Transcript
SOURCE TRANSCRIPT
This transcript is downloaded from the source you provided but we haven't reviewed it for accuracy. Treat it as a starting point, not a verbatim record. You can also request an AI-transcription of the audio file with the button to the left.
These are YouTube's auto-generated captions, not a human transcript — expect occasional errors, especially with names and technical terms.
[0:00]
Council
[0:02]
member Kercher
[0:03]
>> here.
[0:04]
>> Council member Ding
[0:05]
>> here.
[0:06]
>> Council member Salter
[0:08]
>> here. Can you hear me? Okay.
[0:10]
>> Yes.
[0:11]
Can you state your location? Um if
[0:14]
the agenda has been posted and if there
[0:16]
is anybody in the room with you.
[0:18]
>> I'm I'm participating via Zoom from One
[0:21]
Market in San Francisco. The agenda has
[0:24]
been posted and there's nobody in the
[0:26]
room.
[0:28]
>> Thank you. Thank you.
[0:31]
>> Um, has the agenda been posted?
[0:34]
>> Yes, mayor.
[0:34]
>> Any changes to the agenda?
[0:38]
>> Not for me.
[0:39]
>> Um, so what I'd like to do is um
[0:45]
instead of taking public comment right
[0:47]
now, I would like to um go through the
[0:51]
agenda items and then take public
[0:53]
comment um and then we'll bring it back
[0:55]
for discussion at the end.
[0:58]
>> [clears throat]
[0:58]
>> Um and I will allow additional time for
[1:02]
certain members of the public to the
[1:04]
extent that they need additional time.
[1:07]
Okay.
[1:09]
Um, so I called this uh meeting, special
[1:14]
meeting um, Monday morning and it was
[1:17]
based on a meeting that Elizabeth
[1:20]
Robbins and I had with the citizens
[1:23]
advisory committee on Friday morning um,
[1:27]
June 19. and they expressed concern to
[1:30]
us that the momentum and focus of the
[1:34]
CAC plan that they proposed on April
[1:38]
29th was being lost and their the focus
[1:43]
um was to embrace the CAC plan, hire an
[1:46]
architect and start designing right
[1:48]
away. um to them there is no need to
[1:51]
update the facility's master plan.
[1:53]
Various planning and design elements,
[1:55]
driveways, elevation of the bays, police
[1:58]
car parking,
[1:59]
etc. can be worked out by the architect.
[2:02]
Um they also um told us that there's no
[2:06]
need to determine a procurement method,
[2:08]
design, bid, build or design
[2:12]
prior to hiring an architect. They're
[2:14]
very concerned that delays and a shifted
[2:17]
focus from implementing the CAC plan to
[2:20]
updating the facilities master plan is
[2:22]
hurting the support and the momentum for
[2:24]
the CAC plan. And they're concerned that
[2:28]
this this will make it harder to pass a
[2:30]
bond measure to fund the CAC plan when
[2:33]
that happens, probably hopefully March
[2:36]
of 2027.
[2:38]
So, their direction to Elizabeth and me
[2:42]
um on Friday was hire an architect as
[2:45]
soon as possible based on subcommittee
[2:47]
recommendation.
[2:49]
Don't update the facilities master plan.
[2:52]
Resend the RFPs that are currently
[2:54]
outstanding to update the facil's master
[2:57]
plan.
[2:59]
Delay deciding on a procurement process
[3:01]
for now and direct the staff to work
[3:04]
with the CAC.
[3:06]
Um, I felt obligated to bring those
[3:09]
concerns back to the entire council. I
[3:12]
am only one person on the town council.
[3:15]
I'm 20% of the town council. Being mayor
[3:18]
in the town of Ross
[3:20]
means that I just need to be really on
[3:22]
time for our meetings. That's about it.
[3:24]
So, I wanted to share with the council
[3:27]
and with staff um the concerns that the
[3:30]
CAC raised um and we can have a
[3:34]
discussion and figure out how we can go
[3:37]
forward from here. Elizabeth, do you
[3:40]
have anything to add? Well, yes, just
[3:42]
one other thing which is with respect to um the delay um there this really is
[3:48]
timesensitive because we want to be sure
[3:50]
that we can complete the paramedic um um
[3:53]
the paramedic facility before the
[3:55]
deadline of January 2029 and that that
[3:58]
is being jeopardized also. So besides
[4:01]
the reasons you mentioned Julie, this
[4:02]
was the other concern of the CAC that we
[4:05]
weren't moving fast enough to meet that
[4:07]
obligation.
[4:09]
>> Yeah. Thank you. Um, so, um, Town
[4:13]
Manager Johnson, you wrote an excellent
[4:16]
staff report that we received very late
[4:19]
last night. Um, thank you.
[4:21]
>> Um, maybe you could briefly address some
[4:24]
of the concerns that you raised in your
[4:26]
staff report um, briefly because I think
[4:30]
most of us have seen it.
[4:32]
>> Um, that would be really helpful.
[4:33]
>> Great. Thank you. Uh, good afternoon,
[4:35]
mayor and council members. Uh the
[4:38]
purpose as I understand it of today's
[4:39]
discussion is um not to revisit the
[4:42]
council's discussion to identify the CAC
[4:45]
concept as the preferred alternative for
[4:47]
the civic center project. That decision
[4:50]
was made on May 6 when the council
[4:52]
adopted resolution number 2623.
[4:55]
The council has already selected the CAC
[4:59]
concept as its preferred design uh
[5:02]
concept. This is not a debate about
[5:05]
concept B.
[5:07]
versus the CAC concept. The request for
[5:10]
proposals, what we call an RFP, for plan
[5:14]
amendment services is intended to
[5:16]
implement the CAC design concept. It is
[5:21]
not intended to replace it or delay it,
[5:24]
but to implement it.
[5:26]
So the question before the council today
[5:29]
is is a different one and that is how
[5:32]
should the town proceed with the
[5:34]
implementation of the council's preserve
[5:37]
preferred concept which is the CI CAC
[5:40]
concept.
[5:42]
staff evaluated the demands made by CAC
[5:45]
and FORF and prepared the staff report
[5:48]
sent LA late last night uh to the
[5:51]
council um and then posted online this
[5:54]
morning outlining two potential paths
[5:57]
forward. The first option is to continue
[6:00]
with the facility master plan amendment
[6:03]
and concept validation process
[6:05]
authorized by the town council on June
[6:07]
11th. The second option is to terminate
[6:11]
that current RFP process and proceed
[6:14]
directly into negotiations with a single
[6:18]
architectural firm. After careful and
[6:21]
detailed review, I strongly recommend
[6:24]
that the council continue with option
[6:26]
one. Option one is based on sound
[6:30]
project management, fiscal stewardship,
[6:33]
procurement integrity, and risk
[6:36]
reduction. It is not based on opposition
[6:39]
to the CAC pro concept. Again, the
[6:43]
council chose it. That's what we're
[6:45]
doing. In fact, the current RFP process
[6:49]
is intended to substantially advance
[6:52]
that CAC concept, not to replace it, to
[6:56]
advance it.
[6:58]
The purpose of the facilities master
[7:00]
plan amendment process is to refine and
[7:03]
validate the council's preferred
[7:06]
concept. Resolve the outstanding
[7:10]
technical and operational issues which
[7:12]
are outlined in the agenda report.
[7:15]
Develop reliable cost information and
[7:19]
establish a sound foundation for future
[7:22]
design, financing, and implementing
[7:25]
decisions.
[7:27]
Several significant project issues
[7:29]
remain unresolved. These include future
[7:34]
fire service planning, police
[7:37]
operational requirements,
[7:39]
public works needs,
[7:42]
site circulation and parking,
[7:46]
flood plane compliance,
[7:49]
historic preservation requirements,
[7:52]
project phasing, cost validation,
[7:57]
financing strategy, and project
[8:00]
delivery. methodology.
[8:03]
These issues directly affect project
[8:06]
scope, cost, and feasibility.
[8:10]
These significant project issues must be
[8:13]
addressed and resolved before the town
[8:16]
commits to a long-term
[8:18]
multi-million dollar architectural
[8:21]
services agreement. One of the key
[8:24]
reasons for recommending op option one
[8:26]
is that it preserves the integrity of
[8:29]
the competitive procurement process
[8:32]
that is currently underway. The town
[8:35]
council authorized the RFP on June 11th.
[8:39]
10 highly qualified firms have been
[8:41]
invited to participate and proposals are
[8:44]
due on July 2nd. That is 8 days from
[8:48]
now.
[8:50]
Allowing that process to proceed
[8:53]
provides the town with independent
[8:55]
professional perspectives, competitive
[8:58]
pricing, and valuable information
[9:00]
regarding project scope, methodology,
[9:03]
and cost. By contrast, option two would
[9:08]
require the town to terminate to
[9:10]
terminate an active procurement process
[9:14]
and negotiate directly with a single
[9:16]
architect before many of the fundamental
[9:19]
project assumptions have been resolved.
[9:22]
At this time, the town does not yet have
[9:25]
a validated project scope,
[9:28]
a construction budget, an implementation
[9:32]
strategy, or policy direction on several
[9:36]
key issues, including future fire
[9:38]
service planning. As a result, staff
[9:42]
would be negotiating architectural
[9:44]
services without first establishing the
[9:47]
critical information necessary to effect
[9:50]
effectively evaluate scope, fees,
[9:54]
overall value.
[9:57]
Staff is also concerned that unresolved
[9:59]
project issues would continue to evolve
[10:03]
during design, increasing the likelihood
[10:06]
of expensive contract amendments with
[10:09]
the architect, redesign efforts, cost
[10:13]
increases, and schedule impacts.
[10:16]
Another important consideration is
[10:18]
future financing. If the town ultimately
[10:22]
pursues a general obligation bond or
[10:25]
another financing strategy, it is
[10:27]
important that voters and decision
[10:29]
makers have access to a clearly defined
[10:32]
project scope, reliable cost estimates,
[10:36]
and a realistic implementation plan.
[10:40]
Completing the master plan amendment and
[10:42]
concept validation process will help
[10:44]
provide this information.
[10:47]
I would also like to emphasize that
[10:49]
continuing the current process is not
[10:52]
expected to create a lengthy delay and
[10:55]
may in fact save time. Based on the
[10:58]
current schedule, staff estimates that
[11:00]
the amendment and validation effort can
[11:02]
be completed with approximately four
[11:04]
months and enable the council to weigh
[11:06]
in on a potential
[11:09]
funding measure.
[11:11]
This work can position the town to begin
[11:14]
financing evaluations in late 2026 and
[11:17]
early 2027 while substantially reducing
[11:20]
project risk.
[11:23]
Incling
[11:26]
staff's recommendation is
[11:27]
straightforward.
[11:29]
The council has already selected its
[11:32]
preferred concept and now the town
[11:35]
should take the time necessary to
[11:37]
validate that concept. Confirm project
[11:40]
requirements, establish reliable costs,
[11:43]
evaluate financing options, and develop
[11:46]
a clear implementation strategy before
[11:49]
entering into a long-term
[11:52]
architectural design agreement. For
[11:55]
these reasons, I recommend that the
[11:56]
council maintain its current direction,
[11:59]
allow the facility master plan amendment
[12:02]
RFP process to continue. Remember,
[12:05]
proposal is due in 8 days and continue
[12:08]
implementation of the CAC concept
[12:10]
through the structured planning process.
[12:12]
It's already been authorized by the
[12:14]
council.
[12:16]
Thank you for the opportunity.
[12:20]
» Ben, would it be okay if people have if
[12:22]
council members have questions of
[12:24]
Christa to ask them now?
[12:26]
>> Questions, council members?
[12:29]
You know, I just have one um it's
[12:32]
there's a question about the wording. Um
[12:35]
the the beginning of the staff report uh
[12:38]
said that the the that the meeting um on
[12:42]
June 19 um
[12:45]
the meeting today to discuss demands
[12:47]
made by the CAC and friends of the Ross
[12:50]
Firehouse to the mayor and mayor prom on
[12:53]
June 19. It there weren't demands. It
[12:55]
was it was it wasn't forth. It was the
[12:58]
citizens advisory committee that asked
[13:01]
to meet with Julie and me as members of
[13:03]
the the architecture procurement
[13:06]
committee, whatever we call ourselves.
[13:08]
Um and um that and there were
[13:11]
recommendations made at that meeting
[13:13]
discussed amongst everyone. There were
[13:16]
no demands. So really this meeting today
[13:19]
is to discuss the recommendations that
[13:22]
the CAC shared with the mayor and mayor
[13:25]
prom on June 19.
[13:28]
I'm sorry. Is that a question for me or
[13:31]
>> you know I realize I mean the question
[13:32]
was why why is it worded that way? But I
[13:34]
it's it's really I it's okay. I mean
[13:38]
it's not really a question. It's more of
[13:39]
a a reflection.
[13:43]
Mhm.
[13:44]
>> Uh Christa,
[13:47]
are there ways that you could speed up
[13:50]
the process a bit or do things
[13:54]
simultaneously, several things at the
[13:56]
same time
[13:57]
>> as opposed to A, B, C, D, A and B
[14:00]
together, C and D together. some way to
[14:03]
just short speed up the time frame
[14:07]
>> so that instead of having uh a report
[14:11]
available in what November, it might be
[14:14]
available in
[14:16]
end of August, October.
[14:19]
>> Um thank you for the question. Um this
[14:22]
process actually usually takes over a
[14:25]
year. So 4 months is really is uh is
[14:30]
already moving quickly especially
[14:32]
because the CAC
[14:35]
concept
[14:37]
includes
[14:40]
reusing or um an existing trying to
[14:44]
reuse an existing building which is
[14:46]
going to require
[14:49]
um studies and such as hazardous
[14:52]
materials you know really digging in.
[14:54]
Whereas if you didn't have to do that,
[14:57]
you wouldn't we that would save time
[14:59]
right there. So there and there are a
[15:02]
lot of policy issues that the council we
[15:06]
need direction from the council on. So,
[15:08]
I think if the council were to agree to
[15:12]
um you know, setting up a meeting
[15:15]
schedule every two weeks, I recall uh
[15:18]
when I first started working here, um
[15:20]
there was a lot going on with the
[15:22]
Branson school conditional use permit
[15:24]
amendment process and I believe
[15:26]
Elizabeth Robbins was mayor at the time
[15:28]
and and she had a good idea which was to
[15:30]
schedule these she knew there were going
[15:32]
to require special meetings. So, she set
[15:34]
out, let's let's let's put these meeting
[15:37]
dates in place, and if we don't need
[15:38]
them, we can always cancel it. I think
[15:41]
that would be a good place to start. Um so that with the architect on board
[15:48]
and we can get the council and of course
[15:51]
the community input at the meetings and
[15:54]
I think that would be a good place to
[15:55]
start. Um there is already, you know,
[15:59]
the the architect is certainly an
[16:01]
incredibly important part of this
[16:02]
process, but there are other things that
[16:05]
we need to be moving along on. It's it's
[16:08]
the um it's the the trying to figure out
[16:11]
how we're going to finance and like that
[16:12]
is not ending our um our negotiations
[16:17]
working with a affordable housing
[16:19]
partner that moves forward. the
[16:22]
communication the the work with the
[16:23]
telecommunications to come up with the
[16:25]
lease agreement, the discussions ongoing
[16:28]
discussions with the paramedic
[16:29]
authority. There are all different um
[16:32]
parts of this process that are moving
[16:35]
along and that are necessary to keep
[16:37]
moving forward with um
[16:41]
as we get council
[16:45]
policy direction on some of these really
[16:47]
key things that is going to help us. We
[16:51]
need to be developing an RFP for the big
[16:54]
architect contract, right? So, we don't
[16:57]
want to have to wait until the very end
[16:59]
when the council actually adopts the
[17:02]
amendment.
