[This transcript was generated automatically from audio using AI and hasn't been reviewed by a person -- it can contain mistakes, including plausible-sounding sentences that were never actually said. Treat it as a starting point, not a verbatim record.] [0:00] Public government meeting is brought to you by East Works and our local cable subscribers. [0:17] Welcome to the Southampton Planning Board meeting for September 2nd, 2026. I have a quorum present. [0:27] Paul, for God, our member could not make it this evening. [0:33] We have Bob Briggs down the end, Jim LeBree, Mark Darnell, myself, Paul Deem in the chair. [0:39] And our agenda tonight, I'm going to take it out of order because we have a letter from [0:49] Manhattan, LLC, which was a continuation of a public hearing for 4353 pleasant street. [0:58] And I have a letter to read requesting a continuance [1:09] August 28, 2026, Thomas, that's [1:12] Planning Board, requests for continuance of public hearing, site plan review application for 43-53 pleasant streets, [1:20] South Hampton, dear members of the Planning Board, we have a blue wave, man, hand, river, LLC, Weston, and Sampion, and Generous Inc. [1:28] Respectfully request that the public hearing for the above reference site plan review application schedule for September 2, [1:35] 2026, be continued to the Planning Board meeting schedule for October 7, 2026. [1:43] Continuance is requested to allow the Planning Board's peer review consultant additional [1:48] time to complete its review of the application materials and for the applicant to respond [1:53] to any resulting comments. [1:56] The applicant appreciates the Board's consideration of this request. [2:00] Should you have any further questions or require any additional information, please feel [2:05] contact me by phone or by email, sincerely Western and Samson Engineers, Cam Gozine Project Manager. [2:15] So, given that request, I asked for a motion to... [2:21] Before you decide, [2:25] we cannot talk about anything going forward on this until the next meeting. [2:31] You know, the continuous is happening because the peer review is not complete as was stated in the letter. [2:38] We need to peer review to continue it, and because it's not ready, and was not going to be ready until after September 10th from Bercher Design Group, who was the peer review company. [2:49] Then, Mr. Harris is out of town and we have some conflicting dates, so we selected October [2:59] 7th as the next date, and we are not going to hear any discussion or comments on this [3:05] until October 7th. [3:07] There were many questions and concerns brought up, set of July 20, by that. [3:13] That will, myself, down. [3:16] Any other need to go up there and ask questions and how many answers do we get? [3:20] And they will be addressed October 7th. [3:23] Oh, I can see where this is. [3:27] Okay? [3:27] The focus will be on the peer review. [3:29] Everything else gets swept on their own. [3:31] They have, they had the list of all your concerns that will be addressed at that time. [3:39] Okay, do I have a motion that this hearing for manhand L.O.C.B. [3:46] continue to October 7th, 7 p.m. [3:49] 7 p.m. [3:52] I'm moved that the hearing for the post-Demritory facility be continued until October 7th. [4:02] May I have a second? [4:03] I'll second it. [4:06] Motion has been made in the second. [4:07] to continue this hearing for Manhand L.O.C. for October 7 at 7 p.m. any of the further discussion? [4:16] All in favour? I want to speak about it. Right. [4:31] So that is that for that particular agenda item. [4:38] We're moving on now to a continuation of a public hearing for [4:42] site plans to warm water in special permit for KBIP LLC for a 38 college highway, [4:52] which is scheduled for this evening. [4:55] And we have a little bit of a caveat to add to that, which I'd like our consultant to refer to because it seems like in my estimation, [5:09] and he can richer you can certainly address this that the cart was put before the horse because [5:15] ZBA also has a permit in front of them regarding the same project and they are not going to [5:25] meet until September 23rd. So Richard, would you expand on that? [5:29] We back up about a year and a half or so ago, the Planned Ward closed to revise his own [5:38] by-law to change all the special permits from some ZVA, some select board, some Planned [5:45] Ward to all Planned Ward. [5:48] And we did that in the Youth Regulation Schedule. [5:51] While we did catch was in the water supply protection district text, it says a commercial [6:02] and or industrial use that's allowed an underlying district requires a special firm from [6:08] the ZBA. [6:11] Therefore, since this project is within the water supply protection district, [6:17] Not only does it require a site plan to be from Plainboard