right, we're going to go ahead and get
[0:14]
started. Um, thank you everybody for
[0:16]
coming. We obviously overprepared, but
[0:18]
that was that's fine. I don't mind
[0:20]
having extra copies for everybody. And
[0:21]
then we will leave um the extras that
[0:23]
are out there at uh town hall. Um, so
[0:25]
you can let people know if they have
[0:27]
questions or comments after the fact,
[0:28]
they can just, um, stop by and leave
[0:30]
them there. So, um, thank you all for
[0:32]
coming tonight. My name is Mary Fitini
[0:33]
and I am a member of the Rochester
[0:35]
Planning and Zoning Board.
[0:37]
I'm going to be starting with just a
[0:38]
brief overview of sort of how tonight's
[0:40]
going to run, what the point of tonight
[0:42]
is as far as your planning board is
[0:43]
concerned. I'm going to do a thousand
[0:46]
foot view of the permitting process for
[0:48]
cell phone towers in the state of
[0:50]
Vermont. Um, then I'm going to turn it
[0:52]
over to Francis Pissy who is here from
[0:54]
Vert.ex X Towers who is going to give um
[0:56]
a presentation on some of the facts
[0:59]
about this possible project. And there's
[1:02]
a reason I'm calling it a possible
[1:03]
project which is to say the application
[1:04]
has not yet been submitted to the uh
[1:07]
public utilities commission. Um so
[1:09]
that's the reason that that is the very
[1:11]
specific language that I'll be using
[1:12]
tonight. Uh when Francis is done, we're
[1:15]
going to open it up the floor to
[1:16]
questions. Dan McKinley, everybody's
[1:18]
favorite moderator, is going to be
[1:19]
running that. Um, and we planned about
[1:22]
40 minutes or more for that. And since
[1:24]
we're a small group tonight, um, I'm
[1:26]
hoping we can get through your questions
[1:28]
and time permitting, you know, we'll
[1:29]
open up the floor to comments as well.
[1:31]
So, um, this is a public information I
[1:34]
wrote meeting. Let me emphasize that
[1:36]
this is not a formal meeting. This is a
[1:37]
public information session, uh, about
[1:40]
the 248 permitting process for cell
[1:42]
phone towers and the possible cell tower
[1:45]
project um, at 10:30 10:30 Route 100
[1:48]
South in Rochester. There are no
[1:50]
decisions being made here tonight. And
[1:52]
this meeting is specifically designed to
[1:54]
do three things, right? It's so that we,
[1:56]
your planning board, can give you some
[1:57]
basic information about how cell phone
[1:59]
towers are permitted. It's so that we
[2:01]
can get some basic information about the
[2:03]
possible project um from Vert.ex towers
[2:06]
and to give you a chance to ask those
[2:08]
questions either about the information
[2:09]
we're presenting here tonight,
[2:11]
information that is not presented that
[2:13]
you would like us to get for and to you
[2:16]
um or anything else um after we've
[2:18]
covered that that you think um would be
[2:20]
relevant. So um this is not the only
[2:24]
chance you will have to learn about or
[2:26]
talk about cell phone tower permitting
[2:28]
in the town of Rochester. This is not
[2:30]
the only chance. There will be many. Um,
[2:32]
we are very committed as your planning
[2:34]
board to hearing from as many people as
[2:36]
possible in as many forums as possible
[2:39]
at the moments when your contributions
[2:41]
are most useful and effective for you.
[2:44]
So, I just want to keep emphasizing
[2:45]
that. Um,
[2:48]
we will have a couple of people
[2:49]
available via Zoom for some technical
[2:51]
questions if they come up. We have two
[2:52]
people from Two Rivers Aquichi Regional
[2:54]
Planning Commission. We also have an
[2:56]
engineer from Vert.Ex if your questions
[2:58]
end up being a little bit more
[2:59]
technical. So
[3:02]
some of my logistics since we are
[3:04]
smaller I can go I can skip ahead to um
[3:08]
I do want you to know that we are trying
[3:09]
to centralize the information so that
[3:11]
you can go to one point and all of the
[3:13]
documents will be there. We haven't got
[3:15]
that set up quite yet but we have set up
[3:17]
a separate email account for questions
[3:19]
and comments about it. That's what's on
[3:20]
your postcard which is rochestervt
[3:23]
planning commission@gmail.com.
[3:25]
Um, and that again is so that nothing
[3:26]
kind of slips through the cracks, right?
[3:28]
If you email or contact one of the
[3:29]
planning board members individually, um,
[3:32]
we talk a lot, but this way we make sure
[3:35]
that everybody's getting the same
[3:36]
information. So, thousand foot view. Um,
[3:40]
yep, this is what I said. Oops, my
[3:42]
slideshow is not there. There we go.
[3:48]
Oh, no.
[4:05]
There we go. Okay. This is basically
[4:08]
just what I said, equal parts. Um, the
[4:11]
information I'm giving to you is coming
[4:12]
from a public guide that was pres uh
[4:14]
published by the Vermont Public Service
[4:15]
Department. This will be available to
[4:17]
you. I am not a lawyer. I am not a
[4:19]
planner. I am a member of the board and
[4:20]
I am summarizing this public information
[4:22]
to you as best we can.
[4:25]
Uh
[4:27]
the town of Rochester does not permit,
[4:29]
grant, deny cell phone towers. That is a
[4:32]
power that is reserved to the state.
[4:34]
Okay. The town of Rochester does not
[4:36]
grant or deny them. There are specific
[4:38]
ways and moments that we can participate
[4:40]
in this process. But the decision for
[4:42]
permitting uh towers is made by the
[4:44]
public utilities commission. uh the PUC
[4:47]
will grant or deny something called a
[4:49]
certificate for public good. The
[4:50]
department Vermont public service
[4:52]
department will represent the public
[4:54]
interest in such proceedings. Um and
[4:57]
again I'm I'm going to come back to this
[4:59]
because there is a role for the town but
[5:01]
it can be most effective if we're clear
[5:03]
about where we can speak, who we can
[5:05]
speak to, and what it is that they wish
[5:07]
to hear from us at any particular point
[5:08]
in time.
[5:11]
Um
[5:12]
there's two phases to a permit. There's
[5:15]
this the step one, right, which is
[5:16]
submitting the application. Um, an
[5:18]
applicant has to submit what's called a
[5:20]
45day notice of intent to apply. They
[5:22]
have to submit that notice to the public
[5:24]
utilities commission, the department of
[5:26]
public service, the host town, and the
[5:28]
adjoining land owners. After they 45
[5:31]
days or more after that, they submit an
[5:33]
application to the public utilities
[5:34]
commission and the PUC has to declare
[5:37]
the application complete. All right,
[5:38]
this is the first step. So far, we have
[5:42]
received a 45 45day notice of an intent
[5:44]
to apply from Vertex Towers for a
[5:46]
possible project at 10:30 Route 100
[5:48]
South. We received it on June 12th. That
[5:52]
is the only thing that has happened so
[5:53]
far. Okay. The application has not been
[5:56]
submitted and therefore the Public
[5:57]
Utilities Commission, excuse me, hasn't
[6:00]
declared it complete because it doesn't
[6:01]
exist yet.
[6:04]
After the Public Utilities Commission
[6:06]
declares a an application is complete,
[6:08]
we enter the 30-day comment period.
[6:10]
There's 30 days for parties,
[6:12]
interveners, and individuals to submit
[6:14]
comments to the Public Utilities
[6:15]
Commission. The host town is
[6:17]
automatically granted the right to uh
[6:19]
submit these comments. I'll talk about
[6:22]
that a little bit more in a second. Um
[6:24]
after the application has been declared
[6:26]
complete, the Public Utilities
[6:28]
Commission has 60 to 180 days to issue a
[6:31]
ruling. The reason I say 60 to 180 days
[6:34]
is because uh it depends on whether or
[6:36]
not the public utilities commission sees
[6:38]
any significant issues with specific
[6:40]
criteria. If they do not, they have to
[6:42]
issue a ruling within 60 days. If they
[6:44]
do, they can take up to 180 days to
[6:47]
issue a ruling. Okay.
[6:51]
There are three ways for towns to
[6:53]
participate in the 248A process. they
[6:56]
can have a public meeting
[6:59]
uh where we request we can request a
[7:01]
public meeting with the applicant and
[7:02]
the public service department. This is
[7:04]
actually the second time that we've
[7:06]
asked somebody from Vertex to come and
[7:07]
present. Um
[7:10]
we did invite somebody from the public
[7:11]
utilities commission tonight and they
[7:13]
said that they were not going to um
[7:16]
comment until the application had been
[7:18]
filed. So that could very well happen
[7:20]
again. Uh submitting comments. This is
[7:22]
what happens during the 30-day comment
[7:24]
period after the application has been
[7:26]
declared complete. Uh we file them in
[7:28]
writing. The public utilities commission
[7:30]
has to give a detailed response to every
[7:33]
recommendation that we submit also in
[7:35]
writing. And then we can also
[7:37]
participate as a formal party if the
[7:38]
public utilities commission ends up
[7:40]
having evidentiary hearings and things
[7:42]
like that. Um the host town is already
[7:45]
given the right to intervene um as the
[7:48]
host town. Okay. So again, public
[7:51]
meeting is the only thing that happens
[7:52]
after the 45day notice. The comments and
[7:54]
the intervention require the application
[7:56]
to have been declared complete.
[8:01]
Some things that the public utilities
[8:02]
commission considers, and this is not an
[8:04]
exhaustive list, uh will the project
[8:07]
have what's called undue adverse effects
[8:09]
on specific criteria? And I'll list
[8:12]
those criteria in a minute. How will the
[8:14]
project affect the land conservation
[8:16]
measures in the plans of the affected
[8:19]
municipalities?
[8:21]
What are the recommendations that the
[8:22]
town legislative bodies or town or
[8:24]
regional planning commission submits in
[8:26]
writing to the planning uh to the PUC?
[8:29]
How does the project um service the
[8:32]
public good or the state's interest as
[8:35]
it's specifically articulated in a
[8:37]
specific statute? And I'm not going to
[8:39]
go into the statute tonight, but number
[8:40]
four becomes very important in terms of
[8:42]
thinking about how the state does or
[8:45]
does not defer to town plans. Right? Um
[8:49]
this question of what is the public good
[8:51]
and what is the state's interest is
[8:52]
something that the public utilities
[8:53]
commission has to consider.
[8:58]
Uh undue adverse effects.
[9:00]
I'm not going into this in great detail.
[9:02]
These are the categories um that the
[9:04]
public utilities commission is looking
[9:06]
at. If a project causes undue adverse
[9:08]
effects to one of these categories, they
[9:10]
can deny the permit. Okay. Um, we have
[9:14]
more information about this. I can give
[9:15]
you more information about this, but in
[9:16]
general, this is something that the PUC
[9:18]
itself is looking at. Aesthetics,
[9:20]
historical sites, air and water purity,
[9:23]
the natural environment, public health
[9:25]
and safety, and the public use and
[9:27]
enjoyment of the 89 and 91 scenic
[9:30]
corridors and other highways designated
[9:32]
um as scenic roads.
[9:37]
You're probably going to get sick of
[9:38]
hearing me say these words substantial
[9:40]
difference and good cause, but they're
[9:42]
I'm going to say them over and over
[9:43]
again. So, town plans and town planners
[9:46]
fit into this process in a very specific
[9:48]
way. The public utilities commission
[9:50]
must give what they call substantial
[9:52]
difference to the land conservation
[9:54]
measures in the plans of the affected
[9:56]
municipalities and the recommendations
[9:58]
of the municipal and regional plans
[10:01]
unless they find there is good cause to
[10:03]
find otherwise. Okay. So substantial
[10:05]
difference, land conservation plans,
[10:07]
recommendations, good cause, these
[10:08]
things all matter.
[10:12]
So what does it mean? Substantial
[10:14]
difference
[10:16]
means they have to give significant and
[10:18]
meaningful weight to the following
[10:20]
things to the land conservation measures
[10:22]
in the plans of affected municipalities.
[10:24]
This is our town plan which I believe
[10:26]
was most recently updated in 2020 and is
[10:29]
available on the town website. They have
[10:32]
to give substantial difference to the
[10:33]
recommendations of municipal and
[10:35]
regional planning commissions regarding
[10:38]
the impact and the relationship between
[10:40]
a possible project and our town plans.
[10:43]
Okay. Um so they have to give
[10:46]
significant and meaningful weight to
[10:48]
town plans and what towns think the
[10:51]
possible project how it fits into their
[10:54]
town plans. But substantial difference
[10:56]
is not it's a category, right? Unless
[10:59]
there is good cause for them to find
[11:01]
otherwise. And here's what it means to
[11:03]
find otherwise. Right? If deferring to
[11:06]
the land conservation measures in the
[11:08]
plans of affected municipalities and the
[11:11]
recommendations of the planning
[11:12]
commissions would be detrimental to the
[11:15]
public good or the state's interest as
[11:18]
articulated in this specific statute.
[11:20]
Okay. Um, so so they they have to
[11:24]
substantially defer to town plans to
[11:28]
recommendations by the town planning
[11:29]
commissions, but they have to also weigh
[11:32]
this question of the public good and the
[11:34]
state's interest as it's defined in this
[11:36]
statute.
[11:38]
Um,
[11:42]
there's a reason I call this the
[11:43]
thousand foot view, right? Um,
[11:46]
that is very much the thousand foot
[11:48]
view. Um, but I think I find it
[11:51]
important to understand how our process
[11:52]
works in order to figure out where I fit
[11:55]
into the process, how I can make my
[11:58]
voice heard effectively. Um, and in so
[12:01]
far as we are your planning board are
[12:03]
doing that, we want to do that for you
[12:05]
as well. So to sort of sum up my summary
[12:09]
and this document will also be
[12:10]
available. The state grants or denies
[12:13]
permits to cell phone towers through the
[12:15]
section 248A process. Rochester will not
[12:18]
grant or deny the permit. There are
[12:20]
specific steps in applying for a
[12:23]
certificate of public good. The only
[12:25]
step that has been taken so far was the
[12:27]
45day notice of the attempt to apply.
[12:30]
The application itself has not been
[12:32]
filed um or declared complete. So the
[12:35]
rest of that process, which can take up
[12:37]
to 180 days, hasn't started yet.
[12:41]
There are specific ways for the town to
[12:43]
participate. They happen at specific
[12:46]
points in the process and they cover
[12:47]
specific information from the town to
[12:50]
the state regarding our town and
[12:52]
regional plans. And the public utilities
[12:55]
commission considers many elements, but
[12:58]
they are specific criteria,
[13:01]
land conservation measures and town
[13:03]
plans,
[13:05]
recommendations by town and and regional
[13:07]
planners, and this question about the
[13:09]
public good and the state's interest.
[13:11]
Okay. Um that's my thousand foot view.
[13:14]
We do have somebody from um Two Rivers
[13:16]
who will be here to answer questions if
[13:18]
you have more specific things um when we
[13:20]
at the end of the meeting. So thanks
[13:22]
very much for your time and patience
[13:23]
with my little PowerPoint and I'm going
[13:25]
to hand it over to Francis who is going
[13:28]
to present some um basically sub
[13:31]
substantial information about uh the
[13:33]
possible project.
[13:38]
Provided I can get this to work the way
[13:40]
I want.
[13:42]
>> Give you this.
[13:54]
» Are we gonna hold questions until
[13:56]
>> I had Yes. And well, let me rephrase.
[13:59]
Yes, that was my plan.
[14:03]
>> But I
[14:08]
to watch your feet.
[14:21]
» Thanks.
