time if possible. But again, the urgency and importance of understanding what exactly that means is left up to you. 1343 02:00:11,540 --> 02:00:17,080 But when it gets to us, we really try to take on the ship of it and help you to navigate through the system. 1344 02:00:17,760 --> 02:00:23,360 So environmental clearances are the process that is required. We're also the projects that you guys are going to be dealing with. 1345 02:00:23,420 --> 02:00:29,140 We have an aspect of screening, scoping, and then complete evaluation of the projects. 1346 02:00:29,140 --> 02:00:34,420 And the main purpose is to assess the potential impacts of the plan project on the environment 1347 02:00:34,420 --> 02:00:36,760 as well as the people that are surrounding. 1348 02:00:37,620 --> 02:00:43,180 And what we try to do is to obey to minimize anything that could have ever impact. 1349 02:00:44,540 --> 02:00:50,180 So the Council of Environmental Quality, CQ, has provided guidance through a memorandum 1350 02:00:50,180 --> 02:00:55,420 of understanding in the MoU, and that's for the regulations for implementing the procedural 1351 02:00:55,420 --> 02:01:00,400 provisions of the National Environmental Policy Act. 1352 02:01:00,840 --> 02:01:06,920 We follow NEPA, and that's from start to finish, and that's the only way that we can 1353 02:01:06,920 --> 02:01:07,320 operate. 1354 02:01:10,010 --> 02:01:14,250 So, the Texas Department of the TechSite utilizes the following classification, as I stated 1355 02:01:14,250 --> 02:01:20,810 earlier, categorical exclusion, and that is a very detailed list of the Act. 1356 02:01:20,870 --> 02:01:25,970 We look at the activities that your particular project may have, and with that we step through 1357 02:01:25,970 --> 02:01:35,590 see if it will fit into what we call a lease or low impact projects in that set as well 1358 02:01:35,590 --> 02:01:42,790 we have C22s as well as open-ended D. And again, as we're evaluating your projects and 1359 02:01:42,790 --> 02:01:47,350 the activities that those projects may encompass, we step through our checklist to determine 1360 02:01:47,350 --> 02:01:53,570 what may be included and make that determination. The environmental assessment as well as 1361 02:01:53,570 --> 02:01:55,750 doing the environmental impact statements. 1362 02:01:56,370 --> 02:01:58,630 And that's the, the long one. 1363 02:01:58,890 --> 02:02:02,090 If you don't know any more about that process, 1364 02:02:02,150 --> 02:02:04,470 just always understand that big red dot 1365 02:02:04,470 --> 02:02:06,630 is the hazard sign. 1366 02:02:07,110 --> 02:02:10,270 And it takes, or can take a very long time 1367 02:02:10,270 --> 02:02:13,130 to actually get that project completed. 1368 02:02:16,360 --> 02:02:19,800 That's one of the processes that we have created 1369 02:02:19,800 --> 02:02:21,580 where we can look at. 1370 02:02:21,880 --> 02:02:23,880 I'm gonna go through it a little bit more in detail 1371 02:02:23,880 --> 02:02:24,880 as we get for it. 1372 02:02:24,880 --> 02:02:26,420 it breaks down the listing. 1373 02:02:29,240 --> 02:02:32,620 So the CE level will projects or projects that do not individually 1374 02:02:32,620 --> 02:02:40,240 or cumulatively have a significant environmental effect. And normally do not require any additional 1375 02:02:40,240 --> 02:02:50,000 or further need an environment. I mean, that will. So the C-22 projects that are entirely within 1376 02:02:50,000 --> 02:02:56,240 the right away. So these are what we call our simple projects that we're not really doing much 1377 02:02:56,240 --> 02:03:01,260 to it, it could be something as small as coming in and replacing the lights and doing 1378 02:03:01,260 --> 02:03:02,280 reforceation. 1379 02:03:02,880 --> 02:03:07,060 It's not something that's very difficult. 1380 02:03:07,720 --> 02:03:13,100 However, we have a programmatic agreement with the State Historic Preservation Office. 1381 02:03:13,620 --> 02:03:18,980 And with that, that project cannot one trigger a section four. 1382 02:03:19,320 --> 02:03:23,440 That's something like with the Parks and Recreation, a section 106. 