Transcript
SOURCE TRANSCRIPT
This transcript is downloaded from the source you provided but we haven't reviewed it for accuracy. Treat it as a starting point, not a verbatim record. You can also request an AI-transcription of the audio file with the button to the left.
These are YouTube's auto-generated captions, not a human transcript — expect occasional errors, especially with names and technical terms.
[5:58]
words of our mouths and the meditations
of our hearts be acceptable in thy
[6:02]
sight, oh Lord, our strength and our
redeemer. Amen.
[6:06]
Let us pray. Pledge. Ready? I pledge
allegiance to the flag of the United
[6:11]
States of America and to the republic
for which it stands, one nation under
[6:17]
God, indivisible, with liberty and
justice for all. Thank you.
[6:23]
Okay,
council, you have before you an agenda.
[6:28]
The first thing I will do is ask, is
there anyone present who would like to
[6:33]
speak under unscheduled public comments?
That's a 3minut time limit. Is anyone
[6:40]
present in council chambers who would
like to speak under unscheduled public
[6:45]
comments?
[6:49]
Hearing no one. Uh and I am looking here
and I don't believe anybody was on the
[6:54]
schedule public comment list. All right.
Then I have uh at least one
[7:02]
uh
change or addition under Roman numeral
[7:06]
10.
Uh we have a recommendation of the
[7:10]
planning commission. Can we add under
that as A1 the uh report from the IEDA
[7:17]
that would be Joseph Vance and Lena
Mitchell. If council would pencil that
[7:21]
in please. Roman numeral 10 A1.
Uh, there'll be the IEDA represented by
[7:28]
Jo represented by Joseph Vance and Lena
Mitchell. All right.
[7:35]
And I think
that's it. Are there any other changes
[7:40]
to the agenda? Council
>> Mayor.
[7:43]
» Yes, sir. Can we add one item to
executive uh close session subject to
[7:48]
Mike's approval there um for a legal
consultation uh regarding contracts
[7:57]
the electrical contracts
[8:01]
» for
um exist are you talking about
[8:05]
» the existing contracts
>> existing so consultation with legal yes
[8:10]
existing contract
>> so you can update us and I think uh Don
[8:13]
can update hit us on a couple of things.
[8:23]
A7.
[8:29]
» Yeah, let me just confirm on that.
>> Okay.
[8:53]
Is this regarding the probable
litigation or before or just a blanket?
[8:58]
» Just a blanket thing. It's discussed A8
>> A8. What is the number now please?
[9:04]
» Virginia code se Virginia code section
2.2-3711. 2-3711
[9:12]
A8
>> for legal consultation.
[9:16]
» Yes.
>> Regarding contracts, do we need that on
[9:20]
there, Mike?
>> Is that the the energy contracts?
[9:23]
» Electrical energy contracts.
>> Yep.
[9:29]
» Thank you.
>> What is it? Electrical. Yeah, electrical
[9:31]
contracts.
>> All right. Is that to get advice from
[9:36]
Mike or just an update?
>> Yes, to get advice and an uh an update
[9:40]
of a couple meetings that they had this
week.
[9:43]
» We can't do the update, but we can go in
to ask him for advice.
[9:48]
» Well,
>> if it's contract negotiation, there's a
[9:51]
separate thing for that. But if it is
legal consultation,
[9:56]
it's to ask a legal question.
>> Well, I'm asking a legal question.
[10:01]
» Yeah. And I said that was fine. I we
just can't do an update in there. If
[10:05]
it's specific legal question, that's
perfectly okay.
[10:09]
» Yeah.
>> Okay.
[10:11]
» I have
>> Okay. So, what I have here is Virginia
[10:13]
Code section 2.2-3711A88,
[10:18]
legal consultation regarding electrical
contracts.
[10:22]
Okay. Is are there any other additions
or deletions to the agenda, members of
[10:27]
council?
>> Mr. Mayor.
[10:30]
» Yes, sir. Um, can we add financial
policies to the financial director
[10:34]
report?
>> Yes.
[10:36]
» As item D.
>> So that will be under Roman numeral 10
[10:40]
11. We'll put D, financial policies.
>> Yes.
[10:44]
» Okay. That's Ronnie's report. Roman
numeral 11, financial policies.
[10:52]
All right. Thank you. That's added.
Council, do you have that on your
[10:56]
agenda? Okay. Any other additions or
deletions to the agenda changes?
[11:03]
Okay, hearing none. Is there a motion to
approve the agenda as amended?
[11:10]
» Jan makes the motion. Is there a second?
>> Rick has a second. Is there any
[11:15]
discussion on this motion to approve the
agenda as amended?
[11:20]
Hearing no discussion, may we have a
roll call vote, please?
[11:25]
» Yes. Yes.
>> Yes.
[11:27]
Yes.
>> Yes.
[11:29]
» Motion carries. Thank you, council. We
now have a working agenda. Now, Roman
[11:33]
numeral 5 is appointment of the clerk.
And so, if we will please look u I um I
[11:42]
I think I'm glad to report that Amanda
has agreed to continue being our clerk.
[11:47]
Am I correct on that? Am I correct in
saying that? Am I overstepping?
[11:52]
» No, sir.
>> Thank you. So, that's delightful. But
[11:55]
since she resigned, we have to have a
resolution to uh remploy her. She is an
[12:00]
employee of the council. Um so we have
resolution R 202260201.
[12:07]
Has everyone had an opportunity to read
this?
[12:09]
» I'll make a motion that we approve
resolution or adopt resolution R
[12:14]
202260201.
>> Okay. There's a motion on the floor. Is
[12:17]
there a second?
>> I'll second.
[12:19]
» Gary has a second. Is there any
discussion on this motion to adopt the
[12:22]
resolution
hearing? No discussion. We may we have a
[12:27]
roll call vote, please.
>> Okay. Seth,
[12:30]
» yes.
>> Gary,
[12:31]
» yes.
>> Rick,
[12:32]
» yes.
>> Jan,
[12:33]
» yes.
>> And Laura,
[12:34]
» yes.
>> Motion carries. Thank you very much. And
[12:36]
Amanda, it's a delight to have you
return to this role. Thank you.
[12:44]
Okay. Next, we have here um Okay.
Authorization to pay the bills, Roman
[12:50]
numeral six. Does anyone have any
questions about the check register?
[12:57]
» Um, I had a just one specific question
and then one general question. Uh, check
[13:02]
number 18427
to the Virginia Employment Commission.
[13:18]
Those are generally for our
withholdings.
[13:22]
Okay.
Um, and there were a couple things on
[13:27]
here that were over
like 10,000.
[13:34]
Was the
I guess like the procurement policies
[13:38]
were those
followed on those purchases.
[13:55]
» Do you have a specific one, Laura?
>> Um I didn't mark them, Ronnie. I'm
[13:59]
sorry, but just glancing at it, one of
them was um Outdoor Country18477
[14:07]
$16,000.
Um
[14:11]
Schwarz and Associates 18482
for $19,000.
[14:19]
» I know the Outdoor Country was
pretty certain I mean that all of these
[14:24]
have been through the process, but I can
I can definitely follow up.
[14:28]
» Okay. I I trust as long as you're aware
of it, I'm good. Thanks, Ronnie.
[14:32]
» Any further questions? Thank you. Any
other questions?
[14:35]
» Back to that first one that she asked a
question about. That check specifically
[14:39]
is labeled with an employee who's not
been here for a long time. So,
[14:43]
» that's what made me ask about it.
>> That was 18427. Ronnie.
[15:01]
All right, I'll I'll follow up on that
one.
[15:03]
» Thank you.
>> Thank you. Any further questions,
[15:08]
members of council, regarding the check
register.
[15:12]
Uh, if there are no further questions,
is there a motion to authorize the
[15:16]
manager to pay the bills?
>> So move.
[15:18]
» Oh, sorry.
>> Rick has the motion or has a second. Any
[15:22]
uh discussion on this motion
hearing? No discussion. May we have a
[15:26]
roll call vote, please?
>> Okay. Seth,
[15:29]
» yes.
>> Gary,
[15:30]
» yes.
>> Rick,
[15:31]
» yes.
>> Jan,
[15:32]
» yes.
>> And Laura,
[15:33]
» yes.
>> Motion carries. Mr. Mar, you may pay the
[15:36]
bills. Thank you. All right. Now, we
have uh Roman numeral 7, the minutes of
[15:42]
December the 9th.
>> I'll make a motion that we approve the
[15:47]
minutes as presented.
>> I'm just a little second.
[15:52]
» Okay, there's a motion and a second on
the floor.
[16:01]
I'm asking myself, is this is December
9th uh regular meeting minutes? Uh how
[16:07]
about the January minutes?
>> Um those are in progress.
[16:12]
» We don't have the January minute. So
we're approving the December minutes.
[16:15]
Yeah.
>> Okay. Thank you. Thank you very much,
[16:17]
Amanda. I just want to be clear on that.
All right. So is Yes, sir. Just so
[16:21]
you're during the u period between
uh Amanda resigning before she returned
[16:29]
is why do you have that delay for
January?
[16:31]
» Okay, I appreciate that. I was reading I
missing something. Okay, we're good. All
[16:37]
right. So, is there a motion to approve
the minutes of December the 9th?
[16:41]
» I made that motion.
>> Laura had I'm sorry. Was there a second?
[16:45]
» Rick Rick made the motion. I think Laura
secondary.
[16:48]
» Keep straight. Thank you very much. All
right. There's a motion and a second on
[16:51]
the floor. Is there any discussion on
this motion?
[16:56]
» Uh, hearing none. May we have a roll
call vote, please?
[16:58]
» Seth,
>> yes.
[16:59]
» Gary,
>> yes.
[17:01]
» Rick,
>> yes.
[17:02]
» Jan,
>> yes.
[17:04]
» Motion carries. Thank you, council.
Okay, we're on Roman numeral 8. There is
[17:09]
no scheduled public comment. Roman
numeral 9 there. No one uh spoke up to
[17:16]
be on unscheduled public comment. So
we're going on to Roman numeral 9 agenda
[17:21]
items. A recommendation of the planning
commission regarding the proposed
[17:25]
conditional use permit for 120 and that
should be 1205.
[17:30]
Uh Carly, thank you for seeing that.
Let's correct. I should have said that
[17:33]
on your u agenda. It's 1205 Front
Street. Thank you.
[17:38]
» Uh Gary.
>> Yes, mayor. Uh, the planning commission
[17:42]
met just while ago and are in agreement
5 to zero honoring the conditional use
[17:47]
permit for Kevin Schwin Gerber.
>> Okay.
[17:53]
» And I'll just go ahead and make that
motion that we approve that.
[17:56]
» I'll second.
>> All right. There's a motion uh on the
[18:00]
floor to approve the conditional use
permit uh for 1205. And um we're good.
[18:07]
You want to see that? It's just the
document they do. All right. So, there's
[18:12]
a motion and a second on the floor. Any
discussion on this motion to approve the
[18:16]
conditional use permit?
>> Hearing none, may we have a roll call
[18:21]
vote, please?
>> Okay, S.
[18:23]
» I'm going to abstain as that property
belongs to me.
[18:27]
» Okay. Gary,
>> yes.
[18:28]
» Rick,
>> yes.
[18:29]
» Shan,
>> yes.
[18:30]
» And Laura,
>> yes.
[18:31]
» Motion carries. Uh, thank you.
And so I would suggest that the owners
[18:38]
contact the town manager for the
conditional use permit. Thank you. All
[18:42]
right. Next we have uh Thank you. I'll
pass this back. Gary.
[18:48]
All right. Uh I would like to Hold on.
Okay. We're now on Roman numeral 10 A1.
[18:56]
The uh IEDA uh represented by Joseph
Vance and Lena Mitchell. Would you
[19:01]
please come forth?
[19:05]
and uh we know you, but would you tell
us your roles on the IEDA, please?
[19:12]
» Yes.
[19:15]
» So, my name is Joseph Vance. I'm the uh
chairman.
[19:19]
» Thank you, L.
>> for the IEDA.
[19:22]
And Lyn's passing out
some summaries for a little bit of what
[19:27]
we're going to present tonight.
[19:32]
been a lot of work uh put in over the
past uh few months from the IEDA just
[19:38]
working to bring more businesses into
the town of Richlands uh to operate
[19:42]
there. So, I'm going to give a little
bit of an opening comment. I'll be brief
[19:46]
and I appreciate you all appreciate your
time and and looking into this. Uh but
[19:51]
as we've continued to look for
opportunities to develop business within
[19:55]
the town of Ridgelands, um we we're
we're wanting to expand and we're
[20:01]
wanting to do it in alignment with what
council has already done. Um
[20:06]
particularly with the enterprise
incentives that were discussed a few
[20:10]
months ago. Um you know, even agreement
of the council to even lower some of the
[20:14]
FTEES. Um, so you have before you that's
got uh some more of the details, but you
[20:19]
know, other types of enterprise zone,
you know, business license, lodging,
[20:24]
meals, etc. Uh, we're in agreement uh
the IEDA is in agreement with town
[20:29]
council uh to propose those. So, what's
being proposed is what we're referring
[20:34]
to um as a small business expansion
grant. Um, and Lena and Mike have done
[20:41]
uh an incredible amount of work to just
pull the the shell and the concept of
[20:45]
this together. Um, and what we're really
asking for is just continue down the
[20:50]
same path that we already have uh with
this grant. So, the focus of the grant
[20:55]
is uh for capital investment,
specifically for capital investment. Uh
[21:00]
so a lot of times uh a business may
start up and they may need help with you
[21:05]
know operational expenses or rent or
something to that effect. Um sometimes
[21:09]
those are a little harder to defend.
>> Uh but in this cases specifically for
[21:14]
capital maybe it's a software purchase
or hardware purchase or a piece of
[21:18]
equipment or something like that. And
then within that first year um they they
[21:23]
would need to show an increase of at
least one FTE uh to be subject to this
[21:28]
grant. So, it kind of goes along with
what we did uh with the enterprise zone
[21:33]
uh incentives in the fact that um they
they have to provide additional jobs for
[21:39]
them to qualify for these. Um so,
tonight we're not asking for approval
[21:44]
for a a new program. We're really just
asking to to consider as you all are
[21:49]
developing your budget uh for fiscal
year 2026 and 2027. If council is
[21:55]
receptive to that, uh our next step will
be to actually develop u just a good
[22:00]
application um and bring that to council
um obviously for feedback and for public
[22:05]
comment. Um and I'll turn it over to
Lena. She's going to share some details.
[22:08]
» Thank you.
>> Thank you, Alan. Hello everyone. Um
[22:13]
Joseph did a really good job of an
overview of the program. These would
[22:18]
actually be micro grants and um we
anticipate being able to serve
[22:24]
approximately 10 to 11 businesses
depending upon what their need would be
[22:30]
and how much they would request. Um the
grants would be up to $2,500
[22:36]
and as Joseph mentioned um they would be
required to um hire one new person as an
[22:44]
FTE during a one-year period. Now there
is no risk involved in this because it
[22:50]
would be a reimbursement program. And so
after that one year is over, they would
[22:55]
show proof of the new FTE and also then
they would receive their $2500 or
[23:04]
whatever their um ask would be. Um
as he did mention, it would be for
[23:10]
capital purchases, no rent, no utilities
or anything like that. Um, we did
[23:17]
provide you with an overview that you
can take and review at your leisure. And
[23:24]
um, one of the other things I want to
mention though is on the back page, this
[23:31]
is not going to cost council any money
because the money is already there. It's
[23:38]
marked in pink on the last page of the
financials that was in the council
[23:44]
packet. And if you look at that, it's
the exact amount, 27,42.04.
[23:52]
So, um, what we would like is for you
all to review this. Um, if you have any
[23:57]
questions, I've also included all the
members of the IEDA and their phone
[24:03]
numbers. So as you do go on and have
your budget work sessions, if you have
[24:09]
any questions, if you would like us to
come and speak in a little more detail,
[24:14]
we'd be happy to do that. So um I would
be happy to answer any questions right
[24:20]
now.
>> Any questions?
[24:24]
» Yes.
>> Yes.
[24:25]
» Um your focus is on existing businesses
rather than new startups.
[24:30]
» Yes, it is Jan. um mostly the new
incentives that you all did approve a
[24:35]
couple of months ago for the enterprise
zone. We're were more in line in tune
[24:41]
for new businesses. So we don't want to
forget about growing our existing
[24:46]
businesses and so this is more tailored
for for our existing business community.
[24:56]
» Thank you.
>> I just have a quick comment. Um I'm not
[25:00]
saying I'm against it. I'm not saying
no, but I just wanted to give you a
[25:03]
heads up that the money that you
highlighted on the back um we've already
[25:07]
made a motion and approved to move that
money back into our general fund.
[25:12]
» Oh, you did approve that.
>> Yeah. So, it's not setting. I think
[25:16]
Ronnie was going to look into and Mike
or whomever was going to look into um
[25:22]
how much of it we could pull back over
because there was a little bit whatever
[25:27]
it was the town contributed
25,000 and then there was whatever.
[25:34]
Yeah. Grant funding. So, they were going
to look into how much we could put back
[25:39]
from the town and how much if it had to
be returned or reimbursed or used for
[25:44]
that or
>> Well, I remember the original intent of
[25:48]
this these monies were to assist and
support our local businesses. Um, at
[25:55]
that time, I think it was new
businesses, but um I have a soft spot
[26:00]
for our existing businesses, too.
sometimes they tend to get overlooked.
[26:05]
So if you know if that's the case, I
think this money's been sitting there I
[26:10]
know for about 2 years, maybe a little
longer. It hasn't earned any interest.
[26:16]
It hasn't done anything. And so we have
actually as the IDA had been working on
[26:22]
a concept to present to you all for
several months um unaware that a motion
[26:27]
had been approved for this you know
these funds.
[26:32]
» I didn't mean to interrupt you. I had
just u told Mr. Maher today that I felt
[26:36]
like our committees were not we're not
communicating with you enough. You guys
[26:40]
aren't with us enough that it almost
feels like and not just with the IEDA
[26:45]
all of our committees. It kind of feels
like we're all we're not not always on
[26:50]
the same page because we don't
communicate enough. So, I think this is
[26:54]
a great idea. I don't know about the
money. I think it's a great idea and you
[26:57]
you're kind of always known as the grant
queen. So,
[27:01]
» I don't know if I would go that far, but
thank you.
[27:04]
» But I uh I do think that it's great you
guys are here and that we should
[27:09]
communicate with you guys as a council
more and you guys with us as well. and
[27:13]
not just with you guys, like I said, all
of our committees so we can
[27:16]
» well I will speak on behalf of the the
other members of the IDA and I'm sure
[27:22]
that they would appreciate that. I know
I would and I know
[27:26]
» you guys are working hard on it. But um
again when you are doing your budget
[27:31]
work sessions if you don't have another
idea for these monies please just
[27:37]
consider that or maybe there's another
alternative that we could work together
[27:42]
on. So that's all we we have tonight but
question Rick has a question. Rick
[27:49]
» I've got a question like on new
businesses to help them start. This is
[27:53]
not a lot of money and I know this, but
it's like it's like more of an
[27:58]
advertising deal for us. Why don't we
eliminate the like the business license
[28:04]
fee for the first year?
>> That is part of the incentives if
[28:09]
they're located in the enterprise zone
and most of Richlands is located in the
[28:14]
enterprise zone.
>> Well, we're not talking what, $35 or
[28:18]
something.
>> Yeah,
[28:21]
» it's not much. is that the what I
understand is that the $30 is the
[28:26]
initial payment for it. Uh Billy and I
were discussing it the other day. So $30
[28:31]
is the upfront if you file for the
business license.
[28:34]
» Then you settle.
>> What's that?
[28:35]
» You got to settle up with what you sold.
Yeah.
[28:37]
» Right. So you do that to start the year
and then the enterprise zone incentives
[28:42]
actually are the followup to that first
year and they offer I think it's 80%
[28:46]
reduction the first year. Um, and then
it tears down
[28:50]
» and then 40
>> and then 40 through the 30.
[28:52]
» We kind of need to advertise that a
little more. That will draw more
[28:56]
business to our town
>> because people all they want to, you
[29:00]
know, all they're hearing is business
license and all of these license you
[29:04]
have to have to get in business,
>> permit fees, zoning,
[29:07]
» all of this stuff. So, if we could kind
of advertise that, I think that would
[29:11]
help us a whole lot in drawing newer
business.
[29:14]
» We agree. We agree. Totally.
>> We do. We've actually talked about some
[29:18]
ideas to market our existing businesses
and and you know to attract new
[29:23]
businesses using the town's website, the
Facebook page and other ideas. So, thank
[29:30]
you Rick for that suggestion.
>> Well, like today I was in Lebanon and I
[29:33]
seen a book, it was Jonesville,
Tennessee, you know, and it was just all
[29:38]
about that. It wasn't about this thick,
but it had every bis business that they
[29:44]
had in the whole town list it. I mean,
if we're going to invest our town, that
[29:48]
is something we need to invest in.
>> Another idea that we have discussed in
[29:53]
our meetings is having a resource guide
uh sort of like a welcome packet for new
[29:59]
businesses and some of the resources
such as the small business assistance
[30:04]
center at the college. you know, all of
their services are free and they have a
[30:09]
wealth of information and can be of of
great assistance to new businesses
[30:14]
starting out.
>> And that may help us that may help us in
[30:17]
advertising rich lands a little bit
better than we've done cuz we've not
[30:21]
done a good job at it and it's not
working because we're not doing it.
[30:25]
» So, yes, I'm I'll help you anyway I can.
>> Thank you. We appreciate that so much.
[30:30]
» I have a question. Rick, was that
Jonesville or Jonesboro? I believe
[30:34]
Jonesboro.
>> Okay. I'll just add a couple things
[30:37]
here.
>> Say Jonesville. Sorry.
[30:39]
» I I don't know. I really don't know. I
just checked on it. U I am not sure of
[30:43]
this. I may be way off. So, accept this
as a possibility. I think that 25,000
[30:49]
was given uh for the B. The intent was
to help businesses from the Thompson
[30:55]
Charitable Foundation. The next thing is
on Johnsboro, it's not particularly
[31:00]
about the business, but they have
established themselves as the center of
[31:04]
the international storytelling center of
this country. And that is one of their
[31:10]
biggest economic drivers and it all
started with a teacher in a graveyard
[31:14]
telling a story. If you've never been,
it is fantastic.
[31:19]
Just wanted to add that it adds to their
economy, its culture. Thank you.
[31:24]
» Any other questions? Linda, I was just
going to say it. You know, I don't I was
[31:28]
curious about the allocation. I don't
know if we've I don't think we've
[31:31]
allocated that money for anything. I
know we did put it back into the general
[31:34]
fund, but the other thing is um 2500's I
know it's it's money, but it seems like
[31:40]
a little amount, but I wonder if
>> I know and we don't have a lot to work
[31:45]
with. I get it. But I wonder if we could
maybe go to Kland Plateau to see if
[31:48]
there's a way for maybe them to match
what we're putting in or something like
[31:51]
that. I think that would make it because
if you could even get to 5,000 to make
[31:56]
an equipment purchase for a small
business, you know, $5,000 could make a
[32:00]
significant difference.
>> And Seth, that's a great point that we
[32:03]
have uh floated in our meeting. We just
wanted to get this proposal to you all
[32:10]
in advance of discussing and developing
the budget. We didn't want want to wait
[32:15]
on that. Evidently, you know, we are a
little late as far as this particular um
[32:22]
fund, but we did think about VCA and
some other possibilities of funding. Um
[32:29]
this would be a great start to get our
feet under us to make, you know, sure
[32:35]
this is going to work like we think it
will. But um those are some excellent
[32:39]
suggestions we've received
>> cuz they have like um like C Plateau has
[32:43]
revolving loan fund and you know they're
doing like small business things.
[32:47]
There's not a lot of money left in it
cuz they've done some larger things here
[32:50]
lately. But for you know that's not a
lot of money and there's potential you
[32:55]
might be able to go to them and say hey
what if we put this money up could you
[32:59]
help us and that way we're able to do
more because that's their whole mission
[33:01]
and goal anyway is to help people. And
the better thing for that is they're
[33:04]
just putting up the money. They don't
have to monitor it. They don't manage at
[33:08]
all. We would take care of that, right?
>> Just just a thought.
[33:11]
» I think we've got our direction. We'll
get you an application. We're going to
[33:15]
start working on drafting the
application that that you can do for
[33:18]
review. We'll we'll see what we can do
the next time. This is great.
[33:21]
» Thank you.
>> Well, the good thing is there were
[33:23]
questions. That means it's not dead in
the water.
[33:26]
» That's right. That's right. Well, thank
you so much for your time and your
[33:29]
consideration. We appreciate that.
>> Thank you.
[33:31]
» Thank you.
>> Thank you, mayor. I just want to comment
[33:34]
as your interim town council manager. I
would strongly encourage you to look at
[33:38]
these types of programs. You can't cut
your way through a budget all the time.
[33:43]
Sometimes you have to focus and invest
in the top line, which is what they're
[33:47]
focused on. And so I just I I think when
we're having those discussions in the
[33:52]
future that we keep in mind that when
we're looking at a budget, there's two
[33:55]
sides of it. And we need to be looking
at revenue opportunities and growth as
[33:59]
much as we're looking at expense
management and cuts.
[34:03]
» Thank you, Mr. Moore.
>> Great point. Just for some context, Mr.
[34:06]
Maher, the reason that we cut that
initially was because and this IEDA is
[34:12]
they're totally new. Has nothing to do
with them, but we had a former IEDA who
[34:18]
took that money and did not use it the
way that it was supposed to be used. Um
[34:26]
it
lawfully but awfully got funneled back
[34:30]
into IEDA members businesses. Um and
then we had the business owners in here
[34:40]
yelling at us. Weren't able to get the
money. um nothing to do with anybody
[34:45]
sitting in your seat, but a former
former former town manager um was not
[34:53]
thorough with the and fair and equal
with the applications. So, some people
[34:58]
were getting paid, others weren't. Um,
so I really appreciate that you guys are
[35:03]
starting off smaller
>> to be able to master it and, you know,
[35:08]
know what you're doing before jumping
into another
[35:12]
» situation like we had. Um, and that's
why that program was paused. But
[35:16]
» that's even more encouraging for us
because I wasn't part of you
[35:21]
any correlation.
>> No one on your IEDA now.
[35:25]
» No, it's a it's had a total total
change. you know, we we are looking at
[35:29]
sustainability for this if it's
something that you all want to go
[35:33]
forward with and um so that's important
things like Seth said, Mr. Mars and
[35:40]
» cuz because we can't just
>> hand out checks and and then have
[35:44]
nothing left, right? There's got to be
some kind of building to it, some kind
[35:48]
of regeneration
to the process. So, we're definitely
[35:52]
looking at
>> I like how you're thinking.
[35:54]
» Okay.
>> Thanks again.
[35:56]
Thank both of you and thank the members
of the IEDA.
[36:00]
Okay.
Okay. Now, Roman numeral 10B, we are on
[36:06]
um
Quantum Power Project updates. Welcome,
[36:10]
gentlemen. And uh come on up. I would
like to uh share with you the purpose of
[36:16]
there being here is excuse me, I'm about
to sneeze.
[36:21]
Sorry.
We want a clear I'll wait till they're
[36:25]
with me.
>> Welcome. Did you have to travel far
[36:29]
today?
>> No, sir. Not too far.
[36:31]
» Okay. Welcome. So, the purpose of the of
having you guys here, we're very glad
[36:35]
you're here. Is to have a clear
understanding of the milestones uh for
[36:40]
the project and what are the timelines
for the project for these milestones and
[36:46]
how is the progress going with the goals
that we've set that you've set?
[36:51]
Absolutely, Mayor. Thank you for having
me. U council.
[36:58]
» So, I want to address those as
specifically as I can in a in a
[37:02]
presentation. And I apologize. I believe
we were on the minutes for the last
[37:05]
meeting and I was unaware and so we just
didn't make it the last time. But, uh, I
[37:10]
hope to address most of the concerns
with this with this presentation today.
[37:17]
Wait on it to load here.
asking something from me.
[37:35]
» Is it asking something of me?
>> No, it doesn't have a signal.
[37:45]
» Oh, just me.
[37:53]
should be.
[38:04]
It should be up here.
[38:11]
» I just need to choose the window that
I'm
[38:47]
Is this a Samsung?
>> Yeah.
[38:53]
» Okay, great.
[38:57]
» Frank, is there any way you can flip
this TV?
[39:00]
» Sure,
>> please.
[39:04]
I'm just hooked into one, I guess.
>> No, it should be.
[39:07]
» Okay.
[39:12]
» All right.
Technical difficulties. I'm Zach Romano.
[39:16]
This is Mark Romano. I'm the VP and he's
the president of Quantum Power. Uh, it's
[39:21]
first time our being here in front of
the new interim town manager. First time
[39:24]
I've seen you face to face. So, it's
nice to meet you. Um, so I'll start out
[39:29]
with the executive summary. Um, the
Mercury 50 Genset has been purchased and
[39:34]
manufactured and is awaiting transport.
It's currently at the manufacturer in
[39:38]
San Diego. Uh, waiting to be transported
here because of the weather we've had.
[39:42]
I've kept it at the manufacturer. Um,
>> we went and looked
[39:45]
» Yeah, we went and saw them start it up
and run it in December. Um, and since
[39:50]
then, we've been making preparations for
long-term storage for that for that
[39:53]
generator. Um, due to some of the other
delays that I'll discuss a little bit
[39:57]
later. Um
the engineering and procurement are
[40:01]
progressing uh but costs have increased
due to inflation scope changes uh and
[40:08]
Americanmade requirements from Amler uh
for the money that they want to give.
[40:13]
Um the permitting and the land mineral
rights remain on the critical path for
[40:19]
us including storm water permits and
rightway negotiations that are still
[40:23]
ongoing.
