Transcript
SOURCE TRANSCRIPT
This transcript is downloaded from the source you provided but we haven't reviewed it for accuracy. Treat it as a starting point, not a verbatim record. You can also request an AI-transcription of the audio file with the button to the left.
[0:37]
>> All right today is Tuesday July 28th 7:09 p.m.
[0:41]
Calling today's meeting into order madam clerk
[0:43]
if you'll take the roll please.
[0:47]
[Roll call]
[0:50]
[Vice Mayor absent]
[0:58]
>> Mayor you have a quorum.
[1:00]
If you'll lead us in the Pledge of Allegiance please.
[1:04]
>> I pledge allegiance to the flag of the United States
[1:06]
of America and to the Republic for which it stands,
[1:06]
one nation under God, indivisible,
[1:07]
with liberty and justice for all.
[1:22]
>> Item two a presentation of fiscal year 2027 budget
[1:25]
and proposed operating millage rate.
[1:27]
Mr. Manager.
[1:30]
>> Thank you mayor.
[1:32]
If I can have our budget manager come up we've prepared a quick ,
[1:40]
we've prepared a presentation on you on the budget but a quick
[1:44]
summary or what the staff is requesting.
[1:47]
Tonight is about setting the millage rate cap or ceiling,
[1:54]
this is where the commission during your September budget
[1:58]
hearings will not be able to go above.
[2:00]
Staff is currently recommending keeping it
[2:03]
flat at 3.883 for that ceiling.
[2:07]
But we have the presentation for you if you can come up please.
[2:30]
>> Okay I'm gonna start with a quick recap on the budget
[2:34]
principles.
[2:35]
So the principles are ensure compliance with policy statutes
[2:39]
and contractual obligations of the town.
[2:42]
It supports building and maintaining infrastructure,
[2:46]
for the community in the long term.
[2:49]
It establishes spending authorization,
[2:52]
safeguards reserves to save financially sound,
[2:56]
so when our audits are done we have a good financial basis
[3:02]
and we come up with a clean opinion on our audits.
[3:08]
And the budget should be transparent affordable
[3:10]
and sustainable.
[3:14]
The elements of the budget the financial document
[3:17]
used to protect future revenues and expenses
[3:20]
for fiscal year time period.
[3:22]
It's a roadmap to carry out the Town Commission's objectives
[3:26]
and strategies.
[3:28]
Revenues are based on property appraiser
[3:33]
values and the military and our state and local estimates
[3:38]
for the General fund.
[3:40]
Expenses expenditures are based on specific needs and services.
[3:46]
We try to maintain reserves and funding for capital program
[3:51]
and the fiscal year starts on October 1st of every year
[3:55]
and that's on September 30th.
[3:57]
On the budget calendar today is our meeting
[4:02]
to discuss the military to advertise on the trim notice.
[4:08]
That'll be a cap, that's today's meeting and on August 4th
[4:12]
by August 4th we need to provide the information to the property
[4:18]
appraiser so that can be advertised on the trim notice
[4:21]
which goes out around mid-August to the 20 something of August.
[4:26]
We have a first public hearing on the budget and the military
[4:31]
for September 8th 5:01 p.m.
[4:35]
And the second and final hearing on September 22nd at 501.
[4:42]
The budget that the town's budget
[4:46]
is based on several funds.
[4:47]
The compliments of the General Fund which is General Government
[4:51]
operations.
[4:52]
We have special revenue funds which is recreation and culture.
[4:59]
We have the building services and transportation.
[5:01]
We have the Capital Projects fund.
[5:04]
Enterprise funds which is our water sewage
[5:08]
funds our stormwater funds solid waste and parking.
[5:11]
And then we have an internal service fund just
[5:15]
called Fleet Management Fund which
[5:16]
we use to maintain and replace our vehicles.
[5:20]
Tonight we'll be discussing basically the general fund.
[5:27]
So revenues from the general fund
[5:31]
are mainly protecting 27 million in revenues.
[5:36]
Our revenues are mainly from ad valorem taxes.
[5:40]
That's 78% and then we have franchise fees
[5:43]
and some other intergovernmental revenues.
[5:47]
Our budget is based on 24.8 million
[5:50]
in projected expenditures.
[5:53]
The majority of it goes to public safety, then
[5:59]
general government and parks and recreation
[6:01]
then physical environment and we have
[6:04]
11% going to transfer to enterprise funds.
[6:09]
The budget, the proposed budget that you
[6:12]
have would return 2.4 million to general fund reserves.
[6:18]
Operating expenditures are 21.5 and 3.1 million
[6:22]
would go to transfer to the enterprise funds.
[6:28]
These are components of our General Fund revenue.
[6:33]
In dollar value.
[6:35]
As you can see it's mainly 21 million
[6:40]
would be from ad valorem revenues.
[6:48]
We would not be using any fund balance to balance the budget
[6:53]
and we would have an excess which
[6:56]
we would return to reserves.
[7:05]
This is the chart is the same as basically the first slide
[7:11]
that we went through.
[7:12]
78% of our revenues for the general fund
[7:15]
are made up of ad valorem revenues.
[7:20]
And our expenditures these are expenditures in dollar values.
[7:26]
Between public safety and general government,
[7:30]
that's the major portion of what our general fund
[7:34]
expenditures are.
[7:38]
We would be transferring out $3,065,000,
[7:43]
2.5 million would be to provide funding for a Steward project
[7:52]
or Steward projects I'm sorry stormwater projects that we need
[7:56]
to work on.
[7:57]
And then balance of 565, 565,000 would be to balance the water
[8:04]
and sewer fund.
[8:05]
Until we complete our rate studies.
[8:18]
Okay so we have a funding policy base
[8:23]
and based on the funding policy, the amount
[8:27]
that we would need to fund, it's a target
[8:31]
we're striving to fund a target for 2027.
[8:34]
Would be approximately $12.6 million
[8:39]
for committed reserves for operations and maintenance.
[8:44]
Then we have a hurricane and disaster reserve.
[8:52]
A budget stabilization reserve and a capital reserve.
[8:57]
Those combined, for fiscal 2027 be it 12.6 million
[9:04]
which means we would increase those reserves by $1.4 million.
[9:09]
Balance is returning to unassigned fund balance would be
[9:13]
$950,000.
[9:15]
We've budgeted that we would have total return to reserves
[9:21]
of two point 2,000,003 82111.
[9:24]
And that's based on a millage rate of 3.8743.
[9:32]
Just a little lower than the current millage rate.
[9:37]
For property values and millage rates.
[9:40]
So we have a small jump at 6.2% increase in our property values.
[9:47]
That's mainly attributable to the existing properties.
[9:52]
Not new construction.
[9:57]
You'll see the same information.
[10:00]
This is over what properties the increases are
[10:04]
and you can see it's mainly driven by the condominium
[10:08]
buildings.
[10:09]
Any property that's in the condominium buildings.
[10:16]
Okay the adjustable value on the,
[10:20]
so the adjustable value is basically it's like market
[10:23]
value.
[10:24]
Then we have what's called the taxable value so that's
[10:28]
after homesteaded properties and only the 10% increase
[10:33]
on non homesteaded properties.
[10:36]
So for the tax above, just values
[10:41]
the condominiums are 59% of the value
[10:44]
but when it comes to their taxable value
[10:48]
they end up being 67% of our tax roll.
[10:52]
And the single family section is 25%
[10:55]
of the just value which is sort of like a market value.
[10:59]
But when it comes to factoring in homesteads
[11:04]
that percentage goes down to 19%.
[11:12]
Taxable values and the millage rates
[11:15]
so you see over ten years how the military has come down.
[11:19]
Gone all the way from 4.8 we're currently at 3.8830.
[11:24]
And the budget is based on 3.8743.
[11:35]
And then the property a -- where do tax dollars go?
[11:41]
So 21% goes to server side.