1383 02:03:23,440 --> 02:03:28,720 that will be something that's historical, endangered and threatened species, and then the 1384 02:03:28,720 --> 02:03:30,880 Clean Water Act, the Rivers and Harvard Act. 1385 02:03:34,350 --> 02:03:34,510 Yes, 1386 02:03:40,620 --> 02:03:41,860 I'm sorry I can understand it. 1387 02:04:48,820 --> 02:04:52,660 If it's our project, we're going to overlook that anyway. 1388 02:05:28,770 --> 02:05:30,470 They come again on the project. 1389 02:05:31,430 --> 02:05:35,590 We do have CVs that will trigger a perfect request, a plan. 1390 02:05:36,090 --> 02:05:37,630 And we have a little bit of a whole process. 1391 02:05:38,190 --> 02:05:40,530 But if you're triggering that permit and understanding 1392 02:05:40,530 --> 02:05:43,310 if any of that technical permit, just an issue of arts, 1393 02:05:43,790 --> 02:05:46,070 which allow them to think that you have to, 1394 02:05:48,500 --> 02:05:49,860 but if you want to write ID, 1395 02:05:50,220 --> 02:05:52,140 they're trigger hours to you. 1396 02:05:52,820 --> 02:05:53,520 So I think 1397 02:05:57,770 --> 02:05:58,470 part of it, 1398 02:06:03,860 --> 02:06:06,360 is basically, you know, kind of a permanent document. 1399 02:06:26,720 --> 02:06:28,860 Do you want their projects to make sure that they 1400 02:06:28,860 --> 02:06:36,400 look at that and get with us to determine how they can best execute what needs to be assessed 1401 02:06:36,400 --> 02:06:38,120 as they're moving forward with their project. 1402 02:06:39,880 --> 02:06:44,860 So our project must be classified as an open-ended D by the activities of their project. 1403 02:06:46,160 --> 02:06:50,000 So with that we can have, when we're looking at it, it means that it didn't really 1404 02:06:50,000 --> 02:06:57,220 mean to C E and it doesn't mean that E E. But with that we had to look at that classification 1405 02:06:57,220 --> 02:07:03,800 and activities that's being done, we can step through in at the end of the day our environmental 1406 02:07:03,800 --> 02:07:07,980 failures and Austin assist us with making those determinations. 1407 02:07:11,640 --> 02:07:19,640 So there's a number of criteria that are reviewed in order to make that assessment and meet that 1408 02:07:19,640 --> 02:07:26,660 classification. So it opened deep criteria and here we go. So you do not have substantial controversy 1409 02:07:26,660 --> 02:07:35,560 on the environmental grounds. So starting with environmental, when you're looking at the impact that 1410 02:07:35,560 --> 02:07:44,100 you're having on a particular quarter, if the community is not excited about what you 1411 02:07:44,100 --> 02:07:51,740 get ready to do is very unlikely we can do an open-ended dec. So if it has significant impacts to 1412 02:07:51,740 --> 02:07:57,580 plan, the growth of land use, you have relocation that's 1413 02:07:57,580 --> 02:08:02,100 significant that you are impacting or displacing 1414 02:08:02,100 --> 02:08:06,580 individuals, again, very unlikely you'll be able to do an open-ended 1415 02:08:06,580 --> 02:08:11,420 D. And you do not, for an open-ended D, criteria you do not have a 1416 02:08:11,420 --> 02:08:14,840 significant impact on the natural cultural recreation or historic 1417 02:08:14,840 --> 02:08:18,760 and other resources. There's not a significant impact on the air 1418 02:08:18,760 --> 02:08:25,140 nor is a water quality, and there's not a significant impact on the travel plans, meaning 1419 02:08:25,140 --> 02:08:30,820 how that court is designed, we're going to impact that significantly, then an open-ended 1420 02:08:30,820 --> 02:08:32,520 D would not be an option. 1421 02:08:33,640 --> 02:08:41,020 Otherwise, either individually, and significantly, significant environmental impacts will trigger 1422 02:08:41,020 --> 02:08:43,340 the inability to use that open-ended D. 1423 02:08:45,360 --> 02:08:50,940 So, for an EA, it's a primary purpose of an EA is to help fix that determine whether 1424 02:08:50,940 --> 02:08:56,500 or not you have an environmental impact statement, which is the EIS, and we'll report with 1425 02:08:56,500 --> 02:09:00,180 that, or if not, if that's not needed. 