[0:02]
Hey, good morning everybody. I want to
[0:03]
welcome you to the Magna Water Board
[0:06]
meeting at 888
[0:08]
8885 West 3500 South at our general
[0:12]
office building. I'd like to call this
[0:13]
meeting to order. Will you guys all
[0:15]
please stand with for the pledge of
[0:17]
allegiance?
[0:21]
» I pledge algiance to the flag of the
[0:24]
United States of America and to the
[0:27]
republic for which it stands. One nation
[0:30]
under God, indivisible, with liberty and
[0:34]
justice for all.
[0:36]
>> Thank you. I would like to uh welcome
[0:39]
our public and guests. And today sitting
[0:41]
at our dis table is our engineer Trevor
[0:44]
Andre. Our sewer manager is our
[0:48]
wastewater, that's better, his Dallas
[0:50]
headline. Um Steve Clark is over our water and Andrew Sumpion is our
[0:58]
HR. Jeff White, myself, Danny Stewart,
[1:01]
chair and trustees. Leo Fitzgerald is
[1:06]
our controller. Nathan Bracken is our
[1:09]
legal counsel and today will be helping
[1:13]
me is Clint Dilly, our general manager.
[1:16]
So we're going to move on to public
[1:18]
comment. Um, does anybody here have an issue with our agenda today? A
[1:24]
conflict.
[1:26]
Okay, I don't see anything. So, our
[1:28]
first person to comment to the board is
[1:32]
Tommy Martinez. So, Tommy, if you want
[1:34]
to
[1:36]
>> come up and
[1:57]
Yeah, we just want to know what's going
[1:58]
on with her. That bru
[2:08]
uh they take pictures and everything and
[2:10]
we told them it was blocked up the
[2:12]
street by the the tongs and
[2:17]
well here's the the thing on the
[2:19]
plumber. He said it was
[2:24]
>> Thank you.
[2:24]
>> It was in that drain pipe and they came
[2:28]
down there and put that that suction
[2:31]
thingy in that and it rushed all the way
[2:34]
down to my place and mine was the only
[2:38]
house with a basement there. It all
[2:40]
rushed in the house. So, I got I got a
[2:43]
question for you. So, the day I spoke to
[2:44]
you on the phone, um did you say that
[2:47]
now correct me if I'm right or wrong,
[2:50]
did you say that um the road the road to
[2:52]
Rooer I'm going to use that went up the
[2:54]
road they got in our main line?
[2:56]
>> No.
[2:57]
>> Okay. Okay. Okay. But so they didn't
[2:59]
shoot nothing down there cuz I was going
[3:00]
to say if they did that that's really
[3:02]
against the law because
[3:04]
>> we did we just went up there and checked
[3:06]
it. He pulled the that big cover off and
[3:10]
it was stopped right there. And when
[3:13]
they came down with that that shoot,
[3:16]
then it come running rushing down and
[3:18]
then it went right into my basement.
[3:22]
Okay. So, um, Dallas, you brought me
[3:26]
some pictures. I I got to see all the
[3:27]
pictures. They did the report and the
[3:30]
report showed all these rags. Um,
[3:33]
>> rags.
[3:34]
rags like they look like mechanic
[3:37]
rags or whatever they were.
[3:39]
>> No, it's it's more like um paper towels,
[3:42]
toilet paper, flushable wipes
[3:45]
and then that mixes with just your
[3:47]
typical sewer grit and organics and it
[3:50]
just turns into a a black paste.
[3:52]
>> Okay. So, do we have So, when we talked,
[3:56]
you never did really you told me kind of
[3:58]
a number. Do you know do you know what a
[4:00]
number is to make you whole? was
[4:04]
>> what was this going on just to to take
[4:07]
that stuff off the toilet?
[4:10]
>> But I mean,
[4:11]
>> but what I'm trying to say is they cut
[4:13]
your walls, right? They cut your walls
[4:14]
because you had you had sewage and
[4:16]
everything. Did they give you Have you
[4:18]
had anybody give you a bid on Cuz when
[4:21]
you talked to me, you told me it'd be
[4:22]
about $20,000.
[4:25]
>> This one is
[4:29]
gel.
[4:31]
A what?
[4:32]
>> He gave it to the glass filter. Is that
[4:34]
>> And then your uh the water company came
[4:37]
down and give us a bid over the phone
[4:42]
just to put it back together. It was
[4:44]
like 15.
[4:47]
>> Okay. Now, Mr. Chairman, I've got I've
[4:49]
got those numbers handy if you want me
[4:50]
to.
[4:51]
>> Will you please?
[4:52]
>> Sure. So, the mitigation and the cleanup
[4:55]
was $18,245.75.
[5:00]
And then the restoration and the repair
[5:02]
to put it all back together was an
[5:04]
additional $16,28043.
[5:09]
» Okay.
[5:09]
>> So, is that combined?
[5:11]
>> It would be total. So, add those
[5:14]
together.
[5:14]
>> Okay.
[5:15]
>> Holy cow.
[5:19]
» You're roughly 35.
[5:21]
>> I did. Yeah, I was the one $35,000.
[5:24]
>> I was the one that was there that that
[5:25]
day.
[5:27]
>> Mhm.
[5:28]
>> You just had come home from work.
[5:29]
>> So $35,000, right?
[5:31]
>> Roughly.
[5:31]
$35,000.
[5:35]
>> So I think the important thing some
[5:38]
things to consider for the board, we
[5:40]
certainly sympathize with your
[5:42]
situation. Um we know that uh that's
[5:46]
upsetting and no one wants to be dealing
[5:49]
with that issue. Um, I do believe that
[5:52]
we've handled it how we should handle
[5:55]
those situations with coming out trying
[5:58]
to assess what has caused the backup.
[6:03]
And I think that's where we may differ
[6:05]
with your assessment
[6:08]
um is we don't believe that it was
[6:10]
caused by something in the main
[6:13]
originally. Right, Dallas?
[6:16]
>> Right. Um, we believe it was associated
[6:19]
with your lateral
[6:21]
>> and that's
[6:22]
>> and I pushed all that in the
[6:23]
>> Well, that's
[6:25]
>> Are you trying to tell me I
[6:27]
>> no up the sewer line?
[6:29]
>> The issue from what Can you describe
[6:32]
what you found so that the board and Mr.
[6:35]
Martinez can
[6:35]
>> Yeah, I think the important thing to
[6:37]
recognize here is
[6:38]
>> Yeah,
[6:39]
>> we can pull up the pictures too on the
[6:41]
screen.
[6:41]
>> Yeah, let's pull the pictures up,
[6:42]
please.
[6:42]
>> So, Mr. Martinez's house sits two or
[6:46]
three homes.
[6:47]
>> I know exactly where it sits on the
[6:49]
corner.
[6:49]
>> Yep. And that's brick. That's upstream
[6:51]
of the manhole that had the debris in
[6:53]
it. So, you know, no issues at the the
[6:56]
neighbor, no issues at the other
[6:58]
neighbor, no issues across the street.
[7:01]
Um the the the debris that we saw
[7:05]
collecting them.
[7:06]
>> Just to clarify, when you say no issues,
[7:08]
how did you verify that there were no
[7:10]
issues? uh made contact with each of the
[7:12]
customers by knocking on their door.
[7:15]
>> So none of the surrounding homes had any
[7:17]
of the same issues.
[7:19]
>> Does that make sense that
[7:20]
>> Well, it does, but the question I have
[7:22]
here is so if they don't have any they they didn't have an issue, could
[7:27]
that stuff came down and could that came
[7:30]
down through and and brought the
[7:32]
blockage?
[7:33]
The way the way that I perceived it
[7:36]
based on our experience and what we were
[7:37]
troubleshooting that day was the same
[7:40]
type of stuff that the plumber was
[7:42]
pulling out of the floor drain and
[7:44]
pushing through the lateral is the same
[7:46]
stuff that we saw downstream
[7:48]
accumulating in the manhole.
[7:51]
So it's not that um when Mr. Martinez
[7:55]
said they went upstream and saw the
[7:58]
blockage and then we vacuumed it out and
[8:00]
it all rushed down to his lateral. It
[8:03]
was all below his lateral originally. So
[8:06]
it was never upstream of it.
[8:11]
» So do you have a picture of that?
[8:19]
» So this is the this is looking down in
[8:21]
the manhole. That's
[8:23]
>> not on the street. Correct.
[8:25]
>> Correct. Out on the street, two or three
[8:27]
doors down from the corner of Tommy's
[8:29]
home. And you can see that's just black
[8:33]
and brown mush, um, toilet paper, paper
[8:37]
towel, flushable wipes, anything that
[8:40]
you would put down your sink tub or
[8:42]
toilet. And then as that stuff compacts
[8:45]
together in the lateral and the
[8:48]
mechanical snake that the plumber's
[8:50]
using to push it all, once he gets that
[8:52]
to go, then it all rushes out to the
[8:54]
main and we get kind of that surge flow.
[8:57]
Um,
[8:58]
>> so it's in a big surge going through.
[9:00]
>> Correct.
[9:01]
>> Okay.
[9:02]
>> And then that's when their home starts
[9:03]
draining. Um, we never lost flow in the
[9:06]
manhole. There's still a quite a bit of
[9:08]
flow going through there even if it
[9:10]
doesn't look like it. But if we go to
[9:12]
the other pictures, you can see that
[9:15]
that's similar
[9:18]
makeup and and material type of what
[9:22]
they're seeing on the floor and piled up
[9:24]
there that they're pulling out of the
[9:25]
drains.
[9:33]
So, and if you can picture just a a
[9:36]
plugged lateral that's 4 in and it's
[9:38]
jam-packed with debris. and they're
[9:40]
rotting that with a mechanical snake.
[9:43]
You know, you can punch a little hole
[9:45]
and that's when it'll start draining.
[9:46]
And they did that the first day. They
[9:48]
got him draining and he had to call him
[9:49]
back out the next day. The next day he
[9:52]
stopped draining and they worked on it
[9:54]
for several more hours and that's when
[9:56]
they eventually made contact with the
[9:58]
district.
[9:59]
>> I thought we had a picture with some
[10:01]
stuff on the floor there. It's just it's
[10:04]
real hard to tell, but right in front of
[10:06]
that snake machine, um you can see the
[10:09]
pile of stuff that they're pulling out
[10:10]
of the
[10:13]
>> floor drain.
[10:17]
» I don't know.
[10:21]
» Oh, yeah.
[10:22]
>> We had to go to my kids's house to sleep
[10:26]
because of
[10:27]
>> Well, I know. I'm just looking at think
[10:29]
what a mess. I I just don't know how
[10:31]
that those rags and stuff would go up a
[10:33]
4 inch lateral from the main. I I don't
[10:36]
see how that would
[10:37]
>> right. They wouldn't.
[10:39]
>> So So that's the challenge. Um well, I
[10:42]
I'm going to make I'm going to make an
[10:44]
recommendation to the board. Okay.
[10:45]
>> And you guys can go sideways. I mean, go
[10:47]
whatever way you guys want. I recommend
[10:49]
pay the $35,000. Let's let's make him
[10:52]
whole. Let's put a policy together
[10:54]
because we don't Our policies change all
[10:56]
the time. We one time we do this, one
[10:58]
time we do this. My recommendation, give
[11:01]
him the $35,000. Let's make him whole
[11:04]
and then let's us the district get a
[11:06]
policy in place and let's make sure the
[11:08]
policy and give it to legal counsel so
[11:10]
he can review it and we can go from
[11:12]
there. So that I don't know if I could
[11:15]
Can that be a motion, Nathan?
[11:17]
>> It certainly could.
[11:19]
>> That that is my motion.
[11:20]
>> Well, I'm recommending though you've
[11:22]
only got we've only you've only seen one
[11:24]
bid for fixing What's been
[11:28]
>> we went with the cheapest that you know
[11:30]
we
[11:31]
>> How many bids did you get?
[11:34]
>> They told us just to get you guys were b
[11:37]
they sent their people over our house.
[11:41]
>> Who is it that we used? Alice, who is it
[11:43]
we used? It was um
[11:46]
>> Is that the quotes from our insurance?
[11:49]
>> It is. Yes.
[11:49]
>> So that's the underwriter quotes. We
[11:51]
don't have any quotes from a contractor
[11:53]
or anything. That's just from our
[11:54]
instructor. So, you've got to get quotes
[11:56]
from a contractor.
[11:57]
>> So, my recommendation is go out, have
[12:00]
them come out because apparently this is
[12:01]
from our insurance company.
[12:03]
>> I already fixed it. I mean,
[12:05]
>> no, the
[12:05]
>> I couldn't I couldn't wait for you. The
[12:08]
insurance
[12:08]
>> So, do you have do you have receipts of
[12:10]
everything that you've done? If you want
[12:12]
to give
[12:12]
>> about the same
[12:14]
>> if you want to if you want to produce
[12:15]
every every receipt to the to the city I
[12:18]
mean to the to the water district and
[12:22]
that I I myself I don't have a problem
[12:24]
paying it
[12:26]
>> if you have all the receipts but we as
[12:29]
taxpayers as you are and I am and us
[12:31]
here we can't we can't just write you a
[12:34]
check without just you know throwing you
[12:36]
a check out say here you go we need we
[12:39]
need all the receipts to everything that
[12:40]
you've on down there to make you whole.
[12:46]
>> And if you've went over if you went over
[12:48]
on to make things nicer, we can't fund
[12:51]
that either. Just But we can fund I'm
[12:53]
willing to fund I'm willing to fund
[12:57]
>> the 35.
[12:59]
>> Well, if we have the if we have the
[13:01]
receipts.
[13:01]
>> Okay.
[13:02]
>> I can't I I'd get in trouble if I said,
[13:04]
"Here, Leon, go give me a check. Prefer
[13:07]
$35,000."
[13:08]
I can't do that.
[13:10]
How come your insurance company never
[13:12]
covered any of it?
[13:13]
>> Uh they were going to they told us to
[13:15]
come up and talk to them today. We told
[13:18]
them we're going to meet with you guys.
[13:20]
So they were going to come out to you
[13:22]
guys
[13:25]
if they didn't hear anything good from
[13:27]
you guys.
[13:30]
>> So do we want their insurance to come
[13:32]
after us? I mean what do you what's your
[13:34]
recommendation? Typically the two
[13:35]
insurance companies will work together
[13:37]
and find it out. I
[13:38]
>> And then who did you talk to today about
[13:40]
the another person
[13:43]
>> just the state insurance?
[13:45]
>> Okay.
[13:45]
>> So So my suggestion I mean the standard
[13:47]
process is it sounds like there's a a
[13:49]
question as to what's the cause. So
[13:52]
typically we've we've already reported
[13:53]
this to our insurance company.
[13:55]
>> Correct. And they've made they've made a
[13:57]
finding that it was no fault of the
[13:59]
district.
[14:00]
>> So our insurance company's made that
[14:01]
finding. your So my suggestion is before
[14:04]
we go further, have the two insurance
[14:06]
companies talk to each other because
[14:07]
that's usually the standard process.
[14:09]
>> Yeah. And my understanding is your
[14:11]
insurance company found it was no fault
[14:13]
as well
[14:14]
>> to us.
[14:15]
>> Well, to the district
[14:17]
>> and so which case they their insurance
[14:19]
company should pay for it depending on
[14:21]
the terms of their coverage.
[14:22]
>> Right.
[14:23]
>> And so that's that's maybe the question
[14:24]
I have legally. That's our challenge
[14:26]
>> is is the way that this should work is
[14:27]
if it's the district's fault, the
[14:29]
district's insurance should cover it or
[14:31]
you know we pay for it some other way
[14:32]
but if it's the homeowner's fault or if
[14:34]
not your fault but if it's not the
[14:36]
district's that it should be covered
[14:37]
under your insurance policy,
[14:39]
>> right?
[14:40]
>> Insurance should help him.
[14:41]
>> Yeah. So that's and so and the
[14:43]
difference the difference I just for the
[14:46]
board the reason my understanding the
[14:49]
reason that the board has participated
[14:51]
in the past is because when it's not
[14:56]
when it's found no fault but it is in
[14:59]
the main and there's no way to determine
[15:03]
it was a homeowner right
[15:05]
>> it was something that we didn't know
[15:07]
about it wasn't due to improper
[15:09]
maintenance it wasn't doesn't do the
[15:12]
district's done everything in the past
[15:14]
when that's happened and it's affected
[15:15]
multiple homeowners.
[15:17]
>> There have been instances when the board
[15:19]
has held them,
[15:20]
>> right? But I'm going to I'm going to
[15:22]
step out of the lane right now.
[15:24]
Insurance is the biggest fraudulent
[15:25]
thing out there. They turn around and
[15:27]
you pay insurance and pay insurance and
[15:29]
they're going to pick and choose what
[15:30]
they're going to pay. I I just seen this
[15:32]
happen to a friend of mine here about
[15:34]
two weeks ago on an incident and he's
[15:36]
been with his insurance company for 40
[15:38]
plus years and they denied him and and
[15:41]
so my recommendation is have the two
[15:43]
insurance ours and his they're his
[15:45]
insurance work together let's come up
[15:47]
and like you said if you can produce all
[15:49]
the receipts of all the stuff that
[15:51]
you've done then I don't have a problem
[15:54]
moving forward but again I'm only I'm
[15:56]
the chair but these guys are
[15:59]
>> so I agree with that
[16:00]
>> Mick can I maybe motion then
[16:03]
>> I I because what I'm hearing you're
[16:04]
saying and this is my suggestion too is
[16:06]
I agree with you completely. I used to
[16:08]
sue insurance companies, but that said,
[16:10]
we haven't it doesn't sound like this
[16:11]
process is completed,
[16:12]
>> right?
[16:12]
>> So before because there's a chance
[16:15]
they're if they both are on the same
[16:17]
page, then it's a chance that their
[16:19]
insurance company would say, "Yeah,
[16:20]
we'll pay for it, right?"
[16:21]
>> In which case, there's no need for us to
[16:23]
go through it. But if if it ends up
[16:25]
being denied and they're left out in the
[16:26]
cold, then that's when we could have
[16:28]
maybe a further discussion. Okay.
[16:29]
>> It just sounds like maybe we're a little
[16:30]
premature at this point.
[16:32]
>> Okay. I had thought when I heard about
[16:34]
this that the insurance that had already
[16:36]
been denied, but you haven't been denied
[16:37]
yet. My understanding is
[16:39]
>> agree with a lot of stuff and I got to I
[16:41]
can't live like that.
[16:42]
>> No, absolutely not.
[16:44]
>> I had to I can't put my family in
[16:47]
something like that. No,
[16:48]
>> I won't do it
[16:49]
>> for for sure. But
[16:50]
>> I fixed it myself.
[16:51]
>> So, you fixed it yourself, but your
[16:52]
insurance company hasn't denied the
[16:54]
claim?
[16:54]
>> No.
[16:55]
>> Okay. So, that hasn't happened yet.
[16:57]
So
[16:58]
>> they they did too deny it because I got the they did they did deny it
[17:02]
because I got I got the letter. It's
[17:04]
been denied.
[17:04]
>> Okay. But so they denied it, but has
[17:07]
there have they talked with our
[17:08]
insurance company yet?
[17:10]
>> Yeah.
[17:11]
>> Okay. They need to do that.
[17:13]
>> Yeah. So I I mean I typically I'm not
[17:16]
>> Can you give Can you give them the name
[17:17]
of our insurance company so when they
[17:18]
leave here today they have the numbers
[17:20]
that your insurance can come so we're
[17:22]
not going back and forth and all that?
[17:25]
>> Dr.
[17:26]
Yep.
[17:28]
>> But like I said, if you two can work it
[17:30]
out and then whatever we have to do on
[17:32]
our end, I'm willing to do this. But my
[17:34]
deal is we need to have a policy in
[17:36]
place that actually stricts and stands
[17:39]
for where we're at. Cuz as I read our
[17:42]
policy, it's not really I mean it's kind
[17:44]
of here here.