[17:03]
Once we have the council direction on
[17:07]
some of these big policy issues, we can
[17:09]
be in the meantime working on that. So,
[17:12]
it can, you know, it can start right
[17:14]
away. So, I would be working with our part-time project manager, David
[17:20]
Kelly, and our owner's representative,
[17:23]
his name is um Dustin Alamo with Griffin
[17:26]
Structures to who has extensive
[17:29]
experience working on these kinds of
[17:30]
public process to projects to move
[17:33]
things forward as quickly we can. I
[17:35]
mean, I certainly hear that and we all I
[17:38]
mean, as from the employee perspective,
[17:41]
we all want to have a new a new place to
[17:44]
work and we definitely want the
[17:46]
paramedics to have a home to go into as
[17:48]
is our contractual obligation.
[17:51]
So, um, that is our intent. That's what
[17:55]
we we would be doing. But I I have to I
[17:57]
I'm not going to be able to just to say,
[17:59]
"Yeah, we're going to get it done with a
[18:00]
month just to I I need to be
[18:02]
straightforward with you that this is a
[18:04]
public this is a process. It's it's
[18:07]
going to take time and things are going
[18:08]
to come up that need to be dealt with.
[18:11]
But if we have the council prepared to
[18:14]
give us that feedback and allow that
[18:17]
formal process for um community input
[18:20]
that council meetings allow for
[18:23]
that's going to help us tremendously. So
[18:26]
you're saying that one of the ways to
[18:28]
speed up this process maybe for because
[18:31]
you're talking about making policy
[18:32]
decisions that affect the moving
[18:35]
>> right
[18:35]
>> is for us to meet more frequently. Is
[18:37]
that a lot of work on your staff to
[18:39]
prepare for multiple council meetings in
[18:41]
a month
[18:43]
>> in addition to what you're already
[18:44]
doing?
[18:45]
>> Yeah, I mean certainly our our town
[18:46]
clerk and and our staff have to put
[18:48]
together the meeting. It's it's more
[18:50]
about um you know preparing the agenda
[18:54]
items and working with the town
[18:55]
attorney's office on any items that
[18:57]
require his review. But you know my
[19:00]
entire career I've worked for councils
[19:02]
that work twice a that that meet twice a
[19:04]
month or more. So, um I think it really
[19:08]
the hardest part is uh one of the
[19:11]
hardest part is scheduling the meetings.
[19:13]
Hardest it's tangible, but the council
[19:17]
you're busy. You have other boards and
[19:18]
commissions. The town attorney is busy.
[19:20]
He has other clients. They're it's hard
[19:22]
getting everybody together. But if we do
[19:25]
as Elizabeth Robbins did four years ago
[19:27]
and set up a series of meetings and if
[19:30]
we don't need them council them I think
[19:33]
that's a good a good way to start. So so
[19:36]
on the opposite side so if we don't meet
[19:38]
as frequently then the council is
[19:41]
holding up the process.
[19:44]
>> Yeah. I mean that's certainly part it's
[19:45]
part of it. Yeah.
[19:47]
>> Okay. Thanks.
[19:54]
» Assuming we were to go with what is it
[19:56]
option one which is the what we left the
[19:59]
last meeting with
[20:01]
and we go through this initial phase.
[20:04]
What do we end up with by ideally
[20:07]
December? What do we have? How detailed
[20:09]
is that plan? It probably going to show
[20:12]
us where buildings are and so forth.
[20:14]
Will it include a floor plan? Well, or
[20:17]
does that all then go over to the
[20:19]
architectural firm? Do you know
[20:23]
>> what do you mean by to the architectural
[20:25]
firm? The architect would be working on
[20:26]
it.
[20:27]
>> You know,
[20:29]
we we we're throwing all these terms
[20:30]
around and perhaps I I have a
[20:32]
misunderstanding based on those terms,
[20:34]
but based on my experience, you start
[20:36]
out with an idea
[20:37]
>> and then if you have a lot of expertise,
[20:40]
which my firm does, we have people who
[20:42]
do construction on our staff or we used
[20:44]
to,
[20:44]
>> we do a lot of that. Then we go to the
[20:47]
architects and say, "Okay, give us the
[20:48]
plants or tell us what's wrong with
[20:51]
this." And then we go ahead. Now, here
[20:55]
we don't have that kind of in-house
[20:57]
expertise. So, we're looking for some
[20:59]
firm outside to help us, an
[21:01]
architectural firm or another firm. When
[21:03]
we did the original site plan, we did
[21:06]
not start with an architectural firm. We
[21:08]
started with a firm that could help us
[21:09]
think this through and give us a lot of
[21:12]
alternatives. But what we ended up was with was pretty general. It didn't
[21:17]
include detailed plans, but it didn't
[21:20]
take into account what our needs were
[21:22]
space-wise.
[21:24]
>> Are you talking about the the
[21:26]
>> Okay. Well, that actually was done by an
[21:29]
architect firm. Was it?
[21:30]
>> KPA is an architect firm and they're
[21:32]
actually
[21:33]
>> Yeah. Okay.
[21:33]
>> Um but that is a planning document.
[21:36]
>> Yeah.
[21:36]
>> Not construction documents.
[21:38]
>> Yes. And so what I'd like to do is um we
[21:41]
do have David Kelly, our part-time
[21:43]
project manager, is available and I'd
[21:44]
like him to chime in because I don't
[21:46]
want to give you the wrong information.
[21:47]
Is that okay?
[21:49]
>> Yeah,
[21:49]
>> he's right here.
[21:55]
[clears throat]
[21:55]
>> Just
[21:55]
>> I mean, and I don't mean to de labor
[21:57]
bel. I'm just trying to get a clear idea
[21:59]
of how we can move this ahead
[22:02]
>> and whether there's not some duplication
[22:04]
of effort here.
[22:05]
>> Okay. uh particularly if we have two
[22:07]
different firms doing this, we start off
[22:09]
with one firm and then we go to a
[22:10]
different firm for the detailed
[22:11]
drawings. Uh and that I think could
[22:14]
result in delay and more expense.
[22:16]
>> Yeah. And I I at this stage in the
[22:19]
process I I kind of highly doubt that it
[22:21]
would be I mean of course it's always
[22:23]
ultimately up it's up to the council
[22:25]
>> but I think it it would be I think
[22:28]
having a different architect firm come
[22:29]
in and do this to do the other part
[22:31]
would you know they that there's a lot
[22:34]
of work that's already that would have
[22:36]
already been done. So, um
[22:40]
I I I think that would be as we're
[22:43]
looking at um firms that would be a
[22:46]
little more that would be challenging to
[22:48]
have two different firms,
[22:50]
>> but let me
[22:51]
>> Yeah, I I I know we we were starting
[22:52]
from scratch when we did the the
[22:54]
previous thing. We're not starting from
[22:56]
scratch here.
[22:56]
>> Exactly. We're pretty far along
[22:58]
>> and I'm just wondering, do we really
[23:01]
need two FA phases? But sure, if David
[23:03]
has a perspective.
[23:03]
>> Sure. Let me ask uh David is are you on
[23:05]
now? Oh, hi David.
[23:07]
I am Christa. Thank you. Can Can the
[23:09]
council hear me? Okay.
[23:10]
>> Did you hear council member Kercher's uh
[23:13]
question?
[23:13]
>> Yes, I did.
[23:14]
>> Okay.
[23:15]
>> And to rephrase the question, I think
[23:18]
council member, you're asking whether
[23:20]
through the update of the master plan,
[23:23]
you would have or the council would have
[23:27]
uh floor plans.
[23:29]
And uh the answer is not necessarily.
[23:33]
Um, but what you would have is an
[23:35]
advancement of the CAC concept
[23:39]
identifying more specifically
[23:42]
the the square footages that have been
[23:46]
validated for each of the respective
[23:48]
uses uh provided for in the in the civic
[23:52]
center.
[23:53]
um you really get into floor planning
[23:55]
when you get into schematic design and and really
[24:00]
beyond that when you start doing you
[24:02]
know layouts of uh equipment and so
[24:05]
forth. So you you you probably wouldn't
[24:08]
have with the master plan amendment uh
[24:12]
the level of of floor planning that I
[24:13]
think you're you're asking about. Um,
[24:16]
one additional consideration just to
[24:18]
mention is that council is going to uh
[24:22]
consider
[24:24]
uh alternative project or procurement
[24:26]
delivery methods which is going to
[24:29]
include the um one one of those options
[24:33]
for council's consideration is going to
[24:34]
be the progressive design build process
[24:36]
which is being implemented more widely
[24:39]
by a number of local cities in in Marin
[24:43]
County. And in that case, both the
[24:46]
contractor and architected are are
[24:48]
selected together as the design team to
[24:51]
move the project forward. And and there
[24:54]
is some uh opportunities for uh
[24:58]
initiating that process while we're
[25:00]
completing the master plan. Um, and you
[25:03]
know that that obviously there's there's
[25:05]
some work to do uh to implement that
[25:08]
process and and I don't want to assume
[25:10]
that council is ultimately going to
[25:12]
support that but that that would be and and is one of the key reasons why uh
[25:19]
town managers is recommending strongly
[25:21]
option one is because it if you go with
[25:25]
option two it kind of precludes
[25:27]
alternative procurement methods which we
[25:30]
think uh if council does decide to move
[25:33]
in that direction that it's going to
[25:35]
save time uh on the back end. And in
[25:38]
addition to time, reduce risk for the
[25:41]
town because you'll be uh basing the the project on uh cost on a guaranteed
[25:49]
maximum price uh and putting a lot of
[25:51]
the risk on the builder design team
[25:54]
going forward. So that that's just
[25:57]
something to add to to uh Chris's
[26:00]
perspective. The the other element to
[26:02]
consider with respect to saving time
[26:05]
that staff can be working on during the
[26:08]
master plan update is really refining
[26:12]
the project description. And and the
[26:14]
reason I mention that is because the
[26:16]
project description is is really a
[26:18]
critical element of moving forward with
[26:21]
the SQA environmental document. Um and that and that's where there's some
[26:26]
risk if if you do move forward with
[26:28]
schematic design. uh as and if things
[26:31]
change. Of course, we we don't have a
[26:33]
detailed project description. Now, uh it would be ideal to develop that and
[26:38]
then uh concurrently start working on
[26:42]
the environmental review process and
[26:44]
there are probably a number of special
[26:46]
studies that will be necessary to
[26:48]
undertake to to move that move that
[26:50]
process forward. That again is an effort
[26:53]
kind of to uh the earlier question about
[26:57]
uh saving time that that that could also
[26:59]
um if there's some overlap there that
[27:01]
could save time.
[27:04]
>> Could I ask a follow-up question? U what
[27:07]
if we were to go the design build route?
[27:10]
What do we need to have done before
[27:12]
that? I mean to prepare for that what do we need to make a proposal to a
[27:17]
developer and a architectural firm to do
[27:20]
the design build
[27:22]
>> uh my understanding and this is you know
[27:25]
this is something that's new for
[27:27]
Christrista and I and that's part of
[27:28]
bringing on Griffin Structures who you
[27:30]
know has the expertise in in this field
[27:34]
uh but what we what we really need is a solid project description that will
[27:40]
enable us to uh issue a what's similar
[27:46]
to an RFP to select the both the the
[27:50]
builder and the you know who's going to
[27:52]
be the general the GC or the general
[27:54]
contractor along with the architect and that's where you get um a lot of
[28:01]
value in terms of uh cost savings
[28:04]
because they're they're working out
[28:05]
issues in advance. they're working
[28:07]
together to make sure that the it's a a constructible buildable project
[28:14]
and you're reducing ambiguity from the
[28:17]
design process a as you go forward. Uh
[28:20]
and also because of having a guaranteed
[28:23]
maximum price there there's concurrent
[28:25]
value engineering that's being
[28:27]
undertaken to help save to help save
[28:30]
costs. Um but there there is some
[28:32]
process and that we we're going to be uh
[28:35]
we've already have meetings scheduled
[28:37]
with the town attorney to uh you know
[28:40]
work on bringing forward the
[28:41]
implementation strategy for council and again that's that's uh something we
[28:46]
want to advance and would support uh
[28:50]
option one.
[28:53]
» Matt Matt, do you have any questions?
[28:58]
>> Yes, thank you. Um, the first is just
[29:01]
the the the staff report. Who who told
[29:05]
you that the friends were making
[29:07]
demands?
[29:09]
>> Why is that in the staff report?
[29:10]
>> I I told her that.
[29:13]
>> Okay. Cuz the the meeting was with the
[29:16]
citizens advisory committee. Correct.
[29:20]
>> It it was Matt, but there was a
[29:22]
representative from FO for attending the
[29:24]
meeting as well.
[29:26]
>> Okay. But isn't aren't there two members
[29:28]
of FORF on that committee?
[29:32]
» You know, I don't know, but I don't
[29:34]
think that the material issue for us to
[29:36]
discuss today is FORF or
[29:39]
>> No, it's it's all over the staff report.
[29:41]
So, I'm I'm I'm I want to make sure that
[29:44]
the record is very very clear about what
[29:46]
happened at this meeting, what was said,
[29:49]
and what is what what we're putting in
[29:51]
our staff reports. So, um, if for was
[29:55]
not in attendance and it was not a
[29:57]
fourth meeting, I think that this staff
[29:59]
report needs to be amended. So, I I
[30:02]
would like that to be very clear because
[30:04]
we should not be putting in here that
[30:06]
this council is making decisions based
[30:09]
on demands made of it by a group that
[30:11]
made no demands. So, uh, Christa, that you wrote this report, so that's
[30:17]
why I'm asking you the questions.
[30:20]
>> Yeah. and and um you your comments will
[30:24]
absolutely be reflected from the minutes
[30:26]
of that meeting, but I will not be
[30:27]
amending my staff report.
[30:29]
>> I do want to point out, Matt, that the
[30:31]
agenda does not have the word for in it,
[30:34]
and we're not really here to discuss
[30:36]
forth today. So, let's
[30:39]
>> let's try to focus on the CAC
[30:41]
recommendation and how to
[30:43]
>> reading the staff report.
[30:45]
>> The staff report on this item. This is
[30:48]
the item that we're speaking about and a
[30:50]
staff report that is issued for this
[30:53]
item. Is that not correct?
[30:58]
So then you it says right here that the
[31:01]
council
[31:03]
we we in respon that the there was a
[31:06]
promise made by the fourth that was not
[31:09]
being honored.
[31:12]
>> What what does that have to do with with anything?
[31:16]
So, um, Council Member Salter, when we
[31:20]
write staff reports for agenda items,
[31:26]
we
[31:28]
almost always include information about
[31:31]
why the item is on the agenda,
[31:35]
why this is being brought forward to the
[31:37]
council,
[31:39]
what the action is.
[31:42]
Little bit of history, a little bit of
[31:43]
context,
[31:45]
options,
[31:46]
alternatives, financial impact.
[31:51]
This is the information that I was
[31:53]
provided as to why we needed to have a
[31:56]
special meeting.
[31:59]
I had
[32:02]
very very short amount of time to write
[32:04]
my staff report.
[32:06]
I did ask if there was a letter from
[32:09]
FORF that I can include. The mayor told
[32:12]
me there was not.
[32:14]
And this is what this is my staff
[32:16]
report. Your the minutes will reflect
[32:18]
your comments.
