[14:34] Thank you for your patience with us. There's a lot of organizing going on here. This is not an easy thing to put these public hearings together.
[14:46] So you are at the Brisbane Special Meeting of September 29th. Thank you for joining us tonight, and I'm calling this meeting to order at 542 PM. Would you please consider joining me in the pledge of allegiance?
[15:14] All
[15:20] council members are here tonight, so we have none attending remotely city clerk. Could we have roll call please.
[15:28] Council member Davis.
[15:31] Yes.
[15:31] Council member Kern.
[15:32] Yes.
[15:32] Council member Lent.
[15:34] Yes.
[15:34] Council member McConnell.
[15:35] Yes.
[15:36] Then mayor Macken.
[15:37] Here.
[15:38] Can I get a first and second to adopt the agenda as it stands?
[15:42] Some moved.
[15:43] Second.
[15:44] All in favor.
[15:45] Aye.
[15:46] No one opposed.
[15:47] This is a continuation of a public hearing.
[15:52] This is a public hearing continued from September 14, 20, 26.
[15:57] And tonight we have two topics continued from the last meeting, is air quality and greenhouse gas impacts and associated mitigation measures identified in the EIR.
[16:10] The second topic, the new topic, is land use plans and design topics.
[16:18] I'm going to read the caveat that applies to all speakers, both online and present.
[16:25] We welcome speakers providing public comment during tonight's continued public hearing,
[16:29] but please be advised this is a limited public forum.
[16:32] It's therefore important for speakers to stay on topic.
[16:36] On topic matters are those that are within the subject manager's section of the city of Brisbane.
[16:42] speakers will have four minutes for each topic they'll be a timer up on the screen please
[16:48] please honor the four minute timer because remember it's not that we don't want to hear
[16:53] you longer but then you're taking time away from someone else and we want to be fair.
[16:58] Following these rules helps ensure the city council can get to all the items on the agenda
[17:02] including hearing public comment on the items. If a speaker fails to follow these rules
[17:07] they're disrupting the meeting and they'll be warned, I promise you, if a speaker continues
[17:13] to ignore the rules or as otherwise disruptive their opportunity to speak will be ended
[17:17] and they may be precluded from speaking on any other items tonight. So as some starting comments,
[17:26] I think it's wonderful that all of you showed up. This process is not just about the council
[17:32] or the applicant or their marketing agent, this is about an entire community making a massive change.
[17:43] And we're not here to just listen to you.
[17:47] We really hear a lot of your suggestions.
[17:50] We've had some wonderful speakers come up here and bring up things that we might never have thought of.
[17:57] And that's collectively the best of all worlds.
[18:00] So, we encourage you to speak, ask your questions, ask staff, the developers representatives are here.
[18:11] Some questions you might style me, everyone, and we'll have to come back with an answer and another meeting,
[18:18] but please also your comments, your comments are welcome too.
[18:21] We want to know what's on your mind.
[18:23] This is about ensuring the best possible project from all perspectives.
[18:30] There's not one side or another. It's all together.
[18:34] And we are advancing this whole process and your part of it.
[18:39] So thank you for joining us tonight and for everyone online as well.
[18:44] So the first item we have again is air quality and greenhouse gas impacts associated mitigation measures identified in the EIR.
[18:52] And so staff, we had a report on this last time.
[18:57] Would you like to do a short recap on this,
[19:00] or just dust off everyone's brain cells?
[19:03] You have anything you want to show us?
[19:06] Yes, we can start the presentation.
[19:07] We have a brief recap and full pause.
[19:09] Thank you.
[19:10] I appreciate that.
[19:19] All right, good evening, hon. Romero and council members.
[19:22] Tonight, the council will be holding the second
[19:24] in a planned series of public hearings
[19:25] on the Brisbane Bayland Specific Plan
[19:28] and other related approvals, which together,
[19:30] We'll establish the regulatory framework for a buildout of a new mixed use neighborhood in the Bayland sub area of the city next slide
[19:41] Tonight's presentation will be delivered as one contiguous segment. That's actually going to be two now
[19:46] We will begin with a brief recap of the topics previously discussed followed by an overview of the land use
[19:51] Plan and design topics contained in the specific plan
[19:55] The focus for the second part will be on distribution and intensity of land uses location of open spaces and amenities
[20:01] the specific plans interface with see the whole rise objective standards and design guidelines and
[20:07] protection and preservation of the roundhouse. After staff's presentation, the applicant will have an opportunity to address the council
[20:12] followed by a public comment period on the to topics.
[20:16] Jim Maya, can I stop you? Can we break this into two parts so we don't go through the whole land use present?
[20:21] We're not going to go through the whole land use presentation until later, man.
[20:24] Okay, perfect. Thank you. Next slide please.
[20:31] As a reminder to the council on the public, the series of hearings is organized
[20:34] around the requirements of Mr. JJA. Each meeting focuses on a specific set of topics and staff
[20:40] is seeking council comments, questions, and direction on the items highlighted during each
[20:45] presentation. At the end of each topic, folks, the goal is to have clear direction from
[20:50] the council, so staff can prepare and refine a final recommendation for consideration at the
[20:56] concluding hearing. Tonight, the council will complete the remaining discussion from the September
[21:00] 14th hearing on air quality greenhouse gas emissions energy impacts and mitigation measures.
[21:07] After that, the council will provide comments, questions, and direction on the land use plan and design standards.
[21:13] And a rod of summarizing proposed changes, clearifications, and council requested modifications to the specific plan will be prepared and brought forward at the concluding hearing alongside staff's final recommendation.
[21:24] And to be clear, we are not asking the Council to take any votes or formal action tonight.
[21:29] Instead, staff is seeking that clear direction on the topics covered in the presentation,
[21:33] so we can return with a refined, complete, and accurate final package. Next slide.
[21:41] So we have an updated look at the upcoming hearing dates and topics.
[21:45] We made changes after a last meeting.
[21:48] As you can see, most of the meetings are now focused on one primary theme, like water infrastructure,
[21:53] transportation or remediation and we're happy to adjust the schedule further if
[21:58] Council would like to. So, next slide, and we can actually go two slides forward.
[22:07] Alright, at the last meeting, we walk through the key elements of the specific plan.
[22:11] It's overall structure and how it aligns with Measure J. The Planning Commission's
[22:16] recommendations and the plans to sustainability features. Staff also presented
[22:19] air quality and energy topics which you did not get to discuss and will continue
[22:24] that discussion here. So at this time we will pause for council questions or comments and then the council.
[22:30] We may open the floor for public comment on air quality, greenhouse gas emissions, energy and impacts and mitigation measures. Staff will track questions from the public and respond by the end of the meeting when possible.
[22:42] If more time or analysis is needing, we'll bring it back answers at a future hearing.
[22:48] Thank you very much. Let's start with council member O'Connell. Questions for staff?
[22:55] I have got questions at this time.
[22:58] Council Member Lens.
[23:01] Thank you, Madam Mayor.
[23:04] All right.
[23:05] Well, I have decent amount of questions.
[23:08] So I'm going to start off with from the packet from the last hearing.
[23:16] So it was on page nine.
[23:19] In fact, greenhouse gas, two regional GHG emissions, less than significant.
[23:28] And the first line says the Baylands, 2,200 dwelling units, six-naps million square feet of commercial use,
[23:33] and 500,000 square feet of hotel. So I just want to get clarification from staff,
[23:40] and I've seen it throughout the specific plan and also in the EIR.
[23:47] Is the current specific plan that's before us? Is it addressing the total build out to
[23:57] 2,200 housing units in the six and a half million square feet? Is that what this
[24:02] document is trying to deal with?
[24:11] The short answer is yes, but the specific plan does allow for the development of
[24:20] That entire program. Yes, all right, so when we're looking at energy generation and greenhouse gas emissions and these other things
[24:28] It's to accommodate
[24:31] 2200 housing units in
[24:33] six and a half pounds square feet of commercial space
[24:37] That's correct. Okay, great. Thank you. All right, so
[24:41] And in that same paragraph, it says that
[24:50] these uses are already accounted for in the
[24:53] Plan B area of 2050's regional growth projections, because the projects transit-oriented
[24:58] location design will reduce regional mobile source greenhouse gas emissions, relative to
[25:04] that same growth occurring elsewhere in the region.
[25:08] So, is it saying that because other cities maybe aren't doing as, you know, don't have
[25:18] as in a real bust program of reducing emissions, then say this plan is, and therefore,
[25:27] it's less than significant, am I getting that correct or, if not, if you could explain that
[25:33] a little bit better?
[25:55] Oh, yeah.
[25:56] So, no, I think you captured it correctly, because of the location, because of the
[26:03] transit accessibility, and because of the design features that have been incorporated and
[26:09] required throughout the specific plan that conclusion is that development here would
[26:17] reduce GHG emissions compared to a more development that didn't have all of those features,
[26:24] that didn't meet those same performance criteria.
[26:28] I didn't have the same sort of transit access and that didn't have the same mix of uses
[26:34] and that they would a different type of development in a different location would be expected
[26:41] to increase the regional GHG at a much higher rate than this project.
[26:47] So by accommodating this level of development, this project helps
[26:52] in putting it in such a strategic location where you get those benefits,
[26:59] this project helps to implement those GHG reducing goals.
[27:05] Got it. And so based upon this particular view,
[27:10] then mitigation measures don't have to occur.
[27:16] That's correct. This impact was less than significant without additional mitigation measures.
[27:22] There are other mitigation measures incorporated to promote plan consistency, which is a separate impact category.
[27:35] But there are not separate mitigation measures for the regional GHG emissions, because that was found less than significant.
[27:44] Okay, and so based upon that regional viewpoint, it says here, because the project would result in a regional reduction in vehicle miles traveled and green house gas emissions, the draft mitigation measure calling for mandatory offsets was removed from the final EIR.
[28:04] So offsets are mitigation measures if they were applied.
[28:10] I mean, in the, in the, that's correct in the draft EIR, there was a separate impact category with proposed mitigation measures, which included offsets in the responses to comments and the final EIR, the offset requirement was removed as mitigation.
[28:32] And it was found that that was not needed to have the project result in a less than significant greenhouse gas emission.
[28:40] Because of the fact that that project would result in that regional reduction as you were talking about.
[28:46] Got it. So then also, you know, diving into the sustainability framework on page 18.
[28:54] It says that all buildings should be designed for zero carbon emissions by using best practices in passive design,
[29:00] energy efficiency and renewable energy resources.
[29:05] I mean, this could be a question for staff.
[29:08] It could be a question for staff in a, is that being required in the specific plan?
[29:18] Well, the specific plan does have individual requirements for projects to maximize their on-site energy
[29:28] generating capabilities, there's mandatory solar, there's distributed battery facilities,
[29:35] the development standards that we'll be talking about in part two definitely are designed
[29:39] to promote energy efficiency. So the specific plan does have a number of requirements
[29:45] that help implement that stated goal of the sustainability framework.
[29:52] So, here it says that they should be zero carbon, so
[30:02] So, to me, that's stating that, based upon that, that we should be striving for the building civis, zero-carbon.
[30:15] So, yeah, so, key kind of give some language how that might be worded in the specific plan.
[30:23] Well, the buildings are the buildings and the specific plan are zero carbon. They all because they would either produce energy or draw from the renewable energy from the grid that that's a zero
[30:40] zero carbon energy source, so though we think that that's consistent.
[30:45] And so with that show up in the lead certification, is it to verify that?
[30:52] And the lead is a separate, there are also lead and other energy efficiency standards layered on as requirements in the specific plane.
[31:02] I'm just curious to know how would we verify that a building is your own net or zero carbon emissions?
[31:11] Well, in any energy that it wasn't producing would be drawn from a zero carbon, the renewable energy program.
[31:19] So that kind of bite the fault takes care of any, any surplus with a zero energy source.
[31:24] All right. Well, you know, if I could just get something, and maybe, you know, I'm missing it in the specific plan.
[31:31] But if staff can bring that forward, that'd be great. You know, I had a future meeting.
[31:37] So I'm going to go into the, sorry, before we move up, but what is it that you'd like us to bring forward?
[31:42] So I want to make sure that you want to know how buildings are verified to be on that
[31:48] emissions.
[31:49] Is there some kind of certification that this building is on that emissions?
[31:54] I mean, it's a requirement in the specific plan for all buildings to be 100% use 100% carbon-free
[32:06] energy source.
[32:06] So that would be verified, compliance with that would be verified through the development
[32:10] review process.
[32:11] Okay, so I guess the Cal green standard is that I know for residential is 2025 2030 for commercial
[32:21] It's not 23 yet
[32:25] I have a question that's kind of getting at something similar. I don't want to take away from your time
[32:32] I think maybe something that I was thinking we might need site site wide
[32:38] Carbon budgeting monitoring reporting and then
[32:41] a provision for corrective action. If there is something that comes out of those numbers,
[32:48] like if, you know, residents don't opt in to the ECO 100 or what I think we have a really high,
[33:00] I know you have told us we have like one of the highest adoption, but I think maybe while we
[33:06] assume everything is going to be zero carbon. Maybe there is some kind of ongoing reporting
[33:13] that the city could receive just to ensure that that is true for years to come. So is that
[33:22] does that maybe get out of here? So there are certain certifications that a building can apply for
[33:29] If you look in the sustainability framework or just even go online, you know, a building has qualified to be zero net emissions.
[33:41] And so smaller buildings have an easier time of doing that, larger buildings have a more difficult time.
[33:47] So,
[33:50] so that's where I'm asking staff that there's some kind of application.
[33:54] Sure, maybe if you look at Section 4.3 of the specific plan, the zero-carbon buildings
[34:02] requirements, it does have a long list of mandatory steps that a project has to go through.
[34:12] And if it doesn't comply with those standards, it won't be issued permits to develop.
[34:18] So it needs to meet these zero-carbon building requirements in order to develop.
[34:30] I'm going to go to the IAR.
[34:32] I'm going to go to Chapter 8, the Final IAR.
[34:36] And so, in doing my research, you know,
[34:40] I'm just trying to get a understanding of how,
[34:46] you know, you'll look at measure jj,
[34:48] it says it's supposed to be designed to be energy neutral
[34:52] on an ongoing basis.
[34:58] You know, we're looking at like 53% of energy generation
[35:02] in the current specific plan.
[35:05] That was a very conservative metric that was used on the EIR, I think, as was reported, the
[35:17] specific plan, assuming compliance with more up-to-date building code standards would
[35:24] see a much higher percentage of building energy use generated on site.
[35:31] OK. So, you know, chapter 8 talks about alternatives.
[35:37] So, in the sequel process, you know, every development
[35:41] that goes through this type of process has to have alternatives.
[35:46] And so, there are some no project alternatives
[35:48] and then there's four, they call it reduced density alternatives.
[35:54] So there's an alternative, number seven, it's called reduced maximum building heights.
[36:00] So in that particular alternative, it calls for 1800 dwelling units, not the 2,200,
[36:09] it calls for 2.8 minus square feet of commercial 350,000 for the hotel.
[36:17] That's on the west side and the 1.7 on the east side for a total combined of 4.5 million.
[36:24] It also has lower building heights.
[36:27] So 12 story max for commercial eight story max for housing unlike the, you know,
[36:34] the current plans got some 20 plus story buildings in it.
[36:39] So I'm not going to go into all the other things.
[36:42] want to just go to the greenhouse gas emission section. That's on 8146, let me just go over there.
[36:55] All right, so there's a section that has been that was dragged out and you had explained
[37:05] Eric that we're this particular plan is addressing a regional perspective under
[37:14] in house gas emissions or as in the area that is strike doubt, it's a specific plan
[37:21] area greenhouse gas evaluation. But since that was changed, that's why it's struck.
[37:30] But I'm still going to read it, because I think it's important, and so let me just, let me just state what it says.
[37:39] Lowering building highs to reduce bailings to balance by 400 dwelling units, and two and a half assists to an app that is really two million square feet of commercial office.
[37:47] Use would reduce the specific plans, net increase of greenhouse gas emissions and reduce the severity of its significant unavoidable impacts.
[38:01] So
[38:05] just looking at that, when I'm assuming there was a greenhouse gas mission study to come up with these numbers.
[38:19] So did it include this alternative in that study?
[38:24] You will probably want ESA to talk about it, but the EIR definitely includes a quantified
[38:31] GHG emissions study that the climate scientists said ESA prepared and they did compare
[38:39] the project emissions to emissions expected with alternatives.
[38:46] So I don't know if he has, I think we have Brian Schuster from ESA is available online and
[38:54] can speak to exactly what was quantified and modeled, if that's what you're asking.
[39:01] Yeah, just
[39:04] looking at, for I make a request, I'm going to go to the other page and send
[39:15] air quality.
[39:28] So, you know, Stephanie, maybe you can answer this. And regards to how
[39:36] dirt is going from the east side to the west side, what's your plan for doing that? Is it going
[39:43] to be the conveyor belt? Or is it going to be trucks?
[39:50] Good evening, Honorable Mayor, council member,
[39:52] lens, what is studied in the EIR is both the preference in the EIR and quite honestly
[40:02] our preference is to find a way to go over the track and not have to go through the streets.
[40:10] And we have been in discussions with CalTrain about how to do that.
[40:14] We've talked about going over the tracks, we've talked about going under the tracks, we've talked
[40:20] about just going at grade across the tracks, and those are still ongoing conversations.
[40:28] But, yeah, again, both were studied in the EIR, both are still on the table, our preference
[40:36] in the EIR's preference is to try to avoid using the streets.
[40:42] Yeah, that makes sense.
[40:43] Makes sense.
[40:43] Yeah, absolutely.
[40:44] So yeah, but we have, we have to work that through with CalTree.
[40:51] Yes, okay, thank you for that.
[40:54] So based on the potential of having these trucks use public streets, you know, that's a lot of truck emissions, a lot of trips.
[41:08] was that studied in the emissions evaluation, all those truck trips?
[41:17] And a brain, can you talk about what air quality modeling was done for truck trips during construction?
[41:26] Yeah, happy to answer that.
[41:28] Hey everyone, Brian, she's certainly fairly climate energy.
[41:33] So the air quality analysis in the EIR, which includes both an estimate of mass
[41:39] criteria of blue emissions, like ozone precursors and dust as well as particulates as
[41:46] well as health risks, so exposure of people to those emissions during both construction and
[41:54] The construction analysis for both of those look at on-road diesel trucks, moving all of that soil, all two and a half million cubic yards from east to west, and not using conveyor.
[42:08] And that was part of the contributing factor to air quality impact, air quality one being significant and unavoidable.
[42:15] and to help mitigate that impact where IQ-1 is mass emissions.
[42:22] There's a mitigation measure,
[42:23] IQ-1F, which requires best available control technology for soil movement.
[42:28] That could include in all electric conveyor.
[42:31] It could include zero knocks emissions trucks.
[42:34] It could include some combination of those things,
[42:36] or some other technology that might enable
[42:39] contraction to occur with the lowest emissions possible moving that soil. So yes, short answer. Yes, we analyzed in the air quality section
[42:49] Diesel tracks moving that soil. All right, so how many trucks we're looking at if all that had to be moved?
[42:57] With the track on straight
[43:09] Give me can you give me like one minute. Oh, yeah, sure not no problem.
[43:22] Isn't it something like 640 trucks a day? I mean, truck round trips a day. So I don't know how many round trips do I think how many trucks that equates to but I think the amount of round trips is 640
[43:40] Yeah, that's correct. So it's on average the 2.5 is about 640 round trips per day during the almost three year. I believe soil movement activity.
[43:52] Alright, so peak trucking haul, peak truck activity is 640 round trip this
[43:57] pretty. That's not an average, that's peak.
[43:59] Alright, but the route is like 3.6 miles or 3.5 miles, right? So how many trips would a truck
[44:04] do a day? Then you could figure out how many trucks conceivably you're doing, you're having each day.
[44:12] Yeah, that that calculation is pretty straightforward. Yeah, so I don't have a calculator,
[44:16] But I mean, like, is it in the, I don't know, hundreds of thousands of truck trips, just kind of off the top of my head.
[44:25] I mean, if it's that many and you're talking about three years, six, forty, five, three, six,
[44:31] five.
[44:34] Three.
[44:36] So, um, as a...
[44:39] It's over a hundred thousand trucks and we'll talk about it.
[44:42] It's about a twenty cubic yard truck two and a half million cubic yards.
[44:47] 125,000 as one way trips. If I can add a question, was that our quality analysis based on the dirt only having to be
[45:00] Moved, once, because won't the dirt, some of it need to be moved twice to chief final grade on both sides.
[45:12] And was that looked at?
[45:19] I believe analysis looked at moving a one time movement of dirt from the east to the west side and not back again.
[45:30] But I can double check that.
[45:31] But won't it have to be moved back again?
[45:35] Some of it.
[45:37] To achieve a cap?
[45:42] I might defer to Michael if he's here on the cap.
[45:46] Because it's not engineered on the other side.
[45:51] I don't know the answer that question.
[45:53] I'm sorry.
[45:54] Okay.
[45:54] To help her shaking their head now,
[45:56] so do you want to...
[45:59] Should we...
[46:00] here with you?
[46:01] Would you like to respond to that?
[46:11] Evening council members, I'm James Delosso with BKF, I've been supporting the Bailons Project and Bailons Valminink.
[46:19] In terms of the Earthwork, Earthwork will move once from the east side of the project to the west side.
[46:27] And then it will be placed from both to achieve the environmental capping, as well as some of the geotechnical search search programs.
[46:36] It will not be then moved back to the side after that.
[46:42] So, you know, in regards to the trucks.
[46:45] So, I mean, obviously is just going to take a few years to get to that point where you're
[46:50] starting to move dirt.
[46:52] More trucks will be electric.
[46:58] Can we make a requirement in the civic plan that the trucks that are used be electric instead
[47:03] of diesel?
[47:09] That is a question for staff.
[47:10] Is that something that we can put in?
[47:14] If that's feasible and commercially available, but yeah, I don't know that there's
[47:24] That we have a robust enough technology to say that we can definitely do that today
[47:30] But we think we need to be language like that in other plans that
[47:36] Qualify into the extent yeah feasible 100 thousand truck trips
[47:42] You know, and it's going by Central Brisbane and up in Northeastern Ridge.
[47:49] Yeah, I think that would be appropriate.
[47:51] Brian, were you so much say something?
[47:54] Yeah, I was just going to add that the EIR includes a mitigation measure, which is a mitigation measure,
[48:01] 181F, which requires best available control technology at the time construction.
[48:05] And that means the lowest available, the lowest emitting trucks, commercially available.
[48:12] If you can, if they're available commercially, you can buy them and operate them.
[48:18] The applicant must use those trucks.
[48:21] Or they must build a conveyor or some combination of the two to achieve the lowest knocks.
[48:28] The lowest criteria for emissions from material movement.
[48:32] All right, so Brian, so what you're saying is that if that truck say it does exist, I'm assuming that it does today
[48:39] But say if it does
[48:41] Exist, then that those would be the trucks with that would have to be used
[48:46] Yes, right, so the trucks would have to meet the requirements of the construction contractor for moving soil
[48:50] They are heavy duty, and zero mission trucks available now. They would have to be available and quantity
[48:56] You know with the with the in the quantity needed for these activities and
[49:01] and have the capacity to, basically,
[49:05] they have to operate in the way that construction needs to occur,
[49:08] but if those conditions are met,
[49:10] and those trucks are available,
[49:11] then yes, the mitigation measure would require that,
[49:13] or some combination of additional technology.
[49:16] Okay.
[49:17] So, sorry.
[49:18] Yeah, I have no problem.
[49:20] People jump in it, so.
[49:21] What that?
[49:22] So, because that's a mitigation measure in the EIR,
[49:26] Is that enough or should we include that language like whatever is the lowest emitting trucks available?
[49:41] Should we expressly state that in this specific plan?
[49:45] Well, if you end up adopting, certifying the EIR and adopting the mitigation monitoring reporting program,
[49:52] All of the mitigation measures would become requirements of the thing, and so you don't need to then repeat them in the specific plan.
[50:01] That's what I assume, right?
[50:02] It's important.
