School Committee May 5, 2026

Wellesley School District, MA · · More Wellesley School District, MA meetings · More Massachusetts meetings

Agenda

[6:37] Reports
[12:59] Superintendent Update
[22:23] Consent Agenda
[24:39] Discussion: Superintendent Announcement of Last Day of School
[25:56] Discussion/Vote: Air Conditioning Project
[1:14:15] Discussion/Vote: Solar Installation
[1:21:22] Discussion: FY26 Quarterly Report Presentation (Quarter 3)
[1:34:45] Discussion/Vote: Adjusted Grants
[1:35:51] Vote: SY26/27 Academic Calendar

Transcript

Download: Text · SRT
AI TRANSCRIPT

This transcript was generated automatically from audio using AI and hasn't been reviewed by a person — it can contain mistakes, including plausible-sounding sentences that were never actually said. Treat it as a starting point, not a verbatim record.

[0:27] Good evening, everyone. Chris, and are you able to confirm that we're streaming? I didn't hear the
[0:34] topic of announcement. I usually do.
[0:42] Jack.
[1:11] All right. Can take me just a second.
[1:13] Okay. Thank you. I appreciate it.
[1:15] I do see a message saying meeting is now streaming live on customer service.
[1:26] I'm
[1:27] with that assumption.
[1:30] So, good evening, everyone. I want to call to order the May 5th,
[1:34] 2026 meeting of the Walsy School Committee. There we go. That was the prompt. That was the
[1:41] hoping for. So, I'm going to start again. Good evening, everyone. I would like to call to order the May
[1:46] 5th, 2026 meeting of the Walsy School Committee. Our meeting is being held via Zoom as being
[1:51] broadcast by Walsy Media on TV, Comcast 9 and Verizon 39. It's currently
[1:57] available for live streaming and will be recorded as well for future viewing and
[2:00] well as media. For the record, the following school committee members are present.
[2:05] Vice-chair Linda Chow, Secretary of Land of Nistenbaum, members,
[2:09] Cossus Pontgapelis, and Robert Sullivan. And I'm Nikki Ophenlock and I serve as the committee chair.
[2:15] Before starting tonight, I wanted to take a minute to thank the entire WPS team
[2:20] and our community partners at HRS and Riverside that have supported our students,
[2:25] staff and families as we all work to process the deaths that students
[2:28] chai and Ella. And thank you to the community as a whole for the outpouring of love and support.
[2:34] It can take a long time to process loss and bouts of grief can come up
[2:38] unexpectedly. My urge anyone finding themselves or their family need of support to
[2:43] reach out to the schools or community partners. And again, just thank you to the whole
[2:48] community. And I guess there's no elegant way to segue from that. I am going to move
[2:53] to tonight's agenda. We do have one request for public comment tonight. Before we invite
[3:00] our guests to speak, I'd like to review the guideline. Individuals can join the meeting
[3:04] for public comment via the Zoom link. They were provided when requested to speak. This is an
[3:09] opportunity for community members to provide comments to the committee. As noted in our policies,
[3:14] the committee will not engage in a back and forth of the speaker or with one another.
[3:19] Once invited to speak, we ask that you turn your video on, as I see at art is on you and begin by stating your name in a draw.
[3:26] Please let me account once the three minutes.
[3:29] And then after completing your remarks, please log off the Zoom, but you can continue to watch via the live stream or local cable.
[3:36] So at this time, Phyllis, I'm just needable. Well, please, please go ahead.
[3:41] Thank you, Niki. Thank you all.
[3:44] School committee members. I appreciate your time tonight.
[3:46] I will try to be brief.
[3:48] My name is Phyllis.
[3:49] I'm a member of Sustainable Wellesley.
[3:51] I live on Aberdeen Road.
[3:53] We did share a more specific email with all of you,
[3:56] but I just wanted to be more frank during citizen speak.
[4:00] I also want to appreciate and know that you're working
[4:02] on a variety of really important issues.
[4:05] And I thankful for your thoughts on what we shared earlier.
[4:10] For the public, just so you know sustainable Wellesley,
[4:12] a non-profit organization in town for almost 20 years,
[4:15] Well, the Green Schools and the Town Climate Action Committee have been engaged in a school
[4:19] committee since the very beginning to explore ways to cool the schools while simultaneously
[4:26] lowering the schools overall emissions and improving indoor air quality. The reason we're
[4:31] focused on this is that almost 63% of emissions in wealthy come from buildings alone. So it is
[4:38] important topic to think about. It would be a really good way to knock off some of those emissions.
[4:43] After numerous citizens speak similar to this, and meetings with school committee and a variety of other town departments.
[4:51] We've been asking for a meeting with experts in town, most likely FMD, the Climate Action Committee, the Light Plant folks.
[4:59] We'd like them to all be in the room to take a hard look at the feasibility study, which is not publicly available, I don't believe yet.
[5:06] in an effort to find a fiscally, that's important, a fiscally and environmentally appropriate solution.
[5:12] In the email to you, we shared many questions and offered some suggestions, including grants
[5:17] and rebate opportunities, but we asked you to consider holding the vote tonight and allowing
[5:22] the experts from FMD, school committee, climate action and the light plan to look at the feasibility
[5:27] study and hold this joint meeting. We believe this would help the school committee avoid future
[5:32] concerns from other boards and the community in the future.
[5:36] Ideally, once the feasibility study share publicly, that in this joint needy is held, early, maybe late this week or early next week.
[5:46] They can share technical concerns and other opportunities, ways for example to close the gap of baits,
[5:54] some carbon offsetting details, grant opportunities like the war incentive received.
[5:58] All those things could be discussed and you still have time to meet for your next discusses
[6:05] at your next school committee meeting and move it on to PVC as needed.
[6:12] So we do want the momentum to continue going on to cool the schools.
[6:16] We realize it needs to be done in an equitable way.
[6:19] But we also want to have this done like fine and opportunity to do this
[6:25] that a solution that everyone's really proud of.
[6:27] So thank you for your time and sustainable Aussies always happy to meet about this too. Thank you.
[6:33] Thank you, Coach. Now I'm with you reports. So school committee members first I'll just call on people
[6:41] by one. I'll on a do you have a report tonight?
[6:48] Yep.
[6:50] I wanted to share that on Thursday,
[6:55] I attended the town talk dialogue between town, community members, and select board members.
[7:05] It was held at the Honeywell Gym. It was a wonderful evening with food and conversation
[7:10] and welcoming atmosphere. And I want to thank the Civil Discourse Planning Team for organizing
[7:15] such a thoughtful event. The purpose of the dialogue was to build connections across town boards and
[7:23] cities, share both positive experiences and challenges and serving count.
[7:30] Government. Encourage a stronger sense of common purpose and identify ideas for further acceleration. The civil discourse
[7:37] format is very intentional and can feel very structured at first. But it creates space for slower and more thoughtful
[7:47] listening and conversation across different perspectives. This round for me felt very effective. And I left having learned
[7:59] something new, met new people and gained a better understanding of the shared experiences that
[8:05] connect our work across town government.
[8:08] One idea in particular that really spoke to me was the value of mentorship, not only for
[8:15] new members, but also for more experienced board and committee members who benefit from
[8:21] would benefit from guidance, perspective, and institutional knowledge.
[8:25] Overall, it was a meaningful opportunity to strengthen relationship, build community, and continue fostering a culture of respectful dialogue in Wales.
[8:37] So it was a really, thank you.
[8:43] Thank you.
[8:45] Linda, do you have a report tonight?
[8:49] Yes.
[8:49] So I just have a very quick update.
[8:52] This is actually about, I haven't talked about the lights in a long time, but these are,
[8:57] regarding the lights at Honeywell Track and Field and in particular one of the post-construction
[9:05] conditions that the Wetlands Protection Committee had identified when they permitted the
[9:12] lights for the Track and Field was to require that a follow-up wildlife habitat evaluation
[9:18] be done every 24 months. So 24 months after the installation and then again in 48 months and then
[9:27] 72 months and so we are certainly at the 24 month mark and I think the sort of the hypothesis
[9:37] that they wanted to test is to see if there is an impact from the lights on the adjacent wetlands
[9:43] And, you know, the focus being on the wildlife habitat to see if there are any significant changes.
[9:51] The firm we had hired to help us with the study of the adjacent wetlands was a firm named Epsilon.
[10:01] And so they are going to be coming back to do this work.
[10:06] And in fact, they said they could be available in a matter of a couple of weeks.
[10:10] So we certainly want to make sure we're
[10:13] complying with all of the conditions that had been identified early on.
[10:19] And we certainly don't expect to see any impact.
[10:21] That was what Epsilon had concluded when they did their study.
[10:26] But it will be interesting to see the results of sure.
[10:30] That's it.
[10:32] Okay, thank you.
[10:34] Bob, do you have a report tonight?
[10:35] I do not.
[10:36] Okay, and cost us two of our reports tonight.
[10:39] I do not.
[10:40] Okay, thank you. And I just have two items to update the committee on. The first is,
[10:46] I'm doing our last meeting. We discussed the select boards and
[10:48] Coachment Policy. I provided the feedback we discussed to Kenny Largis, who's the
[10:53] select board member who's working on it. He let me know that they'd
[10:56] receive similar feedback from other boards and requested that we not take any further
[11:00] action until they had time to discuss and maybe make some changes to the policy, so
[11:04] that's why it's not on the agenda for a vote tonight and I'll bring it back once they
[11:09] have a chance to look at it. I also wanted to let the committee know that Dr. Lucira's current
[11:14] contract is an effect until June 30th, 2027. Under the terms of that contract, Dr. Lucira
[11:20] needed to notify the chair of his interest in renewing or extending his contract by May 1st.