loss requires a special [6:22] program from the ZBA, and it's clear within the context of all the MEMS that have been [6:28] made. [6:28] Zumballot, that was not anticipated, because it also says in the section Zumballot on special permits [6:38] that in the Plainboard's rules and regulations, where a special permit is required in [6:43] the PIN Board shall require a consolidated PIN application. [6:51] Obviously, we're going to see VA for special PIN Board for PIN [6:56] View, PIN Board can't require a consolidated PIN application or review process. [7:02] So that is you need to be clarified in future amendment. [7:08] But for PIN approval to actually be done, the use has to be permitted [7:15] and without a special permit, this use in this location is not permitted. [7:23] Therefore, the Plain War can't really issue a cyclone view decision until... [7:30] All the special permits, grant by ZBA, if they would do that, and ZBA make any conditions. They have come [7:39] back and apply for a new cycline review, go through the new hearing process, oh, nine yards. So, I think [7:48] the best approach on this is to hear the revision been made. The plan board can then [7:55] of these changes are set up and meet your approval and ask the Plan War Chair to communicate [8:04] that to the ZBA so they know we'll report a satisfied with it and then continue the hearing [8:11] until a time at the ZBA has made their decision and you can then incorporate the ZBA decision [8:19] engine engineers. [8:20] Now, just to make it clear, I had no prior knowledge of this until I went to town hall [8:25] last week to pick up the revised plans that your office provided. [8:32] So I get in there on the 13th. [8:34] Are these yours, too, and here was the whole mother's set of plans that we had a couple [8:40] of weeks ago in an application to the ZBA, for a special parent, and I said, hmm, so I asked [8:49] Richard, they said, why would they be submitting to these CBA and he told me that should have [8:54] been done prior to this coming before us, which was, which is not going to, in the end, [9:02] affect the process, because it didn't link in that process. It's just going to delay it a [9:08] couple of weeks because they're not going to be eaten to September 23. So we won't know until [9:14] our October 7th meeting when we meet again, the outcome is they had, but in the meantime, [9:22] I agree. [9:24] You know, the change is you're going to address tonight from the last meeting. [9:28] We can hopefully find acceptable. [9:32] And then we cannot close the public hearing or not, even though you need, that's right. [9:40] Okay. [9:40] leave open container, if everything is set for here, [9:45] container for the sole purpose of addressing [9:49] ZBA special permit decision. [9:53] We sure that's addressed in some time. [9:56] Because even at a minimum, it needs to recognize [10:01] the ZBA special permit applies to this. [10:05] Ideally, they could submit at the same time, [10:08] and we could run means concurrently with it. [10:13] Well, that didn't happen, so. [10:15] But at any event, I have your letter [10:17] and the board has your letter that you sent [10:19] about some of the questions we had when we met the last time. [10:24] Vehicle turnaround, swept path analysis, [10:28] screening, and sight lag. [10:30] So, your name against her? [10:32] I am Mike Bohn. [10:33] Mike Bohn. [10:35] And I'd like you to address those issues that we've brought up the last time, please. [10:42] So first issue, the vehicle is sweat path for the fire trucks in garbage trucks. [10:50] We performed that analysis. [10:52] Just to make sure my phone's ripped in raw, direct associates that can solve it for the applicant. [11:01] So we did the vehicle track movements, it didn't result in the use to the pervious areas or anything like that. [11:13] What we did was we just striped off this area through Spartan spots right here. [11:18] We just striped it off and this is the far truck turning movement and the garbage truck turning movement. [11:24] And we're able to turn, come into the site, do a free point turn and drive out of the site. [11:33] And we use the specs that were given to us, [11:37] or he stamped in the latter truck, [11:38] which is the largest emergency vehicle that they have. [11:43] So, do you have that? [11:44] I believe. [11:45] Before you go any further with that, [11:46] we have the Fire Chief here, our rich facility, [11:49] and Rich looked at the plan as well, [11:51] and he had commented that it wasn't a problem, [11:54] but you want to maybe come in on Rich just for the right time. [11:57] Yeah, I went over the plan, [11:59] say, well, it will find the reason. [12:02] If we ever needed a call for a ladder, we stand to become a stand in a ladder job [12:08] and if they're longer than our fire