Um the construction is contingent upon
[40:29]
timely permit approval and land
agreements uh with the best case in
[40:33]
service of Q4 of 2027
and that and that is best case with with
[40:40]
quite a few things that we'll discuss in
here how that's going to be
[40:42]
accomplished. Um we want to review the
current and possible economic dispatch
[40:47]
modeling and cost-saving projections
that that's a little bit different from
[40:51]
the original bid that we put in. We
originally had planned on base loading
[40:54]
this, but based on information that we
received along the way with the power
[40:58]
purchase contracts that it wasn't we
weren't able to just base load that
[41:02]
generator 100% of the time, it was it
had to be on a dispatch schedule a
[41:07]
schedule according to the power purchase
agreements that you already had in
[41:10]
place. So, uh, we've had to pivot on
that and and we've we'll talk about that
[41:16]
a little bit further in detail, but the
economic dispatch is is what we are
[41:19]
modeling later in this in the
presentation and, uh, that is the most
[41:24]
economical way for the town of Richlands
to dispatch this asset that they've
[41:27]
purchased.
>> Mayor Curry, um, is there any way that
[41:31]
you guys could email that to our clerk
and let her print this out for us to see
[41:36]
the presentation?
>> I can. Uh, I'll have to make some
[41:39]
changes to it because that's why I
didn't email it earlier. Okay. Some of
[41:42]
the documents are on my computer and so
when I email them, they disappear. The
[41:45]
slide becomes blank. So, I'll be glad to
>> Okay. Print them up and send them. Yeah.
[41:49]
Yeah. I'll be glad to do that.
>> Um, and we're looking for council's
[41:55]
cooperation um or assistance in
finalizing the land and mineral rights
[41:59]
agreements to avoid further delays in
this project.
[42:05]
the uh engineering and procurement
progress embbridge the natural gas prov
[42:10]
the pipeline
for the natural gas uh that you all will
[42:14]
be receiving is a 60% drawing package.
We've been in constant discussions with
[42:18]
them and and um been receiving
engineering updates along the way on on
[42:24]
the progress that they're making as far
as the hot tap and the and the equipment
[42:27]
that's needed to supply the Mercury 50
with the natural gas. Um, we're
[42:33]
coordinating economic the equipment to
handle the economic dispatch.
[42:38]
Um, which which this one piece in
particular is out of scope for what we
[42:41]
originally intended to do for the town
of Richland. We intended to put in this
[42:44]
generator based on a 90% base load
operation like I mentioned before. Um,
[42:49]
but we have moved into an economic
dispatch that we we've engaged with some
[42:54]
consultants on our own dime to help
understand the economic dispatch of this
[42:59]
generator for the town of Richlands.
That's a little bit out of scope from
[43:02]
what we originally had planned. Um but
we have done that at our cost. Um the
[43:08]
civil pad including the soil replacement
and the grading and the road
[43:11]
construction and the storm water are
underway. Um we have bids out for the
[43:16]
line equipment and the poles.
We're focusing on Americanmade equipment
[43:21]
because that's the stipulation from
Amler um in order for them to to
[43:25]
guarantee those funds. So the the poles
are being ordered and and we plan on a
[43:31]
summer delivery on those and a lay down
yard preparation before that
[43:36]
and we are also coordinating with the
vendors on the meter skid and EGM
[43:40]
building that's needed for the natural
gas supply and controlling the mercury
[43:43]
50
[43:47]
back.
>> Zach, are the are these supposed to be
[43:51]
changing up here the uh slides? Yes,
sir.
[43:53]
» Yeah, we went back a little bit.
>> They're not they're frozen. Oh, they're
[43:57]
not they're not changing on there. Okay.
I'm sorry.
[43:59]
» I just wanted to share that with you.
>> Okay.
[44:02]
» Sorry about that.
>> That's okay. I
[44:04]
» Let's move it back so we can see.
So, I want to be clear about why we are
[44:10]
where we are. Right. So, we can sit here
and go, oh, we're at a 60% drawing
[44:16]
package. We're at poll quotes on the
polls. We're at bids out on this other
[44:21]
stuff.
Let's let's be clear. we would already
[44:25]
be under construction. We should be
under construction, right? So, we got
[44:30]
held up because of
some type of scenario that's going on
[44:35]
over there on site, right? So, that's
why we are where we are. If we had been
[44:40]
able to finish the engineering, the line
route engineering has been done a long
[44:44]
time ago. The pad engineering should
have been done, but we couldn't because
[44:49]
we weren't sure if the pad was going to
be here or 30 ft down. Right. Inbridge
[44:54]
would have been a lot further along with
their interconnection on the gas if they
[44:59]
could have said, "Well, we don't have to
move our pipe." Right? So, there's been
[45:03]
a whole lot of pressure from outside
sources that delayed us. Right? So, it's
[45:10]
one of those things where you can't just
say, "Hey guys, go and finish up this
[45:12]
engineering, get it wrapped up so that
uh it can change, right? Because now
[45:17]
we've burnt the town's money. We've
wasted all the time. The paper isn't any
[45:21]
good." Right? So, I'm just clarifying
that this isn't like we're sort of
[45:25]
dragging our feet over here and that's
why we are where we are. You see what
[45:28]
I'm saying? So,
I just wanted to bring that into into
[45:33]
view when it comes to the delays.
>> Yeah. So, I I don't know why that's not
[45:38]
changing. I wish it would. Um,
>> why don't you try to do uh airplane?
[45:42]
» I can try to air it if it's easier. I
know they want to see the slides here.
[45:49]
Just go. Let me see the remote, please.
See,
[45:54]
see if you got to be on the same
internet. You're on the same internet.
[45:57]
» Richland's guest. Is that the same
network? There it is.
[46:12]
» It ought to just pull. You ought to just
see the TV.
[46:39]
You don't see anything at all.
[46:54]
Apple Airplane.
[47:19]
Turn Bluetooth off and back on.
[47:30]
It wouldn't be Bluetooth
[47:36]
on the mirror.
>> That's to my iPad.
[47:42]
Do you have any way?
[48:07]
» Is it up there again?
[48:27]
Okay,
>> he reset the network. It should be on
[48:32]
Richland's guest though.
>> I don't know.
[48:35]
» I doubt it. I said they're not a guest.
Well, I'm asking him. He's the IT guy.
[48:43]
» Is it Richland's Wi-Fi?
>> What is What is your Wi-Fi?
[48:52]
» Oh, well then it's not going to do it.
>> Oh, so it's not even connected to the
[48:55]
» Y.
[49:02]
You got a HDMI first.
>> HDMI is what's plugged in.
[49:25]
I saw something.
>> Did y'all get that?
[49:30]
» It was one slide that was trying to come
up.
[49:34]
» Yeah, I snapped it real fast.
>> It's not a bad joke. It's fun.
[49:43]
» You think your cable's bad?
[49:48]
I tried to. It's not mine.
[50:02]
» I know.
[50:05]
» I can tell it's trying to do something
cuz it keeps bumping it.
[50:15]
Just going to switch it for a second.
[50:27]
We could connect this to the top
[50:35]
to the Richland's guest.
>> Could we?
[50:39]
» Can we do that? set it up for the wrist
lands guest and air play that.
[50:42]
» You want to do that?
>> May, do you want to do a fivem minute
[50:45]
recess now while you're doing that?
>> Let's do a five minute recess. Make it
[50:49]
10 so you don't feel under pressure.
>> Thank you.
[50:52]
» I mean, thank you.
>> Uh, Mr. Romano, who made the joke,
[50:56]
» sir, with the remote. Would you look at
me, please?
[50:58]
» A day without a laugh is a wasted day. I
got it. Thank you.
[1:00:35]
resume.
>> Thank you, Mr. Mayor. All right. Um, so
[1:00:40]
I'm going to get into some of what Mark
was alluding to in just a minute a
[1:00:43]
little bit in further detail. All right.
as far as what it is. What so the the
[1:00:47]
companies that are involved are Embridge
Power Engineers, our engineering group,
[1:00:52]
you know, and we have a group that's
doing the consulting on the economic
[1:00:55]
dispatch, but really we've kind of
saddled oursel with the burden with
[1:00:58]
handling the Embbridge pipeline, the
hottap, right? That wasn't necessarily
[1:01:02]
in our scope, but we took that on as
well with the economic dispatch to try
[1:01:06]
to ensure the successful operation of
this generator. So conditions have
[1:01:10]
constantly been changing since we
originally bid this and and it was a
[1:01:14]
straightforward put in a generator, have
it run at 90% capacity and turn the
[1:01:18]
asset over to the town of Richlands. So,
you know, part of that was securing the
[1:01:23]
land the the land rights for the
generator site itself, which was a, you
[1:01:28]
know,
we were pointing in in a direction of
[1:01:32]
where we would like to have it and the
town of Richlands was supposed to take
[1:01:35]
that over and was supposed to secure
that those land rights so that we could
[1:01:38]
start the engineering for the generator
pad and for the line route itself. So
[1:01:44]
those those uh negotiations early on
kind of stalled and we had to take over
[1:01:47]
and use our engineering group to to
contact Pocahontas land and to deal with
[1:01:51]
Ramaco
um and and find out the the uh the
[1:01:58]
mining permit that was in that area. So,
we originally had a line route
[1:02:01]
engineered when we when we put this
together. And that came with a specific
[1:02:05]
number of poles and conductors and um
and all the equipment that goes on those
[1:02:09]
poles. And the scope has dramatically
changed since we originally bid that
[1:02:13]
because we've re-engineered it twice.
The first time we re-engineered it uh
[1:02:17]
because the we crossed through mining
permit. We already had that engineering
[1:02:21]
in place. And when we went to Pocahontas
land to finish that to help finish the
[1:02:25]
land lease for the generator site
itself, what we ran into was there was a
[1:02:30]
mining permit that interfered with where
we wanted to put our line. So we had to
[1:02:33]
re-engineer the line route. All right.
And we and we did that and we put that
[1:02:38]
in to a contingency budget and that's
what I'm going to show here on this
[1:02:42]
slide. Can you guys see this slide that
showed us the original?
[1:02:44]
» Yeah, it's pretty small. Can you make
it's okay, but can you make it bigger?
[1:02:49]
» Hit control++.
Thank you.
[1:02:51]
» Got it.
>> Okay. So,
[1:02:55]
so you can see um the up we updated the
the line route and did grid analysis
[1:03:02]
back in September. All right. And then
when once we did a a bat portal study,
[1:03:09]
we had to have the line route
re-engineered a second time because of
[1:03:12]
the information that we got back from
Pocahontas Land. You can see on on 53025
[1:03:18]
uh the additional engineering that had
been done to have the line route
[1:03:23]
re-engineered a second time. Um we
caused none of those issues or were the
[1:03:28]
reasons for why we had to re-engineer
them. But nonetheless, they had to be
[1:03:31]
re-engineered because of the way the
line route is set up. Every pole is GPS
[1:03:34]
located. Every piece of equipment that's
on that pole is specific to that pole.
[1:03:38]
The conductor length is very specific
for the overall line route from the
[1:03:42]
substation to the generator site. And so
all of those pieces had to get reeval
[1:03:48]
evaluated every time we ran into an
issue with the engineering. And and and
[1:03:53]
most of it came from Pocahontas's lands
reluctance to give us the information
[1:03:57]
that we needed when we originally did
the engineering. So, uh, you know, we we
[1:04:02]
worked through those issues and we used
the contingency money because that's
[1:04:05]
what we were directed to do was to use
the contingency money to pay for that.
[1:04:08]
Um,
uh, some of the NEPA coordination and
[1:04:12]
the cultural study that you see that's
on there. The NEPA coordination was a
[1:04:15]
consultant that we had to bring in to do
some of the work that's specific to the
[1:04:19]
cultural study. Um and the cultural
historical architectural study that you
[1:04:24]
see on there was all NEPA specific which
is a regulatory body that was guiding us
[1:04:32]
on how we had to engineer this route. We
came through the historical district in
[1:04:35]
downtown Richlands and so certain
criteria had to be met to be NEPA
[1:04:40]
compliant
to to qualify for the Amler funds.
[1:04:45]
from 24 to 25 there was a change in the
NEPA regulation and we were no longer
[1:04:50]
required
to do certain aspects of those studies
[1:04:54]
that had already been done to qualify
for the Amler grant. Uh and so we
[1:04:59]
requested that you guys go back and
reapply for the 2025 funds at the time
[1:05:07]
because it no longer required it. Trump
had uh President Trump had gotten rid of
[1:05:10]
some of the regulations and uh we didn't
have to follow some of the guidelines
[1:05:15]
that we originally did. Now, the
cultural study still had to be done and
[1:05:19]
still had to be studied because we came
through the downtown district, but we
[1:05:22]
didn't have to proceed further with any
NEPA regulations because he had dialed
[1:05:26]
those back. Okay. So there could be
additional costs that would have been
[1:05:30]
associated with this project specific to
the engineering and the environmental
[1:05:34]
studies uh related to the Amler funds if
if NEPA was still compliant. So that we
[1:05:40]
have kind of stopped that and and where
we are with the CNX purchase is there
[1:05:44]
was I put on here 1025 102025 because
that was when we had originally planned
[1:05:50]
to pay for the permit on CNX. So the the
generator site itself has
[1:05:58]
» Yeah, I'm going to. So So the generator
site itself
[1:06:01]
um had other stakeholders. There's
Pocahontas Land, which you guys secured
[1:06:06]
a lease on the piece of property for X
amount of dollars a year and and the
[1:06:11]
rightway for the line route all the way
back into town. Okay. Anything that
[1:06:15]
Pocahontas land. So you had to secure
that. But CNX was on the property. And
[1:06:21]
there's also another entity that's
that's come into play in the last 6 to 8
[1:06:25]
months um that has a claim to some
mineral rights that are on that property
[1:06:30]
or or to to remove some coal and those
are the main issues that are causing the
[1:06:34]
delays at the moment and we have to work
through some of those. But the CNX,
[1:06:39]
there was discussions with CNX about
their piece of the property that
[1:06:43]
encompassed that was on part of the
generator site. And so we helped
[1:06:48]
negotiate some of the contract with CNX
to purchase that permit so that we could
[1:06:53]
have clear title to the land above it.
But we have not seen those that purchase
[1:06:59]
agreement from CNX yet. But this is when
the money was earmarked out of the
[1:07:04]
contingency fund to make that payment.
It has not been made. But that is what
[1:07:08]
the planned use for that money is. So
that shows you see on this slide right
[1:07:13]
there at the bottom for the contingency.
We originally had a million dollars
[1:07:16]
planned in the contingency and that was
supposed to go towards the construction.
[1:07:20]
But as you can see those monies were
taken by each one of those studies
[1:07:24]
re-engineering everything that had to be
done plus the purchase from CNX.
[1:07:29]
The purchase from CNX is minimal dollars
that would have had to been spent rather
[1:07:34]
than re-engineering the entire generator
site had we been that far along in the
[1:07:39]
project.
However, there is still another entity
[1:07:43]
that um that will that I'll that I'll
get to in just a minute. But the
[1:07:48]
contract was originally this 5.29 29
for for the construction and and that is
[1:07:56]
um that number is no longer a viable
number because we're two years later
[1:08:00]
than what we had originally bid this.
So, I'm going to get into some one of
[1:08:04]
some of those additional costs are
unless you guys have some questions
[1:08:07]
about what I've gone through so far.
>> I think we're okay right now. Okay.
[1:08:14]
» Anyone questions at this point? Okay.
So the main drivers in the budget and
[1:08:20]
the cost differences from what we
originally had planned and now uh were
[1:08:24]
some of the things that Mark had
mentioned the delays in the generator
[1:08:27]
site acquisition and the rightway. So
because we had engineering in place when
[1:08:32]
we originally bid this in order to be
able to put a bid in we had a line route
[1:08:35]
engineered
and when the delay happened with the
[1:08:39]
site acquisition and Pocahontas Land
came back and said no you can't go that
[1:08:43]
way we had to go back and re-engineer
it. And while we were doing that, we did
[1:08:47]
the environmental study which found a
bat habitat along that route. So, um
[1:08:53]
that's that's on the second part of it.
But so we re-engineered it a second time
[1:08:57]
to avoid the mining permit and to avoid
the bat habitat. Um but it was because
[1:09:02]
of the delays in the agreement that got
signed with Pocahontas Land was the
[1:09:05]
reason why we got so far behind on that.
Um
[1:09:10]
um and so the but the right-of-way
agreement for the line route from the
[1:09:15]
substation to the generator site was a
pretty agreeable number. I think it was
[1:09:21]
does anybody remember 17
>> 17
[1:09:23]
» $17,000 for the rightway from the
generator site all the way to the
[1:09:27]
substation. That would be a three or
$400,000
[1:09:31]
right away anywhere else, but they were
agreeable uh to do that for that.
[1:09:36]
So the re-engineering costs due to the
the mining permit restrictions and the
[1:09:42]
environmental findings are the two main
drivers in the costs and the delays.
[1:09:49]
Our current projection of of the in cost
increases are between 35 and 40% for the
[1:09:55]
construction and engineering. So the
Mercury 50 has already been purchased.
[1:09:58]
It's on the on site in in San Diego and
will be transported um as soon as it's
[1:10:04]
feasible to get it out here. whatever
makes the most sense. We're making those
[1:10:06]
arrangements, but we have had to um make
arrangements for long-term preservation
[1:10:12]
due to the nature of the delays because
the Mercury 50 generator is ready to
[1:10:16]
receive now and if we were ready with
everything else, we could go ahead and
[1:10:19]
install it, but the we have delays with
the permitting
[1:10:24]
um that were caused by all of the issues
that I've mentioned previously. But the
[1:10:30]
the 35 to 40% additional cost for
construction and engineering is is
[1:10:36]
mainly listed out here for the line
route. On the additional poles after the
[1:10:40]
re-engineering, we originally planned
for 119 poles. Uh on the on the original
[1:10:44]
line route, we're now looking at over
200 poles to make this work. Um the
[1:10:49]
conductor length is roughly the same.
Sorry.
[1:10:51]
» How long is that route now from point A
to B?
[1:10:55]
» It's still four and a half miles. It's
just it has to go through a different
[1:10:58]
route and it requires different pole
length and just it's more complicated.
[1:11:02]
The spans are shorter on some of them so
the poles are closer together. It just
[1:11:07]
roughly 200 and some poles.
>> What is your new number? I know you're
[1:11:12]
saying 35 to 40% increase. What is your
new number on that?
[1:11:15]
» I don't have a specific number. What
we've gone back to because we're waiting
[1:11:18]
on the engineering to still come in,
waiting for the site engineering itself
[1:11:22]
to come back. I can't give you a new
construction and road building and all
[1:11:25]
those costs. I can't give you what those
new numbers are until that is completely
[1:11:29]
finalized and the permits actually come
back um saying that we can do everything
[1:11:33]
that we've planned on doing because
we've lined out the construction route
[1:11:36]
for the permit um but we can't submit
the overall point per permit because
[1:11:41]
it's a joint application in the state of
Virginia and the storm water because we
[1:11:45]
had such a delay with the with the
mineral rights on the on the piece of
[1:11:49]
property which still aren't resolved.
um
[1:11:55]
we we can't give you those new costs.
So, what I do have is a new line route
[1:11:59]
cost, which is roughly one and a half to
$2 million more for the line route
[1:12:04]
itself because of the additional cost in
in the in the labor in the poles itself.
[1:12:10]
» Um and it's and and it's listed here.
>> It's almost double the polls, right?
[1:12:15]
» So, so but but that's the only number
that we really have that we can apply to
[1:12:22]
The overall is really just the
>> which is the majority of the project is
[1:12:26]
the line route. But
>> so we're looking at at least $1.5
[1:12:32]
million additional
>> probably.
[1:12:34]
» And is that already built into this cost
or are you going to come back to us and
[1:12:39]
ask us to
>> pay? There's no there's going to have
[1:12:43]
because we part of it is going to come
from contingency and part of it we're
[1:12:46]
going to have to come up with or the
town.
[1:12:50]
» Yeah. So I'll back up just one slide
here to take a look at that. So um if
[1:12:55]
you just look at 35 to 40% and that's
the initial estimate that I have based
[1:12:59]
on the information that I have
>> um that would be somewhere around 7
[1:13:03]
million7 to $8 million for the
construction and we already have 5.2 to
[1:13:08]
in the budget
um to do that and that includes $542,000
[1:13:14]
of a contingency. But what we're trying
to do to mitigate that is work with
[1:13:19]
Amler to get the $2 million that they
had allocated so that that monies can go
[1:13:23]
towards the line route construction
and stay in compliance. We have to be
[1:13:28]
Americanmade equipment poles and labor
and prevailing wage and all the things
[1:13:31]
that they want. So, there's a lot of
hoops that we have to jump through to
[1:13:34]
qualify for that $2 million.
And we're going to try to avoid
[1:13:38]
everything we can to to um to keep
additional costs from you guys having to
[1:13:43]
go out and borrow anything else. But
this $2 million is not guaranteed
[1:13:47]
either. So, I can't I can't tell. There
will be additional costs. Where the
[1:13:50]
money's come from is what we're trying
to work on on your behalf on a
[1:13:54]
consistent basis. But
>> and and to that premise, we never
[1:13:58]
planned that Amler money because we
didn't know for sure. It was never a
[1:14:02]
guarantee. That was hope that we got
that grant money. So that money was
[1:14:08]
always and Ronnie can tell you that we
never we never pinpointed that and said
[1:14:14]
» correct.
>> But on the good news front on that, they
[1:14:18]
did revert back to where we could use
the less strenuous guidelines for the
[1:14:24]
Amler. They put it they put us to the
new pro I'm sorry they went forward with
[1:14:27]
that instead of backwards. They put us
to the Trump guidelines on the Amler
[1:14:30]
program which makes it much easier. And
if if the only other good thing that
[1:14:34]
comes from a delay and this is why
initially we were hopeful to get the
[1:14:39]
Amler money but we didn't think it was
reality is because you have to have you
[1:14:43]
can't start construction.
>> That's that's the good point. Like if we
[1:14:47]
had been on schedule,
>> then we we wouldn't get the AML money.
[1:14:51]
» All this stuff on the site, you wouldn't
have been able to get the AMR money
[1:14:55]
because we'd already be in construction
already.
[1:14:58]
» So hopefully
>> jump through the hoop. So there's a
[1:15:00]
delay. It brings in money.
>> So hopefully, yeah, if we can if we can
[1:15:04]
secure the Amler money hopefully, then
that offsets, you know, the majority of
[1:15:09]
this uh this overage. Their money has
gotten easier to get when they rolled
[1:15:13]
back the restrictions on on what we had
to comply with NEPwise. But
[1:15:17]
» but we did have it at one point. We had
to forfeit that money because we weren't
[1:15:21]
ready.
>> No, no, no, no, no,
[1:15:23]
» no. They would they had not allocated
any money. You guys hadn't even been
[1:15:26]
accepted into the program. I mean, I
worked through the late the Department
[1:15:29]
of Energy and talked to the Amler folks
when we originally were involved and um
[1:15:36]
there had been some due diligence done
on the town of Richlands, but there was
[1:15:39]
no formal acceptance letter and you guys
had no money earmarked. I mean, they had
[1:15:42]
planned on giving you guys some money,
but there was no
[1:15:45]
» they had approved our project in
controving your project. It wasn't even
[1:15:49]
officially approved or they would have
issued guys a conditional letter of
[1:15:52]
approval.
>> I just I remember we were involved in
[1:15:55]
one of their press releases about
that we were basically going to get the
[1:15:59]
money and a former town manager said we
had to forego that money at that point
[1:16:05]
and then reapply.
>> Yeah. Well, we did because you guys we
[1:16:08]
couldn't I mean
>> Yeah. couldn't take it because we
[1:16:10]
weren't Yeah. Um and since you had
brought up the mineral rights,
[1:16:16]
» what's going to happen if we they never
agree if that's never resolved?
[1:16:22]
Well, that is, you know, for you guys to
decide how you have to move forward with
[1:16:26]
that. Um, I can't tell you exactly how
to move forward with that. I I know that
[1:16:31]
that when the mining company came in and
wanted to mine underneath the pad itself
[1:16:36]
that Embbridge got got notification and
it paused them for about five months on
[1:16:42]
their engineering, would not do any more
engineering on Eur's behalf. And that is
[1:16:46]
a major major delay. Um, and getting
those guys up and going again. They're
[1:16:51]
about to finalize their agreement, but
there is a piece of the agreement that
[1:16:54]
you all you all will have to finalize
for yourselves if that's how you choose
[1:16:59]
to proceed. So that all of the
engineering that we have done on the
[1:17:02]
generator site itself is for is is not
for not because if we engineer that then
[1:17:08]
all those dollars when they take that
coal out from underneath that, no matter
[1:17:11]
what suitable fuel they put back in
there, it'll all have to be restudied
[1:17:14]
from a storm water perspective. It'll
all have to get restudied from
[1:17:17]
engineering so that we can actually put
the generator at the correct elevation
[1:17:21]
because like I previously mentioned
there's everything is GPS located on
[1:17:25]
site. You can't just
>> and and it has a specific elevation that
[1:17:29]
it goes in and everything is pinpointed
to a specific location and the
[1:17:33]
arrangement of the equipment is based on
um everything being where it's supposed
[1:17:37]
to and even the conductivity of the soil
has to get studied for the grounding
[1:17:41]
that has to be done for the generator
itself. So if
[1:17:44]
» to that specific point, I I think that
we should direct um Mike and Mr. Maher
[1:17:51]
to reach out to Blackstone. I think it's
appropriate timing now because you're
[1:17:57]
saying that you've gotten your knowledge
is they're pretty close to an agreement.
[1:18:02]
» Yes.
>> And so I think we should direct them to
[1:18:05]
reach out to them and see if we can get
the agreement now that they won't mine
[1:18:10]
under our site. And so the the the kind
of the the delineation between the rich
[1:18:16]
town of Richlands being protected and
Embridge being protected is 65 ft
[1:18:20]
outside of their rightway. So the
agreement that Blackstone is getting in
[1:18:24]
place or has almost completely gotten in
place with IBridge
[1:18:28]
protects
pipeline and 65 ft outside of that
[1:18:32]
pipeline. Anything that falls 65 feet
outside greater than 65 feet is that's
[1:18:40]
on the pad is something that Richlands
will have to secure that for themselves.
[1:18:44]
» So that agreement would cons would it
would cover portion of our pad not the
[1:18:48]
whole
>> but not the whole pad. Right.
[1:18:50]
» That's correct.
>> How would we cover the whole pad?
[1:18:54]
» We get separate the the lease with
Pocahontas land. You just need to secure
[1:18:59]
that one section so that it doesn't get
mined. and they've I they've already
[1:19:04]
told us that they won't mind that, but
we just need to get that in writing.
[1:19:08]
» Well, it's it's really a couple million
dollar gamble on whether the engineering
[1:19:11]
has to be redone again. If they do,
>> I don't think that they have any desire
[1:19:16]
to do that from the conversation that
I've had. So, I think
[1:19:24]
is going to do that, but but while
you're at it, if they're already signing
[1:19:28]
documents to say they're not going to do
it, it if their word is true, then why
[1:19:33]
would they not hold up and extend
something to the town?
[1:19:35]
» I've said the exact same thing. But
>> but that's that's really what we're
[1:19:39]
talking about here. If if that doesn't
get secured, then it's just the risk
[1:19:42]
that you take on putting all this
infrastructure in there
[1:19:46]
» and then having to redo something.
>> You really have to have that.
[1:19:49]
» Yeah,
>> I believe so. I would also I don't mind
[1:19:53]
to direct them to do that, but I would
also like us to make a decision that if
[1:19:59]
they don't sign that, we hold off on
putting that in because like these
[1:20:06]
gentlemen just told us, that's a couple
million dollar gamble on putting a
[1:20:11]
generator if we don't have that
agreement.
[1:20:15]
» What's that in the CNX, which I feel
like is done. That's sort of the
[1:20:19]
question I have is how close are we on
that?
[1:20:23]
» We have a number that they gave us. I
did call
[1:20:26]
» the funds to do it.
>> I called Mike about that today
[1:20:30]
» and Mike, I don't mean to speak for you,
but he you said that basically you've
[1:20:34]
you've sent several emails and I gave
him a different contact number there
[1:20:38]
today to reach out to. Yeah, I've I've
had talks with CNX and they told me they
[1:20:42]
had an attorney out of Pennsylvania that
was going to draft up an agreement and I
[1:20:47]
have not seen it and I've seen emails to
follow up on that and haven't seen any
[1:20:52]
» any document from them since I think it
was right around Thanksgiving time when
[1:20:56]
they
>> told me they would have me something and
[1:20:58]
I still haven't seen anything.
>> Well, I'm just saying like to to me
[1:21:02]
right just being completely and totally
honest. This is the risk of this is the
[1:21:07]
risk.
>> I couldn't hear you. Sorry.
[1:21:09]
» I said to me, this is this is the risk
to the project. It's this it's delays.
[1:21:16]
» Mhm.
>> Uh because not finalizing the an
[1:21:20]
agreement to where we can move forward
to do what we need to do. It's as you
[1:21:24]
can tell with that clearing window
that's only November to March. Um, it
[1:21:31]
there is on the long side a six-month
time period from the time that we go
[1:21:36]
ahead and say finish up the storm water
permit, finish up the the engineering
[1:21:41]
for the pad so that we can build it.
It's a six-month window.
[1:21:47]
» Mhm.
>> On the long side, 3 months to six
[1:21:50]
months. We're in February, right? So 6
months is
[1:21:54]
» August. So, it's one of those things
like there is no higher priority than
[1:22:01]
driving these things home. You know what
I'm saying? If you got to find the
[1:22:04]
dude's address in Pennsylvania and go up
there and sit in front of his office,
[1:22:07]
like that's what has to happen because
there isn't time to send emails and wait
[1:22:12]
and then let's follow up with it in a
few weeks. Like, this is like time is of
[1:22:17]
the essence. And if we get this and
there's nothing stopping us um from
[1:22:23]
getting this right and knocking it out
of the park for real like we what what
[1:22:28]
what we've found out is that there is
like we asked for the contracts from day
[1:22:34]
one right Ronnie everybody knows guys
can we see the contracts we want to see
[1:22:39]
the power contracts we got to dig into
these power contracts we didn't get them
[1:22:44]
we never got them GDS got them about
what 8 nine months ago.