[11:25] Dr. Lucira has let me know that he would like to extend his contract and turn the committee
[11:30] must inform Dr. Lucira of our interest in entering into negotiations for that extension
[11:35] by June 30th, and the committee will meet tonight in executive session to begin those discussions.
[11:42] Moving on to other reports, Joanne, did you have a report from the McOperian Council?
[11:52] I'm not able to hear you.
[11:58] Here we go. I can't. Yeah. I did that. Thank you. Okay. Thanks for
[12:02] being here. And the high school student route. Alex, I see you. Good afternoon.
[12:10] So, first of all, AP testing began this week, and it's going to continue through all of next week,
[12:16] but it should be finished up by next Friday, meaning that the high school library will be closed for the duration of testing.
[12:22] So, we appreciate everyone's accommodation with that. Additionally, the Spring Coral concert was last week,
[12:28] so we congratulate all of our participating students on another great concert.
[12:33] The freshman semi-formal was also last week on Friday, so we congratulate those class officers
[12:38] on running such a successful and fun event for their peers. The sophomore semi-formal is this Friday,
[12:44] the 8th, and Junior Boot Cruise is the 15th next week. So we hope that everybody has lots of fun
[12:51] of their events.
[12:55] Thank you so much, Alex. And thank you to you and Stephanie for being our museum
[12:58] tonight. And then David, I'll turn it over to you for the superintendent report. Thank you and
[13:04] good evening colleagues and members of the community watching. I of course want to begin
[13:09] By echoing Nicky's acknowledgment of the deep loss, our community experience last week with the
[13:13] deaths of two of our schoolfield students, Ella, and Kaimakaslan. This is a tragedy that is being
[13:20] deeply felt throughout the entire community. I also want to include a few acknowledgments
[13:26] echoing Nicky's sentiments for members of our team and partners who have really rallied in support
[13:32] of our community, the family and our colleagues on it, again, by thanking the well as the
[13:38] police department, as always, for their incredible partnership and coordination, communication
[13:43] with us. I want to give thanks to our principals, our school field principals, Steven Goodwin,
[13:49] and our principal Parent Smith, as well as our Early Childhood Director, Kristen Stacey. Our central
[13:55] office team, in particular, Mitch Carley, and Sharon Gray, for their incredible work coordinating
[13:59] mental health resources on various partners and managing critical communications to our internal
[14:06] mental health team, exceptional team of WPS schools psychologist, adjustments counselors,
[14:13] counselors, nurses who provide critical mental health support last week and into this week.
[14:19] Our amazing community partner, the Human Relations Service HRS, for their work last week at
[14:25] schools. They're also supporting us in partnership this week during the day but also in the
[14:31] evenings we have a session last night. For this co-field community we are hosting another one
[14:35] in partnership with HRS the Sturzy Night at Hardy. Also at 7 o'clock thank you to HRS for all of
[14:41] that work. And to form our HRS headdoctor of Evans who joined us a week ago Sunday for both our staff
[14:50] and parent caregiver sessions at Skofield and just being such a source of wisdom and care and comfort as we all have struggled to both.
[15:00] Better understand the moment and also to think about how to talk to our students, particularly young students, as well as to support one another.
[15:08] I thought Rob's advice was excellent.
[15:11] They do want to give a shout out to Riverside trauma that also joined HRS and supported our district early on last week.
[15:19] Other partners, I want to make sure I'm noting or the Welsie Educators Association of W.A.
[15:24] reached out early and often have coordinated supports and food across our schools.
[15:33] And of course, our PTOs have been just amazing as always in helping to support not only their
[15:39] individual school communities but helping to support school communities throughout Welsie
[15:44] public schools. Of course, I want all of us to keep them across the family and our thoughts and
[15:50] prayers as we go forward. And finally, as Nicky noted, it's an important reminder for everyone,
[15:58] not to worry alone, for anyone in crisis who is struggling with this or any front. Please, please
[16:05] reach out for support, either through the district or through some other adults. We can connect
[16:10] to resources and help going forward, so it's a great reminder of the importance of doing all of that.
[16:19] No, he's the way to segue from that, but I do want to acknowledge just a teacher appreciation
[16:23] week across the United States, and lots of activities happening throughout our buildings this week,
[16:29] showing additional gratitude for the exceptional work that our teachers are engaged in every single day
[16:36] across the public schools and beyond.
[16:38] And so thank you to all of our WKS educators.
[16:41] That's always the case, but in particular this week.
[16:45] I want to recognize Cindy Mar on the call,
[16:48] our Assistant Superintendent for Flight and Operation,
[16:50] who's been appointed to the Asbo International's
[16:53] Meritorious Budget Award Advisory Committee,
[16:55] which of course she knows very, very well.
[16:57] She's eligible to serve two consecutive three year terms
[16:59] beginning on January 1st, 2026.
[17:02] So congratulations to Cindy.
[17:04] Thank you for continuing to support that work amongst your peers.
[17:10] Moving forward, Dr. Hurray Allen or D&I director
[17:13] wanted to recognize Ruth or T's collazzo,
[17:16] able 28th, Ruth or T's to before the Massachusetts Board of Elementary
[17:19] and Secondary Education did something remarkable.
[17:22] She told her story, while there's spoken policy and data, Ruth,
[17:26] who's one of our world language teachers at the elementary level,
[17:29] spoken images, a teacher spent eight years serving
[17:32] Wellesley, waking up in the middle of the night thinking about an exam and facing the uncertainty
[17:36] of a desi license not renewal, her testimony drew the room's attention in a way that
[17:41] others did not, because it was personal and true, and because a reminder of the board
[17:45] that binded every policy of real people with real stories, real stories, the board voting
[17:50] in the anonymously in favor of their proposed amendments to regulations and educated licensure
[17:54] and preparation and program approval, and we wanted to recognize senior Ortiz for her
[17:58] and advocacy and only on her behalf, but also on behalf of all the educators across the
[18:03] Commonwealth who face similar barriers to licensure.
[18:07] I'm Stephanie Holland, our Metcode Director, last week, Metcode Inc. held a 60th
[18:12] opportunity gala at the artist for Humanity in Boston.
[18:16] The event was to celebrate Metcode's 60th anniversary.
[18:19] Walsy was well represented by Walsy Meco staff, members of the Walsy Meco Paraconsel,
[18:24] And members of the Executive Board of Friends of Welsing Mecca, I beg your pardon.
[18:30] The highlight of the evening was the presentation of the student legacy awards.
[18:34] Welsing Senior Dyer, a remak Christopher, was honored along with five seniors from other districts.
[18:38] The awards held very students who demonstrate leadership and invited the mission of the Mecca program.
[18:43] A rema was able to attend with members of our family.
[18:47] From our K-12 performing arts director Lauren Sarasino,
[18:50] Today we surprised WHS Coral director Dr. Kevin McDonald with the special special presentation.
[18:56] He was selected to receive a country musical award, earning their distinction of music,
[19:00] teacher of excellence. The award was presented by Jamie Chism,
[19:04] Lawrence Harris, CEO and members of the Administrative Team,
[19:07] along with members of Kevin's family. Kevin will travel the national October to be honored and
[19:11] celebrated as part of the CMAs. This is a tremendous honor and Kevin is so deserving and I also
[19:17] wanted to highlight as I think Alex noted, if everyone needed a reminder of Kevin's skill
[19:23] anyone who attended last Thursday night's Coral Concert at Wellsie High School was
[19:27] reminded of his exceptional leadership and particularly using that moment to lift up our
[19:31] community when we really needed it. So thank you to Dr. McDonald. I want to get a special shout
[19:37] out to not only a friend of Wellsie Public Schools but just an incredible partner leader in
[19:43] community and that's Rabbi Rachel Sapphire. There was a beautiful and heartfelt recognition of Rabbi Sapphire at
[19:51] Shabbat Services last Friday evening at Temple Bethel O'Heeam. That was exceptionally well attended and rightly so
[19:58] Dr. Rabbi Sapphire believed has been in her role for 17 years and I know I've worked with her for the past 14 and
[20:06] And throughout that time, she's just been an exceptional partner to us.
[20:10] So it's been her sweet as Rabbi Sapphire will be leaving.
[20:14] But we're very excited for her as she will go to Alexandria, Virginia, to lead her own congregation.
[20:19] So they are very, very lucky to have a colleague of such commitment, passion, and a community leader.
[20:26] So congratulations to Rabbi Sapphire.
[20:29] Tomorrow night is the monthly central council meeting.
[20:32] It will be a Zoom meeting, and I want to thank the Assistant Superintendent for teaching
[20:35] learning of Sandy Trock in our director of technology.
[20:39] Dr. Adam Stein, who we're going to be providing an update on the district's AI work,
[20:43] an update that the school committee will be receiving at one of your upcoming
[20:46] meetings as well.
[20:47] So thank you to Sandy and Adam.
[20:50] Finally, a quick reminder about the importance of registration for school the next year.
[20:56] And that could apply to new families in town or families who are already here who
[21:00] may have a rising sibling who may be of age, please, please, please come forward and begin
[21:07] complete that registration process, or if you started it to be sure you completed it.
[21:12] We'll give some updates to the committee a little bit later in the year, but I can share
[21:15] just a quick update this week that we are looking at adding an additional kindergarten
[21:20] section at both hearty and honeywell.
[21:23] Where our enrollment warrants that, but those FTEs are going to result in an additional change.
[21:29] to the section counts, and for elementary, because our enrollment for K, at least currently for both spray and baits, does not lend itself to three sections.
[21:41] So we are going to be adjusting the section counts across the board.
[21:45] We're still in the process of planning to see if there are any other additional financial implications of changing specialist schedules, for example.
[21:53] So I was full to front of that process, but we're still planning on the same number of overall sections,
[21:57] But we are going to be planning for through the sections each of kindergarten at Hardy and Hollywood for next year.
