[0:00] Spaghetti. >> Okay. Thank you all very much for being [0:05] here for this special meeting of the city of Fomit City Council. Uh today is [0:12] Wednesday, April 29th. It's currently 7:12 p.m. And we'll start with a roll [0:18] call. >> Spencer Irwin [0:22] » here. >> Nan Crocker [0:24] » here. >> Teresa Nelson [0:26] » here. >> Brit Salsa [0:27] » present. Mayor Christopher McMorren >> present. Okay. Um the only business on [0:33] our agenda tonight is um discussing the invitation to bid responses for the [0:39] water treatment plant this plant project. Um and then we'll head out. But [0:46] before that we have public comment if anyone's here for public comment. [0:51] I don't believe we have anyone registered online. So, um, now I turn it [0:57] over to our city manager to discuss the intent to bid process. [1:01] » All right. So, we did get, uh, two bids in for the water treatment plant. Um, [1:08] upon receiving the bids, the city staff and then city attorney helped prepare a [1:14] questionnaire to help determine responsibility. responsibility and [1:18] contract language means that the there's some Oregon statute language where the [1:23] the bidder has to show that they are responsible or able to carry out the [1:30] contract. And so we asked questions about history of previous projects [1:35] um uh size of the projects kind of that um nature. Talked about um we got [1:43] resumes from their um higher up employees that were going to be [1:48] overseeing the project, their general that was going to be on site and all [1:51] that type of information. So we got the questionnaire out. There was a protest [1:56] to the questionnaire on some of the language that was used. Um was a little [2:01] more narrative than what the OS specific language is. And so we revised that back [2:07] down, stuck a little bit closer to the exact language in the OS and sent it [2:12] back out to both biders and got both responses. Those were due by 3:00 last [2:16] Friday. We got both of those. I reviewed those with the city attorney, public [2:20] works director, and the city engineer. And we believe based on the responses [2:24] that both biders are qualified, not qualified, are responsible. They've [2:29] shown they're qualified as responsible biders. And so, uh, both biders are [2:33] good. And so, we'll be going with the low bid, um, per state procurement laws [2:38] and and rules. And so, I've got a letter that came in just today from the city [2:44] engineer and ORE, Inc. was the low bid. uh Sladeen uh contractors [2:53] uh was the other bidder uh not to be awarded. [2:58] Once the notice of intent to award goes out, there's a 7-day protest period [3:03] again. Um and then once we're past that 7-day [3:07] period, then we'll enter into contract negotiations and get our contract. [3:11] Shortly after contract negotiations, we'll move forward into pre-construction [3:15] meeting and start getting answers to like when are we going to start, when [3:19] are we going to be done, when is Flo Community Services driveway going to be [3:23] impacted, and all of those types of questions. So, um for tonight, we're [3:29] just looking for approval to go ahead and release this notice of intent to [3:32] award. Um, I can tell you that the um [3:39] low bid came in at 13.8 million. Um, higher than what our engineers [3:47] estimate was. Um, both bids were higher than the engineers estimate, which we [3:51] weren't overly surprised about. Um, there are some specific items that we're [3:57] looking at perhaps being able to shave off of this project, which is why we [4:01] don't have a full narrative there. Um but even with the projects we look to [4:05] shave, we did look at that really closely and even if we shave some of the [4:09] projects off that were listed as optional projects, um the bidding [4:13] preference or the bidding sequence is still the same. The low bid was still [4:16] the low bid even if we remove a couple items that were listed as optional [4:20] things. So we we did look at that very explicitly, but we didn't make any [4:25] decisions at that point on what we were actually going to move forward and [4:28] whatnot. as an example, the well on North or the well on South Ninth Street [4:33] is in there as an option to get that up and going and try to get that connected. [4:37] It's not something that has to happen with construction of the treatment plant [4:40] getting that online. And so that more than likely is and one of those optional [4:44] things that we won't do in order to save some money today. We can do that some [4:48] point in the future. If we need to rehabilitate that well and get it [4:52] connected, we can do that some point in the future. We're just not gonna do it [4:55] as part of this project in order to save some costs there. So, um, so I don't [5:00] have an exact dollar amount, but I can tell you it won't be any more than the [5:02] 13.8, which included every all of the optional items, right? And so, um, we'll [5:08] get the notes of intent toward out and then we'll, um, get through the protest [5:13] period and then we will, um, come back with the agreement for the city to look [5:19] at for approval of of those, um, of the contract. [5:25] I'd like tonight to um I'd like tonight to get approval to [5:30] release the notice of intent award and also direction to go ahead and enter [5:33] into that contract agreement and get moving forward because time is of the [5:38] essence. Um both biders are very aware of the time constraints that we've got [5:43] with the ARPA funding that needs to be spent and reimbured by the end of the [5:47] calendar year. Um, so I'm even waiting until our May meeting that's losing [5:53] another week and a half or two weeks on the project. So, uh, if the council's [5:57] comfortable with giving staff a little bit of lenance to the air, I'd like to [6:00] get, um, direction to go ahead and enter into that contract and get moving [6:03] forward. >> Thank you, Chris. Uh, any questions or [6:07] just councelor Crocker? >> Uh, we had talked about um, do they have [6:12] a large