[1:22:50]
» It was around the same time
>> GDS GDS got the contracts when they put
[1:22:54]
together their pro-form about how to
dispatch the unit. And in that we
[1:23:00]
figured out that the town only has the
availability to to buy or produce or
[1:23:06]
whatever 37% of their power. Of all the
power that the town needs, 63% of it is
[1:23:13]
under contract. and it's under the
contract to the tune of $150 a megawatt
[1:23:18]
on average. That's 15 cents a kilowatt
hour. That's not good.
[1:23:22]
» So, what else we going to do with your
project?
[1:23:25]
» So, no. So, we're, you know, um, so I
don't know if you want to go through any
[1:23:31]
of this anymore.
>> So, I mean, I've already kind of touched
[1:23:33]
on each of these, but this is, you know,
the storm water permit is planning on
[1:23:37]
being submitted in March. They're
they're doing field studies right now
[1:23:40]
that should be submitted in March. Mhm.
>> So that's a 3 to six month approval
[1:23:44]
window. We've been talks with the
tobacco commission. They act like they
[1:23:47]
can put some pressure on politically on
them to get some of these permits
[1:23:51]
returned back in 3 months which helps us
speed up our construction timeline. Uh
[1:23:55]
if it doesn't then, you know, they won't
do the hot tap after October 1st.
[1:23:59]
There's a lot of other deadlines that
we, you know, that we run into. If it
[1:24:02]
takes the full six months between the
back clearing window and when Embbridge
[1:24:06]
can tap their pipeline, we won't even be
able to start construction until
[1:24:11]
uh well into 27. So that's why I
mentioned that Q4 27 is a best case
[1:24:16]
scenario with all of these
>> Q4. I'm lost.
[1:24:19]
» Q fourth quarter 2027. Q4. I'm sorry.
Yes, I
[1:24:23]
» I was thinking Q4. What is that?
February 4th. Thank you. I got you. Q
[1:24:27]
quarter 4. Got it. Thank you.
I have to be explained to.
[1:24:32]
» That's okay. I appreciate it. Maybe I
needed to annunciate, Mayor.
[1:24:36]
» No, no, you're fine. You're fine.
>> So, these are kind of everything I've
[1:24:40]
touched on. It's just all kind of in one
place. We're we we're scheduling the
[1:24:44]
Mercury 50 for delivery. This tells you
the rightway clearing window for the bat
[1:24:48]
habitat. That's where that comes into
play. That's why we can only clear from
[1:24:51]
November to March. Um tells you that
that's pretty much everything we had
[1:24:55]
discussed. But the but the f the risks
are further delays with the land rights.
[1:24:59]
If we don't get that locked up with the
mineral rights, we don't get the CM CNX
[1:25:03]
permit, then all the engineering can
kind of go out the window if we don't
[1:25:06]
secure those. Unless the town feels
comfortable moving forward without
[1:25:10]
those, but that's at your discretion.
>> So the everything about this that's on
[1:25:15]
here is really uh something that we're
that that we can't do until these are
[1:25:22]
secured.
>> Mhm.
[1:25:24]
» Okay. So, it's not at all like, well, we
just want to start it, but we can't.
[1:25:29]
That's why I'm saying that's why I'm
trying to put a lot of emphasis on this.
[1:25:33]
This is a huge deal that we drive this
other stuff and finish it up. And I
[1:25:37]
don't think it's going to take a
tremendous amount of effort. I think the
[1:25:40]
work on it is basically done. People
have agreed. We've got prices. We've got
[1:25:44]
the stuff that we need to do. We're
ready to send them a check. But it's
[1:25:48]
like until the paperwork is done, we
don't want to do go any further on the
[1:25:55]
town's behalf because the reality of it
is we already are. Like Zach had
[1:26:00]
mentioned before, we're operating
extremely out of scope for what we are d
[1:26:06]
for what we uh went under contract to do
because we're acting as an agent for the
[1:26:12]
you know for rich lands and these types
of things are what we're losing sleep at
[1:26:18]
night over
>> because we don't have any control over
[1:26:21]
» mayor
>> and we are uh extremely personally
[1:26:25]
invested in what's going on here.
>> Yes. And um so this is critical. So uh
[1:26:31]
you know there is plenty of actual good
news though based off of where we
[1:26:36]
actually are and the fact that we only
have 37% of the power available to do
[1:26:41]
something about unless we get him to
modify some of these contracts. But what
[1:26:45]
we did we hired a group because GDS was
the group that came in and said okay
[1:26:50]
well you got to do this dispatch in a
different way based on these contracts
[1:26:54]
and this and that. So we went out to a
group PNCAT who runs economic dispatch
[1:27:00]
models for these specific turbines in
multiple locations and said hey how
[1:27:08]
would you dispatch this unit
>> for the town of Richlands based on
[1:27:13]
historical data. So they went back a
year, they took the same turbine, they
[1:27:17]
plugged it into a year, another model,
and they said, "Here is worst case
[1:27:23]
scenario because based off of the uh the
way that the contracts are written, so
[1:27:28]
what we haven't seen, there's an
appendix B that we need for all of these
[1:27:32]
contracts that tells you when you're
allowed to buy power, dispatch power,
[1:27:37]
whatever else." So what we have done is
assumed that you can't pick when you
[1:27:42]
dispatch the unit or when you use the
power that you have under contract.
[1:27:47]
Okay. So they modeled everything um they
modeled everything under a a worst case
[1:27:53]
scenario. And um
>> Mark, are you telling us that Blue Ridge
[1:27:58]
still hasn't provided all of the
addendums to the contract?
[1:28:01]
» No.
>> I have a question. What was the name of
[1:28:03]
the company you said you sought out for
another opinion? Pinat.
[1:28:07]
» How do you spell that?
>> Uh, P E N C A T.
[1:28:11]
» Oh, thank you.
>> And I don't know, is there another
[1:28:12]
division of them that
>> Time out. Time out.
[1:28:15]
» Yeah.
>> Mr. Moore, tomorrow, can you call Blige
[1:28:20]
and demand that we get all the
appendixes to the contract? We have
[1:28:25]
literally asked them a hund,000 times
for this. I didn't know that. I'm sorry.
[1:28:31]
I didn't know that you guys didn't have
that. But the fact that they're not
[1:28:35]
providing all of the information to us
is ridiculous. Please ask for all the
[1:28:40]
appendix. If there's more, if there's
appendix B and C, whatever, I don't
[1:28:43]
care. But make sure we get all of it
because that seems very suspicious that
[1:28:50]
they provided us the contracts less one
of the appendixes. You You got them,
[1:28:54]
didn't you, Ronnie? They emailed them to
you.
[1:28:57]
» Yeah.
>> And you forwarded everything we had to
[1:28:58]
them. So they have the copy. They have
the the same version that we have of the
[1:29:02]
contract. Okay. Yes.
>> But that appendix B tells you when you
[1:29:06]
can buy when you you know that and so
we're have with this we're saying we
[1:29:11]
can't buy at the right time. Right. So u
so
[1:29:17]
» can you make that bigger please?
>> Which which way?
[1:29:20]
» If I'm wrong.
>> That's crazy.
[1:29:26]
» Why would you not give us
>> I'm sorry. I think
[1:29:32]
I'm sorry, just so you know, I I mean it
happens because I asked for the quantum
[1:29:37]
contract and ironically it was missing
um exhibit B and it was it was not
[1:29:45]
intentional. It wasn't suspicious or
anything. It just it happened.
[1:29:49]
» I understand. But the difference with
this is is that multiple people
[1:29:53]
requested this from Blue Ridge on
multiple occasions and they never
[1:29:57]
provided anything. And then when they do
provide it conveniently, the exact piece
[1:30:03]
of information that we need is left out.
>> I for me I like I want you guys in the
[1:30:10]
same room as GDS.
I've there's no
[1:30:13]
» but they've been in the same room as
GDS. They
[1:30:16]
» spent time not with us.
>> Um so I'm pretty lost on where we are
[1:30:23]
with um the generator where we are right
now. So, I've got a little bit of
[1:30:30]
frustration
stemming from that and more questions
[1:30:34]
than other people because I've not been
kept up to date or informed or whatever.
[1:30:41]
So, for me, I want to have a
conversation with you guys and GDS and
[1:30:46]
Blue Ridge. Um, but we can't arrange
that. Uh,
[1:30:52]
» I'm sorry.
>> You can't? Why?
[1:30:54]
Um, it's only myself and Gary Jackson
who would like to see that happen. The
[1:30:59]
we I don't have a majority vote on the
council to
[1:31:02]
» it cost us like six grand every time
that they come.
[1:31:06]
» It's up to $1,800. And I feel like we
could take that out of the the
[1:31:11]
contingency money even, but just to have
a conversation. So, if we're all in the
[1:31:15]
same room, right, we could look at them
and say, "Hey, have you not given them
[1:31:19]
this cuz this is what they're waiting
on." and they you guys could look at
[1:31:23]
them and say we need this and we could
say give it to them. You know what I'm
[1:31:27]
saying? Um because like and you're
really emphasizing
[1:31:30]
time is of the essence here. Um we have
missed the clearing window last year,
[1:31:36]
right? Um and I'm not pointing fingers
or blaming anybody. A lot of that lays
[1:31:42]
on us because again we're just not in
the same room talking about it at the
[1:31:46]
same
>> but none of that none of us missing that
[1:31:48]
clearing window lays on anybody. Doesn't
lay on us. So it doesn't lay on them.
[1:31:52]
» Was crazy out there. I mean, we thought,
oh, look, here's a great spot.
[1:31:56]
» Yeah, it's the middle of nowhere.
>> The gas line is coming through here.
[1:32:00]
There's some electrical infrastructure,
some roads to tap off of. And then next
[1:32:05]
thing you know, it's like, oh, there's
five different interests on this tiny
[1:32:08]
little piece of
>> I'm sorry that happened. I would say
[1:32:12]
research would help that. Let's go on.
If you don't mind, gentlemen, I
[1:32:16]
appreciate what you're doing. We can say
all day who didn't send this and that
[1:32:20]
and that. That doesn't solve anything
right now. So, can we move forward with
[1:32:23]
what we're doing? Thank you.
>> Sure. Um,
[1:32:26]
» thank you very much.
>> So, um,
[1:32:29]
so I know Pinat has talked with GDS.
They've gotten some information from
[1:32:34]
them, but PINCAT is, just so you know,
these aren't some consultants that we
[1:32:38]
hired that kind of fluffed up some
stuff. They're the ones who are actually
[1:32:43]
helping set the controls. They're
working with power engineers and working
[1:32:47]
with solar to set up the controls for
the unit for the dispatch. So they're an
[1:32:52]
integral part of what we're doing here.
>> Okay.
[1:32:54]
» And the dispatch model, not the came
from GDS. So the economic dispatch of
[1:32:59]
the generator was the idea that got
thrown out by GDS and what changed
[1:33:02]
everything for us from the base load
operation that we originally had planned
[1:33:06]
to this economic dispatch.
>> But now we have the numbers to back up
[1:33:10]
what the economic dispatch would look
like. And the reason for the shift from
[1:33:14]
a base load run, you know what I mean by
a base load run? It's just running and
[1:33:19]
we're not up and down and on and off to
uh to a dispatch model. Is this 63% of
[1:33:27]
the power is already under contract?
>> Now, were you aware of this when you
[1:33:30]
started the project?
>> No, sir.
[1:33:32]
» I just was curious. There were some
blocks of power
[1:33:35]
» that were that was you know 2 megawatt
were coming offline and then later on
[1:33:40]
there was more that was coming offline
but we had no idea I don't know if
[1:33:43]
anybody did
>> of the the level of these long-term
[1:33:47]
contracts that weren't going anywhere
you know
[1:33:51]
» I mean I don't mean to interrupt but
mayor we we all sat in the room you were
[1:33:54]
there Allen's Allen was here everybody
but no one no one said 63% of our power
[1:34:01]
not in one meeting. Not one time ever
did someone say, "Well, we're already
[1:34:05]
obligated on 63% of our power." That
includes Blue Ridge, GDS, no one.
[1:34:11]
» Yeah. I mean, I would have been turned
completely away from it, honestly. If it
[1:34:15]
was like if if we had looked into it and
said, "Hey, there's only 37% of the
[1:34:20]
power that's even available at offset."
I' been like, "Well, that's
[1:34:23]
» and I understand your frustration,
right?" But anyway, we we are okay.
[1:34:28]
That's the beautiful thing. So this is
set to only dispatch when the p when the
[1:34:33]
when you could is this to make is that
what is this the the dispatch margin is
[1:34:38]
that when it's over seven cents.
>> So when the the dispatch margin is when
[1:34:41]
it's seven cents profitable for you all
to run over what you would pay on on
[1:34:46]
market for that power and two hours back
to back where you where the generator
[1:34:51]
would would run because this isn't just
a motor that you just turn the key and
[1:34:55]
it starts up. It takes a little while to
start up.
[1:34:57]
» And so what's been modeled in here is
that it it went back and looked at your
[1:35:01]
data at your pricing from the last year
and when it was seven cents more
[1:35:06]
profitable to run this than it was to
buy it on the open market and for two
[1:35:10]
consecutive hours. That's what's being
hardcoded in here. Then the generator
[1:35:14]
will run. That's the only time it's
running. So I mean it was, you know, the
[1:35:18]
hours of operation.
So it's a very
[1:35:22]
» 2400 hours as opposed to
>> all all year, right?
[1:35:26]
» Cost to make the power all in. What's
the all in number? So 4.46.
[1:35:32]
When we came in here the very first
time, we said that we can make power for
[1:35:36]
about 5 cents all in.
>> It's actually 4.5 cents.
[1:35:40]
» Okay. So the bottom line is is that
running it this way when you have that
[1:35:45]
type of a margin and for two hours
minimum, you know, the 10ear savings is
[1:35:50]
right at about 10 million. I mean, right
at about $20 million.
[1:35:55]
» Is that including our debt service?
>> That's not including any debt service.
[1:35:59]
And so here's where it gets a little bit
better, right? We've already engineered
[1:36:05]
everything for the site. We've already
engineered everything at the at the
[1:36:09]
substation, the line, the conductor, the
generator site, everything is sized for
[1:36:14]
a second generator. Okay. So,
>> the the the thing to understand here is
[1:36:19]
that you only have a maximum of about I
think it's 8.8 somewhere around 9
[1:36:25]
megawatt load that you can service.
Okay. So, the most that you can really
[1:36:29]
install right now,
>> the most that you can install without
[1:36:35]
uh you know, going over that would
really be a second generator. You know,
[1:36:39]
it works out to where it's like almost
perfect for another one. So,
[1:36:43]
uh I'm not going to pretend to know
exactly right now what the cost of that
[1:36:47]
would be. I'm going to project that. But
I know that the the 10-year savings on
[1:36:51]
that is 35 million. And that would allow
you to completely offset your mortgage
[1:36:59]
purchases
because you would use your taker
[1:37:03]
contracts for even if it wasn't the best
time to use it, you could use those and
[1:37:09]
you could offset the rest. You know,
you're peak shaving a good amount of the
[1:37:13]
time, which is where you're saving this.
You know, this right here is $ three and
[1:37:17]
a half million dollars because that
almost doubled, right? What is the cap
[1:37:21]
and trans savings from the previous?
What is it? You go back.
[1:37:24]
» I'm zoomed in.
>> Okay. So, it's like $2 million. Do you
[1:37:28]
know what this cap and trans is?
>> No.
[1:37:30]
» It's not it's not energy related. It's
literally your cap your uh your capacity
[1:37:36]
charge and your transmission charge to
get the power. So, it's literally a fee
[1:37:41]
you're paying to not even use any
electricity.
[1:37:46]
» Can we stop right there? And Ronnie,
there's Ronnie in here. So, if we're
[1:37:50]
offsetting $2 million a year, that would
completely offset our debt service.
[1:37:57]
Correct. if we're saving $2 million a
year, which is the initial proposal of
[1:38:02]
this whole thing was that we could
completely offset the debt service on
[1:38:06]
the project by the savings from the
project, which is exactly with one
[1:38:12]
generator. What that does, it more than
offsets the total annual debt payment
[1:38:16]
with $2 million in savings.
>> All right, so go to the next slide
[1:38:21]
again. Okay, so that's your that's your
tenure, right? And then u you know
[1:38:26]
that's completely offsetting this. And
here's the other thing that kind of goes
[1:38:31]
along with the people who economic
development or whatever. There's
[1:38:34]
absolutely nothing stopping you from
coming in and bringing in somebody that
[1:38:38]
uses a megawatt or 2 megawws and saying
hey we're going to lock you in at this
[1:38:43]
you can come in and use this space.
We're going to sell you power at 8 cents
[1:38:47]
or 8 1/2 cents or whatever you want to
sell power for in a locked in contract.
[1:38:52]
There's still available power to use
here because you're not using it all up.
[1:38:57]
You're still the generator. There's
still what what is the usage? Any idea
[1:39:01]
what the percentage usage is on this?
>> No, but I feel like it still has hours
[1:39:05]
or anyway. So, go to the next slide.
[1:39:12]
» Go to the next slide though.
So, here's where it gets super
[1:39:17]
interesting, right? With two generators.
This is calculations used by the people
[1:39:22]
who were setting up the
>> setting up the all the parameters on the
[1:39:27]
generator.
>> Almost 120 million.
[1:39:31]
» One second. We'll get this fixed.
[1:39:36]
» We apologize for that technical problem.
>> Go ahead, Mr. Romano.
[1:39:40]
» No, I was just saying here's your 10ear
number. Same thing. 34.
[1:39:46]
As the cap and trans goes up, like it's
scheduled to keep going up,
[1:39:52]
it's exponential. 20 years from now,
a 4x on your on your on your capex.
[1:40:00]
» Mhm.
>> Huge win.
[1:40:02]
» That's with
>> that's with two
[1:40:04]
» two general. Okay. Well, we working on
the first one.
[1:40:07]
» Yes, sir.
>> Just to be clear.
[1:40:09]
» Yes, sir.
>> We asked them to do this when in two two
[1:40:13]
or three meetings ago. We asked them
what does the number we asked what does
[1:40:16]
it look like
>> with two we had asked Mark to do this
[1:40:19]
that's
>> half it's roughly half on
[1:40:23]
» on on on the one
>> okay
[1:40:25]
» but you can see that this is the the
same information that we got from GDS
[1:40:28]
and the cap and trans is really where
you're saving the most money. you see on
[1:40:31]
the generation itself, you're saving
about threequarters of a million dollars
[1:40:34]
a year, but the cap the capacity avoided
and the transmission costs that are
[1:40:38]
avoided are where you're saving the most
money. And that was what was on that
[1:40:42]
upward trend that we originally talked
about in one of the very first meetings.
[1:40:46]
» Do do you all understand that? And I'm
I'm not trying to to dumb this down, but
[1:40:50]
what what he's talking about is the
reason that this project is so
[1:40:53]
beneficial is we own this line route
that we're engineering. We own 4 and a
[1:40:58]
half miles of line route. So when we
generate for 4.5 cents, we generate it
[1:41:02]
at the site and we deliver it here. It
doesn't cost us a penny. If we were to
[1:41:07]
if if somebody stepped up today and
said, "We'll sell you power at 4.5
[1:41:11]
cents." That'd be awesome, but it don't
cost us 4.5 cents because then we got to
[1:41:16]
pay 10 cents
>> to get it here.
[1:41:20]
» So then you're at 14 to 16 cents. That's
why this is such an exponential win
[1:41:25]
because we own the lines. We generate
the power for four and a half cents and
[1:41:28]
it delivers to our our transfer station
or our substation rather for the same
[1:41:34]
amount. That's what he that's the
difference.
[1:41:36]
» I get that. Thanks. The real issue is we
don't own the land.
[1:41:40]
» And what else? Keep going. I'm listening
intently.
[1:41:44]
» I don't think that there's I I think
that we're right there. We just can't
[1:41:49]
» I'm just asking,
>> you know, I just The only thing holding
[1:41:52]
us back right now is finalizing the
agreements. That's it.
[1:41:55]
» Yeah. finalizing the agreement. The guys
from Blackstone seemed very agreeable.
[1:42:00]
I'm just being honest
>> from the very beginning. They didn't
[1:42:03]
they didn't seem like there was any
intent in holding anything up with the
[1:42:07]
town causing any issues. Definitely
weren't going to do it. They had an
[1:42:11]
economic situation played that they're,
you know, working with Embridge and that
[1:42:16]
seems to be done. I think that's the
perfect time to get something papered up
[1:42:19]
and done with them.
>> Yes, sir. You know, I mean, there's
[1:42:22]
nothing stopping us from just saying,
"Go ahead and finish all the
[1:42:25]
engineering, finish all the other stuff,
get ready to turn in the permits, but
[1:42:29]
it's that's at a risk to you, you guys."
>> You see what I'm saying?
[1:42:33]
» And and it's not a necessary it's not a
negative thing to not own the land. If
[1:42:38]
you draw a circle to determine where we
need to be, the problem with that is is
[1:42:42]
that Pocahontas land owns 99% of all the
land. Mhm.
[1:42:47]
» Because we have to have access to the
gas,
[1:42:50]
» access to the to the line route. But a
long-term lease, there's people who you
[1:42:55]
go to exit 7 or you can go to the
pinnacle. There's people who build
[1:42:58]
buildings, mil multi-million dollar
buildings on land that they don't own.
[1:43:01]
That's that's a common occurrence in
business. It's this whole thought that
[1:43:05]
we have to own the land. We don't have
>> it that way. S I want to clarify that
[1:43:09]
point because I've heard that over and
over
[1:43:12]
from that pipeline was going to be super
expensive. Exactly. This puts us in the
[1:43:17]
closest proximity and as long as we're
in a long-term lease, which we exactly
[1:43:21]
what we what we have with Pocahontas
Land, we have a long-term lease. The key
[1:43:25]
being if we have this agreement laid out
with Blackstone, then we have an
[1:43:29]
agreement with Pocahontas, we have an
agreement with Blackstone that no one's
[1:43:32]
going to mine under our site, then we
are secure and it's no different than us
[1:43:36]
owning land other than we're paying a
lease fee which is built into all of
[1:43:39]
these numbers.
>> Is are they going to sign the agreement
[1:43:42]
that they won't mine them? I mean,
that's been their expression to
[1:43:45]
everybody from day one. I don't know why
they wouldn't. I mean, I think Mike and
[1:43:50]
and Don reach out to him. And I feel
like we all feel a lot more comfortable
[1:43:53]
if they did. And I feel like now's the
time for that
[1:43:56]
» because if they don't, and I think I
don't want to speak for Mayor Curry, but
[1:43:59]
I think when he says we don't own the
land, I've expressed that if we don't
[1:44:04]
have that agreement, they could come
back in a year, 5 years, 10 years, 20
[1:44:09]
years and say, "Hey, we're going to mine
that land unless you give us
[1:44:13]
» You heard Mark say he's been in
conversations with them on phone calls
[1:44:17]
and their whole expression the whole
time has been, "We're not trying to
[1:44:20]
interfere with what you're doing."
>> Yeah. And I I remember you saying that
[1:44:24]
that they told you the same thing, but I
it's still
[1:44:27]
» you want to have something on paper.
>> I I totally agree and that's why that's
[1:44:31]
why I want to direct these guys and I'll
do it by motion if we need to. But and
[1:44:34]
that's why I wanted to to recap and
mayor if it's appropriate. I I can put
[1:44:38]
this some form of motion whatever you
want. But
[1:44:40]
» I don't think we need a motion. They've
got the
[1:44:42]
» but they you know they need to number
one and I've given him some other
[1:44:46]
additional numbers. She's having a hard
time reaching Chuck, but they need to
[1:44:49]
get that deal completed with with uh
with CX. The second thing, they need to
[1:44:56]
go ahead and reach out to um Blackstone
and see if they're at a place where they
[1:45:00]
can do an agreement with us, which I
think they're they will do. And then was
[1:45:05]
there one other another permit or
something to get the appendixes on the
[1:45:09]
current contract
>> on the current contract so we know the
[1:45:11]
district.
>> So you can do
[1:45:12]
» so you guys know what you need to do.
Those are the three action items I have
[1:45:16]
from this discussion so far.
>> But if we get to April, if we get to
[1:45:20]
April or May and we don't have these
things put to bed, then then we have to
[1:45:25]
come back and say, uh,
okay guys, are y'all going to not hold
[1:45:31]
us liable
>> by going ahead and permitting this,
[1:45:35]
doing all these things, or it's with
that clearing window being as absurd as
[1:45:39]
it is, it kicks it out a whole another
year.
[1:45:43]
So, it's just I think it's 100% doable.
I think we got the runway that we need,
[1:45:48]
but it's going to take some, you know,
perseverance. We're going to have to get
[1:45:52]
real serious about this. Push it.
>> Are you guys going to come back to us
[1:45:57]
for approval for the additional million
and a half, whatever
[1:46:02]
the cost, the additional cost?
>> Yeah. Once we understand those, we
[1:46:06]
absolutely will have to. Yeah. I mean it
but it's we have to work through you
[1:46:10]
know I have to we have to lock up the
land rights before we know before we
[1:46:13]
feel comfortable giving you the numbers
for a new engineered you know
[1:46:16]
construction pad and everything else.
The hot tap location means we had to
[1:46:19]
move a road. I mean I could go on and on
but there were there are quite a few
[1:46:23]
things about the scope of the entire
project from the line route to the
[1:46:27]
generator site to all of it that has
dramatically changed since we originally
[1:46:30]
bid this and as you remember it's been
some time.
[1:46:33]
» Yeah. And will you be able when will you
be able to give us like an updated date
[1:46:38]
list like the milestone list?
>> As soon as we have that construction
[1:46:41]
together as soon as the engineering is
finished then we'll be able to provide a
[1:46:44]
much more reasonable estimate of when we
plan to complete.
[1:46:47]
» And have this might be a question for
Ronnie but have we we were supposed to
[1:46:51]
make the final payment December of last
year. Have we made all of those payments
[1:46:56]
to you guys?
>> We still owe them two payments.
[1:46:58]
» Two payments. So we we're just two
payments
[1:47:01]
» about 900,000.
>> And we've paid How much have we paid
[1:47:05]
thus far? Do you know?
>> Oh, thus far?
[1:47:09]
» Yeah. Yeah.
>> 15.5 million.
[1:47:13]
» But part of that is money that went to
Enbridge
[1:47:16]
» directly for the hot tap. We were under
contract for 14.
[1:47:19]
» Yeah. 2.2 went to Inbridge.
>> 2.2 to Enbridge. And
[1:47:24]
» And those are not all in calls for for
Inbridge either. Those were prepaid
[1:47:29]
expenses, but the engineering delays and
everything else could end up costing the
[1:47:32]
town. We don't know. We don't know what
those numbers are until they get done
[1:47:36]
with their engineering either. We have
no control.
[1:47:38]
» Cost more money, too.
>> It could once they settle up at the very
[1:47:41]
end of the project once they're
completed. There could be additional
[1:47:44]
costs that come in from Embridge. I have
no idea or insight into what those would
[1:47:47]
be. So, I I just have to ask, what
happens if you guys come back to us and
[1:47:54]
say, "Okay, this is going to cost
another $3 million."
[1:47:59]
And a majority of this council says,
"We're going to have to pull out. We we
[1:48:03]
cannot keep spending money." Um, I know
at one point you guys kind of gave us an
[1:48:09]
idea of what it would look like to do
that. Um, has that changed at all that
[1:48:15]
cost?
I don't know that I've got that call to
[1:48:20]
my mind. Do you did you have something
specific that you gave me?
[1:48:24]
» I don't remember a number.
>> I don't know. I mean, to me, um, if I
[1:48:29]
was sitting in y'all's shoes, I would
get very serious about
[1:48:34]
figuring out what that extra generation
looks like. because I think when it
[1:48:38]
comes to more grants, when it comes to
um
[1:48:45]
uh financability, long-term finance
ability, the extra generation is it
[1:48:52]
breaks the model. That's that's what I
would
[1:48:56]
» It's hard just from my perspective, and
I'm only speaking for myself. I'm not
[1:48:59]
speaking for anyone else. It's hard to
consider a second generator when we
[1:49:06]
can't get through the first. You know
what I mean? Like once we
[1:49:10]
» doing most of the work for a second. Do
you see what I mean?
[1:49:13]
» Like when you realize it's like
everything except for setting it and
[1:49:17]
connecting it, you are do you are doing
for both right now. You see, you know,
[1:49:23]
so it's a matter like like you like you
said in the beginning, you're frustrated
[1:49:27]
because you hadn't really felt updated
and then you'd like to talk to GDS and
[1:49:31]
you haven't and so like you're just now
having a conversation with us when most
[1:49:35]
likely you had a conversation with us. I
think that if you guys took the time or
[1:49:40]
were able to coordinate the time
>> to to really wrap your head around it, I
[1:49:46]
think you would. I mean, if it's just to
walk in and decide yes or no on
[1:49:51]
something, that's not a comfortable
place to be. But I think you could get
[1:49:54]
comfortable with it.
>> Uh, if you if we take the time to like
[1:49:58]
get the right information across,
>> I completely saying, "Hey, I'm making an
[1:50:02]
educated decision here based on all of
these professionals, you know, but I'm
[1:50:07]
but I'm just telling you I do understand
it from this side intimately." And
[1:50:12]
that's the opportunity
>> is to um offset more than 19% of the
[1:50:19]
available power to offset.
>> Yeah.
[1:50:22]
» And to not and to double like the cap
and trans number the the you know the
[1:50:27]
capacity number and the transmission
number that goes up to a $4 million
[1:50:31]
savings every year. That happens
basically by just putting the available
[1:50:37]
generation right there.
>> It doesn't even really have to turn on.
[1:50:41]
That's what's so weird to to offset that
cap in transit.
