Transcript
SOURCE TRANSCRIPT
This transcript is downloaded from the source you provided but we haven't reviewed it for accuracy. Treat it as a starting point, not a verbatim record. You can also request an AI-transcription of the audio file with the button to the left.
[0:00]
I'd like to welcome everybody to the Town
[0:02]
of Salpich Animal Control Shelter Building Committee, Thursday,
[0:08]
August 27, 2026 at 6 p.m. Vice
[0:12]
Conference Room, First Agenda Roll Calls, Carlisle, here.
[0:17]
Are you here?
[0:18]
Are your tees absent?
[0:21]
Your Provost?
[0:23]
Present.
[0:24]
Chief?
[0:25]
Here.
[0:26]
Katie?
[0:27]
Here.
[0:31]
Josh, are you excused?
[0:32]
Alex?
[0:33]
Here.
[0:35]
Okay, moving on to...
[0:37]
Who are the medics?
[0:38]
Jack, do we have any medics?
[0:39]
No, unfortunately I wasn't able to get them
[0:41]
finalized today.
[0:42]
I apologize.
[0:43]
Okay, we'll take them up on that meeting.
[0:45]
I thought I had one, buddy.
[0:46]
You're fired.
[0:46]
Moving on to number three, review and discuss
[0:49]
the following and take any action.
[0:52]
Chris with an update on MEP, building project
[0:56]
design, and construction dollars.
[1:00]
Chris?
[1:01]
Okay, so, yeah, we provided...
[1:04]
So, we didn't go out to formal estimates
[1:07]
on this because of the...
[1:09]
I'm sure Alex is in the business, and
[1:11]
Sky is in the business.
[1:12]
It's like a moving target.
[1:14]
So, we go and pay somebody the $10
[1:19]
,000 that we were going to do it.
[1:21]
We literally talked to these people, like, you
[1:23]
know, we're going to tell you this today
[1:24]
and tomorrow it's going to change.
[1:26]
Like, you know, pull together an estimate.
[1:29]
What you're looking at is probably on a
[1:30]
high side conservative where we want to be.
[1:33]
If you're looking for funding, you know, it
[1:34]
doesn't always look great when you go off
[1:36]
the initial set of funding, but at least
[1:37]
you'll be covered for the project that you
[1:39]
have going on.
[1:40]
And then, you know, see how that, you
[1:43]
know, see...
[1:44]
Well, you've really got to put it to
[1:46]
bed to find out what you're going to
[1:47]
fund.
[1:47]
So, what we did was use our opinions
[1:50]
of profitable cost.
[1:53]
From the site side, my perspective is I
[1:56]
use all mass DOT budgets for projects that
[2:02]
occurred in the past, from present back to
[2:05]
two years.
[2:06]
So, I'm talking about moving materials.
[2:08]
So, really it is the municipal jobs that
[2:11]
are using actual estimates that have been made
[2:15]
for projects that have been completed.
[2:17]
But, again, those are street jobs, right?
[2:20]
Like a project.
[2:21]
So, if you...
[2:23]
It's likely, again, probably it's a conservative estimate
[2:26]
where we exactly want to be, but there's
[2:29]
probably going to be some savings in there
[2:31]
because you're going to have someone coming and
[2:32]
going and going.
[2:33]
As long as you're following all the public
[2:35]
procurement, you have to pay for building wages,
[2:38]
but you're not always seeing the same swings
[2:41]
you would see for a big highway project.
[2:43]
But that's where we have to come from,
[2:45]
our estimates, because that's basically where the numbers
[2:48]
have come from.
[2:51]
No, I think that makes sense.
[2:56]
Again, it definitely probably seems like it's probably
[2:58]
aligned with a road construction project versus a
[3:00]
site development plan.
[3:02]
I was looking through and just curious about
[3:05]
the site conditions themselves, how much that contributes
[3:09]
to some of those, but nothing really seemed
[3:11]
like crazy.
