what's going on and where we're at. So,
we can all catch up. I know that we've
[0:04]
had multiple communications via text,
email, and phone calls. And just this
[0:10]
right here is a uh
a solidified of everything of that. So,
[0:16]
uh I'd like take uh I'd like to provide
a pull cover project update to this
[0:21]
elected board, citizens, and other in
interested in this project. First, let
[0:27]
me say that this project is more complex
than it may seem on the surface. We've
[0:32]
been continuously receiving information
from multiple stakeholders, but I
[0:36]
believe we have developed a solid
summary of what has occurred and how we
[0:39]
need to move forward in this project.
The original plan called for a new dome
[0:44]
to utilize a gray beam of the same size
as the previous structure, which houses
[0:49]
[clears throat] the anchoring system.
This was was included in the original
[0:54]
designing cost. However, during
excavation of the for the new gray beam,
[0:59]
the contractor discovered several issues
with the existing what I would call the
[1:04]
gray beam's footer, for a lack of a
better term. The footer did not match
[1:09]
the 2000 site plan that was used to
develop this plan. It w it mo most
[1:15]
likely reflected a much older pool
design that was transferred onto the
[1:20]
2000 site plan. So whenever it was first
designed whether it was the 60s7s or 80s
[1:26]
and then it just got transferred year
after year no one dug up the concrete.
[1:30]
So we didn't know the second uh the
areas where the footer existed the
[1:35]
underlying concrete was in very poor
condition and was unable to support the
[1:40]
required load of the new dome.
Third, in some sections, the footer was
[1:46]
missing entirely, leaving nothing stable
to anchor the new gray beam to. After
[1:51]
uncovering these conditions, we had to
investigate further before Yeden could
[1:56]
construct the dome. The most important
thing is to ensure the safety of the
[2:00]
people using the pool facility. Yeeden
contracted their structural engineering
[2:04]
firm, ISG, to review the situation.
Following their evaluation, ISG
[2:09]
determined that approximately 500 linear
foot of gray beam footing would need to
[2:14]
be replaced with a new uh footing system
that measured 24 in wide, 48 in deep in
[2:21]
compliance with the updated 2018
building code requirements. Um, as part
[2:27]
of this deeper assessment, geotechnical
experts was also brought in to determine
[2:33]
whether there was an underlying reason
why the concrete footers had
[2:38]
deteriorated as much as they have. The
geo technical team has recently provided
[2:44]
recommendation that slightly differs of
that of the structural engineers
[2:48]
approach. Both are now working together
to develop a unified solution that
[2:53]
satisfies both the structural integrity
as well as geotechnical requirements for
[2:58]
this for this project. We expect the
final recommendation to be within the
[3:02]
next two to three business days. Uh in
the meantime, we have received
[3:07]
preliminary estimates for the 24x 48
footer system replacement which came in
[3:12]
at 173458.
I would ask for an additional funds for
[3:16]
contingency with a total budget
amendment of 225,000 which I believe all
[3:21]
of y'all have not received a copy of
this morning. Whatever funds aren't used
[3:26]
will roll back into the uh fund balance,
but this is needed to keep us on track
[3:30]
with the six to eight weeks additional
time frame that uh yeen and moss Marlo
[3:36]
has provided to us this morning. In my
opinion, this project has had its fair
[3:40]
share of bad luck from the beginning.
We've encountered several unexpected
[3:44]
challenges from electrical issues to
concrete soil complications. That says
[3:49]
we are dealing with an extremely old
facility that naturally leads to
[3:53]
unforeseen challenges.
Also, due to the age of facility,
[3:57]
there's no reliable original site plan.
As a result, we don't always know what
[4:02]
is or isn't underground and where it's
located. We are gradually building a
[4:06]
better site plan as remodels, upgrades,
and maintenance work is completed, but
[4:11]
unlike but it's unlikely we will ever be
100% accurate under the ground. staff
[4:16]
and contractors have been working as
fast as possible to keep this project
[4:20]
moving and meet the tight November
deadline despite these setbacks.
[4:25]
Ultimately, I believe it's better to
take the proper
[4:28]
corrective steps now, even if it does
mean a short delay, than ask for more
[4:33]
significant and costly issues later. I
think the main thing for the electric
[4:38]
board citizens and swimmers to know is
the dome will be installed. It may just
[4:42]
take a little bit longer than expected.
I also think it's important for everyone
[4:45]
to know because I know I wasn't here but
I know there was a debate whether dome
[4:50]
versus permanent structure. It doesn't
matter which path this council would
[4:54]
have taken. We would have run into the
same bad concrete bad soil issue. Um so
[5:01]
there was it doesn't matter which way we
go we have to address address the soil
[5:06]
and concrete before we [clears throat]
can go up. Uh I think it's uh I would
[5:11]
like to ask council for the authority to
continue moving forward by approving the
[5:15]
budget amendment. I also will keep the
mayor and council updated until the pool
[5:20]
coverage project is completed. And I
also have a copy of the Mars Marlo
[5:25]
estimate I'm gonna give and you pass it
around.