engine, so we'll let it happen better. [12:18] Does this building two stories? [12:21] One story. [12:22] One story. [12:26] And you were all right with the entry coming off the street and turning coming in there. [12:31] And then being on their 75-100 square feet, it does have a wider perspective. [12:39] The power hydrant is a fine, [12:42] and there's a fire hydrant next to the drive-up as well. [12:52] The next issue was the photometric plan, the lighting. We have that as well. [12:58] with pages that seem it's SL-1 and we we've designed for that we know [13:10] light trespasses to the neighbor's property or or onto the street although [13:17] the light will stay on our site. [13:36] And the lighting that once again is on the [13:38] building there's no lighting on poles in the parking lot. We did have to add some [13:44] holes to let up the area on the other side of the building and then there is a pole to [13:50] let up the drive-out as well. [13:54] Those are indicated in the front here, I'm looking, a couple of them in the front on the [14:00] colloquial wayside, is that correct? [14:02] Yes, there should be, there should be, there should be, there should be, there should be, there should [14:05] be, there should be one on the entrance, one on the entrance, one on the entrance, and one [14:11] You know, seven [14:17] on the building. [14:22] Mark, you've got any questions on the lighting at all? [14:25] It's a privilege, you know? [14:26] I don't know any questions. [14:28] Is it going to be 24 or seven at night? [14:31] Or is it going to be just 24 or seven? [14:36] It's more of an operational question, I guess. [14:39] Which, you know, we don't have a tenant yet. [14:41] So I can't safely answer that yet. [14:45] So, not sure about that. [14:47] to be honest, which have these huge roots, I'd like to be honest, I'll make, but the [14:53] photometrics look good that you're seen to be no spill on a Jason's company. [14:59] Yeah, I'm... [15:00] I'm noticing that on the other side, what I can't read it because even my glasses aren't powerful enough. What's the, what's the spillage over the side there? Is that, that's not significant? [15:11] Well, if it's zero means zero means no spillage. [15:15] Well, I can't, as I say, I can't, I can't read it. [15:18] You can't look at the big one. [15:19] Yeah, I don't see anything other than zeroes on the upside of the line. [15:24] In fact, this is both size line and zero. [15:27] This is bigger for you. [15:30] Do you see that on the SL1? [15:35] This is too small. [15:38] Any other questions on the lighting? [15:41] Once. [15:41] We're just trying to get to the bigger page. [15:53] I don't know. [16:04] I'll have no questions on the lighting. [16:07] All right. [16:07] How about screening six foot adjacent to the abutter to the northeast. [16:11] has been added, sheet C4. [16:15] If we added a six-foot stockage fence along that side line, the arbor buddies over there [16:21] at the last meeting, [16:26] and that should block any light from the headlights or anything like [16:29] them. [16:30] Also, any noise from the cars, or anything like that. [16:36] And the fence, from what I remember the last time, has got to be so big to let the turtles [16:41] go through. [16:42] Well, that was only good to do. [16:44] I'd love to have a little national heritage. [16:47] But the chickens aren't going to get under there, are they? [16:59] It should be such as, I'll stick on if you're on my opinion. [17:02] Why wouldn't you? [17:05] Did we have any other... [17:06] Why would I say everybody? [17:07] No, I'm just saying it. [17:08] I'm just saying it. [17:09] I'm just saying it. [17:10] Do you have a question for the board? [17:12] The changes from this submission? [17:16] No. [17:16] I think they're going to prove it. [17:18] I have a question, somebody asked me in an email, I couldn't answer it, but I hope for [17:24] our way from this site plan is to the river, is it more than 200 feet or less than 200 [17:32] feet? [17:33] So this is the river up top of your manhand river, so this line river is dashed line, that's [17:41] the 100. [17:43] So someone asked a question, he thought, in the past, the less it had changed, that [17:48] regulations used to be 200 feet. [17:52] Very, it's jurisdictional within 200 feet. [17:56] But the air 100 is understandable, well, generally uninstirable. [18:01] The outer 100 foot, you can get approval to do work in 70 to 50. [18:07] Yeah, we're going to concomme a couple of weeks from now, September 20th or something like that. [18:15] All right. [18:18] So, do you have approval from Concomment yet? [18:22] Not yet. [18:23] The last meeting they had asked for the septic plan to be submitted before. [18:26] We have submitted the septic plan. [18:29] So, at the next meeting, hopefully we can get