[32:20]
Um
[32:23]
but this is an 11page staff report. So
[32:28]
um
[32:31]
I don't know what else I can say to
[32:32]
answer to your question. So,
[32:34]
>> well, I you know, I'm I'm troubled too
[32:37]
as well, Christa. You know, my time is
[32:39]
being taken and all of our time by this
[32:41]
emergency meeting being called. So, I
[32:44]
I'm surprised and the council only met
[32:47]
less than two weeks ago and already made
[32:50]
their direction clear. So, I am
[32:52]
surprised this emergency meeting was
[32:54]
being called and all of our time is
[32:57]
being wasted. So, I want to make sure
[32:58]
that we understand why we're all being
[33:00]
called together to look at this again.
[33:02]
And I'm very troubled by the
[33:05]
characterization
[33:06]
that there is this other group that was
[33:08]
not at this meeting making demands. And
[33:11]
I don't think that that's fair to
[33:12]
anyone. The second thing in here is that
[33:14]
it's pointing to the fact that we as a
[33:17]
council adopted a resolution based on
[33:20]
this promise, which I also do not
[33:22]
believe is true um at all. I think that
[33:26]
the the citizens group came forward with
[33:28]
a beautiful plan that everybody liked.
[33:29]
it had nothing to do with this quote
[33:31]
unquote promise. So before issuing
[33:36]
reports, I think we need to make sure
[33:38]
that we have the facts straight because
[33:40]
these reports will sit forever and it's
[33:43]
very very disconcerting to be called
[33:44]
into an emergency meeting based on facts
[33:47]
that are not true which are actually
[33:49]
just lies
[33:51]
>> and I'm sorry that you were lied to.
[33:53]
>> So I did not call this special meeting.
[33:56]
Um,
[33:58]
this is the staff report for this item.
[34:01]
Um, and
[34:04]
any council member that has comments
[34:07]
about my ability to write staff reports
[34:09]
or what I write in staff reports are
[34:11]
most are absolutely welcome to provide
[34:14]
those comments to me at any time really,
[34:17]
but um, especially during my annual
[34:19]
review.
[34:22]
>> Okay. Well, to be clear, it's not about
[34:24]
your ability to write the staff report,
[34:26]
>> Matt.
[34:27]
>> And I think it's actually
[34:28]
>> Can you ask a question, please, about
[34:30]
what's on the agenda? Let's focus on
[34:32]
that. All right.
[34:34]
>> Okay. So, Christa, I'm curious since the
[34:37]
council met less than two weeks ago and
[34:40]
voted 4 to one to move forward with your
[34:44]
um option, how you feel about this
[34:46]
special meeting being called. I'm not
[34:48]
I'm still not understanding why we're
[34:50]
here.
[34:51]
>> But Matt, I thought Julie made it clear
[34:53]
that that the CAC met with Julie and me,
[34:58]
made some recommendations that we agreed
[35:00]
with and we thought should be shared
[35:02]
with council members so that we could
[35:04]
consider them. I mean, that's why we're
[35:06]
here.
[35:10]
» Again, it was less than two weeks.
[35:12]
>> The municipal code and the Brown Act
[35:14]
allow the mayor to call a special
[35:16]
meeting. It was not up to the town
[35:17]
manager. So, her feelings about it being
[35:19]
called are somewhat irrelevant. So,
[35:21]
let's move on.
[35:23]
>> Okay. So, Chris said, so to be clear,
[35:26]
you're still standing by the original
[35:28]
decision we made two less than two weeks
[35:31]
ago to continue along that path.
[35:36]
» Yes, as stated in my staff report and in
[35:39]
my verbal report that I made at the
[35:42]
beginning of this meeting at 2 PM, which
[35:44]
is I'm calling
[35:47]
Option one.
[35:49]
>> Okay. Thank you. That's it.
[35:50]
>> Yes.
[35:52]
>> So my question Christa is there is there
[35:56]
any way to does the facilities master
[35:58]
plan have to be amended before we can
[36:01]
jump to working on schematics and layout
[36:04]
of floor plans and trying to expedite. I know in a normal situ normal situation
[36:11]
where we had the luxury of time like we
[36:13]
would have you know if we'd started in
[36:16]
2023
[36:17]
um we would have tons of time but
[36:20]
unfortunately the commitment in the
[36:22]
long-term lease with the paramedics
[36:23]
requires us to deliver a paramedic
[36:26]
facility by January of 2029. Um, I'm
[36:30]
just wondering if there's any way to
[36:32]
layer all these steps together so that
[36:34]
we can be moving forward on multiple
[36:37]
fronts. I know you said we're doing the
[36:39]
housing and we're, you know, we're doing
[36:40]
a lot of other things, but in terms of
[36:43]
the most critical thing right now is
[36:46]
getting this cost information for the
[36:48]
December 4th filing to meet the March
[36:51]
2027 general obligation bond. And so I'm
[36:55]
just wondering if there's any way to,
[36:58]
you know, amend the facilities master
[37:00]
plan later, do the work, but not not be,
[37:03]
you know, kind of bureaucratic about it.
[37:06]
Just jump to schematics and and look at
[37:10]
the asbuilts and get the um open up the
[37:14]
building and get the cost estimate to
[37:18]
the best that we can for the general
[37:19]
obligation bond.
[37:24]
So, I I very much understand the
[37:28]
council's interest in moving forward.
[37:31]
Um, and I hope the council recognizes
[37:34]
that
[37:36]
what we've been doing this past year has
[37:39]
um largely been in response to a couple
[37:42]
members of the city council putting
[37:44]
roadblocks in our way. Okay. So it is
[37:50]
part of my responsibility, a big one of
[37:54]
my primary responsibilities
[37:56]
is my fiduciary responsibility to this organization.
[38:02]
At a project cost that is going to be
[38:05]
upwards of $25 million. If it includes a
[38:09]
fire station, you're looking at $10
[38:11]
million more than that.
[38:14]
you. It is my strong recommendation
[38:18]
that you have a facilities master plan
[38:22]
that is accurate that incorporates your
[38:26]
preferred concept which is the CAC plan
[38:32]
and that we're able to price work work
[38:35]
with get an architect agreement that
[38:37]
will be more than $3 million. It will be
[38:41]
more than that if it really if this
[38:42]
truly has a fire station in it.
[38:46]
I need to be able to negotiate an
[38:49]
agreement that um
[38:54]
I will have no leverage
[38:58]
if there is no competitive process. This
[39:02]
is a it you might not and and the town
[39:05]
attorney is welcome to add in with the
[39:09]
professional services agreement. We do
[39:11]
not have to do low bid.
[39:14]
A best practice is and you will see
[39:18]
every city does request for proposals.
[39:21]
That is a best practice. You can look at
[39:23]
the goa website. You can look at the cal
[39:26]
California cities legal of California
[39:28]
cities website. They all say you do
[39:31]
request for proposals. So there is some
[39:33]
element of competition. We can look at
[39:36]
the qualifications. We can look at the
[39:38]
hourly rates. We can look at uh
[39:41]
milestones and how many hours of
[39:43]
architect work and we want to try to
[39:45]
prevent change orders.
[39:48]
Um, if I am asked to go out and
[39:51]
negotiate with one firm, with no
[39:57]
leverage,
[39:59]
it is in effect the council giving out a
[40:02]
blank check. And I know this is not what
[40:05]
you want to hear, but this is the
[40:06]
reality. A blank check. the the um
[40:12]
contract that we currently have the RF
[40:15]
RFP is that what it is that we currently
[40:18]
have pending is based on time and
[40:21]
materials. Correct. No,
[40:23]
>> it's a fixed fee. We are we are going to
[40:25]
be getting fixed fee proposals.
[40:28]
>> Okay. Um
[40:30]
>> and that but that's just for amending
[40:33]
the facilities master plan. It's going
[40:35]
to be teenytiny compared to what this
[40:37]
big project is. And so what's on the
[40:39]
agenda today? If the council wants me to
[40:42]
go in and negotiate a multi-million
[40:45]
dollar agreement with no competition, no
[40:49]
proposals to compare to and then if they
[40:54]
have uh let's say they say uh it's going
[40:57]
to take 500 hours to do something and I
[41:01]
will consult with my experts, right? I'm
[41:04]
not a contractor, but I'm gonna I have
[41:06]
people that are my experts, and they're
[41:08]
going to say, "Wait, it's it's only
[41:11]
going to take them a hundred hours to do
[41:13]
that. It's going to take them half."
[41:17]
What kind of leverage am I going to have
[41:19]
when all they when they're going to be
[41:20]
able to say and I'm not saying it's the
[41:23]
and they're going to be able to say well
[41:25]
the council said they're you know you have you have completely wiped out
[41:30]
my ability to get a competitive
[41:34]
agreement. It could be a fantastic
[41:36]
architect but they're not doing it for
[41:39]
free. And I don't think a single one of
[41:42]
those 10 firms is a nonprofit. So they
[41:45]
want to make money and
[41:49]
doing an RFP is a recognized
[41:54]
best practiced industry standard.
[41:57]
>> But the the
[41:58]
>> you know what I don't understand is um
[42:01]
>> I I want to ask my followup Elizabeth
[42:04]
and then you can go
[42:06]
>> um the the contract that we ultimately
[42:09]
hire for the the big project. I mean,
[42:11]
I'm looking at the little project, which
[42:13]
is what we're talking about now,
[42:15]
>> and then the big project, which is
[42:17]
actually designing the building, and
[42:20]
>> you know, that's the big project. Isn't it true that that the costs to the
[42:25]
architect would be paid as a percentage
[42:27]
of the construction costs?
[42:29]
>> That that's normally how it's done. Yes,
[42:31]
that's my understanding.
[42:32]
>> Okay. So, if you add in a fire station,
[42:36]
>> right?
[42:37]
>> Yeah.
[42:38]
>> Okay. And so if you if we negotiate an
[42:41]
agreement with an architect and it
[42:44]
doesn't have a fire station in it and
[42:45]
then all is said in through the process
[42:47]
because they would be doing the
[42:49]
facilities master plan process or not.
[42:52]
But if at some point a fire station gets
[42:55]
popped in there 14 to $20 million more
[42:59]
then depending on whether it's a uh
[43:03]
depending on if you're reusing the
[43:05]
building or you're you know it could be
[43:07]
10% to 20% right is what what I've
[43:10]
what's my understanding is what the
[43:11]
architect will get then you're going to
[43:13]
have 10 to 20% more and what's that
[43:16]
going to be it's going to be a change
[43:18]
order and once you have an architect
[43:20]
it's not like you're going to want to
[43:21]
change change horses.
[43:23]
So it it is um it's very important that
[43:28]
we have a really tight scope of work
[43:30]
when we start with
[43:33]
you don't you don't want to come up with
[43:35]
cost you know we need to have a solid project budget and then we can use
[43:43]
that to um for the council to consider
[43:47]
if you want to go to the voters and if
[43:49]
so for how much how much the last thing
[43:51]
you want to do is change your mind or
[43:55]
say, "Oh, sorry of orders. We need more
[43:57]
money. We need and and I I outlined all
[44:00]
this in the staff report and I'm not as
[44:03]
articulate as a, you know, construction
[44:06]
expert would be. I just want the council
[44:09]
to understand
[44:11]
this is a big project for us to begin
[44:14]
with and to be asked
[44:18]
to do it without
[44:21]
a best industry standard best practice
[44:24]
in place is setting us up to fail. It'd
[44:29]
be like asking me to do it without the
[44:31]
town attorney. you know, it would be
[44:33]
like asking me to, you know, it's you're
[44:35]
setting you're setting me you're setting
[44:37]
up our organization to fail and that
[44:40]
that's my honest opinion. I really tried
[44:43]
to put stuff with the help of David
[44:45]
Kelly and my staff report and um we have
[44:49]
every intention of moving this forward.
[44:52]
We have every intention of and have we
[44:54]
are embracing the CAC. It's beautiful. I
[44:58]
hope that's what it ends up being.
[45:02]
Elizabeth, did you want to ask a
[45:04]
question?
[45:04]
>> I I I still don't understand, Christa,
[45:06]
how we got from May 6 where we approved
[45:10]
the uh CAC plan and set up a committee
[45:12]
to choose an architect and then that
[45:15]
committee met on May 12 and we went
[45:17]
through all the RFQS and then on May 13,
[45:20]
the whole plan shifted that now we need
[45:22]
to update the master plan and we're not
[45:25]
working on the architect. I still don't
[45:27]
understand that. I I'm I'm comfortable
[45:29]
going back to where we were on May 12th
[45:32]
and May 6th, planning to choose an
[45:34]
architect. And I I'm sure you could tell
[45:36]
from my comments at the last meeting, I
[45:38]
I'm was not in favor of moving ahead to
[45:42]
update the master plan, but voted for it
[45:45]
because I I didn't want the council to
[45:47]
look, you know, yet again like we're
[45:48]
dysfunctional or divided. I want us to
[45:51]
be moving forward together. But I still
[45:53]
don't think understand how we got from
[45:56]
where we had plans to hire an architect
[45:58]
and then the next day those plans are
[45:59]
gone and you suggested that we need to
[46:01]
hire we need to update the master plan.
[46:04]
Uh that's a a step I have never
[46:06]
understood.
[46:15]
when the council is
[46:22]
um
[46:23]
setting special meetings
[46:26]
and giving me and staff
[46:30]
24 hours to 48 hours to respond
[46:35]
when we're being asked by the council to
[46:37]
respond to the CAC pro proposal
[46:41]
or even last January the fourth proposal
[46:44]
getting it, you know, the day before
[46:48]
January 1st, you your your expectations
[46:53]
are absolutely unreasonable. I called on
[46:57]
May 6th, the council set up a
[47:00]
subcommittee. Great. I set it up, had
[47:04]
myself, a project manager, and a
[47:07]
consultant there.
[47:10]
Six days later over a weekend we hold
[47:14]
the meeting which I had thought would be
[47:17]
the first of many meetings. It was a
[47:20]
kickoff meeting where we had just we had
[47:24]
the 10 proposals. We gave them to you a
[47:27]
few days ahead of time. We had a nice
[47:29]
spiffy matrix. It was the kickoff
[47:31]
meeting and
[47:35]
it is uh you know and it was a I thought
[47:39]
it was a collaborative let's you know
[47:42]
let's brainstorm. I'm getting input from
[47:44]
two longtime council members
[47:48]
on what you thought
[47:51]
your input on the selection of an
[47:55]
architect
[47:57]
and then I went away on vacation for two
[48:01]
weeks. I come back and it was very
[48:04]
apparent to me that staff was not ready
[48:07]
to bring forward to council
[48:10]
information about the procurement policy
[48:12]
on June 11th and rather we needed to
[48:16]
have but I knew that the council very
[48:17]
much wanted to move forward and it
[48:20]
became very apparent to me that there
[48:21]
are so many unknowns there are so many
[48:24]
decisions that the council frankly has
[48:26]
been punting okay there are a lot of
[48:29]
question there are questions there's a
[48:31]
question about this fire station and
[48:33]
until we have that settled, we cannot go
[48:37]
into
[48:39]
a I cannot effectively negotiate an
[48:43]
agreement for a multi-million dollar
[48:46]
contract. So, it's unreasonable to
[48:49]
expect
[48:50]
that things are not going to change,
[48:54]
especially when you're throwing special
[48:56]
counsel meetings, multiple special
[48:58]
counsel meetings at me. Um, I think
[49:02]
you've got to we've got to forward. We
[49:04]
have to look focus on moving forward.
