Agenda
Transcript
AI TRANSCRIPT
This transcript was generated automatically from audio using AI and hasn't been reviewed by a person — it can contain mistakes, including plausible-sounding sentences that were never actually said. Treat it as a starting point, not a verbatim record.
[0:08]
All right, call the ask the city council work session to order here for Monday, February 24th.
[0:14]
Roll call looks like we have all members with us this evening.
[0:17]
I look for approval of tonight's agenda.
[0:19]
So moved.
[0:20]
I get a motion by Council Member Stelmack to approve tonight's agenda. Is there a second?
[0:24]
Second.
[0:24]
Second by Council Member Johnson.
[0:27]
Any further discussion?
[0:30]
Seeing none, all those in favor?
[0:31]
Aye.
[0:32]
All those opposed?
[0:33]
Motion passes 5-0.
[0:35]
Number four discussion items for a Central Avenue streetscape project plan.
[0:41]
Lee, who's taking this one over?
[0:44]
Jeff, who?
[0:47]
Hi, I am Jeff Volner with WSB.
[0:49]
And I have been working with city staff and the streetscape committee on evaluating the Central Avenue streetscape,
[0:58]
which is, well, tonight we're going to go through and kind of talk about the existing conditions,
[1:05]
some of the issues and then the recommendations on the streetscape committee, and then a few
[1:10]
schematic concepts to discuss, and then we'll have some question time after that for discussion.
[1:19]
So again, hard to see here on the photo here, but these were just Google Street View images
[1:25]
of kind of the issues you guys are having out there with your pavers crumbling in
[1:28]
the drive lanes, pavers crumbling in the boulevard in the sidewalk there. You can
[1:33]
see in the sidewalk one panel it looks like has been replaced with concrete. So
[1:38]
you guys are probably well aware of the issues out there on Central Avenue. Again
[1:44]
kind of a broad view of the the drive lanes and what the pavers are going out
[1:50]
there so not holding up and long-term solution is desired.
[1:59]
So some of the
[2:00]
issues we discussed in the areas we talked about within the streetscape so
[2:04]
the traffic lane is one of the big issues where all the traffic is where
[2:08]
the plows are hitting at the hardest where the pavers are crumbling and
[2:10]
making a rough surface so the suggestions and the committee
[2:15]
recommendations are removal of those pavers and installation of a more
[2:20]
durable surface, a concrete surface for the drive lanes and with that evaluating
[2:25]
some of the patterning or coloring and things that could go along with that.
[2:31]
The second area, again vehicular area, would be the parking lanes. One of the
[2:37]
ideas is to evaluate the use of permeable pavement in that area to
[2:42]
catch some of the storm water and clean it and slow it before it gets
[2:46]
in the storm sewer.
[2:49]
As you know there's permeable pavement in the Boulevard
[2:52]
areas now so there is some maintenance costs with adding more permeable
[2:57]
pavements in that area. So just considering that the maintenance of
[3:02]
permeable and the installation cost versus a solid concrete surface which
[3:07]
would be easier to maintain would stand up to plow abuse and that kind of
[3:13]
So, and with the consideration of permeable pavement, since it's not a permeable pavement
[3:19]
in that area now, we need to think about the subsurface conditions there.
[3:23]
So I believe that roadway is built.
[3:26]
The pavers are set on concrete below.
[3:28]
So that would be a significant excavation and I guess rebuilding cost to change those
[3:33]
to permeable to have that water soak through the pavement in that area.
[3:37]
So, the recommendation was to,
[3:41]
even though there potentially are watershed grants available
[3:43]
for permeable pavement and stormwater treatment, maybe this isn't the best place to do that
[3:48]
because of the additional cost and long-term maintenance.
[3:55]
The pedestrian sidewalks, so the actual walkway area or sidewalk area, again, existing
[4:01]
Crumbling pavers are not holding up, there's some falling apart and some rough surfaces
[4:09]
there.
[4:09]
So, recommending a more durable surface or a concrete surface there as well, just for
[4:16]
ease of maintenance and eliminating that trip hazard of the crumbling pavers.
[4:24]
The boulevard treatment, which is currently permeable pavers, and they're probably at
[4:31]
at least halfway through their lifespan.
[4:33]
So some of those are crumbling and moving around.
[4:36]
And just looking at it for,
[4:39]
looking at the rest of this project
[4:40]
or the rest of the street section,
[4:43]
probably doesn't make sense to leave that at its half-life,
[4:47]
but kind of look at the project as a whole side to side.
[4:50]
So that could still be permeable pavements
[4:53]
back in there or again with maintenance
[4:56]
and the equipment with snow removal and that kind of thing, is it holding up as well as
[5:02]
you want or is that somewhere to put a more durable surface as well?
[5:09]
Within the corridor, looking at the pedestrian crossings, again right now in the City Hall
[5:14]
Block, those are pavers, I believe, in the crosswalks, so looking at how to have
[5:24]
those areas stand out and have the crosswalks be more evident not just a
[5:29]
painted line but maybe it's a different color different texture something like
[5:33]
that to include in the paving and looking at the idea of adding the
[5:39]
pedestrian actuated push button lighting to signify when someone's
[5:46]
crossing the street so we'll be evaluating that as well.
[5:53]
The raised
[5:53]
These planters in the city hall block, the committee is recommending keeping those, but
[6:00]
putting a fresh coat of paint or a sealant on those to refresh the look and make them
[6:06]
look new again, updating the plantings within those planters.