[50:03] Yeah, you know, I think it's always better to just repeat just everyone understands, you know, these, these EIR documents are pretty darn thick.
[50:13] I mean, the specific plan is pretty thick, too, but not as...
[50:17] It's not five volumes.
[50:18] is not five volumes, so if the public wants to see it, it's a lot easier to find it.
[50:24] So is the council's thought that all of the mitigation measures should be included as standalone
[50:32] policies in the specific plan? Is that... I'm just talking about this one here. So that's
[50:38] this direction. I mean, we can bring it back, right? Sure. Okay. I just want to make sure that we're
[50:43] the conversation. Yeah exactly.
[50:48] So sort of page 8158. It's an impact GHG1. So it's struck out here.
[50:57] It says the Balaens specific plan would cause an increase in total greenhouse gas emissions
[51:02] generated within the Balaens. Lowering building high to reduce Balaens development by 400
[51:07] dwelling units in two minus square feet of commercial office would reduce the specific plan
[51:12] that increase greenhouse gas emissions.
[51:15] And so what I would like for us to evaluate when we have
[51:22] our discussions is doing a specific plan area
[51:28] greenhouse gas emissions position, as opposed to a regional one.
[51:36] So then moving on to energy resources,
[51:39] And this is still within this particular part of Council Member Lenskin ask a clarifying
[51:47] question.
[51:49] So you want to put into the final specific plan something very specific to the 680
[51:55] acre bail and project around greenhouse gas emission.
[51:59] So what I am requesting is that when the council has its deliberations, this is one of the
[52:03] items that comes back to the council.
[52:05] and we can decide whether or not we want to do the regional perspective,
[52:11] we want to do the site perspective.
[52:14] Okay, thank you.
[52:16] Okay. So moving on to see the energy resources.
[52:20] It says here by reducing its whole number of dwelling units,
[52:24] and commercial school footage within the Bayolans,
[52:27] the specific plans 55 acre solar field would reduce.
[52:30] Use overall energy use, and generate a greater proportion of the specific plans on site energy demand within the billions.
[52:40] So again, I know we talked about trying to be energy self-sufficient. That's a very tall order.
[52:49] Of course, if you have a smaller footprint, and that's less energy for the footprint, and you have a 55-acre solar farm that now can provide energy to you know, and greater proportions.
[53:09] So, it also goes on to say, in addition to the energy efficient features of the specific plan, which is this alternative.
[53:17] This alternative, it would generate a greater proportion of energy if it consumes as well as me tear-to-cow-green standards.
[53:28] So, just putting that out there in the public record.
[53:32] And Stephanie, I know when we talked last time, you said that the solar farm is going to be in the second phase.
[53:40] But when I read your specific plan, it said it was going to be in the first phase of development.
[53:47] It was going to be the west side when the west side gets developed.
[53:49] That is going to happen at the same time.
[53:52] So just kind of clarifying that for the record, unless you've changed your mind.
[53:59] But it's going to be in the first phase.
[54:06] Oh, did you want to respond to that?
[54:08] I mean, that's what I read.
[54:10] And it's also in, it's in your specific plan that you had submitted, and it's also in this one too.
[54:16] Yes, I think you're referring to our phasing table.
[54:19] And if you look at it carefully, Councilmember, it is the, it is sort of sandwiched in between finishing the west side development and starting the east side development.
[54:30] So technically I think it falls into the table of phase one, but it's kind of at the end of the full development of phase one,
[54:37] as we've moved all the dirt, and the landfill has been closed or will be closed in phases than the solar farm goes in.
[54:49] So it's a little, you know, we're mixing with a lot of terms here, but we're mixing it, but yeah, it is not.
[54:54] The solar farm is not on day one. Oh, we don't want to not seeing that, it's during that.
[54:59] But during the transition, I think what you're referring to when you said we said it was in phase one,
[55:04] It was in the transition period between finishing phase one and moving on to the phase two development on the commercial development on the east side.
[55:14] Can I just read it to you?
[55:16] And then maybe that's from your plan.
[55:20] So it says major site infrastructure such as the solar field, water recycling facility, and constructed wetland located within the eastern part of the site.
[55:34] are also required to be completed concurrently with West side development as these
[55:42] provide the sustainable water near a stormwater treatment cycle water and
[55:48] rural energy generation infrastructure for the development. So, yeah. So, yeah, yeah,
[55:53] yeah, we need to do the development to get the water for our recycling facility, right?
[55:59] you to recycle water you can make that you need of course yeah yeah yeah and in order for us to
[56:06] build out the solar farm that dirt has to be moved so when we talked about it in our plan it was
[56:11] really sort of at the end of phase one as part as we moved into the the second phase on the the
[56:19] construction on the on the landfill the sign yeah okay sorry if that confused I yeah this one
[56:27] get clarification. Yeah. Okay. Thank you. All right. That's it for now, Madam Mayor. Okay. Very good.
[56:37] Councilmember Kirk.
[56:40] Thank you so much. Can I go back to Councilmember O'Connell and her question
[56:46] about moving the dirt more than once? It's got me over here thinking. Councilmember O'Connell,
[56:52] what was the reason that you asked that question specifically?
[57:01] I think that there is
[57:03] an excessive dirt on the east side for what the project needs. I think to reasonably
[57:11] cap that project, they are going to need to take it below grade to cap the east side.
[57:21] Meanwhile, they are going to have to move that dirt even if they're done with the west side.
[57:28] the east side still is going to need to be excavated
[57:31] and the dirt moved on the east side to another section
[57:35] to be put back after they do the title seven
[57:40] closure so that dirt is not going to be moved just once
[57:46] that dirt is going to be moved around
[57:50] at least one more time on the east side
[57:55] not all of it, but all the remaining and the overfill that they've got is going to be moved
[58:02] more than once. In my opinion, and I could be wrong, but if you play with a pile of
[58:10] sand, that's what you're going to get. So I guess my question, thank you for that. I would
[58:14] kind of thought that's where you're going. So I guess my question is, in that case, can't
[58:19] additional dirt or covered just be brought in at that point for the east side. Does it need to be moved again?
[58:28] It's not engineered.
[58:30] So it does have to be moved. It needs to be removed back down to ground level from what or to fill level to be properly capped and engineered.
[58:39] Or it's useless.
[58:42] Useless land.
[58:44] I'd love for the developer to.
[58:48] Yeah, please step up, thank you.
[58:52] Thank you, Ann Council members, one to clarify, you make some very good points, so the
[58:57] dirt will be moved, excuse me, you can pull it out, okay, my apologies, the dirt will
[59:03] be moved once from the east side to the west side that 2.5 million to provide the environmental
[59:12] cap as well as some of the geotechnical mitigations. It will not be moved back from the
[59:18] west side to the east side. The existing dirt on the east side will be moved around within
[59:23] the east side as the cap is provided for the title 27 closure of the landfill, but we won't
[59:30] have a need to import more soil to proceed with that process.
[59:34] And is it correct you have an excess of soil for that project?
[59:38] There's no off-haul contemplated, the soil is currently used in terms of setting the pad
[59:46] grades within the east side of the project based on what soil it remains.
[59:51] It will be engineered for the geotechnical engineers' requirements as part of the capping process
[59:57] and creating the development pads.
[1:00:02] Thank you.
[1:00:07] Thank you for that answer, and thank you for the question council member O'Connell.
[1:00:12] My only other question is in March of 25, ESA reported that the, or they stated that the project was not going to be energy neutral.
[1:00:23] And then in August of 26, I just need to remind her on this, something changed and they said that it was acceptable to buy additional energy from the grid that we weren't going to be generating on site.
[1:00:35] But I'm just wondering if you can clarify what changed in that time period.
[1:00:40] Well, the, that option was always available.
[1:00:43] I think the, what changed is that context in which the policies were being evaluated, the calculations
[1:00:51] that were reported in the EIR were done, again, to be using very conservative assumptions
[1:00:59] and to analyze whether or not the way energy was being used would create a physical impact to
[1:01:06] the environment, which is a slightly different question than does Council have the discretion
[1:01:13] to interpret the plan to be consistent with Measure J.J. and in response to questions from
[1:01:19] the Planning Commission who are interrogating the same topic, ESA worked on an analysis to
[1:01:27] explain the tools that the decision makers could use to find the project consistent based on the way
[1:01:35] it was using energy, the balanced goals of Measure J.J. and the intent behind the framework.
[1:01:45] Thank you.
[1:01:46] No more questions at this time.
[1:01:47] Councilmember.
[1:01:48] I'm sorry.
[1:01:49] Mayor Protom.
[1:01:50] It's okay.
[1:01:51] You can call me Councilmember.
[1:01:54] Well, Councilmember Lens asked several of my questions in one form or another.
[1:01:58] So I do have two left and first one is that the final EIR identifies air quality dash 1,
[1:02:07] AQ-1 as significant unavoidable and I'd just love to know from staff if you could explain
[1:02:13] what pollutants specifically are driving the significant unavoidable conclusion.
[1:02:20] Yeah and for that we'll ask Brian to rejoin and he will walk us through that.
[1:02:24] Do you want me to go to my next one while we're waiting for him or
[1:02:30] is by and on or you're ready to answer that or should we come back to you.
[1:02:34] Oh, there he's there. Yeah, I can answer that. Give me one sec here.
[1:02:45] It was a Q dash one. Yeah, yeah. Yeah, of course. Yeah. I got it.
[1:02:51] I just want to get this.
[1:02:54] Really right here. So, all right, after mitigation,
[1:02:58] and
[1:03:00] who would instead exceed thresholds include.
[1:03:06] Okay, so the AQI one evaluate a construction,
[1:03:10] ROG, NOx, P and 10 and P and 2.5.
[1:03:12] That's a different size, particularly if it's in ozone precursors,
[1:03:15] for a construction throughout the buildout,
[1:03:18] as well as operations and combined
[1:03:22] construction operations when those would overlap.
[1:03:25] With mitigation, all four pollutants would still
[1:03:29] will see the significant threshold set by the year district.
[1:03:33] So that's Rob Knox, PM10, and PM2.5.
[1:03:38] And just to follow up, how much of the significant
[1:03:41] air quality impacts are associated with construction
[1:03:45] and how much are associated with the final development?
[1:03:48] And I don't know how you quantify that by a percentage
[1:03:52] or just give me some like thing I can visualize.
[1:03:56] is.
[1:03:58] Sure. Let's see here. How best to do this? The for construction only the only
[1:04:06] pollutant that exceeds thresholds is nox. So oxides in nitrogen,
[1:04:10] raw PM10 and PM225 are well below thresholds. Whereas for operations for
[1:04:16] operations alone all for pollutants exceed the threshold.
[1:04:20] So construction emissions are for rock, for rock PN10 and PN2 and 5, several orders of magnitude below operations.
[1:04:29] We're talking less than 1 pounds per day versus between 60 and between 80 and 300 pounds per day.
[1:04:39] And for knock, it's about about the same.
[1:04:42] So construction knocks is about the same operation knocks.
[1:04:45] Other pollutants are several hundred times higher for operations than construction.
[1:04:51] Thank you.
[1:04:53] That's the extent of my questions on the air quality.
[1:04:57] It has MDHD ones, but there are.
[1:05:00] After you vastures, I do have a couple questions now.
[1:05:04] You want me to go first?
[1:05:08] So when it came to the comment that Council Member Lens made on whether we have a regional greenhouse gas analysis versus a site specific or project analysis.
[1:05:20] analysis. It basically is that if development wasn't happening here, it'd be some more else.
[1:05:29] So there's no impacts to our project, because we're absorbing the rest of the region's impacts.
[1:05:36] And I think that's a way to look at it where the request from council member
[1:05:41] is to have the impacts for our site fully disclosed and declared that they are significant.
[1:05:52] Compared to saying, well, if they were happening in Pleasanton, they'd be more so ours aren't significant.
[1:05:58] When they still are, and so that's a difference of opinion on how we look at it, and is that the only way we are legally allowed to look at impacts
[1:06:09] or is that a choice that our consultants or we as a city decided to look at the impacts?
[1:06:20] Well, the city has discretion to define thresholds as long as there is a basis and evidence.
[1:06:28] So it is a city decision within reason greenhouse gas emissions or not just a regional
[1:06:37] that a global impact.
[1:06:41] So the standard way to analyze that is through not a site-specific analysis, but through
[1:06:49] a broader analysis,
[1:06:53] the california resources board, the expert state agency that's charged
[1:06:58] with oversight of this provides guidance and direction on how to evaluate GHG impact.
[1:07:07] and it was imparted to the air boards comments that the city chose to focus on a regional
[1:07:15] threshold in the EIR rather than a site specific EIR, but ultimately it is the city's
[1:07:22] decision.
[1:07:25] Quickly is, is it termed, it's something termed in the EIR, like it's not here then.
[1:07:30] There is not hear somewhere else. Do you remind us how it's referred to something like a little phrase like that?
[1:07:43] That's a phrase I just used.
[1:07:45] But it's like a cute little, it's not hear than there.
[1:07:52] There, yes, council member Davis, the citation is from the Center of Biological Diversity versus Department of Fish and Wildlife and it's whether hear or there.
[1:08:01] So, you should whether hear...
[1:08:02] I think that's actually a key decision.
[1:08:04] It's associated with such population growth will occur.
[1:08:07] Whether here or there.
[1:08:08] Whether here.
[1:08:08] That's the term.
[1:08:10] One more quick thing I wanted to add for context.
[1:08:13] The EI also includes impact GHG3, which we haven't talked about.
[1:08:18] And GHG3 does evaluate the projects, features and emissions at the project site in isolation.
[1:08:25] So, GHG3 uses the Bay Area or Districts Greenhouse Guests thresholds, which will probably
[1:08:30] projects, specific thresholds, and it looks at consistency with cars 20, 22,
[1:08:35] scoping plan and the scoping plan measures and attributes that apply to when you
[1:08:40] use development projects like the valence. So we also have GCH2.
[1:08:47] So if I may,
[1:08:51] so you talked about having the dust in particular and the NOX as being significant and
[1:09:00] avoidable in during the entire buildout. How long do we expect that buildout to take? And is
[1:09:12] it reasonable to have that effect on residential that are occupied when it's going to be
[1:09:30] So what time frame would it be that they would be considered significant as a residential project that's next to an ongoing construction zone? Is there any metric for that?
[1:09:50] I can help answer that one moment.
[1:09:55] So, Impact EQ1, which is regional criteria polluted emissions,
[1:09:58] so this is new mass emissions.
[1:09:59] So how many pounds are tons of pollutants are being emitted?
[1:10:04] That evaluation looked at all years of construction,
[1:10:07] phase one operations, and full build out operations.
[1:10:11] So in EIR, we looked at construction through, from 2026 through 2033,
[1:10:18] And then fold build out, phase one, initial phase two, and fold build out.
[1:10:23] And then fold build out represents annual emissions as the project is operational at the
[1:10:31] year that it's built out.
[1:10:32] And so we didn't look at future years, future years would be likely lower than that level
[1:10:38] because vehicles continue to get more efficient and technology improves and energy, all
[1:10:44] that stuff gets better. But to your question about exposure, like basically like residents,
[1:10:50] potentially expose to those pollutants during construction, we separately looked at
[1:10:55] in the EIR and that's a separate impact. What that exposure to those emissions would look
[1:11:01] like from a health risk perspective for both on-site residents and off-site residents
[1:11:06] near the project site. And that is a separate evaluation in the EIR with the separate
[1:11:11] personal of mitigation. But when we looked at significant impacts and we're using the
[1:11:19] regional model and it's very different if you have a cloud of dust that is in this room versus
[1:11:31] a cloud of dust that's being analyzed over the entire city of Brisbane. That's the same amount
[1:11:39] dust that might be in this room is so it lessens the impact when you look at it, wouldn't
[1:11:45] it lessen the impact when you look at it from a regional impact for the particle size.
[1:11:53] Yeah, I think I see what you're saying. Yes, is the answer. So when you're looking at
[1:11:58] regional emissions, you're talking about all of the pollutants that project vehicles would admit,
[1:12:05] for example, whatever they're driving in the region,
[1:12:07] in the 9 County Bay Area region,
[1:12:09] potentially, and beyond.
[1:12:10] And when you're talking about health risk,
[1:12:11] you're only talking about the local pollutants,
[1:12:15] like dust that is being produced and dispersed
[1:12:20] at that receptor location.
[1:12:21] So if there's a house here, what is the local pollution
[1:12:24] that that house might be
[1:12:25] in taking during construction and during operation?
[1:12:28] So it's a much smaller subset
[1:12:30] if I'm understanding your question and the full regional picture.
[1:12:33] So, that local impact, that impact at that single receptor point, that house, that resident
[1:12:39] point is less, I guess you could say, but the exposure is less, but the risk assessment
[1:12:47] only looks at that local impact.
[1:12:49] And I think that last point that you just said is important, I want to make sure that we're
[1:12:53] doing an apples to apples comparison, that the health risk is in a very localized and
[1:12:59] on those specific pollutants that affect human health.
[1:13:06] When we're talking about a regional analysis for greenhouse gas emissions, it's a different
[1:13:12] type of impact.
[1:13:13] It's a different type of analysis.
[1:13:16] So they're, and the EIR includes both the regional look for how GHG emissions are handled
[1:13:22] as well as the criteria pollutants in the air quality section.
[1:13:27] So they're, I just want to make sure that folks aren't confused, that we said that there's
[1:13:32] a regional analysis being done for greenhouse gas, looking at it, how we reduce GHGs throughout
[1:13:40] the region, that doesn't affect the type of air quality and health risk analysis that
[1:13:46] was also done in that is very site-specific.
[1:13:48] And that's where you talk about the receptor locations.
[1:13:51] And then there was a comment that made a few minutes ago that we looked at ways to find the project consistent.
[1:14:02] So is that where we are trying to manipulate the data to make it consistent or looking at how we look at the study to find what mitigation measures need to be done?
[1:14:16] I think it was a phrase that Brian used, but we're talking about comparing the project to
[1:14:28] the local air quality districts, GHG thresholds, and figuring out what needs to be done to make it
[1:14:35] consistent, meaning what mitigation measures or modifications to the project need to be imposed
[1:14:40] so that it can meet the policy goals that are in the thresholds that the Air District puts forward.
[1:14:47] Not how do we cook the books so it looks better on paper.
[1:14:51] That's what it sounded like.
[1:14:52] But yeah, so it did.
[1:14:54] I'm glad they do.
[1:14:54] We could clarify that it was specifically,
[1:14:58] and because that in that.
[1:15:00] GHG impact 3 is identified as significant before mitigation. And so it was exactly that process that Brian was describing, identifying mitigation measures that could be imposed that would result in a less than significant impact under that particular criterion.
[1:15:19] So it's definitely a looking at what changes and requirements need to be imposed to meet the policies.
[1:15:28] Thank you. That's all of my questions for now. Before we move to the public, do we have
[1:15:33] anyone else on the council wants to ask another question you thought of?
[1:15:37] I have a Madam Mayor once you ask. You've really gone in the weeds already. I don't need to go further.
[1:15:44] Okay, so I just have this a couple more questions than Madam Mayor.
[1:15:47] So the Air Quality Study, who did the study?
[1:15:54] Okay, all right, so that this one wasn't this one didn't come from VDI.
[1:16:02] No, okay, okay, I'm just
[1:16:06] Thanks, Stephanie.
[1:16:10] Okay, I just so
[1:16:13] Okay, are we going to have a little council discussion after the public speaks or are we going to have a break and then
[1:16:20] Go on to the next item. What was your, would be council's pleasure normally, will we would go to the public after council questions?
[1:16:31] Because I have some, I say I have like a comment that I'd like to make after the public space.
[1:16:36] Just remind me if I miss it.
[1:16:38] Okay, great.
[1:16:39] Do you have another?
[1:16:40] That was it actually.
[1:16:41] Anyone else?
[1:16:47] Okay.
[1:16:47] from the previous meeting on the 14th, I have seven of them here. Again, just to remind everyone that if you wish to speak, we need you to fill out a slip or if you're on the line, use the chat feature and
[1:17:04] and angered will fill out a slip and give it to me.
[1:17:08] We're doing these in the order.
[1:17:09] They're all numbered.
[1:17:11] First come for a serve.
[1:17:14] I'm gonna read some of the names off
[1:17:16] and one of the things that was requested
[1:17:18] from the last meeting is I'm gonna read the names off
[1:17:22] so you know what order you're in.
[1:17:23] And if we could please,
[1:17:25] the next person be ready to come right up
[1:17:27] so we don't just sit and watch people walk up.
[1:17:29] I mean, you could even queue up on the sides
[1:17:31] and be ready to go. That would help us and appreciate that. So the first one I have I'll read
[1:17:37] through them first. I'm going to have Paul Boscow, then Anthony Walker, then Linda Salman, then Michelle Salman,
[1:17:46] then Ali Seperman, and Clara Johnson, then Dan Adilworth,
[1:17:54] and then Karen Cunningham in that order.
[1:17:57] So first two, Paul, you're up first and then Anthony, you'll be after him.
[1:18:08] Thank you,
[1:18:10] So I sat on the drafts environmental impact report committee and other formats and we talked about the conveyor to transport stuff from that site.
[1:18:24] Trucking that stuff from the site is not a viable plan.
[1:18:28] And it's the, it's viable as far as for construction, it's the best way to transport the
[1:18:35] sorrows by trucks to have to put it on the conveyor.
[1:18:39] They have to handle it, they've got to bring it over to the truck and then the loader's
[1:18:43] got to put it on the conveyor and then it's got to come off the conveyor and then a loader's
[1:18:47] got to put it back on the truck's butt.
[1:18:50] It's all within the site.
[1:18:51] It's not driving on the public right away.
[1:18:54] It's within their site.
[1:18:56] I know the cow trance.
[1:18:59] It's been said that they're against a conveyor.
[1:19:02] Although there's many times that temporary construction buildings
[1:19:06] bridges over there.
[1:19:08] The wires over the tracks.
[1:19:12] That way we could use an electric.
[1:19:15] As was said, conveyor.
[1:19:17] And I appreciate back when the developers
[1:19:21] seriously looked at a way of keeping the transfer of the soil off the streets.
[1:19:28] I mean, you mentioned Central Brisbane and the Ridge, so I take it, it can't go through
[1:19:33] there for Cisco through Little Hollywood and Down Basior, which was originally what they
[1:19:38] talked about, and we decided that that wasn't for any neighborhoods the right way to transport
[1:19:43] that amount of soil. So, with that said, I don't know how we can convince CalTrain. I mean,
[1:19:54] you need more of the developer needs more than themselves going to CalTrain. We should
[1:19:58] be supporting that and explaining the advantages of transporting the stuff over with electric
[1:20:07] conveyor. If that's not a viable plan, then we should use the
[1:20:14] Visitation Creek Channel, which is primarily tidal, and if we plugged up the
[1:20:23] outlet to the bay, I've never seen a flood on that road, even with maybe with one of
[1:20:29] the highest tides, but rainfall could be diverted and not come down the channel, and then
[1:20:35] up the base side and then we could run the conveyor underneath through that channel and underneath
[1:20:40] the cow train tracks because I believe I need the cow train tracks. Here's a brick tunnel that's
[1:20:46] a strong green tunnel that could probably accommodate the conveyor. But anyway we look at it.
[1:20:54] I mean the idea of electric trucks, yeah, it's a great idea but I don't think that's going to happen.
[1:20:59] I mean, it's just not to move that amount of soil, the diesel trucks are just, I mean, those kind of trucks are meant for the highway, they're not meant for that kind of transport, even though they have a technology, but we don't need those trucks on our roadways at all.
[1:21:17] It should stay within the property.
[1:21:21] And if a conveyor isn't going to be a viable plan, then I couldn't see why I would be
[1:21:26] unreasonable to have a crossover at the grade level of the tracks.
[1:21:30] Who just mean that Caltrain would have to have somebody on site the whole time to allow
[1:21:37] trucks to cross in between trains coming, and I don't believe that the train except for
[1:21:42] It runs at night, so they can have a night time operations, but what I'm really concerned about is the mitigation measures to deal with the dust.
[1:21:53] And nothing's being done there, nothing's been done at the quarry with all that crushing of the concrete that came off the highway at hospital curve.