[14:24]
>> Uh, good evening. My name is Francis
[14:25]
Paresi. I'm a representative of Vertex
[14:28]
Towers. Um
[14:30]
I was actually here in front of the
[14:32]
planning commission back in early
[14:34]
September and gave a similar
[14:36]
presentation. So that for those of you
[14:37]
that were here, a lot of this is
[14:39]
duplicative, but I think there's some
[14:40]
new people in the audience and um
[14:42]
definitely some um questions with
[14:45]
respect to the the type of facility that
[14:47]
we're proposing. Uh, I actually thought
[14:49]
Mary did a great job of defining kind of
[14:51]
the overview of the the permitting
[14:53]
process and I'll kind of uh defer to
[14:56]
Mary on that, but uh um but I thought
[14:58]
she did a very good job of explaining
[14:59]
it. Um, by way of introduction, Vertex
[15:02]
Towers is what we call a wireless
[15:04]
infrastructure developer. Um, the names
[15:06]
that you've heard of in the cell phone
[15:07]
arena, Verizon and AT&T and T-Mobile
[15:11]
have pretty much gotten out of the real
[15:12]
estate business. They're focused on
[15:14]
developing their telecommunications
[15:16]
networks and they partner up with folks
[15:17]
like Vert.Ex to build wireless
[15:19]
infrastructure. We're actually based in
[15:21]
Massachusetts. We've done uh probably 30
[15:25]
towers throughout Massachusetts and New
[15:27]
Hampshire and Vermont. Um in areas as
[15:31]
equally scenic and rural as as um
[15:34]
Rochester. Um, and what we found is that
[15:37]
if we can be more thoughtful about where
[15:39]
we place these type of facilities, where
[15:42]
because we're not Verizon or not um,
[15:44]
AT&T, we can look more closely at your
[15:47]
land use, your um, zoning regulations,
[15:50]
the PUC process, and come up with very
[15:52]
thoughtful solutions. It's been very
[15:54]
well received. In addition, it's a way
[15:56]
of bringing telecommunications to rural
[15:59]
areas like Rochester because, as you can
[16:02]
imagine, somebody like Verizon is trying
[16:04]
to f provide coverage to the entire
[16:06]
United States, including Rochester,
[16:08]
Vermont, and Montpelia, Vermont, and
[16:11]
Boston, Massachusetts, and Oklahoma, and
[16:13]
California. And it's just a real
[16:15]
challenge for them to get everywhere all
[16:17]
at once and satisfy everyone's
[16:18]
individual concerns. So, they partner
[16:20]
with folks like Vert.Ex s to do like the
[16:23]
infrastructure and the the the due
[16:24]
diligence. Um in this particular case,
[16:27]
we've already got a commitment from
[16:29]
Verizon Wireless. They um they are very
[16:31]
actively uh building out their network
[16:33]
in Vermont. They have pretty good
[16:36]
coverage along the I9089 corridor. Um
[16:39]
but now they're focused on the uh Route
[16:41]
100 corridor. Um there was recently a
[16:44]
tower built in Stockbridge which Verizon
[16:47]
has just installed their antennas but
[16:48]
haven't turned them on yet. There's a
[16:50]
tower in Granville that was built a
[16:52]
couple years ago that uh uh was uh
[16:56]
Verizon is on that as well. There's
[16:58]
towers along the Bethl and the Randolph
[17:00]
and the 89 corridor on the other side of
[17:03]
the hill between here and and 89, but uh
[17:06]
um they're very actively trying to build
[17:07]
out their network along the Route 100
[17:09]
corridor and and have partnered up with
[17:11]
Vert.Ex to find a solution in Rochester.
[17:14]
Um I hope I don't need to sell cell
[17:17]
phone coverage in general. The need is
[17:19]
there. You know, the statistics are
[17:21]
staggering. Over 50% of America has cut
[17:24]
the cord is only using wireless phones
[17:26]
as their only source of communications.
[17:28]
80% of 911 calls are made by cell
[17:31]
phones. And uh you know, there's clearly
[17:33]
if if anyone's a Verizon customer, you
[17:35]
can certainly attest to the fact that
[17:36]
there's a gap in coverage here um with
[17:39]
uh with telecommunications. We do a lot
[17:41]
of work with regional planning
[17:43]
commissions throughout all of New
[17:44]
England including um um New Hampshire
[17:48]
and New Hampshire has deemed the lack of
[17:50]
cell phone coverage a public safety
[17:52]
hazard. So when respect to the
[17:54]
certificate of public good um you know
[17:57]
it's actually really for easy for us to
[17:59]
show that there is a public good because
[18:00]
we're bringing better
[18:02]
telecommunications, a better u um public
[18:05]
safety network, a better um
[18:08]
telecommunications. What's happened too
[18:10]
is that um we actually thought that this
[18:12]
was going to be when I've been doing
[18:14]
this for about 20 or 25 years when I
[18:16]
first started I thought it was a mobile
[18:17]
technology where we're going to provide
[18:18]
coverage up Route 89 and um you know
[18:21]
maybe some of the tertiary roads but
[18:23]
what's happening is it's evolving into a
[18:25]
residential technology and people are
[18:27]
using it in their homes as their primary
[18:28]
source of telecommunications and over
[18:30]
the last several years with the pandemic
[18:32]
people are trying to work from home and
[18:34]
educate from home and so better
[18:35]
telecommunications networks are um are
[18:38]
just a necessity at this point. Um um
[18:42]
Verizon has spent an immense amount of
[18:44]
time exploring different options,
[18:46]
looking at um um um um different
[18:50]
solutions to this. And as you can
[18:52]
imagine, the Route 100 corridor is an
[18:54]
incredibly challenging area given the
[18:56]
topography. You know, Route 100 and the
[18:58]
town of Rochester is in a valley
[19:00]
surrounded by very tall peaks and those
[19:03]
peaks become structural impediments to
[19:04]
telecommunication signal. So even though
[19:06]
there's very good coverage on the other
[19:08]
side in the Bethl and the Route 89
[19:11]
corridor, there's uh a significant gap
[19:14]
in coverage along the route 100
[19:15]
corridor. Uh and we uh um we will
[19:19]
provide all of this to the town as part
[19:21]
of the PUC application process. But this
[19:24]
basically shows all the different sites
[19:26]
that Verizon already enjoys. you know,
[19:28]
along Royaltton, there's a tower in
[19:30]
Bethl, right as you get off the highway,
[19:32]
just pretty close to downtown that uh um
[19:35]
and then um several other sites going up
[19:37]
into along the 89 corridor. But they
[19:41]
actually have no sightes on the air um
[19:43]
south of what I would call north
[19:45]
Granville and um up towards the um um
[19:48]
the the Sugar Ski area. So, there's
[19:51]
really no coverage along now. They've
[19:52]
gotten one tower that they just uh put
[19:55]
the antennas on but haven't turned them
[19:56]
on yet down um at the Stockfield
[19:59]
Stockbridge Pittsfield line that'll
[20:02]
provide some coverage coming up Route
[20:03]
100 from Stockbridge into Rester.
[20:07]
But we're trying to find a solution for
[20:10]
that, you know, very long stretch of
[20:11]
Rochester from the Stockbridge line all
[20:14]
the way going up into Hancock. Um um and we can look at this at at a
[20:20]
unfortunately it gets very technical.
[20:22]
Verizon broadcasts at multiple different
[20:24]
frequency bands. Um, as we get more and
[20:27]
more users of cell phone technology,
[20:29]
they deploy multiple frequencies. Uh,
[20:32]
you know, this was shown at the lower
[20:33]
frequency bands. are some of the
[20:35]
historic um low band frequencies. And as
[20:37]
you go up into the higher bands, 850
[20:39]
meghertz, the the 1900 meghertz of what
[20:42]
they call PCS, the the um the what
[20:47]
happens is that you use higher
[20:49]
frequencies, the coverage gets less and
[20:52]
less. So you want to try to get it as
[20:54]
close to the residential and commercial
[20:56]
and industrial users as possible without
[20:59]
um getting too impactful for them to
[21:02]
take advantage of the higher frequency
[21:04]
bands and the uh um higher data speeds
[21:07]
that come with that. Um and uh um so um
[21:11]
on behalf of Vertex and in partnership
[21:13]
with Verizon, we've been looking for
[21:15]
solutions here and in more urban areas,
[21:18]
you have tall structures, water tanks,
[21:20]
church depotles. I know there's a church
[21:22]
steeple in town that AT&T has antennas
[21:24]
in, but as you can imagine, that's a I
[21:27]
just looked at it. It's about a 30- foot
[21:28]
tall church steeple. It wasn't designed
[21:30]
for telecommunications. It wasn't
[21:31]
designed to get over the hills going
[21:33]
just uh a quarter mile south, just past
[21:35]
where we are right now. Um or even a
[21:38]
quarter mile north. So, it it you know,
[21:40]
AT&T enjoys a little bit of coverage
[21:43]
along the um the what I would call the
[21:45]
downtown Rochester area, but church
[21:47]
steeples weren't designed with
[21:48]
telecommunications in mind. they um they
[21:51]
weren't designed for the type of
[21:52]
antennas that multiple telecommunication
[21:54]
companies enjoy or deploy for their u um
[21:58]
their network. So um although AT&T has a
[22:01]
little bit of coverage downtown, Verizon
[22:03]
has no coverage, T-Mobile has no
[22:04]
coverage, and that's what we're trying
[22:06]
to find a solution to to resolve. Um the zoning map here actually allows
[22:12]
us to go anywhere in town. you know,
[22:14]
there's some restrictions with respect
[22:16]
to uh going too close to the river and
[22:18]
the uh the the resource areas down close
[22:21]
to the river, but for the most part,
[22:23]
we're in a a residential agricultural
[22:25]
zone um which is a permitted zone under
[22:28]
the zoning bylaw. the zoning bylaw even
[22:31]
though it's not applicable here because
[22:33]
as Mary explained uh we are we follow
[22:36]
the state PUC guidelines with respect to
[22:38]
these things but the state actually
[22:40]
looks to the town to say what does your
[22:42]
zoning allow or not allow and this type
[22:45]
of facility is allowed in all um
[22:49]
districts other than the flood overlay
[22:50]
district and the echo for recharge
[22:52]
district which are down closer to the
[22:53]
river um and the only requirement is
[22:56]
that we meet what they call um 150% % of
[22:59]
tower height setback from all abuing
[23:02]
property lines. So from so we look at it
[23:06]
it's compliant in all respects with your
[23:08]
zoning bylaw even though and the PUC
[23:10]
will look at that as part of the the
[23:12]
application process. Um the proposed
[23:15]
facility is 1030 Route 10. It's a very
[23:18]
large I think it's 244 acres um with a
[23:21]
little bit of frontage on Route 100, but
[23:24]
a substantial back lot um going way back
[23:27]
um up uh u for those of you that don't
[23:31]
know it's on the as you're heading north
[23:34]
on Route 100, it's on your right. Um uh
[23:37]
it's kind of um if you look for a
[23:39]
landmark, this I believe this is called
[23:40]
the um the garage road. Um, and so it's
[23:44]
kind of uh straight opposite there,
[23:46]
right down where uh uh I there's a a
[23:50]
little store right here. I forget the
[23:51]
name of it, but uh you can see it's kind
[23:54]
of straight on there from the garage
[23:55]
road looking up the hill. U so and it's
[23:58]
um amply set back from all abuing
[24:01]
properties. We have to be 150% um and
[24:05]
we're uh substantially more than that
[24:08]
from all abudding properties uh and and
[24:11]
public rights away. We're about 2,000 ft
[24:13]
off of Route 100. Um and and I think the
[24:17]
closest property line is um over 300
[24:20]
feet away. So substantially more than
[24:22]
the setback required by the zoning
[24:24]
bylaw. Um one one of the things we were
[24:27]
here back in uh September and a lot of
[24:30]
people expressed questions and concerns
[24:33]
and in anticipation of that I uh I went
[24:36]
back to the engineers and uh asked them
[24:38]
you know can we tweak this at all? Can
[24:40]
we be more thoughtful? Can we be more
[24:42]
responsible to some of the town folks
[24:45]
concerns? And two of the things that we
[24:47]
came up with um to reduce to that we had
[24:50]
originally proposed and the notice that
[24:52]
we provided the town said that we were
[24:53]
going to build a tower that was 170 ft
[24:56]
tall and um given some concerns by the
[25:00]
uh people given the fact that AT&T
[25:03]
already has a little bit of coverage in
[25:04]
town. Um and even though we're trying to
[25:06]
build a a telecommunications facility
[25:08]
that accommodates multiple
[25:09]
telecommunications providers including
[25:12]
Verizon, we've reduced the tower height
[25:14]
to 140 ft. And so I think that's
[25:16]
relevant because when we start looking
[25:18]
at um some of the photos and the
[25:20]
visibility, you'll see that that is a
[25:22]
substantial concession from a visibility
[25:24]
perspective to diminish the visibility
[25:27]
from um the Route 100 corridor and from
[25:30]
like where we are right now and closer
[25:31]
to downtown Rochester where the the the
[25:34]
common is in the library, but also uh um um reducing the impact on on um
[25:43]
nearby residences. Um in addition um we
[25:47]
did a standalone um this this type of
[25:49]
facility will utilize an a very long
[25:53]
existing
[25:54]
uh logging road that's already there. I
[25:56]
have pictures if you want to see it.
[25:58]
We're doing a very short extension uh in
[26:00]
our mind short about 500 ft from the end
[26:02]
of the existing logging road. And we
[26:05]
were able to design that extension and
[26:07]
the compound in such a way so that it
[26:10]
reduces the amount of permanent
[26:11]
disturbance um which is a a technical
[26:14]
term that uh the PUC uses to define the
[26:18]
applicability and the scope of this
[26:19]
project and also um uh uh eliminate the
[26:24]
amount of imperous surface. Um we we
[26:27]
don't uh these facilities once built are
[26:29]
very um dimminimous in nature. Even
[26:32]
though it's a 244 acre parcel, we're
[26:34]
only using about 3,000 square ft of that
[26:37]
for the compound. A 50 by 50, a little
[26:40]
bit of construction and some runoff
[26:42]
prevention, but uh from a a site
[26:45]
disturbance perspective, it's quite
[26:47]
dimminimous. And uh and one of the
[26:49]
require one of the reason why we did
[26:50]
that is because Mary didn't her in her
[26:54]
uh 10,00t overview, there's really two
[26:56]
processes that the PUC looks at. If you
[26:59]
have a taller tower and a more
[27:02]
substantial development, they give a
[27:04]
full review, but uh they give a more
[27:07]
limited review to sites that are what
[27:08]
they call limited size and scope. And by
[27:11]
redefining the height of the tower and
[27:13]
by redefining the the the access and the
[27:16]
uh amount of temporary disturbance that
[27:18]
we're doing, um we we will we will meet
[27:20]
the li the uh limitations of that
[27:23]
limited size and scope under the PUC
[27:25]
regulations. But I think it's relevant
[27:26]
to the town because I just want to show
[27:29]
uh um we're trying very hard to
[27:31]
accommodate the town, accommodate area
[27:32]
residents, but also accommodate the
[27:34]
telecommunications signal because if we
[27:36]
make it too short, then it doesn't get
[27:38]
over the topography and the terrain to
[27:40]
uh um satisfy the coverage objectives.
[27:42]
So um and this was an issue for u that
[27:45]
came up at the last um thing um the last
[27:48]
public hearing that we had at the given
[27:50]
that um because we were using an
[27:53]
existing access road uh we had actually
[27:56]
considered that permanent disturbance
[27:57]
but when we look more into the
[27:59]
regulations and using some construction
[28:02]
techniques um we're we're really just
[28:05]
utilizing an existing road and so that's
[28:07]
a great advantage of town we're not
[28:08]
doing a lot of permanent disturbance to
[28:10]
build an access driveway and If you can
[28:13]
imagine, your zoning by requires us to
[28:15]
be 150% tower height setback. Um um um I
[28:19]
don't and you guys don't want us to be
[28:21]
down in the Route 100 corridor because
[28:24]
that would be way too visible from the
[28:26]
100 corridor. So we got to be up away
[28:28]
from the road and that requires us to go
[28:30]
up substantially up slopes and things,
[28:32]
but we're able to find a a lot that has
[28:36]
an existing logging road. So it it it
[28:38]
minimized the amount of permanent
[28:39]
disturbance that we do. it uh um we were
[28:43]
able to um redesign the compound to make
[28:45]
them more pvious so that really the
[28:48]
total amount of um new impervious
[28:52]
surface is only about a 1500 square ft.
[28:55]
It's just a small equipment compound. Um
[28:57]
and the uh total perimeter earth
[28:59]
disturbance is under 10,000 square ft.
[29:02]
Um um once we um and as Mary showed,
[29:06]
there's a lot of criteria that we need
[29:07]
to satisfy to um to get the certificate
[29:10]
of public good from the uh public
[29:12]
utilities commission. But and once you
[29:14]
reduce the scope of it to its limited
[29:17]
scale and scope really what you just
[29:19]
have to make sure that you're not in a
[29:20]
flood hazard area which we're nowhere
[29:22]
near as you can imagine being up on that
[29:23]
high on the hill and that we don't have
[29:25]
what Mary highlighted was the undue
[29:28]
adverse impact on the scenic or natural
[29:30]
resources um uh and natural areas and we're very conscious of that. We
[29:35]
understand that Route 100 is a scenic
[29:37]
corridor. We also understand that
[29:38]
there's other cell towers already built
[29:40]
along the Route 100 corridor, but um
[29:42]
being respectful of that and being
[29:44]
conscious of that um we believe we've
[29:47]
designed a facility that will not have
[29:49]
an undue adverse impact on the on the
[29:52]
scenic beauty of the Route 100 corridor.