[6:10]
Some of those, some of the comments where they're at an odd height where they block
[6:14]
views when you're trying to pull out or turn the corner, so maybe some lower plantings
[6:21]
or some higher up plantings that you can see underneath to help eliminate that view issue.
[6:30]
The idea of potentially working with a local nursery to develop those plants or planting
[6:35]
plants was brought up as well as part of the committee.
[6:41]
Street and Boulevard trees, again, if we're looking at in the city hall block, if we're
[6:46]
looking at replacing the sidewalk, the pavement, doesn't really make sense to
[6:51]
to work around those street trees that are currently kind of outgrowing their space.
[6:59]
So with the replacement of the pavements replacing the street trees as well,
[7:03]
maybe giving them a little more room or tree grades that would help
[7:07]
denote their area a little better than just the mulch squares that are there now.
[7:12]
And then other amenities. Irrigation is in the city hall block in the planters and in
[7:17]
around those trees and that would be repaired as needed more likely just the the raised
[7:24]
planter areas and then you know beyond the city hall block the lighting the
[7:31]
bollards the seating areas would remain those are still still in good shape so we
[7:36]
did put together some schematic concepts we brought two concepts to the
[7:41]
streetscape committee and got comments on that and from that we revised one
[7:46]
of them to give a couple more options and again for discussion this evening.
[7:54]
So the first concept would be changing the drive lanes to plain concrete so similar to
[8:03]
what you have throughout the rest of the corridor and again this block we're looking at the
[8:07]
city hall block and the elements that we would introduce in this block we would also
[8:13]
slowly introduce into the other blocks as maintenance and replacement takes place.
[8:18]
So, the main drive lanes would remain plain concrete, similar to the other blocks, and
[8:25]
then the sidewalks would be a colored concrete, so a standard broom finish concrete, but in
[8:33]
a tone or color.
[8:34]
So, in this scenario, maybe it's a tan or an earth tone that kind of matches some of
[8:40]
the paver colors that were originally chosen.
[8:42]
In
[8:45]
this concept, we were showing the parking lanes as, again, permeable pavers.
[8:51]
They could be permeable with a simple change of the label.
[8:55]
They could be a stamped or colored concrete and still have that paver feel that you have
[9:00]
out there now.
[9:01]
In the parking areas where they don't get as much traffic, don't get as much abuse
[9:06]
maybe as the drive lanes and as many cars coming up and down, you can have a little
[9:11]
a more decorative surface in there.
[9:15]
Lastly, the boulevard, again, could remain
[9:17]
the existing permeable pavers or like what's there now
[9:21]
so that could remain a permeable surface
[9:23]
or could also change to a stamped and colored concrete.
[9:28]
And the idea in this concept is, you know,
[9:31]
we've still got kind of the full range of color
[9:33]
that you have out there now.
[9:35]
We're denoting the different areas
[9:36]
of the parking lanes in the boulevard,
[9:39]
but really getting more durable surfaces in the main drive lanes and the sidewalks.
[9:48]
In this concept, the crosswalks would be a different color as well.
[9:52]
So they'd be the same color as the sidewalks.
[9:55]
It would kind of tie that pedestrian access area all the same.
[10:01]
So you would be able to see that as you're driving down the street
[10:05]
that it's a different color where the crosswalks are in the concrete itself.
[10:09]
So
[10:13]
again, in the blocks beyond the City Hall Block, so long term as maintenance and replacements
[10:20]
take place, we would continue with that colored concrete sidewalk, so that would be consistent
[10:26]
throughout the whole corridor.
[10:28]
The crosswalks could be replaced in that same way to keep the pedestrian areas, that colored
[10:37]
tone of concrete.
[10:38]
And again, the boulevard could remain the permeable pavers that you have now or replace
[10:45]
with permeable or again switch to a more decorative stamped and colored concrete for a little
[10:52]
more durable finish.
[10:59]
Concept two we were looking at again with the long-term maintenance and holding up
[11:06]
to the abuse that our lovely winters give this area.
[11:10]
the main drive lanes would be primarily plain standard concrete with some
[11:16]
colored concrete bands added within the block so that kind of breaks up just the
[11:22]
the sea of concrete you know plain concrete and gives it some color gives
[11:27]
it some some character similar to the banding that you have in your paver
[11:32]
pavement now. In this concept the parking lanes are treated the same as
[11:37]
the driveline so there's consistency where the vehicles are driving again with
[11:41]
that that banding to kind of break up the overall field. This concept is also
[11:47]
showing plain concrete for the sidewalks so again if there's you know every
[11:53]
everywhere has got plain concrete if we ever need to replace another panel or
[11:57]
something gets cracked or broken it's easy to go back in and and fix and
[12:01]
have things match long-term. Maybe not as decorative as what you have now
[12:06]
or the other concept, but more use of standard materials.
[12:13]
And then here is one where we were showing replacement of the permeable pavers in the
[12:17]
boulevard with a stamped and colored concrete that would match the tone of the bands in
[12:23]
the pavement.
[12:25]
So basically a two color scheme here, we're showing grays, again to work with the gray
[12:30]
tone of the plain concrete.
[12:33]
But a little different look of the overall block.
[12:41]
And again, how that
[12:41]
would be adapted to the other blocks as the sidewalks are replaced, you know, the pavers would come
[12:47]
out and the sidewalks would be put back in as plain concrete, as well as the boulevards being
[12:54]
replaced with the stamped textured concrete.
[13:03]
So again, these are the materials we're talking
[13:06]
about left to right. Left is colored concrete. I guess the left two columns are colored concrete.