[1:50:47]
» I think you're right about like helping
with more updates
[1:50:53]
» and and it's not your fault. I mean,
we've it's we've got a responsibility as
[1:50:57]
well. Um, but I would also ask that when
you do update, and I would say the same
[1:51:02]
about me, not to just talk to me or any
one member of council, but to update
[1:51:08]
through the town manager so he can make
sure that that information has been
[1:51:14]
» I have a I have a I have a bi-weekly
meeting now. Is it It's every two weeks
[1:51:17]
now, Ronnie. But I I had been in direct
com, you know, I had been in direct
[1:51:21]
communication with the town with the
town. If not weekly, it was a bi-weekly
[1:51:25]
update meeting.
>> Question. I appreciate you coming
[1:51:28]
tonight because we all stand to be um
better informed and it's been very
[1:51:32]
helpful for me and I speaking for me uh
and I guess for the council um we were
[1:51:38]
talking about April I forget we hoped to
get something by April. Is it possible
[1:51:43]
that you could give us monthly updates?
Uh I mean either on Zoom or whatever.
[1:51:48]
Can you help us so we're uh feelformed?
I mean what is the best approach? Well,
[1:51:55]
uh, mayor, I I I'll be glad to do it any
way you would like for me to do it. I
[1:51:59]
had been updating according to the the
way that the town manager wanted me to
[1:52:03]
update and I'll be glad to send, you
know, a couple slides on the progress.
[1:52:06]
Right now, we have these these issues
that have to get worked through before I
[1:52:10]
can provide anything else and it's kind
of been in that situation for quite some
[1:52:13]
time.
>> I mean, I'm What council, would you like
[1:52:16]
like a monthly update from these people?
I think it'd be really helpful.
[1:52:20]
» Council members,
>> I would.
[1:52:23]
I can tell.
>> Anybody else want to speak up?
[1:52:25]
» Being completely honest with you, like
it goes back to until we put these
[1:52:30]
couple things to bed. Not going to be an
update.
[1:52:33]
» There's going to be us sitting here like
waiting
[1:52:36]
» for that to be done so that we can move.
>> I feel confident Mr. Mar is going to be
[1:52:41]
all over this this week.
>> Not putting no pressure, D.
[1:52:45]
» Like the call that we have, the
bi-weekly call, is that not something
[1:52:49]
that you guys can participate in?
>> I didn't know you were doing that. We
[1:52:53]
didn't I didn't know you were there.
>> That's been going on since the
[1:52:55]
beginning.
>> I'm sorry. I just didn't realize it.
[1:52:57]
» Uh yeah. And so that's you know it's a
>> it's incremental updates rather than
[1:53:02]
drinking from a fire hose.
>> Majority of the time it's staff and and
[1:53:05]
then meeting every time. So
>> if I can just I think part of what
[1:53:09]
you've got is you've had nine town
managers in three years. You don't have
[1:53:13]
continuity on the project because of
that which would normally be the point
[1:53:17]
that this information would come to.
Right. Yes. And so you're trying to
[1:53:22]
piece together information just like I'm
trying to learn it on the third week of
[1:53:27]
being here.
>> Um the other item is these updates that
[1:53:30]
are there. I certainly think that we can
as staff either recap what's happening
[1:53:35]
every two weeks and provide some type of
update to you because I I think I'm
[1:53:40]
hopefully demonstrating my ability to
communicate and keep you updated.
[1:53:43]
» Absolutely. Um the other thing is is
what the takeaway from tonight is
[1:53:49]
we have time delays which have huge cost
risk around
[1:53:55]
really two things. The CNX contract uh
resolution to get that uh weld cap
[1:54:03]
contract finished and paid for. So, we
know that's done and we have to get a
[1:54:08]
written agreement with Blackstone that
they won't mine under the pad because
[1:54:13]
any further
engineering and investments made on the
[1:54:18]
project are too risky without that in
place.
[1:54:21]
» Yes.
>> And so that is a priority. There's
[1:54:24]
nothing else that's a greater priority
right now than that. And then the third
[1:54:28]
item is which I think is a good piece of
news in tonight's presentation that I've
[1:54:32]
seen anyway is that the dispatching
model still makes this a viable option
[1:54:40]
and even has greater upside once all
this infrastructure is in place and you
[1:54:44]
can just continue to add to it which is
what what the second generation model
[1:54:50]
talks about. But it still comes down to
really knowing what our current contract
[1:54:55]
um usage requirements are in these other
appendances. So that's the third thing
[1:55:00]
that needs to be there. And then um you
know personally I just think that you
[1:55:06]
know
until number one of what I said and
[1:55:11]
number two of what I've said are done
you can't really count on a date to see
[1:55:17]
return for the citizens which is
ultimately our goal right
[1:55:21]
» so um there is no there is no greater
priority that I've heard tonight than
[1:55:27]
that yes
>> I want to point out one more thing about
[1:55:30]
this model
All of that money that we're that we're
[1:55:33]
showing is the savings from what the
town is paying on their electricity. So
[1:55:40]
that savings can either be passed on to
the customer. That savings can be
[1:55:46]
amplified a little bit because you can
say, you know what, we're going to
[1:55:49]
charge one penny more than what this
generation is costing us, which makes
[1:55:55]
the numbers even better. Right? So that
that model that's that's showing there
[1:56:00]
is just a savings from what you
currently what you what you would be
[1:56:05]
going into. Does that make sense?
>> So I didn't I don't want we don't want
[1:56:09]
to complicate it with this other stuff
but that's that's the reality.
[1:56:12]
» Yeah. Reality is that these numbers will
constantly change until that is locked
[1:56:17]
down and you can proceed.
>> That's correct.
[1:56:19]
» Bottom line.
>> Yes. Y so
[1:56:21]
» but we understand this is the biggest
thing that the town has done. We don't
[1:56:25]
take it lightly. We have no problem
coming like last like Seth you messaged
[1:56:30]
me like the day that day and you hey man
did you uh did you not
[1:56:34]
» we were in the meeting and I was like we
never got told about a meeting and you
[1:56:38]
were like oh my bad somebody was
supposed to tell you like you would have
[1:56:41]
been here
>> no and I I want I was going to ask you
[1:56:43]
that very question because that was
asserted by some people that you were
[1:56:47]
told and I knew you were I text you
right here I text you both in a group
[1:56:51]
chat and I said did you know about the
meeting tonight and both of you both of
[1:56:55]
you answered and said No, we had no
clue. And it's not my job or any other
[1:56:59]
council person on here to tell you about
a meeting. It's staff's job to make sure
[1:57:02]
that you're invited to a meeting. And
and that didn't happen. And
[1:57:06]
» we would never just
>> And you've not one time have we invited
[1:57:09]
you guys that you didn't show up or
intentionally not come.
[1:57:12]
» Yeah. So, however it is we need to get
the information across is fine. We can
[1:57:17]
cancel that by meeting and we can do it
at a bi-weekly meeting. We do it later
[1:57:22]
in the day when you guys are off from
work. one. Um, you know, but like I
[1:57:27]
said,
might have approached this differently
[1:57:31]
had we known the available power. It's
incredible that we still got a really
[1:57:35]
solid viable project and as long as we
don't everybody doesn't get all freaked
[1:57:40]
out and the wheels come off this thing.
Still going to be it's going to be an
[1:57:44]
awesome project for the town. There's no
doubt about it.
[1:57:47]
» Thank you.
>> We look forward to continue to work with
[1:57:50]
you. Thank you.
>> Any further questions for council?
[1:57:53]
I have one. Mary
>> Gary,
[1:57:56]
» if you could start tomorrow, what date
how long would it be before it be in
[1:58:00]
production?
[1:58:04]
» Start tomorrow.
>> If we could start tomorrow,
[1:58:07]
» I think he's asking a spitball number. I
mean,
[1:58:11]
» it's fourth quarter 27, right?
>> That would be best case scenario. So,
[1:58:14]
fourth quarter 27.
>> How much delay is that to get us?
[1:58:17]
Because we're delayed by what? Just for
the clearing window. Well, so the
[1:58:20]
construction can start as soon as the
permits come back and then we can start
[1:58:23]
the clearing on the areas that we have
to clear and we can throw,
[1:58:27]
» you know, everybody if we could do it as
in an abbreviated timeline, but it'll
[1:58:31]
cost more with the with the line work
that has to be done. So it's 12 to 15
[1:58:35]
months
>> if if if we
[1:58:37]
» So he's saying they can throw the switch
on it fourth quarter of 27.
[1:58:41]
» Yeah.
>> Right.
[1:58:42]
» Yeah. And and but we are absolutely
delayed.
[1:58:45]
» I got
>> until we get the permits back either
[1:58:48]
way. Right. Here's the thing. We miss We
don't get our contract. We don't button
[1:58:52]
this other stuff up. And guys, we're
kicking it out another 12, 14 months,
[1:58:57]
» you know? I mean,
>> we understand.
[1:59:00]
» Yeah.
>> I think I think we feel it on both
[1:59:04]
sides. We feel it and you feel it. I
think we're all in the same boat.
[1:59:07]
» Yeah, 100%.
>> Trust me.
[1:59:09]
» Yeah.
>> Thank you very much. Any further
[1:59:11]
questions?
>> I do just have one final question. Um,
[1:59:14]
could you give us an updated like if we
were to stop this project today,
[1:59:21]
» could you give us an updated cost
estimate? I know ballpark. Um, like
[1:59:26]
email us and I don't expect you to do it
right now, but what
[1:59:30]
» But I mean, wouldn't any number be
catastrophic? Would terrible.
[1:59:34]
» No, sir. I mean, what? Like if you spent
9 or10 million that you can't get back
[1:59:39]
though, because then you have a payment
on something, you might be able to sell
[1:59:43]
the generator. You probably could sell
the generator.
[1:59:46]
» So, I think and I've got it in my email.
I could pull it up. I think before
[1:59:52]
» when we asked and it's been a few
months. I I don't remember. Um
[2:00:00]
you guys said we would probably be able
to sell the generator. That wouldn't be
[2:00:03]
an issue. and we would be out I don't
remember. I want to say just a couple
[2:00:09]
million. So if I I just want to know,
you know, because I I want to look at
[2:00:15]
it's kind of like you're sitting at a
slot machine or a blackjack table and
[2:00:18]
you're like, "Okay, I'm down $2 million.
Do I want to spend $14 million more to
[2:00:24]
try to get my 2 million back or do I
want to I I just want to know from my
[2:00:28]
information of we we might be it that
number might be catastrophic. You might
[2:00:34]
give me a number that is 9 million and
it's catastrophic and you say you got to
[2:00:38]
go forward. You might come back with a
number that's a million and we we just
[2:00:43]
have that conversation.
>> I mean selling the generator obviously
[2:00:46]
would be a big a big factor in it,
right? So
[2:00:51]
» um
>> yeah, but I mean without selling the
[2:00:54]
generator I know it's going to be a you
know 910 million number right is what
[2:01:00]
can you get from the generator to offset
some? I don't know. But I think that any
[2:01:04]
way you look at it,
I think that that's a catastrophic loss
[2:01:11]
from where you from what you guys set
out to do.
[2:01:14]
» And if you could get these agreements in
place and we can and we can construct
[2:01:18]
this even with the additional costs that
are in there, you can see what the
[2:01:21]
return would be. We've shown you what
those returns can look like on a
[2:01:24]
generation on a cap and trans basis on
the savings that you originally set out
[2:01:28]
to do originally. That's the only way to
recoup the investment at this point. I
[2:01:32]
mean, even if you just cut your losses
and you paid these debts.
[2:01:35]
» And at the end of the day, I can
guarantee you that if we don't do any
[2:01:40]
type of generation that our power rates
are going to continue to increase
[2:01:44]
dramatically. But with us investing in
generation now and hopefully investing
[2:01:50]
in more in the future, we put ourselves
in a position where we can stop our
[2:01:54]
power rates from increasing. Unlike
right now we're at the mercy of
[2:01:59]
transmission which has went up every
year for the past decade and is going to
[2:02:04]
continue to go up exponentially. Power
companies are no longer in the power
[2:02:08]
generation business. Not building power
plants. You guys know this. They're not
[2:02:12]
building power plants. They're investing
in uh these contracts and and
[2:02:16]
transmission. They they realize we can
spend less money and make more money
[2:02:20]
just by increasing transmission rates.
We don't it doesn't cost them anything.
[2:02:24]
So, I can guarantee you our rates are
going to go up if we do nothing. This
[2:02:28]
this sets us up in a place that we can
stem that tide and begin to put our
[2:02:33]
citizens in a place where we can reduce.
Is it an investment? Is it is it an a
[2:02:39]
daunting project? Are we doing something
no one else has ever done before? Yeah,
[2:02:43]
that's exactly what we're doing. And
that comes with challenges. But we're
[2:02:47]
also putting ourselves in a position to
make this viable to live in rich lands,
[2:02:52]
you know, for the foreseeing future.
That's why
[2:02:55]
» over 20 years, not having the generator
cost you $65 million more. You're going
[2:03:03]
to pay you're either going to pay it on
this infrastructure and finish it and
[2:03:08]
pay a whole lot less or you're going to
pay that $65 million over a 20-year
[2:03:13]
period. That's cost savings that we
projected with the generator avoiding.
[2:03:16]
» I would still like to see the number
just for my
[2:03:19]
» I'll be glad I can I'll be glad to put
the number
[2:03:21]
» 100%.
>> I appreciate it.
[2:03:22]
» But I'm just saying the uh um you're
financing it one way or another.
[2:03:27]
» But you know something nobody's looked
at. What have we got? 100 million power
[2:03:32]
company here and we had this generator.
It's worth 200 million. I mean I don't
[2:03:37]
know the number. I'm just using the
number as an example. But the value of
[2:03:44]
this whole thing when you add it into
the power company
[2:03:48]
» really is a asset that's really
priceless.
[2:03:52]
» So you think the generator is going to
add $100 million to the value?
[2:03:55]
» Well, you got picking numbers.
>> You got $65 million. You're going to
[2:03:59]
spend one way or another. If we don't do
the generator, we spend $65 million. If
[2:04:04]
you do do the generator, you're going to
save 35 million.
[2:04:08]
I I I mean I can tell you if we have no
generation 10 years from now, you will
[2:04:12]
not be able to afford to live in this
town. You will not be able to afford the
[2:04:16]
power.
>> I'm sorry. I didn't mean to interrupt
[2:04:17]
you. See, I totally get what you're
saying and that's why we're doing this
[2:04:20]
project. That's the whole point of it
and we we're sold on it.
[2:04:24]
» It's just how we're getting there.
>> Agree.
[2:04:27]
» Any further questions, council?
>> No.
[2:04:30]
» Gentlemen, thank you. Now, where are you
driving back to tonight? Blueville or
[2:04:34]
where?
>> Princeton.
[2:04:35]
» Princeton. I'm going back to Charlotte.
>> Okay. Thank you. I knew I can't remember
[2:04:39]
if you're Bluefield, West Virginia,
>> Lake Norman. I don't know where you are,
[2:04:42]
but I know you're somewhere in the
world. Thank you. Drive safely.
[2:04:46]
» Thank you.
>> Thank you.
[2:04:47]
» If you could just make sure copy that
presentation.
[2:04:50]
» Sure. I I'll print it out and I'll
forward you this the PDFs or whatever so
[2:04:54]
that I don't lose any of the slides.
Thank you for your time.
[2:04:56]
» Thank you so much. We appreciate it.
>> Be safe, gentlemen.
[2:05:03]
Mayor, can I have about a 10-minute
break? Sure. Set this up for
[2:05:08]
» uh 10 minute recess. Thank you. Because
next we have McGill. Thank you.
[2:05:43]
session. We are on Roman numeral 10, uh
item C, McGill task order number four,
[2:05:50]
wastewater treatment plant. And if you
look here, uh we have this in our uh
[2:05:56]
packet right here, wa task order number
four. So I will defer to Mr. Mar and
[2:06:01]
then to uh the gentleman from McGill,
please.
[2:06:05]
» Thank you, mayor. Um, so
in prior council discussions, you all
[2:06:10]
had talked about having uh McGill do the
project management functions
[2:06:17]
um for the wastewater treatment plant um
upcoming construction contract. We went
[2:06:25]
to bid. I'm going to let Wes talk a
little bit about that because we
[2:06:28]
actually got some good news uh on that.
But I think I shared this with you all
[2:06:33]
uh each previously and that is
councils have two different views of
[2:06:40]
contingencies, right? Some people look
at contingencies and say, "Oh, that
[2:06:45]
money is going to be spent and we just
don't know what it is because we can't
[2:06:49]
detail every single thing and we don't
want to make some really high number in
[2:06:53]
this project that we may or may not
use." And so you do you take some
[2:06:57]
percentage of your overall project, put
it in contingency for those unknown
[2:07:01]
items. Other council members sometimes
will say
[2:07:06]
contingency is my savings account that
I'll use if I need it, but I'm not
[2:07:11]
planning to spend it. Right? So, there's
two viewpoints at how people look at
[2:07:15]
that.
>> Thank you.
[2:07:16]
» Um, and the reason that I wanted to talk
about it is because this uh task order 4
[2:07:25]
is planning to be used in the
contingency funds. And a change you'll
[2:07:29]
see in my role as a town manager is I
like to have items not sitting in the
[2:07:35]
contingency when they are known items
that we need to have done. So we need
[2:07:40]
the professional expertise to do the
tasks that are outlined in task order 4.
[2:07:45]
And so I wanted you know Wes to be able
to speak to what that entails, why it's
[2:07:50]
important, what we don't have on staff
to be able to do those type of items and
[2:07:55]
why you would pay for this. And while
we're using contingency to do this, in
[2:07:59]
the future, I've asked them to put these
kind of expenses in the detailed
[2:08:04]
overall project plan and to truly use
the contingency for the unknown. So, if
[2:08:10]
we know we're going to have project
management, then we'll have project
[2:08:13]
management in our cost estimates as an
itemized item. Okay? So, that's just why
[2:08:18]
we're having this discussion. I also
even though you kind of have an overall
[2:08:24]
project associated to this I also
committed to you in session that I would
[2:08:28]
bring any large expenditures to you and
I wouldn't be signing something as your
[2:08:32]
interim without you all going it's okay
to sign it. So it's time to sign this
[2:08:36]
task order 4 as we move forward uh with
this project. Um and so in order for me
[2:08:42]
to sign it I want your authorization to
proceed. So, uh, Wes is going to talk a
[2:08:47]
little bit about kind of what this task
order is, and then at the end of it, I'd
[2:08:51]
like, um, I've asked him to please give
you an update. We had our bid opening on
[2:08:55]
Monday, uh, at 2:00. And just to tell
you kind of where we are with that, um,
[2:09:02]
we will have at the next council
meeting, uh, bring you the actual, uh,
[2:09:08]
next steps for that project. But I think
it's some good news. So, Wes, I'll turn
[2:09:12]
it over to you.
Thank you, Miss Mark. Also, I'm just go
[2:09:17]
ahead and take this moment to mention
that the next council meeting I plan to
[2:09:21]
be with you in person and u that'll that
may uh helps to avoid some technical
[2:09:27]
difficulties as well. Let me also make a
comment about the contingency. uh we we
[2:09:33]
understood uh at the beginning of the
different ways that people look at
[2:09:39]
contingency and one of one thing that
you might have noticed you probably
[2:09:43]
don't have the detailed itemized
cost estimate in front of you that was
[2:09:49]
included in the in the PE that we sent
to DEQ but that uh cost estimate the
[2:09:55]
contingency was 15%
that that number is well above the IND
[2:10:01]
industry standard for contingency
amounts for projects like this which is
[2:10:05]
typically between 5 and 10%. So what we
did was we boosted that contingency
[2:10:11]
number to 15% to cover the cost of
construction administration. One of the
[2:10:16]
reasons we did it that way was because
at the time we had not gotten the
[2:10:20]
information back yet from the
manufacturers as far as lead times for
[2:10:23]
equipment and different things that were
going to affect the project schedule.
[2:10:28]
And of course the project schedule
affects the cost of construction
[2:10:32]
administration. So that's one of the
reasons we did it that way. But I did
[2:10:37]
agree with Mr. Maher after our
discussion that uh going forward we
[2:10:41]
would make sure uh that that we would
find we would figure out how to put that
[2:10:46]
as a line item and not as a contingency
just to avoid confusion going forward in
[2:10:50]
the future. Um, speaking of task order
4, this this project is going to be it's
[2:10:57]
going to be a a big project. It's not uh
the largest that it could be, but it
[2:11:03]
certainly qualifies as a large project.
Um this there is going to be quite a bit
[2:11:12]
of
technical review of shop drawings that
[2:11:17]
those are the um cut sheets and the
drawings that are sent in to the
[2:11:22]
engineer for approval for equipment
that's going to be used in this project.
[2:11:27]
I have received shop drawings before on
previous projects that were uh between
[2:11:32]
600 and a,000 pages and that's that's
not an exaggeration. Those have to be
[2:11:37]
reviewed in detail. And usually when you
get a SH drawing of that size, it gets
[2:11:42]
returned back to the contractor for some
errors of some kind that have to be
[2:11:47]
corrected. Um, a SH drawing of that size
almost always has something that needs
[2:11:51]
to be corrected in it. Um, there are
there are requests for information that
[2:11:56]
will take place during the project that
contractors will ask and and they will
[2:11:59]
be seeking official answers.
There are there's all kinds of
[2:12:04]
coordination with the uh general
contractors, change orders typically
[2:12:09]
take place. There will be inspection
reports and system testing,
[2:12:14]
pre-construction meetings, and ongoing
uh monthly construction progress
[2:12:19]
meetings, warranty inspections. All
kinds of things are going to be taking
[2:12:23]
place in this project that you will need
professional um guidance on during
[2:12:29]
construction phase. And that also
includes all the paperwork like pay
[2:12:33]
applications and so on. you might if you
if you've not dealt with applications
[2:12:37]
and it's possible that all of you have
but if you haven't they're they can get
[2:12:42]
pretty complicated not on the end piece
you know once they go through the
[2:12:46]
process that I put them through at that
point they're pretty simple for you I I
[2:12:50]
typically will review them uh scrutinize
them sign and date them and send them to
[2:12:55]
you once that happens really all you
have to do is just you know make send
[2:13:00]
you write a check to the general
contractor but before that piece
[2:13:05]
the scrutiny that the payout has to go
through uh is is quite extensive and and
[2:13:10]
it involves making sure that that what
the contractor is asking to be paid for
[2:13:14]
has actually been completed. Sometimes
it's not easy to tell that if you're not
[2:13:18]
used to knowing what to look for. Um
there's there's just a lot in the
[2:13:22]
construction administration that goes
wrong. So you definitely want to have
[2:13:27]
for a for a project this size, you
definitely want to have good
[2:13:30]
construction administration. Now, this
task order covers everything that you're
[2:13:34]
going to need. There's you're not going
to get a separate bill for expenses or
[2:13:38]
anything like that, like driving or gas
or miles or anything. There's all the
[2:13:45]
expenses and everything is included in
the task order. And the task order
[2:13:49]
includes all of the paperwork, all of
the administrative duties, all of the
[2:13:54]
site visits, all of the uh the progress
reports, the pre-construction meetings,
[2:14:00]
all the coordination with the with the
contractors. It it really just covers
[2:14:04]
everything that you're going to need
from a construction administration point
[2:14:09]
of view. All you'll need to do is and
your your team is welcome to participate
[2:14:15]
in anything going on. We you'll be
copied on Uh well, what I'll probably do
[2:14:20]
is coordinate with Mr. Mark who should
get copies. I don't want you all to be
[2:14:24]
getting emails that you don't want to
get, but anyone on the Richland team
[2:14:27]
that wants to participate in progress
meetings that we'll be holding every
[2:14:30]
month is welcome to do so. Um so we want
to keep that transparent, but you don't
[2:14:35]
actually have to do anything. M will
handle all the construction
[2:14:39]
administration. We've identified five
members of our team. I'm one of those
[2:14:43]
members and we've got four other members
of team that will be handling various
[2:14:47]
aspects of construction administration.
So really everything from beginning to
[2:14:52]
end will be handled in this task order.
[2:14:58]
» Thank you.
Uh thank you. And you're coming here
[2:15:02]
next for our March meeting, Wes?
>> I will be there in person for your
[2:15:06]
March. Oh,
>> where do you live?
[2:15:10]
» Do you live in Rowan Oak?
I'm in Roman. Yes. But I'll be in person
[2:15:15]
with you in Richmond. Okay. Thank you
very much. Uh any questions uh for Wes
[2:15:21]
or Mr. Maher? If not, is there a motion?
>> I got two questions.
[2:15:26]
» Go ahead.
>> Now, does this cover is this just
[2:15:30]
management of the project or is this
testing and the normal stuff that goes
[2:15:36]
with the engineering part?
[2:15:41]
Your first part question was serious
management and repeat the last part.
[2:15:45]
» Is this just management of the job or is
this like the testing, the inspecting
[2:15:53]
and all of that or do we have to hire a
separate entity to come in and do the
[2:15:58]
testing and stuff like that?
Now the the depends on what kind of
[2:16:04]
testing you're talking about. But for
example, if you're talking about testing
[2:16:08]
of of concrete or testing of rebar, the
kind those kinds of testing, the
[2:16:14]
contractor is going to be responsible
for a third party testing of that kind
[2:16:19]
of equipment. Richlands will not have to
hire anybody else to do any of those
[2:16:23]
things. So we will be managing, but
we'll also be performing. will be also
[2:16:28]
acting as the engineer because there
will be engineering questions will get
[2:16:32]
asked during the construction phase.
They always do it would be impossible to
[2:16:36]
do a project this size and not have
engineering questions get asked. So we
[2:16:40]
will also be acting as the engineer as
well as doing construction
[2:16:43]
administration as far as third party
testing goes. The general contractor is
[2:16:47]
going to be responsible for that.
>> So y'all are going to do the inspection
[2:16:51]
too. The inspection part of it.
>> Yep.
[2:16:54]
» Okay. Okay. Doing weekly inspections on
site weekly inspections of everything
[2:16:59]
that's taking place uh on at the waste
plant.
[2:17:03]
» Okay. Thank you.
>> Any answer?
[2:17:05]
» That's it.
>> Anybody else have any questions?
[2:17:08]
» No.
>> Okay. Is there a motion to authorize Mr.
[2:17:12]
Mar to execute task order number four?
>> I make a motion, Mayor.
[2:17:16]
» All right. Gary has the motion. Is there
a second?
[2:17:19]
» Rick has a second. Any discussion on the
motion? There being no discussion, roll
[2:17:25]
call vote, please.
>> Okay. Seth,
[2:17:27]
» yes.
>> Gary,
[2:17:28]
» yes.
>> Rick,
[2:17:29]
» yes.
>> Shan,
[2:17:31]
» yes.
>> And Laura,
[2:17:32]
» yes.
>> Thank you, council. Mr. Mar, you have
[2:17:35]
your marching orders. Thank you.
>> Finally.
[2:17:38]
» All right. Next, we are on Roman numeral
10.
[2:17:44]
» Of course. Of course.
>> The we opened the bids yesterday for
[2:17:51]
this project. Our project budget was $10
million for this project and that
[2:17:57]
includes the the 15% contingency. So the
actual construction budget was was just
[2:18:03]
a little bit over $8.5 million. And then
with the 15% contingency that brought it
[2:18:09]
to a $10 million budget and the low bid
on the project was $ 8.5 million which
[2:18:16]
is which is very very pleasing. That's
good for Richland. is good for uh for us
[2:18:22]
as well. We wanted to see a bid of that
range. So, we did receive a second bid
[2:18:26]
that was just a little over 11 million,
but the uh low bid was 8.5 million. And
[2:18:32]
we will be able to present an official
recommendation to award totally at the
[2:18:38]
end of this week or maybe early next
week. And then, uh I know you guys will
[2:18:42]
all take that up at your next council
meeting, which I will be at in person as
[2:18:46]
well.
>> Thank you for the information. And
[2:18:49]
again, thank you for your time tonight
and your diligence. Thank you.
[2:18:54]
» You're welcome. Thank you.
>> Have a good evening.
[2:18:57]
» And I'm thrilled with an 8.5 uh million
bid
[2:19:02]
» on a 10 million projected project in
today's time of inflation cost. So, I
[2:19:07]
think we can be really proud that um the
way the bid process went, the
[2:19:12]
specifications that were written, the
questions being answered allow us to get
[2:19:16]
that type of a result. I'm pretty
shocked on that, too, because when we
[2:19:20]
started this sewer treatment plan
update, the the first estimate we had
[2:19:26]
was like 7.3 million if I mean, I can't
remember exactly, but I'm pretty close
[2:19:33]
to what it was. Then during the CO, it
went to like 21 million.
[2:19:37]
» Mhm.
>> Now it's back down to eight.
[2:19:39]
» Well, that's the one area where
construction costs and Gary can say
[2:19:43]
that, you know, some construction
materials have come down.
[2:19:45]
» Yeah. I mean, it's just amazing because
we materials.
[2:19:49]
» We voted to put it off one time when I
was first on council. We voted to put it
[2:19:54]
off because it just went skyrocket.
>> Thank you, Rick.
[2:19:58]
» That's great.
>> Okay. Uh we're Roman numeral 10. Uh item
[2:20:03]
D, uh flood EWP grant match. Okay. Uh
Mr. more.
[2:20:19]
Get my old eyes on this thing here.
[2:20:29]
Okay. back when you had um
the Helen event and you had significant
[2:20:37]
flooding in the town, there was really
direction uh at that time uh by the
[2:20:44]
council to look for grant opportunities
that would allow us to um
[2:20:50]
create resiliency against future floods,
to look for opportunities for funding on
[2:20:55]
the on basically any level uh to improve
um conditions that might take place in
[2:21:05]
the future with future events. And so
the next two items are both related to
[2:21:10]
that time period. Now, all of this has
started before my arrival with you. Uh
[2:21:15]
but one of the programs, the emergency
watershed protection program, um is a
[2:21:21]
program that was identified by the staff
at the time
[2:21:26]
um about the
a program that would would help um
[2:21:33]
locations around natural occurrences,
floods, fires, wind storms, hurricanes,
[2:21:38]
tornadoes, etc. Um
the section of the code that applied
[2:21:45]
this is an EWP authority program. Uh it
was authorized by the Secretary of
[2:21:50]
Agriculture uh the emergency watershed
protection program and it's designed for
[2:21:55]
technical and financial assistance to
implement uh defensible and technically
[2:22:00]
sound emergency recovery measures which
obviously you were in uh at at the time.
