[0:03]
>> Good morning, everyone.
[0:05]
Welcome to the August 26th regular board meeting of Tampa
[0:09]
Bay water.
[0:10]
The meeting is available for viewing through live streaming
[0:14]
and the recording of the meeting will be
[0:16]
posted on the agency's website.
[0:18]
Today we are continuing to use our new feature that
[0:21]
allows board members to request to speak and to make motions
[0:24]
and seconds using their tablets, rather than speaking out.
[0:27]
We expect this change to improve accuracy and clarity,
[0:30]
as it can be difficult to hear across the dais.
[0:33]
Board members, as we move through the meeting,
[0:35]
please use your tablets for these functions.
[0:38]
We appreciate everyone's patience
[0:39]
as we adjust to this new process.
[0:41]
At this moment, we have our pledge of allegiance,
[0:44]
and our vice chair is going to lead us.
[0:50]
>> I pledge allegiance to the flag of the United States
[0:52]
of America and to the Republic for which it stands,
[0:52]
one nation under God, indivisible,
[0:53]
with liberty and justice for all.
[1:02]
>> Thank you.
[1:03]
You may be seated.
[1:04]
Clerk, can you please call roll call?
[1:13]
>> (Calling roll)
[1:28]
Madam Chair, a quorum is present.
[1:33]
Lisset Hanewicz: Thank you.
[1:34]
Board members, were there any changes to the agenda?
[1:37]
I see none.
[1:38]
At this point, we go to public comment.
[1:40]
Each speaker will have three minutes to speak.
[1:42]
The first speaker I have here is David Ballard Gettis,
[1:49]
Jr. Good morning.
[1:53]
>> Good morning.
[1:54]
I live on Georgia Avenue in Palm Harbor.
[1:56]
The Federalist Papers reveals three constitutions, the former,
[2:03]
the latter, and the last resort.
[2:07]
One and one and one is three.
[2:11]
It's got to be good looking, it's just so hard to see.
[2:14]
Tip your hat to the new constitution
[2:15]
and pray you don't get fooled again.
[2:18]
This change had to come.
[2:20]
You knew it all along.
[2:22]
And even Mick Jagger, at Madison Square Gardens in 1969,
[2:27]
said, welcome to the breakfast shell.
[2:31]
The Federalist Papers were not written by Hamilton, Madison,
[2:36]
or John J. The Federalist Papers were originally drafted
[2:41]
by a shoemaker by the name of Jacob Boehme --
[2:45]
shoemaker, stick to thy last.
[2:47]
The Declaration of Independence, in perpetuity,
[2:50]
counterfeits itself as preamble to a second Constitution,
[2:54]
seen as the captures of water, in article 1, section 8,
[3:01]
clause 11, birthing unwarranted 14th amendment water
[3:05]
jurisdictions, as declared, thus revealing the methodology
[3:09]
of the Prince in the Declaration of Independence,
[3:13]
written by Niccolo Machiavelli --
[3:17]
for it is far better to be feared than it is to be loved.
[3:21]
Even George Washington -- he claims to be of greatest
[3:26]
rankness and truly one's worst enemy in his farewell
[3:30]
to Christianity address.
[3:31]
He states that, twice we are being given a useful lesson
[3:37]
on our heads, seen as a useful art for limited times
[3:40]
in article 1, section 8, clause 8.
[3:46]
Our current constitution, unconstitutionally,
[3:49]
is being used as a letter of Marquis, an ex post facto
[3:53]
form of reprisal, seen as inexcusably
[3:57]
defective in Federalist paper number 64,
[4:00]
both deaf to the voice of justice and consequently,
[4:04]
as written in the Declaration of Independence.
[4:07]
Abraham Lincoln -- he did not write the 14th amendment.
[4:11]
He amended it to include the rebellion clause,
[4:16]
denouncing the book of Rebellion,
[4:18]
such Well-bound book of rebellion as possibly
[4:22]
found in statute 298.36.
[4:28]
London bridges falling down, London Bridge is falling down,
[4:33]
and they can take their wayfaring mercenaries
[4:35]
down with them, too.
[4:37]
Welcome to the bond market.
[4:40]
Thank you.
[4:42]
Lisset Hanewicz: Thank you.
[4:43]
Next up, Joe Abersoch.
[4:48]
Good morning.
[4:52]
>> Good morning, ladies and gentlemen.
[4:54]
My name is Joe.
[4:55]
I live in Tampa, Florida, 3.6 miles north of the football
[4:59]
stadium on Lake Carol.
[5:03]
Representing Lake Carol today -- approximately 1000 people.
[5:11]
There's about 400 homes on the lake, about 600
[5:14]
that used the lake.
[5:17]
The lake is at record low, and we are (Inaudible).
[5:23]
Based on that condition, the lake is under duress to this
[5:27]
degree -- there is no boating.
[5:29]
There is no fishing.
[5:30]
There is no action.
[5:31]
And worse, there is collateral damage.
[5:34]
There is a number of boats, probably 50, up on the lift
[5:39]
because we have no water under our dock or lift.
[5:43]
Those boats are stranded there.
[5:46]
That brings us to, why am I here?
[5:50]
I am here representing the three associations
[5:53]
that are asking for help.
[5:56]
We know we cannot solve this problem.
[5:59]
This problem is very complex.
[6:02]
It requires a lot of effort, coordination,
[6:06]
of which I want to report now that there was coordination
[6:11]
being done through the coordination help (Inaudible).
[6:16]
He's going to set up the meeting to do this.
[6:18]
That's why I'm here, is to personally thank him
[6:22]
for his responsibility to support us.
[6:25]
But I also know that it's going to take a lot more coordination
[6:31]
.
[6:32]
We are in a drought.
[6:34]
Where is it going to end?
[6:36]
I don't know.
[6:37]
But that's why we're here.