1426 02:09:00,660 --> 02:09:07,220 So, an EA is prepared when a project cannot be processed as a CE, and does not clearly require 1427 02:09:07,220 --> 02:09:08,960 the preparation of an EIS. 1428 02:09:08,960 --> 02:09:16,740 So it hasn't gone over to the big red dot, but we still have some things that we have to look at. 1429 02:09:17,060 --> 02:09:23,020 It does not clearly require the preparation of an EIS or an EA with assistance determining the need. 1430 02:09:23,400 --> 02:09:32,960 So with that, the end result is either to say that the project in itself was found not to have significant impact. 1431 02:09:32,960 --> 02:09:40,320 impact. So that's a big word there significant and again through the evaluation that we look 1432 02:09:40,320 --> 02:09:44,620 through to determine what that term significant would include. 1433 02:09:47,690 --> 02:09:52,350 So for EIS, in order to do what 1434 02:09:52,350 --> 02:09:58,970 EIS that is, a new control access freeway would be a trigger, a highway project, a four 1435 02:09:58,970 --> 02:10:04,410 more lanes on a new location, new construction or extension of a separate roadway for buses 1436 02:10:04,410 --> 02:10:13,530 or highway occupancy vehicles are not located within the existing highway facility, new construction 1437 02:10:13,530 --> 02:10:21,010 or extension of fixed rail transit facilities such as Reptrial, Light Rail, Pemeter Rail and then 1438 02:10:21,010 --> 02:10:29,730 the Automated Guideway Transit. So, there in that picture is one of our big EIS that's going 1439 02:10:29,730 --> 02:10:32,730 And right now, we see an agency I'll pay from a 45. 1440 02:10:35,980 --> 02:10:39,900 So for EIS, this is a level of project and documentation. 1441 02:10:40,160 --> 02:10:45,000 Typically takes years, we take the way that we're at months, 1442 02:10:45,200 --> 02:10:46,680 because is years. 1443 02:10:47,540 --> 02:10:51,520 And it's a lot of coordination and an extreme amount 1444 02:10:51,520 --> 02:10:56,580 of assessment that has to be done to ensure that we're not 1445 02:10:56,580 --> 02:10:59,980 environmentally impacting the human as well as the property 1446 02:10:59,980 --> 02:11:03,040 that we are working on that particular quarter. 1447 02:11:03,700 --> 02:11:05,520 So some examples of the pieces of the process 1448 02:11:05,520 --> 02:11:08,420 is a notice of intent, which has to go out 1449 02:11:08,420 --> 02:11:10,700 first, participating in incorporating agency 1450 02:11:10,700 --> 02:11:14,640 environment, coordination, plan, and schedule, 1451 02:11:15,460 --> 02:11:15,960 scoping meetings. 1452 02:11:16,780 --> 02:11:19,000 That's with the agency and the public. 1453 02:11:19,680 --> 02:11:22,180 Public meetings, those are very extensive. 1454 02:11:25,520 --> 02:11:28,260 There's a lot that goes into the public meetings, 1455 02:11:28,300 --> 02:11:29,920 because we have to ensure that the public 1456 02:11:29,920 --> 02:11:33,660 is aware of the changes that are being made and proposed. 1457 02:11:34,660 --> 02:11:37,600 But we don't go to the public to say these are our decisions. 1458 02:11:37,640 --> 02:11:41,740 We have alternates on alternatives that we're presenting at that time as well. 1459 02:11:42,380 --> 02:11:46,180 So we have, after that, we have the preparation of the draft and criminal impact and 1460 02:11:46,180 --> 02:11:48,520 which is a DIS, public hearings. 1461 02:11:48,680 --> 02:11:55,600 After we have our public meetings and with EIS is a given that they're controversy. 1462 02:11:55,600 --> 02:12:11,720 So then you have to go and provide your last version, quote unquote final, schematics to the public to say these are the alternatives that we have decided and that we're moving forward with. 1463 02:12:11,900 --> 02:12:17,560 At the public hearing and then you prepare for the final environmental impact statement. 1464 02:12:18,480 --> 02:12:25,400 At that time, shortly thereafter, then there's a preparation of a ride, which is a record of decision. 1465 02:12:26,560 --> 02:12:35,940 And then that note, after that record of decision and everything as finalized, then it goes to the 139 for notice for the public to know that this decision has been made. 1466 02:12:37,640 --> 02:12:46,900 As I was speaking earlier about permits, this is the part that a lot of people neglect to remember or to think about. 