» All right. Welcome to the city council
[0:18]
[snorts] conference for Tuesday,
[0:20]
February 24th, 2026. We have one item on
[0:23]
the agenda, which is an update regarding
[0:25]
the financial status of the Norman
[0:27]
Forward program. And we have Jason,
[0:30]
director of parks and wreck here to talk
[0:32]
about that with us.
[0:34]
» I just saw Clint over in the other
[0:36]
building and I said the the scariest
[0:37]
thing for finance people is a parks uh
[0:40]
person giving a finance report. So, uh
[0:42]
let's go ahead and start but
[0:47]
» Somewhat uh some good news coming on on
[0:50]
this front. the uh I think uh not this
[0:53]
past month but the month before we we at
[0:55]
the finance committee meeting there was
[0:57]
talks uh about there might be some
[1:00]
remaining fund balance at Norford at the
[1:02]
end and so we just wanted to go over
[1:04]
those numbers and uh what it what we're
[1:07]
kind of thinking or projecting at this
[1:09]
point and then uh we were I think we
[1:12]
were instructed to come up with a list
[1:13]
of possible projects to do with uh if
[1:16]
there is a remaining fund balance at the
[1:17]
end but uh first just want to kind of
[1:20]
remind everybody of the full norm
[1:22]
forward program. Uh as you look down
[1:24]
there, this is uh a list of all the
[1:28]
projects that was voted on and uh the uh
[1:32]
original norm for budget and you see a
[1:34]
revised budget. Some of the revised
[1:36]
budgets did increase depending on the
[1:38]
project. Some of them decreased um there
[1:40]
towards the end. Uh the good news is
[1:43]
that when you start looking at this
[1:45]
whole list, uh we got a heck of a lot of
[1:47]
these projects uh checked, done,
[1:49]
completed. Um and uh we're kind of we're
[1:52]
kind of towards the end of Norm forward
[1:54]
where we're at all payo projects. So all
[1:57]
the um the good news is all the large
[1:59]
projects are kind of done and wrapped up
[2:01]
and on the way or towards the end. We
[2:03]
there's a few projects we still have not
[2:05]
um closed out, but we'll be working on
[2:07]
getting those. Um, and then when uh
[2:10]
probably should have started, let's see,
[2:12]
I might have missed that one. Uh, but uh
[2:16]
you start looking at the down this list.
[2:18]
Uh the uh projects that we do have left
[2:22]
is the Canadian River Park, which is the
[2:24]
very top one right there. Uh we also
[2:27]
have uh partial um projects left in our
[2:31]
existing neighborhood parks renovations
[2:34]
and also our new neighborhood parks.
[2:35]
We're down to uh one new [snorts] or one
[2:40]
new neighborhood park that or two
[2:42]
» Two one we're starting and then one
[2:43]
we're getting.
[2:44]
» Yeah, I got Blue Stem in the future
[2:45]
South Lakes uh neighborhood parks which
[2:47]
we're going to get to and trail
[2:49]
development.
[2:51]
Uh when you start looking um into the
[2:53]
future, so this is uh working with
[2:55]
finance finance. This is uh a uh kind of
[2:59]
a list of projections. [clears throat]
[3:01]
Um and I think there's moderate growth,
[3:03]
very conservative growth um factored
[3:05]
into all these. But uh you kind of see
[3:08]
at the very top line beginning fund um
[3:10]
balance uh and that kind of connects
[3:13]
when you start uh or like FYE2 you look
[3:18]
at the bottom you see 10 million 10.2
[3:21]
million and then you go back up there
[3:22]
and it starts uh all over again. And so
[3:24]
there's moderate growth uh figuring into
[3:26]
that. Also our our debt service that uh
[3:29]
which uh there's uh three different debt
[3:32]
services uh programs that we've used uh
[3:34]
thus far uh and uh has the payments that
[3:38]
go along with those. And then uh when
[3:40]
those do get paid off, you see this kind
[3:42]
of spreads out all the way to 2032.
[3:45]
Uh technically in 2032 we do not have
[3:48]
any um we don't project any portion of
[3:51]
norm forward to be coming in at at that
[3:53]
point but we'd still have debt service.