[22:04] And finally I also want echo the, not just the news, but best wishes to all of our high school students.
[22:11] We'll begin their AP testing this weekend to next week as Alex noted in which them well.
[22:16] And that important opportunity.
[22:19] And that concludes my updates.
[22:21] Thank you, David. We'll move on to the consent agenda. There's three items on the consent agenda tonight.
[22:27] For the minutes we have two for Regas.
[22:30] And then also back to February 11th, a set for when we went to advisory and for that, we are just voting to adopt the minutes that advisory already has approved.
[22:42] So with that, does anyone need anything pulled out for separate vote or further discussion?
[22:52] Now, see anything, I wanted you to make the motion.
[22:55] I actually I separated the two. Okay. So if we just do the first one, the the minutes that the Bob and close desk can.
[23:11] That's Dean from.
[23:12] Okay. So those are the February minutes from before they do the committee.
[23:16] Okay. Sounds good.
[23:17] So I move that the school committee approved the minutes from February 11th, 2026 as presented.
[23:26] So I'm interested.
[23:28] Thanks.
[23:29] Linda.
[23:30] Oh, I'm sorry.
[23:31] In my second.
[23:32] Yes.
[23:33] Yes.
[23:33] Thank you.
[23:35] And then I'll roll the call.
[23:39] Yes.
[23:40] Alana.
[23:44] I'm sorry, Lana.
[23:45] Did you roll?
[23:46] Oh, yeah.
[23:47] Am I?
[23:48] Yes.
[23:49] Yes.
[23:49] Okay.
[23:49] Access.
[23:51] Upstate.
[23:52] Okay, Bob.
[23:54] Upstate.
[23:56] And I vote yes, as well.
[23:57] So that pass with three to zero with two abstentions.
[24:00] And then on, you're going to do the motion for the rest.
[24:04] I moved at the school committee approved the remaining consent agenda items, including minutes from March 31,
[24:11] 1st, 2026, April 14, 2026, as well as the spring surplus memo in library surplus memo as presented.
[24:21] I'm sorry.
[24:23] Thank you, Cossus and Linda.
[24:28] Alana.
[24:29] Yes.
[24:30] Cossus.
[24:31] Yes.
[24:33] Fab.
[24:34] Yes.
[24:35] And I vote yes as well.
[24:36] So that path is five to zero.
[24:37] Thank you everyone.
[24:38] We can now move on to our discussion items and the first discussion item is the announcement for the last day of school, which I will turn over to David.
[24:47] Thank you, Nikki and I, I feel like this is an exciting kind of magic, but this is officially us.
[24:54] Notifying and confirming for the community that Monday, June 22nd will be the 180th day or the final day of the school year.
[25:03] We had three snow days. I think it's in everyone knows this year, which which pushed that day out
[25:09] Or nearly we'd be in the prior week because because about the calendar falls Juneteenth
[25:14] That federal holidays that Friday, which pushes us out into Monday
[25:18] So again Monday, June 22nd
[25:21] Barring something I've ever seen happening between now and then is our last day for students
[25:25] It is a half day and I know it seems a little quirky in that the week before
[25:30] We have a Wednesday, regular Wednesday, half day, and then Friday is a holiday, and we're coming back for a half-day on Monday, and that's just the way this schedule breaks this year with the calendar and the holidays that are present.
[25:42] Tuesday June 23rd will be our last additional day for staff to wrap things up before the summer recess begins.
[25:53] Okay, thank you very much, David.
[25:55] And then our next discussion item is the Air Conditioning Project, so I know Joe and several
[26:02] members of his team BLW are here to talk us through that, so Joe, I'll turn this over
[26:07] to you.
[26:08] Thank you.
[26:09] Good evening.
[26:10] Tonight we have Dick Elliott, who is FMV's Project Manager, and then we have some of the
[26:15] team from BLW, Bill Matt and Jared, who you've met before and worked with.
[26:19] So tonight we're giving you on updates since we last made the key decision to focus on
[26:26] option three, the window units and we're going to update you. It looks as you probably
[26:31] seem in the Friday night packet. It looks a lot like the last presentation.
[26:37] The biggest changes were really digging what we've done since then is dig deeper into the cost
[26:48] reliable cost estimates on what would need to be done in terms of electrical service upgrades,
[26:52] things like that. We were back a couple of times with the cost estimator to make sure that
[26:59] we're getting as reliable costs as we can before we go to the PVC the next step.
[27:05] So let me go through the presentation again and then hopefully we'll have some time
[27:14] to for questions.
[27:50] There we go.
[27:56] Okay, can everybody see that?
[27:59] Yeah, okay.
[28:00] Okay, great.
[28:06] Alright, as I said,
[28:08] not a lot of change in the actual presentation,
[28:10] but you have received two versions of the very detailed
[28:13] 95% complete feasibility study from BLW.
[28:18] One version,
[28:20] the lighter version I'll call it,
[28:21] have the appendices and in the larger version was sent through Dropbox, which had all the appendices.
[28:31] So I think it's probably worth going through this. I'll try to go quickly, but this is pretty much what
[28:36] will be presenting when we go jointly to the PVC.
[28:45] So what's happened since the last meeting? We made a
[28:48] key decision, of course, on proceeding with the window units, at the December 9th meeting.
[28:53] And the goal for this meeting is to get a school committee input on the final draft report.
[28:58] Now, I've already received a number of comments and questions of Nikki and I've responded to those.
[29:05] If there are any additional ones that come up tonight or later, we can certainly respond to those.
[29:10] But the BLW team is already incorporating all of those comments and questions.
[29:15] they'll be a final version, a final final version before we go to the PBC.
[29:24] So tonight's two goals tonight to get the committee, get their input on the 95% as I mentioned,
[29:32] so that we can engage with the PBC and then follow the usual process, which is to present to advisory,
[29:38] leading up to the fall special time meeting, where we would request design funding.
[29:43] The other thing we like to do is to get a vote on the project to move ahead.
[29:50] So get your input and get a vote. It's what we're looking for tonight.
[29:56] As far as the contractual study, no changes here.
[30:00] Of course, highlighted option C, which is the window unit option that was to the preferred option. As far as the building code overview, we did save, we had budgeted $40,000 for an MAAB study, which we don't need. So that's great. And that was one of the questions, where do we stand budget wise? We're in really good shape budget wise. But as I said to Nikki, sometimes when we engage with the PBC and the Warren HAC project is a good example,
[30:29] They may request that we look at a bunch of different options, phasing, construction, maybe some technical options, so even though in 95% done with the report,
[30:39] we still want to make sure we have plenty of budget left to address any sort of contingency items that come up as we move towards design.
[30:47] Schedule construction phasing will talk about and how that's important and then the cost estimates, the good news is we went down in option one and two about eight percent,
[30:57] And I believe it went down in the window option, I want to say about 3% roughly.
[31:06] Again, these are the three options that we talked about.
[31:09] There is some nuance between option one and option two in terms of VRF versus heat pump.
[31:17] And it's essentially the rooftop unit on the VRF unit.
[31:22] The VRF system can do multiple.
[31:25] It's configured to such that it can do multiple rooms with one unit in the hybrid option.
[31:31] It can do this one rooftop unit for each unit diffuser in the classroom.
[31:37] So that's really the difference, essentially the same technology.
[31:42] And then option three is the preferred option in the window unit option.
[31:48] So pretty much option one was to do the entire room, the entire building, all spaces,
[31:55] except for our carator's bathrooms and solar spaces like that, a VRF system, again this is the
[32:04] technology that we've been using at Hardy Honeywell, Tom Holland Warren. There would be rooftop
[32:09] equipment, Walmart to diffuse us inside the building with fan quality units as well. We would have
[32:17] large air handling units in the gyms and cafeterias and it'd be controls. And as with all three
[32:22] This is a significant amount of electrical upgrades and this is kind of what it would look like, no change in that
[32:33] Option two was the hybrid option the heat pump option and
[32:38] This would provide
[32:40] Potentially heating and cooling
[32:44] It was it's called a multi split heat pump system and as they said there's one rooftop unit for each room
[32:51] We have the rooftop content to unit as the well-mounted diffuses and controls and electrical upgrades.
[33:00] And this is what that would look like. As you can see, there's one rooftop unit per each classroom.
[33:06] It looks very similar to Option 1.
[33:11] This is the preferred option. Option 3 provided a condition for all of the exterior classrooms, including the libraries and offices.
[33:18] Only no interior spaces where we don't have windows.
[33:22] These are inverter type window units, which is a more efficient unit, this isn't the old-school
[33:30] clanking window unit that made a loud bang when it came on and went off. It ramps up slowly
[33:37] and then ramps down. Again, very efficient. We had a great experience with the pilot program that we'll talk about.
[33:44] key components, the window units themselves, fitting out each window after we take the
[33:50] sac of the window out. And importantly, there's no controls upgrades required to be electrical upgrades as well.
[33:59] And this is what it would look like in PlanView. As I said, the inverter type units are very
[34:07] efficient because of the variable speed compressor. They rank more quietly and you can see a
[34:14] of images of what they look like inside and out from our pilot study.
[34:20] And those are still in place.
[34:22] The pilot study, we did last summer.
[34:27] And I mean, we started the study July 1st,
[34:29] and somehow we managed to get the pilot down over the summer.
[34:34] We designed and installed FMD did it,
[34:37] lasted from August 26 to September 26.
[34:43] and we collected data, we got input from feedback from the staff or in these rooms and we had a
[34:51] acoustical consultant perform a study and again overall we had very good results. Here are some
[34:57] images of the pilot program, you can see the data collection, do some electrical work that we had to do in
[35:09] Again, we got feedback from all of the teachers in these particular rooms.
[35:13] It was very positive.
[35:14] Top left.
[35:15] You can see it three times a day.