[17:46]
>> Yeah.
[17:46]
>> And we need to have we need to look at
[17:48]
our policy and look have legal counsel
[17:50]
re review it and then take it from there
[17:53]
if you guys are okay with that.
[17:54]
>> Yeah. I think that's a good approach.
[17:57]
Um, it's setting aside what that policy
[18:00]
does is it puts money that we would set
[18:04]
aside in the account rather than in the
[18:06]
reserve funds. it goes to a separate
[18:10]
account that's just set aside for
[18:12]
situations
[18:14]
um where the district feels like, hey,
[18:17]
it wasn't our fault, but we'll
[18:20]
participate because maybe there's some
[18:22]
>> Well, and I keep going back I keep going
[18:24]
back to the 7200 deal when we had that
[18:26]
backup that flooded all them homes and
[18:29]
it cost the district a lot of money. And
[18:32]
I I feel like on our end, we could have
[18:35]
probably did things a little bit
[18:36]
different, but you know what? We need to
[18:38]
get a policy in place that's actually
[18:40]
going to be broad. So when something
[18:42]
like this comes, it's either yes or no,
[18:44]
and there's no gray in between.
[18:46]
>> So just for my benefit, why did your
[18:48]
insurance carrier deny your claim?
[18:51]
>> Because these guys said they're going to
[18:53]
pay for everything and they said the
[18:56]
plumber said was was the backup backup
[19:00]
there. So, so your plumber said that it
[19:03]
said it was the district's fault, but
[19:06]
Clint, I thought you said that their
[19:07]
carrier determined that it
[19:08]
>> Yeah, they determined that it was no
[19:10]
fault.
[19:10]
>> I did not.
[19:12]
>> Sure.
[19:14]
>> The letter The letter that I saw that
[19:17]
was mailed to
[19:21]
» Mick
[19:22]
was from our insurance, wasn't it?
[19:24]
>> Yeah. Yeah. There's
[19:26]
>> Have they really been denied?
[19:27]
>> Yeah. What? No, they have they don't we
[19:30]
don't use Kleinfeld. What's it's
[19:32]
Kleinfelter that you've been working
[19:33]
for, right?
[19:34]
>> Your insurance company.
[19:35]
>> Glad filter.
[19:37]
>> Cloud filter. That's your insurance,
[19:39]
right?
[19:40]
>> Yeah.
[19:44]
» Is that what the
[19:45]
>> Clint
[19:48]
filters through? Oh, okay.
[19:54]
» Okay. So, has your
[19:58]
Okay. That's through Oh, this is this is
[20:00]
your insurance through our
[20:02]
>> Olympus. Yes.
[20:03]
>> So, so this is from
[20:04]
>> This is from us from us. Lad Filter
[20:06]
represents us through Olympus.
[20:08]
>> That's right.
[20:08]
>> Yes. So, so you're is Is this what
[20:10]
you're referring to as your insurance?
[20:12]
Okay. So, this is our insurance company.
[20:13]
>> That's right.
[20:14]
>> Have you received anything from your
[20:15]
insurance company?
[20:29]
Okay. Yeah, they're saying that they
[20:31]
initially found it was on the city side,
[20:34]
but it was not from our determination.
[20:37]
>> So, there's a conflict between the two.
[20:39]
Okay. So, so when that happens,
[20:41]
typically the insurance companies need
[20:42]
at that point to confer with each other,
[20:44]
>> right?
[20:45]
>> And then
[20:47]
>> Oh, that'll be good.
[20:49]
>> That's what I said. What are we paying
[20:50]
the insurance for? They ain't covering
[20:53]
anything.
[20:54]
>> Well, that's you know, just like
[20:56]
California and those houses were they're
[20:59]
going out of business. I mean, that's
[21:01]
wrong.
[21:03]
>> Yeah, it is.
[21:04]
>> Trust me. I think about that every day.
[21:05]
I think if I have
[21:06]
>> if I have something happen to my house,
[21:08]
are they going to cover it?
[21:10]
>> It's like they pick and choose who they
[21:11]
want to cover.
[21:13]
>> Yeah. I would say we do both. I say we
[21:15]
instruct these people to call. Can we
[21:16]
make a copy of this? Because what what I
[21:19]
would suggest is that we have we
[21:21]
instruct our guys to contact their guys
[21:24]
and vice versa
[21:25]
>> because I'm not I I think the issue is
[21:29]
to our knowledge did these guys do an
[21:31]
independent investigation
[21:33]
>> or do they just base it off what your
[21:34]
plumber said?
[21:36]
>> You guys did they're the only ones.
[21:38]
>> Yeah, you guys did an independent
[21:39]
investigation. But has your insurance
[21:41]
carrier seen the results of their
[21:42]
investigation?
[21:43]
>> Our insurance come in?
[21:44]
>> No.
[21:45]
>> So they're just going off of what your
[21:47]
plumber said? Yeah.
[21:48]
>> Okay. So, that I think is the problem is
[21:50]
your plumber didn't have the ability to
[21:52]
do the investigation that they did and
[21:54]
your plumber determined that it was
[21:56]
likely on the city main side. And so,
[21:59]
these guys probably just went off of
[22:01]
that and they are denying you based on
[22:04]
in my opinion an incorrect assumption
[22:06]
because they're saying, "Well, you're
[22:07]
what?" They're denying you because
[22:09]
they're saying, "Well, that our policy
[22:11]
doesn't cover the city's system and
[22:13]
therefore you're uninsured. go after the
[22:15]
city or or in this case the district,
[22:17]
but I'm and I don't have your policy,
[22:19]
but I'm willing to assume that it does
[22:21]
cover stuff that's in the lateral. So,
[22:23]
if they're instructed that it is in the
[22:25]
lateral and our guys can give them the
[22:26]
information, hopefully that So, this is
[22:28]
typically how this process should work.
[22:30]
So, it sounds like there's a next step
[22:32]
that hasn't happened yet. So, in my
[22:34]
opinion, it's it's make we can totally
[22:37]
do what you want to do, but I I say
[22:38]
before you spend tax,
[22:39]
>> I agree with you. I I want like I said,
[22:40]
I want to keep us out of trouble. I want
[22:42]
to do the right thing. If we haven't
[22:43]
went and made the whole got it all done,
[22:46]
we need to put the puzzle fully together
[22:48]
and
[22:49]
>> but if their insurance company is on the
[22:51]
hook for this and they've been paying
[22:52]
for that insurance, they're entitled to
[22:54]
it. So, let's work together to make
[22:55]
their insurance pay for it.
[22:57]
>> Yep.
[22:58]
>> And then if that's not possible, then we
[23:00]
can come back and have this discussion.
[23:02]
Does that sound fair?
[23:04]
>> Are you guys okay with that?
[23:05]
>> Yeah.
[23:08]
because I it sounds like your insurance
[23:10]
company's operating off of just that initial fact sheet. They haven't
[23:13]
talked with ours. They haven't seen the
[23:15]
investigations we've done. And hopefully
[23:17]
if they do, that will bring in a
[23:19]
different section of your homeowner's
[23:20]
policy that typically covers this type
[23:22]
of thing. Now, I don't know what your
[23:23]
policy says, but that's what the
[23:26]
insurance company should work out.
[23:27]
>> Yeah. You guys are willing to come in
[23:29]
and take a look, but we did. I mean, we
[23:33]
>> Yeah, but that that should really be
[23:35]
your insurance company, right? and and
[23:37]
it doesn't sound like they have come in
[23:39]
and they they just saw that said it's
[23:41]
not our fault. Deal with somebody else.
[23:44]
>> Um and are trying to wash their hands of
[23:46]
it.
[23:50]
» Yeah, cuz like you like you say, you
[23:52]
just
[23:53]
>> Oh, I can imagine. I mean,
[23:56]
>> we've dealt with quite a bit of this
[23:58]
stuff over when we had an issue and
[24:00]
>> I was mad cuz I yelled at him. I said,
[24:02]
"I want your ass over here and get this
[24:05]
thing cleaned up. This is my house. And
[24:08]
I said, I won't bring nobody in here. I
[24:11]
didn't even want to go downstairs.
[24:14]
>> They came over. I says, "Hey,
[24:16]
>> just get just get it done. I don't care.
[24:19]
I mean, and they said, "Get the
[24:24]
what is it? The disaster thing."
[24:27]
>> Was that disaster cleanup is what we
[24:29]
used? Yeah,
[24:30]
>> we we don't make a specific
[24:32]
recommendation, but we do recommend
[24:34]
calling somebody like that with a
[24:36]
disaster.
[24:36]
>> Do we have do we have a list of of
[24:38]
people on that list that we could give
[24:40]
our people when we have this? So,
[24:42]
>> we do.
[24:43]
>> Okay. So, we do give that to them.
[24:45]
>> We just we do, but we say you can use
[24:47]
whoever you want.
[24:48]
>> Right. Right. Right. Right. You can't
[24:49]
say use me.
[24:50]
>> Looks like true restore was used.
[24:53]
>> Okay.
[24:54]
>> Is that correct?
[24:55]
>> True restore did the work. Yeah.
[24:58]
>> So, Nathan, really fast, you want where
[25:01]
do we where do we proceed from this?
[25:03]
>> So, what I'm what I'm recommending is we
[25:05]
contact our insurer. We explain the
[25:08]
situation in greater detail. We send
[25:10]
them a copy of this letter and we say
[25:12]
here's the issue is we have done an
[25:14]
investigation and determined that it
[25:16]
wasn't in the main and it was something
[25:17]
in the lateral. American Family
[25:20]
Insurance has determined that it it was
[25:22]
in our system which we've shown that
[25:24]
it's not. And so as a result, American
[25:26]
Family Insurance is incorrectly denying
[25:28]
the claim on an improper basis. And
[25:31]
therefore, please work with them to
[25:33]
figure this out and then report back.
[25:35]
Then you guys can do the same. Um, and
[25:39]
so that way now I'm not going to
[25:42]
guarantee that the insurance company's
[25:44]
going to agree, right? And that's but by
[25:46]
that point, maybe we can have the policy
[25:47]
adopted and so, you know, we'll be um
[25:51]
dealt with in that way. But like I think
[25:54]
so what they're excluding is
[26:10]
yeah storm drainer water seam or sewer
[26:13]
pipe off the resident premises. So
[26:15]
that's what they're denying you on is
[26:16]
they're saying it was off the premises.
[26:18]
That's where the blockage occurred.
[26:20]
That's not what we covered. But if
[26:22]
they're showing it's on the premises
[26:24]
that this should not apply. Their denial
[26:26]
would be inaccurate. So does that make
[26:28]
sense?
[26:29]
>> So we'll contact our guys and tell them
[26:31]
to work on this. Explain it. I do the
[26:33]
same.
[26:35]
>> No. No.
[26:36]
>> Are these ours?
[26:37]
>> Oh, did we give them back their copies
[26:39]
already? Okay. All right.
[26:42]
>> Is that fair?
[26:43]
>> Yeah.
[26:43]
>> Okay.
[26:47]
>> Appreciate you.
[26:48]
>> Thank you.
[26:49]
Tommy.
[26:52]
Okay, let's move on to our employees.
[26:56]
Okay, thanks board chair. Uh, first we
[27:00]
got just we had three our three newest
[27:03]
employees attend Flagger certification
[27:05]
course. Gavin Ferguson, D Honey, and
[27:09]
Taylor Warner. Um, this is a good step
[27:12]
for them as we get new employees. This
[27:14]
is one of the first things we like to
[27:15]
get them certified in so that they can
[27:19]
be a good part of uh traffic control
[27:23]
when we're doing some repairs. Um helps
[27:27]
keep us safe and so we're glad that they
[27:29]
were able to get that done. And then
[27:31]
next we have Dylan Delbell. Uh he's here
[27:35]
with us today. Uh what we brought him in
[27:39]
for is a couple months ago we were
[27:42]
looking at possibly making some changes
[27:45]
to our health and wellness program to
[27:47]
see if we could uh boost the
[27:51]
uh
[27:53]
employee
[27:56]
enrollment in it. Get them to buy in a
[27:59]
little bit better. And so at that point
[28:01]
>> say when you say buy in, explain to me
[28:03]
what you mean by that. that we were
[28:05]
going to be doing things that they that
[28:07]
they wanted to participate in better. We
[28:09]
had the same employees doing it every
[28:11]
month, which was probably I'd say around
[28:15]
24 of the 35 were participating all the
[28:19]
time.
[28:19]
>> So when you Okay, I'm lost. So when you
[28:22]
say 30 participating in what
[28:25]
>> we do,
[28:26]
>> is it something that we as the board
[28:27]
don't know about? No, we you've you've
[28:30]
approved it in the past.
[28:31]
>> But what
[28:32]
>> if we do monthly challenges where we
[28:36]
encourage them to do things like
[28:38]
exercise,
[28:40]
uh healthy healthy eating. Um
[28:44]
>> well, where do I where do I sign up for
[28:46]
that?
[28:47]
>> We'll we'll get we'll get you in.
[28:49]
>> And so we do mental health months, we do
[28:52]
>> I need that, too. So
[28:53]
>> we do financial health months. We do a
[28:55]
lot of things with it to try and help
[28:57]
the employees better their their health
[29:01]
and wellness.
[29:02]
>> And I love that. That's a great idea. In
[29:03]
fact, now, okay, it's all I'm trying to
[29:06]
put everything. Okay. Yes. And so
[29:09]
when we decided that we were going to
[29:11]
change the program a little bit, we went
[29:13]
to the employees and we asked them if
[29:16]
there was any ideas that they could come
[29:18]
up with that would make them want to be
[29:21]
more involved as well as help the people
[29:24]
that if they're already doing it, help
[29:25]
the other people get involved. And to
[29:28]
Dylan's credit, he was not only the
[29:30]
first, he was the only one that stepped
[29:31]
up and he came with a lot of good ideas.
[29:34]
>> Great. Um, probably the best the best of
[29:36]
it was not only did he come with a
[29:38]
solution with some some program ideas,
[29:41]
but he also came with the idea of, hey,
[29:43]
let's build a a health and wellness
[29:45]
committee like we have with some of the
[29:47]
other things. We get a person on each
[29:49]
crew that will help drive their crews in
[29:52]
reminding them to participate in these
[29:54]
initiatives. And so, uh, with Dylan's
[29:59]
help, we're making that committee. And
[30:01]
we're just grateful when, uh, employees
[30:04]
take the the role of improving our
[30:08]
culture. And so, thank you, Dylan. We
[30:12]
got to get
[30:13]
>> presenting with a little something from
[30:15]
>> He needs to be in the little back of my
[30:18]
head. The voice in the voice is in my
[30:20]
head. You need to be in there.
[30:22]
>> Do you have anything to add, Dallas?
[30:24]
>> Dylan.
[30:24]
>> Yeah.
[30:25]
appreciate that.
[30:28]
>> Thank you.
[30:29]
>> I would just say Dylan's a huge part of
[30:31]
why morale at the treatment plan is so
[30:34]
big. Um I think the cool thing about
[30:37]
Dylan is he recognizes how hard the
[30:39]
board has worked to try to increase
[30:40]
morale over the last several years. Um
[30:44]
and the board can do so much to increase
[30:46]
the morale, but it's up to all of us to
[30:49]
maintain that morale. Um, so for Dylan
[30:51]
to be able to see the whole picture and
[30:53]
see all the moving parts, um, it's just a testament to how hard he
[30:58]
works and and how much he likes the
[31:00]
district and his role. Um, and we
[31:02]
appreciate the mutual respect and it it
[31:05]
just says a lot about who you are and
[31:07]
where you're going. So, thank you very
[31:08]
much.
[31:09]
>> Great.
[31:09]
>> Thanks, D. And I'm and I'm really
[31:11]
impressed because like I said when I
[31:12]
come down tour the sewer plant you know
[31:14]
just you guys are all big great you know
[31:16]
like a big family and you guys work
[31:18]
really all work really good together and
[31:20]
if there's any issues you guys figure it
[31:21]
out and I'm I've always I've always said
[31:24]
this when I come down there I'm just
[31:26]
amazed how you guys all work together
[31:28]
and that's you don't see that much
[31:29]
anymore.
[31:30]
>> It's good to see a positive person for a
[31:32]
change you know.
[31:34]
>> Thank you.
[31:35]
I've been working on.
[31:43]
» Okay. Thank you, Andrew. So, let's move
[31:46]
on to our our common consent items.
[31:50]
>> Minutes of the regular board meeting
[31:51]
held February 12th, 2026. Minutes of the
[31:55]
public hearing held February 19th, 2026.
[32:00]
Expenses from February uh 2nd to March
[32:03]
1st, 2026. General expenses 1,639,951.85
[32:12]
size bank pal payment $83,53083.
[32:18]
» I'll second it.
[32:19]
>> Motion second. All in favor?
[32:21]
>> I I
[32:24]
Okay, Clint, let's move on to your
[32:25]
general general manage report.
[32:27]
>> Thanks, Mr. Chairman. on staffing. Just
[32:31]
uh highlight a couple things on the
[32:33]
water operations, the construction crew.
[32:36]
We had that service maintenance position
[32:38]
open. Uh we've went through some
[32:41]
selection and uh we've made an offer and
[32:44]
he's accepted. So that position will
[32:46]
start 23rd
[32:48]
>> on the 23rd. October 23 or March 23rd.
[32:51]
>> March 12th. Be a long wait.
[32:54]
>> Six. Wrong season.
[32:55]
>> Yeah.
[32:56]
>> Who is it?
[32:57]
>> Uh Daniel Klein. Daniel.
[32:59]
>> Yep.
[33:00]
>> Daniel
[33:02]
>> came recommended uh several people in
[33:06]
the district. He's from the area.
[33:07]
>> From the area. He's been doing cabinetry
[33:09]
for a while.
[33:12]
>> Well, he's got two weeks. He can get us
[33:13]
some cabinets.
[33:15]
>> That That must be a tough job. That must
[33:17]
be really relentless.
[33:19]
>> And And I just wondered, do we have any
[33:21]
recourse on people to come and treat our
[33:23]
customer service people bad? Oh, on the
[33:27]
Well, obviously with customers, we're
[33:32]
trying to understand what they're coming
[33:34]
in so frustrated and angry about.
[33:39]
So, we have systems in place to try to
[33:42]
diffuse those interactions.
[33:45]
>> Can you share them with me?
[33:47]
>> The first one is is uh Oh, hey, I can
[33:50]
see you're upset. Let me have you talk
[33:52]
to my supervisor. Right. And just that
[33:55]
initial,
[33:57]
we call it stall and call someone
[34:01]
>> that usually brings the temperature down
[34:04]
just by going through that act.
[34:06]
>> Um because it brings the customer now
[34:09]
recognizes oo I've been I'm I'm my
[34:12]
emotional level is enough. I can tell
[34:15]
this person wants to pass me on to
[34:19]
someone else. Right? So that's the first
[34:21]
step. That's usually pretty effective,
[34:24]
but it's still discouraging. I mean,
[34:27]
there's a downside to that in that the
[34:29]
customer or the employee feels like they
[34:33]
can't address the issue, right? And
[34:36]
that's certainly an option for them, but
[34:39]
we also don't want to subject them to
[34:41]
unnecessary
[34:42]
>> taking a toll on our employees though.
[34:44]
This is the second employee we've had
[34:45]
that's turned it down.