[11:44]
36% goes to the school board and 40% of your property taxes
[11:48]
go to state county 4% goes to state funding.
[11:57]
So the majority of your taxes go to the school board
[12:01]
and Dade County and only 21% ends up going to Surfside.
[12:10]
Get to the millage rates and tax revenue.
[12:16]
So we're currently in an adopted rate of 3.8830.
[12:21]
We've prepared the budget based on a rate of 3.8743.
[12:27]
And our rollback rate is 3.5221.
[12:33]
And you'll see the revenues that are generated
[12:38]
by those different rates are current rates would generate
[12:45]
1.967 million, the proposed budget
[12:50]
was prepared based on an increase of 1.919.
[12:55]
Almost 1.92.
[12:56]
And the rollback rate would mean no increase in taxes.
[13:05]
The various rates depend on voting.
[13:09]
The voting that's required.
[13:11]
So if we were voting for the 3.8830 we would need a unanimous
[13:17]
vote.
[13:18]
The proposed rate of 3.8743 we would need four votes
[13:23]
of the governing body.
[13:25]
And the rollback rate would require three votes
[13:29]
which is a majority vote.
[13:32]
So today we're going to determine what the capital would
[13:39]
be for the trim notice and once you've
[13:42]
advertised on the trim notice, it's
[13:45]
really setting the ceiling you can't go down
[13:48]
so you could go down afterwards but you can't go up.
[13:52]
Go above that rate.
[13:59]
Based on the budget was prepared based on the 10% tax increase.
[14:04]
Over the rollback rate.
[14:09]
And then this is just how much each millage rate is worth.
[14:17]
So every one millage is worth 5.4 or 5 $4 million of revenue.
[14:30]
I think that's it.
[14:32]
Okay tonight's staff is only seeking guidance
[14:34]
on a millage cap.
[14:36]
And recommended millage cap that exists,
[14:40]
existing military at 3.8830 mills although we are building
[14:46]
the budget on a military of 3.8743. --
[14:49]
on a millage rate of 3.8743.
[14:57]
>> All right thank you Andrea.
[15:00]
Any questions?
[15:01]
Can we get a motion on the table for reopen to public comment?
[15:07]
>> Make a move for a motion for (Indistinct)
[15:12]
>> Can we get a motion for the item to move proceed --
[15:16]
>> Yeah.
[15:18]
So moved.
[15:20]
>> What's the motion?
[15:23]
>> Motion to proceed with the rate I believe we could get this
[15:29]
to 3.8743 as our cap.
[15:33]
I just wanted feedback from town staff if that's something that
[15:37]
we feel we could --
[15:39]
>> Commissioner.
[15:40]
Yeah you can set the cap at 38743 should you wish.
[15:47]
We always recommend going a little bit above that
[15:50]
simply because we're maintaining a flat millage
[15:52]
rate so that you have flexibility and discussion.
[15:55]
As you start getting into your meetings in September
[15:58]
if you're talking about more projects or different levels
[16:01]
of service or anything like that, if you do not
[16:04]
have any wiggle room because you set the millage too low,
[16:08]
then you're not going to be able to kind of move.
[16:10]
So all staff is building the budget
[16:13]
at a lower millage rate than what's existing,
[16:15]
for the ceiling we recommend at least keeping it flat so
[16:21]
that you have that buffer.
[16:23]
You're talking about , how much is it?
[16:33]
Is it about 50?
[16:35]
Okay.
[16:36]
So 50,000, if you want to set it at the 38743 that's what
[16:41]
we're building the budget at anyways.
[16:44]
You'll be fine with that.
[16:47]
I would just recommend whatever cap you have,
[16:51]
just realize that you will not be able to go above it.
[16:55]
The good thing is that Surfside is in a really good
[16:57]
financial position.
[16:58]
In other places during the special hearings
[17:04]
commissioners would ask well we want this
[17:06]
and we want more of this and we want more of that
[17:08]
and my response is do you want to raise the millage?
[17:11]
Because there was no room but you
[17:13]
guys are in a really good healthy position so setting it
[17:17]
at the, and where we're building the budget is perfectly fine.
[17:21]
>> Okay with that I'm comfortable pushing us to be
[17:26]
fiscally responsible and to drive out that end cap there.
[17:30]
I think it's a good start for a new commission
[17:32]
and I make a motion to proceed with the 3.874.
[17:39]
>> 3.8743 just for --
[17:44]
>> 3.874.
[17:47]
>> I'll second it we'll open it up to public comment
[17:50]
and we'll come back to this.
[17:51]
>> First speaker Commissioner Richard.
[18:10]
>> Marianne Mashhad.
[18:12]
9225 Collins Avenue.
[18:14]
Surfside.
[18:15]
So unless there's something I'm not aware of, I recommend
[18:21]
keeping it at the 3.8830.
[18:23]
Thank you.
[18:25]
>> Thank you Commissioner.
[18:28]
Michael Carrickun.
[18:42]
>> Michael Carrick 9565 Abbott.
[18:44]
So must be nice to be flush with all this cash.
[18:48]
Just to put it in perspective, the first budget I worked on
[18:53]
in 2010 for the fiscal year 2011,
[18:57]
the total revenue from ad valorem taxes was 5 million.
[19:01]
Now it's 20 million.
[19:03]
There was a good graph over there
[19:05]
so you saw the high millage rate actually brought
[19:07]
in very little amount of money.
[19:08]
Back then.
[19:09]
The total amount of resort tax revenue in 2011 was a whopping
[19:16]
250 000.
[19:17]
Now it's I think 6 million something like that.
[19:21]
So anyway my point is I sent everyone an email,
[19:24]
I know that you're not going to go line by line tonight.
[19:27]
So please take it if you have any questions about,
[19:31]
the depth of information that I provided please don't hesitate
[19:34]
to reach out to me.
[19:36]
A couple of points, I want to make sure
[19:42]
that everyone understands that the,
[19:45]
there's liabilities associated with increasing the headcount.
[19:48]
I know this particular budget still
[19:50]
has the CEO or chief of staff position
[19:52]
I think you guys eliminated that already.
[19:54]
I don't know if you did or not but I think you should.
[19:58]
There is also a lot of clarity that's
[20:02]
needed around the new building.
[20:04]
For the building department.
[20:07]
I also wanted to point out that the building Services
[20:12]
department might be right for outsourcing based
[20:16]
on the fluctuating and variable workload over the next five
[20:22]
years or so.
[20:23]
I don't know if that's a smart to actually bring in full time
[20:26]
people for all of that because when you bring in full time
[20:30]
as everyone knows there's a lot more
[20:31]
liabilities associated with that.
[20:33]
So again I'm not going to get into too many details here
[20:37]
I support the 3.8743 thank you very much.
[20:43]
>> Thank you.
[20:44]
Mr..
[20:51]
>> Jeff Somper 8827 Emerson the budget is bloated but that's not
[20:57]
your fault. It's a situation that has developed over at least
[21:04]
ten years.
[21:05]
It's not unusual when money comes in.
[21:10]
Additional money comes in to spend it.
[21:15]
What I recommend is because it's not
[21:18]
going to be able to be done between now and September
[21:21]
when you have to approve a budget.
[21:25]
Is that a deep dive be done on the budget with each
[21:32]
of the departments I don't know whether you'd
[21:36]
want to use the Budget committee or something like that
[21:41]
or how you would like to hire an outside consultant to sit down
[21:46]
and go through line item by line item
[21:50]
find out what exactly is done in operations of each department.
[21:56]
Because Surfside has not grown, we're still a mile square.
[22:04]
We're still close to the same population.
[22:07]
As it has been for the last ten years.
[22:13]
There are many things that have increased in cost.
[22:17]
Pension health care.
[22:20]
Salaries have had to increase because of inflation.
[22:24]
But not to the extent that if you look at the budget numbers
[22:29]
from ten years ago and look at them now, that you can say that
[22:35]
there is not bloat and excess in the budget.