[6:38]
In summary, I want to thank you for the time this morning
[6:41]
and the opportunity to speak with you.
[6:43]
And if you keep in mind, Lake Carroll needs your help.
[6:48]
Thank you very much.
[6:51]
Lisset Hanewicz: Thank you.
[6:52]
I have no more public speakers.
[6:55]
If you can just keep us posted on your work, we appreciate it.
[7:00]
Thank you.
[7:01]
Next up, we move on to consent.
[7:05]
Are there any items that the board wishes to pull?
[7:08]
I don't see any.
[7:14]
So we have the --
[7:16]
I had the mover to approve as Commissioner Wostal.
[7:23]
Seconder, Miranda.
[7:29]
>> I'm going to spam that button the whole meeting.
[7:35]
Lisset Hanewicz: He moved quickly, and he exactly what
[7:37]
he was doing.
[7:40]
Board members, please enter your votes.
[7:45]
>> Motion passes unanimously.
[7:48]
Lisset Hanewicz: Thank you, clerk.
[7:50]
Next up, we move to the regular agenda.
[7:52]
We have the general manager's report.
[7:54]
This item is for information only.
[8:00]
Charles Carden: Good morning, Madam chair and members
[8:01]
of the board.
[8:02]
We will start by having Mr. Hogg go to the presentation podium
[8:08]
as I speak to the conditions out there briefly.
[8:10]
He will get into a little more detail in.
[8:13]
We are still in the drought.
[8:15]
We are about more than halfway through
[8:17]
our typical rainy season.
[8:19]
Good news is, we did put some water in the reservoir,
[8:23]
and it has been a long time coming.
[8:25]
I know we are about -- we are over 4 billion gallons.
[8:29]
The reservoir does hold 15 billion gallons,
[8:32]
so we have got a long way to go.
[8:34]
It took a while to get to where we are,
[8:36]
so it will take a little while to get out.
[8:39]
Warren, would you walk us through some of the statistics?
[8:45]
>> Yes, good morning, Madam chair, members of the board.
[8:48]
We are still looking at drought conditions
[8:50]
that cover most of the state, especially our tri county area.
[8:55]
We have started making some progress
[8:57]
in diminishing the drought conditions,
[8:59]
although it is still persistently
[9:02]
in extreme or severe drought over almost all
[9:05]
of the three county area.
[9:07]
This was an update from last week.
[9:10]
This map is updated once per week,
[9:12]
and we do watch it closely to see how things are progressing.
[9:15]
Since the rains happened, it caused some recovery.
[9:19]
I don't expect a whole lot of gain
[9:23]
to be seen for the next week or so.
[9:27]
But we are anticipating our summer rains
[9:29]
to return later this week.
[9:31]
Hopefully they will return and stay with us.
[9:35]
Our service area remains in a stage 3 regional water supply
[9:41]
shortage under our Water Shortage mitigation plan,
[9:44]
and that is because we are running a rainfall deficit
[9:46]
of 14.3in over the last year.
[9:50]
And the flow in the Hillsborough River
[9:53]
remains at 23.3 million gallons a day
[9:57]
below the normal level for the last 12 months.
[10:01]
Water Management District continues its phase 3 water
[10:08]
shortage restrictions, and that is good until at least October
[10:11]
1st.
[10:11]
If we don't see some improvements in our conditions,
[10:15]
that could possibly be extended.
[10:17]
We'll be continuing those discussions with the Water
[10:20]
Management district.
[10:21]
So water conservation enforcement
[10:26]
will remain critical through the summer
[10:29]
and fall as we try to recover and focus
[10:31]
on storing as much water in the reservoir as possible.
[10:36]
Mr. Carden mentioned, it took a while to get into this.
[10:41]
It's going to take a while to get out.
[10:42]
We started our drought conditions
[10:44]
in September of last year.
[10:46]
We should have gotten 7.5 to 8in of rain,
[10:48]
but we only got about 2.
[10:50]
It has been very, very dry since, with only average rain
[10:55]
in December and July.
[10:57]
We had one good month, and that was May.
[11:00]
That has put us into the significant shortage
[11:03]
that we are in.
[11:05]
We did get River flows increasing in late July,
[11:11]
with rains finally in the upper part of the river basins.
[11:15]
Until then, much of the rain had been
[11:17]
along the coastal communities, which does help reduce demand,
[11:20]
but it did not make the rivers flow to the point
[11:23]
where we could sustainably harvest water.
[11:27]
Through the month of July, for the first ten months,
[11:32]
we delivered an average of 206.1 million gallons a day
[11:36]
for the year to date.
[11:38]
It's about 7 million gallons a day higher than last year
[11:41]
because of the drought conditions.
[11:43]
It's about 3.5% more water than last year.
[11:47]
We are focused on refilling the reservoir,
[11:52]
but we are looking for glimmers of good news.
[11:54]
It appears that the conservation and enforcement of restrictions
[11:58]
is paying off.
[12:01]
We had projected, throughout the beginning of the year,
[12:05]
we project what we need to deliver,
[12:07]
we expect to deliver each month.
[12:12]
For the month of July, we delivered about 10 million
[12:14]
gallons a day less than we had anticipated.
[12:16]
For us, that means that the restrictions and the enforcement
[12:20]
are helping, along with some of the much needed rain
[12:23]
in the coastal communities.
[12:25]
The 12 month average rate for the consolidated permit
[12:30]
Wellfields has been steadily increasing
[12:33]
since July of last year, and we reached a 12 month
[12:37]
running average of 106.3 million gallons a day
[12:40]
at the end of July.
[12:42]
As we are focused on refilling the reservoir as much as we can
[12:50]
this summer, it has caused us to shift our production
[12:52]
to other facilities, such as the well fields,
[12:56]
at the desalination facility, so we can store
[13:00]
as much water as possible.