[35:17] We were collecting data at nine different points in all these classrooms.
[35:20] And on the right, you can see the acoustical readings in fairly favorable level.
[35:28] As I said, we spent a long time since our last meeting working with BLW and MLP and vendors and the cost estimator to come up with.
[35:39] Basically, class would give us a higher level of confidence.
[35:43] So you can see option one with down about just under 8%, it's still total of 39 million.
[35:50] Option two with down about 7.6% again, that's just over 31 million.
[35:57] And the window unit went down, window unit option went down about 3%.
[36:01] So that's coming in at about 16.8 million.
[36:03] So the window unit option is still about half as much as the option 2, and maybe even more
[36:14] than option 1, the discrepancy.
[36:17] So it's a significant cost difference.
[36:21] So this is from the townwide financial plan, and I've served showing the tax impact for
[36:27] this project the way that it's for bond purposes they assumed five years based on the equipment
[36:36] life is what we understand from the CFO and this you can see the five different five years
[36:43] of tax impact first year is 449 last year is 389 dollars on the median home in Welsley.
[36:55] So electrical
[36:55] is really what's driving this project and it impacts all three options significantly as I indicate here.
[37:04] The good news is that only a scope field and the middle school will require a
[37:11] electrical service upgrade under option three. All sites will require a new switch gear
[37:17] and once you're in the building there's new dedicated power supply from the electrical room
[37:23] to the panels to the classrooms.
[37:28] You've seen this before, this is the...
[37:30] This study that BLW did looking at the service sides coming into the building and the green indicates where no service upgrades are required, so that's bates and fisc under option 3, and school field and middle school do require a service upgrade.
[37:47] And this is, this is what would happen at the middle school at Skofiel to be similar at the middle school.
[37:55] We would have a redundant system so that we would like to minimize the downtime when we switch over from one the old transformer to the new transformer.
[38:06] So, lower image you can see the switch gear, this is the new switch gear which is going to be outside of the electrical room.
[38:16] and this happens at all four locations.
[38:23] Good news on the accessibility, none of the buildings
[38:26] meet the 30% limit under option 3.
[38:30] So we didn't have to do that study.
[38:32] That $40,000 study that we budgeted for, which is really good news.
[38:38] And here you can see the scope field cost.
[38:40] If we went with option 1, the full AC, that would have
[38:45] and the middle school was close.
[38:47] So, Skullfield absolutely middle school was close, under option to the hybrid of the Skullfield still would have exceeded the 30%.
[38:56] So, Skullfield over a middle school close and option 3, the Windows, no issues.
[39:03] So, this is a graphic that I presented last time. Just what we did was we looked at the four schools, and we looked at Ashray, which is a technical standard for HVAC,
[39:18] that have data on expected useful life for systems.
[39:23] So we looked at the boilers and the unit ventilators, which are two key components of
[39:29] all these these buildings, mechanical systems.
[39:33] And we estimated based using the ash ray service life, whether it's 2030 years, how much
[39:40] when would we have to replace these systems?
[39:42] So there was a range, Bates would have to be replaced sometime roughly between 2020 and 9 and 2034.
[39:51] Skullfield in Fisk, 2035 and 2040 or 2040 and 2045 in the middle school between 2031 and 2036.
[40:01] And what it says is that both of the options, the fully air conditioning and the window unit option,
[40:08] option three would provide air conditioning up to the time of replacement. So that was a concern,
[40:13] you know, if we're going to put in these window units, you know, are they going to last long enough
[40:18] to the time where we have to replace the HVAC system. And this graphic basically tells you that,
[40:25] yes, they will last that long. And keep in mind, the biggest cost in this project is the power,
[40:32] the electric. Each of these window units probably going to cost $17,000, $1700 somewhere in that
[40:40] range. So we expect them to have a 10-year service life, the window units, perhaps even longer
[40:47] because, again, they're only going to be used a couple of months. And if we have to replace them,
[40:56] it's the electrical infrastructure that's in place doesn't change. The build-out are on the window
[41:02] doesn't change. We're simply going to have to take the unit out and put a new unit in.
[41:09] So, as far as maintenance costs, additional electricity, you can see that the option
[41:19] 3 has an electricity cost of about $42,000. Option 2. And again, that's just doing the
[41:32] exterior classrooms. Option 2 is about electricity costs of about 34,000 and the full AC is
[41:42] about 39,000. So what that says is to no surprise that the option 1 and option 2 are slightly
[41:48] more efficient than option 3, which is what we expected in terms of electricity usage. Also,
[41:57] option 1 and option 2 have more maintenance requirements than option 3. Option 3, the maintenance
[42:02] there. Simply the custodians once a year would take the filters out and vacuum them or clean them
[42:07] and put covers on an office part of their regular duty. So it really is no maintenance in option
[42:12] 3.
[42:16] Again we looked at the electricity and the CO2. The option 3 has higher CO2 than in option 2
[42:29] option one, but not significantly higher. All these systems are considered to be energy efficient.
[42:38] They'll adhere to the Tons Municipal Sustainable Guidelines. GEO Thermal was considered,
[42:44] but it was not viable for this option.
[42:51] So, frozen cons are option one, the full AC. It does the
[42:54] entire buildings, all three buildings. It would provide potentially some level of supplemental
[43:01] heat, the amount to be determined, possibly reducing natural gas, somewhere in the 10% range,
[43:09] possibly. This is a similar system to what's used at the two new schools, electricity
[43:15] slightly lower than the other two options, acoustic, favorable, and it would have limited
[43:20] instead of compact because of the equipment's up on the roof.
[43:24] The negatives for our option 1, the cost significantly higher than an option 3, 39.1 million
[43:32] versus 16.8.
[43:34] That cost could impact potential automating and ballot votes in the future.
[43:37] That significant difference may impact future roofing replacement if we pursued that option
[43:44] and that's something that I'll be coming back to present to you in June.
[43:50] feasibility study done by Simpson Cooperates and Hager on on the roofs at the Bates,
[43:54] Spray and Middle School.
[43:56] The electrical service upgrade except for Bates is a con potential shutdown risk as always
[44:03] a problem nobody ever wants to have to deal with full building shutdowns.
[44:08] And then there's conflicts with potential planned replacement of the HRAC systems.
[44:14] And more maintenance is required.
[44:17] Option two, very similar pros and cons, every view of these, no change in those, but let's
[44:23] focus on one option three, the preferred option, again, it's significantly less cost,
[44:28] 16.8 million versus 39, which could impact, tell me meeting a ballot vote's in a positive way.
[44:36] Provides a required cooling, acoustical goals were met, it's simple, on offset the thermostat.
[44:43] And this is also key number four.
[44:47] It won't impact the roofing replacement or potential solar work on the roof.
[44:53] Positive feedback in the pilot study, electrical service upgrade, not required debates and
[44:59] risk.
[45:01] And it aligns better with the full replacement that I talked about earlier, of the entire HVAC system, in less maintenance. The negatives for this, it does not cool the entire building, electricity usage and CO2 is slightly higher, acoustics are acceptable, but not as good as option one and two. Again, there are sound system using the schools which should help mitigate this.
[45:24] And there may be a static impact, some people might not like seeing the window units, but I'm sure we'll be discussing that when the project goes to the DRB.
[45:37] Okay, the schedule.
[45:39] The plan is this month or next month, school committee in FMD would present to the PBC.
[45:47] I deck is already reaching out to the committee to try to find some dates and we'll get back to you on that.
[45:54] The fall special is what we're driving towards, where we would request design funds.
[46:01] And I believe it's, so the number we have in the cost estimate of 1.
[46:07] I think it's 1.3 million for the option 3.
[46:12] We will have to review that of course with PBC.
[46:17] They generally like to put together their own estimate for design fees, so, but that's in the ballpark I think.
[46:28] And then we would begin design, I believe special Tom meeting this year is November 9th, 10th.
[46:35] So sometime in mid November we would begin design and the ideas that we would complete design in a year.
[46:42] And we would come back to the 2027 fall STM and request construction funds.
[46:49] We're expecting this is going to be a debt exclusion.
[46:51] So we need two thirds vote at special time meeting.
[46:54] We need a ballot vote in December.
[46:56] And hopefully we will execute a contract in January, 2028,
[47:01] which would give us several months to purchase equipment and be ready to go
[47:05] when school gets out in June, 2028.
[47:08] So that's the construction schedule summer, possibly leaking into the fall, 2028, but we're hoping we could get it all done in the summer.
[47:19] This means that with the exception of the middle school, all the schools will be ready to use air conditioning by spring 2029.
[47:28] And I say with the exception of the middle school because at this point we're not 100% sure based on the size of that building that we can do the entire project in one summer.
[47:37] maybe two summers. If we have to break it up into two summers, the goal would be to get
[47:45] one of one half of the school operational. But again, these are these are detailed questions that
[47:53] I'm sure the PBC is going to want to discuss with us. And this is what typically just as we did
[47:59] with the Warren project, we came in discussing the Warren HVAC project, thinking that we were going
[48:06] do a phase construction where wreck and health would stay in the building. And after several
[48:12] meetings with PBC, it became clear that a better option, which reduced cost and impact
[48:20] to the tennis was to move them out into space at 888 and the upper. That of course is not
[48:29] an option here. But the point is that, as I mentioned earlier, we get a lot of really good feedback
[48:35] from the PBC on these studies and basically we take that and that is what ultimately is what
[48:44] we use to determine the request for design and bidding funds at the special time meeting.
[48:50] Again,
[48:51] next steps finalize the report will present it to PBC. Get the school committee vote to move forward
[49:00] and we'll schedule that meeting as they said, Dick is working on that and it's probably going to
[49:06] more than one meeting with them. It's fairly complex project for what appears to be simple. It's
[49:13] not that simple. And the goal is to get to the 20, 26 fall STM. And with that, if you're like
[49:21] I can stop sharing, or would you like me to keep that up? I'm going to pull it down so I can see
[49:27] go on. Okay. Thank you. Sure. And before I open up for questions, Joe, I know this is in the report.