[3:12]
I don't know.
[3:13]
To me, it seemed like you were being
[3:14]
conservative, as you mentioned.
[3:17]
The only thing that really stuck out to
[3:19]
me on the building side, which I don't
[3:20]
know if you want to talk separately about
[3:21]
that, but on the building side, the only
[3:25]
concern I have is some of the specialty
[3:27]
items because those can be, out of left
[3:30]
field, expensive.
[3:32]
So the dog doors, that could be $10
[3:34]
,000, that could be $40,000.
[3:36]
I was like, no idea.
[3:38]
Yeah.
[3:38]
So those are some of the items that
[3:40]
just stuck out to me.
[3:41]
I think specialty-wise, that would be Pamling.
[3:44]
I'm sure it's probably not too far off.
[3:47]
And then I saw there was just a
[3:48]
couple of square foot estimates at the bottom
[3:50]
based on a bunch of different values.
[3:52]
I wasn't sure if there was any insight
[3:54]
as to where those values came from.
[3:56]
Yeah.
[3:57]
That would just—and Jake Align is the architect.
[4:00]
He's pulled those off at his number.
[4:02]
He's sort of basically doing the same type
[4:03]
stuff that did Zazai.
[4:05]
It's kind of how we have to run
[4:07]
it on most recent projects and keep that
[4:10]
as up-to-date.
[4:11]
Yeah, it's an interesting mix because it's a
[4:13]
commercial building, but a lot of construction is
[4:16]
kind of more residential construction-style.
[4:17]
Right, right.
[4:18]
So I think, again, I can't tell you
[4:24]
how much it costs to build an animal
[4:26]
control shelter per square foot necessarily, but I
[4:30]
think figuring out where those—what informs that is
[4:33]
definitely helpful in determining if it's an accurate
[4:37]
estimate.
[4:37]
Right.
[4:40]
Any other questions?
[4:42]
Is there anything that suffers DAW to do
[4:46]
to cut the cost on this?
[4:47]
I mean, anything.
[4:50]
So, I mean, from a public procurement perspective,
[4:54]
it's tough.
[4:55]
I mean, it comes from the chief procurement
[4:57]
officer that says, okay, can we break this
[4:59]
up?
[5:00]
Can we get something done internally?
[5:02]
Have them look at how— And that's really—anytime
[5:09]
you get into a situation like this, they
[5:11]
say, well, as long as it's good with
[5:13]
the chief procurement officer and we get buy
[5:16]
-in from that DAW, then we can say,
[5:18]
hey, this is what we're looking for.
[5:20]
Can you prep this pad for us?
[5:23]
If that's really what we're looking to have
[5:26]
them do.
[5:26]
And then we can do it to cut
[5:27]
the cost.
[5:28]
That's what I'm wondering.
[5:31]
In the realm of— Well, that would be
[5:33]
okay, but then you hire the contractor, then
[5:36]
it's not how people would expect that you
[5:38]
did.
[5:39]
I mean, I don't know in what perspective—
[5:42]
Like site preparedness.
[5:44]
That's what I'm thinking.
[5:45]
We've got all the equipment to do site
[5:48]
preparedness, don't we?
[5:51]
This one I'm going to say no.
[5:52]
Yeah.
[5:53]
We have a ledge at a very shallow
[5:55]
grade with ledges, so there's going to be
[5:59]
a hammer blasting, which I think it would
[6:02]
probably be a hammer, but that is a
[6:04]
different tool than— I didn't notice that.
[6:09]
When you go onto the site and you
[6:12]
lay it out, you're going to do the
[6:13]
foundation, you've already done the deep hole test.
[6:16]
You've already researched where the subject is.
[6:18]
That's Toronto.
[6:19]
Right.
[6:20]
So for us, it's more or less blowing
[6:23]
a hole into the ledge that we can
[6:25]
get some foundation in.
[6:26]
Yeah.