1467 02:12:46,900 --> 02:12:54,760 Sometimes they look at a body of water or river that's in the city and we have a bridge over it. 1468 02:12:55,640 --> 02:12:58,660 And we are not necessarily determined whether or not it's inevitable. 1469 02:12:59,520 --> 02:13:14,680 So with that we rely on these two agencies to look at that very intently to determine whether or not we can get a permit and sometimes it's a very simple permit which doesn't take again. 1470 02:13:14,680 --> 02:13:24,520 But 30 to 60 days, but if not, if we're triggering an IP, then that's going to take a couple 1471 02:13:24,520 --> 02:13:25,080 more months. 1472 02:13:25,540 --> 02:13:30,480 So we're looking at anywhere from 18 to 18 months to two years. 1473 02:13:30,640 --> 02:13:33,100 So we have to be very cautious of that. 1474 02:13:33,820 --> 02:13:36,440 Again, that's where the design is important. 1475 02:13:37,240 --> 02:13:40,680 That's where we need to know what that bridge design looks like. 1476 02:13:40,860 --> 02:13:42,880 We need to know if you're getting into the water. 1477 02:13:42,880 --> 02:13:49,960 We need to know what you're doing on the side so the banks, we put an end riff wrap for how far 1478 02:13:49,960 --> 02:13:56,520 are you going? So all of that is really, really important as we're stepping through what we call 1479 02:13:56,520 --> 02:14:02,740 the environmental clearance process. So this type of permit is for the coastblood, I'm sorry, 1480 02:14:03,220 --> 02:14:12,640 that type of permit is required when work is being done in our over, now with the water or our 1481 02:14:12,640 --> 02:14:20,280 bridges, dolphin, and fender system. So you guys know that we have item bridge, that's an example right there. 1482 02:14:22,000 --> 02:14:31,580 We have fenders that have been compromised as well as the dolphins there. So with that, that 1483 02:14:32,500 --> 02:14:40,660 does require IP and it does take a time anywhere from 18 months to two years to get that taken for 1484 02:14:40,660 --> 02:14:49,640 also modification of any existing structures, any bridges that are already existing that are 1485 02:14:49,640 --> 02:14:57,540 inevitable waters. And we're not always 100% in being able to determine what a inevitable 1486 02:14:57,540 --> 02:14:59,820 water is. And, um, 1487 02:15:00,000 --> 02:15:14,540 And if we have to rely on the expertise as well as their mapping to tell us exactly that flow of water. The application process requires at least 60% of the design, as I was sharing with you earlier, to move forward for the actual pruning process. 1488 02:15:15,160 --> 02:15:26,560 So they want to know exactly what you're doing, they want to know how what it works, they want to know everything that's going on in that area so that we can address that for that permit request. 1489 02:15:29,090 --> 02:15:42,630 So there's two types of permits we have the typical turnaround time, that's 12 months, and then we have the exemption, which allows us to do work over the waterways that's smaller than 21 feet in length. 1490 02:15:43,510 --> 02:15:48,930 So that's your easiest or if you will exemption type of permit that's there. 1491 02:15:48,930 --> 02:15:52,050 All need for requirements and other agency permits, 1492 02:15:52,350 --> 02:15:58,250 Coast Guard must be completed prior to the issue 1493 02:15:59,090 --> 02:16:01,730 of that Coast Guard permit taking place. 1494 02:16:02,910 --> 02:16:05,090 Delineations are performed to determine waters 1495 02:16:05,090 --> 02:16:07,870 at a jurisdictional under the Clean Water Act. 1496 02:16:08,230 --> 02:16:11,830 Permits required for any work done in special aquatic sites such 1497 02:16:11,830 --> 02:16:14,650 as wetlands, and sometimes as hard for us to determine 1498 02:16:14,650 --> 02:16:15,950 what that wetland is. 1499 02:16:15,950 --> 02:16:26,990 So back to boots on on the ground and getting out there to just determine because things change and as those changes are occurring we have to determine exactly what that is. 1500 02:16:27,570 --> 02:16:30,210 And that cannot necessarily can be done. 1501 02:16:30,770 --> 02:16:32,630 Google Earth or anything else. 1502 02:16:32,890 --> 02:16:36,210 We have to literally get out on the ground and see what we're looking at. 1503 02:16:36,230 --> 02:16:42,570 Pervits are required for work to be done below the ordinary watermark of rivers, streams, and channels, just as I spoke about earlier. 