[3:55]
So we we uh did um place that on the
[3:59]
calendar and to um as we get towards the
[4:02]
end of this uh the the norm forward
[4:05]
stops at the end of the calendar year
[4:07]
2030. So that actually rolls into part
[4:09]
of the fiscal year of 2031. So you see
[4:12]
six months of that projection right
[4:14]
there. But uh if you start looking at
[4:16]
the bottom that kind of gives you a
[4:17]
general idea of what ending fund fund
[4:20]
balance will be uh towards that
[4:24]
uh we did add in um as I said we're down
[4:27]
to about five projects uh left in the uh
[4:30]
norm forward program that we haven't um
[4:33]
completed or hit substantial completion
[4:35]
on. Uh those uh Canadian River, Saxon
[4:39]
Park, new neighborhood park development,
[4:41]
neighborhood park renovations, trail
[4:42]
development. Uh those bottom four, we do
[4:46]
have a portion um already spent on some
[4:48]
of those. Saxon Park, uh we do
[4:51]
anticipating that starting sometime uh
[4:54]
probably late spring, early summer. Uh
[4:58]
uh so we already have design done on
[5:00]
that. We're kind of we're working with
[5:01]
public works and I'm making sure that
[5:03]
that the road in front of Saxon gets uh
[5:05]
fully built before we start on that
[5:06]
because there's huge money savings for
[5:08]
for the part portion of that as long as
[5:11]
uh uh the you know the road gets built
[5:13]
with all the utilities and we're able to
[5:15]
um tie into that. And then we still have
[5:17]
a lot of uh when you start talking about
[5:20]
neighborhood park development or
[5:22]
renovation uh still a lot of uh big
[5:25]
portion of that to go. Um we've talked
[5:28]
about that. In fact, we have three um
[5:30]
playgrounds on the agenda tonight. Uh
[5:31]
one is coming up uh with the Blueest
[5:34]
Stem, which is actually a new park
[5:36]
development. So, a lot of tieins to
[5:39]
that. And then you see Canadian River
[5:40]
Park. We're still working on um getting
[5:43]
some uh property to go along with that
[5:45]
either through uh we've had talks with
[5:47]
the Moore family. Um we're looking at
[5:49]
the possibilities of acquiring other
[5:51]
property if needed. And uh when you
[5:55]
start talking about the Canadian River
[5:56]
Park, it uh it can start unfolding
[5:58]
because the idea is originally to have a
[6:00]
trail head and then trails connecting to
[6:02]
to the Canadian River um park. Uh so if
[6:06]
you take what we projected of having
[6:08]
remaining balance and um taking minusing
[6:12]
off the final number we have over here,
[6:14]
which is the $22.7 million, we come up
[6:16]
with uh there could be about 11
[6:19]
millionish dollars left over when we get
[6:21]
to the end of Norm for. So worked with
[6:24]
staff uh um some other departments to
[6:27]
kind of come up with a list of possible
[6:29]
projects that could be used on this is
[6:32]
uh when we start presenting these
[6:34]
projects we'll say that a lot of our
[6:36]
Norman Ford projects we especially talk
[6:38]
about Reeves Griffin uh we only built to
[6:41]
probably about 50% done. So the master
[6:43]
plan is not fully completed on those
[6:44]
parts. So when we start presenting
[6:46]
portions of that to you that is uh all
[6:49]
fits within within um those master
[6:52]
plans. So the first one is and these are
[6:55]
in no specific order. These are just um
[6:57]
we wanted to present it to council to
[6:59]
get some input and then we'll eventually
[7:01]
talk to uh park commissioners uh and
[7:04]
CFOB to also get input before uh we
[7:08]
progress on any of these or make
[7:09]
decisions on any of these to bring it
[7:11]
back to you for final decision. So, one
[7:13]
of the ideas is uh to go for a sudden uh
[7:16]
wilderness land purchase. Uh currently,
[7:18]
we're under a long-term lease with the
[7:20]
state. Uh there is some definite
[7:23]
advantages [snorts]
[7:24]
in in purchasing that land. Uh last time
[7:27]
we talked to to the state uh we got a a
[7:30]
cost estimation around 3 million give or
[7:32]
take uh a little bit. But the yellow box
[7:35]
is an approximate area that we is
[7:38]
stateowned. Of course, set in wilderness
[7:40]
does uh we do have some area that's kind
[7:43]
of in the uh this back portion right
[7:45]
here that we do own. Uh but this is all
[7:47]
the stateowned portion. Uh the
[7:49]
advantages uh of purchasing this now
[7:52]
instead of later. Uh we think that with
[7:55]
Griffin, we we did show that we can get
[7:57]
uh land from the state at a a good cost
[8:00]
and um land is going to be no cheaper
[8:02]
now than it will be in the future. Also,
[8:05]
this says um add insurance um at least
[8:07]
on our portion that there's uh nothing
[8:11]
that could happen with that. Even though
[8:12]
you have a long-term lease, there's
[8:13]
always, you know, there's always a
[8:15]
possibility the state could find a way
[8:16]
to maybe wiggle out of that. And we
[8:18]
always want to make sure that the states
[8:20]
a a wilderness preserve.
[8:22]
Like I said, about $3 million with that.
