Transcript
SOURCE TRANSCRIPT
This transcript is downloaded from the source you provided but we haven't reviewed it for accuracy. Treat it as a starting point, not a verbatim record. You can also request an AI-transcription of the audio file with the button to the left.
[0:11]
We're live now. Um before we start, I'd
[0:14]
just like to uh welcome uh Mark Langden
[0:17]
to the parks and waterways. Um hopefully
[0:20]
uh you have a good three years with us
[0:21]
or more. Thank you, Mark.
[0:25]
» Um we'll start off by uh the opening of
[0:28]
the meeting. Um,
[0:30]
Nathan, can you please play the
[0:32]
recording?
[0:35]
» Today's meeting is being streamed live
[0:37]
on the Township of Rome YouTube channel.
[0:40]
Be advised that by attending a public
[0:42]
meeting of the commission, you are
[0:44]
consenting to your image, voice, and
[0:46]
comments being recorded and will form a
[0:48]
part of the public record. The chair,
[0:51]
CEO or secretary have the discretion and
[0:54]
authority at any time to direct the
[0:56]
termination or interruption of live
[0:58]
streaming in exceptional circumstances
[1:00]
where the content of the debate is
[1:02]
considered inappropriate to be
[1:04]
published. Attendees are advised that
[1:06]
they may be subject to legal action if
[1:09]
their actions result in unacceptable
[1:11]
behavior or comments.
[1:14]
» Thank you, Nathan. Um, one other thing I
[1:16]
did want to say before we started was,
[1:18]
um, on our last parks and waterways
[1:20]
meeting, um, we had people complaining
[1:22]
they couldn't hear what we were saying
[1:24]
and that we had to get closer to the
[1:26]
mic. And when I went home, I went back
[1:28]
and I watched the recording. I could
[1:30]
hear everything plain like didn't seem
[1:32]
to be any issues at all. So, it seemed
[1:34]
more of the problem was in here. So, I
[1:36]
think when there's people here, we got
[1:37]
to get closer to the mic. But other than
[1:39]
that, I think it was fine back back when
[1:41]
they check it. So anyways, to start off,
[1:43]
we'll start the adoption agenda and our
[1:45]
agenda additions. We're trying something
[1:47]
new this time.
[1:50]
» Oh, I did say that. I'm sorry. I could
[1:52]
see my Rebecca was going to tell us. Go
[1:54]
ahead.
[1:55]
» Yes. Through the chair. Yes. So, we do
[1:57]
have um an amendment to the motion that
[1:59]
was on the agenda just to change the
[2:00]
order. Uh so, the amended motion would
[2:04]
be that the Lagoon City Parks and
[2:05]
Waterways Commission agenda dated August
[2:07]
13th, 2026 be adopted as amended to move
[2:10]
item 8.2 to water mover study before
[2:13]
item seven accounts and budgets to allow
[2:15]
for attendance by an external
[2:16]
consultant. Uh so for the commission's
[2:18]
knowledge uh a consultant from TAM
[2:20]
engineering is available on Zoom to
[2:23]
speak to this item. [snorts]
[2:25]
» Thank you. Uh the mayor has moved it.
[2:28]
Second by the deputy mayor.
[2:32]
All in favor? That's pass.
[2:43]
So Rebecca, did you want to read that
[2:45]
the recommendation? [snorts]
[2:47]
» Yes. So through the chair, the next item
[2:48]
will just be adoption of minutes. So we
[2:50]
do have one vote for both sets of
[2:52]
minutes. If you'd like to talk about
[2:53]
either of them separately, please let us
[2:54]
know. So it's just that the minutes of
[2:56]
the following Lagoon City Parks and
[2:57]
Waterways Commission meetings be adopted
[2:59]
as presented. LCPWC meeting minutes
[3:02]
dated July 9th, 2026 and LCPWC close
[3:05]
session meeting minutes dated July 9th,
[3:07]
2026.
[3:09]
» So I need somebody to put on the floor
[3:11]
each one. So we'll do um 3.1 first.
[3:14]
» To the chairs just one vote for both
[3:16]
unless you'd like to talk about them
[3:18]
separately. So if you're comfortable
[3:19]
adopting both without any changes, then
[3:21]
we would just need one mover and one
[3:22]
second.
[3:24]
» Um I guess five to five. Does anybody
[3:27]
have a discussion that before I put on
[3:29]
the Okay. Um we'll put on the floor um
[3:33]
mayor second by uh councelor Hart or
[3:36]
Commissioner Hart.
[3:38]
Um so any there's no discussion. Um
[3:43]
all in favor
[3:47]
um four disclose your appearing
[3:50]
interest.
[3:52]
I don't see anybody. um open form
[3:55]
regarding agenda items only. Uh we don't
[3:57]
have anything that just came. Um
[4:01]
[snorts] presentations and receiving
[4:03]
petitions deputations. We don't have
[4:05]
anything. [clears throat]
[4:06]
Um we'll move then right to 8.3.
[4:11]
Um would you put that up please?
[4:28]
uh through the chair. So we do have a
[4:30]
general manager Laura Pi and the
[4:32]
consultant from Tate of Engineering on
[4:34]
the screen. We do have a draft motion.
[4:36]
However, it is looking for direction
[4:37]
from the commission to be completed. So
[4:39]
I'll read what we have, but my
[4:41]
suggestion would be that the commission
[4:42]
discuss what you would like to do and
[4:44]
then if you have a preferred direction,
[4:46]
we can put that on the floor and take a
[4:47]
vote on it at that time. So currently
[4:49]
it's drafted as that report LC1426
[4:52]
regarding water mover noise study update
[4:54]
be received and that the commission
[4:56]
provide direction to staff as to the
[4:58]
requirement for operation and timing of
[4:59]
the water movers.
[5:02]
So put on the floor deputy mayor second
[5:05]
by uh commissioner um
[5:09]
um I think we have somebody to speak
[5:11]
from Tatum there. Um
[5:16]
» Yes my name is Along Guruhi and I'm from
[5:18]
Tatum Engineering. [clears throat]
[5:21]
» Okay.
[5:24]
» Go ahead. Can you just give us an update
[5:26]
on the report is pretty lengthy. maybe
[5:29]
tell us a little bit about it.
[5:31]
» Of course. Uh I I just add a little
[5:34]
background about the water movers noises
[5:36]
study that Tatum completed. We started
[5:39]
the project in 2023 I believe. Uh at
[5:42]
that time we um the township was
[5:45]
receiving complaints about the noise and
[5:47]
we completed a noises study and uh the
[5:51]
results showed that one of the water
[5:53]
movers noise is exceeding the limits and
[5:55]
and and the noise is tonal. Uh so 5 dB
[6:00]
was added as like [clears throat]
[6:04]
to account for the tonal noise. Uh after
[6:07]
that uh Tatum completed some u
[6:11]
study to offer some modifications to the
[6:14]
water movers uh uh structure uh which
[6:17]
includes VFD uh uh variable frequency
[6:21]
drives to to be able to control the
[6:25]
speed of the pump. However, the township
[6:28]
uh due to co cost uh issues did not
[6:32]
install that and they they made some
[6:34]
other modifications.
[6:36]
Uh Tatum Engineering completed another
[6:39]
site visit in July 14 this year uh to
[6:42]
confirm uh if the modifications were
[6:46]
effective. Uh we did the noise
[6:48]
measurements for both water meters. uh
[6:50]
the uh we did noise measurements on the
[6:54]
shoreline and also uh uh we used barge
[6:57]
to get closer to the water movers. Uh
[7:01]
once we did the measurements we
[7:04]
completed the noise modeling at the
[7:06]
location of the sensitive receptors
[7:08]
closest ones to the water movers. Uh the
[7:11]
sensitive receptors are the locations
[7:13]
where people usually
[7:15]
use um uh it's um it is outdoor spaces
[7:19]
and also the plane of window
[7:21]
representing their bedroom or living
[7:23]
room spaces.
[7:25]
» [snorts]
[7:26]
» The measured noise were modeled at those
[7:28]
locations and the modeling results
[7:30]
showed that uh both water meters can
[7:33]
meet MPC 300 and MECP noise requirements
[7:37]
uh under all like all day conditions
[7:41]
like daytime, nighttime and evening
[7:43]
times. Uh
[7:46]
uh yeah. So both are within uh with
[7:50]
compliance within compliance uh at all
[7:54]
operating hours.
[7:57]
» Okay.
[7:59]
Does anybody have any questions?
[8:05]
» Um I I have a I I have a question. Um I
[8:08]
was just wondering when I'm reading that
[8:10]
one like and like read it properly. Did
[8:13]
one pump sound a lot less and the other
[8:16]
pump was louder? That's what I was
[8:19]
reading and then I was reading somewhere
[8:20]
else that it seemed like both pumps were
[8:22]
too loud.
[8:24]
» Uh originally I think the both pumps
[8:28]
were loud but uh this uh the south water
[8:31]
mover was much louder
[8:34]
uh and tonal. Uh but when we did uh the
[8:37]
revised measurement uh both were in the
[8:40]
same range.
[8:42]
both in the same range.
[8:43]
» Yes.
[8:46]
» So the the like going over it all like
[8:48]
because um I know I was looking at that
[8:50]
report and I'm not an engineer trying to
[8:52]
understand this. The noise really has
[8:54]
not
[8:56]
backed off. It's it's still somewhat
[8:58]
loud for people.
[9:01]
» No, it is not. Uh it is within the um uh
[9:05]
MECP limit. So, MECQ limit says that
[9:08]
daytime noise uh below 50 dBA noise at
[9:13]
daytime and below 45 dBA at night time
[9:16]
is an acceptable level. Uh I think the
[9:19]
water movers noise were all uh time
[9:24]
limit and night limit.
[9:29]
of
[9:30]
» I think it's it was around like highest
[9:35]
level at was at one of the residents up
[9:38]
the living area was 40 40.9 dBA and it
[9:44]
is below the daytime limit of 50 dBA and
[9:48]
nighttime limit of 45 dBA.
[9:51]
» Okay. Um let's do the mayor first then
[9:54]
uh council.
[9:55]
» Well, when I was looking at part of the
[9:57]
report here, it showed that they
[9:58]
actually ran quieter in the evening. Why
[10:00]
is that? Are we reducing the load on
[10:02]
them? Are we turning them down? Why? Cuz
[10:06]
at one time, like one of them was
[10:07]
running 48 during the day, and I know
[10:09]
the limit's 50, but 48 is not
[10:11]
acceptable. I I mean, that's what I read
[10:13]
in here. We'd have to do something. The
[10:15]
quietest I've seen them run is is down
[10:17]
around that 40. And still I would
[10:21]
consider that quite loud. So is there a
[10:23]
reason why the sound is different at
[10:25]
night coming out of the motors? Not I
[10:27]
know the decibels must be lower at night
[10:29]
so people can sleep but why is is the
[10:32]
level changing on some of them but not
[10:34]
the other one.
[10:35]
» Uh the sound level um at night is
[10:38]
similar to the day but the limit is
[10:41]
lower because the nighttime is the
[10:43]
sleeping time. uh and that's why the
[10:46]
MECP put a lower limit for nighttime. So
[10:49]
if a water mover or or any other
[10:51]
equipment uh is to operate at night,
[10:54]
they they must meet the uh nighttime
[10:57]
noise levels uh which is quieter and
[11:00]
more stringent.
[11:04]
» Um Commissioner Hart,
[11:07]
» Turn your mic.
[11:12]
Chairman, I had the same kind of
[11:13]
questions that if so what what I
[11:16]
understand so I'm clear because the
[11:17]
acoustics here is not not the best. Uh
[11:20]
but and I but I've read the report but
[11:22]
so what what you're saying is that there
[11:25]
are acceptable standards.
[11:28]
We're within the reason of acceptable
[11:30]
standards at the present time. Is that
[11:33]
correct?
[11:35]
» That's
[11:37]
sorry chairman. My my question was the
[11:40]
the acoustics here is a bit difficult
[11:42]
for me but I I I have read the report
[11:46]
and just so I'm clear that the the
[11:49]
standards uh that we have now are are
[11:52]
are deemed acceptable
[11:55]
both day and night at at 45
[12:00]
» This center. Yeah, go ahead.
[12:02]
» Um Laura, would you like to say
[12:04]
something? Yeah. So, yes, it both water
[12:08]
movers are currently um the noise coming
[12:11]
from them are below the compliance
[12:13]
limits. However, to the commission's
[12:16]
point, um it may still not be acceptable
[12:19]
to the people who are living nearby
[12:22]
listening to them 247, which is why
[12:25]
we're also seeking direction on how the
[12:29]
commission would like us to operate
[12:30]
these, if at all. Um, I can say that
[12:34]
operationally we are seeing quite a bit
[12:36]
of duckweed um within that canal and
[12:39]
these water movers are effective at
[12:41]
moving those. Uh, we currently have a
[12:44]
timer um that's in the cabinet that
[12:48]
would allow us to have one cycle of on
[12:51]
and off, which is what we were operating
[12:53]
on earlier this year. Um, however, we've
[12:56]
looked and we can invest in a couple of
[12:58]
different timers um that would allow us
[13:01]
to have up to six cycles per day. So, it
[13:04]
could be that we cycle them on for a
[13:07]
duration and then have them off for a
[13:08]
duration as well. So, yes, the water
[13:11]
movers are under the acceptable limits
[13:14]
for sound. However, the people who live
[13:18]
nearby who have complained um may not
[13:22]
appreciate them running 24/7. And that's
[13:24]
where we're seeking that direction from
[13:25]
the commission is do you want us to turn
[13:28]
these on? And if so, how would you like
[13:31]
us to turn those on? Because
[13:33]
understanding that they are meeting
[13:35]
those requirements for both day and
[13:37]
nighttime uh usage.
[13:42]
» Chairman, thanks for
[13:45]
thank you for the clarification. Um the
[13:48]
so the the standards are are per
[13:50]
acceptable but but for for the residents
[13:52]
of that particular area those st is
[13:55]
still is still considered to be um high
[13:59]
or or nuisance or or or troubling for
[14:01]
them. So even though we do meet the the
[14:03]
the standard based on
[14:06]
whatever premise that those standards
[14:08]
come from obviously the engineering
[14:10]
standards um if we we can still can we
[14:13]
still have some flexibility in terms of
[14:15]
of working with that? I like the idea of
[14:17]
having a timer but are there other
[14:19]
options we can consider?
[14:23]
Um is that a question too?
[14:25]
» Yes, that's that's a question.
[14:28]
» So
[14:29]
» Laura, do you want to answer that
[14:30]
question? Yeah, [snorts] through you,
[14:32]
Mr. Chair. Um, so again, the the
[14:34]
commission may remember that the
[14:36]
original uh proposal from TAM
[14:38]
Engineering was to install the variable
[14:41]
frequency drives. Uh, that would have
[14:43]
the potential to reduce the speed of the
[14:46]
pump um in general and what it's
[14:48]
operating at uh which could again
[14:51]
potentially lower the sound. We just
[14:54]
don't know until that uh the VFD is
[14:57]
installed and operating. Um, however,
[15:00]
that came with a fairly significant
[15:02]
price tag. I believe it was close to the
[15:04]
$10 to $15,000 per mover, which is why
[15:09]
we tried to do this less expensive
[15:11]
mitigation measure, which did reduce the
[15:14]
sound below to that acceptable level.
[15:16]
So, we were successful in getting it
[15:18]
below the the the acceptable limit. Um,
[15:23]
other than that, the other option we
[15:25]
could consider is uh leaving them off
[15:28]
for now. Understanding that there's
[15:30]
going to be some uh duckweed um that the
[15:34]
the harvesters do are challenged with
[15:37]
trying to pick it up through skimming
[15:38]
activities. That isn't something that we
[15:41]
can easily achieve. Um however we as
[15:44]
part of the budget consideration for
[15:46]
next year um referencing one of the
[15:49]
other reports we'll be discussing in a
[15:50]
little bit there is a proposal for a
[15:52]
study which could consider other
[15:54]
technologies but at this time we're
[15:56]
limited to uh either the movers being
[16:00]
off or on um and having additional
[16:04]
timers or potentially looking at
[16:06]
installation of VFDs which may or may
[16:08]
not be um successful. Well,
[16:13]
» Uh, Deputy Mayor,
[16:14]
» Yeah, I it's just my opinion, but I do
[16:16]
think that we probably need to look at
[16:18]
shutting these down and start to monitor
[16:19]
them weekly to see what the duckweed
[16:21]
does. Um, and then we can reassess at
[16:23]
that point. But I think we need to give
[16:25]
some of these folks a bit of the summer
[16:26]
that are having a hard time sitting out
[16:27]
on their deck because I know in that one
[16:29]
condo where that mover is, there's been
[16:30]
I've been over there, I visited them.
[16:32]
It's hard to just sit out there. At
[16:34]
first, you don't notice it, but after
[16:35]
you sit there for 15, 20 minutes having
[16:37]
a conversation, you just hear a constant
[16:39]
buzzing and it does get to you. And I
[16:41]
know there's a lady there that did have
[16:42]
an accident that has a brain injury. She
[16:44]
isn't even able to sit outside right now
[16:45]
because it just affects her that
[16:46]
frequency. I think we should give them a
[16:48]
bit of a reprieve, do that, and then
[16:50]
look at the the options for next year.
[16:54]
Laura,
[16:58]
» Uh through you, Mr. Chair, just to
[17:00]
clarify, the water movers have been off
[17:01]
since the last commission meeting. So,
[17:03]
we have not had them on for the last
[17:05]
couple of weeks. Um, they've been on or
[17:08]
off for the purposes of uh TAM finishing
[17:12]
their um noise assessment and then a
[17:14]
couple of operational moments, so not
[17:16]
extended periods. Um, and there has been
[17:20]
uh quite a bit of duckweed growth
[17:22]
through there. Um, I will leave it to
[17:24]
the commission to determine if that's
[17:26]
acceptable or not.
[17:29]
Um, I I I have a question for um the
[17:32]
lady from Tatum. Um,
[17:34]
do you know of pumps that are out there
[17:37]
that are quieter than these ones?
[17:39]
Because I I remember when the old pumps
[17:41]
were there. The first time I You
[17:43]
probably all heard this story, right?
[17:45]
The first time I went, I couldn't figure
[17:47]
out if they were on. They were that
[17:49]
quiet. They were totally quiet. You
[17:51]
didn't even know they were on. And I'm
[17:54]
and I remember back, this goes back, I
[17:56]
don't know, 15, 18 years, when I looked
[17:59]
at the prices, the prices were like
[18:01]
almost $100,000 for these pumps. And I'm
[18:03]
pretty sure the ones we just bought were
[18:05]
like 4550,000.
[18:07]
So the the price difference tells me the
[18:09]
quality. And I'm wondering whether or
[18:11]
not there are quality pumps out there
[18:13]
that we should be looking at. Cut our
[18:14]
costs on this because we're wasting so
[18:16]
much time and money on this. We all know
[18:19]
it works well. It's been working like
[18:21]
that for like 15 years, 12 years. I
[18:23]
don't need a study. I've talked to the
[18:25]
people that have lived over there for
[18:26]
years and years and they used to be
[18:28]
after me when those pumps didn't fire up
[18:30]
in the spring. They were all over me.