[2:22:06]
This particular program is a relatively
new program so a lot of people aren't
[2:22:09]
aware of which is why I'm spend a little
bit of time uh around it. Um
[2:22:16]
it is a coordinated program with FEMA NR
uh CS authority and of course the
[2:22:24]
disaster damages.
um
[2:22:29]
you have a natural event, you have water
shed impairment, an imminent threat, and
[2:22:35]
then obviously you have the emergency
scenario. So um what this program can be
[2:22:41]
used for is permanent structures, houses
and buildings, roads and utilities, dams
[2:22:46]
and flood control areas. Um what it can
um not be used for is standing timber,
[2:22:54]
orchards, ergonomic crops. Um it also
has the the very basis of this program
[2:23:00]
is it must have had negative impact on
property or life in order for this
[2:23:07]
funding to be eligible. And if it didn't
meet that criteria, then it was not uh
[2:23:12]
eligible for funding under this program.
Um
[2:23:17]
there's also some limits on acceptance
like you can't have the same structure
[2:23:22]
uh practice three times within 10 years
and get funding on it again. So um as
[2:23:27]
you um it has to the limits are also on
existing operations and maintenance.
[2:23:33]
It's not allowed to be used for that
repair or rebuild or maintain
[2:23:37]
transportation facilities, utilities or
similar related facilities. I'm not
[2:23:42]
going to go through all the uh items
that it is limited on. I will give you
[2:23:47]
this print out that I have on the screen
today just so you have the program if we
[2:23:52]
decide to move forward with it. Um
basically you put together or did a
[2:23:58]
resource of areas in the town that um
needed to be addressed post event. Um
[2:24:07]
this project was is specifically for
debris removal in your waterways and for
[2:24:12]
stream restoration to uh reduce erosion
and continued impact of future events.
[2:24:20]
Um
it did it does have a cost associated
[2:24:24]
with it. Um we requested
let's see my my numbers right here. Uh
[2:24:31]
it's a 7525%
program. So 75% funded by um the grant,
[2:24:38]
25% by the city, which can be in kind
work or in cash payments. The other item
[2:24:44]
related to this is that you're not
required to do or use all of the funds
[2:24:50]
that are being awarded in this
opportunity today. meaning that um if
[2:24:55]
you're cleaning waterways from debris
and you have various private property
[2:25:00]
owners that are actually along this
route, if you can't get agreement with
[2:25:05]
those individuals, you may abandon that
project because you can't get agreement
[2:25:10]
from the home or the land owner of it to
be able to work on that portion of the
[2:25:14]
property and then you would return the
funds associated to that portion of the
[2:25:18]
project. Um you also can scale down the
money. So, if you don't have the full
[2:25:24]
match amount, which in this case is
um
[2:25:32]
159,000
because the grant uh based on the grant
[2:25:36]
award, you can scale it back to what you
would be willing to fund if you wanted
[2:25:41]
to do these particular projects. And the
issue that you have today is you have to
[2:25:47]
either respond and say okay we're going
to pursue and go to the next step of
[2:25:50]
this um if you don't do projects the
portion that you have to repay is the
[2:25:58]
technical and financial assistance
portion that you received. So if you if
[2:26:04]
you don't spend that then there is not
cost other than
[2:26:09]
um to get out of the program or to
return the money. If you do proceed with
[2:26:13]
it and you take that money and then you
scale back your projects, that portion
[2:26:18]
will be percentage-wise to what you uh
had associated in this grant. And um if
[2:26:25]
you do all of it, then obviously you we
have to come up with $159,000
[2:26:31]
match component. So that's that's grant
one that's on the agenda today. I'm
[2:26:37]
going to have Billy talk about grant
two, which was your flood plan
[2:26:40]
administrator, which is a five-year
position funded um grant, which
[2:26:48]
I believe you also need as many flood
events as you may have here, but that um
[2:26:54]
he can talk about that. It's a much
larger one and there is no match on that
[2:26:58]
particular program. there was a match,
but we applied for um assistance on that
[2:27:04]
portion so that it would be covered
because of the um demographics of our
[2:27:10]
area.
>> Mr. Tomorrow, you need a motion from us
[2:27:13]
to approve up to inind and or andor cash
payments up to 159,000
[2:27:21]
» to proceed with this grant knowing that
we may not use it if there's projects we
[2:27:26]
can't do or we can't an agreement from
property owners, but it's to go to the
[2:27:30]
next step of this award.
>> Is there a time frame?
[2:27:35]
» There is. Um I think I got it in here.
uh I think it's 220
[2:27:44]
work days from the time we begin the
project.
[2:27:48]
» Mhm.
>> So slightly 3/4ers of a year.
[2:27:53]
» Mr. Mayor, I I put that in the form of a
motion uh that we prove up to the full
[2:27:58]
amount subject to, you know, agreements
and that kind of thing.
[2:28:02]
» Okay. There's a motion on the floor to
uh authorize the manager to move ahead
[2:28:06]
with this grant. U is there a second?
>> I'll second. Rick has a second. Is there
[2:28:11]
any discussion on this motion? I want to
say thank you, Billy.
[2:28:16]
Uh, any discussion on this motion?
>> Uh, hearing no discussion. May we have a
[2:28:22]
roll call vote, please?
>> Yeah. Okay. Seth,
[2:28:24]
» yes.
>> Gary,
[2:28:26]
» yes.
>> Rick,
[2:28:26]
» yes.
>> Jan,
[2:28:27]
» yes.
>> And Laura,
[2:28:28]
» yes.
>> Motion carries. Thank you. Now, I'm
[2:28:32]
looking here at the next item on the
agenda. And I do want Billy to come up
[2:28:35]
on the next item because this is the
flood plan administrator position. It's
[2:28:40]
a five-year funded position. There is no
match to the town. What you do have to
[2:28:46]
obviously, so you're hiring someone, you
got someone on board. It's being
[2:28:49]
covered. When you get to the end of five
years, over that 5year period, you have
[2:28:53]
to have incorporated that
uh cost into your budget for it to
[2:28:58]
sustain. Otherwise, the position doesn't
continue. And so that's part of this,
[2:29:04]
you know, commitment to look at and say,
can we have five years of it free, but
[2:29:08]
when we get to the sixth year, uh, to
have this role, this is, you know, going
[2:29:14]
to have to be over that time
incrementally included in future in a
[2:29:17]
future budget.
>> I appreciate that. I have a question. uh
[2:29:21]
at the at the end of the five years a
future council of we don't know who is
[2:29:25]
in sitting here uh would they be
obligated to continue this and hire a
[2:29:30]
person and put that in our budget?
>> It is it is not a requirement to
[2:29:33]
continue it. Now what I want to say on
this is today the the discussion is
[2:29:38]
about we've been awarded it and we've
received the matching
[2:29:43]
funds portion forgiven so you don't have
to come up with that. So, this is 100%
[2:29:48]
funded without any commitment from the
city.
[2:29:52]
» We haven't received all of the paperwork
on this. We've just gotten the
[2:29:56]
notification that we've gotten the award
>> um and we're making you aware of it
[2:30:01]
because obviously
each of these grants we have to respond
[2:30:06]
and say we are we are willing to
continue and pursue moving forward. Um,
[2:30:15]
we will verify all of the contractual
items obviously at that time. Um, and if
[2:30:22]
there's any change than what I'm telling
you today, then I would certainly be
[2:30:25]
back in front of you again. But we did
talk with uh Merchant McIntyre and sent
[2:30:29]
them the original notification that we
received to see if they read it the same
[2:30:34]
way that I read it and Billy read it and
others about the match. They do. um we
[2:30:40]
are to receive the packet in the next uh
5 to 10 days on that. To me, it's a
[2:30:46]
great grant um to be able to do the work
that a um flood plan administrator would
[2:30:55]
do in a town that has these events fully
funded, not coming uh from it. But I we
[2:31:01]
are not aware that there's any required
continued funding of the position.
[2:31:05]
» Thank you. Um, what we would say is you
would see the benefit of that over that
[2:31:09]
five-year period and as you're seeing
that hopefully you would build it into
[2:31:15]
your future funding.
>> Thank you, Mr. Marie. Thank you.
[2:31:19]
» Yeah, we uh we applied here a little
while back for this. I actually applied
[2:31:23]
for 435,000 when they awarded it. They
awarded 657,000
[2:31:28]
which would pay salaries and benefits
packages for five years.
[2:31:34]
Uh, of course, you know, flood plan
administrator job in our town would be
[2:31:39]
pretty huge with this help to get it
with all the problems mitigation issues
[2:31:45]
and and this other grant we're just
talking about. I guess they would be
[2:31:48]
over that too. And also we have what is
uh
[2:31:53]
through the state crisis track which is
how you go along and supposed to go
[2:31:57]
after the flooding event to evaluate the
homes. They have a a online site to do
[2:32:03]
that. We haven't been able to get on
there. There's been some issues with the
[2:32:06]
county log in which we have to go
through and this person would have to be
[2:32:11]
involved in getting that and go to each
home after the flood like we had
[2:32:15]
problems before on the documentation of
people that were flooded. That would be
[2:32:19]
part of their main job plus catching us
up on where we are behind on that at
[2:32:24]
this point. Um,
of course they would go off of uh making
[2:32:29]
sure on the base flood elevations that
everybody's following those rules and
[2:32:33]
regulations when they place a home in
the flood zone. Flood way you can't
[2:32:39]
place a home back in, but flood plane
you can. Um,
[2:32:44]
they would also help with the making
sure people are getting their permits
[2:32:48]
when they redo or clean up or whatever
they have to do on the home. Something
[2:32:52]
happened to it. Um
they would also discourage you know
[2:32:57]
development in these areas because you
can't you don't really want to be
[2:32:59]
developing in in the flood plane.
Uh they would keep up to date and advise
[2:33:06]
other state federal or local permits or
approvals that may be necessary when
[2:33:10]
developing
anything around a flooding area.
[2:33:15]
notify FEMA changes of water course
which is I don't know if y'all noticed
[2:33:20]
I've noticed the last 25 years Clint is
moving so and that really doesn't get
[2:33:25]
reported as well as it should but it is
moving uh educate community members and
[2:33:31]
local officials about flood plane
management which we all need know as
[2:33:35]
much about that as we can
investigate violations of flood plane
[2:33:41]
ordinances initiate corrective action
when there is a issue, they would be in
[2:33:46]
charge of doing that. Uh,
as soon as we get the uh letter, Mr.
[2:33:52]
Mart, as he stated, we'll get in touch
with you on that cuz I always I I'm type
[2:33:57]
person I don't count my chickens till
they hatch. I want to see the award
[2:34:01]
letter besides the one that we got with
all this stuff in it. But, um, it's a
[2:34:06]
good thing. I think it's be really good
for us if we can
[2:34:11]
go forward with this.
>> Thanks, Billy. What kind of action do we
[2:34:15]
need on this, Mr. Maher?
>> This one is just moreformational for you
[2:34:19]
to be aware of and to know that um
assuming it remains a 100%
[2:34:25]
uh grant with no match then we will
proceed unless there's some anxiety
[2:34:31]
among the council uh tonight because
that that would since it would have no
[2:34:36]
budgetary impact it um I would proceed
with that.
[2:34:39]
» Okay.
>> I just have questions. Do we know did in
[2:34:42]
the grant does it outline like what
educational level or you know?
[2:34:47]
» Yes, I I believe it does, but it'll also
when we get this packet,
[2:34:50]
» it'll tell you who who we're looking
for, who we need to hire,
[2:34:52]
» right? It'll it'll give us the
requirements that we have to hire to.
[2:34:56]
» And and I got one other question because
I'm assuming this is an assumption.
[2:35:00]
They're going to say a percentage of
their job, 90% 80% whatever is going to
[2:35:04]
have to be dedicated to this work. But,
you know, a lot of people wear a lot of
[2:35:08]
hats here.
>> Yes. Yes.
[2:35:09]
» Is this an opportunity for us to have
someone that could maybe pick up a few
[2:35:12]
other things? You know,
>> I think it's got a percentage in it, but
[2:35:17]
I don't know exactly.
>> I'm just curious if you can let us know
[2:35:19]
about that because I'm I'm you know, I'm
assuming most of these things come and
[2:35:22]
they say, you know, 75% of their job or
90% or whatever. Maybe it's 100%. I
[2:35:26]
don't know.
>> When I filled out the paperwork, it was
[2:35:28]
on there, but I can't remember the
exact. And that's fine because the good
[2:35:31]
thing is with us that gives us another
full-time employee and maybe someone can
[2:35:35]
wear one less hat because it's related
interrelated to what this person's
[2:35:39]
doing. That that was my only thing that
>> Thank you.
[2:35:43]
» Hey, thank you all.
>> Thank you, Bill. Thanks.
[2:35:46]
» We look forward to the future. Thank
you.
[2:35:49]
» Okay. Uh next, uh we have Roman numeral
10. We're on F Freedom Festival
[2:35:56]
Fireworks. Um, I I hope we have Do we
have information on a cost for that, Mr.
[2:36:00]
Maher? Because I hope we have fireworks.
>> We do. Um,
[2:36:07]
so first of all, you have no money in
the budget. This is one of the items
[2:36:10]
that you took away. And the only reason
that I'm bringing it for you to to touch
[2:36:15]
on this, I get, and correct me if I'm
wrong on that. That is correct, right?
[2:36:21]
um was that this is the time of the year
that they are ordered in order to be
[2:36:27]
here for your event. Um in the last year
you paid $7,250
[2:36:37]
and the cost has had a 15% increase of
product. So it's $8,500 if you did
[2:36:44]
exactly the same thing that you have
historically purchased. and done as a
[2:36:50]
part of Freedom Fest. So, um, obviously
I don't spend money that isn't approved
[2:36:57]
and in a budget. Um, and two, I think
the question is, is it an event? From my
[2:37:04]
perspective, I'll just say to you, this
is the 250th birthday of our country.
[2:37:08]
Um, it's a great time to talk about the
the freedom and living in the United
[2:37:14]
States of America. I think it would be a
terrible year to cut it. uh personally,
[2:37:18]
which is why I'm here in front of you
about it, but I also would need
[2:37:21]
authorization before we pursued that
because we would um you want to speak to
[2:37:27]
where what you told me on funding?
>> Yeah, we would have to do a budget
[2:37:31]
amendment and and take those funds from
unrestricted uh balances
[2:37:35]
» unless we got the money donated.
>> That's correct.
[2:37:40]
» Uh
>> which we do generally every year we get
[2:37:42]
some donations. And then I think this
discussion in general is a question also
[2:37:48]
about just events in the town in
general. You know, you've historically
[2:37:52]
had some of these um you know, I've been
asked by staff to at least bring this up
[2:37:58]
and say, is there still an interest in
the council that we do events? I think
[2:38:02]
you've had a couple of music things that
have taken place historically. You've
[2:38:06]
had this uh festival. Um, so I guess I'm
just generally looking for some
[2:38:12]
direction from the council on that. And
is this something that one of your
[2:38:16]
committees, you do you have an event
committee that you want to have address
[2:38:20]
this um and bring the overall
comprehensive plan back so we talk about
[2:38:24]
it all at once? But the critical
component of this is the ordering of
[2:38:28]
fireworks. That's why it's before you
tonight.
[2:38:32]
» Go ahead and book these fireworks for us
on that same date we've had for several
[2:38:37]
years. and they will wait on the
payment. We don't have, you know, I
[2:38:42]
think the contract said pay half up
front or something like that, but we
[2:38:46]
never have done that. We've generally
waited toward the end to pay the money.
[2:38:54]
» Jan, I'm hearing something. Let me say
something, Mr. Maher. For the past
[2:38:58]
several years, I don't know how many uh
Jan and crew committee, whatever, have
[2:39:03]
put on the Freedom Festival, which is
what you're talking about. I think
[2:39:06]
generally is it the last Saturday in
June. Um and so I it's been very
[2:39:12]
successful and wellreceived and I think
it's important that we have fireworks.
[2:39:17]
There's I know it. I just think it's
important. I don't have to elaborate.
[2:39:21]
» People expect it. I mean
>> and it's part of the 250th anniversary
[2:39:25]
of the country. It's especially
important right now.
[2:39:28]
» Do you need a motion to go forward with
that?
[2:39:32]
I I think because we're talking about
>> a potential budget adjustment if we
[2:39:37]
don't get it covered by sponsorship.
>> I'll make a motion, Mr. Mayor, that we
[2:39:41]
approve to pay for the
>> motion for us to authorize Mr. uh Maher
[2:39:45]
to sign a contract to get the fireworks
and if we don't get the money, we'll
[2:39:51]
have to allocate it. Is that correct?
>> Yes, sir.
[2:39:54]
» We'll allocate it and then maybe pay
that back if you
[2:39:58]
Rick has a second. Any discussion on
this motion? Hearing
[2:40:03]
no discussion, may we have a roll call
vote, please?
[2:40:05]
» Okay, Seth,
>> yes.
[2:40:06]
» Gary, yes.
>> Rick, yes.
[2:40:09]
» And Laura,
>> yes.
[2:40:10]
» It is unanimous. Thank you, council. We
can look forward to that. Okay. Next,
[2:40:14]
we're on Roman numeral 10. Rudy Keith
firet truck pricing discussion. Rudy,
[2:40:21]
» actually, I brought some have more
paperwork back with uh to go in line
[2:40:27]
with what you all had requested last
time.
[2:40:31]
uh for the the change of date.
[2:40:38]
» Nothing changed on it. Everything stayed
the same, but the proposal date did
[2:40:42]
change.
>> Thank you.
[2:40:47]
» Thanks, sir.
>> I put the same It's the same packet just
[2:40:52]
a different front sheet. Thank you.
[2:40:57]
» I think that's
[2:41:02]
» okay.
[2:41:07]
Susan had requested.
[2:41:15]
» So, like I said, uh good evening. Nice
to see you all again today on this
[2:41:20]
project. I know it's been a long evening
for all of us, but uh maybe we can work
[2:41:24]
through the the purchase of this this
piece of apparatus for us.
[2:41:40]
Like I said, it's all the same. It's
just the front sheet's only one
[2:41:43]
different. I got that third I think the
fourth sheet in is where I broke that
[2:41:47]
down last time.
um with the the $100,000 down payment.
[2:41:55]
So you would actually be saving, you
know, roughly $5,000 $125 if you paid
[2:42:00]
with the the $100,000 down. The the big
difference would be upon delivery of the
[2:42:05]
apparatus, you would be looking at a
balance of roughly $470,000
[2:42:11]
at delivery.
>> But just to be clear, this is to replace
[2:42:16]
the tanker that we lost, right?
>> That is correct. at the uh October the
[2:42:19]
10th of 23. Yes.
>> Yes, sir.
[2:42:22]
» And we voted our last meeting to approve
the purchase. Correct.
[2:42:27]
» I think you you all was trying to get
Ronnie to see how he could fund
[2:42:31]
» the uh the down payment or or something
magnitude.
[2:42:36]
» Yeah. So, I I I've done some research
into this and we have 30 about 36,000
[2:42:43]
left over from the uh the first bank and
trust note that we had set aside for
[2:42:49]
part of the down payment. The other
67,000 would we would need to do a
[2:42:53]
budget amendment and uh use unrestricted
funds um for that.
[2:42:58]
» How much do we have left over from the
insurance?
[2:43:02]
» 37 36.
>> No, no, no. He said 37 from the first
[2:43:04]
bank of trust loan. Yeah, the from the
insurance that was from like two years
[2:43:09]
ago. It's it's
>> that was about 70,000, but we we didn't
[2:43:14]
ever designated for this purpose.
>> I just wanted to hear somebody tell me
[2:43:19]
it's gone.
>> Okay. Because just this is side note, if
[2:43:25]
we wreck another truck,
>> we shouldn't allow any of that money to
[2:43:29]
be spent on anything else
>> other than replacing the vehicle that we
[2:43:34]
wrecked.
>> Just just making a point of that.
[2:43:37]
» I know that's irrelevant at this point,
but
[2:43:40]
» relevant. It's relevant,
>> but
[2:43:41]
» we shouldn't do that. Uh cuz then then
you've got $70,000 of what we're looking
[2:43:46]
at $100,000 down payment. So Ronnie, I
guess my question is I don't really see
[2:43:50]
the advantage of paying $100,000 down in
this situation. It it's only going to
[2:43:56]
alter the financing, you know,5 or
$10,000 a year in a situation where
[2:44:03]
every penny counts.
>> Yeah, I I felt the same way. I've also
[2:44:06]
talked to uh had some discussions with
VRA
[2:44:10]
on on loans and um like a 10-year loan,
they had a rate of 10 2.6% 6% a 15-year
[2:44:19]
loan. They had a rate of three and a
quarter. I did not ask them about the
[2:44:22]
20-year, which is the useful life. They
usually don't go over the useful life.
[2:44:26]
So, um those are some other options as
far as the financing.
[2:44:31]
» And I think the the last apparatus we
purchased, uh I think it's on a 10-year
[2:44:36]
note. It's like 65,000 a year is what we
pay on it.
[2:44:41]
» That's with First Community Bank. Okay.
>> This is the thing that I got problem
[2:44:45]
with.
We're paying 575,000
[2:44:49]
for a tanker truck.
[2:44:54]
Okay. Our insurance pays us if we wreck
it 75,000.
[2:44:58]
» Yeah, but it was like 100 years old.
>> But we've got a problem there. What if
[2:45:02]
we wrecked the new fire truck? What are
they going to pay? We paid 750,000 for
[2:45:06]
it. But the problem is is nobody's
keeping up with that, working on that,
[2:45:11]
making sure that we get our money back
from the insurance company. Because if
[2:45:16]
like my equipment, if I don't list what
it's worth,
[2:45:20]
» well, and I don't disagree with you.
However, in this situation, they're only
[2:45:24]
going to pay us what it's worth at the
time. It's not it's not what what I
[2:45:27]
mean, if you buy if I buy a new vehicle
at Rays and I wreck it, you know, a year
[2:45:31]
down the road, it's not worth as much as
it was when I drove it off the lot.
[2:45:34]
» Appreciate it.
>> Yeah. And I think that's a situation.
[2:45:37]
It's the depreciable asset. That thing
was what 20 years older.
[2:45:39]
» The the tanker was probably 25 to 30
years old,
[2:45:43]
» but the truck wasn't
>> the truck was like an ' 07. I mean, that
[2:45:47]
cabin chassis didn't cost $70,000 when
that cabin chassis was bought,
[2:45:51]
» right? So, it's still almost 18 years
old.
[2:45:53]
» Yeah.
>> But we got our we got our money back.
[2:45:56]
But what I'm worried about, if we buy a
$500,000 tanker truck, we need to make
[2:46:01]
sure the insurance will cover that
truck. Well, if we have a loan, then
[2:46:05]
you've got your own right there. You've
got an amortization schedule on it
[2:46:09]
immediately. And and if we do it through
Virginia um resource authority, I feel
[2:46:14]
like that's that's also another credible
factor in that insurance piece. I'm not
[2:46:17]
so much worried about that and I
understand exactly what you're talking
[2:46:20]
about, Rick. But I I feel like in this
situation, we re we probably got more
[2:46:24]
than we should have out of a, you know,
out of a 20 or 30 year old asset. And I
[2:46:30]
still I wish we had that money today cuz
it would make it a lot easier.
[2:46:33]
» Yeah.
>> And we just had uh Skyline that just had
[2:46:37]
re remanufactured everything underneath
the tank probably
[2:46:41]
» I don't know maybe six months prior to
it cuz every all the bolts broke loose
[2:46:44]
out from under
>> and that probably cost it
[2:46:47]
» uh it's probably 10 or 15,000 just for
that. But
[2:46:51]
» I mean and you know they're keeping
meticulous records on this kind of stuff
[2:46:54]
anyway. I I'm not concerned about that
as much as now we got to figure out how
[2:46:58]
to finance a because we don't have a
plan. We have to figure out how to
[2:47:02]
finance a, you know, half a million
dollar fire truck. And thankfully,
[2:47:05]
Virginia Resource Authority will give it
if we go 15 years, we'll get it for 3%,
[2:47:09]
which is wonderful, you know, but at the
same time, we still have to budget now
[2:47:13]
to pay for a tanker truck, which we got
to have because everybody in this town's
[2:47:17]
ISO rating depends on the equipment that
we have, the manpower that we have, and
[2:47:23]
the ability that we have to put out a
fire. You guys have to have that. I know
[2:47:26]
you have uh, you know, interoperation
agreements now. You got other people
[2:47:30]
backing you up. We have another tanker
truck at Clayo Hill. But at the same
[2:47:32]
time, you got two fires that you need
them right now. We're
[2:47:35]
» And that tanker at Clayo Hill is
actually in Ron Oak. Been there since
[2:47:39]
December.
>> It's being repaired. Yeah.
[2:47:41]
» Being prepared. I got email uh Thursday
of last week.
[2:47:45]
» They got all the Darly parts in. They
were just they supposed to start uh
[2:47:49]
fixing it today. Two weeks out, but you
know, that's that's another truck that's
[2:47:54]
the county was gracious enough to give
us a tanker to put in its place and it's
[2:47:57]
it's prevailed. I promise you.
>> What's delivery on this Rudy?
[2:48:01]
» Uh 2 to 3 years. 24 to 30 months I think
is what he said.
[2:48:05]
» So the other benefit is
>> we got we got 24 to 30 months to
[2:48:10]
prepare.
>> Right.
[2:48:12]
» But I mean Ronnie, unless you unless I'm
wrong, my my inclination would be we
[2:48:18]
finance the whole thing. I don't see a
tremendous advantage of us spending
[2:48:22]
$100,000 that extra that we don't have.
>> Yeah. No, no, I agree with that.
[2:48:26]
» Okay.
>> Yeah. your your saving is only $5,125,
[2:48:29]
» right?
>> I mean, to me, that's
[2:48:31]
» I'm not making light of that. It's a
significant amount of money. It's just
[2:48:34]
» for us to not have to put out $100,000
right now is probably makes more sense.
[2:48:37]
» Keith Keith, I got a question.
>> Yes, sir.
[2:48:39]
» What do we have to pay to get it
started?
[2:48:43]
» Nothing. And your payment is due the day
that it's delivered.
[2:48:46]
» Okay.
>> Start the process with VRA and let them
[2:48:50]
know in 24 to 30 months that you're
going to start the finance of this
[2:48:54]
apparatus. And then once it's delivered
from Wisconsin to Ron Oak and then to
[2:48:59]
us, that's when the payment is is
>> But over the next two budgeting cycles,
[2:49:03]
we need to begin to plan
>> and look at incorporate this in.
[2:49:08]
» So what is Go ahead. What is the will of
the council? Would you like to make a
[2:49:12]
motion to proceed?
>> Mr. Mr. Mayor, I'll make a motion that
[2:49:15]
we proceed and that we proceed with
option one, I believe, which is to
[2:49:19]
finance the entire vehicle and have uh
our staff reach out to VRA and begin
[2:49:25]
preparation for that.
>> Okay, there's a motion to proceed. Rick
[2:49:28]
has a second. Is there any discussion on
this motion to get a tanker truck,
[2:49:33]
» which we need hearing? No discussion.
May we have a roll call vote, please,
[2:49:37]
Amanda?
>> Yeah. Okay. Seth,
[2:49:38]
» yes.
>> Gary,
[2:49:39]
» yes.
>> Rick, yes.
[2:49:41]
» Shan, and Laura?
>> Yes.
[2:49:43]
» Motion carries. Thank you, Rudy.
>> Thank you all.
[2:49:45]
» Trucks on the way. All right.
>> Two or three years.
[2:49:47]
» One question, Rudy.
>> Yes, sir.
[2:49:49]
» Is it yellow?
>> No, sir. No, sir. It's red and white.
[2:49:52]
That's the only picture he had. Uh, no.
No. Uh, fire trucks are designed to be
[2:49:56]
red and white for honor and courage.
>> Amen.
[2:49:58]
» Y'all, there's no choice of it.
>> Thank you.
[2:50:01]
» Thank you.
>> I'm glad you said that. That's
[2:50:03]
important.
>> Red and white. Everything we got is red
[2:50:06]
and white.
>> Thank you.
[2:50:09]
That's a cool little tidbit. All right.
It's very important. All right. Next we
[2:50:13]
have uh Roman numeral 10 H salt building
and we have a folder here and I'll defer
[2:50:22]
to Mr. Maher
or whomever
[2:50:27]
Jason come on up chef. So, this is just
a again
[2:50:33]
a bigger discussion. You're having a lot
of them tonight, but um
[2:50:39]
one of the things that we're going at
least from my assessment that we're
[2:50:42]
going to have to think about long term,
right, is all of the assets that we
[2:50:48]
have, their life of them. Things don't
have indefinite lives. You have How many
[2:50:53]
of you have actually seen our current
salt building?
[2:50:57]
» I have.
>> Thank you. It it is with this recent
[2:51:02]
high usage is even worse.
I believe it's a huge safety risk from
[2:51:09]
my experience. You have cracked
foundations, doors that won't open on
[2:51:15]
the back of it now because of its
movement. And when you go with a loader
[2:51:19]
into a building that has that type of
disrepair to try to pick up salt and
[2:51:25]
load it, you're creating risk for your
driver on your loader. You're create of
[2:51:30]
the building collapsing in its current
condition. That's an issue with this. We
[2:51:36]
don't have the capacity we need, which
we've experienced it this year with
[2:51:39]
multiple back-to-back events.
