[0:03]
regular meeting of February 8th at 8:00
we are in session. I don't see anybody
[0:08]
here for public comments. We'll move
into the minutes of January 28th.
[0:15]
» All good. I'll make a motion.
>> I have a motion.
[0:19]
» Second
>> and a second.
[0:21]
Any discussion on the minutes?
Hearing none. All those in favor?
[0:27]
» Opposed? Motion carried.
Moving on to the financial statements.
[0:33]
Anything uh to highlight there, Kyra?
[0:38]
» Um I don't believe so. I did just get
one more bill in this morning if we want
[0:44]
to add that uh for Kennedy Electric in
the amount of $1,29848.
[0:52]
And I'm assuming that 11,000 something
to Shannon's was for them to fix that
[0:57]
correct sewer system.
[1:06]
» I still stand with the motion.
>> Yeah, we have a motion to approve the
[1:09]
financials.
>> A second.
[1:12]
» And we have a second
>> to include the Kennedy
[1:14]
» to include the additional
>> Yep. Okay.
[1:18]
» Okay.
>> Any more discussion hearing? None. All
[1:22]
those in favor?
>> I
[1:24]
» opposed. Financials are carried.
>> Engineers report. You're up. Chelsea,
[1:30]
» good morning everyone. How are you doing
today?
[1:33]
» Good.
>> Good morning, Chelsea.
[1:35]
» Good. I got sunburned yesterday down
here in Texas. So,
[1:41]
» throw that in there. There's [laughter]
a blizzard here.
[1:45]
» Yeah. Oh, big time. Yeah.
>> Sorry about that. [laughter]
[1:50]
She looks so
[1:54]
[snorts]
>> All right. Well, we'll get started.
[1:56]
We'll start with the transient hanger.
Um, so the grant we have a grant request
[2:04]
letter uh that Bindot is asking for. So
this is a the heating component is not
[2:10]
federally eligible with the IGA funding.
So the heating and insulation we are
[2:17]
asking the state to uh uh look into that
and and support that part of the
[2:23]
transient hanger. Obviously up there you
want heating and insulation because it
[2:28]
is cold. So we have a uh grant request
letter that we're submitting to the
[2:33]
state that Brian has to sign. I don't
know if we have to have approval for
[2:36]
that, but it essentially is um we'll
submit to them and hope that they
[2:41]
respond that they will support the
heating and insulation of the transient
[2:45]
hanger.
>> Okay.
[2:48]
» Do we need approval for that?
>> I think they approved it last month to
[2:52]
for for a letter.
>> Yeah, I thought we were good with that.
[2:56]
» Okay. All right. It sounds good.
>> That's not the one I signed yesterday,
[3:00]
is it?
No, that was uh that was the FAA
[3:03]
provisions that were including the
complex. So, I will send this one to
[3:07]
Brian. I have it prepared um for
signature and we'll get that sent to the
[3:11]
state. Um as far as schedule goes for
that one, uh we'll have 60% plans in
[3:18]
mid-March for it. Uh we have been
meeting with Dora's team uh to do a
[3:22]
little bit of, you know, design and
figure out some of the areas and things
[3:26]
that are in the way and uh trying to
work through that. And we're also
[3:30]
working through the size of the building
um and working with the building
[3:35]
inspector on that.
>> Thor is that
[3:40]
» excuse me. Is that why they were had did
checking the ground?
[3:44]
» Correct. Yeah. Doing the borings with
Okay.
[3:49]
» See how the boring
>> the borings were completed and the
[3:52]
survey.
>> Okay. Good.
[3:53]
» Green County need a permit for that to
build that
[3:57]
» building permit. I think we're working
on that with the building inspector
[4:00]
right now. Yeah.
>> Yeah. Yeah. Eventually this um so we're
[4:03]
just in preliminary like we're just in
design right now. So the 60% plans will
[4:07]
be completed by mid-March and 90% will
be made. Uh the construction for this
[4:12]
project is not until spring of 2027.
>> Yeah. See
[4:18]
» very good.