[6:28]
And I don't think they have the capacity.
[6:29]
No, they don't.
[6:30]
It's probably a difficult part of balancing.
[6:33]
Like, your budget needs to be as low
[6:34]
as it can be.
[6:36]
Because we're abetting the project between the general
[6:39]
and the DBW.
[6:41]
Yeah, because they're going to pull off the
[6:43]
plan if they have some emergency content.
[6:45]
Right.
[6:45]
And you're just trying to get a pad,
[6:46]
a simple pad, and pull it down.
[6:48]
I think where we've got to go is
[6:49]
we've got to find out what the actual
[6:50]
number is.
[6:52]
What is it?
[6:52]
How many square feet is the building?
[6:54]
3,000.
[6:55]
3,000?
[6:55]
Yeah.
[6:58]
I gave the prints to a contractor to
[7:01]
look at it, and then we plugged in
[7:02]
the numbers, and they thought it was about
[7:04]
$500,000 high.
[7:06]
But again, this contractor deals in commercial work
[7:10]
and stuff like that.
[7:13]
Yeah.
[7:13]
And I'm going to agree with you 100%.
[7:14]
Yeah.
[7:15]
These numbers are going to be all over
[7:16]
the place.
[7:17]
You know, 3,000 square foot building, and
[7:19]
gentlemen were talking about it, and he told
[7:21]
me this idea, okay.
[7:23]
But then, I know Jeff and I have
[7:25]
a little bit of experience with how the
[7:27]
bids come in.
[7:28]
You know, we did the middle high school.
[7:29]
We did the fire station.
[7:31]
You know, go for a rebid.
[7:33]
You know, there's a lot of chess pieces
[7:34]
to move around.
[7:35]
But the thing is, on this one here,
[7:37]
I think, there's a lot of money that's
[7:40]
been donated, and there's still people that want
[7:43]
to donate heavy money, and I'm turning around
[7:47]
and going, I don't have a solid number
[7:50]
to tell anybody.
[7:51]
Yeah.
[7:51]
So, to me, I think we've got to
[7:53]
go to the next step, which is going
[7:55]
to cost money, and this is why we're
[7:57]
here.
[7:57]
We're going to discuss, do we want to
[7:59]
go to the next step, which is, you
[8:01]
know, a bid process.
[8:04]
You know, how long will it take.
[8:06]
Yeah, I mean, we're all in line to,
[8:08]
this is all, we're in line to stop
[8:10]
pulling bid docs, because we just have them,
[8:12]
because we didn't want to start charging town
[8:14]
if they weren't going to put it on
[8:15]
the street.
[8:16]
Yeah, because I think it's 6 and 1
[8:17]
1⁄2, because, yeah, it would be great to
[8:20]
have, like, a realistic number, but to this
[8:22]
point, by the time we get the money
[8:24]
in line, is that going to be the
[8:25]
realistic number anymore?
[8:26]
Or are you low, because you were basing
[8:29]
it off of bids from months ago?
[8:30]
That's part of the construction of the world.
[8:33]
Oh, yeah.
[8:34]
But, if I may, we're not going to
[8:37]
go out to bid if we don't have
[8:39]
the money allocated to the project, because then
[8:44]
you're out to bid, and you don't have
[8:45]
the funding to do it.
[8:46]
So, it's going to have to be presented
[8:48]
to the council of how you're going to
[8:50]
fund this.
[8:51]
Right.
[8:51]
Because we could throw it out on a
[8:52]
bid, and if the bid's coming in too
[8:53]
high, now you've got to change the scope,
[8:55]
because you can't rebid the same job.
[8:59]
So, unless you make a change, a substantive
[9:01]
change.
[9:03]
So, like, for the fire station, when we
[9:04]
did that, our first bid package was the
[9:06]
fire station, alternates and all that, but it
[9:10]
was all that included demolition of the properties
[9:13]
where the original bid documents were.