[13:02]
We do anticipate this will begin to decline as soon as we
[13:07]
can get some sustained rains.
[13:09]
We are running our surface water treatment plant
[13:11]
at 30 million gallons a day.
[13:13]
For this month, we have been running that simply
[13:15]
from river flow, not taking any out of the reservoir.
[13:18]
That's good news.
[13:20]
We are either running at 30 for what we capture --
[13:23]
everything else is going right into the reservoir for storage.
[13:26]
The south Central Hillsborough Regional Wellfield, the running
[13:31]
average, average 26.57 million gallons a day
[13:35]
at the end of July, which is below its permit limit.
[13:38]
And we expect to remain pretty close to the permit limit
[13:42]
for the coming months.
[13:44]
Our reservoir was forecasted to be almost 3.5 to 4 billion
[13:52]
gallons at the end of July.
[13:55]
We were flat lined, as we have not stored any water in it
[13:59]
until really the end of the month.
[14:01]
As of last night, we did increase over 4 billion gallons.
[14:07]
We are now about 26% full.
[14:10]
That's an encouraging sign.
[14:13]
If we can get good summer rains starting again this week,
[14:16]
we will store as much as we can for the coming dry season.
[14:20]
Before we transition, I'd be happy to answer any questions
[14:25]
on this section.
[14:30]
Lisset Hanewicz: Questions?
[14:33]
Thank you.
[14:38]
Charles Carden: I will continue with some
[14:38]
of the topics on this slide.
[14:40]
In July, our IT department and some of our other leadership
[14:44]
departments conducted a cybersecurity tabletop exercise.
[14:48]
It was our first time doing that internally.
[14:52]
It Was very well attended, and we
[15:00]
learned a lot working amongst ourselves
[15:01]
and something that is a different threat out there.
[15:05]
We also continued to closely monitor
[15:07]
reports of the cyber activity targeting water utilities
[15:11]
across the United States.
[15:13]
We remain actively engaged in evaluating possible threats
[15:17]
to our systems.
[15:19]
Also, last month, at the agency hosted a series of knowledge
[15:22]
to implementation workshops --
[15:27]
we call them K2i.
[15:27]
We had three of our members -- they were represented here,
[15:32]
Hillsborough County, Pinellas, with these workshops.
[15:36]
We shared knowledge and explored innovative solutions
[15:38]
to some of the common utility challenges that we all face.
[15:43]
Also, just Tuesday last week, at the Pasco County Commissioners
[15:49]
formally approved requesting with Tampa Bay water, somewhere
[15:55]
east of Cypress Creek.
[15:55]
We have to work out the details.
[15:57]
It is something that will come to this board
[16:02]
in the form of a letter.
[16:03]
We will bring it to the next board meeting for approval,
[16:06]
and then we will evaluate and work out
[16:09]
an agreement with the county.
[16:11]
I believe the letter coming will say a new point of connection
[16:15]
is needed by the year 2035.
[16:17]
Also wanted to give you an update on our pricing of bonds
[16:22]
that we did in July.
[16:24]
The board approved a resolution to secure $292 million
[16:28]
for our capital improvement plan coming up and also refunded
[16:33]
a portion of the outstanding 2016-A bonds.
[16:38]
On August 4th column at the agency price the revenue bonds
[16:41]
and the refunding bonds, and they were well received
[16:46]
by the investors.
[16:47]
In fact, they were oversubscribed six times,
[16:51]
meaning we needed $360 million, and we ended up
[16:55]
getting orders for over 2.3 billion,
[16:57]
which put us in a good position to negotiate lower rates.
[17:01]
The next challenge or milestone will be August 27th.
[17:05]
That will be the closing of the bond funds.
[17:09]
So that should be coming up here in the next two weeks.
[17:13]
Also, we have been busy talking to local stations
[17:19]
and the newspapers about the recent rain in our drought
[17:22]
conditions.
[17:23]
You see here, Warren, myself, Paul
[17:26]
or on some of the local news stations
[17:29]
talking about the recent rains and how they are affecting us.
[17:33]
Malik Rankin -- she is on the picture on the far right --
[17:39]
she is our public communications specialist.
[17:41]
She participated in Keep Tampa Bay Beautiful Back to School
[17:45]
Bash earlier this month.
[17:47]
We sponsor their education program,
[17:49]
which helps make these events and activities possible.
[17:53]
And recently, our staff attended the
[17:57]
build Saint Pete Construction Expo, which
[18:00]
connects businesses and buyers and agencies
[18:02]
to provide access to opportunities and partnerships.
[18:06]
And finally, I would like to congratulate the finance team
[18:11]
for receiving the Government Finance Officers Association
[18:17]
Distinguished Budget Presentation Award.
[18:21]
I believe it is the year number 18 in a war, so --
[18:26]
your number 18 in a row, so -- year number 18 in a row,
[18:34]
so congratulations.
[18:35]
With that, I'm happy to take any questions.
[18:41]
Lisset Hanewicz:18 year streak.
[18:41]
I don't see any requests to speak.
[18:43]
We are going to move on to our action items.
[18:45]
We have C.1 and C.2 that are going to be presented together.
[18:52]
Good morning.
[18:56]
>> Good morning, madam chair, members of the board.
[18:58]
Today will present two related action
[19:00]
items that support the final delivery of the South
[19:03]
Hillsborough pipeline and associated projects.
[19:06]
This map illustrates our South Hillsborough pipeline project.
[19:12]
The pipeline is essential to meeting
[19:14]
Hillsborough County's growing water needs in the 2028 time
[19:18]
frame.
[19:19]
In addition to the pipeline, the project
[19:22]
also includes the requested improvements
[19:24]
to Hillsborough County's infrastructure, as well as
[19:28]
new points of connection and a new alkalinity adjustment
[19:34]
facility.