>> Any questions on the transient hanger?
[4:23]
» No.
Uh, I have no updates for the GA apron
[4:27]
reconstruction and runway 422 project
that we are just waiting on that spring
[4:32]
warranty inspection. So, we'll have an
inspection with KGM in the spring and
[4:36]
then we'll pay that uh final retainage
to them uh and hopefully close that
[4:41]
project out early spring.
[4:47]
For equipment acquisition, we have been
pushing on the the ramp plow. Uh and it
[4:54]
does appear that they have given us a
date of mid-March now. So first it was
[5:01]
» you might get to use
>> might. Yeah.
[5:04]
» Big big might. [laughter]
>> Big might. Yeah.
[5:09]
» Um I don't know if you have any other
updates on that, Thor.
[5:12]
» No, that's it. Uh yeah, that and that
and um uh and and we still haven't
[5:17]
received our pickup yet, which was
supposed to be um yesterday, I think,
[5:21]
and then they changed. They were
concerned about the storm, and I said,
[5:24]
"It's 100 miles. It's him being boys." I
said, "Drive and drive back." So, we
[5:27]
we'll see.
We're hoping. Yeah.
[5:31]
» There you go.
>> Yeah. And on the um on the pickup truck,
[5:35]
so I did not include a pay application
for that, but I was hoping that we could
[5:39]
get that approved today. Um that would
so that one was funded uh supported by
[5:45]
MIDOT. It's a MDOT state grant request.
Uh so they you would have a 30% share of
[5:51]
that. Um the total for it is
uh $70,9046.
[6:01]
That would be the total pay application
amount.
[6:07]
» So do we have a motion for that?
I'll make that motion.
[6:12]
» We have a motion. Is there a second? And
a second
[6:15]
» for the 71,000 with the 30% match from
city county.
[6:23]
Any discussion?
All in favor?
[6:27]
» I
>> opposed. All right.
[6:31]
» On that,
>> if I may. Yeah, it's it's it's
[6:35]
» we need it yesterday cuz the one we're
running right now we're
[6:39]
» it's done. [laughter]
>> It's been used. Yes, we're I'm happy to
[6:43]
say that.
>> Say again.
[6:47]
» I didn't say that. [laughter]
>> And it is painted yellow.
[6:51]
» Yes, true.
[6:54]
» Moving right along, Chelsea.
>> Yeah. So, with that, thank you for that.
[6:58]
Um, I'll get that pay application pulled
together for Brian's signature and we'll
[7:01]
get that sent to um Bob at and get him
get him on so we can get the truck as
[7:06]
quickly as possible. That does include
um radios that is was considered
[7:12]
eligible and quite a few other things
that we fought uh the state for. Um but
[7:17]
the one thing that they did not consider
um state eligible was a remote start and
[7:22]
additional fog for $752. So that portion
of that 70,000 is locally funded by
[7:28]
itself. Just throwing that out there.
[laughter]
[7:32]
Not sure why, but got to deal with it.
[7:38]
All right. Any questions on any of the
equipment acquisitions?
[7:45]
Electric uh gate, the automatic gate
installation. So we are working on a
[7:50]
design for that project. that 90% review
will be planned for March. The uh
[7:56]
essentially this is the two gates that
uh were um in the part 139 inspection
[8:02]
that were flagged uh as not being
adequate or to their standard. So, we're
[8:08]
we're planning on putting in two
vertical lift gates. Um so, there will
[8:12]
be no no rolling mechanisms, but it
there'll be the vertical lift gates and
[8:16]
that'll be at the Crescent Drive
entrance and right by Thor's. So, we're
[8:20]
working with Thor's team on kind of some
of the design elements for that and he's
[8:24]
provided us some measurements. Thank
you, Thor. And, uh, we also are working
[8:29]
with the part 139 inspector to
determine, you know, what the heights
[8:32]
requirements are for the 1x4s and and
things like that. So, any questions with
[8:38]
that?
>> Nope.
[8:41]
» That construction will be planned this
summer.