[34:47]
>> Yeah,
[34:47]
>> it's a tough role. So, what can we do to
[34:49]
improve that? Do we need to send letters
[34:52]
out to our customers to say
[34:54]
>> I don't we could I don't know that that
[34:57]
would
[34:59]
>> it's going to it's going to reach the
[35:01]
people that we don't need to reach in my
[35:03]
>> well and and and right now let's just
[35:05]
say we're in a really ugly place right
[35:08]
now in this in this country and I'm just
[35:10]
going to say as me as the mayor of the
[35:12]
town I deal with this every day. Nathan
[35:14]
knows what I go through. uh he because
[35:16]
he's our legal counsel and it's ugly and
[35:19]
you know and you try sometimes you just
[35:21]
you want you if they're wrong you can't
[35:24]
just say agree because then they figure
[35:25]
you you're on their side but you say hey
[35:27]
I understand I understand but that still
[35:29]
ain't good enough people get really mean
[35:31]
and nasty I mean and and and like you
[35:34]
say I understand your point but I
[35:36]
understand I like what Clint does is I
[35:38]
wish I had some say oh by the way here
[35:40]
let me hand this over to somebody else
[35:41]
well I'm the the buck stop this buck
[35:44]
stops at me Right. So I just but I like
[35:47]
that. I mean you know
[35:49]
>> it does seem to be effective in a lot of
[35:51]
cases
[35:52]
>> but like I said
[35:53]
>> but if it reaches if the customer
[35:55]
becomes belligerent and name calling and
[35:57]
personal attacks we have direct we have
[36:00]
directed them to say hey I'd love to
[36:02]
help you but I can't help you if you're
[36:04]
going to call me names.
[36:06]
>> I got to let you go into Cape that's
[36:08]
professional. Give us a call back when
[36:09]
you are able. So they
[36:12]
>> mostly phone or in person?
[36:15]
>> Phone.
[36:17]
>> A lot of people say a lot of things over
[36:19]
the phone that they won't say to you
[36:20]
face to face. Right.
[36:21]
>> Okay.
[36:22]
>> I think we try to do is we have a daily
[36:26]
check-in meeting in the morning. We try
[36:28]
to talk about those things. Uh we try to
[36:31]
have a sense of humor about it if we
[36:33]
can. Um we try to talk through
[36:36]
strategies. we work on mental health and really trying to and Lyle has done a
[36:43]
great job with the team. Um I think it's
[36:47]
one of those unfortunate circumstances.
[36:50]
There's probably more uh going on. It
[36:54]
sounds like there's some interest in
[36:56]
going back to school. Um so
[36:59]
>> how long has she been with us? Three
[37:00]
months?
[37:01]
>> No.
[37:01]
>> Uh probably six.
[37:03]
>> Six months.
[37:04]
>> And she started in June. I really like
[37:07]
her a lot. She's got a great personality
[37:09]
and she was able to deal
[37:10]
>> a lot to the office.
[37:12]
>> She was a sweetheart.
[37:14]
>> Yeah.
[37:14]
>> Okay.
[37:15]
>> You know, but I understand that with
[37:16]
this incident that we had up here on
[37:18]
4100, I got called a a death mayor, you
[37:21]
know, like everything falls onto me.
[37:24]
>> Awful.
[37:26]
>> But we'll continue to look. I think it's
[37:29]
always good to look at things that we
[37:31]
can do.
[37:32]
>> Turn the volume down and say hello.
[37:34]
What?
[37:36]
The hardest part is they're dealing with
[37:37]
people that are having one of the worst
[37:39]
days of their of their year.
[37:40]
>> No kidding. I I just don't.
[37:42]
>> But nobody needs to be cussed and sw and
[37:44]
swore at, you know. I mean,
[37:46]
>> cuz I've done that and had people hang
[37:48]
up and then I even get mad and then they
[37:49]
won't answer the phone.
[37:53]
>> So,
[37:53]
>> no. And if is there classes? I mean, I
[37:56]
don't know what kind of classes, but
[37:57]
>> yeah, they have taken classes on
[37:59]
>> customer service classes
[38:00]
>> on how to deal with upset customer.
[38:02]
>> I think you're doing a good job. Yeah,
[38:05]
>> you just can't predict what kind of
[38:07]
stuff that's going to come in on the
[38:08]
>> you know and each of us each of us has a
[38:11]
different sensitivity to that. Some
[38:13]
people it doesn't bother, others it
[38:15]
really bothers and that's okay. You
[38:19]
know,
[38:19]
>> it's like having thick skin, but how
[38:21]
thick that how thick can that skin
[38:22]
really be, right?
[38:24]
>> Happy leather.
[38:26]
>> So, that position we did post in house
[38:29]
and one of our other employees is going
[38:31]
to move over uh to that position.
[38:34]
>> Can I ask you really quick just off
[38:35]
hand, what is the pay of that job
[38:37]
starting out? Do you know what that pay
[38:39]
is?
[38:39]
>> Uh I can tell you the job.
[38:42]
I'm sorry. I I should know all these
[38:45]
>> free I was thinking,
[38:46]
>> wasn't it?
[38:47]
>> I should know what these pay
[38:49]
>> pay is, but I just
[38:51]
>> starts at 2146
[38:54]
and the range ends at 2980.
[38:58]
>> And does that go by qualifications to
[39:00]
get you more money?
[39:01]
>> Yes.
[39:02]
>> Okay.
[39:03]
>> Yeah. Like I said, if you're going to
[39:04]
take all that abuse, you should just go
[39:05]
down to McDonald's and make that.
[39:09]
» They'll list it to you down there. you
[39:11]
get the wrong order. Okay.
[39:13]
>> Um I guess maybe we could focus on
[39:17]
more ways that the customers feel heard
[39:21]
and that we're responsive to them.
[39:24]
>> I think you're doing a good job.
[39:25]
>> So do I. The bad thing is when the
[39:27]
customer is so mad you can't talk over
[39:29]
them, right? Because they're just
[39:32]
>> um So that position will be filled, but
[39:35]
we're having to wait another week before
[39:37]
we can go outside.
[39:40]
That'll be posted.
[39:41]
>> Okay, that sounds great.
[39:43]
>> And you thought we the four 10-hour
[39:45]
days, right? And all the holidays and
[39:46]
vacation, all that. But
[39:48]
>> Oh, yeah.
[39:50]
>> On the operations, I'll point out a
[39:52]
couple things. We have been, as you
[39:55]
know, continuing work on draining and
[39:57]
cleaning and inspecting the drinking
[39:59]
water storage tanks. Unfortunately, we
[40:02]
did run into a issue that I'll have uh
[40:06]
Steve and Trevor and maybe Don even
[40:09]
might provide his input with regards to
[40:11]
the painting system in the big tank over
[40:14]
here.
[40:14]
>> And when was the last time you told me,
[40:17]
Steve, when was the last time we painted
[40:18]
the inside of that tank?
[40:20]
>> Five years.
[40:21]
>> Has it been five years?
[40:23]
>> Yeah. 21.
[40:24]
>> Um what's happen is the top layer is
[40:27]
peeling off.
[40:29]
I don't know if you
[40:31]
>> I pretty well thought we repainted that
[40:33]
because the top was all corroded.
[40:36]
>> It was repainted.
[40:37]
>> Yeah, it 5 years ago it was repainted
[40:40]
and
[40:41]
>> and it's coming off now.
[40:42]
>> Yeah, it's failing. So
[40:43]
>> So who did it? We better get a hold of
[40:45]
them.
[40:45]
>> So that's where we can have Trevor and
[40:48]
Don maybe
[40:49]
>> what we've investigated, what we found.
[40:52]
>> I remember we had we went out extra for
[40:54]
that just because it was corroded. We
[40:57]
because of that.
[40:58]
>> Yep. The metal.
[40:59]
>> Yeah. As you can remember, these tanks
[41:01]
have periodically been taken down
[41:03]
>> and repainted. Sometimes they're touched
[41:05]
up. Sometimes a whole new systems put
[41:07]
in.
[41:08]
>> So, can you
[41:08]
>> This was a This was a new system.
[41:11]
>> We paid for sand blasting and repainting
[41:14]
that roof. I remember positivity.
[41:16]
>> We did. And that's this is the new
[41:18]
system that's filled.
[41:19]
>> And that isn't the tank that what got in
[41:21]
there, right?
[41:23]
>> So, what happened is is that
[41:27]
We sanded it down and then we put a
[41:30]
three to
[41:36]
» tan color and finish with a
[41:40]
shown evidence here is we've got problem
[41:44]
second and third coat.
[41:46]
>> So we don't have any rusting that's
[41:48]
occurring between the codes. It's just
[41:51]
>> it's laminating.
[41:52]
>> What we're trying to find out how
[41:56]
We can determine the magnitude of it.
[41:58]
But it does mean we're need to go in
[42:02]
and sand
[42:05]
profile so we can put another coat on.
[42:10]
>> I've never I've never seen that ever in
[42:12]
my career. We don't know yet what the
[42:16]
reason is. We're trying to scan the logs
[42:18]
to see if we have a temperature problem.
[42:22]
Did we have something that froze?
[42:29]
But it doesn't look like it's the entire
[42:32]
tank. Looks like it's on the north side,
[42:36]
but clearly our
[42:40]
emergency repair.
[42:43]
We don't need it down there because all
[42:45]
primer and the first coat on it is fine.
[42:48]
It's just our second coat.
[42:52]
peel off big sheets. It's just bizarre.
[42:56]
>> When was these When was these tanks
[42:58]
built?
[43:01]
>> I think they're in the 60s.
[43:03]
>> Yeah. But the whole question is he could
[43:05]
have had moisture on that between those
[43:08]
coats and he wasn't paying attention.
[43:11]
>> Yeah. They're also analyzing the paint
[43:15]
chips to see if the mix was correct,
[43:18]
which could potentially
[43:19]
>> mixes it and he probably didn't mix it
[43:21]
right
[43:21]
>> and that's so we're Yeah. part of the
[43:24]
investigation
[43:24]
>> for it.
[43:25]
>> Yeah.
[43:25]
>> Well, the company that did it in 21 is
[43:29]
out of business.
[43:31]
Um, Tenemic has been very helpful.
[43:34]
They're doing their analysis. Um,
[43:37]
they've made they'll make some
[43:38]
recommendations. Um, they have some
[43:41]
painters that we're trying to schedule
[43:43]
to have come look a little more.
[43:45]
>> That all we use is tiny meat because
[43:46]
there's other better ones out there.
[43:48]
>> Well, they were the ones that provided
[43:49]
the product for this volunteer.
[43:56]
» That's pretty neat.
[44:00]
» Well, I don't know if I agree that now
[44:02]
because Sher Williams has sure tried to
[44:04]
come up to speak.
[44:05]
>> I do agree with that. I do agree with
[44:08]
big strides.
[44:10]
So I think the concern is timing. These
[44:14]
tanks are critical to have online during
[44:17]
June, July,
[44:19]
>> middle of summer.
[44:20]
>> So we're going to have if we're going to
[44:22]
do it now, we're going to have to move
[44:23]
rather quickly. Uh if or we make the
[44:27]
decision to clean it up and then put it
[44:31]
back into service and do a repair later.
[44:34]
>> I don't think we want to do that.
[44:35]
>> I don't think so either. I think we just
[44:37]
need to do the emergency deal and get it
[44:39]
done because why go back through it?
[44:41]
Yes,
[44:41]
>> they just got to block it and don't let
[44:43]
any animals in the damn thing in
[44:44]
between.
[44:45]
>> Yeah, it's closed off.
[44:47]
>> When Matt called me, that was all he
[44:49]
said is, "Hey, I need you to come up to
[44:51]
the tanks. I got something to show you."
[44:52]
>> Oh, no.
[44:55]
>> Yeah, if you've got it down, there's no
[44:56]
reason, like Nick said, to not take care
[45:00]
of it right then. We don't want flakes
[45:01]
going out in the water and stuff. That
[45:03]
would be bad.
[45:05]
>> No. Um, so I think we'll move forward
[45:08]
then. We appreciate Dons. He's been
[45:12]
knowledgeable about these tanks for
[45:14]
almost as long as they've been there.
[45:15]
>> Don, do you have any idea? Don, do you
[45:18]
have any idea how long
[45:22]
>> Don, do you have any idea how old them
[45:23]
tanks are when they were put in? Cuz I I
[45:25]
keep thinking they were there when I
[45:27]
grew up.
[45:30]
>> Oh,
[45:30]
>> okay. Then they were there when I was
[45:32]
there. Okay. Growing up.
[45:35]
comment that I want to make is you go into these tanks
[45:40]
at least particularly these older ones
[45:42]
and we've got a lot of evidence for
[45:45]
corrosion but I can tell you once the
[45:48]
district
[45:49]
realizing
[45:52]
they
[45:55]
look at you see all this corrosion
[45:57]
district
[46:00]
since they repainted them and used the
[46:02]
system we use You know the team 25 years
[46:06]
out of it since we painted it the first
[46:09]
time. We really have got good service on
[46:12]
I got compliment history. They have
[46:14]
never hesitated once they recognize the
[46:17]
problem those tanks of them and we're
[46:21]
going to get a lot of them and I have
[46:23]
never in my career seen this type of
[46:28]
two. I've seen it between the seen other
[46:32]
systems but this particular epoxy. So,
[46:35]
this this is a first for me.
[46:37]
>> And Don, I I tell you, I've been around
[46:39]
them a long time. A lot of that coating.
[46:42]
We need to look harder at the people
[46:43]
that are doing the work. I I have a
[46:46]
feeling they This isn't the first time
[46:48]
they've had a problem. I guarantee you
[46:50]
>> that way.
[46:50]
>> Well, it's frustrating because all the
[46:51]
other tanks they did are in good shape.
[46:54]
>> Our exteriors are good. The They did the
[46:56]
inside of the other the smaller one
[46:58]
here, and it's great. It And like Don
[47:01]
said, it it's not the whole tank. It's a portion of it. So, there was
[47:05]
something that happened.
[47:06]
>> Well, it's it's not the company. It's
[47:08]
the guys actually not paying attention.
[47:11]
So,
[47:11]
>> they come and go.
[47:12]
>> Workers.
[47:13]
>> Yep.
[47:13]
>> Yeah.
[47:14]
>> Different crews, not
[47:15]
>> Yeah.
[47:18]
>> I want to take a second. I want to thank
[47:19]
Don though for being You've been here my
[47:21]
whole time and I want to thank you for
[47:24]
everything that you do.
[47:25]
>> Absolutely.
[47:27]
I've known Don for a few years,
[47:30]
>> not Don, but I remember those takes when
[47:33]
I was in high school or there.
[47:35]
>> Yeah.
[47:35]
>> I mean, in the 60s.
[47:37]
>> Yeah. Don's been uh involved in a lot of
[47:39]
the critical decisions that I think have
[47:42]
been great for the district like the
[47:43]
secondary water, the reuse, the master
[47:47]
planning and rates. Uh been instrumental
[47:50]
in helping guide us and done a great
[47:53]
job. Hey, I want to thank him for doing
[47:55]
such a good job bringing you up through
[47:57]
the ranks. Look where we're at now.
[47:59]
>> And Trevor.
[48:03]
» Yep. We owe him that, too.
[48:08]
» Sorry. Sorry.
[48:11]
>> He's been a good man, Don.
[48:16]
» All right. But uh only other thing I'll
[48:19]
highlight here is we did get the lease
[48:20]
agreement signed by the Great Salt Lake
[48:23]
Commissioner.
[48:24]
>> Hi.
[48:25]
>> So our canal shares 75% of those we're
[48:29]
going to lease to the
[48:31]
>> Great Salt Lake. And so
[48:35]
» you want permission from the board.
[48:45]
Um,
[48:45]
>> do you want to come back and be
[48:48]
approved?
[48:48]
>> Well, I think there's an item on the
[48:51]
agenda that could give us a little more
[48:53]
flexibility with that depending on the
[48:55]
estimated cost.
[48:58]
>> We're the board last time asked to raise
[49:01]
the limit for the general manager to be
[49:04]
authorized up to 100,000. Yeah.
[49:06]
>> So, if you think that that those repairs
[49:09]
would be below a h 100,000, which I
[49:11]
would be hopeful.
[49:14]
>> Um I think we could handle it that way
[49:16]
if that goes through.
[49:17]
>> Yeah, that sounds great.
[49:18]
>> So, maybe we address it at the end of
[49:20]
the meeting
[49:22]
>> uh during the other if that's okay with
[49:24]
the board.
[49:24]
>> Yeah, let's do that.
[49:25]
>> Um and then if you you can decide what
[49:29]
you want to do.
[49:29]
>> Sure. But that stays within
[49:31]
>> But I think that's a good point
[49:33]
>> because it stays within the scope of the
[49:34]
repair. So, let's let's go that way.
[49:40]
» Um, the other things I'll highlight,
[49:43]
wastewater operations. Just excited that
[49:46]
we're back to
[49:48]
putting that reuse water to use. Steve
[49:50]
and Dallas have been coordinating. I
[49:54]
think your plan is to start at the end
[49:55]
of March, 1st of April, right?
[49:57]
>> Yeah, that's what we're shooting for.
[49:59]
>> So, when will there be water in
[50:00]
secondary?
[50:01]
>> Probably April 1st at the latest. Yeah,
[50:04]
we're shooting for April 15th actually
[50:06]
be fully operational, but there'll be
[50:08]
water before that so people will start
[50:10]
seeing it might have questions, but we
[50:12]
want to do some aggressive flushing.
[50:14]
>> Okay, I'll tell them.
[50:16]
>> I'll tell them maybe. But not going to
[50:18]
guarantee anything.
[50:18]
>> Tell them to wait till April 15th to use
[50:22]
that.
[50:22]
>> We'll be flushing ahead of that.
[50:25]
>> Okay.
[50:25]
>> Uhoh.
[50:28]
>> Should be better than last year.
[50:29]
>> Yeah, it'll be a lot better.
[50:30]
>> Rugging out all them fish. No, there's
[50:32]
no fish. At least At least not in the
[50:35]
reservoir, huh?
[50:36]
>> Yeah.
[50:36]
>> No.
[50:38]
>> Um Dallas has been working on bids for
[50:42]
contracting out the sledge hauling um
[50:44]
when ET Technologies closes and moves. I
[50:49]
think he's got some promising numbers so
[50:52]
far. He'll continue to evaluate that,
[50:54]
but it looks like a potentially good
[50:58]
option to do the contracted hauling.
[51:00]
When does it have to start? When will
[51:02]
they actually be because I heard they're
[51:04]
already doing stuff out at the site?
[51:06]
>> Yeah, they said they're planning a soft
[51:08]
startup date of January 1, 27.
[51:11]
>> 27. Okay.
[51:16]
And then on the office, uh, LIL
[51:19]
completed a drinking water consumer fee
[51:22]
incentive verification survey. That's
[51:25]
will be the basis for that new drinking
[51:27]
water fee calculation. that we have to
[51:30]
pass along to the customer.
[51:32]
>> Yeah.
[51:33]
>> Um but again, if you remember, they've
[51:36]
cut down how much that will be and they
[51:38]
pushed it back. So
[51:40]
>> So it will now be 2028.
[51:42]
>> 2028 fiscal year.
[51:44]
>> Well, I think that's when the fee will
[51:45]
be due by us. So if that's
[51:49]
start collecting,
[51:50]
>> when will we know what number?
[51:52]
>> Are they going to wait the last minute?
[51:54]
>> I hope not.
[51:55]
>> It will be based on usage, right?
[51:57]
>> Yeah. The survey didn't really ask a
[52:00]
whole lot of questions.
[52:01]
>> It's based on us. Will it go in tiers or
[52:03]
will
[52:05]
>> it's just a
[52:05]
>> right now it's not planned to.
[52:07]
>> Yeah. It's just how much
[52:09]
>> flat fee on usage.
[52:11]
>> It will be up to us to decide how we
[52:13]
pass that along.
[52:14]
>> Okay. But I'm just wondering they will
[52:16]
give you a number that they have to have
[52:19]
>> and then you guys have to fit it in to
[52:21]
see how it fits in the system,
[52:22]
>> right?
[52:23]
>> When will we know that? Will we know
[52:25]
before 2028? Hopefully.
