[0:00] what's going on and where we're at. So, we can all catch up. I know that we've [0:04] had multiple communications via text, email, and phone calls. And just this [0:10] right here is a uh a solidified of everything of that. So, [0:16] uh I'd like take uh I'd like to provide a pull cover project update to this [0:21] elected board, citizens, and other in interested in this project. First, let [0:27] me say that this project is more complex than it may seem on the surface. We've [0:32] been continuously receiving information from multiple stakeholders, but I [0:36] believe we have developed a solid summary of what has occurred and how we [0:39] need to move forward in this project. The original plan called for a new dome [0:44] to utilize a gray beam of the same size as the previous structure, which houses [0:49] [clears throat] the anchoring system. This was was included in the original [0:54] designing cost. However, during excavation of the for the new gray beam, [0:59] the contractor discovered several issues with the existing what I would call the [1:04] gray beam's footer, for a lack of a better term. The footer did not match [1:09] the 2000 site plan that was used to develop this plan. It w it mo most [1:15] likely reflected a much older pool design that was transferred onto the [1:20] 2000 site plan. So whenever it was first designed whether it was the 60s7s or 80s [1:26] and then it just got transferred year after year no one dug up the concrete. [1:30] So we didn't know the second uh the areas where the footer existed the [1:35] underlying concrete was in very poor condition and was unable to support the [1:40] required load of the new dome. Third, in some sections, the footer was [1:46] missing entirely, leaving nothing stable to anchor the new gray beam to. After [1:51] uncovering these conditions, we had to investigate further before Yeden could [1:56] construct the dome. The most important thing is to ensure the safety of the [2:00] people using the pool facility. Yeeden contracted their structural engineering [2:04] firm, ISG, to review the situation. Following their evaluation, ISG [2:09] determined that approximately 500 linear foot of gray beam footing would need to [2:14] be replaced with a new uh footing system that measured 24 in wide, 48 in deep in [2:21] compliance with the updated 2018 building code requirements. Um, as part [2:27] of this deeper assessment, geotechnical experts was also brought in to determine [2:33] whether there was an underlying reason why the concrete footers had [2:38] deteriorated as much as they have. The geo technical team has recently provided [2:44] recommendation that slightly differs of that of the structural engineers [2:48] approach. Both are now working together to develop a unified solution that [2:53] satisfies both the structural integrity as well as geotechnical requirements for [2:58] this for this project. We expect the final recommendation to be within the [3:02] next two to three business days. Uh in the meantime, we have received [3:07] preliminary estimates for the 24x 48 footer system replacement which came in [3:12] at 173458. I would ask for an additional funds for [3:16] contingency with a total budget amendment of 225,000 which I believe all [3:21] of y'all have not received a copy of this morning. Whatever funds aren't used [3:26] will roll back into the uh fund balance, but this is needed to keep us on track [3:30] with the six to eight weeks additional time frame that uh yeen and moss Marlo [3:36] has provided to us this morning. In my opinion, this project has had its fair [3:40] share of bad luck from the beginning. We've encountered several unexpected [3:44] challenges from electrical issues to concrete soil complications. That says [3:49] we are dealing with an extremely old facility that naturally leads to [3:53] unforeseen challenges. Also, due to the age of facility, [3:57] there's no reliable original site plan. As a result, we don't always know what [4:02] is or isn't underground and where it's located. We are gradually building a [4:06] better site plan as remodels, upgrades, and maintenance work is completed, but [4:11] unlike but it's unlikely we will ever be 100% accurate under the ground. staff [4:16] and contractors have been working as fast as possible to keep this project [4:20] moving and meet the tight November deadline despite these setbacks. [4:25] Ultimately, I believe it's better to take the proper [4:28] corrective steps now, even if it does mean a short delay, than ask for more [4:33] significant and costly issues later. I think the main thing for the electric [4:38] board citizens and swimmers to know is the dome will be installed. It may just [4:42] take a little bit longer than expected. I also think it's important for everyone [4:45] to know because I know I wasn't here but I know there was a debate whether dome [4:50] versus permanent structure. It doesn't matter which path this council would [4:54] have taken. We would have run into the same bad concrete bad soil issue. Um so [5:01] there was it doesn't matter which way we go we have to address address the soil [5:06] and concrete before we [clears throat] can go up. Uh I think it's uh I would [5:11] like to ask council for