[8:43]
» Perfect.
>> We also have a beacon replacement
[8:46]
project that uh we've been working with
team on. Uh the decide is underway for
[8:50]
that same schedule as the electric gate.
We'll have a 90% review discussion in in
[8:54]
March. Um and that's to replace the
beacon that is out there now to one of
[8:58]
those tip down ones. So we don't have to
climb up and replace the bulb. It tips
[9:02]
down. It's it's kind of a nice setup. So
that'll replace the foundation
[9:08]
» the new beacon.
>> Nice.
[9:10]
» It'll be it'll be a good act. So
that construction is also in summer of
[9:15]
26. So any questions on that?
>> Nope.
[9:20]
All right. Uh, runway 1331
reconstruction phase 4. So, I think at
[9:25]
the last meeting we did talk about how
this project uh with the reimburseable
[9:31]
agreements that it kind of pushes things
out. So, it will be constructed either
[9:37]
2027 or 28 um with it bidding next
spring. Um, so we did have an FAA
[9:44]
discovery meeting for that they and had
a discussion, you know, on how the
[9:49]
resident engineer, which is something
that the FAA provides when there's FAA
[9:53]
equipment located in the area during
construction, they have to have someone
[9:57]
on site. We saw this during phase uh two
and three of uh the runway projects. So,
[10:03]
they have to have someone on site to
observe the construction around their
[10:06]
equipment. Um, so we did have a
discussion with them and we're planning
[10:10]
for a 10day
uh resident engineer on site. So that
[10:14]
would be around those malls and bars,
the papy um and anything that is, you
[10:21]
know, their equipment in that area. But
we'll plan to do all of the construction
[10:25]
around their equipment uh during 10
days. So that's kind of the plan for
[10:29]
that. We did have that meeting and there
is some grading corrections that need to
[10:34]
happen in the ILS critical area. Uh so
that would then generate another flight
[10:40]
check. So from that meeting, that's kind
of what came from that. There was one
[10:44]
other thing. They do want us to correct
the grading past the blast pad on the
[10:50]
runway 13 end. So that's the end that we
did during phase one. So all of that
[10:56]
pavement has been redone, but we did not
go past um the blast pad and do any
[11:01]
correct corrective grading at that time.
So from this uh last meeting with the
[11:06]
FAA, they have requested that we include
that grading to correct it to RSA FAA
[11:12]
standards in that last 1,000 ft um pass
for the runway end. So that will also be
[11:18]
included in this project. Now
[clears throat]
[11:21]
any [snorts] questions on any of that?
>> Lots of information.
[11:28]
» Well done. Um for the state projects,
the terminal improvements have all been
[11:33]
completed. That was the security
upgrades uh that uh Brothers Fire and
[11:39]
Security did.
>> So to my knowledge, it's all been
[11:42]
completed. Have you Has everything been
working well?
[11:44]
» Yeah, that's correct. Yeah, we're in the
process as we speak learning the new the
[11:49]
new camera systems, but yeah, we're
getting there. It's I mean the cameras
[11:52]
are the same. It's just the software is
funky.
[11:56]
» Okay, sounds good. Um, so that has a pay
application that I believe that you
[12:02]
approved in the financials, but that
that was for an amount of 60,381
[12:08]
and that's at that 70% 30% split from
the state.
[12:17]
Um, for COP updates, uh, we've gone
through those quite a bit, but the one
[12:22]
that is coming up, when did you say that
ASOS was going to be installed?
[12:26]
» Yeah. Uh we're anticipating starting the
project in June.
[12:31]
» Okay, great. So I think we'll there is
some uh obstruction removal with that
[12:37]
new ASOS location. With the new one,
it'll be it'll be limited. It's a lot
[12:42]
less than where it is now. Um but we
will uh prepare a proposal uh in the
[12:47]
next couple meetings for that project so
that we can get that obstruction removal
[12:51]
completed for that ASOS to work
properly. [clears throat]
[12:57]
Okay.
>> And then uh any upcoming meeting dates?