[8:24]
Uh in a norm uh program, we did have a
[8:29]
project set aside for softball in a
[8:31]
football park. Uh we that was about $2.5
[8:35]
million when we tried to progress on
[8:37]
that. Um when it came for that that
[8:40]
portion or that turn for that project to
[8:41]
come up. Uh this was the the uh
[8:45]
schematics that input that we got back
[8:48]
from the our adult softball group and
[8:50]
the Norman Optimus Club at that time. Uh
[8:53]
and this uh schematic had a um cost um
[8:56]
estimation of about $9.5 million. So,
[9:00]
uh, when we, uh, started working on
[9:02]
that, we saw that that was not
[9:04]
attainable. Um, no matter how hard we
[9:06]
try, we can't you can't fit a $2.5
[9:08]
million budget into a $9 million
[9:11]
project. So, we decided to at that time
[9:14]
along with, um, council, uh, we decided
[9:16]
to split that project up and make, um,
[9:18]
make some developments or progressions
[9:21]
at both Ree Park and at uh, Ruby Grant
[9:25]
Park. The softball portion was upgraded
[9:27]
at Ree Park and then um we do have some
[9:30]
practice softball fields out at
[9:33]
uh Ruby Grant. This is for possibly
[9:37]
purchasing land. So we've uh looked at
[9:38]
two different sites. One of them is the
[9:40]
old north water treatment plant which is
[9:42]
uh never got developed. Uh we have
[9:44]
talked to um we the utilities department
[9:47]
actually owns that property. So we would
[9:49]
need to purchase that from them. Uh, and
[9:52]
it's been a few years ago. Um, and
[9:54]
[snorts] that was with a different
[9:55]
director. So, I don't remember what the
[9:56]
negotiated price is at that, but
[9:58]
recently talking to Chris and Chris
[10:00]
would love uh if we do progress on that
[10:02]
area to get a a appraisal of that
[10:05]
property and for us to to pay whatever
[10:07]
the market price is for that because
[10:08]
they are a utility enterprise fund. They
[10:10]
do need to make be made whole. We're
[10:12]
also looking at um another property
[10:15]
maybe uh towards the center part of town
[10:19]
also owned by the state. So, uh, we have
[10:21]
not dived too deeply into that, but
[10:24]
there's a possibility of [snorts] us
[10:25]
purchasing that property along with
[10:27]
maybe splitting the cost with utilities
[10:29]
to buy that. And we kind of estimate
[10:31]
that uh no matter where we buy, we need
[10:33]
somewhere between 40 and 60 acres and
[10:35]
that would be about $2.5 million to to
[10:38]
uh get that property. And now this is
[10:41]
just for a property purchase and this
[10:42]
would be kind of held aside um for a
[10:46]
future norm forward or a future bond
[10:48]
election. uh we don't think that that we
[10:50]
could develop it. Um that would just be
[10:52]
for the the land purchase.
[10:57]
Another big thing and when we start
[10:59]
talking about possible projects that go
[11:01]
along with this thinking of layups
[11:03]
basically things that would be very very
[11:06]
popular with the public. Uh there is
[11:09]
nothing more popular um with the public
[11:11]
than the adult wellness and education
[11:13]
center. Uh, as we were building that,
[11:16]
uh, we did original cost estimations. I
[11:19]
think we're about $12.4 million for for
[11:22]
the adult wellness and education center.
[11:24]
Uh, we we ran into this wall called
[11:26]
COVID. And then during CO everything,
[11:28]
um, the market went crazy. So, uh, we
[11:31]
ended up spending about $14 million on
[11:33]
building what you look at as just a gray
[11:36]
portion. Uh we wanted and hoped to build
[11:39]
a multiple u multi-purpose gym along
[11:42]
with that project, but we couldn't
[11:43]
afford it at the time. That got cut out
[11:46]
uh to add that back in. The estimated
[11:48]
cost at that time was about a million
[11:50]
and a half. So uh to build it if we
[11:52]
would have added it to it, in hindsight,
[11:54]
it probably probably would have been a
[11:55]
wiser idea uh right now to uh go back
[11:57]
and uh add that in. We're probably
[12:01]
looking at somewhere in about $2.5
[12:02]
million.
[12:05]
that would be all in soft cost
[12:08]
um design
[12:11]
everything to go along with that.
[12:15]
Another thing which we have talked about
[12:16]
several times before uh is uh updates to
[12:21]
re park mainly to uh replace kids space
[12:24]
or and or to add in a miracle field
[12:28]
which is an ADA accessible field for
[12:31]
everybody all children. Uh so the uh
[12:35]
estimated cost between that is 2.5. I
[12:37]
think we had about a million dollar set
[12:38]
aside for the kit space and uh
[12:41]
approximate cost about a million and a
[12:42]
half for [clears throat] the the miracle
[12:44]
field.
[12:45]
» Uh so couple caveats to go along with
[12:48]
these as we're pointing these out. We
[12:50]
did file for a T set grant um in the
[12:52]
amount of about $600,000 to go along
[12:54]
with kids. That was our our um
[12:57]
beneficiary of that grant. We're still
[12:59]
waiting to hear back. We'll hear
[13:00]
something uh hear something back next
[13:03]
month. Um about that is a two-year
[13:05]
grant. So that would be uh getting
[13:07]
$300,000 uh in the next [clears throat]
[13:10]
calendar year and then following that
[13:11]
another $300,000. But uh if we don't get
[13:14]
that, we do need to make plans to
[13:16]
replace kids space. And the playground
[13:18]
alone is about $700,000, but we think
[13:20]
the uh infrastructure to go around that
[13:24]
uh between lights and sidewalks and
[13:27]
other updates that that need to be made
[13:29]
uh around a kid space that probably be
[13:31]
somewhere around a million dollars. And
[13:32]
then the uh miracle field which we've
[13:35]
come and presented to you a few times.
