Agenda
Transcript
SOURCE TRANSCRIPT
This transcript is downloaded from the source you provided but we haven't reviewed it for accuracy. Treat it as a starting point, not a verbatim record. You can also request an AI-transcription of the audio file with the button to the left.
[0:00]
That's it.
[0:01]
Great.
[0:03]
All right. Okay, well, maybe I I guess
[0:04]
I'll I'll call to order and start the
[0:07]
meeting. Um
[0:08]
first order is roll call and I'll start
[0:12]
and then we can go around. John Tantum,
[0:14]
I volunteered to be chair of this
[0:15]
committee, a Cove Road resident.
[0:18]
Go ahead, Mr. Isaacson. Sitting in for
[0:20]
Larry Store.
[0:22]
Keith Fagan, a
[0:24]
town resident. Uh Peter Mark, city
[0:26]
council member. I'm going to excuse
[0:28]
myself and get a pen. This one doesn't
[0:29]
work good.
[0:30]
Okay.
[0:34]
Julian Poolweiler with Stetson
[0:35]
Engineers, uh design team for the Beach
[0:37]
Road stabilization project.
[0:39]
Adrian Formaini, both with the city
[0:41]
project management team.
[0:43]
Great.
[0:44]
Tony Boyd, public works director.
[0:46]
Um
[0:48]
and uh the others I I can chime in that
[0:50]
Robert's uh
[0:52]
excused himself from from being here. He
[0:54]
wasn't able to make it, but he is
[0:55]
joining us on Zoom. So, yeah, that's
[0:58]
city manager Robert Zadnik.
[1:00]
Robert, Robert, can you hear us? Are you
[1:03]
on audio?
[1:05]
Uh yeah, hi everyone. Can you hear me?
[1:07]
Yes.
[1:08]
Yeah, can you can you hear us okay,
[1:10]
Robert?
[1:11]
Yes. Yeah, you're coming through loud
[1:13]
and clear. Thanks.
[1:14]
Great.
[1:17]
And I'm Chris Berry, assistant engineer
[1:18]
with the city of Belvedere in the public
[1:20]
works department.
[1:22]
Peter, were you out when
[1:24]
when the
[1:25]
when the call came around to your your
[1:27]
seat?
[1:27]
» You know I said it, Peter. Okay, thanks.
[1:30]
Yeah, um
[1:32]
All right. Okay, well, the next item is
[1:34]
the approval of the minutes from our
[1:36]
prior meeting on February 26th,
[1:39]
uh which are in the packet here and were
[1:42]
distributed earlier. Are there any
[1:43]
comments?
[1:46]
on those?
[1:47]
Happy to make a motion to approve it.
[1:50]
I'll second that.
[1:51]
In favor? I.
[1:54]
Uh the minutes were approved from the
[1:56]
February 26th meeting.
[1:59]
Um
[2:02]
next is the the the matter at hand to
[2:04]
talk about the Beach Road stabilization
[2:06]
project and the bids and reviewing the
[2:09]
bids and
[2:10]
uh
[2:11]
discussing those and hopefully come out
[2:13]
come up with a recommendation for the
[2:15]
city council.
[2:16]
Great. So, maybe Tony, I'll let you take
[2:18]
it take over. Yep, thank you. Yeah, and
[2:21]
um thank you everybody for for being
[2:23]
here once again um
[2:24]
in your time.
[2:26]
And um
[2:28]
this uh this meeting is a follow-up from
[2:32]
our last meeting which really introduced
[2:33]
you all to the to the plans for the
[2:35]
project and uh the context for it. Um
[2:39]
this meeting is to uh present the
[2:42]
selection process
[2:44]
um
[2:44]
uh to you all and uh basically um
[2:49]
uh request a recommendation uh that the
[2:53]
city council approve uh the the contract
[2:56]
uh for the for the project and award the
[2:57]
contract uh to a contractor. Um
[3:01]
and so, what I'll be doing is I'll walk
[3:03]
you through the selection process um
[3:06]
and we are uh I think it's fairly
[3:09]
informal. We can, you know, discuss and
[3:11]
ask questions as we go. And um yeah,
[3:14]
happy to fill you in on on any of the of
[3:17]
the details.
[3:20]
All right. So, um
[3:23]
so, to start with I'd like to clarify in
[3:25]
my memo um
[3:28]
» [clears throat]
[3:28]
» Uh that because I didn't point this out
[3:31]
in the memo. Um this contract is for the
[3:34]
sheet pile installation portion of the
[3:36]
project, which is the main uh the sort
[3:38]
of the meat of the project. Uh there is
[3:40]
another um
[3:42]
segment which it which has to do with
[3:44]
the the private properties on Beach
[3:45]
Road, number 16 uh to number 28 Beach
[3:48]
Road, um where there are gangways and
[3:52]
utilities on on the properties there
[3:54]
that will need to be removed for the
[3:55]
installation of the pre of the of the
[3:57]
sheet piles.
[3:59]
And that's a project in itself. Um and
[4:01]
so, that will be a a separate contract.
[4:03]
Um
[4:05]
And there there's a little bit of
[4:07]
possible confusion with with uh with the
[4:09]
numbers that that amount was included in
[4:11]
the engineer's estimates um
[4:13]
uh
[4:14]
you know, and and that's not really I I
[4:15]
didn't really um clarify that or point
[4:18]
that out in the memo.
[4:19]
Um
[4:21]
and yeah, we we can we can look at it
[4:24]
more closely uh but uh exhibit C, the
[4:26]
engineer's estimate will will show
[4:29]
uh
[4:30]
that uh where that that line was
[4:32]
included in the total cost of of the
[4:34]
estimate versus the cost of this
[4:37]
proposal.
[4:38]
Um
[4:40]
and
[4:42]
yeah, if need be um I could also
[4:46]
it'll take me a few minutes, but at some
[4:47]
point I did
[4:49]
uh pull up uh some of these documents
[4:51]
onto the screen if it's helpful.
[4:53]
And Robert might find that
[4:55]
that useful.
[4:56]
Um okay. Um so, the RFP was posted on
[5:00]
February 20th.
[5:02]
There was a lot of interest um it seemed
[5:04]
to us with uh 58 downloads of uh of the
[5:08]
RFP materials. Um
[5:11]
uh it gives some indication, I guess, of
[5:13]
of uh all the contractors out there and
[5:15]
and who are kind of perusing the sites
[5:16]
and
[5:17]
uh
[5:18]
interested to see what what projects are
[5:20]
going on.
[5:21]
Um
[5:22]
that was followed by a mandatory site
[5:24]
meeting uh with with prospective
[5:26]
contractors.
[5:27]
Um so, any contractor who wanted to
[5:30]
submit a bid would have to be at the at
[5:32]
the site meeting.
[5:33]
Uh there were 14 companies represented
[5:35]
there.
[5:36]
Um and the deadline for questions
[5:40]
following that was March 9th. Um we
[5:42]
received four questions in writing
[5:45]
and responded to in in in an addendum.
[5:49]
Um there were two adden- addenda issued.
[5:52]
Uh the first addendum was um
[5:55]
a change to the insurance requirements
[5:56]
in the contract.
[5:58]
Um so, that uh yeah, basically uh
[6:01]
provided uh the details of that.
[6:03]
Um and then addendum two um
[6:06]
uh provided details on the on the uh
[6:08]
pre-bid meeting, um
[6:10]
the questions received, um the responses
[6:13]
to those questions, and also a
[6:14]
clarification of of some of the uh
[6:16]
contractor's responsibilities uh during
[6:19]
during the project um
[6:21]
related to workflow, their workflow, and
[6:23]
coordination.
[6:26]
The deadline was March the 19th um
[6:29]
and that was uh attended by four
[6:32]
different contractors' representatives
[6:34]
uh as well as a union representative
[6:36]
representative. Um A union from
[6:39]
local three. Operators. It's not
[6:42]
uncommon that they show up knowing about
[6:44]
this type of projects. Yeah, thank you.
[6:48]
Thanks, I wouldn't have known that.
[6:50]
Um
[6:51]
and then
[6:53]
uh yeah, so and it was fairly
[6:55]
straightforward. Each uh each envelope
[6:58]
each sealed envelope was opened and the
[7:01]
bids uh bid amount was was read out
[7:03]
loud. Um
[7:05]
uh people people, you know, took notes
[7:07]
and uh and then asked some questions. Um
[7:11]
most of the questions, I think all the
[7:12]
questions were
[7:13]
» So, they they they opened up their bids
[7:15]
amongst all the other competitors?
[7:17]
Yeah, so basically we received the bids
[7:20]
um at a table we had a little table
[7:21]
stationed next to the door there. As
[7:22]
they came in, uh they they uh handed in
[7:25]
their bid
[7:26]
um and then um at the designated time
[7:29]
which was 11:30 on that day,
[7:31]
um we declared that uh bids were now uh
[7:35]
closed and then uh and then we stood up
[7:37]
at a at a table and opened each bid
[7:39]
individually, pulled out the the
[7:41]
documents, and read out the number to
[7:43]
the to the uh the contractors. Is that
[7:46]
is that a requirement? So, is that a
[7:48]
requirement? It is the It's a law. I'm
[7:50]
sorry, I didn't mean to speak over you.
[7:51]
Yeah, that's right. Yeah, that was that
[7:52]
is the procedure for
[7:53]
uh public opening. And it sort of takes
[7:55]
away your ability to negotiate with
[7:56]
anybody.
[7:58]
It does and the law it's it's it's uh
[8:03]
it's a legal requirement for for public
[8:05]
agencies. Um
[8:07]
and and
[8:08]
the the possibility to negotiate um
[8:12]
is actually extremely limited. I mean,
[8:13]
the the the amount on the bid uh if the
[8:17]
city is to accept a bid,
[8:19]
um
[8:20]
it has to justify not accepting the
[8:22]
lowest bid, basically. Um if it's not
[8:25]
going to accept the the lowest bid, um
[8:27]
there there needs to be a reason in, you
[8:30]
know, um
[8:31]
uh that the city would would do that. I
[8:34]
mean, it's very seldom that that a city
[8:36]
would want to not [clears throat] accept
[8:37]
the lowest bid. But but is there is
[8:39]
there I'm sorry to meet you.
[8:41]
» No, no.
[8:41]
Just just
[8:43]
couple questions. So, you went from 58
[8:46]
downloads, I guess, I know it's a it's a
[8:48]
gross number um
[8:50]
to 14 visits and four
[8:52]
made meeting the deadline. Did anybody
[8:54]
come in after the deadline? Um which I
[8:56]
know you you need to exclude, but I'm
[8:58]
saying anybody come in just for
[9:00]
information.
[9:01]
» No, no, nobody came in after the
[9:02]
deadline.
[9:03]
» Normal or why would you think you'd go
[9:04]
from 58 to 14? I I understand a 58 to
[9:06]
14, but 14 to four seems a larger jump
[9:09]
than I would expect. I'll go over the
[9:10]
bats and then I'll and then I'll let
[9:12]
I'll let you Adrian chime in. He's
[9:14]
definitely um
[9:16]
kind of written a few more of these
[9:17]
rodeos than I have. Um but
[9:19]
um I think uh one of the main reasons
[9:22]
was there was this a specific piece of
[9:24]
equipment that was um specified in the
[9:27]
RFP and and uh and that was this uh
[9:30]
silent piler, this guy can machine. And
[9:34]
there are very few uh if
[9:36]
if any, I think, in Northern California
[9:38]
um
[9:39]
uh companies that that provide that. Um
[9:42]
so,
[9:43]
you know, that was another thing is that
[9:45]
all of them had the same subcontractor
[9:47]
uh to drive these piles in.