[49:08]
And I would appreciate
[49:10]
not having to constantly defend myself
[49:12]
about something that happened a month
[49:14]
ago. We just need we need to move
[49:16]
forward.
[49:20]
» Okay.
[49:20]
I I think I'd like to um open
[49:23]
>> you know I have one last question.
[49:25]
>> Okay.
[49:26]
>> Uh just to for clarification, Christa,
[49:28]
you just said that it would cost $25
[49:31]
million without a fire station and 10
[49:34]
million more with a fire station. Where
[49:37]
are you getting those numbers?
[49:41]
So,
[49:45]
$25 million is what the current
[49:50]
last in as part of the election code
[49:53]
report that staff prepared with
[49:57]
many consultants that we presented and
[50:00]
the council accepted on January 8th. It
[50:02]
included a um an update of the cost estimate to implement concept B.
[50:14]
>> Okay. Yeah.
[50:15]
>> Updated that to $25 million and it also
[50:18]
had a cost escalation. So $25 million
[50:22]
would be what it would a cost estimate
[50:24]
to do concept B if we were to build it
[50:27]
in 2026 27. And then that that
[50:32]
spreadsheet showed that by the time if
[50:35]
we didn't build it till 2031,
[50:37]
it would be upwards of over $30 million
[50:40]
with costs with construction cost
[50:42]
escalation. So that's where the $25
[50:45]
million came from. the $10 million is in
[50:49]
I will not be held to the $10 million
[50:51]
because I actually think that it's more
[50:54]
is based on the fact that what was it in
[50:57]
2020
[50:59]
the council got an estimate that having
[51:02]
a fire station was $14 million.
[51:05]
Well, that and and we just received
[51:08]
actually as part of that election code
[51:10]
report
[51:12]
um Mary McGrath,
[51:15]
the very experienced fire station
[51:18]
architect
[51:19]
indicated and actually Chief Weber,
[51:22]
chief of Marin County Fire Services, I
[51:24]
believe he has said that fire stations
[51:27]
now cost 19 to20 million. So adding on
[51:32]
$10 million even if I know the CAC
[51:35]
proposal they're basing it on on well
[51:38]
let's have share let's have more let's
[51:40]
incorporate more shared spaces between
[51:42]
the paramedics and police and fire
[51:44]
station. So maybe it's there's some
[51:47]
savings because you won't it wouldn't be
[51:49]
a standalone fire station. But $10
[51:52]
million is very conservative number. If
[51:56]
you have a if you have a full fire fully
[51:59]
outfitted fire station,
[52:02]
it's going to it's going to cost a a
[52:04]
lot. But again, during a facility master
[52:07]
plan process, if the council makes the
[52:10]
decision to include into the facilities
[52:12]
master plan a fully loaded um with all the tenant
[52:19]
improvements, fire station, you will get
[52:23]
the cost. It's not going to be me
[52:25]
saying, "Oh, 10 million." It's not going
[52:27]
to be forth saying what they think. It's
[52:29]
going to be actual PE. It's going to be
[52:33]
professional cost estimating from fire
[52:36]
department professionals and you'll have
[52:39]
that as an outcome as a deliverable with
[52:43]
your facility master plan amendment
[52:45]
process.
[52:47]
>> Okay. So, I just want to call your
[52:49]
attention to the um the April 29th
[52:52]
meeting from the CAC proposal on page 23
[52:57]
where concept B just as as you said with
[53:00]
no fire station is about 25 million, but
[53:04]
their proposed civic center and town
[53:06]
center with a fire station is $22.7
[53:09]
million. And they said this was
[53:12]
extracted from a bid from a contractor.
[53:15]
So I just want to make sure that we are
[53:18]
using apples to apples or comparison
[53:20]
because we're no concept B is no longer
[53:22]
on the table. So I don't think we should
[53:24]
be talking about it. And uh what we
[53:28]
received from the CAC was an estimate of
[53:30]
22.7 million.
[53:32]
>> And needs to be validated. That's why
[53:35]
it's called a validation process.
[53:37]
>> No, I agree. I just think we should be
[53:39]
using th those numbers because that's
[53:41]
what we have right now. that that that's
[53:44]
not being that's coming from a a group
[53:46]
of citizens, but that's not coming from
[53:49]
um town staff. That's not an official
[53:51]
town number. I just want to add it's
[53:54]
also very unclear the scope of how much
[53:57]
of the fire station is actually built
[53:59]
out just versus empty space
[54:02]
>> um including in that meeting. So, we're
[54:05]
going to move to um public comment. Um,
[54:09]
I think given um I I'm happy to allow
[54:14]
people additional time if people need
[54:16]
additional time. Let's just be
[54:18]
respectful that it's a Wednesday
[54:21]
afternoon at almost 3:00.
[54:23]
So, who wants to go first?
[54:43]
Good afternoon, Madame Mayor and members
[54:44]
of the council. My name is Mike Rosenbal
[54:46]
and I live at 14 Madna Avenue here in
[54:48]
Ross.
[54:50]
I am here to address my ongoing concerns
[54:52]
regarding the Friends of Ross firehouse
[54:55]
forth initiative and the town's current
[54:57]
policy direction.
[54:59]
First, there is a fundamental lack of
[55:01]
clarity regarding leadership. We need to
[55:03]
know who is driving decisions at FORF.
[55:06]
If the board's president, Mr. Herp's
[55:08]
word is no longer reliable from the
[55:10]
April email, the town deserves to know
[55:13]
who is actually setting their agenda.
[55:16]
We are witnessing a tail wagging the dog
[55:18]
scenario where an outside organization
[55:21]
appears to dictate policy to the town of
[55:23]
Ross leading to the rescending of
[55:25]
resolutions that were passed only months
[55:27]
ago.
[55:29]
Second, the abrupt cancellation of an
[55:31]
architect RFP authorized just two weeks
[55:33]
ago is deeply troubling. Bypassing an
[55:37]
established competitive process in favor
[55:38]
of a no bid arrangement undermines the
[55:42]
integrity and ethical procurement
[55:43]
standards for a municipality and raises
[55:46]
significant questions about fiscal
[55:48]
responsibility.
[55:50]
Third, we are being asked to evaluate
[55:52]
tax concept of a plan without a clear
[55:55]
financial strategy. If FORF is confident
[55:58]
in their vision, they should be
[56:00]
transparent about their funding. I ask
[56:03]
that for provide specific details on
[56:05]
their pledges and financial backing
[56:07]
rather than operating in opacity.
[56:10]
I suggest the town of Ross demand
[56:12]
Stephanie DeMarco produce a validated
[56:14]
list of contributors and amounts to the
[56:16]
town manager and the town treasurer so
[56:18]
that an adjusted parcel tax can be
[56:20]
associated with the upcoming ballot
[56:21]
initiative. It is time to put up or shut
[56:24]
up or admit that the parcel tax will be
[56:26]
$6,000 in perpetuity.
[56:29]
Finally, I must remind the town council
[56:32]
of the Marine Grand Jury report, which
[56:34]
explicitly describes the Ross Fire
[56:36]
Station as a misguided civic engagement.
[56:40]
By disregarding these findings, the
[56:42]
council's exposing the town to
[56:44]
unnecessary liability. I urge you
[56:47]
consider the long-term risk. The
[56:49]
citizens of Ross should not be forced to
[56:51]
bear the cost of defending council
[56:52]
decisions that ignores established
[56:54]
guidance.
[56:56]
I call on the council to maintain the
[56:57]
integrity of our existing processes,
[57:00]
honor previous commitments, and stop
[57:02]
allowing external pressures to dictate
[57:04]
policy that risks our fiscal and legal
[57:06]
standing. I'm going to leave copies for
[57:08]
the county council and the Marin. Thank
[57:10]
you.
[57:13]
>> Thank you.
[57:16]
Anyone else? Mr. Cune.
[57:20]
>> Um, I would like
[57:23]
Dan to be on simultaneously.
[57:27]
» Zach, can you can you um
[57:31]
can you move Dan Weiny? Um,
[57:36]
>> there he is. Dan Winey is allowed to
[57:37]
talk.
[57:38]
>> There you go. Can you guys hear me?
[57:40]
Okay.
[57:40]
>> Yeah. Hi, Dan.
[57:42]
>> Can you Can you see me? You can't see me
[57:44]
though. Just my hand, right? Can we see
[57:46]
him, Zach?
[57:50]
» Mr. Winy, um, is your camera on?
[57:53]
>> Yep, my camera's on.
[57:55]
>> Um, promote you to panelist.
[57:57]
>> Okay, great.
[58:11]
So, do you guys have the start the
[58:14]
video?
[58:16]
Okay. Can you guys see me? Okay.
[58:18]
>> Yeah. Yes.
[58:20]
>> Okay. So, boy, you guys uh you guys
[58:23]
brought up a lot of a lot of questions
[58:25]
and a lot of really good information.
[58:28]
Um I just say just a couple things. one
[58:31]
is is that, you know, we all have the
[58:33]
same goal here in terms of what it is
[58:35]
that we're trying to do. And I think in a lot of ways we're we're sort of
[58:41]
talking past one another. When I when I
[58:44]
listen to to Kristen and I read the
[58:46]
staff report, everything that Christa
[58:48]
has said is absolutely true. Everything
[58:51]
that she outlined in terms of scope of
[58:53]
work needs to be done. Um, and I think
[58:58]
there's a difference in sort of the the
[58:59]
words that we're using and maybe a
[59:01]
little bit more about the process that
[59:03]
we're going through here that the when
[59:06]
we talk about updating the master plan,
[59:09]
everything that's articulated in that
[59:11]
scope of work that went out in the RFP
[59:14]
actually is part of schematic design. I
[59:16]
mean, that is essentially schematic
[59:18]
design. Um, and I disagree. I guess the
[59:21]
one thing, David, where I would disagree
[59:23]
with you is that schematic design in
[59:25]
fact does typically include um detailed
[59:28]
floor plans, space plans, uh, conceptual
[59:31]
reflected ceiling plans, sections,
[59:33]
elevations, that kind of thing. And it
[59:36]
is a normal process that I think every
[59:39]
client goes through. Um, many times when
[59:43]
we're at this stage of the of the
[59:45]
process, we don't really know what
[59:46]
things are going to cost. It's
[59:47]
interesting. You know, we're throwing
[59:50]
numbers around it, which makes me
[59:51]
extremely nervous because the reality is
[59:53]
we just don't have the information to
[59:56]
really know exactly what those numbers
[59:57]
look like. So, I my my recommendation
[1:00:01]
would be to what Christa has right now
[1:00:04]
at the table. If you were to simply if
[1:00:06]
we were to simply layer on more
[1:00:08]
information, let's get let's meet with
[1:00:11]
the department heads, verify the
[1:00:12]
program, uh take a look at the building.
[1:00:15]
There's some, you know, work certainly
[1:00:17]
that needs to be done in terms of an
[1:00:19]
engineering analysis. We need to get as
[1:00:21]
built done. We need to lay out, I mean,
[1:00:24]
the fact of the matter is we need to lay
[1:00:25]
out the departments. Listening to the
[1:00:27]
police chief in the last meeting, one
[1:00:29]
thing he talked about is, you know,
[1:00:31]
where's my evidence room and where's my
[1:00:33]
locker for weapons and everything else.
[1:00:35]
All those things need to be determined
[1:00:39]
right now and should be included in what we call it. Maybe we just call it
[1:00:43]
simply a updated master plan and
[1:00:45]
schematic design package. But that will
[1:00:49]
allow us to get a very detailed cost
[1:00:52]
estimate. So we'll have plans,
[1:00:54]
elevations, sections. We'll understand,
[1:00:57]
we'll have some preliminary engineering
[1:00:59]
that gets done. We'll have a cost
[1:01:01]
estimator on board. We'll be running
[1:01:03]
concurrent um you know meetings in terms
[1:01:06]
of environmental requirements or maybe
[1:01:09]
looking at what has to happen with staff
[1:01:11]
in terms of relocation. All those things
[1:01:13]
are done as part of schematic design
[1:01:15]
work. I think the question of I I think
[1:01:20]
what's what's happening here is that in
[1:01:22]
many ways we're trying to define exactly
[1:01:24]
what it is that we want to do and we
[1:01:25]
don't know what it is. We don't know
[1:01:27]
where we're going with this yet. So, so
[1:01:29]
David, when you're talking about um the project delivery method, that is in
[1:01:36]
my mind um a very important part of the
[1:01:39]
role that the architect would have in
[1:01:42]
this next phase is helping town and
[1:01:45]
staff and you and the owner's rep
[1:01:49]
ultimately determine what is the best
[1:01:51]
delivery model. Could be design build,
[1:01:53]
could be design bid, build build, it
[1:01:55]
could be some modified design build
[1:01:57]
process. That is very typical. And we
[1:02:02]
don't have to sign a multi-million
[1:02:05]
dollar contract with an architect. We
[1:02:07]
don't we can take what Christa has right
[1:02:10]
now, embellish it a little bit more in
[1:02:12]
terms of scope of work, get us to the
[1:02:15]
point where we know exactly what project
[1:02:17]
what it is that we're getting in terms
[1:02:19]
of of content, right? What kind of
[1:02:21]
drawings are we getting? Are we getting
[1:02:22]
outline specifications?
[1:02:25]
Everything that we need so that at the
[1:02:27]
end of this phase, we're going to have a
[1:02:29]
number that we're comfortable with. And
[1:02:32]
so I think the question comes up, the
[1:02:34]
fire station keeps coming up here. The
[1:02:37]
fire station in this next phase right
[1:02:40]
now needs to be laid out. Needs to be
[1:02:42]
laid out. We need to understand the
[1:02:44]
requirements. We need to understand from
[1:02:45]
an operational standpoint whether we can
[1:02:47]
accommodate them or not. It doesn't mean
[1:02:50]
that the fire station needs to be part
[1:02:52]
of the scope of work moving forward. It
[1:02:54]
needs to have space allocated for it. We
[1:02:57]
need to understand that it works in the
[1:02:58]
context of all the other departments.
[1:03:01]
But we can draw a line around it and say
[1:03:03]
this portion of the project um can be
[1:03:06]
held till a later date because there's
[1:03:08]
other things that we need to go through
[1:03:09]
to get citizens approval for that. And
[1:03:12]
if it is approved, great. And if it
[1:03:14]
isn't approved, then we need to have
[1:03:15]
options for what we do with that space
[1:03:17]
if we don't move forward with it. So
[1:03:20]
it's and I think that the issue of the
[1:03:22]
architect is that it is very very very
[1:03:26]
common for an architect to be hired only
[1:03:29]
for schematic design or feasibility
[1:03:32]
studies or or you know developing a
[1:03:35]
detailed master plan only for that scope
[1:03:38]
of work. And the town can always reserve
[1:03:41]
the right to bid that project later,
[1:03:44]
right? You always we always have the
[1:03:46]
right to bid it later. And quite
[1:03:48]
frankly, from an architect standpoint
[1:03:51]
and from an engineer standpoint and all
[1:03:54]
the other consultants involved, the more
[1:03:57]
clarification they have on scope, the
[1:03:59]
better. The fees are going to be
[1:04:01]
tighter. They're going to have a better
[1:04:03]
understanding what the deliverables are.