[13:37]
Uh this is uh kind of imagine the if
[13:41]
you're out at Andrews Park or at Ruby
[13:43]
Grant the playground surface that's
[13:45]
there as a full baseball field of that
[13:47]
same kind of poured soft surface and
[13:50]
it's perfect space for uh to have uh
[13:54]
have a baseball field for kids of all
[13:55]
abilities and uh to have that um we
[13:59]
already have the corner kind of marked
[14:00]
out for that. Uh there's a field right
[14:03]
there that we kept. Uh we talked about
[14:07]
shrinking the the pond size to make sure
[14:09]
that that always stays in. Uh so we
[14:12]
think that would be about a million and
[14:13]
a half dollars for that poured surface.
[14:15]
Upgrade to the lights and uh going
[14:17]
through there and making sure that the
[14:19]
everything around there is fully
[14:21]
accessible for those who who would use
[14:22]
that field.
[14:24]
» That's the current layout of the park,
[14:26]
right?
[14:27]
» Correct. Correct. So, this is currently
[14:28]
out with the the park and those two
[14:30]
yellow squares would be the project
[14:32]
areas
[14:32]
» And there's other phases of Reefs Park.
[14:35]
» Yeah. And I didn't add in uh the full
[14:37]
master plan. So, because no part of the
[14:40]
park would be we're not saying that
[14:43]
would be a good project at this time.
[14:44]
It's just that to build out those
[14:46]
baseball fields or other parts of those
[14:48]
baseball fields. I say I think the cost
[14:50]
would be too great for us to to probably
[14:52]
fit in to the into a extension of or
[14:56]
this extra funding from Norford without
[14:59]
um taking out some other things that we
[15:01]
think would probably be more vi viable.
[15:03]
» The long range plan for park is to
[15:06]
replace all the fields like we did.
[15:07]
» Correct.
[15:08]
» The first four.
[15:09]
» Correct.
[15:13]
» Griffin Park updates. Uh, one of the
[15:15]
things that we want to get in there, and
[15:17]
we've talked to council about this
[15:18]
before, is, uh, and I know that we're
[15:20]
hitting up, that's playgrounds,
[15:21]
playgrounds, playgrounds. Um, this is
[15:23]
another one that would be highly
[15:25]
popular. Uh, we want to go through all
[15:28]
of our our, uh, community parks and make
[15:30]
sure make sure they have what we refer
[15:32]
to as highly accessible playgrounds. Uh,
[15:35]
uh, the playground costs uh that we, uh,
[15:38]
would put out at Griffin's about
[15:40]
threequarters of a million, $750,000. um
[15:42]
adding a public restroom building out
[15:44]
there next to the playground which would
[15:46]
uh uh service the the dog park
[15:50]
playground and the disc golf u would be
[15:53]
about a half million dollars
[15:56]
and it would go up in the that corner
[15:58]
and that once again this is part of our
[15:59]
master plan already planned um and
[16:03]
talked to the public and went through an
[16:05]
ad hoc committee.
[16:07]
» That's the master plan not what it all
[16:09]
currently is.
[16:10]
» Correct. I kind of I kind of switched
[16:11]
that one backwards. Should have put the
[16:14]
other one in there now that you got me
[16:15]
talking out loud, Mayor.
[16:17]
» But that's where that other soccer
[16:18]
field,
[16:19]
» Correct?
[16:20]
» Stand still.
[16:22]
» Yes. And and now kind of thinking back,
[16:25]
the reason I didn't put the other map in
[16:27]
there like I did with Reese Park is
[16:28]
because the uh the the current map we
[16:31]
have now does not have a playground or a
[16:33]
a restroom. It did have a restroom
[16:35]
building up there that got um demolished
[16:37]
with that putting in that new road area
[16:40]
out there that leads back to the
[16:42]
» Dogfield might not be their highest
[16:44]
priority.
[16:45]
» Do what?
[16:46]
» The
[16:46]
» Oh, the Yeah. So when you you start
[16:48]
talking about that right there, the
[16:50]
talking to the soccer club in uh certain
[16:54]
areas of that like the indoors I think
[16:57]
that is becoming more and more reality
[16:59]
especially that now that we have true
[17:00]
cost with the by factor of how much
[17:03]
utilities cost. There's no way that any
[17:06]
private Yeah. I mean you're talking
[17:08]
somewhere in the neighborhood of
[17:09]
$100,000 a year just for utilities. And
[17:11]
I think they're mentioning improvements
[17:13]
to the field surfaces was correct
[17:15]
probably more more beneficial to them.
[17:20]
» Uh another one that that we would want
[17:23]
to offer up which we think is a a very
[17:25]
valuable
[17:27]
chance of uh that has a lot of valuable
[17:30]
uh chance for and be very popular with
[17:32]
our product or for the public is the uh
[17:35]
Andrews Park updates. Uh now the master
[17:38]
plan did come in after
[17:40]
uh Nora Ford, but Andrews Park is listed
[17:44]
as one of the uh beneficiaries of Nor
[17:46]
Ford in the original ordinances. So we
[17:48]
do think that that it's possible to go
[17:50]
through here and um build the pond,
[17:53]
which would also have a storm water um
[17:56]
benefits to go along with it, not only
[17:57]
recreational benefits uh and a restroom
[18:00]
building. Uh so to go all the way in
[18:03]
cost for everything that's surrounding
[18:04]
that the the survey engineering and
[18:08]
design of the pond along with uh
[18:11]
pond and storm water construction and a
[18:14]
public restroom building that's all
[18:15]
about 2.75 million all in for all that
[18:18]
area right there. Um and we think that
[18:21]
we can get that fully built out as is or
[18:24]
as it's shown in those yellow boxes.
