Transcript
SOURCE TRANSCRIPT
This transcript is downloaded from the source you provided but we haven't reviewed it for accuracy. Treat it as a starting point, not a verbatim record. You can also request an AI-transcription of the audio file with the button to the left.
These are YouTube's auto-generated captions, not a human transcript — expect occasional errors, especially with names and technical terms.
[0:02]
Utility Board August 18th 5:00 PM
roll call
[0:10]
» present
>> Hamilton
[0:11]
» present
>> present
[0:13]
» Peterson and Brisley are out.
>> Um item two public comment
[0:22]
» not hearing any loyal observer.
All right.
[0:28]
Move on to number three. Approval of the
agenda.
[0:33]
Motion to approve. Second
[0:41]
statement.
>> Gooding.
[0:42]
» Yeah. Moved by Gooding, second by
Hamilton.
[0:47]
All those in favor say I.
>> I.
[0:50]
» I.
Those opposed same.
[0:56]
The uh agenda is approved.
Uh approval of the utility board minutes
[1:01]
from August 4th.
Any comments or corrections?
[1:09]
» Motion to approve.
[1:14]
» Second motion made a second by Hamilton
to approve the minutes from the August
[1:19]
4th meeting. Those in favor say I.
>> I.
[1:23]
» I. All opposed.
The minutes are approved.
[1:29]
All right. Financial administrative
consideration to prove the bills
[1:32]
payable.
>> I didn't see anything jumped out.
[1:38]
» I just had a question on some of these
payment. What is W4 for um aligned
[1:43]
permit American
WS
[1:49]
request and then catch Walter Scott?
It's our draft request to Walter Scott
[1:55]
and then the other
Walter Scott.
[1:58]
» Yes.
>> Thank you.
[2:04]
» Any other questions or comments?
Take a entertain a motion to approve.
[2:10]
» Motion to approve. Second.
>> Motion to approve by good and second by
[2:14]
Hampton. All those in favor? I
>> I
[2:18]
» I
know that hearings on the uh
[2:24]
bills are approved.
Discussion and consideration to approve
[2:29]
resolution 2025-
2026-07
[2:34]
ENW appointing city clerk finance
manager.
[2:52]
» Congratulations Satie.
>> Thank you. Have you started yet?
[2:57]
» Not no yet.
>> When Martha gets back off, [laughter]
[3:03]
» I do have one question, Satie.
>> Sure.
[3:06]
» Just to clarify for everybody, what more
are you picking up with this?
[3:13]
» You understand where I'm going with it?
I mean, what more are you doing going to
[3:16]
be doing in
>> So, the biggest thing is going to be
[3:19]
bank wreck. I mean, there'll be a few
other smaller things, but I think we're
[3:24]
going to we'll see how it goes and
realign some of the job duties amongst
[3:28]
everyone in the office.
[3:32]
But that'll be the biggest one.
>> Okay.
[3:38]
» Thank you.
[3:43]
I hear
a motion to approve. We have to have a
[3:47]
roll copy.
>> [clears throat]
[3:48]
» Y the first until I can approval on it.
>> So I say what to say.
[3:56]
» Motion make a motion to approve.
>> Motion to approve.
[3:58]
» Second.
>> All right. Now I'll ask Gage for a roll
[4:01]
call. Deb
>> present. I
[4:09]
» He's
[4:13]
only one I guess
[4:22]
update.
>> I don't have anything today.
[4:25]
» Okay,
to the electric department number five.
[4:31]
Yep.
>> Uh yeah, I got some outages to report.
[4:34]
Um on August 7th uh
vacation, I got a phone call. There was
[4:40]
a blink here at 305 North Third Street.
Um I called So I called Devin. Um he was
[4:46]
here. Um he found a well she was down
further down the street um on West
[4:53]
Donahue um off of main theater that was
from Don to Davenport. Uh
[4:59]
he walked the line, didn't find anything
obvious. Um, I have to leave that as an
[5:03]
unknown cause for now. So, but he
refused it and um, everybody was back
[5:08]
on. There were 16 customers affected.
Everybody's back on at 230.
[5:13]
» It was a [clears throat] big boom.
>> Yeah, those are
[5:17]
15 to 20 amp fuses. Those are loud. So,
yep.
[5:23]
On August 9th, uh, in the morning at
9:00, I got a call from the answering
[5:27]
service. It was out recorded at 700
Westclair Road.
[5:34]
Gabe, I called Gabe. He was then go
check that one out. Um, he found a tree
[5:38]
branch on the 100 block of
between
[5:45]
8th and seventh street across two
phases. So, um, he cut the tree out
[5:51]
while the line was dead quick and then,
um, he went down the line and had it
[5:56]
refused two fuses there. So they were
back on by 10:15. Those are 43 customers
[6:02]
affected between those two blocks.