[9:49]
Um
[9:50]
and I think yeah, some of the comments
[9:52]
at the pre-bid meeting um
[9:54]
related to that. They they sort of said,
[9:56]
well, I mean, if we're all going to have
[9:57]
the same prime I mean, if we're all
[9:59]
going to have the same sub,
[10:00]
um
[10:01]
what difference does it make to you
[10:02]
guys? And so, I think a lot of people
[10:04]
felt that they wouldn't have a
[10:06]
competitive chance. So, you know, so
[10:08]
didn't didn't want to waste their time.
[10:10]
Um but yeah, Adrian Yeah. So, uh you
[10:14]
know, it was certainly a great turnout
[10:17]
at the pre-bid versus who pulled plans.
[10:19]
And who pulled plans could be a host of
[10:21]
individuals that may actually not even
[10:23]
have any
[10:25]
ultimate goal of bidding on the project.
[10:27]
However, they are very interested
[10:28]
whether it be a vendor. Uh there are
[10:31]
several
[10:32]
uh communication
[10:35]
uh companies that will track projects
[10:37]
and then, you know, post items. Um so,
[10:40]
you usually have a very broad spectrum
[10:42]
of individuals that will pull plans and
[10:45]
and anyone's allowed to do it. So, then
[10:46]
you get down to the pre-bid meeting,
[10:48]
which is certainly a more uh fine-tuned
[10:51]
group of individuals
[10:53]
that still may consist of additional
[10:57]
individuals outside of who will be
[10:59]
bidding on the project. Myself signed in
[11:02]
on the pre-bid sheet because I was an
[11:04]
attendee.
[11:05]
Um my project manager Kyle, you know,
[11:07]
Tony. So, there were
[11:09]
others at the pre-bid that necessarily
[11:11]
weren't going to be bidding on the
[11:12]
project including subcontractors
[11:15]
to potential primes.
[11:17]
So, one of the critical uh
[11:20]
subcontractors and at that point we
[11:22]
weren't sure if there was a
[11:25]
uh a prime or a subcontracting component
[11:28]
to the uh company that does retain
[11:30]
several of these Dyken silent pilers.
[11:33]
And they were, you know, there with
[11:34]
three individuals, you know, that are
[11:36]
all from Blue Iron. So, that's how your
[11:37]
list kind of kind of kind of
[11:42]
that we ended up with? Is that a
[11:43]
successful process or would we wish we'd
[11:45]
had more or what what how do we how do
[11:47]
you evaluate that? Exactly. Yes. So,
[11:49]
good question. So, because of the uh
[11:52]
selective equipment for installation,
[11:55]
these contractors all knew that Blue
[11:58]
Iron was going to be
[12:00]
involved with this contract. You can
[12:02]
only make the case Blue Iron's you know,
[12:04]
selected who they who they want to work
[12:06]
with. Correct. So, we do know based on
[12:08]
the bid results that Blue Iron so
[12:10]
provided numbers to several contractors
[12:12]
and that's great. And all of them were
[12:14]
very close on that one particular bid
[12:16]
item when we analyzed the results.
[12:18]
» But they're not though. But they're not
[12:20]
though. I mean, unless it's embedded in
[12:21]
these lines. I mean, there's there's
[12:22]
there's quite a big of variance in the,
[12:24]
you know, uh line five, six, seven, and
[12:26]
eight.
[12:27]
You would think you would think if it's
[12:28]
the same contractor between the same The
[12:30]
contractor is this the opinion of cost
[12:32]
for the
[12:33]
project? I'm just looking at the
[12:34]
line-by-line breakdown. Must be in the
[12:36]
bid
[12:36]
Okay. Yeah, so that's a computer too.
[12:38]
I'm sure it's in a more detailed
[12:39]
tabulation. But but you know, where you
[12:42]
would where you would expect to see
[12:44]
So, I'm I'm my bad. I'm sorry. I didn't
[12:45]
have a thought that was on the one Where
[12:47]
you would expect to see some consistency
[12:49]
among them all
[12:51]
would be alignment A, alignment A,
[12:52]
alignment B, alignment C, you know,
[12:54]
where this where where the the
[12:55]
structural steel um sheet piles are
[12:57]
being driven. You know, basically line
[12:59]
five, six, and seven.
[13:00]
Um
[13:01]
and part of I guess
[13:05]
Yeah. I don't know what I'm seeing right
[13:06]
now, but
[13:07]
To jump in, I'm I I I 100% see what
[13:10]
you're saying and it is a bit of a head
[13:11]
head scratcher about why Valentine
[13:14]
uh uh
[13:15]
have 2.3 million whereas the other
[13:18]
contractors I think are more
[13:20]
closely um converged at, you know,
[13:24]
between 1.6
[13:27]
and and 1.8 million. Quick question. Are
[13:30]
uh are
[13:31]
are we we're in at this point we're not
[13:32]
even discussing Valentine's numbers or
[13:34]
do you want to discuss their I mean,
[13:37]
they're they're they're way high. No,
[13:39]
no, no, I know. I know. I know. I'm I'm
[13:40]
I mean, well, just just with four on the
[13:42]
page and I you may want to just mention
[13:44]
why you knocked out Corcus.
[13:46]
Yes. Yeah. Yeah, definitely. I was
[13:48]
coming to that. Yeah.
[13:50]
Yeah, so
[13:50]
they knocked out Corcus. They didn't
[13:52]
they didn't really follow the process.
[13:53]
Yeah, we can we can look at the
[13:54]
administrative oversight by Corcus and
[13:56]
they just forgot to sign something or
[13:57]
was it like a substantial
[13:59]
they didn't
[14:00]
complete something important? Uh it was
[14:02]
an it was I think
[14:04]
I if it was me, if it was my company,
[14:07]
I'd be very frustrated uh because um
[14:10]
it is it's it's a very minor
[14:13]
detail when you're filling out a form,
[14:15]
but
[14:16]
in in an RFP um it's it's significant
[14:20]
um and
[14:22]
uh it basically
[14:25]
um
[14:26]
The frustration for us too is that um we
[14:29]
we were aware that Corcus had downloaded
[14:31]
those those addenda
[14:33]
um and
[14:35]
so when they when they filled in their
[14:37]
form um saying that they had not they
[14:39]
they did not acknowledge uh the the
[14:41]
addenda basically. I mean, but but but
[14:43]
in the city's defense and our in our
[14:45]
broader legal defense of this is also
[14:47]
that when and if
[14:49]
they're they're not acknowledging those
[14:50]
two addenda which we we we can't verify
[14:52]
that it's in their their their budget
[14:53]
data and and they'll perform the work
[14:54]
according to the specs that you laid
[14:56]
out. Exactly. What's your real change?
[14:58]
Which is why you have to sort of
[14:59]
eliminate that.
[15:00]
There's no way to have them acknowledge
[15:03]
the addenda after the fact. It was too
[15:06]
late at that point after the envelopes
[15:08]
have been opened. Is that right? It you
[15:10]
know, it's
[15:13]
It would have been basically, yeah. I
[15:14]
think that would have resulted in
[15:16]
protest from from the other bidders um
[15:19]
basically that they didn't follow
[15:20]
procedures and then were being given an
[15:22]
allowance for
[15:24]
you know, to to correct items in their
[15:26]
in their bid.
[15:27]
Um
[15:28]
Yeah. And you know, I mean, I think
[15:31]
ultimately um
[15:33]
you know, the city attorney weighed in
[15:34]
on it and and uh
[15:36]
yeah, it it was quite clear that uh this
[15:38]
was the only option.
[15:40]
Yeah. Um
[15:43]
Luckily for us the the next the next
[15:45]
bidder was was a very close in price and
[15:47]
they, you know, for the total.
[15:49]
I mean, but on those my question was a
[15:52]
lot of those install sheet pile. Yeah,
[15:54]
you go from
[15:56]
even if you take out Valentine, you
[15:57]
know, there's a six there's a $300,000
[15:59]
swing on line five.
[16:03]
Between between between Thompson and and
[16:07]
Gordon Gordon Mhm. And and Thompson
[16:09]
being the third. That's why they were in
[16:10]
third place. No, no, no, but I'm saying
[16:12]
but if if if the same subcontractor is
[16:14]
providing the service, maybe there's
[16:15]
more detail that that there that I'm not
[16:16]
seeing. Because they are carrying costs
[16:18]
of unforeseen to for covering a sub. So,
[16:22]
guaranteed Thompson is a more local
[16:24]
contractor from Nevada and they may or
[16:27]
may not have worked with um um Blue Iron
[16:30]
as much, but I do know that both Corcus
[16:32]
and Gordon Ball both
[16:35]
work with them quite often and that is
[16:37]
probably that is a reflection in Gordon
[16:39]
Ball's number is that they have a very
[16:42]
good understanding and operation for
[16:44]
their subcontractor which is carrying,
[16:47]
you know, 75% of this this project
[16:50]
weight here.
[16:51]
Um that is the way I see it.
[16:54]
What a really good question. Um what is
[16:57]
the ultimate nature of our agreement
[16:59]
with this contractor? Is it a guaranteed
[17:00]
max? What factors you you mentioned that
[17:03]
in your review of um
[17:07]
uh
[17:08]
references that one of the one of the
[17:10]
things you got back about Gordon Ball in
[17:11]
particular was that they were able to
[17:13]
finish the project on time and on
[17:14]
budget.
[17:17]
What
[17:18]
what are the opportunities or what are
[17:19]
the negative opportunities to be off
[17:21]
budget for us? I mean,
[17:23]
if is this a guaranteed max? Is this a
[17:24]
fixed price? What happens
[17:27]
um certainly I understand client driven
[17:28]
change orders or or or material driven
[17:30]
change orders, but is that what can can
[17:32]
can can drive this into an overage
[17:33]
situation? Yes. And and it's really and
[17:36]
and Adrian definitely please do chime in
[17:38]
here, but
[17:39]
um
[17:40]
my understanding is that
[17:42]
uh they based their
[17:44]
their their estimates of of costs or
[17:46]
their their price
[17:50]
on the If if other
[17:52]
you know, if they get out to the sites
[17:54]
and and um you know, they start digging
[17:57]
and there's something something else
[17:59]
down there than other than loose sand
[18:00]
and rock, for example, um that causes
[18:03]
delays and
[18:05]
you know, changes um then then costs can
[18:08]
change. Yeah.
[18:12]
Yeah. Most of them Yeah, and then some
[18:13]
of the units are are are stated you have
[18:16]
you do a square foot for the sheet pile,
[18:18]
but primarily they are either single
[18:21]
units or total and or, you know, lump
[18:23]
sum. So, each the only the square
[18:26]
footage is on the the sheet pile, which
[18:28]
is total.