enough uh, personnel to work longer hours to get it done on time? or [6:18] are they limited on? >> We weren't able to ask like qualifying [6:22] questions to qualify them for the job. It was listed as [6:27] » no qualifications necessary. We could only ask questions about their [6:31] being a responsible bidder or not. Um that's not something that we could [6:36] address. We will be looking at their schedule and looking at um that during [6:43] the contract phase and trying to ensure that we can frontload that project as [6:49] much as possible. Um I can tell you [6:55] that I think it's still possible. I I I don't think we're I mean, we're in [6:59] danger, right, of not being able to get all that, but um you know, it's not like [7:04] we're a month out from having to have it all done where it's impossible. I I [7:07] think there is still a good possibility that that work can be done and that [7:11] money can be spent down in the time frame that we have, but we do need to [7:14] get going. If if we get two months into this and hit a substantial delay, we [7:19] could be in jeopardy. So, there's definitely concern about watching that [7:22] time frame, watching the timelines closely. And they do understand that or [7:26] you have that. Yep. They they know that there's ARPA funds involved. They know [7:30] that they need to be spent this year so they're aware. Y [7:34] » thank you. Other questions or discussion? [7:41] Okay. Um I guess I'm assuming we'll get some kind [7:46] of update on this at our May meeting. In May, we'll have the letter with the [7:51] breakdown and the options that we're choosing to not do. We'll have a total [7:55] price. >> Okay. [7:56] » And we'll probably have it drafted. I mean, we won't do the full contract, but [7:59] we'll have the kind of the high points of the contracts and time frames. [8:03] » So, hopefully we have all that wrapped up by May is the goal. [8:06] » Okay. >> And what's your ask, Chris? What are you [8:11] looking for? uh a motion to direct staff to or direct the city manager to release [8:17] the notice of intent to award and following the 7-day protest period to go [8:22] ahead and enter into contract negotiations with the low bid. [8:26] » So move. >> Okay. Is there a second? [8:29] » Second. >> Okay. It's been moved by councelor [8:32] Salsa, seconded by councelor Crocker to direct staff to release the notice of [8:38] award and following the 7-day protest period, move forward with the contract. [8:44] Is that right? >> Perfect. Look at that. Um, any [8:48] discussion on that motion? [8:53] Seeing none, would all those in favor please raise your hand and say I. I. [8:57] » The motion passes unanimously. Thank you. [9:01] » Now that you've said yes, [9:04] » I I do just want to make you aware we are actively working with Business [9:11] Oregon, some of our elected officials at the state level, the federal level to [9:17] try to get any wiggle room that we can out of making sure that we can use those [9:21] ARPA funds. So, I just want you to know that your staff is working diligently [9:25] and looking in at multiple scenarios. um we're not resting on our laurels and [9:30] assuming that we're going to get this done and be able to do it. So there's I [9:34] won't go into all the different details because there's about four or five [9:37] strategies that we're kind of going after right now to ensure that we can [9:40] maximize our use of the ARPA funds that have been awarded to us already. So um [9:45] just want you to know that we're we're aware we're concerned. We're trying to [9:49] even look at like the water reservoir if there's a way that we can help get [9:53] reimbursement for some of that instead of just all the money we did there which [9:56] would be about $4 million we can get reimbursement for right now which would [10:00] mean we only got like four million to spend between us. So there's some [10:04] strategies that we're trying to do on the back end but it's going to take some [10:08] flexibility on business Oregon where they can be flexible. They've got very [10:11] stringent guidelines they have to follow as well. It's their federal dollars that [10:15] came to the state that had very tight cords and strings attached to it, things [10:20] they have to do. Um, and they're trying to work with us as well. So, anyway, I [10:26] just want you to know staff's working hard to make sure we maximize that. [10:29] We're not just hoping for the best. >> Um, thank you very much. [10:34] » Yeah. >> Um, what was that deadline? Was it [10:36] October or was it December? >> December. [10:39] » December. By the end of the year, everything has to be spent and re [10:44] submitted and reimbursed. So, >> our target is like November. [10:48] » Okay. >> To try to finish spending the money and [10:50] give ourselves a half, two months to get reimbursed. [10:57] » Um, yeah, I I appreciate that. I know something I've talked about with the [11:01] city manager is obviously right now our focus just needs to be on getting this [11:06] done. Um, and I am grateful for all hands on deck getting it done. I think I [11:13] just want to kind of put a flag down for the council that when it is done, I want [11:17] us to take a serious look back at some of the things that made this get so [11:21] delayed. I think it can be tempting for the project to be done to be like, "Oh, [11:25] okay. We're done. Moving on." Um, and I just want us to do a little post-mortem, [11:29] I think, after the project. Um, just to make sure we don't run into these same [11:34] types of delays in the future. Obviously, this is somewhat of a unique [11:38] case with the ARPA funds, but um just some of the engineering delays and other [11:43] concerns I want us to have like a serious conversation about down the [11:47] road. So, >> yeah, [11:50] » that's all we have. Thank you. >> All right, I'll keep you posted. [11:54] » I brought two drinks. [12:00] Okay. If there are no final uh comments, questions, discussion items, then I will [12:06] adjourn this meeting at 7:24 p.m. and we'll see you in May. [12:12] » Thanks.