[52:28]
>> Yes.
[52:28]
>> Okay.
[52:29]
>> We should know. They'll use I think they
[52:31]
said they were using 2025's
[52:34]
data. So, we actually know I think now
[52:36]
we could get an idea.
[52:38]
>> Okay.
[52:40]
>> For that 2028 calculation.
[52:43]
>> All right.
[52:44]
And then
[52:46]
as far as coord communication, just a
[52:49]
heads up, I met with Jordan Valley,
[52:52]
their GM and Granger hunters, and that
[52:57]
Jordan Valley has that water budget
[52:59]
policy uh for
[53:02]
annexation,
[53:04]
new annexations, they have to meet a
[53:07]
certain water budget per acre or they
[53:10]
have to bring in their own water.
[53:12]
>> Oh, wow.
[53:12]
>> Okay. that's currently in place for
[53:15]
Jordan Valley.
[53:17]
So, they're moving that internal to
[53:20]
within their district now as well. And
[53:24]
so, they're talking with the districts
[53:27]
on how that will be implemented, but it
[53:29]
sounds like it would be a similar
[53:32]
budget.
[53:34]
Um, and they would ask
[53:36]
>> the drinking water budget.
[53:37]
>> Well, similar budgetary per acre amount.
[53:42]
They're just moving that inland now into
[53:44]
their existing district. So any
[53:46]
development within the district will be
[53:49]
when they pass this will be subject to
[53:51]
that budget.
[53:52]
>> Right.
[53:53]
>> So they'll have to bring water if they
[53:56]
want service from Jordan Valley.
[53:58]
>> Are we involved in that?
[54:00]
>> We are since we contract with Jordan
[54:02]
Valley.
[54:02]
>> Right.
[54:04]
>> And so it would affect us if we needed
[54:06]
to go to Jordan Valley for more water.
[54:08]
We need to go for more.
[54:09]
>> But if we don't, we're okay.
[54:11]
>> Okay. And right now,
[54:13]
>> right now it affects us less and it
[54:16]
affects Jordan or Granger Hunter less.
[54:18]
So they met with us together because it
[54:21]
will affect us the least out of all of
[54:23]
the agencies because we supply the most
[54:26]
of our water. But I think it's important
[54:27]
for the board to be aware that the
[54:30]
industry is moving that direction.
[54:32]
>> Okay. and we will likely need to be
[54:35]
aligning
[54:37]
um our budget policy in some time in the
[54:40]
future. So, okay.
[54:44]
And then we've got the golf course here
[54:47]
today. Um there's an agenda item uh for
[54:53]
the board to consider
[54:55]
their request. It is towards the end of
[54:58]
the
[54:59]
>> agenda. I want to move out of I want to
[55:01]
move out of out of uh
[55:05]
out of the direct what do I want to call
[55:07]
that? I I want to move I want to go move
[55:09]
off the agenda and tend to the golf
[55:11]
course stuff right now and then go back.
[55:13]
>> I that's all with my reports.
[55:15]
>> Is the council okay? I mean the council
[55:17]
is the trustees okay with that?
[55:19]
>> Okay, let's move over to the golf course
[55:24]
and that way they don't have to sit here
[55:25]
and listen to everything we have going.
[55:27]
Do you guys want to come up?
[55:36]
So that is under administrative
[55:39]
item two I believe.
[55:41]
>> Thank you Leo.
[55:43]
>> How are you doing?
[55:48]
» First off, this lady here that's in
[55:51]
front of us today, her her boy works for
[55:54]
us, Gavin Henshaw.
[55:55]
>> Oh no.
[55:57]
>> So
[56:01]
and
[56:01]
>> we're very very very fortunate to have
[56:03]
Gavin.
[56:03]
>> So all of these problems you can blame
[56:05]
her.
[56:07]
>> So Mr. Chairman, yes,
[56:10]
>> I'll introduce them and then Trevor
[56:13]
might provide a little context and then
[56:16]
we'll if the golf course would like to
[56:19]
uh make any comments. But as you know,
[56:23]
they have used a combination of our
[56:26]
drinking water and then water from
[56:30]
Kennott to water the golf course over
[56:33]
the years. and they have formally
[56:37]
approached Magna Water and the board to
[56:41]
consider some
[56:44]
combination of transferring over that
[56:48]
water
[56:50]
uh to Magna Water uh and the reuse
[56:54]
system now that we have. And so
[56:58]
the cleanest option is the first one
[57:02]
which is what they use to water their
[57:05]
drinking water greens, right? I mean
[57:08]
their greens
[57:10]
>> with drinking water. Um we feel like
[57:13]
that is a pretty good option and we
[57:16]
think we can make that work fairly
[57:18]
easily. the other the rest of the golf
[57:21]
course that they water with the kick hot
[57:23]
water. That's quite a bit of volume,
[57:26]
>> right? And it could be potentially some
[57:31]
substantial
[57:32]
capital costs. Um the golf course was
[57:36]
going to look into that to see what they
[57:38]
can do with their system and maybe
[57:39]
they'll be able to give us an update,
[57:41]
but they've requested us to consider
[57:44]
those two options.
[57:46]
um and any participation
[57:49]
that Magna Water District can consider
[57:52]
to help offset or delay cost uh to the
[57:58]
golf course, whether that's payback,
[58:02]
whether that's um donation of piping
[58:06]
materials, they have asked requested
[58:08]
that. Um and so I'll let Trevor,
[58:12]
anything else that you wanted to add to
[58:14]
that? Um just
[58:17]
the option one connection. We did kind
[58:20]
of a a cost estimate of what that would
[58:23]
take and kind of looked a little bit
[58:26]
more and revised that this week. Um
[58:29]
roughly I mean between we'll say 35,000
[58:33]
to 50,000 to extend the pipe. Um, they
[58:38]
have a 4-in meter that they use for the
[58:41]
outdoor watering and then they have a 1
[58:43]
in that goes to the clubhouse. That 1 in
[58:46]
would need to be uh basically a new
[58:48]
connection for that if they were to go
[58:50]
this route. Um, and so we've taken all
[58:53]
that into account. We kind of have a
[58:54]
really good grasp of what's required.
[58:57]
Um, but that's kind of the cost range
[58:59]
for that.
[59:01]
>> Okay. And they don't need to change the
[59:03]
4 inch. They can live with them. I I we
[59:06]
have an option to you to put in uh what
[59:09]
is our standard 4-in vault. Um but I
[59:13]
don't believe that would be required to
[59:16]
make the connection to change it from
[59:18]
drinking water to secondary.
[59:20]
>> How big is the meter now that furnishes
[59:22]
it?
[59:23]
>> A 4 inch.
[59:24]
>> A 4 in.
[59:25]
>> And that wouldn't have to be increased
[59:27]
on secondary water to
[59:29]
>> not for the greens.
[59:30]
>> Okay.
[59:31]
So is that taken and bringing the line
[59:34]
over so it lines up and then like we
[59:36]
talked that day at the golf course.
[59:38]
>> Correct.
[59:39]
So a portion of that work benefits Magna
[59:42]
Water and I think something
[59:44]
>> I think that's something one of the
[59:46]
reason that the board could consider is
[59:48]
that the main in the road in front it's
[59:52]
in 2600 South
[59:54]
>> right
[59:54]
>> the bulk of the cost um
[59:57]
>> because we're going to eventually do it
[59:58]
anyhow right
[59:59]
>> it will be need to be done at some point
[1:00:02]
um so that's that's something for the
[1:00:04]
board to consider um we do usually put
[1:00:08]
the onus on development when it is in
[1:00:11]
this situation. They usually have to
[1:00:13]
front that cost if they want the water.
[1:00:16]
But but there are factors where like I
[1:00:18]
said, we benefit
[1:00:20]
uh some from that. So that's something
[1:00:23]
that you can consider. Um the second
[1:00:26]
option, we're still getting information.
[1:00:30]
I don't know if you've got enough.
[1:00:31]
>> We've done a lot of analysis. I don't
[1:00:33]
know that right here is the time and I don't have the figures but it they
[1:00:39]
it is a lot of water. It could be an
[1:00:41]
average of a,000 to 1,800 gallons a
[1:00:45]
minute um depending on when they're
[1:00:47]
using zones and which zones and how
[1:00:49]
many. Um so it is a significant amount
[1:00:53]
of water and so the infrastructure that
[1:00:56]
Clint mentioned is pretty significant.
[1:00:58]
It's an 8 to 10 inch pipe. It's a large
[1:01:01]
meter. Um, so I think that one still
[1:01:05]
needs to be fleshed out a little bit
[1:01:08]
more and the and there's an impact that
[1:01:10]
has never been on our system that would
[1:01:14]
then be be there
[1:01:15]
>> that needs to be evaluated
[1:01:17]
>> the impact of so are we incomplete at
[1:01:20]
this point to make
[1:01:21]
>> the option number two I don't think
[1:01:23]
we're at a point where we can make a
[1:01:25]
decision that that's
[1:01:26]
>> so out of the two when you're looking at
[1:01:27]
them both would you recommend one?
[1:01:29]
>> I would. Yep. 100%.
[1:01:31]
>> I think the number one benefits both the
[1:01:34]
golf course and NS long term.
[1:01:37]
>> Um would you guys like to add anything?
[1:01:40]
>> Yeah, I agree with that too. We want to
[1:01:43]
move forward number one.
[1:01:44]
>> Okay.
[1:01:44]
>> Like I'd love to have that done this
[1:01:46]
year.
[1:01:47]
>> Okay.
[1:01:48]
>> Both of us. Um
[1:01:50]
>> aside from that option number two, this
[1:01:53]
kind of goes I mean it's kind of off the
[1:01:55]
script, but we'd like to approach you
[1:01:58]
guys for
[1:01:59]
We're reaching our 100 year anniversary
[1:02:01]
this year and the coffee club is
[1:02:05]
probably the biggest green space in that
[1:02:08]
>> right
[1:02:09]
>> 70 plus acres of green space open.
[1:02:13]
I would like some help
[1:02:16]
maybe using the 100 year anniversary as
[1:02:18]
a starting point to reach out to other
[1:02:24]
entities for grant assistance.
[1:02:28]
the copper more sustainable when you're
[1:02:30]
talking about the amount of water we use
[1:02:32]
on the fairways.
[1:02:34]
The I don't know how old that system is.
[1:02:37]
It's not efficient and I'd like to start
[1:02:42]
>> and you could like do sections at a
[1:02:44]
time, right?
[1:02:46]
>> Absolutely. Absolutely. And you know if
[1:02:51]
using the macar is a great option there
[1:02:54]
with you guys to discover a better
[1:02:56]
option
[1:02:57]
>> something that's more
[1:03:00]
help.
[1:03:03]
» Well, you know what? I'm going I'm going
[1:03:04]
to just make a comment or two. I if the
[1:03:08]
number one option is feasible for them
[1:03:11]
and ourselves, I move that we we go
[1:03:14]
ahead, and go with option one and help these guys get this put in. And
[1:03:23]
>> what's the cost for option one? It's
[1:03:25]
right here between 20 uh between 35 and
[1:03:29]
$50,000.
[1:03:30]
>> Okay.
[1:03:31]
>> And that will like Clint said that will
[1:03:32]
actually benefit us too.
[1:03:34]
>> Where will that come from?
[1:03:36]
>> It ties
[1:03:37]
>> I I'm sorry. Did you make
[1:03:38]
>> We're talking about the option one where
[1:03:40]
it comes off 2600.
[1:03:42]
>> Oh, where did the where did the amount
[1:03:44]
come from?
[1:03:44]
>> What's the cost and who's going to pay
[1:03:46]
for it?
[1:03:47]
>> We are Well, there would be options for
[1:03:50]
the board to consider. could be um any
[1:03:54]
portion of that we could most likely do
[1:03:57]
that inhouse.
[1:03:59]
>> Um
[1:03:59]
>> as far as the extension
[1:04:02]
>> foot extension
[1:04:03]
>> so that estimate is
[1:04:05]
>> it's the 180
[1:04:08]
>> that estimate is include is assuming a
[1:04:10]
contractor came and did that. Right.
[1:04:12]
>> Correct.
[1:04:13]
>> So there could be some savings in terms
[1:04:15]
of labor. So, you're probably looking at
[1:04:17]
half on the labor, right?
[1:04:19]
>> That could be passed on or could not be
[1:04:21]
for the board to consider. The other
[1:04:24]
option is they you could do a payback
[1:04:28]
agreement where the district would front
[1:04:31]
the money um and do the work, get it
[1:04:34]
installed, and the copper cup could pay
[1:04:37]
it back over time potentially with the
[1:04:39]
savings. Um, so there will be savings
[1:04:42]
when they use reuse water versus
[1:04:45]
drinking water. You could say, "Hey, if
[1:04:47]
you would pay what you've been paying
[1:04:50]
until that's paid back, that's an option
[1:04:52]
for the
[1:04:53]
>> They haven't agreed to that yet."
[1:04:54]
>> They haven't. Um,
[1:04:55]
>> that needs to be done before we can
[1:04:57]
approve.
[1:04:57]
>> But the question I have on that though
[1:04:59]
is if it's going to benefit us, I mean,
[1:05:02]
you got to you got to stop and take that
[1:05:03]
in consideration. It's not just benefit
[1:05:05]
the golf course, it's benefiting us. Am
[1:05:06]
I right or am I wrong?
[1:05:08]
>> Yes. The portion of the upsize in the
[1:05:10]
road benefits us
[1:05:11]
>> the 180 ft.
[1:05:12]
>> Yeah.
[1:05:12]
And is that 35,000 the extension?
[1:05:16]
>> No, that's a portion of
[1:05:18]
>> very portion of the cost because that
[1:05:20]
includes Yes. that extension of that
[1:05:22]
line. There's blowoff on the end.
[1:05:24]
There's the connection to the meter
[1:05:26]
vault. There's the 1 in meter.
[1:05:29]
>> So, we didn't have a we didn't actually
[1:05:31]
have a motion uh on this. We wanted it
[1:05:36]
to beformational for the board to give
[1:05:39]
us direction. If you wanted more
[1:05:41]
information, if you wanted us to come
[1:05:44]
back with more details on one thing or
[1:05:46]
the other, um, that was kind of the
[1:05:48]
intent here. Um,
[1:05:50]
>> so the only thing we'll motion on today
[1:05:52]
is to go ahead with option one, but they
[1:05:55]
still need to approve whatever you come
[1:05:58]
up with and so that we can then
[1:06:00]
>> So do we know what do we know when you
[1:06:03]
say it benefits us in so what's the
[1:06:07]
cost?
[1:06:07]
>> That's something we could come back
[1:06:09]
with.
[1:06:10]
>> Good.
[1:06:12]
>> When can you have all this stuff done so
[1:06:14]
we can have it back to us? Um, I think
[1:06:16]
the intent was you wanted something in
[1:06:18]
place before the start of your
[1:06:20]
irrigation.
[1:06:21]
>> Correct.
[1:06:21]
>> When when do you guys plan?
[1:06:23]
>> May 1st.
[1:06:24]
So, we could have it in the
[1:06:26]
April meeting.
[1:06:27]
>> Okay.
[1:06:27]
>> Um, and we would get close. I think
[1:06:31]
Steve, as long as your crews could have
[1:06:33]
that done
[1:06:35]
>> if that's what it's looking like we're
[1:06:36]
going to go to, then
[1:06:37]
>> we'll How long will it take to do that,
[1:06:40]
Steve?
[1:06:42]
Um, I'd probably plan a couple weeks.
[1:06:46]
>> Okay. Not over three weeks. That's only
[1:06:49]
180 ft.
[1:06:51]
>> So, I think it's doable.
[1:06:53]
>> I say a couple weeks because you never
[1:06:55]
know what's going to happen. We might be
[1:06:56]
pulled off for sure emergency.
[1:06:59]
>> Sure.
[1:07:02]
But it's like I said, we need all this
[1:07:05]
put down and everybody agrees on what
[1:07:07]
it's going to cost and who's going to
[1:07:08]
accept.
[1:07:09]
>> You may get me back
[1:07:10]
>> certain things.
[1:07:13]
>> Okay, then I got it wrong because I
[1:07:14]
thought we were going to put I thought
[1:07:15]
we were going to run this ourselves.
[1:07:18]
>> Well, that's an option for sure.
[1:07:19]
>> I thought that's what we talked about. I
[1:07:21]
thought we was going to run it ourselves
[1:07:23]
and then they'll be liable for the rest
[1:07:25]
of the stuff. But I thought we my
[1:07:27]
agreement was is I thought we were going
[1:07:29]
to run it over there. We were going to
[1:07:31]
we talked about that that we were going
[1:07:32]
to do that and now it's all going to
[1:07:34]
come with this cost and this cost and
[1:07:36]
this cost. So I'm I'm kind of confused
[1:07:37]
about it.
[1:07:38]
>> Well, I think we talked we could get to
[1:07:40]
that point, but I think we talked about
[1:07:42]
the first step was they would come back
[1:07:44]
and formally
[1:07:46]
tell us what they wanted,
[1:07:47]
>> right?
[1:07:48]
>> And there
[1:07:48]
>> they want they want one
[1:07:50]
>> and they want both options,
[1:07:52]
>> right?
[1:07:55]
I mean obviously we wanted to benefit
[1:07:57]
both of us and I think both options
[1:07:59]
would
[1:07:59]
>> okay
[1:08:00]
>> we haven't flipped over both options up
[1:08:04]
so far you know the questions you've
[1:08:07]
been asking I haven't
[1:08:10]
>> at all I I've given you guys what we pay
[1:08:15]
Utah power to run our currently
[1:08:18]
>> I think it benefits
[1:08:20]
magma magma water to keep the resour
[1:08:24]
coming to Utah power resources meaning
[1:08:29]
>> and we're willing to you know we're
[1:08:32]
willing to pay that but I don't know how
[1:08:36]
>> we don't know
[1:08:38]
>> so do you guys have a count on how many
[1:08:40]
heads you've got and all that kind of
[1:08:42]
stuff
[1:08:43]
>> so when can you give that to
[1:08:45]
>> we we have that and we we've started
[1:08:47]
doing it doing an analysis and that's
[1:08:50]
where I mentioned that well I mean when
[1:08:52]
they're in their peak season, it could
[1:08:54]
be 1,800 gallons a minute that they're
[1:08:56]
watering.
[1:08:57]
>> So, is that is that what we base it on
[1:08:59]
for option two to come up with a number?
[1:09:01]
>> Correct. But that that full analysis
[1:09:04]
isn't done. The impact on our system,
[1:09:06]
what that cost might be, what what they
[1:09:08]
would pay monthly, we haven't got to
[1:09:10]
that point.
[1:09:11]
>> It's just like we find on an airline.
[1:09:13]
You walk into a place and you hear air
[1:09:15]
leaking all over what they pay for the
[1:09:17]
compressor cost. I have a feeling you
[1:09:19]
guys got a lot more leaks than you think
[1:09:20]
you do under that ground.
[1:09:21]
>> I agree with you. And that's and that's
[1:09:24]
where I would reach back out
[1:09:28]
and help us. We're operators, right?
[1:09:30]
We're both operators of this property.
[1:09:33]
We don't
[1:09:34]
>> right.
[1:09:34]
>> I can't for
[1:09:36]
>> right
[1:09:38]
>> there are many grants that suit our
[1:09:39]
needs as far as you know infrastructure
[1:09:43]
and water consery. There there grants
[1:09:46]
out there that we look at.
[1:09:50]
>> Could a cut apply for the grant? cop can
[1:09:53]
>> since they're the property owner.