[18:31]
They wanted those pumps running because
[18:33]
they saw the duckweed and they saw the
[18:35]
issues that were happening there. So, it
[18:37]
does help and we do need them there. We
[18:38]
do need the water movement and we should
[18:41]
even be looking to look at other areas
[18:43]
to move water around and maybe that's
[18:45]
what that study could do. But I I wonder
[18:47]
could we just get some prices on like a
[18:50]
pump and if there's this pump out there
[18:51]
because I know I googled and said
[18:53]
quietest pumps in the world and they
[18:54]
bring me a whole bunch of pumps and
[18:56]
things. Well, we just go out and take a
[18:58]
look and listen to it. And I know I
[19:00]
brought this idea to Laura when I was
[19:02]
talking to her about it and her comment
[19:04]
was and I I appreciate what you're
[19:07]
saying that it depends on the location
[19:09]
and where it is and so on and so forth
[19:11]
vibrations, but I think if the pump's
[19:13]
that quiet, I can't hear it out there.
[19:15]
it's going to work a lot better. Uh, I
[19:18]
agree 100% with what the deputy mayor
[19:20]
said. I've been over there, too. I
[19:22]
couldn't put up with that noise. I I
[19:23]
think it's too loud. I know it's legally
[19:25]
loud, but illegally allowed to be that
[19:28]
loud, but it's just constant. And it's
[19:30]
not a nice feeling. It It's not really
[19:32]
It's It's just I don't think it works.
[19:34]
And I wouldn't want to run them again,
[19:36]
even if they're at 40. I I think they
[19:39]
got to be like under like 20. I think 15
[19:42]
even, right? So that's something that I
[19:44]
would really like to look into and we'll
[19:46]
I think we're going to be talking about
[19:47]
that later. Correct. Uh Laura, we'll be
[19:50]
just Oh, no. We're talking about it now
[19:52]
because we have to make decision now. My
[19:53]
apologies. Yeah. So, mayor.
[19:56]
» Well, my Yeah, now I they're off, but if
[19:59]
the duckweed builds up, I certainly
[20:00]
wouldn't be turning them on, leaving
[20:02]
them on all day. If you've got the
[20:03]
capability of up to six times, you know,
[20:06]
have them How long does it take to
[20:08]
establish the water flow? Like if they
[20:09]
ran for two hours and shut off for two
[20:11]
hours, ran for two and then not on at
[20:13]
night at all. Like is there a way do you
[20:16]
know roughly how long it takes to
[20:18]
establish that water flow?
[20:20]
» Uh through you, Mr. Chair. Um I
[20:23]
understand uh from Mr. Lenny who's
[20:26]
joining us today. Um he's our new
[20:29]
operations manager that um last week
[20:32]
within five minutes we saw a noticeable
[20:34]
change to the duckweed. So, I agree that
[20:37]
we could do it for short durations, um
[20:40]
potentially on for even um 30 minutes
[20:44]
and then off for uh an hour and do that
[20:48]
during some daytime hours. We can put a
[20:50]
break in there um as well uh and see if
[20:54]
that's effective and we can kind of
[20:55]
adjust uh those timings as we see um how
[21:00]
effective it is and if uh the commission
[21:03]
would give us direction uh delegation to
[21:05]
be able to adjust them minimally to to
[21:08]
make sure that they're still being
[21:09]
effective without uh um changing it
[21:12]
drastically.
[21:13]
» That would be my suggestion if we have
[21:15]
to turn them back on so they're not
[21:16]
running constant. U and just in in that
[21:20]
when um and this I quote back when I
[21:23]
became a um a commissioner back many
[21:26]
years ago, one of my biggest complaints
[21:28]
was the electrical bill with that and it
[21:30]
had been running for 24 hours. So we
[21:32]
started experimenting on using it at
[21:35]
night where the electricity was cheaper
[21:37]
and we found it did work. We were
[21:39]
running it in the morning and at night
[21:41]
except in the spring. We left them on 24
[21:45]
hours because we really needed it
[21:46]
because the p they were power hogs. The
[21:49]
old ones they used up so much power. So,
[21:51]
uh, what the mayor is saying, I I agree
[21:53]
we can do that, but maybe pick an hour,
[21:56]
say 11:00 or 12:00 during the day where
[21:59]
everybody's up and let them run for a
[22:01]
little bit. But the key right now is
[22:03]
that we can pick up the duckweed with
[22:05]
our harvesters now. We can get in the
[22:07]
area. The problem with the duckweed is
[22:10]
when um we do and I do want to talk
[22:13]
about skimmers and that and that's
[22:14]
something we're going to talk about
[22:15]
later I guess at capital but um to pick
[22:18]
it up now and the reason I say we pick
[22:19]
it up now is if you go down and you pick
[22:22]
up weeds and then you bring the weeds up
[22:24]
as you're bringing it you can draw the
[22:26]
duckweed off the top of the water but
[22:28]
when we're just skimming during
[22:30]
springtime we have a lot of problem with
[22:32]
the screen it falls right through but if
[22:34]
we're taking weeds out we utilize the
[22:36]
weeds to help lift the duckweed Yeah,
[22:38]
I've watched um them do it before. It
[22:40]
really works quite well. And and I do
[22:42]
understand what you're I know what
[22:43]
you're about to say, Laura.
[22:45]
Yeah. But you could say that if you
[22:47]
want, but that's how we we learned how
[22:48]
to do it. Yeah.
[22:51]
» Um definitely.
[22:52]
» I think back in 2022, I had asked um
[22:55]
Josh Kavanagh, who was here with us, um
[22:57]
to look at brushless motors. At that
[22:59]
point, they didn't they couldn't find
[23:00]
any brushless pumps. I'm just don't know
[23:02]
if that's maybe something that's come
[23:04]
about. I know I put him in contact with
[23:06]
a company called NCH in Barry on Wellm
[23:08]
Road um and they specialize in in
[23:10]
specialty pumps. So maybe that would be
[23:12]
somewhere to start when we start looking
[23:13]
at that study. But there there does I
[23:15]
agree with Cal. We were actually looking
[23:16]
at rebuilding one of those. Um we had
[23:18]
one left in the core. We were going to
[23:20]
rebuild it, but I don't know what ever
[23:22]
happened to that.
[23:22]
» I asked that. I [clears throat]
[23:25]
Laura
[23:25]
» Uh uh through you, Mr. Chair. Yes, we
[23:28]
still have had one of the pumps.
[23:30]
However, getting parts for it was uh the
[23:34]
challenge. So, those pumps were original
[23:36]
with the original water movers in 1999,
[23:39]
early 2000. Uh and the the uh repair
[23:43]
parts are not available for those pumps
[23:45]
anymore, which is why the decision was
[23:47]
made to replace those. Um and again, we
[23:50]
can definitely consider options for
[23:52]
different pumps um going forward. I
[23:55]
would say that that would be a request
[23:57]
for 2027 budget.
[24:01]
I would like to see that in the budget
[24:02]
for sure that in the study I think we
[24:04]
need to this has been gone going since
[24:05]
I've been on in 2022 and long before
[24:07]
that I think how you and the mayor
[24:09]
probably remember how far back it's gone
[24:11]
but previous people that lived there
[24:13]
have had the same issues so that we need
[24:15]
to look at this and get a final
[24:16]
solution.
[24:19]
Uh, Commissioner.
[24:20]
» Yeah, Chairman, if I just may comment,
[24:22]
it it it's so just to so I understand it
[24:25]
meets the acceptable standards, but it's
[24:27]
not acceptable to the people uh of of of
[24:30]
that area and and
[24:34]
we have to uh and the water moves big
[24:36]
plays a big important role in in proper
[24:39]
uh canal maintenance as well as as
[24:42]
harvesting. But I think we have to move
[24:44]
forward and and and examine what if
[24:46]
there is a cost look at other options.
[24:49]
But this is something that we have to
[24:50]
take uh we are taking very seriously and
[24:53]
we got to come to a a favorable
[24:55]
conclusion that we can have the water
[24:57]
movers and still meet uh acceptable
[24:59]
standard for the people who live in that
[25:01]
area.
[25:03]
I I think we all agree with that. Yeah.
[25:06]
So I guess what we need to do now is
[25:09]
figure the direction that we're going to
[25:10]
ask of staff. And I I would love to
[25:13]
actually look at new pumps. I really
[25:15]
would. And see how much they are and
[25:17]
this could solve all our problems in one
[25:19]
shot. Like, you know, we might have to
[25:20]
pay a little more for the pumps, but
[25:22]
these pumps here, I I just think they're
[25:24]
cheap pumps. Actually, my my feeling
[25:26]
with about it right now. Um Deputy
[25:29]
Mayor,
[25:29]
» But I do know that's not in the budget
[25:30]
this year. So, that's something we need
[25:32]
to add to the budget when we're talking
[25:33]
about the budget. But this year, I don't
[25:35]
know. I think we need to let staff kind
[25:37]
of experiment a little bit whether it's
[25:39]
every day or every other day and do the
[25:41]
timers and see if we can if that can
[25:43]
kind of mitigate some of the complaints
[25:44]
and keep that duckweed down. I think
[25:46]
that would be the direction I'd
[25:48]
» Yeah, I think we've agreed that we can
[25:49]
run it for an hour or two at lunch at
[25:50]
noon or something like that, right? And
[25:52]
see how it works, right? uh it it does
[25:55]
help us and we do need it on. So we
[25:58]
really know we have to get the pumps,
[26:00]
but I think really we should be giving
[26:01]
direction also to be looking at new
[26:03]
pumps because we're going to be looking
[26:04]
at budget today. We may want to get a
[26:06]
rough idea like what that's going to
[26:08]
cost us too because we might want to
[26:10]
move something out that's in there, you
[26:12]
know, to put it forward. And I I don't
[26:16]
we'll talk about the budget later now.
[26:18]
So I I guess we're we're kind of done
[26:22]
with Tatum. I don't Do you guys have any
[26:24]
more questions for Tatum? I guess
[26:26]
because we're gonna have to discuss it
[26:27]
now or what are we going to do like um
[26:30]
would would if we're looking at getting
[26:32]
an idea of new pumps and and exploring
[26:35]
that. Would you be doing that Laura?
[26:37]
» Uh Laura?
[26:38]
» Yes, we would be able to help with that
[26:40]
and also uh the new pumps will have
[26:42]
manufacturer data on their noise levels.
[26:45]
we can uh review all those manufacturer
[26:47]
data and model it uh if needed to see if
[26:52]
they are meeting uh the requirement
[26:54]
levels for the residents.
[26:58]
» Is that how you would do it Laura? Like
[27:00]
would you then go through Tatum or would
[27:02]
you look like how would we what would be
[27:04]
our next steps?
[27:05]
» I I think because this has been an
[27:08]
ongoing issue and the noise sensitivity
[27:11]
is important. Yes, I would um I would
[27:14]
contract a consultant to assist with
[27:16]
that procurement uh to determine which
[27:19]
path would be the best option. We could
[27:22]
look at that being conducted as part of
[27:24]
the overall study that's proposed for
[27:27]
2027. Uh when we get to the budget
[27:30]
portion of that, um for the purposes of
[27:33]
this report though, I need direction on
[27:36]
what you would like us to do with the
[27:39]
water movers right now. And so we can
[27:42]
leave the other discussion for budget.
[27:44]
Uh but for right now, what do we want to
[27:46]
do with the existing water movers? Uh
[27:48]
and when do you want and if we're
[27:50]
running them, how would you like us to
[27:52]
run them?
[27:54]
» So that's discussion. Many people said
[27:56]
that you want to run for a couple hours.
[27:58]
» Yeah, I would say. But what what if we
[27:59]
just gave you say three hours a day m is
[28:02]
the maximum we want to see them on Laura
[28:03]
and let you decide when when it might be
[28:05]
the most effective to use those three
[28:06]
hours with the less less least impact.
[28:10]
Is that enough direction
[28:12]
» Through you? Yes, that's fine. Um, I
[28:15]
would like also maybe uh a time frame of
[28:18]
what would be acceptable hours to run
[28:20]
them in.
[28:22]
» How many hours do you think would be
[28:23]
acceptable?
[28:25]
» I believe an hour in the morning or an
[28:26]
hour in the afternoon, an hour in the
[28:27]
evening. Just take an hour block out of
[28:29]
each each section. That gives people
[28:31]
windows of those sections depending on
[28:33]
when they like to go and enjoy the
[28:34]
water.
[28:35]
» Can you do that, Laura? Like an hour in
[28:36]
the morning, an hour in the afternoon,
[28:37]
an hour a day.
[28:39]
Uh yes, we can. We'll we'll purchase
[28:41]
those uh different timers which will
[28:44]
give us flexibility for that. Um it
[28:47]
should be able to be accommodated within
[28:49]
our operating budget for this year for
[28:51]
us to get those purchased and installed.
[28:54]
Um and then just to clarify, morning
[28:57]
would be anything beyond 8:00 a.m.
[29:02]
between 8 and 12 noon. Afternoon would
[29:05]
be 12 to 4 and evening would be 4 to
[29:10]
8:00 p.m. That's where I I need to
[29:12]
understand
[29:13]
what your distinction of the times are.
[29:16]
» So really what they're saying is you're
[29:17]
saying an hour. So 9:00 in the morning
[29:19]
till 10:00 uh 2:00 till 3:00 and 7
[29:23]
o'clock to 8 o'clock. Is that all right?
[29:28]
And and before going forward, you're
[29:31]
saying we're going to have to purchase
[29:32]
timers and labor to do that. Couple
[29:35]
thousand dollars. Is that what we're
[29:36]
talking now?
[29:37]
» Yeah, less than that. I would suggest
[29:39]
» Less than that. What about weekends?
[29:44]
» You would keep it the same.
[29:47]
» That's what I'm asking at. So,
[29:49]
» All right. So, we'll do it seven days a
[29:51]
week then. Is that enough guidance?
[29:56]
Yes, that's fine. Um, and I just want to
[29:59]
confirm with uh Madame Clerk that she
[30:02]
has that for the motion uh to confirm
[30:06]
» Uh through the chair. I'm just getting
[30:07]
that motion drafted. If I could just ask
[30:09]
for clarification. Uh, Commissioner
[30:11]
Johnson, you had mentioned a time frame
[30:12]
for the afternoon. So, you had 9 and
[30:15]
10:00 a.m. for the morning, 7 and 8:00
[30:18]
p.m. for the evening. What was the time
[30:19]
that you had noted for the afternoon?
[30:22]
» I think we had initially said 2 to
[30:24]
three. There is some discussion on the
[30:25]
floor right now though, Laura, just so
[30:26]
you know. I think we're we're
[30:27]
questioning that time at night because
[30:29]
people do like to go out and have a
[30:30]
coffee and watch the sunset. So maybe
[30:32]
that that 8:00 is a bad one. Maybe we
[30:34]
need to do kind of 5 to 6 or 6 to 7.
[30:37]
» 6 to 7 when people are eating dinner
[30:39]
maybe.
[30:39]
» Yeah, [laughter] I'm thinking 9 to 10 in
[30:41]
the morning is better as well. They can
[30:43]
have the coffee in the morning, but
[30:44]
that's just me. 9 to 10, 2 to three,
[30:47]
» And then six to seven. And you do know
[30:49]
what we're doing now is we're making it
[30:51]
louder when it goes on because people
[30:53]
are used to the silence. And when that
[30:55]
turns on, they're going to hear the
[30:57]
noise. So they're going to hear it three
[30:58]
times a day. And I noticed that with a
[31:00]
piece of equipment I had in my plant
[31:02]
that as long as we left it running, we
[31:04]
had no complaints was when we turned it
[31:05]
on and off at times it was off for a
[31:07]
couple hours complaints came.
[31:08]
» I know. So be prepared for
[31:10]
» One complaint at a time. That's all.
[31:14]
» So anyways, so did you get that time up?
[31:17]
Yeah. Rebecca
[31:18]
» To the chair. Yes. So, I do have a
[31:19]
motion drafted. If you'd like, we can
[31:21]
put it on the screen and I'll read it
[31:22]
and if you have any changes, please let
[31:23]
us know. Uh, so what we have drafted
[31:26]
currently is that report LC1 1426
[31:29]
regarding water mover noise study update
[31:31]
be received and that the commission
[31:33]
direct staff to evaluate variable timing
[31:35]
for the water movers to a maximum of 3
[31:37]
hours per day, 1 hour in the morning
[31:39]
between 9 and 10:00 a.m., 1 hour in the
[31:41]
afternoon between 2 to 3:00 p.m., and 1
[31:43]
hour in the evening between 6:00 and
[31:45]
7:00 p.m. 7 days a week. and assess the
[31:47]
impact for the remainder of the 2026
[31:49]
season and that the purchase of new
[31:51]
water mover pumps be referred to the
[31:52]
2027 budget process for consideration.
[31:57]
» Who was the um put it on who put it
[32:00]
» I'll wear the heat for that one.
[32:02]
» Did you put on the floor
[32:04]
» Through the chair? We did have uh the
[32:05]
deputy mayor as a mover and commissioner
[32:08]
Langden as the seconder for the
[32:10]
original.
[32:10]
» So you all right with the changes then
[32:12]
you guys?
[32:13]
» Yeah, you're all right with the changes.
[32:15]
Okay. So, uh, no more discussion on
[32:17]
that. All in favor?
[32:21]
Thank you very much. Thank you very
[32:22]
much. Uh, I could I'm trying to see your
[32:25]
name by the lady from Tatum. Thank you
[32:26]
very much.
[32:29]
» No worries.
[32:32]
» We're done. Um, next one we're going to
[32:35]
go to 7.1.
[32:38]
Um, account vouchers dated July 31st,
[32:41]
2026.
[32:44]
uh through the chair. The motion for
[32:46]
this is that the accounts vouchure date
[32:47]
at July 31st, 2026 be received as
[32:50]
information. Let
[32:52]
» Me put on the floor for me, please. I
[32:54]
see the mayor's looking at me and I'll
[32:56]
look over here to commissioner and you
[32:59]
second it.
[33:02]
Um discussion.
[33:08]
Okay, I have stuff on here. I just I got
[33:11]
to find it now.
[33:13]
here.
[33:17]
Bear with me while I find this. Thanks.
[33:20]
Yeah, I know. I think we're all firing
[33:21]
up our computers now.
[33:54]
Does anybody got something to say while
[33:55]
I'm looking here? I do have things. I
[33:57]
just have to find it. I haven't found it
[33:59]
yet. Um,
[34:03]
that's what happens without order, huh?
[34:13]
There we go. I finally found my um I
[34:16]
have a couple questions on that. Um the
[34:18]
scare tape, we're still using that
[34:22]
like we're selling it to residents.
[34:26]
» Uh
[34:27]
» Sorry, Mr. Chair. Yes, that's correct.
[34:29]
If if a resident um is requesting it, we
[34:33]
do sell it at the township office. Do
[34:35]
you sell a lot of it? Like I I thought
[34:37]
we stop I thought we stopped um
[34:38]
supplying it.
[34:40]
» Uh no, we don't sell uh a lot of it. I
[34:44]
think this was the first um that we sold
[34:47]
this year. Um it we may sell one or two
[34:51]
uh a year. It is in our fees and charges
[34:53]
bylaw that we do have it available for
[34:55]
them.
[34:56]
» Now I know where the my neighbor got it
[34:57]
from because I saw them with it. Um the
[35:00]
insurance is 16. Um the question I had,
[35:04]
I guess the $6,614
[35:06]
to find the anchor for the um water
[35:08]
moves. Are we going to identify where
[35:10]
because I think we've done this before.