[13:00]
We have a mindot FAA coordination
meeting on March 12th. That's our next
[13:05]
meeting with the FAA. Uh so feel free to
join if you'd like.
[13:11]
» Very good.
>> Any any questions for me?
[13:15]
» No.
>> All right. That is all I have this
[13:19]
morning.
>> Very good. Thank you. Thank you,
[13:21]
Chelsea.
Take care of that sunburn.
[13:25]
» Yeah, [laughter]
>> but keep the smile you have there. Keep
[13:30]
the smile.
>> You got to keep that smile though.
[13:32]
» There you go.
[cough]
[13:38]
» Old business.
[13:42]
» Entrance sign looks. It's done. Uh,
credit to Mr. Matar with the beautiful
[13:48]
new lettering there. It's a It's a
greater It's a better contrast
[13:51]
particularly at night. It looks better
at night. It's very reflective. Yeah,
[13:54]
we'll we'll do the the uh landscaping
obviously when the when the when the
[13:58]
frost goes away. So, we'll be back on
target.
[14:00]
» Plant those thistles back in there
again. [laughter]
[14:04]
» Only if you're going to pluck them.
>> I can I always thought about the person
[14:07]
who designed it. Why would you put
those? Yeah, exactly. Keep the kids out
[14:11]
of the way.
[14:18]
New business title six resolution
approval. Do you have that in the packet
[14:26]
somewhere?
That's just something FA is requiring of
[14:31]
us. Correct.
>> Yes, it is. Um I had to complete a
[14:34]
survey and in the survey I checked one
of the boxes incorrectly. So this is the
[14:39]
result of that.
I guess I wouldn't say it incorrectly,
[14:43]
but [laughter]
>> I checked that it we did not have this
[14:48]
in place. So, um I had to create a
>> plan and put together a number of
[14:56]
different documents to go along with
this. Um and then I've got a sheet that
[15:03]
will be posted in the the hallway that
just kind of explains non-discriminatory
[15:09]
stuff. So,
Just one of the boxes that we got to
[15:13]
check. So
>> that's right.
[15:15]
» Good job, Kyra. She's being kind. I
better reflect to you.
[15:19]
» Very good.
>> Mhm.
[15:20]
» Is there a motion to approve it?
>> I so move.
[15:22]
» We have a motion. Is there a second and
a second to approve the title six? Any
[15:27]
discussion?
Hearing none. All in favor?
[15:30]
» I opposed.
>> That motion's approved.
[15:37]
Manager's report.
>> Yeah. quick uh you Chelsea and Kyra
[15:41]
covered most of most of my agenda. Yeah.
One thing that she mentioned about the
[15:46]
new ASOS system can't happen early
enough. We were down again last week and
[15:50]
and uh what happens is that the current
system fails and without you have to
[15:54]
have a certified weather observer to to
provide information to the airline
[15:57]
whether the party Minneapolis or even if
they're on the ground here and it's just
[16:01]
totally crazy. can be crystal clear day
as it was in perfect conditions, but by
[16:06]
legal definition, the pilot, the captain
can't walk on the wrap and go, "Yeah,
[16:09]
the weather's good." They need a report.
So, it just adds another step and it's
[16:12]
not always delicate. So, that that's a
really good great project. All these
[16:16]
parts are great, but that one is really
essential. So, we're looking forward to
[16:19]
that.
>> Um, yeah, just going along. Projects are
[16:23]
going along well. Very thankful that the
that the weather forecast was off
[16:28]
currently in Seattle, so it's good.
They're normally inaccurate with the
[16:32]
amounts on on on the higher higher
higher rates, but this time we're on the
[16:37]
low rate. Been looking at that low
pressure coming across. I think we're
[16:40]
we're in much better shape than they
predicted us to be and we'll have a
[16:43]
little bit of wind issue, but we're good
and keep pushing. Thank you.
[16:46]
» All right. Super, super. Thank you.
>> New DI truck.