[19:34]
This project is being delivered through the Construction Manager
[19:40]
at risk.
[19:43]
The work is competitively bid and awarded
[19:45]
as the project advances, allowing construction
[19:50]
to proceed while remaining design elements are finalized.
[19:52]
The board initially approved Garney and has already
[19:59]
approved the Preconstruction services and three
[20:02]
guaranteed maximum GMP packages.
[20:05]
Today's action is for the fourth and final package.
[20:07]
The project is well underway, and work on segment B
[20:12]
of the pipeline is beginning.
[20:13]
And approval of this package will
[20:16]
provide the remaining construction
[20:17]
scope needed to complete the South Hillsborough pipeline
[20:21]
project.
[20:22]
I will proceed with a more detailed construction
[20:25]
update at the end of this meeting under Agenda Item D.1.
[20:31]
Now, moving on to the action Items, agenda item C.1 --
[20:35]
we request approval of the Fourth Amendment --
[20:42]
GMP number 4 includes the new alkalinity adjustment facility,
[20:48]
Hillsborough County improvements, and the points
[20:50]
of connection work.
[20:51]
The total value of this GMP is $53.65 million,
[20:55]
with Tampa Bay water funding about 38.8 million
[21:00]
and Hillsborough County funding about $14.8 million.
[21:04]
With that, staff recommends the approval of this GMP amendment
[21:12]
in the amount of $53.65 million.
[21:25]
Dave Eggers: Thank you for the presentation.
[21:25]
Just a brief update on how we are doing with these projects,
[21:28]
as compared to what we were estimating costs to be --
[21:33]
just trying to get a feel overall.
[21:37]
>> Sure.
[21:37]
I have my handy notes in here.
[21:39]
So initially, the project scope included segment a, segment B,
[21:43]
and the points of connection work.
[21:46]
The current budget, as published in our latest program,
[21:51]
is $505.7 million, and with the work
[21:56]
that we are requesting approval today,
[21:58]
the total budget is $534.4 million.
[22:03]
It's about $28.7 million above the current budget.
[22:11]
Most of the work and the delta that we see in this project
[22:17]
is reflected with work that was requested
[22:20]
by Hillsborough County, a significant portion of that.
[22:23]
In addition to that, we have increased slightly the budget
[22:28]
for property acquisition for segment B.
[22:32]
That's the delta that you will see and the net increase.
[22:40]
Dave Eggers: Thank you.
[22:43]
Lisset Hanewicz: I don't see any other request to speak.
[22:45]
If anyone wants to make a motion --
[22:49]
we have Commissioner Wostal moving with a second
[22:56]
by Commissioner Cohen.
[23:01]
>> Motion passes unanimously.
[23:04]
Lisset Hanewicz: Thank you.
[23:05]
Move on to the next item?
[23:08]
>> With approval of the GMP amendment addressed in this
[23:10]
agenda item, I will now transition to agenda item C.2,
[23:14]
which addresses the program and Construction Management services
[23:17]
for this project.
[23:19]
Now, they have supported Tampa Bay water
[23:22]
throughout the planning, design, GMP negotiations,
[23:26]
and construction phases of the South Hillsborough pipeline
[23:28]
program and associated projects under their Integrated Program
[23:35]
Services Management contract.
[23:36]
They have been supporting this program since 2022.
[23:40]
This amendment to task authorization under
[23:44]
their contract -- they will continue to provide the three
[23:47]
key functions shown on this slide.
[23:50]
Through these efforts, they will continue overseeing program
[23:54]
delivery, coordinating the engineering and construction
[23:57]
services and teams, and provide a strategic support to Tampa Bay
[24:05]
Water --
[24:06]
completion and closeout.
[24:07]
With that, staff request approval of this assignment
[24:12]
increase to Black and Veatch in the amount of $3.76 million.
[24:19]
Lisset Hanewicz: I don't see any request to speak.
[24:24]
Dave Eggers: Again, kind of a cost --
[24:25]
this is just the last piece, so what is their contract total bid
[24:31]
so far?
[24:33]
>> Agenda item C.2 do have the total number reflected.
[24:37]
If you give me one second, I will find it exactly.
[24:39]
I believe it is $7.3 million, the total, since 2022,
[24:49]
through the end of this project, which will be by the end of --
[24:57]
Dave Eggers: 3.7 that we are --
[25:00]
>> The aggregate of the entire assignment will be 7.37.
[25:07]
Dave Eggers: $534 million?
[25:12]
>> That's included in that total.
[25:15]
Lisset Hanewicz: I don't see any other requests to speak.
[25:15]
If there is a motion to approve --
[25:17]
there is a motion by Commissioner Wostal and second
[25:23]
by Commissioner Eggers.
[25:30]
>> Motion passes unanimously.
[25:33]
Lisset Hanewicz: Thank you.
[25:34]
Next up, we have C.3 that is going to be presented
[25:38]
by our general counsel.
[25:41]
>> This is another item related to the South Hillsborough
[25:42]
pipeline, requesting approval of the settlement with the Fishhawk
[25:46]
Community Development District for easements and two temporary
[25:49]
easements -- that's the most property we are obtaining from
[25:53]
any one parcel or property owner.
[25:55]
The amount of the settlement is a little over $2.1 million in.
[25:59]
Recommended by our Special counsel,
[26:01]
and we are recommending approval.
[26:03]
Happy to answer any questions.
[26:08]
Dave Eggers: Same question -- how are we doing as it relates
[26:11]
to what we were estimating those costs to be total?
[26:16]
>> I would have to defer to Maribel to give you those
[26:20]
figures.
[26:24]
>> I'm glad I prepared for this in.
[26:25]
So actually, property acquisition
[26:27]
have increased slightly for segment B. Most of the remaining
[26:33]
parcels that we are acquiring are undergoing the eminent
[26:35]
domain process.