[22:39]
So I think you need to take a hard look at it.
[22:43]
Have somebody take a hard look at it.
[22:44]
Because you don't have the time to do so.
[22:55]
>> Please double check on that thank you.
[22:57]
>> Thank you.
[23:02]
>> All right thank you everybody for your comments
[23:04]
and your feedback Mr. Zumper when I hear you won't be
[23:06]
on the Budget Committee in August.
[23:08]
We don't have quorum yet we would
[23:10]
love to have your eyes on it this month but.
[23:13]
Thanks for your input.
[23:15]
Tonight I'm just going to remind everybody tonight
[23:17]
is just about setting the cap right?
[23:19]
We are going to spend the next two months still going
[23:22]
through this budget, there's still a lot to look at.
[23:25]
But we want to set our cap tonight.
[23:27]
That's the requirement that we have to do.
[23:29]
We want to be responsible and not limit ourselves.
[23:32]
That's all we're here to do tonight.
[23:34]
So we have a motion unless there's
[23:35]
a need for further discussion we can call the roll?
[23:39]
>> I very much share Commissioner Wingard's goal
[23:43]
of getting to a number like 3.8743.
[23:45]
But I do, I'm inclined to support the staff's
[23:53]
recommendation which was also made by Commissioner Mic'd just
[23:57]
having done this before you just never know,
[24:00]
and voting tonight to lower the taxes versus voting in September
[24:04]
makes absolutely no difference in what anybody ever
[24:06]
pays I want to make sure that's clear.
[24:08]
All of this is effective next year.
[24:10]
So it's just a question of whether we leave ourselves
[24:13]
that bit of wiggle room.
[24:15]
But I would rather us say agree that we
[24:18]
want to get to 3.8743 in September and make that a goal.
[24:23]
The budget is in fact built on that goal
[24:26]
so it shouldn't be too hard.
[24:28]
But I think just out of prudence you never know,
[24:31]
nothing really is gained tonight by lowering
[24:33]
the military e millage rate.
[24:39]
It seems like a show to lower taxes I want to do it anyway
[24:43]
but I want to do it in September.
[24:45]
I think we should go with the manager's recommendation.
[24:48]
And stick with the current rate for the trim notice.
[24:51]
Again, I have every intention of getting to 3.8743
[24:56]
at the next meeting it doesn't make a practical difference.
[25:04]
>> Yeah just Segway to what Commissioner Valdosta was
[25:11]
saying.
[25:14]
I mean I tend to sort of try to give myself the ability
[25:25]
to decide what I want to do based on ,
[25:34]
like what could be reasonable from a military standpoint which
[25:37]
would be like keeping the same rate.
[25:41]
I don't know if we're going to get to a practical --
[25:48]
I don't think actually, I we're not
[25:51]
going to get a particular advantage
[25:53]
if we're going to set a lower millage rate tonight.
[25:57]
From now in September you know we'll
[25:59]
be talking about many things during our budget workshop right
[26:02]
like we want to do this, we want to do that.
[26:06]
And things that ultimately are going
[26:08]
to be vetted by the community.
[26:10]
So I want to make sure that this is ,
[26:14]
that everybody understands that.
[26:15]
So that the idea is not to waste money absolutely not.
[26:23]
We want to lower taxes as much as possible.
[26:26]
But at the same time we want to listen to the community
[26:30]
and give the services that the community think that we
[26:34]
should have in Surfside.
[26:36]
So that's why if we want to do that,
[26:39]
and we keep thinking about that, then maybe leaving 3.883
[26:46]
would give us an extra 50 K which is not a lot.
[26:51]
But still.
[26:52]
A little bit of wiggle room.
[26:57]
I don't feel strongly about it, I mean at the end of the day
[27:01]
with this commission we're going to settle for 3.8743.
[27:04]
Like I said it's just 50 K. It doesn't change it that much.
[27:10]
However, you know.
[27:12]
The final decision is going to be in September
[27:15]
so it's just a limit now.
[27:22]
Mayor Danzinger: I just want to say I've seen this commission
[27:24]
spend almost $300,000 with less of a discussion
[27:27]
and we're talking about $50,000.
[27:28]
So this is boggling my mind I don't know
[27:31]
if there's another purpose.
[27:32]
I just want to say two years ago we were at $15 million spending
[27:37]
close to 16.
[27:38]
We're at 21 now the town is asking for that's
[27:41]
a lot of growth in two years.
[27:42]
So I am not passing a 3.87 budget I
[27:46]
expect us to bring a lot lower.
[27:48]
Because yes there's a lot of revenue coming in
[27:51]
but unless we can articulate during my time
[27:53]
with that 15 million we built three parks,
[27:55]
we did the Dune resiliency we did project after project
[27:57]
after project.
[27:58]
So I think there's a lot of room in again
[28:01]
we have two months to figure out where this money is going.
[28:04]
And how a lot of these departments
[28:06]
I don't know how many of you have gone
[28:07]
live I know by a line item yet in the budget
[28:09]
and how I don't want to use bloat is the wrong word
[28:12]
but how those numbers have exceeded in the last two years.
[28:16]
And I ran on fiscal responsibility
[28:18]
and I'm going to be there so to say that I'm just
[28:20]
going to adopt the same number as last year is completely
[28:22]
wrong.
[28:23]
And I don't know again why we're going
[28:25]
in circles on less than a percentage of a point.
[28:27]
>> It's just an opinion.
[28:31]
>> I mean my suggestion was we informally agree among ourselves
[28:35]
that the goal is to get it down.
[28:37]
Which we all agree we all want to be
[28:39]
the politician who cuts taxes nobody's disagreeing about that.
[28:43]
It's just, to the mayor's question he's asking
[28:47]
what is the reason the reason is that our fundamental goal here
[28:51]
should be prudence not sort of a soundbite.
[28:54]
Tomorrow.
[28:55]
And just in the interest of prudence nothing
[28:58]
is lost by staying with the current tax rate.
[29:01]
Some scenario is foreclosed.
[29:05]
And I just think our obligation is
[29:08]
to be the most prudent tonight.
[29:10]
Than in September we can all cut taxes
[29:12]
and we can say we cut taxes.
[29:13]
So I would opt for again, because I
[29:17]
don't feel this proposal is really considered.
[29:19]
We informally agree that that's what we're going to go.
[29:22]
But then we still vote for the current rates
[29:25]
just to give the staff and everybody wiggle room.
[29:27]
Mayor Danzinger: So there's a great line
[29:30]
item becomes a role when action is
[29:31]
taken towards its achievement.
[29:33]
>> And the best time to start doing something better is now
[29:36]
so this isn't for a sound bite if I need a sound bite
[29:39]
I'll create one.
[29:40]
Everyone's over on the record.
[29:42]
And everyone can hear it.
[29:44]
But this is about setting a precedent
[29:46]
and if it's our first budget and we've heard from town staff
[29:50]
that we're in a good place here.
[29:53]
And my motion was to get into action right away.
[30:00]
Being fiscally responsible and even
[30:02]
though it's just a small amount but that's one step.
[30:05]
And that's that the precedent and how
[30:06]
we're going to move forward.
[30:08]
>> Thank you Madam clerk.
[30:10]
>> Commissioner Giovanni?
[30:13]
>> We need four votes or three to pass on the three?
[30:19]
>> That's entirely different that's when you --
[30:22]
that's in December. --
[30:25]
September.
[30:26]
Tonight you need a majority to set the millage that's
[30:29]
all you're doing.
[30:41]
Commissioner Travani: It's 50 K. Yes.
[30:43]
>> Commissioner.
[30:45]
Again I share the goal of lowering
[30:48]
the taxes per field tonight we need to be prudent so no.
[30:51]
>> Commissioner Weingart.
[30:54]
>> Yes.
[30:56]
>> Vice mayor Birnberg?