[18:30]
Another one that we have listed on here
[18:33]
which we do think it has a little bit of
[18:35]
interest uh for us uh uh is a young
[18:40]
family athletic center. We have had
[18:42]
conversations with with young family.
[18:45]
There is some benefits both for us and
[18:48]
um when we start talking about
[18:50]
membership and going farther into um a
[18:53]
revenue um creator for the Young Family
[18:56]
Athletic Center where we're we think we
[18:58]
are to the point where we could break it
[19:00]
even this year for the first time u
[19:02]
because now we've taken over concession
[19:05]
uh operations inside the YFAC. But we do
[19:07]
think there's a lot more opportunity to
[19:09]
to grow revenue and make that that uh
[19:12]
special revenue fund even more
[19:13]
independent. And the number one thing
[19:16]
that we always hear feedback is that
[19:18]
y'all don't have a gym space to lift
[19:20]
weights or work out in. And um we don't.
[19:23]
And I think that would uh put us on par
[19:25]
with some of the other or above par uh
[19:27]
with uh everybody else in town that
[19:29]
offers the same kind of programming. Uh
[19:31]
I think that that would uh take the
[19:34]
membership up where we could definitely
[19:36]
be a very independent um special revenue
[19:38]
fund. Uh we have had cost uh
[19:42]
conversations with the young family uh
[19:44]
if we are able to come up with it. The
[19:46]
the wait room cost estimation is about
[19:49]
$4 million. They said that they would be
[19:50]
willing to split that cost with us if we
[19:53]
are able to uh come up with that $2
[19:55]
million. And we also have a bond that
[19:59]
was taken out during the construction of
[20:01]
the Young Family Athletic Center that
[20:03]
was taken out against our guest tax. And
[20:06]
as of right now, it has about I think
[20:08]
about 2.4 $2.5 million payoff on that.
[20:12]
But that would be beneficiary, very
[20:14]
helpful for our guest tax, which would
[20:15]
open up other areas for uh the guest
[20:18]
tax, especially if that election passes
[20:21]
where we can start doing capital
[20:22]
[snorts] projects with that because that
[20:23]
is taking up I think about $400,000 a
[20:26]
year out of our our guest tax. Um so
[20:28]
when you start talking we get $600,000 a
[20:31]
year. $400,000 is taken out for a bond
[20:34]
payment.
[20:35]
you know, don't have to be a parks and
[20:37]
rent guy to figure out that's not very
[20:39]
good. U but the uh it would even be even
[20:42]
better uh when the guest tax hopefully
[20:44]
does pass and then we would have this uh
[20:47]
fully available with full bonds. Like I
[20:49]
said, we have 70 parts um about 150 $160
[20:54]
million worth of assets. It's really
[20:56]
hard to take care of on our liable or
[20:58]
limited availability of capital funds.
[21:03]
We do have miscellaneous other projects
[21:05]
which have been uh talked about.
[21:07]
Westwood uh start out with Ruby Grant
[21:09]
since that's at the top of the list. Uh
[21:11]
Ruby Grant trail upgrade upgrades. We
[21:13]
have had uh talks with OU about uh
[21:16]
upgrades to our cross country areas out
[21:19]
there. Uh they do hold the SEC
[21:22]
championships uh for cross country I
[21:25]
think in 2029.
[21:28]
Uh so they've had talks with us about
[21:30]
sharing a project uh out there and
[21:32]
hopefully making that their home course
[21:34]
along with holding the SEC championship
[21:37]
uh cross country meet uh where this
[21:39]
would come beneficiary outside of just
[21:43]
hosting college meets. Uh this would
[21:45]
make it a primary very high desired
[21:49]
uh cross country track for not only for
[21:52]
you college meets but also for high
[21:54]
school meets and other recreational
[21:56]
features. So it would do full upgrades
[21:58]
to that. I think when we start talking
[22:00]
about what upgrades they need, uh it
[22:02]
needs the the track has to be at least
[22:04]
10 10 meters wide all the way through.
[22:07]
Uh it has to be a constant uh surface.
[22:09]
So we do have uh some limited uh because
[22:13]
we have concrete surfaces, we have uh
[22:15]
granite surfaces, we have grass
[22:16]
surfaces. Their preference would be all
[22:18]
grass. So we just need to figure out a
[22:20]
route through there and make sure
[22:21]
everything is about 10 meters high. Once
[22:23]
again, not only would we be a be able to
[22:25]
host a college cross country, but we
[22:27]
would also be able to do uh state
[22:29]
championships and districts and so forth
[22:32]
and so on. So, I think that would be a
[22:35]
great ad to the to uh the the parks. Um,
[22:39]
also at Westwood, we haven't uh opened
[22:42]
that in 2018.