[26:36]
We have seen that we have been negotiating quite a lot
[26:41]
with the property owners.
[26:43]
So initially, segment B had a budget of $9 million,
[26:49]
and we are estimating, as of today,
[26:50]
that we will be spending $11.4 million -- fron 9,
[26:59]
initial budget on property cost only.
[27:03]
Dave Eggers: Let me just add, that is to segment B.
[27:05]
The entire property budget for that whole pipeline is $23 --
[27:13]
Charles Carden: Let me just add, that is segment B. We've got --
[27:18]
a total of 204.
[27:19]
We are getting close to the end.
[27:21]
We have some -- in the budget.
[27:27]
Dave Eggers: You have spent 11.4 on B?
[27:32]
Charles Carden: On the entire A and B.
[27:36]
Dave Eggers: The budget was 23 originally?
[27:41]
Charles Carden: Yes.
[27:43]
Dave Eggers: Thank you.
[27:45]
Lisset Hanewicz: I don't see any other requests to speak.
[27:45]
There's a motion to approve.
[27:47]
There is a motion by Commissioner Eggers,
[27:53]
second by Commissioner Wostal.
[27:58]
>> The motion passes unanimously.
[28:02]
Lisset Hanewicz: Thank you.
[28:04]
C.4 -- this is going to be presented by Danielle,
[28:07]
the senior project manager.
[28:08]
Good morning, Danielle.
[28:12]
>> Good morning.
[28:13]
Agenda item C.4 is an action item.
[28:17]
At the end of this presentation, I
[28:18]
will be requesting approval for the Professional Engineering
[28:21]
Services contract.
[28:22]
As a reminder, the South Hillsborough Wellfield
[28:26]
has been a potential water supply project since 2018,
[28:30]
and public engagement has occurred since 2021.
[28:33]
Staff completed a feasibility study in 2021
[28:36]
that included the construction of the test production well
[28:39]
and aquifer performance Test.
[28:40]
The study confirmed the project's feasibility
[28:43]
and alignment with the board's approved evaluation criteria
[28:46]
of cost effectiveness, environmental stewardship,
[28:49]
and viability.
[28:51]
The second aquifer performance test
[28:53]
was conducted in 2023, which validated these results.
[28:57]
October of 2025, the board approved this project
[29:00]
as a new water supply and treatment capacity project.
[29:03]
Since then, the team has advertised
[29:05]
request for proposals for professional engineering
[29:08]
and Construction Manager at Risk Services.
[29:10]
Today's presentation is for approval of the Professional
[29:13]
Engineering Services contract.
[29:15]
This project was originally contingent on agreement with
[29:18]
Hillsborough County that included the purchase
[29:20]
of groundwater recharge credits to provide the net benefit
[29:29]
associated with our proposed withdrawals --
[29:34]
unable to reach terms of agreement in a timely manner,
[29:38]
and the project was put back into the long term master water
[29:41]
plan for future consideration.
[29:42]
Since that time, this board has approved the acquisition
[29:45]
of water use permits from private landowners,
[29:47]
enabling the transfer of water use permits to this wellfield.
[29:51]
We now have acquired 3.7 million gallons per day
[29:54]
and are working towards three more
[29:56]
water use permit acquisitions that we estimate
[29:59]
will yield about 5.5 MGD.
[30:05]
We can also increase the yield of this wellfield
[30:07]
by up to 6.1 million gallons per day
[30:09]
if we can successfully negotiate to buy reclaimed credits
[30:11]
with Hillsborough County.
[30:12]
This yield is based on the county's minimum recharge
[30:15]
of up to 10 million gallons per day.
[30:18]
The total potential yield of 6 to 12 million gallons
[30:21]
could go up if we acquire additional permits
[30:24]
or if Hillsborough County increases its aquifer recharge
[30:26]
system.
[30:27]
This project does have potential to be implemented in phases,
[30:31]
as we acquire additional quantities.
[30:35]
The proposed wellfield layout shown here
[30:37]
would support withdrawals of 6 to 12 MGD,
[30:43]
with the design and construction of up to eight production
[30:45]
wells, monitoring wells, approximately four miles
[30:47]
of collector main piping, a groundwater ozone treatment
[30:50]
facility for the removal of hydrogen sulfide,
[30:52]
and a point of connection and metering facilities.
[30:54]
This project will be delivered using a construction manager
[30:57]
at risk, which is the same delivery
[31:00]
method being used currently for the South Hillsborough pipeline.
[31:03]
The estimated completion date is November 2029,
[31:06]
which will help meet the region's growing drinking water
[31:10]
needs.
[31:11]
The scope of services for this project or this contract
[31:14]
includes a well design and testing, water treatment
[31:17]
and collector main design, groundwater modeling,
[31:20]
permitting support, surveying services,
[31:24]
CMAR collaboration and negotiation support,
[31:28]
and public outreach.
[31:30]
And with that, staff recommends approval of the Professional
[31:34]
Engineering Services contract with Stantec consulting
[31:38]
for $14.3 million.
[31:44]
Lisset Hanewicz: Thank you.
[31:44]
I don't see any requests to speak on this item.
[31:46]
Is there a motion on this item?
[31:49]
There is a motion to approve by Commissioner Cohen, seconded
[31:54]
by Council Member Miranda.
[31:58]
Please enter your votes.
[32:03]
>> Motion passes unanimously.
[32:06]
Lisset Hanewicz: Thank you.
[32:06]
We are done, I think, with the South Hillsborough items.
[32:09]
Next up, we have surface water treatment plant item.
[32:12]
That is C.5.
[32:15]
The project manager is going to be presenting.
[32:18]
Good morning.
[32:22]
>> Good morning Madam Chair, and members of the board.
[32:24]
I am Tampa Bay Water Project manager I'm.