[1:04:05]
And typically, I would also argue that
[1:04:09]
typically construction projects in this
[1:04:12]
day and age are not bid on a percentage
[1:04:14]
of construction costs. That is
[1:04:16]
incorrect. They are typically a lump
[1:04:18]
sum. What architects will do is they
[1:04:22]
will look at their fees and the
[1:04:23]
consultant fees as a percentage of
[1:04:25]
construction cost to try to understand
[1:04:28]
the magnitude of this project compared
[1:04:31]
to other work that they done to try to
[1:04:33]
understand whether the scope is such
[1:04:35]
that they have a really good sense of
[1:04:37]
exactly you know where the where they
[1:04:39]
need to come in at but it will not be a
[1:04:41]
percentage of construction cost it'll be
[1:04:42]
a lump sum David it may be a GMP maybe
[1:04:46]
it won't be a GMP maybe it'll be a cost
[1:04:48]
plus model. We can get the general
[1:04:51]
contractor to bid general conditions,
[1:04:53]
overhead and profit, put a 8% fee on it,
[1:04:56]
and we can look at every single bid. We
[1:04:59]
can look at every subcontractor bid. The
[1:05:01]
whole point is there's a lot of
[1:05:03]
different ways to deliver this project
[1:05:05]
that will give us the best project we
[1:05:07]
can, the highest quality that we can.
[1:05:10]
And it's not a decision that we need to
[1:05:12]
make right now. is not a decision and it
[1:05:15]
will be a decision that we'll need to
[1:05:16]
make in the next you know six months but
[1:05:19]
getting this first piece of the puzzle
[1:05:22]
in place making sure that we can
[1:05:24]
accommodate from an operational
[1:05:26]
standpoint everybody's needs make sure
[1:05:28]
that we understand the implications site
[1:05:30]
planning all of it so that we've got a
[1:05:32]
package so that I think from the from
[1:05:35]
the citizens advisory advisory
[1:05:38]
perspective we want this to move forward
[1:05:41]
and it enables us to have a number that
[1:05:44]
everybody's comfortable with so that if
[1:05:46]
we do offer a bond, the sooner the
[1:05:48]
better and we're going to know that we
[1:05:51]
can stand behind that number. Um, and
[1:05:53]
the fire department piece of it can be
[1:05:56]
bid and bid or can be estimated as a
[1:05:59]
separate piece of the puzzle. So that as
[1:06:01]
we're moving forward and trying to
[1:06:03]
understand whether we want a fire
[1:06:05]
department or not, what is the what's
[1:06:08]
the infrastructure cost of doing that?
[1:06:10]
And then we have to layer on the
[1:06:12]
operational cost, but we don't need to
[1:06:13]
make that decision right away. So, I
[1:06:16]
mean, I I think again,
[1:06:18]
we're all we're all saying it's
[1:06:20]
interesting because we're all saying
[1:06:21]
exactly the same thing, but I do think
[1:06:24]
in some ways we're just talking past one
[1:06:26]
another. And I think the right way to go
[1:06:27]
about this is to get together, is to try
[1:06:30]
to move forward in this next phase as
[1:06:32]
quickly as we can because it it time is
[1:06:34]
of the essence. And I guess the one
[1:06:36]
concern that I would have just observing
[1:06:39]
this is things like the paramedic, you
[1:06:42]
know, conversation that need to take
[1:06:43]
place, Ross Valley fired, all all the
[1:06:46]
other things that need to happen. Boy,
[1:06:48]
we're time is of the essence here and we
[1:06:50]
could get ourselves pushed back into a
[1:06:53]
corner early next year where all of a
[1:06:56]
sudden we don't have a choice of
[1:06:58]
incorporating the paramedics facility in
[1:07:01]
the existing building. We've got to
[1:07:02]
build a separate building for it. And I
[1:07:04]
think that would be a real a real
[1:07:05]
mistake and a shame. So I I think again
[1:07:09]
taking what Christa has layering on
[1:07:11]
another, you know, another more detail
[1:07:14]
to it, make sure we understand what
[1:07:16]
deliverable what we want back as a town
[1:07:18]
and move forward, but reserve the right
[1:07:20]
to move forward with the project with
[1:07:23]
the architect that may do the first
[1:07:25]
phase. Maybe they do great, we love
[1:07:26]
them, and maybe they don't. But and I
[1:07:29]
think the other piece of this David is
[1:07:31]
I'll go back to drawings that need to be
[1:07:34]
done for design which let's talk about
[1:07:36]
design builds for a second because I
[1:07:38]
think it is important an architect a
[1:07:40]
design architect can do schematic design
[1:07:44]
and advanced DD that package the town
[1:07:48]
will retain the ownership of all the
[1:07:50]
drawings that are done. That package can
[1:07:53]
be given then to another general
[1:07:55]
contractor and a general contractor will
[1:07:57]
hire their own architect. Most of them
[1:07:59]
are not architects. That package will go
[1:08:02]
to a GC and architect. They'll do the
[1:08:04]
construction drawings and then the
[1:08:06]
design architect overviews the entire
[1:08:09]
project to make sure that from a design
[1:08:11]
intent and from a quality standpoint
[1:08:14]
that the general contractor and the
[1:08:16]
general contractor's architect is doing
[1:08:18]
exactly what they should be doing. It
[1:08:21]
can also go a different route. The
[1:08:22]
architect that does the design
[1:08:24]
development drawings can also be the one
[1:08:26]
that gets assigned to the general
[1:08:28]
contractor. So, and that's a very common
[1:08:31]
delivery model on the on the, you know,
[1:08:33]
it's a very different scale project, but
[1:08:35]
on the San Francisco airport, we're the
[1:08:37]
conceptual design architect. We did the
[1:08:40]
design development drawings and then we
[1:08:41]
were assigned to the general contractor
[1:08:44]
as their architect. So we had a dual
[1:08:46]
role of overviewing the quality of the
[1:08:48]
construction design intent but our we
[1:08:52]
move from the client being the airport
[1:08:55]
commission to the general contractor
[1:08:57]
andor both. So the the the point is
[1:09:00]
there's just a lot of different ways to
[1:09:03]
do this and I think it's premature to
[1:09:05]
try to outline exactly what it is that
[1:09:09]
we're how we're going to go about it
[1:09:10]
without really having an understanding
[1:09:12]
of exactly what needs to be done and
[1:09:15]
ultimately what is the best approach.
[1:09:16]
So, I mean, that's my input as a as an
[1:09:20]
architect in trying to help, you know,
[1:09:21]
move this process forward because I I do
[1:09:23]
think ultimately again the goal is the
[1:09:25]
same that we just want to have a great
[1:09:27]
project and we want to get it done, you
[1:09:29]
know, all the right, you know, the right
[1:09:30]
way for the right reasons.
[1:09:33]
>> Let me add to that. I'm not an
[1:09:36]
architect. I'm another finance guy. We
[1:09:39]
have four months
[1:09:42]
before we have to file
[1:09:45]
for the bond measure in March. We we
[1:09:48]
missed it for this fall. We only have
[1:09:52]
four months.
[1:09:54]
That is like overnight in this business.
[1:09:57]
The reason we ask for the acceleration
[1:10:01]
is to avoid missing the November ballot.
[1:10:07]
is July, August, September, October.
[1:10:10]
Four months. The actual filing date is,
[1:10:13]
as you said, uh November 7th, I think,
[1:10:16]
is December 4th.
[1:10:20]
We don't have time. And so we've got a
[1:10:23]
guy who is about to retire from the
[1:10:27]
world's largest, most sophisticated
[1:10:30]
architecture firm on the planet who
[1:10:33]
knows more about this stuff than we do,
[1:10:38]
more than David does, more than anybody
[1:10:41]
does. If you think there's a weird thing
[1:10:43]
that we've got to do research for, you
[1:10:46]
can bet somebody inside Gendler
[1:10:48]
somewhere on the planet knows the answer
[1:10:50]
to that. They find it out like that. So,
[1:10:53]
we've got the varsity team getting
[1:10:56]
behind us here and we're not doing
[1:10:59]
anything to hurt anybody else's position
[1:11:02]
inside the town. [snorts] We have to be
[1:11:06]
right and we have to do it fast.
[1:11:11]
And the whole town there's there about
[1:11:13]
500 people who have seen the video.
[1:11:19]
Nobody said that sucks.
[1:11:22]
quite the opposite. And they know
[1:11:24]
exactly who built it.
[1:11:28]
So Gendler is way ahead of everybody
[1:11:30]
else that's on the list. So why not do
[1:11:34]
it? They're not going to be more
[1:11:36]
expensive than anybody else on the list,
[1:11:38]
but they're already on first or second
[1:11:40]
base. Nobody else is even at the plate.
[1:11:46]
Any questions?
[1:11:48]
Are are you suggesting to hire Gensler
[1:11:51]
for the to just start and work on the on
[1:11:54]
the
[1:11:54]
>> I'm sorry. Say again.
[1:11:56]
>> Are you proposing hiring the architect
[1:12:00]
to start the design and the scope of
[1:12:02]
work and the project or are you
[1:12:03]
proposing to hire an architect to update
[1:12:06]
the master plan?
[1:12:08]
>> I I don't think that there is much of a
[1:12:11]
difference. We need to get the schematic
[1:12:13]
design done and we have to have that
[1:12:16]
done. So I understand what is likely to
[1:12:19]
be the cost of this project. Now you can
[1:12:22]
call it facility master plan or you can
[1:12:25]
call it something else. Doesn't really
[1:12:27]
matter. But this particular subject at
[1:12:30]
this particular time is about schematic
[1:12:34]
design and the cost associated with what
[1:12:37]
is likely to ensue after that. That's
[1:12:41]
why we need to have the information for
[1:12:44]
the ballot initiative.
[1:12:46]
So we already have those RF
[1:12:49]
uh cues for an architect. So is that
[1:12:53]
enough to go on? Uh
[1:12:55]
>> we need them now. We just need the
[1:12:57]
schematic design work done. And as Dan
[1:13:00]
said, we can deal with whatever
[1:13:02]
architect we want later and it might be
[1:13:05]
Gendler. It should be Gendler in my
[1:13:08]
view, but it could be somebody else.
[1:13:10]
Dan, say what you want.
[1:13:12]
>> Yeah. Elizabeth, Councilman Robinson.
[1:13:15]
So,
[1:13:17]
I don't you know, I I guess I want to
[1:13:19]
make sure that you guys all understand
[1:13:21]
that that
[1:13:23]
my viewpoint of this and everything that
[1:13:27]
I've talked about as far as I'm
[1:13:29]
concerned represents town's interest.
[1:13:32]
That's first and foremost in my mind. I
[1:13:35]
don't I mean I would be great if the
[1:13:38]
firm got the project, but it doesn't
[1:13:39]
really matter to me in all it doesn't in
[1:13:41]
any way. whatsoever and moving forward
[1:13:45]
on this and any guidance that I've tried
[1:13:47]
to give today or in the previous
[1:13:49]
meetings or even the work that we've
[1:13:50]
done is simply done to try to do the
[1:13:54]
right thing for the town for all the
[1:13:55]
right reasons. So I don't you know I
[1:13:58]
just want to make sure people understand
[1:13:59]
that it could be any architect and you
[1:14:02]
know I would be sitting here and if it
[1:14:04]
was another architect that wasn't
[1:14:05]
performing or wasn't doing the things
[1:14:06]
that we I'd be all over their case as
[1:14:08]
well. So, it's just that I I think
[1:14:10]
everybody needs to understand that
[1:14:13]
that's really what, you know, I'm
[1:14:15]
personally trying to do and I think the
[1:14:17]
CIS citizens advisory committee is
[1:14:19]
trying everybody's trying to do the same
[1:14:21]
thing and how we go about it. Um, I I
[1:14:25]
wish in a lot of ways we could clearly
[1:14:27]
define exactly what the road forward
[1:14:29]
looks like, but you know what? 99.9% of
[1:14:33]
the projects you can't. you know, you
[1:14:34]
sort of go down the road and you make
[1:14:36]
good decisions and you work
[1:14:38]
collaborative collaboratively and
[1:14:40]
ultimately you get to a place hopefully
[1:14:41]
where everybody walks away when it's all
[1:14:44]
said and done and you've done a great
[1:14:45]
project. And so I think you know to me
[1:14:47]
that's what the goal is here.
[1:14:50]
>> Can I ask you a question Dan? Um given
[1:14:53]
that the um RFPs are due in 8 days,
[1:14:58]
would you be troubled by allowing those
[1:15:01]
um RFPs to come back and then
[1:15:05]
look at look at them and figure out, you
[1:15:07]
know, the top few based on that and then
[1:15:11]
negotiate a scope that accommodates the
[1:15:14]
schematic element as well to ensure that
[1:15:17]
we can meet this December 4th filing for
[1:15:21]
the general obligation. bond in March.
[1:15:23]
>> Yeah, I think I think that's a you know,
[1:15:25]
town council wants to move in that
[1:15:27]
direction. I think that's a very
[1:15:28]
reasonable way to go. I mean, at this
[1:15:31]
point, we're only you know what, 10 days
[1:15:33]
away. Um I think the only thing is, and
[1:15:36]
I'm not sure whether you've heard back
[1:15:37]
from architects, but I would guess that
[1:15:39]
the architects probably would ask for a
[1:15:41]
fair amount of clarification. Uh because
[1:15:44]
when I did read the RFP that went out, I
[1:15:46]
thought there were a lot of I mean, if I
[1:15:48]
was bidding it, there were a lot of
[1:15:49]
questions that I would have. So it would
[1:15:52]
be an opportunity to go back and uh
[1:15:54]
clarify the scope to the point where
[1:15:56]
we're saying these are the drawings that
[1:15:58]
we want as part of this next phase.
[1:16:02]
These are, you know, these are this is
[1:16:04]
the we want outline specifications,
[1:16:06]
whatever it is, but be very very clear
[1:16:08]
with the architects as to what the
[1:16:10]
deliverable is because the more clear we
[1:16:13]
are in terms of what it is that we want
[1:16:15]
and what it is that we expect, the
[1:16:16]
better the price is going to be, right?
[1:16:17]
Because they're not going to put
[1:16:18]
contingencies in or whatever. But, um,
[1:16:21]
yeah, I think that's a it's a reasonable
[1:16:24]
way to go. I think we need to keep in
[1:16:25]
mind that that
[1:16:28]
and this goes back to what Krista was
[1:16:29]
saying and this is where I think it does
[1:16:31]
time is of the essence in the sense that
[1:16:35]
if we go through this next phase as
[1:16:36]
outlined right now I didn't know whether
[1:16:39]
the intent was going to be to hire an
[1:16:41]
architect to do the whole project or
[1:16:42]
just up the date the master plan and
[1:16:45]
then go back out for architects to do
[1:16:46]
the whole project. I think in this case,
[1:16:50]
you know, your schematic design,
[1:16:52]
basically updating the master plan and
[1:16:54]
schematic design is going to take
[1:16:56]
probably about 12 weeks would be my
[1:16:57]
guess. At the end of that 12 weeks, we
[1:16:59]
should have a very comprehensive set of
[1:17:01]
drawings and we'll have, you know,
[1:17:03]
everything that we need to be able to
[1:17:04]
get pricing, including we probably
[1:17:07]
should have a cost estimator running
[1:17:09]
concurrently with us. So, at the end of
[1:17:11]
this 12week period, we know exactly what
[1:17:14]
those numbers look like. But um as long
[1:17:17]
as we don't get bogged down in having to
[1:17:20]
you know two weeks of negotiations and
[1:17:23]
then two weeks of this and two weeks of
[1:17:25]
that because all of a sudden our back's
[1:17:27]
going to be up against the wall in terms
[1:17:28]
of trying to do what we need to do you
[1:17:30]
know early next year.
[1:17:33]
>> My view is get it going now. Why wait
[1:17:36]
another week?
[1:17:38]
Gendler did the did the planning for
[1:17:41]
this. They've already had a team who's
[1:17:42]
been looking at this building.