[16:50]
» Yeah. today conference call with the
with the team and I'm going to put this
[16:55]
put the uh I'm going to put uh shall we
say a little more heat under him today
[16:59]
and we'll we'll get it done.
>> Yeah, I'm done messing. I'm probably
[17:03]
rephrase that.
>> Yeah,
[17:05]
» today's the day. Yeah. Yeah, we'll go
with that.
[17:08]
» Whatever.
>> We may have to do a rough thing again.
[17:10]
What? Okay. I'm not sure why that takes
that, but who knows?
[17:15]
» I personally like to open buckets. So,
>> me too. Anyway,
[17:21]
» we'll light them up.
>> It's just the fact that it's a brand new
[17:25]
truck.
>> Oh, it's absurd. And Biji's having the
[17:28]
exact same issue. Identical.
>> Yeah.
[17:31]
» Yep.
>> Send [snorts] them over.
[17:33]
» Yeah.
>> Yeah. Right on.
[17:36]
» Yeah. They they haven't quite got
clarity. I'm hoping today they get
[17:39]
clarity.
>> Okay.
[17:40]
» And I don't like doing that. I really
don't. I But yeah, it's the way you
[17:43]
need.
>> They'll get it fixed. We'll be
[17:45]
» right.
>> Start it for next season.
[17:47]
» Yeah. It makes it difficult when you
talk to people and they make promises
[17:51]
and you and you keep giving them a
chance and you want to work with them
[17:54]
and you try and then
>> that means our warranty doesn't start
[17:58]
till next year, right?
>> That is correct.
[18:00]
» Right on.
>> Yeah. So, we'll make double sure we're
[18:03]
in that window, but
>> yeah, we're we're going to get really
[18:06]
active here. So,
>> Okay. Thanks.
[18:08]
» Thank you, Tara. What do you have for
us?
[18:12]
» Uh employments are in the packets. Uh we
were up again last month over last year
[18:18]
which is yet another good sign that each
year they continue to
[18:22]
» increase
>> increase.
[18:23]
» There's been quite a few car testers
>> definitely
[18:27]
» more than usual coming.
>> Yeah.
[18:29]
» Mhm.
>> Which is which is good.
[18:33]
» Excuse me.
Um, and then the only other thing I have
[18:37]
in the packets is uh an email from Betty
of the city in regards to um
[18:46]
the legislation and land use committee
uh who is requesting a meeting with the
[18:51]
airport commission members to discuss
annexation of the airport property that
[18:56]
is not within city limits. Uh, the
requested meeting
[19:03]
would be Monday, March 2nd at 400 p.m.
it looks like.
[19:12]
» Put that on your calendar.
>> No,
[19:17]
» I'll be out of town for that. But I
>> I'll be here.
[19:20]
» But I've expressed my
>> Okay. thoughts on it. So far as you
[19:24]
know,
>> I don't see any reason not to.
[19:28]
» Makes sense to do it,
>> right?
[19:30]
» You know, to help get water to our
hangers, right?
[19:33]
» Those kind of things.
>> Yeah.
[19:37]
» Yeah. We've proved it before here at
this.
[19:40]
» Yes, we have.
>> Stable.
[19:41]
» Yeah.
>> The goal.
[19:44]
» So hopefully it moves forward. So yeah,
good.
[19:50]
» Anything else, Kyra?
[19:54]
Nope.
>> Any other business
[19:59]
other than next meeting date?
[20:08]
» Getting better. Well,
[20:13]
» uh,
looks like the last Wednesday would be
[20:18]
March 20th.
[20:23]
March what?
>> 25th.
[20:25]
» 25th.
>> Five or six. 25 26.
[20:29]
» 25 is a Wednesday.
>> Thank you.
[20:36]
» How does that look for them?
>> Will that work, Charles, for your team?
[20:40]
March 25 at 8 a.m.
>> It does. Yep.
[20:43]
» Thank you.
>> All right. I [clears throat] got it my
[20:48]
calendar.
There's nothing else to come before us,
[20:51]
so I'll adjourn the meeting. Thank you
every