[1:22:02] So, where's our oversight?
[1:22:06] And if they are going to be doing that, the mitigation measures should be monitored, and I mean seriously monitored, so thank you.
[1:22:15] Really quickly, can I just get a clarification from staff?
[1:22:19] I had one, two.
[1:22:19] Oh, okay, um,
[1:22:24] we heard caltrane and caltrance and just to make sure...
[1:22:30] The word that we had from Stephanie was that you were in negotiations with CalTrain, not CalTrain. Is that correct?
[1:22:41] So it was not CalTrain's objecting to a conveyor.
[1:22:46] And it gets confusing, I'm sorry, I'm a spoke.
[1:22:50] You meant CalTrain. I figured that.
[1:22:52] Yeah, okay.
[1:22:53] Okay, thank you.
[1:22:54] Well, I know we've kind of started talking about the conveyor, and I mean, I could see why we started talking about truck trips as it pertains to GHG and air quality, but I do want to just confirm that we're really going to get much deeper into this.
[1:23:10] When we get to remediation and that really this meeting is not the time to be diving deep into Earth movement.
[1:23:20] The truck trips are kind of on the fringes in terms of how they relate to air quality,
[1:23:25] but I just don't want to get off track right now and really, and I'm sure the public,
[1:23:31] this is something I know is a hot topic in the public, and that people really want to
[1:23:34] weigh in, and I'm sure the council wants to weigh in, and I just want to make sure that we're
[1:23:37] staying on the topic of this meeting, and so I want to understand that this is really not
[1:23:45] for this meeting and for remediation correct?
[1:23:49] Well, yeah, I guess it's up to the council
[1:23:51] and the way that you frame the issues
[1:23:53] because yeah, you're right on both counts.
[1:23:57] That there's a separate remediation focused meeting
[1:24:00] where there'll be much more talk about how the technologies
[1:24:06] that are used, the process, the locations,
[1:24:09] a lot of what you're talking about,
[1:24:12] but as you just pointed out as well,
[1:24:13] to the extent it relates to the air quality impacts and the impacts that we're being mitigated
[1:24:18] through the EIR that that is ostensibly what we're we're discussing here as well.
[1:24:24] I'll just add that but yes we got it. Thank you Peter. If I may so I mentioned the truck trips
[1:24:30] because of the dust is was my and and of diesel fumes I mean the diesel fumes within the
[1:24:37] site instead of the three and a half miles was what I was kind of getting at thank you.
[1:24:42] Anthony Walker, and after Anthony, we have Linda Salman.
[1:25:02] Good evening, everybody.
[1:25:05] So on greenhouse gas emissions, I just wanted to make a comment.
[1:25:12] EIR projects that the bail-ans will add 51,260 metric tons of greenhouse gas emissions annually at full buildout.
[1:25:23] Brisbane's entire 2023 community-wide inventory was 71,222.
[1:25:32] So that equals approximately 72% of our total current emissions added on top of what we're already dealing with.
[1:25:41] So without any kind of failing reductions or accountability,
[1:25:45] You know, Brisbane's total would reach 122,480 metric tons, that's approximately 45% above the 2005 baseline that we're measuring this all against.
[1:26:00] So how we call that and increase that consequential less than significant with the straight faces kind of beyond me.
[1:26:08] A less than significant sequifinding establishes a regulatory floor, it should absolutely not become Brisbane's climate policy ceiling in my mind.
[1:26:20] The draft EIR included an offset program, annual documentation, a true up mechanism, and personally, frankly, I thought parts of that framework went a little bit too far.
[1:26:31] But, finally, I did not attempt to moderate it.
[1:26:34] Instead, it snapped back in the other direction,
[1:26:37] the opposite extreme, and removed any outcome-based measurement
[1:26:42] or accountability measures entirely.
[1:26:44] It crossed it all out.
[1:26:47] And what remains are design requirements.
[1:26:49] It's a checklist, such as electric buildings,
[1:26:53] electric vehicle infrastructure,
[1:26:56] considered better than regional averages.
[1:26:58] and those are good requirements. I'm not against those. But they do not tell us what the project
[1:27:05] actually emits.
[1:27:08] Whether the model reductions from those positive urbanist features actually
[1:27:12] occur or whether corrective action is needed.
[1:27:17] And, you know, being better than regional averages
[1:27:19] at this point is just not enough. We've just had the hottest summer on record.
[1:27:25] Our regional norms
[1:27:26] and business and usual are failing as miserably worldwide.
[1:27:32] We need to aim higher.
[1:27:34] I just want to bring up Brisbane's Climate Emergency Declaration
[1:27:38] commits us to reducing emissions 66% below the 2005 baseline by 2030,
[1:27:47] and achieving carbon neutrality by 2030.
[1:27:51] As of our last GHG inventory in 2023, we had achieved only a 15.73% reduction.
[1:28:00] So we are very far behind where we need to be.
[1:28:03] Brisbane identifies itself as, you know, with environmental stewardship as a core part of its identity.
[1:28:12] But there is a profound hypocrisy in celebrating that identity while refusing to even track the actual missions.
[1:28:19] of the largest single development in our city's history.
[1:28:24] We should not dismiss our sustainability framework or climate emergency declaration as merely
[1:28:29] aspirational as has been done in the final EIR and look the other way.
[1:28:33] Sequoid didn't require solar panels on mission blue or converting the municipal pool off
[1:28:39] of fossil fuels.
[1:28:40] It didn't require the BBEP program and it didn't require the climate emergency declaration.
[1:28:49] or writing a detailed sustainability framework to guide this whole process.
[1:28:53] We did those things because the community aspired to do more and to be better.
[1:28:59] Asperations, the reason we adopted the goals more ambitious than the legal minimum requirements aspiration was the point.
[1:29:09] So if this is really the best that we can manage when it comes to GHG and the Baylands,
[1:29:13] We take those projections in the finally IRF, face value, and neither the city nor the public
[1:29:19] may ever know whether those assumptions used to justify the project were accurate, conservative
[1:29:24] for simply wrong.
[1:29:27] Frankly, to my mind if that's the best we can do, then I really don't want to hear anyone
[1:29:31] going on again about how much Brisbane cares about the environment.
[1:29:37] Our actions will have told a very different story when it matters.
[1:29:42] We're almost done. We're past time.
[1:29:44] Oh, apologies. Yeah.
[1:29:46] So, at a minimum, I urge you to reconsider guidance being offered on GHG emissions and
[1:29:53] require periodic developer-funded greenhouse gas inventories public reporting and ongoing city review.
[1:30:00] Thank you. Linda Salmon. And after Linda, we have Michelle Salmon.
[1:30:05] Okay.
[1:30:09] Michelle Salmon, Brisbane resident. With the JST emissions, everything that Anthony said, I totally agree. And I support what he said.
[1:30:20] And we really need to look to the long future because this planet is in dire straits.
[1:30:26] But on a day-to-day issue, dust is a serious issue, and I will say that the balance is
[1:30:34] not have a good track record with desminigation.
[1:30:38] I myself have, you know, Bay Area, Air Quality Control and Speed Dialite, you just be on
[1:30:44] a first name basis with Dick, their investigator, who rarely showed up in time to do anything
[1:30:49] about it. So I'm not really happy about moving, you know, 125,000 truckloads of dirt, but some
[1:30:58] of the things that we could do to mitigate that is make sure that those loads are covered when
[1:31:03] they're moved. So dust doesn't build out of the trucks everywhere. And that didn't happen with
[1:31:10] the concrete coming from the freeway project, by the way. I think all of us really suffered a lot
[1:31:16] during the smoke this past week from the angel island incident and also all of the dust.
[1:31:22] I know that I've been horse, we've taken a really big load of dust from the quarry during
[1:31:27] this crushing process, everything's covered with dirt.
[1:31:32] So I really want us to think about the day-to-day of covering the trucks.
[1:31:37] I'd like us to test this soil on a regular basis as they move through this pile because
[1:31:42] Because we do not actually know the origin of all of the dirt that is on the east side
[1:31:49] of the train tracks.
[1:31:51] And I think it's important because when we talk about GHG emissions, we're talking about
[1:31:56] the number of tons of pollutants that are in those emissions.
[1:32:03] And eventually those come to ground.
[1:32:05] I mean, they float up and they come back down.
[1:32:09] And when you water it, it becomes silt and goes into the bay and you look at historical photographs and aerial photographs.
[1:32:19] You can see how much siltation has happened just from the dirt that has blown off of the bay land site over the last 10 to 15 years.
[1:32:30] And I used to commute that corridor every day and sometimes in the afternoon the dust would be blowing so hard.
[1:32:36] off of the site across the freeway and into candlestick coven and then on across the bay
[1:32:41] that would be this big brown like swath of dirt in the air and it would there would be so much
[1:32:49] of it blowing off it would be actually hitting the car with dirt everywhere and it didn't matter
[1:32:55] how many times you called air quality control. So I don't trust the regulatory agency to be able
[1:33:01] handle monitoring the amount of dust that this produces and wetting it down is kind of
[1:33:08] moving the problem from the air to the water quicker than if it goes up and settles down.
[1:33:14] So, it really isn't an issue, that's all I have to say, but I really think that we need to
[1:33:20] to really tighten a lot of the regulations on that if we do have a conveyor belt,
[1:33:25] it needs to be a covered conveyor belt so that dust just doesn't blow everywhere.
[1:33:30] That's just really, really dangerous, and it causes silicosis for if it's been, and it causes pollutants, and it has nauseous things in it.
[1:33:41] And we don't really want people to be breathing that. And we don't want it in the water either. Thank you.
[1:33:49] Thank you, Linda Salman. And after Linda, we have... Alley.
[1:33:56] I'm sorry, I'm late and without my notes, I just go back from the eye doctor and I can't even see.
[1:34:02] So with this, you can, that's all we have.
[1:34:05] Just silica.
[1:34:06] Yeah, I have silica in my lungs from two seasons of the harm attend.
[1:34:10] And it's not fun and it has caused other problems in my body.
[1:34:15] And I don't recommend it to anyone.
[1:34:17] So I really, I think we need to work better on this whole thing.
[1:34:22] In terms of the EIR itself, I really still do not feel that it's complete.
[1:34:28] It doesn't address so many issues like this.
[1:34:32] The idea that they're going to build out these single family homes on a five feet of
[1:34:39] clay and then expect nothing's going to happen.
[1:34:42] People aren't going to try and grow anything there when they show pictures of houses
[1:34:45] with trees and gardens.
[1:34:48] Not real.
[1:34:49] The whole thing is not real.
[1:34:50] And I just want to add that, I guess it was 32 years ago, 1994 General Plan, which I was
[1:34:58] part Arthur of, called for all kinds of things and allowed them to build at the beginning
[1:35:05] of the site where the sledge lock is where you might be able to get footing and have businesses
[1:35:13] and dwelling units. Not single family dwellings with children on toxic soil and dust. The way it seems
[1:35:21] like it's planned out, they're going to be having building houses and having kids there and then
[1:35:28] moving all the stuff from the dump with just not, it's not about safe, period, period. It's not
[1:35:36] and for us to do that? No. The other point I want to make is let's not make the same mistake we do
[1:35:43] the North East Ridge, where as soon as they got the permits they sold it and then they ignored
[1:35:48] every single thing that we had conditioned to make a safe place and make the construction
[1:35:55] saved, which is why I sued them. And I am just going to say one more time, if we're going to give
[1:36:02] do anything or give them permits for anything is going to be only for this owner and if they sell it,
[1:36:07] all has to start over again. I'm sorry. This is not. This is a show and we've
[1:36:14] were done with it. It's been for so many years. Thank you.
[1:36:19] Thank you. Allie and then after Allie, we have Clair Johnson.
[1:36:30] Good evening, Mayor and Council members. I'm Allie Saperbidden with the Housing
[1:36:33] Action Coalition. The Baylands is one of the most significant opportunities in
[1:36:36] San Mateo County to deliver new housing while advancing California's
[1:36:41] climate goals. In our comment letter on the draft EIR, we raise concerns about the proposed
[1:36:46] mitigation measure requiring the project to purchase offset credits for 1.5 million metric
[1:36:51] tons of CO2. We're raising this again because of the comments on this topic appear to
[1:36:56] misunderstand it. Requiring this project to buy carbon offsets will not produce better environmental
[1:37:01] outcomes. There's a reason this type of mitigation has only been applied to suburban
[1:37:06] straw projects, straw projects. And full development in existing urbanized areas is the best way to protect natural and agricultural lands and reduce greenhouse gas emissions.
[1:37:16] Thank you for recognizing that and revising the final EIR greenhouse gas chapter to better align with a state and regional climate policy.
[1:37:24] That correction matters not just for the balance but for transit oriented housing across California. Thank you.
[1:37:30] Do you? Clara?
[1:37:34] Here we go. And Dana, you're after-clear.
[1:37:47] Good evening. I'm here to state my support for the environmental
[1:37:52] issue. We're your alternative. We could have the least impact on the physical environment. If
[1:37:57] we let pressure on our water supply and our electric power supply, I would prefer an even smaller
[1:38:02] project, but that choice is not offered. The specific plan is to large and act in a dedicated
[1:38:08] open space. We should view GHG gases from a local point of view, I think. The pressure of
[1:38:17] the construction will be so loud and cause so much traffic for such a long time that people
[1:38:23] would become demoralized by the conditions. The animals that are near will probably flee.
[1:38:30] I appreciate the attempt that mitigation and wish there could be more effective ones in order
[1:38:35] to move the soil going from topic to topic to get through and get you on further on the list.
[1:38:43] In order to move the soil around, more of each 1,200 daily chives, 640 in one direction
[1:38:49] and then going back to where they came from the other empty.
[1:38:54] But that's still on the road and fouling the traffic.
[1:38:58] And the truckfifks are in the area of Blankin' Tunnel based where Boulevard, the Tunnel Avenue Bridge with the trucks coming every three or four minutes for three years.
[1:39:11] In order that the phasing functions well enough to avoid things descending into chaos, the phasing requires a very disciplined oversight by the developer and by the city.
[1:39:21] That discipline means on-site monitors and coordinators overseeing work every day.
[1:39:27] They need the power to shut it all down when everything starts to go south on them.
[1:39:32] If the FER suggests a mitigation mentor, then that mitigation must contain tests, just
[1:39:40] I'm sorry, text describing how it will be achieved, otherwise there isn't any mitigation.
[1:39:45] In the FER there is a response to a comment that since it is not a significant impact, then
[1:39:51] We don't have to do anything under sequo.
[1:39:54] The fact that the measure was included in the document means there was a significance to
[1:39:59] someone, and that may be to a lot of people, or to a threatened species.
[1:40:03] I think we can do better.
[1:40:05] I strongly object to the road diet that's included in the Vesior Mobility Plan because
[1:40:10] it fails to recognize that Vesior Boulevard is a sub-regionally important north-south
[1:40:15] road.
[1:40:16] It needs to be more attention, fades of protecting workers from the toxic contamination in the soil and airborne dust and extreme air pollution and noise intensity surrounding them constantly from highway 101, base or boulevard and heavy construction.
[1:40:33] The landowner was not an arrest to get this project built here for decades. We should take the time needed to explore all the details and do it right.
[1:40:42] I think that we're going to review, again, I know and you're just discussing and I appreciate it, in order to determine whether some of it should be not locked out, but rather continue to be included.
[1:41:00] I'm interested in the idea that mitigation measures could be in the specific plan as policies and I hope you will consider that some more.
[1:41:10] Thank you very much.
[1:41:12] Thanks, Clara. Thank you, Dana. And after Dana will be Karen Cunningham.
[1:41:22] Thank you, Madam Mayor, council members. I have two questions from the prior meeting and a couple of questions about greenhouse gas emissions.
[1:41:33] What has happened to the city's agreement with the Oakdale Water District? Do we still have an obligation?
[1:41:40] because I remember the contract that was to be signed, said that after a certain date of
[1:41:46] something hasn't happened, that the city would continue to pay. And so I'm wondering if
[1:41:53] that expense is part of the revenue policy, if you remember. Regarding revenue policy, are there
[1:42:03] provisions, disallowing crypto, or the financing sources, and the reason, or even the
[1:42:14] ownership sources, and I would remind you of the experience with the sunset building where
[1:42:22] there was a Russian oligarch that wants to put an 80-story tower down on the old in Menlo Park
[1:42:28] of the old sunset building. So I'm wondering how we get protected from something like that.
[1:42:36] Regarding the greenhouse gas emissions, I would like to know if anything about Kinder Morgan
[1:42:42] was factored into it and if anything about the dump has been factored into it because as long as
[1:42:51] Those two places are not mitigated from the start.
[1:42:59] They continued off-gas, and I would like to remind you of the gas report that Barbara
[1:43:06] Abel had presented and it mysteriously disappeared, but it showed that all along the old
[1:43:15] There are emissions that exceed anybody's regulations and I don't understand why closing that landfill with the proper, there is only an interim system set up that a proper system be done first or else you cannot say that you're reducing gas house emissions.
[1:43:45] And the part about Kinder Morgan, I know we've been very careful not to bring it up,
[1:43:53] but it has had to spill.
[1:43:56] The spill is heading towards the bay.
[1:43:59] It will continue to off-gas unless the area around Kinder Morgan is mitigated.
[1:44:08] And we were told that there's an industrial cleanup standard for Kinder Morgan, and they expect there to be gas fumes because hey, it's a tank farm and therefore there's really no mitigation because that they expect all of those gas fumes to be coming off the tank farm.
[1:44:31] So, as long as you just ignore Kingdom Morgan, you are doing the public at this service.
[1:44:39] So, I would like to know if those were factored in the greenhouse gas emissions by leaving them silent for 10 or 15 years, how much more we have to endure.
[1:44:58] a program that should have...
[1:45:00] Then handled 35 years ago when the endangerman, eminent endangerman orders were first put on this property, 1988. Just reminds you. Thank you.
[1:45:16] Do we have Brian on line still?
[1:45:20] Yeah, that's a good question.
[1:45:21] Brian, could you answer the question about whether Kinder Morgan and the euphemistic
[1:45:29] unregulated garbage dump were factored into emissions?
[1:45:36] If the, sorry, I'm not sure I fully understand the question, but if the question
[1:45:40] had to do with hazardous materials, the release of hazardous materials and remediation,
[1:45:45] is that...
[1:45:46] No, no.
[1:45:47] So she was talking about the fact that the dump actually has emissions that have been ongoing
[1:45:52] for decades.
[1:45:54] And the Kinder Morgan also has, as a tank farm, a certain amount of gases that are emitted
[1:46:01] and whether those were in the calculations.
[1:46:06] So, as Brian's thinking about that, is it that those would be part of what Sequel would
[1:46:11] call the baseline conditions when we're analyzing impacts from the projects, so we're looking
[1:46:17] at the project's effect on new emission sources. Things that are already existing part of the
[1:46:25] environment are part of the environmental context, the setting, the baseline for the analysis,
[1:46:31] and then we're looking at how the project makes changes to those existing conditions.
[1:46:37] Thank you.
[1:46:39] Thank you. Karen, I guess Madam Mayor, City Council. I guess my comment question here
[1:46:46] is kind of a follow-up to that, so Brian, don't run away.
[1:46:51] Thank you, Dash, one, we have listed ROG, Knox, PM10, and PM2.5 is the major issues.
[1:47:02] I want to take us back to when the bail-ans was medical, military, and post-1906 earthquake.
[1:47:18] It's where all the waste went, was into the bail-ans, and everything that was in those buildings, including a specialist, et cetera.
[1:47:27] The one thing that has always stuck with me, and I've asked the question multiple times over the years,
[1:47:34] is, what were alpha-mometers prior to the 1970s?
[1:47:38] Alpha-mometers were all mercury.
[1:47:43] And if you look at every piece of information we have relative to the baylands,
[1:47:47] and all of the studies that have been done,
[1:47:49] the word mercury does not shock one time in my searches on the city's website
[1:47:54] or anywhere else. And as we're talking about air pollutants relative to these truck trips,
[1:48:00] when soil contaminated with mercury is excavated, transported or relocated,
[1:48:05] the mercury spreads through mechanical movement, dust inhalation, water runoff, and vapor emissions.
[1:48:12] So that is my comment. And I think some of these things...
[1:48:16] I don't know why they're not front and center on the things that we're talking about relative to moving this kind of dirt.
[1:48:23] So I really want you to think about that.
[1:48:26] That's my only comment.
[1:48:27] Thank you.
[1:48:29] Fine.
[1:48:30] Brian, did you have a comment on the Mercury?
[1:48:35] Yeah.
[1:48:35] I would just say that I think that we'll be covered in the upcoming hearing on hazards
[1:48:41] and hazardous materials that is part of the hazardous remediation planning requirements.
[1:48:48] Okay.
[1:48:49] Thank you.
[1:48:50] Stores.
[1:48:51] Sorry.
[1:48:52] I didn't tell you.
[1:48:53] Give you for warning. So after scores, we have Jeremy and Levine online. After that, we'll have Roland online, then Charles Spencer and then Jordan Grimes online, just to give everybody a little advance notice. Thank you, George.
[1:49:10] Hi, thanks so much for letting me ask a few questions and make a few comments. Again, with Brian being up there when I was looking at the EIR.
[1:49:21] And it really does seem that the operational greenhouse gas emissions is going to be the largest and it really seems that by far the largest driver of that is mobile, which I guess is just transportation, I love to have clarification whether that's true.
[1:49:44] And then on something else in terms of air quality, we, several places in the EIR, we talk about wastewater treatment plant.
[1:50:01] And I just want to make sure that we do put some teeth in that it is modernly designed to reduce the noxious smells,
[1:50:13] which come from waste water treatment, because Brisbane has a history of being known as the
[1:50:20] smelly town. I don't want us to go back to that. So those are my two comments. Thanks so much.
[1:50:29] Do we have a comment from the developer's agent about the wastewater treatment plant
[1:50:36] standards of design? I'm not trying to put you on the spot if you'd like to make a comment if not
[1:50:42] is going.
[1:50:46] There is a mitigation measure that the the water recycling facility will not stink.
[1:50:54] Okay. All right. Jeremy online. Jeremy Levine.
[1:51:05] Hey, good evening for Spans City Council. It's good to be back. I enjoyed watching the other meeting,
[1:51:11] so I went a little long. My name is Jeremy Levine. I'm the policy manager with Housing Leadership Council.
[1:51:18] of San Jose of County. I'm also for what it's worth. I do use pay in Sierra Club member and um
[1:51:26] you know I'm in all this discussion uh I thought a little bit about me might be helpful.
[1:51:32] I'm 29 years old. I know it's it's it's young. I suspect that I'm less than half the median age
[1:51:41] of the people who have been commenting and so there's a lot of wisdom. I've appreciated hearing
[1:51:47] I'm not bringing that up to past dispersions, I'm bringing it up to make the point that I have a really big vested interest in the future of the environment and the planet.
[1:51:57] I'm really worried about climate change.
[1:51:59] I'm really worried about being able to breathe clean air, about being able to have high quality water, about being able to live in communities that are healthy and sustainable and clean.
[1:52:12] And when I look at projects like the Baylands, I see so much opportunity.
[1:52:22] There is a cow train sitting next to a recycling plant and a duck.
[1:52:29] This is like...
[1:52:30] What? Hundreds of millions of dollars, billions of dollars of infrastructure that are not able to get the kind of ridership. It's the lowest ridership station in the entire corridor.
[1:52:42] Because people can't live near it. There aren't enough jobs near it. There are many ways that this project will have local impacts. But man, when I think about local impacts, I think a lot about a police officer from daily city, who I talk to at the months again.
[1:52:57] And I know it's Daily City not Brisbane, but hear me out, because I think Brisbane probably has some of the same circumstances also.
[1:53:05] This police officer was telling me about how he lives in Modesta and commutes every single day to Daily City.
[1:53:15] There's no public transit option. He sits in traffic for an hour and a half or two hours.
[1:53:21] Each direction, just so that he can reach a good
[1:53:25] page of and provide for his family, and he used to live in the peninsula.
[1:53:30] But as he got married and had kids, there was no home for him nearby.