[9:15]
When we went out the second time, it
[9:17]
was a built-in, and all that demolition
[9:20]
was out, and that type of work was
[9:22]
out of it, and so that was enough
[9:23]
of a substantive change in the bid documents
[9:25]
that we didn't have to change the scope
[9:26]
of the building anyway, because it was, like,
[9:30]
we took a substantial portion out of the
[9:32]
project.
[9:33]
So, that's the caution, right?
[9:35]
So, is it you invest $10,000, like
[9:37]
you say, and get an actual closer cost,
[9:40]
then go to council?
[9:42]
Is that what you do?
[9:43]
Or do you go to council and say,
[9:45]
hey, the opinion problem cost is $2.1,
[9:47]
but we only have $475,000 left.
[9:51]
Where's the $1.7?
[9:53]
But I think that number's way high.
[9:55]
Well, how do you determine that?
[9:57]
By going out to bid.
[9:58]
But then you're going to have to have
[10:00]
town council support.
[10:01]
How do you find that?
[10:02]
So, not trying to dissuade anybody, but you
[10:06]
can't go out to bid unless you have,
[10:08]
how do you fund the project?
[10:12]
How much money do we have right now?
[10:15]
A little bit undefined.
[10:20]
We're getting more from...
[10:22]
But you can't go out to bid, say,
[10:23]
right?
[10:23]
Yeah, we don't even live.
[10:25]
One of the fun things was, it says
[10:27]
how much do you need.
[10:30]
How good of a relationship does the town
[10:32]
have with any of the general contractors that
[10:34]
were not working recently?
[10:36]
They might be willing to give you some
[10:38]
pretty good estimates at no cost.
[10:45]
A lot of late work for $0.
[10:49]
Yeah.
[10:50]
So, people want you guys on a time
[10:51]
track sort of thing?
[10:52]
Yeah, because they want to be in your
[10:55]
good graces, so that you're happy.
[10:57]
If we want to go down that road
[10:59]
beforehand, I'd ship this off to our owner's
[11:02]
project manager.
[11:04]
Does a lot of the design, and if
[11:05]
I have good, at least baseline documents they
[11:07]
can give me that, we can send to
[11:09]
him.
[11:10]
Rick Pomeroy does a very good job.
[11:11]
They're very good on...
[11:13]
That's the owner's project manager.
[11:15]
Yeah, the fire station.
[11:15]
And they'll probably do that estimate for you.
[11:19]
I mean, again, we didn't want to go
[11:21]
to an estimated knowledge gap because...
[11:23]
He may be able to just take a
[11:24]
quick look at it Yeah, your risk is
[11:27]
a lot lower because you have a set
[11:28]
drawing.
[11:29]
It's not like you're at a 50%
[11:30]
set drawing.
[11:32]
You're going to come back and...
[11:35]
It's probably enough for them to be able
[11:38]
to...
[11:39]
Yeah, just give a baseline, because they're out
[11:42]
there bidding on the public side, not just
[11:43]
the commercial side.
[11:44]
They're bidding on the public side.
[11:46]
If we had some good scope of, okay,
[11:48]
it's a septic, the waterline is this, this
[11:52]
is the site, what is the general site
[11:54]
work, what is all that?
[11:56]
Yeah, you build in some sort of escalation
[11:58]
anticipating that you're not going to actually buy
[12:00]
the project until, say, a year later or
[12:02]
something along those lines.
[12:03]
And that's essentially right on your contingency of
[12:07]
5% escalation, anticipating that next year it's
[12:10]
going to cost 5% more to build.
[12:11]
So if you send a PDF to Jack
[12:14]
to give to Pomeroy, that would be a...
[12:16]
Send you this site, the architectural, and the...
[12:22]
And I'll ask them, I'll see if they'll
[12:24]
do it for us with no cost and
[12:26]
go from there.
[12:28]
Just so you can...