[1:09:55]
>> It's they're the property owner you can
[1:09:57]
because
[1:09:59]
that's
[1:10:00]
>> so I got a question on that Nathan. So
[1:10:03]
under that deal with them the grant
[1:10:05]
there's a bunch of grants I understand
[1:10:06]
what it is I thing we dealt up here with
[1:10:09]
this project that we're working on right
[1:10:11]
now is
[1:10:14]
how you know cuz we're providing the
[1:10:16]
water right we're going to we were going
[1:10:18]
to provide the water and and like Jeff
[1:10:20]
said there's a lot of leakage he's
[1:10:21]
assuming there's a a bunch of leakage
[1:10:25]
how since Kakott owns the land how could
[1:10:29]
they get how could how could we put any
[1:10:32]
pressure on Kakott
[1:10:33]
to have them apply for these grants
[1:10:36]
because at the end of the day, Kennot
[1:10:38]
owns the land, right?
[1:10:39]
>> Yeah. And so there's a couple things to
[1:10:40]
keep in mind as and as I understand what
[1:10:44]
you're saying is what you're asking is
[1:10:46]
can the district or the city also put in
[1:10:49]
for grants because the city as the
[1:10:51]
district and the city as government
[1:10:52]
entities are going to be
[1:10:53]
>> they got a grant coming to us from the
[1:10:56]
city coming up.
[1:10:57]
>> Yeah, but that's that's something the
[1:10:58]
city's providing.
[1:10:59]
>> Right. Right. So Riotinto as the owner
[1:11:01]
could apply for those grant programs
[1:11:03]
that Riotinto as a private for-profit
[1:11:05]
company is eligible to apply for, but a
[1:11:09]
usually there's public entities have
[1:11:12]
other programs that are in addition or
[1:11:14]
separate to from what Riotinto could
[1:11:16]
apply for. So, it's not uncommon, this
[1:11:19]
is an odd situation, but for entities
[1:11:22]
that provide some public service to a
[1:11:23]
community that aren't eligible for a
[1:11:25]
grant to partner with the the entity
[1:11:27]
that is, which would be the district or
[1:11:29]
the city, to then have that entity apply
[1:11:32]
for the grant and pass it through to to
[1:11:35]
them. I assume you're a nonprofit
[1:11:37]
organization, right?
[1:11:38]
>> So, there's and that happens relatively
[1:11:42]
frequently. And so, yes, you could go
[1:11:44]
and work with Riotinto, but I think what
[1:11:46]
maybe makes the most sense is if you're
[1:11:48]
aware of grant programs that you're
[1:11:50]
interested in, give us a list because
[1:11:52]
some of those are things that Riointo
[1:11:54]
may be able to apply for that we can't.
[1:11:56]
But I think more than likely,
[1:11:57]
>> most of those are going to be things
[1:11:58]
that we could apply for that the city
[1:12:00]
could apply for that Riointo can't. And
[1:12:02]
so my thought is is let's see what's out
[1:12:04]
there and then maybe pass it over.
[1:12:06]
>> Yeah. Or you could sit down with Rio
[1:12:08]
Tinto and say, "Let's coordinate on
[1:12:09]
this.
[1:12:10]
>> What do we do? What's best for the Gulf
[1:12:12]
District? It looks like Riotinto.
[1:12:13]
There's some that you might be able to
[1:12:14]
apply through and pass to them and it
[1:12:16]
looks like there's some that we can. But
[1:12:18]
my guess is, and correct me if I'm
[1:12:20]
wrong. Most of what's going to be
[1:12:22]
available are things that you can apply
[1:12:23]
for that Rio Tinto can. Because a lot of
[1:12:25]
times with grant money, they're going to
[1:12:26]
be like, okay, a government entity gets
[1:12:28]
grant money. One of the richest
[1:12:30]
corporations in the world that has mines
[1:12:31]
all over the place. Why are we giving
[1:12:33]
public money to them?
[1:12:35]
And I think one of the things that could
[1:12:38]
tie that together, which is why option
[1:12:41]
two might be a little more complicated,
[1:12:43]
is there may be some partnership we can
[1:12:46]
make with Kakott over that pump station
[1:12:49]
itself. And so that's something that
[1:12:51]
we're pursuing as well. Um I think that
[1:12:54]
could be a win-winwin. Um so
[1:12:58]
>> because it's between the owner of the
[1:12:59]
property and the water company, right,
[1:13:01]
that could be really valuable.
[1:13:02]
>> Yeah. and then and then that could be an
[1:13:05]
asset to the district that we could then
[1:13:07]
in turn pass on uh the water and manage
[1:13:11]
that potentially.
[1:13:12]
>> That's two concerns I have with the golf
[1:13:14]
course. Number one, your quality of your
[1:13:16]
grass and your water leaks. Those are
[1:13:18]
the two biggest things. You really need
[1:13:21]
to look at that grass and if you're
[1:13:23]
using more water than you should be. I
[1:13:25]
think there's a lot of help out there.
[1:13:27]
Somebody needs to consider what grass
[1:13:30]
you have, what how much water it takes
[1:13:32]
and that's on and above besides all the
[1:13:34]
water leaks you have under the ground.
[1:13:36]
>> So,
[1:13:37]
>> well, that's what I'm saying. So, where
[1:13:38]
do we move from here? Do we have them
[1:13:41]
get a list?
[1:13:41]
>> Yeah. What I would recommend, and this
[1:13:43]
is not my call, but I would recommend
[1:13:45]
sounds like you've done some homework on
[1:13:46]
this, right? Provide I guess Clint or
[1:13:50]
whoever you guys designate a list of
[1:13:52]
what that stuff is so we can take a look
[1:13:53]
at it and see what makes sense. Now, I
[1:13:56]
will be clear. There are going to be
[1:13:57]
requirements. We'll need to have some
[1:13:59]
sort of a pass through contract. May
[1:14:01]
want to talk with Seth Oson with local
[1:14:03]
government's uh section of the state
[1:14:05]
auditors because there are some
[1:14:06]
reporting requirements. So, for
[1:14:07]
instance, anything over $25,000 that you
[1:14:09]
receive in public funds, whether it's
[1:14:11]
from us, the state or uh typically in
[1:14:13]
those different with federal government
[1:14:15]
grants too, there's there's reporting
[1:14:17]
there going to be mainly reporting
[1:14:19]
requirements on your ends, but if it's a
[1:14:21]
federal grant, potentially reporting
[1:14:22]
requirements on ours. Now that be said,
[1:14:25]
that being said, um there may be we may
[1:14:29]
need to work with Riotinto on this too
[1:14:31]
if with the ownership issue. It's just
[1:14:33]
each grant program is going to have its
[1:14:35]
own separate requirements and its own
[1:14:36]
separate eligibility criteria.
[1:14:39]
>> So what do we want to sit down? I mean
[1:14:41]
once he recognized what grants do we
[1:14:44]
want to sit down I mean bring them
[1:14:45]
through us or do we want to kind of sit
[1:14:47]
down and have a meeting with us and
[1:14:49]
kakott and just
[1:14:50]
>> yeah I would I would suggest that we see
[1:14:52]
what's out there first because you may
[1:14:53]
look at it and there may not be anything
[1:14:55]
that Riotinto can apply for.
[1:14:56]
>> Okay.
[1:14:57]
>> Or it may be that these are things that we can do but Riotinto needs to
[1:15:01]
sign off on it as the owner. So I think
[1:15:03]
it's premature to schedule anything with
[1:15:05]
Riotinto until we've seen
[1:15:07]
>> Okay. No, I was just asking how that
[1:15:08]
works. So,
[1:15:09]
>> and and I agree with you, Mick, as far
[1:15:11]
as that 180 foot extension down the main
[1:15:15]
street, which is in the city. Um, I
[1:15:18]
don't have a problem with that, but I
[1:15:20]
think we need to nail down the cost.
[1:15:22]
>> I I I can agree. I agree with that.
[1:15:25]
>> So, if what I'm hearing is we would come
[1:15:27]
back to the board with a next month with
[1:15:30]
a final cost. That would be the B what
[1:15:34]
Magna Water's participating in and what
[1:15:37]
we're providing. and then the cost that
[1:15:39]
they would need to be expected to pay
[1:15:42]
back. Is that Yeah. Is that a fair
[1:15:44]
>> That's what I was hoping because I don't
[1:15:46]
have a problem. Anything that goes in
[1:15:47]
the street, I don't I don't think we
[1:15:50]
necessarily need to push them on because
[1:15:51]
they're an existing customer, not that
[1:15:53]
it's a new facility where we, you know,
[1:15:56]
push that on as part of that. So,
[1:15:59]
>> how does that sound to the board? I I'm
[1:16:01]
a little different about that, but my
[1:16:03]
different is is if we're going to put
[1:16:05]
that if we got to run that line over,
[1:16:07]
why let's just put it in?
[1:16:10]
>> Well, I think we are saying we would put
[1:16:12]
it in.
[1:16:12]
>> We would put it in and then
[1:16:13]
>> but then the 4 in to their
[1:16:15]
>> Oh, no, no, no. I understand that part.
[1:16:16]
Okay.
[1:16:16]
>> That would be what they would be
[1:16:18]
responsible to pay back. Is that seem
[1:16:20]
reasonable? I think that's that's
[1:16:22]
>> and we could just have them pay back
[1:16:24]
materials
[1:16:26]
for that portion or we could have them
[1:16:29]
pay back labor and materials since if
[1:16:31]
we're putting that in.
[1:16:32]
>> So
[1:16:33]
>> bring it bring it back to board and then
[1:16:34]
we can make a decision on that.
[1:16:36]
>> We'll we'll make sure that those options
[1:16:37]
are all available in that cost
[1:16:40]
>> so that you could determine what com
[1:16:43]
combination works. Does that sound okay?
[1:16:47]
>> Yeah. I don't want to hold that up at
[1:16:48]
all.
[1:16:48]
>> Does that work with the golf course?
[1:16:54]
I really want to use this as a starting
[1:16:55]
point to build a partnership
[1:16:58]
>> right
[1:16:58]
>> with the board with water.
[1:17:03]
I keep talking about 100 years. It's
[1:17:04]
important it's important to
[1:17:11]
basis or starting pointy
[1:17:14]
project that we can apply for to ensure
[1:17:16]
that that stays down there.
[1:17:21]
» Well, like I said, this is how I feel.
[1:17:23]
I'm going to speak as the chair of the
[1:17:25]
board. I'm going speak as the mayor. Um
[1:17:27]
I don't want to see that golf course go
[1:17:29]
away. So, whatever we can do to help
[1:17:30]
sustain that golf course, if we lose the
[1:17:33]
golf course, you might as well say kiss
[1:17:34]
good Magna goodbye because that's all we
[1:17:37]
have out here that's ever stayed here.
[1:17:40]
And we'll work, you guys have worked
[1:17:41]
very hard to keep that. You run off a
[1:17:43]
shoestring
[1:17:45]
and u you know, so whatever I could do
[1:17:48]
at my end, I'm willing to you know,
[1:17:52]
again, I have people I answer to, too.
[1:17:54]
So,
[1:17:56]
>> but I want to see the golf course stay
[1:17:57]
too on that.
[1:18:00]
>> So, I I think we
[1:18:01]
>> wants to talk.
[1:18:02]
>> I think we can make a motion to move
[1:18:04]
ahead on option one if we need to.
[1:18:07]
>> I I agree.
[1:18:08]
>> But we also need to con continue with
[1:18:11]
option two and get the rest of the data
[1:18:13]
from the golf course
[1:18:14]
>> on option two because we have incomplete
[1:18:16]
data.
[1:18:17]
>> Right. I think we're I think we're
[1:18:19]
getting there on that. We just have the
[1:18:22]
analysis. It's so much more volume.
[1:18:24]
Yeah,
[1:18:25]
>> that it changes what we can do,
[1:18:29]
>> how we would approach that. Okay.
[1:18:31]
>> So, that's what's going to take a little
[1:18:32]
bit of time.
[1:18:33]
>> Well, if it is 1,800, that would make a
[1:18:36]
big difference over a,000. That's almost
[1:18:38]
double.
[1:18:39]
>> Yeah.
[1:18:40]
>> So, I don't know if they I don't know if
[1:18:43]
they have anything that
[1:18:44]
>> you can run across the ground that would
[1:18:46]
determine if there's a leak or something
[1:18:48]
in the line. turn.
[1:18:49]
>> I mean, all I know is you can shut the
[1:18:51]
valve off and see how long it takes and
[1:18:53]
it would probably like that.
[1:18:55]
>> Yeah.
[1:18:58]
>> Sound
[1:19:00]
>> It's It's a lot of water. There's
[1:19:02]
probably some leaks. I mean, you know,
[1:19:04]
you've got trees, it's mature, their
[1:19:06]
pipes been there a long time.
[1:19:08]
>> We just know in this ground, it doesn't
[1:19:10]
go to the surface.
[1:19:11]
>> A water leak doesn't go to the surface.
[1:19:13]
It goes in the ground.
[1:19:15]
>> Yeah. It goes down into that pipe right
[1:19:17]
where they need to get that all piped
[1:19:19]
in.
[1:19:22]
>> Okay, that is that's it.
[1:19:24]
>> Thank you you guys. Appreciate you.
[1:19:26]
>> Can I ask a question?
[1:19:27]
>> What is that?
[1:19:28]
>> This is Canox's property or whoever. If
[1:19:31]
it's a major improvement for their
[1:19:32]
personal property, wouldn't they be
[1:19:34]
interested in paying money to have
[1:19:37]
improved if it's an upgrade for their
[1:19:39]
property?
[1:19:40]
>> You know what? You would you would think
[1:19:42]
so, but unfortunately it doesn't work
[1:19:44]
that way. and we'll I'll give you detail
[1:19:46]
down the road. So,
[1:19:48]
>> they're they're really tight right now.
[1:19:50]
They're being very cautious what they
[1:19:51]
spend.
[1:19:57]
» I know. I I I Hey, I understand that.
[1:20:00]
>> They won't talk about that.
[1:20:03]
>> Thank you,
[1:20:03]
>> Mr. Chair. We have a motion on the floor
[1:20:05]
that
[1:20:06]
>> to continue option one. So, we just
[1:20:08]
>> the motion on the floor, option one. We
[1:20:11]
need a second on it.
[1:20:13]
>> Oh, sorry. Been motion second. All in
[1:20:15]
favor?
[1:20:16]
>> I
[1:20:16]
>> thank you.
[1:20:28]
» Okay, let's move on to engineering.
[1:20:31]
>> Okay,
[1:20:32]
>> let's move back to our regular bean. I
[1:20:34]
mean back to our on our agenda.
[1:20:37]
>> Thanks, chair and board. Um the
[1:20:39]
engineering report. Things to note. Um
[1:20:43]
the Influent pump station project uh
[1:20:46]
moving along well. The pumps, screw
[1:20:48]
pumps are in there. They're working on
[1:20:51]
some power things and then we'll be able
[1:20:52]
to grout those channels and we'll see
[1:20:54]
those spin. That'll be really really
[1:20:57]
great. Um they installed some large
[1:21:00]
manholes continuing to put in some of
[1:21:02]
that piping and the grit is moving along
[1:21:05]
well. Also a lot of electrical and
[1:21:08]
mechanical within the building. and then
[1:21:10]
also working on one of the grit
[1:21:14]
separators and the piping over to the
[1:21:16]
new grit building.
[1:21:18]
Um Hanes well number eight, we have that
[1:21:22]
out to bid right now. Um that and that
[1:21:25]
is strictly the drilling of that well.
[1:21:29]
Um the building, we're still working
[1:21:32]
with the EPA and that grant funding. Um,
[1:21:36]
and that'll be used solely for the
[1:21:38]
building, uh, the pump station itself.
[1:21:40]
So, we moved forward on the drilling of
[1:21:42]
that. The bids will be due on the 23rd.
[1:21:44]
We had a pre-construction meeting which
[1:21:46]
went really well or a pre-bid meeting,
[1:21:48]
sorry. Uh, went really well. There's
[1:21:51]
seems to be quite a bit of interest.
[1:21:53]
There's, I think, eight contractors that
[1:21:56]
have requested plans and specs and so
[1:21:59]
looking forward to to that bid opening.
[1:22:03]
um Westside Collection Project 1B. Um
[1:22:06]
the fiber optic conflict, we've got a
[1:22:09]
final design on that. Um we're turning
[1:22:12]
that over to BD Bush, who was a
[1:22:14]
contractor on that project to get us a
[1:22:16]
cost
[1:22:18]
>> to
[1:22:19]
>> BD Bush.
[1:22:20]
>> Oh, never heard.
[1:22:22]
>> They did the the collection piping
[1:22:25]
install. They have a separate bore
[1:22:26]
contractor, but they'll there'll be a
[1:22:28]
separate one for this also because it
[1:22:30]
has to be under UDOT's uh spec and one
[1:22:33]
of their contractor preferred
[1:22:36]
contractors. So, we'll have a number on
[1:22:38]
that I I believe by next month.
[1:22:42]
Um,
[1:22:44]
we change house. We do have 90% plans
[1:22:48]
that we'll start reviewing and we'll share some of that information
[1:22:51]
with you.
[1:22:53]
um zone 3 reservoir. Um there's a lot of
[1:22:58]
groundwater up there. Um didn't see a
[1:23:01]
lot in the geotechnical, but we're
[1:23:03]
seeing quite a few little bubble up
[1:23:06]
>> pit springs
[1:23:07]
>> areas. And so we've been chasing that a
[1:23:10]
lot, working a lot on on the drain
[1:23:12]
piping um to dry that up. Uh very
[1:23:16]
important for the constructibility and
[1:23:18]
longterm on that. Um they've they've
[1:23:20]
installed some of the 16inch pipe and
[1:23:23]
that was going well. Also, uh lead and
[1:23:26]
copper, that project is underway.
[1:23:29]
They're starting on 9100 South. Um
[1:23:33]
the they did some saw cutting and
[1:23:35]
investigation yesterday and today, and
[1:23:37]
they'll start replacing service lines on
[1:23:40]
our side um starting next week, Monday.
[1:23:44]
Um we've had a lot of good interaction
[1:23:47]
with the public. They seem to be
[1:23:49]
receptive of allowing us to replace
[1:23:51]
their lines. I think we have a couple
[1:23:53]
that have denied it, which is okay.
[1:23:57]
>> Really? I can't believe that. It's
[1:23:58]
weird. Why wouldn't you want your line
[1:23:59]
changed out for nothing
[1:24:01]
>> for yard displays?
[1:24:03]
>> Yeah.
[1:24:04]
>> One one of them has a lot of trees. He
[1:24:07]
really loves his yard and he doesn't
[1:24:08]
want anyone touching it. And
[1:24:10]
>> we do have them sign a waiver.
[1:24:11]
>> Yep. Exactly. And then we just have to
[1:24:13]
track it and we each year we have to,
[1:24:16]
you know, notice them and say, "Hey, you
[1:24:18]
should get this replaced." And then if
[1:24:21]
the home sells, we have to update, you
[1:24:23]
know, inform that new person, but
[1:24:25]
they're not eligible for us to replace
[1:24:27]
it in the future, which they understand.
[1:24:29]
>> We connect inside the house where the
[1:24:31]
main goes to.
[1:24:32]
>> It depends on what the material is
[1:24:34]
coming out. We're seeing a lot of them
[1:24:35]
are copper stubbed and then galvanized
[1:24:38]
to that. And so we'll replace up to
[1:24:40]
that. Some of them were we are going to
[1:24:42]
go inside. Um
[1:24:44]
>> I just wonder what you're going to find
[1:24:45]
inside.
[1:24:46]
>> It's
[1:24:47]
>> So what do you do when you hit a problem
[1:24:49]
like that? Do we write a letter and say
[1:24:52]
>> Well, the contract
[1:24:54]
>> the contract is to go into the shut all
[1:24:56]
the way to the shut off valve.
[1:24:58]
>> So we're covered that way.
[1:25:00]
>> Yeah.
[1:25:01]
>> Some of them don't have shut offs.