[49:37] I just want to clarify in June the meeting. Option three handles all the exterior classrooms and also
[49:44] any meeting space that has the window is accurate and my voice. Yes, I would say meeting space. Yes.
[49:51] Anywhere anywhere there has a window that we can put a unit in and take this as shown. Yes.
[49:56] And so that includes libraries, but we know is not going to include cafeterias where the school has them or gems.
[50:04] Thank you.
[50:06] And then I'll open it up to the committee for further questions.
[50:14] I guess when I look at the solar project, there's, you know, that's a lot of that seems to be driven by grants and things like that.
[50:23] there's there's no mention of that in these projects is up because the offset to the gases so small is it there's no sort of
[50:32] environmental
[50:32] the
[50:33] grants available
[50:36] So this the scope of this project did not include
[50:40] Looking at PVs however that roofing project that I mentioned that we'll be coming back in June to present to you
[50:47] for for baits and spray and middle school does include
[50:53] photovoltaic installation in fact the same consultant that's working on the
[50:57] hearty and honeywell solo design associates was a sub consultant to
[51:00] Simpson and Gumperson Hager so we will be presenting that as part of the
[51:05] roofing project but that just to be clear that's primarily a roofing
[51:09] replacement study and we included a fair amount of PV work as well but you know
[51:16] without giving out the headlines I can tell you that there's a fair amount of
[51:20] structural analysis and potential upgrades that would have to be made on all three buildings to put the pv's on there, so
[51:30] Maybe didn't ask it right it is when I would like the 5.2 million for baits and somebody had brought this up to me
[51:35] I want to look at the 5.2 million for baits for option one versus the two point whatever it is for option three
[51:42] Is
[51:43] Are there grants that would bridge that yet at all?
[51:47] Um, I would say if this were a, um, like, if this were a heating project, we're providing
[51:55] a heat pump that did heating and cooling or replace the boiler, I would say yes, it's definitely
[52:00] potential grants.
[52:01] In fact, the MSBA, as part of their accelerated repair program, is looking into heat pumps
[52:08] instead of boilers.
[52:10] The problem here is that we still have the boilers.
[52:12] We're not replacing the boilers.
[52:13] We're just doing an add-on to provide cooling.
[52:17] So it's getting the offset, in regards to the option of versus three.
[52:25] And I guess in option...
[52:30] One again on Bates
[52:34] with the HVAC being replaced fairly soon, what's the plan for the HVAC replacement in context of the window units? Does that, do we keep the window units or would we do we?
[52:49] So the window units would stay until a major renovation project was done is done at the Bates.
[52:55] and I know I've talked about it before. I think this is something that school committee will be
[53:03] looking at as part of a strategic facilities assessment that we've talked about as well. I think
[53:10] it may be on the agenda tonight. That would be something that would need to be looked at as part
[53:17] of that initial long-term facilities plan and if it's determined that we should do a major project
[53:25] at the base, then we need the feasibility study. So what I've talked about at the base, we know we need
[53:31] to replace the roof sometime around 23 or 23 or 23 or 34 according to the report you'll get next
[53:38] month. We know the HVAC system by 2034 will be 30 years old, so it'll be at end of life. So it only
[53:47] makes sense if you're roof in your HVAC system both need to be replaced around the same time. You would
[53:54] I think it makes sense to do a more comprehensive major renovation project at the time and so what would you add to that?
[54:03] It'd be ADA upgrades because we'd hit the 30% of the assess value.
[54:09] Probably some sort of interior finishes and fit up work as we did at school field in the fifth 15, 10, 11 years ago.
[54:18] So, I think the Bates projects is something that we are going to need to talk about and think about major innovation.
[54:28] To me, it doesn't make sense to do these as one-off projects, right, to do a place to the roof and then come back and replace the HAC.
[54:35] But it needs a lot of thoughtful planning.
[54:38] You know, when should it happen?
[54:40] This is a 2034, 2035, 2033, and how do we think of that project in relation to all the other needs in town, right?
[54:54] So last question, would you still get, I think you mentioned something about the units themselves don't cost much, but the electric work you would still have that if you chose to do something outside the window units at that time, you would still benefit from that electric work that you've done for this project.
[55:11] That's the case with all of them.
[55:15] Yeah, I think there may be, that would scope you like, for example, a base if we did a major
[55:22] renovation, could you salvage any of the electric work that was done?
[55:25] I would say possibly, certainly, I would think the, you know, the transformer and the primary
[55:32] climate was coming into the building, the secondaries, all that I would imagine would be,
[55:39] Could be selfish if it's part of a major renovation project that pays for example?
[55:53] About any further questions?
[55:54] No thanks.
[55:56] Okay, thank you, Cossus. Go ahead.
[55:59] Thank you, Nikki. Two questions. One is regarding the kind of this timeline and the process here in
[56:07] terms of next steps for tonight or for this meeting. We've heard from members of the community
[56:14] including in public comment that they may benefit from additional time to consider aspects
[56:21] of this and have an opportunity for additional inputs. So I'm just wondering if there's a
[56:25] reason why we would not want to allow for that if there are less there are some pressing deadline
[56:32] to get this to PBC in time for fall STM or other kind of deadlines in place. So that's one question.
[56:43] The second question is, and this has kind of been alluded to in the discussion about
[56:48] baits that sort of have been separated out. I'm just wondering, it seems to me that in these
[56:52] discussions, there's been, as you've considered, the various options that you've put before us,
[56:58] it seems that there's been kind of a one-size-fits-all approach for every option, and I'm just wondering
[57:06] if how much consideration was given to kind of different approaches, that different buildings,
[57:12] and whether that would make sense to think about in light of specific circumstances at each
[57:19] of these locations, so any clarity on that would be helpful.
[57:28] So, this was a feasibility study, and we did not get into, for example, doing heat pumps
[57:39] for part of this building and window units, it was just too complicated to try to do something like that.
[57:46] And it was basically decided that in discussions with school committee that there were the three options.
[57:53] And I think early on we talked about not trying to mix and match the options that it wasn't really feasible to do that.
[58:01] But in answer to your question about the project is on a schedule, and according to article 14 of the PBC by law, the project needs to be presented to PBC, I believe 128 days prior to town meeting.
[58:17] And if my math is right here, that's early August, it needs to be presented.
[58:24] people go away over the summer. I know that. We're still here. So absolutely puts the project in jeopardy if it gets pulled off and delayed. And again, this is this is your decision school committee's decision. We've been following the guidance and the vote along in the way. Option three was a key decision that we've vetted and spent a year talking about it. Why it was the way to go. And you know,
[58:55] The most energy-efficient option, the least CO2 impact, is to not do the project.
[59:01] I said that before, and, you know, obviously that is not an acceptable solution, but
[59:08] what we're proposing, I think, balances cost and CO2 and impact, O&M impact rate is very
[59:16] little additional work needed by maintenance on option 3.
[59:20] So I think the pros and cons kind of laid it out.
[59:25] This is, there really is no other option here.
[59:28] But again, school committee could decide to stop the project,
[59:33] direct us to look at something else.
[59:35] And as I said, it's 120 days goes by pretty quickly.
[59:43] And what are we worried?
[59:48] I would not recommend it.
[59:50] think if you pull this off the track, you're in danger of it's going to be tight anyway as it is to
[59:55] to get the design funds approved at the fall special in this.
[1:00:00] In the year later, a comeback for construction funds. That's moving pretty fast in a public bid environment, design and construction. We have to have bids in hand a month and a half before a special time meeting,
[1:00:16] but again, it's school committees decision. If you want to look at other options. I just would need to know what the other, we have the budget. We just have to execute an amendment with the consultant.
[1:00:29] So, it's going to be time and money.
[1:00:33] Thank you.
[1:00:35] Joy, do you want to clarify?
[1:00:37] We didn't discuss or really look into mixing and matching different systems within a single building.
[1:00:44] But when we looked at each building, we did look at the three options separately for each building.
[1:00:49] And it was just the fact that the window units seem to be the best option for each of them.
[1:00:55] But it was feasible that we could have chosen a different option for different buildings, but I think in terms of the, and we really the cost for to the school is the cost, the triggers for the mandatory upgrades was a major decision point and then just overall the cost.
[1:01:13] you know, even with looking at East School individually,
[1:01:18] the cost benefit of the window units
[1:01:20] proved to be in my mind, make it the best option for each individual school.
[1:01:26] I would say this for anyone that's interested in information on the project.
[1:01:29] They could look at Wellzing Media presentations from December, the power points that have been posted
[1:01:37] on the F&B webpage, in school committee webpage, and also the report, which once we finalize
[1:01:45] it, it will be made available with the version without the appendices and a much larger version.
[1:01:52] And a lot of work's been done in the last year to kind of arrive at this point where we have the
[1:01:58] preferred option.
[1:02:01] So, I think to change direction here, there's definitely some risk.
[1:02:11] other questions and committee members,
[1:02:21] thing none. So the plan for tonight was to vote and that vote is to take this 95% complete study and present it to PVC.
[1:02:34] And again, then then take their input and refine it into the actual final report. So that's kind of what we're voting on tonight is to take the 95% to be to PVC to get there.
[1:02:47] I mean, I'm going to bring it to you.
[1:02:50] Do you have anything to add to that?
[1:02:52] Does that capture that correctly?
[1:02:54] You did.
[1:02:54] I just want to clarify that we will ultimately incorporate those
[1:02:59] comments that even I emailed back and forth,
[1:03:02] build that.
[1:03:02] I'm going to incorporate all of those into the.
[1:03:06] Call the final.