approval. [18:32] So, hopefully, October 7th, we'll have ZBA's Fesh Permanent and Concomment approval. [18:37] That's the hope, yeah. [18:38] Because that's the other issues. [18:41] Inga's Fesh Permanent, if Concomment changes the regard change in site plan, [18:45] They'd have come back on this, on this resource also. [18:52] So, if they make changes to this, anything on the plan, then they have to come back. [19:00] So, you want to be sure that no one do you have special permit laws that they've come come? [19:06] No, we're south-hally, we didn't always write to the con-com issue their decision, but we have a [19:12] level from the conservation administrator that they're satisfied with it, [19:20] because I always [19:20] can request a chicken leg, who makes the decision for his concomo planable concomo planable. [19:34] Any other questions about the site? [19:41] Hearing none, then, I guess pending the approval of ZBA, I'm going to ask one or the question. [19:46] Okay, go ahead, Mark. [19:48] For you. [19:48] For you. [19:49] This is also for a storm or permit. [19:51] How are we addressing that tonight? [19:55] Stormwater. [19:58] I would not, I would just continue everything until, [20:02] October 7th. [20:04] In case there's any changes that result in changes in [20:07] per-visurface statement, dress all that. [20:09] And your motion, since Concomme has act on yet, [20:13] until October 7th, for Purpose of Incorporated [20:17] and any changes required by Concomme, [20:19] or by ZBA in conditions of their decisions. [20:27] Is there anything on stormwater you want to, [20:30] can you address anything with stormwater tonight? [20:33] Or is that someone else in your office? [20:35] I'd be happy to answer any questions. [20:37] Mark, do you have any details you have [20:39] in your calculation of last time? [20:41] I actually need to be. [20:41] Last time you said you were fine, didn't you? [20:44] Didn't you appear a view of the correct? [20:47] I think it warned you enough. [21:00] That being said, entertain a motion to continue this to our October 7th, it's 7 p.m. [21:12] I will contact, I believe they'll be meeting between now and then. [21:17] I know ZBA has their schedule for the 23rd of September. You said they'll meet September 20th. [21:23] Don't hold me to that day. I don't know the excellent. [21:25] It's around that date. I will confirm that. [21:31] So, a motion to continue this application for 38 college highway for campbrothers to October 7. [21:42] To be included language to welcome corporate aid and address any changes from the ZVA or Association Commission. [21:50] To incorporate new conditions or other decisions of the ZVA or concom. [21:58] So moved? [22:00] Yeah, so moved. [22:01] There's [22:07] a second. [22:08] I'll second. [22:09] May I have a second? [22:10] I'll second. [22:11] I'll second. [22:13] Hold on, favor. [22:14] Aye. [22:17] Okay. [22:18] Thank you for coming by for such a short meeting. [22:21] I'll start again. [22:23] And hopefully we'll have some final results for you then. [22:28] Thank you. [22:37] Is there any other business, any other committee reports, or anything that anyone you would like to discuss, sort of mentioned? [22:45] I have a warrant. I need approval from the Daily Hampshire Gazette. It was for three legal notices. One was for man hand. [22:53] One was for Atlantic Seltower, or Atlantic Communications, and one was for Mr. Plastawa there, [23:02] the residential storm water over on Crooked Ledge, in the three of them totaled $127. [23:09] $127.93. That asked for approval to pay that. [23:18] So moved. [23:20] Motion by Jim, do I have a second? [23:24] Second. [23:25] motion made in second all in favor and [23:32] this is a good time. I've talked to Jeff Lacy with [23:39] rural plan associates. [23:42] The type of thing they do, he does is similar I do and I've talked [23:47] about the positive that since I'm not going to continue at the next June if he be interested [23:53] in doing work and he is. He tried to look more than me and I shared some of the Paul [24:05] Ballon. One thing he asked me in the email yesterday was he'd be happy to attend the [24:11] Plain Board Meeting to see if it's a good fit. I'm going to tell you how I feel about that [24:18] if you own vitamin, if you don't, I mean, tell me every, like, maybe attend, meeting [24:24] sometime near future, to see. [24:27] Maybe after the first year, when the fireworks are, or maybe before the fireworks. [24:34] Maybe with the fireworks, maybe you can tell me what's the wash of the fireworks? [24:38] Well, you can tell me he's welcome to attend any meeting he'd like to watch them. [24:44] Yeah. [24:45] Now, they might be good up to him if, if, if, if, if, if, if after the firework is made, there's [24:50] time we all had a discussion with him, but it might be