[29:54]
Um like I said, the compound itself is
[29:56]
really dimminimous. It's a three a 60x
[29:58]
60 bench in compound which will have a
[30:01]
small foundation for the tower itself
[30:03]
and small equipment pads for initially
[30:06]
Verizon and then other
[30:07]
telecommunications companies that'll uh
[30:10]
collocate on the future um you know so
[30:12]
from and given that the you know it's
[30:14]
350 ft from the nearest uh property line
[30:19]
and thousands of feet from the nearest
[30:21]
public rightway no one's going to see
[30:23]
the compound itself or the electronic
[30:25]
equipment um once It's constructed. It's
[30:28]
completely unmanned. There's no noise,
[30:30]
smoke, odors. Um there will be a small
[30:32]
generator up there that is a third
[30:35]
source of power. We'll bring primary
[30:37]
power up there. We will bring um backup
[30:40]
batteries in case of a short-term power
[30:41]
failure. And if there a long-term power
[30:43]
failure, there'll be a generator, but
[30:45]
it's not something that's powered
[30:46]
primarily by generator. So, the
[30:47]
generator runs only in the um uh event
[30:51]
of a very long-term power failure. Um
[30:53]
the tower itself is what we call a
[30:55]
lattice tower. It's basically a giant
[30:57]
erector set on which um um Verizon will
[31:01]
attach antennas and then over time
[31:02]
multiple other telecommunications
[31:04]
companies will attach antennas. It's
[31:05]
similar to other towers in the area. Um
[31:08]
we find that this um um erector set, you
[31:12]
know, it's um when you look at it from a
[31:15]
distance, you actually can see through
[31:17]
it. So it actually provides a more um
[31:21]
unobtrusive um visibility from various
[31:24]
vantage points. And this picture is
[31:26]
significant because the picture that I
[31:27]
showed at the last meeting showed 170
[31:29]
foot tower, but again due to um attempts
[31:33]
to address towns folks concerns um we've
[31:36]
reduced the height to 140 ft. U and
[31:39]
everyone thinks that 140 ft you're going
[31:41]
to see that all over town because that's
[31:43]
the tallest thing in town. But as you
[31:45]
can imagine, when you're set back from
[31:48]
abuing property lines by hundreds and
[31:50]
from the from route uh 100 by thousands
[31:52]
of feet and when you have a tree in your
[31:55]
foreground, you know, you don't see 100.
[31:58]
No one's going to see 140 ft of tower.
[32:00]
Um, I I can't make it invisible, but I
[32:03]
think it's you're going to uh find that
[32:05]
it's going to be of minimal visibility,
[32:07]
distant visibility, and and very short
[32:11]
amounts of the tower and not the full
[32:13]
140 ft. Um um with respect to public
[32:18]
safety, these are very lowowered
[32:20]
transmissions. These are um um it's not
[32:23]
designed to cover all of Vermont or even
[32:25]
all the 100 corridor from Killington to Sugar Bush. It's really designed to
[32:29]
cover a couple square miles. And don't
[32:31]
quote me on that because it's a very
[32:33]
amorphous coverage objective, but uh and
[32:36]
as you can imagine, given the Route 100
[32:38]
corridor, it's really a linear coverage
[32:40]
objective as opposed to a a 360 degree
[32:43]
coverage objective. But uh um these are
[32:46]
designed to be well below Apple FCC
[32:49]
limits. And the reason is it's a two-way
[32:51]
communication. Everyone has a cell
[32:52]
phone. This is a low powered
[32:54]
communication to the nearest cell phone
[32:56]
tower which the nearest cell phone tower
[32:58]
is on the other side of the hill in
[32:59]
Bethl doesn't work but uh um but uh and so for that cell phone antenna to
[33:05]
reach this it's an equally low powered
[33:07]
and they broadcast out at about 100
[33:09]
watts which is dimminimous as compared
[33:12]
to other forms of radio communications
[33:14]
that we already enjoy. There are uh FM
[33:17]
stations and AM stations in Burlington
[33:19]
that broadcast out at 50,000 watts
[33:22]
because they're trying to cover as large
[33:24]
a an area as possible. Whereas this type
[33:27]
of technology is only designed to cover
[33:30]
a stretch of Rochester going south
[33:32]
towards Stockbridge and north towards
[33:33]
Hancock. U and I'll also point out that
[33:36]
from a radio frequency perspective, the
[33:39]
town already has AT&T antennas on a
[33:42]
30-foot church depot about three blocks
[33:44]
from here. So, the downtown area gets
[33:46]
some coverage, but it's also, you know,
[33:48]
people have been living with that RF
[33:50]
exposure harmlessly. Um, and you know,
[33:54]
your zoning bylaw, Vermont law, state
[33:56]
law says if there was any um tall
[33:59]
structures that we could utilize, we
[34:01]
would. And those tall structures tend to
[34:03]
be in more habited areas. I I I actually
[34:06]
go to a church that has a 150 church,
[34:09]
150 foot steeple, and there's two it's
[34:11]
the tallest thing in the area by far.
[34:14]
and there are two sets of antennas in it
[34:16]
and I live in a much more dense village
[34:17]
area similar to Rochester and we enjoy
[34:20]
good coverage because of that church
[34:22]
steeple but because there's not a lot of
[34:24]
um other tall structures uh in um
[34:28]
Rochester we're forced to look at a new
[34:30]
tower but we've set it back so
[34:32]
substantially that it's going to be
[34:34]
significantly below all applicable FCC
[34:36]
limits with respect to radio frequency
[34:38]
exposure and what we're anticipating is
[34:41]
that we're going to get pretty decent
[34:43]
coverage along the 100 corridor from the
[34:46]
uh um um Stockbridgeidge line going up
[34:49]
all the way to the Hancock line. It's
[34:50]
going to provide uh much um and and what
[34:53]
these different colors represent is the
[34:56]
different levels of coverage. As you can
[34:58]
imagine, when you stand outdoors and use
[35:00]
your cell phone, there's no structural
[35:02]
impediment as compared to in your car or
[35:05]
in your residence or in a building like
[35:07]
this where there's a a lot of structural
[35:09]
impediment to the signal. And what this
[35:11]
tells me is that in the downtown
[35:14]
Rochester area, we'll get very good
[35:16]
inbuilding coverage um you know
[35:18]
throughout the entire what I would call
[35:21]
populated area of Rochester from here um
[35:24]
north going past the bike shop and um um
[35:28]
and the village of Rochester. And then,
[35:30]
you know, you're going to get um decent
[35:32]
coverage along the uh um the Route 100
[35:35]
corridor, all going up into Hancock,
[35:37]
connecting up with sites that are being
[35:39]
proposed in in Granville. And again,
[35:42]
this is all the different frequency
[35:43]
bands that we um talked about easier. Um
[35:47]
but everyone wants to know what's it
[35:48]
going to look like. A year ago, we
[35:50]
actually put a balloon up in the air as
[35:51]
required by the public utilities
[35:54]
commission application process to uh um
[35:58]
to put a balloon up in the air to 176 ft
[36:00]
was which was the height of the old the
[36:02]
formerly proposed tower and we took
[36:04]
pictures and I can show them to you
[36:06]
tonight. I showed them at the last
[36:08]
meeting, but I'm going to tell you as
[36:10]
was requested by the the planning
[36:12]
commission at the last meeting. Um,
[36:14]
we've agreed to put up another balloon.
[36:16]
And this balloon will be up at 140 ft.
[36:19]
And uh um and I'll I'll I'll let
[36:22]
everybody know as best I can when it's
[36:24]
going to be. We'll talk about it
[36:26]
tonight. Uh and I think that's going to
[36:28]
be very telling because people are going
[36:30]
to be able to stand in their own
[36:32]
residences or on their own properties
[36:33]
and everyone think, "Oh my god, I'm
[36:35]
going to see 140 foot thing from all
[36:37]
over Rochester." But I think you're
[36:38]
going to find that you're not going to
[36:39]
see it because of the way the topography
[36:41]
is, by the way canopy is. Um I um
[36:45]
unfortunately I'm I'm struggling with
[36:47]
dates. So that's what we'll talk about
[36:48]
as part of this process. And the reason
[36:50]
I was struggling with dates is because
[36:51]
we have an election in two weeks uh and
[36:53]
then Veterans Day. And uh so I I don't
[36:56]
want to um um talk about a date yet, but
[36:59]
uh we'll talk about it before that the
[37:01]
night is out. But the one thing I want
[37:02]
to jump to is u um the photos that we
[37:05]
took of the 176T balloon.
[37:29]
We engage engineers to um uh take these
[37:33]
photos and they do very accurate um
[37:35]
depictions. Um and what this represents
[37:38]
is a map of the town of Rochester, the
[37:40]
star being where the proposed facility
[37:42]
will be. And the red are photo places
[37:45]
where they took photographs from,
[37:46]
including the the closest places, you
[37:49]
know, along Route 100 at the base of the
[37:51]
subject property. Um um and then um up
[37:55]
here in the village and then farther
[37:57]
south along Route 100 looking towards
[37:59]
the facility. And the red spots means
[38:02]
places where they took photographs. So
[38:04]
we can scroll through that. Um there was
[38:06]
no visibility. And as you can imagine,
[38:09]
going west towards um Pittsfield,
[38:11]
there's really um you know, given the way the roads flow, given the uh
[38:16]
topography, you're not going to see it
[38:17]
from the western um looking east. Um but
[38:22]
there was some spots, pockets of
[38:24]
visibility from the village photos 8, 9,
[38:26]
and 10. And then farther south looking
[38:29]
north uh on Route 100 where that the big
[38:32]
farm is along the 100 corridor where
[38:35]
there's no uh trees to to to mitigate
[38:37]
the view. And so I'm just going to jump
[38:39]
to those photos because what those what
[38:41]
I actually have are simulations as to
[38:43]
what it's going to look like. Um so we
[38:45]
took all these photographs here. U but
[38:48]
I'm just going to jump to 8 n and 10
[38:50]
which were the three photos from
[38:51]
Rochester Village.
[38:56]
Um,
[38:58]
and this is a picture shown from, I
[39:02]
guess, the library parking lot or across
[39:04]
the street from the library by the uh um
[39:07]
the residential building across the
[39:08]
street. And uh um you could just see the
[39:10]
balloon over the trees, over the
[39:12]
buildings there. And what this
[39:13]
represents is a photo simulation of what
[39:16]
the tower is going to look like from um
[39:19]
I'm thinking that's either the library
[39:21]
parking lot or the library driveway
[39:23]
right next to it. And uh uh and as you
[39:25]
can see, it's just above the trees, just
[39:27]
above the tree canopy. What this photo
[39:29]
goes actually tells me too is that by
[39:31]
reducing it down by to the uh 140 ft
[39:34]
height, you're not going to see it at
[39:36]
all. And we will have um for the PUC and
[39:39]
for the town's view as well, um uh a
[39:42]
photo after the 140 foot balloon float
[39:45]
to to substantiate that. Um from um
[39:50]
where are we at here? Riverbrook Road.
[39:52]
Uh again, farther south looking farther
[39:56]
north looking south. Um you know, again,
[39:58]
you could see the the the balloon over
[40:00]
the the tree canopy. And then um um
[40:04]
oops. Um and then uh where's this? Um
[40:11]
uh here.
[40:12]
>> What's that?
[40:13]
>> It's here.
[40:14]
>> Oh, right here. Yeah, exactly. Right
[40:15]
here. That's And then you know, you can
[40:17]
just see the balloon over the thing. And what this tells me, like like I
[40:21]
said, I don't want to rely on these
[40:22]
photos because when we submit new photos
[40:24]
for the 140 foot balloon, you'll see
[40:27]
that you're not going to see it from
[40:28]
here as well. Um and then the other
[40:31]
places u just jump to my map there where
[40:33]
there was some visibility u you know
[40:36]
about what what looks like to be about a
[40:38]
mile south looking north. Um so photos
[40:42]
12 and 13. So I'm just going to jump to
[40:44]
those.
[40:45]
Um
[40:48]
uh and and and you know um at this point
[40:51]
you're about I think you're about a mile
[40:54]
um south of the property looking north
[40:56]
and you can you could just see the
[40:57]
balloon over the uh the tops of the
[40:59]
trees and that's what it looks like um
[41:03]
when we add when we built the tower and
[41:05]
add the antennas to it. And again, this
[41:06]
is another vantage point that I believe
[41:08]
that it will be much less visible with
[41:12]
the 140 foot tower because what I'm what
[41:14]
I can see there is about 20 to 30 ft of
[41:17]
tower. So, if we eliminate 20 ft of
[41:20]
tower height, it's going to be virtually
[41:21]
invisible on the horizon. And then u a
[41:24]
little bit uh farther back um you know,
[41:27]
it's uh um it's there. And they actually
[41:29]
enlarge it, which no one ever sees. But
[41:32]
uh um
[41:34]
uh that tells me that you're seeing
[41:36]
about 30 ft of tower. So uh again at
[41:39]
this vantage point, if we lower it down
[41:41]
from 175 to 140, it's going to be
[41:45]
virtually invisible. So I think we've
[41:46]
done um um a pretty good job of
[41:49]
addressing the town's concerns with
[41:51]
respect to visibility along the 100
[41:53]
corridor. Um
[41:56]
I just want to jump back to my other
[41:58]
presentation.
[42:12]
Um the one thing that Mary didn't talk
[42:15]
about as part of her um um presentation,
[42:20]
she and she talked very um articulately
[42:22]
about the state law PU process. The
[42:26]
federal government is also very much
[42:28]
involved in wireless infrastructure
[42:29]
sighting. About 25 years ago at this
[42:32]
actually almost uh 30 years ago the the
[42:35]
federal government adopted very
[42:36]
comprehensive um guidelines and and
[42:41]
laws. And it really stem from the fact
[42:43]
that uh you know we had one telephone
[42:45]
company back I don't want to sound like
[42:47]
my dad but back when I was a kid we only
[42:48]
had one telephone company AT&T. and they
[42:50]
broke up AT&T into multiple um
[42:54]
components and they um they gave out
[42:57]
multiple wireless licenses for the
[43:00]
purpose of promoting competition within
[43:02]
the telecommunications industry. Um and
[43:05]
at the same time the the federal
[43:07]
government adopted laws to encourage the
[43:09]
development of infrastructure. They
[43:11]
recognized the great public benefit.
[43:12]
They recognized um the the safety
[43:15]
inherent in all of this and the and and
[43:18]
the uh the benefit to all of America,
[43:20]
but certainly Rochester and the rest of
[43:22]
Vermont. Um and it just basically says
[43:25]
um uh two things that towns can't have
[43:29]
the effect of prohibiting
[43:31]
telecommunications. You can't say no, we
[43:33]
don't want it anywhere in Rochester. We
[43:35]
don't want this technology. Uh you know,
[43:37]
you can be very thoughtful as Mary
[43:39]
explained. You know, you can make sure
[43:40]
it's consistent with your plan. you can
[43:42]
make sure it's consistent with your land
[43:44]
use regulations. Um, and and again, the
[43:47]
town doesn't actually issue the permit.
[43:50]
It just makes recommendations to the
[43:53]
public utilities commission who has
[43:55]
overriding authority to determine
[43:56]
whether or not it's in the public good.
[43:59]
And you also can't say you can't uh
[44:01]
discriminate a bunch providers. And
[44:03]
that's actually relevant here. It's
[44:05]
never relevant in my world, but it's
[44:06]
actually relevant here in Rochester
[44:08]
because at the last meeting, everyone
[44:10]
said, "My AT&T phone works fine. I don't
[44:13]
need Verizon." But that's not what the
[44:14]
government's trying to do. The
[44:15]
government's trying to say, "We want
[44:17]
competition." Um um we also are work
[44:20]
with T-Mobile, another carrier that's uh
[44:23]
probably not that popular in Rochester,
[44:25]
Vermont, but they just put antennas on
[44:27]
the Stockbridge tower. They're coming on
[44:29]
our tower as well, and they'll put
[44:31]
they'll go they're building out the 100
[44:33]
corridor as well. And that provides
[44:35]
another outlet for um consumers, you
[44:38]
know, uh uh uh um you know, so that you
[44:41]
have competition within the uh um the uh the telecommunications market. Um
[44:47]
and there's been an immense amount of um
[44:51]
discussion among courts and everything.