[32:26]
Agenda item C.5 is an action item at the surface water
[32:33]
treatment plant.
[32:34]
At the end of this presentation, I
[32:35]
will be requesting your approval for the contract amendment
[32:39]
for the construction phase services associated
[32:43]
to this project.
[32:46]
The supervisory control and data acquisition system, better known
[32:53]
as the SCADA system, is used by Tampa Bay Water
[32:57]
to monitor and control facilities remotely, using
[32:59]
real time operational data.
[33:01]
The SCADA system project, which is included in our capital
[33:07]
improvement program, will modernize the technology
[33:09]
behind the system, including PLCs,
[33:13]
data networks, and cybersecurity controls, among others.
[33:18]
The design phase services, known as the phase 1 ,
[33:26]
was approved by this board back in February 2025.
[33:28]
Since then, our team have finished 100% design,
[33:32]
which includes engineering evaluations and the negotiated
[33:37]
guaranteed maximum price for phase 2, construction phase,
[33:42]
which is amendment being -- which is presented today.
[33:45]
As for the coming milestones, we will start construction
[33:50]
activities now in August, concurrently
[33:53]
with the surface water treatment plant expansion project,
[33:56]
and we will reach substantial completion and final completion
[34:01]
by December 2028 and February 2029, respectively.
[34:06]
Moving on, this slide summarizes the project costs
[34:12]
under the existing contract and the proposed $20 million
[34:21]
amendment, which includes equipment and materials,
[34:25]
construction labor, and owners allowances and contingencies.
[34:29]
With that, staff requests approval of the negotiated
[34:34]
agreement amendment with Veolia for the construction services
[34:40]
in the amount of $20.3 million, which includes about --
[34:45]
this concludes my presentation.
[34:46]
I'm happy to take any questions.
[34:51]
Lisset Hanewicz: Thank you.
[34:51]
I don't see any requests to speak at this time.
[34:53]
Is there a motion on this item?
[34:55]
There is a motion from Commissioner Wostal, seconded
[35:01]
by Council Member Miranda.
[35:02]
If you can open voting, Council members,
[35:08]
please issue your votes.
[35:12]
>> Motion passes unanimously.
[35:14]
Lisset Hanewicz: Next up, we have C.6.
[35:16]
This is for professional services contracts,
[35:18]
as needed engineering services.
[35:20]
This is going to be presented by James
[35:22]
Smith, professional engineer.
[35:26]
>> Good morning.
[35:27]
Again, my name is James Smith.
[35:27]
I'm a professional engineer in the engineering department.
[35:30]
This, I will present agenda item C.6 regarding the new as needed
[35:34]
engineering services professional services
[35:38]
contracts and request your approval.
[35:40]
The current as needed engineering contracts
[35:44]
approved in September of 2021 are nearing expiration.
[35:47]
Recent updates to Florida's consultants Competitive
[35:50]
Negotiation Act increased the threshold
[35:52]
for continuing contracts, allowing
[35:55]
Tampa Bay water greater flexibility in delivering
[35:58]
smaller engineering projects.
[36:00]
Tampa Bay Water continues to advance major capital
[36:03]
improvements, asset renewal efforts, and long term planning
[36:07]
initiatives.
[36:07]
To support this work, we need to access a wide range
[36:10]
of engineering expertise.
[36:12]
These contracts provide flexibility to obtain
[36:14]
specialized support through studies, design, permitting,
[36:18]
and technical services, as needs arise,
[36:21]
without conducting separate -- for each assignment.
[36:25]
We conducted a procurement process
[36:27]
that is described in your agenda memo.
[36:29]
Firms were invited to create teams
[36:31]
that qualified for all engineering disciplines.
[36:34]
There were 25 responses to Tampa Bay Water's invitation
[36:38]
for the five year contract at a value
[36:40]
not to exceed $1.25 million.
[36:42]
And individual tasks to up to $500,000.
[36:44]
Tasks above this amount will require board approval,
[36:48]
as the task that supports a CIP project.
[36:54]
Evaluating 25 responses is a significant effort.
[36:57]
A special thank you to the Committee for their huge effort
[37:01]
in evaluating the responses.
[37:02]
Award of these contracts does not obligate the board
[37:05]
at this time.
[37:06]
The budgets for these expenditures
[37:09]
are (Inaudible) approved each year or in the project
[37:12]
budgets, as approved by the board.
[37:14]
Based on the qualifications and very tight scoring,
[37:17]
all 25 contracts are recommended for award
[37:20]
for as needed engineering for the next five years.
[37:23]
This slide lists the recommended firms.
[37:26]
Out of the 25, nine firms are brand new
[37:32]
or have not worked with Tampa Bay Water recently.
[37:35]
Staff recommends approval.
[37:38]
This concludes my presentation.
[37:40]
I'd be happy to answer any questions you may have.
[37:45]
Lisset Hanewicz: Thank you.
[37:46]
Any comments, questions?
[37:48]
I guess we have increased over 100% -- from 12 to 25?
[37:54]
That's good.
[37:55]
More competitive.
[37:55]
If there is a motion on this item --
[37:57]
there is a motion to approve by Commissioner Wostal.
[38:02]
Clark, if you can open the machine
[38:03]
for voting, board members, please enter your votes.
[38:09]
>> Motion passes unanimously.
[38:12]
Lisset Hanewicz: Thank you.
[38:12]
We move on to presentation and reports.
[38:14]
The first presentation is the South Hillsborough pipeline
[38:18]
and surface water treatment plant expansion projects
[38:20]
construction update, and Maribel Medina is going to present this.
[38:28]
>> Now to the fun stuff, right?
[38:34]
Agenda item D.1 provides an update --
[38:37]
I will start with an update on our surface water treatment
[38:39]
plant expansion project.
[38:41]
Now, the surface water treatment plant
[38:44]
is the heart or workhorse of our surface water system.