[13:15]
The second column is what the sidewalk could look like with a tan tone. Again,
[13:22]
standard broom finish concrete but an integrated or an integral color that would give it that
[13:27]
softer warmer tone to it.
[13:33]
The column on the right permeable pavers again they come
[13:36]
in different shapes, textures, sizes from what you have now.
[13:40]
So if we choose to maintain that type of pavement,
[13:44]
we can get a slightly different look
[13:46]
or keep similar to what you have now.
[13:49]
And then I guess the second column from the right
[13:53]
are different textures of stamped and colored concrete.
[13:57]
So a little bit more decorative concrete could be used.
[14:02]
We were thinking more in the boulevards
[14:04]
than the drive lanes or the crosswalks
[14:07]
because with vehicular traffic that patterning can wear a little more and show wear patterns
[14:16]
and is a little more costly to put in to get that stamp and color.
[14:21]
So
[14:23]
the preferred concept with the streetscape committee was the first one.
[14:28]
So we went ahead and put together with some recommendations some other alternatives based on that first concept.
[14:35]
So this one again the main drive lanes would stay plain concrete through the
[14:42]
whole block with the crosswalks having a different tone or different color to
[14:46]
to make them stand out. The parking lanes would be similar color but a
[14:57]
plain a colored concrete in a standard finish.
[15:01]
In the parking lanes. So not a permeable pavement, but a different color just to denote those parking lanes.
[15:09]
The sidewalks in this scenario would change to plain concrete. So plain gray concrete.
[15:16]
And then the boulevard would have the colored, stamped, textured concrete.
[15:22]
concrete. This concept had more of the gray tones, again, kind of shifting from the earth
[15:29]
tones that you have now, simply to kind of work with standard materials with the gray
[15:36]
tones of the plain concrete, darker tones in the parking lanes for turning tires, and
[15:42]
things like that where they get dirty would not show as much in this concept, but a different
[15:49]
look overall than what you have out there now.
[15:56]
And then concept we're calling 1C,
[15:59]
another variation on that first concept. Again, standard concrete in the drive
[16:05]
lanes, the parking lanes would have a different texture or stamp to them or
[16:14]
different scoring in the parking lanes and the crosswalks, but again plain
[16:18]
concrete and in this one the sidewalks of the pedestrian areas have the similar
[16:23]
color tones that you currently have so the tans and the sidewalk the boulevard
[16:28]
could have more of that brown earthy tone whether it's a permeable pavement
[16:34]
whether it's a stamped and colored concrete but would have kind of a blend
[16:38]
of the colors of your current current streetscape and then as you as you phase
[16:47]
it in. I'm assuming this is the first block that will be addressed. You wouldn't have
[16:51]
that totally different look as you phase it into the other blocks.
[17:02]
So that's really what
[17:03]
I had quickly to go through as far as concepts. So I guess I'd like to open it up for your
[17:07]
discussion.
[17:09]
What's all our questions?
[17:12]
Mr. Mayor. So just to kind of talk a little bit about some of the comments that he
[17:18]
made, and Harold, jump in and interrupt me any time, okay?
[17:23]
When you get to the
[17:24]
concepts, the B and the C concepts, the biggest thing about that is that we
[17:31]
originally did explore utilizing the potential of a lot of the
[17:34]
permeable pavers.
[17:37]
We feel confident we could get a grant for some of it, but to
[17:41]
his point specifically about the stuff on the street part of it itself, is that
[17:47]
that we're pretty confident thinking back and remembering that the whole roadway bed
[17:51]
is concrete. And then when they built it, it was too low, so then there's some bituminous
[17:57]
underneath there. And then it's glued to the bituminous. So going the direction of
[18:02]
trying to add permeable pavers, we kind of felt would be cost prohibitive.
[18:08]
If it
[18:09]
was the desire to do that as well, the other thing about some of the permeable
[18:13]
pavers that if we decide to stay with them, when we might still be able to get some funding
[18:18]
for permanent waivers to the watershed district for back-of-curb usage, but one of the factors
[18:25]
to consider there is while it does have some water type of benefits, the other part of
[18:34]
it is that it does need to be sprayed out, cleaned out, maintained otherwise it gets
[18:40]
clogged up and once it's clogged up there's just nothing else that can be done.
[18:44]
So then we're looking at a continue maintenance and work component for public works to maintain
[18:51]
that which I personally I don't know if Council Member Johnson feels the same way kind of
[18:57]
walks on the edge of not a really good benefit to return ratio simply because of the fact
[19:04]
the ongoing maintenance of that could potentially make even using permeable pavers there not
[19:12]
necessarily a great idea. It was great back in the day, but now we know and have learned
[19:17]
more about that part of it. So that's where the whole permeable paver part comes into
[19:22]
place.
[19:24]
Can I just jump in real quick? The other part too that we talked about is with the
[19:29]
permeable pavers, really, that's only affecting those kind of gentler rains where you have
[19:36]
the gully washes.
[19:38]
That's just, it doesn't matter if you have permeable or not, that's going to run right
[19:40]
off into the gutter line and go right into the storm sewer, so we also consider that
[19:45]
as well.
[19:46]
Yeah, so I mean the mountain vima rain, but even still if we don't maintain those
[19:52]
permeable pavers very well, it's a very limited time perfume which they're no longer
[19:56]
very functional anyways.