[22:44]
I haven't had a new feature out there.
[22:46]
the uh in a shortterm when we're talking
[22:50]
about a 100 day program per year we pull
[22:53]
in about a million dollars worth of
[22:54]
revenue um out there it's the most
[22:57]
successful highly highly public used uh
[23:02]
uh municipal pool in the state uh other
[23:06]
places come to us to try to figure out
[23:08]
what we did we kind of got lucky uh I
[23:11]
think as a combination with our
[23:12]
population center only having uh one
[23:15]
pull uh for the amount of population we
[23:17]
have in here and we did it really really
[23:19]
good. Um but brings in about a million
[23:22]
dollars. We need to add a new feature to
[23:23]
keep make sure that we have eventually
[23:25]
add a new feature out there to make sure
[23:27]
that uh we have public interest and keep
[23:29]
coming out there because Oklahoma City
[23:31]
starting to redo pools or or private
[23:33]
always that private pool uh feature that
[23:36]
you have white water or the the harbor
[23:40]
[snorts] whatever the heck they're
[23:41]
calling it nowadays. um that that
[23:44]
they're always upgrading and making
[23:45]
advancements and and uh when we talk
[23:48]
about a new feature, it could be
[23:50]
anything from a uh a surf type machine,
[23:54]
new slide, new feature. We already have
[23:56]
everything plumbed in going back to our
[23:58]
pool house. We just need to figure out
[24:00]
and purchase that new feature, whatever
[24:02]
that would be to add to to Westwood. Uh
[24:07]
also we have sign packages uh that a lot
[24:09]
of our uh the parks that we have been
[24:12]
working on uh especially Ruby Grant,
[24:14]
Griffin and Ree. We did not progress
[24:18]
with a full sign package out there
[24:19]
because budgets were so tight when we
[24:21]
were working on those projects. Uh we
[24:24]
did uh put in a capital request for a
[24:27]
sign package to come out of uh current
[24:30]
norm forward um this upcoming year. um a
[24:34]
sign package for all of our neighborhood
[24:35]
parks along with uh upgrading our our
[24:38]
community parks with this type of
[24:40]
signage. And there is about $550,000.
[24:42]
And like I said, we did not do any re um
[24:45]
um signage at Reeves or at uh Griffin
[24:48]
because those projects were I mean, we
[24:50]
were down to pennies towards the end of
[24:51]
those projects. So, we want to go
[24:52]
through there and clean it up and get
[24:54]
way finding signage at those parts along
[24:56]
with uh obvious
[24:59]
um placemaking signs in in front of
[25:02]
those.
[25:04]
» Can we uh build it west with the
[25:07]
airport? How tall can we build?
[25:08]
» Do what?
[25:09]
» How tall with the airport being close
[25:10]
by? Do we have the highest?
[25:13]
» So, the um
[25:15]
» Just
[25:16]
» What's the tallest slide?
[25:17]
» I [clears throat] think we can go up to
[25:18]
about 25 ft.
[25:21]
That's probably about as tall as the
[25:22]
ones that are out there.
[25:23]
» So, the think of if you go look at those
[25:26]
lights, they're about 35 uh I think
[25:28]
they're 35 ft in the air. That's I think
[25:30]
that was the the top that the FFA
[25:36]
would allow us so we could um mix up
[25:39]
with flights and farmers. Um
[25:41]
» Cool people could see.
[25:43]
» Yeah. Got to go to Westwood.
[25:46]
» Yep.
[25:48]
But everything we looked in is about
[25:50]
anywhere between um a new feature is
[25:52]
about a million dollars and you start
[25:53]
adding in uh design cost and insulation
[25:57]
on that. We we think that'd be about an
[25:59]
extra half million to to go all in. Uh
[26:02]
so when we start talking about this is
[26:04]
all the project summary. Of course we
[26:06]
don't have $22 million uh to spend on on
[26:09]
all this, but these are just some ideas
[26:11]
wanted to present to you. Uh, also
[26:14]
there's been um talks with the CFOB uh
[26:17]
if we do have excess uh amount or C's
[26:21]
financial oversight board. Shannon,
[26:24]
there you go. The uh to make sure that
[26:26]
that that uh if we have overages they
[26:30]
wanted to possibly set some aside for
[26:32]
maintenance or or
[26:36]
redoing of things that kind of get worn
[26:38]
out um there towards the end. So there
[26:40]
there's also that hanging out there. So,
[26:42]
just wanted to uh tell you the good
[26:46]
news. There's a possibility that we will
[26:47]
have a fund balance there towards the
[26:49]
end and and um what possible projects
[26:52]
that the the parks department would
[26:54]
suggest going along with everything.
[26:56]
» A balance of 11.08
[26:59]
million left over.
[27:00]
» Yes.
[27:01]
» So, that's the possible projects that we
[27:04]
could do left over, but there's 11
[27:06]
million and you [snorts] would say maybe
[27:07]
reserve some of that for maintenance
[27:09]
stuff. So maybe 10 million.