[44:54]
you know um you know you um you can't
[44:57]
say we don't understand the health
[44:59]
effects of these type of facilities
[45:01]
therefore we don't want it because the
[45:03]
government has deemed this technology
[45:04]
safe um you uh you can't just you just
[45:08]
can't say no um you can say uh I'm sorry
[45:12]
you you you don't have to say yes you
[45:15]
but you can't say no without sufficient
[45:18]
reason like for example um I'll tell you
[45:21]
the best place to to to put a tower
[45:23]
would probably be right around here,
[45:27]
right where all the users are. You know,
[45:29]
uh, all you know, I bet half the kids in
[45:31]
the elementary school have cell phones,
[45:33]
let alone the people that used to come
[45:34]
to the high school. All of you, the
[45:36]
population of Rochester is pretty, um,
[45:39]
uh, not compact, but there's a a density
[45:42]
here in the village. Uh, and um, but
[45:45]
that wouldn't be the most appropriate
[45:46]
place to put a tower from a land use or
[45:48]
a visibility perspective. So, um um you
[45:51]
know, they they they don't say you have
[45:52]
to say yes, but they they say you can't
[45:54]
say no without sufficient reason. Um so,
[45:58]
as Mary explained, we um this process is
[46:01]
we file a notice with the town. The town
[46:04]
asked me to come. I spoke in September.
[46:06]
I'm here again. Happy to come further if
[46:08]
there more questions, but ultimately
[46:11]
we'll be filing an application with the
[46:13]
public utilities commission. And then
[46:14]
that starts a clock with respect to the
[46:16]
town. The town will have an opportunity
[46:19]
to comment. The town will have an
[46:21]
opportunity to express its opinions to
[46:22]
the public utilities commission. Uh the
[46:24]
public as well will be able to express
[46:27]
their public opinion to public utilities
[46:29]
commission. Um we've gotten through the
[46:31]
process very successfully in other um um
[46:35]
other jurisdictions. I think the public
[46:38]
utilities commission and the state of
[46:39]
Vermont recognize the need for the
[46:42]
technology. They just want to make sure
[46:44]
we've done our homework to make sure we
[46:46]
found an appropriate location and uh you
[46:49]
know something that does not have an
[46:51]
undue adverse impact with the scenic
[46:53]
resources and other um environmental
[46:56]
concerns. So with that, I'd be happy to
[46:58]
answer questions. I think Mary wants me
[46:59]
to sit down uh or or the planning
[47:02]
commission has any questions.
[47:03]
>> Uh Dan's going to moderate a Q&A. So
[47:05]
>> Okay, perfect. You
[47:06]
>> chill out here and then if there's a
[47:08]
question, we'll hand you a mic.
[47:09]
>> I don't know. You might have to go back through your
[47:13]
slides at some point if folks have
[47:15]
specific questions. So, I'm just gonna
[47:17]
sit here and call people or can folks
[47:21]
hear me? Okay.
[47:22]
>> Um,
[47:23]
actually, Dan, can you use a mic just
[47:25]
because it's running through Orca, so
[47:27]
have one share a mic? Yep.
[47:29]
>> All right.
[47:31]
>> Okay. Can you hear me right now?
[47:33]
>> All right. Great. Um, this is great.
[47:35]
turnout. We're going to have a lot
[47:37]
of questions, I'm sure. So, the way
[47:38]
we're going to work this is going to ask
[47:40]
you to just do one of your questions at
[47:42]
a time and we'll keep going around the
[47:44]
room till everyone has exhausted their
[47:46]
questions if if we have enough time to
[47:48]
do that. And if we've exhausted the
[47:50]
questions, then we'll get into hearing
[47:52]
about your thoughts on the project. Um,
[47:55]
>> a lot of people on Zoom.
[47:56]
>> Yes. Great. So maybe what we'll do is um
[48:00]
>> we'll do a we'll take a question from
[48:03]
the room and then we'll check and see if
[48:04]
there's a hand up in Zoom and then we'll
[48:07]
call on them. Um and we'll just uh give
[48:11]
hopefully everyone an opportunity to ask
[48:13]
their questions. Sound all right.
[48:17]
We'll start right here.
[48:25]
» Uh hello everyone. Excuse me. Uh Justin
[48:27]
Stober living out uh West Rochester and
[48:30]
uh thank you very much sir for coming
[48:31]
and we appreciate your presentation. Is
[48:33]
it possible that you could go through
[48:34]
your slide deck to show the coverage
[48:36]
area of the reduced height 140 foot
[48:38]
tower?
[48:39]
>> I don't have that yet but um
[48:41]
>> so there was one though that depicted
[48:43]
>> Yeah. Um I'm going to tell you what we
[48:45]
had what we had presented at the last
[48:46]
meeting was at the height of the taller
[48:49]
tower.
[48:50]
>> So this this is the 178 whatever point.
[48:52]
>> Yes. Uh, and I got to tell you, we will
[48:55]
produce that for the benefit of the town
[48:56]
of the PUC. I don't think it's going to
[48:58]
change that dramatically. By reducing
[49:01]
the height, what you're actually doing
[49:04]
um um one of the things you got to look
[49:07]
at this is um um we call them vertical
[49:11]
totem poles. Verizon will put its
[49:13]
antennas at the top of the tower and
[49:15]
then we'll have space and structural
[49:17]
integrity for other telecommunications
[49:19]
companies, T-Mobile, AT&T, and there's
[49:23]
always talk about others coming in the
[49:24]
market. So, we don't want to be
[49:25]
shortsighted and design towers that are
[49:27]
too short. By reducing the height of the
[49:30]
tower, you're um um reducing the height
[49:34]
of the bottom antennas as well as the
[49:36]
top antennas. So, we don't anticipate
[49:39]
that there's going to be much change
[49:40]
with Verizon, but I I can certainly
[49:42]
provide that to you, but uh
[49:44]
>> well, and and the just the concern is
[49:46]
related, and I don't mean to have
[49:47]
repetitive questions, but the concerns
[49:49]
would be for the residents of West
[49:50]
Rochester. Uh which if we can get any
[49:53]
map, would be on the the very left edge
[49:56]
of this photograph. Uh, so any reduction
[49:59]
in height would potentially eliminate
[50:01]
coverage for several hundred town
[50:02]
residents that live west of town, which
[50:05]
I realize is probably not the Verizon or
[50:08]
any other telecommunications provider's
[50:10]
main focus is obviously the Ruben
[50:12]
corridor, but there's tremendous
[50:13]
potential to provide uh communication to
[50:16]
several hundred town residents that live
[50:18]
out the 73 corridor. Thank you.
[50:19]
>> Where where were you last month?
[50:22]
>> I'm I'm being facitious. Uh um
[50:26]
>> is this you'll have updated coverage
[50:28]
maps?
[50:28]
>> Oh, absolutely. Yes.
[50:29]
>> And when when you submit your
[50:30]
application.
[50:31]
>> Absolutely. Yes.
[50:34]
>> Ask the question.
[50:37]
>> Thank you.
[50:38]
>> Lori, did you
[50:41]
>> raise my hand?
[50:41]
>> Oh, I thought you had it up the first
[50:43]
time.
[50:44]
>> Oh, Jerry, I'm sorry.
[50:55]
testing
[50:57]
>> Jon Rochester. Uh how wide will the uh
[51:01]
construction road be? And uh second
[51:04]
question is uh uh has your company ever
[51:07]
used helicopters to drop uh towers in to
[51:12]
reduce the impact on the landscape.
[51:14]
[Music]
[51:16]
>> Uh the first question, how road wide is
[51:18]
the access driveway? The existing
[51:20]
logging road is about 10 feet wide and
[51:22]
um I'm going to stop and I on the line
[51:25]
with us is Scott Adams who's a civil
[51:26]
engineer. If I say anything out of line
[51:28]
u make sure he can interrupt me. Um and
[51:31]
we might have to uh expand it a little
[51:33]
bit in places to uh facilitate bring up
[51:36]
utility access. But one of the reasons
[51:39]
why this particular site is immensely
[51:41]
attractive to us and the town of
[51:43]
Rochester is there's, you know, we're
[51:45]
about 2,2500
[51:47]
ft u meandering off of Route 100.
[51:52]
The vast majority of that already has an
[51:54]
existing logging road. So we don't need
[51:57]
to utilize helicopters because really
[52:00]
all we're doing is taking the existing
[52:02]
logging road and extending it about 500
[52:04]
ft to kind of the top of the hill to get
[52:06]
to a plateau where we can construct. So
[52:09]
from a um a disturbance perspective it's
[52:12]
dimminous. We have utilized helicopters,
[52:14]
but those tend to be on sites at the
[52:17]
very top of mountains which are far more
[52:21]
visible from a uh you know I think
[52:23]
there's one as you come up um 91 um just
[52:27]
past the uh Chester exit uh and uh um
[52:31]
there there's one that you see quite
[52:32]
prominently on the 91 corridor and
[52:34]
that's clear at the top of a mountain uh
[52:37]
and it far more visible but it was
[52:39]
designed for a different perspective to cover more along Route 100. I mean,
[52:44]
Route 91. Um, so we're trying to avoid
[52:47]
going on the tops of peaks to mitigate
[52:51]
the visual impact.
[52:52]
>> Scott Adams does want to add something.
[52:54]
>> Go ahead.
[52:56]
>> Oh, actually, no. I just wanted to make
[52:57]
sure I I was unmuted so I could answer
[52:59]
any questions should someone ask me one.
[53:00]
Okay. Okay. Thank you.
[53:01]
>> Thanks. Thank you, Scott.
[53:02]
>> So, the road won't be widened.
[53:04]
>> Yeah. No, it it in in at in a couple
[53:06]
spots it might be on a temporary basis
[53:08]
to facilitate um the construction of the
[53:10]
utility run, but we're also going to
[53:12]
deploy um originally we had talked about
[53:15]
putting um more permanent disturbance
[53:18]
down, meaning gravel and crushed stone.
[53:20]
Um but now we can utilize they're called
[53:23]
construction mats. Um really the access
[53:26]
driveway is only for construction. We
[53:29]
have to bring a tower up there. We have
[53:30]
to bring a crane up there. We have to
[53:32]
bring some concrete up there. Uh it's a
[53:34]
construction road after this. It's
[53:36]
unmanned. We don't plow it in the
[53:38]
winter. If someone needs to get up there
[53:40]
um um they can uh in the winter time
[53:44]
they bring a snowmo vehicle. Uh in the
[53:46]
summertime they if after we eliminate
[53:49]
the construction match if they they can
[53:51]
bring all-terrain vehicles. So it it's
[53:53]
designed to be not passable and and it
[53:57]
will um
[53:59]
you know but like I said the majority of
[54:01]
it is an existing logging drive. So
[54:03]
without with u dimminimous amounts of
[54:06]
improvement to just facilitate
[54:07]
construction.
[54:10]
>> Any hands in the Zoom thoughts?
[54:16]
» Something went wrong. Please try again.
[54:21]
» Thanks Francis. So you said in this uh
[54:24]
in this meeting which is different than
[54:26]
the last meeting that um you're just
[54:28]
extending the logging road but there are
[54:31]
concrete trucks crane the crane heavy
[54:33]
equipment has to get up there. So
[54:36]
wouldn't a logging road have to be quite
[54:38]
a bit changed to get the that equipment
[54:43]
uh thousand vertical feet up the
[54:44]
mountain?
[54:45]
>> Uh I'm going to do two things. I'm going
[54:48]
to jump to the plans that show kind of
[54:50]
an overview of the road and I'm going to
[54:52]
ask Scott to answer that question. Um,
[55:05]
let me know when you're ready, friend.
[55:10]
» Scott, I have C1 shown on the screen.
[55:16]
» Okay. Yep. that. So that shows pretty
[55:18]
much the extent of the existing uh on
[55:20]
top of an auto photo. C2 may be a little
[55:22]
more valuable. May show more detail. The photo is with the photo in the
[55:26]
background. It's kind of hard for the
[55:27]
public to probably see it,
[55:29]
>> but that shows the the ex Yep. C2. So
[55:32]
that shows the extent of the existing uh
[55:34]
topography and the existing logging
[55:36]
trails. There's a pretty substantial
[55:37]
logging trail that extends to
[55:40]
approximately within about 400 ft of the
[55:42]
proposed compound. So that last 400 ft
[55:45]
would require a little bit more
[55:46]
improvement and that's what the plans
[55:47]
indicate that that that section of it
[55:49]
will receive um 6 to 8 in of crushed
[55:52]
stone, not gravel. So it's going to
[55:54]
remain a permeable surface and
[55:56]
infiltrate um as well as the compound
[55:58]
will be a crushed stone surface as well,
[56:00]
which will allow for infiltration
[56:02]
through the voids of the stone and into
[56:04]
the ground where it's intercepted. But
[56:06]
the vast majority of of the the trail is
[56:08]
existing. Um I believe it's over 75% is
[56:12]
existing. Um, so there will be a lot of
[56:14]
limming and things like that that will
[56:15]
occur. The extent of tree removal is
[56:18]
primarily to get the overhead utilities
[56:20]
up to the site. It's really just
[56:22]
clearing the tree, not trying to not,
[56:24]
and there are notes on the plans to say
[56:25]
this, to not clear the stumpings. You
[56:28]
know, that's not our intention is to
[56:29]
clear the stumps for the for the
[56:30]
overhead operations. It's just to clear
[56:32]
the trees out of the way so that the
[56:34]
overhead wires can be installed uh to
[56:36]
service the site. The the path is quite
[56:40]
substantial. I know I sent photos to the
[56:42]
team. I don't believe I can share my
[56:43]
screen here now, but it's it's a pretty
[56:45]
substantial path majority of the way up
[56:47]
until the last, you know, few hundred
[56:49]
feet. Um, part of it is timing, right?
[56:52]
And that's why the, you know, timing of
[56:54]
the year when the work takes place. Um,
[56:56]
the extent of the amount of mats that'll
[56:57]
be required will vastly dispend depend
[57:00]
upon the amount of precipitation that
[57:01]
has been received in the months prior to
[57:03]
the to it getting constructed. So,
[57:04]
that's a little bit of a gray area that
[57:06]
the contractor is going to have to work
[57:07]
with. But um for instance, going through
[57:09]
the farmer's field, we really didn't
[57:11]
want to disturb his field and then have
[57:13]
to put it back and then once you try to
[57:15]
drive on it, the loom for the next year
[57:17]
is going to be soft and punky and you're
[57:18]
going to you you'll potentially make a
[57:20]
mess of his grass. So with the extent
[57:22]
there going through the field, we're
[57:23]
going to put down the mats. The
[57:24]
vehicular the construction vehicles will
[57:26]
drive over those mats to service the
[57:28]
site. And then once the site is built
[57:30]
and the site is we're going to kind of
[57:31]
think ahead and we're going to install
[57:34]
um more of the carrier equipment that
[57:36]
normally they would install up front on
[57:38]
the tower so that they don't need
[57:39]
cranes. Um self-support towers are
[57:42]
readily climbable and they'll be able to
[57:44]
use rigging and ropes to be able to
[57:46]
install their um remote radio heads and
[57:49]
their antennas. As part of the initial
[57:51]
tower installation, we're going to
[57:52]
propose to install their frames for
[57:54]
them. Um, so they'll already be
[57:56]
installed on the tower themselves and
[57:58]
make it easier for them and less con
[58:00]
less disruptive during construction of
[58:02]
their operations. That may could come a
[58:03]
year or two years later. Um,
[58:06]
so like I said, there'll be a lot of
[58:08]
limming and things like that to get it
[58:10]
through, but the path is quite
[58:11]
substantial now. It's 10 feet in some
[58:13]
areas it's 15t wide as it extends there
[58:15]
now. And and as the plans indicate, you
[58:18]
know, they it's basically an exempt
[58:20]
agricultural logging roads, you know,
[58:22]
that they could make minor improvements
[58:24]
to. It's going it's an existing logging
[58:26]
road now and agriculture road and it's
[58:28]
going to be that in the future. So those
[58:30]
uses are allowed um and it's going to be
[58:33]
continued to use for that purpose.
[58:39]
» Yeah, I have a question here. Question
[58:41]
on
[58:44]
» Regina Kil has a question.
[58:47]
>> Yes. Um hi, I own a house on Route 100.
[58:53]
I've owned it for the past 16 years.
[58:55]
It's at 791
[58:58]
Route 100 South. So, it's in in the
[59:01]
vicinity of this um project. And I'm I'm
[59:06]
obviously in Connecticut um where I
[59:09]
live. It's just a vacation house there.