[19:57]
which is what we haven't done. Right. So they probably are not even effective at
[20:03]
all right now the way they are. Right. And really the main difference between, you
[20:09]
know, in his print kind of like the the B and the C concept, I think that's what
[20:14]
it was, yeah the B and the C concept, is with the B concept there's a little bit
[20:21]
more limited use of some of the colorings. We are shifting away from the
[20:25]
overall color scheme of what's going on, which is where the C1 kind of makes some sense because
[20:33]
we are kind of sticking with the color scheme of what we have now moving forward, so it's
[20:36]
not going to be as much of a dramatic change, especially if we decide through this that
[20:43]
we have to address that north end of Central Avenue on the west-hand side, then also you're
[20:49]
going to have something totally different on one side.
[20:50]
The other side doesn't need the work, really.
[20:52]
it's just in front of city hall here and then that one area down there. So it's really kind of a
[20:57]
matter of comfort and design shifting that we're really looking at right now but really we focused
[21:03]
on delineation of the parking lanes, the crosswalks and then really additionally we all have been
[21:11]
exposed to the challenges that we have with trying to get across central and somewhere
[21:16]
pedestrian challenges and so looking at pedestrian actuated crossing signals at
[21:23]
the ends of the plaza there as well. On both sides of City Hall Block. Yep.
[21:31]
Here's talking. Crosswalk sign, we push the button and it flashes.
[21:35]
Yep.
[21:38]
So it's taken a lot of hours of meetings to get to this point and
[21:42]
several different renderings to give to you guys to get your feedback and
[21:47]
and hopefully come up with some consensus to move ahead.
[21:50]
Well, I think one of the things is with the concrete,
[21:57]
you're going to have a lot longer life than what
[22:00]
we have with pavers.
[22:02]
Pavers, even the ones that are there that are still
[22:06]
surviving, are near their end use
[22:10]
and are just going to continue to deteriorate.
[22:12]
and see we got we're ten years in and and got a lot of deterioration so the
[22:18]
deterioration is going to start to just multiply from here on and with some of
[22:27]
these designs of what they can do with the concrete it to make it look
[22:32]
attractive I think is the important thing that I like about this changing to
[22:39]
concrete rather than even thinking about any type of pavers at all.
[22:51]
Other opinions, thoughts?
[22:55]
Mr. Mayor, I want to thank the committee for spending the time to put this together
[23:03]
and putting the research into it. A lot of the questions were answered.
[23:10]
In short, I like option 1C, not having the pavers, I think is a good idea, because it's
[23:23]
hard and it's not that our public works department doesn't do their job.
[23:27]
They do their job really well, and they put in long hours and every hour they're working,
[23:31]
they're giving it their all.
[23:32]
But there's only so many hours in a day and we only have so many people.
[23:35]
So, to be fair to that group, I think putting in pavers is thinking more about a pretty
[23:42]
look then about what it takes to maintain that for the future and the stress that it
[23:46]
would put on the team.
[23:49]
I'm more in favor of like a colored or stamped concrete, but I'd like to learn a little
[23:53]
bit more about when we're coloring concrete, what's the life expectancy of a color before
[23:59]
it goes to that beautiful dull gray and gray?
[24:04]
I think it varies. Again, depending on who you talk to, some people say that if you get
[24:12]
the right air mixture, the right color mixture, the integral concrete will stand up as well
[24:17]
as the regular concrete as far as durability. Color does fade over time. I don't know that
[24:23]
there's a set amount of time. I guess a lot of that's probably amount of salt that
[24:27]
goes on it, amount of sun that it's in, there's a number of variables.
[24:32]
So I don't know that there's a set.
[24:35]
And it's probably batch dependent, too.
[24:37]
I mean, you're going to want to pour something all from the same batch
[24:40]
so that it is through at least the same pour the same.
[24:44]
So for something that way, these colors, and I'm not a concrete guy,
[24:48]
so bear with me, these colors, are they topical in nature?
[24:52]
Are they blended in with the mist?
[24:54]
This would be an integral color, so the color would be throughout the concrete.
[24:56]
And the thought there is if a plow does scratch it or a corner chips, it's the same color
[25:03]
through.
[25:04]
It's not a colored sealant or an acid wash that will wear off as quickly.
[25:10]
This, if the surface wears down, shows wear patterns, it's going to have that same color
[25:15]
throughout the concrete.
[25:16]
Yeah, I, thank you.
[25:18]
Thank you.
[25:19]
I just, I like the look of one.
[25:21]
see it keeps it got some different colors going on which was the the one nice
[25:26]
thing about having pavers but obviously they deteriorate too quickly and the
[25:32]
city still got to pay a bill for that but I think going with concrete however it
[25:37]
goes is the right way to go my my thought council and as far as looks
[25:43]
go I really like the look of 1C I think it has a lot going on and is pretty
[25:48]
visually pleasing.
[25:53]
How does one see a dress where you may have a bump out in
[25:59]
the future?
[26:02]
Would you be looking at taking that out or? I'm sorry the bump out
[26:07]
word? Like if we went into the next block or something that had a bump out
[26:14]
that would we be looking at getting rid of that since we'd be going with
[26:20]
concrete and they're more of a block kind of no the the bump-outs would stay
[26:27]
exactly where they are we're not anticipating changing the curb line or
[26:31]
anything on any of the blocks whether it's a central avenue block or the other
[26:35]
blocks up and down central or sorry the city hall block or the other blocks
[26:39]
up and down central avenue it wouldn't that the bump-outs would not
[26:45]
change the curb line would not change its location so
[26:50]
yeah just to follow up
[26:51]
on that. The road geometry would stay the same. The parking lanes would be in the
[26:54]
same area. The bump-outs at the corners would remain the same. They would just be
[26:57]
different materials. Okay.