[18:29]
And then it's a furnish and install, so
[18:31]
it's a completed system. I mean, Jason
[18:34]
repair that was completed a few years
[18:35]
ago. Were there many change orders
[18:36]
associated with that project? Not one.
[18:40]
And did it come in on budget? Uh well,
[18:43]
that one was a little There was there it
[18:45]
was not the same development of that
[18:48]
project based on the situation because
[18:50]
it was more of a observation that was
[18:53]
made with both and Miller Pacific during
[18:55]
and Stetson during the H and H study in
[18:58]
2019 for the shoreline resiliency for
[19:01]
both shoreline and
[19:03]
Santa Paula and Beach.
[19:04]
Uh so, that was when it was prompted and
[19:07]
the wall was showing uh significant
[19:09]
signs of failure. So, that was what
[19:11]
prompted that project. So, it certainly
[19:13]
was in line with pricing
[19:16]
um and there was no additional inflated
[19:19]
costs due to a
[19:20]
you know, expedited, you know, time
[19:22]
frame. Blue Iron came in well under
[19:24]
because they had a unique perspective on
[19:26]
the installation of sheet with uh
[19:29]
um just cutting edge tech
[19:32]
you know, so
[19:34]
they were we were able to complete the
[19:36]
project faster than other companies.
[19:38]
So And can you confirm my understanding
[19:41]
as well that it's it it would go both
[19:43]
ways as well. So, if less materials are
[19:45]
used, for example, um
[19:48]
than than anticipated calculated the
[19:50]
square footage, um then
[19:53]
then uh that's what's that is what it's
[19:56]
built to the city as well as well
[19:57]
invoiced. Yeah, I mean they're they're
[20:00]
you know, this is what they were
[20:01]
expecting and they're going to they're
[20:03]
going to procure sheets like this is the
[20:05]
first thing that has to happen. So
[20:07]
» Right. So as far as the sheets go those
[20:09]
that would be a single kind of bulk
[20:11]
order I guess.
[20:12]
» Oh yeah, and they're going to jump on
[20:13]
that as soon as possible just because of
[20:15]
the lead time and getting into a roll
[20:17]
because these sheets very well may not
[20:19]
be on the brand yet. Okay. So it's yes
[20:22]
specific to sheets yeah. Okay.
[20:25]
I just know that I mean you know with
[20:27]
paving for example if um
[20:29]
you know for whatever reason it turns
[20:31]
out that it's a few tons less than than
[20:33]
expected. Absolutely
[20:37]
and that's what's important just for
[20:38]
keeping on track with you know that all
[20:40]
those all those things. But yeah we'll
[20:42]
certainly do that. And the good thing
[20:43]
that we have going for us is
[20:45]
the knowledge base of both Gordon and
[20:47]
Blue Iron is that they're
[20:48]
straightforward contracting that very
[20:51]
they work well together. So the mere
[20:53]
fact that they are a well-oiled machine
[20:56]
is going to have you know it's going to
[20:58]
just you know
[21:00]
assist tremendously versus you know
[21:03]
other subs that may or may not have that
[21:05]
well of a communication yeah you know
[21:08]
so. And then also yeah just to just to
[21:11]
add
[21:13]
if there is if there are complications
[21:15]
you know it's it's uh
[21:18]
the city you know through its through
[21:20]
its engineer engineering team would have
[21:23]
to
[21:24]
um
[21:24]
um
[21:25]
uh
[21:26]
basically approve any any changes like
[21:28]
that any changes to the to the scope.
[21:32]
So cost would be a part of that
[21:34]
decision. So if you know if there's a if
[21:36]
there's a huge change
[21:38]
it because of you know some
[21:41]
some unforeseen circumstance that that
[21:44]
results in a big change in cost
[21:45]
somewhere
[21:47]
that would be a decision that the city
[21:48]
would weigh
[21:49]
for in terms of the project as a whole.
[21:52]
What we do know is that we had very
[21:54]
little issues whatsoever with a
[21:56]
significant section of Beach Road
[21:58]
several years ago. We saw very
[22:01]
very bland questions from contractors.
[22:04]
The bids came in without carrying costs
[22:07]
of which we had no idea how this is
[22:09]
going to go down.
[22:11]
So that was those were all really good
[22:12]
signs of a well-designed bid package
[22:15]
from both the technical side as well as
[22:17]
the opinion of cost. It was it was very
[22:20]
it was right in line with what we you
[22:22]
know we were hoping to see. We're just
[22:24]
very excited we didn't see this as a
[22:26]
huge The lowest the lowest bid it's
[22:28]
Gordon Ball not Norman Ball right. I
[22:31]
think in your memo you Yeah right sorry
[22:33]
I for some reason I kept So I think a
[22:36]
little bit of Herman Ball I don't know
[22:37]
why it is wrong. See you the experience
[22:39]
they have but we have not worked with
[22:41]
Gordon Ball before as a city. They are a
[22:44]
large contractor so there's a very good
[22:46]
chance that they wouldn't have probably
[22:48]
been worked on any They are typically a
[22:50]
huge large scale commercial contractor
[22:54]
doing anything else than that.
[22:56]
But I I do know of that nature cuz they
[22:58]
they do a lot of municipal work.
[23:00]
» Okay. I don't know but I don't know the
[23:01]
company is that are public company or a
[23:03]
privately held company we have I'm not
[23:05]
sure and or if it's a member owned we
[23:07]
have to you know have to look into look
[23:09]
into that. One of them There was there
[23:10]
was a level of analysis required for
[23:14]
for this
[23:16]
review. But this is this is They they
[23:18]
are a large company that does many
[23:19]
projects that's not name I've never
[23:22]
heard of. No yeah.
[23:23]
um Yeah it's I have noted them either.
[23:27]
um
[23:28]
I don't know if they're nationwide I
[23:30]
don't know if they're that
[23:31]
» No they're not. I do know that they do a
[23:32]
lot of work with PG&E. They do a lot of
[23:35]
public utility work so they are they
[23:38]
understand the public process. And I do
[23:41]
know again that they work with Blue Iron
[23:43]
quite a bit with projects. And a lot of
[23:45]
times Gordon Ball is in prime for PG&E
[23:47]
projects where Blue Iron is their sub.
[23:50]
Yeah their their references were um
[23:53]
uh were I thought I thought very good
[23:56]
that the projects that they that they
[23:58]
highlighted
[23:59]
were very similar to this.
[24:01]
They all involved installing sheet pile
[24:05]
in in locations a lot of locations with
[24:07]
with water river banks and and boat
[24:10]
launches and and these kind of
[24:12]
situations and and one of the
[24:14]
one of the project managers that I spoke
[24:16]
to from I think it was the Santa Clara
[24:18]
Santa Clara
[24:19]
water district
[24:21]
said that they
[24:23]
um
[24:24]
that they were also in very close
[24:25]
proximity to homes and that they
[24:28]
uh you know they performed everything
[24:30]
that they needed to with you know
[24:31]
vibration monitoring and and that kind
[24:33]
of equipment so they they're definitely
[24:35]
familiar with with this this type of
[24:38]
work. They were they were nearby
[24:40]
projects here in the area in Northern
[24:42]
California.
[24:42]
» Yes yes yeah.
[24:49]
Yeah.
[24:51]
Right well so okay
[24:56]
where did I where was I? um
[24:59]
» [clears throat]
[25:00]
» Addenda yeah okay. So
[25:05]
The addenda were were required to be
[25:07]
acknowledged and and one contractor
[25:09]
didn't as we know
[25:11]
um
[25:13]
Is there
[25:14]
and I understand that the strict nature
[25:16]
of the
[25:17]
bid process
[25:18]
uh
[25:22]
We're not obligated to take anything
[25:23]
just just thing you guys have to get
[25:25]
right? Correct.
[25:26]
» Right we can say cuz you're
[25:28]
you're above what our expected cost will
[25:29]
be we're not obligated to take anything
[25:31]
on
[25:31]
» Yes. Yeah. Um it's still subject to city
[25:34]
approval
[25:35]
but you I mean there's there's there's a
[25:37]
number of line items you know
[25:40]
you know 10 12 and 15 for example where
[25:43]
they are higher than everybody else.
[25:46]
Uh and I know that just the it's the
[25:48]
discrepancies that you guys have the
[25:50]
uniqueness of that individual
[25:51]
contracting approach and their their
[25:53]
sensitivity to that particular line item
[25:55]
I can imagine. But you can't go back to
[25:57]
them and say you know we'd like to we'd
[25:58]
like these three items to be
[26:00]
reconsidered or looked at is does does
[26:02]
this municipal process allow for that or
[26:03]
not?
[26:05]
No um
[26:06]
yeah unfortunately not because of the
[26:09]
because of the RFP process um
[26:12]
you know everybody
[26:14]
uh everybody provide you know has the
[26:16]
same uses the same parameters for their
[26:19]
for their costing and and the the final
[26:22]
price
[26:23]
um
[26:24]
can't be changed before the before the
[26:26]
contract is awarded. After the contract
[26:28]
is awarded
[26:30]
then there can be some negotiation with
[26:33]
with the contractor. The contractor is
[26:35]
awarded at that price but change orders
[26:37]
can
[26:39]
be
[26:41]
generated by the city that change the
[26:43]
scope of work. So that's often in
[26:46]
negotiation.
[26:47]
» Be I mean I'm just saying cuz we have to
[26:49]
separate decision by the city as to
[26:51]
appropriate more money for this
[26:53]
right. So that's not insignificant. um
[26:56]
uh ask so it would be against this
[26:59]
process and perhaps municipal law I
[27:02]
don't know
[27:03]
that you can't go to them and say you
[27:06]
were the low bidder
[27:07]
after we excluded one you know full
[27:10]
transparency you're the low bidder
[27:12]
but you're still above our budget we
[27:13]
can't award the contract unless you were
[27:15]
to reconsider these three line items
[27:16]
which you're you're you're 10% above the
[27:18]
competitors. Would you consider to do
[27:20]
so? That's not you can't do that?
[27:23]
We do you Yes so
[27:26]
and and just so you know that we have
[27:28]
discussed
[27:29]
that
[27:30]
angle because in a public contract
[27:32]
that's kind of where you go next. You
[27:34]
look to VE or value engineer some of
[27:37]
your items
[27:38]
and where you do not take away or
[27:42]
we don't want to adjust and or go back
[27:45]
to the design team to say we need to
[27:49]
change the how we go about getting you
[27:52]
know this design completed. It is maybe
[27:55]
a reduction of overall footage and we
[27:57]
can't you know there's a very good
[28:00]
chance that the contractor is going to
[28:01]
be willing to negotiate cuz they want
[28:03]
this project that's for certain. But if
[28:04]
you
[28:05]
by your process you award the contract
[28:07]
at this price what reason do they have
[28:09]
to negotiate It's not as easy as looking
[28:12]
why are you well you're $80,000 more
[28:14]
than the competitor so why can't you do
[28:16]
it for their cost? Because there are so
[28:17]
many different moving mechanics we don't
[28:20]
know what the other contractor may or
[28:22]
may not have had or if they underbid
[28:23]
that.
[28:24]
But
[28:25]
at this point with them we don't care.