[6:08]
And here recently uh last week on the
12th on Wednesday, we had a big storm
[6:16]
system come through right away in the
morning. Uh,
[6:22]
we got a call at 7:15 a.m. for at 7:25
South 11th Avenue.
[6:31]
They didn't have any power. We got
there, they had a branch in the yard
[6:35]
come down on the service line and ripped
it out of our transformer legs on the
[6:40]
pole. So, had to get that one, which
that was just a quick prehook up for
[6:45]
that. They were back on by 8:30. The
next house next door at 18:03. They were
[6:52]
also without power reported at 7:30 a.m.
Uh we had to wait to put that one back
[6:57]
up because it really didn't do any
damage to our line, but it ripped their
[7:01]
uh their mast and their meter socket off
the house actually. So, we had to wait
[7:06]
for an electrician on that one before we
get get them hooked back up properly.
[7:10]
So, we got them back up and going at
12:45 in the afternoon.
[7:15]
That's all I got.
>> Thank you. Department update, Colin. Uh,
[7:21]
not so much for any. Um, we had new
electric install here at the uh the new
[7:26]
storage units that we're putting up on
East Franklin Street and North 12th
[7:30]
Avenue
and uh
[7:35]
did complete a pool change out on 6th
Street and then
[7:41]
run more services here.
So,
[7:46]
» thank you.
[7:50]
Item seven, water department.
Do water breaks?
[7:54]
» Yes, we did have another breakdown
[7:59]
from 7:31. Uh on 84, we had a break
right here in front of city hall. We
[8:05]
were operating a hydrant to pull a water
sample from and as soon as we got the
[8:08]
hydrant turned up, water started coming
out of the road. So, shut that down
[8:13]
really quick. So, we were able to
respond to it within seconds. Um,
[8:19]
yeah, ended up taking us nine hours. We
had to the blowout was on the bottom of
[8:24]
the pipe. It was right next to a bell,
so we had to cut the bell out and splice
[8:27]
a new pipe in. Um, just took us a while
cuz the sand and the residual water just
[8:33]
kept coming back in. [clears throat] So,
excavating to find the break just just
[8:37]
took a little extra time. So, about
10,000 gallons lost. The same set of
[8:42]
residents that were affected by the
break on 7:31 were also affected by this
[8:46]
break.
Yeah, big team effort. Everybody stepped
[8:50]
up helped out a lot when public works
helped us with trucks and closing the
[8:54]
road down electric guys later and they
help get equipment and stuff moved
[9:00]
around. So
the team makes it go easy. So So that
[9:06]
one had a boil order. Did the other one
too? Is they both had boil orders?
[9:11]
Does that have I mean do you typically
have to do a boiler on your main?
[9:14]
» Yeah. So if the if the main drops below
20 PSI we were supposed to do a boil
[9:18]
order and because we had to splice both
of those brakes both they shut down. So
[9:24]
we obviously at zero PSI so
I never really have any concerns cuz we
[9:30]
flushed after every break.
Yeah. Both uh we had two consecutive
[9:35]
passing back TE's and each break we had
consecutive passing back TE's. Good.
[9:42]
Thank your water test results.
>> Yeah. Uh July's bacteria was good. The
[9:46]
fluoride was good. We were right at uh
the recommended levels. And our
[9:51]
disinfectant byproducts, which is our
dhalmethanes and haloidic acids.
[9:57]
Those are all under the MCL compliance.
Okay. Thank you.
[10:04]
Uh item C is discussion and
consideration to begin the well drilling
[10:08]
permit process.
>> Yeah. So I think this is something
[10:12]
that's becoming more urgent as we keep
moving forward. Um it is one of the
[10:17]
projects that we included into the rate
study and that has been approved to kind
[10:23]
of for us to move forward. The biggest
thing that we need to decide to start
[10:27]
this process is the first thing that has
to happen is a wellsight survey that the
[10:31]
DNR will conduct and we just need to get
the ball rolling by pretty much choosing
[10:36]
who you want to set up.
Be our consultant pretty much our
[10:40]
engineering consultant. Sh's been our
the main state around here. They've
[10:44]
helped us I think they helped with the
design of the the treatment plant. I'm
[10:48]
pretty sure they've been a part of here
in Eldidge. Um ISG obviously has kind of
[10:54]
come in as a new engineering firm that
we've been working with recently. So
[10:58]
they're another candidate that we could
possibly use in these upcoming projects.
[11:04]
But the biggest one is just choosing
who we want to use as consultants and
[11:09]
then they'll move forward. They'll
submit the the proper paperwork for the
[11:13]
DNR to come here to a site survey.
[11:22]
So, so we're just [clears throat] you
got dollars here and everything. So, are
[11:26]
we approving that every item on here
just item one the board would just be
[11:33]
choosing who we want to use as
consultant? This isn't like there's no
[11:38]
like dollar amount here that we need to
get.