[1:03:06] I got school committee 95% final.
[1:03:09] Okay.
[1:03:10] Very good.
[1:03:13] Um, a lot of go ahead.
[1:03:17] I'm just trying to clarify for my own process here.
[1:03:25] So we're voting on to present the feasibility study to the PBC with what we already
[1:03:37] kind of said to pursue the option three, which is already voted on, right?
[1:03:47] Okay. In December we did vote. Sorry. I don't mean to call you off. No, no, no. I'm not sure. So I'm just trying to wrap my head around this. And so it's simply for finalizing the whole report is that it should be helpful. So PPC, the way they work is they like to have the project proponent in this case school committee come to them and say here is the feasibility study.
[1:04:17] that we had prepared. And we want you to take this,
[1:04:21] vet it, and then proceed with design. So they want,
[1:04:25] they want to know that you voted on this document that you're
[1:04:28] asking them to take to Tom meeting for design fund requests,
[1:04:32] and that you picked, you know, option three, which the report says.
[1:04:36] Okay. So we, we already picked, we already voted on that.
[1:04:42] We've already said we're picking option three. There's no going back or
[1:04:46] anything like that. I'm just wondering is it worth having heard the public comment
[1:04:56] today, just hearing out what the different groups are saying?
[1:05:06] Is there anything that
[1:05:07] given the very tight timeframe and we'd like to avoid that to not delay it anymore? Is there
[1:05:16] Anything we could actually do to, I don't know, to be able to listen to them for like
[1:05:28] one last time before we moved forward, would there be anything we could do to change anything?
[1:05:36] It might have been, you know, okay.
[1:05:40] And you're saying it would jeopardize the whole project as a timeline because it's 128 days.
[1:05:47] 120 days prior to Tom meeting, according to Article 14,
[1:05:53] project has to be submitted to the PBC. So again, I think it's you in
[1:05:57] early August and it's may now and they still have to wrap it up and
[1:06:05] so I don't know what their schedules like PBCs, we, there's other issues going on that I don't want
[1:06:12] get it through here as far as bandwidth and staffing and let me just say that if you pull it and delay it
[1:06:19] this risk that we might not get there in time. And so if there's a risk and we don't get there on time,
[1:06:26] it means no air conditioning for even longer. Twenty twenty-nine. Right. So the goal is we want
[1:06:34] the kids to have air conditioning as soon as possible. We're just schools to have.
[1:06:40] Okay, I was just clarifying in my.
[1:06:46] And a lot of I can jump in and save it just to that point.
[1:06:49] I think the committee knows this.
[1:06:52] You know, especially as we head into the warmer months,
[1:06:56] you know, particularly at those four schools,
[1:06:59] we know that there's a lot of interest and urgency
[1:07:04] and getting this done as soon as possible.
[1:07:07] You know, even on the timeline, Joe presented,
[1:07:09] I think there's wondering,
[1:07:11] if that go any faster, I think we know we can't,
[1:07:12] we have to fall that process.
[1:07:14] So I'm very mindful of anything that creates risk
[1:07:16] to take us off that timeline given.
[1:07:19] The overwhelming feedback we've received
[1:07:21] about the desire to get there as quickly as we can.
[1:07:26] I guess I would say this.
[1:07:28] It's really a school community decision.
[1:07:30] You could go with option 1 option 2, which have somewhat lower electricity usage in CO2 impacts, but cost twice as much or more than twice as much.
[1:07:42] I mean, to me, that's pretty obvious, just based on cost, that option 3 comes to the top.
[1:07:48] But I would say if you wanted to pursue that, we would have to revise the report, look a little deeper at those two options.
[1:08:01] And it would be tight to be ready by August 18th.
[1:08:04] In other words, if you changed your preferred option to one or two, as sustainable wealth, I think is suggesting.
[1:08:14] There's even more risk to that.
[1:08:18] I'm not sure I would characterize the stand-in-law Walshley's view as exactly that,
[1:08:28] they may have some additional input, but I think that they recognize that at least on some level that option 3 will be the preferred option.
[1:08:44] It's just a matter of whether option three makes sense for all the buildings involved.
[1:08:56] I don't want to speak for them or anyone else, but in any case, thank you.
[1:09:03] Okay. I guess I'm going to, did you ever come up?
[1:09:07] Yeah, I just wanted to add, since I was part of that discussion back in December.
[1:09:15] I recall that, well, first of all, I think we need to acknowledge the fact that the committee
[1:09:21] already voted, and I think it would be highly unusual at this time, unless someone's ready
[1:09:26] to make a motion and try to get the committee to reconsider and take a different hope to get
[1:09:33] a different outcome with the vote. So that's just one comment, but in terms of what I recall,
[1:09:40] I know there was concern that if, you know, in the case of Bates, we had them take a different approach.
[1:09:48] That would actually mean that they would end up most likely air conditioning later than the other three schools.
[1:09:56] And I think, you know, the focus, certainly, for my standpoint, was around equity.
[1:10:02] You know, of course, we're already dealing with a challenge from an equity standpoint for these four schools compared to the other schools.
[1:10:10] And in the case of Bates, we want to look at the strike, the right balance, and if we're saying that Bates would then have to wait even longer than the other schools, because of wanting to take a different approach, that would definitely be a concern.
[1:10:32] So that's what I recall from our conversation back in December.
[1:10:37] Thank you.
[1:10:39] I agree, and I think from a cost benefit analysis, it's been clear to me through the study
[1:10:47] that the window units are the best option to get us to a solution, and I'll say as quickly
[1:10:53] as possible, and I know I hear from community members, probably at least once a week telling
[1:10:58] me that we're not moving quickly enough, which I appreciate, but we are trying.
[1:11:04] So I guess I want to say the, this isn't to use the winter air conditioners in this project.
[1:11:09] It does not, in my mind, it's not taking away from the advantage that he pumps can provide in certain situations and projects there.
[1:11:18] They can play an important role in inducing emissions.
[1:11:22] I just think for this specific project and, and the cost that we've looked at the winter units happened to be the best option.
[1:11:29] And so I really hope that no one is taking this decision as a sign that school committee
[1:11:34] is stepping away from any of our sustainability considerations or the important to place
[1:11:40] on it.
[1:11:40] I think I'm hearty are great examples of where we really have been into building sustainable
[1:11:45] buildings and I think the next item on our agenda tonight is going to be solar for those schools,
[1:11:51] which again is I think leaning in to sustain about projects and outcomes for our community
[1:11:58] So, I think for this specific project, I feel like we've vetted it, and there's a lot of considerations.
[1:12:06] And the window units are the right option for this, but definitely moving forward when I continue to look at sustainable options.
[1:12:14] And I think even when we get into the facility's master plan task force, making sure that the climate action committee has a role on that task force and their input is being heard as we discuss different projects and the timeline that will stretch out well over a decade.
[1:12:28] And so, I guess, to wrap it up like I said it three times already, but I think the window units are the best option for this, just a big project.
[1:12:37] And so, I'm comfortable moving forward with those.
[1:12:41] And with this report.
[1:12:47] So, if there's no other comments, then I think Alana, I'll ask you to make a motion.
[1:12:54] I move the school committee and facility management department, present the feasibility study in the recommendation to pursue option 3, the window unit solution, to the permanent building committee to obtain their input prior to finalizing the report.
[1:13:13] Upon completion and acceptance by the parties of said report to then pursue in conjunction with FND and PVC design funds at the fall
[1:13:29] STM
[1:13:30] Thank you. Do I have a second fall 2026 STM. Okay. Just to be clear. Yes. Yes.
[1:13:41] Thank you.
[1:13:43] Second.
[1:13:44] Okay.
[1:13:45] I got classes from that one.
[1:13:46] I'll roll.
[1:13:46] Linda.
[1:13:48] Yes.
[1:13:49] Marana.
[1:13:51] Yes.
[1:13:51] Cossus.
[1:13:53] Yes.
[1:13:55] Bob.
[1:13:56] Yes.
[1:13:57] And I vote yes as well for that carries five to zero.
[1:14:01] Thank you very much.
[1:14:02] And thank you for the team from BLW for being on tonight.
[1:14:05] I appreciate you joining us.
[1:14:09] I'm going to move on to the update about the solar project at Honeymont and Hardy, and that's the
[1:14:20] I'm going to share a slide here in a second.
[1:14:45] Okay, so I think then we talked about this
[1:14:49] a few meetings go and we go to more than that. I guess and we voted on February 3rd to use the
[1:14:55] But we made some remaining funds in both the Honeywell and Hardy project for the salt.
[1:15:00] For the solar installation. And so that presentation remains the same and I have a link to it here on the bottom of the slide.
[1:15:07] But what I've just updated is there's been some updates into the timing and next steps that I wanted to go over.
[1:15:12] And then the PBC did ask for a vote for by school committee just to acknowledge these changes.
[1:15:18] So, as I said, on February 3rd, we voted to use the project funds for the solar installation.
[1:15:23] There's a grant that has been submitted by the Climate Action Committee and we're expecting
[1:15:29] really almost any day now to hear back on that grant certainly sometime this month.
[1:15:37] The construction phase of the project will be revisited again, so we will talk about this
[1:15:42] project at least one more time once we know the status of the grant funding.
[1:15:47] And if all is approved, instead of insulation in summer of 27, which is what we talked
[1:15:52] about last time. It's an accelerated installation in 12, 20, 26. And the reason for this is the
[1:16:00] PVC, we discussed this with the construction teams that built the schools and they're available
[1:16:08] to do the installation this fall. That means that we have people that know our buildings well,
[1:16:13] who built our buildings doing this rather than, you know, they of course will move on to
[1:16:17] additional projects so if we waited until next summer, their teams would be working on other
[1:16:22] buildings and other projects and not be available for the installation. So that's part of the
[1:16:26] reason to move it up to accelerate it. What the big difference is that it will happen while school
[1:16:33] is in session and students are in staffer in the buildings. So David did have a chance to speak with
[1:16:41] I believe a principal at a school where this happened and got positive feedback that, you know,
[1:16:48] they work on the roof of schools and the question was not disruptive at all, and they're able to coordinate anything like trains lifting materials onto the roof.