[28:27]
Realistically we don't care. I mean if
[28:28]
if if if we're if we're now one to one
[28:30]
with these folks
[28:31]
and we want to award it then we don't do
[28:33]
it. I I get where you're going with
[28:34]
this. I
[28:35]
I'm just I'm just saying that.
[28:37]
We haven't added obstacle here that
[28:39]
we've got to get this money from this
[28:40]
from the city and ultimately from our
[28:41]
residents. And
[28:44]
that's not a
[28:46]
you know
[28:47]
something the city council is going to
[28:48]
love to be vote on and be comfortable
[28:50]
with and the the way you propose to do
[28:52]
it is to put up other projects.
[28:54]
You know other lanes other maintenance
[28:56]
projects other other capital
[28:57]
improvements
[28:58]
or finding it in the this this this
[29:00]
broader budget whether it's contingency
[29:01]
or things like this which probably
[29:03]
possible but
[29:05]
depending on what you find out there.
[29:07]
Yeah
[29:08]
yeah no for sure. 300,000 for
[29:10]
Belvedere's is is a big
[29:11]
» Well let's let's let's shelve that
[29:13]
aspect over for now cuz if and when we
[29:14]
go there there's other things to talk
[29:15]
about certainly. Um
[29:17]
I would just say that it's a it's a
[29:19]
competitive public bidding process and
[29:22]
so you've provided all the parameters in
[29:24]
the contract documents and these
[29:25]
contractors have put their best foot
[29:27]
forward so to speak. This is this is
[29:29]
what they're proposing to do and I would
[29:32]
say you're not really one to one with
[29:33]
anybody until the contract is awarded.
[29:36]
But they also know your estimate going
[29:38]
in.
[29:39]
I mean it's it's it's not it's not a
[29:41]
it's a coming from the private you know
[29:43]
construction world that's just lunacy
[29:45]
lunacy to me.
[29:46]
But
[29:47]
Well I get it. If you if you if you're
[29:49]
attempting to negotiate with one
[29:51]
contractor before awarding a contract,
[29:53]
all the other ones say, "Well, how come
[29:54]
you didn't come to us? We We could We
[29:56]
could do it, too." And it just, you
[29:58]
know, it could sort of unravel the whole
[29:59]
process. I get it. I get it.
[30:02]
Yeah, and I I mean, to your point, you
[30:04]
lose all your leverage if if you've
[30:06]
already signed a contract with them. Um
[30:08]
but I think I mean, in my in my
[30:10]
experience, and and maybe you you guys
[30:12]
can chime in on this, um
[30:15]
you know, contractors are generally uh
[30:18]
willing to talk. You know, they they're
[30:21]
um
[30:22]
that
[30:23]
if you say, you know, "By the way, you
[30:25]
know, we We've got everything signed,
[30:26]
but
[30:27]
um
[30:28]
this is this uh you know, finances are
[30:30]
very tight for us, and we would like to
[30:32]
find ways to to reduce the costs. Um we
[30:35]
we may want to reduce the scope
[30:37]
somewhere. Um
[30:38]
but we did notice in your in your uh bid
[30:41]
that you know, these were much higher
[30:43]
than than other people's, and Okay. are
[30:45]
you able to, you know, you know, share
[30:47]
with us what the you Cuz we can always
[30:49]
say to them, "So, we're not going to
[30:50]
either uh
[30:52]
Ball, you reduce by this amount. And and
[30:55]
we'll award it to you, otherwise we will
[30:56]
award it to nobody, and we will we will
[30:58]
we won't go forward, and we'll do
[31:00]
another RFP, and we'll just
[31:02]
we'll rebid the whole thing, and let let
[31:03]
them it's a little bit of a
[31:06]
Put that on the table then. If they say
[31:08]
they won't, then we just put the RFP out
[31:09]
again, and start the process again. I
[31:11]
don't think you can Well, well, I don't
[31:13]
think you can do that. Well, why not?
[31:14]
Why Why What What Well, look, it's
[31:16]
public I mean, I'm not a I'm not a I'm
[31:17]
not a contractor. It changes the scope.
[31:19]
It changes the scope. I mean, obviously,
[31:20]
or the timing. No, no, because because
[31:22]
basically, if if if if if we choose not
[31:24]
to do this now, realistically at this
[31:26]
point in time, even with the same scope
[31:27]
in a rebid process, or modify this
[31:29]
slightly, we missed the '26 window.
[31:31]
Right. If you miss the '26 window, it's
[31:33]
not going to get any less expensive
[31:35]
knowing, you know, that
[31:36]
» That, for sure. And the re so the the
[31:38]
re-solicitation process, what we've done
[31:40]
is certainly has a a cost that isn't
[31:43]
going to necessarily, you know, be able
[31:45]
to be recouped as well in a lot of the
[31:47]
public, you know, process has, you know,
[31:49]
there's has to be, you know, completed
[31:51]
again. But but if we don't have the
[31:52]
money Yeah, no, I I they might say,
[31:54]
"Okay, well, we'll we'll help you with
[31:56]
that." So, I mean
[31:58]
they might say, "Okay."
[32:00]
And that's why I know that, you know,
[32:01]
again, internally within you know, with
[32:03]
James, I'll try to remember who else was
[32:05]
on that call, but Stetson, we talked
[32:07]
about at least areas identified that we
[32:10]
can discuss, um and it was confident We
[32:12]
don't have specifics, you know, but
[32:14]
there were certainly some areas uh to
[32:16]
look at that we started to discuss. You
[32:18]
know,
[32:19]
one of them would be, you know, just uh
[32:21]
essentially
[32:23]
I I think again, though in accordance
[32:25]
with the public contracting, you you
[32:27]
can't begin these negotiations until
[32:29]
after a contract is awarded to to one of
[32:31]
these. And so, I think that's probably
[32:34]
what the city is looking at. You You
[32:35]
either have to make the decision to
[32:36]
award a contract Could we go to all of
[32:39]
them and say, "This is This is our
[32:40]
budget. Would you like to Uh I think
[32:42]
that that that sort of involves
[32:44]
reopening up the bidding process. I
[32:46]
don't I can't I think once it's closed,
[32:48]
you can't reopen it. You would be
[32:49]
looking at a rebid.
[32:51]
The issue with the timing is that
[32:53]
there's an in-water work window, June
[32:55]
through October.
[32:56]
And so, to start the process over means
[32:59]
we wouldn't have enough time to issue a
[33:01]
rebid, open it all up, and receive bids
[33:04]
in order to construct this year. So,
[33:05]
re-bidding the project does mean you're
[33:08]
you're you're looking at next year,
[33:09]
2027.
[33:14]
Let's be realistic.
[33:15]
Um
[33:17]
how confident are we that
[33:19]
with the ability to start this project?
[33:21]
First question. Second question is
[33:23]
um what I would be afraid would happen
[33:26]
is that there would be a delay, there
[33:27]
would be a uh uh
[33:29]
a backlog of this particular equipment
[33:30]
or something like that, and the
[33:31]
contractor gets started under this
[33:33]
price, and says we have to finish it
[33:34]
next year, and here's the here's the
[33:35]
cost to do so.
[33:38]
Well, I think they would be under
[33:39]
contract to um
[33:41]
uh you know, to to complete it by
[33:43]
October uh 15th, I think is what the
[33:45]
contract says. But just like but just
[33:47]
like finding a a a you know, Right.
[33:49]
immovable boulder under the ground,
[33:51]
there's a there's a there's a delay with
[33:52]
Blue Hill Stetson. I apologize. Blue
[33:55]
Iron. Blue Iron. That That can't deliver
[33:56]
it. It's out of their control, and
[33:58]
they're they're they're delayed a month,
[33:59]
and they and they That's I don't for I
[34:01]
mean, anything's possible, but I'm um
[34:03]
they're they're they have agreed to
[34:06]
perform this project by a certain date,
[34:08]
and if not, there are liquidated damages
[34:10]
daily that occur if they are not
[34:13]
complete by that time frame.
[34:16]
Do we Do we think we'll get this done in
[34:17]
this time frame?
[34:19]
I mean, can it be They need to go, yeah.
[34:20]
Permit I mean, we're you know, there's
[34:22]
Um there are there are a few factors um
[34:25]
that that are outstanding. Um
[34:28]
Yeah. What Like what? So, first of all,
[34:31]
uh permitting. Uh we're waiting for a
[34:32]
BCDC permit. Um
[34:35]
and they are in a review sort of stage.
[34:39]
Um they have a commission meeting where
[34:41]
it needs to be approved. Um and which I
[34:45]
believe it is April 29th, I think, 19th
[34:48]
or 29th, so it can only be after that.
[34:51]
Um
[34:52]
uh PG&E need to complete some uh some
[34:56]
work in on Beach Road to modify their uh
[35:00]
their lines, their um
[35:02]
utility lines, main lines through there.
[35:04]
» Before we get going.
[35:05]
Yes. Yeah. Given what we've heard from
[35:07]
PG&E, is that is that likely?
[35:10]
Uh they uh we we ask them We We meet
[35:13]
with them about every 2 weeks uh
[35:15]
to get progress and and update uh
[35:17]
updates from them. Um
[35:19]
they
[35:21]
assure us that um that that it's that
[35:24]
it's
[35:25]
doable to do before before June. Um
[35:28]
but we have no control over that or or
[35:31]
over their their work. So, if these
[35:33]
dependencies um if if Gordon and
[35:36]
Company, Gordon Ball, can't get started
[35:39]
to comfortably make the window
[35:41]
this contract's void then, right? We're
[35:42]
not, you know, cuz obviously, the prices
[35:44]
probably wouldn't be held for the next
[35:45]
year.
[35:47]
Well, I think there's probably room to
[35:49]
negotiate, and and if they would like to
[35:51]
keep the contract for next year um you
[35:54]
know, they may they may be some uh some
[35:57]
way to um
[35:59]
you know, to
[36:00]
to keep them on board um with some kind
[36:03]
of uh
[36:04]
you know, adjustment in price, you know,
[36:06]
related to inflation or something. There
[36:09]
There is some flexibility built into the
[36:11]
way this is structured. There's a
[36:12]
There's a The in-water work window is a
[36:14]
5-month period, June through October,
[36:16]
but the actual construction period is
[36:18]
only 65 days. And so, even if they don't
[36:21]
necessarily have to start on June 1st, I
[36:23]
mean, that can slide backwards, and
[36:25]
there would there would still be room
[36:26]
for them to complete this project. And
[36:28]
in theory, the the out-of-water work can
[36:30]
continue outside that window. That's
[36:31]
correct. It is. Yeah. Yeah.
[36:33]
Um
[36:35]
And so, you know, that's
[36:36]
that's the reason we did try to put this
[36:38]
out to bid early, to get the bids early,
[36:40]
to have a contractor under contract
[36:42]
early so that these these scheduling and
[36:46]
um
[36:47]
the the coordination between the city,
[36:50]
Hadley, PG&E, this can all kind of be
[36:52]
worked out over the next several months
[36:54]
until June, and when when the
[36:55]
construction would actually occur. Mhm.