[1:25:03]
>> Some some of them have whatever wonky
[1:25:07]
valve they had at the time, too. So,
[1:25:09]
we'll end up improving some of that,
[1:25:11]
too.
[1:25:11]
>> Okay.
[1:25:12]
>> For them as part of this. And that's all
[1:25:14]
under the contract.
[1:25:18]
» That sounds great.
[1:25:19]
>> Um, and then yeah, the EDR just in
[1:25:23]
design there um for the finishing feed
[1:25:25]
and the master plan. We're moving into
[1:25:28]
our rate study analysis portion of that.
[1:25:31]
>> We can report more on that in the
[1:25:34]
future. But
[1:25:34]
>> yeah,
[1:25:35]
>> that's it
[1:25:36]
>> for now.
[1:25:37]
>> Thanks, Trevor. appreciate the report.
[1:25:39]
Thank you.
[1:25:40]
>> Okay, let's move on. See to your water
[1:25:41]
report.
[1:25:42]
>> All right. Thank you, board chair. So,
[1:25:44]
the culinary water production for the
[1:25:46]
month of February was 94.02
[1:25:50]
million gallons or 288.56
[1:25:53]
acre feet. And that's a 38% decrease
[1:25:58]
from February of 2025.
[1:26:01]
So far, year to date, we purchased 60.02
[1:26:05]
acre feet of water from Jordan Valley.
[1:26:08]
As far as the call outs go, we've had a
[1:26:11]
total of 14 for the month. 10 of those
[1:26:13]
were on the water side and four were on
[1:26:16]
the wastewater side for a total of 45.5
[1:26:20]
hours. 30 of those were water and 15.5
[1:26:24]
ended up wastewater.
[1:26:26]
>> Steve, do we notice them lower in the
[1:26:28]
winter time than in the summer?
[1:26:30]
>> You know, it just varies. I mean, yeah.
[1:26:33]
>> So, temperature doesn't matter as
[1:26:35]
>> it it does. part in it, but it kind of
[1:26:39]
changes the calls from a different type
[1:26:42]
of call. So,
[1:26:44]
>> um like this month we didn't have any
[1:26:47]
main lines. Um we had one service line
[1:26:50]
and then the rest of them were pretty
[1:26:53]
much like for the water part anyways.
[1:26:55]
The rest of them were on the homeowner
[1:26:57]
side.
[1:26:58]
>> It seems like when we get really
[1:26:59]
extremely cold weather that seems when
[1:27:02]
everything shows up.
[1:27:03]
>> It Yeah, it does. I mean,
[1:27:06]
but at the same time during the summer,
[1:27:09]
the spring, fall, it kind of the
[1:27:12]
ground's shifting and we start to see a
[1:27:14]
lot then too. So, it just depends. It
[1:27:16]
varies.
[1:27:18]
Um, that's really all I have unless you
[1:27:21]
guys had any questions about any
[1:27:22]
questions about earlier.
[1:27:24]
>> No. Thank you.
[1:27:26]
>> Okay. Dallas.
[1:27:27]
>> Yes, sir. Mr. Chairman, I've got just a
[1:27:29]
couple things I wanted to go over. Um,
[1:27:32]
Mr. Dilly mentioned that we filed the
[1:27:34]
annual bioolids permit. Um that's an
[1:27:37]
annual report that we have to do to the
[1:27:38]
state. That just talks about how much
[1:27:40]
sludge we've hauled, how much chemical
[1:27:42]
we've used. Um there's two different
[1:27:45]
units that they look at that in 866
[1:27:48]
drymetric tons. That's how we report it.
[1:27:51]
And the way we calculate that inhouse,
[1:27:53]
it was just over 14,45,360
[1:27:58]
lbs for the year 2025. That's 440 loads
[1:28:02]
with no deficiencies reported. Um,
[1:28:06]
February operations are really stable
[1:28:08]
even with the fluctuating temperatures.
[1:28:10]
We've been able to walk the mix liquor
[1:28:12]
suspended solids concentrations in the
[1:28:14]
aeration basins down to about 2,000. Um,
[1:28:17]
that's going to be really good for us as
[1:28:19]
we move into April and May. We like to
[1:28:21]
operate between 1,800 and 2,000 during
[1:28:24]
the summer months. Um, so to be there,
[1:28:26]
that's a good head start for us. Um,
[1:28:29]
when I say operations are stable and
[1:28:31]
running well, I think the board's been
[1:28:34]
around long enough to know that there's
[1:28:35]
been some issues with ammonia in the
[1:28:37]
past. Ammonia is really stable. We're
[1:28:39]
getting good nitrification reliability.
[1:28:41]
Um, and everything's looking really
[1:28:43]
good. So,
[1:28:45]
um, the collections crew,
[1:28:47]
>> I got one question.
[1:28:48]
>> Yes, sir.
[1:28:49]
>> So, the ammonia thing, does it have
[1:28:50]
anything? We've had really good weather.
[1:28:53]
>> So, does that change when it's really
[1:28:55]
cold and the bugs are cold? really cold
[1:28:58]
is one factor in it. Um the mixed liquor
[1:29:01]
concentration if that gets too high and
[1:29:04]
then our our lack of air injection. So
[1:29:07]
um but when you balance all those out we
[1:29:09]
can get the we can keep the ammonia low.
[1:29:12]
So we've got a monthly permit limit of
[1:29:15]
seven but then we have a max daily of
[1:29:18]
30. Um and we haven't been over a max
[1:29:21]
daily of three this year. Wow.
[1:29:23]
>> So we're we're doing really well. Um,
[1:29:26]
just an update on the collections crew
[1:29:28]
and some of the maintenance that they're
[1:29:30]
doing right now. They're working in
[1:29:32]
downtown Magna. They're on the 8800
[1:29:35]
block below 3100 and they're kind of
[1:29:37]
working their way north and then over
[1:29:39]
towards that corner pocket of 84 and um
[1:29:43]
down there by Magnum Main Street. So,
[1:29:46]
and that's all I have, Mr. Chairman,
[1:29:47]
unless you've got any questions.
[1:29:49]
>> Nope, that's it. Thank you, Leo.
[1:29:52]
>> Thank you, chair board. Um,
[1:29:56]
the only thing I have to report that we
[1:29:58]
need to comply with by the end of this
[1:30:00]
month is our impact fee report. It's due
[1:30:03]
to the state auditor's office um on
[1:30:06]
March 31st.
[1:30:08]
Uh, wanted to also report the pretty
[1:30:11]
much final trial balance was submitted
[1:30:13]
to the auditors this week. So, Mick, you
[1:30:17]
just signed a auditor's engagement
[1:30:19]
letter,
[1:30:20]
>> right? They should be up and going
[1:30:23]
probably after I don't know when when
[1:30:25]
they have time but everything is
[1:30:27]
submitted to them
[1:30:29]
and that's my report unless you have any
[1:30:31]
questions.
[1:30:32]
>> You guys have any questions?
[1:30:34]
>> Good.
[1:30:34]
>> Okay. Thank you. Um so I guess we'll
[1:30:37]
move on. Andrew's left the room so let's
[1:30:40]
go to water and sewer availability.
[1:30:43]
>> Okay.
[1:30:46]
>> Go ahead. Just go ahead.
[1:30:50]
Okay,
[1:30:51]
first one here is uh SLCE 319
[1:30:55]
development.
[1:30:57]
So this is uh let's see, I'm going to
[1:31:00]
pull it up on
[1:31:03]
GIS so we can see visually where this
[1:31:06]
is. Uh Ana Caroline Drive, uh Parkway
[1:31:10]
Boulevard, if you you know where the
[1:31:12]
Windco is over there. If you head north
[1:31:14]
along along that street
[1:31:17]
>> is that along the WCO road is right.
[1:31:19]
Okay, I know what you're talking.
[1:31:20]
>> Just keep heading north. 2400 south goes
[1:31:24]
over Mountain View and this is 2300
[1:31:27]
>> under Mountain View. Right.
[1:31:29]
>> Goes over
[1:31:30]
>> over the top.
[1:31:30]
>> Goes over the top.
[1:31:31]
>> Oh
[1:31:32]
>> yeah. But just Yeah. give you an idea of
[1:31:35]
where we're at. They this this
[1:31:37]
development has purchased
[1:31:40]
parcels on both sides of 2300 South and
[1:31:44]
what they're planning right now is a a
[1:31:45]
single warehouse to the north. Um and
[1:31:48]
you'll notice in the letter that we
[1:31:50]
reference our water and sewer in 2300.
[1:31:53]
Still be to be determined if that's
[1:31:55]
remaining in initial con conversations
[1:31:58]
that would remain. Right now it's in
[1:32:00]
rightway. we would get an easement as
[1:32:02]
part of that. But as far as providing
[1:32:05]
water and sewer, we have sufficient
[1:32:07]
flows, fire flow, um, and capacity, and
[1:32:13]
we'd recommend providing water and sewer
[1:32:15]
service to this development.
[1:32:18]
Do you have any questions?
[1:32:19]
>> I don't. We just We need a motion on it,
[1:32:21]
right?
[1:32:22]
>> Yep.
[1:32:25]
» So, Mr. Mr. Chairman, make a motion
[1:32:28]
uh for SLC 319 development located at
[1:32:32]
5750 West, 2300 South for sure and
[1:32:36]
water.
[1:32:37]
>> I'll second that.
[1:32:38]
>> A motion second. All in favor?
[1:32:40]
>> Okay, Trevor, I'll let you take the next
[1:32:42]
one and then we'll come back over to
[1:32:43]
Andrew.
[1:32:44]
>> Uh next one is Moody subdivision lot
[1:32:46]
number four. Um
[1:32:49]
if you recall there is we we had a
[1:32:53]
previous subdivision Moody Sillmaster.
[1:32:56]
Um and this is what that was was a
[1:32:59]
commercial development. They put in the
[1:33:01]
initial infrastructure with that
[1:33:03]
development and then they let the lots
[1:33:06]
were bare. Um and so as each of those
[1:33:09]
lots come in and develop, we're
[1:33:11]
evaluating what goes in there uh in
[1:33:14]
those connections. So this is lot number
[1:33:17]
four of that subdivision. We did lot
[1:33:20]
eight and nine.
[1:33:21]
>> So Trevor was one big lot and so then
[1:33:24]
they decided to subdivide it.
[1:33:26]
>> Correct.
[1:33:27]
>> How do we get the water and sewer? Do we
[1:33:29]
have to do a rightway to get to the back
[1:33:31]
lots?
[1:33:32]
>> So So when they did the overall
[1:33:36]
subdivision
[1:33:37]
>> Uhhuh.
[1:33:38]
>> we already had, and this is pretty
[1:33:40]
accurate, we already had water in here,
[1:33:43]
a water loop. Um, and they they ended up
[1:33:46]
putting in w a secondary and sewer back
[1:33:49]
into here. It's like a culde-sac. Um,
[1:33:52]
and then they stubbed out services to
[1:33:54]
each of these lots very similar to a
[1:33:58]
residential subdivision, but it's a
[1:34:00]
commercial one. And so when these lots,
[1:34:03]
all that main infrastructure is in. And
[1:34:06]
when these lots come in, then we know
[1:34:08]
what building type is going to be there.
[1:34:10]
And then we evaluate the service
[1:34:12]
specific to that to that building on
[1:34:14]
that lot.
[1:34:15]
>> So how many are still vacant then?
[1:34:18]
>> Oh, there's got to be one, two, three,
[1:34:22]
four, probably five.
[1:34:24]
>> Is there impact fees for each?
[1:34:26]
>> Correct.
[1:34:27]
>> Yeah.
[1:34:31]
» All right,
[1:34:33]
Mr. Mr. Chairman, I'd like to make a
[1:34:34]
motion for uh Moody subdivision lot 4
[1:34:38]
located 2258 South Moody Drive.
[1:34:42]
>> I'll second that.
[1:34:43]
>> A motion second. All in favor?
[1:34:45]
>> I I
[1:34:46]
>> Okay, Andrew, I'm coming back to you.
[1:34:47]
So, I'm all over the place this morning.
[1:34:49]
Apologize.
[1:34:49]
>> You're okay. I apologize. I had to step
[1:34:51]
out. I had a multiple phone calls from
[1:34:53]
an employee and would need to make sure
[1:34:54]
it wasn't an emergency. So, everything
[1:34:57]
was okay, though.
[1:34:58]
>> Okay.
[1:35:00]
Um
[1:35:01]
so as you can see we have 35 of our 36
[1:35:05]
positions currently filled here at the
[1:35:07]
district. Um some of the trainings that
[1:35:10]
we have coming up we have our uh our
[1:35:15]
bianual on-site CPR and first aid and
[1:35:18]
AED training coming up uh on the 23rd of
[1:35:21]
March. We have Jean Stock getting ready
[1:35:23]
to go to water efficient landscaper
[1:35:25]
training. Uh so he can care for our
[1:35:28]
gardens. It's through Jordan Valley.
[1:35:31]
>> Um it should be a good training.
[1:35:33]
>> Uh we have our team building coming up
[1:35:36]
in April for the second quarter and then
[1:35:38]
we have uh the fire department coming
[1:35:40]
out to do an on-site fire extinguisher
[1:35:42]
training with us at the end of April. Um
[1:35:46]
this month we're focusing on blood work
[1:35:48]
pathogens. It kind of coincides with the
[1:35:50]
first aid and CPR training. Uh so
[1:35:53]
everybody understands the risk that
[1:35:55]
they're taking on as they respond to any
[1:35:59]
emergency with first aid or CPR. Um got
[1:36:03]
some conferences coming up. Probably the next two that are coming up that are
[1:36:07]
going to be before the next board
[1:36:08]
meeting. Uh March 16th through 18th
[1:36:11]
water users in St. George. And then
[1:36:14]
March 21st through April 2nd, Utah GFAO
[1:36:18]
Le will be attending that.
[1:36:19]
>> Should be the 31st, not there.
[1:36:22]
>> That is a typo. Apologize.
[1:36:24]
>> That's That one's in St. George as well.
[1:36:27]
That's the government uh accounting
[1:36:29]
organization.
[1:36:31]
>> So, we've started the secession
[1:36:33]
planning. Um the managers went through
[1:36:36]
and filled out some information on where
[1:36:39]
they see the key positions are and needs
[1:36:42]
that are going to be coming up in future
[1:36:44]
years as well as some of the risks that
[1:36:46]
they're seeing. Uh right now we're in
[1:36:49]
the stage of the employees are filling
[1:36:51]
out a survey on positions that they
[1:36:54]
might be interested in filling and then
[1:36:56]
next week we'll start meeting with those
[1:36:58]
employees to uh align their goals with
[1:37:03]
the district goals. Um give them a
[1:37:05]
better understanding what what's going
[1:37:07]
to be available. Um and then lastly,
[1:37:10]
annual employee goals. We've wrapped
[1:37:13]
those up. We brought them to the board
[1:37:15]
to review. Um, we'll take any changes
[1:37:18]
that the board sees fit and then we'll
[1:37:21]
get started on them.
[1:37:23]
>> That's it for me, chair board. Thank
[1:37:25]
you. Is there any other questions?
[1:37:26]
>> On the uh April 22nd to the 24th, Jordan
[1:37:30]
Valley is putting that on. Is that
[1:37:32]
right?
[1:37:33]
>> Yes.
[1:37:33]
Correct.
[1:37:34]
>> And where will that be?
[1:37:35]
>> At their facility.
[1:37:37]
>> Yes.
[1:37:38]
>> Is any public invited to go there?
[1:37:40]
>> Um, yeah. I think anybody can do it.
[1:37:42]
landscapers, they they encourage
[1:37:44]
landscapers to get it so that they can
[1:37:48]
start performing those things here in
[1:37:50]
the communities when they go build
[1:37:51]
somebody's landscape.
[1:37:53]
>> So, is that make sure that the
[1:37:55]
contractors putting something in that
[1:37:57]
they could get a grant for, get
[1:37:59]
reimbured for?
[1:37:59]
>> I believe so.
[1:38:00]
>> That's what the whole thing is is for
[1:38:02]
qualifications.
[1:38:03]
>> Yes. We also have that class on the
[1:38:05]
15th, April 15th here that Jordan Valley
[1:38:08]
puts on the local scapes class and
[1:38:10]
they'll go over a lot of that
[1:38:11]
>> for the public.
[1:38:14]
>> Who teaches the class there?
[1:38:16]
>> They do.
[1:38:16]
>> It's Jordan Valley.
[1:38:17]
>> Oh, they come here.
[1:38:18]
>> So, is that that's at night, right?
[1:38:19]
>> You don't get that.
[1:38:20]
>> What time does that stop?
[1:38:21]
>> 5:30.
[1:38:22]
>> April 15th.
[1:38:23]
>> How How long does it go for?
[1:38:25]
>> It's about an hour.
[1:38:26]
>> Okay.
[1:38:27]
>> We had a pretty good turnout last time.
[1:38:29]
We
[1:38:29]
>> We did. We'll be getting a flyer put
[1:38:31]
together and sent out. So, so that one
[1:38:33]
that he's talking about is geared
[1:38:34]
towards homeowners. This is a larger
[1:38:37]
course that's geared towards landscapers
[1:38:39]
themselves. And then there's a Yeah. And
[1:38:41]
then there's a exam that they have to
[1:38:43]
pass to show that they're qualified.
[1:38:46]
>> Oh, wow.
[1:38:46]
>> And then that they carry that
[1:38:49]
qualification.
[1:38:51]
>> Okay.
[1:38:52]
>> Well, thank you, Andrew.
[1:38:53]
>> Yep.
[1:38:55]
>> Okay. Let's move it on to the part uh
[1:38:57]
our project reward and agreement. Uh
[1:38:59]
Trevor.
[1:39:00]
>> Okay.
[1:39:01]
Thank you, chair board. First one here
[1:39:03]
is for JUB engineers.
[1:39:06]
Um, if you remember, they helped us with
[1:39:09]
design of Westside Collection project
[1:39:12]
number two. Um,
[1:39:14]
as they got done wrapping that up, I
[1:39:17]
believe they did a really good job, uh,
[1:39:20]
very thorough, um, responsive to our
[1:39:23]
concerns and our comments during that
[1:39:26]
design. and we had anticipated doing um
[1:39:31]
project number three design as well. So
[1:39:34]
I asked them to put together um this
[1:39:38]
task order um scope and fee for design
[1:39:41]
of Westside Coll sorry Westside
[1:39:44]
Collection project number three and
[1:39:46]
that's what this is for.
[1:39:49]
Um if you have any specific questions to what's in there um otherwise
[1:39:55]
>> is going to be on and above what's
[1:39:57]
already been approved or
[1:39:59]
>> so they did we we had already approved
[1:40:02]
um Westside Collection project 2 and
[1:40:04]
they and we took that to 95% because we
[1:40:07]
weren't going to bid it. So those specs
[1:40:09]
and and plans are complete. Um, and then
[1:40:13]
we wanted to move to designing project
[1:40:15]
number three, and that's where this
[1:40:18]
scope and fee is for.
[1:40:20]
>> So, Mr. Chairman, I'd like to make a
[1:40:21]
motion to approve the
[1:40:24]
JUB task order for Westside Collection
[1:40:27]
Project 3, design and bidding in the
[1:40:29]
amount of $190,200.
[1:40:32]
>> I'll second that.
[1:40:33]
>> Motion a second. All in favor? I
[1:40:35]
>> I
[1:40:36]
Trevor.
[1:40:37]
>> Thank you. Um,
[1:40:40]
jump back here.
[1:40:43]
Okay. Uh, we just talked about Westside
[1:40:47]
Collection. So, this easement is for
[1:40:50]
Westside Collection project number two.