[11:42]
» So, you're just starting the process.
So, we're just starting the process.
[11:45]
We'll get forms and things submitted and
then
[11:48]
» and then you get your bids and stuff
>> and then right as as we continue working
[11:51]
with whatever consulting firm we want to
work with, they'll obviously help us
[11:56]
progress through this bus
>> and the fee for them we pay we pay them
[12:01]
an annual fee for doing things or
they'll charge us by the hour for you. I
[12:06]
think in this project we would end up be
a portion to us the bid process would be
[12:11]
their engineering
just trying to understand what we're
[12:15]
what we're approving.
>> Yeah.
[12:17]
» So it's basically just you guys telling
me to reach out to SH. So the other
[12:24]
thing too is we're meeting with SH
battery this Friday to discuss future
[12:29]
projects. They've taken a peek at the uh
the per that we have conducted. They
[12:35]
took a they took a look that look at
that. So we're going to sit down with
[12:38]
them and go through that VR and
see what they agreed with and what they
[12:43]
don't agree with.
>> Okay.
[12:47]
» So those are my questions have any
questions or comments?
[12:50]
» The funding for project like this just
looking at the well cost of 1.6 million.
[12:55]
How does that work?
the uh
[13:01]
it's in it was in this forecast scene
that we got from PFM
[13:06]
and you can ask the specifics but they
showed us the rate increases as we and
[13:12]
it also showed the date approximately
what years that each of the amounts
[13:16]
would come into the bud.
>> So we we would have to bond out for
[13:19]
that.
>> You have to answer that. not
[13:23]
[clears throat]
>> so the the clear well the clear well and
[13:25]
the chlorine reconditioning projects
have been accounted for in the rates
[13:30]
study and I think those were I think we
allotted $200,000 and
[13:35]
20 25 and 26 and 26 and 27 and then for
the new thing it's I'm pretty sure it's
[13:43]
accounted for 27 28
or 26 and 27
[13:51]
I I'm sorry. I thought one was the uh
the long formula.
[13:57]
» So what the the anticipation with this
one is I mean the SRF bond rule SRF.
[14:06]
There were two different it7
to 275 for the clear well and the
[14:12]
detention
and area 450 and the 2627 forecast.
[14:19]
They have them highlighted green and
purple and purple I thought was the one
[14:22]
that might have to go in.
I just want to get to your answer. I
[14:26]
know
[14:33]
I know the two projects that were
included in that race study were the new
[14:37]
well and clears
[14:44]
projects.
Um, but I know that ISG had already
[14:49]
recommended using this the SRF funds or
the FRS loans and rolling that into a
[14:55]
construction loan that we can include
any of these projects into and that's
[15:01]
something that the consulting firm that
we use that will assist us with that
[15:04]
process.
So it's not worth a bomb then right on
[15:10]
on this page they show the uh proposed
electric inter fund loan is 1.5 million
[15:16]
for the well site then they have
upcoming loan bond issuances and
[15:20]
proposed water revenue bond series 2027
920,000 bond issue for clear well
[15:26]
detention fix
[15:31]
and then they go the cash flow and
payment up till 2031
[15:37]
had discussion with Nevada because
electric has some upcoming projects that
[15:42]
may be larger.
They want us to see the SR funding
[15:45]
instead.
>> Okay. So that's a discussion that we
[15:48]
want to have as a large as like a full
group and then maybe for the user to
[15:52]
talk about as well.
>> So at this point we're just getting
[15:54]
started then we'll come back and discuss
funding. So pretty much we're just so I
[15:59]
would just basically have whatever
consulting firm you want to work with.
[16:03]
They would submit the initiation forms
for the DNR to come do a wellite survey
[16:07]
and then that starts the process.
>> I think we're behind the eight long to
[16:11]
get it started.
>> Yeah.
[16:14]
Even straight from the DNR they said
that on the low end it's three years.
[16:19]
» Wow.
>> So could get moving.
[16:22]
» There's no question.
Is there is there a firm that you would
[16:27]
would prefer to work with? I mean, one
that's
[16:32]
I guess I can't favor one or the other,
but I would say Shadre's been here is a
[16:39]
I mean, they intimately know everything
in our system and we're working with
[16:44]
them in every facet and every
department. So, I think they're pretty
[16:49]
much on retainer for both utilities,
right? Yeah, they're currently
[16:52]
conducting our electric system study,
too.
[16:57]
» And ISG did perform the engineering
report that they found some of these
[17:04]
things, but I think previously shy of do
the same things. And I'm willing to bet
[17:09]
when we talked to them on Friday, they
probably would say that a lot of these
[17:12]
projects were things that they wish they
recommended as well.