[1:53:38] So that seems like a pretty big cause of greenhouse gas emissions.
[1:53:42] That seems like a pretty big cause of particular matter.
[1:53:45] You have somebody driving a car, spewing up, you know,
[1:53:49] rubber articulates and gas into the air for hours every day, going through communities across the peninsula, going through Brisbane.
[1:54:04] So, you know, this, this EIR, this project was first proposed when I was eight years old.
[1:54:12] In that time, the median home price in Brisbane is more than doubled, the median rent is more than doubled.
[1:54:16] There are really big environmental impacts.
[1:54:19] There's already been a certified IAR for this project, you know, maybe it's because I don't
[1:54:25] have the experience of everyone in this room, but a lot of this conversation seems
[1:54:28] pretty redundant from what already happens just eight years ago.
[1:54:32] The conditions haven't changed, the conversation has just become more complicated.
[1:54:37] So, you know, it was speaking on behalf of myself as a young person looking to the future,
[1:54:42] not just the first thing or San Mateo County, but of the planet.
[1:54:45] I really hope that the council will really try to find a way to get to guess without imposing
[1:54:53] the costs that make this impossible.
[1:54:56] Without imposing costs that don't consider not just the global but the regional and the
[1:55:01] local impacts of a police officer or somebody like me who can't afford to live in the
[1:55:07] community.
[1:55:07] So thank you for your time.
[1:55:09] We'll look forward to your discussion.
[1:55:12] Thank you, Jeremy.
[1:55:14] Roland, online.
[1:55:17] And after Roland, we have Charles Spencer.
[1:55:21] Thank you, Madam Mayor and the Council.
[1:55:23] Thank you for the opportunity.
[1:55:25] So I have an extremely quick question.
[1:55:29] Which has to do with moving all these dirt across the country.
[1:55:33] And I'm wondering if it would be possible
[1:55:37] prioritize the Geneva of new extension overpass over the counter-intracts and then that
[1:55:45] use that overpass for all the truck movements across the tracks.
[1:55:51] I believe you'll be cutting the truck mileage by about 90% and the solutions are
[1:55:58] coldingly.
[1:55:59] So if somebody could speak to that, that would be much appreciated.
[1:56:02] Thank you.
[1:56:04] Anybody want to tackle that, that might be a little difficult rolling to answer on the spot tonight.
[1:56:12] It's a bit subjective.
[1:56:16] We do have the transportation topic in the next meeting, so we can take this question down.
[1:56:23] And at that point, we will have our transportation consultant and perhaps they can help us on that.
[1:56:29] Okay, perfect. Thank you, Kevin. Thank you, rolling Charles.
[1:56:32] Thank you.
[1:56:32] Yeah, thank you. I want to thank the kids who were I am after for hosting this meeting. I have two questions concerning the cap.
[1:56:40] The first underneath the cap, the contaminated liquid will flow. I'd like to know what analysis you have on the direction of the flow and potential accumulation points.
[1:56:50] Second question. Also underneath the cap, pressure will be old. We've got heat from the top and heat from underneath below ground.
[1:56:57] this the soil will not be able to breathe like it naturally would. So a pressure is going to
[1:57:03] build. I'd like to know what analysis you have on how that pressure will relieve itself and
[1:57:09] where you expect it to relieve itself. Thank you. Staff want to tackle that one, but isn't that
[1:57:15] for like a future meeting? That was what we were going to say. So when we go through the remediation
[1:57:22] topic, we'll have the engineers and experts to talk about how those systems will work.
[1:57:27] So, can you capture that, try to just drop that question down to ensure that it's included?
[1:57:34] Yes, thank you.
[1:57:36] Jordan Grimes Online?
[1:57:44] Yes, good evening, Council Honorable Mayor.
[1:57:46] My name is Jordan Grimes, and I'm the Legislative Director for Green Belt Alliance.
[1:57:50] We are a nearly 70-year-old environmental organization, working throughout the Bay Area on conservation, climate resilience, and sustainable land use policy.
[1:58:00] We've been long time supporters of the Baylands project and have been tracking this very closely for more than a decade now.
[1:58:10] I want to say there are a number of significantly or what I view to be significantly misinformed claims presented this evening during some of the comments about the EIR and greenhouse gas reduction more broadly.
[1:58:21] So, I want to make this pretty clear, advancing this project is one of the best things
[1:58:28] that Brisbane could possibly do in terms of reducing greenhouse gas emissions.
[1:58:33] Brisbane is not an island, it is a city that is part of a region, and as such, emission
[1:58:38] reduction has to be considered holistically with the entire region in mind, and creating
[1:58:43] a dense, walkable transit-oriented area, and allowing tens of thousands of people to live
[1:58:49] work there will have an enormous positive effect on reducing greenhouse gas impacts.
[1:58:57] The single largest source of emissions in the Bay Area and California more broadly is the
[1:59:01] transportation sector. It is driving, it is you driving your car to get from point A to point B,
[1:59:07] and that is other people driving their cars to get from point A to point B. That is where more than 45%
[1:59:12] of our emissions come from. They are the result of vehicle miles traveled. And the only way to
[1:59:19] really deal with that is through land use change, and that is backed up by the UC Berkeley
[1:59:25] local government climate policy tool, which allows local governments to look at different
[1:59:30] potential policies to reduce greenhouse gas emissions, and which shows that additional
[1:59:34] infill development in Brisbane blows other GHG emission reduction strategies, things like
[1:59:41] heating electrification, commercial efficiency, et cetera, out of the water. It's infill.
[1:59:46] we know this, it's, it's, it's infill.
[1:59:49] Greenbelt first endorsed this project as far as I can tell back in 2011, and as a lifelong
[1:59:55] San Mateo resident, is someone who grew up in this county, the fact that we are still debating.
[2:00:00] This is first for him to say the least. When you think about how many metric tons of greenhouse gas emissions, we could have prevented had it been built earlier. And that is that is something that I think the entire Bay Area has to reckon with, certainly Brisbane is not the only city that is engaged this way, but it is a significant problem. And fixing it is going to require us to think a little bit differently.
[2:00:22] So I do want to sincerely thank City staff for advancing this, for getting us to what I hope is the end of a very long and arduous process.
[2:00:32] I understand that many of the concerns this evening, I understand where they're coming from.
[2:00:37] I certainly believe that they're legitimate, but many of them are also unfounded.
[2:00:41] So I hope you will advance this project sooner rather than later and look forward to attending the other meetings.
[2:00:48] Thanks so much.
[2:00:50] Thank you. So I have two more slips and I have a question. Ariel, you have open space. We're on greenhouse gas emissions.
[2:00:58] Did you really mean open space?
[2:01:04] Because that's coming up after this.
[2:01:08] Okay, so you want it then.
[2:01:12] Okay. We'll put you on the second part.
[2:01:15] So I have Matt Regan or Reagan?
[2:01:20] That's online. Oh, sorry.
[2:01:22] Online, Matt.
[2:01:24] Good evening, Madam Mayor Council members. My name is Matt Regan. I'm a chief policy officer at the Bay Area Council and like my good friend Jordan, he just spoke, we did first of the endorsed this project back in 2011, back when Council member Lance and I were much younger and much faster, I want to paraphrase one of my favorite Joe Bidenisms.
[2:01:50] And urge you to resist the temptation to compare this project to the Almighty and instead compare it to the alternative.
[2:01:59] The Almighty of a course of course is zero emissions, which we know is a physical impossibility.
[2:02:05] The alternative is, as Jordan Grange explained, tens of thousands of people living somewhere else.
[2:02:12] San Mateo in the California Coast writ large is one of the lowest greenhouse gas places in the world to live.
[2:02:20] It's temperate, it's transit served, it's 50 degrees in January, it's 50 degrees in July.
[2:02:27] You don't need heat, you don't need AC, you can live without a car, you have access to services and employment within very short distances of where you live.
[2:02:37] It is the lowest GHG existence you can possibly have on the planet.
[2:02:41] So to build in these sites, if you care, if you honestly care about reducing greenhouse gases and impacts on our climate climate,
[2:02:52] then sites like this be the absolute pinnacle of development and growth.
[2:02:59] The average per capita greenhouse gas production of a San Mateo resident is seven tons.
[2:03:05] The average California resident is 9 tons.
[2:03:09] People who live in the Central Valley, it's about 10 tons.
[2:03:12] That daily city cop who commutes every day to ours each way.
[2:03:16] He's not the only one who makes that commute.
[2:03:18] According to MTC data, 120,000 people every workday commute into the Bay Area from their homes
[2:03:26] in the Central Valley because we have for a generation refused to build sufficient housing
[2:03:33] to match our job growth.
[2:03:34] And we have forced all of our affordable housing into auto-dependent far-flung suburbs in the Central Valley and beyond.
[2:03:42] They're the lucky ones, 40,000 Californians each year move to Texas one state.
[2:03:48] The per capita greenhouse gas production in Texas is 27 tons.
[2:03:52] That's a 400% increase over the residents that would live in this project in San Mateo.
[2:03:59] So I would urge you, do not compare it to the Almighty compared it to the alternative, to those alternatives.
[2:04:07] This project meets all of the standards, environmental standards, and greenhouse gas production standards that have been laid out by HCD
[2:04:14] and by the California Air Resources Board. Again, if you care about the reduction of greenhouse gases, if you care about the future of the planet and our climate,
[2:04:24] Then this is exactly the sort of project that you should be approving and it should not be taking 15 years to get it approved
[2:04:32] And this is why we have a climate crisis and why we have a house in crisis because project like this are taking
[2:04:40] Too long to get approved. So please move it forward as quickly as possible. Thank you
[2:04:46] All right. Thank you. That is all I have on slips to have any other
[2:04:50] that they don't have, that being said, Councilmember Lens, you asked me to circle back.
[2:04:56] Yeah, thank you, Madam Mayor.
[2:05:00] I appreciate all the comments that the people raised one of the comments from
[2:05:06] the member of the public was about climate change.
[2:05:12] And for me personally, I think climate change is the greatest threat, not only to humans, but to all living things.
[2:05:20] You know, Anthony brought this up and I'm just going to read it again, which is resolution number twenty twenty one dash sixty two and this is Brisbane's climate emergency declaration.
[2:05:30] Which commits the city to reducing greenhouse gas emissions sixty six percent below two thousand five levels by twenty thirty and achieving net zero emissions by twenty forty.
[2:05:42] I also want to echo what Anthony said about being better than average compared to the rest of the series in the area and that that should be the standard that we shoot for.
[2:05:54] I think we can do better and I want to partner with you, BDI, to make that happen.
[2:06:01] You know, in measure JJ, it's item G, it's the Bayland's development shall be designed
[2:06:09] so as to be energy neutral on an ongoing basis.
[2:06:14] And so one of the requests that I'd like to make for future discussion is for us to evaluate alternative
[2:06:23] 7 and compare it to the current specific plan.
[2:06:29] In my mind, I think that alternative 7 is more in line with the measure JJ item, where that
[2:06:39] is designed so has to be energy neutral on an ongoing basis, while still providing the housing
[2:06:46] and commercial that we all need, and that I am in favor of.
[2:06:53] All right.
[2:06:53] Thank you.
[2:06:55] any member council want to comment from that or have another comment? I have just
[2:07:02] things that the public has mentioned that I just don't know that we're answering. Okay, I do too.
[2:07:09] So Michelle Salman brought up requiring the trucks to be covered.
[2:07:14] Is that is that something that is a provision in the AIR that already requires that or is that something that
[2:07:20] We would need to build into the specific plan.
[2:07:25] It's required in connection with the air quality.
[2:07:30] The EIR does require dust mitigation that meets all air district standards. And I think it's regulation 6. So Brian will correct me if I don't have that correct, has basically particulate matter and dust controls that are imposed on construction projects like this. And that doesn't include a requirement to have the trucks be covered.
[2:07:56] Okay, I thought that was the case. Is that only when they're on a public highway or is that covered when they're with an excite?
[2:08:04] I'd have to double check. I don't remember off the top of my head. I can answer that it's all during it's all hall trucks transporting soil
[2:08:13] Offsite shall be covered so any any any any transport of soil requires covering
[2:08:19] And I'm on that question councilmember or mayor pro-tendavis what about the conveyor belt that we're talking about as well
[2:08:26] Is that included in that?
[2:08:28] Yeah.
[2:08:28] The conveyor belt also is specifically addressed in the Medication Program.
[2:08:32] Thank you.
[2:08:33] To have, you know, watering coverage and have the air district standards applied to it.
[2:08:40] Okay.
[2:08:42] And then I had kind of touched in the questions about, like, some statewide carbon budgeting monitoring, reporting, etc.
[2:08:49] There was also something that I had discussed with legal before about the more that the city
[2:08:58] involves itself in oversight, beyond what's charged with the regulatory agencies, the more
[2:09:07] that the city then exposes itself to future liability.
[2:09:11] And so I, you know, I've heard this several times in these meetings where it's like,
[2:09:20] well, I don't trust DTSC or I don't trust this agency to do their job and therefore
[2:09:27] the city needs to implement some kind of additional oversight.
[2:09:32] And I think it's important because that was kind of discussed a little bit here from the
[2:09:38] look tonight, if as well intention as we may be and wanting to, you know, ensure that everything's done right, adding that additional level of scrutiny on the city's part does that in fact.
[2:09:53] Now potentially exposes to liability if something does go wrong in the future and they can point to the city and say, oh, what you've you've involved yourself in the process of regulating this.
[2:10:08] I mean, I guess it depends on the specific topic and actions, but in general, that's correct.
[2:10:15] If there's regulatory agencies, they have specific jurisdiction, they have particular expertise,
[2:10:23] then it often can be the safest approach for the city to defer to those expertise and not change that framework
[2:10:33] to avoid inserting yourself into a potential liability chain?
[2:10:41] So, you know, to put these measures in place to avoid a problem,
[2:10:45] could in fact create a problem,
[2:10:49] especially a major financial problem for the city and the future.
[2:10:54] So, I think it is just important that we hear a little bit more about that,
[2:10:59] because I have a feeling that's going to come up again.
[2:11:04] Um, and I think all the rest of the things that have come up, maybe are more for future meetings, so I'll leave it at that.
[2:11:14] Okay, so I do have a question, again, based on Michelle Salmon's question.
[2:11:23] Because the east side has vastly unregulated, not just garbage but toxic waste that was just dumped into the bay,
[2:11:31] And moving soil from east to west we know historically dirt or not dirt but garbage and refuse and toxic waste was deposited about 40 feet deep.
[2:11:45] Is anywhere is this written into the specific plan?
[2:11:50] I took a bit of solace from what Michelle was saying in that if you're moving dirt and you're a contractor, how do you know when you've hit 40 feet?
[2:12:01] How do you know when you're moving dirt and suddenly you're hitting toxic waste?
[2:12:07] So I don't know if anyone can answer that but I'm not saying that the city of Brisbane
[2:12:12] should assume any liability or do monitoring or testing but should we not have something put
[2:12:22] in that specific plan addressing that issue just because of the anomaly of the east side and
[2:12:30] And it's the airborne contaminants, but it's also people who might be working out there, even
[2:12:36] the truck drivers.
[2:12:38] And whatever is airborne out there comes either south or it blows east into someone else's.
[2:12:48] No more area.
[2:12:49] And so the remedial action plans all identify quantitative metrics for handling of soil,
[2:12:57] soil vapor ground water. And again, I think that when we're doing the remediation specific
[2:13:03] discussion, we can get into a lot more detail about the different measures, the type of testing
[2:13:09] that's already been done and how that will be implemented and monitored going forward.
[2:13:15] Okay, thank you, Eric. Anyone else? Council?
[2:13:22] Okay. Do we need a break? Yes. Okay, let's take a
[2:13:27] 10 minute break, it will turn into 15, but we'll take a 10 minute break and we'll see you back here.
[2:13:33] So for the public and the next topic so that people can prepare their slips is distribution
[2:13:40] and intensity of uses or what do you want to do next? Just so like if people want to submit slips,
[2:13:46] they know what the next thing is. We have land use plans and the design is coming up next.
[2:13:51] Okay, I've already got some slips, but I welcome anyone who hasn't filled one out,
[2:13:55] That's our city clerk, just hand it to our city clerk.
[2:24:19] Okay, we're back in session. Second topic is land use plans and design. Could we have a staff report, please?
[2:24:29] Yes, sure. We'll get the presentation up.
[2:24:32] And really, I'm just here to introduce Eric Galaway from ESA and he's going to review the specific plans land use plan and design standards.
[2:24:41] Go ahead, Eric. Thank you for joining us.
[2:24:44] Of course, thanks for having me and thank you, Jeremiah, staff and council.
[2:24:54] You can go to the next slide.
[2:24:59] So, chapter two of the specific plan is the chapter that contains the plan's land use program and planning districts.
[2:25:05] This chapter establishes maximums of 2,200 residential units.
[2:25:09] 6.5 million square feet of commercial uses, 500,000 square feet of hotel uses.
[2:25:17] Then this chapter establishes minimum average densities for the projects by land use designation.
[2:25:23] Higher densities are located to the north near the Caltering Station.
[2:25:27] Next slide.
[2:25:32] Then planning districts are established.
[2:25:34] Residential and mixed use development is located on the west side of the Plane area.
[2:25:38] And east side of the Plane area consists of lower intensity commercial, open space, habitat, and sustainability infrastructure.
[2:25:45] Next slide.
[2:25:50] Finally, the plan distributes the amount of permitted development across individual
[2:25:54] blocks within the planning districts. A development allocation process is established that
[2:25:59] allows those allocations to shift between blocks as long as the overall district level and plan
[2:26:05] level limits are maintained. Slide.
[2:26:11] Chapter 3 contains the plan's objective design standards
[2:26:14] and design guidelines. These standards and guidelines are organized into building standards,
[2:26:19] performance standards and allowable uses. There are project-wide building standards, which control
[2:26:24] characteristics of development, including building height and scale, towers, ground floor design,
[2:26:30] and public realm, and then there are building standards that are specific to a range of residential
[2:26:35] and commercial building types. Next slide.
[2:26:41] Performance standards, control lighting, bird-safe
[2:26:44] design, landscaping, noise, and vibration, and allowable uses establish what specific uses
[2:26:51] are permitted, conditional, or prohibited in each land use designation, as well as establishing
[2:26:57] active crown floor requirements.
[2:27:00] Now, note that uses not listed in Table 3.4.1 allowable uses are prohibited unless determined
[2:27:07] to be similar to a listed use through an administrative interpretation by the community development
[2:27:12] director.
[2:27:13] next slide.
[2:27:18] So as we discussed at the last meeting, chapter four establishes the requirement to dedicate
[2:27:23] 148.4 acres of land for recreational and habitat restoration, conservation and open space.
[2:27:31] This succeeds the general plan requirement that a minimum of 25% of the plans year 2,100 land area be preserved as open space.
[2:27:41] The approximately 26 acres expected to be inundated daily by 2,100 to see level rise are not counted towards that 25% requirement.
[2:27:52] Chapter 5 conservation and open space then establishes how that land creates a network of open spaces and amenities.
[2:28:02] Now that is accomplished by defining and locating a range of open space typologies across the plan area with conceptual programming and design guidance.
[2:28:11] Note that chapter 3 includes requirements for open area per unit, which may include private
[2:28:18] or common areas such as balconies, padios, courts, yards, usable setbacks, outdoor recreation
[2:28:24] area, and rooftop gardens or decks.
[2:28:27] And these open areas are separate from 148-acre public open space requirement.
[2:28:33] Next slide.
[2:28:38] Now the plan protects against the 100-year flood, including 100 years of projected sea level
[2:28:43] rise are merely through three strategies.
[2:28:47] First, by prohibiting development on 26 acres projected
[2:28:51] to experience daily in indation by the year 2,100.
[2:28:56] Area subjected increased title in indation due
[2:28:58] that proximity to visitation Creek and Prisfein Lagoon
[2:29:02] are proposed to be open space with gradients of title
[2:29:05] and freshwater wetlands that can adjust to sea level rise.
[2:29:09] Second, the plan is to grade and maintain minimum
[2:29:13] protection against flooding and sea level rise.
[2:29:17] Public infrastructure, as well as residential, commercial, and institutional development,
[2:29:22] are proposed that elevations above the 100-year flood, plus and allowance for more than
[2:29:27] six feet of sea level rise.
[2:29:30] And third, improve and manage ecological and hydrologic functionality of the plans that
[2:29:35] are through a network of public green spaces that's connected to the Brisbane, Lagoon,
[2:29:39] and the station creek.
[2:29:41] This network will be designed to capture stormwater, direct and treat seasonal run-off via multiple green infrastructure strategies, and establish Echo Hydrological landscape typologies appropriate to the region.
[2:29:54] Next slide.
[2:29:59] Now with the EI,
[2:30:00] Our use the state's most recent guidance to evaluate the plan. This guidance estimates that 6.5 feet of
[2:30:07] sea-level rise has less than a 1,000 chance of being exceeded by the year 2001. Relative to the 2018
[2:30:16] state guidance, the 2024 state guidance notes existing and ongoing efforts to analyze and plan for the
[2:30:23] impacts of sea-level rise should be able to proceed with little to no adjustments. There are likely
[2:30:29] very few if any situations in which work will need to be redone as a result of the new sea level
[2:30:34] scenarios. In the very unlikely scenario that sea level rise does exceed 6.5 feet by the year
[2:30:41] 2,100 or into the 22nd century. Potential adaptation measures that are being considered for lower
[2:30:48] lying Bay Area communities include shoreline flood protection barriers such as levees or float walls
[2:30:53] integrated with that nature based solutions. Next slide.
[2:31:00] Finally, the plan requires that the historic
[2:31:03] roundhouse be preserved and repurposed to serve as one of the main focal points on the west
[2:31:08] side of the baylands. That includes creation of a roundhouse park, implementation of a five-stage
[2:31:14] plan for restoration and adaptive reuse of the historic roundhouse and regulations in chapter three
[2:31:21] requiring all bail-ins development within 50 feet of the roundhouse or the machinery and equipment
[2:31:26] building to be designed to ensure their architectural compatibility with those historic structures.
[2:31:33] And with that, I'll pass it back to staff.
[2:31:38] Thanks Eric. Next slide.
[2:31:39] As you mentioned at the start of the meeting, staff is in asking the council to make a final recommendation
[2:31:44] or take any votes tonight. We're sharing staffs, one more slide please. We're sharing staffs
[2:31:49] overall recommendation again for context. This slide is the same when you saw in September
[2:31:54] 14th. Real briefly, it staff's recommendation is to certify the final environmental
[2:31:59] impact report for the Bay of Lines specific plan and improve the project entitlements,
[2:32:03] including the general plan and zoning ordinance amendments, adoption of the Bay of
[2:32:07] Lines specific plan and approval of the Bay of Lines. And if the project is approved,
[2:32:12] the council would also adopt the findings of fact and a statement of overriding considerations
[2:32:16] and a mitigation monitoring and reporting program.
[2:32:19] Next slide.
[2:32:21] Along with its final recommendation to the Council,
[2:32:23] the Planning Commission also endorsed additional modifications
[2:32:26] to the specific plan.
[2:32:28] This slide indicates the Commission's recommendations
[2:32:30] related to tonight's presentation,
[2:32:33] and topic for the Council to consider.
[2:32:35] So it's one is to change the biosephety level BSL threshold
[2:32:40] for conditionally permitted life science uses
[2:32:42] from bio safety level 4 and above to level 3 and above. The specific plant currently mirrors
[2:32:49] the existing zoning requirements in the city for BSL levels at zero point. To retain the
[2:32:55] mission blue nursery in its current location, the nursery is located at the southern end of the
[2:33:00] bay and ends within the ice house hill area and the plant proposes relocating it to a publicly
[2:33:04] accessible site on the south side of ice house hill, just a little north. And EIR mitigation
[2:33:10] requires that the nursery not be displaced and it's current site not be disturbed until the
[2:33:15] new site is fully ready for operations. Three, implement staffs recommended clarifications presented
[2:33:22] at the July 23 planning commission meeting. These clarifications affirm that hospitality uses
[2:33:27] and building types are permitted in the high and medium density commercial districts and that
[2:33:33] minimum residential density and commercial intensity standards apply on an average
[2:33:38] basis by land use designation rather than block by block, these changes improve administrative
[2:33:44] implementation of the plan. And for consider requiring conservation easements for open space
[2:33:49] has suggested by written correspondence received. While conservation easements provide
[2:33:54] permanent legal binding protection against development, the plan already prohibits development
[2:33:58] within any area designated as open space through its land use plan and permitted uses by
[2:34:04] new designation. The staff is available to provide more information regarding these topics specific
[2:34:09] commission recommendations. Next slide,
[2:34:14] and then one more or wrap it up here.
