Roll call, please.
[3:28]
Let the record reflect that a quorum on members is present, commissioner Metzger and commissioner Stein absent.
[3:34]
All right. Follow me again. Pledge of Allegiance, please.
[3:45]
For which it stands, one nation under God, indivisible with liberty and justice for all.
[3:52]
Thank you.
[3:57]
Oral communications. Are there any members of the public who wish to speak on non-agenda items today?
[4:03]
Seeing
[4:06]
none,
[4:09]
can we get approval of the minutes of the regular meeting of June 9th, 2026?
[4:16]
I'm
[4:20]
sorry, I don't have my glasses.
[4:21]
We'll put them on.
[4:23]
We move through the minutes of the regular meeting of June 9th, 2026.
[4:29]
I'll second that.
[4:34]
And I neglected to mention today's date.
[4:37]
I apologize.
[4:38]
Today is Tuesday, July 14th, 2026.
[4:41]
6. Moving on, do we have any department reports?
[4:48]
Oh, I'm sorry. Take a vote on the motion.
[4:56]
You can still vote so long as you're comfortable voting if yes.
[5:05]
Motion carries. All present voting aye.
[5:08]
Thank you. The next item is department reports.
[5:14]
Staff has no update today. Thank you.
[5:20]
Check that general
[5:24]
business review the three accessory dwelling unit floor plans and designs
[5:30]
for the city's pre-approved accessory dwelling unit program.
[5:35]
Is there a staff presentation please?
[5:37]
There is.
[5:38]
Thank you, Mr. Chair.
[5:40]
So as part of the 2024 housing element update, the city set forth certain policies and
[5:45]
goals that they're going to follow through within that element update cycle.
[5:50]
So one of those is to create pre-approved ADU plans that can be used by any applicant
[5:55]
in the city.
[5:56]
The idea is to have the review process be more streamlined and more cost effective.
[6:00]
So they'll have to look at certain site plan, things that are specific to the site obviously,
[6:05]
but as far as engineering and construction, they'll all be standardized.
[6:10]
So in early 2025, we put out an RFP to find a firm that can help us put together
[6:16]
those designs.
[6:16]
we ended up with our M design group who's been working with us since then which
[6:21]
has been a great process creating three specific layouts that can be used and
[6:26]
then also three architectural designs that can be mixed into those. So there's
[6:30]
different combinations that can be used for those pre-approved designs. We went
[6:34]
through and looked at a lot of different sites and Randy will walk you
[6:36]
through sort of our thought process around both the designs and then
[6:41]
and also the sizes that we landed on.
[6:44]
So I'll kick it to him and we'll work through these.
[6:47]
Happy to answer any questions as we go through this.
[6:51]
Yeah, thank you.
[6:53]
Thanks Randy.
[6:54]
I'm
[7:01]
Randy Bressen with our design group.
[7:03]
You'll forgive my coughing and hopefully I had the pleasure
[7:05]
of my granddaughter being out from Colorado last weekend
[7:08]
and she passed along summer cold to me.
[7:11]
So hopefully you can bear with me.
[7:14]
Thank you for letting me make this presentation
[7:17]
and sharing our program with you.
[7:22]
Kurt, could we sort of start with our process document?
[7:24]
Is that what we have up here?
[7:31]
So we don't pull these things out of the air.
[7:34]
We try to go through some process
[7:35]
that customizes the solution to your city.
[7:39]
I've done these in probably 40 jurisdictions
[7:41]
throughout the state.
[7:43]
And what we typically will do is working with staff,
[7:46]
we're gonna take a look at your architectural styles.
[7:49]
We're going to look at your, I would like to call them opportunities, basically your
[7:55]
lot stock, see what we can fit in there because it's often an RFP may have three different
[8:00]
sizes that have nothing to do with what really we can put on a site.
[8:03]
So we like to back check that.
[8:05]
And then we check things like what ADUs have already been permitted and built around
[8:11]
here.
[8:12]
Best example of what people want to build is what they've already done.
[8:14]
So we sort of use this process.
[8:16]
This is the document where we produce a context study.
[8:18]
And, Kirk, if you just want to step through, I'll speak to it really briefly here.
[8:23]
We picked out, we looked here, someone in Mac picked out different areas that had slightly
[8:32]
different minimal lot sizes and configurations.
