Transcript
SOURCE TRANSCRIPT
This transcript is downloaded from the source you provided but we haven't reviewed it for accuracy. Treat it as a starting point, not a verbatim record. You can also request an AI-transcription of the audio file with the button to the left.
[0:00]
Yeah.
[0:00]
The problem is this is not natural for checking accounts.
[0:03]
We have a lot of residents who
[0:07]
don't check their accounts.
[0:08]
Depending on what account.
[0:10]
Yeah, well, just because it's inaccessible to certain people.
[0:14]
That's what's disturbing. I think this
[0:16]
era where we get so reliant on so much
[0:20]
and won't double-check, and then when we actually .
[0:24]
You start it out. That's a little start.
[0:27]
Again.
[0:28]
Sure, it makes it easier.
[0:30]
Yeah.
[0:30]
So it's an offset. Sometimes you can't access the offset.
[0:34]
Sure,
[0:35]
but I think it's a thing.
[0:37]
What?
[0:37]
If it's an extension of a book or whatever you need.
[0:41]
Use it lots so you're comfortable with it.
[0:44]
Certainly makes it not have to stare at a book by yourself.
[0:48]
Use a book. It doesn't
[0:52]
.
[0:52]
Yeah.
[0:52]
Are we watched? Did I watch anything?
[0:54]
Right.
[0:55]
Well, I don't know, but they should've been talking, but especially if you're still
[0:58]
writing.
[1:09]
Yeah.
[3:18]
No,
[3:30]
if
[3:31]
we're
[3:51]
talking.
[6:05]
So then Joe,
[6:06]
she watches. So Joe sent a,
[6:10]
"What was the speeding ticket?"
[6:14]
For two diapers in an hour, in the one hour.
[6:18]
I love it.
[6:19]
So whatever. But the second one was the best one.
[6:23]
Resisting arrest.
[6:26]
And then she-
[6:26]
Oh, get it. Ah.
[6:28]
And then she
[6:30]
all started to cry when she discovered.
[6:34]
That is perfection.
[6:37]
Yeah. I love it. I mean, it's just two ordinary nights.
[6:41]
There's a busy weekend.
[6:42]
Yeah, for some reason.
[6:43]
14.
[6:44]
All
[6:50]
of you?
[6:52]
Two. That's a big kid. He's tall.
[6:54]
Very tall. He was as big as my two daughters.
[6:57]
Good stuff.
[6:58]
No,
[6:59]
for a second, I want to go to the store up there, but I got to drink another sip,
[7:03]
man. I need to get a lot.
[7:05]
It's just me.
[7:06]
This is Mom and
[7:10]
Dad.
[7:10]
My uncle lived there, so.
[7:13]
One more.
[7:13]
Super nice studio.
[7:17]
It's just anywhere I go.
[7:21]
Well, is it a
[7:23]
bungalow? She said my niece's dad or sister is doing that.
[7:29]
Nothing in
[7:31]
Princeton. Both sides of the
[7:34]
family.
[7:36]
I said to her, "If you like this, she won't."
[7:42]
She loved that.
[7:54]
Okay.
[7:57]
Good
[7:57]
question.
[8:18]
All
[8:28]
sharing gen approach.
[8:33]
I just love this. So cool.
[8:39]
Yeah, I know.
[8:40]
From here.
[8:45]
As I feel like we're going to be referencing that for some years, but I wanted to
[8:48]
get started talking to you all early.
[8:50]
But it's not, yeah, just-
[8:52]
But so Steven, yeah. Just Steven.
[8:54]
Took a little while to get done, so
[8:58]
here.
[8:58]
I
[9:00]
will tell you, I went to Arthur for a little bit on that race.
[9:05]
Hated it.
[9:06]
Oh,
[9:07]
no.
[9:07]
It was just too long, too much, too hot. Too definitely.
[9:11]
Yeah.
[9:11]
Their roads are very uneven, and I was behind a
[9:15]
woman with just water, just like this, like, "Oh, just walk down."
[9:20]
It made me nervous.
[9:22]
Actually, my best friend, she loves ours, said...
[9:28]
Yeah. Mine's evolved. I know they are.
[9:32]
I know, I can tell you the same.
[9:35]
It's longer. Ours is like-
[9:37]
It's not as long.
[9:38]
So all part of.
[9:39]
No, limit is more.
[9:41]
Limit is more.
[9:42]
Yeah, by a lot.
[9:42]
But it turns slightly on a straight path, so you're like, "Is this?"
[9:46]
But it has some cute ones, but there was one guy, I didn't know he was at ours.
[9:58]
Wow. It did. I walked very slowly
[10:02]
because I was like-
[10:02]
She is going to, yeah.
[10:05]
Having a
[10:06]
normal day,
[10:10]
yeah.
[10:10]
Yeah.
[10:11]
Hey,
[10:19]
Pete.