[36:58]
» [clears throat]
[37:00]
» Yeah. Um
[37:02]
The other The other factor is uh
[37:04]
easements with uh temporary construction
[37:06]
easements with the property owners on on
[37:08]
Beach Road, because uh
[37:10]
the work that would need to take place
[37:12]
on their property um for this project to
[37:15]
to go ahead. I mean, the seawall
[37:16]
actually
[37:17]
enters their property at uh you know,
[37:20]
at at their property lines. Um
[37:22]
so, it's a couple of feet in from the
[37:24]
property line, so the the work and the
[37:25]
structures would would all be on their
[37:27]
on their land.
[37:29]
Um
[37:30]
and we've met we've met with them um
[37:32]
a few times, uh described the project,
[37:35]
and we've sent over the uh the easement
[37:38]
agreements. Um
[37:40]
So, at this point, we're waiting for
[37:41]
them to
[37:42]
um review those. Uh
[37:46]
And we're we're ready to go for the for
[37:48]
the April meeting for them uh to to have
[37:51]
those easements um
[37:53]
approved by City Council. Um
[37:55]
And yeah, but but we do have to wait for
[37:57]
their their signatures, basically, on
[37:58]
their side.
[38:00]
How many property owners are we talking
[38:01]
about again? Uh three property owners.
[38:03]
Um Yeah. Um
[38:05]
And one of them has indicated that um
[38:09]
he's is absolutely willing. Um he's just
[38:12]
out of the country right now. Um so,
[38:14]
he's uh seems seems like he's ready to
[38:18]
sign as soon as he gets back. Uh the
[38:20]
other two
[38:21]
uh are new uh new owners of of the
[38:24]
property. And um
[38:26]
I think it seems like they're wanting to
[38:28]
review the the language more carefully,
[38:30]
and um Was it a
[38:32]
It's three properties, but two owners,
[38:34]
right? Cuz there's Yeah.
[38:36]
Yes.
[38:37]
» Hadley owns one building, and the Spruce
[38:39]
Group owns the other two. Yes, yeah. And
[38:41]
those other two are are owned, I think,
[38:43]
on paper by two different LLCs, but it's
[38:45]
the same people. Okay, so that's okay.
[38:47]
Yeah.
[38:49]
Yeah.
[38:51]
So, from a financial perspective, I'm
[38:53]
looking at
[38:54]
this overall project budget relative to
[38:56]
appropriations funding at the top. Um
[38:59]
we're looking at that 3.475
[39:02]
line
[39:04]
of which includes two $280,000 or so,
[39:08]
that's going to a separate contractor to
[39:11]
do the utility work.
[39:13]
Right? So, that's where we get the 300
[39:15]
So, that the the we have a $315,000
[39:17]
variance on that line if we take this
[39:19]
this this bid from Gordon and Ball,
[39:21]
right?
[39:23]
Uh yeah, it's it's
[39:26]
uh without knowing it, we don't have the
[39:27]
exact number for the contracts uh of the
[39:30]
other amounts. I would assume the 279
[39:33]
that the way you got your 315 was the
[39:34]
279
[39:36]
um plus the 35 over
[39:39]
this number. Correct, yeah. With a with
[39:41]
a little bit of Yeah, yeah. flexibility
[39:43]
to in case that 279 is over.
[39:45]
» So, I'm just writing 315 in parentheses
[39:47]
next to the 3475, which means Right. on
[39:50]
this page we're 315 over budget on that
[39:53]
particular line. And you've
[39:56]
discussed this with Helga and her and
[39:58]
your recommendations with Robert as well
[40:00]
is to handle this either within this
[40:04]
$4.6 million
[40:06]
total project expenditures
[40:08]
budget, finding it somewhere, whether
[40:10]
it's coming out of your hide
[40:13]
I mean from a project manager
[40:14]
perspective or somewhere along this line
[40:15]
of our mass remediation, somewhere
[40:17]
somewhere through here you think you
[40:19]
might be able to find some
[40:21]
money. That that's option one, right?
[40:23]
Just confirming that's what that means.
[40:24]
» Yeah. And option two is in the broader
[40:27]
public works budget.
[40:28]
Um capital improvement projects, whether
[40:30]
it's paving or whether it's a retaining
[40:32]
wall or whether it's a lane improvement
[40:34]
or something like that, finding that
[40:35]
money in that over the next couple
[40:37]
years. Yeah, and and
[40:38]
and there are two components to that,
[40:40]
too. So, there are existing CIP funds
[40:43]
that
[40:45]
that that
[40:46]
overlap with
[40:48]
with with some of the work in this
[40:50]
project. So, paving for example, there's
[40:52]
a we have a we have a CIP fund for
[40:53]
paving.
[40:55]
And that that could cover the cost of
[40:58]
the the paving restoration
[41:00]
in instead of using this
[41:02]
this account for that for for those
[41:04]
costs.
[41:05]
» Use that account.
[41:06]
» Yeah, exactly. I get it. Um
[41:12]
Yeah, exactly. And the sidewalk, yeah,
[41:13]
exactly.
[41:14]
And and we have it in we have not
[41:16]
embedded the contingency on this budget.
[41:20]
Um
[41:22]
Well, with that
[41:24]
so
[41:25]
so with that over
[41:29]
I'm just saying on paper on paper right
[41:31]
now we're talking about that one line
[41:32]
item having a
[41:34]
a negative variance.
[41:35]
But that 383 arguably still exists if we
[41:40]
if we know we have 4.6 in our in our in
[41:43]
our fund at this point.
[41:44]
» Yes, right. Yes. So, so yeah,
[41:46]
sorry I I I
[41:48]
took me a minute there, but yeah,
[41:49]
basically that would restore that that
[41:51]
contingency amount.
[41:52]
» Yeah, yeah, absolutely.
[41:53]
So,
[41:55]
however we decide,
[41:57]
you may want to work with Helga. I would
[41:58]
suggest if this is to be recommended to
[42:00]
the city council, I wouldn't go in with
[42:02]
this to $315,000 over tier.
[42:05]
I would I would I would front it by
[42:07]
saying exactly what you've talked about
[42:09]
before, that we're going to approach
[42:10]
this if we award this contract with
[42:14]
diligent approach to value engineer to
[42:16]
to line item look at things to to
[42:18]
recognize this is over budget and see
[42:20]
where we can get some some some
[42:21]
potential savings out of this contract.
[42:24]
May yield nothing, but but that's an
[42:25]
approach and we certainly should do
[42:26]
that. I would also try to identify
[42:28]
specifically where you think this money
[42:30]
can come from. Meaning if you if you if
[42:33]
you have known expenditures that you
[42:35]
think are going to be less than what you
[42:36]
have up here anyway,
[42:38]
for example, if you know that
[42:40]
you know, the
[42:42]
the
[42:43]
environmental mitigation costs are not
[42:45]
$100,000, but they're going to be
[42:46]
$80,000 much like we had with the repair
[42:48]
over there on Beach Road. You know,
[42:50]
you that came in less than we thought we
[42:52]
were going to commit. So, I'm not saying
[42:53]
we take that money, but I'm saying if
[42:55]
you know already where we are, I
[42:57]
identify it. You could you could
[42:59]
probably say of that we know we've got
[43:03]
$35,000 in
[43:05]
city planning paving sorry, sidewalks
[43:08]
for the next 2026 2027 we have
[43:12]
$45,000 in in road paving for the 2026
[43:16]
and 2027 budget that we can apply to
[43:18]
this.
[43:20]
And our assessment is that that won't
[43:21]
damage our overall
[43:24]
value of our infrastructure around the
[43:26]
city. So, we can apply that those small
[43:27]
amounts of those larger budgets. We can
[43:29]
also apply
[43:31]
$200,000 of contingency to that and
[43:33]
that's where we think we can make up
[43:34]
this money and still and still retain
[43:36]
the 4.630.
[43:37]
Right.
[43:38]
» Yeah, exactly. You need to present it in
[43:40]
a fashion like that. Right. Yeah, and
[43:41]
that's that's that is definitely what's
[43:43]
what we had planned was you know, be
[43:46]
able to be specific about you know,
[43:48]
about how you know, how this is
[43:50]
possible.
[43:52]
And and there would be council approval
[43:55]
for for some of those changes as well.
[43:57]
Well, they'll have
[43:58]
comments and they'll and they'll
[43:59]
probably stress you know, we really want
[44:01]
you to push the value engineering and
[44:03]
and really you know, sharpen your pencil
[44:05]
on the scope, you know, once you have
[44:06]
the contract selected to keep within the
[44:08]
the appropriate public bidding process
[44:10]
so that we can make sure we we make this
[44:12]
project as as tight and and not only
[44:14]
timely, but also it does our our our
[44:17]
base minimum needs for the for the for
[44:18]
the for the money we're spending so we
[44:20]
get as much value as we possibly can.
[44:21]
Right. Yeah. Yeah.
[44:23]
Yeah, I yeah, I I hear you and I think
[44:27]
um
[44:28]
I we all feel that way. We definitely I
[44:30]
know I I you know, and and and I
[44:32]
definitely know Robert does and
[44:33]
everybody does.
[44:36]
Yeah, I mean it's it's um it's
[44:39]
we we all want a want a project that's
[44:41]
delivered on time and under budget.
[44:44]
You know, some of this this
[44:47]
law that we have to
[44:49]
comply with
[44:50]
is is a little cumbersome and
[44:52]
frustrating,
[44:54]
but you know, from from the time that we
[44:56]
start meeting with the with the
[44:59]
contractor,
[45:00]
there will definitely be you know, a lot
[45:02]
of emphasis on on um
[45:05]
keeping costs you know, within budget.
[45:08]
Um and if I mean you know, I I
[45:11]
to be fair, I think I think the
[45:13]
contractors probably get that from from
[45:14]
everybody that they all the cities that
[45:16]
they work with. Um But yeah, and I mean
[45:20]
you know, some of the costs, you know,
[45:21]
and I can I can point to some in on here
[45:23]
that's um
[45:24]
we anticipate
[45:26]
not not having to pay for example,
[45:29]
environmental mitigation costs.
[45:32]
BCDC
[45:33]
uh
[45:34]
may ask us to you know, mitigate for
[45:37]
much more than than we are already. Um
[45:40]
but it seems like they're not
[45:43]
um
[45:44]
in in our discussions with them so far,
[45:45]
they haven't said that they that they
[45:47]
will that they will and they've accepted
[45:49]
our
[45:50]
submission with with the mitigation that
[45:52]
we've proposed. Um So,
[45:55]
uh you know, for example there, there's
[45:56]
potential for that full 100,000 to be
[45:59]
available to be to be moved into another
[46:01]
sort of road. Um
[46:04]
Yeah. Um
[46:06]
Yeah, and then
[46:08]
you know, land surveying and mapping for
[46:09]
example, that's another item that's we
[46:11]
haven't we haven't had to Yeah, I you
[46:14]
know, I I I Yeah. You understand me.
[46:17]
Just as you prepare it, sharpen your
[46:19]
pencil in because you you know, come in
[46:22]
solution oriented to the council.
[46:23]
» Right. Right. Yeah. Yeah, okay.
[46:26]
Yeah, appreciate that.
[46:31]
Are you guys probably I mean
[46:33]
you've sat down with them. You've you've
[46:35]
you've you've met with them. Are you
[46:37]
comfortable with them being a partner in
[46:39]
in if not that it it doesn't sound like
[46:41]
it's a big job for them, but it's a big
[46:42]
job for us.