[27:05]
Follow-up question. Now, did I understand that the
[27:12]
fading with what you're proposing here is not going to be a factor like we
[27:18]
talked about some of these other areas where concrete has been fading and it
[27:23]
end up a different color in five years?
[27:26]
I think it will fade slightly as concrete cures and ages,
[27:31]
even plain white concrete changes color some.
[27:34]
So it will fade and probably lighten up.
[27:36]
But where some concrete coloring is a topical sealant
[27:41]
or paint or acid stain that's just
[27:45]
in the very top film of the concrete that would wear off,
[27:49]
this would be concrete that would be the same color
[27:51]
throughout.
[27:52]
So, again, if it chips, if it shows wear patterns, it should be the same color underneath.
[27:59]
It's not a coating on top that would need to be replaced or refreshed.
[28:06]
Explain to me this one that's up here now on the Central Avenue driving lanes.
[28:13]
you've got lines across you know making squares out of small squares is is that
[28:22]
just a that's cut only just a little bit or how far yeah control joints are
[28:30]
typically through is it a third of the concrete isn't it so you don't want
[28:35]
concrete panels too big or they'll crack so you're you're kind of guessing
[28:39]
where they'll crack and keeping panels in a size that won't crack, so you put that
[28:44]
decorative scoring in there to try and control where it'll crack.
[28:49]
Now you also mentioned something about replacing panels.
[28:54]
Are you saying that if we have one of these that goes bad, that it can be replaced?
[29:01]
Just like with any other city street or concrete street, if you have a utility repair that
[29:06]
that you need to do in the middle of the street
[29:07]
or if there's an accident or something and one does crack.
[29:11]
Yeah, you can go in and saw cut out that square,
[29:14]
kinda drill the dowels into the remaining concrete
[29:17]
around there and tie a new panel of concrete back in there.
[29:21]
Yeah, and to piggyback off that,
[29:24]
that's why the Concept 1B, can you go back to that, Jeff?
[29:27]
Concept 1B is a little more just uniformed
[29:32]
gray concrete for that exact reason.
[29:35]
And if we have to, for some reason, go in there for utility work or one of the panels
[29:41]
in the sidewalk gets really heaved and breaks up, it's far easier to replace a piece
[29:46]
of gray concrete with another piece of gray concrete to match versus even with concept 1C
[29:52]
where you have some of this beige kind of, you know, brownish coloring.
[29:56]
In five years, you're not going to be able to replace that exactly with the same color panels.
[30:00]
So it's going to look off, which is why the concept 1B was one of our preferred options
[30:06]
in the committee for just ease of replacement of various panels.
[30:26]
One of the other things that we did discuss was the tree placement. We talked about, you
[30:34]
know, getting rid of the bark and putting down the steel plates, grates, whatever you
[30:41]
call them.
[30:42]
Yeah that's one thing we did talk about as well. It doesn't really show here in
[30:46]
the concepts but something we fight the battle of putting new mulch out there
[30:52]
every single year to only have it get flushed away down the drain during a
[30:56]
big storm and it's frankly it's kind of stupid to continue to just replace
[31:01]
you know with mulch and stuff so you know one thing I know Nick was
[31:08]
really interested in would be when we take all the trees out and when we
[31:13]
redo block by block is to bury those trees a little bit lower and then have a
[31:17]
great, you've all seen the grates in various different applications, but
[31:21]
that just gets away from having to re-put mulch and then that's frankly
[31:25]
going to be washed down during the next big rain.
[31:33]
Do you have any examples? Have
[31:35]
you done any of this anywhere locally? Of switching a whole streetscape or
[31:42]
just using the stamped and colored concrete? Yes. Yes, there's numerous examples. Lee actually
[31:50]
was just showing me one. He took a picture in Maple Grove where they just replaced
[31:54]
paper crosswalks similar to what you have here, but they were just the crosswalks
[32:01]
in the streets and they replaced it with stamped and colored concrete for the same reason.
[32:06]
Papers were crumbling. They had really gotten uneven. Some of the pavers had settled.
[32:27]
You saw me texting before the meeting, I was sending a picture to Riley and to Nick.
[32:32]
If you know where the hospital is in Maple Grove, they got the shops just north of there.
[32:38]
They have literally gone in and tearing up all the pavers.
[32:41]
And they do have some stamped colored concrete that they've put in place of the pavers.
[32:47]
So if you want to see a good example of that.
[32:49]
and they really, it's been in there for about a year, year and a half maybe, but
[32:55]
they pound the daylights out of it with their with plows and loaders and things
[32:59]
like that, so it appears to be holding up very well, but the same concerns that
[33:04]
Councilmember Schulz and Johnson brought up with regards to
[33:06]
color-grafating and things like this, that's, that's, it's going to be an
[33:12]
issue. One thing that I thought of after we met with the Street Escape
[33:17]
committee last week. I didn't mention I had a project 25 years ago used black concrete
[33:24]
carbon gutter and it's holding up really well. But what I did explain the streetscape committee
[33:29]
is that before even thinking about pouring that out in the street, we did test samples.
[33:36]
So in this case what I would say be very easily to get to work with a concrete supplier
[33:42]
and pour some test sections and I'm just gonna pick maybe not public works for Nick
[33:47]
and you could just have just some test panels that you just throw away later on
[33:51]
but you could actually see the color and let it let harden up and let and let it
[33:56]
and you possibly put some joint joint patterns on there just you want to do
[34:01]
that just to make certain that you're okay with the color before it
[34:05]
starts getting poured right right in your on your front door so I would see if
[34:10]
Jeff, can you go back to either one of these?