1504 02:16:43,690 --> 02:16:53,070 So, for nation warming, that's part of the course program for permits, and that impacts 1505 02:16:53,070 --> 02:16:55,090 below the set thresholds. 1506 02:16:55,410 --> 02:16:58,970 So, their process takes typically three to six months. 1507 02:16:59,210 --> 02:17:07,710 We've been working very diligently to try to get that process streamlined, but again, there's 1508 02:17:07,710 --> 02:17:12,230 a lot that goes into that, and then the other type of permit is individual permits, and 1509 02:17:12,230 --> 02:17:14,550 this requires is required for impacts 1510 02:17:14,550 --> 02:17:16,470 rate of then the set thresholds. 1511 02:17:17,270 --> 02:17:19,810 And that process averages about 18 months 1512 02:17:19,810 --> 02:17:20,990 to two years. 1513 02:17:23,350 --> 02:17:26,350 So that is a summary of what our environmental 1514 02:17:26,350 --> 02:17:27,310 parents process. 1515 02:17:27,770 --> 02:17:30,530 And it very simple here, but it is something 1516 02:17:30,530 --> 02:17:32,650 that we take a lot of time. 1517 02:17:32,830 --> 02:17:36,910 We do a lot of group meetings, if you will, 1518 02:17:37,070 --> 02:17:39,650 from the consultants to the staff, 1519 02:17:39,750 --> 02:17:41,450 to make sure that we actually 1520 02:17:41,450 --> 02:17:47,150 hoping these projects out as they should be so that we can address any of our mental issues that 1521 02:17:47,150 --> 02:17:54,130 may occur that we're trying to mitigate those impacts and more importantly we're trying to 1522 02:17:54,130 --> 02:18:01,110 note in advance what it is that we really need to do so Ken says why is important to provide 1523 02:18:01,110 --> 02:18:06,370 this that information and get with us so that we can step through and make those assessments. 1524 02:18:07,250 --> 02:18:08,290 Yes, sir. 1525 02:18:26,480 --> 02:18:30,160 What obligations they have would take stock? 1526 02:18:37,640 --> 02:18:45,120 They still have to oversee the permanent, we want to do any of the, if it's your local 1527 02:18:45,120 --> 02:18:47,100 let, we want to be involved in that. 1528 02:18:47,280 --> 02:18:52,620 But your final reports, your tech reports and everything has to be sent to us for final 1529 02:18:52,620 --> 02:18:53,160 reviews. 1530 02:18:55,620 --> 02:18:55,880 I'm sorry. 1531 02:18:57,380 --> 02:19:04,960 No, that part, first you have to provide the, we have to do some type of scoping together, okay? 1532 02:19:05,240 --> 02:19:12,540 So even though you would be responsible for the, the, the let, we still have to sit down and do our scoping together. 1533 02:19:12,540 --> 02:19:15,260 So that we can make sure that you're following our standards, 1534 02:19:35,520 --> 02:19:36,160 we've funded. 1535 02:22:15,100 --> 02:22:15,580 All 1536 02:23:22,110 --> 02:23:24,950 right, I believe we have one last presentation. 1537 02:23:25,890 --> 02:23:27,590 on right away. 1538 02:23:34,800 --> 02:23:41,160 One last presentation on right away acquisition by Miss Angela Leach J. Row from 1539 02:23:41,160 --> 02:23:41,620 textile. 1540 02:23:55,820 --> 02:24:01,340 Can everyone hear me fine? Good afternoon. My name is Angela Leach J. Row and I'm one 1541 02:24:01,340 --> 02:24:10,360 of the right away project delivery managers with textile in right away. As you notice this afternoon, 1542 02:24:10,980 --> 02:24:15,780 There's a lot of different steps before we get to this process to actually the right-of-way process. 1543 02:24:16,300 --> 02:24:19,140 For instance, Katherine is talking about earlier about the step. 1544 02:24:19,280 --> 02:24:20,900 The step needs to be in place. 1545 02:24:21,640 --> 02:24:24,340 Also, the advanced finding agreement needs to be in place. 1546 02:24:25,420 --> 02:24:35,520 Once steps all done, I will usually get notified by one of Mark's project engineers and projects coming up. 1547 02:24:35,520 --> 02:24:42,240 So with that, before we can actually get started, the main thing that most local governments 1548 02:24:42,240 --> 02:24:46,520 are looking forward to is when we're going to get the statutory letter to proceed. 