[0:00]
So, depending on the weather, there's
threats of a little bit of rain, it
[0:02]
shouldn't slow us down.
Um, but long and short of it is we
[0:06]
should see from about Brenda to Highway
10 should be paved, let's just say by
[0:11]
Friday. Okay, and most of the curb and
gutter will be in place.
[0:16]
And um, as they continue to work on that
in all likelihood next week,
[0:22]
uh, we probably won't see any paving,
but the following week we'll see them
[0:25]
pave from then where they're likely
leaving off to
[0:28]
the the um,
right away of of County Road 23 on
[0:33]
Edgewood. So, that intersection is going
to be a little wonky for a while until
[0:37]
they get their structure there.
I did talk in conjunction with that,
[0:41]
we're waiting for a structure on the
county project so we can get the uh,
[0:44]
drain pipe in. We'll start at the golf
course and move across 23 and connect in
[0:49]
with the drain collection that we're
working on Edgewood with right now.
[0:52]
Um,
that work is is uh, scheduled to be done
[0:55]
next Wednesday.
So, there's going to be a time the
[0:59]
county will announce it. We'll try and
share that on social media as well that
[1:02]
23 will be absolutely closed cuz they
got to dig a trench through that to set
[1:06]
that pipe.
It should only be a few hours, but you
[1:09]
never know with construction what what
we're going to see. But, Edgewood is
[1:12]
getting really really close. So, the
more people can stay off the main line
[1:16]
of Edgewood and just cross where you
need to to get in and out, the easier it
[1:20]
is for the paving crews and the fine
grading crews. The more you drive on it,
[1:24]
the harder it is to get that flat
surface back out there. They are going
[1:27]
to use the paddle paver out there so
they're going to be dumping it. It gives
[1:31]
us a better product, it puts it down
faster, they can cover a lot of ground,
[1:34]
and they're going to bring bring two
crews in if they need to to get that
[1:37]
done. So, the bulk of the base course
paving is going to be done, um,
[1:41]
likely by Thursday, just give it Friday
and and call it good. But, again, we do
[1:46]
appreciate there's we've had some very
positive feedback. We've got a few
[1:49]
question marks, and that's okay. People
can reach out and ask us questions,
[1:51]
we're trying to keep it updated, but uh,
the project has gone pretty well and
[1:55]
pretty quick.
Uh, but they're they're going to come
[1:58]
back and pave the wear course all in one
shot. They'll do it under under traffic
[2:03]
more than likely, and they'll pave the
trail at the same time. So, that could
[2:07]
happen next week. In all likelihood,
it'll happen the following week in
[2:10]
September.