[8:36]
These are essentially, we're calling them typical examples.
[8:40]
I don't know if anything here is typical, to be honest with you, but it was our
[8:43]
best shot at this.
[8:44]
From this, we started identifying these, you know, here's your lot configurations
[8:49]
And the areas that might be available for putting ADUs on, which starts speaking to
[8:54]
length and width of them or configuration, sometimes we might find ones that really need
[9:00]
a very skinny design that's only 40 feet wide for a 50-foot lot.
[9:06]
Sometimes L-shaped ones, it can vary with different cities.
[9:09]
This is a process we used with yours.
[9:11]
We went through and test fit those along with parking, I think.
[9:14]
Did we have some of those on here?
[9:16]
I'm not sure if we have that in this selection.
[9:19]
Parking.
[9:19]
Yeah, we did.
[9:20]
It's kind of hard to see on here, but we also even tried to identify how we're going to
[9:24]
deal with parking because you do have a requirement for that here, which is kind of unique for
[9:28]
your city.
[9:30]
From that, we also kind of go around the community and identify styles, which is
[9:35]
what the next section is here.
[9:37]
You live here.
[9:38]
I don't have to belabor this, but this is our process we go through to say what
[9:42]
would be appropriate.
[9:44]
A lot of this comes out of the RFP, but also we test this sometimes.
[9:46]
I've had communities that didn't know that they had about 15-20% of their buildings were
[9:52]
tutor style and they were all surprised by it.
[9:55]
We didn't do it but they were surprised at how prevalent that was.
[9:58]
Anyway, we want to go through that so we make a good fit.
[10:01]
Now we can bring up the, this is my clicker here, bring up the other presentation.
[10:05]
So from that process we end up, we started probably with 12 different examples to identify
[10:15]
by what the values were, what the characteristics were for your ADUs that would be right for
[10:22]
your city. I have communities where bedrooms are everything. How many bedrooms can we squeeze
[10:28]
in this? And I'll tell you, I have a three-bedroom, 750 square foot design. As tight as that seems
[10:33]
that is valuable in certain communities. That is not what your communities look like.
[10:37]
It was exactly the opposite of that. It was these things are used, are going to be
[10:41]
used not only as ADUs, but they're going to be used as granites. They're going
[10:44]
uses guest houses for people and so we need to build flexibility into him and build a level
[10:50]
of character like volume ceilings and things like that are consistent with the community.
[10:59]
Nobody really cared that we had lots of washer and dryer space, that was not what this was
[11:03]
going to be about.
[11:04]
So it was a little bit different for us but it was great to hear we talked to
[11:07]
a few locals, a builder, maybe two builders, that's all that showed up for our attempt
[11:13]
to talk to people but we do get some feedback and they had some great input on on some of this stuff.
[11:18]
Anyway, we ended up with these three different plans. It was the smallest of them right around 400
[11:24]
square feet.
[11:27]
You'll notice that this has a very, this is what we call an efficiency kitchen. It's
[11:33]
about a smaller kitchen as you can do in something. In fact, we even considered the
[11:37]
washer and dryer being those single unit under cabinet styles. This could be configured as a
[11:43]
one bedroom or as a studio so that whole space could be open. We put those walls in optionally
[11:50]
as well as the closet there. The way we structure these things allows for a lot of flexibility.
[11:59]
We do have engineered structure. It's not just right out of the code so it allows
[12:04]
us to design for a lot of flexibility. Any of these openings could be changed into
[12:11]
slider. If you had a five-foot opening for a bedroom window, you wanted to have it open
[12:16]
to a patio, drop a slider in there if we don't have a problem with that. We'll do the title
[12:20]
24 energy compliance to account for worst case scenarios. So we try to build flexibility
[12:25]
into these. I think it's something I really want to let you guys know that's what's
[12:30]
going on here. We also generate these in the three different styles. Kind of a coastal
[12:37]
cottage style,
[12:41]
a Mediterranean influenced, fits in anywhere in California, and then a little more
[12:49]
uniquely to you guys is a contemporary modern style. You'll notice as we go through each of these
[12:57]
plans, they will all have those same styles replicated, and I want to
[13:04]
to assure you these are intended to be representative of what can be done. Our goal
[13:08]
is to have something that's wood-sided. If it's at a house, if it's a shingle house
[13:14]
and a shingle and horizontal siding, you don't need to use our board and bat one, but you've
[13:19]
used the mass in the form that matches that cottage style and then apply the colors and
[13:25]
materials that would be in the primary residence. Same with the Mediterranean, that's representative.