[46:43]
» Yeah, no, we haven't actually met with
[46:44]
them.
[46:45]
Yeah, we we wanted to but you know, I
[46:47]
actually I I spoke to
[46:51]
Gordon Ball yesterday on the phone. Um
[46:54]
And
[46:56]
um but we had wanted to have this
[46:59]
meeting before we you know,
[47:01]
provided any kind of official
[47:03]
communication to especially well, to the
[47:06]
other contractors. Um and it's obviously
[47:08]
not going to be an easy phone call with
[47:10]
Marcus, but um
[47:12]
yeah, that's So, Peter, I mean so
[47:15]
if we make a recommendation, we're
[47:17]
making a recommendation knowing it's
[47:18]
higher than the budget, although with
[47:20]
your mitigating
[47:22]
recommendations, it may be lower, but it
[47:24]
sounds like it's it's worth discussing
[47:25]
among the city council anyway. I mean
[47:27]
it's it's not so far out there.
[47:28]
» Absolutely. It's
[47:30]
it's achievable potentially. Well, I
[47:32]
mean
[47:33]
I mean I'm sure maybe Glenn you less so
[47:34]
than us, but we're
[47:36]
we're just all reacting to that like
[47:38]
public process is you know, I wouldn't
[47:40]
bid my house with that process. You
[47:42]
know,
[47:42]
and it's just a it's just a just a it's
[47:44]
sort of frustrating, but um
[47:47]
I think you need to present it that you
[47:48]
know, this is the process and and it's
[47:51]
not it's not unusual to have our
[47:52]
estimate be be a little bit short of the
[47:54]
of of the in fact, the dynamic of the of
[47:57]
the process to to to almost have that be
[48:00]
the the norm.
[48:02]
But there is an opportunity
[48:04]
and I and I do believe it's worth the
[48:06]
time because because we have a lot to do
[48:07]
between BCDC, PG&E and the easements um
[48:11]
which would at the end of the day if
[48:12]
those if those don't come through,
[48:14]
you know, this project's not going to go
[48:15]
ahead anyway. So, work aggressively with
[48:18]
with the selected contractor to and it's
[48:21]
not like we have much of a choice. We
[48:22]
have to choose
[48:23]
the non-eliminated low low bid, right?
[48:26]
Right. Yeah, and and I think
[48:29]
if if we're choosing if we're choosing
[48:30]
any, yeah.
[48:31]
Right, yeah, exactly. And and I I think
[48:33]
that you know, if if if there was
[48:35]
another close bid for example, and and
[48:38]
you know, there was a way to parse
[48:39]
through the qualifications, um then then
[48:43]
we might be having a different
[48:44]
conversation, but I think you know, we
[48:46]
have one apparently bidder. The the next
[48:48]
one is you know,
[48:49]
500,000. I mean you know, higher. I
[48:52]
touched on this last meeting, too, and I
[48:53]
know this will come up in the city
[48:54]
council is
[48:57]
and it's hard it's hard to weigh this
[48:59]
against known risk failure there, but is
[49:03]
this is this something that you know, in
[49:04]
a year or two might be might be better
[49:06]
pricing?
[49:07]
I'm not saying non-inflationary pricing,
[49:09]
but just better pricing relative to the
[49:11]
war, the supply chain issues, steel
[49:13]
prices, gas petroleum prices. Good good
[49:15]
question. And currently so far, we
[49:17]
actually
[49:19]
do a lot of supply chain analysis for
[49:21]
our projects nationwide.
[49:23]
So, right now I do know that most of the
[49:27]
sheet pile is coming from US. So, no
[49:31]
tariffs. So, that has not been impacted.
[49:34]
Currently, the price of oil has not
[49:37]
impacted the sheet pile pricing. And
[49:40]
that was something that, you know, once
[49:42]
we started to see what was happening in
[49:44]
around and that's typically one of the
[49:45]
first triggers is the price of oil will
[49:47]
just start to impact everything for
[49:49]
production and
[49:51]
specifically sheet pile. So, at this
[49:54]
point we don't foresee
[49:56]
any changes and we're that close that it
[49:59]
would be not a major escalation. We may
[50:02]
have more impacts if we push the project
[50:04]
and
[50:05]
you know, without
[50:07]
you know, we're talking, you know, two
[50:10]
years down the road we're probably Even
[50:12]
these folks these folks gave these bids,
[50:14]
you know, these orders are good. The
[50:16]
price associations have been two or
[50:17]
three weeks, right? Two three and a half
[50:18]
weeks.
[50:19]
Um
[50:20]
would it could or would they come back
[50:21]
and say there's a 10% premium based on
[50:24]
recent events?
[50:26]
They I do know that there there is a
[50:28]
level of like they are entitled to that,
[50:31]
but I don't know the specifics
[50:32]
personally to what that is.
[50:33]
» They could do that. They could come back
[50:34]
with a I'm not sure to the specifics.
[50:36]
So, it all depends on I think on the
[50:38]
specifics of the contract. I'm just not
[50:40]
fully aware they are, you know, entitled
[50:43]
to that.
[50:44]
» [clears throat]
[50:45]
» All the good scenario I mean as far as
[50:47]
whether the contract
[50:49]
Yeah, yeah, two or three two or three
[50:51]
as as as they go lower their price they
[50:52]
can ask us to raise the price. No, this
[50:55]
is what the contract would be. Yeah.
[50:57]
And that's yeah, they're they're hanging
[50:58]
their hat on that and knowing that okay,
[51:00]
well, you know, we have to
[51:02]
we get a word once, you know, supposed
[51:04]
to that we you know, move specifically
[51:06]
on the sheets that would be the big
[51:07]
thing. So, I mean if it's if it's if
[51:09]
it's
[51:11]
legitimately now a cost of theirs big
[51:13]
it's
[51:14]
choose not to take the contract, right?
[51:16]
Or the or are they obligated to take
[51:17]
this contract?
[51:19]
Well, they're I think yeah, they have
[51:21]
you Julian can speak to this as well.
[51:22]
Again, are they obligated or that's
[51:23]
where they're yeah, that's where we have
[51:25]
a bond. Mhm. A bid bond.
[51:29]
Yeah.
[51:31]
» [clears throat]
[51:32]
» Well, so this committee we were going to
[51:34]
make a recommendation. It sounds like
[51:36]
the staff's recommendation is to to
[51:38]
recommend city council to accept the bid
[51:41]
of Gordon
[51:42]
Ball.
[51:43]
Um are we ready to decide on that with
[51:46]
the committee? I don't know how we what
[51:48]
do we further questions or discussion?
[51:51]
I would I would
[51:54]
edit that a bit in the sense that
[51:57]
it's not this committee's decision to go
[51:59]
ahead with the project.
[52:00]
Right? From a from a broader risk
[52:02]
perspective from a broader financing
[52:04]
perspective and from a broader um
[52:06]
operations perspective. But in in the
[52:08]
event the council is clearly said to us
[52:09]
at a retreat hence the formation of this
[52:11]
committee is um
[52:14]
we want this project to go forward. It
[52:16]
should it go forward we want you to do
[52:18]
the proper due diligence and proper
[52:19]
transparency to make sure that it's done
[52:21]
in a fair equitable manner and that
[52:23]
you're getting as much value for the
[52:24]
process as possible.
[52:25]
I think we should that's what we should
[52:26]
say is that given the process and given
[52:28]
the understanding of the project and the
[52:29]
scope,
[52:31]
this is the best contract for the job
[52:32]
and given the conditions that we talked
[52:33]
about a second ago that you're going to
[52:35]
post awarding of the contract value
[52:36]
engineer and look for look look for
[52:39]
potential values in the scope itself and
[52:42]
um
[52:42]
here are ways we can potentially
[52:43]
mitigate the cost in the existing
[52:45]
budgets or other budgets. Um that's the
[52:48]
recommendation to choose Gordon Ball.
[52:51]
What is it the
[52:52]
» Yeah, I think it should be yeah. We're
[52:53]
not saying the project should go ahead
[52:54]
with this. Ultimately,
[52:56]
you know, five people up there with
[52:57]
public comment are going to decide
[52:59]
whether this is this this, you know,
[53:01]
$4.6 million is something the city sees
[53:03]
a priority for the next, you know, year
[53:05]
and a half to
[53:06]
to mitigate this risk. Yeah. Yeah.
[53:09]
Um so it sounds like it it's um
[53:13]
on the understanding that there will be
[53:15]
you know, aggressive um
[53:18]
uh
[53:21]
what
[53:22]
I don't want to say reduction in cost
[53:25]
I mean, you know, you know the people up
[53:27]
there myself and and what I mean
[53:30]
they're going to say, you know, find a
[53:31]
place, you know, figure out the 315,
[53:33]
right? You know, we'd rather not have
[53:34]
that. We'd rather we'd rather you, you
[53:36]
know, get it out of the get it out of
[53:38]
the project one way or the other, you
[53:39]
know, either sharpen your pencil from a
[53:40]
scope perspective, value engineer it or
[53:42]
if you have to do exactly what what what
[53:45]
you guys talked about is is, you know,
[53:47]
take a portion that that's responsible
[53:49]
of a paving and a sidewalk budget or
[53:51]
other public works budgets and apply it
[53:53]
to this recognizing that you're you're
[53:55]
you're you're stealing from Peter to pay
[53:56]
Paul, but but be confident that you're
[53:59]
you're doing that in a in a in a in a
[54:01]
balanced way that you're not
[54:03]
jeopardizing Paul in that scenario.
[54:05]
They're going to want to see that
[54:06]
information. Right. Yeah. Yeah.
[54:09]
And and just just be confident that you
[54:10]
thought about it so that if you're not
[54:12]
able to lower the price
[54:14]
that we're not we don't have a, you
[54:15]
know, day one $315,000
[54:17]
hit to this budget. You don't want to go
[54:19]
through a project day one with that kind
[54:20]
of, you know, budget deficit.
[54:23]
» For sure.
[54:24]
Um
[54:25]
Yeah, absolutely. I mean, I I
[54:27]
» Help you with the staff report too. I
[54:28]
mean, like I'm don't stress about that.
[54:30]
Between Robert, you and me and Helga we
[54:31]
can figure out how to Yeah. write that
[54:33]
up. Yeah, that that
[54:35]
I really appreciate that. Um
[54:38]
Yeah, and and I think I think part of
[54:40]
the
[54:41]
um
[54:42]
you know, one of the questions that that
[54:43]
we'd have for you is is uh whether you
[54:45]
think, you know, where would be a more
[54:48]
appropriate um place to to look for um
[54:51]
savings uh and yeah, so
[54:54]
you know, see our existing CIP funds
[54:56]
versus scope of the projects and um
[54:58]
yeah, these kind of Well, that's kind of
[55:00]
a contract. I mean, I mean, yes
[55:03]
the the city can start with, you know,
[55:06]
what what what what um
[55:08]
parks and lanes what what what broader
[55:10]
public works infrastructure are you
[55:11]
doing that one you don't think you're
[55:13]
going to get to. Every year we don't get
[55:15]
to projects, right? That happens all the
[55:16]
time. So so so so
[55:19]
figure out which are the ones we don't
[55:20]
think we're going to get to
[55:21]
and roll that into '27 '28 or '26 '27 or
[55:25]
even '26 '27 '27 '28 and that's that's a
[55:28]
that's appropriate that potentially
[55:30]
could be used um for this recognizing
[55:33]
you're just kicking a can down the road.