[35:12]
Uh can we identify where it is so that
[35:15]
or do you need them to dive down to tie
[35:17]
onto it or can we put some sort of boy
[35:19]
on it or something so that we know where
[35:20]
it is?
[35:21]
» Uh through Mr. Chair, we'll we'll look
[35:24]
at that for this year. Yes, that was the
[35:27]
challenge was that um with all our
[35:30]
poking and proddding in the the lagoon,
[35:32]
we could not find the anchor block to
[35:34]
tie the water mover to. So, we were able
[35:36]
to locate one ourselves, but the other
[35:38]
one did require the diver. So, we'll try
[35:41]
and um even if we can't put a buoy in
[35:44]
because generally it's going to be also
[35:47]
over the winter that we'll need to it's
[35:49]
in the springtime, we'll need to be able
[35:51]
to identify it. Um, even if we GPS it,
[35:54]
it'll give us a little bit better idea
[35:56]
so that we can uh try and locate it
[35:58]
again in future years.
[36:00]
» So, you don't need them to dive down and
[36:02]
hook it all up. You just have to tie it
[36:03]
down with
[36:04]
» Yes, it it was that we couldn't locate
[36:06]
the chain to connect it to it.
[36:09]
» Um, the other one I had was the uh, and
[36:12]
anybody wants to jump in question what
[36:13]
I've asked them is the compressor
[36:15]
repair. What was that compressor repair?
[36:18]
Is that what the ones from over on
[36:19]
Paradise? Is that what you were
[36:20]
repairing? false ones.
[36:22]
» Uh it was the compressors in the bubbler
[36:25]
shed. I don't recall. I thought it was
[36:27]
two of them that needed to be repaired
[36:30]
and they are completed now. Um that had
[36:32]
been brought forward as a report from
[36:34]
last year. We did do the expansion of
[36:37]
the bubbler system. Instead, we did the
[36:39]
repairs to the compressors.
[36:41]
» Right. Okay. Because I know the
[36:42]
compressors over at Paradise, they're
[36:44]
the they're not the very they're not a
[36:46]
good type. They wear out. So, I was
[36:48]
thinking that next time they wear out,
[36:49]
we look at updating them or upgrade into
[36:51]
a better system.
[36:53]
And my last one was the shed purchase.
[36:55]
What was the shed for?
[36:58]
» Uh, the shed is located at our um
[37:00]
offload site and it was a capital
[37:02]
project that had been approved for 2026.
[37:06]
» Okay. Yes. That so that was the shed
[37:08]
then at the actual removing removal area
[37:10]
to keep our equipment there. Okay.
[37:12]
» Correct. Yes.
[37:13]
» Okay. Um, the deputy mayor,
[37:16]
» Uh, I just had a couple questions from
[37:17]
residents. Something I don't see on the
[37:19]
vouchers. Who does the cleaning? And is
[37:21]
there anybody who does a cleaning or
[37:22]
maintenance, cleans the sand or picks up
[37:24]
garbage or empties garbage? What what
[37:26]
line would that fall under? I don't see
[37:28]
it.
[37:29]
» So that uh through you, Mr. Chair, that
[37:31]
is the contracted services for Summit
[37:34]
Property Group. Um, Summit is the
[37:36]
contractor this year for one both the
[37:39]
uh, lawn cutting as well as the garbage
[37:42]
pickup and um, and maintenance of the
[37:44]
sites, the beaches.
[37:46]
» Followup.
[37:48]
» You have follow?
[37:48]
» Yeah, I just had a followup. Uh, do they
[37:50]
just do it when they come to cut the
[37:51]
grass, they just do a quick clean and
[37:53]
empty the garbages once a week or do
[37:54]
they come back more often than once a
[37:56]
week?
[37:57]
» Uh, through you, Mr. Chair. I'd have to
[38:00]
look back at the requirements of the
[38:02]
contract. Um, I do know that they're uh
[38:06]
we've been working well with them and
[38:08]
they'll be following whatever we've
[38:10]
requested them to be doing. Um, off the
[38:13]
top of my head, I don't recall what
[38:14]
those requirements are.
[38:15]
» Okay. Thank you. I don't I don't know.
[38:17]
It may be something we need to ask the
[38:18]
public if they feel there's needs to be
[38:19]
more cleaning. There may be something we
[38:21]
want to add to the next contract. That's
[38:23]
» Thank you.
[38:24]
» Well, to follow up on that, um, we had
[38:26]
looked at getting a sinker to go in
[38:28]
there. We actually got went over to
[38:29]
Barry and took a look at some of that
[38:31]
equipment and it's really expensive. We
[38:33]
were hopefully trying to say tie into
[38:36]
council because with their public
[38:37]
beaches and utilize something like that,
[38:39]
but that didn't seem to go anywhere. But
[38:40]
it really works well. You go to most of
[38:42]
these beaches like Barry, desert, all of
[38:44]
them, they have this piece of equipment,
[38:46]
they move it around and it cleans up
[38:48]
everything. It just filters. It really
[38:50]
does a great job. Um, the one thing down
[38:53]
there on that beach too is when they do
[38:54]
that plowing, what we have to do is make
[38:57]
sure that they go from end to end
[38:59]
because we've probably lost over what 50
[39:01]
100 feet of our beaches because they
[39:04]
haven't pulled it out. I think they use
[39:05]
like a plow or something that they pull
[39:07]
back and forth and they just really all
[39:09]
they're doing is just moving the dirt
[39:11]
and turning it over. But what was
[39:13]
happening was the sides were all coming
[39:15]
in. And you go take a look at the
[39:17]
especially the North Beach. The North
[39:18]
Beach has lost maybe half of its beach.
[39:20]
It's all gone and you can't go
[39:22]
afterwards as Laura has told me. We
[39:24]
can't go in there.
[39:26]
» Yeah. Um uh Commissioner
[39:30]
Chairman Beach Security
[39:36]
have
[39:38]
uh
[39:41]
for
[39:43]
the beach the the beach security piece.
[39:48]
I have uh
[39:54]
for for uh the for 2025 it's 25 and then
[39:59]
for 2026 is 10. It's been reduced. Is
[40:02]
there any consideration to having it
[40:04]
increased?
[40:08]
» Uh sorry.
[40:09]
» Yes. Yes. Thank you.
[40:11]
» Uh through you Mr. Chair. That'll be
[40:13]
discussion at budget. So not at this
[40:15]
report.
[40:16]
» Okay. Thank you.
[40:19]
Um, any other questions?
[40:23]
All in favor?
[40:25]
Pass. And next one is uh 7.2
[40:32]
uh through the chair. This motion is
[40:34]
that the budget to actuals report dated
[40:36]
July 31st, 2026 be received as
[40:38]
information
[40:41]
on the floor. Mayor, second by
[40:44]
Commissioner um Hart. Um, any
[40:47]
discussion? Seems as we're all there on
[40:49]
point. Uh, mayor,
[40:51]
» I'm just looking at uh I guess second
[40:54]
last page here. The harvester repair was
[40:56]
12,000. So that was over budget, but
[40:58]
every year we've always budgeted 15. Was
[41:00]
that a typo when we only budgeted 5,000
[41:03]
this year or was it just 5,000 budgeted?
[41:12]
» Um, Laura is there. Laura
[41:15]
» Uh through sorry which line was that Mr.
[41:18]
» So we're on the well basically the last
[41:21]
page it like the totals are on and it's
[41:24]
so it's under just above capital
[41:28]
vehicles and it's number 41 harvester
[41:31]
15,000 budgeted two years ago 12,000
[41:33]
spent last year we only budgeted five or
[41:35]
is that a typo because it's always been
[41:38]
15 and we're budgeting 15 for next year.
[41:41]
Yeah, through you. We were expecting
[41:43]
because um we had done the significant
[41:46]
repairs that we weren't expecting to
[41:48]
have to do uh that much work on it this
[41:51]
year. Um and so yes, that was a correct
[41:54]
uh we were
[41:55]
» We had only budgeted 5,000 this year
[41:57]
recognizing the age and and the work
[42:00]
that does need to be done and the
[42:01]
expectations of that vehicle. That's
[42:03]
where for 2027 we've put it back in at
[42:06]
15.
[42:07]
» Okay. But and if I may continue, three
[42:09]
lines below that, how do we make a
[42:11]
profit on the harvester trailer? We
[42:14]
budgeted 300 and we've got in brackets
[42:18]
1,200. How do we did we get money back?
[42:20]
Was it moved to a different account?
[42:22]
What happened there?
[42:24]
» Uh through you there was um a correction
[42:27]
that needed to be made. So it's I'm not
[42:30]
clear on why it's showing the negative.
[42:32]
It should have been a zero. Uh there was
[42:34]
a charge that went to that line item and
[42:36]
then was removed. Okay, I'll I'll
[42:39]
confirm with finance. It should be at
[42:40]
$0.
[42:42]
» Okay, that's fine. I just Yeah, we made
[42:44]
a profit on a repair. I couldn't figure
[42:46]
it out.
[42:52]
» Mayor.
[42:53]
» Yeah. Um down on the last page as well
[42:56]
under capital, there's capital weed
[42:57]
control. I just wanted to show find out
[43:00]
like I I think people asked because
[43:02]
we're not spraying anymore there that's
[43:04]
not in the budget, right? We've removed
[43:05]
that from the budget. They're not paying
[43:06]
for it and not getting it. I just want
[43:08]
to clarify those things.
[43:10]
» True, Mr. Chair. Yes, this capital
[43:12]
project, the name of it is a little bit
[43:15]
misleading. Um it's actually uh a
[43:19]
consortium of a bunch of various little
[43:22]
uh items including the um north uh beach
[43:28]
drainage uh work, the shed purchase. Um
[43:32]
there's a couple of other projects in
[43:34]
there. So, uh, the name is just a little
[43:36]
bit misleading, but it was all capital
[43:38]
works that was approved by the
[43:39]
commission for 2027. And the spraying,
[43:43]
uh, was in a different in the operating
[43:45]
budget, uh, line items, and that's not
[43:48]
part of the ongoing budget request.
[43:52]
» And just one more comment on that, I
[43:53]
guess, is because we didn't do a lot of
[43:55]
the skimming at the beginning of the
[43:56]
year, those things, do we have recognize
[43:58]
the savings or did we put that savings
[44:00]
into overtime to get caught up in the
[44:01]
weed harvesting?
[44:04]
um through you, Mr. Chair. The that is
[44:07]
correct that there's not I haven't run
[44:10]
the numbers to be able to see uh we did
[44:12]
do overtime. We were still out on the
[44:15]
boats and doing some work early in the
[44:17]
season uh to get things ready to install
[44:20]
the water movers and stuff like that.
[44:21]
So, there is still going to be some
[44:23]
labor costs associated with it. Um and
[44:26]
that's where we'll have to wait till
[44:28]
we're further in the season to see how
[44:30]
that all shakes out.
[44:33]
We're really not be able I know I was
[44:34]
looking for that too. We're not going to
[44:36]
be able to tell till what October like
[44:38]
what our costs once they all come in.
[44:39]
We'll be able to take a look at it
[44:42]
and see what there is. I I'm assuming
[44:44]
there'll be a savings. And just saying
[44:46]
all of that um watching what the what
[44:49]
your uh staff did out on the water. They
[44:51]
did a phenomenal job when they jumped on
[44:53]
it that quick and I could not believe
[44:55]
how fast they were taking those weeds
[44:57]
out and how fast they were moving. and
[44:59]
that piece of equipment, the big one
[45:01]
that went out there. This was the first
[45:03]
time. It really showed like last year we
[45:05]
were kind of breaking it in. It was kind
[45:07]
of new, but this year it was phenomenal
[45:09]
what it did. And to thank all your staff
[45:11]
from working the overtime. We did see
[45:13]
them there, you know, working and it
[45:15]
made a big difference. It caught up so
[45:17]
quickly. And I'm assuming your um
[45:19]
complaint calls must have dropped right
[45:21]
off because when I drove around my boat,
[45:23]
I looked, it was amazing what what a
[45:25]
good job they've done. And they're still
[45:26]
out there working way on. So yeah, thank
[45:29]
them from us. Great job done. Um, and I
[45:32]
jumped in on there because I should have
[45:34]
said that at the beginning, but yeah.
[45:36]
Um, any other questions here.
[45:39]
All in favor? That's what
[45:43]
Okay, we'll move to the front one.
[45:46]
7.3.
[45:48]
Um,
[45:50]
Rebecca. Oh, sorry. I see Laura put her
[45:53]
hand up.
[45:54]
» Uh, through you, Mr. Chair. I'll let uh
[45:56]
the clerk read the motion and I just
[45:58]
have a couple of updates before we get
[46:00]
into some discussion before we get too
[46:03]
far if after the motion is on the floor.
[46:05]
» Okay.
[46:08]
» Uh through the chair, the motion for
[46:10]
this item is as follows. that report LC
[46:13]
1326 regarding draft Lagoon City Parks
[46:16]
and Waterways Commission 2027 budget be
[46:18]
received and that the draft 2027
[46:20]
operating and capital budgets for the
[46:22]
Lagoon City Parks and Waterways
[46:23]
Commission attached to schedules A and B
[46:26]
to report LC 1326 be presented to
[46:28]
council for consideration
[46:31]
» Put on the floor
[46:34]
deputy mayor second by um commissioner
[46:37]
Lang
[46:39]
discussion
[46:41]
got myself organized here now for this.
[46:45]
» So, you Mr. Chair, um a couple of two
[46:49]
items. Um I did want to just give you a
[46:51]
couple of small updates uh that I had
[46:54]
after I had submitted the report. Um
[46:57]
first one is for staff wages and
[46:58]
expenses. Uh I believe it's showing
[47:02]
$250,000.
[47:04]
Um that can come down to $230,000. I was
[47:07]
waiting for some adjustments from our HR
[47:09]
department. Um, and then the other one
[47:12]
is beach security. Uh, and yes, we would
[47:15]
like to increase that from 10,000 up to
[47:17]
15,000.
[47:24]
So those two lines will be different
[47:26]
than what were submitted as
[47:28]
» Sorry, Laura, could you The numbers were
[47:32]
» Yeah. So staff wages would change to
[47:35]
$230,000,
[47:41]
» Right?
[47:42]
» And the line item for beach security
[47:44]
would be 15,000
[47:52]
» And then to have discussions. So, so
[47:54]
starting all this like and the one thing
[47:56]
I've noticed and I'm not sure whether or
[47:59]
not you've noticed it too, mayor, deputy
[48:00]
mayor, that normally when we get this
[48:03]
and when it's showing that it's a zero
[48:06]
increase like this is what they're
[48:07]
recommending here, the zero increase
[48:09]
when we look at that
[48:12]
like on this whole budget is that when
[48:15]
it's all finished in the bottom line
[48:16]
dollars and I'm trying to find that too,
[48:18]
is that recognizing a zero increase in
[48:22]
any capital cost now or anything new
[48:25]
that we add, it's going to increase the
[48:27]
actual um um um possible increase
[48:32]
like where where is all that? Like
[48:35]
normally you can see that here's where
[48:37]
we're at. Here's what it's actually um
[48:39]
here's our budget and if we want to add
[48:41]
something it means the the the actual
[48:45]
increase it goes up on that it and and I
[48:47]
don't see any of that there. I don't see
[48:49]
how I can bring it back and forth.
[48:51]
» So through you, Mr. Chair, this was uh
[48:54]
presented this way based on comments
[48:56]
from last year's presentation that the
[48:58]
operating and the capital be separated.
[49:00]
So that's what I have done this year. Um
[49:02]
in the body of the report, you'll note
[49:05]
that there is a proposed transfer to
[49:07]
reserves of approximately I think it was
[49:10]
300 and um let me just pull it up uh
[49:15]
$350,000.
[49:17]
That's an estimate because that's at
[49:19]
this point we are meeting our expenses
[49:22]
are being met by the revenues and at
[49:25]
this point there's a proposal of
[49:27]
$350,000 to go into the reserve. If
[49:31]
there's a change in the capital projects
[49:33]
or in the operating budget as part of
[49:35]
the discussion, that number will adjust
[49:38]
to bring it to that the the budget is
[49:41]
balanced. um it's difficult for us to
[49:43]
present that when we aren't clear on
[49:45]
what that's going to look like. So when
[49:47]
it goes to council, that's where that
[49:49]
will be presented as a a balanced
[49:52]
budget. At this point, $350,000 is going
[49:56]
to be transferred into the reserve
[49:58]
holding that levy at a 0% increase. So
[50:03]
if the commission so chooses, that
[50:07]
number could go down, that number could
[50:09]
go up. We could still increase the levy.
[50:11]
This is just the recommendation from
[50:13]
staff at this point.
[50:15]
» So that's really my answer right there
[50:17]
that that you're at budget plus 350,000
[50:20]
to go into reserves.
[50:21]
» That's how that's how I have to read
[50:23]
that then. Okay. So when I look at that
[50:26]
now and I guess my other question was I
[50:28]
was just kind of curious. Um do you know
[50:31]
what our reserves are right now?
[50:35]
» Um Miss Fischer is on and maybe she can
[50:38]
question for us.
[50:40]
» Yes. Um through you Cal I've got um so
[50:45]
if you have referred to the 2025 uh
[50:47]
financial statements the balance for
[50:49]
LCVW per the financial statements of
[50:50]
December 31st 2025 was about 892,000.
[50:55]
We budgeted a transfer to reserves in
[50:58]
2026 of 178,400.
[51:01]
So our projected ending balance in
[51:04]
December will be about 1,70,000
[51:07]
and that doesn't account for the
[51:08]
interest on reserve funds yet. We're not
[51:10]
certain what the um percentage might be
[51:12]
by the end of the year, but
[51:13]
approximately $20,000 increase there. Um
[51:16]
given Laura's report, we've currently
[51:18]
got a um transfer to reserves of about
[51:21]
350,000,
[51:22]
which might be reduced uh or increased
[51:26]
based on decisions today. Um but this is
[51:28]
looking at a projected December 2027
[51:31]
balance of 1.4 million.
[51:37]
» Okay, so that's our reserves now. So
[51:41]
um with our our income statement, what
[51:44]
is what is the normal reserves that we
[51:47]
should have? Like just so everybody
[51:49]
knows like um what should what because I
[51:52]
know there was a number that we were
[51:54]
given that we should always try to keep
[51:55]
our reserves at a certain amount. Um do
[51:58]
you know what that number is?
[52:00]
» I don't recall a number being given. My
[52:02]
best recommendation would do be to
[52:04]
maintain a reserve to meet future
[52:06]
capital expenditures or anything that
[52:08]
you might need to pull from their
[52:09]
reserves
[52:11]
um
[52:12]
for future years. So if you have a
[52:14]
future plan um and you're anticipating
[52:17]
additional expenses um a good reserve
[52:20]
would be to keep um to keep sufficient
[52:24]
funds for future costs.
[52:27]
Um, deputy mayor,
[52:29]
» I'm just wondering, would this benefit
[52:30]
us to create a 10-year capital plan like
[52:33]
the township does, like most
[52:34]
municipalities does specifically for the
[52:36]
commission? This would help us plan for
[52:38]
reserves and know exactly what we need
[52:40]
in there, anticipate new purchase of
[52:42]
equipment or things we want to look at
[52:43]
down the road.
[52:44]
» I thought
[52:47]
um we'll I guess with Laura first.