[13:32]
You don't have a tile band.
[13:34]
You have another band on there.
[13:35]
Your windows are, you know, I don't know.
[13:40]
Maybe they're a brown versus a black iron window.
[13:45]
That all works.
[13:46]
These are intended to be flexible in that manner.
[13:49]
But from a baseline, we have a contemporary form,
[13:54]
a form that'll go well with the meta-training
[13:57]
can be finished that way,
[13:58]
a form that goes well with a cottage coastal cottage look. We'll take you
[14:03]
through these last couple here. Again this is built-in flexibility a little bit
[14:07]
bigger not a lot bigger we had you know small lots small opportunities this one
[14:12]
has can be done as a one-bedroom or as a studio and again you start seeing these
[14:20]
how they manifest themselves architecturally in the coastal cottage
[14:26]
in Mediterranean and again the contemporary and finally got a little bit
[14:33]
bigger one not huge under 700 square feet designed to be a one bedroom or a two
[14:39]
bedroom really flexible space a little bit bigger kitchen a little more
[14:45]
articulation a little more interesting in a backyard but also takes up a little
[14:49]
more depth so it might not be a be applicable to too many lots but it but
[14:53]
But you'll notice this one again.
[14:55]
This is 42 feet long, fit in a 50-foot lock with the state-limited...
[15:00]
Four foot side yard setbacks.
[15:02]
Those are some of the parameters we try to design to when we do this.
[15:06]
And then, again, this is how it starts to play itself out.
[15:10]
If the primary house doesn't have stone base columns,
[15:14]
I wouldn't expect someone to build it here.
[15:16]
We try to build that flexibility in there.
[15:19]
Our plans are not going to show every single option
[15:21]
that these can be conceived as.
[15:23]
We'll indicate that these are optional things
[15:26]
and then they can build them out as needed.
[15:29]
Some of that flexibility also comes from how your building department wants to deal with
[15:34]
them.
[15:35]
I will tell you that from my perspective, I don't care what order your appliances are
[15:42]
in your kitchen.
[15:43]
I don't really care that that's the kitchen wall, to be honest with you.
[15:46]
That's not a big thing for my architectural integrity.
[15:51]
And many jurisdictions, as long as you meet the code, you know, where the GFIs
[15:57]
are what the spacing is, some of that, you know, that basic stuff, minimal amount of
[16:00]
countertop, all these code minimums, they're perfectly fine with it. Other jurisdictions
[16:06]
want to be very strict, so nope, what you see is what you get. That's up for you guys
[16:10]
to deal with internally. For me, you're not stepping on my toes when people move those
[16:15]
things around.
[16:17]
Anyway, I think that really kind of covers the package we have here. I really came
[16:23]
down to introduce you to this and answer your questions along the way.
[16:34]
Can I jump in to clarify some of that real quick?
[16:37]
Thanks.
[16:38]
Yeah, thanks Randy for all of that and walking us through and then especially around the options.
[16:42]
I think especially with external materials that will be really easy from talking to
[16:47]
Damon our building official about you know what he's going to look for if it's what
[16:52]
type of shingled siding versus a hardy plank siding it's not really going to be an
[16:56]
issue and same on planning's end.
[16:58]
As far as where appliances go and things like that,
[17:00]
it may end up triggering more of a review, which then sort of
[17:03]
puts in a different process, where it's not
[17:06]
going to be as streamlined.
[17:07]
But it is totally possible.
[17:09]
So any changes can be made.
[17:10]
They can use this as a template and make all sorts of
[17:13]
changes if they want to.
[17:14]
But then it is going to have to go through our review
[17:17]
process, because we have to make sure that it meets
[17:20]
code.