[1:17:45]
>> Yeah.
[1:17:45]
>> And a week is a lot of time in the
[1:17:48]
amount of time that we have left.
[1:17:50]
>> Well, and whether we do Yeah. Whether we
[1:17:51]
do it or not, I mean, whether our look
[1:17:54]
at I'm retiring you guys, so it's not my
[1:17:56]
firm anymore. But whether Gensler does
[1:17:58]
it or not, if you do take it the next
[1:18:00]
nine days, you will have you'll have
[1:18:02]
pricing. So I think that'll satisfy
[1:18:05]
probably some you know certainly
[1:18:08]
interest in the room that you know want
[1:18:10]
to make sure that the pricing is is
[1:18:12]
comparable. Um I doubt you know being in
[1:18:15]
this business for 45 almost well 50
[1:18:18]
years now that you know what Chris has
[1:18:20]
said is true. You know it doesn't have
[1:18:23]
to be low bid. You want to pick the
[1:18:25]
right firm for the right reasons and I
[1:18:27]
think you know ultimately you know that
[1:18:29]
should be the endgame here.
[1:18:32]
But if we were to stay with the current
[1:18:34]
plan, I'm not sure the council has the
[1:18:36]
right dates and availability to make
[1:18:38]
that work. I mean, I I I think we were
[1:18:41]
told that these bids for the RFPs for
[1:18:44]
the um to update the master plan were
[1:18:46]
due soon, but we were to be reviewed by
[1:18:50]
the committee. That's Julie and me and the staff committee um on July 8th,
[1:18:56]
I think the day before our July 9
[1:18:58]
meeting, but that would be too late to
[1:19:01]
put it on the July 9 agenda. And that
[1:19:03]
pushes it all the way back to August to
[1:19:04]
even hire someone because there weren't
[1:19:06]
many dates in July when we could get
[1:19:08]
together for a meeting. So, I think that
[1:19:11]
I mean I think we want to I think we
[1:19:14]
want to make this process work so that
[1:19:17]
July 9 at our meeting we've hired an
[1:19:20]
architect to do whatever we want whether
[1:19:22]
it's just start with a project or the
[1:19:24]
master plan or whatever. But I I I you
[1:19:27]
know my concern about these RFPs is as I
[1:19:30]
said they're going to come in too late
[1:19:32]
and the council doesn't have a meeting
[1:19:34]
time to go over it until August.
[1:19:39]
Whereas the committee has met already
[1:19:41]
and looked at the RF.
[1:19:42]
>> Let's just we're supposed to be asking
[1:19:46]
the [clears throat] public questions
[1:19:47]
then we'll have a chance to deliberate
[1:19:49]
and so is there anyone else in the
[1:19:52]
chamber who wishes to make a public
[1:19:54]
comment.
[1:19:55]
>> Yes, Mr. Hanam.
[1:20:00]
» Um thank you very much madam. Uh Richard
[1:20:03]
Hanam architect developer known Dan for
[1:20:06]
those whole 50 years. Um,
[1:20:10]
we develop a lot of high-rise buildings,
[1:20:13]
apartments, multif family. I spent 50
[1:20:15]
years as an architect in the city doing
[1:20:18]
these things. What Dan described is the
[1:20:21]
critical path to delivering a project
[1:20:23]
and establishing your scope, your
[1:20:25]
budget, and your financability. And you
[1:20:27]
have none of that information right now.
[1:20:30]
You don't have the weeks of public
[1:20:32]
process to establish what that will be
[1:20:35]
in order to make the deadlines that are
[1:20:37]
being looked at. It's going to just
[1:20:39]
simply take too many cycles.
[1:20:42]
The shortest distance as Dan has
[1:20:44]
provided it and we by the way happen to
[1:20:46]
also as architects hire Gensler to do
[1:20:49]
all these projects for exactly this
[1:20:51]
reason. We have assurityity of
[1:20:53]
completion of the product in a certain
[1:20:55]
time schedule and they understand what
[1:20:56]
we need to do pricing
[1:20:59]
and that pricing is what everybody's
[1:21:00]
going to be concerned about is do we
[1:21:01]
have the right scope and do we have a
[1:21:03]
reasonable set of numbers that when we
[1:21:05]
go for before the public for financing
[1:21:08]
we can stand behind it and make sure the
[1:21:10]
project that we want to bring on can be
[1:21:12]
delivered within that framework. The bad
[1:21:15]
part is to go for it and be wrong and
[1:21:17]
then you have to go back and then you
[1:21:19]
stop. So in order to not stop, you have
[1:21:22]
to shorten the time frame. One way
[1:21:25]
quickly to look at it is a backoff
[1:21:27]
schedule from the due date for this
[1:21:31]
election and you're going to find out
[1:21:33]
that you're three weeks behind schedule
[1:21:35]
because you can't get there unless you
[1:21:37]
make this decision. So from that
[1:21:39]
standpoint alone, shity of information,
[1:21:42]
quality of work, this still leaves
[1:21:44]
totally open the discussion of what
[1:21:46]
happens after you get to that point of
[1:21:48]
scope and budget. and then you're free
[1:21:50]
to do what you want and you have time.
[1:21:53]
But right now, you really don't. So,
[1:21:55]
thank you.
[1:22:11]
Hi, Laura Conroe. Um, first of all,
[1:22:14]
friends, support the town hiring an
[1:22:17]
architect to draft schematic designs for
[1:22:21]
the center that include a fire station.
[1:22:24]
The people of this town want a fire
[1:22:27]
station back. Um, I think it's important
[1:22:31]
to keep in mind, which it seems to be
[1:22:33]
getting lost sight of by some of the
[1:22:35]
comments that I've heard made made
[1:22:37]
today, is that our town is very lucky.
[1:22:40]
We are not a large city. Um we are very
[1:22:44]
lucky that we are a small town that have
[1:22:47]
dedicated citizens that truly want um to
[1:22:53]
deliver to this town a fire station in a
[1:22:57]
very coste effective way. It has been
[1:23:01]
demonstrated over and over again that
[1:23:03]
there are dedicated people who have
[1:23:07]
expertise in construction and
[1:23:09]
architecture that have shown time and
[1:23:11]
time again that this project can be done
[1:23:16]
and can be done cost effectively. Um and
[1:23:20]
yet it seems and it's very frustrating
[1:23:23]
that this seems to get ignored. the
[1:23:26]
citizens committee which was um approved
[1:23:30]
and was supported have shown that a fire
[1:23:33]
station design is possible in a
[1:23:36]
costeffective way. You have a whole
[1:23:38]
committee of town residents that have
[1:23:41]
expertise in construction and in
[1:23:43]
architecture. You heard Dan today talk
[1:23:47]
about it. You've have the friends commit
[1:23:51]
the friends who have two individuals
[1:23:55]
that are expertise is construction that
[1:23:58]
have demonstrated and shown that cost
[1:24:00]
effectively
[1:24:02]
um this can be built in numbers that are
[1:24:06]
much lower than the numbers the town was
[1:24:10]
floating several years ago and still
[1:24:12]
keep being cited that are inaccurate.
[1:24:16]
And um it's time that the council leans
[1:24:19]
on the experts in this town and believes
[1:24:23]
what they are presenting to you. There is an incredible
[1:24:28]
um divisiveness that there is this
[1:24:31]
resistance to to believe what these
[1:24:34]
experts in our town who have devoted
[1:24:37]
their time for free out of the goodness
[1:24:40]
of making sure that this town can have a
[1:24:42]
fire station. Um, and you should just
[1:24:45]
embrace that. There is another town many
[1:24:49]
years ago that they needed to rebuild
[1:24:52]
their school, the town of Piedmont. they
[1:24:55]
couldn't. They then finally um used
[1:24:58]
architects and a construction company in
[1:25:00]
their own town to get the job done that
[1:25:03]
they got numbers could do the project
[1:25:07]
because they leaned on and embraced and
[1:25:10]
relied on people in their little town to
[1:25:13]
get the job done. That's the same thing
[1:25:15]
here. Lean on the people in this town
[1:25:18]
who have the expertise that know how to
[1:25:21]
complete this project cost effectively.
[1:25:23]
you're going to get more from them than
[1:25:26]
you are hiring some third-party
[1:25:28]
consultant who has no genuine interest
[1:25:32]
or vested um commitment to making sure
[1:25:36]
there's a fire station. We all want a
[1:25:38]
fire station. Everybody wants a fire
[1:25:40]
station in their town. Believe the
[1:25:43]
people that have devoted their time and
[1:25:45]
expertise to show that it's possible. I
[1:25:48]
don't understand why why members on town
[1:25:51]
council and um on staff just keep
[1:25:54]
resisting this fact. Thank you.
[1:25:58]
>> Thank you, Laura. Anybody else?
[1:26:02]
Tom.
[1:26:04]
Uh I'm Tom Gaffne, a town resident, and
[1:26:07]
I uh strongly encourage the council to
[1:26:11]
adopt a speed up action on proceeding
[1:26:15]
with this project. I think redoing the
[1:26:18]
master plan, it will get done if you
[1:26:21]
hire the correct architect. So, um,
[1:26:24]
please consider uh the fact that you're
[1:26:27]
not paying for the architecture for the
[1:26:30]
final consideration as Dan has told you
[1:26:33]
and it's time for the town to get
[1:26:35]
together so that uh we can because we're
[1:26:38]
going to have to to to approve a bond
[1:26:40]
issue and I think uh once we get a a
[1:26:43]
good design and some good cost cost
[1:26:46]
estimates then we can proceed with a lot
[1:26:48]
of confidence. So, thank you very much.
[1:26:53]
Bill.
[1:26:59]
» Hi, Bill Poland. Um,
[1:27:03]
resident of the town. I just want to say
[1:27:07]
that having worked on the committee for
[1:27:11]
these past months and have known the guy
[1:27:14]
for for many many years. What's been
[1:27:19]
offered up by Dan is extraordinary.
[1:27:23]
He's is the most altruistic person I've
[1:27:26]
been around in many many years. So we
[1:27:29]
have the benefit of going slowly in one
[1:27:34]
fashion in that you all are allowed to
[1:27:36]
many other decisions but in the meantime
[1:27:39]
he gets us on the right track out of the
[1:27:41]
gates so that we can meet the various
[1:27:43]
deadlines that that have been talked
[1:27:47]
about.
[1:27:49]
So thank you.
[1:27:52]
>> Thank you. Anyone else in the chamber?
[1:27:55]
Anyone online? Zach?
[1:27:57]
>> Yes, mayor. There's two online. Molly,
[1:28:00]
can you please unmute?
[1:28:05]
» Hi there. Can you hear me?
[1:28:07]
>> Yes, we could hear you.
[1:28:08]
>> Yes.
[1:28:09]
>> Uh, I'm Molly Gamble, 14 Norwood. Um,
[1:28:13]
and my message to the council and staff,
[1:28:16]
um, is to take Dan Wein's lead. Um, I
[1:28:19]
think your time is up. Uh the residents
[1:28:22]
have been watching and listening and
[1:28:25]
waiting as this conversation gets lost
[1:28:27]
in a bureaucratic morass for at least
[1:28:30]
six years and it's actually much longer.
[1:28:34]
Um and the process that has unfolded is
[1:28:37]
really unrecognizable to me as a
[1:28:39]
lifelong resident of Ross.
[1:28:42]
um you've had years to get this done and
[1:28:46]
through all these years the cost
[1:28:47]
projections just rise and we just keep
[1:28:50]
shuffling the papers to show that the
[1:28:53]
costs just keep rising and it's a
[1:28:55]
complicated process as Christa outlined.
[1:28:59]
Um but the town needs the process to
[1:29:02]
change. Um, the process that the town
[1:29:06]
has been using for years since this
[1:29:08]
decision was made in 2019, it's not
[1:29:11]
working anymore.
[1:29:13]
You are losing precious time. You are
[1:29:16]
losing precious support. You are losing
[1:29:19]
credibility and trust to ever get this
[1:29:21]
project done. The project plan changed
[1:29:25]
in May, so change your plan to get it
[1:29:28]
done as soon as possible. Thank you.
[1:29:33]
Anybody else?
[1:29:35]
>> Yes. Uh Stephanie DeMarco, please
[1:29:37]
unmute.
[1:29:43]
» Hi, can you hear me?
[1:29:44]
>> Yes.
[1:29:45]
>> Okay. Um I wanted to share the
[1:29:47]
perspective of uh friends of Ross
[1:29:50]
Firehouse. So we were very encouraged by
[1:29:52]
the CAC committee concept in April and
[1:29:55]
the uh unanimous support of the council.
[1:29:58]
Um, we've always had a single single
[1:30:00]
objective, restoring a fully operational
[1:30:03]
fire station in Ross. We've repeatedly
[1:30:05]
stated that we would consider
[1:30:06]
withdrawing our ballot initiative if the
[1:30:08]
town made a clear and binding commitment
[1:30:10]
to achieve that objective.
[1:30:12]
Unfortunately, little meaningful
[1:30:15]
progress has occurred since April.
[1:30:17]
Rather than moving forward with hiring
[1:30:18]
an architect to create the schematic
[1:30:20]
design for a new fire station consistent
[1:30:22]
with the CAC proposal, the council
[1:30:25]
instead chose to hire a new consultant
[1:30:27]
to do further study and update the
[1:30:29]
facilities master plan. As a result, the
[1:30:31]
amended plan will not be completed until
[1:30:33]
later this fall, well after the August
[1:30:36]
7th deadline by which friends must
[1:30:38]
decide whether to draw withdraw the
[1:30:40]
initiative. The staff report circulated
[1:30:42]
ahead of the special meeting today as as
[1:30:45]
Matt has pointed out asserts that the
[1:30:48]
friends dem made demands to the town
[1:30:50]
council. We want to set the record
[1:30:52]
straight. We have never made any demands
[1:30:54]
to the council, the town or its staff.
[1:30:57]
The delays in moving forward on this
[1:30:59]
project have nothing to do with the
[1:31:01]
initiative. The pattern of delays,
[1:31:03]
hiring more and more consultants, but
[1:31:05]
not an architect, and escalating budgets
[1:31:07]
has unfortunately characterized this
[1:31:09]
project for many, many years. We welcome
[1:31:12]
the opportunity to avoid a divisive
[1:31:14]
election and unite the town community
[1:31:17]
over a shared solution. The CAC plan
[1:31:20]
provides a path forward, rebuilding the
[1:31:22]
town center in a cost-effective ma
[1:31:24]
manner, including a fire station. We
[1:31:27]
encourage the council to adopt the CAC
[1:31:29]
plan, commit to rebuilding the fire
[1:31:31]
station, and hire an architect. Then we
[1:31:34]
can begin the important work of
[1:31:35]
restoring the fire and emergency medical
[1:31:37]
services that Ross residents want, need,
[1:31:40]
and deserve. Thank you.
[1:31:45]
» Thank you. Anyone else, Zach, online?
[1:31:48]
>> No one else online. Mayor
[1:31:49]
>> Julie.
[1:31:50]
>> Yes. Before you close public comment,
[1:31:52]
could I pose some additional questions
[1:31:55]
to to Dan if still online?
[1:31:57]
>> Yes, Dan. Hi, Bill Kercher.