[2:34:19] Okay, we have one
[2:34:19] last reminder of the upcoming hearings, dates and topics. Again, transportation then is coming up
[2:34:26] on the six. Then we have phasing and remediation on the 15th, widened for structure on the 20th.
[2:34:31] Again, we're happy to adjust the schedule further if the council would like. Next slide.
[2:34:36] And we'll conclude staff's presentation.
[2:34:39] So at this time, the applicant is ready to address the council.
[2:34:42] Following BDI's presentation, the council may ask any questions
[2:34:45] about tonight's presentation.
[2:34:47] Staff will answer what we can now and note anything
[2:34:50] that requires more review for our future hearing.
[2:34:53] Once the council questions are completed,
[2:34:55] the council may open the floor for public comment
[2:34:57] on tonight's topics.
[2:34:58] Staff will again track questions from the public
[2:35:00] and respond at the end of the meeting or possible.
[2:35:03] And if we need more time, we'll come back
[2:35:04] at a future meeting. After public comment, staff is ready to receive clear counsel direction
[2:35:09] on the items discussed tonight. I'll give a quick summary. It's the kind of broader
[2:35:14] measure JJ topics and specific policy refinements. So it's going to be measure JJ in
[2:35:20] design topics, distribution, and intensity of those line uses that you saw from Eric,
[2:35:25] location of open spaces and amenities. The specific plans interface was sea level rise
[2:35:29] and related design topics on the objective design standards and design guidelines in the plan,
[2:35:35] and the treatment of the roundhouse. And then the kind of the topics from the plan commission,
[2:35:41] whether to require conditional use points for BSL level 3 and above, whether to retain the
[2:35:45] mission, blue nursery and its current location, whether to clarify that hospitality uses and building
[2:35:50] types are committed in medium and high density commercial, and whether to confirm the minimum
[2:35:56] Excuse me, and whether the council wishes to consider requiring conservation easements for designated open areas
[2:36:03] Finally, before concluding the meeting
[2:36:06] Staff recommends continuing the public hearing to a special meeting on October 6 at 530 p.m.
[2:36:13] Okay, I believed Apca has a presentation.
[2:36:20] We have a few slides
[2:36:32] Good evening, Mayor Mackin.
[2:36:35] To the council members, thank you for the opportunity to speak with you tonight. I am Katie Lowe Accende.
[2:36:40] I'm part of the team at the Baylands and I'm also joined tonight by B.K.A.F, who you've already heard from as well as O.J.B. landscape architects and our project designer, all of whom who have been with the project since shortly after, Measure J.J. or in James's case since I think 2006, so we have a wealth of knowledge here with us tonight.
[2:37:03] Forget to go to the next slide, please.
[2:37:11] One moment.
[2:37:13] No worries.
[2:37:15] As we're moving on to the next slide,
[2:37:18] I'd like to begin the presentation tonight by talking about the land use map
[2:37:22] and providing some details on the characteristics of each district.
[2:37:31] I'll explain them while we're getting the slides going and then you'll get a visual on a minute. So, starting at the north of the map, which I'm sure you will see, is the Bayshore district, and this is the northern gateway to the baylands.
[2:37:47] This district covers the area west of the Caltering Tracks in north of Geneva Avenue. This district is the most urban transit oriented area in the specific plan.
[2:37:57] it concentrates high density uses near the Bay Short Cal Transation, while lower density housing
[2:38:03] at the western edge. Thank you. Provides for transition to the surrounding neighborhoods.
[2:38:10] So again, we were just talking about that northwestern quadrant, and we called that the Bay Short
[2:38:15] District. So when we move south of Geneva in that area that you see is predominantly yellow,
[2:38:21] Um, that is the Roundhouse District. So as you heard, that district really frames the historic
[2:38:27] Roundhouse Park and it features a mix of single family, town home, and multi-family housing types.
[2:38:35] These two northwest districts, Bayshore and Roundhouse are the only districts in the Baylands that allow for residential uses.
[2:38:44] As we continue for their south, we go south of Main Street, you see those purple areas.
[2:38:49] That last district on the west side is the Ice House Hill district, and that area begins, as I said, South the Main Street, and it encompasses ecological park as well as Ice House Hill.
[2:39:00] And this district includes mid-rise and research buildings as well as retail and public gathering spaces.
[2:39:09] As we go across the Caltering onto the east side of the property, the campus east district provides for low density commercial office development
[2:39:18] and this district also provides trail connections to the Bay Trail and to the Visitation Creek Park.
[2:39:25] Also on the east side we have the Sustainability District, which provides the essential infrastructure and renewable energy that enable the Baylands to function as a climate resilient community.
[2:39:36] All of these districts are connected by an accessible award-winning open space system, which makes up more than 25% of the property, as is required by Measure J.
[2:39:47] Each of these open spaces are intended to preserve, enhance, and protect the ecological areas while balancing the needs of the community and protection of habitat resources.
[2:39:58] And throughout the project, there's also an extensive bike and pedestrian network that connects the surrounding areas to the Baylands so that everyone can enjoy these new spaces.
[2:40:08] And we will be talking more about that when we get to circulation.
[2:40:12] which I believe is next week, and then one last thing I want to point out on this slide before we move on.
[2:40:18] So this map that we have right here is actually the land use map that was the original version in BDI specific plan.
[2:40:27] So if you've seen the 2023, 2025 versions of the specific plan, they have this map.
[2:40:32] As you just heard, Brisbane City staff are recommending some modifications to this map,
[2:40:37] which would relocate some of the high-density uses
[2:40:41] and then reduce the density south of Geneva Avenue.
[2:40:44] But despite these proposed changes,
[2:40:46] the overall plan is the same framework
[2:40:48] that was established by Measure J.J.
[2:40:51] 2,200 units of housing, 6,5 million square feet of commercial space,
[2:40:55] 500,000 square feet of hotel,
[2:40:57] and more than 25% of the land dedicated to open space.
[2:41:02] Next slide, please.
[2:41:06] So just like every aspect of the specific plan,
[2:41:08] The Bayland's infrastructure is guided by the General Plan provisions established by Mr. J. J.
[2:41:14] One of those provisions is that the development shall be designed to detect uses from the
[2:41:20] hundred year flood, including 100 years of projected sea level rise. To develop a resilient site,
[2:41:26] the specific plan includes a combination of permanent sea level, sea level, rise designs,
[2:41:38] and
[2:41:38] measured sea level rise. Some of these measures include raising the elevation of the site so that
[2:41:45] the finished floors are protected from future sea level rise and flooding risks, construction
[2:41:50] of on-site storm drainage collection facilities and drainage improvements, some of which you can
[2:41:56] see in the graphic on the slide, establishing a new stormwater detention area and also planting
[2:42:02] The vegetated slopes that diminish wave force provide refuge to marsh wildlife and provide
[2:42:08] plant community migration space.
[2:42:11] These approaches are prepared buildings, roadways, and open space areas for both sea-level
[2:42:17] rise risks and associated flooding potential.
[2:42:21] Next slide, please.
[2:42:26] So Eric already covered some of this, but I'll talk a little bit about the design standards
[2:42:31] and the balans.
[2:42:32] So the Baileyens' specific plan includes multi-layered standards that create unique quality for each block,
[2:42:38] district and building, while allowing for flexibility and variations throughout the project.
[2:42:44] These standards set the allowable parameters for everything from building heights and facade design,
[2:42:49] to entryway elements and rooftop mechanical systems.
[2:42:53] Our design approach emphasizes neighborhood compatibility, while also recognizing,
[2:42:58] preserving and celebrating the unique aspects of this site. For example, the historic
[2:43:03] ground house that you also heard about. As you may be aware, the round house is a
[2:43:08] large brick building that was once used for the Southern Pacific Railroad to conduct
[2:43:14] daily maintenance on their trains. It is one of the few remaining roundhouses in the
[2:43:20] state and the specific plan includes the rehabilitation of that building to
[2:43:25] celebrate the legacy of the site.
[2:43:28] Roundhouse Park will be a unique multi-purpose feature
[2:43:31] of the valence and some of the proposed uses,
[2:43:33] which you can see on the slide here,
[2:43:36] or a flexible lawn, outdoor dining,
[2:43:39] an art and history garden, event pavilion,
[2:43:42] berm seating, and an open air theater
[2:43:44] that utilizes the cast iron columns
[2:43:46] and beams at the inner curved wall of the roundhouse.
[2:43:51] And that's all I have to cover,
[2:43:52] and I'll turn it over to Stephanie Shakovsky
[2:43:55] to finish our presentation. Thank you.
[2:44:02] Good evening, Mayor, council members.
[2:44:04] Once again, Stephanie Shukowski with the Bailons Project.
[2:44:09] As we've been talking about, we all know that this EIR
[2:44:14] and this specific plan is going to shape this project
[2:44:17] for generations.
[2:44:21] And so to deliver the housing, the parks,
[2:44:24] and the community benefits outlined in the plan,
[2:44:28] These documents must be economically viable and flexible enough to adapt to both market conditions and the realities of long-term operation.
[2:44:42] We have asked the council in a letter that we sent last week to consider three changes to the city's current proposed specific plan.
[2:44:52] them quickly run through those. First is that we ask the Council to remove the land dedication.
[2:45:00] The high-speed rail, light maintenance facility.
[2:45:04] As you know, the bail-ins has been opposed to this project from the beginning and we remain opposed to the LMF at the bail-ins.
[2:45:13] Setting aside 45 acres of potentially developmental area for a speculative future high-speed rail, light maintenance facility reduces our open space, negatively impacts our stormwater detention.
[2:45:28] And impedes the sustainable infrastructure projects on-site, particularly our battery storage project.
[2:45:36] It's also important to recognize that a high-speed rail like maintenance facility was never contemplated as part of Measure JJ.
[2:45:47] And so it's not an issue that the Brisbane community has voted on or weighed in on.
[2:45:52] We ask the council to align the bail-ins land use program with the general plan policy established by measure J.J.
[2:46:01] and plan these 45 acres for the bail-ins sustainability open space and our infrastructure.
[2:46:08] If the high-speed rail authority eventually decides to proceed, they can acquire the property through a negotiated purchase agreement
[2:46:17] or the typical imminent domain process.
[2:46:21] The city settlement with the high speed rail authority gives the council, this council, the final decision.
[2:46:28] It is the council's decision to adopt the Baylands Pacific plant without the LMF area and we would respectfully ask that you consider doing so.
[2:46:42] Second, we ask the council to allow interim uses that support the Baylands and makes way for the development.
[2:46:49] The City's 2026 specific plan revisions included new restrictions that ban intermuses on the property outside of the outside of the 45 acres of the LMF set aside and prevents existing intermuses from continuing once their permits expire.
[2:47:07] Interim uses create important really important revenue streams that help support our current
[2:47:13] environmental maintenance and environmental cleanup obligations.
[2:47:18] We understand the city's concerns related to compatibility of interm uses and permanent
[2:47:24] development as well as the concern related to interim uses that may hinder the future
[2:47:29] development.
[2:47:29] But the specific plan can easily address both those issues directly through enforceable operating requirements and enforceable termination provisions for those in term uses.
[2:47:44] Lastly, we ask the council to broaden the range of allowable commercial businesses that are currently under the allowable uses table in the specific plan.
[2:47:58] Back in 2023, when the specific plan was submitted and accepted by the city, it had and still has a heavy emphasis on biotech.
[2:48:09] While most market forecasters are predicting that first stabilization of biotech, and eventually a rebound of biotech, particularly in South San Francisco and the Brisbane market, no one can know today, which businesses will be looking for space at the Baylands.
[2:48:28] Allowing a broader range of compatible uses gives Brisbane more competitive opportunities to attract employers and fill the commercial space as demand changes.
[2:48:38] We have requested the council consider allowing the following advance manufacturing, warehousing for businesses to store goods.
[2:48:47] We are not talking about large fulfillment centers.
[2:48:50] And lastly, outdoor storage and select areas where low-density commercials are permitted.
[2:48:57] And that is the conclusion of my remarks tonight, and we are happy to answer any questions.
[2:49:03] Thank you.
[2:49:04] Okay, thank you.
[2:49:05] I think just based on that presentation, I'm going to start with the question for legal
[2:49:13] regarding the light maintenance facility.
[2:49:18] And the settlement reached by the city of Brisbane with high speed rail.
[2:49:24] Are we legally able to change the use of that property,
[2:49:30] or do we know, or do we need to investigate?
[2:49:32] No, we can be convinced that for you right now may or so, the settlement agreement obligated
[2:49:37] the city to analyze the light maintenance reality and the EIR to bring forward and staff
[2:49:45] is recommending that. However, the settlement agreement does not bind council in terms of what
[2:49:51] it's final the end use decision is. So the council has the discretion under the settlement
[2:49:57] agreement and under state law to adopt either alternative.
[2:50:03] Okay. Thank you. Council questions. Starting with Mayor Pro Tem Davis.
[2:50:13] This is for you,
[2:50:17] You mentioned interim uses that advance environmental cleanup.
[2:50:25] And I just would like for you to give some examples of what interim uses you're looking for.
[2:50:32] I think we've sent a list, but it would be, along the lines of the existing interim uses, we have so trans-dev
[2:50:43] Outdoor storage, as long as it's properly maintained,
[2:50:51] parking storage, we also have Avis as a tenant, as you know, it's a surplus overflow for Avis.
[2:50:57] That's not really, that is a really advanced environmental question.
[2:51:00] No, no, I'm sorry. The quote, when I say it's the revenue that's generated to us that allows us to pay our environmental guidance.
[2:51:09] So they're doing the current.
[2:51:11] Yeah, yeah, yeah, yeah, um, got it.
[2:51:15] Sorry if that was that was good.
[2:51:17] I think that's my only question for you.
[2:51:20] OK.
[2:51:20] See, you're good.
[2:51:25] So for commercial and other non-residential development,
[2:51:31] what architectural and design review authority
[2:51:33] will the city retain when proposals come forward?
[2:51:43] commercial and non-residential properties would have to get a design permit very similar to what's going on in the rest of the city of Brisbane.
[2:51:50] Okay.
[2:51:51] Both of the planning commission.
[2:51:54] And are the architectural standards in chapter three intended to be a complete and final set of architectural standards for the entire build-out of the balans or can the city supplement or a fine those standards as individual development areas move forward?
[2:52:18] They are intended to be all encompassing, but that is not to say that they cannot be amended over time.
[2:52:28] So I know with my experience was specific.
[2:52:30] Civic plans, that is one of the things that often triggers and amendment is new types of buildings appear that we're not foreseen and that would be the kind of thing you might want to change over time, but to answer the question it is meant to address all of the different building types that are proposed.
[2:52:49] I don't know if our design team wants to add anything more to that. That's a response.
[2:52:55] Okay, would the city have the authority to retain an independent architect, urban designer or other qualified design professional to assist with developing architectural standards and reviewing subsequent development proposals within those standards?
[2:53:15] a couple of things with that. Well, first of all, we do have a design consultant on board
[2:53:20] who has had that task exactly, so we have some individuals from site lab and they have been
[2:53:26] working on the cities behalf to refine the standards that were proposed in the plan. But then
[2:53:33] as a kind of policy or operations matter, the city can always consider the use of third party
[2:53:42] outside design consultants for any kind of design review. Particularly the commercial ones,
[2:53:49] there's a little more leeway, it's a little harder on housing developments. Those are more applicable
[2:53:54] to objective standards, but should the city want to have outside third-party design review for
[2:54:02] the Baylands and any other part of the city, that's always an option. Okay. I really want to make
[2:54:08] we can ask one question of yeah I thought we were working on the land use plan based upon the
[2:54:15] presentation that was just given in the topic and design topics were a later topic
[2:54:19] in tonight's session are we murdered all of these other. I thought of them in another section but
[2:54:24] then I had thought that you know the result was now. They're together yeah so okay thank you so much
[2:54:29] I just need to clarify our presentation thank you okay and then I think you know for me it's like
[2:54:38] I just want to make sure that this development looks amazing.
[2:54:43] And it feels like Brisbane and is something
[2:54:46] that we can be proud of and when we drive through it,
[2:54:50] which we will, we won't say, this is horrible.
[2:54:54] We want to be proud of what's there.
[2:54:57] And so I think that having some oversight over that
[2:55:05] is essential because we don't want to look like just anywhere else, right?
[2:55:12] We want to look like us.
[2:55:16] So getting back to the objective development standards,
[2:55:21] so the specific plan describes
[2:55:22] many of it's architectural provisions as objective development standards, but does that mean
[2:55:27] that the city can only enforce those specific standards that are written today, or can the city
[2:55:32] develop additional objective standards as subsequent phases of the
[2:55:36] valence are designed.
[2:55:42] Yeah, so the I think it's similar to what Kevin was
[2:55:47] explaining before the city can refine the standards it
[2:55:52] can adopt new standards. It would do that through an
[2:55:55] amendment to the specific plan as it's as it's shown
[2:55:58] right now. The specific plan does include the all
[2:56:02] encompassing design standards and then it would be a
[2:56:05] question about, you know, what that applies to,
[2:56:08] perspectively, if you do adopt amendments in the future,
[2:56:14] you would apply that to two projects that don't have
[2:56:17] vested rights, so it would apply to things that
[2:56:21] maybe hadn't applied yet or were still often the future.
[2:56:26] Because I know objective standards, that's really what's
[2:56:28] guiding the housing development, whereas for commercial,
[2:56:32] you have much more say in that because often cities make it so difficult for housing developers
[2:56:41] by having all of these guidelines that projects don't move forward and so I think that's
[2:56:48] the state is trying to curb some of that but I could envision us coming up with objective
[2:56:56] standards that may be create housing that's a little bit more refined and what we want
[2:57:03] to see and so just wanting to clarify if that's possible or if we need to work out
[2:57:09] all the kinks immediately.
[2:57:17] the next, the last question I have for this section, is there anything in the specific
[2:57:25] plan language already or is it something that we could add? As a condition that states that
[2:57:33] approval of the specific plan does not constitute final architectural approval of individual
[2:57:38] buildings and that the city will retain architectural and design review authority to the
[2:57:42] fullest extent permitted by the law. And I don't know if there's anything legally problematic about
[2:57:48] including that provision. I know that obviously you're saying that that's something that we can do
[2:57:54] But I'm wondering if it benefits the city to state that expressly, and if so, maybe you could bring back language.
[2:58:06] Sure, yes.
[2:58:07] The specific plan doesn't approve any individual development project.
[2:58:13] It functions more than zoning.
[2:58:16] It has many more details in it, but it's more like a zoning code than a conditional use permit,
[2:58:22] or a specific development approval, it does have provisions that talk about what subsequent
[2:58:29] approvals with that process is required for our project that wants to seek individual development
[2:58:35] and you can review that language to make sure that it's clear enough that council has the
[2:58:40] type of architectural discretion that you're looking for. I think it's just like clarifying and
[2:58:45] exerting as much architectural oversight and design oversight as we possibly can have is really what I'm
[2:58:55] hoping to achieve. So, that's it for me. Okay, at this time I'm going to ask council
[2:59:05] we must have a motion to extend the meeting if we were to do so. If you'd like a discussion first,
[2:59:13] Normally, we extend the meeting for an hour, sometimes we've done two hours and if we finish early, then we finish early.
[2:59:20] What is council's pleasure? I'm going to ask each one at a time. Council member Kern.
[2:59:25] Two hour extension.
[2:59:27] Mayor Proto.
[2:59:32] I would start with an hour.
[2:59:34] Council member Lens?
[2:59:38] I can only do one.
[2:59:41] I feel I only have an hour less than me.
[2:59:43] Okay.
[2:59:44] It's a sand.
[2:59:45] And Council member Kernel?
[2:59:48] I think that we should go for an hour and see where it takes us and see where the appetite of the audience is and if we start.
[3:00:00] They stopped to start to drop like flies, we'll know.
[3:00:04] Okay. So my weighing in on it is the complaint I got with the late meeting the last time, I would prefer we just extend an hour and see where we're at and see how everyone feels.
[3:00:16] I'll make a motion to extend until 930.
[3:00:19] Okay, second. All in favor?
[3:00:21] Aye. No one opposed. Okay.
[3:00:26] Council member, current question.
[3:00:29] Thank you, Mayor.
[3:00:32] I guess my first question is regarding the light maintenance facility.
[3:00:39] So in my mind, and I guess I'm directing this towards you, Eric, and maybe you, Kevin.
[3:00:44] In my mind, it looks like maybe we have three options here.
[3:00:47] One is to accept the final specific plan in its current state right now.
[3:00:53] reserving the land for high speed rail.
[3:00:57] Do we have an option to eliminate the reservation and adopt the plan and amend the plan later with some sort of additional reservation or change coding?
[3:01:15] I think the answer is going to be yes, but do you say it's say it back one more time so I can follow it?
[3:01:20] And so my thinking is that we would adopt the final specific plan with or without the reservation.
[3:01:30] And at some point in the future we could amend the plan when we have more information, or as council wishes.
[3:01:37] Yeah.
[3:01:38] So if you were to adopt the plan as recommended by staff with the area that would allow for
[3:01:47] company uses within the area that could develop for a future light rail maintenance facility.
[3:01:53] You could still amend the plan in the future to remove that put other designations in along
[3:01:59] the lines of put BDI is asking for or make other changes.
[3:02:03] And the flexibility to do either of those, either now or in connection with future amendments
[3:02:10] in part was granted under the EIR we have both of those alternatives have been studied that
[3:02:16] The project that was studied in the draft EIR includes the mix of Lyonducers that BDI is asking to include tonight.
[3:02:27] The staff recommended version was included as one of the alternatives in the final EIR.
[3:02:33] So we do have information about the environmental impacts from both alternatives and you could.
[3:02:40] So you have the flexibility to adopt them as part of this or in the future tiering off of that environmental work that was already done.
[3:02:51] Thank you.
[3:02:54] And one more option is it possible to adopt the final specific plan with the reservation for the rail yard with an explanation date.
[3:03:06] Meaning we're going to hold that zoning and that reservation for that space for 10 years
[3:03:12] If high speed rail does not come forward with an offer to buy the property and offer to do something with the property
[3:03:18] Then it would expire and we would have to revisit it
[3:03:21] Yeah, so you could stretch of that in in
[3:03:25] Two different ways you could have
[3:03:28] Allow for temporary uses for a period of time and then yeah
[3:03:33] there's a certain trigger hasn't been met
[3:03:35] allow for the development of permanent uses
[3:03:38] or you could
[3:03:39] set an expiration and a future council could revisit it in the future
[3:03:44] but you could build in that sort of structure now if you are interested in that.
[3:03:50] Thank you didn't mean to put you on the spot with all that.
[3:03:54] I do have a question. I'm going to assume that this question is for staff
[3:03:57] In this regarding the existing use, we've got a bunch of them, folks.
[3:04:04] If you've not seen the documents, everything from the Kinderborn take farm to the
[3:04:08] CalTrain Rails to Golden State Lumber.
[3:04:12] So we're going to be, quote unquote, moving dirt and changing the grading, but we're just
[3:04:16] going to go around all of these facilities, is that really, I mean, that's how we're going
[3:04:21] to plan to proceed.
[3:04:24] I've got an entire row of people nodding there.
[3:04:27] One of us are clicking this, yes, but yeah, that's correct.
[3:04:32] Thank you.
[3:04:33] And then last but not least, in the final specific plan, this is a 2.5, or 2.5.2 in the
[3:04:41] Brown House district.
[3:04:43] It says a potential middle school, great sixth grade is proposed in the vicinity of Main Street,
[3:04:47] and it's got a list of blocks here on the map, B6, B9, B10 and C2.