[17:21]
The purpose of this would be to say, well, this already
[17:23]
does meet code does not need that review so does that kind of make sense there's
[17:27]
sort of two ways you can do it you can make the very simple changes of like
[17:33]
exterior stuff but then once you start altering it it's possible but then we
[17:37]
will have to review it to ensure that it does meet code since the changes
[17:40]
were made. For our perspective you know our our relationship with the city and
[17:44]
the project ends when we get these things approved and so all those types
[17:48]
of variability I like to build in up front as much as possible so if
[17:52]
There's input on what can you do.
[17:54]
And maybe you have suggestions of what you'd like to see
[17:56]
that then we then run past the building official
[17:58]
is how do we approach this?
[18:00]
This is something you can manage.
[18:02]
And we build those into the plan.
[18:03]
So there isn't another loop for anybody
[18:06]
going through the process.
[18:08]
There are whatever it be, 10 different options
[18:11]
that they can work with and create some flexibility under.
[18:15]
That's our goal, anyway.
[18:20]
Any questions?
[18:22]
I have many.
[18:24]
Excellent presentation, thank you. When you said we can do, you know, whatever you want
[18:32]
to do you can do, specifically let's just use electrical as an example. So as this goes
[18:39]
forward I'm assuming that your firm is going to do the engineering, do the structural engineering
[18:45]
on these prototypes, correct, whereupon you would also be doing an electrical base,
[18:53]
you know, electrical plan that passes through code, exactly. So if somebody
[18:59]
wanted to add something, you know, some more lights or some fans or more outlets
[19:06]
or something like that, how, how do you see, and this question may be directed
[19:11]
for Coronado Planning Department,
[19:16]
how would someone move forward
[19:19]
if they wanted to add some of the electrical?
[19:24]
Yeah, a lot of it will depend.
[19:26]
So as they prepare those, we're going to work,
[19:29]
obviously we're gonna have them approved
[19:31]
through ESGIL and then also through
[19:34]
the building department here.
[19:36]
And so I think we're gonna learn those limits
[19:37]
a little bit more as we go through that process,
[19:40]
like it doesn't outlet trigger more review does anything I mean at some point it does require at
[19:47]
least a little bit more review because we have to determine whether it needs review or not you know
[19:51]
what I mean so it does add one layer how far does that go I think it really does just depend on
[19:57]
how big of a change it is so we're going to sort of learn those limits and Randy probably
[20:01]
has experience working with other cities and knows those a bit but for us as we get those
[20:06]
construction drawings, we'll know more about what's going to trigger that. I know
[20:11]
that's kind of a bogus answer, but... No, that's a good answer. Well, to your
[20:15]
question, Dana, then something like an EV charger or something would throw that
[20:23]
off. I'm sorry. Like an EV charger, like for a Tesla or a charger, so it needs
[20:30]
a particular outlet and everything to do that with that. Well, there are no
[20:35]
garages for you know for you could still know but it doesn't have to have a
[20:39]
garage yeah that's a great that's a great example how would you manage that
[20:46]
well something like probably it's laid out in infrastructure it's not a
[20:50]
requirement you're not required to supply as you would on a new home you're
[20:56]
required to provide those you know PV for for a car so there I mean that
[21:03]
would be, when you said be flexible, I build houses. There are just so many factors that
[21:13]
could play in. I'm just curious how this falls into, or is this meeting, is this unimportant
[21:21]
for this meeting to okay these design, these prototypes too? Am I going further than I
[21:30]
need to be going by asking these questions?
[21:32]
staff here but I will speak for where I'm coming from. We are on our way to putting the permit sets
[21:38]
together and at this point I'm looking for feedback from the city for these types of things. We want
[21:46]
to see this and maybe not everything can be flexible. That's obvious and we'll go through a
[21:52]
process with your building official or your building department to try to find their boundaries
[21:57]
of comfort on some of these things and that's really what drives most of that flexibility.
[22:01]
When you start talking about outlets, you know, like I've said, I've also been building for
[22:07]
30 years, do my own stuff, and I've never had anyone raise a finger when I added an outlet
[22:13]
in a wall somewhere.
[22:15]
Well, you don't have the corn out of building inspectors coming to your job, just letting
[22:20]
you know.
[22:22]
That's another factor.