[1:40:53]
There's a large portion of our existing
[1:40:55]
sewer. Um, I'll pull up a map here that
[1:40:58]
runs along Highway 2011
[1:41:01]
along the south side between 8000
[1:41:06]
west and 8,400 west. And as part of
[1:41:10]
project number two, we're going to
[1:41:11]
parallel that sewer line. It's this one
[1:41:14]
here. You can
[1:41:15]
>> What's the offset?
[1:41:17]
>> Offset.
[1:41:18]
>> Yeah.
[1:41:19]
It's roughly
[1:41:21]
it it differs a little bit but generally
[1:41:24]
around 30 ft of separation between the
[1:41:26]
two and that puts us a little bit
[1:41:28]
further to the south which essentially
[1:41:31]
all these parcels are kicott parcels. Um
[1:41:35]
primarily the existing line remained in the UD do rideway. um with our new
[1:41:42]
alignment, we're needing some easement
[1:41:45]
from Kennot for this new line. And so
[1:41:48]
that's what this easement agreement is.
[1:41:51]
Um we we have a pretty standard easement
[1:41:54]
agreement with Kakott that we've used
[1:41:56]
throughout the district over time. It's
[1:41:58]
changed a little bit. So we've gone
[1:42:00]
through this, reviewed it with them.
[1:42:01]
Nathan and I have both looked at this
[1:42:04]
and reviewed. Um and if you It gives us
[1:42:08]
the easement that we need for access. um
[1:42:11]
to maintain this sewer line. And if you
[1:42:15]
look at the last page in your packet
[1:42:19]
with this one, you'll see a cost
[1:42:23]
associated with that easement.
[1:42:27]
Keep scrolling.
[1:42:30]
>> You were able to cut that down a little
[1:42:32]
bit.
[1:42:33]
So in discussions with them um these are in their mind and according to
[1:42:42]
what they've been offered kind of prime
[1:42:45]
areas near 8,000 near 2011 and so
[1:42:49]
they've actually got some offers for
[1:42:50]
these properties that are quite high. Um
[1:42:54]
and they weren't interested in
[1:42:56]
negotiating the easement cost.
[1:42:58]
>> Well,
[1:43:00]
yeah,
[1:43:00]
>> it doesn't hurt to try. We're beholden
[1:43:02]
to that. We do need it. Um I you know
[1:43:06]
they're still fair in the respect that
[1:43:08]
they're they're looking at a 20%.
[1:43:11]
A lot of easements when people are
[1:43:13]
getting those they can be a lot higher
[1:43:15]
than that. Um so that equals out to $6 a
[1:43:19]
square foot. We've got 27,955
[1:43:23]
square feet for a total of $167,730.
[1:43:28]
Um so as part of this you know uh
[1:43:32]
approving the going through with the
[1:43:34]
agreement it would also be to pay that
[1:43:36]
cost for the easement.
[1:43:37]
>> Okay. So that cost has to be associated
[1:43:40]
with that.
[1:43:41]
>> Okay. So um
[1:43:45]
Mr. Mr. Chairman, I'd like to make a
[1:43:46]
motion to approve the lease agreement
[1:43:48]
with Kennott or
[1:43:50]
>> the easement.
[1:43:52]
>> Oh, the easement agreement with Kennott
[1:43:54]
on Westside Collection Project 2, the
[1:43:57]
amount of 167730
[1:44:01]
$167,730
[1:44:05]
in motion second. All in favor?
[1:44:08]
>> K. Dallas.
[1:44:08]
>> Thank you.
[1:44:09]
chair and board. Uh we've got
[1:44:11]
today presenting the annual acoustic
[1:44:14]
assessment project um that we partnered
[1:44:17]
with RH Bordon. We're targeting this
[1:44:19]
year 250,000 linear feet or or just
[1:44:23]
under 50 miles of sewer pipeline. Um
[1:44:27]
I've got a picture of a map to kind of
[1:44:29]
talk through about how we're
[1:44:31]
prioritizing and targeting the system.
[1:44:33]
>> Wow.
[1:44:34]
>> Anything that's orange has been done and
[1:44:37]
we have a solid baseline on. We won't
[1:44:40]
redo that this year. Um, anything in
[1:44:43]
that main trunk corridor that's red,
[1:44:45]
yellow, and green, we'll target that
[1:44:47]
area specifically. Um, we no longer
[1:44:51]
assess downtown Magna. We know that
[1:44:54]
based on um, pipe conditions and roots
[1:44:58]
and stuff, we have to flush that twice a
[1:45:00]
year. So, we don't inspect that
[1:45:02]
acoustically. Um, and then on those main
[1:45:04]
trunk lines, we don't acoustically
[1:45:06]
inspect those. We did it initially to
[1:45:09]
establish that baseline and then get
[1:45:11]
these geo tags so that we can populate
[1:45:13]
these these uh base maps into our GIS
[1:45:17]
system. But really the
[1:45:21]
our our strategy is that center corridor
[1:45:26]
um that's where we spend most of our
[1:45:27]
time. These guys will come in and
[1:45:29]
they'll assess all of that. Um that
[1:45:32]
would take us over a year to do. They
[1:45:34]
can come in and help us out with that.
[1:45:36]
It gives it gives each section that's
[1:45:39]
assessed a grade from good to poor. If
[1:45:44]
there's anything that comes up that's,
[1:45:46]
you know, on a 1 to 10, five or less,
[1:45:48]
it'll automatically send us an alert and
[1:45:50]
we'll be able to go and target that
[1:45:52]
section specifically. So, um,
[1:45:54]
>> does that determine that determine leaks
[1:45:57]
or quality of the material?
[1:45:59]
>> It'll it'll detect any type of blockage
[1:46:01]
or flow restriction.
[1:46:02]
>> Oh, okay. That's all it is is for flow
[1:46:05]
or blockage. Yeah. Um it's been a great
[1:46:08]
service for us. So they're now you know
[1:46:13]
through your permit you have to inspect
[1:46:16]
your entire system x amount of times per
[1:46:19]
x amount of years. Um this is now an
[1:46:22]
approved inspection device. So if we run
[1:46:25]
through this with if we run this
[1:46:27]
equipment through our system, we can
[1:46:29]
check that box as an inspection. So, um,
[1:46:32]
>> so everything you've got green and red
[1:46:35]
now will be yellow by next year.
[1:46:37]
>> No. So, when you look at that, those are
[1:46:40]
the different grades that have come
[1:46:41]
back. So, X amount of our system is
[1:46:43]
green, which is a grade of seven or
[1:46:47]
higher. Anything that's yellow would be
[1:46:49]
seven to like four, and then anything
[1:46:51]
that would be red would be three to
[1:46:53]
zero. Um so if you see something that on
[1:46:57]
that inspection day um resulted in a red
[1:47:02]
section then we would go out immediately flush that and then it'll go
[1:47:06]
back to green. So it's just one way to
[1:47:09]
track and then we've got a dashboard
[1:47:11]
that we can layer the data
[1:47:13]
year-over-year so we can see how much
[1:47:15]
we're improving. Right now we've got
[1:47:17]
about 95% of our system is seven or
[1:47:23]
higher. Oh wow, that's good.
[1:47:25]
>> So, but without the data, we're just
[1:47:28]
guessing.
[1:47:28]
>> Um, but this is a this is using
[1:47:32]
technology to strategically maintain and
[1:47:36]
assess our system.
[1:47:37]
>> That's pretty cool.
[1:47:38]
>> Yeah.
[1:47:39]
>> So, I remember when they came up with
[1:47:41]
that saves a lot of men.
[1:47:44]
>> And what what we're asking for on this
[1:47:46]
contract, Mr. Chairman, is just uh
[1:47:48]
64,500
[1:47:50]
is the dollar amount.
[1:47:54]
Okay.
[1:47:55]
>> How many miles of pipe is that?
[1:47:57]
>> It's about 47.5.
[1:47:59]
>> Say 47.
[1:48:04]
» Okay. Mr. Chairman, I'd like to make a
[1:48:06]
motion to approve the annual acoustic
[1:48:09]
inspection services with RH Bordon
[1:48:13]
the collection system in the amount of
[1:48:15]
$64,500.
[1:48:17]
>> I'll second that.
[1:48:18]
>> In motion second. All in favor? Hi.
[1:48:20]
>> Hi.
[1:48:21]
>> Okay, Trevor, let's do the lease
[1:48:22]
agreement with Kakott.
[1:48:23]
>> Okay,
[1:48:25]
so water right lease agreement. Um, this
[1:48:29]
is for a kakott spring right uh 593198.
[1:48:34]
And right now we collect that water and
[1:48:36]
we put it in our zone 2 reservoir.
[1:48:38]
>> Um, and we've been doing that since that
[1:48:40]
reservoir was built um, 2021. And we do
[1:48:44]
an application or rather Kakott fills
[1:48:48]
out an application each year, a
[1:48:50]
temporary change application to allow us
[1:48:52]
to use that water. At the back in 21
[1:48:57]
when we first started taking the water,
[1:48:59]
there was talk of a lease agreement.
[1:49:01]
There was a draft of it and it went
[1:49:04]
nowhere. Uh we don't truly know where
[1:49:07]
the hangup was. It seemed like uh
[1:49:11]
>> that's personnel changes
[1:49:12]
>> personnel changes at Kennott and it
[1:49:14]
slipped through, but um they reached out
[1:49:17]
to us several months ago last late last
[1:49:20]
year um talking about this lease
[1:49:23]
agreement. They wanted to get it back in motion and get it in place.
[1:49:27]
>> Is this a little creek that runs down?
[1:49:30]
>> We've piped it from within their
[1:49:32]
property and it goes makes its way over
[1:49:35]
to our reservoir.
[1:49:38]
Um, it was like 10 I want to say 10
[1:49:42]
roughly 10 acre feet
[1:49:45]
a year. Um, it's not a tremendous
[1:49:49]
amount, but
[1:49:50]
>> what what I've been told like over the
[1:49:53]
winter time, you know, we'll lower the
[1:49:54]
level of our reservoir and it's full. I
[1:49:59]
mean, it's just a constant flow of
[1:50:01]
water. Um,
[1:50:02]
>> so maybe it's depending on how much rain
[1:50:05]
water we get. We've seen it fluctuate a
[1:50:07]
little bit.
[1:50:08]
>> Oh, really?
[1:50:08]
>> Um, we measure it every month and that's
[1:50:11]
how we report to Kakott that reports to
[1:50:14]
water rights.
[1:50:15]
>> Kennot probably has got a water right on
[1:50:17]
that water.
[1:50:18]
>> They do and they need beneficial use. We
[1:50:20]
provide that. So, with with all of that,
[1:50:23]
they would like a a lease agreement in
[1:50:25]
place. Um,
[1:50:28]
>> the right is 29 acre feet, but we we
[1:50:32]
have not seen it produce that much. Um,
[1:50:34]
like I said, around 10 acre feet each
[1:50:37]
year. Um, if you scroll through, what
[1:50:41]
this comes with is a cost to the
[1:50:42]
district. Um, and
[1:50:47]
the way it's structured here is year 1
[1:50:49]
through five, which they want to go
[1:50:51]
retroactive back to 2021 through end of
[1:50:54]
26. It would be $10 per acre foot. So 10 time 10 $100. I mean, we're $100.
[1:51:04]
cost us more to to write it up.
[1:51:07]
>> Yeah.
[1:51:08]
>> Um so it's it's a pretty in
[1:51:11]
insignificant amount of water. Um but
[1:51:15]
they would like this in place and
[1:51:16]
>> just trying to get credit for it, right?
[1:51:18]
>> Yeah. I think within their to be able to
[1:51:20]
lease that water and and have it
[1:51:22]
>> right.
[1:51:23]
>> Yeah.
[1:51:23]
>> Have it documented this way is important
[1:51:25]
to them. I
[1:51:27]
>> Well, they never want to be accused of
[1:51:29]
giving something away. I can think uh
[1:51:31]
back in the day that those guys grabbed
[1:51:33]
the water that was going down creek
[1:51:35]
that's been a plus for us.
[1:51:37]
>> Yeah.
[1:51:37]
>> Uh if the state would have got a hold of
[1:51:39]
that that could have been pretty bad.
[1:51:41]
>> Yeah.
[1:51:41]
>> And I think it actually helped us be
[1:51:43]
able to get it over in C7. Right.
[1:51:46]
>> Yeah. So,
[1:51:48]
um I I recommend
[1:51:52]
approving this lease and allowing us to
[1:51:54]
move forward with Kennot
[1:51:55]
>> the lease agreement.
[1:51:56]
>> Yep.
[1:51:58]
>> Um
[1:51:59]
So, Mr. Chairman, I make a motion to
[1:52:02]
approve the lease agreement with Kennoff
[1:52:04]
for Water Ride 59-3198.
[1:52:08]
» I'll second that.
[1:52:09]
>> Motion second. All in favor?
[1:52:11]
>> I
[1:52:12]
>> Okay, Trevor.
[1:52:13]
>> Okay, last one.
[1:52:14]
>> All on you.
[1:52:16]
>> Okay, this is a storm drain easement.
[1:52:19]
Um, we've discussed this in the past. Um
[1:52:23]
there's construction waste management,
[1:52:25]
the waste management company near the
[1:52:27]
wastewater treatment plant. Um their
[1:52:30]
intention is to reroute some storm water
[1:52:33]
that runs through their property so that
[1:52:35]
they can expand their waste site. And in
[1:52:39]
doing so, they've approached us for an
[1:52:42]
easement through a portion of a
[1:52:44]
wastewater treatment plant property
[1:52:47]
um over to take that, you know, pipe it
[1:52:50]
and move the storm water into um
[1:52:54]
what's that?
[1:52:55]
>> Kersy.
[1:52:55]
Yep. Kersy Creek.
[1:52:58]
>> Did they take out the reservation? Did
[1:53:01]
Are they the ones that marked this out
[1:53:02]
or did we mark that out? Another
[1:53:04]
>> us. So, so I'm in um Nathan and I are
[1:53:09]
still working through this um some back
[1:53:11]
and forth and but what I'm I guess what
[1:53:15]
I'm looking for here is um you know we
[1:53:19]
we've discussed providing this easement.
[1:53:22]
Um so just an approval to continue to
[1:53:27]
refine this agreement with with Nathan
[1:53:29]
and myself and and move forward with
[1:53:32]
them on providing the easement. One of
[1:53:34]
the things is that we've kind of had
[1:53:37]
some back and forth with them. First, it
[1:53:40]
sounded like it was an easement to
[1:53:42]
construction waste management and then
[1:53:43]
it
[1:53:45]
they provided something that had Magnus
[1:53:47]
City on it and that that made some, you
[1:53:50]
know, confusion on our end and I've
[1:53:52]
gotten to the bottom of it. What they're
[1:53:54]
working on with Magnus City is a storm
[1:53:56]
drain um like management agreement. So
[1:54:00]
this storm drain pipe would be owned and
[1:54:04]
managed by construction waste
[1:54:06]
management. It wouldn't be turned over
[1:54:07]
to any public agency and that's where
[1:54:09]
this agreement is with them um
[1:54:14]
specifically and not with any city or
[1:54:17]
>> other entity.
[1:54:19]
>> No. And we'll make sure that that that
[1:54:22]
agreement is you know we're not
[1:54:24]
providing an easement if that agreement
[1:54:27]
isn't in place.
[1:54:28]
>> Okay.
[1:54:28]
>> Does that make sense? So,
[1:54:31]
>> so Mr. Chairman, I'd like to make a
[1:54:33]
motion to approve the uh storm drain
[1:54:36]
easement agreement to be granted to
[1:54:38]
construction wast.
[1:54:40]
>> I'll second that.
[1:54:41]
>> Motion second. All in favor?
[1:54:43]
>> I
[1:54:45]
>> Okay, let's move on. Andrew Levolution.
[1:54:52]
» Um, you want to take that first one le?
[1:54:56]
>> Yeah, sure. Oh, so this is our
[1:54:58]
resolution 202602
[1:55:01]
and it includes
[1:55:04]
basically
[1:55:06]
three changes to our ARRS. So the first
[1:55:10]
portion of the resolution is changing.
[1:55:13]
Sorry, let me get
[1:55:14]
>> section A.
[1:55:16]
>> 6.4.
[1:55:17]
>> Yeah. So the first one is isn't it the proceed or
[1:55:24]
purchases?
[1:55:25]
>> Yes.
[1:55:25]
>> Yeah. Okay. So, it takes uh Clint's
[1:55:28]
authorization from 50 to 100,000 um that
[1:55:31]
was recommended by the board last month.
[1:55:34]
>> And then the following B letter B
[1:55:37]
through F I believe has to do with um
[1:55:40]
>> the new junior executive
[1:55:42]
>> adding our junior executive
[1:55:44]
classification in the AR and are where
[1:55:46]
it's applicable.
[1:55:48]
>> Just can I speak to that? So, so most of
[1:55:51]
the changes to the junior executives are
[1:55:53]
in addendum E of the AR&Rs and that's
[1:55:55]
the addendum that goes over all of their
[1:55:57]
benefits, but we also needed to make
[1:55:59]
some conforming changes throughout other
[1:56:01]
sections of the A&R. So, this is kind of
[1:56:03]
structured just sequentially with the
[1:56:05]
numbers of your section, but
[1:56:07]
categorically we're increasing Clint's
[1:56:09]
purchasing threshold.
[1:56:10]
>> Then the rest of these changes are
[1:56:12]
dealing with just junior executive
[1:56:14]
stuff. So it's it'll look weird as you
[1:56:16]
go through because we're saying we're
[1:56:17]
adopting the attached version of Adende
[1:56:19]
and then we're amending all these other
[1:56:20]
sections. And then the third category
[1:56:22]
and I'm just beating Lelay all to the
[1:56:24]
punches
[1:56:25]
>> is to make our language consistent with
[1:56:27]
the three tardies policy that you had.
[1:56:29]
We had some inconsistency in the AR. So
[1:56:31]
using the same term
[1:56:33]
>> and that's all that this resolution
[1:56:35]
does.
[1:56:36]
>> I sorry I figured that would be easier
[1:56:38]
than going through like nine different
[1:56:39]
lines of technical legal changes.
[1:56:42]
>> Thank you.
[1:56:44]
That looks good.
[1:56:45]
>> So, we have to uh we have to um approve
[1:56:48]
it, right?
[1:56:49]
>> Yeah. So, what'll happen is is the way I
[1:56:51]
drafted this resolution is if this is
[1:56:53]
acceptable to you, you'll approve it and
[1:56:55]
then we will then implement these
[1:56:57]
changes to the AR&Rs which will be easy.
[1:56:59]
We'll have to update the you know
[1:57:01]
pageionation and things like that and
[1:57:02]
then we'll get it uploaded.
[1:57:03]
>> Yeah, that makes it good. And one of
[1:57:05]
those forms that you signed, Mick, kind
[1:57:07]
of prompted this because,
[1:57:09]
>> right,
[1:57:09]
>> our APA benefits that administers the
[1:57:12]
benefits,
[1:57:13]
>> right?
[1:57:14]
>> One of this signed and approved. So,
[1:57:18]
>> so, Mr. Chairman, do I want to make a
[1:57:20]
motion?
[1:57:20]
>> Yes.
[1:57:21]
>> Mr. Chairman, I'd like to make a motion
[1:57:22]
to approve resolution 2026-02,
[1:57:27]
approve the changes to the district's uh
[1:57:30]
A&R as outlined in in that resolution.
[1:57:34]
I'll second that
[1:57:35]
>> in motion second. All in favor?
[1:57:37]
>> I
[1:57:39]
>> Okay, we don't need to do number two.
[1:57:41]
We've already had that discussion
[1:57:43]
information discussion only. No, no
[1:57:46]
action. Nathan, do you want to give an
[1:57:47]
update on the legislation?