[10:19]
Well, how are
[10:21]
you?
[10:21]
Good, how are you?
[10:21]
We're good.
[10:22]
Last night and then this morning.
[10:23]
Getting ready to be an empty nester.
[10:26]
If we do-
[10:27]
Whoa
[10:27]
... I'm an empty nester.
[10:28]
We hit that also.
[10:30]
Well, I have another one, though, but I'm sending mine first
[10:34]
off.
[10:35]
Oh, your first is going. You're beginning the process of
[10:38]
empty nesting. Kicking them out.
[10:44]
Now you get to work, Steve.
[10:46]
What's that?
[10:47]
We like how they said-
[10:49]
College or did they move couch? So I think
[10:52]
most, a lot of kids move back in with their parents after
[10:56]
grad. So it could be only a short-
[10:58]
For now.
[10:59]
Yeah, for now.
[11:00]
Empty nester for now. We get a taste of it.
[11:02]
Yeah. This will be the first semester that he's going away to school.
[11:05]
The others were already-
[11:06]
Do you know something? It relates to something-
[11:09]
Yeah.
[11:10]
My cousin looked at that.
[11:11]
What's that?
[11:11]
And then her brother moved-
[11:13]
I know
[11:13]
... over to her cousin's.
[11:14]
It's amazing. It's amazing.
[11:16]
So we're going to talk about future.
[11:19]
So I need to know-
[11:20]
I need you working, spending.
[11:24]
That was our first rescue.
[11:27]
NGTA.
[11:30]
The son of the
[11:35]
daughter.
[11:38]
I don't know what's going to become check after this.
[11:41]
My middle child,
[11:42]
they have it.
[11:44]
My 30-year-old, Linda,
[11:47]
she knows she'll need to do that alone for her mental health.
[11:51]
Everyone has to see.
[11:53]
She's like, "I need to live alone." She actually lives with her boyfriend right
[11:57]
now, and I think she's possibly going to a place on her own.
[12:00]
Not because she doesn't love him or whatever. They've been together for what?
[12:04]
All projects.
[12:06]
Will you help at least-
[12:07]
I think I know who
[12:08]
... Craig, Cindy, and Ruggieri could help you.
[12:11]
Yeah. So we know that we'll have people, but we'll see who plays.
[12:15]
So who knows. But what you were in the library on-
[12:17]
Yeah, we will.
[12:18]
I can't make sense right now. Slow down.
[12:22]
Sam, are we good to go?
[12:24]
I don't know. Just one at
[12:27]
a
[12:27]
time.
[12:33]
I'm trying to.
[12:34]
Yep.
[12:35]
She's wiggling the camera with us.
[12:38]
So we'll call to order the Plymouth Downtown Development Authority-
[12:40]
Recording in progress
[12:41]
... meeting for August 10th. Sam?
[12:46]
Yeah. Just a couple of reminders. To make sure you have your mics on when making
[12:49]
comments, so the folks on Zoom, which I don't think there are any yet,
[12:53]
but if there are any that pop in, they can hear us.
[12:56]
And then for those on Zoom,
[12:59]
we can get you in the panelist room to make comments at the appropriate time.
[13:03]
We will do a roll call.
[13:07]
Attendance. Director Saloom?
[13:09]
Here.
[13:10]
Director Signs?
[13:11]
Here.
[13:12]
Director Perry is not here.
[13:14]
Director Harris is excused. Director Frye?
[13:17]
Here.
[13:17]
Director Elliott?
[13:18]
Here.
[13:18]
Director Eckley?
[13:19]
Here.
[13:20]
Mayor Phillips-Ack?
[13:21]
Here.
[13:21]
Vice Chair Matsu?
[13:22]
Here.
[13:23]
And Madame Chair Pollard?
[13:24]
Here.
[13:25]
We have a quorum.
[13:26]
Thank you.
[13:27]
Do we have any citizens' comments this evening for anything not on the
[13:31]
agenda?
[13:33]
Do we have anyone online?
[13:36]
Nope.
[13:37]
All right. I'll take a motion to approve the agenda with one
[13:41]
addition. We did not list
[13:44]
Director Eckley as being present for last month's
[13:48]
meeting.
[13:49]
That is actually in the minutes.
[13:50]
Oh, okay.
[13:53]
Okay. Sorry. Oh, that's right. I apologize. Motion to approve. I apologize.
[13:56]
Motion to approve the agenda.
[13:58]
Second.
[13:59]
Motion made by Director Signs, seconded by Mayor Phillips-Ack.
[14:03]
All in favor?
[14:04]
Aye.
[14:04]
Aye.
[14:04]
Aye.
[14:04]
Aye.
[14:05]
All opposed?
[14:08]
Motion carries. All right. Now I'll take a motion to approve the
[14:12]
minutes with the addition of Director Eckley being present for the meeting.