[31:01]
>> (Indistinct) yes it's a yes.
[31:04]
>> Mayor Danzinger?
[31:07]
>> Yes.
[31:09]
>> The motion carries.
[31:12]
>> I think it needs to be charged.
[31:15]
This is the new one.
[31:18]
Don't worry.
[31:20]
You guys want to be (Indistinct).
[31:29]
>> All right moving on to item three a.
[31:31]
Approval of revised drawing of the scope of the Champlain
[31:33]
Towers CTS Memorial madam clerk if you
[31:35]
read the title of the resolution into the record please.
[31:38]
>> A resolution of the Town Commission of the town
[31:41]
of Surfside Florida approving revised drawings and scope
[31:43]
of work for the Champlain Towers South Memorial authorizing
[31:45]
the Town Manager to negotiate and finalize a contract
[31:47]
for construction with Schiff Construction and Development
[31:50]
Inc. For the project providing for implementation and provide
[31:53]
for an effective date item three eight.
[31:57]
>> Thank you Mr. Manager if you introduce this item please?
[32:00]
>> Yes mayor thank you very much.
[32:03]
>> Is there a motion?
[32:06]
>> I was going to let him introduce it two minutes to make
[32:10]
a motion --
[32:11]
>> Mayor so in March or prior to March we received ,
[32:19]
we put out a bid and we received a total project cost
[32:22]
for the memorial of over $5 million.
[32:25]
With regards to the voter referendums
[32:27]
that would have required a voter referendum either now
[32:32]
or in August or November.
[32:34]
The Commission directed staff to look at the project
[32:37]
and see if we can get it below the threshold
[32:39]
and the total budgeted amount is 3.55 million.
[32:43]
Staff and our consultant Keith Engineering
[32:48]
which we have present here who will walk you
[32:50]
through the presentation, was able to take a look
[32:53]
at the project and identify certain aspects of the project
[32:56]
that we can split up in construction phases.
[33:01]
So what is before you tonight is for the substantial contracts
[33:06]
and it's substantial form.
[33:08]
For approval with shift we're going to give you the update
[33:12]
and then staff does need direction may be separately
[33:16]
from the contractor altogether however you want to handle it.
[33:20]
Mayor.
[33:21]
With regards to the image on the wall itself.
[33:25]
During the memorial, I had the memorial event in June.
[33:33]
There were, those attending who put me aside
[33:38]
for at least a good 5 to 10 minutes.
[33:41]
Talking about how the image was not appropriate.
[33:45]
The families did discuss this during their designs,
[33:49]
the image that is there is being,
[33:53]
is what their recommendation is.
[33:56]
And I believe several families are
[33:58]
members of the community have also reached out to some of you
[34:00]
on the commission as well.
[34:02]
And so seeing and hearing a lot I just
[34:07]
wanted to make sure that whatever we move forward with
[34:09]
is what the Commission wishes to move forward
[34:11]
with so I'm asking you for direction on that as well.
[34:14]
With that if I can have correct from Keith
[34:18]
to just kind of walk us through to show what
[34:22]
the overall update on what we faced
[34:25]
for this phase of the construction project is.
[34:30]
>> I'm just going to get a motion on the table and then
[34:33]
we'll proceed. (Indistinct) and also I just want to reiterate
[34:38]
some of the history because I think June 24th some articles
[34:41]
were put out with some misinformation which is that
[34:44]
this commission value engineered this project delayed
[34:46]
the project.
[34:47]
I think there's a referendum item
[34:49]
and I forget which month it was exactly
[34:51]
but it was last year which the residents voted
[34:56]
to restrict the commission from spending
[34:59]
I believe it was 5% of the ad valorem revenue
[35:01]
which equated to roughly 3.5 million I'm going to say?
[35:05]
Of the proposed budget without a referendum.
[35:08]
Comes the memorial at 7.5 million
[35:11]
which exceeds that amount which would require the commission
[35:13]
go to the referendum by the residents.
[35:16]
Obviously that would a delay the project
[35:18]
but you run the risk of the residents
[35:19]
saying we don't want this project
[35:20]
and there goes the entire memorial we've
[35:22]
been building for five years.
[35:24]
So the commission, the previous commission
[35:26]
went out and had Keith Valley engineer this down to an amount
[35:30]
that the commission can authorize
[35:32]
without referendum so that's what we have here today.
[35:35]
As manager stated the images yes I
[35:37]
get it was pushed by 1 or 2 family members.
[35:40]
I've been hearing a lot about it it's
[35:41]
extremely I mean as a resident come on it's traumatic.
[35:45]
To see a site where so many people lie dead.
[35:48]
A lot of the first responders a lot of the residents a lot
[35:52]
of family members (Indistinct) so it
[35:55]
was a proposal for an additional this image has become iconic
[35:58]
for this event.
[36:01]
It signifies multiple things including
[36:03]
the continuation of life the infinity sign
[36:06]
that is built in there.
[36:07]
It was an entire different aspect
[36:10]
and that became the vision so what we have here tonight
[36:13]
is a revised plan.
[36:15]
Conforming to hopefully a value engineered down to the price
[36:19]
that we can improve here tonight.
[36:20]
With a revised design so I would ask
[36:22]
for a motion to approve this with the revised design.
[36:26]
>> I'll make the motion to approve and proceed with this
[36:33]
project that's so important and I committed to family members
[36:36]
that I've talked with that were going to get that done.
[36:38]
In our commission so I ask for fellow commissioners
[36:42]
support their.
[36:42]
And moving this along.
[36:45]
Expeditiously.
[36:46]
Also motion to approve the revised image of love lives
[36:54]
on, it's a beautiful message, it's
[36:57]
a hand from below connecting to a hand from above.
[37:00]
That's remembering the past showing the future.
[37:03]
So I make a motion to approve this.
[37:08]
>> I'll second it.
[37:10]
All right.
[37:12]
Let's hear the updates.
[37:15]
>> Good evening Mayor and Commissioners my name is Greg
[37:19]
Cheverie I'm vice president of Keith.
[37:22]
Been a pleasure working on this project with the town
[37:27]
and stakeholders.
[37:28]
Just wanted to give you an update
[37:31]
on what the manager mentioned.
[37:33]
Also you described it very well mayor.
[37:36]
All the different activities and events that took place
[37:42]
and how everything just resulted in this version, this latest
[37:48]
iteration of the design, some of the major modifications
[37:51]
that were made were to fit the project into a budget
[37:56]
that could be adopted by the commission
[37:58]
and also that could fit efforts needed for the contractor to do.
[38:04]
What was done was this area here on the eastern side
[38:10]
of the proposed memorial was scaled
[38:14]
down so that this area now becomes a more green space area.
[38:19]
And also there were some scaled down areas
[38:25]
as well as far as some of the attributes that were again,
[38:30]
tailored so it could mean project budget.
[38:35]
Nevertheless, what you see before you
[38:38]
is a rendering of a, the wall where we would commemorate
[38:44]
or memorialize the victims as well as a waterfall feature that
[38:50]
would show an image in the background.
[38:53]
And also a lot of landscape that would provide the experience
[39:03]
that was established by stakeholders of this design
[39:08]
throughout the process.
[39:09]
Nevertheless at the end of it shows
[39:12]
how the entrance from the Western side
[39:15]
towards the eastern side would look.
[39:17]
With some of the remnants that came from the building itself.
[39:23]
And those will remain as part of the design.
[39:26]
This is now also an eastern look from Western side.
[39:31]
As to how the memorial will look as you can see,
[39:36]
the area that has been modified now
[39:39]
shows a view and a perspective to the ocean.
[39:43]
And right now we are in the final stages
[39:48]
of obtaining all permits.
[39:49]
And this has been our latest iteration update
[39:53]
for the Surfside Memorial.