[59:11]
So, I'm not able to attend in person and
[59:14]
I'm on Zoom. I have been unable to see
[59:18]
the screen as
[59:20]
uh the gentleman has been talking. the camera has been on his face and not
[59:26]
on the screen. So I have missed being
[59:28]
able to see anything um that he has
[59:31]
shown which I really would have liked to
[59:33]
have seen the screen and even now the
[59:36]
camera is a little further back but the
[59:38]
screen is so bright white that I as a
[59:42]
viewer we can't see what's on the
[59:44]
screen. So I that's just a comment and I
[59:47]
don't know if I could see the
[59:49]
presentation since you're recording it
[59:51]
if you'd be able to provide me with like
[59:54]
a way to see the recording. That's at a
[59:56]
later date.
[59:59]
>> Regina, I can actually I can actually
[1:00:02]
answer that. There we go. Um yes, we
[1:00:06]
will be a we will be able to provide you
[1:00:09]
with copies.
[1:00:13]
Hold it away. I did so much better with
[1:00:15]
that one. Okay. Um, yes, we are not able
[1:00:19]
to show you the
[1:00:23]
screen. Ah, we are not able to show you
[1:00:25]
the screen on Zoom. Um, we were not able
[1:00:27]
to get that set up for tonight. There is
[1:00:29]
a recording and we will be able to make
[1:00:31]
that available to you through Orca and
[1:00:34]
the documents that are presented tonight
[1:00:35]
will be available once uh, Vert.Ex makes
[1:00:39]
their submits their application to the
[1:00:40]
public utilities commission. All the
[1:00:42]
documents will be public. Um, so I will
[1:00:44]
um encourage you to um drop an email to
[1:00:47]
us at rochester planning
[1:00:49]
commissiongmail.com
[1:00:51]
and I can add you and anybody else to
[1:00:53]
the email list um to make sure you get
[1:00:55]
all the information.
[1:00:57]
>> Okay. I didn't get that email address.
[1:00:59]
I'd like to write that down. that how
[1:01:03]
what did and it you're
[1:01:05]
>> it's Rochester
[1:01:11]
planning commissiongmail.com.
[1:01:19]
» Okay. I would be very interested in
[1:01:22]
seeing it sounded like he was showing
[1:01:24]
photographs because I'm just from what
[1:01:28]
I've seen tonight I still don't know
[1:01:30]
exactly where this is planned for
[1:01:33]
because I've been unable to see any of
[1:01:35]
the photos as well.
[1:01:39]
>> Mary, if I could jump in.
[1:01:40]
>> You may.
[1:01:40]
>> I can email this presentation and the
[1:01:44]
photos and the plans. Um, recognizing
[1:01:47]
that it's all preliminary based on what
[1:01:49]
we've talked about tonight, but I can
[1:01:50]
email them to you tomorrow and then you
[1:01:52]
can put them on the website. I recognize
[1:01:55]
limitations, but I think she's asking
[1:01:57]
very legitimate questions.
[1:01:58]
>> Great.
[1:02:02]
» Thanks, Regina.
[1:02:03]
>> Thank you.
[1:02:05]
>> Alina, Harvey, Rochester.
[1:02:14]
Uh just couple questions. Uh in the
[1:02:17]
original plan submitted here, it shows
[1:02:20]
that the pad area, the enclosed area is
[1:02:24]
50 by 50, yet tonight in the
[1:02:27]
presentation it was 60 by 60. I'm
[1:02:30]
wondering why the change when the tower
[1:02:33]
is smaller. And I'm also wondering how
[1:02:38]
the construction
[1:02:41]
plans on dealing with the ledge in the
[1:02:44]
lock log road
[1:02:57]
» I think.
[1:02:58]
>> No. Um I um I believe that and Scott
[1:03:02]
interrupt me if I'm wrong. The compound
[1:03:04]
itself is 50 by 50. We fence in 50 by
[1:03:08]
50, but we sign a lease with the
[1:03:10]
landlord for 60 by 60 in order to have
[1:03:14]
areas outside the compound for utility
[1:03:17]
infrastructure or parking space and
[1:03:19]
things like that. So, the total limit of
[1:03:22]
clearing um was on that other sheet, but
[1:03:25]
it's a u it's about 3,000 square feet.
[1:03:31]
on a 244 acre parcel.
[1:03:35]
>> I understand. I'm intimately familiar
[1:03:38]
with
[1:03:40]
>> uh the question regards the
[1:03:44]
uh ledge on the access road.
[1:03:48]
>> How's that going to be dealt with?
[1:03:52]
>> We're not aware of any ledge now, but we
[1:03:54]
haven't done any geotechnical analysis.
[1:03:58]
What happens is after the PUC approves a
[1:04:02]
process, we do some preliminary
[1:04:04]
clearing, we um bring a geo tech rig up
[1:04:08]
to the top to determine what's exactly
[1:04:11]
at the base where the tower will be and
[1:04:13]
along the access road and uh um and
[1:04:17]
design a foundation very specific for
[1:04:19]
that. Um we're not anticipating ledge,
[1:04:22]
but
[1:04:24]
we're in Rochester, Vermont, so we have
[1:04:26]
no idea. and uh uh but um um you know
[1:04:29]
we've dealt with ledge previously in
[1:04:32]
many uh similar situations and they can
[1:04:35]
design a foundation very appropriate for
[1:04:37]
the ledge.
[1:04:38]
>> Okay. I'm not worried about the
[1:04:39]
foundation for the tower. I'm my concern
[1:04:42]
is on the log road. Uh how do you
[1:04:46]
normally deal with ledge in the roads?
[1:04:52]
» Scott, you want to try to answer that?
[1:04:53]
How do you deal with ledge on the
[1:04:54]
logging trail? So, as the way the trail
[1:04:58]
is now, we've literally driven up there
[1:04:59]
with our ATVs in our company survey
[1:05:02]
vehicle. So, we can drive up the trail
[1:05:04]
in its current state with with a
[1:05:06]
four-wheel drive vehicle as it stands.
[1:05:08]
It's not suitable for a passenger
[1:05:09]
vehicle, but it's suitable for
[1:05:11]
construction vehicles that would be
[1:05:13]
necessary for construction of the site.
[1:05:15]
They can access it the way it is right
[1:05:16]
now. There's no large outcrops of ledge
[1:05:19]
within
[1:05:21]
the logging road that would be an
[1:05:23]
impediment for the construction of this
[1:05:24]
site.
[1:05:26]
and you plan on taking concrete trucks
[1:05:29]
up this logging trail.
[1:05:31]
>> There's there's a lot of unique things.
[1:05:32]
I mean, sometimes they do small batches,
[1:05:34]
meaning they won't fill the the concrete
[1:05:36]
truck full. They'll do you they'll do it
[1:05:38]
in five yards. Um they've they've had
[1:05:41]
them in the past where they would
[1:05:42]
literally give it a tug with a
[1:05:43]
bulldozer. Like they the contractors are
[1:05:46]
very familiar with construction of rural
[1:05:47]
sites such as this. Um, I've been
[1:05:50]
involved with sites in the top of Mount
[1:05:51]
Washington, Sunday River, u, Bolton
[1:05:54]
Valley, Ski Resort. Um, we've done some
[1:05:57]
very difficult construction sites. It
[1:05:59]
gets done in a matter of a couple of
[1:06:01]
months and then it's built and the the natural topography will reveate
[1:06:07]
and go back to the way mother nature
[1:06:10]
intended, you know, once it's
[1:06:11]
constructed.
[1:06:14]
>> Okay. Thank you.
[1:06:15]
>> Yeah, these sites are unmanned. There's
[1:06:17]
no water sewer. There's no man
[1:06:19]
facilities. Um um they're all remotely
[1:06:22]
monitored um for security and and
[1:06:25]
electronic purposes. The the antennas
[1:06:28]
are actually getting smarter so that if
[1:06:30]
they ever had to tweak them, they have the ability to tweak them
[1:06:34]
remotely so that because of situations
[1:06:37]
like this uh u you know we've as Scott
[1:06:40]
mentioned built many equally if not way
[1:06:43]
more challenging terrain type
[1:06:45]
situations. The gentleman mentioned
[1:06:47]
helicopters. We've deployed them before.
[1:06:49]
We don't need to here, but we've
[1:06:51]
utilized that. And there are a lot of
[1:06:52]
sites built in in Vermont and New
[1:06:54]
Hampshire that are only helicopter
[1:06:57]
accessible. Uh and and no one goes there
[1:07:00]
because they work and they uh and if
[1:07:02]
they have to, they bring uh all train
[1:07:05]
type vehicles to get there.
[1:07:08]
>> Anybody on Zoom?
[1:07:10]
>> Not at the moment. Oh, what? Yes. Uh
[1:07:12]
yes, I do. Well, um Evelyn
[1:07:16]
You have to Evelyn, you need to unmute.
[1:07:22]
Evelyn, you're muted.
[1:07:36]
» We're still You're still muted.
[1:07:43]
for me. The system wasn't allowing me to
[1:07:45]
unmute. It had to be come from the host.
[1:07:48]
>> Yeah. Well, I'm ask Okay. Ask to unmute.
[1:07:51]
All right. I did. I asked to unmute. Uh
[1:07:54]
huh. Whoa.
[1:07:58]
» Okay. Is that right?
[1:08:00]
>> Yes.
[1:08:01]
>> Okay. Great. So, obviously the logging
[1:08:03]
roll that we're talking about is our
[1:08:05]
snowmobile trail
[1:08:07]
>> for a portion of it. For a portion of
[1:08:09]
it.
[1:08:09]
>> Yeah. Um, and so f how far away is the
[1:08:13]
site from the snowmobile trail?
[1:08:15]
>> It's quite far. It's from the from the
[1:08:17]
vast snowmobile trail that's on the vast
[1:08:19]
maps,
[1:08:20]
>> right?
[1:08:21]
>> Yes. It's it's probably 3,000
[1:08:24]
additional feet away from there.
[1:08:26]
>> Really?
[1:08:27]
>> Yeah. It's quite far.
[1:08:29]
>> What is the altitude of the site that
[1:08:31]
you've chosen?
[1:08:32]
>> The site is uh the altitude is 1,585T.
[1:08:37]
1,585.
[1:08:41]
Okay. All right.
[1:08:45]
Okay. I see it. Okay. I was just
[1:08:47]
wondering where it was on the map.
[1:08:50]
>> Absolutely.
[1:08:50]
>> All right. Thank you very much.
[1:08:55]
» Question back there.
[1:08:59]
>> Bruce Danick, North Holler Road. Um I'm
[1:09:03]
I apologize if this was answered
[1:09:05]
previously. Why is it that these uh
[1:09:09]
antennas are not going on one of the two
[1:09:12]
existing towers just south or north of
[1:09:14]
Rochester? And also there's antennas in
[1:09:17]
the church steeple here. Those all seem
[1:09:20]
like great existing infrastructure to
[1:09:22]
put more antennas on.
[1:09:25]
Thank you.
[1:09:28]
Uh the first question, um Verizon will
[1:09:31]
be putting Verizon has just recently put
[1:09:33]
antennas on the new tower in Stockbridge
[1:09:35]
and that's really designed to cover um
[1:09:39]
the the area from the Pittsfield
[1:09:41]
Stockbridge line to the Stockbridge uh
[1:09:44]
Rochester line. Uh and as you can
[1:09:46]
imagine, the the terrain here is so
[1:09:49]
dramatic that if you go a quarter mile
[1:09:52]
up the road, you're curving around a
[1:09:54]
bend. Uh and uh that tower in the in
[1:09:58]
Stockbridge is um there's something like
[1:10:00]
the Wild Fern Cafe or something like
[1:10:02]
that. It's behind there closer to
[1:10:04]
Pittsfield into Rochester, but Verizon's
[1:10:07]
going on that. Uh in addition, there's a
[1:10:10]
tower that was just built um Buts Hill
[1:10:14]
Road in Granville that Verizon is also
[1:10:18]
on. And there's another tower being
[1:10:21]
proposed on North Hollow Road in the
[1:10:23]
north end of Granville going up towards
[1:10:25]
Warren U that Verizon will be going on
[1:10:27]
as well. These aren't designed to cover
[1:10:30]
huge swats of area and in addition the
[1:10:33]
topography limits the the the ability as
[1:10:36]
well as uh regul FCC regulations with
[1:10:40]
respect to the power output. So you
[1:10:43]
can't just turn up the antennas at one
[1:10:45]
space to get more coverage. You're
[1:10:47]
limited by the power output. With
[1:10:49]
respect to the church steeple, AT&T
[1:10:51]
already has antennas in there. Verizon
[1:10:54]
looked at it too, but as you can
[1:10:55]
imagine, church steeples a 100 years ago
[1:10:57]
weren't designed with telecommunications
[1:11:00]
antennas in mind. Um, they uh they
[1:11:04]
generate a little bit of heat as all
[1:11:05]
electrical uh apparatus do. Um, where
[1:11:09]
the church steeple, it's unventilated
[1:11:12]
area where you put it on an antenna, a
[1:11:14]
tower 140 feet in the air, you don't
[1:11:16]
require ventilation because there's
[1:11:17]
plenty of natural ventilation. So,
[1:11:19]
there's just no room in the um um the
[1:11:24]
church people for more antennas. In
[1:11:27]
addition, there's not even enough room
[1:11:28]
for AT&T because what's happened over
[1:11:32]
time is uh we call them the antennas
[1:11:35]
have gotten smarter. there's more
[1:11:37]
electronics
[1:11:38]
um baked into the antennas and less
[1:11:41]
electronics at the base of the tower or
[1:11:44]
I'm not sure where they are at the
[1:11:45]
church table, maybe the basement of the
[1:11:47]
church. Uh and so th those antennas just
[1:11:51]
require more space and a confined area
[1:11:54]
like a churchle wasn't designed 100
[1:11:57]
years ago and it's not getting better
[1:11:58]
because of this the antennas. So, and so
[1:12:01]
that's why um we need a tower to and and
[1:12:05]
one of the benefits of a tower is that
[1:12:07]
it's uh um it's adaptable. Um you know,
[1:12:11]
you hear about 3G, 4G, 5G, 6G, all the
[1:12:14]
different generations of technologies
[1:12:17]
that the type of tower and the structure
[1:12:20]
is adaptable to future technologies. Uh
[1:12:22]
so that in the event something happens
[1:12:25]
in the future, it's a lot easier
[1:12:26]
retrofitted. a ch a church people didn't
[1:12:29]
have room the first time no longer has
[1:12:31]
room now. So
[1:12:34]
>> anybody on
[1:12:41]
» uh one of the questions I have more for
[1:12:42]
the community is thinking about is this
[1:12:46]
technology actually outdated now? Should
[1:12:50]
we be holding off? We do have plenty of
[1:12:51]
cell service around because of Starlink,
[1:12:55]
other technologies,
[1:12:57]
uh, and before we'll create another
[1:13:00]
piece of equipment that may be outdated
[1:13:03]
before you even know it. So, it's
[1:13:05]
something that we should be looking at.
[1:13:08]
Uh, maybe this is uh, too quick to move
[1:13:11]
on this.
[1:13:18]
Uh, Kevin Guyger has something to say
[1:13:20]
about that. Hannah,
[1:13:28]
» hi Sandy, can you hear me?
[1:13:31]
>> We can.
[1:13:32]
>> Yeah. My my comment wasn't regarding
[1:13:34]
whether this technology is outdated or
[1:13:36]
not. I had other other comments.
[1:13:39]
So, I don't know if now's the time you
[1:13:41]
want any of that, but
[1:13:44]
>> we'll go. You have the floor.
[1:13:46]
>> Okay. Um and my understanding was this meeting wasn't to talk about merits
[1:13:51]
of the projects or demerits of the
[1:13:53]
projects. So I I won't get into that. I will just say issues that I have heard
[1:13:58]
and that we will raise in the future. Um
[1:14:01]
which is this this project will involve
[1:14:03]
significant tree cutting in our in our
[1:14:06]
opinion to put up poles and lines. Um
[1:14:08]
and that's going to be an issue. Uh
[1:14:10]
gravel roads are impervious surfaces for
[1:14:13]
Vermont storm water purposes. So despite
[1:14:15]
the gravel, they they don't really
[1:14:17]
behave that differently. Um and and we
[1:14:20]
will have some other concerns as well
[1:14:22]
about getting equipment up there, but I wanted to raise those.