[27:12]
» Yeah.
[27:13]
» So we might have 10 million to actually
[27:17]
do some of that with. I would maybe just
[27:19]
» Correct.
[27:20]
» Council.
[27:21]
» Oh, thank you. Um just for the record,
[27:25]
» Excess funds in Norman Ford can only
[27:27]
spend be spent on Norman Ford projects.
[27:30]
Correct.
[27:30]
» Correct. [snorts]
[27:32]
» You have a windfall of savings. You
[27:34]
can't spend it somewhere else.
[27:35]
» It's limited on it. So it has to be
[27:36]
anything that was described in the
[27:38]
ordinance that set off the [snorts]
[27:39]
walls.
[27:40]
» So we have a limited view of what we can
[27:42]
spend it on.
[27:42]
» What's the proposed process for Weeden
[27:45]
through these projects and kind of
[27:46]
selecting the final candidates?
[27:48]
» Is that going to be the decision of us
[27:52]
nine or are they going to the parks
[27:54]
department going to bring us
[27:54]
recommendations on what they think the
[27:56]
highest priorities are? final decision
[27:59]
lays with right with the the council and
[28:02]
I think we can go through there and
[28:04]
whatever the process that we all think
[28:06]
or you think that's best uh we can go
[28:08]
through there with CFOB we can parks
[28:10]
board we can vet vet some of this
[28:12]
through them and I I think that they
[28:14]
will definitely have some priorities and
[28:16]
suggestions to go along with that uh you
[28:19]
we definitely have some opinions and
[28:21]
then we come through there and put that
[28:23]
all together and present to you there
[28:25]
towards the end especially the feedback
[28:26]
that we get from our our public.
[28:29]
» Okay. And when do you think when do you
[28:30]
anticipate we be making those decisions?
[28:33]
» It's a good question. So the um and we
[28:36]
probably need to talk to um make sure on
[28:38]
finance one is is that the schedule of
[28:41]
available funds and so we don't want to
[28:43]
get too far ahead of of where we need to
[28:47]
be. We don't want to go out and start
[28:48]
spending a whole bunch when there's not
[28:50]
that amount in the bank. Uh, and one of
[28:53]
the things that kind of [snorts] works
[28:55]
in my mind, you start talking about the,
[28:58]
uh, we have an obvious delta at Andrews
[29:01]
Park. Uh, we have things, we don't have
[29:04]
a public restroom out there. The the
[29:05]
park's very tired. So, when you start
[29:08]
looking at uh, it does have storm water
[29:11]
advantages to go along with this. So,
[29:13]
the when you start looking at the
[29:15]
possibility of that, so when you start
[29:17]
looking especially start picking out
[29:19]
Canadian River Park. Yes, that is a
[29:22]
project, but that has always been
[29:24]
planned to be one of the last part
[29:26]
projects in North Fort. So, can we bump
[29:28]
up something else on this because now
[29:32]
Canadian River Park, we still don't have
[29:34]
land. Um, and we have to have land
[29:38]
in our possession to basically start the
[29:40]
project. We have to know what the park's
[29:42]
going to look like. We're going to have
[29:43]
to know how we connect trails to it. And
[29:45]
right now, uh, we've had several
[29:48]
conversations about land, but nothing
[29:50]
nothing anywhere close to being a sure
[29:52]
thing. So, that's still hanging out
[29:54]
here. Now, if council makes it a
[29:56]
priority to bump one of these suggested
[29:58]
projects up ahead of that, you know,
[29:59]
that could be within y'all's realm.
[30:03]
» So, would you prefer us to I mean, I
[30:05]
know which one's on the list that I
[30:07]
would push as priorities. Is it helpful
[30:10]
for us to just send you our individual
[30:11]
list or how, mayor, how would you like
[30:13]
for us to do this?
[30:17]
» [clears throat]
[30:17]
» We're in kind of uncharted territory.
[30:19]
We've never had such a scenario where
[30:21]
we've got
[30:23]
» Available resources and you know a wish
[30:26]
list kind of put together by staff, but
[30:28]
there may be other park or recreational
[30:32]
projects you have in mind that we didn't
[30:34]
cover that we'd be happy to add to that
[30:36]
list as we work our way through. Um, I I
[30:40]
think if maybe we could assemble a list
[30:43]
if council submitted their priorities,
[30:46]
we'll make sure I mean this this
[30:47]
presentation is on YouTube, but we can
[30:50]
send you the list and yeah, love your
[30:53]
feedback and we'll start bundling it up
[30:55]
into a package that we think will fit in
[30:57]
the budget. We can bring it back to a
[30:59]
study session or uh an appropriate
[31:01]
committee meeting as we work through a
[31:02]
process.
[31:04]
» Thank you. Grant
[31:07]
» Um I like list being sent to us and
[31:09]
maybe a line item for maybe holding some
[31:13]
back for maintenance. Um, so we can rank
[31:16]
it appropriately. I'm just going to say
[31:18]
W4 and the fact that Andre's Park
[31:21]
doesn't have a restroom and we have
[31:22]
events that happen out there and we
[31:25]
don't have a central library. Police
[31:27]
station is somewhat of an option. So is
[31:29]
municipal complex.