the authority to continue moving forward by approving the [5:15] budget amendment. I also will keep the mayor and council updated until the pool [5:20] coverage project is completed. And I also have a copy of the Mars Marlo [5:25] estimate I'm gonna give and you pass it around. [5:34] » Okay. Council questions. >> Um so you were saying that we're looking [5:39] at a six to eight week delay. >> Yes, ma'am. So, uh it's 6 weeks for the [5:45] new footing system, 500 foot of that. >> And then afterwards, uh yeeden it'll [5:50] take pro approximately two weeks to install the dome. Um it's my [5:55] understanding that once the footer system is in place, they will take I get [6:00] I'm assuming laser measurements to be exact and then they will build the dome, [6:05] which it takes seven days to build the dome. Uh they've already we've already [6:09] paid 50% of it. They've already got the material. They're just waiting for those [6:13] measurements to put it together and then it'll take another week to to construct [6:17] it. >> Okay. So the six to eight weeks will be [6:20] from like November 1st. So >> from today [6:23] » from today. Okay. So we're saying >> we approve this a budget amendment. [6:26] We're going to give them a sign a change order and move forward. But [6:29] » okay. So we'd say mid December is that sort of approximately [6:33] » barring any other unforeseen uh unforeseen incidents. Now I will say [6:38] I mean this ain't the most elegant way to say it. This is the way I grew up. [6:42] This project's been somewhat snake bitten from day one. I mean, the first [6:46] thing we did, we ran into electrical issues. [6:48] » And then now we run into concrete and soil complications. [6:52] » Um, that's this thing that was underground [6:56] that we didn't know about. >> So, [6:58] » and again, that were that was things that we would have come across no matter [7:02] what we did. Yeah. Either structure just to verify. Yes. [7:06] » It's an old facility. I mean, you're going to run into issues. [7:10] » Mr. Mayor, I move that we authorize the additional funds of $225,000 [7:19] uh so that we can move this thing along as [7:22] quickly as possible. >> Okay, council, you hear the motion. Do I [7:26] have a second? >> Second. [7:28] » Okay, motion and second. Any further discussion? just uh uh just just comment [7:34] or two and there's there's a a lot of unanswered questions but uh [7:39] [clears throat] one of them is uh well doesn't matter. [7:43] Let's just move on with it so you know I don't have anything else to say about [7:48] it. >> Um I'd just like to say um as a former [7:52] high school principal I have been to many meets in that bubble. I understand [7:57] the importance to our high school swimmers and we have got to get that [8:01] bubble ready for a high school swimmer. Also, I was a member of Linda Kids [8:06] Aquaize class in the morning. Those ladies need that bubble. There's a a [8:12] good group of ladies that come every morning and are a part of Miss Kid's [8:15] class. I've also been a member of Tony Reese's class, Aquaciz class. So, I have [8:22] been very involved in that poll and I'm very vested that we get this fixed as [8:27] soon as possible. >> I also want to say one thing. We're [8:32] going to continue to look for alternatives, but we're going to keep [8:37] the project moving forward and we're going to do it as as cheap and as [8:41] effectively as we can, but we're not going to cut corners to maintain safety. [8:45] So, I know that number y'all just got it. You ain't had a whole lot of time to [8:50] research it. We haven't either. We're going to spend the day doing that and [8:53] then we're going to if this budget amendments approved, we're going to move [8:56] forward with it. >> Yeah, that's good. Thank you. [8:59] » Anyone else? >> Now, Moss Marlo will be doing this work. [9:02] Is that correct? >> Yes, sir. [9:04] » Okay. >> Okay. I'd like to commend staff and our [9:08] engineers and our contractors on the job they've done in identifying the problems [9:15] and also identifying the solutions. And I know uh staff has worked overtime on [9:20] this and I certainly appreciate your work, Mr. Terms. [9:24] » Thank you. >> And rec staff and both. Thank you. Okay. [9:28] Anyone else? >> And I just want to um say that I [9:31] appreciate the updates that we have gotten and I know you'll keep us updated [9:34] on this. I know the six to eight weeks is fluid, I guess, for lack of a better [9:39] description. And I'm sure you're going to try to attain that all the uh parties [9:44] involved. And I think everybody of course overall wants it to be safe and [9:49] ready for use when it is open. So I think that's [9:52] » we have uh all part all the stakeholders know this is a important project that [9:58] has to be completed. >> Anyone else? Okay council I have a [10:03] motion and a second. All those in favor signify by saying yes and raising your [10:07] right hand. >> Yes. [10:09] » Seeing none opposed motion carries. I will now entertain a motion to adjurnn. [10:14] So move >> second. [10:17] » Have a motion and a second. Those in favor signify by saying yes and raising [10:20] your right hand. >> Yes. [10:21] » Motion carries. >> Thank you, St. Be safe.