[12:30]
I mean, I think it's not going to
[12:31]
go into big detail.
[12:33]
They'll be able to just look at it
[12:34]
pretty quick and go, okay, I know...
[12:35]
There'll still be unit rates and all that
[12:36]
stuff.
[12:37]
Yeah, of course.
[12:37]
But it'll be forked off of hopefully something
[12:39]
that's slightly dialed in.
[12:42]
It'll be a much more scientific process than
[12:44]
what we've been practicing so far.
[12:46]
And I have mentioned to Tom...
[12:46]
They're not giving you any different answers.
[12:49]
I have mentioned to Tom that he was
[12:51]
willing to take a look at it.
[12:52]
I just need more details as to what
[12:54]
I've said to him.
[13:01]
Excuse me, I have a question.
[13:04]
Go ahead.
[13:04]
Actually, I have two.
[13:06]
Why would the doors be so expensive?
[13:09]
You said that they would vary from $1
[13:12]
,000 to $4,000?
[13:14]
The dog doors?
[13:15]
Oh, I was saying the...
[13:17]
Yeah, the...
[13:17]
Just specialty items in general, I guess.
[13:20]
Any really specialized that you're not installing all
[13:23]
the time, you have a really difficult time
[13:25]
estimating what that cost would be without actually
[13:27]
getting somebody to give you a price.
[13:29]
Really?
[13:30]
Yeah.
[13:30]
Oh, okay.
[13:32]
And I assume those are just like the
[13:34]
doors that let dogs out?
[13:36]
Yeah, but I think, if I'm not mistaken,
[13:38]
you were saying they have a pulley system
[13:39]
so you don't have to actually be in
[13:40]
there to open the door.
[13:42]
It's a little more complicated than a dog
[13:44]
door.
[13:45]
Oh, okay.
[13:45]
Yeah, because they seem cheaper at a pet
[13:49]
store.
[13:49]
Yeah, of course.
[13:50]
So I was like, wow.
[13:52]
And my second question is, I haven't been
[13:55]
at these meetings in a long time.
[13:57]
Are there any changes of proximity to the
[14:02]
roof or any of the buildings?
[14:06]
I mean, really, I don't think I've been
[14:09]
here since last February.
[14:12]
Yeah, these are the same ones that were
[14:14]
submitted and approved through planning and constitution.
[14:18]
Yeah.
[14:18]
Oh, okay.
[14:19]
No changes?
[14:20]
No.
[14:21]
Okay.
[14:22]
Thank you.
[14:23]
Sure.
[14:25]
Hey, Chris.
[14:26]
I'm going to move on.
[14:27]
We talked about reviewing preliminary cost estimates, the
[14:31]
funding, update on the bid process.
[14:34]
If, Jack, you take a look at that
[14:36]
hypothetically, what are we talking?
[14:39]
Say he comes through with a projected number
[14:43]
and we go with his number and we
[14:46]
say, we think we're going to go forward
[14:49]
with this.
[14:50]
From the time we go off to bid,
[14:52]
what are we talking timeframe-wise?
[14:54]
So we have to pull the documents together
[14:57]
and then there's usually a standard 30, 60,
[15:00]
90, depending upon, because, again, Jack's office tells
[15:03]
us, okay, we want to give folks 30
[15:05]
days to review this and 60 days to
[15:07]
review it, get the bids in by then,
[15:10]
whether they need We did 30 the first
[15:13]
time.
[15:13]
We did 30 the first time.
[15:15]
So, you know, the MEPs are ready to
[15:18]
pull the bid documents together.
[15:19]
I'm ready to pull the bid documents together.
[15:21]
So that could be within a month, we
[15:22]
could have everything together fully.
[15:25]
And then it's just I'll lay out the
[15:27]
timeframe for standard bidding.
[15:30]
It's going to be bid for two weeks.
[15:31]
It's going to be, you know, review.
[15:37]
So that's usually a few-month process.