[14:18]
So moved.
[14:19]
Second.
[14:21]
Move.
[14:22]
Motion made by Mayor Phillips-Ack, seconded by Director Signs.
[14:26]
All in favor?
[14:28]
Aye.
[14:28]
Aye.
[14:28]
Aye.
[14:28]
Aye.
[14:29]
All opposed?
[14:31]
Motion carries.
[14:33]
Do we have any board comments this evening?
[14:39]
Sure.
[14:39]
I have board comments. I always have board comments.
[14:42]
So we didn't have a meeting in July, so it's kind of funny all
[14:46]
the stuff we missed, but Fourth of July parade was great.
[14:49]
Hopefully people were there. I was there. It was great.
[14:53]
I think the concerts are going really well.
[14:57]
James is doing a great job. Rico, you and Sam are just doing a really good
[15:01]
job at... Really good comments from people about the vendors
[15:05]
and the music and everything's really, really good.
[15:08]
So,
[15:09]
as to be expected.
[15:11]
And also, I want to let everybody know at The Pen next month, so it'll be before
[15:14]
our next meeting, on September 10th, we have a collaboration we're doing with
[15:18]
Michigan Environmental Council.
[15:22]
We're showing a documentary film called "Troubled Waters," and
[15:26]
we're going to have a panel discussion with the Michigan Environmental Council
[15:31]
organizational members there. And I think it'll be a very
[15:35]
engaging conversation because when you think about it, we are so
[15:38]
fortunate. We have 20% of the world's fresh
[15:42]
water supply that we have surrounding us, and so our
[15:45]
responsibility is great. So I think it'll be a really good conversation, and it's
[15:50]
a free program, and I invite everybody to hopefully come and
[15:53]
check it out. That's all I got.
[15:56]
Thank you, Commissioner. Thank you.
[15:58]
Anyone else?
[16:00]
I have something to add. Not this past weekend, the weekend before,
[16:04]
Joe and Ellen and I were standing around and talking to our permits
[16:08]
colleagues, and a young man or old man, I don't know which,
[16:12]
came up to her and told her what a fabulous city we live in.
[16:15]
And this is a credit to our DDA because he said,
[16:19]
"You cannot get bored. There is something to do every night of the
[16:23]
week here," and it's the best city he's ever seen.
[16:26]
And that's all I keep hearing, is everybody loving our city, so thanks for all the
[16:29]
hard work everyone's doing.
[16:32]
Thank you.
[16:36]
I just wanted to add my thanks to Municipal Services, that the
[16:39]
morning after Art in the Park, I could not tell that Art in the Park had happened
[16:43]
over the weekend. And I know that that's something that they always accomplish, but
[16:47]
it always amazes me how we can come in on a Monday morning, and they've done such
[16:51]
an incredible job overnight to clean up.
[16:53]
I'm not implying that Art in the Park leaves the city a mess at all, but it is a
[16:57]
lot of work to kind of rearrange and put everything back together.
[17:00]
And I always appreciate when they make that happen.
[17:03]
Even by the end of night, it's spotless.
[17:06]
Yeah.
[17:06]
It's pretty impressive. DMS just plows out and takes care of it.
[17:09]
Yeah. And I feel like Art in the Park went pretty smoothly this year.
[17:14]
There were a few parking issues, but not any more than we normally have,
[17:18]
and they were resolved relatively quickly.
[17:20]
So
[17:22]
yeah, it was a good event this year.
[17:25]
Shannon, do you have any board comments?
[17:27]
No. Thank you.
[17:29]
All right. Then we will move on to 6A, strategic plan
[17:33]
update. Sam?
[17:35]
Yeah, just a few updates this month.
[17:38]
If you remember back in June, the DDA board accepted the
[17:41]
deliverables from SmithGroup on DTP Forward.
[17:45]
Staff has started exploring some of the implementation and funding
[17:49]
options. It looks as though we're going to be beginning
[17:52]
with project set two, which is the
[17:56]
area around Harvey and Wang.
[17:59]
There's potential for maybe something to happen before then.
[18:02]
In early 2027, there's a water main that may be
[18:06]
addressed in another section of town, but that's to be determined at this time.
[18:13]
City staff met with the DDA a few weeks
[18:17]
back. We're working on a plan for some upgrades on the north side of the parking
[18:20]
deck. You remember that garage that housed the old
[18:24]
sweeper there was removed last year.
[18:26]
So we're looking at cleaning up the pavement there, it's in pretty
[18:30]
rough shape, adding some bike racks in that area.
[18:33]
And we're also looking at cleaning up the area, the walkway between the
[18:37]
parking deck and Main Street, the lower
[18:40]
portion that is right behind Campari's there.
[18:44]
So, there's some painting that needs to be done.
