1 00:00:00,680 --> 00:00:29,900 So now that they have improved this, this type of treatment system or this specific treatment system, we're requesting to, you're approval to purchase it simply because, if the contract purchases, they're going to be paying taxes and there will be attention upcharge as well. So, rather than that, we're saving 17% of that. So we just, and there is a 30-week lead time too. So it kind of plays well into the contract period as well. So we're just requesting your consideration in the purchase of this treatment system for the perpetrator as well. 2 00:00:29,900 --> 00:00:32,300 for the total of $741,800. 3 00:00:32,800 --> 00:00:34,980 And you just need a measure to get through the great existence. 4 00:00:35,520 --> 00:00:35,760 Yes sir. 5 00:00:36,000 --> 00:00:36,420 You look good. 6 00:00:36,740 --> 00:00:37,420 Yeah I'm the same. 7 00:00:37,640 --> 00:00:38,360 But they're not having the course. 8 00:00:38,820 --> 00:00:46,400 OK, so I want to make sure that the city of Ringo is going to purchase this. 9 00:00:46,500 --> 00:00:46,780 That's correct. 10 00:00:47,020 --> 00:00:47,240 Yes sir. 11 00:00:47,760 --> 00:00:47,980 OK. 12 00:00:48,200 --> 00:00:50,020 And it will be reimbursed through the wind grant. 13 00:00:50,280 --> 00:00:52,240 That's what, OK, that's what I was going with this. 14 00:00:52,560 --> 00:00:55,200 OK, and the number, you just have to phone with the guy. 15 00:00:55,360 --> 00:00:56,960 And the number is this number. 16 00:00:56,960 --> 00:01:01,800 that that number is is also has freight included and you know there's an 17 00:01:01,800 --> 00:01:05,960 exception there for terrors and he Chris the representative told me that he 18 00:01:05,960 --> 00:01:13,410 did not expect any additional part is for terrors at this time okay on day 19 00:01:14,110 --> 00:01:19,470 and the sport it's time thanks sir and the Peter's line project is officially 20 00:01:19,470 --> 00:01:24,670 complete or I think they have a little bit of grassing at finish to you but the 21 00:01:24,670 --> 00:01:29,370 The change order that's in front of you is a total of $8,200, $39.25. 22 00:01:29,790 --> 00:01:37,110 This is mainly because the bid was based on trench patching, going on Peter's lane and 23 00:01:37,110 --> 00:01:37,910 Depot Street. 24 00:01:38,530 --> 00:01:44,030 As you may know, both of those streets were completely full overlay with asphalt so that 25 00:01:44,520 --> 00:01:45,190 did increase. 26 00:01:45,610 --> 00:01:49,350 But all in all, it made those areas much better. 27 00:01:49,350 --> 00:01:55,270 Peter's line is one hundred percent better that section of depot street did have some base values so 28 00:01:55,270 --> 00:02:03,730 I think I think it's a win-win for both the report and the and the water department. The 88,000 to $30,000 to $25 cents actually is 29 00:02:03,730 --> 00:02:12,530 reimbursed for the jeep alone which we have full principal in general's office. So we request your approval on this string to work. 30 00:02:12,530 --> 00:02:16,270 any questions on the phone? 31 00:02:16,910 --> 00:02:17,610 Thank you. 32 00:02:18,570 --> 00:02:22,990 My name is Jim.