[1:32:01]
>> Just we're I'm trying to sort out the time deadlines here. Um I think we
[1:32:06]
all agree that time's of the essence. We
[1:32:08]
want to get through this uh schematic
[1:32:12]
design process and have numbers by uh
[1:32:16]
the deadline which is I think let's say
[1:32:19]
at the end of November maybe before that
[1:32:23]
um and the the the question we have is
[1:32:25]
do we just short circuit this this the
[1:32:28]
whole thing now before the all the RFPs
[1:32:32]
are responded to and uh move ahead with with hiring a preferred uh
[1:32:38]
candidate or do we wait for those u
[1:32:42]
remaining RFPs to to come through and
[1:32:45]
have some further process and it's not
[1:32:48]
clear to me uh you know what what
[1:32:51]
difference I mean I guess my question is
[1:32:54]
how much of a difference does it make in
[1:32:57]
terms of being able to get to the point
[1:32:59]
of say the council approving the
[1:33:02]
contract which the contract which the
[1:33:03]
council has to do meaning it would have
[1:33:05]
to be negotiated by say the April
[1:33:08]
meeting, I mean August meeting. Is that realistic? I don't know how long
[1:33:13]
this process takes. Um and particularly
[1:33:16]
if you're going to wait for all the RFPs
[1:33:18]
to come in.
[1:33:20]
>> Yeah. Um I think we could work backwards
[1:33:23]
from it, but let's assume that schematic
[1:33:25]
design will take somewhere between 12
[1:33:29]
and ideally 14 weeks.
[1:33:33]
So I think it I think there's a number
[1:33:35]
of questions that come to mind. One is clarification of the scope for this
[1:33:41]
next phase updating the master planning
[1:33:44]
and doing some level of schematics. So
[1:33:46]
that is going to take some time right
[1:33:49]
because they're going to have to clarify
[1:33:50]
the scope going to have to get it back
[1:33:51]
to an architect and architect's going to
[1:33:53]
have to respond. So if so if we were to
[1:33:56]
go through the process, I
[1:33:58]
[clears throat] guess it would be two
[1:34:00]
weeks out if it would be possible and I
[1:34:03]
don't know how it works with the town
[1:34:05]
council schedule to be able to get an
[1:34:08]
architect on board and start negotiating
[1:34:11]
the contract immediately after that. So
[1:34:14]
we had somebody let's say on board
[1:34:17]
within three to four weeks. So that
[1:34:19]
would take us to the end of July. Then
[1:34:22]
you've got August, September, October,
[1:34:25]
you're in the early part of November.
[1:34:29]
And assuming I I'll turn to Jeff now for
[1:34:31]
a second. If we had a very comprehensive
[1:34:34]
package, we had all of our cost
[1:34:36]
estimating, we had all the engineering
[1:34:38]
work that needed to be done, all the
[1:34:40]
backup stuff. Is that say first second
[1:34:44]
week of November realistic in terms of
[1:34:46]
being able to meet the deadlines that we
[1:34:49]
need to meet in terms of a ballot? I
[1:34:51]
mean initiative for a bond
[1:34:59]
» and that would be for Jeff. So I don't
[1:35:01]
So I think that you know we could get
[1:35:03]
everything done by the first part of
[1:35:04]
November and then the question is how
[1:35:08]
quickly could we get what we need to get
[1:35:10]
to the town for a vote? You know, how we
[1:35:13]
describe the bond measure in the u in
[1:35:18]
the ballot has a ton to do with how
[1:35:21]
successful we are going to be to get the
[1:35:22]
71% we need. And in order to have that
[1:35:26]
well written, we've got to have at least
[1:35:28]
a week or two before to plan this out.
[1:35:32]
You don't get it on November X and then
[1:35:35]
file on X plus one. You just don't. Is
[1:35:39]
that fair? Anybody else?
[1:35:45]
So [clears throat] I I guess I guess in
[1:35:47]
the conclusion would be that if going
[1:35:49]
through this next two weeks, I mean look
[1:35:51]
at we're only 10 days away. I think the
[1:35:53]
question is how quickly can we move
[1:35:54]
after that after all the submittals come
[1:35:56]
in to negotiate a a contract with an
[1:35:59]
architect. And if we can do it in a
[1:36:00]
couple three weeks, which we should be
[1:36:03]
able to, I just don't know what it
[1:36:04]
requires in terms of town council's
[1:36:06]
approval and any other sort of internal
[1:36:09]
process that needs to take place. I
[1:36:11]
mean, judging from emails from Christa
[1:36:14]
about our availability in the second
[1:36:16]
half of July, it seems to me that unless
[1:36:19]
we move in early mid early to mid July,
[1:36:23]
so the July 13th or whatever, the July 9
[1:36:25]
meeting, I don't think we make those
[1:36:27]
deadlines. I don't think we get an
[1:36:29]
architect on board until the August
[1:36:30]
meeting, that's August 13, and that puts
[1:36:33]
us way behind in terms of trying to meet
[1:36:36]
that November deadline. So I guess my
[1:36:38]
question to to you Jeff and Dan and also
[1:36:41]
to Ben is what what is what is the way
[1:36:44]
to fasttrack what is the fastest way we
[1:36:47]
could fasttrack bringing an architect on
[1:36:49]
board to do what we've talked about that
[1:36:51]
is clarify the scope do schematics and
[1:36:54]
have a budget. So if if th if those are
[1:36:56]
our projects now um what can that be
[1:37:00]
fasttracked so that we're making a
[1:37:02]
decision at the July meeting?
[1:37:05]
Sure, you could even Yes. I mean, I
[1:37:08]
think we could take you could take
[1:37:09]
Christa's RFP as it stands right now.
[1:37:13]
Um, as we talked before, add additional
[1:37:16]
information to it in terms of
[1:37:17]
deliverables and scope. Um, take a look
[1:37:20]
at the RFQS that came in, select the
[1:37:23]
architect. I don't whatever process you
[1:37:26]
go through in selecting the architect.
[1:37:27]
Get an architect in and any I think any
[1:37:31]
good architect would work under a
[1:37:33]
letter. It doesn't you don't need to
[1:37:35]
have a a final contract at that point,
[1:37:38]
but they would certainly be able to give
[1:37:39]
you a cost of doing schematic design
[1:37:43]
based on what we have outlined right
[1:37:44]
now. Um, and that would no doubt be a
[1:37:47]
lump sum. It could be, you know, I don't
[1:37:49]
I would not recommend going TNM with the
[1:37:51]
not to exceed. I just do lumpsum I think
[1:37:54]
is the easiest way to do as long as we
[1:37:55]
have a clear scope. But you could get
[1:37:57]
them started on a on a letter intent and
[1:38:00]
that would be it. and the final
[1:38:02]
negotiations or the final contract, you
[1:38:05]
know, the terms and conditions and such
[1:38:06]
could be approved at a later date. I
[1:38:08]
just think getting somebody on board and
[1:38:10]
getting them moving as quickly as we
[1:38:12]
can, you know, the better off we're
[1:38:14]
going to be.
[1:38:15]
>> So, Ben, is there any reason we can't do
[1:38:18]
that? basically choose an architect at
[1:38:21]
the July 9 meeting.
[1:38:25]
And if we're doing that, are we basing
[1:38:26]
that on the RF uh cues from uh May or do
[1:38:32]
we are we waiting for the RFPs from
[1:38:35]
early July? Elizabeth,
[1:38:38]
>> I think what Mr. was saying and which I
[1:38:40]
would agree with is you should you
[1:38:41]
should definitely wait for the RFP
[1:38:43]
response for July 2nd and then negotiate
[1:38:46]
with whoever you want to negotiate with
[1:38:49]
based on those responses a a revised
[1:38:52]
scope or maybe it's not revised maybe
[1:38:54]
the scope that comes in is exactly what
[1:38:55]
we were thinking one of the things Mr.
[1:38:57]
said was it seems like a lot of people
[1:38:59]
are talking past each other. We looked
[1:39:01]
at a resolution that the council
[1:39:02]
approved in May. A lot of these
[1:39:04]
components that are on the agenda today
[1:39:06]
are already being considered as part of
[1:39:07]
the master plan amendment process. The
[1:39:10]
validation, the cost updates, all those
[1:39:13]
things are coming forward in that RFP
[1:39:15]
which is due on July 2nd. So what I
[1:39:18]
would recommend is you get those
[1:39:20]
responses come in, you negotiate with
[1:39:23]
the architects however you think is
[1:39:25]
appropriate based on those responses and
[1:39:28]
get the scope and the agreement ready
[1:39:30]
for approval as soon as possible. And if
[1:39:33]
that means having a special meeting in
[1:39:35]
July, then we have a special meeting in
[1:39:37]
July. I doubt July 9th is going to
[1:39:38]
happen if they're coming on July 2nd,
[1:39:40]
but middle of July or the third week of
[1:39:43]
July seems very reasonable as far as
[1:39:45]
getting a scope hammered out and a
[1:39:48]
professional services agreement signed.
[1:39:51]
>> I I don't think that I mean, Christo,
[1:39:52]
you can correct me, but I thought that
[1:39:54]
you said that the council absolutely has
[1:39:55]
no way to meet between July 9 and August
[1:39:58]
7 or something. you know, I think we can
[1:40:01]
work out those details. And I think this
[1:40:03]
meeting and the, you know, the meeting
[1:40:06]
that we had on Friday underscores as
[1:40:09]
well as the schedule to try to meet the
[1:40:10]
December 4 filing deadline that we all
[1:40:14]
need to be flexible and available and
[1:40:17]
just because you're, you know, on
[1:40:19]
vacation, just like you're on vacation,
[1:40:21]
Elizabeth, but you called in and here
[1:40:22]
you are on a Wednesday afternoon when
[1:40:25]
you could be at the beach. So we all
[1:40:27]
we're we're all very committed and
[1:40:29]
dedicated to getting this done. So um
[1:40:33]
Richard, did you have one more thing
[1:40:35]
brief thing to No. Okay. So I want to
[1:40:37]
bring it back for um discussion and
[1:40:40]
direction to um provide to the town
[1:40:44]
manager. Um what I'm hearing is
[1:40:48]
um we should wait for the RFPs to come
[1:40:51]
in on July 2nd. We should meet
[1:40:54]
expeditiously thereafter and from that
[1:40:57]
choose an architect to work on
[1:40:59]
schematics and cost information and the
[1:41:03]
other items that are identified in that
[1:41:05]
earlier what is it resolution 2623
[1:41:09]
um and time is of the essence and in
[1:41:12]
order to meet this December 4th filing
[1:41:15]
is going to be a herculean effort by the
[1:41:18]
council by the consultants by the
[1:41:20]
architect by staff
[1:41:22]
by the CAC, by everyone. Um, and I think
[1:41:27]
we're all committed to doing that. We
[1:41:29]
all want what's best for the town and so
[1:41:32]
we need to move forward. That's my
[1:41:34]
recommendation.
[1:41:36]
Others?
[1:41:40]
Well, I think we should probably pick
[1:41:42]
dates if we're doing that, Julie, so
[1:41:43]
that we really are moving forward. I
[1:41:45]
mean, I we'd heard that these RFPs are
[1:41:48]
due on the 2nd. I I mean I get that you
[1:41:50]
know month Friday is a holiday but if we
[1:41:53]
want to have a council discussion on
[1:41:56]
July 9 you know why not meet on July 6
[1:42:00]
or 7 to go over the RFPs so that we can
[1:42:03]
present something to the council on July
[1:42:04]
9.
[1:42:06]
>> I I am confident that you and I and
[1:42:09]
Christa can work work and staff can work
[1:42:12]
offline to be as prepared as we possibly
[1:42:15]
can by July 9th. I I think we we are all
[1:42:20]
hearing the urgency of what we need to
[1:42:23]
do. So, I'm we will get that done. I
[1:42:28]
don't want to sit here and go over dates
[1:42:29]
right now with there's a lot of people
[1:42:31]
here, Elizabeth, that would be leaving.
[1:42:35]
[laughter]
[1:42:37]
>> I I have some comments if I may.
[1:42:40]
>> Yep. Matt, go ahead. So, we met um June
[1:42:44]
11th and I was the only person who voted
[1:42:46]
against this plan and now we're here we
[1:42:48]
are again. And I would just say this has
[1:42:51]
just been a complete failure of
[1:42:53]
leadership. And I personally believe we
[1:42:57]
should just appoint Gendler and Dan
[1:43:00]
Weiny to see this process through. And I
[1:43:04]
am just I I don't need any more
[1:43:06]
information. I don't need any RFPs. We have experts and they actually live
[1:43:12]
in town and are very dedicated and have
[1:43:14]
worked for free for a number of months
[1:43:17]
to bring us to this point. And you know
[1:43:20]
I you know there are people on this
[1:43:22]
council that have been on it for almost
[1:43:24]
a decade and past that. There was many
[1:43:26]
opportunities to get us this project
[1:43:29]
done and it hasn't. And in fact, I feel
[1:43:32]
like it was the worst decision ever to
[1:43:35]
close the fire station down under false
[1:43:37]
pretenses that we can't afford it. And
[1:43:40]
so here we are. The time to get going is
[1:43:42]
now. We have a group of citizens, 10
[1:43:46]
people of experts that live in town and
[1:43:48]
care about this. I have no fear that
[1:43:51]
they're trying to price gouge anybody. I
[1:43:54]
think they're dedicating their time and
[1:43:56]
service out of love of their community.
[1:43:58]
And I think that any more wasted time on
[1:44:02]
process is just going to look terrible
[1:44:05]
to the community. It will look like a
[1:44:08]
failure of leadership yet again. And we
[1:44:10]
just need to put this to bed. Appoint
[1:44:13]
Gendler and Dan Weiny and the committee
[1:44:16]
to work on this project on our behalf
[1:44:19]
and set the process forward so that we
[1:44:22]
can move forward together in clarity.
[1:44:25]
Get it out of this council. let the
[1:44:28]
experts do their job and stop running
[1:44:31]
around pretending that we know what
[1:44:33]
we're doing because if we did this
[1:44:36]
project would have been done a long time
[1:44:39]
ago.
[1:44:41]
>> So Matt, I I agree with you. And Ben, do
[1:44:43]
we have the ability to appoint an
[1:44:46]
architect firm today?
[1:44:48]
>> No, that's not on the agenda, nor would
[1:44:50]
it be uh you don't have a contract
[1:44:53]
before you. You don't have So the answer
[1:44:55]
is no. That would violate the Brown Act.
[1:44:58]
>> What would it take?
[1:44:59]
>> Can No, it says in there that we can
[1:45:01]
direct staff to negotiate with a
[1:45:04]
selected preferred vendor on a contract.
[1:45:07]
That is completely within our
[1:45:08]
discretion.
[1:45:12]
That is what I'm saying. Direct staff to
[1:45:14]
negotiate a contract with Gendler to see
[1:45:18]
this project forward.
[1:45:19]
>> No, it doesn't. And that is on that is
[1:45:21]
actually on the agenda is one of the
[1:45:23]
options
[1:45:23]
>> the architect to bring bring back the
[1:45:25]
agreement later not to choose the
[1:45:26]
architect tonight. We cannot do that
[1:45:28]
this afternoon.
[1:45:29]
>> That would be a Brown Act violation.
[1:45:31]
Council member Salter and I'm not going
[1:45:33]
to let
[1:45:33]
>> it's one of the options listed in the
[1:45:35]
agenda.
[1:45:37]
>> Um
[1:45:38]
>> that that would be my recommendation.
[1:45:40]
>> Bill or Terry, do you have things to
[1:45:43]
say? Okay. Uh,
[1:45:47]
I support moving on with the RFP
[1:45:50]
process. I think Christa gets the
[1:45:53]
importance of moving as quickly as we
[1:45:55]
can. Um, I'm not fond of uh a uh what is
[1:46:01]
it? Just appointing some hiring an
[1:46:04]
architect to do it without any um uh
[1:46:08]
opportunity for other architects to
[1:46:10]
weigh in. We have an RFP process. Let's
[1:46:13]
finish it. I think if we dropped it, to
[1:46:15]
be perfectly honest, I think our
[1:46:17]
credibility would be zero.