[1:16:57] Either in the evenings or most likely on weekends, schools are not not being used.
[1:17:02] And just like an act you just, yeah, thank you for summarizing that.
[1:17:09] Sort of high, which was a new school was a school identified, and, you know, I had a
[1:17:14] lengthy conversation with the principal about impact, and one of the things, of course, that made the impact a little bit less significant.
[1:17:21] And I think joled it into this earlier, is that that school was designed for PV, and that's also true at Hardy and Honeywell, where some of that infrastructure was
[1:17:32] built into the design of the roof. Therefore, the, you know, the amount of disturbance is a little bit less significant, you know, to the school.
[1:17:40] So we have that in common that these schools were designed, you know, to carry that weight, you know, and to have some of the infrastructure built into the roof itself.
[1:17:49] So I just went to highlight that additional piece.
[1:17:52] Appreciate that David. Thank you.
[1:17:54] And then we did have an on-site meeting on Honeywell last the end of last week to kind of talk about the logistics and make sure that
[1:18:01] the team there at the school was comfortable, which they were. We had intended to have that meeting
[1:18:06] earlier last week at Hardy, but obviously she was shifting our focus to supporting students and
[1:18:12] staff in other ways at Hardy last week. So without meeting is actually happening tomorrow morning,
[1:18:17] but I did want it, but we're assuming that the outcome will be the same that of
[1:18:22] positive experience and we can work through any concerns or issues that the staff at Hardy might
[1:18:29] So what we're looking here tonight is a vote on this installation for fall, 2020-26.
[1:18:37] So I will stop my share there and just ask if anyone has any questions or comments.
[1:18:42] Thank you.
[1:18:45] can try to get it some other time because it doesn't seem related to this particular vote.
[1:18:51] It's just this vote is timing, right?
[1:18:53] Um, are there any numbers handy, and I don't know if anybody's on the call, like how much electric savings that would be from these installations, like dollar.
[1:19:06] I don't have the dollar. I know that the estimate was that it could provide up to 70% of, I know for Honeywell 70% of electrical needs of the building. So that would be off that.
[1:19:20] I can I can reach out and get a dollar now.
[1:19:23] any
[1:19:32] other questions or comments?
[1:19:37] Okay, thank none. A lot of you want to make the motion.
[1:19:42] I move the school committee approve the permanent building committee to move forward with
[1:19:47] planning for a fall installation. The solar project of the Hardy and Honeywell Elementary
[1:19:53] schools contingent upon the outcomes of the logistics meeting at the Hardy scheduled for May 6.
[1:20:03] tomorrow.
[1:20:05] Yes. Thank you. Thank you. Thank you, Carlson. So, the second window. Yes, I want to. Yes.
[1:20:15] Carlson. Yes. Bob. Yes. And I vote yes, as well. So, that passes five to zero. And I will let the
[1:20:24] you see now. So thank you very much. The next item on our list was the facility's Master Plan Task Force.
[1:20:32] I know I had sent out materials and then I sent out an update and some discussions with Joe earlier
[1:20:41] today. He let me know that there's some staffing concerns and bandwidth concerns with a big retirement
[1:20:47] happening over on his staff and wanted to talk through kind of the timing of this a little more this
[1:20:54] week. So I'm meeting with him on Thursday to talk to that and so I didn't want to go forward with
[1:21:02] this whole discussion and then find out, you know, I just feel like I need all the information
[1:21:06] before we bring it and discuss it with the whole committee. So I apologize for the change in plans
[1:21:12] there but I think it'll be more productive conversation if we have all the information. So I will
[1:21:17] putting this on a future agenda.
[1:21:22] And then with that, we'll move on to the quarterly report presentation
[1:21:26] and David, I'll kick that over to you first. Yeah, thank you. And I'll just as quickly
[1:21:31] I'll turn over to Assistant Superintendent for Finance Operations anymore.
[1:21:41] It's in your unmute.
[1:21:44] Yeah.
[1:21:50] Okay. I'm having the same issue about pulling up the presentations I've had in the past.
[1:21:56] So I'll share for my insidient.
[1:21:58] Okay, that would be fabulous. Thank you.
[1:22:02] Just does not like my setup recently, so I apologize.
[1:22:06] Can everyone see that?
[1:22:08] Yes.
[1:22:08] Okay.
[1:22:10] All right. So we go to headlines next page.
[1:22:15] The FY26. So just so you know, in your packet, you do have the full written report.
[1:22:21] The highlights are going to be discussed here in the presentation,
[1:22:24] but certainly the full right and the report is included in the packet.
[1:22:29] So I want to start.
[1:22:30] By saying the FY263rd Court of Report reflects a surplus of $423,000. The surplus is driven by one
[1:22:39] number of out-of-district tuition placements classified as reasonably known as well as lower transportation
[1:22:46] costs. Revenue receipts from fees intuition or close to budgeted expectations. And we do receive
[1:22:54] We did receive one new grant and two amendments to grants that will require school committee approval.
[1:23:00] Next slide.
[1:23:04] The district budget is reviewed and updated regularly and known and anticipated changes are reported to the school committee each quarter each year.
[1:23:13] I present the adjusted budget in the fall, the second quarter and February and the third quarter report may.
[1:23:19] The final year and financial position on school department is presented to the school committee each September.
[1:23:24] And as you know, our quarterly budget is broken out the $94 million is broken out across two different categories salary and expenses and four departments instruction instruction administration operations and student services.
[1:23:40] And so this is our breakout of our quarter two budget, so if we go to the next slide.
[1:23:49] And so I did want to just put a note here,
[1:23:51] a negative figure indicates that there's a transfer into the category,
[1:23:56] so in this case, we're transferring $361,000 into salary
[1:24:00] and other compensation.
[1:24:04] So it does reflect a transfer from non-cellary to our salary accounts,
[1:24:09] and that is driven primarily from the salary reserve being increased by 423,000 dollars.
[1:24:16] I'll talk a little bit more about that, but that represents our current surplus.
[1:24:22] Substitutes across old categories. We added $64,000. We do have savings in athletic
[1:24:28] coaches. There are a number of positions that we were unable to fill because we just didn't have
[1:24:33] the students and so that was about a $47,000 savings.
[1:24:38] Student activity reductions is about $14,000,
[1:24:41] and again, part of as due to unfilft positions.
[1:24:44] We are anticipating some additional staffing needed
[1:24:48] and human resources, temporary staff for about $12,000.
[1:24:52] That is covered by a reduction in my office
[1:24:55] due to a number of vacancies.
[1:25:00] So that's it's about $12,000.
[1:25:01] And then extended school year, we're expected to go in is going to increase by $32,000.
[1:25:09] We'll talk a little bit more about the FTE.
[1:25:11] There is an increase due to additional teaching assistance and savings from our reduction
[1:25:17] in paraprofessionals.
[1:25:18] But we'll go over those in just a little bit.
[1:25:20] So if we go into the next slide.
[1:25:23] So in terms of full time equivalents, FTE change noted here in instruction.
[1:25:29] So this essentially is showing us from annual town meeting, we plan 786.6 FTEs.
[1:25:36] We are up 8.5 FTEs over the course of the year so far.
[1:25:42] Quarter 3 has us at 795.
[1:25:45] So the change in instruction is due to a correction and hours of a unit D staff member.
[1:25:51] In terms of the third quarter, we have added five additional teaching assistant positions
[1:25:57] since quarter two, we have reduced one parallel professional or beat what we call behavioral
[1:26:03] technician positions and one special educator, so it's a net increase of three FTEs.
[1:26:10] At the time the report was generated, there were 11.03 general fund positions open and three
[1:26:16] grant funded positions open. To date the unbudgeted impact to FY27 at this point is three FTEs
[1:26:26] cost of $98,000. Next slide.
[1:26:33] In terms of expenses, we anticipate, again, transferring $361,000,
[1:26:39] from salaries into the non-sourists. Part of the changes is we do have a reduced budget offset
[1:26:48] at middle school athletics and high school athletics, so it's about $65,000 savings or a loss
[1:26:55] of revenue. Transportation is being reduced by $128,000. Most of that is due to additional
[1:27:02] grants that we have received that we are going to put towards offsetting some of those costs
[1:27:07] and then we will detail the tuition account student services changes in the next slide, David.
[1:27:16] Thank you. So the district has budgeted for 60 out of district placements that currently is 59
[1:27:23] known placements and one potential placements for a total of 60 placements in quarter-three,
[1:27:30] the out-of-district placement is over budget currently by $288,000.
[1:27:36] That results in a reduction of collaborative cost by about 20,000 in increase in professional
[1:27:42] services by about 24,000. A reduction to private school by about 200,000 in a reduction to residential
[1:27:50] over about 91,000.
[1:27:53] Circuit Breaker is still unknown at this point in the year.
[1:27:57] Transportation is currently reimbursed at 61.36%
[1:28:01] if additional funds do become available from the state.
[1:28:04] We could receive an additional $145,000.
[1:28:08] If, in fact, it was funded at a full 75%.
[1:28:11] So if we go to the next page.
[1:28:15] So this is just a summary that shows that we're making transfers
[1:28:18] between salary and non salary. As we do, although we're showing a surplus on paper,
[1:28:27] I must maintain the total appropriation that was approved at town meeting and that is the
[1:28:33] 94 million dollars. And so any budget surplus that we have, we are simply transferring that into the
[1:28:39] salary reserve account, which kind of resides in the 320 instruction. So that's how we have to
[1:28:45] Make sure it nets to zero at this point once we close out the fiscal year, in mid July, obviously will show in amount less than $94,000.