[31:31]
I hear a lot about there not being a
[31:32]
restroom out there and if it's only 500k
[31:35]
I you know I would advance that before
[31:37]
the other things with Andrew.
[31:39]
» So to just be clear to get to the
[31:41]
restroom we have to
[31:43]
» Survey it and then we have to move dirt
[31:46]
to make sure because we're that you're
[31:48]
going to there's a order of operations.
[31:50]
We can't just go put the restroom in
[31:52]
there.
[31:52]
» So there's no getting away from the
[31:53]
2.75. I would still agree
[31:55]
» It's somewhere in it doesn't have to be
[31:57]
the full amount but it's somewhere
[31:58]
within there because the uh the restroom
[32:01]
right now is placed where the the
[32:03]
man-made ditch is and that and what we
[32:05]
want to do is go back to the original
[32:06]
water flow that was in the park and that
[32:08]
man-made ditch is right where the
[32:10]
restroom is designed or picked out to
[32:12]
be. So we need to get that
[32:14]
» Moved.
[32:15]
» Well, obviously I feel [clears throat]
[32:17]
strongly about it. So, I'm putting a one
[32:19]
on it when it comes to us. And maybe
[32:22]
that needs to be bundled together
[32:24]
considering um what needs to happen in
[32:27]
the order of operations.
[32:30]
» Yeah. and the the one for that being the
[32:32]
storm water part and I don't know what
[32:34]
the total I can't recall what the total
[32:36]
cost is that we're spending on the south
[32:39]
I creek
[32:41]
project that's going on right now stream
[32:43]
bank stabilization and all that but the
[32:46]
the uh capacity for this water to be
[32:50]
held at in the Andrews Park and provide
[32:54]
some relief for all the neighborhoods
[32:56]
downstream of here between here and the
[32:59]
Canadian
[33:00]
um I think is a pretty
[33:03]
good point for including that one
[33:05]
because it has an impact that stretches
[33:07]
through the middle of the city for a
[33:09]
couple miles all the way south.
[33:11]
» And and I want I want to be very clear
[33:13]
this is not a full fix storm water-wise.
[33:15]
This is only a small
[33:17]
» Small small portion of what all the
[33:19]
capacity we need to do it. It does
[33:20]
expand it but it's not near enough.
[33:23]
» Yeah, there's none now. That's just a
[33:25]
rock channel that runs through. U but
[33:28]
yeah, um I think council members
[33:31]
evaluating that list, thinking about how
[33:33]
much we have there. Um and letting staff
[33:36]
know and then we can discuss it further
[33:38]
and either a committee oversight or
[33:40]
community planning, transportation or
[33:41]
finance. Um I suppose maybe
[33:46]
» Or study session, whichever. And then I
[33:49]
I know we'll get questions about the
[33:50]
library um about, you know, should we
[33:55]
reserve any of this for that issue? And
[33:58]
I know we're litigating it, the
[34:00]
potential of getting uh the construction
[34:02]
company and those involved to be held
[34:06]
responsible for that cost to fixing it.
[34:08]
But I know we'll get that question is
[34:10]
should we save this and use it for that
[34:12]
instead?
[34:13]
I think that's a viable option. Uh point
[34:17]
out that right now that the hopes is
[34:20]
that you know that gets fixed by the
[34:22]
contractors and everything gets worked
[34:24]
out through mediation or litigation
[34:26]
whatever it comes down to. But us
[34:29]
working ahead and I know it's been
[34:31]
there's been some suggestions maybe we
[34:33]
use some of this to go there in there
[34:34]
and fix it now. That that should not
[34:36]
that's not an option because one we
[34:38]
don't we have to have an architect and
[34:40]
we have have a number two we have to
[34:41]
have the contractor. Number three, that
[34:43]
thing is evidence. It's a big box of
[34:46]
evidence. So, we don't want to go in
[34:47]
there and change or fix or do anything
[34:49]
right now. And number two, there's no
[34:51]
contractor or no architect in the world
[34:53]
that it's going to touch that and take
[34:55]
the responsibility of shifting all the
[34:58]
liability to them if something in the
[35:00]
future goes goes wrong with it.
[35:02]
» We fix it, you own it.
[35:03]
» Yep.
[35:06]
» All right. Any other questions or
[35:07]
comments from council about number four
[35:10]
finds?
[35:10]
» All good news. Um, yeah. I think there's
[35:13]
a bunch of stuff on there. I think
[35:15]
there's stuff that we had to cut out
[35:19]
that we can sort of put back in. I think
[35:21]
that'll help people um, you know, that
[35:25]
may have felt like they voted for some
[35:26]
stuff and we weren't able to get it all
[35:28]
done, but we can get maybe some more of
[35:32]
it done with this. So, um, okay.
[35:36]
All right. Well, thank you very much,
[35:37]
Jason. appreciate the update and look
[35:40]
forward to the continued conversation
[35:42]
on uh this list of potential uh
[35:45]
projects. Okay, if that's it, then this
[35:48]
meeting is adjourned.