[1:46:20]
Um, and I think that even if legally it
[1:46:24]
would be not a conflict of interest to hire just make a decision to hire an
[1:46:30]
architect without any competition,
[1:46:33]
there's also the issue of perceived
[1:46:35]
conflict of interest which can also
[1:46:38]
really hinder the town.
[1:46:40]
Um, I think it's going to be an
[1:46:43]
exceedingly busy four months. I was
[1:46:46]
listening to some of the things that
[1:46:48]
needed to be done. For example, refine
[1:46:51]
the project description,
[1:46:53]
begin environmental review,
[1:46:56]
select the project delivery meth
[1:46:58]
alternative project delivery methods,
[1:47:00]
update the master plan, begin the
[1:47:02]
process to hire an architect, and do the
[1:47:05]
schematic design. It's a lot. Are you
[1:47:08]
ready for it? I hope so. And I think
[1:47:11]
that the council is interested in
[1:47:14]
working with you to make this happen as
[1:47:16]
quickly as possible. And I know some of
[1:47:19]
us be more than willing to meet night
[1:47:21]
and day to move it along. So, um, so I'm
[1:47:26]
for continuing on with the process that
[1:47:28]
we started.
[1:47:32]
» As as I understand it, based on Chris's
[1:47:35]
report and what she's indicated this
[1:47:38]
afternoon, she has three concerns. One
[1:47:42]
is what we're doing is not what would be
[1:47:45]
described as best practices, and I'd
[1:47:48]
agree with that if we had more time, but
[1:47:50]
we don't. And we're also halfway or
[1:47:52]
somewhere. We're well into the process.
[1:47:54]
We're not starting from scratch. If we
[1:47:56]
had more time, then I I I suppose I
[1:48:00]
would be my concern would be different.
[1:48:04]
Transparency and fairness. Um
[1:48:08]
transparency and fairness sort of
[1:48:10]
militates in favor of at least getting
[1:48:12]
all the proposals that we have
[1:48:14]
requested. how long we take going
[1:48:17]
through those and so forth. Uh I think
[1:48:19]
we should be ready to really really roll
[1:48:21]
and maybe we can start beforehand.
[1:48:24]
But that is why I think we should not
[1:48:26]
just well there's also the Brown Act
[1:48:29]
problem. But I don't think we should
[1:48:31]
just say okay let's go with Gendler or
[1:48:33]
something today. I I I I I would not be
[1:48:37]
in favor of that. Nine days is something
[1:48:39]
I think we can live with. But we we we I
[1:48:43]
think we're committed to the urgency of
[1:48:44]
this. The last point was possible
[1:48:48]
duplication and and having to to
[1:48:52]
actually end this ended up costing more
[1:48:54]
or taking longer when we're trying to
[1:48:56]
save time. If we had all the time in the
[1:48:59]
world, I would agree with that. Let's
[1:49:00]
take it step by step. But after hearing
[1:49:03]
Dan Weiny particularly uh describe this
[1:49:07]
whole process, the schematic design
[1:49:09]
process, I I have I don't actually I
[1:49:12]
think that removed that concern. I think
[1:49:14]
we have a a clear demarcation between
[1:49:17]
the design phase and the schematic
[1:49:20]
design schematic phase
[1:49:22]
and the then the detailed architectural
[1:49:25]
plans and and I think we can segment
[1:49:28]
this. I think we can divide it further
[1:49:30]
into stages. I think it's possible when
[1:49:32]
we negotiate the contract we could say
[1:49:35]
by a certain date we would like this
[1:49:38]
information for the council. We would
[1:49:39]
like this issue resolved to the extent
[1:49:42]
you can and you know pick an issue where
[1:49:45]
the public works department goes where
[1:49:48]
you know what are we looking at with the
[1:49:49]
firehouse do we have to elevate it or
[1:49:51]
not
[1:49:53]
um and and work with that. I mean,
[1:49:56]
nobody can, you know, I mean, it happens
[1:49:58]
when it happens, but if we have that
[1:50:01]
kind of detail in advance, I think it'll
[1:50:03]
move along more rapidly. And I do agree
[1:50:05]
with take your finish date and work back
[1:50:07]
from there to make sure you've given
[1:50:10]
yourself a cushion and you can do it.
[1:50:12]
Uh, with the idea being we have a
[1:50:14]
complete package to go to the voters
[1:50:16]
with, not all the details. That's later.
[1:50:18]
That's after the architects get
[1:50:20]
involved. That can change. So, that's
[1:50:23]
what I would think. I I would agree with
[1:50:25]
that, but um I I do think we ought to
[1:50:28]
get this nailed down just as soon as we
[1:50:30]
can.
[1:50:32]
>> So I um I still don't understand why we
[1:50:35]
need to wait for RFPs. I mean, first I
[1:50:38]
think it was way overreaching to send it
[1:50:40]
to 10 different architects when we only
[1:50:42]
had three or four on a short list to
[1:50:44]
begin with. But leaving that aside, I I
[1:50:48]
I'm hearing that we need to hire an
[1:50:49]
architect, choose an architect quickly.
[1:50:51]
We have RFQS from from a few months ago.
[1:50:55]
I don't understand what's wrong with
[1:50:56]
just using those and choosing an
[1:50:58]
architect as quickly as we can. I don't
[1:51:01]
understand why we need RFPs to choose an
[1:51:03]
architect. So, and and you know, yes,
[1:51:06]
counting back makes is important to be
[1:51:09]
sure that we have a cushion, but I don't
[1:51:10]
think we have a cushion unless we're
[1:51:11]
actually choosing an architect on July
[1:51:14]
9. So, the only way I'd be okay with
[1:51:16]
waiting for these RFPs is if we have it
[1:51:19]
scheduled that we that we recommend an
[1:51:21]
architect either based on the RFQS from
[1:51:24]
last spring or the RFPs from July 3 or
[1:51:27]
two or whatever and and that we we
[1:51:29]
recommend an architect on July 9. I
[1:51:32]
think anything less than that is too
[1:51:33]
much of a delay. And if and again, I
[1:51:35]
don't see why we need to wait for the
[1:51:37]
RFPs. We have RFQS. I I just don't I I
[1:51:41]
don't get the whole RFP process
[1:51:44]
and I would like to make sure that we
[1:51:45]
choose an architect on July 9 and you
[1:51:49]
and base that on the RFQS that we've
[1:51:51]
already received or sooner or choose an
[1:51:54]
architect sooner a special meeting.
[1:52:02]
I I think we we're all committed to
[1:52:04]
expedite this as quickly as possible and
[1:52:06]
to the extent we can get the RFPs by
[1:52:11]
July 2nd and distill them down and come
[1:52:14]
to the council with a recommendation on
[1:52:17]
July 9th, which would have to be in the
[1:52:19]
packet the Friday before. And I think
[1:52:21]
there's a holiday in there, too. So,
[1:52:23]
that's going to be I don't even know if
[1:52:25]
that's possible.
[1:52:27]
Christa is saying that it's not possible
[1:52:29]
in terms of getting that information
[1:52:31]
into the packet. So, we're going to have a special meeting probably the
[1:52:35]
following week um to you and I can meet
[1:52:39]
and with staff and we'll have a really
[1:52:41]
good idea of what we're doing and then
[1:52:43]
we'll have to have a a special meeting.
[1:52:45]
Hopefully, it will be very quick pro-
[1:52:47]
fora special meeting the following week.
[1:52:50]
Um, we have to set we we know the end
[1:52:55]
deadline, the December 4th deadline, but
[1:52:57]
we also have to be realistic about, you
[1:53:00]
know, what staff can do and what's
[1:53:02]
entailed. So, and I do want to just say
[1:53:05]
one other thing. Um,
[1:53:08]
I have been on the council since 2017
[1:53:11]
and I have been working literally almost
[1:53:14]
every month on these facilities and Dan
[1:53:18]
Weiny and many others started working on
[1:53:20]
these facilities in 2000 26 years ago
[1:53:25]
and I don't think anyone ever
[1:53:27]
anticipated how difficult this issue
[1:53:30]
would be and we want to do this right. I
[1:53:34]
don't want any other council in the next
[1:53:37]
100 years to have to deal with these
[1:53:39]
issues. It's too divisive. It's too
[1:53:42]
painful. It's too upsetting.
[1:53:45]
So, we need to do this right. And we
[1:53:47]
understand the schedule, but we can't
[1:53:50]
make compromises just to meet a
[1:53:51]
schedule. We have to do this right.
[1:53:54]
So, I think I think I'm not sure we have
[1:53:57]
anything else left to left to discuss.
[1:53:59]
It was just
[1:54:00]
>> I I No, but I wanted to add to Alyssa's.
[1:54:03]
Why can't you use the RFQS? Was there
[1:54:05]
not enough information in there maybe to make a good judgment?
[1:54:09]
>> There's no cost in the RFQS. They're
[1:54:12]
just like beautiful brochures with
[1:54:14]
pictures of past projects.
[1:54:17]
>> But that's what we were planning to use
[1:54:19]
to choose to recommend an architect
[1:54:21]
until the question of how what's the
[1:54:23]
procure procurement going to be. And so
[1:54:25]
then that [clears throat] morphed into
[1:54:27]
let's update the master plan and that
[1:54:29]
morphed into let's sending out RFPs. But
[1:54:31]
if we back up, we did have RFQS that we
[1:54:34]
meant to use to choose an architect. So
[1:54:37]
I still I mean if I'm out voted that's the way it goes. But I I still
[1:54:40]
don't see why we can't back up to that.
[1:54:43]
>> I think Christa was being really prudent
[1:54:45]
in getting those RFQS so that we would
[1:54:47]
be positioned once there was a decision.
[1:54:49]
we would be nimble and flexible and be
[1:54:52]
able to go out with RFQS or RFPs, sorry.
[1:54:57]
So,
[1:54:58]
you know, we can beat this horse to
[1:55:00]
death. I think we've beaten it enough.
[1:55:02]
Ben, do you have anything to add?
[1:55:05]
>> No, I mean, I would just add, Elizabeth,
[1:55:07]
when you look at the resolution that
[1:55:09]
required us to do the RFP, it has a lot
[1:55:11]
of information in there. That's exactly
[1:55:13]
the information that is going to be
[1:55:15]
helpful for the schematics that Dan Wein
[1:55:17]
is talking about. So I think that's why
[1:55:19]
it just makes sense to get the RFPs,
[1:55:21]
which you don't have that in the RFQS.
[1:55:23]
The RFQ is just aformational sheet about
[1:55:25]
architects and their rates. So you're
[1:55:27]
going to have something to work with as
[1:55:29]
far as a scope that they're already
[1:55:30]
responding to, which will have to be
[1:55:32]
massaged a little bit more once you
[1:55:34]
engage in the, you know, review and and
[1:55:36]
discussions with those architects. But
[1:55:39]
um I think the scope of the RFP is going
[1:55:42]
to be a lot more tailored to what it
[1:55:43]
sounds like the town is looking to move
[1:55:46]
forward to the next step in order to get
[1:55:47]
a cost estimate.
[1:55:50]
>> Then I I'm hoping that we can have the
[1:55:53]
town staff commit to having uh a
[1:55:58]
selection meeting. I guess that's Julie,
[1:56:00]
you and me and the committee by the by
[1:56:03]
the next week June the week of June 15.
[1:56:06]
hopefully early in the meet, you know,
[1:56:07]
the the early in the week, Monday, June.
[1:56:10]
>> Give me July. Give me July.
[1:56:11]
>> For July. So, so yeah. Sorry. Uh
[1:56:13]
>> I already have that committee
[1:56:15]
subcommittee meeting scheduled with you
[1:56:18]
both for 2 p.m. on July 9th. I did that
[1:56:22]
like that was done like two weeks ago.
[1:56:24]
>> I already have um I've already sent out
[1:56:27]
a save the date for August 4th as a plan
[1:56:30]
B. And but I need to remind the council
[1:56:34]
I we don't need to get into more to
[1:56:35]
scheduling but you must have three
[1:56:37]
people physically in Ross. So all your
[1:56:41]
intentions of being able to zoom in
[1:56:44]
that's great but you need to have three
[1:56:47]
people here and that is the issue with
[1:56:50]
the availability I have received thus
[1:56:52]
far. It's not staff.
[1:56:55]
So the week of July 13,
[1:56:57]
>> we can continue to discuss, but you need
[1:56:59]
three people here.
[1:57:01]
>> But the week of July 13 is an option if
[1:57:03]
there are three people here. Is that
[1:57:04]
right?
[1:57:11]
» You have one council member that is
[1:57:13]
leaving town on the 15th on an airplane.
[1:57:17]
You have another one that is on the
[1:57:19]
airplane on the 16th.
[1:57:22]
and I will do my best to try to see if I
[1:57:25]
can get it on the 14th. I'm sure those
[1:57:27]
council members that are leaving on
[1:57:28]
airplanes are going to love to have to
[1:57:30]
spend a council meeting, but you know, I I it depends on if we have an
[1:57:35]
agreement in place. I have to bring
[1:57:38]
forward a complete contract
[1:57:43]
with to the council. So, it's not just
[1:57:46]
me. It's not just the council. It
[1:57:48]
depends on the firm. It depends on legal
[1:57:51]
review. It's all I mean there's there's
[1:57:53]
just a lot of going on. There's a lot of
[1:57:55]
different um uh
[1:57:58]
>> Can I can I off to like alter an opinion
[1:58:02]
of what we could do? What about an
[1:58:04]
interim step where we the CAC created
[1:58:08]
this concept with Dan Weiny and Gendler?
[1:58:11]
What about just engaging and we could
[1:58:13]
hire Dan Weiny and Gendler to take that
[1:58:17]
project a little bit further? So why not
[1:58:20]
just start the next step of there and
[1:58:22]
engage just them to keep working because
[1:58:26]
we don't want to lose time in the midst
[1:58:28]
of this process. So instead of you know
[1:58:31]
like let let them continue to work as
[1:58:33]
long as he's obviously Gendler and Denny
[1:58:35]
want to do it but we just sort of engage
[1:58:38]
them to continue working till we figure
[1:58:40]
out the next phase and it's maybe a
[1:58:43]
limited engagement with Gendler to just
[1:58:46]
keep the work moving forward until we've
[1:58:48]
completely all been able to meet and
[1:58:50]
select the person and it might be
[1:58:52]
Gendler at the end of the day but we can
[1:58:54]
at least hire them for an interim
[1:58:55]
period.
[1:58:58]
I'd kind of rather make it the 13th or
[1:59:00]
14th of July if we possibly could
[1:59:02]
because then we've made a a bigger step.
[1:59:05]
But um maybe if we can't do that, maybe
[1:59:08]
yours is
[1:59:08]
>> Yeah. Yeah. If we can by the 13th, you
[1:59:10]
just keep saying we might all be out of
[1:59:12]
town and I would hate to lose a whole
[1:59:14]
month.
[1:59:14]
>> Right. I agree.
[1:59:18]
>> Okay. I think the three of us think we
[1:59:20]
should go forward, receive the RFPs, and
[1:59:23]
then move as expeditiously as possible
[1:59:25]
after we receive the RFPs in eight days.
[1:59:29]
Um, so I I think I think it's a wrap.
[1:59:33]
It's 4 o'clock. Thank you everyone for
[1:59:35]
being here and being online.