given, see how the board works, and [24:55] see if he thinks he could work, see, see how professional we are. [25:01] I don't let y'all be aware that the, he, he, he, he, he charges, hunders and arvers, my, [25:07] And, uh, why he told me the town, he's didn't seem to work with now. [25:11] They budget 10,000 a year, it doesn't ease it all, but that's what they budget, which is not an unreasonable amount of budget for it. [25:24] So that's something else you all may want to be thinking about too. [25:27] What challenge is that Richard? [25:29] What challenge? [25:29] What challenge is it? [25:30] He didn't tell me the channel. [25:31] I don't know. [25:33] I think it's weightly in it. [25:35] I don't know. [25:35] It's like a question, the process of hiring, we had to send out the RFP for the people, [25:41] which is higher to the extent that we need somebody. [25:43] Not even as below a certain level, it depends on your peer, see, to start. [25:50] I've done a thing to 110,000 usually is, don't have to. [25:55] There's one of the surprising, say, 10,000, because you're like, [25:58] a contract with Leningenburg, they made from 99, 90, and then they would amend it as necessary [26:08] to go, but the niche contract was under 10,000. [26:13] So, I didn't see what I had typically been doing with Richard these past years and there [26:19] was Smith before him. [26:21] I wouldn't ask him to come to a meeting for an A&R or residential solar or residential storm water type of thing. [26:32] It's like the big projects we had before us that need some of the more technical assistance. [26:38] So you didn't have to attend the meeting and they tried that way to keep the cost down. [26:42] And hopefully going forward I can do the same thing because I don't personally don't think I need Jeff Lacy here for A&Rs [26:49] But you might want to, might want to, for the applications to them to [26:54] take a look at them, see if there's any, such as, you had a residential stormwater [27:00] which they, the applicant didn't properly reference the town code, and that result in [27:08] advertising, not being correct. [27:10] No, things like that is good to send, just for them to check that out. [27:17] So, my one thing about that. [27:18] that's understood. [27:23] Because if it gets to 10,000, hopefully it won't. I'm going to have to [27:29] ask the town for that, because I revolveing fun to money right now is $67 [27:39] ,000. And that [27:40] is only because of the solar project, Pleasant Street, which was in 5,000 feet right there. [27:48] prior to that I was pretty bare bones because I think this year the only a lot of me [27:56] five thousand dollars in the budget. [28:02] And I would suggest that you think [28:04] about asking for a operation. Pain Bush always had an appropriation term, but I'm [28:09] sorry they really should. That's my opinion. Timing should appropriate funds to [28:15] for the plane board. [28:17] Absolutely. [28:19] Of course. [28:22] Even with the plane director, like in South [28:24] Ali, until they changed the town charter, [28:31] the planning [28:32] staff budget was within the plane board budget. [28:36] And they changed the town charter, they put all those [28:39] and town minister. [28:40] But it's not uncommon even if they plan a town planner [28:46] to have the budget as part of the Pineapple Budget. [28:53] Speaking of RFPs in whatever, George Russell from Conservation, [29:00] and we have a discussion Richard was in Anna, [29:04] because they have need for peer review on occasion. [29:08] We do certainly. [29:10] I don't know about ZBA sometimes does, [29:12] But in any event, he created a job description to send out [29:19] for an RFP for... [29:20] It was a consolidated peer review. [29:23] A consolidated peer review. [29:26] So if we need one, the town has one on the contract, [29:29] so we don't have to go out and submit and look for a different review. [29:34] And on that journey, works, there may be situations such as a cell tower, [29:39] which has specific skill sets that most engineering firms respond to their RFP are not going to provide. [29:48] And that's when you had to bring in the special consultant for that. [29:52] And, typo, control and respond, there's going to do the site plan review. [30:00] The GONBIA do a conservation review, the GONBIA do a storm overview, but we can get into tank [30:08] demand such as the RF frequency for a cell tower, the federal regulations governing house [30:17] cell tower functions, and what, and permanent, that is a separate question. [30:23] What about the solar with the best systems? [30:26] What about solar with best? [30:29] That might take expertise. [30:31] That might have depends on how the town approaches it. [30:39] Okay. [30:43] Unrelated. [30:44] Can I just ask a question regarding upcoming meetings