You can't buy enough salt at a time when
[2:51:45]
it's cheap for you to get it because you
can't store it because you don't have
[2:51:50]
capacity in the facility and you have a
building that leaks, which I don't know
[2:51:55]
if you're aware, but water and salt
mixture is not what we want to happen
[2:52:02]
when we're going to use it for uh
spreading on roads and having safety for
[2:52:06]
our streets. So, we look for
opportunities when we have these things
[2:52:11]
come forward for um
what will some of our VOTE money help us
[2:52:18]
do? Because we should think about that
in multiple buckets. We have a bucket of
[2:52:23]
labor when we have these snow events,
when we're doing VOTE roads that we can
[2:52:26]
build back. We have equipment buckets
for where we can get resources um that
[2:52:31]
are utilized on those projects. And then
of course um we have dollars for our our
[2:52:38]
Virginia road paving programs. So I'm
going to let turn over to Jason. I think
[2:52:43]
he did a great job. I'm very proud of
the proposal that he has outlined for
[2:52:48]
you. There are details that still need
to be worked out. Um he had shared with
[2:52:52]
me that some of you have said, "Well,
where are we going to put it?" um which
[2:52:56]
is something that as a council I'd like
you to ultimately end up with a public
[2:53:00]
works committee uh to be able to talk
about these kinds of of things. But
[2:53:05]
that's something that can come forward
because again this is putting in an
[2:53:08]
order. Um you can imagine that all of
the
[2:53:13]
um towns and municipalities in the state
of Virginia today that have similar
[2:53:18]
situations without adequate buildings
are talking about this. And so, um, he
[2:53:25]
can speak to the timing of the the
project. I think it's an item that we
[2:53:30]
should be looking at, which is why I
have it in front of me today.
[2:53:35]
» Thank you.
>> I put together this for you guys. Um,
[2:53:39]
this Greystone Construction, they, uh,
they do a lot with DOS, municipalities
[2:53:46]
across the state of Virginia and all
over the country. Um, the, like Mr. Mar
[2:53:51]
said the great thing about this whole
project is and I added the email just to
[2:53:56]
kind of clarify that. So I reached out
to VOTE to make certain of it and they
[2:54:02]
will fully let us use our maintenance
money for the salt building because we
[2:54:07]
use it so heavily on VOTE roads. So
that's, you know, as far as the money
[2:54:12]
aspect of it, me and Ronnie have made a
few times on it. Um there is no money
[2:54:18]
that I'm asking for. It's just more of,
you know, we got to get this thing
[2:54:22]
moving and so we can have it. You know,
like Mr. Marsh said, if we if we don't
[2:54:29]
get going on it now, then we're not
going to have it by next year or maybe
[2:54:33]
the next year. Um, the VOTE funding is
there. It It is I think, you know, I
[2:54:40]
know we have some paving projects we
want to do, but me and Ronnie's looked
[2:54:44]
at it a few different times, a few
different ways, even moving money. I
[2:54:47]
think tonight he's proposing maybe to
move some money over for labor and stuff
[2:54:51]
like we talked in the past, but um the
the cost of the building is is pretty
[2:54:57]
low considering the type of building it
is versus what
[2:55:02]
uh building kind of building we have
now. So, if you guys have any questions,
[2:55:06]
really now would be the time. I pretty
much laid it all out in front of you,
[2:55:09]
but now's the time to hit the questions,
I guess.
[2:55:14]
» Who are you considering putting this?
That's a really good question. Um, I got
[2:55:19]
He said too, I showed him our our public
works building and where we're at, you
[2:55:23]
know, considering where we are coming
off of 67 to everybody seeing me and
[2:55:28]
Rick has spoke about it a few times. I
know we have the property on Iron
[2:55:32]
Street, you know, that's a thought. Get
us out of the middle of Richlands and
[2:55:36]
then that opens up this property that
you guys have for anything. You know,
[2:55:41]
sky's the limit there. Um,
if that's not an option for you all,
[2:55:47]
then you know we we have the big open
field over here that we could put it.
[2:55:52]
But I think, you know, getting us out of
the middle of Richlands is is the ideal
[2:55:57]
thing. And that would be great to have
that public works committee to kind of
[2:56:01]
sit down and talk through these things
of where where you guys look to see a
[2:56:05]
public works building. Do Let me
question. If we agree to do the
[2:56:09]
building, do we have to identify where
we're building the building today?
[2:56:13]
» No. No. This just gets them to order to
or to get it ordered and then they'll be
[2:56:19]
it'll be probably I talked to the guy
earlier this week. You know, of course,
[2:56:23]
they're not going to give me any kind of
timelines until I say, "Hey, we're
[2:56:26]
buying a building." That's just how that
works. But he feels like where we're at
[2:56:30]
with approval now about middle of
summer, end of summer by he I he ensured
[2:56:36]
me by winter time next year we are
having a structure with salt in it. So
[2:56:42]
and and none of that's kind of
negotiated until we say hey yeah we're
[2:56:46]
going forward with this project.
>> Um obviously we need it. U I'm just
[2:56:52]
looking at pictures. Uh do you what do
you think it's going to look like? Uh
[2:56:57]
you have any thoughts here?
>> Uh I'm looking on page 11. All these
[2:57:02]
place Menota Heights, Upper Marra,
different kinds. Not that it really
[2:57:06]
matters. I just want to It's curious.
>> Yeah. The the more the more one the one
[2:57:11]
that's more along the lines that's in
the the
[2:57:15]
back of this that they presented is the
one that's in the uh North Carolina
[2:57:19]
there in the middle.
>> Monroe.
[2:57:21]
» Monroe. Yep. Monroe. That's that's the
one that it's got the
[2:57:27]
the it's got outside peers and then
inside peers which the only other cost I
[2:57:32]
do want to mention that. So once this is
built I all we have to have is a level
[2:57:36]
surface. That's it. A graveled level
surface. They come in they set the peers
[2:57:41]
they set the inside peers and we they
they're kind of like teed on the bottom.
[2:57:45]
So then the paving company that would be
the other cost which we can also use VOT
[2:57:49]
money for would be paving the inside of
it. So once it's built, then we go in
[2:57:53]
and pave the inside of it and it's a
done deal. And that kind of locks all
[2:57:57]
those peers in once the way they're made
on the bottom. And it's doublewalled. So
[2:58:02]
that galvanized material sets on those
outside peers and then you have inside
[2:58:08]
peers to where your salt actually is
stored. And it kind of you kind of
[2:58:13]
» it's not putting pressure on the
outside.
[2:58:14]
» Exactly. And you don't have that
spillage constantly on on the on the
[2:58:19]
material itself. And I figured a
question. So I reached out to him
[2:58:22]
earlier this week too. I figured a
question that might arise is the
[2:58:26]
lifespan of it being a tarp basically a
fabric building. I figured that was a
[2:58:31]
question. So he he says 20 to 25 years.
And I said the question that I had, you
[2:58:37]
know, was that cost look like? He said
the framing material, you know, is
[2:58:44]
indestructible other than if you just
run it over. He said the, you know, the
[2:58:48]
20 to 25 year mark on the fabric. He
said right now, if I was fab, you know,
[2:58:52]
putting fabric on one now that we had,
you're looking at about a 20 to $30,000
[2:58:56]
cost. You know, 25 years from now, it's
>> going to be more. But
[2:58:59]
» if we're all still standing here, it's
going to be more. But that kind of gives
[2:59:02]
you an idea in today's world what the
fabric cost if you have to refabric it.
[2:59:07]
» So, Ronnie, and you you've checked and
we 100% can use road maintenance funds
[2:59:12]
to pay for this.
>> Yep.
[2:59:14]
The email we have it in.
>> Yeah, I I sent an email.
[2:59:18]
» You you actually emailed me, didn't I?
>> The email's in this packet. If you'll
[2:59:21]
flip, it's like let's see. It's like
middle ways.
[2:59:25]
» It's right here. John Leonard here.
>> The John
[2:59:28]
» Leonard.
>> Leonard is is the guy that's over.
[2:59:31]
» I made certain that that was
>> No, that's great. Great plan. I
[2:59:35]
appreciate that.
>> So,
[2:59:37]
» yeah. I mean, I think we need it. I
think that I'd like to see um I'd like
[2:59:42]
to see us decide where that's going to
be working with with you guys to figure
[2:59:46]
out what that looks like cuz that's we
need to put this into a long range plan
[2:59:51]
with all the everything else and as long
as I know I'm I think this is a a great
[2:59:57]
idea. It's kind of terrifying looking at
that other building.
[3:00:01]
» Do we need a motion on this to proceed?
Is there a motion to authorize uh Shep
[3:00:08]
and Mr. Mar to proceed with the purchase
of this this structure?
[3:00:12]
» I'll make the motion.
>> Rick has the motion. Is there a second?
[3:00:16]
» Second, Mr. Mayor.
>> And Seth, there's a second. Is there any
[3:00:19]
discussion on this motion?
>> I have a question.
[3:00:22]
» Yes.
>> You're checking on the co costs and
[3:00:25]
different things. This is not to
actually purchase right now. This is a
[3:00:30]
purchase.
>> It is the purchase, I think. Yeah.
[3:00:33]
» Do we know the cost?
>> This the Yeah, it's in the back there.
[3:00:37]
The cost is at the bottom. And
>> do we procure this or how do we get
[3:00:40]
this? Is this a already precured?
>> It's source. I don't have to do any kind
[3:00:44]
of procurement. So, it's
>> once I get the go ahead, it's done. That
[3:00:48]
that price.
>> The third page from the back has your
[3:00:51]
cost.
>> It's right here.
[3:00:52]
$60,000.
[3:00:56]
» And if you on the next page, if you have
any questions about that where it says
[3:01:00]
the the add the 20,000, that's if we
don't have a level surface. But, you
[3:01:05]
know, we have the equipment and the
means to add the surface. That's for
[3:01:08]
additional peers. I don't feel like
that's going to be it.
[3:01:14]
» Okay. Any further questions,
>> ma'am?
[3:01:18]
» I do. Yes.
>> Sorry, Gary. You go. You
[3:01:20]
» go ahead. Um, Jason, I just want to tell
you why I'm going to vote no on this.
[3:01:25]
Um, if you would bring this back for the
next budget, and it was in the budget, I
[3:01:31]
would completely work that into the next
budget. U, we've had a lot, even tonight
[3:01:37]
with the fire truck. We've had a lot of
budget amendments, things come up. um
[3:01:43]
nothing to do with you, but the a former
town manager um kind of got creative
[3:01:50]
with some of the VOTE funds. And I
personally want to see and make sure
[3:01:56]
ensure that we are using that not just
for all this equipment, but also to make
[3:02:02]
sure that our paving projects are
covered. Um so tonight I'm going to be a
[3:02:06]
no on it. However, if if and I I think
it'll pass either way, but um if it were
[3:02:14]
in a capital expenditure for the next
budget, I absolutely would work that in
[3:02:18]
there.
>> Okay. Any further discussion? Thank you.
[3:02:23]
» Uh yes, on the uh VOTE funding, Ronnie,
how much paving are we going to do this
[3:02:29]
year
and how much money will be left or is
[3:02:33]
available for how much? I think the new
plan was for us to do like 500,000 every
[3:02:38]
other year and then the other balance of
the 1.3 million we received would be
[3:02:43]
used for things like this labor
materials.
[3:02:48]
Um is that coming quarterly
or
[3:02:52]
» Yes. Yeah, we get 325,000 quarterly.
[3:02:58]
» Thank you, Ron.
>> Any Thank you. Any further questions
[3:03:02]
from council regarding this motion?
Hearing no further questions, may we
[3:03:07]
have a roll call vote, please?
>> Okay. Seth,
[3:03:10]
» yes.
>> Sherry,
[3:03:11]
» no.
>> Rick,
[3:03:12]
» yes.
>> Jan,
[3:03:14]
» yes.
>> And Laura,
[3:03:15]
» no.
>> Motion carries. 3 to two. Let the record
[3:03:18]
reflect. Thank you.
[3:03:23]
» We're good. Thanks, Y.
>> Okay. I think I'm up again.
[3:03:26]
» Yeah, I'm up again.
>> Okay. Now we've next we've got Romanal
[3:03:31]
10 uh I motor graater which is this.
[3:03:39]
So just to give you a quick rundown I
know everybody's tired and ready to get
[3:03:42]
out of here. um when this big snowstorm
come about, you know, when you get when
[3:03:49]
you're getting the levels of snow that
they first said we were going to get
[3:03:52]
that twoft, you know, on range, you
know, that becomes really hard for the
[3:03:58]
snow trucks to plow back. So, you know,
VOTE, uh Rick can speak to this, all
[3:04:02]
other companies, they start seeking out
graders. Uh you know, a grater has the
[3:04:07]
ability to have that down pressure. It's
a lot bigger machine to kick that snow
[3:04:11]
off the road and get it kicked back. Um,
we've always did that and through big
[3:04:16]
snows. We've not had a lot of big snows
in the last several years. Some of you
[3:04:19]
have maybe have seen it. Some of you may
have not. But so I kind of panicked a
[3:04:24]
little bit when when I knew we was going
to get that level of snow because our
[3:04:27]
motor is a 1984 model and it's been
broke down since last year. It's can't
[3:04:33]
find parts for it. It's it's just been a
nightmare. Just a money pit. So
[3:04:37]
scrambled a little bit. Carter Cat of
course is biggest greater place to
[3:04:43]
purchase rental here and around close.
Then John Deere everybody in the state
[3:04:48]
grabbed graders up. We we had nothing to
get. So I reached out and found you know
[3:04:52]
United Rental Company and they actually
didn't have this grater. They on their
[3:04:57]
lot and then they called me back and
said, "Hey, you're in luck. We actually
[3:05:01]
have one." So, of course, I went ahead
and rented it. And going back to VOTE
[3:05:06]
funds, you know, all that all that time,
and it kind of talks about that in in in
[3:05:13]
the financial plan, you know, all that
time spent with that greater. Uh we have
[3:05:17]
a set rate that we charge hourly when we
run a machine. So, that's per the
[3:05:24]
operator, the machine, what have you.
So, we had a plan to pay that 10,000
[3:05:30]
rental costs back through using it
through that snowstorm. Um, went ahead
[3:05:34]
rented the grater. Then they let us know
that, you know, hey, this grater is
[3:05:38]
actually for sale. Uh, just a crazy
opportunity that come about. They
[3:05:43]
offered to sell the sell the grater to
us for $70,000.
[3:05:47]
I knew that, you know, asking for that
amount just to come out of general fund
[3:05:51]
money was just uncalled for right now. I
know the situation. I see the budget.
[3:05:55]
Uh, so I kind of hit the ground running
on my budget that's already approved and
[3:06:02]
I started looking towards my my street
bridge sidewalk maintenance. So in my
[3:06:06]
budget, that money is more so for town
road projects. Um, most of the time
[3:06:12]
that's eat up pretty quick. The reason
that there's a a bigger amount in there
[3:06:16]
right now is because as all of you know,
we work pretty much all summer, all fall
[3:06:21]
on BOT projects like the project up at
the school. That was where our main
[3:06:26]
focus went to. So, I had available money
sitting there and also in my traffic
[3:06:32]
safety line, I had money in my budget
due to the fact that I know that's
[3:06:37]
amount that's not really used right now,
but typically it is. But where the
[3:06:42]
detour project come in, I used a lot of
VOTE money to to fund buying a lot of
[3:06:47]
the traffic safety stuff that we would
generally buy. So, I did have money in
[3:06:52]
both of those accounts. So, I'm not
really asking to for money. I'm asking
[3:06:57]
for more permission to purchase this
grater with money that I have in my
[3:07:01]
budget.
>> So, thank you, Chef. I've got a I have a
[3:07:05]
quick question. Uh, you run this
particular grade, right? Personally,
[3:07:09]
» yes. Do you think it's in good shape for
a used one?
[3:07:12]
» Absolutely. It is. It is in great shape.
I I personally think it would be a great
[3:07:18]
buy for the town. I honestly think this
thing will be here when I'm retired and
[3:07:23]
gone and 20, 30 years from now. It is a
great grater. You know, and that's why
[3:07:27]
we've always held on to a grater for so
many years. You know, the one that I
[3:07:31]
first run when I come here was a 1960
model. Uh they had that thing for 40ome
[3:07:36]
years, 50 some years. uh this dresser
they've had for 20ome years. They bought
[3:07:42]
from the county, I think, for the same
almost the same price 20ome years ago.
[3:07:47]
So, you know, absolutely. I think this
is a great purchase. $70,000 for
[3:07:52]
$300,000 machine. Uh that, you know, I
know a lot of the heartburn with a
[3:07:58]
grader is, well, we don't use it a lot.
But if you all think back to
[3:08:03]
when I took the public works director
job, I said there's a lot of things that
[3:08:06]
we that a lot of the reason our roads
are in the shape that they're in is lack
[3:08:11]
of maintenance that we wasn't doing that
made our roads in bad shape. And
[3:08:15]
shouldering roads is one of those. And
you know, if you all remember back when
[3:08:19]
we did Kinch Ridge, you know that that
road's holding up great. The shoulders
[3:08:23]
aren't breaking off, but we're they
haven't done that in a year or so. This
[3:08:26]
summer we're going to have to rent a
grater again and cut shoulders across
[3:08:31]
Kent Ridge. We're going to have to cut
shoulders on Pizza Hut Highway. We're
[3:08:34]
going to have to cut shoulders going on
across Farmer Street. You know the if
[3:08:37]
you don't maintain those roads, you're
going to then you're going to be, you
[3:08:41]
know, breaking the sides off. It is an
important piece of equipment. And when
[3:08:45]
it snows, like this past snow, had we
not had it, the roads would have been in
[3:08:50]
awful shape. When everything froze, we
got down to zero temperatures. I know
[3:08:54]
Laura seen me coming up through Hidden
Valley. There's no getting that snow off
[3:08:58]
the road. Plow trucks, they have no down
pressure. You can't cut that stuff off.
[3:09:02]
When when it comes to freezing, you have
to have something to cut it off. I think
[3:09:05]
you even seen I come up your place.
>> Uh that was so packed down, those plow
[3:09:10]
trucks aren't going to pile it off. Had
I not made I mean made that run up
[3:09:13]
there, you'd have never it would have
been days before that melted off. So
[3:09:17]
having it during these last two
snowstorms was and especially where we
[3:09:21]
were short on salt was
was a great move by renting it and I
[3:09:27]
think it'd be a great move to you know
have y'all's permission to
[3:09:32]
» actually using this gratorm.
>> Yes, ma'am. They had to rent it cuz the
[3:09:38]
other one's been broken down.
>> I saw I saw it but I I thought they got
[3:09:42]
it fixed.
>> It's the rented one. It's It's only 45
[3:09:48]
years old.
>> Uh council, what you you've got the
[3:09:51]
money. What you're wanting is approval.
>> Yeah. It's just such a large, you know,
[3:09:57]
expense and we're going to have to move
money around to do it.
[3:10:00]
» That's very thoughtful to ask. Council
council, what is your desire here? Would
[3:10:04]
you like a motion to approve this? I
think it would be a proper one.
[3:10:08]
I'm just going to say I cannot support
it. Another piece of equipment to set
[3:10:13]
out in the weather over there because
that's the worst thing on this
[3:10:16]
equipment. We've got a bunch of it over
there now. New equipment. We should
[3:10:20]
build some sheds or something first. But
if we go with this now, I will be a no
[3:10:25]
due to that back. Sorry. Okay. Any other
uh thoughts, council?
[3:10:32]
Um
>> I same thing, Jason. I'm sorry. I know
[3:10:35]
you guys need it, but we have not had a
good and it's not you. We as the
[3:10:41]
council, we've not had a good track
record of following our own budget this
[3:10:44]
year. So, I will be a no on it. But
again, um I think before we do our next
[3:10:51]
budget, I think we should have you guys
more involved and talk about your
[3:10:56]
capital projects so we can work that
into a budget, start to plan for it. Um,
[3:11:02]
but since it is an amendment, budget
amendment now, I' I've got to be a no on
[3:11:07]
it until the next budget.
>> Well, we have uh no motion. We have two
[3:11:12]
nos.
>> Well,
[3:11:13]
» anybody want to take um an alternate
course?
[3:11:17]
» Question. What happened with the sheds
that you all were going to build to
[3:11:21]
store the equipment in?
>> They kind of died when Jason left and I
[3:11:26]
actually spoke it on, you know, and it
it all kind of falls in together, Gary.
[3:11:30]
me and you've talked about it.
>> When this salt building comes, you guys
[3:11:34]
absolutely need to build us a public
works department. We have 20ome men in
[3:11:38]
one bathroom. We don't, you know, I
showed Don a place. We don't have a
[3:11:42]
place. You know, absolutely we have
nowhere to store this equipment, but
[3:11:46]
absolutely we can't do work without the
equipment. So, you know, you're either
[3:11:50]
going to pay for this grater now or
you're going to pay for it throughout
[3:11:53]
the year if you want road maintenance
done because it's 10 grand to rent one
[3:11:57]
every time.
>> I have a question. I mean, if we have
[3:12:00]
this salt building built,
>> can you not park some stuff underneath
[3:12:03]
the salt building?
>> Absolutely. I mean,
[3:12:04]
» during most of the year, we're not I
mean, obviously not during, you know,
[3:12:08]
the time when we're using it, but
>> I don't I don't see you having it full
[3:12:11]
of salt all the time.
>> That ain't a good idea. Salt rust metal
[3:12:16]
and parking equipment in there just
makes
[3:12:19]
» it's not a bad idea. No,
>> you know, my thought was and I talked to
[3:12:22]
Don about it. You know, if we get the
salt built, which you know, you guys
[3:12:26]
approved moving forward with the salt
building, we find a home for it. I would
[3:12:30]
like to sit down with you guys and talk
to you about my budget and be involved
[3:12:35]
in it and let you understand why we're
doing the things we're doing and we're
[3:12:39]
not just wastefully spending things. And
I would like to put in, you know, if
[3:12:44]
we're going to build our salt building
on Iron Street, then let's budget in
[3:12:47]
letting me get a general contractor to
build some sheds to put this equipment
[3:12:51]
under. You absolutely need your
equipment under sheds. But
[3:12:55]
» I mean, I and I understand what Gary and
Laura are saying. I completely agree
[3:12:59]
with that. Here's the problem. If he
came to us during the budget cycle and
[3:13:03]
he said, "I need $100,000 to buy a
grater." I know what everybody would
[3:13:07]
have said. No, we're not buying any
equipment. So, I mean, correct me if I'm
[3:13:13]
wrong, but I'm pretty sure that we said
no expenditures, no rate. You know what
[3:13:18]
I'm saying? We wouldn't have agreed to
do it then anyway. So, I I 100% get what
[3:13:23]
we're saying. But luckily, this year
with the bridge project, you haven't had
[3:13:27]
to use your bridge funds because we got
a we don't have we only have two bridges
[3:13:33]
instead of three. You know, you're not
doing as much. And thankfully once this
[3:13:37]
bridge is complete, we have three fairly
new bridges. I'd say a lot of your
[3:13:42]
bridge funds every year went to fix this
mess.
[3:13:45]
» It did
>> over here. So you haven't had to spend
[3:13:48]
that this year cuz that's under contract
with VOTE to build that.
[3:13:51]
» We do have another bridge to build Maple
Lane.
[3:13:56]
» Is that this year? Is that in
>> I don't know.
[3:13:58]
» Maple Lane will should you know we
should be moving forward with FEMA money
[3:14:03]
with Maple Lane. That's to tear the
house down. We're not building a bridge,
[3:14:06]
right?
>> Yeah. We don't Yeah, we're not even
[3:14:08]
looking.
>> There won't be a bridge.
[3:14:10]
» House is gone. Yeah,
>> just a road.
[3:14:12]
» We're actually I'm getting ready to put
out working on RFP now to put out for
[3:14:16]
someone to go ahead this summer and move
forward with the paving and everything
[3:14:20]
where we already tore the house down. So
hopefully by, you know, just, you know,
[3:14:24]
how slow FEMA moves, hopefully by end of
the summer, you have a road through
[3:14:28]
there and there is no bridge issue. And
that's that's not money. That's FEMA
[3:14:32]
money that that we have. But I mean, I
guess that's my point is that we're
[3:14:36]
close to the end of your budget cycle
that still leaves you some money in
[3:14:40]
there. I mean, I I get it. We have to
have a place to store this stuff. Maybe
[3:14:45]
when we get to the end of his budget
cycle, whatever money's left, we can
[3:14:49]
take that money and allocate that to
build buildings wherever we do this for
[3:14:53]
our equipment. You know, hopefully he
doesn't spend the rest of his money, but
[3:14:58]
you know, it's definitely something that
we need. And if we if we have two more
[3:15:03]
snow events, we're going to spend
another $20,000 anyway renting one.
[3:15:08]
» Well, time you do shoulders and stuff
this summer, you you're going to spend
[3:15:12]
304,000 on something,
>> right?
[3:15:14]
» So, you might as well pay 70. And
>> I mean, that's just But I'll put that in
[3:15:18]
the form of a motion that we allow the
the inner budgetary transfers to pay for
[3:15:26]
the equipment out of this year's
existing budget. There's a motion on the
[3:15:31]
floor. Is there a second?
>> I'll second.
[3:15:34]
» Rick has a second. Any further
discussion on this motion to authorize
[3:15:39]
uh SEP to move forward with the purchase
of this grater?
[3:15:43]
» Mayor Curry, may I speak?
>> Yes.
[3:15:45]
» Um just we we did um approve some
capital expenditures and equipment
[3:15:52]
purchases in this past budget that we
approved now. And to me, like I said, I
[3:15:59]
know you need it. If it were the next
budget, I would absolutely work it in. I
[3:16:05]
think we me I will take responsibility.
Made a big mistake in not asking the
[3:16:11]
department heads to come in more during
the budget cycle. Um and asking you guys
[3:16:18]
what do you need? What are we looking at
during, you know, during this budget
[3:16:21]
cycle? Um but and we did a couple in a
couple departments factor some of that
[3:16:28]
stuff in last budget. Um and I'm totally
willing to do it again in this budget.
[3:16:35]
And again, Jason, it was my fault for
not speaking up more and saying, "Hey,
[3:16:40]
let's get the department heads in here."
So that's that's just why I'm a know. I
[3:16:46]
just wanted to clarify. We we did I know
Jordan and I did a lot more with the
[3:16:50]
budget this past year, but we did factor
in some equipment stuff.
[3:16:55]
» Last thing, Mr. Mayor. Only thing I else
I would say is that I totally agree with
[3:16:58]
y'all. If we were spending any money
outside of the budget, if we were asking
[3:17:01]
for money from general fund, I would be
a no as well. The only reason that I'm
[3:17:05]
willing to do this is because you do
have extra money in your budget. And I
[3:17:09]
appreciate you and I appreciate Don
coming to us with this and not just
[3:17:13]
making the just not doing it without
asking us and then asking us to approve
[3:17:18]
it after the fact. I appreciate that.
>> I'd I'd also like to say I got them if
[3:17:23]
we approve this tonight, they're going
to wave the rental 10,000 and I mean
[3:17:28]
we're 3 weeks in that thing. They but I
told them, you know, if I can get an
[3:17:32]
answer yes, then they're going to wave
that 10,000 and we're just going to pay
[3:17:36]
70,000 for the greater. You're not
paying 80,000 for the grinder. You only
[3:17:39]
pay 70 for it.
>> Fantast.
[3:17:58]
I'm no math guy, but you guys can add
that up pretty quick. I I figured I'll
[3:18:03]
tell you with this. I figured when I
when I rented it, I could run it for I
[3:18:07]
think a like I think we rented it for
160 hours is a month.
[3:18:13]
» I think I could run that for like 2 and
1/2 weeks and I would I would already
[3:18:16]
made like
>> 13,000 on a $10,000 rental 208.
[3:18:21]
» Yeah. So we I mean it pays for this
grader will pay itself back when we do
[3:18:25]
budget amendments through and we use it
on VOT roads. And one more thing I'd
[3:18:29]
like to add is if you guys do let us
department heads come in. I've already
[3:18:34]
showed Don a little bit of it. I'm
working on like a little PowerPoint to
[3:18:38]
show you guys how I do work my VOTE
money and how I am using the eligibility
[3:18:43]
tools that they give me and looking at
ways that we can use it towards
[3:18:48]
equipment purchases or there's so much
stuff we can use that's not going to
[3:18:52]
take from the general fund because
that's where my budget comes from that
[3:18:56]
we can use for VOC money if we get a
paving schedule. You know, it's it's got
[3:19:00]
to be planned out though. It can't just
be I agree with Laura. just can't we
[3:19:04]
can't you know just willy-nilly do it
but we're not this is not you know we're
[3:19:09]
we're looking there
>> it's there
[3:19:11]
» I'm not your learn long-term town
manager yet but I will tell you just
[3:19:15]
from a process perspective in my
experience you need a couple of these
[3:19:20]
departments as in actively involved in
the budget process your your public
[3:19:26]
works is a huge area that should be
involved you also need long-term
[3:19:30]
planning because everything's not about
a short 12-month period. You've got
[3:19:34]
buildings that don't have an indefinite
life. You have equipment that doesn't
[3:19:38]
have an indefinite life. You have pieces
of things that you have to build into a
[3:19:42]
structure to replace. It's just a part
of how
[3:19:47]
a town, no matter what size it is, has
to manage those assets. And on top of
[3:19:52]
that, you've also got to continue to
address your payroll, your benefits
[3:19:58]
cost. I mean, all of these things, you
know, work together. your capital plan,
[3:20:03]
your operating plan, um your your
vision.
[3:20:07]
We really shouldn't have a public works
building with 20ome people in one
[3:20:12]
bathroom that with leaking roofs. I
mean, to me, I'm taught that when you
[3:20:17]
get water in a structure from the roof
roof itself, you're going to have a
[3:20:20]
deteriorating structure. I mean, that's
what's happening obviously with that
[3:20:23]
salt building. So I think there's really
some long-term strategy opportunities
[3:20:30]
around fleets as a category, around
buildings as a category, and then your
[3:20:36]
operating structure. And you know, I'm
smart enough to know you can't do all
[3:20:40]
these things in one time. So you also
have to prioritize what's important,
[3:20:44]
what's tied to a service that people
value, and what isn't, what can wait.