[22:23]
That's a layer that's going to have to follow this whole process, and the man in
[22:28]
charges right here? Flexibility. Their operation is what's going to decide how
[22:32]
that works. Yeah and as Randy's saying you know we're gonna work with them
[22:35]
through this process and that's kind of the that is the next step is to see you
[22:39]
are asking the right questions and that is what's coming next is we're going to
[22:43]
hammer out those those limits and because we want to make it efficient to
[22:48]
we want the process to be where you're not selecting from a menu of a
[22:51]
million things it's sort of meant to be the point is to make it streamlined
[22:55]
So to have that menu be very clear and concise and the process actually be quicker, I guess, is the point.
[23:03]
I think the designs aren't great. I mean, they fit our community perfectly based on, you know, the research and the study that you've done.
[23:13]
So I really appreciate that and the fact that someone doesn't have to use these.
[23:20]
This only facilitates doing something a little quicker and our community is such
[23:28]
that most building the individuals can afford to make their choices how they you
[23:38]
know want to put in an ADU or granny flat or whatever so based on what I'm
[23:44]
seeing it. I like it. Yeah that's a great point Sue. I thought as somebody that's
[23:52]
actually lived in ADU for 10 years I really thought the designs were really
[23:57]
very clever in terms of everything that you've been able to fit in a tight
[24:01]
spot because some some ADUs are designed a little bit better than others so I
[24:06]
thought the designs themselves are really nice. I agree. Another question the
[24:13]
you mentioned volume ceilings.
[24:19]
I've also noticed that the minimum building height
[24:23]
for an ADU or a structure in the back 40% of our lots is 14 feet 4 inches I
[24:32]
believe and some of these are quite a bit lower than that. You've got a 9 foot
[24:36]
plate. If somebody wanted, so here's a great question,
[24:42]
the engineering I know
[24:44]
how much it costs to change engineering. Once you have an approved set of plans, you have
[24:50]
to have your shear walls have to be right. I mean everything has to be such. And for
[24:55]
these to go back to Intermark for another round is going to defeat the whole purpose
[25:02]
of the affordability that these plans are providing for an honor. So would that mean
[25:12]
And if somebody wanted a 10-foot plate so that they could get up to the, let's say they
[25:20]
had 14 feet, 2 inches or something, and plan, I think plan 1 and 2, well, let's see, plan
[25:27]
3 is 14, 2, so that's pretty much it.
[25:31]
But plan 1 and 2, they have a 9-foot plate, but are there going to be plans where it's
[25:40]
The vaulted ceiling is, I mean, an affordable structure
[25:43]
would typically be a truss roof.
[25:46]
Is that gonna be part of the plan going forward?
[25:50]
The structure would typically be a truss roof, yes.
[25:54]
In our conversations previously,
[25:58]
the desire to have an option for a volume ceiling
[26:01]
was in there, so that is, we're building to that.
[26:04]
I think we're doing, I haven't read the contract
[26:07]
a little bit, I believe we're doing cut and stack
[26:09]
and trust options so you have both going on there it may just be cut in stack the
[26:14]
idea of being able to change plate height is suggesting that that is an option that
[26:18]
would not be a realistic option that I mean like you said they're engineered at
[26:23]
that point and yes thank you I agree that's that I just wanted to ask that
[26:28]
question any
[26:32]
other questions from commissioners the sorry
[26:45]
just give me a
[26:45]
moment oh
[26:49]
here here was one this is this would be a simple change the if
[26:57]
the
[26:58]
hot water heater you know now that we're not putting on-demand gas hot water
[27:02]
heaters on the side of a house. Now we're back to a closet for an electric hot water
[27:11]
heater, large tank. To capture some closet space, let's say in plan 3, one of the bedrooms
[27:19]
could have a larger closet if that water heater was an appendage.
[27:28]
Well, the electric
[27:29]
tankless are really not very efficient. It's gas is the way to go with the tankless. And
[27:36]
gas is no longer, gas tankless are no longer permitted in California. That I believe I could
[27:44]
be wrong. It's very recent. So just trying, California is trying to eliminate all gas
[27:50]
appliances.
[27:52]
We've been doing this for five or six years now and we used to do on demand gas water
[27:58]
heaters in places that you know wanted that and we can't we can't get them to
[28:02]
work anymore in title 24 it's they're gone so they have to be condensing
[28:07]
electric which means they need to be in an enclosed
[28:14]
environmentally you know a conditioned space they can't be just like in a little
[28:18]
they could be in a lean tube but we got insulated we got to seal it we've
[28:22]
got to do all that type of stuff it's not just like the old days where
[28:25]
you'd have a little shed from Hope Depot
[28:27]
and you stuck your water heater in.