1549 02:24:47,740 --> 02:24:55,620 So with that, there's a lot of steps within that process. So once we're aware of the project, 1550 02:24:57,360 --> 02:25:01,760 unfortunately I can't just go ahead and write a letter for you guys to be able to start. 1551 02:25:01,760 --> 02:25:14,020 One of the things I have to do is actually the review that executed aFA, and then I actually have to submit a request to the right away program office in Austin. 1552 02:25:15,260 --> 02:25:20,880 They have them place federal funds on the project and grant authority to proceed. 1553 02:25:21,280 --> 02:25:26,780 Once I receive that information, then I will send a letter to the local government to tell them to proceed. 1554 02:25:26,780 --> 02:25:34,620 Within that process, however, while you're waiting, you can do, you can do, you can do 1555 02:25:34,620 --> 02:25:38,160 title work in a prison work prior to that point. 1556 02:25:38,500 --> 02:25:43,260 And just one of those things that we actually want to keep the project progressing to 1557 02:25:43,260 --> 02:25:44,320 meet the elect date. 1558 02:25:44,520 --> 02:25:49,380 So if you're able to, do your title work, do your prison work. 1559 02:25:50,300 --> 02:25:55,840 We actually work through the local government with the provider that you have selected 1560 02:25:55,840 --> 02:26:04,620 to do the project. So a lot of times with that information, the provider will, I guess the 1561 02:26:04,620 --> 02:26:10,460 local government will select an initial appraisal and review appraisal. Once that information 1562 02:26:10,460 --> 02:26:17,220 is done, then it's sent to text.com and we have our appraisers take a look at that and 1563 02:26:17,220 --> 02:26:18,680 then gets approved by text. 1564 02:26:19,340 --> 02:26:26,480 Once that's in place, and you can actually start acquiring. 1565 02:26:27,560 --> 02:26:29,660 But I actually forgot one thing. 1566 02:26:30,100 --> 02:26:34,420 When I talked about the step in and place, the AFA environment 1567 02:26:34,420 --> 02:26:36,180 also has to be in place. 1568 02:26:36,580 --> 02:26:40,480 We actually had situations that local governments 1569 02:26:41,120 --> 02:26:44,480 had started the process before environmental clearance 1570 02:26:44,480 --> 02:27:00,380 What's completed before, there we see the statutory letter to proceed, and that's one of the things that you really want to avoid because when it comes to the part of being able to get your reimbursement, 1571 02:27:00,380 --> 02:27:07,420 Most likely, you will not be eligible for those funds because you didn't fall the process. 1572 02:27:08,740 --> 02:27:20,400 With that said, you pick your provider, you get your initial appraisal review appraisal, 1573 02:27:20,400 --> 02:27:30,420 Tech start approves that you already have the statutory letter proceed, and then you can actually start acquiring your parcels. 1574 02:27:32,020 --> 02:27:40,800 One of the things that I do, there's a lot of local governments that have been given the opportunity to start doing this process. 1575 02:27:40,800 --> 02:27:45,900 may be needed to this process. I'm probably the most, I'm the primary person, you'll probably 1576 02:27:45,900 --> 02:27:53,100 be talking, speaking with. And so one of the things that I did do do is when you're starting 1577 02:27:54,360 --> 02:28:04,580 to do your informational letter to the property owners, and then you do your initial offer packets, 1578 02:28:05,320 --> 02:28:09,960 and one of the things that I offer is to review the initial offer packets that you put together 1579 02:28:09,960 --> 02:28:13,780 to make sure that you have all the information intact. 1580 02:28:14,660 --> 02:28:19,640 And usually, once I look at one and we're in agreement, then you can go ahead and continue 1581 02:28:19,640 --> 02:28:21,740 with that acquisition process. 1582 02:28:22,520 --> 02:28:27,500 Hopefully, with your initial offer letter, you know, with the 30 days, hopefully the property 1583 02:28:27,500 --> 02:28:35,300 on her will like the price value on their property and the parcels closed. 