[3:20:48]
Um, and because you're going to need you
when you just look at the equipment
[3:20:54]
you've got, trash trucks don't last
forever, right? And you have a
[3:20:58]
sanitation business, you know, roads. To
me, we got to be careful about not
[3:21:03]
stepping over a dollar and picking up a
dime
[3:21:07]
because it is about cost,
not just the price of things. And what
[3:21:12]
is that long-term cost over that time
period? So, um,
[3:21:18]
we're trying to be very conscious when
we bring these decisions to you and say
[3:21:21]
we're looking at it. So, to me, a
$300,000 piece of equipment for $70,000,
[3:21:27]
waving a $10,000 rental fee that would
have made it 80 if we had rented it and
[3:21:32]
paid 10. That's the kind of negotiating
things that we're trying to do and bring
[3:21:36]
you these opportunities. And I
completely agree with Gary that you
[3:21:41]
really need um places to park equipment
because part of their long-term care is
[3:21:48]
protection from elements. But again,
that's a facilities uh discussion and we
[3:21:54]
have to prioritize what what we do
because every town has limited
[3:21:59]
resources.
>> Thank you.
[3:22:01]
» May I?
>> Um this we have a motion going on. We
[3:22:04]
have two comments. Is this your second
one, Laura? Okay, go ahead.
[3:22:09]
» Um, also
there was an issue where we're paying
[3:22:16]
quite a bit of repairs for damage being
done by one of the trucks. Will everyone
[3:22:22]
be allowed to drive this grater or are
you
[3:22:26]
» as as I have some people I'm training?
As of right now, I'm the only one that's
[3:22:32]
probably going to be running that grater
because I'm the only one that can. It's
[3:22:35]
kind of a little harder machine to run.
I have a few guys I'm teaching. We're
[3:22:40]
working on it. But yeah, no. And here's
the thing. You got to have like on those
[3:22:47]
I know we've talked about some damages
and things along the lines. You know,
[3:22:51]
when we're when you're working with
heavy equipment, those things do happen.
[3:22:54]
You know, there's a lot of moving parts,
a lot of big, you know, a lot of tight
[3:22:58]
quarters. You know, you take that
grapple truck, uh, just drive down one
[3:23:01]
of these alleyways over here and then
just in your car and then imagine that
[3:23:06]
grapple truck in that alleyway and that
person puts a whole grapple truckload of
[3:23:11]
brush in that same alleyway, you know.
So things do we do have accidents but
[3:23:15]
these guys are held accountable and I've
took on safety pretty heavy since I've
[3:23:19]
took this role on and you know we work
through those things and we don't just
[3:23:24]
you know the damage that's happening you
know we do investigate and make sure
[3:23:27]
they're not just carelessness mistakes
they're they're mistakes it's m you know
[3:23:32]
just accidents
>> thank you chef we is any further
[3:23:37]
discussion
hearing no further discussion maybe we
[3:23:41]
have a roll call but we have a motion
for may be sess and seconded by Rick.
[3:23:46]
» Okay. Seth,
>> yes.
[3:23:47]
» Gary,
>> no.
[3:23:49]
» Rick,
>> yes.
[3:23:50]
» Jan,
>> I'm going to vote yes because I don't
[3:23:52]
want us to miss this opportunity.
>> Laura, no.
[3:23:57]
» Motion carries 3 to two. Let the record
reflect. Thank you.
[3:24:01]
» Thank you.
>> Thank you, Chef. All right. Now we are
[3:24:04]
on
Turn the page. Roman number 11, finance
[3:24:10]
director. Can we before we go on, I need
to ask Jason something.
[3:24:15]
» Sure. Chef, uh, Jan's got a question.
>> Um, I hate to harp on this, but all that
[3:24:23]
stuff you all got scooped up over in the
yard, I thought FEMA was paying some to
[3:24:31]
remove all that.
>> Yes, ma'am. So what what happened is
[3:24:34]
we're and I'm working on it and I think
I have us a place the last couple years
[3:24:39]
Rick helped us a bunch with this in the
past. We don't have a dump site. We have
[3:24:44]
nowhere to dump. I I have a couple
places that I've been reaching outside
[3:24:48]
of just in I try to keep it in
Richlands. You know I don't like
[3:24:52]
traveling 50 milesi out of Richlands to
go dump a load of dirt. Um, a lot of
[3:24:57]
what you see over there was when we done
the big project up here at um, Pizza
[3:25:03]
Hut, you know, there's a lot of material
come out of there
[3:25:06]
» and we had to have somewhere to get it
quick because the time frame we was
[3:25:09]
trying to get that done. So, we did put
it down here, but there is a plan for
[3:25:12]
that down here, too. You know how we
originally when I got that doer and I
[3:25:16]
built that back wall up and cleaned all
that up? Well, we didn't do but about
[3:25:20]
half of that. So, I've actually reached
out to Carter and they're going to be
[3:25:24]
gracious enough to help us with another
dozer. No cost to the town. They're just
[3:25:28]
helping out and uh I'm working out a
deal with them and we're going to clean
[3:25:32]
that all back up come spring when it's
good weather. Looks
[3:25:35]
» terrible.
>> It does. It looks awful right now. But,
[3:25:38]
um if you hear anybody that needs a dump
area, Rick, too. I mean, we we need
[3:25:43]
somewhere badly to dump right now just
to take that material to. So, but we
[3:25:49]
will get it cleaned up. And I do have a
plan on getting it cleaned up for free
[3:25:52]
hopefully. So other than my labor in it,
but
[3:25:56]
» thank you J.
>> Hey Jason, I just had a citizen send me
[3:25:59]
a message and ask me to ask you the
status of the bridge.
[3:26:04]
» The bridge over here.
>> They poured today. So I mean we're
[3:26:08]
getting super close and it they
completed their pour today. They hit a I
[3:26:13]
would say I'm I don't want to put
anything on loop but I would say you're
[3:26:18]
getting real close to that probably
April midappril somewhere
[3:26:23]
» I would imagine so
>> sounds promising. Thank you
[3:26:28]
» mayor.
>> Yes sir.
[3:26:29]
» In in essence of uh to save time tonight
we've kind of gotten pretty long. Can we
[3:26:35]
have and we can vote on it or talk about
it or whatever. Could Ronnie maybe just
[3:26:39]
hit the highlights for us and and not go
through everything on
[3:26:42]
» financial appropriate. Uh council okay
with that.
[3:26:45]
» Ronnie doesn't mind.
>> I'll do the um income statement and uh
[3:26:50]
reserve summaries.
>> Okay, that's totally fine. Thank you.
[3:26:53]
» If you guys have any questions on the
detail, just just email me or or give me
[3:26:57]
a call.
>> Thank you, Ronnie. Okay, we're on
[3:26:59]
finance directory report, Ronnie. on the
um the income statement summary. We'll
[3:27:06]
we'll go through that. Uh on the general
fund, uh 316,000
[3:27:12]
net loss. Um that results from lower
revenues in real estate taxes, business
[3:27:18]
licenses, bank stock taxes, meals taxes,
garbage collections,
[3:27:24]
sales taxes, other taxes and fees, and
other revenues. That's a hurt. uh 53.5%
[3:27:30]
of budget or 3.9 million and that is
offset by a net help on the expenses
[3:27:37]
um
30 57.2 of budget or 3.6 million and
[3:27:43]
that's lower expenses in all departments
and capital purchases except for non-EP
[3:27:48]
departmental.
I would attribute the the revenues to
[3:27:52]
timing
um the expenses to timing and there's
[3:27:57]
been some capital projects done and
there's some that we still have to do.
[3:28:01]
So I'm designating that as timing
permanent
[3:28:06]
on the uh water fund. Um year-to- date
560,000
[3:28:11]
year-to- date net loss. Um that's
primarily from lower revenues hurt 32.6%
[3:28:17]
6% of budget or 1.9 million and that is
offset by lower expenses help
[3:28:25]
of 34.9%
of budget or 1.3 million.
[3:28:31]
On the sewer, we have 109,000 year-to-
date net income variance. Um that
[3:28:37]
results from lower revenues hurt 41% of
budget or 1.4 4 million and that is
[3:28:43]
offset by our lower expenses help uh
30.1% of budget or 1.5 million.
[3:28:50]
Uh I would designate the revenues as
timing permanent and then the expenses
[3:28:55]
are still timing
on the water sewer line maintenance. Uh
[3:29:01]
354,000 year-to- date net income. Uh
this is not a revenue uh department, but
[3:29:08]
it's uh it's a help from lower expenses
of 50.6% of budget or 354,000.
[3:29:17]
I would still attribute that to all
timing at this at this point.
[3:29:21]
Um the electric without generator, uh we
did review that just this week. 138,000
[3:29:29]
uh year-to- date net income variance. Uh
results from lower revenues hurt 47.1%
[3:29:35]
of budget or 5.2 million and that is
offset by lower expenses help 45.7% of
[3:29:43]
budget or 5.4 million.
Uh the revenues are timing permanent
[3:29:48]
differences and the expenses are
primarily timing at this time.
[3:29:54]
And then the generator, we did not have
any activity this month. So we're still
[3:29:58]
at uh 2 million
uh variance for the year. Um that was
[3:30:05]
related to the inbridge pipeline
contract second payment and the quantum
[3:30:09]
power progress payments.
And this is where I I list out the
[3:30:14]
cumulative funding. Uh 15.5 million
includes 12.6 from the note payable.
[3:30:22]
uh 0.9 was funded from unrestricted
funds and 2 million was funded from the
[3:30:27]
Virginia Small Business Authority loan
under the Tobacco Regional Commission.
[3:30:32]
And I would attribute that to all uh
permanent differences at this time.
[3:30:39]
And then skipping through the all the
detail,
[3:30:46]
we'll jump over to the cash reserve
summaries.
[3:30:51]
Starting with the general fund,
um
[3:30:56]
the unreserved cash balance is uh
roughly about $2 million. Uh 300,000 of
[3:31:03]
that is from uh primarily from timing of
the real estate taxes.
[3:31:10]
And then there was no change in the
projected uh from November.
[3:31:19]
Uh from the water
[3:31:23]
water fund
unreserved balance is 512,000.
[3:31:28]
That was a $59,000 decrease from
November.
[3:31:33]
And then the projected went down 21,000
from November.
[3:31:42]
Then on the sewer department, uh, still
tracking at about a negative $400,000
[3:31:47]
unreserved cash balance. And that was a
$20,000 decrease from November.
[3:31:54]
And on the projected uh same uh small
difference, $22,000 increase from
[3:32:01]
November. Actually, that's an increase
and the other was a decrease
[3:32:09]
on the electric reserve balance. Um
649,000
[3:32:16]
negative. Uh that was actually a
$538,000
[3:32:19]
decrease from November. And this is we
had two ant bills post in December. One
[3:32:26]
was on uh December the 2nd for October
and then the second one was on November
[3:32:33]
um for November on 12:30.
That puts us where we truly are year to
[3:32:39]
date because the only open bill to pay
is the one that we will receive um in
[3:32:44]
February for January.
[3:32:48]
And I'm going to be working through this
projected on the electric. Some of that
[3:32:54]
is a result of us running it um
for funding the the the project, but
[3:33:00]
that's been paid back. So, I'm going to
it won't look as as unusual with the 4.2
[3:33:07]
uh negative projection once I figure in
that timing.
[3:33:14]
Any questions on the income statement
summary or the cash reserve summary?
[3:33:22]
Okay.
>> Any questions for Ronnie? Council.
[3:33:26]
» Thank you.
>> All right. Then the next one is just the
[3:33:31]
the all the loan balances. Um that
should be current through December.
[3:33:36]
Um that we've got the first bank and
trust note on there as well. And if
[3:33:42]
you're trying to tie back the first bank
and trust note, you have you you'll see
[3:33:47]
at the top there 285,000 for the trash
truck. There's the 36,000 for the fire
[3:33:54]
truck. And then the 12.6 million is the
generator project. And that will those
[3:34:01]
three amounts will sum up to the total
uh first bank and trust uh note.
[3:34:08]
And that is all I had on the financial
statement review.
[3:34:15]
Sorry I went by kind of kind of quickly.
>> You're fine.
[3:34:18]
» Don't apologize.
>> Any other information that you feel is
[3:34:21]
pertinent to us, Ron?
>> Um, not with the financials. Uh, I did
[3:34:27]
include uh the PCA kind of role for it
at a high level. I didn't know if we
[3:34:31]
wanted to talk about that this meeting
or not.
[3:34:34]
PCA.
>> Mhm.
[3:34:36]
» What does council desire?
[3:34:40]
» Do you want us give you the report
electrical committee?
[3:34:43]
» Um,
we're talking about PCA.
[3:34:46]
» Yes.
>> U, so Seth is asking if he if the
[3:34:50]
council would like a report from the
electoral committee. Uh, anything else
[3:34:54]
on your part? What tell us about the PCA
from your point of view, Ronnie, please?
[3:34:58]
Uh the PCA is still where we're still
tracking a um a negative uh unreserved
[3:35:05]
balance. Um if I did a a rough estimate
of looking at the current tracking and
[3:35:12]
trends of this year's revenue versus
expenses plus the current rate of the
[3:35:17]
PCA
between now and June, it looks like
[3:35:22]
we're going to gain about another
$240,000
[3:35:25]
in net income. But I do not have the
actual results for January yet. That
[3:35:30]
could could change that.
>> Okay.
[3:35:35]
» So my recommendation is still to kind of
hold hold the current pattern versus
[3:35:39]
ramping up and down with it.
>> Okay.
[3:35:43]
Um Okay. Seth, did you want to
>> Yeah. Just what we discussed at the u
[3:35:48]
the meeting last night. So there's
basically two ways of thinking about
[3:35:54]
this. One is we can maintain throughout
the year a steady level on the PCA which
[3:36:02]
is what we've done for the last few
months. Now that means that your bills
[3:36:07]
are going to be a little higher in the
winter time. They're going to be a
[3:36:09]
little bit lower in the summertime. Now
the because we use less energy in the
[3:36:16]
summertime. The other thought is we
discussed with Ronnie building a formula
[3:36:21]
where in the shoulder months into spring
and the fall we would actually in the
[3:36:27]
colder months decrease the PCA like
throughout the winter time. Then when we
[3:36:32]
get to spring we would ramp it up. But
what we want everybody to understand and
[3:36:36]
I think this is maybe something we need
more discussion on and after Ronnie has
[3:36:41]
time to develop a formula. What we have
to understand is the PCA is just to be
[3:36:47]
able to get us to break even. That, you
know, the goal is we don't we're not
[3:36:52]
we're not trying to make we're not
trying to make a profit. You know, we're
[3:36:55]
here to try to to run the utility to pay
its bills. That that's it. That's that's
[3:37:00]
the desire. And I don't think anybody on
this council wants anyone's electricity
[3:37:05]
to be $1 more than it should be or has
to be to pay those bills. That's that's
[3:37:08]
all we care about. But if we were to
reduce it now, we can do that. But that
[3:37:14]
means that prepare like look just for
simple math because this is not how it
[3:37:19]
is. But let's say it's 2 cents right
now. If we go reduce that by half to 1
[3:37:23]
cent right now, then prepare yourself
that in April, May, June, we're going to
[3:37:29]
be raising it to 3 cents. Does that make
sense? So we can keep it even kilter
[3:37:35]
throughout the year and then make the
adjustments once we have more data you
[3:37:40]
know and and the hopes are that we can
get to a place where we we see okay we
[3:37:46]
are taking in a little bit more than
what it takes to pay the bills now we
[3:37:49]
can reduce this but we're not there yet
and we really need the January data
[3:37:54]
which Ronnie's not going to have for
another seven days some you know some
[3:37:57]
sometime in the next seven days so the
committee last night said that we can
[3:38:03]
either we can have another meeting after
the data comes in. We're will you know
[3:38:06]
everybody was willing to do that and to
prepare something for council but really
[3:38:11]
our recommendation was we go back to
council and discuss this of whether do
[3:38:15]
you want Ronnie to build a formula where
it's lower in the winter time higher
[3:38:20]
other times of the year or is it better
just to leave it on an even kill. And
[3:38:26]
one of the things with Ronnie's formula,
I think Jordan said, you know, if it's
[3:38:29]
if we get there could be a number, there
could be a trigger number that if it
[3:38:33]
gets to that, then Ronnie automatically
increases the PCA.
[3:38:40]
» I'm listening. Uh
>> I'm not saying listen, the other thing
[3:38:43]
we all acknowledge this is not simple.
>> Are we ready to do this right now? I'm
[3:38:49]
waiting for the numbers, right?
>> Yeah, we we don't know. Correct.
[3:38:53]
» I'm fine. I have a thought. I'll just
share it. And I'm not nearly as
[3:38:56]
knowledgeable as people serving on the
committee because you do it all the
[3:38:59]
time. For me personally, I do better in
my life just speaking as a citizen. If I
[3:39:06]
know it's this,
I count on that. But up and down, I feel
[3:39:11]
like I'm in a skip rope and I get real
confused. That's just me. I'm only
[3:39:16]
speaking for Rod Curry, not everybody. I
don't disagree with you, mayor, and we
[3:39:19]
said that is that
>> it might what it might do, it's more
[3:39:23]
like a budget plan. If we were to if if
Ronnie developed a formula were to alter
[3:39:27]
it, it's going to keep your bill more
even throughout the year. That's a good
[3:39:31]
thing. But it's a complex thing to
understand that in the winter time, I'm
[3:39:36]
only paying this much PCA, but I'm using
more. Then in those other months, I'm
[3:39:41]
paying more PS more PCA, but I'm using
less energy. It it it that would that
[3:39:46]
would more regulate everyone's bill, but
I just think everybody needs to have
[3:39:50]
input on it because I don't know that we
can we don't want to decide that on our
[3:39:54]
own. We wanted you all
>> I I I think it needs some consideration.
[3:39:58]
Council, your thoughts, anyone by
personally, I'm just speaking not only
[3:40:03]
as an elected official, but as a
citizen, as I said, I do better
[3:40:07]
personally if I know it's this. I'm
thinking about if I get my bill on look
[3:40:11]
in the winter, my PCA is low lower. I'm
using tons of energy and in April and
[3:40:17]
May I'm using less energy but my PCA
goes up.
[3:40:21]
» It's contrary to to my thinking. Yes.
Now I get exactly what you're saying
[3:40:25]
about the formula, but it to me it's
just counter to me. Uh any other
[3:40:30]
thoughts on that? I think you're right.
It says we'd have to wait for the
[3:40:32]
figures and I'm sharing my thinking.
Anybody else want to share their
[3:40:36]
thoughts? I think you need the figures
of Ronny's calculation and look, let's
[3:40:41]
all look at it and see if it's something
we want to do or is this something that
[3:40:46]
» it's going to
say we're chief
[3:40:51]
» confusing.
>> Any other thoughts here, council
[3:40:56]
members?
>> So says we're on hold for that one. Is
[3:41:00]
that correct?
>> Yeah. And Ronnie agreed and he promised
[3:41:02]
electrical committee once we know the
numbers and he he he's willing to look
[3:41:05]
at that and Right.
Okay. Uh, so if I'm pushing too hard,
[3:41:11]
you guys tell me, but I'll move on.
>> Mhm.
[3:41:14]
» All right. Here we go. Uh, finance
director PCA. PSA PCA. Good God. Uh, PSA
[3:41:21]
Cedar Bluff.
>> Yes.
[3:41:24]
So when I first started with the town
back in July of 2023
[3:41:30]
and one of the first meetings we had
with the PSA was about this
[3:41:34]
reconciliation that had not been done at
that time for probably 2 or 3 years and
[3:41:40]
also they approached us about uh the
reserve balances that we have for for O
[3:41:45]
and M and debt.
So, we started looking into it and we
[3:41:50]
were making some headway with it and
then uh when Jason was here, we we kind
[3:41:55]
of put a stop to it waiting until we got
caught up on the audits to make sure
[3:41:58]
that we had all the final information
from those years. Well, we finally got
[3:42:03]
caught up with the audits. So then I
once we got caught up with audits, I
[3:42:07]
went back on this review and then
started working with the PSA and Cedar
[3:42:11]
Bluff to reconcile those years where we
build them on budget and never truded up
[3:42:16]
to actuals. So we went through four
years of four years of that and um then
[3:42:25]
one of the things they were were still
pushing on was to you know that they
[3:42:30]
wanted some level of that O andM balance
or reserve balances back to them and
[3:42:38]
once we did the true up it it made sense
but I also made a recommendation that in
[3:42:43]
order for us to release those reserves
in total I think we should uh start
[3:42:49]
billing you on a monthly basis of
actuals. So that's what we've got.
[3:42:55]
Mike's got them in in in his hand. We've
got some draft amendments where we will
[3:43:01]
switch over to billing on a monthly
basis actuals. We will no longer have
[3:43:06]
the annual true up and that also relie
relieves the necessity to have those
[3:43:11]
on&m reserve balances for one year of uh
budgeted amounts. Would it relieve extra
[3:43:17]
discussion?
>> Yes.
[3:43:19]
» Thank you. All right. Here we go.
Recommendations. Do you mind if I go on?
[3:43:23]
Recommendations. Given the importance,
sorry, Ronnie, of timely business
[3:43:27]
partner reconciliations and settlement
of outstanding balances, staff
[3:43:31]
recommends the town council approve the
annual billings refunds. This shall
[3:43:35]
include the reserve account balances
associated with the process,
[3:43:39]
improvement, and transition to monthly
actual billings. Is that correct?
[3:43:43]
» That's correct. Uh, do you want a motion
on this?
[3:43:46]
» I would like one. Yes.
>> Is there a motion to go with the
[3:43:49]
recommendation of the uh, finance
department?
[3:43:53]
» Dan has the motion and Rick has a
second. Is there any discussion on this
[3:43:57]
motion?
>> I have a couple questions. Ronnie.
[3:44:00]
» Yes, ma'am.
>> Um, the It says the contract has been
[3:44:04]
amended, but
are you saying that because we never
[3:44:10]
voted on that? I
>> I can speak on that. It's in the
[3:44:13]
process. Uh it's been um Eric Young has
sent me a draft. I think we got that
[3:44:21]
Thursday or Friday. Um we've been in the
process of amending it, but obviously
[3:44:26]
you all would have to vote on that. So
that's not
[3:44:28]
» Sorry about that misunderstanding.
>> Oh, no, you're good. Um and another
[3:44:32]
question,
>> I don't want to drag anyone else into
[3:44:36]
it. It wasn't Ronnie. It was a former TI
manager. When they were kind of
[3:44:42]
explaining this to us, I asked about the
refund and was told that the refund that
[3:44:49]
they are owed would be offset by
something that they owe to us. So, it
[3:44:55]
would be I've got that on here on the
the detail behind it.
[3:45:01]
each uh
you'll see the reserve account then
[3:45:05]
you'll see the on andm capital
adjustment on each page.
[3:45:08]
» Mhm.
>> So that that is being netted in with the
[3:45:11]
uh with the reserve balance.
>> So like on the first page that says
[3:45:16]
Tazzle County PSA uh water plant reserve
account and it says due refund $228,944.
[3:45:25]
» Yes.
>> That's what we're going to pay to them
[3:45:28]
» out of that reserve account.
net of the see the 59,5
[3:45:35]
915
>> that's the part that we're billing them
[3:45:38]
for.
So that we will actually put that money
[3:45:43]
back into our unrestricted general fund
and then that reserve balance will come
[3:45:48]
down to zero.
>> But we're going to actually cut them a
[3:45:52]
check for $228,000.
>> But it's out of a reserve account, not
[3:45:56]
money that we use or touch or for
anything else. And the basis of it is is
[3:46:01]
that we've completed these projects. So
when Jordan and I attended the meeting
[3:46:05]
with Ronnie and um
Ron that day, the way that it was
[3:46:12]
described to us was that you know these
projects were gone. Plus we didn't have
[3:46:16]
the reconciliation. So we knew we owed
them some money. But what we agreed to
[3:46:20]
was just to hold 6 months of
expenditures or one year.
[3:46:24]
» We're going to hold one year of debt. Of
debt
[3:46:28]
» of debt. But there's not um it's not
like it used to be. We were these
[3:46:32]
reserves were built up on the old
formulas based on um
[3:46:38]
old projects that are paid out. Now with
the new things that are coming online,
[3:46:42]
those are calculated in this number or
those are going to go up.
[3:46:45]
» He he plans they plan to add $100,000 as
an estimate for for themselves and Cedar
[3:46:52]
Bluff 50,000 on the water wastewater
plant debt. And then once we get the
[3:46:57]
actual loan, we're going to chew up
those and then we'll do something
[3:47:00]
similar on the the water reserve
accounts once we get further along with
[3:47:03]
that loan process.
>> So it's just a plan that we have. We'll
[3:47:06]
have one year of expenses in the reserve
account instead of holding I mean I
[3:47:11]
don't know how many how much expenses we
had here but multiple 24
[3:47:14]
» I mean yeah because we didn't do it for
like four years,
[3:47:17]
» right?
>> So there's no nothing. It's not hurting
[3:47:21]
us anyway. This is just extra money that
we've held on to because our former
[3:47:26]
staff members were not doing the
reconstruction.
[3:47:28]
» Let me ask a question, Amanda. Just I've
lost in the shuffle. Sorry. Uh we have a
[3:47:33]
motion and a second on the floor, do we
not?
[3:47:35]
» Yeah, you have um Jan and Rick.
>> Okay, I want to be clear. So, uh any
[3:47:40]
further discussion on this motion
hear? No further discussion. May I have
[3:47:45]
a roll call vote, please?
>> Ray says,
[3:47:48]
» yes.
>> Gary,
[3:47:49]
» yes.
>> Rich, yes.
[3:47:50]
» Jan,
>> yes. Laura,
[3:47:51]
» no.
>> Uh, motion carries, four yeses and one
[3:47:56]
nay. Let the record reflect. Thank you.
All right, Ronnie. Next. Budget
[3:47:59]
amendment uh 11 C.
>> Yes. This this amendment is similar to
[3:48:04]
what we did last year when we moved over
the the salaries, equipment, and
[3:48:09]
materials used in the street department
uh to the to the VOTE reimburse
[3:48:14]
expenses. Um so basically we've got by
doing this we'll have the budget
[3:48:21]
compared to the same amounts on an
actual basis
[3:48:25]
and it will be something that we do in
the new budget. We won't have to do
[3:48:30]
these amendments anymore. We'll actually
have it budgeted correctly uh for fiscal
[3:48:34]
year 27.
>> Okay. And some of this is also a result
[3:48:39]
of the audit we did um on the VOTE where
we went back like five years and got
[3:48:45]
some guidance from John Leonard uh at
VOTE as well. I mean Tom Leonard and um
[3:48:51]
so between those two between that group
and John we've gotten some definite
[3:48:57]
feedback of what we can and cannot put
in these lines. So we'll be figuring
[3:49:01]
that into the new budget.
>> Thank you. Um I just want to read this.
[3:49:05]
I know you can read. I'm just going to
go for it to move this along, not to
[3:49:08]
rush it, but anyway. Town council
meeting staff summary budget amendment
[3:49:12]
recommendation. Staff recommends the
town council review and approve the
[3:49:16]
budget amendments to allow continued
services, operating efficiencies, and a
[3:49:20]
safe environment for the staff and
citizens by directing VOTE revenues to
[3:49:24]
the proper expense items. Okay.
Um,
[3:49:31]
is there uh does council wish to make a
motion to approve these recommendations
[3:49:37]
for the budget amendment?
[3:49:41]
On this next page,
>> I'll make a motion to approve.
[3:49:46]
» Seth makes a motion to approve the uh
budget amendment. Is there a second?
[3:49:51]
» I'll second.
>> Uh Rick has the second. Uh we have a
[3:49:55]
motion and a second. Now for proper
discussion. Is there any discussion on
[3:49:59]
this budget amendment?
>> I have a question.
[3:50:02]
» Yes, ma'am.
>> Um is this going into the general fund
[3:50:06]
restricted account?
>> Yes.
[3:50:10]
» Why would it go into the restricted
if it's like a reimbursement?
[3:50:18]
» Yeah, it's I mean it
>> what isn't restricted?
[3:50:21]
It's coming out of the restricted
and and then we're moving it to the
[3:50:26]
actual expense line item.
>> Oh, you're taking it out of restricted
[3:50:32]
» and putting it in
VOTE,
[3:50:36]
» right,
>> in the public works department.
[3:50:38]
» That's right.
>> And
[3:50:42]
they will reuse that for VOTE only.
>> Yeah. It'll offset against the actual
[3:50:48]
expenses that we we will incur this year
as well.
[3:50:53]
Okay.
>> Thank you, Laura. Thank you, Ronnie.
[3:50:57]
Further questions, members of council
[3:51:02]
to my left, to my right. May we have a
roll call vote, please?
[3:51:06]
» Okay. Seth,
>> yes.
[3:51:08]
» Gary,
>> no.
[3:51:09]
» Rick,
>> yes.
[3:51:10]
» Jan,
>> yes.
[3:51:11]
» And Laura,
>> no.
[3:51:14]
Madame Clerk, if I counted right, it's
three yeses and two nos. Is that
[3:51:19]
correct?
>> Yes, that's correct.
[3:51:20]
» Thank you. Motion carries. Okay. Now,
Ronnie, last one. Uh 11D, financial
[3:51:26]
policies.
Yes. And the only comments I've had on
[3:51:30]
this was from you, Laura, I believe.
>> I'm shocked, Ronnie,
[3:51:38]
» but I I'm prepared to answer them or or
help walk you through them. Um, yeah. I
[3:51:43]
I don't mind to cuz I think I told you
in the email, if I'm remembering
[3:51:47]
correctly, that I would like to have a
public discussion just so everybody on
[3:51:51]
the council hears where I'm coming from.
I don't have the financial policies in
[3:51:56]
front of me. Um, but there was there
were two that really stood out to me.
[3:52:01]
The one major one being
>> um Oh, yes. if you've got and I've got
[3:52:07]
my phone, but
>> it was capital projects and um intra
[3:52:11]
department transfers. Intra
>> Yeah.