[1:28:57] So if we go to the next slide, we're going to go into grants, perfect.
[1:29:05] So in FY26, we have been awarded $2.9 million of state and federal grants.
[1:29:11] Since quarter two, Desi has awarded or modified three grants that do require school committee approval.
[1:29:20] So the Mechko Special Education Supplemental Award, the New Award amount is 54,959.
[1:29:27] This will be used to offset the cost of special education transportation for Boston resident students.
[1:29:33] Title one increased by a whopping $166, entitled to a has increased by another whopping $657.
[1:29:45] So all those three amounts are what we would seek your vote on.
[1:29:52] When we go to the next slide and talk about the carry forward grants.
[1:29:56] So we did carry forward money both in 24.
[1:30:00] However, in 2025 into 26, essentially we have about $21,000 that remains open of those carry-for demands. So, as is our current practice, as we try to expend the oldest federal funds.
[1:30:16] First, sometimes there are some requirements that we can't quite meet, and so we sometimes have to fund current year before we go back to prior year.
[1:30:24] But we're working to close those out just as quickly as we can.
[1:30:28] So if you go on to cash capital, we have been, thank you.
[1:30:33] We have been able to close out 24 and 25,
[1:30:38] that you know once cash capital is appropriated,
[1:30:41] it is good for three years.
[1:30:43] So we can use those funds over three years.
[1:30:45] We do try to use the oldest funds first.
[1:30:48] And we have about $1.1 million of that white 26 remaining.
[1:30:53] So this evening marks my final financial report to the committee before I transition to my new role as CFO and Hopkins in public schools.
[1:31:03] I hope these currently, quarterly reports have been provided clear and meaningful insight into your financial position across all funds,
[1:31:12] helped illustrate how staffing levels naturally fluctuate throughout the year,
[1:31:16] and clarify the rational behind the position adjustments as needs of all.
[1:31:20] Then a privilege to support this work and to contribute to the committee's understanding and decision making.
[1:31:26] Thank you.
[1:31:29] Thank you very much, Cindy, and as always, we appreciate the support and the detail that you provided.
[1:31:36] I will open it up to committee members for their questions.
[1:31:41] We're coming
[1:31:47] from the thing, any, I had one question on the athletics.
[1:31:52] I believe the, it looked like we were expecting less revenue in Q3.
[1:31:58] And I, if I'm understanding that correctly, I believe we had the theme,
[1:32:03] we'd made a similar adjustment in Q2.
[1:32:05] And I just wanted to make sure I'm understanding it correctly.
[1:32:08] That was two adjustments.
[1:32:11] So twice, we look at that number this year.
[1:32:14] Yes, that is correct. And and again, part of what I'm so yes, we have revenue is less certainly at the middle school level. We have a number of sports that we couldn't run again this year. I think that's going to be something that the committee is going to want to look at in the future that is becoming more challenging for us.
[1:32:34] The second thing is we do have a retirement and we are looking to do some overlap days and so I'm buffering in a way the ability to cover some of those overlap days in the summer and early fall and to do that through the revolving fund when we have sufficient revenue to do it and we have a current fund balance.
[1:32:56] in our general fund to seem appropriate, so that is some of the reasons for making those reductions this year.
[1:33:04] Okay.
[1:33:05] To talk about, thank you.
[1:33:07] And up and up one more time for questions from anyone.
[1:33:10] Mr. Nick, can you just, I think you did say it and I just didn't quite get it.
[1:33:15] The student services increase in FTEs.
[1:33:18] What type of positions are those again?
[1:33:20] So it is an increase of five teaching assistants, a reduction of one per professional and a reduction of one teaching position.
[1:33:30] In terms of the change between quarter two and quarter three.
[1:33:44] Any other questions?
[1:33:47] And you've probably already said the Cindy, but those are those changes are based on student needs.
[1:33:55] Yes.
[1:33:57] Yes, and it might be able to go into more detail if you'd like, but yes.
[1:34:03] I'm good.
[1:34:05] Yes, it is based on student need, and we also had a teacher leave and we were able to reallocate resources without in any way impacting negatively students access to their IP services.
[1:34:29] Thank you.
[1:34:32] All right.
[1:34:32] It looks like that.
[1:34:34] Well, Cindy again.
[1:34:35] Thank you very much for so very appreciative of everything that you do for the district.
[1:34:41] And we know.
[1:34:42] I think we do have enough.
[1:34:44] Thank you.
[1:34:44] Oh, we do need to prove the grant.
[1:34:46] Yes.
[1:34:46] Thank you.
[1:34:49] Very good.
[1:34:50] So I want to do you have the motion's language for the grant?
[1:34:55] Yes.
[1:34:57] Okay.
[1:34:57] I think I moved at the school committee vote to accept the, of the metco, is that the one we're talking about the grant metco special education supplemental grant in the amount of 54,959 dollars and increases to the title one grant of 166 dollars and the title two title two a grant of 657 dollars.
[1:35:25] Thank you. Thank you, Kassas and Linda.
[1:35:36] Yes.
[1:35:36] Thank you. Alana. Yes. Kassas. Yes. Bob. Yes.
[1:35:44] And I vote yes as well. So that carries five to zero.
[1:35:48] Thank you everyone.
[1:35:50] And I think we have one final discussion and vote item for our open session tonight,
[1:35:56] which David I'll turn it over to you for the academic calendar for next year.
[1:35:59] Great. Thank you, Nicky. And I'm going to share my screen just to get this document up in front of you.
[1:36:07] I think everyone can see that. So, colleagues at your last meeting, we're joined by Dr. Jamie Chism, our high school principal.
[1:36:15] You know, coming seeking approval for an update to the approved academic calendar for the 2026-2027 school year.
[1:36:23] and the proposal was specifically around moving the graduation date from the first Friday and June,
[1:36:33] which for next year for 2027 would have been Friday, June 4th with the recognition that
[1:36:41] because we have a later start to the year we have a late Labor Day next year and as a result,
[1:36:47] Our last day for students with no snow days is June 21st and the state has a provision
[1:36:55] that the last day for seniors can't be more than 12 days beyond the scheduled last day
[1:37:03] for students.
[1:37:04] And if you do the count, that would have put the last day for seniors, literally the day
[1:37:08] before graduation, which is simply not feasible for us, given all of the need to close
[1:37:15] out, classes, senior week activities, et cetera, and so the proposal was, as you see highlighted
[1:37:22] here, to move our high school graduation in 2027 from Friday, June 4th to Friday.
[1:37:30] 11th, which will allow us to have that time for all the traditional senior activities that would occur before graduation.
[1:37:42] Okay, thank you, David. Does anyone have any questions or comments on that change?
[1:37:47] Just fun. This may be a typal David, but it looks like June 3rd is a Friday and also June 11th is a Friday, so probably you mean June 4th?
[1:38:01] June 4th is the correct, would be the graduation day.
[1:38:04] Cause is where you're seeing that.
[1:38:06] And the calendar that you put, well, I'm seeing it in the packet,
[1:38:10] but maybe you put up something different.
[1:38:13] Well, there are two calendars.
[1:38:14] It says June, June 3rd, F Friday.
[1:38:19] So I think you mean June 4th, is that type of?
[1:38:24] David, it's in the text on the right hand side.
[1:38:29] Or the seniors last day.
[1:38:30] Right, so the seniors last day will be that that is June 3rd. That is not which is
[1:38:37] Right, which is a Thursday. Oh, there should be Thursday. Yep. Yep. Okay. Got it. Yeah. Thank you, fastest. Perfect.
[1:38:45] There's some eagle life. Yeah, no great job. Thursday. We'll make that change.
[1:38:54] Any other questions or comments?
[1:39:00] Okay, then Alano are ready for the motion and if you can just say half amended.
[1:39:05] to capture the conversation about date.
[1:39:09] Um, wait.
[1:39:13] I didn't, okay.
[1:39:16] Uh, wait, as amended.
[1:39:19] Added that update to the calendar, is everything?
[1:39:22] Just say that we're voting to approve the calendar as amended.
[1:39:26] Okay.
[1:39:27] I move that the school committee approve the, uh,
[1:39:36] Revised S.Y. 2026-2027 academic calendar as amended.
[1:39:43] A second.
[1:39:45] Second.
[1:39:47] Thank you, Linda.
[1:39:51] Yes.
[1:39:52] Alana.
[1:39:53] Yes.
[1:39:54] Castless.
[1:39:56] Yes.
[1:39:57] Bob.
[1:39:58] Yes.
[1:39:59] And I vote yes as well.
[1:40:01] So that passes five to zero.
[1:40:03] So at this time, if we concluded all our business for open session,
[1:40:07] before we transfer to executive session, I do want to, just again,
[1:40:12] thank all our teachers on this teacher appreciation week for all.
[1:40:16] They do in our classrooms each and every day,
[1:40:18] and encourage anyone to reach out to their teacher or their child's teacher
[1:40:23] and let them know how much they are appreciated.
[1:40:28] So now we're ready to move into our executive session.
[1:40:31] So, I moved at the School of Committee,
[1:40:33] enter into Executive Session under National Law,
[1:40:36] Chapter 38, Section 21A,
[1:40:39] exemption number two, to discuss strategy
[1:40:42] with respect to non-union salaries and contracts,
[1:40:45] because non-union salary increases
[1:40:47] and the superintendent contract,
[1:40:49] as well as to approve executive session minutes
[1:40:51] from March 24th, and invite into the Executive Session
[1:40:55] Superintendent David Lucia, HR Director, David Turcott,
[1:40:59] and it's the sense of superintendent than be more.
[1:41:02] And to not return to open session.