[5:34]
» Okay. Council questions.
>> Um so you were saying that we're looking
[5:39]
at a six to eight week delay.
>> Yes, ma'am. So, uh it's 6 weeks for the
[5:45]
new footing system, 500 foot of that.
>> And then afterwards, uh yeeden it'll
[5:50]
take pro approximately two weeks to
install the dome. Um it's my
[5:55]
understanding that once the footer
system is in place, they will take I get
[6:00]
I'm assuming laser measurements to be
exact and then they will build the dome,
[6:05]
which it takes seven days to build the
dome. Uh they've already we've already
[6:09]
paid 50% of it. They've already got the
material. They're just waiting for those
[6:13]
measurements to put it together and then
it'll take another week to to construct
[6:17]
it.
>> Okay. So the six to eight weeks will be
[6:20]
from like November 1st. So
>> from today
[6:23]
» from today. Okay. So we're saying
>> we approve this a budget amendment.
[6:26]
We're going to give them a sign a change
order and move forward. But
[6:29]
» okay. So we'd say mid December is that
sort of approximately
[6:33]
» barring any other unforeseen
uh unforeseen incidents. Now I will say
[6:38]
I mean this ain't the most elegant way
to say it. This is the way I grew up.
[6:42]
This project's been somewhat snake
bitten from day one. I mean, the first
[6:46]
thing we did, we ran into electrical
issues.
[6:48]
» And then now we run into concrete and
soil complications.
[6:52]
» Um,
that's this thing that was underground
[6:56]
that we didn't know about.
>> So,
[6:58]
» and again, that were that was things
that we would have come across no matter
[7:02]
what we did. Yeah. Either structure just
to verify. Yes.
[7:06]
» It's an old facility. I mean, you're
going to run into issues.
[7:10]
» Mr. Mayor, I move that we authorize the
additional funds of $225,000
[7:19]
uh
so that we can move this thing along as
[7:22]
quickly as possible.
>> Okay, council, you hear the motion. Do I
[7:26]
have a second?
>> Second.
[7:28]
» Okay, motion and second. Any further
discussion? just uh uh just just comment
[7:34]
or two and there's there's a a lot of
unanswered questions but uh
[7:39]
[clears throat]
one of them is uh well doesn't matter.
[7:43]
Let's just move on with it so you know I
don't have anything else to say about
[7:48]
it.
>> Um I'd just like to say um as a former
[7:52]
high school principal I have been to
many meets in that bubble. I understand
[7:57]
the importance to our high school
swimmers and we have got to get that
[8:01]
bubble ready for a high school swimmer.
Also, I was a member of Linda Kids
[8:06]
Aquaize class in the morning. Those
ladies need that bubble. There's a a
[8:12]
good group of ladies that come every
morning and are a part of Miss Kid's
[8:15]
class. I've also been a member of Tony
Reese's class, Aquaciz class. So, I have
[8:22]
been very involved in that poll and I'm
very vested that we get this fixed as
[8:27]
soon as possible.
>> I also want to say one thing. We're
[8:32]
going to continue to look for
alternatives, but we're going to keep
[8:37]
the project moving forward and we're
going to do it as as cheap and as
[8:41]
effectively as we can, but we're not
going to cut corners to maintain safety.
[8:45]
So, I know that number y'all just got
it. You ain't had a whole lot of time to
[8:50]
research it. We haven't either. We're
going to spend the day doing that and
[8:53]
then we're going to if this budget
amendments approved, we're going to move
[8:56]
forward with it.
>> Yeah, that's good. Thank you.
[8:59]
» Anyone else?
>> Now, Moss Marlo will be doing this work.
[9:02]
Is that correct?
>> Yes, sir.
[9:04]
» Okay.
>> Okay. I'd like to commend staff and our
[9:08]
engineers and our contractors on the job
they've done in identifying the problems
[9:15]
and also identifying the solutions. And
I know uh staff has worked overtime on
[9:20]
this and I certainly appreciate your
work, Mr. Terms.
[9:24]
» Thank you.
>> And rec staff and both. Thank you. Okay.
[9:28]
Anyone else?
>> And I just want to um say that I
[9:31]
appreciate the updates that we have
gotten and I know you'll keep us updated
[9:34]
on this. I know the six to eight weeks
is fluid, I guess, for lack of a better
[9:39]
description. And I'm sure you're going
to try to attain that all the uh parties
[9:44]
involved. And I think everybody of
course overall wants it to be safe and
[9:49]
ready for use when it is open. So I
think that's
[9:52]
» we have uh all part all the stakeholders
know this is a important project that
[9:58]
has to be completed.
>> Anyone else? Okay council I have a
[10:03]
motion and a second. All those in favor
signify by saying yes and raising your
[10:07]
right hand.
>> Yes.
[10:09]
» Seeing none opposed motion carries. I
will now entertain a motion to adjurnn.
[10:14]
So move
>> second.
[10:17]
» Have a motion and a second. Those in
favor signify by saying yes and raising
[10:20]
your right hand.
>> Yes.
[10:21]
» Motion carries.
>> Thank you, St. Be safe.