[3:52:14]
» department transfers. Yeah. So, um the
capital um I I sent an email and I told
[3:52:22]
him um that I'm a no on the
capitalization policy for equipment
[3:52:26]
being increased from $5,000. I think
anything over 5,000 should be approved
[3:52:31]
by council just so we know what's going
on financially because that has the
[3:52:35]
potential to add up quickly before we
realize it. I'm also a no on the intra
[3:52:39]
department
intradep departmental transfers and
[3:52:44]
again I believe that's a pretty big
thing the council should be aware of and
[3:52:47]
oversee before happening. Um we saw that
tonight when Mr. Shepherd asked to
[3:52:54]
allocate to the budget amendment and we
all told him we appreciated the clarity
[3:53:00]
and the honesty. Um not that I don't
trust people and I know I've got to
[3:53:05]
trust people but um I just feel like the
taking away and allowing the interdep
[3:53:11]
departmental transfers is going to take
away from us
[3:53:16]
» being able to be as involved especially.
So that particular item I'm not
[3:53:21]
hardwired on that was that was a Jason
May proposal
[3:53:24]
» but what we had been doing in the past
and Jason's his his budget amendments
[3:53:29]
were going to be between O and M
accounts
[3:53:32]
» those we we didn't have to get approved
before but if we went from O and M to
[3:53:36]
capital or O andM to payroll that's the
ones that were not in the policy before
[3:53:43]
I'm not hardwired on on switching to
those because it makes sense because
[3:53:47]
we're crossing categories. Yeah. Yeah.
Yeah.
[3:53:49]
» But the way he was presented
>> supportive of that.
[3:53:52]
» Okay. I appreciate that.
>> So if I'm asking to be clear uh and
[3:53:57]
thank you for the questions and uh
insight we it's the book I don't have it
[3:54:02]
with me. The booklet that we have about
financial policies
[3:54:05]
and so does any So if we were to accept
this we would if council as a whole
[3:54:12]
wants to make changes we couldn't be
ready to vote on it right now could we?
[3:54:17]
» Right. Yeah.
>> Yeah. So, I think our issue is this is
[3:54:21]
you've had this in front of you two
prior meetings. This is the third
[3:54:24]
meeting.
>> That's right.
[3:54:25]
» And um in our audit, on-site audit, we
were also asked about these, you know,
[3:54:31]
what our policies are and whether these
have been adopted by our auditors. And
[3:54:36]
so, I do think there's a time
sensitivity to
[3:54:40]
um resolving these issues. That's why I
reached out again and said if any of you
[3:54:44]
had other items, let's bring them
forward. when when Loris and hers and I
[3:54:48]
had a discussion with Ronnie about the
uh inter uh funds I'm like I don't
[3:54:53]
support it. So if I were writing this
now I would want that change itself. Now
[3:54:58]
I think he had some
>> that would just I would just delete
[3:55:01]
that. That was a proposed change that we
won't put in.
[3:55:04]
» Okay.
>> Um and then I I think Ronnie had some
[3:55:06]
comments about why he still wanted to
have the discussion with you about the
[3:55:10]
capital number.
>> Um and do you want to
[3:55:13]
» Yeah. So on the capital, it's more of a
threshold for creating a fixed asset in
[3:55:18]
our subleddger. You would still be
either approving it as an O andM item or
[3:55:24]
a capital item. It just we won't have to
create an an asset that's going to be
[3:55:29]
depreciated for $5,000 over 10 years. I
mean, it was it was something our
[3:55:34]
auditors asked if we could look at
increasing as well.
[3:55:38]
So, if um
just for example, I'm totally making
[3:55:43]
this up. Um let's say that
someone was going to buy a trash truck
[3:55:49]
for $4,500.
That would be great, right? Um they
[3:55:54]
wouldn't need our approval cuz it's
under the $5,000. But if we were to
[3:55:57]
raise that to 20,000,
>> it's not really for the approval. I
[3:56:02]
mean, you still have the dollars. It's
just do I need to create an asset that's
[3:56:07]
going to be systematically depreciated
in our subleddger? The dollars are still
[3:56:13]
in the budget as either being in on&m or
capital for approval. It's just do I
[3:56:19]
have to create an asset for $5,000
>> a single identified item. And with these
[3:56:27]
costs that we've got today, the cost of
tracking those based on where prices are
[3:56:31]
today, it seems like a very low
threshold to create.
[3:56:35]
» That makes way more sense. I interpreted
it the same way that she did, but what
[3:56:39]
you're explaining to us makes way more
sense.
[3:56:42]
» And that was why in my email, it's here.
Anybody can read it. I did ask that we
[3:56:47]
talk about this as a group so that we um
we all understand if we have the same
[3:56:52]
questions or whatever. So, I'm fine with
keeping that. And um you guys have
[3:56:56]
obviously said the other one, the
interdep departmental, you're good with
[3:57:00]
taken out.
>> Yes. Thank you.
[3:57:01]
» So, I'll make a motion that we approve
your financial policies with the
[3:57:07]
interdep departmental transfers taken
out.
[3:57:10]
» Thank you.
>> There's a motion on the floor to approve
[3:57:12]
the financial policies as presented with
the exception of the uh interdep
[3:57:18]
department transfers being removed.
>> I'll second.
[3:57:21]
» All right. Is he's got a second, Seth?
Yeah.
[3:57:23]
» Okay. Laura has the motion. Seth has a
second. Any discussion on this motion?
[3:57:28]
Council
[3:57:31]
» hearing. No discussion. May we have a
roll call vote, please?
[3:57:35]
» Yes. Seth,
>> yes.
[3:57:36]
» Gary,
>> yes.
[3:57:37]
» Rick,
>> yes.
[3:57:38]
» Jan,
>> yes.
[3:57:39]
» Yes.
>> It is unanimous. Thank you.
[3:57:43]
» Thank you, Ronnie.
>> That's all I have.
[3:57:44]
» Now, let's move on to Roman numeral 12,
Attorney Report. Mike,
[3:57:49]
» I had a phone call today with Kurt
Hodgegkin
[3:57:53]
um with SGR. He uh let me know that the
second round of um applicants that will
[3:58:01]
close February 17th, so a week from
today. Um, I know I had sent you all an
[3:58:08]
email with updated
um updated applicants as well as he told
[3:58:14]
me that the first round of applicants
with their um
[3:58:20]
I guess with their interviews that they
had the the internet interviews he's
[3:58:25]
supposed to be sending to me. I haven't
received those yet, but as soon as I get
[3:58:29]
those, I'll forward on to you all. So, I
just wanted to give you an update as far
[3:58:32]
as the manager search goes.
Thank you.
[3:58:36]
» Anything else, Mike?
>> When does he think you have somebody to
[3:58:41]
interview and stuff?
>> Well, with that second round, it would
[3:58:45]
be the 17th. I think they usually take
another week or two to go through those
[3:58:52]
applicants, find out what tier, you
know, tier one, two, or three. Um, I
[3:58:58]
would imagine he would be able to uh I
could ask him to be available for the
[3:59:02]
March meeting if that's something that
you all would want me to do uh either by
[3:59:06]
Zoom or in person for him to give an
update on that.
[3:59:10]
» I mean, I just don't feel like we're
moving with this. I mean, it's two weeks
[3:59:15]
this, two weeks for that. It's next
month, next month, and next month. We've
[3:59:19]
got to get this thing.
>> We extended the application.
[3:59:24]
» All of us agreed to it.
Yeah. And that that means that the the
[3:59:28]
closure is the February 17th. I'm just
saying as far as next month if you all
[3:59:32]
would want me to have him here. If you
don't, then that's fine. But
[3:59:35]
» that takes two weeks.
>> Yeah.
[3:59:39]
» That gives him three weeks to review and
be ready to talk or you can have him.
[3:59:43]
» Oh, yeah. He'll I'm sure he'll email
them to me and I'll forward them on to
[3:59:46]
you, you know, prior to that date. But,
um, just wanted to give you an update
[3:59:51]
that I talked to him today.
>> Thanks for your question, Rick. Anybody
[3:59:55]
else um have a comment about SGR?
Anything else? Mike? Okay. Uh Roman
[4:00:02]
numeral 13 town manager report. Mr. Mar,
what a pleasure.
[4:00:06]
» I'll be brief and because there's
nothing that's so time pressing. And I
[4:00:10]
just wanted to, you know, one I think uh
the staff in public works and uh they've
[4:00:16]
done a phenomenal job during this recent
uh I from my perspective, we've gotten a
[4:00:21]
lot of positive citizen comment about
road conditions and um resolving issues
[4:00:28]
that have come up. Um so I just want to
thank them publicly here um as well and
[4:00:34]
let the citizens who have contact us to
say that know that we've shared it with
[4:00:38]
the staff and we appreciate those
comments as well as those of you who
[4:00:42]
have sent very kind comments um and uh
assisted them. Nothing else I have is
[4:00:48]
that pressing so I'll wait.
>> Way to go apartment
[4:00:55]
swallow this thing hole medics. All
right, 14
[4:01:01]
captain reports. Miss Balo,
>> I just have one quick thing. Um, so I
[4:01:07]
attended the electric committee meeting
last night as a citizen. I'm able to do
[4:01:12]
that as long as I don't participate with
the meeting and I didn't. But um I just
[4:01:18]
want to recommend to us that our
generator project is so large that um I
[4:01:27]
really feel like the council should be
having joint meetings with the electric
[4:01:31]
committee so that we are all getting the
the same information at the same time
[4:01:35]
being on the same page. I really enjoyed
being there hearing about, you know,
[4:01:40]
that there are different conversations
with um Allan from their electrical
[4:01:45]
department and Ronnie talking about the
the PCA and um I would like to hear
[4:01:51]
those conversations and I think all of
us should hear them. So I would like to
[4:01:57]
consider for everyone to consider that
we start having joint meetings. So the
[4:02:03]
electrical committee and council's
meeting together.
[4:02:06]
» Okay. I I would just say to that I'm
sorry. Well, I'll just wait till my
[4:02:10]
call. No, no, go on. I'll just wait.
>> Okay. So, that's part of your report,
[4:02:15]
Laura.
>> Yeah, that's all.
[4:02:16]
» Okay. I think that's something council
would have to take into consideration.
[4:02:19]
Uh, Miss White,
>> I don't have anything except I'd like to
[4:02:23]
thank the U public works department for
their good work during all these snow
[4:02:29]
storms.
I appreciate what you all do. Thank you
[4:02:34]
so much.
Thank you, Jan.
[4:02:38]
Uh Jordan is not with us tonight. Rick,
Mr. Wood,
[4:02:41]
» I'd like to thank the police department,
rescue squad, public works, and the
[4:02:46]
water company because we had a lot of
leaks during the cold weather, burst
[4:02:50]
pipe everywhere. I'd like to thank for
all thank them for all the hard work and
[4:02:54]
the errors that they put in here.
That's all I got.
[4:02:58]
» Thank you, Rick. Uh Mr. Jackson.
>> Yes, Mayor. Um, one I have is I had a
[4:03:04]
couple calls from
Oral Street and Lake Park from my
[4:03:09]
neighbors basically. Was they some
surveyors down there? I know probably
[4:03:13]
where it's going with the road, but was
they down there this week surveying
[4:03:19]
for where we tore the house down? You
may not be aware of that, dog.
[4:03:22]
» I don't know. Sorry, but I'll be happy
to find out for you. Does anyone here
[4:03:27]
know?
>> Yes, they were. I I called them.
[4:03:31]
Can you come to the mic?
>> Yeah.
[4:03:37]
» So, part of that uh with FEMA, you know,
and it was finding out boundaries. So,
[4:03:43]
we wanted to get it surveyed. So, we
went ahead and I called three weeks ago
[4:03:47]
and got on schedule and they went down
there, I think this week and surveyed. I
[4:03:51]
think it was they supposed to went last
week, but I think they was Did you say
[4:03:54]
they was down there yesterday or today
or
[4:03:57]
» Yeah, yesterday I believe. supposed to
come sometime this week and start survey
[4:04:01]
that and that was mainly just to get the
boundaries where we're like I said I'm
[4:04:05]
getting ready to put the RFP out that
way we know where to take that road
[4:04:08]
through and where our boundaries are we
don't
[4:04:10]
» is that just for information to get out
the RFP
[4:04:13]
» it is yep and that way we have exact
boundaries you know we obviously don't
[4:04:17]
want to pave on somebody else's land so
I wanted to get that survey that way we
[4:04:21]
know
>> I didn't see them but was that our
[4:04:23]
employees count employees
>> no I hired u I reached out to Um,
[4:04:29]
I called a bunch. There was so many that
I've called. I think uh uh Dr. Price was
[4:04:35]
one of them that uh was supposed to look
at doing it. So,
[4:04:40]
» all right. Thank Well, since you're
there, too, Jason, this one falls on
[4:04:43]
you. I had a few calls this past on
Shell Street. Is that a town road?
[4:04:49]
» It is and it isn't. Like, it's, you
know, we we we do catch that main route
[4:04:54]
going through there,
>> right? up to uh
[4:04:56]
» Delaware.
>> Delaware.
[4:04:58]
» Yep. So, yeah. And it got real where
it's real shaded when you first start up
[4:05:01]
in there. I think Rick brought it to me.
That was to the point of the grater
[4:05:05]
again. I had to take the grater up there
cuz where it's shaded, it it just packed
[4:05:09]
down real hard. There's a lot of
residents in one small area there. They
[4:05:12]
packed it down quick. We We got to it a
little later. We got the grater up there
[4:05:16]
and cut it off and I think within a
couple hours hitting it solid, it
[4:05:19]
melted.
>> But y'all do keep it scraped.
[4:05:21]
» We do.
>> Okay.
[4:05:22]
» Absolutely do.
>> Thank you. That's all I have. Mayor,
[4:05:25]
» thank you. Mr. White.
>> Yes. Back to what Laura was saying. The
[4:05:29]
only comment I had to that is that the
reason we have committees is because,
[4:05:32]
you know, look, it's 10:15 tonight. The
reason we have committees is because we
[4:05:36]
can have longer discussions in a
committee format than we can in here.
[4:05:40]
And I'm not saying that there might be
times when it is appropriate to have
[4:05:45]
them here, but we we certainly have to
make the best use of our time here. And
[4:05:51]
that's the whole point and and idea of
having committees is that if we have
[4:05:55]
committee meetings, we have longer
discussions about items. We can't we
[4:05:58]
can't have all those discussions. You
know, council should be a highlevel
[4:06:02]
discussion of everything else that we
have going on throughout the month. And
[4:06:07]
that's why you assign committees and we
can come back. Gary reports to us from
[4:06:11]
planning or Jordan and I report from
electrical or whatever the committee is
[4:06:15]
to to give you the five minute synopsis
of the 2-hour conversation that we have.
[4:06:20]
That's just my opinion that you know we
do whatever but that's my opinion and um
[4:06:26]
Don what Gary and Jason were talking
about we during the flood event we had a
[4:06:31]
bridge that failed we were able to do a
temporary repair to that bridge but it's
[4:06:36]
a very unique situation that is the only
way in and the only way out to what 30
[4:06:42]
20 30 houses
>> 30 plus yeah
[4:06:44]
» yeah so it's it was a very critical
issue so we all teamed up on this and
[4:06:48]
came up with a plan There was one house
there that if we could buy that house,
[4:06:53]
we could tear it down and then open that
up. So now you have two ways in, two
[4:06:58]
ways out. But we're going But by doing
this, we can eliminate that bridge,
[4:07:02]
which is a danger. And then this will
become the primary entrance and exit
[4:07:07]
into it and it's a much safer path and
no one's going to be cut off. And I
[4:07:10]
think during that event, we had an
ambulance issue. There was other things
[4:07:13]
that happened, very serious things like
if you could pick the worst timing for
[4:07:17]
something to happen, those those are the
kind of things. And we had people up
[4:07:20]
there who were, you know, uh, need an
ambulance to take to the hospital and
[4:07:23]
stuff. And it just, it created a bad
situation. Jason, these guys put
[4:07:27]
together some large steel plates and we
made it work, but at the same time,
[4:07:30]
everybody's we were a little bit nervous
there for a little bit. That's so that's
[4:07:34]
what that was about. And
>> funding the new
[4:07:37]
» Yeah. So we worked through FEMA to get
funding to purchase the house, the
[4:07:40]
property, and we we were able to get a
good price on that. And that was the
[4:07:44]
best solution that we could come up
with. and and then it and it was the
[4:07:48]
only place only possibility. You have
two possibilities. One, you have to go
[4:07:51]
through a trailer park across the river
again, but to stay away from the river,
[4:07:54]
you tear this down and pave it and
you've got access to the road.
[4:07:58]
Um,
>> you're you're welcome. And I think one
[4:08:04]
other thing that I I think that's it,
Mary. Oh, no, no. Yes, one other thing.
[4:08:07]
I drove by the section house
>> and I it looks like a pipe burst,
[4:08:13]
something happened, but no one's told us
anything about what's going on. Okay.
[4:08:17]
Okay.
>> Anything else? Yeah,
[4:08:19]
» that that's all that I had.
>> Okay. Mayor comments. All right. Uh,
[4:08:23]
first I want to add my thank yous to our
town crew. I'll be very broad because
[4:08:27]
they did an outstanding job in this town
during the storm. Um, as you all know, I
[4:08:33]
live right smack dab in the middle of
town and I didn't receive any
[4:08:37]
preferential treatment, believe me. But
they were I could see them on Second
[4:08:41]
Street and Tazwell Avenue and Fairfax
Avenue where Cornerstone Church is. I
[4:08:45]
could go on and on. Thank you. U and uh
there is just no way to say thank you
[4:08:50]
enough. The section house had a a
terrible problem. It I'll make it brief
[4:08:57]
because it was lengthy. Um I discovered
on Friday night that there was a leak in
[4:09:02]
the house and um the heat pump had
stopped working. Pipe froze, burst,
[4:09:10]
flooded the house on the inside of
floors. the big pile that you see in
[4:09:15]
front. And I want to say thank you to
Mr. Mar and thank you to Jason Shepard.
[4:09:19]
He responded immediately that night and
all day Saturday working on it. Um, we
[4:09:26]
had a crew, I forget the name of them,
they came and they had they had to tear
[4:09:30]
out all that mess you see in the front
yard. The front I have you ever been in
[4:09:36]
it? Okay. I mean the house.
>> Mhm.
[4:09:39]
» Okay. in the front floor is was new wood
uh because when the restoration took
[4:09:46]
place there wasn't enough salvageable of
the original wood. So the front room is
[4:09:52]
re was replaced with the original pine
flooring which was what the old wood was
[4:09:57]
like. The back part of the house and the
side going over to the kitchen had the
[4:10:01]
original wood in it. So all that wood
for the front room had to be taken out
[4:10:07]
because of the leak. It's just something
more than unfortunate. It was horrible.
[4:10:12]
And I don't mind to tell you, anybody
knows me. It's near and dear to my
[4:10:15]
heart. Uh when I went home
Friday night and Saturday night, oh, Rod
[4:10:21]
Curry had a big ball because it is near
and dear and it's such a good thing for
[4:10:26]
our town. So, that's what it is. And
they are working to uh take all the
[4:10:32]
possibilities of anything that's wet out
and there'll have to be replacement. As
[4:10:36]
far as cost, we are insured. The house
is totally insured except for a $1,000
[4:10:42]
deductible. Am I correct?
>> That's correct.
[4:10:44]
» So, you know, go ahead, Mr. Mar.
>> No, I I would just say that, you know,
[4:10:47]
anytime we have a city asset and a
disaster, we're going to try to do what
[4:10:52]
we can to address it. To put it in
perspective, that line break was 111,000
[4:10:58]
gallons of water. That is more than it
takes to fill your pool. Um, so it was a
[4:11:05]
significant impact. Um,
again, I think a lot of people got
[4:11:12]
involved because we're trying to get
heat to it. Obviously, you can't even if
[4:11:16]
you stop that. If you don't have heat,
you got a problem. All this is after
[4:11:20]
hours. Um, and trying to get it done.
Ronnie did a great job of looking up to
[4:11:26]
make sure the questions like, is this on
our insurance so that we can make calls
[4:11:31]
to restoration people, the people who
helped with the original renovations to
[4:11:36]
get them involved so that we could get
it addressed very quickly. Um, and so
[4:11:41]
all of that to say, you know, a
disastrous situation is being made as
[4:11:45]
best as it can um at this point. So, um,
but the for the amount of expense
[4:11:54]
associated to this to be covered under
under our plan, I think is, you know,
[4:11:58]
we're going to be lucky.
>> Yes.
[4:12:00]
» And I want to add to uh Sep um I talked
with him Friday night. We were both over
[4:12:06]
there. Uh on Saturday morning, I was
over there from 8:30 until about 1:30
[4:12:12]
approximately uh with the town people
and also people who work for me. uh
[4:12:19]
personally and we to had to take every
single thing out of the house, all the
[4:12:23]
furniture, everything off the walls,
tons of documents that we've collected
[4:12:28]
in this 16 years. We have tons of things
and all those things uh were put in
[4:12:34]
boxes, rolled in paper, and we're all
working frantically because the people
[4:12:38]
who were tearing out the floor in there
pulling up the floor. So, it was a big
[4:12:43]
thing and I'm just so grateful for all
the support of the town crew and the
[4:12:49]
interest. Thank all of you for your
support. I hope that that could go on,
[4:12:53]
Seth, but it's tremendous.
>> No, I I just we didn't know about it. I
[4:12:56]
just I
>> I thought I'd just talk about it right
[4:12:58]
here.
>> It's good. Thank you. Uh uh any other
[4:13:03]
things here under my report? Um I just
want to say we do spend a lot of time in
[4:13:09]
long council meetings. Senate were known
for it. But in the scheme of things, we
[4:13:13]
have a tremendous amount of interest in
from these council members in this town.
[4:13:18]
It does not go unnoticed.
And um
[4:13:24]
I don't want to get religious, so I
won't I'm not that religious. So um the
[4:13:30]
next big holiday is Valentine's Day. Be
sweet. Thank you.
[4:13:35]
» President Day Monday.
>> Yes.
[4:13:38]
» Yes. And then Valentine's Day is
Saturday.
[4:13:42]
» President's Day is Monday and we're
closed Monday. So that's an announcement
[4:13:46]
to the public. And the only other thing
I have to say is that's it. I'm good.
[4:13:50]
» I hope this Valentine's Day ain't like
last Valentine's Day.
[4:13:54]
» We had that major flood.
>> It was horrible. So um anyway, there's
[4:13:59]
tons about all this that I could say,
but we could be here for the rest of the
[4:14:03]
night and nobody wants to hear that. Uh
it's too late. Uh so Roman numeral 16
[4:14:09]
executive close session. Is there a
motion to go into close session per code
[4:14:14]
section 2.2-3711A1
[4:14:20]
personnel discussion of hiring of frozen
open positions.
[4:14:26]
A revenue part-time position, B public
works foreman, C part-time rec position,
[4:14:33]
and then we added one which is code
section 2.2-371188,
[4:14:40]
legal consultation for electrical
contracts.
[4:14:44]
» Got the motion the motion. They're fine.
Uh we have a motion made by Gary and
[4:14:48]
seconded by Rick. Any discussion on this
motion?
[4:14:51]
» I just want to quickly say just because
we can doesn't mean we should. I the
[4:14:56]
open positions are not about specific
people. I would prefer to talk about it
[4:15:00]
publicly. It's budget thing. That's all.
>> Okay. Well, we have a motion on the
[4:15:06]
floor. So, we'll uh go um in that
direction. So, we have a motion and a
[4:15:11]
second. Um any further discussion on the
motion
[4:15:16]
hearing? None. Move we have a roll call
vote, please.
[4:15:19]
» Yes. Okay. Seth,
>> yes.
[4:15:20]
» Gary,
>> yes.
[4:15:21]
» Rick,
>> yes.
[4:15:22]
» Jan,
>> yes.
[4:15:23]
» And Laura,
>> no. Motion carries 421.
[4:15:28]
So, u I would like to ask I am hot,
physically hot. Can we stay in here and
[4:15:34]
I may ask you to please step out. Thank
you.
[4:40:11]
just say yes.
>> Uh Gary,
[4:40:14]
» yes.
>> Rick,
[4:40:14]
» yes.
>> Dan, Laura,
[4:40:16]
» yes.
>> We're in open session now. Is there a
[4:40:19]
motion to certify that nothing was
discussed in executive session other
[4:40:23]
than Virginia Code Section 2.2? 2-3711A1
[4:40:29]
personnel discussion of hiring of
frozen/open
[4:40:34]
positions revenue part-time position
public works foreman part-time rec
[4:40:40]
position and code section 2.2-3711A88
2-3711A88
[4:40:46]
legal consultation for electrical
contract. That's what it says on the
[4:40:50]
agenda. Make a motion.
>> Oh, there's a motion. Is there a second?
[4:40:54]
» I has a second and a yay vote indicates
nothing was discussed other than these
[4:41:00]
things. Uh, is there any discussion on
this motion to certify? All right, roll
[4:41:05]
call vote. Seth,
>> yes.
[4:41:08]
» Rick, Jan, Laura,
>> yes. Motion carries. Uh we are now fully
[4:41:14]
in open session. Is there any action
that council wishes to take at this
[4:41:17]
time?
>> Mr. Mayor, I'd like to uh make a motion
[4:41:21]
to direct the town manager to create a
new RFP um similar to the one we created
[4:41:26]
before to hire a electrical contract
attorney. I guess that'd be the best
[4:41:31]
way. And and for him and and Mike to get
together on that and craft that in the
[4:41:35]
best way possible.
>> Okay. Thank you. All right. Is there a
[4:41:39]
mo a second to that motion? Rick has a
second. Any discussion?
[4:41:43]
» Uh yes, ma'am.
>> Is this to try to get out of the
[4:41:47]
contracts that we have now?
>> This is to analyze the contracts that
[4:41:51]
we're in to tell us where we are. We
don't understand. We we don't still to
[4:41:56]
this day two years later don't have full
versions of the contracts that we're in.
[4:42:01]
So this is to do the analysis of what we
can and cannot do.
[4:42:04]
» And what is the the end? Because I'm
thinking of money, right? Like we
[4:42:09]
couldn't allocate $1,600 for GDS to come
back. So what is the endg game with the
[4:42:15]
attorney
to to analyze this?
[4:42:20]
» Well, this is recommendation electrical
committee, which this council already
[4:42:24]
voted on and approved. We just did not
hire anyone from the first RFP. So this
[4:42:29]
is just a repeat of that. As far as I
don't have an endgame. I'm just carrying
[4:42:33]
forth the recommendation of the
electrical committee and backing up the
[4:42:38]
approval that was probably unanimous. I
don't have it in front of me, but I
[4:42:41]
believe that it was unanimous when we
voted on this last time as a council to
[4:42:44]
do it.
>> So, this is just to extend that RFP and
[4:42:47]
to recraft it.
>> So, we got a motion and a second on the
[4:42:50]
floor. Any other discussion?
>> Yeah, I just want to Yes. It was just
[4:42:53]
the the financial aspect of it.
>> Don't when we talked about it before it
[4:42:58]
was to get out of the contracts. I don't
think we should get out of contracts now
[4:43:02]
because we're halfway into it. We will
own a piece of a hydro plant. We're too
[4:43:08]
far into it to It's probably the same
situation with generator. This is
[4:43:12]
another reason why I wanted to meet with
the electrical committee and the
[4:43:18]
electrical committee has got to start
taking
[4:43:21]
um minutes so we can reference things
like this. It's required by foil law,
[4:43:27]
but also so we can reference things like
this. Just throwing that out there.
[4:43:30]
» Only if three of us are there is it
required to take minutes.
[4:43:33]
» No. Okay. Any any committee appointed by
call for the question?
[4:43:37]
» Two each.
>> Seth, have you got your two?
[4:43:40]
» Yeah, I don't.
>> Yes.
[4:43:42]
» Any other discussion?
>> Okay. Um, so we have a motion and a
[4:43:47]
second on the floor. Uh, somebody taking
notes on this. Okay.
[4:43:52]
» Seth made the motion. Rick has a second.
>> All right. We've had discussion. Any
[4:43:56]
further discussion from anyone who has
not spoken? Hearing no discussion, roll
[4:44:00]
call vote. Seth?
>> Yes.
[4:44:02]
» Gary?
>> Yeah. I'd like to make know more about
[4:44:05]
this contract myself. So, I'm going vote
yes.
[4:44:07]
» Okay. Rick.
>> Yes.
[4:44:09]
» Yes.
>> No.
[4:44:10]
» Okay. It is a 41.
Let the record reflect. Now, is there
[4:44:16]
any action that council wishes to take
regarding these part-time positions or
[4:44:19]
part regarding these positions? Sorry.
>> All right. Revenue part-time and public
[4:44:25]
works. I'd like to make a motion to open
that new
[4:44:30]
» he this one or this one read that one
and that one
[4:44:35]
» public works foreman and the part-time
the revenue clerk part time
[4:44:42]
Rick's making a motion uh to authorize
the uh manager uh Mr. Mar to uh find
[4:44:49]
someone to fill the revenue part-time
position and to hire a public works
[4:44:52]
foreman. Is that correct Rick? I don't
put words in your mouth
[4:44:55]
» and to fill any spots that opens up to
somebody internal takes it.
[4:45:00]
» Yes.
>> All right. Is there a second to that
[4:45:02]
motion?
>> Second.
[4:45:04]
» Gary has a second. Any discussion on
this motion?
[4:45:09]
» I hear no discussion. Uh Seth,
>> yes.
[4:45:13]
» Gary,
>> yes.
[4:45:14]
» Rick Jan,
>> yes. The motion carries. It is
[4:45:18]
unanimous. Our next regular meeting is
on March the 10th. Is there a motion to
[4:45:22]
adjurnn? I'll make the motion.
>> Rick has the motion to adjurnn. Laura
[4:45:25]
has a second. All in favor of adjourning
say I.
[4:45:28]
» I.
>> Any opposed?
[4:45:31]
» The meeting is adjourned. Thank you.
[4:45:36]
I've been working here