[38:49]
In 2022, the board approved this project
[38:52]
as part of our long term master Water
[38:54]
plan to meet the region's needs by the year 2028.
[38:59]
The plant expansion will provide up to an additional 12.5 million
[39:04]
gallons per day to the region.
[39:07]
It includes a fifth treatment train,
[39:12]
along with supporting systems, which are labeled A
[39:16]
through E on the diagram.
[39:18]
The new treatment train will mirror the existing treatment
[39:21]
processes currently in operation.
[39:24]
Area A represents the fifth treatment train.
[39:27]
Area B shows the built -- belt press replacement.
[39:34]
Area C identifies the location of the three new filters.
[39:39]
Area D shows the location of the chemical buildings,
[39:43]
and area E shows the expanded solids drying beds.
[39:47]
In area A, ground reinforcement has been completed.
[39:50]
The team is currently working to cut these reinforcement columns
[39:55]
down to grade before installing the load to transfer platform.
[39:58]
The picture on the bottom right shows the ongoing work
[40:01]
for the routed columns cut down to rate in support of the load
[40:06]
transfer platform installation.
[40:08]
The main picture shows the pipe Gallery new overhead conduits
[40:14]
piping from the south electrical building into train number 5.
[40:20]
In area B, three of the belt filter presses
[40:22]
have been delivered to the site and are set in place.
[40:25]
The installation of piping and feeding
[40:27]
connections to support the new presses is now in progress.
[40:31]
And the main picture shows the new belt filter
[40:35]
press area and plumbing work, and the top left picture
[40:39]
shows one of the belt filter presses containment
[40:42]
walls and concrete pedestals.
[40:45]
In area C and D, the team have completed the installation
[40:51]
of the 16 inch filter to waste piping and concrete encasement,
[40:56]
the installation of formwork and Rebar
[40:58]
at the hypochlorite and ferric tanks, and leak
[41:02]
testing of the chemical tank containment area walls.
[41:07]
The team is now working on the installation of the 48 inch
[41:10]
piping at an existing connection and new filter 16
[41:15]
through 18, load transfer platform, and conduit
[41:19]
installation from the dry chemical building
[41:21]
to the electrical building.
[41:23]
Now, the top right picture shows the chemical tank containment
[41:27]
wall Rebar installation, and the main picture
[41:33]
shows the final product and leak test for this new chemical tank
[41:37]
containment area.
[41:38]
Overall, the surface water treatment plant project
[41:41]
is progressing well and remains on track.
[41:44]
Construction work is currently at 10% of work completed,
[41:48]
and spending is aligned at 20% of the total $167 million
[41:54]
budget.
[41:56]
As construction activities increase,
[41:58]
our effort will continue to be on maintaining
[42:02]
alignment between progress, spending, and schedule
[42:05]
performance.
[42:06]
At this stage, we have not identified any need
[42:09]
to use our owner's allowances.
[42:14]
Now I will proceed with an update on our distribution
[42:18]
system expansion project, the South Hillsborough pipeline.
[42:25]
Lisset Hanewicz: Before you proceed,
[42:27]
I have Commissioner Wostal.
[42:29]
You want to wait till the end?
[42:33]
Okay.
[42:34]
>> This pipeline will carry water from our surface water
[42:34]
treatment plant at the Regional Facilities site to Hillsborough
[42:38]
County to meet the county's water needs.
[42:43]
You will recall, from previous presentations,
[42:46]
that we have identified 17 tunnel locations that
[42:50]
were strategically planned to minimize traffic disruptions
[42:54]
and reduce environmental impacts during construction, as well.
[43:00]
Those are shown in the orange diamonds
[43:03]
across the entire route.
[43:05]
Since our last update, we have added
[43:08]
two additional red circles, which
[43:10]
show the locations where tunneling work has
[43:13]
been completed.
[43:14]
A total of six locations have been completed.
[43:17]
Now, here is another look at the route,
[43:21]
showing all the locations under construction for both segments A
[43:27]
and B. These sites include micro tunnels, open trench
[43:34]
installation.
[43:35]
Over the past month, the project team
[43:38]
has worked really hard to prepare
[43:41]
for back to school traffic near construction zones.
[43:44]
Numerous coordination meetings were
[43:46]
held with Hillsborough County Public Schools, transportation,
[43:50]
and safety departments, and Hillsborough County Sheriff's
[43:53]
Office was represented in some of these meetings.
[43:57]
There was also close coordination
[43:59]
with Brandon High School, Kingswood Elementary,
[44:02]
Boyette Springs Elementary, Valrico Academy,
[44:08]
Bell Creek Academy, and Saint Stephen's Catholic.
[44:12]
Before the school started, the team
[44:15]
created and printed fliers for six different schools'
[44:19]
back to back nights and created social media graphics
[44:22]
for schools to post on their websites or social media
[44:26]
channels.
[44:27]
And we are happy to report that construction, despite all
[44:31]
the weather-related challenges, at Brandon High
[44:36]
School has been completed.
[44:37]
The east and west parking lots were
[44:39]
accessible before the start of the school year.
[44:41]
And to make up time and minimize impacts at Kingswood Elementary
[44:45]
School, the contractor had two crews working, one day crew
[44:52]
and one night crew, to complete the installation
[44:55]
as soon as possible.
[44:56]
This morning, I got the text message
[44:58]
saying that all work is complete.
[44:59]
So this is excellent news for the project
[45:01]
and the parents in that area.
[45:04]
Moving on, crews also are making progress in other locations.
[45:11]
In the image on the left shows installation of the carrier pipe
[45:15]
for the Lakewood Micro Tunnel.
[45:18]
The pipe has been installed, and crews
[45:21]
are working to backfill the tunnel so that the roads reopen
[45:26]
within the next two weeks.