[18:46]
We want to update the planters, and
[18:50]
improve pedestrian flow,
[18:53]
and potentially some decorative lighting in that location that's been similar to
[18:56]
what's been done in a couple of the other walkways.
[18:59]
So,
[19:00]
we're developing that plan, and
[19:03]
hopefully in the next month or two, this board will see what we're looking to do.
[19:08]
With the Main Street median trees being removed, we're looking at
[19:12]
options to light the median for the holiday season, so we're
[19:16]
looking into some options there. We're meeting with the chamber
[19:21]
next month to talk about, or actually next week, to talk about holiday
[19:25]
decorations. Outdoor dining season ends October
[19:28]
31st.
[19:30]
The renovation project, the parking deck, that actually wrapped up a while
[19:34]
ago, but we haven't had a meeting since it was finalized.
[19:38]
And we also had, when the city contractor, many of you might have noticed right
[19:41]
before Art in the Park, we had a contractor in doing some
[19:44]
spots around downtown patch work.
[19:48]
We had some issues in the park, lower level of the parking deck that
[19:52]
needed to be addressed in the near term, so that was done at that point.
[19:58]
Appreciate that.
[19:59]
Yeah. It was great. With people walking on the streets, it was important to get
[20:03]
that fixed up. So, the only other update I have is our
[20:07]
contractor did come in,
[20:10]
again, right before Art in the Park, and shaved and smoothed some additional
[20:14]
areas of sidewalks as well. So,
[20:17]
any questions or comments?
[20:21]
Sam, do you know if
[20:24]
the
[20:26]
valet parking's coming back for the fall?
[20:30]
I do not at this point. It's open for people to apply.
[20:34]
There hasn't been any applications as of yet.
[20:36]
I would assume The Ledger would return again, as the
[20:40]
first couple of years have been successful.
[20:42]
But that's entirely up to them if they want to apply.
[20:45]
And I haven't had any conversations with Stefan or
[20:48]
anybody else from The Ledger at this point about that.
[20:51]
Sam, is that open for people to apply right now, or...?
[20:55]
It's a good question. I don't know if it
[20:59]
stipulates in the policy of when applications can start.
[21:02]
I'd have to check on that. But yeah, probably within the next month.
[21:06]
If you want to pass that along to Stefan that he needs to get a jump on it, that
[21:10]
would be helpful. Yeah. That's the reason I was asking. I didn't know- Yeah. ...
[21:12]
if they already started, so yeah.
[21:15]
Yeah. Yeah. It's always better to be early on that, because it does
[21:19]
take a few weeks for administration to process everything.
[21:23]
Yeah.
[21:26]
Sam, I don't know if I missed it or not.
[21:28]
When is the tree light contractor
[21:31]
coming through?
[21:32]
Oh, well, he actually started today.
[21:34]
Oh, good. Okay. Good.
[21:35]
He was on Forest today.
[21:38]
Got a big chunk of Forest done today.
[21:41]
He'll be returning in the next two or three days, before completing.
[21:45]
We will probably have him back again in November, as
[21:49]
DMS crews are planning doing significant tree trimming
[21:52]
on Ann Arbor Trail and then on Main, and that can cause some
[21:56]
issues where we're gonna have to clean some stuff up.
[21:59]
But we usually do that anyway before
[22:02]
our event, the holiday event. So,
[22:05]
I would anticipate when he has to come in in November, it's just a few hours to
[22:08]
clean a couple things up. But yeah, the majority should be done by the end of the
[22:11]
week.
[22:12]
Great. Thank you.
[22:13]
Yep.
[22:13]
It makes our city look so special with the sparkle lights.
[22:20]
Yeah, they had a good setup. We were walking by on Forest this
[22:24]
morning, when they were... And it was interesting how they
[22:28]
didn't take up more space than what they needed to for the parking, and so they had
[22:32]
it blocked off and had their hi-lo just
[22:35]
moving along. But then they would put the
[22:39]
spaces back in use as soon as they could.
[22:41]
So I thought that was good that they seemed to be conscious of the need for the
[22:44]
parking spaces as well.
[22:45]
Yeah, and the new contractor's been really good about meeting and discussing those
[22:48]
potential impacts. We don't want to
[22:52]
put no parking in half the downtown.
[22:54]
We're taking 15 to 20 spaces at a time, so then he can work, move
[22:58]
the spaces as he goes. And then really,
[23:02]
the early morning is the best time, because there's not as much
[23:06]
impact on the park. There's not as many activities downtown.
[23:10]
Mm-hmm.
[23:10]
So yeah, moving forward, he's gonna be starting on Mondays.
[23:13]
We have a lot of the retailers are closed on Mondays.
[23:15]
Awesome.
[23:15]
It's a really good day to get a big chunk done.
[23:17]
So, he's very cognizant of those issues, so...
[23:23]
Any other questions?
[23:26]
Nope.
[23:27]
Thanks, Sam.