[39:55]
>> Thank you Craig and for the commission because I know we
[39:58]
received an email from residents I think today or yesterday,
[40:01]
Keith and the team has walked the site with Miami Dade Fire
[40:08]
Miami Dade County to make sure that there sufficient room to go
[40:12]
through and any other concerns that Miami-Dade fire may have
[40:15]
and we are good to go.
[40:17]
We're submitting the final response to their comments
[40:21]
by the end of the week and once they have that,
[40:25]
we should get a pretty quick turnaround for approval
[40:27]
as we've already addressed in the field with them.
[40:33]
>> Thank you.
[40:37]
>> (Indistinct) okay so I had a bit of a question.
[40:41]
Because I was checking this over today.
[40:44]
Item number, I can't even see.
[40:47]
Item number six I think it >> Number six?
[40:51]
This area?
[40:52]
>> Or maybe it's number one.
[40:54]
Can scroll down.
[40:55]
>> So this is on the Western side there's a memorial signage.
[41:00]
And then item number six, we will have,
[41:05]
these are points where we will have certain degrees of, debris
[41:10]
that comes from the site itself.
[41:13]
>> Craig can you scroll down so they can see the column again
[41:16]
of what that looks like?
[41:17]
I think it's the, there.
[41:19]
This one's a good one or even at nighttime
[41:21]
if you want to show it.
[41:23]
>> Two separate things I have an item for a column and then you
[41:26]
have an item for debris so what I saw when I read that is a pile
[41:28]
of debris which we're seeing now on the --
[41:32]
>> So these are all these are the columns that you see
[41:36]
and then inside of the columns are the chunks of the various
[41:40]
debris that is currently across the street from the site.
[41:44]
So it's meant to memorialize the actual pieces in the columns
[41:50]
as a feature that will also have light in their.
[41:53]
>> Okay but it's not a pile up like we're seeing
[41:56]
in the entrance park right now.
[41:58]
>> It would be broken down to fit the area.
[42:01]
>> Because if you go to the map there's another item
[42:05]
for the pillars.
[42:06]
You have two as a pillar feature and then six as debris.
[42:12]
>> Yeah if I may -- so the six, this area here and here
[42:20]
and here.
[42:21]
And over here.
[42:23]
And towards the end.
[42:24]
These are small debris that we will blend in
[42:29]
with the landscape.
[42:30]
It's debris that was preserved from the site.
[42:33]
And that was a feature that was requested
[42:37]
throughout the process.
[42:38]
>> Do we have a photo of what that looks like
[42:40]
because we're looking at a photo of a pillar so you're telling me
[42:43]
it's two separate things?
[42:44]
>> I don't have that on the on --
[42:48]
I don't have that here.
[42:49]
It's basically positioning a piece of debris
[42:52]
in those areas with the landscape.
[42:54]
>> So judging on the faces of the crowd and the feedback that
[42:59]
we got from when they moved the debris to the tennis center.
[43:02]
Was people can't drive up columns anymore.
[43:05]
They can't look at this this is their home this is their life
[43:08]
and what you're doing is you're putting
[43:10]
a piece of someone's home in the grass in front of them.
[43:13]
And so I mean again, I don't want to judge it yet
[43:16]
before I've seen what it looks like but I've seen nothing
[43:19]
of what that is supposed to be.
[43:21]
Is that a nice rock that has been put into the gardening,
[43:24]
is it a giant, is what we're seeing now
[43:26]
in the tennis center which is extremely disturbing to a lot?
[43:31]
And again I want to thank you you've
[43:33]
been on this for the last five years with us.
[43:35]
Through a couple of commissions.
[43:37]
And it's a very difficult position you guys were in
[43:39]
and I think you did a great job of managing
[43:41]
all the feedback and input so just
[43:44]
bear with us a little longer and we're almost there.
[43:46]
I just want to clarify something.
[43:51]
>> So I can look for what that would look like.
[43:56]
I just have to, I need some time or I
[43:58]
can send that to the manager.
[44:00]
Thereafter.
[44:01]
>> Yeah that's not even a feature that I remember even
[44:06]
seeing any of the plans or anything so we can definitely
[44:09]
bring that back.
[44:10]
To the commission and if the commission
[44:12]
decides that's not a type of feature that's just debris
[44:15]
that we wouldn't use or place because that's more
[44:17]
of a gardening type of feature.
[44:19]
It's a hardscape more than anything so.
[44:22]
That wouldn't stop the whole project.
[44:25]
It wouldn't cause like a complete redesign of anything.
[44:29]
>> It's just positioning of debris.
[44:32]
>> I would just ask again before it gets placed
[44:35]
or if there's something we can see on that first.
[44:38]
>> Are we requesting an amendment or a amended motion?
[44:44]
I mean we can approve -- can't approve something we can't see.
[44:49]
But we want to move the project along.
[44:51]
We don't have any photo of that?
[44:54]
>> I just need a few minutes to see what I can find.
[44:58]
>> In the meantime through the mayor may I ask him questions
[45:02]
of the manager and attorney I'm confused about a few things.
[45:08]
If we approve a design tonight does it
[45:11]
still go to the PNC under the recently adopted law
[45:17]
that major design elements go to the PNC?
[45:22]
>> No sir again the design isn't changing and this was all done
[45:26]
and approved prior to that occurring.
[45:28]
The only thing that we've done -- prior to the April ordinance.
[45:36]
The only thing that we've done is taken a look
[45:40]
at the phase construction project
[45:41]
to get it under the budget we haven't changed the design we
[45:44]
haven't done anything with regards
[45:46]
to the overall design of the project.
[45:49]
>> And is there any, my understanding and you can please
[45:54]
correct me if I'm wrong.
[45:56]
The Memorial committee hasn't weighed in on the project at all
[46:01]
since, not since the April meeting or whichever meeting it
[46:04]
was that -- approved the scaled back project.
[46:08]
Okay.
[46:09]
Third question.
[46:12]
Through the mayor for the attorney.
[46:13]
What is the current status of those spending limits
[46:18]
from the referendum because when we've talked recently
[46:21]
about the Collins Water main, I've
[46:24]
gotten the impression from the attorney
[46:26]
that the intention is to hold that referendum to be illegal.
[46:35]
I haven't been totally convinced by that
[46:37]
but that's my understanding of where the attorney's advice has
[46:40]
been leaning.
[46:41]
So doesn't that create an opportunity then
[46:43]
for us to discuss the project as originally designed including
[46:46]
the canopy and the other feature that was taken out
[46:53]
in March or April which I think was the concrete benches?
[46:56]
I mean I think if we're going to be
[46:59]
not hemmed in by the referendum, spending limits
[47:02]
when it comes to the water main why are they hemming us
[47:05]
in now in the memorial project I'm
[47:07]
not quite sure what the different approaches.
[47:09]
Why we have two different approaches
[47:11]
to do different projects.
[47:14]
>> The answer is I don't know who you mean they.
[47:18]
Who's hemming you in?
[47:20]
>> I'm just saying we, the reason why this was,
[47:25]
the project was scaled back was to fit underneath the spending
[47:29]
cap.
[47:29]
So if the spending cap is no longer in your opinion, law,
[47:36]
then shouldn't we be considering the full project
[47:41]
that was before us originally that went out to bid?
[47:47]
>> You're going to the motivation as to why
[47:51]
there's been a modification and whether you just want to --
[47:55]
>> The should question is for the commission but the legal
[47:58]
question is, is it your opinion that --
[48:02]
that we're not bound by the referendum?
[48:04]
Spending cap?
[48:05]
>> That is where I'm heading that I haven't come to that
[48:09]
final conclusion yet but that is the direction that I'm headed
[48:11]
in which is that the unanimous vote provision as well
[48:19]
as the 60% provision were not properly placed before
[48:23]
the voters.
[48:25]
>> Okay.
[48:27]
>> But that's the direction that we're headed in.
[48:32]
I haven't come to that conclusion
[48:33]
so as of tonight, you're still, my advice
[48:37]
is that you're still bound by that provision.