[15:39]
And then at this point in time, you
[15:41]
could, you know, get construction ready for the
[15:46]
spring if we had everything in place.
[15:48]
Perfect time, this time of year to do
[15:50]
everything.
[15:52]
People, when it's in, then they're just setting
[15:54]
this work aside, maybe the first job, or
[15:56]
whatever else, but at least they're, you know,
[16:00]
this is a good time for bidding anyways.
[16:02]
The spring.
[16:05]
And then the site would allow them.
[16:08]
The site would allow this at any time
[16:09]
because it's not in the world.
[16:11]
You know what I'm saying?
[16:12]
If they wanted to move in and move
[16:13]
in during the wintertime, there wasn't, they're out.
[16:17]
Is it fair to say that the whole
[16:18]
building is going to be on ledge?
[16:22]
It won't be on ledge, but it's going
[16:25]
to be close.
[16:26]
I mean, the footings and everything will be
[16:28]
pretty much on ledge.
[16:30]
Right.
[16:30]
So in the wintertime, ledge doesn't freeze.
[16:34]
I'm just thinking about your company did a
[16:36]
high school, and there was no ledge.
[16:39]
The winterization was tremendous.
[16:42]
Expensive.
[16:44]
Following the ground is not a good idea.
[16:45]
Yeah.
[16:47]
Did we have to follow the ground?
[16:48]
Because I thought we had a good spring.
[16:51]
There were envelopes.
[16:51]
No.
[16:54]
Everything went well under budget, on time, with
[16:57]
what I got, but when you're dealing with
[16:59]
a palm field, when you're dealing with bedrock,
[17:01]
it took two different worlds.
[17:03]
And maybe that's aggressive, but like I said,
[17:07]
sometimes the state says you can't go on
[17:08]
the road April 15th, but we don't mean
[17:10]
to wait until April 15th, because they're off
[17:12]
in the backfield.
[17:14]
They're not in anybody's way, really.
[17:16]
It's whatever they do their work.
[17:22]
We're going to get the PDFs out.
[17:25]
I'll get it from him.
[17:28]
I'm rolling to you to be ready very
[17:29]
good.
[17:31]
All right.
[17:31]
So at this point, we'll move on to
[17:34]
any other discussion.
[17:36]
If not, moving on to four, approval of
[17:39]
any invoices to be submitted to the finance
[17:42]
department, payment from McClure.
[17:45]
This is just an invoice for Chris for
[17:47]
$2,990.
[17:51]
Invoice number 22970.
[17:55]
Sorry for the delay.
[17:57]
At least it's a small number for you.
[18:01]
What's it for?
[18:02]
It was for the last revision.
[18:05]
It's all in line with our contract.
[18:07]
So we haven't touched the bidding.
[18:09]
The next thing for us to do is
[18:10]
start the bidding process so that money doesn't
[18:12]
set aside.
[18:13]
So we heard the finalization of it.
[18:15]
What was that number again, Jack?
[18:17]
$2,990.
[18:19]
A motion.
[18:20]
It's a motion to pay invoice for $2
[18:24]
,990.
[18:26]
Do I have a second?
[18:27]
Second.
[18:27]
Alex seconds it.
[18:29]
Any discussion?
[18:31]
All those in favor?
[18:33]
Opposed?
[18:34]
Unanimous, all present.
[18:37]
Discussion of the next meeting day.
[18:40]
Do you want to wait until we retrieve
[18:41]
that?
[18:42]
Yeah, I guess, yeah.
[18:43]
We should have a quick turnaround, but I'll
[18:45]
put it in today.
[18:46]
Sounds good.
[18:47]
Motion to adjourn?
[18:48]
Motion.
[18:49]
Second.
[18:50]
All in favor?
[18:51]
Opposed?
[18:52]
Where's the motion?
[18:53]
I'm sorry.
[18:54]
I motion.
[18:54]
Second.
[18:55]
I second.