[3:04:51] Are these actually these blocks are these actually large enough for a middle school?
[3:05:05] We'll look at that a little more closely and get back to you. Thank you so much.
[3:05:10] Those are all my questions for now.
[3:05:14] Councilmember Liz.
[3:05:16] Madam, I have a lot of questions. So maybe councilmember McConnell and yourself should ask questions.
[3:05:21] Councilmember O'Connell.
[3:05:23] Sure.
[3:05:25] So if we were to remove the reservation for high speed rail, what will we lose in our negotiated
[3:05:36] settlement with high speed rail?
[3:05:40] So the settlement agreement obligates high speed rail to use the smaller facility, the 45
[3:05:49] of acres that are included in the specific plan,
[3:05:52] previously they had considered a significantly larger facility
[3:05:55] in a different location.
[3:05:57] So this should they go forward.
[3:06:00] The settlement agreement locks them into the location
[3:06:02] that's shown in the specific plan.
[3:06:06] There's also ongoing coordination and opportunity
[3:06:10] with for them to collaborate with the city on design
[3:06:15] and potential mitigation measures related to reducing visual impacts or undesirable impacts
[3:06:23] of the light, light, rail, maintenance facility should we not be under the settlement agreement
[3:06:29] and they just go forward and condemn the property in theory they would then design it the way
[3:06:36] they wanted without collaborating with the city on the design and there's also some consultant reimbursement
[3:06:44] costs that would be funded if the staff recommended version of the plan is adopted.
[3:06:55] Is there more to about like when they would be able to in this Edelman agreement about when
[3:07:04] they would actually be able to purchase it? And also if they purchased it and didn't use it for
[3:07:12] mean it's facility, like there's also stuff around use. So I believe in the settlement agreement,
[3:07:20] it's also that they could only use it for that. They could never, they could not acquire the property
[3:07:24] and then, oh, we don't have funding, we change now we're going to put something else there.
[3:07:30] So it was my understanding in the settlement agreement and you may need to get back to us on this, that we would have final design review.
[3:07:42] So it wouldn't just be a collaboration, we would have many, many tools in our toolbox to control noise, lights, uses, future uses, they couldn't just rent it out to CalTrain or use it to store their units and so it gave us a lot of concessions.
[3:08:13] which is sort of unheard of with negotiating with high speed rail.
[3:08:18] So it gave us a lot of power over what that facility looked like,
[3:08:25] sounded like to the residents, both at Brisbane and at the ridge
[3:08:30] and the new people that will be moving into that area.
[3:08:34] So, well, I would like to really hear what those upsides and downsides would mean to us and I think you can come back with those.
[3:08:52] And as Council member,
[3:08:56] current said, we could later upzone or we could allow temporary uses.
[3:09:03] But in the letter from BDI,
[3:09:06] they're very concerned that they wanted to use that for infrastructure and drainage for the entire site.
[3:09:13] And if that is the case,
[3:09:15] And the LMF did come in to use to eminent domain.
[3:09:22] There would be no place for the drainage and for the infrastructure.
[3:09:27] So I think if we gave up that settlement agreement,
[3:09:30] we could put ourselves in that whole project in jeopardy.
[3:09:36] So that's one comment there or question that you can get back to us on.
[3:09:47] And then the interim uses that their request for to allow interim uses that support the property and make way for development.
[3:09:57] You know, their opening statement is that the bail-ance will be developed in phases over many decades, many decades.
[3:10:05] And so,
[3:10:09] do we really want to, is this asking to keep the use of crushing gravel?
[3:10:21] Is this, you know, uses that we really want to see?
[3:10:25] And I somehow missed the memo of the list of what uses they want to add.
[3:10:33] I didn't get that or notice it, but,
[3:10:44] and I goes along with the question that they wanted
[3:10:47] to bring, broaden the range of permitted commercial businesses.
[3:10:50] And I do think that no one knows what is going to be useful, but I do think that bringing
[3:10:57] in more light industrial type businesses might be appropriate in the specific plan because
[3:11:05] there's a it's what's kept our crocker park. So vibrant is that we have a lot of mixed
[3:11:13] smaller uses instead of just giant life sciences. So I'd be interested to see if there was
[3:11:21] some mix that the city could bring in to the specific plan that would allow some of those smaller
[3:11:28] or uses in the permitted use in the industrial areas.
[3:11:38] I second that interest.
[3:11:45] That's it.
[3:11:47] You want me to go ahead.
[3:11:49] I'm going to be very short.
[3:11:53] I have a question and I don't know where it lies or if it belongs in this topic tonight.
[3:11:58] But I found it interesting reading about pile driving and pile driving being inherent
[3:12:04] to certain type of structures and tonight we've talked about the existing specific plant being proposed
[3:12:11] some of those buildings 22 stories high and councilmember lenses alternative where he was
[3:12:19] talking about much shorter buildings and I read about a mitigation measure m m n o i one it talks
[3:12:28] about an alternative method to pile driving
[3:12:31] where geological conditions permit.
[3:12:35] And so there's two questions in there.
[3:12:38] At what point does the height of a building
[3:12:41] require pile driving on this particular site,
[3:12:46] knowing that it used to be the bay, water,
[3:12:49] and it's all filled on regulated fill.
[3:12:51] Yes, it's had decades to compact,
[3:12:54] but I'm not a geologist
[3:12:57] and I'm not a building engineer.
[3:13:00] So first of all, what threshold is
[3:13:05] piled driving necessary, height of the building?
[3:13:07] And also, what is this reference to where geologic conditions
[3:13:11] permit that there could be an alternate method to piled driving?
[3:13:27] If you have to get back to you, we'll
[3:13:30] want to consult with the engineers and get back to you on that.
[3:13:34] Okay, and in that question is,
[3:13:39] where geologic conditions permit, I would like to then know also, is it the whole site, or is it only certain areas and if it's only certain areas, if we could please identify which areas those are, thank you.
[3:13:55] Tell us a member of Lens.
[3:13:58] Thank you, Madam Mayor.
[3:14:01] You know, I was going to mention this early.
[3:14:03] I mean, later, but since you've brought up the pile driving, I'll just start right now.
[3:14:09] Because in Alternative 7, it has some interesting information that I'd like to read.
[3:14:17] It says that Lomeran-the-Hight's guitar buildings, while simultaneously reducing the...
[3:14:25] Specific plants that have guitars.
[3:14:28] Overall development intensity could reduce
[3:14:30] the number of buildings that would require
[3:14:32] pile foundations.
[3:14:34] The combination of reduced building
[3:14:36] highest and development intensity could enhance
[3:14:38] the feasibility of constructing pile
[3:14:41] foundations using quieter technologies
[3:14:43] which reduce the amount of pile driving required for
[3:14:46] the balance development.
[3:14:50] It goes on to say that it would also
[3:14:53] reduce the severity of the specific plans, significant, unavoidable impact if you're filled.
[3:15:00] Things would require powder driving. So just putting that out there for the record.
[3:15:08] I'm trying to get rid of this little book. Stick it right there.
[3:15:13] And this one over. So yeah, so my questions are going to be related to chapter 2 of the land use.
[3:15:22] So Katie, thank you so much for the presentation, Stephanie.
[3:15:26] So, Katie, in your last slide that you showed, you know, there was a picture of the round
[3:15:33] house and I looked like some of the taller towers in the background.
[3:15:39] So I had office hours on Sunday, and the number one thing that people asked about were
[3:15:45] renderings.
[3:15:46] So, you know, in this chapter, it talks about the low density residential on the density
[3:15:53] in high and then same thing with commercial. And I have to agree with them. I don't know what
[3:15:59] that looks like. You know, to be quite honest with you. I mean, obviously, you all don't know
[3:16:04] what it's going to look like either. There's going to be these project applications that
[3:16:09] you know, that will come before us. But you'll based upon what is in the specific plan and how
[3:16:16] you lay out the different districts, it would be so helpful if you could use AI. And
[3:16:23] and just put it in there, and then do a presentation for the council and for the public.
[3:16:30] So that we get an idea of, okay, what does a 24 story tower, a couple of towers, look
[3:16:38] like with the other residential, how does the single family homes where the round house
[3:16:46] is, how does that really look like?
[3:16:50] So just putting that out there, and if you could bring that back, you know, for a future
[3:16:56] hearing, that would be so beneficial.
[3:17:00] All right.
[3:17:03] So, kind of piggyback on what you had said,
[3:17:09] mere pretend Davis, you know, and regards to design standards for residential.
[3:17:16] yeah, you know, difficult. However, with the roundhouse area, within that 50-foot area,
[3:17:27] there's the curved residential, there's the brick clad, right? There's trying to, you know,
[3:17:33] that tied to the historic building. So I'm sure it's why only 50-t, why not, you know, maybe
[3:17:39] expanded a little bit more. So if you want to come on up and talking about that, sure. I can speak to a little bit. So I think the 50 feet that you're mentioning comes from the mitigation measure. So I do want to note that that came from the city team. So site lab may be able to speak a little bit more about why they chose 50 feet as a radius. And while I'm up here, I did also want to mention the
[3:18:07] staff did add some helpful sort of inspiration photos to chapter two and three if you look at
[3:18:13] on in chapter three under each housing product type. So single family, you know, multi-family,
[3:18:22] mid, multi-family, high, et cetera. They do have some inspiration photos that might be helpful,
[3:18:26] but I do take your point that we can... Yeah, I think we can do better. Maybe if there was kind of
[3:18:33] Like a drone footage, you know, some of the really, you know, like gives you a feel, you know, as council member Davis had said, I mean, she, you know, we'd like to see this, this site be beautiful, you know, and we do attractive, absolutely everyone does, so, but being able to see it, would, would be extremely helpful.
[3:18:57] I appreciate that feedback and I'll let the team answer your other question.
[3:19:01] Okay, great. Thank you.
[3:19:03] So that, yeah, it's the 50 foot.
[3:19:09] We have our historical consultant online, who's going to help answer that?
[3:19:13] Kathy's.
[3:19:16] Hi, this is Kathy Cleveland.
[3:19:17] I'm a senior architectural historian with Environmental Science Associates.
[3:19:20] And I worked on the built environment analysis for the EIR.
[3:19:26] The 50 foot buffer specifically was regarding the historical significance of the roundhouse
[3:19:33] facility in order to minimize the visual impact of new construction in the immediate vicinity
[3:19:41] of the building itself. So the height restrictions, the materials, the brick requirements, and
[3:19:49] the curvilinear mapping, all kind of speak to that issue. So that's why the 50 foot buffer. We
[3:19:55] to encourage consideration of the resource, the roundhouse, as a historical resource. So.
[3:20:04] That's why. Oh, okay. So could that, I mean, is 50 feet the minimum? I mean,
[3:20:11] could it be 100 feet? I'm just kind of curious about why it's 50 feet.
[3:20:16] It was the idea of the immediate visual impact. Just the immediate, okay. All right. And then
[3:20:25] You know, also kind of piggybacking on what Councilmember Davis said about having buildings
[3:20:34] look inviting and kind of playing on the theme of building thriving neighborhoods, engaging.
[3:20:43] So, did you ever consult, say, with the Urban Lands Institute or American, this is your
[3:20:50] architects, you know, that were their, you know, helping developers, helping cities to implement those things.
[3:21:00] I see you nine or eight, like,
[3:21:03] okay.
[3:21:04] So, I mean, how about you guys?
[3:21:06] Did you?
[3:21:08] I mean, I know you, you know, your specialized in doing that.
[3:21:11] But, you know, it's always good to get other opinions, you know,
[3:21:15] And the city has also utilized UI and AIA for various parts of Brisbane.
[3:21:24] I know I'm members of both, and I think I really don't want to go.
[3:21:29] Yeah, likewise.
[3:21:33] Good question.
[3:21:34] Council member.
[3:21:36] I would say, you know, a lot of our role in this project was shifting the design guidelines
[3:21:46] at the time into objective design standards and so we and watching out for feasibility challenges
[3:21:54] associated with development. We did not add meaningful significant number of design standards on
[3:22:01] top of the components that already existed in the plan from 2025 unless they directly address
[3:22:06] mitigation measures from the EIR. If we were to go down a path of doing more what you're
[3:22:12] which is, there's two sort of paths that we've taken on this. One is looking at precedent
[3:22:19] and we've done design standards and guidelines documents up and down the peninsula.
[3:22:25] And the other would, and our preferred approach would be to engage the community in what is
[3:22:30] Authentically, Brisbane, and bring that character in. That was not within the time constraints of sort of where we were to get from the 2025 applicant specific plan to this specific plan.
[3:22:43] So, we to the extent we could, we added the layers, well, we directly added the layers associated with mitigation measures, but we stopped short of trying to add additional layers to support the feasibility of the project and flexibility there.
[3:23:00] Okay, thank you for just being a friend and and to straightforward. I appreciate that
[3:23:08] You know, I'm being under the gun so to speak, right to to move this thing forward
[3:23:15] I think that would be a shame if that
[3:23:18] Was to cause us not to have that kind of engagement and create those types of guidelines
[3:23:26] So I
[3:23:27] would like for staff in an all-store with the developer to think of a way given our schedule
[3:23:36] that maybe we could have that public engagement. If that is something that the council
[3:23:42] would be okay with as long as it doesn't disrupt our current schedule.
[3:23:47] I'm not sure you're asking for to have another hearing or engagement about what the buildings
[3:23:56] are going to look like so that, but we don't even have someone who's going to build them
[3:24:02] yet.
[3:24:03] Wouldn't that be up to the developer, the actual builder to come in with those that information
[3:24:12] rather than trying to be prescriptive at this point in a specific blame?
[3:24:17] Well, you know, I'm not an expert, but what I'm sorry, your name sir, my name is Woody
[3:24:25] and some from site lab urban studio.
[3:24:28] Well, Woody, Woody, Woody, oh sorry,
[3:24:31] geez, man, it's apologize for Woody.
[3:24:33] But what he said, to me, that made a lot of sense.
[3:24:37] And that would be, I think, a real benefit for the community
[3:24:40] and for us is a council to put forth,
[3:24:45] I think, some buildings that look really beautiful.
[3:24:47] So Woody, what I would clarify is you can always go
[3:24:55] further on objective design standards, right?
[3:24:58] But that runs up against feasibility
[3:25:02] that nature of feasibility and flexibility
[3:25:04] of a project and how descriptive something looks.
[3:25:07] So what I was suggesting for is not to come forward
[3:25:10] with specific architecture,
[3:25:11] but if there were components of the plan
[3:25:14] that feel underrepresented in terms of the level of definition
[3:25:18] you want to see in characteristics
[3:25:20] that are defining of Brisbane, those would be elements
[3:25:24] that you could add as objective design standards,
[3:25:26] but then future architecture would have to adhere to.
[3:25:30] Okay, thank you for clarifying, Katie.
[3:25:33] Yeah, I may.
[3:25:35] Thank you.
[3:25:35] It's a great topic, because obviously we all want the bail-ins
[3:25:39] to feel like it's part of Brisbane
[3:25:40] and we don't want it to feel like it's this separate thing.
[3:25:43] You know, we want it to feel cohesive
[3:25:46] and to reflect the community's values.
[3:25:48] And that's why this land use plan really was built
[3:25:52] around a long series of community workshops and input that happened when it was first put
[3:25:57] together. And then, of course, at the time, we also did work with leading architecture firms
[3:26:01] to put it together. We were, you know, we engaged with ULI for a long time. And then I do
[3:26:07] have Allison Harvey from OJB on who can speak a little bit about the Open Space Network
[3:26:14] that they recently received an award on. And so I think I bring all this up to illustrate
[3:26:20] that we are trying to be at the forefront of good design
[3:26:26] and making sure that this is a program that is practical
[3:26:29] and beautiful but also realizing that the specific plan
[3:26:33] has to be able to adapt to changing conditions over time.
[3:26:37] We don't want to say all these houses have to be blue
[3:26:39] and then 10 years from now everyone says I hate blue houses.
[3:26:44] So that's a simple example, but we really need to have
[3:26:48] adaptability in the specific plan, and so I think that's why we have a good mix
[3:26:53] right now of these design standards that kind of put the shell and the
[3:26:56] parameters in place, but then allow for some growth in dynamic changes over time
[3:27:03] as the community and in others give us input. Yeah yeah and I hear what you're saying
[3:27:08] and I agree. You know having those renderings I think would be really helpful. You
[3:27:15] being able to apply, say, soon, ULI additional objective standards. I mean, obviously ULI's, you
[3:27:23] know, top of the line, they're not going to say, yeah, all the houses we can be blue. Yeah, right? They're
[3:27:29] going to provide objective design standards that provide the flexibility and also have great design.
[3:27:37] Yeah. Yeah. Would it be okay for Alice and to speak about, oh, yeah, I guess we're bored. I think she,
[3:28:05] I may for just a moment, when you talk about setting up a design standard, you know, you can tell when a house was built in the 60s, 70s, 80s, 90s, 2000s, 2010s and 2020s.
[3:28:20] Is that what we want to design to when this is going to take decades?
[3:28:24] Now, what it is is applying objective standards that create flexibility, so, you know, the thing about buildings, you know when a building has been designed well, and it could have, it could have been designed in the 1930s or in 1950s, and it might not look for you all, very good, but you could have a building that was designed in the 1970s or just a few years ago.
[3:28:52] But if it, you know, quality is, it never goes out of style. And so you have someone like ULI,
[3:29:01] you know, providing those objective standards, you're going to have the very best. So,
[3:29:07] is your colleague, online,
[3:29:11] Alison?
[3:29:16] Alison, go ahead.
[3:29:25] We can come back to Alison as you'd like.
[3:29:34] Hello everybody, I'm Allison Harvey, I'm a landscape architect with OJB Studios.
[3:29:41] We have been involved with the specific plan since 2019 and one of the things that I'm
[3:29:50] extremely proud of is actually the specific plan received an ASLA San Diego.
[3:30:00] A SLA Green Ribbon Award for its advancement in sustainability and sensitivity to environmental needs, specifically looking at the American society of landscape architects, schools in their climate action plan.
[3:30:17] And this just happened a couple months ago, and, you know, another thing is that I'm very proud to be a part of OJD, which has received four ULI awards for designing urban open space.
[3:30:32] So it has been a goal within this document to ensure that the flexibility that we need as designers is there,
[3:30:43] But that there is a strong framework to the design that's going to yield those values within that I think you're talking about, you know, body by the ULI, which is about, you know, what makes great public space, what makes great communities.
[3:31:00] And each open space that we documented really strives to create unique opportunities within
[3:31:10] Brisbane that celebrates the character of the region.
[3:31:19] Thank you, Allison. I appreciate that.
[3:31:23] All right.
[3:31:26] Council member Kern mentioned the middle school and the size.
[3:31:32] So,
[3:31:35] the valiance is in the Bay Thore school district, as not in the Brisbane school district, a couple
[3:31:42] of months ago, some parents started a petition, and I'm just curious, have you seen the
[3:31:50] petition and Stephanie? You have seen it. Okay, all right, and I just printed it out yesterday,
[3:31:57] It's got 284 signatures and the title of the petition says one school district for all
[3:32:05] Brisbane students. I'm going to read a passage in it. It says,
[3:32:13] our local schools are a vital pillar of our community. When the Northeast Ridge was built,
[3:32:19] the Brisbane school district served as the bridge,
[3:32:22] lighting new and long-time residents as new neighborhoods arise in the bayonel and how will we connect with these future citizens so yeah
[3:32:33] So I mean, do you feel that that schools are vital to community and so that's the first question and then
[3:32:42] That connection so if you went mine coming to the podium, please and Madison if you want to add any
[3:32:48] questions
[3:32:50] Yes
[3:32:56] Thank you for that.
[3:33:00] So, of course, obviously, school is important to community and we recognize that and we're
[3:33:04] where the petition and we want the balans to reflect the interests of the community, ultimately
[3:33:10] what school district the balans is is more complex question that we can't answer alone.
[3:33:16] That's going to require engagement with the community with both school districts,
[3:33:21] probably with the Department of Education.
[3:33:22] And so we're not, we don't see ourselves as the final decision maker on that.
[3:33:27] As part of the specific plan, we responded to a city of Brisbane commission study that said a middle school would most likely be necessary.
[3:33:37] And so we set aside some potential parcels for a middle school.
[3:33:41] However, again, we are really just here to be reflective of the community's needs.
[3:33:47] You know, we're not the ones who are going to define what school should go there, but we're happy to participate in any conversations about that.
[3:33:57] All right.
[3:33:58] How smart it is.
[3:34:00] But don't you don't you do have a role to play?
[3:34:04] I mean, as the property owner and that the property is vacant, right?
[3:34:10] It's my understanding that properties of this nature.
[3:34:12] you could as a property owner petition the county to redraw the district
[3:34:18] lines and that would be something that would come from you it would
[3:34:22] come from us. So I do think that there is a little bit of a stronger role
[3:34:28] that you could play in determining the elementary school district that's
[3:34:32] served by the balance. Yeah I'm vaguely familiar with that process. It's not
[3:34:38] something that we have a lot of deep expertise on,
[3:34:42] but I know what you're referencing about a landowner
[3:34:44] being able to put forward a request to change the school district.
[3:34:49] Again, I don't mean to say that we wouldn't be involved.
[3:34:52] We're happy to have these conversations with the community,
[3:34:55] to have these conversations with the district,
[3:34:57] but it's my understanding that even if we were to put forward
[3:35:01] that request that it still would need to be approved
[3:35:04] by the appropriate districts
[3:35:06] and potentially the county, maybe even the state or of education, I don't know the exact details of that.
[3:35:12] So again, we, I'm not saying we are not involved, we are happy to be involved.
[3:35:16] I think we just are not the main, we're not the folks who are guiding the direction that that's going,
[3:35:24] that really should come from the community and the parents in Brisbane and the school district.
[3:35:29] So it needs to be a more collaborative discussion, but we are happy to take an active role in that discussion.
[3:35:36] I'm asking you how many other questions I have, I have a couple more, but I'll, if I
[3:35:39] was going to, I'll let you. Okay, and then I'll chime in. All right, all right, so getting back
[3:35:47] to the, the petition, there, it says here, when the VLans was annexed into the city of Brisbane
[3:35:53] in 1963, so the city became a city in 1961. It's school district boundaries were never updated
[3:36:00] to match, leaving the land in the baseball school district, and back in the day, Brisbane
[3:36:05] and baseball were one school district, the visitation school district, back in the
[3:36:09] therase they split up, and then it goes on to say rather than accepting outdated boundaries
[3:36:15] that risk dividing us, we shouldn't brace a one-bris-bain vision. It just makes common sense
[3:36:22] for a small city to keep all of its elementary students together, and I hope I don't
[3:36:31] So, then it goes on to say, you know, for people to sign the petition and then to urge the
[3:36:36] Brisbane School District, the Brisbane City Council and the Baylands development eat to
[3:36:43] collaborate on the necessary steps to unite all Brisbane students under one school district.
[3:36:49] So,
[3:36:51] I have this flow charter, it's from a study that you guys funded, it was maybe in 2019.
[3:36:59] I mean, it gets to Councilmember Davis's point, I just got this flow chart, and it talks
[3:37:05] about how if there's property that's uninhabited, that is the property owner, they're
[3:37:12] the ones to do the petition, and then set it into the county superintendent, goes before a
[3:37:20] committee, and then that committee decides who's going to vote.
[3:37:23] So don't wait for this really to start but be from you guys and I just curious to know if
[3:37:30] That's something that you are considering doing. I'm just asking a question.
[3:37:45] I will have to take another look at the flow chart because I'm not intimate with you.
[3:37:50] But yeah, I think, as I mentioned, we want to be open to any kind of conversation around whatever school might come to fruition at the bail-ins.
[3:38:00] Again, we aren't in a position where we should be moving unilaterally, I think we need to take into consideration all the different community stakeholders and make sure that everyone has an appropriate voice in this, but we're happy to continue this conversation further.