[34:12]
Well, that's one B or one C.
[34:14]
I'd really recommend that that would be a part of it.
[34:16]
We'd pour some concrete, some panels, maybe eight by eights
[34:19]
or something like this, just so you get a good,
[34:22]
you can visualize what that color's gonna look like.
[34:24]
And you could pour two or three different test areas
[34:27]
just so you can understand what the colors
[34:29]
are gonna look like.
[34:31]
And where would you pour those test areas
[34:34]
within this block?
[34:37]
I think we just pick a spot down public works shop and you just build some frames and some
[34:44]
plywood and you just bring them in there and just pour them differently so you can actually
[34:48]
see them after they start setting up.
[34:50]
If you do that, at least you got your at least readily assured that when it does go in,
[34:56]
you like the color and you can maybe start telling that if it's a little too red or
[35:00]
something like this you can maybe modify it but if it looks wrong there it's likely
[35:05]
going to look wrong when you when you pour it out here.
[35:11]
Did the committee go as
[35:13]
far as coloring or decisions like that? Did you have any directives that you
[35:21]
thought were better than? The only coloring examples are what you see in
[35:25]
front of you today. Yeah I think and correct me if I'm wrong committee but
[35:31]
So I think the thought was the 1B concept was a little bit better just simply because
[35:39]
of the replacement factor,
[35:42]
at least in my opinion, that's what I liked better.
[35:45]
And also the dark concrete is going to thaw faster than the light colored concrete or
[35:55]
that or any other color, but the darker the concrete, the better it's going to
[36:02]
thaw for winter.
[36:08]
And I would add at the concept level, you know, what we're
[36:12]
showing you is high level. Do we like the more earthy tans brown similar to the
[36:18]
paver tones that are out there? If that's the direction we go, yes, we'll
[36:22]
get a full color palette of what would go out there and some options kind of
[36:26]
forward. If we're okay with changing direction of the overall look of the
[36:31]
corridor and going more grays, again we'll do the same thing. We can we can
[36:37]
get some more samples and colors and overall color palette moving forward, but
[36:43]
at this point it's pretty high level to try and determine a direction for the
[36:49]
overall look of the corridor and what the hardscape would look like. So I guess
[36:55]
As for tonight, what we're looking for from the council is really shoring up all of the
[37:02]
various components of this plan and getting some pretty firm direction on which, you know,
[37:08]
kind of an either or you want so then we can take all those components and formalize
[37:13]
it into a final plan.
[37:14]
So maybe what I can do, maybe I'll just go down the list and I'll just kind of
[37:19]
take head nods here.
[37:21]
Is there a leaning towards more of the gray tones versus the earth tones?
[37:26]
Because that's a key component of what we're doing here.
[37:33]
My personal preference is that I like the earth tones, but I just don't know longevity and potential replacement
[37:41]
if that's the best course to do long term.
[37:45]
So, you know, visually appealing is definitely the more earth tones, but I think the most practical approach is more of the grays than the B type of a configuration.
[37:57]
I would agree with that.
[38:02]
I mean, obviously I think C is better, but if we can assure some sort of...
[38:11]
I don't want to do this again in five, ten years.
[38:14]
Exactly. I mean, if it's going to be an issue, but I mean, if the strength and durability
[38:20]
is similar, then, you know, all things equal of those two, I lean towards C, but it's going
[38:33]
to last half as long, then it makes no sense. You know, I mean, that's the thing that I
[38:38]
don't...
[38:39]
And I don't think there's a longevity question between the two.
[38:42]
I don't think there's a durability question or a longevity, I mean, concrete essentially
[38:49]
is concrete.
[38:51]
There might be some colors or mixes that maybe don't wear quite as well, but again, with
[38:58]
the test panels and working with concrete manufacturers, we'd get the air mixture and
[39:03]
the color mixture right for what's going in.
[39:06]
I think more of the concern is if for some reason you do need to replace something
[39:10]
or you decide to widen the sidewalk when the park gets redone or something like that, you'd
[39:17]
have that patch essentially that might not match exactly, which it probably wouldn't
[39:21]
match exactly with plain grey concrete.
[39:24]
But over time that kind of fades out and it gets dirty and they start to match.
[39:30]
Color concrete would act similarly. It's just probably not as used and not as, you know,
[39:41]
tested and gone through as plain concrete which has been used for hundreds of years.
[39:47]
That's right. I'm kind of in the same camp. If durability and longevity are about the same,
[39:54]
I like the look of sea. If they're really going to last about as long,
[39:58]
You just I just think it's a nicer look I think in the spring and the summer when there's the greens the color is going to pop nice
[40:07]
And then we're sure you're probably not going to see it anyway
[40:09]
So I don't know where to go with that
[40:11]
But I just I just think it's a nice look so it's you know
[40:15]
Function functionality has to come first. We're not stressing out public works team to go fix something that got jacked up and try and
[40:21]
match color
[40:23]
That it's also going to give the residents good bang for their buck so that we don't have to come back and do come back and do this again
[40:29]
So durability longevity the same I would go with the one that just looks nice
[40:34]
Which for me again is one see
[40:40]
Council members
[40:42]
There's there's a hybrid in between two as Jeff was mentioned. This is just a menu. Yeah, I like what I give you in some street
[40:48]
Brought it's a menu. So, you know this could you go to one B?
[40:55]
I'm sorry, go back to 1C.
[40:58]
Something like this, you could still have the white sidewalk, but have a colored boulevard.
[41:03]
As Nick mentioned, the streetscape committee last week, that area doesn't take a lot of
[41:08]
abuse.