[52:51]
» Uh through you, Mr. Chair. Um, I do
[52:54]
agree that we should be updating the
[52:56]
10-year capital plan. Um, I'm not sure
[52:58]
if there had been one in the past, but
[53:00]
we would like to look at that. Uh, and
[53:02]
the hope is that we'd bring that to the
[53:04]
September meeting so that we have that
[53:06]
information.
[53:07]
» Exactly. Because I don't want people to
[53:08]
think that 1,100,000 is a fantastic
[53:11]
reserves when, you know, if a piece of
[53:13]
equipment goes, you're you're talking a
[53:15]
half a million dollars like for the
[53:16]
equipment that we have. So, you've got
[53:18]
to constantly be saving for. And that's
[53:20]
something that we didn't have when we
[53:22]
first became parks and waterways and we
[53:23]
needed this and I I just want to make
[53:25]
sure we stay with it and that's why I'm
[53:27]
bringing it up right now. All right.
[53:30]
Okay. So, um I guess sorry did Lord do
[53:33]
you need us to pass a motion to to
[53:35]
create that or are you good with that
[53:36]
direction?
[53:38]
» Uh through you, Mr. Chair. I'm good with
[53:41]
that direction. We'll bring that at the
[53:42]
September meeting. That was part of our
[53:44]
plan anyway. So,
[53:45]
» Perfect. Thank you.
[53:48]
Did you want to just go through page by
[53:50]
page and go through this? Do you? Um I I
[53:52]
can we go through it quickly like now
[53:54]
like go through the pages like
[53:57]
well I was just like doing the prep at
[53:59]
the beginning like I'm not sure if you
[54:01]
looked at I I know um commission Hart I
[54:03]
think the mayor
[54:04]
» Why don't we just do it page by page and
[54:06]
then you're covering it and we can ask
[54:07]
our questions is that's usually the
[54:09]
question.
[54:09]
» Okay. So I'm going to do like and I'm
[54:10]
starting uh I think it's uh page one I
[54:13]
got one to seven the way I did it but um
[54:15]
agenda 7.3
[54:17]
um so the very first page it's a
[54:20]
background and discussion anybody have
[54:21]
anything to talk about there
[54:25]
um
[54:27]
the expan the only thing I had the
[54:28]
expansion of the bubbler system um I I'm
[54:32]
not sure have we not finished the total
[54:33]
expansion and we are looking at the next
[54:36]
expansion or do you have two in line
[54:38]
right Yeah, like you have another
[54:40]
expansion
[54:42]
[clears throat]
[54:42]
» Through you, Mr. Chair. We deferred the
[54:44]
expansion for 2026 to do the compressor
[54:46]
repairs. So, the proposal is to have the
[54:51]
expansion that was originally proposed
[54:53]
for 2026 take place in 2027. Uh I do
[54:57]
believe we were still going to have
[54:59]
further discussions um before that went
[55:02]
for procurement to determine exactly
[55:04]
where the expansion was going to be. Uh
[55:07]
this is just an earmark for that project
[55:09]
to continue.
[55:11]
» And are we going to talk about that
[55:12]
today?
[55:14]
» No, not at this meeting.
[55:19]
» Any other questions on the first page?
[55:21]
Second page.
[55:27]
Um I guess my first question on it when
[55:29]
I'm going down is the concrete pad. Is
[55:32]
that to put the bin on in the new uh
[55:34]
takeoff area that we have down by the
[55:35]
mailboxes?
[55:39]
Um through you, Mr. Chair. I'm going to
[55:41]
actually ask Mr. Lenny to address that
[55:43]
question.
[55:47]
» Uh through you, Mr. Chair. Yes, that's
[55:48]
exactly um the proposal for the pad is
[55:51]
to um have a bin area and then a safe
[55:55]
secure area for offloading. um at this
[55:58]
time with the uh the weeds and the
[56:01]
gravel at this time it gets very um
[56:04]
slippery and I guess messy for lack of a
[56:07]
better term. So looking to uh clean that
[56:10]
area up and uh make it safer for the
[56:12]
operators and aesthetically um nicer uh
[56:15]
for the area.
[56:16]
» So the the actual concrete pad's not for
[56:19]
the actual bin. It's just for the area.
[56:21]
» No, it will encompass the it will for
[56:23]
the bin to sit on as well. Yeah,
[56:24]
» It will. Okay. It'll put the bin across
[56:26]
and I guess we'll get that price after.
[56:29]
Um, also, was there an issue with the
[56:31]
flooding there? Is that kind of why
[56:32]
we're doing that? From what I
[56:34]
understand, you guys were underwater
[56:35]
there for a while, right?
[56:37]
» Um, yes. I can't really speak exactly to
[56:39]
the flooding. Um, I have only been here
[56:41]
four weeks, but by the time that I have
[56:42]
spent down there, um, every time I've
[56:45]
been down there, there is, um, standing
[56:48]
water. Um, I wouldn't say it's flooded
[56:50]
out, but it's definitely standing water
[56:52]
um, and mud.
[56:55]
All right. Um,
[56:58]
do you want me to just keep going down?
[57:00]
Like I've got another question. Um,
[57:10]
so this I guess I'm talking about the
[57:12]
study. This is what Laura was talking
[57:14]
about. This is the study that we would
[57:16]
be looking at doing the condition of the
[57:18]
canals regarding depth, aquatic growth,
[57:20]
species, so on and so forth. We have
[57:22]
done studies like that before. or do we
[57:24]
have that information that we can
[57:26]
utilize
[57:27]
like I know there was a massive one done
[57:29]
by the college uh back I don't know
[57:32]
eight years ago seven years ago
[57:35]
» Through you Mr. chair. Yes, we do have
[57:37]
those th that information. Uh what we're
[57:40]
looking to do is make sure that it is up
[57:42]
to date. Uh like with most studies um
[57:46]
and including uh the discussion with the
[57:49]
Department of Fisheries and Oceans uh
[57:51]
regarding our operations this year,
[57:53]
having that information that's up to
[57:55]
date um is really important for us to be
[57:58]
able to show uh with evidence and data
[58:03]
uh what we're looking at and what we're
[58:05]
proposing to do. and what the impact is
[58:07]
going to be. Uh so there is information
[58:09]
available to us. it doesn't answer all
[58:11]
of our questions that we're looking at
[58:13]
and that's where this study would be
[58:15]
more of a comprehensive again giving us
[58:18]
targeting um monitoring programs so that
[58:23]
we can benchmark um I know even thinking
[58:26]
about discussions that uh I've had um at
[58:31]
various times about uh depth of the
[58:33]
lagoons and dredging operations and uh
[58:36]
items like that. That's what I I want to
[58:39]
take that all into consideration into
[58:41]
one one study. Um and also this is where
[58:46]
we would also consider
[58:48]
uh what technologies are available for
[58:51]
pumps um for water movers um making sure
[58:55]
that they're in the best locations and
[58:57]
doing um what we need to do. Uh I think
[59:00]
it's also important to really
[59:02]
characterize with very specific
[59:05]
information. for instance, you know, um
[59:08]
what what is the goal of um the the
[59:12]
goals that we're trying to achieve? So,
[59:14]
for instance, with water movers, it's to
[59:16]
manage and uh the duckweed growth. Okay.
[59:19]
Well, what does it take in order for us
[59:21]
to do that? What does that look like? So
[59:24]
that in future years, we have that
[59:27]
identifiable target. We can report back
[59:29]
to the commission and say we're meeting
[59:31]
those targets or we're not meeting those
[59:33]
targets and here's why. um and also
[59:36]
putting in a monitoring program so that
[59:38]
we're clear on
[59:40]
um what what we're actually achieving.
[59:44]
So it's not just anecdotal. It's not
[59:46]
just you know um yourself as the uh
[59:49]
chair walking down the road and giving
[59:52]
anecdotal evidence. We have a way to
[59:54]
measure um and provide that evidence. So
[59:57]
this study would be confirming all of
[59:59]
those pieces. I think the past studies
[1:00:01]
have given components of that but have
[1:00:03]
not been that full breadth and it's
[1:00:05]
important for us to make sure that this
[1:00:06]
is it stays up to date. So we'd be
[1:00:09]
looking at targeting an update to this
[1:00:12]
moving forward probably every 5 years or
[1:00:14]
so.
[1:00:15]
» So so this study would be strictly
[1:00:17]
Lagoon City like the the canals and so
[1:00:20]
on so forth water quality things like
[1:00:23]
that or like that's what it's going to
[1:00:25]
include or
[1:00:27]
» Yeah through the chair. Yes, that's
[1:00:28]
correct. it would only be targeting
[1:00:30]
Lagoon City, these canals and the
[1:00:32]
lagoons um and looking at all of the
[1:00:35]
pieces that go into the maintenance of
[1:00:37]
those canals.
[1:00:38]
» And how much input would the parks and
[1:00:40]
waterways have with all this? Like would
[1:00:42]
we be you would keep us informed at all
[1:00:45]
times on this or uh I guess so because
[1:00:47]
we have to pay for it, right?
[1:00:49]
» Uh through you, Mr. Chair. Yes. And I do
[1:00:52]
expect to have engagement as part of it.
[1:00:54]
That's where um we will be needing to
[1:00:57]
set what those goals are. What are those
[1:00:59]
performance targets? What are we looking
[1:01:01]
for um and then there'll be uh
[1:01:04]
recommendations that come back uh out of
[1:01:06]
that. So there will be um ongoing
[1:01:09]
discussions as well as probably some
[1:01:12]
community engagement as as what I see as
[1:01:14]
part of this study.
[1:01:16]
» And when will we expect to see this?
[1:01:18]
» So um I'm expect so this is an ask for
[1:01:22]
2027.
[1:01:24]
uh as soon as budget is approved for
[1:01:26]
2027, we can start that. I am expecting
[1:01:29]
that it will take at least three or four
[1:01:31]
seasons dep because of the data that
[1:01:34]
we're asking for them to be collecting.
[1:01:36]
Um and so that would be where it would
[1:01:39]
likely take the entirety of 2027 to do
[1:01:42]
the work um and then come back in 2028
[1:01:45]
with uh recommendations.
[1:01:47]
» Excellent. Okay.
[1:01:49]
Um Commissioner Hart.
[1:01:51]
» Yeah. U thank thanks Laura. I think this
[1:01:53]
uh study is important. I I just missed
[1:01:55]
the first part. Who's actually going to
[1:01:56]
be conducting the study? Uh how is that
[1:02:00]
going to work out?
[1:02:01]
» Uh through you, Mr. Chair, we would need
[1:02:03]
to go through our procurement channels
[1:02:05]
for that. So, it's not um we haven't
[1:02:08]
decided any of that yet. We would go out
[1:02:11]
to market and we would also be looking
[1:02:13]
at leveraging some of those educational
[1:02:15]
institutions potentially uh for
[1:02:18]
partnerships for some of the data
[1:02:19]
gathering as well. Um, but I do
[1:02:22]
anticipate that there will be paid
[1:02:23]
consultants as part of this as well.
[1:02:26]
» Excellent. Thank you. Anybody else have
[1:02:28]
anything on this page? Uh, mayor.
[1:02:30]
» Well, I don't know if it's on this page,
[1:02:31]
but we were talking about the movers
[1:02:32]
here. So, if we are looking at do we
[1:02:35]
need to increase the budget to look at
[1:02:37]
new movers, quieter movers. Where do you
[1:02:39]
want to see that? because we did have
[1:02:41]
that discussion earlier that rather than
[1:02:43]
just keep throwing money at these ones,
[1:02:45]
we start researching for something
[1:02:47]
quieter.
[1:02:49]
» Um through you, Mr. Chair, I would
[1:02:52]
suggest that yes, we do increase the
[1:02:54]
budget specifically for those,
[1:02:56]
especially if the commission is looking
[1:02:59]
to potentially purchase
[1:03:01]
» Um new pumps in 2027 as opposed to
[1:03:05]
waiting for 2028.
[1:03:07]
Um my recommendation would be to
[1:03:10]
increase the study budget by $25,000 or
[1:03:13]
sorry by $10,000.
[1:03:15]
Um and potentially add another line item
[1:03:18]
for water mover pumps
[1:03:21]
in an amount that the commissions these
[1:03:24]
appropriate um for the size of these
[1:03:28]
pumps without looking what technology is
[1:03:31]
out there on the market. I would say
[1:03:34]
somewhere between
[1:03:36]
um 30 to 50,000 per pump would be uh on
[1:03:41]
par what I would expect to pay.
[1:03:43]
» And I would expect as part of that would
[1:03:45]
be loc because I don't know if there was
[1:03:46]
ever a study done on the location where
[1:03:48]
they sit. I I think probably 20 30 years
[1:03:52]
ago they said, "Well, there's duckweed
[1:03:53]
here, put a pump there, and there's
[1:03:54]
duckweed there. Put a pump there."
[1:03:56]
» I asked that question, Kathy [laughter]
[1:03:57]
Wayman. She said there was
[1:03:58]
» Well, there was a exactly where it was
[1:04:00]
supposed to go. I think it came from the
[1:04:01]
engineers. Okay. I asked her, "Why don't
[1:04:03]
we just move it here? Do that." She
[1:04:04]
said, "You can't do that."
[1:04:05]
» All right. Okay.
[1:04:06]
» That's what she told me. But I I wonder
[1:04:07]
your pumps. So, 30,000 to 50,000. These
[1:04:10]
uh other pumps that don't work so well
[1:04:12]
were close to 50,000. Were they not
[1:04:15]
» Through you, Mr. Chair? I'm not sure
[1:04:18]
what those prices were. Um what the cost
[1:04:21]
of those previous pumps were. I just
[1:04:23]
know the market for this type of pump is
[1:04:25]
isn't around that area for that size.
[1:04:28]
Yeah.
[1:04:28]
» Yeah. I would like to see it a bit
[1:04:29]
higher than that. Yeah. But yeah, it's
[1:04:31]
cuz I'm almost puzzled. It's 45,000 when
[1:04:34]
I think about it. I
[1:04:34]
» I think you're right. I would I would
[1:04:36]
air on the side of caution say 120 for
[1:04:38]
the two pumps and then we can always I
[1:04:40]
mean it's a savings at the end of the
[1:04:41]
day. It just goes
[1:04:42]
» Into reserves, right?
[1:04:46]
» So $120,000
[1:04:48]
for water mover pump. Okay.
[1:04:50]
» Yeah.
[1:04:53]
» Well, I want to sort of stop spending
[1:04:55]
money on this. I think it's a lost
[1:04:57]
cause. I think it's time that we cut our
[1:04:58]
col our and see if anybody's in the
[1:05:01]
market for some uh hardly used used
[1:05:03]
pumps, right?
[1:05:06]
Um does anybody else got anything on
[1:05:08]
this page two? Because that's where I
[1:05:10]
was at there. No, we're all done there.
[1:05:12]
Um I got nothing on page three. Now I'm
[1:05:16]
right into this um I guess the beginning
[1:05:18]
of the budget
[1:05:21]
starting with revenues.
[1:05:27]
Um,
[1:05:31]
that's the last one thing. Anybody would
[1:05:33]
like to start, we'll do this page. You
[1:05:34]
can start from the top and come down.
[1:05:36]
Um,
[1:05:38]
I guess my question is there's something
[1:05:40]
here. Why why is this lower? Just trying
[1:05:43]
to figure this number out. Hold on a
[1:05:45]
second.
[1:05:49]
Here
[1:05:55]
it is. Here the actual.
[1:06:01]
Okay.
[1:06:04]
Sorry, mayor. If you want to go. I just
[1:06:06]
have my head down.
[1:06:07]
» I'm not in the revenues. I'm on the
[1:06:08]
expenses. I just
[1:06:09]
» You're jumping ahead on us here.
[1:06:10]
» Are you want the revenue? You want to
[1:06:12]
stay there? I'm just on the same page.
[1:06:14]
Just uh
[1:06:15]
» Yeah, just Yeah. On the page.
[1:06:16]
» Yeah. on uh so legal expenses uh you
[1:06:19]
know 20,000 in 2024 we used 19 uh 20,000
[1:06:24]
last year of course we went over budget
[1:06:26]
uh last year we budgeted 20,000 we've
[1:06:28]
used close to eight so why are we only
[1:06:30]
budgeting 2,000 for next year for legals
[1:06:34]
that seems right
[1:06:37]
» Through you uh Mr. Chair, the legal
[1:06:40]
budget has been proposed by our new the
[1:06:42]
township's new in-house legal
[1:06:44]
department. He's uh reconfiguring how
[1:06:48]
the legal will be um divvied up between
[1:06:51]
the different areas. And at this point,
[1:06:54]
uh the expectation having cleared some
[1:06:57]
of the past legal matters that $2,000 is
[1:07:00]
appropriate.
[1:07:04]
I I guess my concern I don't want to be
[1:07:06]
the devil's advocate but we know we're
[1:07:08]
doing the study and part of it and we're
[1:07:10]
going to have an open house I think in
[1:07:11]
Lun City later this month and it'll go
[1:07:14]
off to a consultant who's going to bring
[1:07:15]
back recommendations. We don't have no
[1:07:17]
idea what those recommendations are
[1:07:18]
going to be. We have no idea what
[1:07:20]
council's going to do with those
[1:07:21]
recommendations like council we we've
[1:07:23]
done efficiency studies in the past
[1:07:25]
where yes we've put some of the things
[1:07:27]
in place but not others.
[1:07:30]
We don't know if they're legal though.
[1:07:32]
» Well, no. But would parks and waterways
[1:07:34]
think they might want to get a legal
[1:07:36]
opinion on any changes that are
[1:07:38]
proposed?
[1:07:39]
» Well, just so you know, I actually am
[1:07:40]
proposing that uh through [laughter]
[1:07:42]
parks and waterways people go speak to
[1:07:44]
their own lawyer.
[1:07:44]
» Oh, yeah.
[1:07:45]
» So, yeah, you are. That'll be later on.
[1:07:48]
» So, that's why I'm wondering just in
[1:07:50]
light that there is an efficiency study
[1:07:52]
being done. Changes may be coming
[1:07:55]
whether or not
[1:07:56]
» We've always put 20,000.
[1:07:58]
I would not want to see it lowered at
[1:08:00]
this time. Again, I won't be here, but
[1:08:02]
you may want to have a legal opinion on
[1:08:04]
suggested changes that council is
[1:08:06]
deciding to make that that
[1:08:08]
» I agree with you. Actually, I'd marked
[1:08:10]
it.
[1:08:12]
» So, what do you want to bring it up to?
[1:08:13]
Back to what it was
[1:08:14]
» Back to the 20, I think.
[1:08:21]
» Oh, yeah.
[1:08:24]
» Okay. So, we're going to So, are you is
[1:08:27]
someone going to track that for us then?
[1:08:28]
Okay, Rebecca. Perfect. So, we're going
[1:08:30]
to increase that to 20 then. Um, I guess
[1:08:34]
I guess my question too was going back
[1:08:36]
to staff wages and expenses.
[1:08:38]
The actual in 2026 is 130,000 and now in
[1:08:43]
2027 it's jumped to 250. That's a fair
[1:08:47]
jump. I was just c Oh, sorry. I got
[1:08:48]
Laura's hand up. You're stepping ahead
[1:08:50]
of you time.