[28:28]
And that doesn't work anymore either.
[28:29]
Right.
[28:31]
And what happens is it impacts your setbacks.
[28:35]
So now you've got to set back from that.
[28:37]
So instead of a four foot, now you've
[28:39]
got four plus a water heater room of three feet.
[28:42]
So right.
[28:44]
No, it could not go.
[28:45]
And if there's a four foot setback,
[28:49]
it certainly could not go there.
[28:51]
It's not an architectural projection.
[28:54]
That's only 12 inches by eight feet.
[28:57]
Correct, yeah. It would just be part of the structure.
[29:00]
But, you know, maybe, I mean, if it could, I mean, the other thing too, this is a question I have for you guys.
[29:09]
So there are, you know, FAR requirements, there's lot coverage.
[29:14]
All of these structures still have to meet the same zoning that we have currently in our Title 86, right?
[29:21]
and that's correct and that's what we'll be reviewing in the next steps when they
[29:26]
go through building plan review and through ed skill they'll also go through
[29:29]
planning also and then when they go on to the to a site we're going to review
[29:34]
them for that as well so we will review the site plan you know where they
[29:37]
gonna get their parking what's their lot coverage etc and there are
[29:41]
exemptions from because of state codes there are where they are exempt from
[29:46]
FAR requirement and I think structural coverage so those two won't matter as
[29:51]
much but as far as setbacks and parking and everything distance from the main
[29:56]
house we have to look for all those and height you know if it's
[30:00]
You know, not that we have much grade change in the city, but we have to make sure it all
[30:06]
works. Does that answer your question? Yes, thank you.
[30:12]
Yeah, I was just, when I had a conversation
[30:14]
with Jesse yesterday and I was just talking about specificity, you know, it's like these,
[30:21]
there's, and particularly building in Coronado, it's, your point is well taken, Edry, that
[30:29]
if somebody really wants to make a change, they're just going to go ahead and spend
[30:33]
and the money to make the change.
[30:34]
And this is great for people who say,
[30:37]
okay, this is gonna be my budget,
[30:39]
this is what I'm gonna build,
[30:40]
this is what I'm allowed to build,
[30:41]
otherwise I gotta go back to Intermark, Eskil,
[30:45]
I don't know what it's called now,
[30:47]
but that's very clear, so.
[30:58]
Approve these, essentially, to a certain extent,
[31:00]
like you talked about, the coverage,
[31:02]
the setback, some of those things.
[31:03]
So in places that an individual
[31:05]
might not be able to do something
[31:07]
because of your development standards or a neighborhood that's going to come out and
[31:13]
raise cane about it or whatever the issue may be, the state's going to force this down
[31:18]
people's throats.
[31:19]
No, you have to, you don't get to have a say on this.
[31:23]
This is, matter of fact, there are jurisdictions that don't even go before planning commission
[31:26]
because it doesn't really matter.
[31:27]
They don't really have a say.
[31:28]
Anyway, the state said we have to do this.
[31:30]
Thankfully, you guys don't do that.
[31:31]
and the whole purpose of those types of programs is to bring forward designs that are incentivized
[31:39]
through time and money that are designed to fit your community, hopefully, so that you
[31:45]
don't get people just saying, yeah, I bought something off of Amazon and I'm training
[31:48]
it into my backyard and you can't do a thing about it.
[31:50]
And that happens.
[31:53]
All
[31:59]
right.
[32:00]
Well, thank you very much.
[32:01]
That was a terrific presentation.
[32:03]
Appreciate it.
[32:09]
We agree.
[32:20]
any more comments commissioners any more discussion okay moving forward can we
[32:31]
get a motion to to approve or not move
[32:42]
to recommend City Council approve the
[32:45]
three accessory dwelling unit floor plans and designs as presented by staff
[32:53]
Seconded. Let's vote.
[32:59]
Motion carries. All present voting aye.
[33:08]
Appears we're at the
[33:09]
end of our meeting. It is 3.30. Thank you.
[33:18]
Thank you. Thanks Dana. Thank you.