[55:34]
It's not a savings, but
[55:36]
but it's a new public works budget next
[55:38]
year. Right. Yeah, exactly. And and if
[55:41]
through your personal or a professional
[55:43]
assessment
[55:44]
that
[55:45]
project can be deferred for that amount
[55:47]
of time. I mean, that's got to be part
[55:49]
of it as well.
[55:50]
Yes, exactly. And I think I actually
[55:52]
didn't get to that part of when I was
[55:54]
talking about the CIPs and the and the
[55:55]
paving um yeah, the It's got to be based
[55:58]
on some assessment
[55:59]
Well, exactly. Yeah,
[56:01]
I mean, because there are as you say
[56:02]
projects that roll over every year and
[56:04]
there are also, you know, sort of
[56:07]
forecast funds for
[56:09]
for for different projects that you
[56:12]
know, won't be used for one reason or
[56:13]
another and and can be pushed off to the
[56:16]
following year. Yeah.
[56:18]
And we'll just see if there are any I
[56:19]
see Patrick has joined. If there are
[56:21]
comments from Patrick or any I don't
[56:22]
know if there are any other Robert or
[56:23]
Rob or Glenn or anyone else who might
[56:26]
not have a chance to speak about this
[56:27]
and
[56:30]
Robert, Patrick, Glenn, any
[56:35]
Hey,
[56:36]
» [clears throat]
[56:36]
» I can go ahead and comment. I've just
[56:38]
been listening to this
[56:40]
well, to the whole conversation, but on
[56:41]
this last part we we did actually meet
[56:44]
Tony, myself and Helga and take a look
[56:46]
at our 20 our current budget in terms of
[56:49]
rollover and then what we're looking at
[56:51]
for next year in terms of projects that
[56:53]
have funds assigned, but not necessarily
[56:55]
a project earmarked for those funds. So,
[56:58]
I think there um you know, to Peter and
[57:00]
and Tony to your point there is enough
[57:02]
flexibility in the next, you know, this
[57:04]
current year and next year
[57:06]
we need to we we can find a way to pay
[57:07]
for this 315. Um but but the broader
[57:10]
point is let's let's work really hard
[57:12]
and try and bring the cost down, which
[57:14]
is of course what we'll present to city
[57:15]
council.
[57:21]
Yeah,
[57:22]
and so and this is just Robbie, you've
[57:25]
just reminded me of another thing that's
[57:27]
um
[57:28]
we would like to emphasize is that we
[57:30]
have no plans to request more funds from
[57:34]
from reserves
[57:35]
uh from general fund or critical
[57:37]
infrastructure reserves.
[57:38]
Um the you know, all the all the cost
[57:41]
savings would come from existing and
[57:43]
forecast funds and from the projects
[57:46]
itself.
[57:47]
Yeah.
[57:49]
That's a bit that's that's
[57:50]
sort of splitting hairs because it's
[57:53]
Well,
[57:54]
it's just going to be it really comes
[57:55]
from the city
[57:56]
» All all the same funds. So, it's a
[57:57]
matter of Right.
[57:59]
» Whether it's
[58:00]
in an existing appropriation or not.
[58:02]
Right. Yeah, yeah, no, absolutely. We
[58:05]
can't print money. So, it's it's at the
[58:07]
end of the day it's coming from
[58:08]
something or we're not doing something.
[58:11]
Oh, yeah, exactly. We're putting
[58:12]
deferring something or yeah. But I I I
[58:14]
think Robert said it exactly right and
[58:17]
Yeah. we can we can endeavor to to make
[58:19]
that presentation and I'll and I'll
[58:20]
certainly
[58:21]
be part of that and help explain it to
[58:23]
the council as we go forward.
[58:25]
Yeah, well, thank you. Yeah.
[58:27]
Okay, well, there's no further
[58:29]
discussion. It seems like we should try
[58:31]
and bring our our committee's
[58:33]
recommendation to our to a vote and
[58:35]
I think the movement is that the sub
[58:38]
committee
[58:39]
will vote to
[58:41]
um
[58:42]
I guess
[58:44]
that the vote along with the the staff
[58:46]
has made the proper recommendation to
[58:49]
the city council subject to the
[58:51]
adjustments and sort of
[58:53]
financing and payment. Um
[58:57]
and I I I guess we're not quite
[58:58]
endorsing that the the committee should
[59:00]
do this, but the committee supports the
[59:01]
staff's recommendation. I think you said
[59:03]
it exactly right that that that we we
[59:05]
support the recommendation of the of the
[59:07]
city staff that
[59:09]
Gordon Ball is the is is the contractor
[59:11]
to select and that
[59:13]
um
[59:14]
uh we encourage the the staff in the
[59:16]
presentation to city council to to focus
[59:18]
on
[59:19]
you know, value engineering and and and
[59:21]
scope considerations and then identify
[59:24]
where the
[59:25]
surplus $315,000 can come from within
[59:27]
existing budgets.
[59:30]
I was um [clears throat] may I move into
[59:32]
the vote on that?
[59:34]
Uh second that.
[59:35]
I can second that. And all all in favor,
[59:38]
I
[59:40]
I think it's just the three of us
[59:42]
Well, thank you. Yeah, and hopefully the
[59:44]
the speaker caught all of the
[59:46]
caught all of the language in there.
[59:48]
It's much better than the last one, I
[59:49]
know that.
[59:50]
Um so, the microphone of the speaker,
[59:52]
yeah.
[59:53]
And so, this may be the final time we'll
[59:55]
have to meet, I guess maybe subject to
[59:57]
Yeah, I don't know.
[59:59]
Robert, remind me, do we think it makes
[1:00:01]
sense to because because there's still
[1:00:05]
as you mentioned between BCDC, Genie,
[1:00:07]
and the
[1:00:08]
easements and the ultimate, you know,
[1:00:11]
issues of permits and getting going. Uh
[1:00:14]
and and after all, this committee
[1:00:16]
is designed to be the eyes and ears of
[1:00:19]
the community just just just just to
[1:00:21]
understand and, you know, either
[1:00:22]
anecdotally or or publicly make a
[1:00:23]
comment that, you know, we've been aware
[1:00:25]
of what's going on. I'd suggest another
[1:00:27]
in, you know,
[1:00:29]
if not one or two month at monthly
[1:00:31]
intervals, just to check in where you
[1:00:32]
are in this process
[1:00:34]
um so that the next month you presumably
[1:00:36]
would have received city council
[1:00:37]
approval, you presumably would have
[1:00:39]
engaged in a contract with Gordon Ball,
[1:00:41]
and have those initial discussions, and
[1:00:43]
have a tentative timeline for the
[1:00:45]
project. That would be So, in about a
[1:00:47]
month's time from now That's what I
[1:00:48]
think unless you think that's that's too
[1:00:50]
soon.
[1:00:51]
Um
[1:00:52]
No, I think I think there would be uh
[1:00:56]
quite a few there'd be a few updates in
[1:00:58]
a month's time. Um and we can
[1:01:01]
possibly, you know, change the date if
[1:01:03]
if we need to if we're waiting on for
[1:01:04]
some, you know, some
[1:01:06]
um decision or something. Robert, that's
[1:01:08]
not surpassing the the the um
[1:01:12]
charter or design of this subcommittee?
[1:01:16]
No, the the subcommittee is ad hoc. We
[1:01:18]
can't exist forever. Um but if we have a
[1:01:20]
clear ending point which may align
[1:01:23]
you know, with the duration of the
[1:01:24]
project and maybe at the close out uh
[1:01:27]
we'll have a final report that goes back
[1:01:29]
to council. I think that's still the
[1:01:31]
scope. Yeah, I would agree. I think it'd
[1:01:33]
be good to meet in another month.
[1:01:35]
And actually maybe throughout the until
[1:01:36]
the project is completed I absolutely We
[1:01:38]
discussed even having maybe one
[1:01:39]
committee member available for whether
[1:01:42]
it be every construction meeting, but at
[1:01:44]
least it's certainly up to speed whether
[1:01:47]
it's even also a follow-up after our
[1:01:49]
construction meeting with the
[1:01:51]
contractor. I'm under the impression
[1:01:52]
we'll be doing those weekly. Could be a
[1:01:54]
bi-weekly check-in or something of that
[1:01:56]
nature, but I think that it's very
[1:01:58]
important to keep you guys in the loop
[1:02:00]
throughout the process, too. You know,
[1:02:02]
we'll also have the have the contract
[1:02:04]
happening,
[1:02:05]
it sounds like. So, you'll you'll bring
[1:02:07]
this to council in April?
[1:02:08]
Yes. Yeah, that is the plan. Okay. Yeah.
[1:02:13]
Um
[1:02:14]
Yeah, so April 13th
[1:02:16]
um and
[1:02:18]
yeah, unfortunately, I'm going to be out
[1:02:20]
of town for a couple of weeks here, but
[1:02:21]
I have the the draft staff report and um
[1:02:26]
you know, uh I think the finance the
[1:02:29]
fiscal impact section is is the part we
[1:02:31]
need to um
[1:02:33]
drill down into. Yeah.
[1:02:35]
But uh
[1:02:37]
yeah, that and hopefully the
[1:02:39]
construction easements
[1:02:40]
and maybe even a contract for the other
[1:02:43]
portion of the work if that can all
[1:02:44]
happen in in in April,
[1:02:46]
uh that would be There's no bid
[1:02:49]
requirement for that? Is that the bid
[1:02:51]
threshold or something? They would
[1:02:52]
typically be, yes,
[1:02:54]
but there is in this case
[1:02:57]
what's called a sole source
[1:02:58]
justification
[1:03:00]
for for this for this contract
[1:03:03]
because they have specialized
[1:03:06]
knowledge of that company.
[1:03:07]
» Installed it.
[1:03:08]
Yes, exactly. Yeah. Yeah.
[1:03:12]
Yeah, and
[1:03:14]
but that's, you know, these are all
[1:03:15]
updates that can can come at the next
[1:03:17]
meeting for sure. Yeah. Okay, so we'll
[1:03:19]
plan on having a meeting probably late
[1:03:21]
April after the city council meeting and
[1:03:23]
after progress has been made. Um
[1:03:25]
and then we'll see
[1:03:26]
periodically after after that. Um would
[1:03:29]
you like to pencil in a date now that we
[1:03:30]
can
[1:03:32]
uh
[1:03:32]
or or uh
[1:03:35]
Would you Yeah. prefer to to wait and
[1:03:38]
have a a poll maybe further down the
[1:03:40]
line? If we if we sort of have a a
[1:03:42]
target date that we are, you know, can
[1:03:44]
then confirm, I think um
[1:03:46]
All right, for me that always seems to
[1:03:48]
work work better.
[1:03:50]
So, maybe the week of the 27th?
[1:03:53]
Okay.
[1:03:55]
I'm gone that whole week.
[1:03:57]
Are you there the week of the 20th? I'm
[1:03:59]
there the 20th.
[1:04:02]
I I'm here the week of the 20th.