[1:08:52]
The 2026 actuals are not on this
[1:08:55]
schedule. That's the 2025 actual. Um,
[1:08:59]
and so 2026 budget was 20 225,500
[1:09:05]
and we're going to 230,000. So it's a
[1:09:08]
small increase. Um, and the the actuals
[1:09:12]
for 2026 will be on the most recent
[1:09:14]
report. You'd have to add up all the
[1:09:16]
wages and and staff, but I did do that
[1:09:19]
as preparation. And we are on R for the
[1:09:22]
spend of 225,400.
[1:09:27]
» Okay. I thought 20256.
[1:09:29]
» It It says 2027 pro proposed is 250. Is
[1:09:32]
that what you're talking about?
[1:09:34]
» Oh, she did. Okay. I didn't miss that.
[1:09:36]
» She corrected it back to 230 at the
[1:09:38]
start.
[1:09:38]
» Okay. Gotcha.
[1:09:41]
» Okay. Got that. All right. That was
[1:09:43]
good. That's good. Um the actual levy
[1:09:49]
That's where I was on.
[1:09:53]
I just was curious why it bounces
[1:09:55]
around. We should be almost dead on that
[1:09:56]
level, right?
[1:09:58]
Okay. Doesn't matter then. Anything else
[1:10:00]
on that page for anybody?
[1:10:03]
No. Okay. Let's go to the next page. If
[1:10:05]
you see we miss anything, Laura or um
[1:10:08]
the I guess the treasure or not the
[1:10:10]
treasury but the other lady there. Um
[1:10:13]
next [sighs] one.
[1:10:20]
No, I'm good with that. With that
[1:10:23]
pontoon boat, that's
[1:10:28]
um $3,500 for the pontoon. Laura, um
[1:10:31]
that is there something wrong with it or
[1:10:33]
or it's just maintenance? 3500
[1:10:36]
» Uh through Mr. Chair. Yes, that's just
[1:10:38]
maintenance. Um,
[1:10:42]
and I just realized that uh number 41,
[1:10:45]
the harvester, uh, that should be at
[1:10:47]
15,000
[1:10:52]
to match the other harvester.
[1:10:55]
» 41, right?
[1:10:56]
» Yes. Correct.
[1:10:57]
» Okay.
[1:11:01]
Again, you're getting that, Rebecca,
[1:11:02]
right?
[1:11:05]
Anything
[1:11:08]
else on that page?
[1:11:12]
No. There.
[1:11:21]
» I'm at account subscription building.
[1:11:27]
» Before we go on to account,
[1:11:29]
» You want to go back to
[1:11:30]
» Well, I just didn't see it. I thought we
[1:11:32]
continue on, but the one expense I'm not
[1:11:33]
seeing Laura is drudging. So, are we
[1:11:35]
done judging now where there's no more
[1:11:37]
planned or to do in the future?
[1:11:40]
» Uh, through you, Mr. Chair, that is
[1:11:42]
correct. At this point, there's no
[1:11:43]
planned judging. Um, we had completed
[1:11:47]
the outstanding judging that had been
[1:11:50]
proposed from 2023, I believe. Um, and
[1:11:53]
again, I'm hoping that that study that
[1:11:55]
we'd conduct next year would inform what
[1:11:57]
future dredging would be required.
[1:11:59]
» Thank you. So the dredging that um Bob
[1:12:02]
had done many many well I guess you said
[1:12:05]
2023 right um are we still using that or
[1:12:09]
is that now gone to the wayside or is it
[1:12:11]
is because he spent a lot of time
[1:12:13]
measuring he we he measured everything
[1:12:14]
out and that's what we used for the last
[1:12:16]
number of years
[1:12:18]
» Uh through you Mr. chair. No, and that's
[1:12:21]
what my understanding is. So, finally,
[1:12:23]
uh, the last of that dredging was
[1:12:25]
completed in 2025.
[1:12:27]
And so, I believe we had completed all
[1:12:29]
of the required dredging. That
[1:12:32]
information would be provided to the um,
[1:12:37]
whoever the consultant would be for the
[1:12:39]
study to make sure that it's taken into
[1:12:41]
consideration going forward as well as
[1:12:43]
providing us with that plan for future
[1:12:46]
judging.
[1:12:49]
Did you have any more questions back
[1:12:51]
there? No.
[1:12:54]
» Oh, no. No problem. Any anybody else has
[1:12:57]
have any here?
[1:13:00]
Okay. So, I'm out on the last page now.
[1:13:02]
Oh, no. Second page before I get
[1:13:06]
um
[1:13:08]
so does anybody have any question on
[1:13:09]
accounts description, building
[1:13:11]
maintenance?
[1:13:13]
Pretty straightforward there. Um,
[1:13:18]
» No. Okay, we'll go to capital
[1:13:22]
» Before we go to capital. So, I'm showing
[1:13:24]
we've changed the budget by 13,000. Is
[1:13:27]
that correct? Not counting the water
[1:13:28]
movers. I assume they go under capital
[1:13:30]
because I believe you gave us a
[1:13:32]
correction at the start of 15,000
[1:13:35]
and then you just added 10 to the one
[1:13:37]
boat and we added 18 for the legal. So,
[1:13:39]
is that where we are? We've increased
[1:13:41]
the budget by 13,000 I think. Does that
[1:13:44]
change
[1:13:46]
uh our levy or anything that 13,000 or
[1:13:49]
is that just going to come out of
[1:13:50]
transfers
[1:13:51]
» Through you? I believe that would come
[1:13:53]
out of the transfer to reserve. That's
[1:13:55]
where we would balance from. We're still
[1:13:57]
not in a significant expense that would
[1:14:00]
impact that we have a uh a balance going
[1:14:04]
to the reserve for 2027.
[1:14:06]
» We've changed at 13K that I could tell.
[1:14:08]
[laughter]
[1:14:09]
» Yeah, Rebecca's tracking that. Carly,
[1:14:11]
did you have something you wanted to
[1:14:12]
say?
[1:14:13]
through you, Mr. Chair. There was
[1:14:15]
discussion about $120,000 for water
[1:14:18]
mover pumps. I didn't in my sheet. I
[1:14:21]
wasn't sure if that was already there or
[1:14:22]
if there was a change, just that there
[1:14:24]
was discussion and I'm uncertain how
[1:14:25]
that impacted the budget.
[1:14:29]
» So, that would be a new ask, uh, Ms.
[1:14:32]
Fischer. And so that would impact the
[1:14:34]
amount going to the reserve, but we
[1:14:36]
would still have at this point it's
[1:14:38]
still a surplus that we would be
[1:14:40]
transferring into the reserve, just a
[1:14:42]
smaller amount. Yeah. So right now I'm
[1:14:45]
calculating a approximately $133,000
[1:14:49]
reduction to the transfer to reserves.
[1:14:52]
So the existing 350
[1:14:54]
less 133 approximate. So then the
[1:14:57]
existing transfer to reserves is
[1:14:58]
approximately 217,000.
[1:15:01]
How how much we take off the 350 130. Is
[1:15:04]
that what you said?
[1:15:07]
» I don't I I can try to review the
[1:15:10]
minutes um after the meeting's done, but
[1:15:13]
based on what I've heard, it sounds like
[1:15:15]
$133,000
[1:15:17]
reduction in the transfer to reserves.
[1:15:21]
» We just did a $13,000 change here plus
[1:15:24]
120 for the water movers would be 133.
[1:15:27]
» And those are all capital, right?
[1:15:28]
» No, only the water movers. Would they
[1:15:30]
not, Carly? [clears throat] Would the
[1:15:32]
water movers not be under capital or
[1:15:34]
what line were we getting? Yes.
[1:15:37]
» Uh, I I believe they would be under
[1:15:38]
capital. Yes. Um, however, that would
[1:15:42]
still impact the net levy requirement
[1:15:45]
from LCPW. It would have an impact on
[1:15:47]
LCPW's reserves.
[1:15:50]
» Yeah.
[1:15:50]
» Okay. So, did that come off our the
[1:15:53]
transfer reserves 13? Did it go into
[1:15:55]
capital?
[1:15:57]
» Yeah. Where are we putting water?
[1:16:04]
Sorry, turn your mic on. I can't hear
[1:16:06]
the
[1:16:06]
» Oh, sorry. I thought it was on. I shut
[1:16:07]
it off. Where did we put the 120 for the
[1:16:10]
water movers? Is that going to go in
[1:16:11]
capital now as a new line?
[1:16:13]
» Correct. Yes, that's what I've proposed.
[1:16:15]
It'll be a new capital project.
[1:16:17]
» Right.
[1:16:26]
» Okay. Okay, so now we're at the capital.
[1:16:32]
So just just put my head down here. Look
[1:16:36]
at this one.
[1:16:45]
So
[1:16:52]
» Okay. So, um, deputy mayor,
[1:16:54]
» What all has to be done with the kiosk?
[1:16:56]
I I understand there's a quite a bit of
[1:16:57]
upgrades that had to be done to that
[1:16:58]
Laura or through the chair to Laura. Um
[1:17:01]
is 165 going to be anywhere near what we
[1:17:03]
need for that?
[1:17:06]
» Um through you, Mr. Chair. That was the
[1:17:10]
proposal that we've put in. Uh we've
[1:17:12]
earmarked for it. I believe there's some
[1:17:15]
electrical work and some door work as
[1:17:17]
well as some structural repairs. Uh and
[1:17:19]
we do think that that's going to be
[1:17:21]
adequate. We also suspect that there is
[1:17:24]
also an underground water line that
[1:17:27]
needs to be repaired um that's providing
[1:17:30]
potable water to the kiosk. Um and that
[1:17:33]
that will be a significant portion of
[1:17:35]
the 16,000 proposed. Um
[1:17:39]
we're we're hopeful that that is
[1:17:42]
adequate for the repairs that are
[1:17:44]
necessary. Uh we don't have any firm
[1:17:47]
quotes though on that.
[1:17:49]
That's why we couldn't get Georgia
[1:17:50]
College carpentry or something to do
[1:17:52]
bring some students and do some project
[1:17:54]
on it.
[1:17:56]
It's pretty tough to do that though in
[1:17:58]
public.
[1:18:00]
Um I I as far as I'm concerned the kiosk
[1:18:02]
we should just maintain it for now
[1:18:04]
because we're not really using it. But I
[1:18:06]
think in the future it'll be used. It's
[1:18:07]
not something we want to fall down. We
[1:18:10]
all agree with that.
[1:18:12]
Um when I the clean flow system here,
[1:18:15]
this $55,000,
[1:18:17]
right? That's what we had budgeted um I
[1:18:20]
guess 2026. You just want to increase it
[1:18:22]
by another 10,000 and up to 65,000.
[1:18:26]
» We we can if that's what the commission
[1:18:29]
» No, it says here 65,000 your proposed
[1:18:31]
budget. So
[1:18:33]
» I I I guess what I'm asking is
[1:18:36]
what what are actual what do we plan on
[1:18:38]
doing like for $65,000? Like what's left
[1:18:41]
that we have to do?
[1:18:43]
I'd have to pull the maps and I don't
[1:18:45]
have that um with me at this moment. I
[1:18:48]
increased it to $65,000 just to account
[1:18:51]
for inflation over the time period from
[1:18:53]
the original quotes from 2020
[1:18:56]
» Uh 4 or 2025 budget preparation in for
[1:19:00]
2026. So that was why I added 10,000 was
[1:19:03]
just to account for inflation.
[1:19:06]
» Um Carly, did you want to say something
[1:19:08]
to that?
[1:19:10]
No, when I see you appear there,
[1:19:11]
normally you want to say something
[1:19:13]
[laughter]
[1:19:13]
» Through you, Mr. Chair. No, I I just
[1:19:15]
turned my video back on. I didn't have
[1:19:17]
any additional comments at this time. Um
[1:19:19]
I I guess really what we need to do is
[1:19:21]
um for the 65,000 we probably could do
[1:19:23]
the extension from the um two pumps that
[1:19:26]
are on Turtle right now because that was
[1:19:28]
our next step because um I was trying to
[1:19:30]
figure out why there was no um uh clean
[1:19:33]
flow, no bubblers um across from the um
[1:19:37]
the the sailboats and I think that's
[1:19:40]
what we've been waiting for. And that
[1:19:42]
expansion all that includes are pipes
[1:19:44]
and diffusers. There's no pump houses or
[1:19:46]
anything we have to get. we can go on
[1:19:48]
the existing um pumps that are there and
[1:19:50]
that would give us enough to connect to
[1:19:52]
there and then connect back up towards
[1:19:54]
the inn and we would have that and the
[1:19:56]
only thing that would be left would be
[1:19:57]
Gondola Lagoon from Popppler down to uh
[1:20:01]
um the end um to South Island Trail to
[1:20:04]
the bridge. That would be it. And then
[1:20:05]
the marina those only spots we have left
[1:20:08]
to really look at and I think you
[1:20:10]
probably only need one more house maybe
[1:20:12]
if we're a little bit of luck or maybe
[1:20:13]
another house along Gondola. So that's
[1:20:17]
really what we're looking at right now.
[1:20:18]
But are we going to talk about that at a
[1:20:20]
later date then or uh more what we're
[1:20:23]
going to do next
[1:20:25]
» Through you, Mr. Chair? Yes. That's the
[1:20:27]
idea is that we'll put in $65,000 that
[1:20:30]
will allow for us to do some of the
[1:20:31]
expansion work and we'll bring forward
[1:20:34]
what the plan will be um at a later date
[1:20:38]
for it depicting exactly what we're
[1:20:40]
proposing for each year.
[1:20:42]
» And I'm going to go backwards now. Um
[1:20:44]
what about the treatments that we've
[1:20:46]
done with the um the the bubbler system,
[1:20:48]
the clean flow system? You're examining
[1:20:51]
all of that. Do we have money built in
[1:20:52]
for that this year
[1:20:54]
» If we decide to re renew our treatments
[1:20:58]
» Uh through you, Mr. Chair? Yes. That was
[1:21:00]
still incorporated as part of the
[1:21:01]
budget.
[1:21:02]
» Do you know when you're going to have um
[1:21:04]
that finished that we know if not we're
[1:21:06]
going to continue treatments?
[1:21:07]
» Uh it's still under review at this time.
[1:21:09]
» It's under review. Okay. So you don't
[1:21:12]
have it's gone to the government. So,
[1:21:14]
uh, to the ministry and so on and so
[1:21:15]
forth.
[1:21:16]
» We're we're reviewing it internally
[1:21:18]
first and so and then we'll reach out to
[1:21:20]
any partners that we need to. So,
[1:21:22]
» Okay. But again, did I don't know if I
[1:21:23]
heard do we have money in for the
[1:21:25]
treatments or
[1:21:26]
» We didn't adjust the budget to to not
[1:21:28]
treat for it? So, that should still be
[1:21:30]
in the budget. Yes.
[1:21:31]
» Okay. I just wanted to confirm that. Um,
[1:21:37]
temple insurancees.
[1:21:42]
Um, do we have a rough idea what the
[1:21:45]
labor charge is like the town like for
[1:21:47]
what we're being built for everything
[1:21:49]
here on this? Is there rough numbers on
[1:21:51]
that yet or do I see them? Because I
[1:21:52]
know it started off at around 220 and I
[1:21:55]
know last year um Gail brought it up by
[1:21:58]
another 50,000 60,000. So I'm just
[1:22:01]
curious where that number is at now.
[1:22:05]
It's our labor charges. Yeah.
[1:22:07]
» Our staff wages and expenses are
[1:22:08]
proposed to be 230,000 for 2027.
[1:22:12]
» It's 230 then.
[1:22:14]
» Yes.
[1:22:14]
» Okay. Because I know it was that and I
[1:22:17]
support Gail said it was be there was
[1:22:19]
going to be an increase of almost
[1:22:21]
50,000.
[1:22:22]
» So 2026's budget. So 2025's budget for
[1:22:26]
staff wages was 173,000.
[1:22:29]
2026 we changed it to 225,400
[1:22:34]
and for 2027 it's 230,000
[1:22:37]
» 230 okay is that that does that include
[1:22:42]
that does include the um the harvesting
[1:22:44]
people does it or does that include the
[1:22:46]
harvesting
[1:22:46]
» That's all staff wages
[1:22:48]
» Everything yes
[1:22:50]
» Thank you
[1:22:56]
» Okay I'm actually pretty good with all
[1:22:57]
this So, I'm not seeing an increase yet
[1:23:01]
for any I don't see an increase.
[1:23:04]
» No, I'm I'm just wondering at some point
[1:23:06]
in time if if there if would help Laura,
[1:23:09]
should the commission kind of give him
[1:23:11]
some time to get some capital project
[1:23:13]
ideas for you for building this 10ear
[1:23:15]
capital? What is should we have a
[1:23:16]
meeting specific to that? Right? Because
[1:23:18]
if we're going to build a 10-year
[1:23:19]
planet, then we should be looking at do
[1:23:21]
we want to add a beach cleaner to it at
[1:23:23]
some point? Start acrewing money so we
[1:23:24]
can save up for it. I'm not sure. But
[1:23:26]
what what do the people want to see,
[1:23:28]
right?
[1:23:29]
» Well, we roughly did one. I remember
[1:23:31]
doing it a few years ago. We roughly
[1:23:32]
did, but there's something out there
[1:23:34]
because I remember sitting doing it
[1:23:35]
because we had never had it and we
[1:23:37]
needed I can remember doing it. So, I I
[1:23:39]
don't know where it is.
[1:23:40]
» But even for an updated NoCal, we should
[1:23:42]
have anything new that's coming about.
[1:23:43]
» But what you're talking about is things
[1:23:44]
we already talked about, right? That
[1:23:45]
same like we've been talking about that
[1:23:47]
since my first term we looked at.
[1:23:50]
» I'm just not sure if Laura has something
[1:23:52]
specific that's actually been put
[1:23:53]
together. I'm not sure. I'm assuming
[1:23:55]
she's going to wait for that meeting
[1:23:56]
that we're going to talk about right
[1:23:57]
now.
[1:23:58]
» Go ahead, Laura.
[1:23:59]
» Yeah, through you, Mr. Chair. The
[1:24:01]
expectation will be that in September,
[1:24:03]
we'll bring it forward and absolutely at
[1:24:05]
that point we can have the discussion
[1:24:07]
with the commission and determine what
[1:24:09]
other items need to be added in. We'll
[1:24:12]
put in what we've already understood. Um
[1:24:15]
and again with us being still uh with a
[1:24:18]
fairly short history of um what's been
[1:24:21]
done in the past and what we need to do
[1:24:24]
uh we may be missing some things. But
[1:24:26]
that's where that we're hoping um at
[1:24:28]
that meeting in September then we can
[1:24:30]
bring that forward and and have those
[1:24:31]
filled in uh to then again go forward
[1:24:34]
and with a full 10-year plan for
[1:24:36]
council's consideration.
[1:24:41]
» Any other questions on this?
[1:24:46]
So, Rebecca, have you got all those
[1:24:47]
numbers that we've talked about because
[1:24:49]
that's what's going to come up next, I
[1:24:50]
guess. Right.
[1:24:51]
» Through the chair. Yes. So, I do have an
[1:24:52]
amendment prepared for the motion uh
[1:24:54]
that I we can put on the screen and then
[1:24:55]
we can go through and if the commission
[1:24:57]
has any changes uh or if there's
[1:25:00]
anything that you would like um that you
[1:25:02]
think I've
[1:25:04]
written down uh differently than what
[1:25:06]
you had thought or you had said. So, let
[1:25:08]
me know. We can make any adjustments to
[1:25:10]
it. But this is what we currently have
[1:25:12]
drafted.