in public speak? [30:53] And how do manage that? [30:56] a manager? Well, yeah. Well, it's a good question because, all right, so how many [31:03] continuance is we have no matter what? The public is there. We can't. [31:10] Laws them to speak at every public hearing? No, you can't. If you continue [31:16] in public hearing, you, and that's how it's put on the agenda. Therefore, the [31:28] allowed the discussion of the substance of the application. [31:33] Right, I understand that. [31:35] That's not what I'm talking about. [31:36] When the hearings continue, [31:40] yes, the public can speak. [31:42] The board can restrict discussion to new items, for instance, if Mr. X has said the noise [31:55] ZXZ and then Newher and he says it and then Ms. Y wants to say the same thing. No, we've [32:01] done it so you don't have to allow. [32:07] So just take it one step further at every [32:12] continuance and now there's a hearing. Can all the same things just be brought up every single meeting. [32:20] They can, but they shouldn't be, you should be restricting them to have new information like the top. [32:29] So that's allowed, that's what I guess I'm asking. [32:31] Yes, but it's news being new information on that topic. [32:35] Not the same things they've already said. [32:38] Now, they can't bring the same speech they did. [32:41] Two months ago, two new hearing, because that's already been heard and part of the record already. [32:46] It's not a repeat here. [32:49] Right. [32:50] In other words, otherwise, you'll never finish a hearing. [32:52] In other words. [32:53] Well, that's what I'm concerned about. [32:54] I'm concerned about. [32:57] Right. [32:58] It's why the chairman gets the big bucks. [33:02] I have to mention the board. [33:08] Okay. [33:09] So there's some. [33:10] Yeah. [33:11] It's a judgment called by the chair. [33:15] If it's a redundancy, redundancy, redundancy, [33:18] no, it needs a new information. [33:19] And that's my fear. [33:21] That's all. [33:21] It's just. [33:22] Because otherwise, you have two-hour hearing and then you bring in the peer review, and [33:29] then comes a two-hour hearing plus and another two-hour hearing, and that it comes far [33:35] hearing, cause your looping or things that are previously. [33:38] Okay. [33:39] So in terms of the order of discussion, are you allowing the public to speak first or after [33:48] The applicant in the peer review, here here in public here, [33:52] and should always be acting, well, the board. [33:56] And the chair introduces it. [33:59] The chair can ask staff if they have any thing they want to say, [34:03] and I won't. [34:05] And then have the applicant present their new visions they got in [34:10] the updates and then go to the peer reviewer [34:15] and then open up and then questions by the board. [34:19] and they're not going to public. [34:21] And can that public segment be limited in time at all? [34:26] We can limit it to two minutes of these, sir. [34:28] Yeah. [34:28] And it's a joyful call. [34:30] There are some communities that restrict the public hearing to one hour. [34:38] I question with that's reasonable. [34:41] But if you've got a general with four public hearings or I understand, they're going [34:47] restricted to because the four hearings of one night and some things have that, some have more. [34:55] You can't have in this public hearing, you've got a time restricted. [35:02] We do that. [35:04] The amp in these notes had time, hey, we're limiting the public hearing to one hour or so. [35:08] You've got maybe 15 minutes at tops. [35:11] If you're trying to hit your notes in five, ten minutes, so the public has about half the time. [35:23] And that's the date for the solar hearing receptor October 7th because the cell... [35:34] And at that time on the 7th there wasn't going to be any more other gender items, but because of the medical office and the ZBA and the Cannescom having to deal with that, hopefully, their report comes back, we can move on that medical office terribly swiftly and get that out of the way, and then that will leave the rest of it. [35:54] I would put the third aid at Conch Highway before and put the solar. [36:00] That looks like that. [36:01] I'll move fairly quick. [36:02] One way I think I'll do either. [36:03] It needs to help. [36:04] I'll continue and sort of. [36:06] Ten minutes. [36:07] You know what we mean? [36:10] We have. [36:10] All right. [36:10] Hearing anything else pertinent. [36:13] Otherwise, I'll entertain a motion to adjourn. [36:17] I'll second it. [36:19] I'll second it. [36:20] I'll second it. [36:21] I'll second it. [36:21] I'll second it. [36:22] I'll second it. [36:24] I'll second it. [36:25] for the discussion on favor. [36:27] All right. [36:29] Thank you. [36:30] Did I ever want to thank you? [36:31] Have a good week.