[23:30]
Moving on.
[23:33]
Seven, new business.
[23:37]
So back in June of 2026, the DDA board accepted and approved the final
[23:41]
deliverables for DTP4ward, our streetscape upgrade
[23:45]
project,
[23:47]
from the consultants at Smith Group.
[23:49]
Over the past month, DDA and city administration met to discuss project
[23:52]
implementation, phasing, and funding strategies.
[23:55]
Preliminary discussions focused on engineering and construction projects for
[23:59]
2027. Again, what I mentioned before, project
[24:03]
set two, or the area near Harvey and Froehlich, where underground
[24:07]
work is needed.
[24:09]
While specific allocation of funds for the 2027 infrastructure project has
[24:13]
not been determined at this time, it's believed that most of that portion of the
[24:16]
project can be funded through DDA and city funding
[24:19]
While work on DTP4 is expected to begin in 2027 with DDA and city
[24:23]
funding, significant funding from outside sources such as state and federal
[24:27]
grants will be necessary to continue future work.
[24:30]
Project set one, the Main Street corridor and around Kellogg Park, is estimated to
[24:34]
cost around $20 million, and project set four, Ann Arbor
[24:38]
Trail and Forest, is estimated to cost approximately $8 million.
[24:42]
Though construction on those sets is not expected for several years,
[24:46]
the timeline to apply for grants that can address such costs
[24:50]
dictates near-term preparation.
[24:53]
DDA Deputy Director Rakow is participating in
[24:57]
SEMCOG and Grant Writing
[25:01]
USA's administered workshops to grasp the fundamentals of grant writing
[25:04]
and administration. DDA staff met with SEMCOG
[25:08]
representatives to explore funding sources that match the DTP4 project.
[25:12]
We'll be hosting SEMCOG in a couple of weeks as well.
[25:17]
But based on many exploratory discussions with SEMCOG, city administration, and
[25:21]
leaders from other communities with experience in similar projects, DDA staff has
[25:25]
identified the need for professional grant writing assistance,
[25:29]
especially for the state and especially for the federal-based
[25:32]
grants that have complex technical requirements and are
[25:35]
resource-intensive and very competitive.
[25:38]
Smith Group's proposal for the Streetscape Upgrade Design project listed
[25:42]
professional grant writing assistance as an add-on service at a cost of $10,000 to
[25:45]
$20,000. While Smith Group's exemplary work thus far
[25:49]
indicates probable high-quality services, DDA staff believes that it's
[25:53]
best to practice due diligence to ensure the best possible professional
[25:57]
grant writing assistance.
[25:59]
The RFP process to hire Smith Group for the design phase of DTP4 took more
[26:03]
than six months to complete, with many dedicated DDA staff hours.
[26:07]
As there is some urgency in beginning the grant writing process, a federal grant
[26:10]
application may take up to and potentially more than a year to be
[26:14]
prepared and finalized, a more streamlined process is
[26:17]
recommended. Instead of a comprehensive RFP, it may be best for DDA staff
[26:21]
to gather cost quotes and qualifications over the next month or so to
[26:25]
allow work on grant writing to begin before the end of 2026.
[26:29]
DDA staff would like the DDA board to discuss and give direction before proceeding.
[26:33]
Just to note, under Section 2-126 of City Code
[26:37]
of Ordinances, professional grant writing services would be considered a
[26:41]
professional service, not a traditional contractual service, so a formal
[26:45]
bidding process is not required for professional services.
[26:49]
DDA staff recommends reaching out directly to two
[26:53]
to four reputable providers of professional grant writing assistance, in addition
[26:56]
to the Smith Group, to obtain quotes and qualification references.
[27:00]
Submitted quotes will be reviewed, and DDA staff will make a recommendation to the
[27:04]
DDA board in the next month or two.
[27:06]
Although the resolution is attached for consideration, DDA staff requests that the
[27:10]
DDA board discuss the issue and give direction to the DDA
[27:14]
staff
[27:16]
prior to the DDA staff proceeding with seeking
[27:19]
professional grant writing assistance.
[27:23]
I move the resolution.
[27:24]
Second.
[27:26]
I'm sorry, who was the second?
[27:27]
Second. Me.
[27:28]
Oh. So motion made by Director Elliott, seconded by Mayor
[27:33]
Phillips.
[27:34]
Yeah.
[27:34]
Anybody have questions, discussion?
[27:38]
Mitch?
[27:40]
So the idea of not doing the full-blown RFP over the next six
[27:43]
months sounds like a good idea, because that sounds like more work than is
[27:46]
necessary. But is there an idea of doing some
[27:53]
preparation to make it as good evaluation process as
[27:56]
possible? I would suggest that's a good idea.
[27:58]
I'm curious to hear what you think.
[28:00]
Yeah. We've had some discussions.