[1:25:13]
That the motion before the commission be
[1:25:15]
amended to make the following changes to
[1:25:16]
schedules A and B. Schedule A,
[1:25:19]
housekeeping adjustments. Staff wages
[1:25:21]
and expenses decreased to $230,000.
[1:25:24]
Beach security increased to $15,000.
[1:25:28]
Schedule B, increase canal/ Lagoon City
[1:25:30]
Condition and maintenance study by
[1:25:32]
$10,000 to include analysis of
[1:25:33]
technology for water mover pumps.
[1:25:36]
Schedule Accreased legal fees $20,000.
[1:25:40]
Schedule A number 41 LCBW harvester
[1:25:43]
increase to $15,000
[1:25:45]
and schedule B addition of $120,000 for
[1:25:48]
new capital project for replacement of
[1:25:50]
water mover pumps.
[1:25:53]
» What about what we're putting to
[1:25:54]
reserves? Do we do we need that there?
[1:25:58]
No.
[1:25:59]
» Uh through the chair, my understanding
[1:26:00]
and if general manager PI or Miss
[1:26:02]
Fischer have anything to add, please
[1:26:04]
feel free. But my understanding is that
[1:26:05]
that would be determined based on the
[1:26:07]
budget. So it's not doesn't have to be a
[1:26:09]
direction of the commission because it
[1:26:11]
would be resulting from your overall
[1:26:12]
direction for the budget.
[1:26:14]
» But if there's any substantial change,
[1:26:16]
we'll be fully aware of it then. Okay.
[1:26:17]
Yeah, we need to know that for sure.
[1:26:19]
Yeah. All right. Perfect.
[1:26:23]
Any discussion? So
[1:26:25]
» Now I guess
[1:26:27]
who I heard somebody talk.
[1:26:29]
» Uh yes, sorry through you, Mr. Chair. Um
[1:26:32]
I apologize, Miss Clerk. Uh was the
[1:26:34]
adjustment for the legal expenses on
[1:26:36]
there as well?
[1:26:38]
the 18,000
[1:26:40]
» Through the chair. I do have Yes.
[1:26:42]
increase the legal fees line to $20,000
[1:26:44]
total. So the $2,000 plus the 18. Yes.
[1:26:48]
» So I guess my question now and this is
[1:26:50]
probably to you guys like if there's an
[1:26:53]
election coming and you can't do your
[1:26:54]
budget till after the election. Why are
[1:26:57]
we zipping in because this is not going
[1:26:58]
to be okay after the election. Correct.
[1:27:01]
» Well, it's
[1:27:03]
kind of kind of going to do the same at
[1:27:04]
the county too. to try and get a
[1:27:06]
preliminary budget to put it forward for
[1:27:08]
the new mayor to come in to look at,
[1:27:10]
right? Because it's it's the mayor that
[1:27:12]
does the budgets now. So, at least
[1:27:14]
you've presented it. Here it is. This is
[1:27:16]
what we'd want. There's something there
[1:27:18]
for staff to organize the whole thing
[1:27:20]
and then it's presented to the mayor at
[1:27:21]
that time. Right.
[1:27:22]
» So, we have a doover right up till
[1:27:24]
October then.
[1:27:25]
» Yeah. Yeah. We could keep amending it.
[1:27:26]
Yeah.
[1:27:27]
» Oh, sorry, Laura.
[1:27:29]
» Uh through you. Yes. I don't know that
[1:27:31]
finance appreciates us. keep amending it
[1:27:33]
as we're going. But it is gonna it is a
[1:27:36]
living document. A budget is our our
[1:27:38]
forecast and our best plan. Um the idea
[1:27:41]
that we're working on it now is so that
[1:27:43]
it is still ready on the normal time
[1:27:45]
frame that we would have uh in a non
[1:27:49]
election year so that whenever the new
[1:27:53]
um mayor is elected uh and we have this
[1:27:56]
information available and ready to go as
[1:27:58]
soon as possible. We don't want to delay
[1:28:01]
the approval of the budget um further
[1:28:05]
into the year as possible because that
[1:28:07]
means projects are delayed uh
[1:28:09]
procurement is delayed and it can limit
[1:28:11]
what we can purchase operationally. So
[1:28:13]
we want to have this uh all buttoned up
[1:28:15]
and ready and again it's a typical
[1:28:17]
schedule for us to keep in a
[1:28:20]
non-election year as well.
[1:28:22]
» So then we if we have any issues with
[1:28:24]
our budget then we have a last chance to
[1:28:27]
take a look at it. Um, I believe now
[1:28:29]
that we're changing our meeting till a
[1:28:32]
October 6th or 7th or something. All
[1:28:34]
right. So, I I'm going to probably ask
[1:28:36]
to take one more look at the budget
[1:28:38]
then.
[1:28:39]
» Yeah. We'll see it coming on, right?
[1:28:41]
Yeah. Okay. All right.
[1:28:44]
Well, it makes I don't feel so like to
[1:28:47]
me I gota like normally I like to go
[1:28:48]
home and think about this because this
[1:28:49]
has been kind of rushed. I didn't see
[1:28:51]
this till Tuesday. So I was up late last
[1:28:53]
night and uh when I hit that report from
[1:28:55]
the uh the engineers that that was it
[1:28:58]
for me 11 o'clock my brain was fried. So
[1:29:01]
anyways if we could if I would suggest
[1:29:04]
get the updated version even for the
[1:29:05]
next meeting so that it's just there you
[1:29:08]
know as information because we do make
[1:29:09]
some changes here.
[1:29:12]
» Okay. So with that all in favor
[1:29:15]
» Uh through the chair. So, I'll just need
[1:29:16]
a mover and a seconder for that
[1:29:18]
amendment. If you were okay with those
[1:29:20]
lists of adjustments, the schedules A
[1:29:21]
and B, and then we would have a final
[1:29:23]
vote on the motion as amended. So, if
[1:29:26]
you're okay with that list, we can put
[1:29:27]
it on the screen again. I'll just need a
[1:29:28]
mover and a seconder for this as an
[1:29:30]
amendment.
[1:29:31]
» So, I need a mover and a second or do I
[1:29:33]
not just talk to the mover and a
[1:29:35]
seconder and see if they're okay with
[1:29:36]
this?
[1:29:36]
» Uh, no. Through the chair, we have an
[1:29:38]
original mover and a seconder for the
[1:29:40]
original motion, but this is an
[1:29:42]
amendment to the original motion. So, we
[1:29:44]
need another mover and a seconder for
[1:29:45]
the amendment.
[1:29:46]
» Okay.
[1:29:48]
So, somebody to put that uh you want to
[1:29:50]
read it again or no, we already saw it
[1:29:52]
or
[1:29:54]
» Okay, we no need to put on the floor. Um
[1:29:56]
somebody put on the floor for me. Um
[1:29:59]
deputy mayor, second by the mayor. All
[1:30:01]
in favor?
[1:30:04]
» Now, we'll go back to the other one. Um
[1:30:07]
I've already got a mover and a seconder
[1:30:09]
» To the chair. That's correct. So, this
[1:30:10]
would just be a vote to adopt the
[1:30:12]
original motion as amended.
[1:30:14]
» Okay. And that's okay for whoever put on
[1:30:17]
I guess whoever did it. All in favor?
[1:30:20]
That's pass.
[1:30:29]
Okay. 8.1 Rebecca
[1:30:35]
uh through the chair. So this is another
[1:30:37]
one where we would be looking for
[1:30:38]
direction from the commission and this
[1:30:39]
is regarding the October uh 2026 meeting
[1:30:42]
date. So currently we just have that the
[1:30:45]
commission provide direction on the
[1:30:46]
scheduled meeting date for October 2026.
[1:30:49]
Um we did originally have this scheduled
[1:30:51]
for October 8th and we are going to be
[1:30:54]
commentering the council chambers on
[1:30:55]
that day for the voting period. Uh so
[1:30:58]
this was just seeking the commission's
[1:30:59]
direction on how you would like to
[1:31:00]
proceed with the October meeting. If you
[1:31:02]
would like to meet uh earlier uh or if
[1:31:05]
you have another direction, please let
[1:31:06]
us know and we can make that happen.
[1:31:09]
» I'll put on the floor. Um deputy mayor
[1:31:15]
second by uh
[1:31:17]
» We're county on the six both of us.
[1:31:20]
Second by Mark. Uh I'm sorry,
[1:31:22]
Commissioner L.
[1:31:25]
» It can't be first thing basis. I like
[1:31:28]
the six actually. You want to make it
[1:31:29]
look cal.
[1:31:31]
» Yeah, except both uh the deputy mayor
[1:31:33]
and I are at county.
[1:31:35]
» Well, one of you can skip. [laughter]
[1:31:38]
» Well, I know I can't.
[1:31:50]
Okay. I think we got to do it before.
[1:31:54]
Do you have dates for us to look at, um,
[1:31:57]
Rebecca? Because I know we got to, um,
[1:31:59]
get this room right.
[1:32:06]
» Uh, we do have a calendar. uh or if the
[1:32:08]
commission prefers we could if you give
[1:32:10]
us direction during this meeting send
[1:32:11]
out kind of a calendar poll following
[1:32:13]
the meeting and see if there's a
[1:32:15]
compatible date for all. If you prefer
[1:32:17]
to check your calendars now we can do so
[1:32:19]
as well. We have a calendar for this
[1:32:21]
room the council chambers. Uh it's
[1:32:24]
available
[1:32:25]
uh various dates before October 7th. It
[1:32:28]
won't be available post October 7th
[1:32:35]
» The 29th.
[1:32:37]
Well, I could come. Yeah, if it's a
[1:32:39]
short meeting, that'll be
[1:32:41]
» What about the first?
[1:32:45]
» I can't attend the first time out of the
[1:32:46]
country.
[1:32:47]
» That's a happy face. I don't want the
[1:32:50]
first, but I'm available the second,
[1:32:53]
» But yeah, we can do the 29th.
[1:32:56]
» What's What do you like?
[1:32:59]
» 9th. The 29th. What about you? Actually,
[1:33:03]
everybody's nodding on the 29th. What
[1:33:04]
about you're good with that
[1:33:06]
» Through the chair? Yes, we can make that
[1:33:07]
work.
[1:33:08]
» I can sorry
[1:33:09]
» Through the chair. Yes, we can make
[1:33:10]
September 29th work.
[1:33:12]
» Um,
[1:33:16]
» So they're looking direction. So, our
[1:33:18]
direction will be to um meet on the
[1:33:20]
right at 9:30.
[1:33:29]
No, that's
[1:33:32]
right after the election. I'm gone.
[1:33:37]
Okay. Um, we'll let um Rebecca put that
[1:33:41]
up.
[1:34:01]
through the chair. So, the motion um
[1:34:04]
before the commission is that the
[1:34:05]
October 20 26 commission meeting be
[1:34:07]
moved to September 29th, 2026 at 9:30
[1:34:11]
a.m.
[1:34:13]
» Um the the people that put that on the
[1:34:15]
floor, you're okay with that? Okay. All
[1:34:18]
in favor?
[1:34:20]
That's all. Yeah, we did. Didn't Yeah.
[1:34:25]
I try to that first. I don't forget from
[1:34:27]
now on. That's why I always do it first.
[1:34:29]
Okay. So 8 um two the we've already done
[1:34:34]
that so we're going to skip to 8.3.
[1:34:36]
Um 8.3 would be our next one. Rebecca
[1:34:40]
» Uh through the chair. The motion for 8.3
[1:34:42]
is that report LC526
[1:34:45]
regarding operations update for canal
[1:34:47]
maintenance be received as information.
[1:34:51]
So on the floor, deputy mayor, second by
[1:34:54]
the mayor.
[1:35:17]
Anybody want to start there?
[1:35:21]
» Yeah, I see that. So, the review is
[1:35:22]
valid. So, we're good now for 26 right
[1:35:24]
to 28 operating season. Is it just a is
[1:35:27]
it an easier application to renew that
[1:35:29]
now, Laura, moving forward, or would it
[1:35:31]
be the same process? We start all over
[1:35:33]
again for another three-year period.
[1:35:36]
» Uh through you, Mr. Chair, my
[1:35:38]
understanding is we would we would need
[1:35:40]
to continue Sorry, it would be similar
[1:35:44]
to what we did this year. So, we would
[1:35:45]
start um that discussion with the
[1:35:48]
Department of Fisheries and Oceans uh
[1:35:51]
ahead of the 2029 season um in order to
[1:35:56]
get the uh approvals and the review
[1:36:00]
completed ahead of that.
[1:36:01]
» Okay.
[1:36:01]
» And we weren't too late getting that
[1:36:03]
approval, but probably started earlier
[1:36:04]
in the year just to put people's minds
[1:36:06]
at ease that it won't delay that start
[1:36:08]
again. Okay. Thanks, Laura.
[1:36:09]
» For sure.
[1:36:11]
Um I what's the discussion over the
[1:36:14]
skimming? Like they're not saying yes,
[1:36:15]
they're not saying no.
[1:36:18]
» Uh three, Mr. Chair. So they've said
[1:36:20]
skimming should not occur prior to July
[1:36:22]
15th window. Um so we are hoping to
[1:36:25]
discuss with them as we move forward
[1:36:27]
ahead of the operating season of 2027
[1:36:31]
uh to see if we would be able to do any
[1:36:34]
mitigation or any type of skimming
[1:36:36]
activities prior to that. Uh but as it
[1:36:39]
stands right now um for 2027 skimming
[1:36:42]
and harvesting would both initiate at uh
[1:36:45]
July 15th. Um and not none of the
[1:36:48]
inwater work would begin prior to that.
[1:36:52]
» What about turning on the water systems?
[1:36:54]
They don't have an issue with that at
[1:36:55]
all. The the all our systems the
[1:37:00]
» Part of our discussion with them.
[1:37:02]
» That's part of the discussion. So you
[1:37:04]
still have all that to discuss that
[1:37:06]
before.
[1:37:08]
Um,
[1:37:18]
so they are open to discussion is what
[1:37:20]
you're saying because um the the thing
[1:37:22]
I've noticed this year is a lack of fish
[1:37:24]
and minnows and we've we've stopped all
[1:37:27]
these things and I got to tell you like
[1:37:30]
normally I got minnows swimming across
[1:37:32]
the front of my place all the time and I
[1:37:33]
don't see any minnows. I'm as normally
[1:37:35]
when you're in the lake, they're
[1:37:36]
nibbling away on your feet. I don't see
[1:37:38]
them anymore and I'm I'm not sure what's
[1:37:40]
happened to them. Uh I I see a bunch of
[1:37:43]
turtles actually, but then I don't see
[1:37:47]
but I'm just kind of curious. Was there
[1:37:48]
any discussion about that? Like with the
[1:37:50]
lack of fish, do they are they noticing
[1:37:52]
it or
[1:37:54]
» You Mr. Chair, that's not part of the
[1:37:56]
discussions with them. They're reviewing
[1:37:58]
when when we put forward our
[1:37:59]
application. We're saying this is the
[1:38:01]
work that we're doing. this is the um
[1:38:04]
status that we are observing um and then
[1:38:08]
they review that and determine where we
[1:38:10]
go forward from it. So they're not
[1:38:11]
discussing current states or anything
[1:38:13]
like that. This is the hope also though
[1:38:15]
that the study that we've proposed and
[1:38:17]
it's part of the budget for next year is
[1:38:19]
that they're going to do some of these
[1:38:21]
species counts and identify what is in
[1:38:24]
the canals and in the lagoons are likely
[1:38:26]
to be um so that we can show a positive
[1:38:30]
or negative impact um of of the
[1:38:33]
operations or of the conditions that are
[1:38:35]
outside of our operations just changes
[1:38:38]
in general because again it's a living
[1:38:40]
ecosystem. So those are obviously going
[1:38:42]
to change uh many different factors
[1:38:44]
influence that. So that's the idea is
[1:38:46]
that we would be able to provide them
[1:38:49]
with a lot more evidence-based
[1:38:52]
information to help potentially guide uh
[1:38:55]
what we'd be allowed to do or not to do.
[1:38:58]
Um and to your comment about are they
[1:39:01]
open for discussions? We we they have
[1:39:04]
said yes that we can discuss with them
[1:39:06]
whether it's going to change the outcome
[1:39:09]
or not. that's where I wouldn't be able
[1:39:11]
to speak for another agency. So,
[1:39:14]
» And the people that are discussing it
[1:39:16]
with them is yourself that's who's
[1:39:17]
discussing it or do you need assistance
[1:39:19]
from um say experts in different fields
[1:39:22]
that would help us?
[1:39:24]
» So, through you Mr. Chair, we're
[1:39:25]
starting with ourselves to determine
[1:39:27]
what they would want to see from us. um
[1:39:30]
what information would be required, what
[1:39:32]
potential mitigations could we put in
[1:39:34]
place and then we would go from there
[1:39:36]
and we would advise the commission if
[1:39:38]
external resources are required but at
[1:39:41]
this point we don't we haven't
[1:39:42]
identified that be
[1:39:43]
» Because I guess the argument can go is
[1:39:45]
the fact that we are not dealing with
[1:39:47]
anything native in our lagoons
[1:39:48]
everything we're dealing with is
[1:39:50]
invasive and there's nothing native in
[1:39:52]
there at all and that's where I
[1:39:54]
sometimes think they don't look at what
[1:39:56]
we're doing as an advantage like just
[1:39:59]
putting the oxygen in the water. It's
[1:40:01]
got to be great for the fish, right?
[1:40:03]
That's you think for the habitat and
[1:40:04]
everything that went on and that sort of
[1:40:06]
thing. And when the soldier weave gets
[1:40:09]
there, the fish won't be swimming in
[1:40:10]
there till we cut out that stuff and get
[1:40:12]
it out to allow them to get in there.
[1:40:14]
So, it's just I and I guess I see all
[1:40:16]
that then I hear about the uh global
[1:40:18]
warming. Like, should that not be
[1:40:20]
changing the fish when they have their
[1:40:22]
their babies? There's so many things
[1:40:24]
going on here. I hope that our our
[1:40:26]
agencies out there are paying attention
[1:40:28]
to this and they can work with us on
[1:40:30]
this and maybe we can help them with
[1:40:32]
what we're doing. So that's my little
[1:40:35]
speech.
[1:40:37]
But anyways, but good report, Laura. I
[1:40:39]
really liked it and I saw your question
[1:40:41]
and answers there. I read all that.
[1:40:42]
Yeah.
[1:40:45]
» Um does anybody else have any questions
[1:40:47]
for Laura?
[1:40:50]
Um I guess all in favor.
[1:41:00]
» Okay. Now this is the unfinished new
[1:41:02]
business.
[1:41:04]
Um let's scroll first on that.
[1:41:07]
» I think Commissioner Hart's on 9.1
[1:41:10]
with the South Bridge lighting. We
[1:41:13]
» Oh, sorry. Okay. I'm sorry. I Okay. I'm
[1:41:15]
sorry. Um Yeah. I'm sorry. My apologies.
[1:41:18]
Okay. Just so I can
[1:41:21]
It's on the other sheet. It's the one I
[1:41:23]
printed didn't have that. Sorry. Sorry
[1:41:25]
there, Commissioner. Um 9.1.
[1:41:28]
Um I don't think I have to put this on
[1:41:30]
the floor, do I? Or should I?