[41:10]
If you needed to inject, instead of just the whites and the grays, you could actually
[41:15]
interject maybe a little different color in the boulevard, so you'd have, maybe it's
[41:20]
a happy medium.
[41:21]
but that would be the probably all if you want the
[41:26]
That the tans in the sidewalk. I think councilman Schultz brought up. It's just your it's
[41:32]
When you start remembering was the city administrator when you start replacing it
[41:36]
It could it'll look a little more different than white concrete. Well, you're gonna have to try and match
[41:41]
So if you want to incorporate some color one area you could it could be a blend between B and C and just
[41:47]
Put it put in the Boulevard area
[41:49]
that won't obviously won't take as much abuse and Nick just reminded me that's
[41:56]
the area he just really broom off to where he doesn't have to get up and
[41:59]
plow at lucky that more heavier equipment on the street and the sidewalks
[42:02]
especially with the purchase of the new blade from last year it's reduced the
[42:08]
impact at the curb and behind for remove off a central significantly I
[42:13]
mean pretty much they don't have to do anything there anymore which that
[42:19]
That's really where a lot of the structural damage came from is scraping everything back
[42:23]
off of there.
[42:24]
So, you know, the other part of it is, is whatever we go through with this, making sure we have
[42:29]
a procedure in place for snow removal along that area that is, this is the way we're going
[42:36]
to do it.
[42:37]
Now Riley's on board and this is where we're going to do it from here until eternity
[42:40]
no matter who is there.
[42:48]
Alstrom, what was your...
[42:52]
I don't have any strong opinions either way.
[42:56]
In terms of color?
[42:58]
In terms of color, I think that maybe the committee should, they're the ones that actually put the work into it.
[43:08]
Well, what I think I'm hearing is, assuming that longevity is all the same and durability is all the same,
[43:15]
that a majority of the council is looking like earth tones is the preferred palette.
[43:19]
So I think we'll move forward with that.
[43:21]
More accommodations are off.
[43:23]
Yeah, I mean, it doesn't have to be exactly this.
[43:25]
Well, we can work with Jeff and Lee to figure out something.
[43:28]
So let me try moving this forward here.
[43:31]
The drive lanes, the standard concrete pavement,
[43:35]
that seems acceptable to everybody.
[43:41]
And then for the parking lanes, we're
[43:47]
showing colored and stamped concrete or colored
[43:49]
and custom scoring.
[43:52]
Is that, obviously, do we want to have
[43:55]
have different color from the dry vials on that?
[43:58]
I think that's a good idea.
[44:00]
Kind of delaying the reference.
[44:01]
Yes.
[44:02]
Yes, but I don't think it needs to be scored like it appears here, like it's small favors.
[44:09]
We can, you know, that's one of the things we can look at, you know, what's the ultimate
[44:14]
financial impact with, you know, the scoring, the tool cutting, saw cutting versus the
[44:18]
stamping?
[44:19]
Let's figure out what that is and then decide, quite frankly, what's the most
[44:23]
economically feasible to put into other elements of this.
[44:26]
That's my preference.
[44:27]
I'm going to put it on the same page.
[44:28]
As you start putting stripes on there and stuff, I mean, if you color and stamp, and
[44:33]
stripes are going to fall off, and have to repaint those over time.
[44:37]
Well, it's one of the reasons that we were looking at this is to do away with the striping,
[44:41]
to create such a visual change that we don't have to paint it anymore.
[44:47]
So, I mean, people aren't going to be able to park wherever they want.
[44:50]
It won't be like ...
[44:51]
Well, there was that.
[44:53]
And that's an aspect that we can put into it.
[44:56]
In there, again, we could actually put in.
[45:00]
Riding lines in that, there's several different ways that we can do it. I don't mean truthfully.
[45:05]
I don't think there's parking lane stripes there now.
[45:07]
There isn't now there?
[45:09]
There's a contrast in the pavers or the banding.
[45:14]
But I don't know that, honestly, I think when we looked at that, we don't believe that was intentional for parking lanes.
[45:20]
Sure people can't see them.
[45:22]
Right. I mean, having a business on Central Avenue seems like it's nice to have striping of some sort in there,
[45:28]
But it's often more of a suggestion rather than anything else. It's quite fun to watch people try to park out there
[45:34]
I can tell you that. All right, let's let's move here to the
[45:39]
The boulevard so right now we have the
[45:43]
Permable pavers in there assuming that a the base isn't really workable would cost far too much to
[45:50]
Replace that do we want to move towards again? Just a can't a concrete
[45:54]
whether that be stamped in some fashion. What coloring are we looking at? Do you
[45:59]
want a different color from the dry vials? What's the thought there?
[46:05]
We're in the middle.
[46:06]
No, in the boulevard. So where the permeable pavers are now. So in this,
[46:11]
the red area in this concept.
[46:19]
I would like the idea that he suggested that we put, you know,
[46:23]
some sample concrete poured at different colors. It costs a little bit, but it would
[46:28]
give us an idea of what this is going to look like.
[46:32]
So go more towards the stamping thing, correct? That's what I'm hearing you say. I agree
[46:38]
with that, too.
[46:38]
But I mean like pour some at the public work so you can see.
[46:42]
Yeah, we'll do that.
[46:43]
I think we'll do that either way.
[46:45]
Everyone else?
[46:46]
That's good.
[46:50]
And then the sidewalk areas, obviously one straight paneled, will match something, we'll
[47:00]
figure out a tone to kind of, that works with the pallet we're thinking of here, okay.