[17:23]
obtain a motion to um
[17:28]
approve
it's a process started I don't know what
[17:33]
the right language is yeah it begin the
well well drilling process which
[17:38]
includes getting
into firm get
[17:44]
motion to approve second
a Voice vote. No voice in. So all those
[17:50]
in favor say I.
>> I.
[17:52]
» I
[17:55]
department update.
>> Not much. Uh our one of our operators,
[18:01]
Tanner and his wife, Haley, they had
their baby. So Tanner is out for the
[18:04]
next uh 3 weeks. He'll be back on the
31st. So congratulations to them,
[18:09]
obviously. Um our new truck is here in
Davenport now. We're just waiting for
[18:15]
the spray-on bed liner and the custom
formats, like the printed floor mats. As
[18:21]
soon as those get done, they're going to
deliver it. So, like maybe later this
[18:23]
week or early next week that we'll get
that truck.
[18:26]
» Okay.
>> Um then we don't have to worry about
[18:28]
that. Uh, we're potentially I think the
plan right now is for the truck that we
[18:33]
were going to get rid of is that we're
going to
[18:36]
possibly move that vehicle over to
public works and parks and then get rid
[18:41]
of a truck that they have that's
significantly older and will be done.
[18:45]
So, we'll see how that is for as soon as
we get new as soon as we get the new
[18:50]
truck. Otherwise, we just been keeping
up with maintenance and making large
[18:55]
flow.
>> I have a question. Never know if I can
[18:59]
what I can ask with um can I ask you can
I ask him about the service rules?
[19:04]
» So service rules are in process right?
I thought we we were going to move
[19:09]
forward with getting service rules.
I have not received an update as far as
[19:15]
how far is but they're working. We we've
had a couple meetings about it.
[19:22]
» So I have a question. Do you plan or
have they talked about the is there a
[19:25]
curtailment plan part of the service
rules or is that something that would be
[19:29]
discussed and handled separately
[19:35]
and we really don't have a big enough we
don't have a lot of big users that we
[19:39]
would look at curtailment but with the
fact that you talked last week about
[19:43]
well five you were having issues
and their demand was high if we
[19:49]
» if we do have issues like that in the
future how do we curtail do you have a
[19:52]
plan I So we do there is a a portion of
it is water conservation and when I was
[19:58]
make creating the document
I was using other municipalities that
[20:02]
have water conservation programs in like
in place I used them as a template and
[20:08]
it seemed like pretty much everybody was
like almost word for word the same
[20:12]
conservation plan. So I pretty much just
took all those and plugged them into
[20:16]
this rules of service.
So, I don't think there's going to be an
[20:21]
issue with the water conservation plan.
I think there were some questions on
[20:24]
their end about it, but it's going to
hopefully it will be in place that if we
[20:29]
got to a point where we had to start
slowing people down, we could
[20:33]
find with the wells we have if if we
lost that well permanently or you had
[20:38]
and we did have reduction below demand
besides coffers. I mean to me
[20:43]
conservation is not going to get us much
[20:47]
and and again the biggest user the
biggest use other than when Manassa is
[20:51]
busy as a school system correct the
waste treatment plan
[20:55]
» waste treat okay that's something really
okay just discussion I just
[21:02]
» we don't really have many like
commercial industrial production places
[21:06]
that use a lot of
>> right there so it's basically the
[21:10]
plans yeah waste Water and the schools
are the two biggest.
[21:14]
» Yep.
Reason I asked is when we were talking
[21:18]
about if we ever did hook up with
American Water, it was bulk when they
[21:21]
cut us off, then we would then have to
make sure we had a curtail on the plan
[21:25]
if we grew that far and I didn't know if
we had one.
[21:28]
» Yeah. Um I guess as far as restricting
large users, I don't know if there's
[21:34]
something in there like that or we just
purely restrict large users. Well, I
[21:38]
think yeah, you appealed and if and then
making sure we have something in place
[21:41]
that if they are watering their lawns
and you've said no that we have that
[21:45]
worked out with the city that we can
um write a ticket.
[21:50]
» Yeah. Anyway, it's probably something
way out there, but it's something that I
[21:54]
» Well, I think that was the other issue,
too, is that
[21:57]
so I think as as a utility, we're not
allowed or able to issue citations,
[22:06]
» right? then we just would we work with
the city. So it is it's just something
[22:10]
to think about as they do your service
rules. Maybe have a conversation with
[22:14]
them on if there's anything we should do
in in addition to just a conservation
[22:18]
program.
>> Yeah. All right.
[22:25]
» Thanks.
>> Y
[22:28]
we've come to item eight.
Is there a motion to adjourn? Motion to
[22:34]
second.
Motion to uh forget I forget to do this.
[22:43]
Motion to adjourn my getting second by
Hamilton.
[22:48]
All those in favor say I. I.
Negative.
[22:54]
I are