[45:28]
The image on the right is a drone view
[45:33]
of the Little FishHawk horizontal directional drill.
[45:39]
Completion of the horizontal directional drill
[45:41]
marked a significant milestone, as
[45:44]
both horizontal directional drilling
[45:47]
crossings for the project are now complete.
[45:50]
The remaining trenches work consists
[45:54]
of microtunnel installations.
[45:59]
Beyond the outreach to local schools,
[46:00]
the public engagement team has created a video reel
[46:06]
on the horizontal directional drill which received about
[46:10]
158,000 views across all platforms through July.
[46:14]
We also created one on the process that received about
[46:20]
43,000 views and ones on the bentonite slurry used
[46:24]
for the pool that received about 81,000 total views.
[46:27]
The team is also coordinating efforts
[46:30]
with two tours for Hillsborough County staff
[46:33]
and a presentation to the Brandon Rotary Club.
[46:39]
Overall calm at this project is progressing well
[46:41]
and remains on track.
[46:42]
Construction is about 8% completed,
[46:46]
based on the number of linear feet of pipe installed.
[46:50]
And construction spending is aligned
[46:52]
at 20% of the total $461.2 million
[46:57]
construction budget, which includes construction
[47:00]
costs, engineering services during construction,
[47:04]
and support.
[47:07]
At this stage, we have not identified any correction
[47:09]
actions for schedule and budget.
[47:11]
And this concludes my presentation.
[47:13]
I will be happy to answer any questions.
[47:19]
Lisset Hanewicz: Commissioner Wostal?
[47:24]
Joshua Wostal: Thank you.
[47:24]
My comments are particularly about the pipeline, not
[47:25]
the water treatment plant.
[47:27]
I know that you guys have done significant outreach,
[47:30]
and I understand that, in general,
[47:34]
the public would like their water to just magically come
[47:37]
from the faucet, and they don't want
[47:39]
to see the construction that goes along with it.
[47:41]
I met a nice young British woman,
[47:47]
about 76, who stopped short of calling me the devil
[47:51]
the other day, after acknowledging that I didn't even
[47:53]
vote for this because it was done before I was elected.
[47:56]
Factually, I would not have voted
[47:59]
for this route had I been on the board at this time,
[48:01]
or voted for the other one.
[48:03]
The school images that we get are just --
[48:08]
kind of negate all of the work that we have done to notify
[48:12]
the public.
[48:13]
You can't force people to be engaged,
[48:15]
but we have got to do something more,
[48:18]
whether if it is coordinating with Hillsborough County's sign
[48:24]
Department that sticks the rezone signs everywhere --
[48:27]
perhaps they can, way ahead of time,
[48:32]
view scheduling construction, particularly near intersections
[48:34]
and schools, that we are posting signs saying, hey,
[48:41]
expect delays, explore alternative routes,
[48:44]
whatever it is.
[48:46]
We have got to find something to notify the public.
[48:50]
I mean, I think that it was a poor idea to not do the more
[48:57]
rural areas during the --
[49:00]
or the more active areas during the summer
[49:02]
and the more rural areas during the school season.
[49:05]
Whatever can be done, whether if it
[49:09]
was from Hillsborough County's water department,
[49:11]
just helping notifying the public better,
[49:14]
I think the general public would really appreciate it.
[49:17]
I mean, they don't want to hear that we did something
[49:20]
at the rotary.
[49:21]
You can't force people to be engaged.
[49:23]
But they are just going to blame no matter what.
[49:28]
Whatever we are doing right now doesn't seem to be working.
[49:30]
158,000 views on Facebook might be nice,
[49:35]
but I don't think that that's educating the actual residents
[49:39]
that are going to see a disruption.
[49:41]
Anything that can be done, I would appreciate it.
[49:44]
I believe that this constituent was actually the one that came
[49:49]
-- she said sometime last year with her daughter.
[49:53]
Anything that we can do, I would appreciate it.
[49:57]
Thank you.
[50:01]
Lisset Hanewicz: I don't see any other comments.
[50:03]
Commissioner Wostal, it's horrible to inherit a vote ,
[50:09]
and you are not happy with the boat.
[50:12]
I know I wasn't for this item because I
[50:13]
thought some of this stuff was going to happen.
[50:15]
But in any event, I think our team
[50:17]
is trying to do the best they can
[50:19]
with getting the communications out.
[50:20]
If we can do more work, that would be great,
[50:24]
to let parents and schools know.
[50:28]
I will tell you, no one likes car lines,
[50:32]
and no one likes traffic getting to car lines.
[50:38]
Yeah, any work on this could be appreciated
[50:40]
so we could get the word out.
[50:42]
I do agree, the posts getting the views just shows people
[50:44]
are interested in the issue.
[50:46]
They probably need more communication.
[50:48]
Okay, I don't see any other requests to speak.
[50:52]
Do we have any other items, administrative matters
[50:58]
that any board member wants to address?
[51:00]
I don't see any requests to speak on that.
[51:03]
That means that we have reached receive and file, which requires
[51:08]
a motion to receive and file.
[51:10]
I have a motion by Commissioner Wostal and a second
[51:20]
by Commissioner Cohen.
[51:26]
>> Motion passes unanimously.
[51:28]
Lisset Hanewicz: Thank you.
[51:29]
We have come to the end of our board meeting,
[51:31]
I think, in record time.
[51:34]
We have an October scheduled meeting that is one
[51:36]
of the meetings that we can decide to go forward or not --
[51:40]
I'm sorry, September.
[51:42]
I'm looking at October --
[51:43]
September meeting.
[51:44]
I'm going to fast.
[51:45]
We may look to see if maybe we don't have a September
[51:48]
meeting, depending on what is on the agenda.
[51:50]
I just wanted to let the board members know about that.
[51:53]
With no other request to speak, this meeting is adjourned.
[51:55]
Thank you, all.