[28:02]
I'm not exactly sure what that's going to look like at this point, but we have
[28:05]
about five or six bullet points that we're going to include when we reach
[28:09]
out to these organizations directly.
[28:12]
That will include some of the... This may sound kind of obvious,
[28:16]
but obviously, qualifications,
[28:20]
grants that they've gotten, what
[28:24]
communities they've worked with, and which grants they've obtained.
[28:28]
Obviously, cost,
[28:30]
and there's I think two or three other bullet points-
[28:33]
One-
[28:34]
... that were on the top of my head-
[28:35]
... run-on thought is-
[28:35]
... that we were talking about. Yeah
[28:36]
... that Smith Group probably has
[28:38]
a deeper understanding than others about
[28:41]
what's been done so far. Maybe it's a good idea to somehow level the
[28:45]
playing field a little bit so that it sounds like they could be a good candidate,
[28:49]
but so that it's a fair evaluation.
[28:52]
So it's about getting the other participants a little bit up to speed on what has
[28:56]
been done.
[28:56]
Yeah. We plan on including all of that information.
[28:58]
We have all that stuff listed on our website, the plan,
[29:02]
the whole process, and all of those things.
[29:05]
I've also met with Oliver from Smith Group in recent times just to
[29:09]
discuss
[29:11]
some of the things that they've done with other communities to get a little bit of
[29:14]
better understanding from our perspective of what we need to seek out.
[29:17]
So,
[29:19]
yep. That's-
[29:21]
From your discussion with SEMCOG, could you get some referrals from them as
[29:25]
well from working with the different mayors?
[29:27]
Are they trying-
[29:28]
They shy away from-
[29:29]
Okay, because they don't want to be liable? Okay. Fair enough.
[29:31]
Well, they don't want to play favorites, I don't think-
[29:34]
Okay
[29:34]
... with that.
[29:34]
I didn't know if they had a list they could share.
[29:36]
Yeah.
[29:36]
That's okay.
[29:36]
That was the conversation-
[29:37]
Okay. Figured.
[29:37]
... that we had, and that was their response.
[29:39]
That was actually my question.
[29:40]
Which makes sense.
[29:41]
That was my like, "How do I phrase that without it seeming..."
[29:43]
No, I think once you start evaluating and you see the success rate,
[29:49]
you're
[29:51]
looking at the right metrics, you're looking at the right things.
[29:53]
And I appreciate the fact that you're not going for an RFP, because that
[29:57]
I don't think is necessary at all.
[30:01]
The grant writing now is much different than it used to be.
[30:04]
You're right.
[30:05]
For sure. Things have streamlined.
[30:06]
But I've written federal grants before, not for this much,
[30:10]
but if you don't have it done the right way, it's a
[30:13]
technicality that throws your application out.
[30:16]
So to have people who have seen success- And
[30:20]
understand the system. I have no doubt you're going to find the right
[30:23]
person. And I appreciate the fact that you acknowledge the fact that you
[30:27]
need to find someone to help with this because of the complexities there.
[30:31]
And Reiko, at some point,
[30:33]
you will be able to do it. It's just-
[30:35]
You will.
[30:37]
Trust me.
[30:37]
You will.
[30:37]
You will.
[30:38]
Once you see it, you'll go, "I could do that."
[30:39]
But right now,
[30:41]
this is a perfect setup for you to be able to take the SEMCOG
[30:44]
training and watch the process of what a professional does, and that
[30:48]
eventually will save us money
[30:51]
when we've got someone on staff who
[30:54]
has experience, which you will get experience once you go through the process.
[30:57]
So, I really appreciate the fact that you're doing this, because
[31:00]
the money is there. You just have to have the right
[31:04]
person to find it, and you can mess it up really easy if you
[31:08]
don't have the right person. So, I really appreciate the fact that you guys
[31:11]
are doing this in really a thoughtful,
[31:16]
very precise way. So, thank you for doing that.
[31:19]
I wanted to add that to address Director Matu's
[31:23]
question.
[31:23]
I'm sorry, can't hear you.
[31:25]
Oh. To address Director Matu's
[31:29]
question, I think the upcoming meeting with SEMCOG and
[31:33]
the conversations that will-
[31:35]
Yeah
[31:35]
... continue is going to really help us in shaping the evaluation process as well.
[31:39]
That's what they do. They're experts, so they are a really good resource, and
[31:43]
they seemed very open to keeping the communication channels
[31:47]
open and for us to lean on them as that kind of resource.
[31:51]
And thank you for being proactive as opposed to having to be
[31:55]
reactive. You guys are so far ahead of the game, which is a great thing for
[31:58]
everyone because it'll allow you to gather all that data.
[32:01]
I've seen, and I'm sure you guys have as well, when you have some grant writers
[32:05]
that come in and say they can do grants, and then you go, "No,
[32:09]
not so much."