[3:38:18] So to me, I mean, it seems like next steps are outside of a council meeting, but probably
[3:38:23] based on this conversation, I mean, when you were up at the podium last time, you said
[3:38:31] that the momentum really needs to come from the community, and I feel that the petition
[3:38:38] is exactly that, it characterizes the momentum in the community and the whole point of that
[3:38:46] is to inspire action from the city's leaders and also those who have the ability to affect
[3:38:55] this issue.
[3:38:56] So I feel like the momentum is already there, the parents are already there, the conversations
[3:39:01] are already happening.
[3:39:02] So that doesn't need to be validated.
[3:39:05] The petition has done that.
[3:39:07] That petition has more signatures than I think any petition we've ever received as council
[3:39:12] members in the 11 years that I've served.
[3:39:15] And so I think at this point if you are serious about kind of exploring the conversation what would be the next step would be to have some kind of meeting and that would bring to the table maybe a couple of members of the Bayshore school district
[3:39:39] couple members of the Brisbane school district potentially a couple members of the city council could be the
[3:39:51] two-by-a members of the two-by-two, but it seems like it seems like it's time to plan something.
[3:40:00] Yeah, and I don't want to get too far off of, you know, we're approaching 9.30, but I think
[3:40:07] based on the petition and your willingness to explore further, I think we should just plan a meeting.
[3:40:19] Absolutely. Yeah, I, and there's a lot of folks here have been waiting to speak, so I don't want to stand in their way too much longer,
[3:40:25] but I think that this is a really important topic and I do think it's one that warrants probably having some discussion outside of this forum,
[3:40:33] And making sure that the appropriate stakeholders are there from both school districts and from this community and you know, to make sure that it's a comprehensive conversation, but we're happy to engage with that and I can talk to staff about the most appropriate way to go about setting that up.
[3:40:53] Yeah, okay, Bayland's Boulevard, right?
[3:40:59] So that's the shopping street,
[3:41:04] but it has,
[3:41:05] as far as I could tell, it doesn't have any residential.
[3:41:09] So, you know, past renderings that I had seen,
[3:41:14] you know, past specific plans.
[3:41:18] There was a, like a neighborhood downtown,
[3:41:21] You know, something somewhere to, you know, maybe no way valleys, a little neighborhood downtown
[3:41:28] or a union street or something like that.
[3:41:32] Is that something that you had contemplated, but didn't, you know, decide to implement?
[3:42:01] I don't know if staff has a map handy of the specific plan, but I can sort of talk through it.
[3:42:07] But there is both residential and retail along Balan's Boulevard.
[3:42:13] So there is a graphic also in the specific plan that outlines the areas where ground floor,
[3:42:19] active ground floor uses are permitted, and where active ground floor uses are required.
[3:42:26] And so there is some overlap between these things, right, between where there's commercial,
[3:42:30] there's retail, and then there's residential, and then there's these opportunities for active
[3:42:35] ground floor. And so that is my understanding is sort of all mixed within the different uses
[3:42:43] that border, balan's bullet bar.
[3:42:45] Oh, okay, so you're saying that there is retail activity commercial space down below and
[3:42:50] then residential above. Because I didn't see it, but maybe I missed it in my bad.
[3:42:58] Hi, hi, hi council member. So yeah, so here's the perfect link you've mapped. So if you're
[3:43:04] look at the balance blue barring and zoom in a little bit. On the right-hand side is side,
[3:43:09] those are all commercial uses and on the left-hand side of balance is all residential.
[3:43:14] So the retail is essentially underneath all the commercial uses and then the on the left-hand
[3:43:21] size is residential. So it's basically a true mixed use.
[3:43:25] Okay, so residential is on one side of the street. That's correct. That's correct. That's correct.
[3:43:35] I'm just going to ask you, I mean, obviously, you know, we have this line, right?
[3:43:41] It's in Measure JJ, says that the line is Main Street.
[3:43:48] I'm just curious I'm just going to ask you a question, and if that line was a little bit
[3:43:51] farther south, would you create more of a true mixed use where you'd have commercial on
[3:43:57] the bottom and residential on time, or would you just design it to select this?
[3:44:01] So, in the, actually, the original proposed land use, we had asked for the residential use to allow some ground floor retail activities.
[3:44:20] So,
[3:44:22] I believe, we, so that was trying to structure, you know, there's a little bit more kind of like entrepreneurship
[3:44:31] of the residents that can be a business owner themselves, so that was actually in our
[3:44:39] original proposal. But we don't have a true mix, residential,
[3:44:48] and on top of a commercial,
[3:44:50] what we do have is for all those residential mid-rise buildings, we do have a retail on the ground
[3:44:59] the way.
[3:45:00] That's basically facing over the public, like bail and street and the plaza.
[3:45:05] Okay. All right. You know, as an item for us to discuss, I would like to discuss, perhaps, you know,
[3:45:14] allowing some residential below Main Street to explore.
[3:45:22] Let's see. Can we do that because JJ defined a cleared boundary?
[3:45:26] You know, what I'm looking at is, you know, not as potentially a significant, but perhaps
[3:45:34] a minor movement.
[3:45:39] You know, obviously there's a lot of things in measure JJ that we're trying to work through.
[3:45:46] And so it's just something for the council to consider and have staff come back with some information.
[3:45:55] If we were to deviate from measure JJ, would we have to go back to the voters?
[3:46:02] I didn't think these are questions, right?
[3:46:03] You know, I mean, I think, you know, let's have that discussion.
[3:46:10] So, I'll just remember once.
[3:46:11] Yeah. Oh, okay.
[3:46:12] I don't understand what your question was. What is the ask?
[3:46:15] The ask is to evaluate the potential of having some residential below the Main Street line.
[3:46:25] Thank you.
[3:46:25] But before staff doesn't I mean can we do that like if does that have to go back to the voters because that would not be an alignment with what JJ says right now am I right you're you're correct that that's not
[3:46:41] Let me see if I can find the exact words from from JJ
[3:46:47] Well he does that this is kind of circling back, but there is a figure in the specific plan and we did show it on our slides
[3:46:55] but I kind of went by pretty quickly, but it does show where ground floor active ground floor,
[3:47:04] which would be, for example, of retail stores, is required, and then there's another
[3:47:09] section, so you've got kind of the solid line where these uses are required on the ground floor,
[3:47:15] and then there's a dotted line in many more blocks that show where they can be allowed,
[3:47:20] they're not required. But there are three four block faces on Baleans Boulevard at the
[3:47:31] north end that would require that ground floor sets to solidline and then there's another
[3:47:37] section just south of Main Street that would also require that. Okay.
[3:47:49] Yeah, I'll I'll I'll
[3:47:52] Well, I'm not going to figure it out tonight, but I would like to perhaps maybe offline
[3:48:01] and just talk a little bit more about what is the actual, like, letter of the law.
[3:48:07] Sure, yeah.
[3:48:08] So residential uses shall be permitted only in the northwest quadrant of the site, bounded by
[3:48:14] Bay Shore Boulevard on the west, the city and county of San Francisco on the north, the
[3:48:19] train rail line on the east and the line of Main Street extended on the south has shown
[3:48:25] on the general plan land use diagram.
[3:48:27] All right.
[3:48:28] So what you're saying then is if there was to be a change, it would have to go back
[3:48:32] before there's any change of residential.
[3:48:36] Yeah.
[3:48:37] That that language because it's residential uses shall be permitted only does look like
[3:48:42] that sort of.
[3:48:43] Because it's a shell.
[3:48:44] Yeah, Amanda, clear, fundamental mandatory policy where literal compliance would likely be required.
[3:48:52] I don't know, okay.
[3:48:54] All right.
[3:48:55] It comes.
[3:48:56] Yeah.
[3:48:56] If I may.
[3:48:58] The figure that Kevin was pointing to is a helpful one and it actually slightly different than the one that was in the applicant presentation.
[3:49:06] and that's to say that the solid red line requiring retail on the ground floor includes both
[3:49:17] commercial and residential buildings in that zone so it is a mixed use area. If that helps.
[3:49:24] Yeah, I know that.
[3:49:27] I know that.
[3:49:27] Thank you.
[3:49:29] Appreciate it.
[3:49:31] Yeah, you know, I'm just really, you know, as we're in this final stage, just really thinking
[3:49:36] out loud, what's the best way to create the most dynamic urban planning, right?
[3:49:46] And so giving ourselves flexibility, I know that we made that decision back in 2018,
[3:49:51] is that really something that is appropriate for today. And perhaps that's a discussion that we can have later on in the process.
[3:50:04] So that's really, I guess maybe my ask is just to bring it back so the council has a discussion about it then.
[3:50:12] Let's see.
[3:50:12] Oh, okay. Mission blue nursery, but I had to plan a commission said yeah, we should keep it
[3:50:21] I know that you guys are talking about putting it in the shooting range. Um,
[3:50:32] yeah, just um,
[3:50:35] and I know that I already owe this here as well. I hope we can keep it in that place.
[3:50:45] Okay, Judo, the Ice House Hill, so I know it's in the sustainability framework and it talks about having an urban farm in that North area.
[3:51:04] And there's the agreement that you have with the folks that have the horses.
[3:51:08] Is that something that you, yeah, thought about, perhaps, retaining, you know, some kind
[3:51:15] of rural connection that Brisbane, you know, kind of has that's, you know, that you
[3:51:19] can't find in other parts of this area.
[3:51:22] Everything's just all been built up.
[3:51:24] One of the great things about living in Brisbane is that we've kept our roots.
[3:51:28] So that's something that you thought about.
[3:51:30] I see you nodding your head.
[3:51:32] The current plan does contemplate the stables saying, and I believe the horses can still
[3:51:43] grace on the Ice House Hill, and that's actually discussed in the EIR.
[3:51:50] Okay, all right,
[3:51:54] good, done, done, oh yeah, so we've got a letter from buildup in regards
[3:52:03] to child care facilities.
[3:52:08] And, you know, it's talked about in the sustainability framework,
[3:52:12] you know, as one of those uses that you should just have. And so, and I was curious to
[3:52:19] know that, you know, it's stated that it's a, you know, it's a allowed use. But there's
[3:52:28] like talk about so I'm this
[3:52:30] Sure is why that wasn't why you didn't put that in the risk. Yeah, we're going to do this.
[3:52:43] I mean child care is an allowed use. And I think all the residential and most of the commercial, if not all, the commercial areas.
[3:52:51] So almost in most areas, the property, child care is an allowed use. So there's no issue with the child care operating on the property.
[3:52:59] Okay, so, you know, from their letter, they add, you know, something for us to consider, you know,
[3:53:10] and they state in the specific plan and section 2.2, integrate child care as a central community infrastructure.
[3:53:18] Plan for licensed child care and early learning facilities as an integral component of the balance.
[3:53:24] with the facilities, conveniently,
[3:53:27] located in relation to residential neighborhoods,
[3:53:30] and employment centers, and plan and phase
[3:53:32] and coordination with development and occupancy.
[3:53:35] I see nine-year-head, okay.
[3:53:37] I mean, I would like for us to have that as an item
[3:53:40] for us to consider implementing
[3:53:43] into the specific plan when we talk.
[3:53:46] I support that.
[3:53:48] Okay, cool.
[3:53:52] We do.
[3:53:56] Playgrounds, or are they not playing on the ball field?
[3:53:58] All right, so the current ball field is, you know, you had a home run, you hit the tank farm, you get an extra price.
[3:54:05] So,
[3:54:09] I'm just kind of curious why the ball field's weren't next to the school, which just seems like an obvious place to put a ball field.
[3:54:16] You know, you want residential.
[3:54:19] You know, so the, you know, the folks that are living there, they can walk and play baseball or play soccer.
[3:54:26] But that site is isolated, so I'm just kind of curious why that location and would you consider placing it in the residential neighborhoods?
[3:54:40] So a lot of the locations of the different uses on the land use plan were informed by some workshops that the team conducted with OJB and some of our other consultants in 2019.
[3:54:51] And there was a real desire from the community to have the ball fields close to central Brisbane.
[3:54:57] And a unique feature of that property where the community fields is contemplated is that there will be a trail that connects through the Old Bay Short tunnel
[3:55:06] and connects up with the current Crocker recreational trail.
[3:55:11] And so that also gives kids an opportunity to cross underneath Bay Short for a little bit of a quieter route to get to the ball fields and it's closer.
[3:55:20] to town. So that was the history of the hotel that came about.
[3:55:24] That's good to know. All right. Okay.
[3:55:29] And I have the last question, Madam Mayor.
[3:55:32] And it's in regards to a civil rise.
[3:55:36] So, thank you for sponsoring the study for the Lagoon being one of those
[3:55:45] funders. So, the mayor and I sit on the sustainability,
[3:55:52] I mean, I mean, the sea level rise.
[3:55:55] Sorry, committee. And, you know, we recently received an update regarding the lagoon study.
[3:56:04] And I'm just kind of curious, like, you guys are the vast majority owner of the lagoon, correct?
[3:56:11] All right. So, of the lagoon.
[3:56:14] So,
[3:56:17] you know, during the last King Tide, the Lagoon, you know, it might have broke its banks.
[3:56:24] You know, it was pretty close.
[3:56:25] It was lapping up against Sierra Point Parkway Road or Boulevard.
[3:56:34] One of the options to mitigate that is doing a title gate.
[3:56:39] And yeah, so I'm just curious, you know, like, you know, this property, during, you know, these, these
[3:56:52] kintaisin is, is, sea level rise, expand the lagoon is going to just spread out, right?
[3:57:00] Unless we do something, right, it's going to impact other properties.
[3:57:03] So I'm just curious, like, what you've been thinking about in regards to how to keep your properties in the lagoon
[3:57:11] from spilling over into other properties nearby.
[3:57:21] I might ask if Alice and is still on, although it's, she's in a different time, so that's quite late.
[3:57:28] But we'll see if she raises her hand. There are a number of sea level rise, sea level rise related measures planned for the lagoon, and especially for the lagoon park.
[3:57:40] I think in terms of this tight gate you're talking about, obviously, we sat on some of those planning committee meetings.
[3:57:48] I think that's something that would probably have to be studied further to understand what makes the most sense in conjunction with the mitigations that we are implementing and how those would come together.
[3:58:02] So, I don't know if Alice has any love here.
[3:58:06] You can hear me? Okay.
[3:58:08] So I think, like, when you look at the specific plan again, you can look at the, there's
[3:58:16] some elevation or sections through the Bay Trail.
[3:58:20] I think that those exemplify the challenge here and that is that it's not really a title
[3:58:28] gate to you.
[3:58:29] It's a, like, highway 101 is really low, and so there's a larger infrastructural challenge.
[3:58:36] to controlling that edge of the bay. Does that make sense?
[3:58:43] Yeah, no, all those factors plan to it. The consultants who are doing this study have presented several options for us to evaluate.
[3:58:56] It seemed like the title gate was maybe...
[3:59:02] Well, it's I guess I should say it peaked my interest and seemed to be economical as well as being able to
[3:59:12] not
[3:59:13] Really impact infrastructure and and
[3:59:17] Be used when the tide is high and then when the tide's go down
[3:59:22] The gate goes up and and we're fine. So
[3:59:27] I do think I am not, I don't represent the ecologist point of view on this, but there are sensitive month-slats that align the edge of the lagoon, so I would say before deciding on anything that we would really want to make sure that those are preserved to the greatest possible extent that we can and that a type gate would not impact that.
[3:59:56] What's so ever?
[4:00:00] All right, thank you. We also, from the ESA team, we have Dr. Matt Brennan, who was also involved with the EIR and looking at sea level rise, so he might be able to add some additional technical information for this question as well.
[4:00:17] Sure, good evening, Council members. My name is Matt Brennan. I'm a coastal engineer and I've worked on
[4:00:23] sealed rise adaptation projects along the base shoreline as well as helping with drafts in the EIR and also the
[4:00:29] sealed rise technical report for the study. In my mind, I would think that these are somewhat independent
[4:00:37] the north shore of the lagoon that's mostly within the specific plan area. Actually is relatively high and has a pretty
[4:00:45] good adaptation approach in terms of it's basically on the north shore of the lagoon because
[4:00:52] of the space there and because of the proposed setback for the road there, you can basically
[4:00:58] create a horizontal levy there if you've heard that terminology. So it's actually a good
[4:01:02] setting along the specific plan site to create this sort of gradually gently sloping 50 to
[4:01:09] and slope that can gently allow wetland habitats to move up slope. You don't
[4:01:16] almost call it like a managed retreat there for missing the name of the roadway right
[4:01:22] now, but some lagoon road. Right, so lagoon road will actually be set back by two or
[4:01:27] three hundred feet under the plan area that will allow for this very nice green
[4:01:35] So, the specific planary on the North Shore is actually better situated than most of the
[4:01:40] Lagrange shoreline to be able to adapt to sea of ORIs in this way that has a much more
[4:01:46] nature-based transgressive space.
[4:01:50] Under the other report that I believe are referring to a couple of memorands, which is the
[4:01:56] S-SAP program and Shaffin Wheeler's adaptation plan for the Lagoon, that addresses the
[4:02:02] to, you know, I think the lagoon is a triangle. The other two shorelines. So I think there may be
[4:02:09] other decisions that you make for the other two shorelines of the lagoon, but in terms of the
[4:02:16] southern part of the plan area, which has been northern part of the lagoon, it's actually fairly
[4:02:21] well accommodated to adjusting to see a little rise without a tidy.
[4:02:26] Madam Mayor, if you don't mind, I think I may be confused about the structure of this meeting.
[4:02:32] Last time we had a meeting, we did measure JJ compliance public comment, then we did
[4:02:45] energy use public comment, then we didn't make it to GHG air quality, so you rolled
[4:02:53] that topic over, we started with that public comment, then I thought we are doing land use
[4:03:01] and design guidelines, public comment.
[4:03:04] And then open spaces and amenities, public comment,
[4:03:07] seal of a rise, public comment.
[4:03:09] So are we asking all of our questions right now,
[4:03:12] because I have questions about open space and amenities,
[4:03:15] and I have questions about seal of a rise,
[4:03:17] but I thought that I'm withholding those questions
[4:03:20] until we get.
[4:03:20] So I just don't know, like,
[4:03:24] because we're at 930.
[4:03:26] So I almost feel like going forward,
[4:03:29] and I don't know if this is appropriate, really,
[4:03:30] to suggest, because it really is a departure
[4:03:32] from our process, but I see so many people in the room here and I'm also cognizant of the
[4:03:37] amount of time that the council is taken in this meeting and in the meeting last time for
[4:03:42] our questions and to the point that a lot of people didn't get to ask their questions and
[4:03:47] had to come today and still wait like an hour and a half minimum to get to the question that they
[4:03:52] were here for a while. So I'm going to wonder if next time we should just start with the public's
[4:03:58] And then ask our comments, start with the public's questions and the public's comments.
[4:04:04] And then we ask our questions because we really were taking a significant amount of time,
[4:04:08] which is part of the process and it is part of our job.
[4:04:12] But I'm seeing all these people in the room.
[4:04:14] I know Ariel is here for open space.
[4:04:18] And we haven't even, I don't think we've even gotten to that.
[4:04:22] So just trying to think of how we can better utilize our time.
[4:04:26] And if I'm understanding the structure of this meeting right.
[4:04:30] We're following the same structure that we normally would do, which is a staff report, council
[4:04:36] questions, and then the public.
[4:04:38] And that's just simply how we've been doing it.
[4:04:41] I'm not saying it has to be that way.
[4:04:43] That's so should we right now be asking questions about open space and amenities and also
[4:04:48] see low rise because last time we took it topic by topic, each topic, we asked questions,
[4:04:54] And then the public came like Michelle commented like three, four times right and Paul commented several times because we took it just
[4:05:04] With their this tonight has multiple topics within the subject matter, so we did it
[4:05:11] Toppip by topic, and I just I was assuming we were doing it like that and I don't know
[4:05:17] So your question is this is the way it was set up on the agenda
[4:05:20] So it's the whole ball of wax
[4:05:23] Okay. So if I may, I would make a motion to extend the meeting by half an hour, but that we go straight into public comments if the council members could wrap up their comments and then we could hear from the public who's here so that we get their point of view.
[4:05:43] But with that, make a motion to extend half an hour. And are you including then continuing council questions to the next meeting?
[4:05:51] I think we're not going to continue the meeting, yes, yes.
[4:05:56] Okay, and I'll second, I'm sorry.
[4:05:58] And I was just going to say, and instead of going right to the public,
[4:06:01] I had one comment on what you were saying about the lagoon,
[4:06:05] but I didn't get a chance.
[4:06:06] Sorry, sorry.
[4:06:08] So, I make a motion to extend the meeting for half an hour, second.
[4:06:15] All in favor?
[4:06:16] Hi.
[4:06:16] Okay.
[4:06:17] So, the meeting will be extended till 10, 30, I'm sorry, 10 o'clock.
[4:06:24] A question for Mr. Brennan,
[4:06:29] in the sea level, I subcommittee in the meetings that we've
[4:06:33] had, and what you characterized on the North Shore of the Lagoon, we were actually told
[4:06:39] that there was a problem at the intersection, right near our bridge, and that is the North
[4:06:46] part of the shore and that potentially that could affect the caltrane tracks and it wouldn't
[4:06:52] affect the lagoon road being moved further north on the east side of lagoon road but on the
[4:06:59] west side that it would and they were very concerned about that. So it's more of a comment that
[4:07:04] maybe it would be a good idea to consult with all the consultants that are working on that project
[4:07:12] and one shoreline. Because we did go over that about railroad tracks and the roadway where
[4:07:20] everything intersects in that little corner and that they had identified it as a problem area.
[4:07:30] We also have those existing use areas that I mentioned earlier, and that includes recology. And that includes Golden State Lumber, Kinderborn and Take Farm. They are not being raised up. They will also be low areas that are subject to flooding once everything is graded and raised. So I just want to add that in before Matt potentially dives into the question there. Thank you.
[4:07:52] And one other thing that I was going to say is that one of the other comments that was made in the meeting we had about that was that it's not just that it's a part of a lagoon, but that's where there's a lot of runoff, especially in storms, it comes down that hill, naturally feeds into the lagoon part of it there and that that's why that area might be subject to flooding.
[4:08:16] So, sure, I had happy to comment on those.
[4:08:19] I have not reviewed the in detail the area outside the plan area, though I am familiar with
[4:08:23] chef and lillare and their work to a certain degree, but we're absolutely good.
[4:08:27] I think you may be talking about where tunnel, having you cross this railroad tracks, and that small drainage
[4:08:31] creek becomes out there.
[4:08:33] I think that actually is technically outside of the plan area, so I haven't looked at that in detail.
[4:08:37] And that would, in my mind, be sort of in that western side of the, you know, if you can go with doing shoreline is just a triangle, but obviously the western side needs to meet the northern side at that northwest corner.
[4:08:51] And often the sea will rise.
[4:08:53] I totally agree that well it may meet the conditions on one parcel you have to obviously work with the grades that go from one parcel to the joining parcel.
[4:09:02] So, both those things can be true.
[4:09:05] Let's see the other one that was brought up with, sorry, was the Kinder Morgan, I know Kinder Morgan came up as a specific question in some of the comments on the EIR that I responded to and we looked at the relation there, the Kinder Morgan parcel is not quite as high as what is proposed for the rest of the balance, but it's pretty close.
[4:09:25] So, while it may not be resilient for quite as much civil rise as the specific plans for
[4:09:31] post-grading, it was fairly close, say, you know, up to five feet of civil rise and sort
[4:09:36] of was just starting to infringe on the edges.
[4:09:39] I don't know the particulars about Golden Gate Lumber, but like I said, Kinder Morgan was
[4:09:44] a comment that was brought up for the EIR that we could look at in detail.
[4:09:50] One of the last ones is for the other drainage part is, there's that small creek that comes
[4:09:55] under tunnel avenue which is just south of the specific plan area but there is also a
[4:09:59] visitation creek which is part of the drainage from the hillside and there is concern about
[4:10:06] drainage and flooding along like base where Boulevard and like the Levinson detention basin right
[4:10:12] where like there's that sort of corner of base where Boulevard. That area under the specific plan we
[4:10:17] protected because there would be to your point about like you know the opportunity for using a
[4:10:23] This specific plan proposes adding a tide gate to visitation creek for the areas on the eastern side of the parcels, so the same idea of having a tide gate that doesn't allow tides to propagate upstream would occur that tide gate would be just on the eastern side of the both stormwater detention basin.