[1:14:28]
So my understanding from speaking with
[1:14:29]
the the owner that's going to be
[1:14:31]
building the site is that uh the poles
[1:14:33]
will be private. Um he's intending for
[1:14:36]
the private poles. Yes, they'll need
[1:14:37]
electric service on it, but they're
[1:14:38]
intended to be privately maintained
[1:14:39]
poles. There will be no gravel used on
[1:14:42]
this site to be clear. um any access
[1:14:44]
road or or the compound itself is going
[1:14:46]
to be pvious crushed stone. It's kind of
[1:14:49]
a more innovative low impact uh proposal
[1:14:53]
that will allow infiltration and it
[1:14:55]
allow storage of any runoff from the
[1:14:57]
cabinets within the crush stone, the
[1:14:58]
voids of the crush stone to allow it to
[1:15:01]
uh basically it's about a 40% void ratio
[1:15:03]
and that water will be able to
[1:15:05]
infiltrate into the soil as it as it did
[1:15:07]
prior. There should actually be less
[1:15:09]
runoff from from this system than
[1:15:11]
pre-existing conditions. So there will
[1:15:13]
not be any gravel utilized even on the
[1:15:15]
access road. It'll be physically crushed
[1:15:17]
stone.
[1:15:22]
Um, I want to remind folks, uh, if you
[1:15:25]
please, uh, let us know your name when
[1:15:27]
you when you have a a question. And that
[1:15:30]
was, um, Kevin Guyer, you heard from the
[1:15:32]
regional planning commission just prior
[1:15:36]
talking about those those issues.
[1:15:44]
» Go ahead, Ben.
[1:15:46]
>> Thanks. Yeah, my question is actually
[1:15:48]
related to that the because the regional
[1:15:51]
plan um designates this as a highest
[1:15:55]
priority forest connectivity block this
[1:15:57]
area. It's also a deer wintering yard.
[1:16:00]
Um
[1:16:02]
my first question is what what have you
[1:16:05]
uh researched on that front and why is
[1:16:08]
this um acceptable in in those two
[1:16:12]
specifically called out designations?
[1:16:16]
Um,
[1:16:17]
two things. One, in addition to local
[1:16:21]
and state regulations, these facilities
[1:16:24]
are also heavily federally regulated as
[1:16:27]
well. The federal government um um
[1:16:31]
requires us to go through a very
[1:16:32]
extensive environmental analysis. It's
[1:16:35]
under the National Environmental Policy
[1:16:37]
Act, NEPA we call it, in our our world.
[1:16:39]
and it requires us to make sure that we
[1:16:41]
have no impact on um plant and wildlife
[1:16:45]
species. So, as part of this process, we do that. We contact the state and um
[1:16:51]
state databases and things like that. Um
[1:16:55]
we
[1:16:57]
don't have any
[1:16:58]
>> the mapping already shows these are
[1:17:00]
these have special resources on that
[1:17:02]
front. I understand that, but we're just required to make sure we
[1:17:06]
don't have an ad an undue adverse
[1:17:08]
impact. We're building a 60 by60
[1:17:12]
clearing, 3,000 ft clearing in the
[1:17:15]
middle of a 244 acre parcel. So, I
[1:17:19]
suspect that habitat is a vast majority.
[1:17:23]
So, we don't have a significant or an
[1:17:25]
undue adverse impact on that. um they're
[1:17:28]
really quite dimminimous when you look
[1:17:30]
at the volume of activity in the the
[1:17:33]
entire area. So, uh, but again, we need
[1:17:36]
to satisfy.
[1:17:36]
>> You're saying you don't have an adverse
[1:17:38]
impact. That study's been done. You How
[1:17:41]
do you How do you know that? I guess
[1:17:42]
you're saying you're you're saying
[1:17:43]
that's already a conclusion.
[1:17:45]
>> We just need to make sure that um we
[1:17:49]
satis what we look for is endangered
[1:17:52]
species and endangered plant species and
[1:17:54]
wildlife species and we need to make
[1:17:56]
sure we don't have an an an adverse
[1:17:58]
impact on that and we don't. So the fact
[1:18:01]
that there's deer in the area, there's
[1:18:03]
deer all over Rochester. So uh and we're
[1:18:06]
not completely
[1:18:07]
>> So on the on the endangered species
[1:18:09]
piece, which is one piece, what studies
[1:18:11]
have have been done to to allow you to
[1:18:13]
say that that you know you don't have an
[1:18:15]
adverse impact on endangered species
[1:18:18]
since you brought them up.
[1:18:21]
We don't have to do specific studies
[1:18:23]
because we look at it and the volume of
[1:18:27]
land that we're disturbing
[1:18:29]
to the size of the parcel to the area
[1:18:31]
within the habitat. Uh and again all
[1:18:34]
we're required to look at is whether or
[1:18:37]
not there's any endangered species and
[1:18:39]
endangered plant and wildlife species.
[1:18:47]
Anyone
[1:18:50]
on Zoom
[1:18:51]
>> on that front? I have another question,
[1:18:53]
but you said you said the best place to
[1:18:54]
put a tower would be close to where the
[1:18:56]
users are. I totally agree with you
[1:18:58]
rather than up on a mountain surrounded
[1:19:00]
by deer and bear and other animals that
[1:19:03]
aren't checking Facebook. Uh surrounded
[1:19:05]
by wilderness basically. What other
[1:19:08]
areas did you guys look carefully at at
[1:19:11]
putting a transmitter? What other sites?
[1:19:14]
Um,
[1:19:15]
I don't have specific locations, but
[1:19:18]
what we look at is topography and
[1:19:20]
terrain. Um, um, you know, uh, we we
[1:19:24]
look at a whole host of things. Uh,
[1:19:27]
somebody commented that we're taking
[1:19:29]
down trees. Well, I could put it in the
[1:19:31]
ball field behind the elementary school,
[1:19:33]
but I don't think that would be popular.
[1:19:35]
And I'm being facitious because we've
[1:19:36]
been doing this for a long time. Uh we look at things very um globally in
[1:19:42]
the sense that um we want to be close to
[1:19:45]
downtown Rochester, but my suspicion is that if we put it any closer to
[1:19:49]
downtown Rochester, we'd have more
[1:19:51]
public opposition. We want to be close
[1:19:52]
to the users, but at the same time not
[1:19:55]
have an undue adverse impact on the
[1:19:57]
residential uses in the area, on the
[1:19:59]
scenic highway. Uh and so we we looked
[1:20:02]
at a lot of different areas and I will
[1:20:04]
provide that information to the the
[1:20:07]
commission but uh at the same time uh
[1:20:10]
you know I think we found a site that
[1:20:12]
satisfies the PUC's requirement
[1:20:14]
satisfies the town zoning requirements
[1:20:17]
um and no one said during this process
[1:20:21]
and you're welcome to why don't you go
[1:20:23]
here because we'll look at that but uh
[1:20:25]
um we I think we have found a site that
[1:20:28]
complies with your zoning bylaw. for uh
[1:20:32]
for good effect and complies with PUC
[1:20:35]
regulations and satisfies the
[1:20:37]
telecommunications and coverage
[1:20:38]
objectives which is really
[1:20:40]
>> but it conflicts with the town plan in
[1:20:42]
like 20 different bullet points and the
[1:20:43]
town plan calls out the north hollow the
[1:20:46]
scenic route 100 corridor Bethl Mountain
[1:20:49]
the village and other view sheds which
[1:20:52]
this will be highly visible from like
[1:20:54]
your the balloon test was all from the
[1:20:56]
valley floor none of it was from the
[1:20:58]
north hollow the north hollow In most of
[1:21:00]
the North Hollow, you'll see at a level
[1:21:02]
at a similar level, like you made that
[1:21:04]
good point, when you're looking up, you
[1:21:06]
won't see the whole tower um above the
[1:21:08]
canopy, but in the North Hollow, you you
[1:21:10]
will see most of the tower that's above
[1:21:11]
the canopy. Um but none of your none of
[1:21:14]
your visual simulations that you call
[1:21:16]
them were from anywhere else but the
[1:21:18]
valley floor.
[1:21:19]
>> And and I'm going to agree with you on
[1:21:21]
that. We didn't consider that, which is
[1:21:23]
why when the planning commission asked
[1:21:25]
us to do another visibility
[1:21:26]
demonstration, we agreed to do that. So,
[1:21:29]
we'll advertise it. I'm sure before the
[1:21:31]
night's out, we'll agree on a date and
[1:21:33]
uh um u the planning commission will get
[1:21:35]
the word out and uh we'll put an
[1:21:37]
advertisement in the newspaper if
[1:21:38]
necessary and uh um and people will be
[1:21:41]
able to assess it from their own
[1:21:43]
particular vantage points.
[1:21:45]
>> Mhm. That'll be a balloon test.
[1:21:47]
>> Yes.
[1:21:47]
>> And what's the balloon? 4 foot balloon.
[1:21:50]
Is that right? How big?
[1:21:51]
>> Yeah, exactly.
[1:21:52]
>> Yeah. You were saying the the balloon is
[1:21:54]
representative um of the tower, but the
[1:21:58]
tower is about 800 square f feet and the
[1:22:00]
balloon a 4ft circle is about 12 1/2 ft.
[1:22:03]
So you would need like 66 balloons to be
[1:22:07]
the same size as a tower.
[1:22:08]
>> No, what we can do what the balloon
[1:22:10]
indicates is whether or not you can see
[1:22:12]
it from a particular location. And then
[1:22:14]
if there's visibility like we showed at
[1:22:16]
the the previous visibility
[1:22:18]
demonstration, we can engage engineers
[1:22:20]
to scale it off and do a photo
[1:22:23]
simulation of what it will look like
[1:22:25]
from that vantage point.
[1:22:26]
>> Okay. You just you had said this is what
[1:22:28]
the tower is going to look like the
[1:22:30]
balloon.
[1:22:30]
>> No, no, no.
[1:22:32]
>> So the balloon is
[1:22:34]
>> Sorry. So yeah, just to reiterate on the
[1:22:35]
balloon test. So the balloon Yes, it
[1:22:37]
absolutely is 4 ft in diameter. the
[1:22:39]
standard uh sector frame that that the
[1:22:41]
carriers mount their equipment on is
[1:22:42]
about um 12 feet in width. So basically
[1:22:45]
the balloon is about a third the width
[1:22:47]
of the tower. So between that and then
[1:22:49]
we also use markers on the the string or
[1:22:52]
the cable at 10 foot in increments so we
[1:22:54]
can actually see the direction confirm
[1:22:56]
the direction. We usually have two
[1:22:57]
people on site, one person at the
[1:22:58]
balloon at all times, one person driving
[1:23:00]
around taking photos to try to make sure
[1:23:02]
that the balloon is as straight as
[1:23:03]
possible, as accurate as possible when
[1:23:05]
we take those photos. And then we
[1:23:06]
utilize 3D
[1:23:09]
drafting software um as long as as well
[1:23:12]
as Photoshop to basically superimpose in
[1:23:14]
a realistic view of the tower. And when
[1:23:16]
you compare the size of the balloon with
[1:23:18]
the safe face of the tower, I'm
[1:23:19]
confident you'll see that the scale is
[1:23:22]
representational of of what you would
[1:23:24]
expect it to be.
[1:23:28]
» I'm gonna get let someone else have a
[1:23:29]
opportunity.
[1:23:30]
>> Dan, um Kevin has had Kevin Guyger has
[1:23:33]
his hand up again. All right, go to
[1:23:35]
Kevin and then Alvina and then back
[1:23:38]
there.
[1:23:44]
» Sorry, I think that just has stayed up
[1:23:46]
somehow.
[1:23:48]
>> Okay. Okay.
[1:23:49]
>> Oh, okay.
[1:23:56]
» Rochester.
[1:23:58]
All right.
[1:23:59]
I understand
[1:24:01]
the logic and lowering the counter is
[1:24:06]
also
[1:24:08]
a little disturbing that you're going to
[1:24:11]
lower and thereby restrict
[1:24:15]
the signal
[1:24:17]
that is going to be available to West
[1:24:19]
Rochester and north and south
[1:24:23]
of town.
[1:24:25]
And in this day and age, it was seeing
[1:24:28]
that
[1:24:29]
tower should be back at its original
[1:24:32]
height. So that the areas west of town
[1:24:38]
73 will also be able to serve it as well
[1:24:43]
as a greater areas north and south 100.
[1:24:47]
I understand everyone's concern about
[1:24:50]
the tower being visible, but uh I think
[1:25:06]
Um, let's remember to keep this to our
[1:25:08]
questions and we'll come back around to
[1:25:10]
your your comments about what you think
[1:25:12]
about the project.
[1:25:16]
» Go ahead and zoom land.
[1:25:18]
>> Uh, yes. I had a question for you and
[1:25:21]
that is who is incentivizing you and
[1:25:24]
your company to build the tower? Um, is
[1:25:28]
it the state of Vermont? Is it the
[1:25:30]
federal government? like where's the pot
[1:25:32]
of money coming from for your company to
[1:25:36]
come in and build the tower? And also uh
[1:25:38]
the second question is you mentioned
[1:25:40]
that you colllocate if you could and
[1:25:43]
somehow I'm guessing that that's not
[1:25:45]
exactly the case because then you would
[1:25:47]
not be building a tower, you would not
[1:25:48]
be having a job from this project. So I
[1:25:52]
think Verizon should actually speak to
[1:25:54]
that, not you specifically.
[1:26:01]
Um I I explained in the beginning Vertex
[1:26:04]
is a wireless infrastructure developer.
[1:26:07]
We are essentially real estate
[1:26:08]
developers. We partner up with
[1:26:11]
telecommunications companies. We use our
[1:26:13]
own capital. Um uh we bring
[1:26:17]
telecommunications to rural areas
[1:26:20]
because getting Verizon or anyone else
[1:26:23]
to build their own tower and and what
[1:26:26]
happened in the old days is that Verizon
[1:26:28]
would build its towers and then when
[1:26:30]
people wanted to share like Verizon or
[1:26:32]
AT&T or T-Mobile, they wouldn't play
[1:26:34]
well together because they were
[1:26:36]
competing in a telecommunications arena.
[1:26:38]
So wireless infrastructure developers
[1:26:40]
like Vertex came out to um you know do
[1:26:45]
all the due diligence. We've done an
[1:26:47]
immense amount of work just to be
[1:26:48]
standing here tonight. We still have a
[1:26:50]
lot of work to do to get through the PUC
[1:26:52]
process and then we have to do the
[1:26:54]
construction work. All of which costs
[1:26:56]
money, but it uh enables companies like
[1:26:59]
Verizon to focus on Rochester and
[1:27:02]
Stockbridge and Granville and the rest
[1:27:05]
of Vermont. It's a it's a we utilize our
[1:27:08]
capital. The the state also by um using
[1:27:12]
the PUC process as opposed to local
[1:27:16]
zoning um is encouraging the development
[1:27:19]
of this to have a uniform process as uh
[1:27:22]
which is uh Connecticut does the same
[1:27:24]
thing but Massachusetts and Vermont and
[1:27:27]
Maine we have to comply with 300
[1:27:29]
different zoning bylaws all of which are disperate. So the state of Vermont
[1:27:34]
is actually encouraging this because
[1:27:36]
they recognize the public good in better
[1:27:38]
telecommunications.
[1:27:40]
So uh but the the the you know this is
[1:27:43]
not government subsidized. This is uh
[1:27:46]
privately subsidized by uh Vert.Ex and
[1:27:49]
Verizon.
[1:27:59]
Hi, Janna Marie here and I just
[1:28:01]
wanted to ask you sir to go on record
[1:28:04]
because some people are concerned about
[1:28:05]
visibility that could you tell everybody
[1:28:08]
here would you agree that it's not going
[1:28:10]
to be an accurate representation the
[1:28:12]
balloon test will not be accurate
[1:28:14]
because it's much smaller than the
[1:28:16]
actual tower would be. So the visibility
[1:28:18]
I understand you're doing a test so that
[1:28:20]
people can look but it's not really
[1:28:21]
going to accurately represent what it
[1:28:23]
would look like. Is that correct?
[1:28:26]
No, but what I can then do if there's a
[1:28:29]
place that you can see the balloon, I
[1:28:31]
can then take a um we do a photo
[1:28:34]
simulation with engineers to scale it
[1:28:37]
out. And that's what we had done
[1:28:38]
previously. And uh and the engineers
[1:28:40]
have done it many many times and uh
[1:28:43]
certify us to the accuracy of it. So um
[1:28:46]
you know I if you'd rather I'll build a
[1:28:47]
tower and then that'll show what it'll
[1:28:49]
look like. But I can't do I can't. Yeah,
[1:28:51]
I agree. I again I'm sorry for being
[1:28:53]
facicious but uh uh but you know that
[1:28:57]
you know we this is the best that we can
[1:28:58]
do and it's worked very successfully in
[1:29:01]
many many other cities and towns
[1:29:02]
throughout uh New England.
[1:29:04]
>> I understand but you were just showing
[1:29:05]
us a lot of photos of a balloon and it's
[1:29:07]
not an accurate representation. Correct.