[32:10]
Well, and then you don't want to be scrambling at the last second-
[32:12]
Yes
[32:12]
... trying to get your-
[32:13]
No
[32:13]
... phrases correct and things done-
[32:14]
No
[32:14]
... clinically correct and then-
[32:16]
Right
[32:16]
... mess it up.
[32:17]
And the federal government requires some of-- The one grant I wrote,
[32:21]
and we got it, it was almost $200,000.
[32:24]
But the paperwork, it was three-inch thick stack of paperwork, and you had
[32:28]
to make sure that everything was done exactly right or it was out the
[32:32]
window. But
[32:34]
yeah. So, I think it's interesting. Now, Sam, do you know if...
[32:39]
And I don't even, Redevelopment Ready Communities program,
[32:43]
is there anything within that
[32:46]
with how far we have our certification that can help
[32:49]
with funding any of these little
[32:53]
things?
[32:55]
Or do you know?
[32:55]
That, I don't know off the top of my head exactly, but I do know
[32:59]
there's opportunities. I know at the Michigan Downtown Association conferences,
[33:04]
they've mentioned opportunities.
[33:07]
There's usually a representative from MEDC that does a presentation at those.
[33:11]
And
[33:12]
I
[33:13]
don't know exactly where we're at in the certification process, and that kind of
[33:17]
does dictate-
[33:17]
Yeah
[33:17]
... what you're eligible for.
[33:19]
Right.
[33:19]
I have an idea, but I don't know exactly.
[33:21]
So, if you have the full certification, that does open a lot more
[33:25]
funding opportunities.
[33:26]
Yeah.
[33:26]
So, I don't think we're quite there yet.
[33:29]
We're working toward that, but-
[33:29]
But I think we still, we're far enough along that we do-
[33:31]
Yeah
[33:31]
... have some resources that we could use.
[33:34]
Yeah, 100%. Yes.
[33:34]
Yeah.
[33:34]
Yes.
[33:34]
Because I don't want to forget those things, because that took a lot of time to get
[33:37]
the-
[33:37]
So-
[33:38]
... process done
[33:38]
... between SEMCOG and the MEDC, I think,
[33:42]
I don't want to say all of that work, but I think-
[33:45]
Yeah
[33:45]
... we can explore kind of what the
[33:48]
obvious opportunities are.
[33:50]
Yeah.
[33:50]
Because there are some that are relatively obvious.
[33:53]
TAP Grant being one from SEMCOG. In the plan that y'all have,
[33:59]
Oliver and Smith Group listed quite a few that
[34:03]
would be probably in the wheelhouse that we can kind of look at ourselves.
[34:06]
But the bigger federal ones are just so complex.
[34:10]
Yeah.
[34:10]
So, we may be able to get the ball rolling on some of
[34:14]
the, whether at the MEDC and the SEMCOG level, because there is support
[34:18]
within those organizations to help you with the application process.
[34:22]
But the federal ones are just a completely different level.
[34:24]
Yes, they are. Absolutely. Okay.
[34:26]
One more. So, once you get your hands around
[34:30]
the different options and their strengths and weaknesses, will we get a chance to
[34:34]
take a look at-
[34:35]
100%, yeah.
[34:36]
If that's the next good event-
[34:37]
Yeah
[34:38]
... for
[34:39]
us. Yeah.
[34:39]
I didn't want to
[34:43]
just jump right into that. I wanted this board to have the opportunity to give
[34:46]
direction about how we attack that first.
[34:49]
So, if this resolution is approved tonight, that'll give
[34:53]
us the direction, and then we'll be coming back to the board either
[34:57]
at no later than October, unless something strange happens with the
[35:00]
process where we're having trouble contacting people or something.
[35:03]
But
[35:04]
I would like to have it on the next agenda.
[35:06]
That may be a little bit optimistic, but for sure by October.
[35:09]
And then you'd get the opportunity to see what
[35:13]
the qualifications to different companies that we've looked at, and we'll
[35:17]
likely have a recommendation at that point.
[35:20]
Awesome.
[35:22]
Any other questions for Sam and Reiko?
[35:26]
No?
[35:28]
All in favor of the resolution?
[35:30]
Aye.
[35:31]
All opposed?
[35:34]
Motion carries.
[35:37]
Yay.
[35:39]
Sam, reports and correspondence?
[35:44]
Yep. We have one Downtown Day in Michigan 2026, and I'm going to
[35:48]
let Reiko handle this one.
[35:52]
We've been celebrating Downtown Day in Downtown Plymouth for several years now.
[35:56]
It is usually the fourth Saturday in September.
[36:00]
It's usually declared through a proclamation by the
[36:04]
Governor of Michigan.
[36:06]
Downtowns across the street are celebrated as unique commercial and social
[36:10]
cores of their community. The City Commission approved this
[36:14]
year's DDA run Downtown Day event at its July 20th,
[36:18]
2026 regular meeting. And so we are planning for Downtown
[36:22]
Day on Saturday, September 26th from noon to 7:00.