[1:41:32]
» Uh to the chair. There isn't a motion
[1:41:34]
associated with it right now. If there
[1:41:36]
is any action to come out of it, we can
[1:41:38]
consider that as a motion if needed.
[1:41:40]
» Okay.
[1:41:43]
Yeah. Uh chairman uh with regards to the
[1:41:45]
uh south uh foot bridge lighting u that
[1:41:49]
that's been an issue for the resident of
[1:41:51]
16 South Island Trail for some time and
[1:41:55]
uh as a result they uh that that
[1:41:58]
resident has submitted a report of
[1:42:00]
concern on uh July 22nd and uh there has
[1:42:06]
been some action taken from the township
[1:42:08]
so far. Uh but in the meantime, uh that
[1:42:11]
that light is is works is on and off. Uh
[1:42:16]
there there's been times where it's is
[1:42:18]
not on at all. There's times where uh
[1:42:21]
there's been uh some lighting between 2
[1:42:23]
am and 3:30 a.m. and then other times.
[1:42:26]
So it it needs to be reviewed and when
[1:42:30]
it is working it is it is it is bright
[1:42:34]
and it's to the point where it could
[1:42:36]
also be considered u a violation on
[1:42:41]
bylaw in terms of
[1:42:44]
nuisance. the the light the light has to
[1:42:46]
be examined and I see uh as a result of
[1:42:50]
uh uh report of concern followup two
[1:42:52]
days ago that uh the uh the township is
[1:42:57]
is looking into review of this light. So
[1:43:00]
I just want to get on on record chairman
[1:43:02]
that that we're we're looking at this
[1:43:04]
and the township has taken some action
[1:43:07]
to uh get get this uh resolved.
[1:43:11]
So do you want to put a motion forward
[1:43:13]
that we request something here?
[1:43:16]
» Well, this is where I I need direction
[1:43:19]
by the by this by the commission is the
[1:43:23]
the report of concern has been res has
[1:43:26]
been respon the resident had has had a
[1:43:28]
response from their their inquiry to
[1:43:31]
report a concern and um the township has
[1:43:34]
received the request regarding the south
[1:43:36]
footbridge light which has been
[1:43:38]
forwarded to the appropriate staff for
[1:43:40]
review.
[1:43:43]
That's what's taken place so far. I just
[1:43:45]
want to be ensured by the commission uh
[1:43:48]
that that uh this this will be followed
[1:43:50]
up on and and and and it appears it is
[1:43:53]
» Also the town's following up on because
[1:43:55]
there's a lot of um u back like I know
[1:43:58]
this was the same thing happened a
[1:44:01]
couple years ago and there was a full
[1:44:03]
report done on it. there was pricing
[1:44:05]
done uh all different types of lights
[1:44:07]
and everything and uh I think you were
[1:44:09]
here even in the mayor you guys were
[1:44:11]
both there when we talked about that. So
[1:44:13]
maybe you should pull that information
[1:44:15]
out because it could save you a lot of
[1:44:16]
time, right? Like that report and bring
[1:44:18]
it all out, take a look and bring it
[1:44:20]
back maybe to the commission. Take
[1:44:22]
another look at um I know when um
[1:44:25]
Commissioner Hart told me about I went
[1:44:27]
over there, I could never find the
[1:44:28]
lights on and that's just a couple doors
[1:44:30]
from I was down there and the lights
[1:44:32]
were never on. So I I have you ever seen
[1:44:34]
the lights on, Commissioner? Uh yes,
[1:44:36]
chairman. I've been there uh when I've
[1:44:39]
seen the lights on and it it is
[1:44:41]
definitely a nuisance for the resident
[1:44:44]
of 16 South Southern uh trail and um I I
[1:44:48]
think if this gets reviewed, let let's
[1:44:50]
take a take a look at it. It's action
[1:44:53]
has to be taken on terms of the
[1:44:54]
intensity of the light, but it's got to
[1:44:56]
be consistent.
[1:44:57]
» I just don't understand why the light's
[1:44:58]
not going on and off. That that's there
[1:45:00]
that's a problem that's got to be out.
[1:45:02]
» Yeah.
[1:45:05]
» Okay. So, um, it's being looked after.
[1:45:07]
So, I don't have the motion on the floor
[1:45:08]
right now. You want to bring it up the
[1:45:10]
next meeting?
[1:45:10]
» We'll we'll follow up on this on on the
[1:45:12]
next meeting. If we can we can end it at
[1:45:14]
that. Yeah,
[1:45:15]
» I'd be happy with that. Thank you. Thank
[1:45:16]
you, chairman.
[1:45:19]
» The next one you got is nine. I'm going
[1:45:20]
to leave you right on the hot seat now.
[1:45:21]
Uh, 9.2. That's your thought.
[1:45:23]
» So, the other one [snorts] is is
[1:45:25]
regarding uh beach security. it it's
[1:45:29]
come to my attention and and others that
[1:45:32]
that lack of security on certain dates
[1:45:35]
and um I had the uh the benefit of of of
[1:45:40]
talking to the uh the manager of of
[1:45:45]
uh Brian Brainer and uh Brian uh reached
[1:45:49]
out to me and offered an opportunity for
[1:45:51]
me to meet with him and uh a
[1:45:54]
representative of 247 Guard. Uh we did
[1:45:58]
this last Friday and uh uh I was happy
[1:46:01]
to uh have an opportunity to meet with
[1:46:03]
Brian. Brian's already identified the
[1:46:05]
problem and has already created a
[1:46:08]
solution and uh I'm satisfied as as a
[1:46:11]
member of the commission that that
[1:46:12]
they're moving forward on this. So when
[1:46:15]
we did meet with the guard uh we were
[1:46:17]
assured that he would be working as per
[1:46:19]
the contract and it's and it's also my
[1:46:22]
understanding that we're not going to be
[1:46:24]
charged for those days. August 1 weekend
[1:46:27]
for example where uh they uh July first
[1:46:31]
weekend they they didn't show up. So
[1:46:33]
there are a few days that they they
[1:46:34]
didn't show up and that that's been
[1:46:36]
that's been corrected. Um and as a
[1:46:40]
followup uh I I know that he was working
[1:46:44]
on the Saturday and uh and one family
[1:46:47]
was approached where was the wristband
[1:46:50]
and the wristband was in place and they
[1:46:52]
gave it up and they they allowed the the
[1:46:54]
rest of the family to participate. So
[1:46:56]
sec beach security is important. it it's
[1:46:59]
got to be uh used in proper patrols. And
[1:47:02]
uh when I met with with with Brian and
[1:47:05]
the security guard, it was Brian's
[1:47:07]
clearly uh pointed out the the
[1:47:10]
responsibilities and expectations that
[1:47:12]
uh that that uh we expect and and I'm
[1:47:15]
I'm happy to report that they're they're
[1:47:17]
being met at this point. There was some
[1:47:19]
discussion though of of having uh two
[1:47:23]
security guards and uh I guess that's
[1:47:26]
for discussion some other time but uh as
[1:47:29]
long as we uh you know have one security
[1:47:32]
guard meeting the contractual
[1:47:33]
obligations and uh I I think as a
[1:47:37]
commission we're satisfied with that.
[1:47:40]
Um, the one thing I would tell you,
[1:47:42]
you'd mentioned to me about the two. Um,
[1:47:44]
I I thought that we had two and we'd
[1:47:47]
always went out like for two. So, I
[1:47:50]
phoned another commissioner who was like
[1:47:52]
involved in all. He said, "Absolutely.
[1:47:53]
There's always two." He says, "This
[1:47:55]
time's only one."
[1:47:56]
» Well, chairman, if you look back at at
[1:47:58]
the budget two years ago, it was
[1:47:59]
$25,000. Now, it was $10,000. So, that's
[1:48:02]
why I raised it uh uh earlier during
[1:48:04]
this meeting. And uh that's something
[1:48:07]
that's open for discussion. Even if we
[1:48:09]
had just but the one if we had one
[1:48:12]
security officer back and forth with
[1:48:14]
each beach and uh uh and and and during
[1:48:18]
the next contract agreement we we just
[1:48:20]
don't go for the the the the cheapest uh
[1:48:25]
u sec security uh company available. So
[1:48:29]
u but I I I'm really impressed with what
[1:48:32]
Brian's done so far. obviously
[1:48:34]
identified the problem, got ahead of it,
[1:48:36]
and so far it's meeting a contractual
[1:48:39]
obligation.
[1:48:42]
» Did you want to say something, Laura? I
[1:48:43]
saw it pop out. You just turn to your
[1:48:44]
mind.
[1:48:46]
» Uh through you, Mr. Chair. Yeah, I just
[1:48:47]
wanted to remind the commission that we
[1:48:49]
are bound by our procurement policy and
[1:48:51]
we do need to follow that um with all
[1:48:53]
purchases including beach security. We
[1:48:56]
can look at um ensuring that there's
[1:48:58]
it's not just price that is part of the
[1:49:01]
consideration. Um, and I did want to
[1:49:04]
remind you that we did increase that to
[1:49:05]
15,000 for 2027 as part of those
[1:49:09]
previous discussions.
[1:49:12]
» Thank you.
[1:49:13]
» Well, on behalf of what um, Commissioner
[1:49:15]
Art was saying, the other issue is is
[1:49:17]
the the gate with all of that. And
[1:49:21]
» Yes, the so to follow up on on I think
[1:49:24]
there's been some correction on that as
[1:49:26]
well. There's that the gate and the gate
[1:49:28]
we're referring to is what used to be
[1:49:30]
pier one and it's a gate that goes on on
[1:49:33]
the on the south beach but leads along
[1:49:35]
uh the canal path to the pumping
[1:49:37]
station. And it's my understanding
[1:49:39]
talking to uh uh my understanding that
[1:49:43]
uh the gate is is open because people
[1:49:46]
have to have access to the pumping
[1:49:48]
station and they're back and forth
[1:49:50]
throughout the day and and sometimes
[1:49:51]
it's a little difficult to keep it
[1:49:52]
locked. Uh I've been down there.
[1:49:55]
personally seen cars drive in and and
[1:49:58]
park along the canal and and uh one last
[1:50:02]
two weeks ago on a Saturday there was an
[1:50:04]
individual had his car parked and a lawn
[1:50:07]
chair out and and fishing uh and then
[1:50:10]
two other vehicles came in and and and
[1:50:13]
uh decided to park there. This is before
[1:50:15]
the bylaw officer was able to get down
[1:50:17]
there and and clear it out which I I'm
[1:50:18]
grateful for that to happen. My concern
[1:50:20]
is if that gate is not maintained uh
[1:50:23]
kept kept locked and and people get in
[1:50:26]
there, it could obstruct the the access
[1:50:28]
for the uh fire and rescue people to get
[1:50:31]
to the boat if there is in need of an
[1:50:33]
emergency. And and that's that's
[1:50:35]
important.
[1:50:37]
But I also been assured and I and I've
[1:50:40]
witnessed uh bylaw officers doing their
[1:50:42]
their routine there.
[1:50:46]
So, so on that gate though, I I myself
[1:50:48]
notice it seems to be open more times
[1:50:51]
than it's closed when I go by. Um, but I
[1:50:53]
have watched the awkward once come. He
[1:50:55]
was parked the gate mocked all the way
[1:50:57]
up. He didn't bother unlock it. So, um,
[1:51:01]
and saying that is that that is
[1:51:03]
something else I wanted to talk about
[1:51:04]
too is where our gate is and they've got
[1:51:06]
the pole that runs to the lagoon. We
[1:51:08]
never went that extra three feet. We
[1:51:10]
didn't think people would squeeze around
[1:51:12]
it. They all do it now. Um, I know the
[1:51:14]
hotel, they shut it all down. So,
[1:51:16]
something we have to look at is to shut
[1:51:18]
that down because that's the new way
[1:51:20]
because there's nobody at the hotel.
[1:51:22]
They're all parking in the hotel now.
[1:51:23]
It's a wall access coming around. Before
[1:51:26]
it was always safe there because the
[1:51:27]
hotel didn't allow everybody to park.
[1:51:29]
But when you take a look, you see all
[1:51:31]
the parked cars all the way along. And I
[1:51:34]
give the hotel credit because they throw
[1:51:35]
all their garbage in the bin. It's all
[1:51:37]
piled there. I go by the next day, it's
[1:51:38]
all cleaned up. So they're obviously
[1:51:40]
paying pay up all that because I we're
[1:51:43]
not that's not ours, right?
[1:51:45]
Okay. So I I don't know that's something
[1:51:48]
I'll probably bring up in the next
[1:51:49]
meeting. It's not something that has to
[1:51:50]
be rushed, but I do think we should
[1:51:52]
cover that.
[1:51:54]
» Yeah. Thank you. Uh thank you chair. And
[1:51:56]
one one other comment the last one is
[1:51:58]
the
[1:52:00]
we can move on to the other uh new
[1:52:04]
business goose. Is that
[1:52:05]
» Yeah. So the goose management. The
[1:52:06]
reason why I I I wanted that in there is
[1:52:09]
that I I' I've read and and received uh
[1:52:14]
message that the uh the the geese uh the
[1:52:19]
the goose the goose treatment is is all
[1:52:23]
over the place and it's a mess. And I I
[1:52:25]
I in my observation, I think the the
[1:52:27]
gate goose population is is is down. And
[1:52:32]
uh of course this time of the year is
[1:52:33]
not as a problem as it was a few months
[1:52:35]
ago, but I think the wildlife management
[1:52:38]
under the direction of Michael Van Cass
[1:52:40]
is doing an amazing job and uh I just
[1:52:42]
want to put it on that uh I think the
[1:52:45]
goose management system is working for
[1:52:48]
uh for what the township is providing
[1:52:50]
and that's why I have that on there.
[1:52:52]
Chairman, thank you.
[1:52:54]
Do you have anything else here? Huh? Or
[1:52:57]
that's it. Um, I got I got a couple
[1:52:59]
things here. Um, first thing I want to
[1:53:02]
talk about is this rafting party that's
[1:53:04]
happening down on the the beach the
[1:53:07]
beach there. Do you know anything about
[1:53:08]
it? Does anybody know this whole rafting
[1:53:12]
party that's happening in the marina?
[1:53:14]
No, nobody knows about it. Council,
[1:53:17]
there's no permits, no nothing,
[1:53:19]
right? Um, the only thing I'm saying is
[1:53:21]
I know there's a rafting thing there and
[1:53:23]
Parks Water was hadn't heard anything
[1:53:24]
about it and I'm what I'm more concerned
[1:53:26]
about and I'm not trying to stop this
[1:53:28]
and I think it's a great idea, but I we
[1:53:31]
don't know about it. If they're coming
[1:53:32]
onto our beaches, I I guess there might
[1:53:35]
be an issue and I'm hearing that there's
[1:53:36]
going to be a beer tent or something
[1:53:38]
along the um the area like up near their
[1:53:42]
gas pumps. I don't know if that's all
[1:53:44]
true. I don't know. So I I I'm not
[1:53:47]
getting involved in all this, but I just
[1:53:48]
want to make sure parks and waterways,
[1:53:50]
if you guys were aware of what they do.
[1:53:53]
» Anyways, chairman, I I I'm not
[1:53:56]
completely sure, but I think they own
[1:53:57]
that property and uh that's their that's
[1:54:00]
their discretion and uh I think what
[1:54:02]
what uh that business does is is is an
[1:54:06]
enhancement to our community. and uh why
[1:54:09]
would we want to prevent a an
[1:54:11]
opportunity for a business to do well in
[1:54:15]
our community and uh and just
[1:54:20]
quality of our our Lagoon city. I'm not
[1:54:23]
trying to shut it down and I respect the
[1:54:25]
fact that there's that's their property,
[1:54:28]
but if they're putting a tent there
[1:54:29]
where the beer is on the rightway, if
[1:54:32]
the fire department needs to get out of
[1:54:34]
there, there's a tent in the way of the
[1:54:35]
rightway and that's the only room that
[1:54:37]
they have there. And it's not my issue,
[1:54:40]
but I'm just saying when I hear things
[1:54:41]
like that from my life living and all
[1:54:44]
the permits and all the things that have
[1:54:46]
to go on, these are the problems that
[1:54:47]
happen. Like I think it's a great idea.
[1:54:49]
Enjoy it all, right? But I'm just saying
[1:54:52]
that there are like people think you
[1:54:54]
could just do this stuff, right? And
[1:54:55]
there's ramifications like because that
[1:54:58]
you know the the driveway, right, that
[1:54:59]
we're talking about where else would the
[1:55:01]
tent go,
[1:55:02]
» Right? But it's not I and it's not my
[1:55:04]
problem. I now that I know that it's not
[1:55:07]
included on parks and waterways. It's
[1:55:08]
not my issue at all anymore. That's all
[1:55:10]
I wanted to make sure was that if the
[1:55:12]
washrooms are being used or whatever,
[1:55:14]
we're going to have to deal with all
[1:55:15]
that. We're gonna have to get them
[1:55:16]
cleaned earlier whenever. Well, let's
[1:55:18]
have to make sure the individuals know
[1:55:20]
that they would have to get a permit for
[1:55:21]
the tent. Any of those large tents for
[1:55:23]
functions, you do require a building
[1:55:25]
permit. So,
[1:55:26]
» But I'm not trying to stop this. I'm not
[1:55:28]
being the guy. All I'm trying to say is
[1:55:29]
that I'm covering off the people the
[1:55:32]
Lagoon City and what we stand for and
[1:55:34]
that's what our job is. The rest of that
[1:55:36]
is not our job. It's not my job to do
[1:55:38]
that. And so, just so you know, I'm 100%
[1:55:40]
behind it. Yeah.
[1:55:41]
» Yeah. I'm not against it all, but I've
[1:55:44]
just seen it when other people have
[1:55:46]
tried to set up other tents. I've seen
[1:55:48]
the um the amount of paperwork and the
[1:55:50]
amount of permits that you need. There's
[1:55:51]
so much people don't realize that,
[1:55:53]
right? You know, and then all hell break
[1:55:55]
and then when something happens, that's
[1:55:57]
when all hell breaks, right?
[1:56:00]
So, I think all the power to them.
[1:56:01]
They're out in the water. They're going
[1:56:02]
to have a band on a like it sounds like
[1:56:04]
a lot of fun. They're gonna have a band
[1:56:05]
on a raft out there the whole bit. So,
[1:56:07]
all the power to them. Great for going
[1:56:09]
on.
[1:56:10]
» All right.
[1:56:12]
Um, the other thing I wanted to talk
[1:56:14]
about was this hiring prog process that
[1:56:16]
happened over the parks and waterways.
[1:56:19]
I'm I'm sort of disappointed that we
[1:56:21]
weren't involved in any of that. Like
[1:56:23]
because I've always looked at the fact
[1:56:24]
on the parks and waterways and it's
[1:56:27]
nothing against you at all, just so you
[1:56:28]
know, Mark, I think you're a great asset
[1:56:30]
to this and the whole bit, but it's just
[1:56:32]
the whole process that went on.