1584 02:28:35,300 --> 02:28:44,420 If when the parcels close, one of the things that we like for people to do is not wait for your total project to be completed, 1585 02:28:44,920 --> 02:28:51,280 before you start asking or requesting for your reimbursement on your parcels. 1586 02:28:51,720 --> 02:28:59,300 So when she have that parcel closed, go ahead and start your reimbursement process information. 1587 02:29:00,580 --> 02:29:05,160 Again, I'm there textiles there to walk you through that process. 1588 02:29:05,560 --> 02:29:10,680 I usually deal with the local government on that, in official basis, to walk them through 1589 02:29:10,680 --> 02:29:11,080 the process. 1590 02:29:11,260 --> 02:29:14,960 So, if you're new, we'll lead to through that process. 1591 02:29:15,440 --> 02:29:21,400 A lot of times, there could be different parcels, there could be some easements, some 1592 02:29:21,400 --> 02:29:29,660 class, different situations, a lot of times, they're really unique, and we usually rely 1593 02:29:29,660 --> 02:29:33,640 to our text auto-turning on that type of information. 1594 02:29:35,320 --> 02:29:41,500 One of the other things I just remembered too before you can start this whole process is that 1595 02:29:41,500 --> 02:29:43,360 we have to have approved maps. 1596 02:29:44,940 --> 02:29:50,420 If the maps aren't approved, again, we don't proceed forward, and a lot of times what happens 1597 02:29:50,420 --> 02:29:58,420 is that the local governments will have a consultant that the whole work with and once the 1598 02:29:58,420 --> 02:29:59,980 consultant has completed the... 1599 02:30:01,080 --> 02:30:18,940 We have a preliminary maps. They get to have to come to text out for text out approval. So, anyway, that's pretty much the process you do. You do your initial offer letter 30 days. Hopefully the property owner will accept. 1600 02:30:19,540 --> 02:30:24,120 If not, then we sent out a final offer letter. 1601 02:30:25,080 --> 02:30:28,700 Within that time, we can also do a counter offer. 1602 02:30:29,120 --> 02:30:33,900 One of the things that's very critical with the counter offer is that they have supporting 1603 02:30:33,900 --> 02:30:39,240 documentation submitted, and they also have to have a sign letter from the property owner 1604 02:30:39,240 --> 02:30:41,960 in that packet. 1605 02:30:42,700 --> 02:30:50,480 I'm going to say the counter offer doesn't work during the final offer phase we're going 1606 02:30:50,480 --> 02:30:54,580 to do a dual path and it's going to go to ED. 1607 02:30:55,420 --> 02:31:02,380 Usually with the ED process that is handled through the local government, however let's 1608 02:31:02,380 --> 02:31:06,600 say if you have updated appraisals, the updated appraisals can come to text. 1609 02:31:06,600 --> 02:31:09,880 thought for review and approval. 1610 02:31:12,680 --> 02:31:14,780 I've been doing this for about five years, 1611 02:31:17,000 --> 02:31:19,040 and it's been 1612 02:31:19,040 --> 02:31:20,920 interesting to still have learning process. 1613 02:31:21,320 --> 02:31:26,580 And so with that, if anyone needs any assistance, 1614 02:31:27,340 --> 02:31:28,960 you know, I walk you through the process. 1615 02:31:29,420 --> 02:31:33,380 One of the things that we also take a look at is text 1616 02:31:33,380 --> 02:31:40,940 has really been evolving into performance management and tracking. So one of the things that we do 1617 02:31:40,940 --> 02:31:47,520 ask the local government to do is to send a project status sheet. And that kind of relates to what 1618 02:31:47,520 --> 02:31:55,140 one was talking to earlier about the quarterly reviews that we do at text. To see and review the progression 1619 02:31:55,140 --> 02:32:03,080 of the project, if we're doing really well, the project may get moved up, if we're having a little bit 1620 02:32:03,080 --> 02:32:10,100 difficulty you might get pushed back. But with the project status sheet that is required 1621 02:32:10,100 --> 02:32:18,380 from the local government, we used that information in our quarterly meetings and also in 1622 02:32:18,380 --> 02:32:23,560 our letting meetings, which Katherine had talked about earlier. And this information is actually 1623 02:32:23,560 --> 02:32:36,780 uploaded into our dashboard system, so everyone's able to review it at any level of the organization. 