[47:06]
And then anything special for the crosswalks, other than, you know, we already talked about
[47:11]
the activated pedestrian crosswalks, signs and signals, but I'm talking actual pavement.
[47:18]
Some contrasting, some contrasting element in there to really make it set apart.
[47:23]
Yeah.
[47:25]
The picture in 1C has just a different design on it, slightly different coloring.
[47:43]
Good.
[47:44]
I think we're good.
[47:46]
We'll get a new concept developed, and then the idea would be that we'll bring
[47:51]
this forward to another council meeting for kind of final approval of the overall
[47:54]
concept plan.
[47:55]
take that concept plan then start looking at the actual construction component of
[47:59]
this.
[48:09]
My takeaway is that it's a colored, slightly colored, again we'll work with
[48:17]
kind of the tones that you would like to see and we'll try to figure out
[48:22]
that's that's what I'm thinking okay
[48:26]
clear enough for you there's mud okay okay
[48:37]
thank
[48:38]
you thank you thank you all right 4b special assessment policy so for the
[48:47]
last 22 years at least the council has allowed partial prepayments on special
[48:51]
assessments for New Street and alley construction projects Leanne brought this
[48:57]
forward and suggest that, hey, we should probably follow Minnesota State statues when it comes
[49:01]
to this. So 429.061 states that the prepayment of special assessments should be all or nothing.
[49:11]
That information was included in your packet this evening. I don't have anything else to
[49:17]
add to that. It would be a really small change to our policy. You see the highlighted
[49:20]
page number nine there, the partial prepayments and blah, blah, blah, blah. So that would
[49:26]
really be the only change we're looking at.
[49:30]
But I'm just looking for a general
[49:31]
direction if that's something you want to get rid of. Mr. Mayor, Councilmember
[49:36]
Ralu is very patient with me with my emails trying to find any type of wiggle
[49:41]
room in this to allow residents and anybody in Osio to maintain some type
[49:48]
of ability to continue to make partial payments but there there just
[49:51]
really isn't any. And if there really isn't the opportunity to do that
[49:56]
legally, which again, thank you for your patience rally with communication on that.
[50:03]
Then we just have to follow the letter of law and eliminate it, I suppose.
[50:16]
I personally would like to see if we could keep at least within the 30 days a partial
[50:25]
payment.
[50:28]
That gives these people a chance to at least pay down part of it and not have to have
[50:34]
at all on the tax rolls, save them a little interest.
[50:40]
The example that you give here for the 2019 Street Project, well, I think that there was
[50:49]
fault in the staff taking any payments after the first 30 days in that, which you highlight
[50:56]
here as being confusion to the calculating of interest and so forth and so on.
[51:01]
But if at all possible, I'd like to see us to be able to at least take partial payments for the first 30 days.
[51:09]
And this was one of the questions I always had every one of these street projects, exactly when can payments be made?
[51:17]
And it has always been a question as to how that's identified.
[51:24]
and this is now is saying that those payments are to be 30 days from the
[51:30]
time the assessment I think is determined as I followed this through but if it's
[51:38]
against the law and there's a legal problem with it then we probably can't
[51:42]
do that but I'd like to see a lot of partial within that 30 day period
[51:51]
Minnesota Statute 429.061 states that the property owner has the right to pay for the
[52:00]
pay the whole of the assessment on such property with interest accrued to the date of payment.
[52:05]
So that's, you know, we've been forever and a day now been allowing partial prepayments
[52:11]
probably against what Minnesota Statutes suggests that we do.
[52:16]
And so to Leanne and Leanne's point, her suggestion is we should really be following what the
[52:22]
statute says.
[52:25]
Absolutely.
[52:28]
Mayor and council, and I don't want to throw a monkey wrench into this.
[52:32]
I think that under state statute, there's an option to do some partial pre-payments
[52:40]
by ordinance rather than policy.
[52:43]
policy. I think the frustration with this has been more of a practical one that it causes
[52:48]
confusion with how the interest payments are calculated.
[52:54]
So we can, I think there is, and I'll have to, I'll double check it prior to the regular
[53:01]
meeting but I do think that there's some language that we can allow it by ordinance
[53:05]
but not policy. So that's just a little sort of clarification but I'll confirm
[53:11]
that and double-check the statute. That's for 29.061. Subsection 3. Yeah I
[53:19]
don't remember the subdivision off the top of my head. The council may authorize
[53:23]
by ordinance partial payments of assessments prior to certification to
[53:26]
the county auditor. Correct that's it. I'd like to discuss that a little further
[53:31]
about tonight at a different work session. That and but to follow up to
[53:36]
Riley's point there may be reasons to just take it out other practical reasons
[53:43]
and I know that the city clerk has had some ongoing issues with this over the
[53:47]
years and it did raise some confusion and problems last year when when we
[53:53]
encountered this issue so there may be other reasons to take out of the
[53:56]
policy all together yeah so I agree I agree with that but I just wanted to
[54:00]
make that clarification I think we need to get some more clarity on some of
[54:05]
points okay
[54:10]
so so will this be at the regular council meeting no not tonight
[54:16]
no no this wasn't planned to be at the next at this meeting is that going to
[54:22]
give us time to have it on this current street project I believe the
[54:27]
assessments are in April so yeah we have I mean we can we can try to get taken
[54:32]
care of in March happen thank you yeah I look for a motion for adjournment second
[54:43]
motion by councilmember Schultz second by councilmember Stelmack not
[54:47]
unavailable all those favor hi hi all those post we're adjourned at six fifty
[54:52]
Thank you.