[1:29:09]
>> No, the photo simulation is an accurate
[1:29:12]
representation. I uh many times we go
[1:29:15]
back and take photos of the actual tower
[1:29:18]
after we build it to show that the
[1:29:21]
simulation that we produced a year
[1:29:23]
before is accurate.
[1:29:25]
>> No, but we're here now and we're asking
[1:29:28]
questions and one of the concerns has to
[1:29:30]
do with visibility and what it would
[1:29:33]
look like and a balloon test is not
[1:29:35]
accurate to what it would look like as a
[1:29:37]
fully built tower. Correct. I
[1:29:39]
>> I respectfully disagree with you, ma'am.
[1:29:43]
So Francis, can I ask you a question
[1:29:45]
just so that I'm understanding?
[1:29:47]
>> You are going to do another balloon test
[1:29:49]
at a date to be determined, preferably
[1:29:51]
tonight.
[1:29:52]
>> If uh the balloon is visible from a
[1:29:54]
specific location, your engineers will
[1:29:57]
take that location and turn it into
[1:30:01]
a 2D representation of what a tower
[1:30:04]
would look like there using modeling
[1:30:06]
software.
[1:30:07]
>> That's correct.
[1:30:07]
>> And then you would provide us with those
[1:30:09]
images.
[1:30:10]
>> That's correct. Okay.
[1:30:14]
» Thanks for that clarification.
[1:30:18]
» Scott has something to add here.
[1:30:21]
>> Just just for kind of a point of
[1:30:23]
clarification. So once we set the date,
[1:30:25]
myself and one of my staff will visit
[1:30:26]
the site. We will drive up to the top of
[1:30:29]
the site where where we have staked out
[1:30:30]
the proposed tower location. We
[1:30:32]
pre-measure in the in the field ahead of
[1:30:34]
time the length of u it's basically kite
[1:30:37]
flying string that's capable of holding
[1:30:39]
250 pounds. We blow up via a helium
[1:30:43]
balloon over 4t in diameter. Usually
[1:30:45]
four feet is the minimum. It's usually
[1:30:46]
even larger than that. And we we measure
[1:30:48]
the circumference, you know, when we're
[1:30:50]
on site. And then we raise that balloon
[1:30:52]
so that the bottom of the balloon is
[1:30:54]
equal to the height of the tower. And
[1:30:56]
the reason we do that is so that I can
[1:30:58]
attest that if I if I can
[1:31:01]
cannot see the balloon, that means the
[1:31:03]
top of the balloon is four to five feet
[1:31:05]
higher than the tower. So if I can't see
[1:31:07]
the balloon, then you will not be able
[1:31:08]
to see the tower. And if I can only see
[1:31:10]
a sliver of the balloon, you still will
[1:31:12]
not be able to see the tower. So the the
[1:31:15]
tower, the top of the tower was equal to
[1:31:17]
the bottom of the balloon. And that is
[1:31:19]
absolutely accurate. And we field
[1:31:21]
measure it with electronic distance
[1:31:22]
measuring devices while on site standing
[1:31:25]
below the tower in addition to literally
[1:31:27]
using a tape measure at the at the site
[1:31:29]
prior to driving up to the top.
[1:31:35]
» Thanks Jake.
[1:31:37]
>> Hey Jake Wildwood from Rochester, your
[1:31:39]
2,000 ft neighbor to the tower. Uh how
[1:31:43]
long is the lease
[1:31:45]
um on the property and what happens at
[1:31:49]
the end of the lease? Do you take it
[1:31:51]
down, do you leave it up, etc.?
[1:31:55]
>> Um, I don't usually get involved in
[1:31:57]
that, so I can only speak generically,
[1:31:58]
but generally they're about 50-year
[1:32:00]
leases. And uh um we've never had to
[1:32:03]
take one down yet, but um if uh as part
[1:32:08]
of the PUC process, if the town asks, we
[1:32:12]
will agree to post a bond so that uh and
[1:32:15]
then I can get Scott to estimate the
[1:32:17]
cost of removing it and bring it down
[1:32:20]
and we can post a bond for that amount.
[1:32:22]
And it's a common ask and uh I'm not
[1:32:24]
supposed to offer it, but my suspicion
[1:32:26]
is someone in the process will. and uh
[1:32:29]
um and and so it's we're not
[1:32:31]
anticipating that this is going to
[1:32:33]
become obsolete. However, it's a
[1:32:36]
legitimate concern and uh I'm not going
[1:32:38]
to be here at the end of that 50 years,
[1:32:39]
but uh there's a mechanism that we've
[1:32:42]
used previously to make sure that if I
[1:32:44]
disappear and Vertex disappears and
[1:32:46]
Verizon disappears that there's a
[1:32:48]
mechanism to take it down.
[1:32:56]
I have a couple of questions if you
[1:32:58]
don't mind.
[1:32:59]
>> Identify yourself.
[1:33:00]
>> Oh, sorry. Lori Church.
[1:33:02]
Uh,
[1:33:04]
one question on back to the balloon
[1:33:06]
test. If you said I mean I'm I'm little
[1:33:09]
girl. I'm math. So, if you say that the
[1:33:11]
balloon is four feet in diameter and the
[1:33:14]
top of the tower is 12 feet, why would
[1:33:16]
you not put up three balloons so that we
[1:33:18]
can know that we could see it? Because
[1:33:20]
to several neighbors points, we're
[1:33:22]
concerned about the visibility of it.
[1:33:24]
>> Uh um yeah, well, let me explain that.
[1:33:28]
Um the balloon is just a visual
[1:33:30]
representation and we have limits. If I
[1:33:33]
put a 12-oot balloon, then it there's
[1:33:35]
more surface area for the wind. One of
[1:33:38]
the things that's going to happen is
[1:33:39]
we're going to agree on a date and I'm
[1:33:40]
going to throw out November
[1:33:43]
12th and but if you can tell me that
[1:33:47]
it's going to be calm on November 12th,
[1:33:49]
thank you. But I can't predict that. So
[1:33:51]
what I'm going to do is advertise it and
[1:33:53]
say we're going to put up on November
[1:33:54]
12th, but check a website the day before
[1:33:57]
and we'll make the determined for that
[1:33:59]
the winds are cooperative or not
[1:34:00]
cooperative. And we've done this so many
[1:34:03]
times that um you know and we've tried
[1:34:06]
bigger balloons and we've tried um other
[1:34:09]
technologies and the more surface area
[1:34:13]
the less accurate it will be because
[1:34:15]
then that the balloon will blow over. So
[1:34:17]
this is but like I said what Scott can
[1:34:20]
do is if he sees the balloon he can then
[1:34:24]
do a scaled model to show what it will
[1:34:27]
look like. So I don't think it's not
[1:34:29]
representative because I can produce a
[1:34:32]
model u um that that shows you're not if
[1:34:36]
you can't see it seven miles away
[1:34:37]
whether it's this big you're not going
[1:34:38]
to see it whether it's this big it
[1:34:40]
doesn't change that
[1:34:41]
>> that logic doesn't work
[1:34:43]
>> um well I I'm telling you we've done
[1:34:45]
this many many times successfully u so
[1:34:48]
uh and uh and the issue that we have is
[1:34:51]
predicting the weather um in advance but
[1:34:54]
we've come up with a mechanism to
[1:34:56]
advertise that um once we get the
[1:34:58]
balloon up and and you know we have to
[1:35:00]
pick a day where the wind speeds are 5
[1:35:04]
to 10 miles an hour and not more because
[1:35:07]
if they're more than 10 then the balloon
[1:35:08]
blows around and then folks complain
[1:35:11]
that it's not accurate because the
[1:35:13]
string is like this as opposed to like
[1:35:14]
this. So um we've uh we try very hard to
[1:35:18]
make it as representative as possible.
[1:35:20]
Uh and our our choice is to build the
[1:35:23]
tower and take pictures of it but I
[1:35:25]
don't think the town wants us to do
[1:35:26]
that. So this is the limitation that we
[1:35:28]
have with the technology that we have.
[1:35:31]
>> Okay. Second question, just a simple yes
[1:35:32]
or no. Would you say that your plan
[1:35:36]
conforms to the town plan and regional
[1:35:38]
plan?
[1:35:39]
>> Yes.
[1:35:40]
>> Do you want to rethink that one?
[1:35:43]
>> That's not a question.
[1:35:45]
>> That actually was a question.
[1:35:46]
>> No, no, that was a great question. I
[1:35:47]
actually thought your yes or no was a
[1:35:49]
great question, but you want to rethink
[1:35:51]
that is not a question. I was allowing
[1:35:54]
him a second chance to answer.
[1:35:57]
>> The answer is yes. Again,
[1:35:58]
>> literally not phrased as a question. So,
[1:36:00]
part of the reason, and I'll say this
[1:36:02]
because I'm a process here, right? We
[1:36:05]
want to be able to provide you with
[1:36:07]
information and we want to know what
[1:36:10]
information we need to provide to you.
[1:36:13]
And then we want to provide you with
[1:36:16]
multiple opportunities to make comments
[1:36:18]
to say them in good faith and receive
[1:36:20]
them in good faith. And so, as My
[1:36:23]
request would be for you to think about
[1:36:25]
the form of your question and whether or
[1:36:28]
not it is inviting somebody to actually
[1:36:31]
answer it or setting them up
[1:36:35]
in a way that is just guaranteed to
[1:36:37]
fail. And I my my request goes in both
[1:36:41]
directions to both people who are
[1:36:42]
presenting to us and presented to. So
[1:36:47]
that's
[1:36:48]
>> okay.
[1:36:49]
>> My not me breaking my own rules and
[1:36:51]
making
[1:36:53]
Start that way.
[1:36:54]
>> I understand, however, that good faith
[1:36:57]
does go both ways because I lost count
[1:36:59]
on the number of times I was writing
[1:37:00]
down
[1:37:02]
minimal visibility, virtually invisible,
[1:37:06]
no one overseas,
[1:37:08]
not going to see it at all. You won't
[1:37:10]
see it.
[1:37:13]
Is that real?
[1:37:15]
>> That's why we do a visibility
[1:37:16]
determination so that you can make your
[1:37:18]
own assessment of that, ma'am.
[1:37:19]
>> Okay. My final question is
[1:37:23]
the standard is the certificate of
[1:37:25]
public good. That's what you're seeking.
[1:37:29]
Whose public good is this? Or is this
[1:37:31]
corporate good? Because if the town of
[1:37:33]
Rochester has multiple landline
[1:37:36]
providers, EC Fiber, AT&T, I live very
[1:37:42]
of town. Also, I have great coverage
[1:37:44]
with AT&T.
[1:37:46]
>> That may be that could very well be. I'm
[1:37:48]
saying I have it.
[1:37:50]
But even the attorney said that it's
[1:37:54]
mostly for visitors. So is this a
[1:37:56]
certificate of public good or is there a
[1:37:59]
certificate of for Verizon and T-Mobile
[1:38:02]
to come in?
[1:38:05]
>> There are an immense amount of Verizon
[1:38:06]
and T-Mobile customers who hopefully
[1:38:09]
live in Rochester, who live throughout
[1:38:11]
the state of Vermont, who come to
[1:38:12]
Vermont to enjoy uh the scenic
[1:38:15]
resources. Uh there's an immense amount
[1:38:17]
of public good. There's an immense
[1:38:18]
amount of public safety benefit that
[1:38:21]
comes from a tower like this. Uh uh I I go to a lot of public hearings like
[1:38:26]
this and I hear so many stories about
[1:38:28]
people who had a house fire and couldn't
[1:38:31]
get a telecommunications signal, so the
[1:38:33]
house burned to the ground as opposed to
[1:38:35]
fire engines uh coming on a timely
[1:38:38]
manner. I was at a hearing a couple
[1:38:40]
months ago where a woman said, um, just
[1:38:43]
so you know, I'm going to look at this
[1:38:45]
tower every day. This is in my line of
[1:38:48]
sight from my picture window. But the
[1:38:50]
benefit is is that I'm going to be able
[1:38:52]
to live in my house because my husband
[1:38:54]
died 10 years ago. And uh I can't live
[1:38:57]
alone without my call button. My help,
[1:39:00]
I'm fallen. I can't get up button. And I
[1:39:03]
can't walk to my mailbox and get a Wi-Fi
[1:39:06]
signal. So if I fall on my way to my
[1:39:08]
mailbox, I'm lying there. But this
[1:39:10]
telecommunications tower is going to
[1:39:12]
allow me to stay in my home. And I could
[1:39:14]
tell you a thousand stories like that.
[1:39:16]
Um and so there's an immense public
[1:39:19]
good. And uh um and and again the fact
[1:39:23]
that we're bringing a structure that
[1:39:25]
allows competition that's certainly in
[1:39:28]
the public good. It's certainly in
[1:39:30]
Verizon's but Verizon's not doing this
[1:39:32]
altruistically. They're doing it to um
[1:39:35]
to bring telecommunications to places
[1:39:38]
like Rochester, Vermont, which as you
[1:39:40]
can imagine isn't as populated as Boston
[1:39:43]
or Montpielar or Burlington, where you
[1:39:46]
know you get more return on your
[1:39:48]
investment, but they also have
[1:39:50]
requirements from the federal government
[1:39:52]
to uh develop better telecommunications
[1:39:56]
networks to bring better
[1:39:58]
telecommunications to Rochester and
[1:40:00]
Stockbridge and everywhere up and down
[1:40:02]
the Route under corridor. So, we're all
[1:40:04]
working together for the public good.
[1:40:06]
And uh you know, I've I've had several
[1:40:09]
people here tonight say, "How come
[1:40:11]
you're not building a tower taller to
[1:40:14]
cover my house as opposed to your
[1:40:17]
house?" So, and we try the best we can
[1:40:19]
to address everybody's concerns, but I
[1:40:22]
can assure you not everybody in town is
[1:40:24]
going to be happy. And um uh I I never
[1:40:27]
once said it was going to be invisible.
[1:40:29]
I never once. And I I um I I and I can't
[1:40:33]
say that. Uh the last time I went to
[1:40:36]
England, I went to Diagon Alley and I
[1:40:37]
tried to buy an invisibility cloak and
[1:40:39]
they just don't sell them. Harry Potter
[1:40:42]
joke. Uh Harry Potter joke.
[1:40:44]
>> I do.
[1:40:48]
» Sharon has a something.
[1:40:50]
>> Hi. Uh this is Sharon again. I do have a
[1:40:53]
question. Um and it's actually for the
[1:40:55]
Vertex gentleman. I've actually been
[1:40:58]
injured by this technology.
[1:41:00]
And I know other people that have been
[1:41:02]
too. And so I'd like to know how this is
[1:41:04]
in my public good. When I moved up to
[1:41:06]
Rochester to get away from this type of
[1:41:08]
stuff and pe people in Pittsfield,
[1:41:11]
Massachusetts are suffering from this
[1:41:13]
stuff for Verizon not taking the towers
[1:41:16]
down after they've caused them health
[1:41:18]
issues for the last three to four years.
[1:41:20]
I really don't want to have to leave my
[1:41:22]
home again. And where you're talking
[1:41:24]
about putting this P tower might make
[1:41:26]
that have to happen. So, how is this in
[1:41:29]
my public good as a person that has been
[1:41:31]
injured by this technology?
[1:41:37]
» Rochester already has telecommunications
[1:41:40]
companies operating right in the
[1:41:43]
downtown area and is the most densely
[1:41:46]
populated of Rochester. The same
[1:41:48]
technology has been deployed thousands
[1:41:51]
of times throughout
[1:41:53]
uh I mean several hundred times
[1:41:54]
throughout New Hampshire, I mean
[1:41:56]
Vermont, tens of thousands of places
[1:41:58]
nationally. Uh in more densely populated
[1:42:03]
areas uh uh sometimes the residential
[1:42:06]
buildings are the tallest buildings in
[1:42:08]
town. I I I did a project in Worcester,
[1:42:11]
Massachusetts where the tallest
[1:42:13]
buildings in Worcester were all the
[1:42:14]
public housing authority buildings and
[1:42:16]
we put antennas on all of those. We've
[1:42:18]
lived with this technology for a hundred
[1:42:21]
years because it's the same as radio and
[1:42:24]
you know the um the fire and police
[1:42:27]
chief use a form of radio
[1:42:29]
telecommunication that's the same
[1:42:30]
technology just a different frequency
[1:42:32]
band than what we deploy. So, uh, and
[1:42:35]
the bottom line is, um, the federal
[1:42:37]
government has deemed it safe. They've
[1:42:39]
done a lot of testing. They've, they've,
[1:42:41]
in in order to get the public good to
[1:42:44]
better deploy, we um, we need more
[1:42:48]
telecommunication sites. And the last
[1:42:50]
thing I'll point out is I'm not
[1:42:52]
proposing something in downtown
[1:42:54]
Rochester. I'm proposing something 2,000
[1:42:56]
ft off of Route 100 about uh 3/4 of or
[1:43:01]
to a mile south of downtown as far away
[1:43:04]
as you can get from the population and
[1:43:06]
from residential users.
