Transcript
SOURCE TRANSCRIPT
This transcript is downloaded from the source you provided but we haven't reviewed it for accuracy. Treat it as a starting point, not a verbatim record. You can also request an AI-transcription of the audio file with the button to the left.
These are YouTube's auto-generated captions, not a human transcript — expect occasional errors, especially with names and technical terms.
[1:52]
I can hear it on the Okay,
>> we had the rim
[1:55]
last week
[1:59]
and he's you can see like all the smoke
is from the valley.
[2:04]
Yeah, we came back from the second
launch the other morning that have a
[2:07]
remark over the radio.
Oh yeah, we better turn to that.
[2:34]
Um, and we won't stream it. We'll just
have it recording and then when the
[2:40]
meeting's over, we'll we'll download it
and upload it to YouTube. Okay.
[2:44]
» It'll just be done after the meetings.
Okay. No one's going to be able to
[2:48]
» stream said airport meeting.
>> Hey, William.
[2:51]
» How's it going, man?
>> Good. How are you?
[2:52]
» Long time no see.
>> Yeah, it's been a while.
[2:54]
» We'll fix it afterwards. Yeah, we just
can't get into that other But we're
[2:59]
legal though.
>> Oh, yeah. We're fine. Okay. Yeah, every
[3:01]
as long as it's recording, we are fine.
Awesome.
[3:03]
» Thank you.
[3:09]
» All right. So, let's get started.
[clears throat] It is uh
[3:14]
» they can hear us. Sorry.
>> Can Rachel hear us?
[3:19]
» You Oh, I didn't.
>> Yeah, I can hear you.
[3:27]
So, uh, this is the, uh, Grand County
Airport Board. It's 4 o'clock on July
[3:33]
6th.
I'll call this meeting to order.
[3:39]
First of all,
who's here? Randy, Jason, Dan, Jeff,
[3:47]
Bill, Bill, Howard,
whatever that Steve [laughter]
[3:55]
Steve,
>> we have Rachel.
[3:57]
» Rachel's online.
>> We have a listener from the yard. So,
[4:01]
» okay.
>> Enjoy.
[4:03]
» All right. Any We do we have any
citizens to be heard?
[4:08]
» They can't hear us. It's not streaming,
right? So, anybody online that wants to
[4:12]
say anything?
All right.
[4:17]
First order of business, uh, approve the
minutes from the June 1st, 2026 meeting.
[4:25]
I'll make a motion to approve the
June 1st, 2026 airport board. I'll
[4:31]
second.
>> Jason uh moves that we approve them as
[4:35]
is and Howard seconds. All in favor?
>> I
[4:40]
» I unanimous.
>> All right. I
[4:45]
» Yeah. I
[laughter]
[4:49]
» All right. Um,
Steve, you're up. Report director
[4:55]
report. Okay, first off, um, let's talk
about the Sky West Airlines schedule a
[5:00]
little bit. Most of you should have had
a chance to go through what they're
[5:04]
proposing.
Um, which is, um, October 1st start to
[5:12]
Salt Lake.
We're proposing an October 7th start to
[5:20]
Denver. We are working really hard to
see if we can't eliminate that 7-day gap
[5:27]
in another way. So, I've spoken with Sky
West about it. Um, they're looking for
[5:33]
whatever way we might be able to keep
that keep that running so that we don't
[5:38]
lose that week. Uh, but Salt Lake will
definitely start October 1st. Just to
[5:42]
tell you what the issue is. Um because
DOT took so long in making this
[5:48]
decision. United requires a certain
amount of training time and that's as
[5:54]
fast as they think they can get it in.
We're petitioning them to see if we
[5:58]
can't condense that down a little bit um
to make that October 1st date. So more
[6:05]
to follow on that. I'm working with Sky
West closely with Sky West to see if we
[6:09]
can't make that happen. Also, while
we're on the topic of Sky West,
[6:15]
um, want to make sure that everybody
understands that what if, if you read
[6:19]
their posting for the jobs, um, read
them closely because some of them say
[6:24]
full-time positions with an S positions.
So, it's easy to get confused and think
[6:30]
there's maybe one full-time person, two
full-time persons. Right now, they're
[6:34]
proposing five full-time people. Um,
which is, I believe, Rachel can correct
[6:40]
me if I'm wrong. I believe is what
Contour is doing as well. And then
[6:44]
there'll be part-time positions along
with that. Some of this will be seasonal
[6:48]
as it is with Concour. You ramp up uh
when it's busy and you slow down when
[6:54]
it's not. Um, so
>> we don't have we don't have seasonal
[6:59]
employees.