[1:04:05]
When does city council act? Uh you said
[1:04:08]
it was the
[1:04:09]
13th. 13th, yeah. So, that's great.
[1:04:12]
So, that's a week after the city council
[1:04:13]
meeting. But you might not have made
[1:04:15]
much progress with the contract. Yeah,
[1:04:17]
it might be a little soon. Might shoot
[1:04:18]
for beginning of May, like the week of
[1:04:20]
the 4th. Early May might be better. I'm
[1:04:21]
away the week of the 4th, so I can do
[1:04:23]
the Monday or Tuesday.
[1:04:26]
And there's always, you know, we can
[1:04:28]
there's no reason this for emailing
[1:04:29]
communication Personally, I could I
[1:04:31]
could join a Zoom call.
[1:04:32]
» Or even a remote call if that's Yeah.
[1:04:34]
Yeah, I know it works for you. I guess
[1:04:35]
it would do we if we're not voting on
[1:04:37]
things necessarily, we don't have to all
[1:04:39]
be present, correct? And
[1:04:41]
I don't know what the or can we not have
[1:04:42]
a meeting? It's not a Brown Act, I don't
[1:04:43]
believe. Right, Robert?
[1:04:47]
That is correct. I don't believe this is
[1:04:49]
a Brown Act. I don't believe
[1:04:50]
So, I mean If this same group is meeting
[1:04:53]
Sorry, sorry. If this same group is
[1:04:55]
meeting meeting the
[1:04:57]
you know, the the core group that we
[1:04:58]
have here today, then it is a Brown Act
[1:05:00]
meeting. If it's just one person
[1:05:02]
assigned to meet with staff and what's
[1:05:04]
not
[1:05:06]
Well, I I guess our question, Robert, is
[1:05:08]
if
[1:05:09]
we couldn't do this as a complete remote
[1:05:11]
meeting.
[1:05:15]
Right, we need to have a quorum. Then
[1:05:16]
then the majority a majority of the
[1:05:18]
members have to be in person.
[1:05:20]
It worked out today because only one
[1:05:22]
person
[1:05:23]
member of that sub of the subcommittee
[1:05:25]
was was connected remotely.
[1:05:28]
Do we want to shoot for say Wednesday
[1:05:30]
the 6th and
[1:05:32]
if John can't I did do it remotely, but
[1:05:34]
I'm happy to do that remotely. Yeah,
[1:05:36]
sure. Let's do that. Okay. Let's May the
[1:05:39]
6th.
[1:05:43]
2 2 p.m. Or sorry, 1 p.m.
[1:05:47]
Yeah, if that time works for everyone.
[1:05:51]
Keep it consistent, I guess.
[1:05:55]
Okay.
[1:05:57]
All right, I just need to raise one
[1:05:59]
point.
[1:06:01]
Yes, a design point. Yeah, uh go ahead.
[1:06:03]
Yeah, that's okay.
[1:06:05]
So, this is addressed to Stetson.
[1:06:07]
Uh has to do with the height of the
[1:06:09]
sheet piling.
[1:06:11]
Larry's question to you apparently was
[1:06:13]
misunderstood.
[1:06:15]
He's asking why not
[1:06:18]
maintain the level the
[1:06:20]
» [clears throat]
[1:06:20]
» Same as the existing sheet piling.
[1:06:25]
Oh, the 2019 sheet piling, the top of
[1:06:27]
it.
[1:06:28]
Um
[1:06:29]
» Maintaining that height. It was It was
[1:06:32]
primarily to save cost to to not have a
[1:06:35]
higher sheets and more concrete backfill
[1:06:38]
and any any fill you put along the wall
[1:06:41]
um requires a mitigation from the
[1:06:45]
jurisdiction. So, the wall where
[1:06:47]
existing sheet piling
[1:06:49]
is the new sheet piling. It's It's
[1:06:52]
approximately a foot lower.
[1:06:55]
You're cutting it off.
[1:06:57]
You're cutting off longer pieces anyway.
[1:07:00]
Maybe. I mean, it depends where they
[1:07:02]
where they drive it to. Well,
[1:07:04]
I could drive it in and drive it in
[1:07:06]
those. These aren't being driven.
[1:07:09]
These aren't being driven. Yeah, they're
[1:07:10]
being pressed. There's no driving.
[1:07:13]
There there will be a It's that We did
[1:07:15]
We did We did design it so there's a
[1:07:17]
It's a It's a It'll be a gradual
[1:07:19]
transition, so it's not going to be a an
[1:07:21]
abrupt, you know,
[1:07:22]
90° change. It's There is going to be a
[1:07:25]
transition
[1:07:27]
over over a period of a horizontal
[1:07:28]
distance, so
[1:07:29]
» And and the 2019
[1:07:31]
repair has one as well. There's a a
[1:07:33]
little slope down to two different
[1:07:35]
elevations.
[1:07:37]
Um but to add
[1:07:38]
Julian to the reason for keep reasons to
[1:07:41]
keep it keep it down, one is the
[1:07:43]
permitting
[1:07:45]
because permitting agencies um
[1:07:47]
were
[1:07:49]
happy to see that if that's the the all
[1:07:52]
the pile would be kept below the the
[1:07:54]
height of
[1:07:55]
where the sea sea lettuce reaches
[1:07:58]
because that would be colonized much
[1:08:00]
more quickly by sea lettuce and
[1:08:02]
barnacles and so on. So, the lower the
[1:08:03]
better for them
[1:08:05]
as far as habitat goes.
[1:08:07]
Um then also aesthetics. Um right now
[1:08:10]
from from the the homes along there or
[1:08:13]
from from the water
[1:08:15]
um
[1:08:16]
it's it's less visible
[1:08:17]
the the lower down it is.
[1:08:19]
Um so,
[1:08:21]
that along with the embedding the
[1:08:23]
uh the gravel into the top of the
[1:08:25]
concrete along there um
[1:08:27]
you know, sort of the the permitting and
[1:08:29]
and somewhat for aesthetics. So, we're
[1:08:31]
talking about a foot.
[1:08:33]
About a foot, yes. Yeah. Yeah.
[1:08:36]
Yeah, so I mean, and if you look at the
[1:08:38]
the 2019 piles, there's a point on the
[1:08:40]
piles where the barnacles stop. And then
[1:08:42]
above that is just the the metal, you
[1:08:45]
know. So, the idea here was that
[1:08:47]
the this would be completely below that
[1:08:49]
that level of
[1:08:51]
you know, habitat. Is Is there Is there
[1:08:54]
inherently a
[1:08:55]
you know, for the people viewing it from
[1:08:57]
the water side or from the
[1:08:59]
homes out there? Obviously,
[1:09:01]
um
[1:09:01]
I mean, there is every every aesthetic
[1:09:03]
appeal to having it consistent as as
[1:09:05]
much as consistent as as possible. Um
[1:09:07]
but you're saying there's there's
[1:09:09]
there's no structural need for it cuz
[1:09:11]
that the note we got today clearly said
[1:09:14]
that the the the structural requirements
[1:09:16]
are really down below as opposed to
[1:09:17]
above. No structural need for it. My my
[1:09:19]
biggest concern is is it would add
[1:09:21]
additional mitigation measures and
[1:09:23]
potentially hold up the BCDC permitting
[1:09:25]
process. Um you guys need to sort of
[1:09:27]
give us a thumbs up and thumbs down
[1:09:29]
this. I mean I see Larry's point that it
[1:09:30]
might look better if it was less It was
[1:09:33]
all the same. jig jaggy.
[1:09:35]
But not enough to delay or or the
[1:09:38]
project or to have a cost consideration
[1:09:40]
or have
[1:09:42]
you know, permitting issues with you
[1:09:43]
know, the lead agency there. Right.
[1:09:45]
Yeah. Or even if we can do it from an
[1:09:47]
environmental perspective whether
[1:09:48]
whether ours are are
[1:09:51]
review covered that scope. But then
[1:09:53]
again, we did we're we're we're we're
[1:09:55]
we're we're
[1:09:56]
we're we're I'm leaning on the broader
[1:09:58]
review, right? So that matter that
[1:10:00]
should matter. The environmental review
[1:10:01]
should matter, right?
[1:10:03]
No, so that it wouldn't I don't think
[1:10:05]
impact the EIR if it was you know, if if
[1:10:09]
what you're talking about is is the 2019
[1:10:11]
sheet piles cuz I think that's
[1:10:14]
probably what was kind of envisioned as
[1:10:17]
the sort of a comparable Yeah, exactly.
[1:10:20]
Yeah, I don't know if Julian if you have
[1:10:21]
any thoughts on that. Well, it would
[1:10:24]
require going back to all the agencies.
[1:10:26]
It would be it would be more fill in the
[1:10:28]
jurisdictional waters. So we'd have to
[1:10:29]
restart or you know, renegotiate with
[1:10:32]
all the agencies and there would be a
[1:10:34]
cost increase.
[1:10:36]
Yeah.
[1:10:38]
Any answer?
[1:10:39]
» If I could chime in here too, from from
[1:10:41]
what we've talked about on this project
[1:10:44]
from the beginning we we always
[1:10:45]
envisioned I think this aesthetic
[1:10:47]
improvement that we're talking about
[1:10:49]
whether that be a cap or riprap or some
[1:10:51]
other kind of concealment method
[1:10:53]
for hiding that you know, the steel
[1:10:55]
sheet piles and the concrete. That would
[1:10:57]
always be coming as kind of a phase two.
[1:11:00]
And it's just a matter of when we can
[1:11:01]
get that done in terms of you know,
[1:11:03]
perhaps the larger project or when funds
[1:11:05]
are available. But you know, the
[1:11:08]
structural [clears throat] component
[1:11:09]
holding up the wall and you know,
[1:11:11]
keeping the cost down low was always our
[1:11:13]
primary target at least in the short
[1:11:15]
term.
[1:11:17]
Okay, I'll tell Larry. Thank you.
[1:11:21]
Yeah, he raised it last month also. And
[1:11:22]
I think
[1:11:23]
Yeah. You should I don't know if Larry
[1:11:25]
got that note you sent around today. Um
[1:11:27]
Um I I think he uh
[1:11:30]
with with the response from the state
[1:11:31]
and I think he must have because I think
[1:11:33]
that's what what you might be referring
[1:11:35]
to then for the
[1:11:37]
as far as the the misunderstanding. I
[1:11:40]
think that's maybe what what he was
[1:11:41]
referring He brought it up last week too
[1:11:42]
last month too. So he he may or may not
[1:11:45]
have it well.
[1:11:48]
» Right. Yeah, and I I mean I I
[1:11:49]
misunderstood it too actually cuz I
[1:11:51]
thought he was talking about having a
[1:11:53]
higher up
[1:11:54]
you know,
[1:11:55]
to support the wall. I think he just
[1:11:57]
wanted it to match what was there. Yeah,
[1:11:59]
I understand. And yes.
[1:12:01]
And so
[1:12:03]
Okay, I think we can adjourn unless
[1:12:04]
there's any further comments. Thank you
[1:12:06]
so much. So many thanks. Thanks. Yeah,
[1:12:09]
thank you all. Thank you all so much.
[1:12:11]
Thanks Robert.
[1:12:11]
» Thanks Robert.
[1:12:16]
What