1624 02:32:39,620 --> 02:32:41,880 I'm trying to think it's late and afternoon. 1625 02:32:43,080 --> 02:32:51,620 I can't really think of anything else, but yeah, many questions, hopefully not. 1626 02:32:53,760 --> 02:33:01,200 Um, but, um, you know, my name is, um, if you want to write it down, it's, um, my email address 1627 02:33:01,940 --> 02:33:14,560 is Angela, that's A-N-G-E-L-A dot L-E-A-C-H at text.gov, and I'm available to answer any questions 1628 02:33:14,560 --> 02:33:20,740 and walk you through their process for local government acquisition. 1629 02:33:24,040 --> 02:33:29,780 It's 713-802-5753. 1630 02:33:35,320 --> 02:33:35,480 Hi. 1631 02:33:49,280 --> 02:33:49,600 Okay. 1632 02:33:50,020 --> 02:33:56,740 With the reimbursement, let's say once you're a parcel, once you have acquired your parcel, 1633 02:33:58,000 --> 02:34:05,740 That's when you can submit the paperwork which I can provide you a list through email of what's required for you to send in. 1634 02:34:07,000 --> 02:34:14,860 And that's basically the 80% that Mark was talking about earlier, and you can do that after each parcel closes. 1635 02:34:18,050 --> 02:34:24,410 Okay, yes. Okay. At the very beginning, yes, we have, we'll have to have approved maps. 1636 02:34:27,870 --> 02:34:42,610 Okay, yeah, we have approved maps, we have environmental clearance, and then we'll get a release authority to proceed and we'll get that granted through the right away program office. 1637 02:34:43,030 --> 02:34:52,230 And that's when I'll send out a statutory letter to proceed to the local government for them to proceed with acquisition. 1638 02:34:56,960 --> 02:35:10,200 Actually, when it comes to your appraisals, once the local government, whoever appraisers 1639 02:35:10,200 --> 02:35:14,360 are working with, they'll have an initial appraiser, a review appraiser. 1640 02:35:14,900 --> 02:35:20,500 Once that's completed, then that paperwork will be sent to text odd, and I'll be 1641 02:35:20,500 --> 02:35:22,740 the third review, and final review. 1642 02:35:24,980 --> 02:35:26,640 Yeah, we're doing, yeah, reimbursements. 1643 02:35:30,940 --> 02:35:31,580 Well actually, 1644 02:35:31,680 --> 02:35:37,220 I guess I do, I forgot about that. Yeah, so when the reimbursement package is submitted to text 1645 02:35:37,220 --> 02:35:41,980 thought, I do review it and make sure that the local government means all the requirements 1646 02:35:41,980 --> 02:35:48,640 for the reimbursement, and it's really important to follow the federal guidelines, but also follow 1647 02:35:48,640 --> 02:35:52,420 the right-of-way guidelines within TechStot. 1648 02:35:55,040 --> 02:36:00,680 Yeah, and I think, like I said earlier, we actually had a local government that they 1649 02:36:00,680 --> 02:36:04,360 follow the federal guidelines, but they didn't follow the right-of-way guidelines for 1650 02:36:04,360 --> 02:36:07,260 TechStot, and they were not eligible for reimbursement. 1651 02:36:18,280 --> 02:36:18,880 Yeah, 1652 02:36:28,200 --> 02:36:32,960 and that is based on also with your project status sheet that you can send 1653 02:36:32,960 --> 02:36:36,880 usually weekly or bi-weekly to text. 1654 02:36:37,940 --> 02:36:42,040 And we're reviewing that the whole time through. 1655 02:36:46,970 --> 02:36:47,330 Got it? 1656 02:36:47,650 --> 02:36:48,330 Thank you. 1657 02:36:54,960 --> 02:36:57,440 I just wanted to thank everyone for coming out. 1658 02:36:57,820 --> 02:36:59,940 Thanks a lot to text. 1659 02:37:00,220 --> 02:37:04,600 Staff for coming and trying to educate us so that we can make sure 1660 02:37:04,600 --> 02:37:10,340 projects get developed and get implemented in a timely manner. 1661 02:37:11,020 --> 02:37:17,260 So just to close things out, this, the presentations will be posted online, we'll send out a link. 1662 02:37:17,440 --> 02:37:20,620 If you sign me in, we'll make sure we send out a link to those. 1663 02:37:20,620 --> 02:37:28,260 And we'll make sure that for the livestream folks that you can search our HJC website and get straight to the materials. 1664 02:37:29,140 --> 02:37:32,020 With that, we'll close it up and thanks a lot for coming out.