[48:40]
>> We are okay.
[48:42]
But right but we might not be a month from now or --
[48:46]
>> Might not be if you want to put this off you can.
[48:49]
>> Those are my questions I mean are we having discussion then I
[48:53]
mean I would like to -- those answers are hopeful
[48:57]
for the point I wanted to make but.
[48:59]
>> Before we get into discussion I'm going to bring up public
[49:03]
comment is the presentation (Indistinct).
[49:07]
No we can do public comment while you're checking
[49:10]
if you have a few minutes.
[49:12]
All right where's my speaker.
[49:16]
Barbara Cohen.
[49:17]
You sure?
[49:19]
Okay.
[49:20]
I'll come back to you.
[49:25]
George Cousillas.
[49:32]
>> George 9225 Collins Avenue.
[49:37]
First Mr. Mayor, your description
[49:41]
of the timeline and culpability where we are
[49:44]
is exactly accurate.
[49:45]
That this commission didn't get us here.
[49:49]
But I want to talk about probably something very
[49:53]
dull to most people here.
[49:55]
But the construction contract.
[49:57]
I've gone through it come on I've go through construction
[50:00]
contracts all the time.
[50:02]
There's some weird things in here which,
[50:05]
I mean if the contract is fine with it,
[50:09]
but it looks like it things were trapped in many months ago not
[50:12]
by our current attorneys -- drafted many months ago not
[50:18]
by our current attorneys and there's things that strike me --
[50:21]
you have liquidated damages that apply to the contractor.
[50:25]
But you don't have a waiver of consequential damages.
[50:28]
Typically when you have liquidated damages
[50:30]
you also have a waiver of consequential damages.
[50:33]
The difference between them is a consequential damages
[50:37]
a direct cost.
[50:39]
I wasn't able to open, I lost so many thousands
[50:42]
of dollars of business a day, you owe me for that
[50:45]
or I rented a tent for a big grand opening
[50:48]
and I didn't get that.
[50:49]
Liquidated you just apply a number.
[50:52]
So that's not in there so the contract
[50:55]
is kind of on the hook for both because you don't have it
[50:58]
and when you go into nets and 2.3
[51:01]
and when you go further down into 8.6,
[51:05]
that's where the waiver of consequential damages portion.
[51:11]
Paragraph is.
[51:12]
And it's really only waiver of the contractors.
[51:17]
Consequential damages so they can't
[51:19]
go after the town for loss of profit or loss
[51:21]
of this or loss of that.
[51:23]
You usually have consequential damages for both parties.
[51:25]
And that's not in there.
[51:30]
Finally and this is an important part of any construction
[51:34]
contract, you have this, what's usually
[51:38]
called a continuing performance clause in a contract.
[51:40]
And what it does is the beauty of construction contracts
[51:44]
as opposed to most contracts is everything goes to hell.
[51:48]
During construction.
[51:49]
And the contract is designed to manage that right?
[51:53]
According to the terms for regular contract,
[51:56]
people would be in default by the second day.
[51:58]
Both parties.
[51:58]
But not so in a construction contract
[52:01]
there are changes and all these mechanisms in place.
[52:04]
And if you let me run just a few seconds over.
[52:07]
So typically what you say is if we
[52:10]
have a dispute over the change order for the new bathroom that
[52:13]
was added, the contractor is still
[52:15]
obligated to perform the work.
[52:17]
While the dispute goes on.
[52:19]
And the owner is obligated to keep paying
[52:22]
while the dispute is going on.
[52:24]
Here you only have continuing to performance
[52:27]
on the part of the contractor.
[52:29]
Again it's kind of an uneven thing
[52:31]
I'm surprised any contractor would agree to it.
[52:34]
If they have that's fine but this was written by an earlier
[52:37]
attorney I presume, and so I would
[52:40]
recommend going through this very carefully
[52:43]
and seeing, wringing out things like this.
[52:46]
Thank you.
[52:47]
>> Thank you George.
[52:54]
Commissioner?
[52:59]
>> Marianne Marcia 9225 Collins Avenue.
[53:03]
So this is a first view of the revised memorial
[53:09]
and I see life through trees and fountain.
[53:14]
But I just wish it would reflect more of the positive view
[53:21]
of hope and life.
[53:23]
For the future.
[53:24]
Versus the sadness and tragedy of the past.
[53:29]
Thank you.
[53:30]
>> Thank you Commissioner.
[53:33]
>> Robert Cohen last chance?
[53:37]
Okay.
[53:37]
All right let's close public comment
[53:41]
and go back to the commission.
[53:45]
Is Keith ready to do find anything or not yet?
[53:59]
>> Do not have with me a rendering that would show
[54:02]
or depict that.
[54:04]
What I can say is, I believe in prior presentations
[54:09]
that we submitted we did show how that would look
[54:14]
and basically just to describe.
[54:17]
It's pieces of debris that are similar to like manager
[54:22]
mentioned art scape that would be positioned
[54:25]
around some landscape.
[54:28]
So that was something that was very well described in the past
[54:35]
but apologies I don't have that rendering with me right now.
[54:43]
>> (Indistinct) what?
[54:45]
>> Yes would you have that?
[55:06]
>> Sandra did the 60% go to PNC?
[55:11]
>> Yes August 28th 2025.
[55:15]
That's what I'm looking for actually.
[55:34]
Here Greg.
[55:35]
It's in here.
[55:59]
>> (Indistinct) No this one doesn't have it.
[56:39]
So this came on a different rendering.
[56:49]
>> We can mayor Commissioner, again that's hardscape,
[56:54]
we can go back and tomorrow email you all what the rendering
[56:59]
would look like.
[57:01]
And then that's something that during construction or prior
[57:04]
to construction starting, if the commission
[57:07]
wants to give certain direction on that we can adjust.
[57:10]
That doesn't stop the project.
[57:12]
>> Would you mind sorry Mr. Trevor can you leave that file
[57:17]
open I want to make reference to it.
[57:20]
>> Or this one?
[57:23]
Oh the 60%?
[57:46]
>> So just to clarify come on to the motion maker
[57:48]
if you're willing to amend it to exclude I guess item six until
[57:52]
such time it can be reviewed and added?
[57:58]
>> I see a number of sixes throughout that's all the same
[58:01]
item?
[58:02]
Same future?
[58:03]
I see six throughout the --
[58:07]
>> These are the sections where that hardscape would be placed.
[58:14]
>> Okay but if we're able to proceed with the overall project
[58:17]
and isolate this component, for further direction then
[58:22]
I'll amend my motion.
[58:23]
As such.
[58:24]
>> Second I agree.
[58:27]
>> The pending motion is to move forward with the alternative
[58:34]
design and to direct the attorneys and manager
[58:43]
to negotiate the terms of a final contract.
[58:46]
That's the pending motion that's there.
[58:49]
>> And with that you can still review the contract given
[58:52]
the concern that was --
[58:53]
>> So this plan here, I'm not sure that this is in the revised
[58:58]
drawings.
[58:59]
Is this in the revised packet that's been approved by shift?
[59:04]
Okay.
[59:06]
>> The position of the hardscape yes.
[59:09]
>> And so within their contract, and within the scope of what
[59:15]
you're awarding tonight, is the specification if you will,
[59:23]
that at those locations there will be the placement of certain
[59:28]
debris right?
[59:29]
That's what.
[59:30]
Okay.
[59:35]
You can go ahead on the motion if you
[59:39]
want to place a further directive, separate and apart
[59:45]
from the contract, that the Council, the commission
[59:51]
would like to have input in the materials that are being placed
[59:58]
at each of these debris locations,
[1:00:00]
and we can do that separate from the contract.
[1:00:04]
You don't want to pull out this from the contract,
[1:00:08]
it's part of the contract it's part of what's being bid.
[1:00:11]
He's including these items as placing these things there.