[1:57:50]
>> Yep. I know this is your favorite part
[1:57:51]
of the meeting in the year. Um, so I've
[1:57:55]
got a few bills. I'll go through them
[1:57:57]
quickly. The first is HB147. that's
[1:57:59]
going to require all government entities
[1:58:01]
to provide an option for people to
[1:58:03]
submit any forms or permit applications
[1:58:06]
or things like that electronically.
[1:58:09]
So, I mean, we can have the form and
[1:58:11]
they can fill it out. There just needs
[1:58:12]
to be a way that they can submit it
[1:58:13]
electronically. Um, I think that's
[1:58:16]
already kind of happening via email, but
[1:58:17]
now it's so I don't think that's going
[1:58:19]
to be a big deal. Um, another one that actually may be important for you
[1:58:23]
is HB296.
[1:58:25]
What that does is it allows for water
[1:58:27]
that is being leased or provided to the
[1:58:30]
Great Salt Lake, which you were doing,
[1:58:31]
to be included in your 40-year plan,
[1:58:34]
which is the topic of another bill that
[1:58:35]
I'll get to. But essentially, with with
[1:58:38]
public entities like you guys, you can
[1:58:40]
hold your water rights without
[1:58:42]
perfecting them for a period of 40
[1:58:44]
years. And during that time, you're
[1:58:45]
entitled to get any extension that you
[1:58:47]
want. Once you hit 40 years, then the
[1:58:49]
state's like, "Okay, you know, we don't
[1:58:51]
want you just to hoard water. You've got
[1:58:53]
to have a plan showing how you're going
[1:58:54]
to use it for the next 40. Actually, I
[1:58:55]
think it's 50 years and then you have to
[1:58:57]
show how it's going to be used for the
[1:58:58]
next 40.
[1:58:59]
>> So, if we have a plan, we're okay. We
[1:59:01]
can even roll it over after
[1:59:03]
>> it just the So, the point is is our
[1:59:05]
state's water laws are intended to
[1:59:07]
ensure that people actually use the
[1:59:09]
water and they're not hoarding it.
[1:59:10]
>> So, public water suppliers are a little
[1:59:12]
different. So, for instance, if we were
[1:59:14]
to go out and prove up all your water
[1:59:15]
right now, the state engineer would just
[1:59:17]
give you a certificate for what you're
[1:59:19]
using right now, not for what your water
[1:59:21]
rights are approved. And so for a
[1:59:22]
growing community like you guys, you
[1:59:24]
have a lot of water that you have on
[1:59:26]
standby that isn't being used yet.
[1:59:28]
That's the intent here. But the
[1:59:30]
legislature or the state at the same
[1:59:32]
time, it's like, okay, you've had this
[1:59:34]
water, it's been approved for 50 years.
[1:59:36]
Like, are you going to need it or not?
[1:59:37]
You got to show us a plan that there is
[1:59:39]
an actual chance it'll be used in the
[1:59:41]
next 40 years. What this does is it says
[1:59:43]
that if you're leasing water to the
[1:59:44]
Great Salt Lake, that counts as part of
[1:59:46]
your 40-year plan. So otherwise, absent
[1:59:50]
this bill, if we continue to lease water
[1:59:52]
the Great Salt Lake, they could say,
[1:59:53]
"Well, you're not using that water, and
[1:59:55]
that doesn't qualify."
[1:59:57]
>> Excuse me.
[1:59:58]
>> So, does this account also for
[2:00:00]
groundwater, well water?
[2:00:01]
>> Yeah. But well, what this bill does is
[2:00:03]
any water right that you're leasing,
[2:00:05]
which is almost always surface water.
[2:00:07]
People aren't leasing groundwater the
[2:00:08]
lake, but it it I don't think it's
[2:00:10]
limited to surface or groundwater. So,
[2:00:11]
the point is is that and we we we're
[2:00:14]
going to have to do a 40-year plan under
[2:00:15]
another bill that I'll get to in a
[2:00:16]
second, but when we do it, we can
[2:00:18]
include those shares. So, the next thing
[2:00:21]
is um HB 319. Uh this, I think, is a
[2:00:25]
good bill. It provides a process by
[2:00:26]
which we can have electronic notary
[2:00:29]
documents be filed with the the the
[2:00:31]
county. Um it's not mandatory, but it
[2:00:34]
provides an option by which the county
[2:00:36]
recorders can allow that. So, that makes
[2:00:37]
it a lot easier if we can do electronic
[2:00:39]
notoriization instead of having people
[2:00:41]
come and physically sign. We'll see what
[2:00:42]
the county recorders want to do. Um,
[2:00:45]
there's some grammar changes. HB325 is
[2:00:48]
one we'll need to go over those. Um,
[2:00:52]
there's another bill, HB349, that comes
[2:00:55]
it provides a new process by which you
[2:00:57]
can apply for money from the Board of
[2:00:59]
Water Resources to help increase
[2:01:00]
reservoir capacity. I know you have a
[2:01:02]
few small ones there. Um,
[2:01:06]
there was a big bill that we talked
[2:01:07]
about, HB501. This was the bill that was
[2:01:10]
going to essentially require local water
[2:01:12]
providers to impose a a local income tax
[2:01:15]
essentially to help fund infrastructure
[2:01:18]
projects. It was modified several times,
[2:01:20]
but as we estimated, I think it was
[2:01:21]
going to be what, $1,400 a year per
[2:01:23]
connection. That bill ultimately did not
[2:01:26]
pass at the last minute. Um, was kind of
[2:01:28]
watching that till the end of the day. I
[2:01:30]
do expect we're going to see something
[2:01:32]
similar. My recommendation to rural
[2:01:34]
water and to um the UASD and the water
[2:01:38]
communities in general is the water
[2:01:40]
community needs to come up with a
[2:01:41]
proposal uh because to be fair to the
[2:01:44]
legislature they are trying to fill a
[2:01:45]
huge gap in the federal funding that
[2:01:47]
we're no longer getting and it's an
[2:01:49]
issue that needs to be addressed and if
[2:01:50]
the water community doesn't come up with
[2:01:52]
a way to fund it then the legislature is
[2:01:53]
going to keep coming up with proposals
[2:01:55]
we may not like. Um the other one uh
[2:01:58]
there is a new bill HB535 that comes up
[2:02:00]
with a new process by which a public
[2:02:03]
entity has to follow before they can
[2:02:04]
dispose of property. So for some of the
[2:02:06]
properties we've acquired if we ever
[2:02:07]
wanted to sell them. But the long and
[2:02:09]
short of is we have to go through a
[2:02:10]
45day notice period so people have an
[2:02:12]
idea that we're selling it.
[2:02:14]
>> Um perhaps the the the biggest bill
[2:02:16]
that's going to require us to do things
[2:02:18]
is SB284. Each year the legislature has
[2:02:21]
a very large land use bill that is
[2:02:23]
passed that isn't typically targeted at
[2:02:25]
water but often has uh tangential
[2:02:28]
impacts and and that bill usually passes
[2:02:31]
at the very end of the session. That was
[2:02:33]
the case here. This was SB284. It was
[2:02:35]
passed at 11:45
[2:02:38]
on Friday, so 15 minutes before the end
[2:02:40]
of the session. Um so what it does is it makes detached ADUs a permitted use.
[2:02:47]
Um, we and I think we're going to have
[2:02:49]
to sit down and figure out to change our AR&Rs on how to deal with that. We
[2:02:53]
had some language years a couple years
[2:02:55]
ago where it allowed basement ADUs to
[2:02:57]
basically be a permitted use. So, um,
[2:03:01]
that's that was something we'll need to
[2:03:03]
work with. And the other one is what I
[2:03:05]
said before, and that is if a water
[2:03:07]
provider is requiring a water exaction,
[2:03:09]
which has typically been a a water
[2:03:12]
dedication, you have to have a 40-year
[2:03:14]
plan that I discussed before in order to
[2:03:17]
do that. And you have to have that in
[2:03:18]
place by January 1st, 2028. And
[2:03:21]
technically, the way the bill's drafted
[2:03:22]
is you have to have it we we all need to
[2:03:24]
do it if you're a culinary water
[2:03:26]
provider. And I do we have a a 40-year
[2:03:29]
plan?
[2:03:30]
>> Yeah.
[2:03:31]
>> So, we already have one. we're probably
[2:03:33]
in good shape. It may we may want to
[2:03:35]
update that now to include the water
[2:03:37]
that we're leasing to the Great Salt
[2:03:39]
Lake. And there were other some some
[2:03:40]
other Great Salt Lake bills that um
[2:03:44]
allow for water to be like for instance
[2:03:46]
if we wanted to add the Great Salt Lake
[2:03:48]
as a permanent place of use for your
[2:03:51]
shares. So, you know, that that's
[2:03:53]
another option now. So, you wouldn't
[2:03:55]
have to necessarily use it all the time.
[2:03:57]
It would just be there for for leasing
[2:03:59]
when it's available. So that's
[2:04:01]
essentially my report unless you have
[2:04:02]
any questions.
[2:04:04]
>> Cool.
[2:04:04]
>> Thanks, Nathan.
[2:04:07]
We're all done now up there for right
[2:04:08]
now.
[2:04:10]
>> Yeah. Just it'll just take us another
[2:04:12]
couple months to implement it all.
[2:04:14]
>> This is this large amount of the most
[2:04:17]
bills they
[2:04:18]
>> every year is the most they have. So
[2:04:20]
they broke a record last year. They had
[2:04:21]
over a thousand bills this year. There was legislation by Representative
[2:04:25]
Oerlin to limit the number of bills that
[2:04:27]
the legislature can have, but it didn't
[2:04:29]
make any progress. He's a new
[2:04:30]
representative, and his argument was
[2:04:32]
we're introducing so many bills, we
[2:04:34]
can't review them or vet them or process
[2:04:36]
them appropriately. But I I there's it's
[2:04:39]
just a it's a the
[2:04:43]
end of January through first week of
[2:04:45]
March is just a it's a marathon.
[2:04:47]
>> Were there bills they tried to pass that
[2:04:49]
was out of the time limit? There was I
[2:04:53]
think one bill that there's a question
[2:04:55]
on that and I think they ultimately did
[2:04:57]
determine that it was outside of the the
[2:05:01]
time limit and that was one that
[2:05:02]
Representative Tusher ran to create a
[2:05:06]
process by which um
[2:05:09]
people in a first class county which is
[2:05:11]
basically only Salt Lake County at this
[2:05:13]
point where they could divide it and I
[2:05:14]
think his his motivation wasn't to force
[2:05:16]
a split of Salt Lake County but to give
[2:05:18]
Westside interests an ability to split
[2:05:21]
with the county if they wanted to, but
[2:05:23]
that I think passed just like a couple
[2:05:26]
seconds after midnight. So, I I think
[2:05:28]
that was one that they ultimately ruled,
[2:05:30]
don't quote me, that it didn't pass in
[2:05:32]
time. Um,
[2:05:33]
>> you don't know if it passed or not.
[2:05:35]
>> Well, I know it passed. I just think it
[2:05:37]
passed right after because they're they
[2:05:39]
have so many things they are working
[2:05:41]
like they're moving and then midnight
[2:05:43]
hits and they just got to
[2:05:45]
>> the coach turns into a pumpkin and it's
[2:05:47]
done. Yeah.
[2:05:48]
>> Is that the one where they can make a
[2:05:50]
county within the city?
[2:05:52]
>> No.
[2:05:53]
>> That was divided up, right?
[2:05:55]
>> Yeah. Well, it was a process. What what
[2:05:57]
he was trying to do is not force a
[2:05:59]
split, but just say, "Hey, if if you're
[2:06:00]
in a county of the first class and you
[2:06:02]
think it's too big and you want a
[2:06:04]
smaller county, here's the process you
[2:06:06]
go through to split into two."
[2:06:08]
>> How long does that process take?
[2:06:09]
>> I I don't know. The bill didn't It
[2:06:12]
passed, but it's not going into effect
[2:06:13]
because it didn't pass it.
[2:06:14]
>> It'll probably come up next year now.
[2:06:16]
>> Yeah, it'll come up next year. And one
[2:06:17]
of the ones that I really like the most
[2:06:19]
too is the charter schools don't ain't
[2:06:22]
equal with the public schools. So when
[2:06:24]
the public school sells the land, they
[2:06:26]
they're not equal with us. We have we um
[2:06:30]
the public schools um don't have to have
[2:06:33]
I mean we don't have to give the charter
[2:06:35]
schools, you know, first. They follow
[2:06:38]
under the city and that for whenever
[2:06:41]
they're selling.
[2:06:42]
>> So yeah. So that bill was so right now
[2:06:45]
certain municipalities that have a
[2:06:46]
population density of over 3,000 people
[2:06:49]
per acre have a first right of refusal
[2:06:51]
if a school district sells property
[2:06:53]
within their boundaries. Magna doesn't
[2:06:56]
currently meet that because your density
[2:06:58]
isn't that high. But what this bill was
[2:07:00]
going to do initially it was going to
[2:07:02]
give um charter schools that first rural
[2:07:06]
the league and and Mick and Karns Magna
[2:07:08]
and others pushed back on that. Holiday
[2:07:11]
and I think a couple other cities and we
[2:07:13]
were able to get it to be kind of a
[2:07:14]
co-equal thing for every city. So every
[2:07:17]
city would have a co-equal uh approach
[2:07:20]
with the charter schools regardless of
[2:07:22]
population density. But then the bill
[2:07:24]
ultimately didn't pass. So
[2:07:26]
>> are we going to see a lot more charter
[2:07:27]
schools popping up now?
[2:07:29]
>> I I the state's very pro-charter
[2:07:31]
schools. So I think we have and I think
[2:07:33]
we will continue to see them. I don't
[2:07:35]
know if you'll see them. Um,
[2:07:38]
usually usually charter schools in my
[2:07:41]
experience seem to be proposed by
[2:07:42]
developers in places where there isn't
[2:07:44]
an existing school. And so here where
[2:07:46]
you already have pretty good coverage
[2:07:48]
and you have a brand new school, it
[2:07:50]
seems unlikely that there would be a
[2:07:51]
need. But then you have concerned
[2:07:53]
parents that just want to have a charter
[2:07:54]
school that deals with specific things.
[2:07:56]
So
[2:07:56]
>> I I don't know if you'll see any in
[2:07:58]
Magna, but I think you'll probably see
[2:07:59]
charter schools continue to pop up
[2:08:01]
throughout the state. How do they g how
[2:08:03]
does how does the public gauge how full
[2:08:08]
I I'm assuming if a charter school is
[2:08:10]
filling up pretty fast? Of course there
[2:08:13]
again gender I mean kids move on get
[2:08:16]
older and then they go to high school
[2:08:17]
whatever but uh how do they gauge the
[2:08:21]
how crowded the the charter school
[2:08:24]
becomes? I mean if it gets real crowded
[2:08:25]
do that oh we better build another one
[2:08:27]
or
[2:08:28]
>> Well charter schools are I I'm not a
[2:08:30]
charter school expert. I'll find it
[2:08:32]
through. Tell me if I'm right or wrong.
[2:08:33]
It's pretty much developers that are
[2:08:35]
building these charter schools.
[2:08:37]
>> Yeah, but not always. You know, where I
[2:08:39]
live in Daybreak, you know, we've been
[2:08:40]
there for almost 20 years and we were in
[2:08:43]
the old section and the parents there
[2:08:44]
started their own, which is still there.
[2:08:46]
But I think the difference between a
[2:08:47]
charter school is charter schools kind
[2:08:49]
of have an admissions process. They're
[2:08:51]
not required to take everybody the way a
[2:08:53]
public school does, right?
[2:08:54]
>> So, if you want to have your kid in a
[2:08:55]
charter school and charter schools
[2:08:57]
aren't aren't um service area specific.
[2:08:59]
So for instance, Cypress, people that
[2:09:01]
live within Cypress's service area go to
[2:09:03]
that school. But if you go send your kid
[2:09:05]
to a charter school, they can that
[2:09:06]
charter school can be anywhere and the
[2:09:08]
kid can go there. So charter schools
[2:09:10]
have a little bit more of a say over how
[2:09:12]
many people they accept and will control
[2:09:14]
over crowd.
[2:09:16]
>> I like the school district.
[2:09:17]
>> You may have to even apply for charter
[2:09:19]
school.
[2:09:19]
>> You do have to apply to charter schools
[2:09:20]
and a lot of them only have so many. So,
[2:09:22]
the one I mentioned in my neighborhood,
[2:09:24]
my kids never went there, but it's a
[2:09:26]
pretty competitive process to get in
[2:09:28]
because there a lot of people that want
[2:09:29]
to go and there only so many spots each
[2:09:31]
year.
[2:09:31]
>> Wow.
[2:09:31]
>> It it's public schools that have the
[2:09:33]
overcrowding issue because they have to
[2:09:34]
take everybody.
[2:09:37]
>> And you know, the problem that I had
[2:09:39]
about u them being equal with us. I've
[2:09:42]
lived out here my whole life in Magnum.
[2:09:44]
I paid school district taxes, right, for
[2:09:46]
the high the old high school and
[2:09:47]
everything. So why should the why should
[2:09:49]
the charter still be able to come in and
[2:09:51]
be able to take that school over and we we have lived out here and we've paid
[2:09:56]
taxes for that school all these years.
[2:09:59]
>> So I think that and and this isn't my
[2:10:01]
argument but I think that where the
[2:10:03]
legis where Representative Peruchi who
[2:10:05]
ran that bill was thinking is that
[2:10:08]
charter schools are also funded with
[2:10:09]
public taxes too. um and that it's a lot
[2:10:13]
cheaper if they're a public entity as
[2:10:15]
well to just acquire and use an existing
[2:10:17]
building rather than having to build a
[2:10:18]
new one.
[2:10:20]
>> So that that I think was the what they
[2:10:21]
were thinking.
[2:10:24]
>> Well, thank you for the update. So our
[2:10:26]
next board meeting is going to be April
[2:10:28]
9th, 2026 at 10 a.m. here.
[2:10:32]
Uh we are in need of a close um a close session.
[2:10:40]
So if someone wants to make a motion to
[2:10:43]
close the open meeting.
[2:10:45]
>> Mr. Mr. Chairman, I'd like to make a
[2:10:46]
motion to take a brief recess and
[2:10:49]
immediately following meet and close
[2:10:51]
meeting to discuss the purchase,
[2:10:53]
exchange, lease of sale of real
[2:10:55]
property, including any form of water
[2:10:58]
right or water shares pending on
[2:11:01]
reasonable, imminent litigation, and
[2:11:05]
collective bargaining issues pursuant to
[2:11:07]
Utah code uh 52-4-204
[2:11:11]
through 205.
[2:11:13]
>> I'll second that.
[2:11:14]
>> Motion second. All in favor?
[2:11:15]
>> I
[2:11:17]
>> There's 12 in.
[2:11:20]
>> Does anybody want We need a motion to
[2:11:22]
someone to motion to close the close and
[2:11:24]
open the open.
[2:11:26]
>> I'll make a motion to close the close
[2:11:28]
and reopen the public board meeting. It
[2:11:31]
is 11:15.
[2:11:33]
>> I'll second that.
[2:11:34]
>> Motion second. All in favor?
[2:11:36]
>> I
[2:11:37]
>> I'd like to make a motion to immediately
[2:11:39]
meet
[2:11:40]
>> Oh, what's that?
[2:11:41]
>> We don't We were going to have a closing
[2:11:42]
personnel, but we don't need to. Okay,
[2:11:44]
we're good.
[2:11:46]
>> So, do you any do we have any other
[2:11:48]
business that needs to come before this
[2:11:49]
body or are we all good?
[2:11:52]
>> Think we're good.
[2:11:53]
>> Okay. Someone want to make a motion?
[2:11:57]
>> I'd like to make a motion to adjurnn.
[2:11:59]
>> Thank you.
[2:12:00]
>> You need a second, Danny? I'll
[2:12:02]
>> second it.
[2:12:02]
>> Motion second. All in favor? I