[36:28]
There will be live music, family-friendly entertainment.
[36:32]
We will also be giving some information regarding DTP
[36:36]
Forward, and DTP businesses will participate in several
[36:40]
options.
[36:42]
The bulk of our activity will be in Kellogg Park.
[36:46]
We're currently booking music and entertainment, and we've reached out to
[36:50]
businesses regarding event sponsorship and participation options, and
[36:54]
we are creating marketing materials to promote the event.
[36:58]
One of our new fun ideas we had, a little twist on the
[37:01]
scavenger hunt that we've done for several years.
[37:03]
We're calling it the DTP Token Scavenger Hunt.
[37:06]
Businesses that donate gift cards towards prizes will be listed
[37:10]
as scavenger hunt participants, and they'll receive DTP
[37:14]
tokens, which are customized coins, to hide at their
[37:17]
locations. Visitors will visit participating businesses,
[37:21]
explore, hunt, and hopefully shop for a token, and find
[37:25]
the tokens and shop at the locations and claim prizes at the DDA
[37:29]
tent in Kellogg Park.
[37:32]
Last year, during our Downtown Day, we worked with consultant Smith Group
[37:36]
to have a community engagement pop-up for DTP Forward.
[37:40]
This year,
[37:42]
we are finalizing an informational video highlighting the major
[37:46]
themes from those final designs.
[37:49]
The video is expected to be available for public viewing at the DDA tent in
[37:52]
Kellogg Park on Downtown Day, and we hope to continue informing the
[37:56]
community and maintaining momentum for the DTP Forward project.
[38:02]
Thank you.
[38:03]
Any questions about Downtown Day?
[38:05]
That's awesome.
[38:07]
Any last-
[38:07]
You'll probably see us out, Julie and I will be out doing some recording for that
[38:11]
video this week.
[38:13]
Yes.
[38:13]
As long as the weather's nice on Wednesday, we'll-
[38:15]
Hopefully.
[38:15]
Yeah, we got
[38:18]
the voiceover and if you see me out on the
[38:21]
Main Street median or right there along Kellogg Park, that's what I'll be doing on
[38:24]
Wednesday if the weather's nice.
[38:26]
Well, the videos for the Michigan Downtown Association were
[38:30]
good. They were very cute and nicely done, and...
[38:33]
Yeah, that's something that we forgot to mention during the update.
[38:35]
We
[38:38]
took over the Michigan Downtown Association social media on Friday.
[38:41]
They allow for communities to take over their social media during the
[38:45]
month of August. So, Reiko and Alex did a great job with that,
[38:49]
making videos and talking about some of the historic and the landmarks
[38:53]
and showing the activities of the concert, so I thought they did a really good job.
[38:57]
Yeah, I would say it was 90% Alex, our PR assistant. She does a great job.
[39:02]
And y'all know Sam Scanell. Yeah.
[39:06]
I thought he was going to go under, like you go under the stairs and do it.
[39:10]
That's one take.
[39:17]
Any other questions for Downtown Day?
[39:20]
Last year was fun.
[39:22]
I know you'll send out a note for volunteers as well, but if-
[39:25]
Yeah, well, we're looking for volunteers, so if anybody wants to help out, we
[39:28]
usually need some volunteers just to help man the tent.
[39:31]
So, when we do the scavenger hunt, staff's got to run around, and
[39:35]
so we give the tokens to the business, but we'll also be hiding many around just
[39:38]
the outside of downtown. So, if anybody's interested in helping out just manning
[39:42]
the tent, we have a... What do you call the bingo?
[39:47]
Uh-
[39:47]
Like a-
[39:48]
Little bingo ball-
[39:49]
Got a bingo cage
[39:50]
... cage. Yeah, thank you.
[39:50]
The cage, and-
[39:51]
Little bit. Small cage
[39:51]
... so people will come, and they'll get to choose.
[39:54]
The ball will have a corresponding prize.
[39:56]
So, that will be the main thing, maybe a little bit of set up and breakdown, so
[40:00]
we'll be looking for volunteers. So, if you or anyone you know is
[40:03]
interested and, or have any kids in the eight hours or anything like
[40:07]
that, we're happy to have them.
[40:11]
It is always a fun day, so...
[40:19]
All right.
[40:20]
We will take a motion to adjourn.
[40:23]
Motion to adjourn.
[40:25]
Support.
[40:26]
Motion made by Director Sign, second by Director Fry.
[40:32]
Yep. All in favor?
[40:36]
I.
[40:36]
I.
[40:36]
I.
[40:36]
I.
[40:36]
All opposed?
[40:38]
Motion carries. Thank you, everyone. Have a good evening.
[40:47]
Record-