[1:00:14]
If you want to select the individual pieces that
[1:00:17]
you'd like to do, do that separate from the follow up --
[1:00:22]
>> We want to know what this is there's no image of what
[1:00:26]
we're approving here tonight.
[1:00:27]
It says debris.
[1:00:29]
The feedback and again this is started a year ago when they
[1:00:33]
moved on --
[1:00:35]
>> So then you can approve this project with a modification that
[1:00:38]
removes the debris from the approved plans.
[1:00:42]
>> Why don't we leave the debris analyze the alternative we can
[1:00:48]
still do a change order if it's going to be a change order
[1:00:51]
or just swap the materials at no cost.
[1:00:53]
But right now, they have in the contract
[1:00:56]
the cost of the placement if you take it out,
[1:00:58]
and I did later it's going to cost more.
[1:01:01]
For sure.
[1:01:03]
>> We've asked to bring it back to the council.
[1:01:06]
If we come back and we say we don't like this you take it off
[1:01:09]
the contract right now the contract let's say whatever two
[1:01:12]
point, $3.550 million is approved.
[1:01:15]
That's what's approved tonight.
[1:01:16]
And if we decide we don't want to move forward with debris
[1:01:19]
because it's traumatic -- then It's a change order --
[1:01:24]
>> Yeah that's what I said yeah.
[1:01:27]
>> But we're not approving the design it's --
[1:01:31]
>> You're approving the plans that are in the --
[1:01:37]
>> We're approving the contract with the plans with
[1:01:39]
the stipulation that the artwork on the walls changes and the six
[1:01:42]
comes back to the commission to see --
[1:01:44]
>> No problem.
[1:01:46]
Got it.
[1:01:47]
>> So there's a motion --
[1:01:51]
>> There's a pending motion you can call the question and --
[1:01:57]
>> So we can call to vote.
[1:01:59]
To approve it.
[1:02:00]
>> Mayor do you want to go ahead and call the question?
[1:02:05]
>> Sorry my questions were preliminary to discussion.
[1:02:11]
I mean sorry I got -- there's a lot I have to say.
[1:02:17]
This represents a major departure from the memorial
[1:02:21]
as planned before.
[1:02:23]
>> Which her commission did by the way.
[1:02:26]
>> Please be clear about what you're saying.
[1:02:30]
You're just commission denied this right?
[1:02:31]
We're approving it tonight.
[1:02:33]
>> I know I know but I need to --
[1:02:37]
in the past two years plus the memorial committee,
[1:02:40]
they're the ones I want to put front and center not
[1:02:42]
the commission.
[1:02:42]
And I have the floor it's not appropriate for you --
[1:02:46]
>> Which you took without us.
[1:02:49]
>> I have the floor.
[1:02:51]
I want to make a comment because I haven't
[1:02:54]
had a chance to make a comment.
[1:02:55]
>> Make your comment accurate please that's what I'm going
[1:02:59]
to ask you to do or we're going to move on to commission
[1:03:01]
we're going to vote --
[1:03:02]
>> I'm not saying anything inaccurate I'm saying this
[1:03:06]
design represents a major departure from the original
[1:03:09]
design and we need to be clear about this there's a two year
[1:03:11]
process not led by the commission but by the memorial
[1:03:13]
committee that resulted in this design.
[1:03:15]
I want to say for the benefit especially
[1:03:18]
the two commissioners who are new.
[1:03:20]
Because I know the Planning and Zoning Board
[1:03:22]
had something to do with this.
[1:03:24]
I think the members of the Memorial Committee
[1:03:27]
will be extremely upset with this decision.
[1:03:30]
Extremely.
[1:03:31]
The decision to, I mean there's a general esthetic principle
[1:03:36]
that came out of years of planning.
[1:03:40]
And it started with mood boards in this very room.
[1:03:43]
Like over two years ago.
[1:03:46]
They wanted the memorial to be a little bit challenging.
[1:03:49]
They weren't looking for just hopeful.
[1:03:51]
They wanted it to be a sign that something horrible had
[1:03:55]
gone wrong here.
[1:03:56]
And that wasn't the commission's decision.
[1:04:00]
That came from the committee through many many open meetings
[1:04:04]
so the committee.
[1:04:06]
I just want everyone to appreciate
[1:04:07]
this is why I feel the need to put this on the record
[1:04:10]
because this is a dramatic dramatic change of direction
[1:04:13]
from what the committee considered.
[1:04:16]
The decision to have debris the decision even
[1:04:18]
to have that image, came from that vision which was not
[1:04:22]
a one off thing and certainly wasn't from the commission.
[1:04:25]
So in the interest of accuracy I need to make that clear.
[1:04:30]
I think this decision about the wall art in particular
[1:04:35]
is really taking us, again not just in a direction
[1:04:39]
but here I'm making a different point
[1:04:41]
I'm in the wrong direction.
[1:04:44]
I would ask the motion maker and the commission
[1:04:46]
I would think the wall art should go back
[1:04:48]
to the memorial committee and it should go back
[1:04:50]
to PNC for comment.
[1:04:52]
And I want to, I'm expressing my own opinion.
[1:04:57]
With all due respect to the manager
[1:05:00]
or to whoever came up with this image of the two
[1:05:02]
hands and the love lives on script.
[1:05:05]
It's schmaltz.
[1:05:07]
It looks like the kind of wall art
[1:05:10]
that you might buy at target.
[1:05:12]
The cursive script of love lasagna,
[1:05:16]
looks like those live laugh love designs that
[1:05:21]
are already kind of a joke.
[1:05:24]
It really, it really lowers the design quality of the memorial
[1:05:28]
and I'm just saying that.
[1:05:30]
Please before we approve this a design professional should look
[1:05:34]
at it the PNC board should look at it
[1:05:36]
and I think the memorial committee should
[1:05:38]
look at it because it really is a step in the wrong direction
[1:05:41]
these two hands touching it looks extremely cheesy.
[1:05:45]
And I think that's not, I mean it's not
[1:05:49]
an image worth engraving in stone.
[1:05:51]
It's not timeless.
[1:05:52]
It looks outdated.
[1:05:53]
It looks cheap.
[1:05:55]
And I don't say that lightly I really think
[1:05:57]
we're going in the wrong direction.
[1:06:00]
The reason why I asked Mr. Ashbury to bring back
[1:06:03]
the 60% design is because they actually had
[1:06:05]
a pretty elegant design there.
[1:06:08]
Of a kind of abstract that's it right there.
[1:06:13]
And abstract version of the building.
[1:06:16]
And the memorial committee thought they didn't want that.
[1:06:19]
But this is much much much better than the love lives on.
[1:06:24]
Much better.
[1:06:25]
And that's just my opinion but I have
[1:06:28]
a feeling that if you took this to PNC
[1:06:29]
and you took this to Memorial committee
[1:06:31]
they would pick that over this.
[1:06:33]
So I really hope we still have time
[1:06:37]
and I think we should get an opinion from all those parties
[1:06:40]
that are interested.
[1:06:42]
I think the love lives on is terrible I'm not
[1:06:44]
going to belabor the point you might disagree but from,
[1:06:48]
I don't think any serious artist or designer
[1:06:50]
would approve of this.
[1:06:51]
And again it looks like something from target.
[1:06:56]
The other thing, I don't really understand
[1:06:59]
the logic of how we got here.
[1:07:02]
If we're expecting that we're going
[1:07:05]
to be no longer subject to the spending cap in a month's time,
[1:07:11]
then why not consider the entire project
[1:07:14]
with the canopy which was really the central design
[1:07:17]
feature of the whole thing that took years?
[1:07:19]
To come up with?
[1:07:20]
Why not have that?
[1:07:22]
So I think they should come back to us in August
[1:07:25]
after it goes to PNC and after it
[1:07:26]
goes to the Memorial committee.
[1:07:28]
May I make one other point I think
[1:07:31]
it's important to the process?