[4:10:45] And just to revisit back to the question about the LMF, the LMF would reduce the size of the tension basin that was proposed originally in the older specific plan.
[4:10:57] And so that's where some of that benefit of having that tension basin and the tide gate that would, you know, sort of be on the east side and allow that tension basin to not get in the tide would be reduced.
[4:11:10] It could be addressed, and as an alternate that has been discussed with their vice-plans,
[4:11:16] by having some other ways of conveying what are sort of a dealing with that reduced conveyance,
[4:11:22] reduced storage volume that would be there for the honor.
[4:11:28] Okay.
[4:11:28] Thank you very much.
[4:11:32] All right.
[4:11:34] I'm going to read the names that we've got on slips, so that you know the order.
[4:11:40] We first will have Melissa Foley followed by Paul the Scale, Anthony Walker,
[4:11:49] Alice Seperman,
[4:11:52] Claire Johnson, Karen Cunningham,
[4:11:57] Michelle.
[4:11:59] I can't read Alamon,
[4:12:04] Ariel, Linda Salman, Roland, Ileen McLaughlin.
[4:12:19] That's the one I can't read.
[4:12:23] Okay, yes, that's you.
[4:12:26] Alman, it's salmon.
[4:12:28] All right, Melissa Foley.
[4:12:36] Good evening.
[4:12:37] Mayor Council members.
[4:12:38] My name is Melissa Foley and I'm a science director at the San Francisco Estuary Institute
[4:12:42] or SFI where research and nonprofit that provides science to managers and communities
[4:12:47] to revitalize nature and our communities in the Bay area.
[4:12:51] SFEI reviewed and provided independent ecological planning and design recommendations to BDI to incorporate into the updated bail and specific plan that you're considering this evening.
[4:13:02] The recommendations we provided align the best available science on native plants wildlife safe design and connectivity with feedback from local environmental organizations.
[4:13:12] The bailins will be the first of its kind development in the Bay Area that intentionally brings together people and nature at this scale by employing a range of nature-based solutions to provide multiple benefits ranging from access to nature to heat mitigation to biodiversity that will support healthy and resilient outcomes for people and wildlife.
[4:13:34] As long as the bail-ins is planned, designed, implemented, and maintained, with these multiple benefits in mind,
[4:13:42] the bail-ins conserved as an example to cities throughout the Bay Area of how communities and nature can thrive together.
[4:13:50] I wanted to highlight three examples from the specific plan that stand out for the region.
[4:13:55] First, the commitment to a high proportion of native plants throughout the project area,
[4:13:59] and 100 percent native in the habitat restoration enhancement and other sensitive areas is
[4:14:05] commendable. A diverse assemblage of native vegetation will support local wildlife,
[4:14:11] expand populations of locally adapted plants, and reduce maintenance needs,
[4:14:15] particularly the need for irrigation once plants are established.
[4:14:20] Second, by recognizing the importance of the balans for supporting local and regional habitat
[4:14:25] connectivity wildlife movement and habitat access to green space.
[4:14:30] He's our human access to green space.
[4:14:32] This specific plan takes a landscape scale view that is needed in the Bay area to make our urban
[4:14:37] areas healthier for people in wildlife and more resilient to climate change.
[4:14:43] Third, the wildlife safe design features included in the specific plan, particularly for lighting
[4:14:48] and building design ensure that the developed areas introduces few hazards as possible for wildlife
[4:14:54] while ensuring residents' safety.
[4:14:57] I know there will be challenges along the way of impl...
[4:15:00] Niting this project and trade off some on all of the ambitious goals. A functioning ecosystem is at the heart of thriving communities, so I encourage the city of Brisbane to lean in and make this an example of urban planning and development that is looked to throughout the region. Thank you.
[4:15:17] Thank you, Melissa. Public scale.
[4:15:25] Total scale of Brisbane resident. So as far as sea level rise, adaptability,
[4:15:33] visitation Creek seems to be, would seem to have the most impact on the development.
[4:15:42] So I thought that would be possibly to close off the outlet to the bay, and on the railroad
[4:15:54] side, which was not unregulated they had filled, run a pipeline from this station creaked
[4:16:03] to the Lagoon, along the backside of the corp yard, and not have the channel with the
[4:16:13] leechate in the unregulated landfill. That's an issue. And then that could be just filled
[4:16:20] that channel. Because unlike the Lagoon, which was stated to have habitat in the mud flats,
[4:16:33] that channel east of Tunnel, well it does support habitat. It's not mud flats and it's
[4:16:50] the channel and ran that water to the lagoon. So that was one thing I thought we could do.
[4:16:58] The other thing that I thought we could do, and I mentioned it before, is move the housing out of
[4:17:04] the billions.
[4:17:08] I like the idea of the smaller units, and maybe live work was mentioned like
[4:17:13] people that own businesses, not necessarily families, for a lot of reasons I'd like to
[4:17:21] see the development, because there aren't elements yet, and Cliff, you mentioned that
[4:17:27] you get in close to wrap up this up. You'd like to get this movement. I don't think we're
[4:17:34] close at all. You should have an entertainment center, or some real big draw in the Baylorians
[4:17:42] to take advantage of the public transportation
[4:17:45] that's inadequate for housing.
[4:17:50] You know, the housing transit oriented doesn't work.
[4:17:54] It's not frequent enough.
[4:17:56] So I think we should move the housing
[4:18:00] to 11th and property and set money aside
[4:18:05] through the HCP because it's any HCP
[4:18:08] for the fragile habitat on the upper slopes.
[4:18:11] the lower slopes are impacted by Eucloptes trees.
[4:18:17] It's right near infrastructure,
[4:18:20] stream water, sewer, talking about water.
[4:18:24] If we just took the housing out of the baylands,
[4:18:27] maybe not all of it, but the family style homes,
[4:18:32] not homes, but probably high rises,
[4:18:37] give the developer a density transfer,
[4:18:40] like we did in the acres. We gave people their own property makers an opportunity to build twice
[4:18:46] the density down here because we wanted to save the habitat. I think building homes in the
[4:18:54] bail hands with the issue with local faction even if they go down to you know high rises of course
[4:19:02] you're going to go to the bedrock they have to they didn't have the marina all those buildings are
[4:19:07] piled ribbon in the bedrock, the same 40 feet of mud, so let's take this opportunity
[4:19:17] and make something really special. I mean, you mentioned having something special, let's
[4:19:24] get these houses built in our school district. We don't need to be working with the school
[4:19:29] district, it does want to work with our school districts.
[4:19:34] So we have a pedestrian bridge going
[4:19:36] over from those high rises into the Baylands, eventually, but we need to build houses now, right?
[4:19:45] And maybe they could help us do it.
[4:19:47] Thank you.
[4:19:50] Anthony Walker, is he still here?
[4:19:55] No.
[4:19:56] Okay.
[4:19:57] Alley?
[4:20:14] Good evening, Mayor and Council members.
[4:20:16] I'm Alley.
[4:20:16] See, I prevent with housing action coalition.
[4:20:18] We urge the Council to certify the final EIR and adopt a bail-in-specific plan that is
[4:20:23] feasible, flexible, and able to deliver thousands of homes, including affordable homes
[4:20:28] this region urgently needs.
[4:20:30] We already committed to the bail-ins as a majority of the site inventory in the housing
[4:20:34] element.
[4:20:35] The city could have chosen to build housing elsewhere, but instead you all committed to the
[4:20:40] bail-ins.
[4:20:41] Due to significant delays on the bail-ins plans, on June 30, HDD revoked its finding that
[4:20:47] that Brisbane's housing element complies with the law.
[4:20:50] Brisbane is now exposed to the Builders' remedy,
[4:20:52] laws of state funding, court and post penalties,
[4:20:55] and referral to the Attorney General.
[4:20:57] There's a clear, simple path back to compliance,
[4:21:00] adopt the Bayland's specific plan and zoning.
[4:21:03] The Bayland's will take decades to build out,
[4:21:05] so the win-use plan must be flexible,
[4:21:07] enough to adapt over time while still delivering housing and community benefits.
[4:21:11] We recognize this is a complicated project,
[4:21:14] and the city has put substantial effort into getting here,
[4:21:16] But these hearings are already behind schedule and after 20 years of analysis and public input, it's time to move forward.
[4:21:23] Brisbane, our region and the state cannot afford further delays. Thank you.
[4:21:28] Okay, thank you.
[4:21:30] Clara Johnson.
[4:21:33] Clara still here. No longer no.
[4:21:36] Karen, Connie, no. Michelle.
[4:21:45] I am still here.
[4:21:47] Still alive. It's been so long. I forgot what I was going to say. No, what I really want to say is I think that the draft EIR is still incomplete.
[4:21:57] And one of the areas of grade is concerned for me is the lead deposition along Old Bay Shore and along the 101.
[4:22:06] and that has not been studied. It is not in the draft EIR, which I read. We've had
[4:22:13] Leigh Gasoline vehicles going there from 1925 till 1992. That's a lot of led
[4:22:20] deposition that hasn't been studied and also pollution from tires, etc. And that's where
[4:22:27] you're planning to put a school and that's everything.
[4:22:30] Really, really bad idea, unless we figure that out. So that's really been on my mind a lot.
[4:22:38] I'm a yes for conservation easements. I'm a yes for lower heights of the buildings. I think 12 stories is just plenty.
[4:22:48] design. The day-conbuilding built its year point, part of its year point, was an award-winning
[4:22:55] design. It was a building beyond belief when they first built it. And yet, over time, it
[4:23:02] was bought by somebody else and remodeled into something that is really not very spectacular.
[4:23:07] I just want to remind people of that. And there are many more things that came up during
[4:23:12] this, but I'm going to be brief, the only one thing I want to make sure I do is,
[4:23:16] And by the way, everybody to come Monday night here in this room for the Brisbane Baylands Community Action Group meeting where representatives from the Department of Toxic Substance Control and the Regional Water Quality Control Board will be here to answer questions about remediation and I think it is very, very important for the community to attend.
[4:23:44] So you really do learn more about what lies beneath.
[4:23:49] Thank you.
[4:23:51] Thank you, Michelle, Ariel, Ariel,
[4:23:58] Ariel.
[4:24:04] Good evening, Mayor and members of the City Council.
[4:24:07] Thank you very much for that opportunity to talk and thank you for the pointy me to the right comment period.
[4:24:13] I did not want to talk about greenhouse gases, but I do want to talk about a greenhouse.
[4:24:18] I'm here with San Benomat watch, but also here representing Mission Bluner Street.
[4:24:23] As you know, the nursery has been on the Bayland since 2009.
[4:24:27] We really appreciate the support of the Bayland's development company.
[4:24:30] That's given us that property to use for those many years.
[4:24:34] And we think of the nursery as the example of the screening of the Bayland.
[4:24:40] It's the place that was at peace of empty bay fill in over these past years with the support of the community has been transformed into a really beautiful community gathering place into a place that's grown hundreds of thousands of native plants restoration on on San Brito Mountain.
[4:24:58] It's also a place that is noted in the Beren's Plan,
[4:25:02] connects the mountain with the bay.
[4:25:05] We see e-gits at our nursery garden.
[4:25:08] We see to saw some scrubjays on Monday and our oak trees.
[4:25:11] We have painted ladies and green heres streaks
[4:25:13] and in these small tails and more butterflies that use our nursery.
[4:25:18] And so the values are nursery and bodies using
[4:25:21] and growing locally native plants and connecting the mountain with the community.
[4:25:25] our values that we see represented in the Brisbane open space plan.
[4:25:31] In the open space plan and the Balaens specific plan,
[4:25:36] we appreciate that the Balaens specific plan requires the use of native plants
[4:25:41] in the restoration locally, certainly,
[4:25:43] to plants in the restoration of open spaces like Ice House Hill,
[4:25:49] really loved being part of the first Ice House Hill,
[4:25:51] how would our restoration event in partnership with the city of Brisbane last December?
[4:25:55] And we'd love to see more events like that happen in the near future and long-term.
[4:26:00] There are still not just ice-haves here in the Butterfly Habitat there,
[4:26:04] but also the visitation creek and the Marsh Habitat and Upline Habitat around the Brisbane Lagoon.
[4:26:12] We think that the nursery can be a key part of future restoration around the Dalans properties,
[4:26:18] growing plants for these areas and also for the urban portions and community parks.
[4:26:24] And so we really want to thank the Planning Commission and City staff for the recommendation that the nursery
[4:26:31] stay in this current location. That's where we think it would best operate and we think it could also
[4:26:37] fit well as a side of recreation where students and team members could be going to exercise and could also be coming to volunteer
[4:26:46] as well as another form of outdoor recreation. And so to conclude, we just want to say we appreciate
[4:26:54] these portions of the open space plans that are in the
[4:26:59] balanced specific plan. And we support the passing of a
[4:27:03] balance plan that keeps the nurse screen and
[4:27:05] its current location and includes this sensitive
[4:27:08] restoration to happen. So thank you very much. And if I
[4:27:11] could just take a few seconds on a separate note to think
[4:27:14] the council also for course sponsoring the meet meet meet
[4:27:18] the mountain fair that happened this past Saturday. It was a
[4:27:20] really beautiful event and the city staff that supported
[4:27:23] day and day I say it to Africaardo and everyone else. We just want to say thank you. So thank
[4:27:29] you very much. Thank you. Linda Salmon.
[4:27:43] Hi. I hope we have time after all this is done when
[4:27:47] we have public comment again because having the middle of it is kind of crazy at least for me.
[4:27:54] I'm not opposed to having dwelling units on the Bayland. When we did the 1994 general plan
[4:28:02] we gave plenty of FARs so that some high rises, I don't know about 20 stories, but could be built
[4:28:12] with dwelling units, like apartments, that could be either bought or rented to working people
[4:28:18] on top of it so that they weren't on toxic soil directly. And I still think that that's the best solution
[4:28:26] for housing on the baylands and rather than putting actual people on the toxic stuff, it's just not safe.
[4:28:43] And instead, we got from, I don't know, ton text, sequest, whatever you're calling yourself now.
[4:28:50] We have this incredible architect that came here to Brisbane.
[4:28:53] Some of you may remember, you were around.
[4:28:55] And with this wonderful building that everybody in the town was so happy about saying yes
[4:29:00] We're gonna have this it was it was beautiful and do you remember that Terry?
[4:29:05] I don't know if you were here, but anyway, so and then it got taken away just like just like that
[4:29:13] What have we we hit agreed for what we had put in the in the 30s so a lot years ago so when you're complaining to about 20 years
[4:29:22] verses 30 years. I mean we've been doing this for a long time. It's definitely time to come
[4:29:30] to some kind of a plan that is also flexible that will allow dwelling units. I call them dwelling
[4:29:38] units not houses because houses implies that they're on the land and they can have a garden and
[4:29:44] do all kinds of other things that houses do. And this is not safe for this area. Sequo is about
[4:29:51] Safety is not about not building it's about safety and this is why we're not building on our own mountain because our soil
[4:30:00] Wacky is subject to landslides in a big way, as we discovered a few years back, a couple years ago, on the
[4:30:08] other, another can in the next to us. And this is why we said no more, no more, this is why we started
[4:30:14] the program of building up land, taking land with this wouldn't happen. And we have the same problem
[4:30:20] here. We do have a lagoon, and the lagoon gets fed in part by mountain, by suffering from
[4:30:28] mountain that comes down, says freshwater and salt water. And there is a problem with the overpass
[4:30:34] that I think it was Walt Peters, who when he was part of our city, identified and that has never
[4:30:43] been fixed and it has to be done. So we have, we do have issues that we have to do before we can do
[4:30:50] other kinds of buildings and figure and things out. So in some sense we're not there yet and in
[4:30:57] For instance, we could be there.
[4:30:59] We don't have an adequate EIR that still doesn't look at the racetrack on the glue factory
[4:31:04] and other stuff that happened on the baylands.
[4:31:08] We need to remedy that before we can actually do authorize the journal plan.
[4:31:14] And if there's some way that the in the authorizations are permits that we give can be made
[4:31:19] for this owner only, and if they sell off the property as a whole, as I think they're
[4:31:25] to do, then they have to start all over again. I'm sorry. But we don't want another situation
[4:31:31] that we had on the North East Ridge. Thank you.
[4:31:37] Thank you. Roland is Roland still online.
[4:31:41] City court?
[4:31:45] Yeah, I've already seen Silly here in Sory, I didn't be in a clock.
[4:31:51] I'm going to be very quick. So Kapal advances, I'm out of Maya with regards to the question about
[4:31:57] Silent Piling. The answer is called Geekunpal, G-I-K-E-N. First came across them in 2008 and
[4:32:09] most recently, they were used by the boring company in Las Vegas for the people move
[4:32:15] for the Convention Center. Now, moving on to the last item is my proposal to basically
[4:32:24] in completely eliminate the HMF in Brisbane and relocated to Auckland and I'm pleased to inform
[4:32:33] you that first of all this has been rejected in the IR as an alternative that I'm going to
[4:32:41] explain to you why that's not necessarily right. The state rail plan was modified in 2018 to
[4:32:50] modified the Salesforce Transit Center from the Terminers, which is what has been real
[4:32:55] a lot, still thinks it is to a true station, and it was reaffirm in 2024 in the 2024
[4:33:04] California state rail plan. Thank you and goodnight.
[4:33:09] All right, thank you. And this is my last one. I lean McLothan online.
[4:33:18] I lean.
[4:33:21] Good evening.
[4:33:23] Yeah.
[4:33:23] Do you hear me?
[4:33:24] We can hear you go ahead.
[4:33:26] Okay.
[4:33:27] Good evening, Mayor Mack and members of Council.
[4:33:30] I am Eileen McLaughlin representing the Citizens Committee to complete the refuge.
[4:33:34] We are co-shiners and co-authors of the joint letter referred to as the Sierra Club Letter.
[4:33:40] We are pleased that multiple recommendations of the letter have been considered in the city's process.
[4:33:47] Remarkable and exceptional intentions of the specific plan will establish restore or enhance
[4:33:55] ecologically which areas provide the habitats that attract and serve increasingly biodiverse
[4:34:02] wildlife communities.
[4:34:04] We sincerely hope you will see those intentions become reality.
[4:34:09] Indeed it has been recommended that conservation easements be applied to help ensure those
[4:34:15] ecological goals can be met. We hope that requirement is established.
[4:34:23] Toward that goal, and as discussed in our letter, we recommended that the city's
[4:34:28] dark skies policies be improved on behalf of healthy habitats. In general, dark skies
[4:34:36] policies emphasize limiting the escape of light skyward and is controlled within urban areas.
[4:34:43] The needs of ground-welling species and species that are mobile at night are often not considered in those dark skyward policies.
[4:34:54] Night creatures are biologically adjusted to thrive in the darkest conditions.
[4:35:00] Light exposes them to predators, reduces their time to forage, and is a stressful disturbance affecting their reproduction.
[4:35:09] For those reasons, light fixtures, as on trails, need to be placed and shielded to prevent
[4:35:17] spill into sensitive habitats.
[4:35:20] Local windows, balconies, outdoor lighting, sports courts, or other fixtures should be
[4:35:27] timed and shielded to avoid light spill into those sensitive habitats that we so want
[4:35:35] to see developed here.
[4:35:37] One lighting reference used in the documents is a daily standard is the brightness of the full moon.
[4:35:45] This was confusing.
[4:35:47] We note that the light of the moon is full or near full for very few days of each month.
[4:35:54] Night creatures reduce their activity during those bright nights.
[4:35:59] For that reason, daily light fixture standards should not be set to the light of the full moon.
[4:36:05] As neither we nor wildlife ever experience a full moon every night.
[4:36:12] Please reset the outdoor and habitat adjacent light standard to 2700 Kelvin and be restricted to a warm color range that does not spill into ecologically sensitive areas.
[4:36:27] Again, we look forward to an ecologically rich shoreline for Brisbane. Thank you.
[4:36:35] Thank you. Next I have Dow Jane Pi online.
[4:36:47] So hopefully you can hear me. Good evening.
[4:36:51] Council members. My name is Dow Jane Pay. I'm the Program and Operations Manager for Buildup
[4:36:57] Semitail County. Really quick buildup is a multi-sector initiative whose mission is to preserve
[4:37:02] expand and improve child care facilities and I'm here tonight to build on the letter that we sent to
[4:37:09] the City Council dated September 11th, 2026. Thank you to Council Member Lens for calling
[4:37:15] attention to that letter tonight and I really appreciate this opportunity to participate in the
[4:37:21] the Baileyens project process. Because tonight's discussion is specifically about the
[4:37:28] planned. We did want to...
[4:37:30] Point out, which I think we did in our letter also, is that we didn't see child care specifically addressed in the staff report.
[4:37:38] So with 2200 new homes and 6.5 million square feet of commercial development, the Baylands project, when completed, will create child care needs from both new residents and it will also bring in a significant new workforce.
[4:37:52] child care is a part of the economic infrastructure of any community and it allows parents to work and it helps employers to attract and retain a workforce.
[4:38:05] Brisbane already recognizes daycare as a residential support of use in its general plan.
[4:38:11] Our request is that child care should also be intentionally considered as a council continues to discuss how uses are distributed across the balance.
[4:38:20] particularly in relation to residential neighborhoods and employment centers.
[4:38:26] With the scope of this project, you all are really designing and planning for residents and a workforce that doesn't exist in Brisbane yet.
[4:38:35] And that's a really hard job. It's a really hard job to predict the future.
[4:38:41] But we already know that child care is infrastructure and is an integral part of any thriving city.
[4:38:48] As we've said throughout this process, allowing child care is not the same thing as planning for child care.
[4:38:55] So tonight's land use discussion is an important opportunity to make sure that this planning begins.
[4:39:02] I just wanted to give a special thank you to Council Member Lens for reading our for reading build up recommendation to add a child care goal to section 2.2
[4:39:11] supporting this addition to the specific plan. I also think I heard council members
[4:39:17] Karen and Davis voice their support for the addition. Buildup is always available for
[4:39:22] continued discussion with all city council members about our recommendation. And I also wanted
[4:39:28] to spend to say thank you to the entire council and the city staff for the care and careful
[4:39:34] analysis you are putting into this project. It really shows in your questions and your comments
[4:39:40] and the staff reports and presentations,
[4:39:45] I wish I could say this was probably going to be the last,
[4:39:48] you know, meeting that goes until 10, 10, 30, but I think this is just the beginning of these
[4:39:54] long special meetings, but I do look forward to the upcoming discussions and participating in this
[4:40:00] exciting journey with you all. Thank you. Have a good night. Thank you. That's all the slips that we have
[4:40:08] and we are now out of time that being said could I get a first and second to continue the public hearing
[4:40:20] to October 6, 26 at 530 PM. When we say continue the public hearing and we continue
[4:40:28] in the public hearing on the topics of land use and design topics or we moving on to the next
[4:40:32] topic which is transportation and transit topics. We still had council questions on the
[4:40:38] land use topic. So that portion will appear on the next hearing along with some other topics.
[4:40:46] To clarify, it is one public hearing. You're continuing the public hearing on the approvals
[4:40:53] before the council. You can discuss the topics as you like at the next meeting. Thank you for that.
[4:41:01] So I did want to mention in the initial presentation from staff, they did leave off the Monday,
[4:41:07] October 26th meeting in the announcement of the meeting.
[4:41:12] Schedule.
[4:41:14] Okay.
[4:41:15] Thank you.
[4:41:15] Councilmember O'Connell.
[4:41:17] And with that all second the motion.
[4:41:19] I didn't get a first.
[4:41:20] I don't know.
[4:41:21] Oh, I'll make the motion to continue the meeting to.
[4:41:27] I need a second.
[4:41:28] October 6.
[4:41:29] All seconds.
[4:41:30] All in favor.
[4:41:33] Thank you everyone.
[4:41:34] Thank you for your endurance.
[4:41:36] Thank you for showing up in your interest.
[4:41:38] Your comments and your questions.
[4:41:39] Have a good night.
[4:41:41] Thank you.
[4:41:42] Bye bye.