[1:43:08]
Still providing great benefit and a
[1:43:10]
significant public good without any
[1:43:12]
having any effect on any neighboring
[1:43:15]
properties.
[1:43:26]
I I guess this is a question for Mary
[1:43:29]
maybe.
[1:43:30]
>> Hi.
[1:43:30]
Um so uh you said there will be many
[1:43:35]
opportunities to ask uh or to for public
[1:43:39]
comments and so
[1:43:42]
when would that start? I mean when when
[1:43:45]
would that happen?
[1:43:48]
>> So okay this is working. I believe and
[1:43:50]
I'll go back and check my notes that
[1:43:52]
this would be the third opportunity and
[1:43:55]
I'm going to be cautious here with my
[1:43:56]
public meeting because a meeting versus
[1:43:58]
a session versus a hearing are very
[1:44:00]
different things but this has been on
[1:44:02]
the agenda at the planning commission
[1:44:04]
twice
[1:44:05]
and uh both of those are public
[1:44:07]
documents publicly circulated and the
[1:44:10]
minutes are there. This will be the
[1:44:11]
third time that we have the planning
[1:44:13]
commission or the planning and zoning
[1:44:15]
board has created a public space for it.
[1:44:18]
And I would like to reiterate that the
[1:44:20]
application has not yet been submitted.
[1:44:23]
Okay? And so until the application is
[1:44:25]
submitted, all of the formal processes
[1:44:28]
don't kick in. And so once the
[1:44:31]
application is submitted, we will
[1:44:33]
continue. And please planning board
[1:44:35]
people like I'm speaking for the process
[1:44:37]
tonight because that was something that
[1:44:39]
I took on to organize. I am not speaking
[1:44:41]
for the planning board in total. But so
[1:44:44]
what I would say is I believe this is
[1:44:46]
the third public opportunity that the
[1:44:49]
planning board has created for people to
[1:44:52]
learn about ask questions about
[1:44:55]
telecommunications permitting. And I
[1:44:57]
believe we will continue to offer more
[1:44:59]
as we go through this 60 to 180day
[1:45:02]
process. And I would like to try and
[1:45:06]
continue to bend over backwards to make
[1:45:08]
them as accessible as possible, learn
[1:45:10]
from what people have said and um
[1:45:13]
make there be a single point you can go
[1:45:15]
for the documents. Um so that's where
[1:45:18]
I'm going. Well, well, I have a I mean
[1:45:21]
more question about this because there
[1:45:23]
there's like this in this particular um
[1:45:27]
opportunity that we had. It was about it
[1:45:30]
was about asking questions. Maybe some
[1:45:32]
of some of us have information that we
[1:45:35]
want to give in anformational
[1:45:38]
venue.
[1:45:39]
>> Yep. And I and I believe that that is
[1:45:42]
the a next step for us is to is is for
[1:45:46]
something like that. Right. Part of what
[1:45:48]
we want to do is to be very targeted
[1:45:50]
with what our goals and purposes are for
[1:45:53]
each meeting so that people can best
[1:45:55]
decide how to deal with the information.
[1:45:58]
So I agree with you and I think that's
[1:45:59]
something that we're looking forward to
[1:46:01]
with future opportunities is to think
[1:46:04]
about what other information people from
[1:46:07]
the town want us to help them access. So
[1:46:11]
I would I does that answer your
[1:46:13]
question?
[1:46:14]
>> I think so. I hope so. except for um if we would if some of us would like to
[1:46:22]
propose other kinds of experts
[1:46:26]
perhaps. Is that a possibility?
[1:46:28]
>> Uh yes.
[1:46:30]
>> And how would we go about doing that?
[1:46:31]
>> Um so I would contact a we can talk
[1:46:34]
about it after the meeting tonight. Um,
[1:46:36]
but B, I would send an email, and I did
[1:46:38]
get your email, but I would send an
[1:46:39]
email to the Rochester VT planning
[1:46:41]
commission@gmail.com,
[1:46:43]
and I would say um
[1:46:46]
that you would like I I'll think about
[1:46:48]
how to word this, but who who you think
[1:46:51]
we should listen to, why you think we
[1:46:54]
should listen to them, suggestions you
[1:46:56]
might have for for how we could um
[1:46:59]
connect people with that person, and and
[1:47:01]
we'll talk about it a little more
[1:47:03]
because I I will emphasize, right, we
[1:47:05]
are making this process up as we go
[1:47:08]
along and so I do take your suggestions
[1:47:11]
very seriously for how to change the
[1:47:14]
formats going forward.
[1:47:15]
>> Okay. Thank you.
[1:47:16]
>> Scott has a comment on this.
[1:47:19]
>> Um just speaking of the balloon test
[1:47:22]
that we're going to schedule that, you
[1:47:23]
know, I will be on site for with my
[1:47:25]
staff. Two other things came to mind.
[1:47:26]
Uh, number one, with respect to the
[1:47:29]
tower itself, the physical tower, not
[1:47:32]
the attachment mounts that are roughly
[1:47:33]
12 feet wide, but the tower is typically
[1:47:36]
5 feet in width. So again, that's very
[1:47:40]
close to the di the typical diameter of
[1:47:42]
the balloon in question. So the the
[1:47:44]
balloon is very representational of the
[1:47:47]
tower face and all of this stuff is to
[1:47:49]
scale. We have detailed engineering
[1:47:50]
drawings for these towers. So, you know,
[1:47:53]
we can quickly make sure that this is a
[1:47:55]
very accurate representation as close as
[1:47:57]
humanly possible given what we have um
[1:48:01]
and the again the face width of 12 ft.
[1:48:03]
But if there's key locations that people
[1:48:05]
want us to consider, it's helpful for me
[1:48:07]
to know ahead of time what the you know
[1:48:09]
for the planning commission there or the
[1:48:11]
town there to provide Fran and myself a
[1:48:13]
list of in of other locations that we
[1:48:16]
haven't taken photos from. And believe
[1:48:18]
it or not, we actually took more
[1:48:19]
locations than than is shown on that
[1:48:21]
map. We while the balloon was up for
[1:48:23]
hours, I literally did it myself. I
[1:48:26]
drove the town trying to find it and I
[1:48:28]
went basically a mile in all directions
[1:48:30]
because once you get behind a mile, if
[1:48:33]
you can see it from another mountaintop,
[1:48:34]
it's like looking at at the tower on top
[1:48:36]
of Mount Washington. It's a dot. It's
[1:48:38]
like a speck. It's it's it's almost
[1:48:40]
impossible to really simulate because
[1:48:42]
it's a speck. Um, so usually I I stick
[1:48:45]
to within a mile radius when I'm when
[1:48:47]
I'm driving trying to drive around the
[1:48:49]
block. here the block is quite large. So
[1:48:52]
the eastern side of the site, you know,
[1:48:54]
it's probably three miles away, you
[1:48:56]
know, to get to the next closest road
[1:48:57]
that that direction. And the closest
[1:49:00]
residential house, just because it came
[1:49:01]
up, is it in the area of about 1,800 ft
[1:49:04]
away from this tower. Um, and that
[1:49:06]
that's unusual. That's that's actually a
[1:49:08]
pretty big distance, you know, um, from
[1:49:11]
typical standards.
[1:49:26]
This is just a dumb question, but is
[1:49:28]
this going to have a flashing light on
[1:49:30]
top of the tower?
[1:49:32]
>> Not a dumb question. And the answer is
[1:49:35]
no. Um, I know the short answer is no. I
[1:49:39]
think I gave way too many long answers.
[1:49:41]
So,
[1:49:43]
>> you have another question.
[1:49:44]
>> Yeah. on um regarding the the public
[1:49:48]
good because I I have the the regional
[1:49:50]
plan the Two Rivers Adquichi regional
[1:49:52]
plan in front of me and it it's pretty
[1:49:54]
clear. It says the use of the region's
[1:49:56]
ridges for telecommunication towers and
[1:49:58]
related facilities needs to be
[1:50:00]
undertaken in a manner that will not
[1:50:02]
unduly detract from nor adversely affect
[1:50:04]
these scenic values. Protections
[1:50:07]
protection of these areas from
[1:50:09]
developments is a matter of public good.
[1:50:12]
Did Vertex refer to the regional plan
[1:50:15]
for this area?
[1:50:17]
>> We're not on the top of a ridge and
[1:50:20]
we're very conscious of that. If you
[1:50:21]
look past it, goes thousands of feet
[1:50:24]
higher and
[1:50:26]
>> Oh, no. You're definitely on a ridgetop
[1:50:28]
at that site. That's totally incorrect
[1:50:30]
to say. I I read maps for a living and
[1:50:33]
>> you're you're at a high point or you
[1:50:34]
wouldn't put it there. It's line of
[1:50:36]
sight technology, so you have to put it
[1:50:37]
on high points. I I understand that, but
[1:50:39]
it it's but when we look at it from the
[1:50:41]
route 100, it's it's not in a position
[1:50:46]
where it it projects significantly
[1:50:49]
farther above the ridge and by reducing
[1:50:51]
it down, we don't think you're going to
[1:50:53]
see it above the tree line.
[1:50:55]
>> I understand that, but this talks about
[1:50:56]
ridgetop development and you're on a
[1:50:58]
ridge. Did you refer Did Vertex refer to
[1:51:00]
the regional plan? That that was my
[1:51:02]
question. Yes, we look at the regional
[1:51:04]
plan. We look at the town's plan. We
[1:51:05]
look at the town zoning bylaw. We look
[1:51:08]
at the PUC regulations. Uh the um the
[1:51:11]
problem is is that I can't appease
[1:51:14]
everybody. And I've got multiple people
[1:51:17]
here saying I should have built it
[1:51:19]
taller. I've got people at the last time
[1:51:22]
said I should have built it um so that
[1:51:24]
you can't make it visible. I I have the
[1:51:26]
RF engineers at home saying it's got to
[1:51:29]
be a requisite height to provide the
[1:51:30]
signal or it has no benefit to the town.
[1:51:33]
So we try very hard and we've looked at
[1:51:36]
all these things and uh um and and I
[1:51:39]
believe that u that we are compliant.
[1:51:42]
You know you you said that that the
[1:51:45]
standard is an undue adverse impact. It
[1:51:48]
doesn't say invisible. And so we don't
[1:51:52]
believe that we have an undue adverse
[1:51:54]
impact in compliance with the regional
[1:51:56]
policy plan with the town zoning bylaw
[1:51:59]
and the town's plans and that the PUC
[1:52:02]
regulations.
[1:52:02]
>> Well, no, it actually says not detract
[1:52:05]
from or adversely affect the scenic
[1:52:07]
values. I
[1:52:09]
>> is what the regional plans.
[1:52:10]
>> We we are quite confident that we do not
[1:52:12]
detract or undo.
[1:52:15]
>> Okay, I understand. Thank you.
[1:52:23]
Okay. Jake Wildwood again. Uh, Vert.Ex
[1:52:26]
has a history of suing towns and public
[1:52:28]
utility commissions when you don't get
[1:52:30]
the answer you want. Is that sort of
[1:52:32]
what we're expecting here?
[1:52:35]
>> We expect the public utilities
[1:52:37]
commission to issue a certificate of
[1:52:39]
public good.
[1:52:40]
>> And if not, will you just go away?
[1:52:45]
» I'm not trying to be mean. I just want
[1:52:47]
to know what's going to happen.
[1:52:48]
>> I don't want to project that firehead.
[1:52:51]
I'm like I said, we've designed a site
[1:52:53]
compliant with all the regulations and
[1:52:55]
we expect a certificate of public good.
[1:52:57]
>> Thanks.
[1:53:02]
» Before we hang up, I want to talk about
[1:53:04]
the date of the balloon.
[1:53:07]
>> I want to ask a question if I may. Can
[1:53:09]
you hear me? Okay. Um
[1:53:12]
uh so now under the um 248 it's a
[1:53:16]
limited project where it was a full
[1:53:18]
>> limit limited size and scale. Yes,
[1:53:20]
>> limited size and scale. Um and I in
[1:53:23]
reading the the the primer there. I
[1:53:25]
couldn't quite tell if the analysis that
[1:53:28]
PUC does is the same. Um the the limited
[1:53:31]
size and scale didn't talk about the
[1:53:34]
criteria, but it did say something about
[1:53:36]
significant issues. Do you know if or
[1:53:40]
regional planning folks know that the
[1:53:42]
difference between those two processes?
[1:53:44]
>> It it's the same criteria but there's
[1:53:48]
different presumptions like there's
[1:53:50]
certain criteria that don't apply to
[1:53:53]
these type of like air quality for
[1:53:55]
example there's no air issues. However,
[1:53:58]
u before we had to put in affidavits to
[1:54:01]
say there's no impact on air quality.
[1:54:03]
Now because it's limited size and scale
[1:54:04]
we don't. uh uh things like that uh
[1:54:08]
things that don't there's no impact on
[1:54:10]
traffic for example but before I used to
[1:54:12]
have to get a traffic study now we don't
[1:54:15]
because there's a presumption because
[1:54:16]
it's limited that there's no uh impact
[1:54:18]
on traffic things like that
[1:54:22]
>> do you want to do
[1:54:25]
>> I'll do a wrap
[1:54:28]
>> uh okay so we're going to wrap it up for
[1:54:30]
tonight um if you are physically here
[1:54:33]
and I know many of you were on Zoom so
[1:54:35]
this does not apply. But if you were
[1:54:36]
physically here, um just drop and you
[1:54:39]
picked up a comment form, a bulletin,
[1:54:41]
not a bulletin board, a clipboard, a
[1:54:43]
pen, just drop it on the table or on the
[1:54:45]
empty boxes under the table on your way
[1:54:46]
out and we will uh take those written
[1:54:48]
comments and gather them all into a
[1:54:50]
document to share amongst the planning
[1:54:52]
commission and to turn into a fact sheet
[1:54:54]
so that I can start coating the
[1:54:56]
frequently asked questions, putting
[1:54:58]
answers to them and putting them up as a
[1:55:00]
publicly available document for people
[1:55:02]
who are coming into this process as it
[1:55:04]
goes forward.
[1:55:05]
Um and um
[1:55:08]
I suppose if you if anybody if any
[1:55:11]
individual person has a question, a
[1:55:12]
comment or a suggestion about the
[1:55:14]
process that they'd like to uh make in
[1:55:16]
person, I'll hang out for a few minutes
[1:55:18]
tonight. But otherwise, thank you very
[1:55:20]
much for coming. Thank you for my
[1:55:21]
patience with my insistence on process
[1:55:23]
and Christine's going to say something.
[1:55:26]
>> So, thank you all for coming. I just
[1:55:28]
want to point out how much time and
[1:55:31]
effort Mary put into making this event
[1:55:34]
happen for you. It was not it was
[1:55:38]
voluntary, completely voluntary because
[1:55:40]
we as a commission re really want to
[1:55:43]
make sure you know the information and
[1:55:45]
have an idea of what to do with it. So
[1:55:47]
can we give Mary and Greg a round of
[1:55:49]
applause for all that they
[1:55:53]
all
[1:55:55]
>> Mary who wanted to talk about the date
[1:55:58]
and just um terms of the process uh at
[1:56:02]
this point we'll be answering questions
[1:56:05]
u from through email
[1:56:08]
sharing information um if we get the
[1:56:10]
website set up we'll put um Fran's
[1:56:14]
presentation up there and all the other
[1:56:16]
documents ments that they've provided
[1:56:18]
with that you can also get from the PUC
[1:56:20]
website and then once there is a U um
[1:56:26]
application then we'll go through this
[1:56:28]
again and then you'll have then you'll
[1:56:31]
have real opportunities to stand up and
[1:56:32]
speak your mind about what what this
[1:56:35]
means to you.
[1:56:38]
>> Thank you very much everybody. Can can I
[1:56:41]
just I just want to talk about the
[1:56:42]
balloon and the issue I I would have
[1:56:44]
come in with a prepackaged date but the
[1:56:46]
problem is is that we have an election
[1:56:47]
in a couple
[1:56:48]
>> Francis what I would say is let's figure
[1:56:50]
out the date and then we can tell
[1:56:51]
everybody but rather than keeping
[1:56:53]
everybody here past 8.
[1:56:54]
>> That's fine.
[1:56:54]
>> Okay. Thanks very much everybody.
[1:56:57]
close.