[1:07:33]
>> I need you to land the plane and hurry up already.
[1:07:37]
>> I understand that both the manager and the mayor have been
[1:07:40]
hearing from people who have strong views but the memorial
[1:07:42]
committee met in public and those people need to express
[1:07:46]
their views in public otherwise it's kind of like a sort
[1:07:49]
of hearsay and I am not comfortable with rejecting
[1:07:52]
the open deliberative decision of the committee in favor
[1:07:56]
of privately delivered remarks.
[1:07:59]
To the mayor and the manager.
[1:08:00]
That's not right.
[1:08:01]
This was always meant to be an open design process
[1:08:03]
and I don't know who's saying that they're traumatized
[1:08:06]
but they need to say it in public.
[1:08:08]
This is too important to make a decision
[1:08:11]
in this kind of hearsay manner.
[1:08:12]
And so again I think we're going in the wrong direction
[1:08:15]
and we're doing it through the wrong process.
[1:08:18]
>> So first of all I think you heard from your own residents
[1:08:21]
right here.
[1:08:22]
But I get it.
[1:08:25]
You're entitled to your opinion and we have ours.
[1:08:27]
And the memorial committee which I
[1:08:28]
put together five years ago, they were input
[1:08:31]
and we hear their input but we're building with resident
[1:08:34]
money and item for the residents for the town of Surfside too
[1:08:37]
remember.
[1:08:37]
We are not building something for three family
[1:08:40]
members that provide input.
[1:08:41]
We hear it and we took it under consideration.
[1:08:43]
And I would say a large, this entire thing was pretty much
[1:08:47]
designed with their input.
[1:08:48]
But there's certain elements that offended others there
[1:08:51]
are certain elements that are just not what we
[1:08:53]
are looking for as a community.
[1:08:54]
And we are the ones that live here we're
[1:08:56]
the ones that have to see it every time I've
[1:08:58]
walked through the beach.
[1:08:59]
So you're entitled to your opinion we've heard it.
[1:09:02]
We're moving on we are not going to be the commission that
[1:09:04]
comes here tonight and continues to further delay
[1:09:06]
a process that's now been five years in the making.
[1:09:09]
>> I'm not interested in delaying we have consultation
[1:09:12]
on the wall art please I would ask Commissioner Weingart to get
[1:09:15]
that feedback this is going to be an embarrassment to the town
[1:09:17]
if we go ahead with this.
[1:09:19]
>> I've heard you and you've asked me a number of times
[1:09:22]
to change my motion and I've extended an olive branch
[1:09:25]
a number of times now and good grace but I haven't seen that
[1:09:28]
returned.
[1:09:29]
But you're definitely entitled to your opinion.
[1:09:32]
I find it very interesting you know
[1:09:34]
there's so much talk from the memorial committee
[1:09:37]
and from vocal family members that this hasn't gotten done.
[1:09:40]
Yet when we try to make movement,
[1:09:43]
we get into this paralysis from analysis cycle
[1:09:45]
and just going in circles while it could
[1:09:48]
be better it could be better.
[1:09:49]
I mean a picture of the building collapsing is ridiculous
[1:09:52]
and that should absolutely not be up there.
[1:09:54]
And there's a proposed beautiful lovelies on message
[1:09:58]
as I shared earlier.
[1:09:59]
And my motion stands and I committed
[1:10:02]
to family members that came up to me
[1:10:03]
and said why don't we have this yet?
[1:10:05]
As if it's our fault but we're just elected in March.
[1:10:08]
For three months and.
[1:10:09]
And I said we're going to be the commission that's
[1:10:10]
going to move it forward.
[1:10:12]
I can't answer for what happened in the past.
[1:10:15]
So I'm moving forward.
[1:10:18]
>> We did find a rendering of those Hardscapes if you'd like
[1:10:23]
to look.
[1:10:24]
This again was a while ago.
[1:10:27]
But the idea is to have hardscape
[1:10:30]
throughout the landscape.
[1:10:31]
Throughout the project.
[1:10:34]
>> That looks like debris again this looks like Rebar sticking
[1:10:38]
this looks like exactly what we have in the tennis center
[1:10:41]
so I'm absolutely against that.
[1:10:44]
That is someone's home right there.
[1:10:46]
Somebody died on that thing.
[1:10:48]
I'm not putting that in the garden
[1:10:50]
for everybody to look at and walk past.
[1:10:52]
There's people that will not walk into the city that have
[1:10:55]
lived here hundreds of people.
[1:11:00]
So I would ask the motion maker to take out
[1:11:03]
number six from the design.
[1:11:05]
>> I did that previously I amended my motion.
[1:11:09]
>> So we can value it down further if required
[1:11:13]
but we're not looking to maintain that visual.
[1:11:18]
Madam clerk call the roll please.
[1:11:22]
>> I have a question -- so this design of the two hands is
[1:11:26]
coming from where?
[1:11:27]
Like who did that?
[1:11:32]
>> Symbol of it for the last five years.
[1:11:35]
>> This is the image that is on the temporary banners that have
[1:11:39]
all the names that are, that have been on the site it's also
[1:11:43]
been used in the fliers and whatnot.
[1:11:44]
I don't know where the original image came from.
[1:11:47]
But the town's used it for many years.
[1:11:52]
>> Yeah but what I'm saying is like the complete thing like
[1:11:56]
with the, because I don't remember if the writing is
[1:11:59]
on that image or not.
[1:12:00]
Is it on that image?
[1:12:02]
It is?
[1:12:03]
Okay.
[1:12:05]
>> Madam clerk.
[1:12:08]
>> Call the roll?
[1:12:12]
>> No.
[1:12:15]
>> Commissioner Weingart.
[1:12:17]
>> Yes.
[1:12:20]
>> Commissioner Trevanny.
[1:12:22]
>> I'm going to make my comment before voting.
[1:12:26]
This we said this is not going to go back
[1:12:28]
in front of the PNC or the committee right?
[1:12:33]
>> They've already seen it.
[1:12:35]
This design has been approved and done in the last commission.
[1:12:39]
What we are doing now is just approving the contract.
[1:12:42]
You're talking about the image.
[1:12:45]
Did not see that image no but they saw this memorial --
[1:12:49]
>> I'm talking about the image and the debris.
[1:12:54]
Yeah I don't feel comfortable voting yes
[1:12:58]
just because this went through a process
[1:13:03]
and I'm okay with something that comes out of a process.
[1:13:10]
I'm less okay with us coming back at the end
[1:13:14]
and doing modification without the input of the people
[1:13:16]
so I'm going to vote no.
[1:13:17]
>> Remember you're now on the record for voting no
[1:13:21]
for a memorial that's all.
[1:13:23]
So whatever process is not fitting in your head properly
[1:13:26]
you will always be on record that you said no to a memorial.
[1:13:29]
Something that the families have waited
[1:13:31]
five years something this committee
[1:13:32]
is waiting to heal and move on to the next chapter
[1:13:34]
of our community you guys want to say no that's fine.
[1:13:37]
>> True but -- you made a comment to what I said so I can
[1:13:42]
--
[1:13:45]
>> (Indistinct) debate is over debate is over
[1:13:47]
the question's been called.
[1:13:48]
Madam clerk let's finish this up please.
[1:13:52]
>> Absolutely yes I'm very glad to vote yes for this it's been
[1:13:56]
five years.
[1:13:59]
And absolutely yes thank you.
[1:14:01]
>> Mayor Danzinger.
[1:14:04]
>> Yes and I there's not one family member here so.
[1:14:09]
We're going to say yes.
[1:14:10]
>> Motion carries.
[1:14:12]
Motion to adjourn?
[1:14:14]
>> For what?
[1:14:22]
>> The budget was already approved by the previous
[1:14:25]
commission back in, this is just the contract terms.
[1:14:30]
>> Motion to adjourn?
[1:14:34]
>> Second.