[1:56:33]
Normally, I know as a counselor, I used
[1:56:36]
to always talk to the people and I used
[1:56:38]
to talk to the people on parks and
[1:56:40]
waterways, too, because what you're
[1:56:41]
looking for is to mix somebody in with
[1:56:44]
the people um from park or from the
[1:56:47]
Lagoon City. And most of the people
[1:56:49]
sitting sitting here know of the person
[1:56:52]
the people that put their names in
[1:56:54]
because they've asked us, they've
[1:56:55]
touched base with us, they've asked us
[1:56:57]
what the job is. And so, we kind of
[1:56:59]
already know who's put their names. We
[1:57:00]
know who's going there. And I have never
[1:57:03]
been asked maybe a couple times by you
[1:57:05]
but never by yourself about what's your
[1:57:07]
opinion or what you're feeling or
[1:57:08]
anything like that. And I know when I
[1:57:11]
became a counselor the first thing I did
[1:57:12]
I called every single person on parks
[1:57:14]
and waterways to talk with each
[1:57:15]
individual and then I met with them just
[1:57:17]
to understand what was going to happen
[1:57:18]
when I became a counselor. And I I just
[1:57:21]
sort of feel like we got left out of
[1:57:23]
this whole process. I really did. I feel
[1:57:25]
like we got left out and I think it
[1:57:27]
wouldn't have hurt to reached out and
[1:57:29]
spoke to us about it all. Uh, and I
[1:57:31]
think a lot of us do have experience. I
[1:57:33]
question, and I'm going to say it in the
[1:57:35]
nicest way on council, how many people
[1:57:37]
on council have an experience of what
[1:57:39]
goes on in parks and waterways and the
[1:57:41]
experience of hiring somebody, what
[1:57:42]
you're looking for. And just to finish
[1:57:44]
it, then I'll let you go. Is the fact
[1:57:46]
that when somebody says to me, well, he
[1:57:48]
was an engineer, so he was a great
[1:57:49]
choice. We have engineers here doing all
[1:57:52]
this information. If I was that
[1:57:53]
engineer, I'd be very careful with what
[1:57:55]
I say because he could get himself in
[1:57:56]
trouble, right, if we go by what he
[1:57:58]
said. So I I just wanted to make that I
[1:58:00]
I I want to make the point that part
[1:58:02]
it's part part of I don't know where we
[1:58:04]
stand as parks and waterways and that's
[1:58:06]
why I'd like to have the access that we
[1:58:09]
can go to our lawyer like our own lawyer
[1:58:12]
not your lawyer like and and I say
[1:58:14]
nicest way again but that is the lawyer
[1:58:16]
for the town and his job is to protect
[1:58:18]
the town and any other lawyer that's
[1:58:20]
involved that's his job. Well, I'd like
[1:58:22]
to get a lawyer that says, "Okay, parks
[1:58:24]
and waterways, this is what you have."
[1:58:26]
And when I hear about this, you know,
[1:58:27]
um, thing coming up in two weeks from
[1:58:29]
now, I I would like to get a heads up
[1:58:32]
with the lawyer where we stand on that
[1:58:34]
or where this could be going, right? And
[1:58:36]
who knows where this could go, right,
[1:58:38]
with what's about to be talked about.
[1:58:40]
And I I'll stop there because I want to
[1:58:42]
continue to that, but you can speak
[1:58:44]
there. Uh, counselor, Commissioner.
[1:58:48]
» Yeah. Uh, thank you, Chairman. I just
[1:58:50]
want to top up on on your point. You
[1:58:52]
made a valid point. I I think it's it's
[1:58:54]
it's dismissive and uh irresponsible
[1:58:58]
to not include the chairman in part of
[1:59:01]
the uh process of of of uh of that
[1:59:05]
hiring.
[1:59:07]
But uh I'm I'm grateful that Mark is on
[1:59:10]
and I think it's uh I had to uh ask Mark
[1:59:15]
three times to get his resume and I had
[1:59:18]
had a look at it. is very very
[1:59:20]
impressive and and Mark is very humble
[1:59:22]
and Mark is going to be a tremendous
[1:59:24]
value to to the parks and waterways
[1:59:27]
commission. So I want to I want to thank
[1:59:29]
the committee uh the council to to
[1:59:32]
electing Mark as a as a commissioner but
[1:59:35]
I I think uh it's it's disrespectful and
[1:59:38]
dismissive for not to include the
[1:59:40]
chairman in that process. kind of
[1:59:42]
leading back to uh your other comment
[1:59:45]
about independent council for us. I
[1:59:47]
think it'd be uh it'd be the timing is
[1:59:50]
right now. I I I' I've witnessed things
[1:59:53]
where uh
[1:59:56]
it would it would be in the best
[1:59:57]
interest of the commission to have an
[1:59:59]
independent council as as we move
[2:00:01]
forward and and and I I think that
[2:00:03]
having this meeting coming up in a
[2:00:05]
couple weeks is great. having community
[2:00:07]
engagement is important uh especially
[2:00:09]
this particular uh October that's coming
[2:00:12]
up uh but the the it more more just for
[2:00:16]
a comment and I'll keep it fairly short
[2:00:19]
uh township Romero is unique in the
[2:00:23]
sense it has 16 kilometers of canal uh
[2:00:26]
which I don't know any other township in
[2:00:28]
Ontario has that so consequently you
[2:00:30]
know we have uh the lagoon city is is
[2:00:33]
unique and uh each resident pays like
[2:00:37]
$900 to $1,000
[2:00:39]
uh a year to to assist the township in
[2:00:44]
and uh m main maintaining the the canal
[2:00:47]
system which is is unique and uh uh I
[2:00:51]
think we have an obligation to maintain
[2:00:53]
the the commission and uh I'm looking
[2:00:56]
forward to this this meeting coming up u
[2:01:00]
and that's just my my comment uh
[2:01:02]
chairman [clears throat] thank you
[2:01:04]
» Well that'll be a good suggestion when
[2:01:06]
the consultants here and we're when
[2:01:08]
we're gathering the information that
[2:01:09]
because we like library board we appoint
[2:01:11]
the members and we appoint the members
[2:01:13]
to our community center boards but
[2:01:14]
sometimes throughout the year you and
[2:01:16]
you've seen it the board might say hey
[2:01:18]
we'd like to add this member to our
[2:01:20]
board and they make the request so maybe
[2:01:22]
one of the suggestions could be that the
[2:01:25]
commission recommends to council who
[2:01:27]
they would like to see added to the
[2:01:28]
board whenever there's a new member but
[2:01:30]
that would require a change in how we do
[2:01:32]
things but it's a good suggestion to put
[2:01:34]
in like any of these these concerns, now
[2:01:35]
is the time to bring it to that
[2:01:37]
consultant that the commissioner would
[2:01:38]
like more involvement in the appointees
[2:01:40]
on the board with recommendations.
[2:01:43]
[snorts]
[2:01:43]
» Yeah. So certainly go ahead.
[2:01:45]
» Yeah. I just want to top up on that a
[2:01:46]
little bit because I I don't want the
[2:01:47]
misunderstanding to ever feel that it
[2:01:49]
was a slight or nobody wanted to reach
[2:01:51]
out because that's the bylaws that we
[2:01:52]
have to follow, right? At this point in
[2:01:54]
time, bylaws are very clear that council
[2:01:56]
choose those members from those
[2:01:58]
applications. It's also confidential. So
[2:02:00]
we can't share that unless we change
[2:02:02]
those procedures. So that's the way this
[2:02:04]
whole system's been designed. So part of
[2:02:05]
my reason for the engagement and why
[2:02:07]
this consultation, I don't mind speaking
[2:02:08]
about that is because I believe that
[2:02:10]
levy payers should be the voters who
[2:02:12]
actually vote in the commission decide
[2:02:13]
in their community who they want to
[2:02:15]
represent them. And that's part of what
[2:02:16]
I'm hoping comes out of this and I hope
[2:02:18]
people speak up because I think that's
[2:02:19]
the best way to do it so that you have
[2:02:21]
the people you want to represent who
[2:02:23]
want this commission. You'll still have
[2:02:24]
two members appointed from council, but
[2:02:26]
you'll you'll be able to choose a
[2:02:27]
majority that can actually create the
[2:02:30]
votes. But I I guess part of the problem
[2:02:33]
that we had with that is that the system
[2:02:35]
way it worked is they reached out and
[2:02:37]
spoke to us. Nobody spoke to us. They
[2:02:39]
first we heard that this whole
[2:02:41]
interviewing process was happening when
[2:02:43]
it happened. Where did that decision
[2:02:45]
come from? Right? Like where how did
[2:02:46]
that all happened? Like we had nothing
[2:02:48]
to do with it. Nobody told us anything
[2:02:49]
about it. And going to this review
[2:02:51]
that's coming up. I'm 100% I asked for
[2:02:54]
it. So like we asked for it. I I believe
[2:02:56]
we all asked for it. But I what I didn't
[2:02:59]
like about it was when I I don't like
[2:03:00]
the wording. And when I look at the
[2:03:02]
wording there, it's like it could turn
[2:03:04]
into a uh situation over the the
[2:03:08]
people on parks and waterways. And
[2:03:10]
that's what kind of bothers me. I'd like
[2:03:11]
to see I would like to know and I read
[2:03:14]
in there further. I like to know what
[2:03:16]
you're we're telling the people to come
[2:03:18]
because if somebody says I've got no
[2:03:20]
problems with the parks and waterways,
[2:03:22]
then they're not coming. But if they
[2:03:23]
have ideas to make it better or they
[2:03:25]
have ideas on what we should do, like as
[2:03:28]
you said about the election, I don't
[2:03:29]
have an issue with that. I said that
[2:03:30]
eight years ago. That was one of the
[2:03:32]
ideas that we looked at. But I don't
[2:03:34]
have a problem with that. But what I
[2:03:35]
think we got to do is make sure that
[2:03:37]
it's not just going to turn into a
[2:03:38]
complaint session. And that's what it
[2:03:40]
read. I handed to a couple people when I
[2:03:42]
received it yesterday and that's what
[2:03:43]
they said to me. That's what they read
[2:03:45]
in it too because I wanted to make sure
[2:03:46]
I wasn't being oversensitive over this.
[2:03:49]
And that's what I didn't like about it.
[2:03:50]
So, I'm hoping that there's some sort of
[2:03:53]
guidance, not at the meeting, but before
[2:03:55]
the meeting, so people can actually
[2:03:57]
prepare for it because it's in two
[2:03:58]
weeks. And to me, I think it's one of
[2:04:00]
the most important things for parks and
[2:04:02]
waterways. I really did. I really feel
[2:04:03]
it was an important thing. But if it's
[2:04:05]
coming and there's just a complaint
[2:04:06]
session. Sorry. Um I think I'm stopping
[2:04:09]
here. What's What's wrong?
[2:04:10]
» Through the chair, um you're welcome to
[2:04:12]
finish your thought. I just had a couple
[2:04:13]
things to add uh if able when when it is
[2:04:16]
time.
[2:04:17]
» What? Sorry.
[2:04:17]
» Uh through the chair, you're welcome to
[2:04:19]
finish your thought. I just had a few
[2:04:20]
things to add to clarify the process if
[2:04:22]
there is an opportunity to do so.
[2:04:24]
» Okay. Um so that that was the point that
[2:04:27]
I was trying to make with that. I was
[2:04:29]
going to lead into that next. I know um
[2:04:31]
commissioner wanted to speak. Uh but
[2:04:33]
that that's what we really need to look
[2:04:35]
at. That that's I guess and that's where
[2:04:38]
I would actually like to actually talk
[2:04:40]
to an independent lawyer so that we know
[2:04:42]
where we stand on some of these things
[2:04:43]
like to come back out and he may look at
[2:04:45]
and say no absolutely not. You can you
[2:04:47]
should be able to do this. you should
[2:04:48]
have this rights, you should be able to
[2:04:50]
have this, right? And I think it would
[2:04:52]
help all the commission. Um, and and not
[2:04:55]
sometimes I feel like it's you guys and
[2:04:58]
us guys, right? And that's where
[2:04:59]
sometimes I don't like that feeling and
[2:05:01]
I don't think it's right because we
[2:05:03]
never had that feeling before. We never
[2:05:05]
we had a good relationship with council.
[2:05:07]
We had it worked out perfectly the way
[2:05:10]
that we had the deputy mayor. We had me
[2:05:12]
as I guess the counselor and it was
[2:05:14]
phenomenal. And the deputy mayor at that
[2:05:16]
time, he he did it correctly. He was a
[2:05:19]
commissioner when he sat here and he was
[2:05:20]
a counselor when he sat as counsel. And
[2:05:22]
he went both ways. And it's a hard thing
[2:05:25]
to wear two hats, you know.
[2:05:28]
» Well, that's what I'm just saying.
[2:05:29]
There's got to be like a give and take,
[2:05:32]
» Huh?
[2:05:35]
» Yeah.
[2:05:36]
» Well, it's not like we're going to go
[2:05:37]
consult them all the time. What I'm
[2:05:39]
saying is that it's just like there's
[2:05:40]
some questions that we've had and you
[2:05:42]
know I don't think your lawyer really
[2:05:44]
wants to speak to us on that, right?
[2:05:46]
He's representing you guys.
[2:05:49]
» And I I do think just in clarification I
[2:05:51]
think going back it's important for
[2:05:52]
people to understand the history because
[2:05:53]
I believe out of the PR11 it gave
[2:05:55]
council the the ability to create a
[2:05:58]
commission based on a bylaw which was
[2:06:00]
done in 2005 to delegate
[2:06:02]
responsibilities to the commission. So
[2:06:04]
going back in history, that's how it's
[2:06:05]
kind of evolved through the time from my
[2:06:07]
understanding of what it is. Uh but I'll
[2:06:09]
let uh maybe Rebecca want to jump on
[2:06:12]
» I
[2:06:13]
» Um through the chair, I just wanted to
[2:06:14]
clarify a bit about the legislation and
[2:06:17]
uh just note a few things for the
[2:06:18]
commission's knowledge. So the power to
[2:06:21]
appoint and remove members of the
[2:06:22]
commission is appointed to council
[2:06:24]
through bill PR11
[2:06:26]
and that is included in the the MARA
[2:06:29]
act. Uh and then the commission
[2:06:32]
responsibility would be to appoint a
[2:06:34]
chair of the commission andor designate
[2:06:35]
a meeting chair. Um council can decide
[2:06:39]
what that process looks like for
[2:06:40]
appointment and removal. So that was
[2:06:42]
what part of what occurred with the most
[2:06:44]
recent uh appointment is that council
[2:06:47]
directed to do interviews. So that's
[2:06:48]
what we proceeded with. Uh but
[2:06:51]
ultimately the bill is what gives that
[2:06:53]
authority to council to do so. Uh, I
[2:06:55]
would just like to also note for the
[2:06:57]
commission that a legal opinion uh was
[2:06:59]
secured by the commission in 2025 giving
[2:07:02]
a summary of the roles and
[2:07:03]
responsibilities for the Lagoon City
[2:07:04]
Parks and Waterways Commission and the
[2:07:06]
Township of Amara. This is available on
[2:07:08]
our website at www.rra.ca/lcpwc.
[2:07:13]
So, it's linked for anyone to review and
[2:07:15]
it does break down what the roles and
[2:07:16]
responsibilities are for each under the
[2:07:18]
MARA act and under the uh establishing
[2:07:20]
bylaw. So, if you haven't seen that, I
[2:07:22]
certainly encourage taking a look at it
[2:07:24]
because it is a good breakdown. Um, the
[2:07:26]
commission is welcome to secure its own
[2:07:29]
legal uh representative at any point. We
[2:07:32]
would just have to make sure that there
[2:07:34]
is a budget approved for it as that is
[2:07:37]
one of the um requirements of the MARA
[2:07:39]
Act is that the budget for the
[2:07:41]
commission needs to be approved by
[2:07:42]
council. So, if it's not in our current
[2:07:44]
budget, then requests would need to be
[2:07:46]
made to council to um approve that
[2:07:49]
budget. But it is within the
[2:07:50]
commission's um purview if they would
[2:07:54]
like to seek independent legal advice to
[2:07:55]
do so as long as it's within budget.
[2:08:02]
» So I think it's tied in already. So it's
[2:08:04]
in the budget. The other thing to um I
[2:08:07]
did read exactly what you what you read
[2:08:09]
there about what our job is because you
[2:08:10]
sent it all to us. But what I guess the
[2:08:12]
point I was trying to make is the fact
[2:08:14]
that nobody reached out from council to
[2:08:15]
us and kept us informed, even asked our
[2:08:17]
opinions and that the way it always had
[2:08:20]
been and we did follow the rules like
[2:08:22]
you know before but it was more of a a
[2:08:25]
input that came right in. It worked
[2:08:27]
well. I I I never had an issue with it
[2:08:29]
like when we did it like and I'm just I
[2:08:31]
was kind of disappointed with what I saw
[2:08:33]
right there. And um and I think um
[2:08:37]
Commissioner uh like it's great. I think
[2:08:40]
you're gonna do a great job. I think
[2:08:41]
you're a really good asset. So, it's
[2:08:43]
nothing against you. It's just that this
[2:08:44]
all came up over this talking. So, but
[2:08:48]
anyways, that's what I'd like to do is
[2:08:49]
like reach out and just talk to this
[2:08:51]
lawyer because as you know, talking to
[2:08:53]
like Ryan, he works for you. That's
[2:08:55]
that's how simple it is. Okay. And I did
[2:08:58]
not know that, thank you, Rebecca, that
[2:09:00]
we can get our own independent counsel.
[2:09:01]
I just wanted to double check that.
[2:09:03]
» So, basically the actual money that we
[2:09:05]
put for legal is kind of for us too,
[2:09:08]
right?
[2:09:09]
» To the chair. Yes, it's just dependent
[2:09:10]
on if the budget is available within the
[2:09:13]
current year. Um, so if there is
[2:09:16]
availability remaining in that budget
[2:09:18]
line, uh, the commission can direct how
[2:09:20]
that budget is to be used. If there
[2:09:22]
isn't budget remaining, then a request
[2:09:24]
would need to be made to council for
[2:09:25]
approval to have that budget allocated.
[2:09:28]
So if it if you're looking to transfer
[2:09:30]
money from reserves, for example, that
[2:09:32]
would need to go to council to have that
[2:09:34]
approved
[2:09:34]
» If we had to transfer money.
[2:09:36]
» Exactly. Yes. which I think we already
[2:09:38]
did for that massive amount of money
[2:09:39]
that came right. So I don't remember
[2:09:41]
asking for permission. Do you
[2:09:45]
» I believe there is money left in the
[2:09:46]
legal budget this year too.
[2:09:49]
» And that was um
[2:09:56]
process. Okay. So we are going there and
[2:09:59]
that's all I got. Do you have any
[2:10:08]
» Does anybody else have any new business
[2:10:10]
or Okay. So, I don't have to put any
[2:10:14]
motions forward, Rebecca. And nothing
[2:10:15]
here.
[2:10:16]
» Uh through the chair, if there's no
[2:10:17]
action coming out of those items, then
[2:10:19]
no, they'll just be listed on the
[2:10:20]
minutes as that they were discussed. Um
[2:10:23]
if there are any actions you would like
[2:10:24]
to see or any direction for future
[2:10:26]
meetings, please let us know and we will
[2:10:28]
put that on a future agenda if needed.
[2:10:33]
Yeah, there's a couple other things I
[2:10:35]
think. Um, there's no close session. No.
[2:10:39]
Um, adjournment. Um, going to put it on
[2:10:42]
the floor that we adjourn at 11:41.
[2:10:46]
Um,
[2:10:47]
huh. Put on the floor of the mayor.
[2:10:49]
Second by the deputy mayor. All in
[2:10:51]
favor? 11:41.