>> Oh, you don't? Okay. No,
[7:01]
» I understood that you did, but that's
totally okay. Um, we're working with Sky
[7:05]
West to I was saying that because I
thought Contour did that. Um, Sky West
[7:10]
is not committed to doing that. So, we
are certainly going to try and get uh
[7:15]
the we should have the exact same level
of employment. We're also working on
[7:19]
making sure that they don't post a lower
wage um which they've posted. So, all
[7:24]
those things are still in flux and we
are working hard to hold them hold their
[7:28]
feet to that fire. So
>> great.
[7:31]
» Just FYI.
Um the numbers from January and May.
[7:37]
» One one question now the the winter off
peak no flies to Salt Lake.
[7:43]
» Yeah.
Right now that is the plan. We'll see
[7:47]
how but all of this can change depending
on usage. It's like
[7:52]
» that's what Sky West did last time. They
didn't operate in the winter to Salt
[7:56]
Lake.
>> Yeah. It it's like we're stopping the
[7:58]
Phoenix flights now in in the winter
when the traffic goes down. It's just an
[8:05]
off peak thing. If there's if there's
enough usage, of course, they'll keep
[8:10]
flying it. So, some of that just depends
on how it turns out. The schedule can
[8:14]
change as we find out who's using which
flights,
[8:18]
» right? But they if they're not scheduled
flights, they can't book. So, we have no
[8:21]
way of knowing. Right now they're
proposing it based on um past
[8:25]
performance, based on what happened last
time they were here and also based a
[8:29]
little bit on what contours Phoenix
flight was doing. So they're kind of
[8:33]
trying to look at all of that, piece
together a schedule that gives us the
[8:36]
most flights during the busiest times.
[8:42]
» They shouldn't look too hard at the
timing of their flights. Are they good
[8:46]
that it roll food to other?
>> Yes, they the the timing is to hit the
[8:51]
hub to hit the hubs at the hub times.
>> Okay.
[8:54]
» Now, the problem is there's a hub coming
and a hub going,
[8:58]
» right? So, some of these were hitting
the hub coming and some of these were
[9:00]
hitting the hub going. So, it's
when you got two flights a day, you can
[9:05]
hit both. um when you get one flight a
day, you're either hitting the hitting
[9:09]
the hub time to go somewhere go in the
middle or you're you're trying to get it
[9:14]
somewhere in the middle so you can get
you know everybody everybody connected.
[9:19]
» Yeah.
>> So yeah, that is also a topic for
[9:22]
conversation with with them ongoing.
>> Okay.
[9:27]
» Other questions before we get to
numbers?
[9:31]
This
is what's out there now. It's not
[9:35]
necessarily what's going to be
permanent.
[9:38]
So, just FYI.
[9:44]
» And last I looked, last I looked, we're
unable to book right now,
[9:49]
» right? Yeah.
>> I haven't tried that. It was supposed to
[9:51]
go online.
>> Well, it be this Saturday.
[9:55]
» Oh,
>> I thought it was going to be I thought
[9:57]
it was going to go online.
>> This coming Saturday. Yes,
[10:00]
» I'll tell Cody and confirm exactly when
this will be live for booking. They
[10:05]
waited for us to approve this schedule,
which I told him just get get it out
[10:09]
there as quickly as possible. So, I was
on the phone with Cody today, but I did
[10:13]
not ask that question. Cody from Sky
West. So, I will I will ask that
[10:18]
question. When will it be able to be
blocked?
[10:25]
And I will get that sent out to all of
you tomorrow.
[10:29]
So you don't have to wait till the next
meeting. I'll have Sarah send out
[10:33]
exactly what date we can expect it to go
live online.
[10:38]
Um so you can see our our operations
again have have grown through May. Uh we
[10:45]
expect they'll probably level June and
start bumping off in July and August.
[10:53]
That seems to have been the pattern. Um,
days of the week, again, it's pretty
[10:57]
consistent.
Not much talked about there.
[11:03]
Visiting versus based aircraft, still
tracking that. Obviously, most of our
[11:08]
most of our operations are from visiting
aircraft, much fewer than base.
[11:18]
You see which way the wind's going.
We're uh doing a lot more on 21 than on
[11:24]
03
which
[11:28]
seems like that should be bringing the
smoke to us
[11:32]
and a little less smoke as kind of
anticipated.
[11:35]
» Take off on 21.
That's more just a function of shaping
[11:41]
the airport.
>> Yeah. No, for sure. You don't have to do
[11:44]
as much taxing. If it's calm wind,
obviously you're able to
[11:48]
» up like 10 knots the other way
>> or they're willing to make that long
[11:53]
taxi.
>> Yeah. Notice even the airlines, they
[11:57]
will also take off with a fair amount of
tails when it's cool, it's hot, they
[12:03]
change, but
>> yeah. Yeah.
[12:06]
um when landings uh basically kind of
the same information
[12:12]
fuel flowage
I don't know that we're up over last
[12:16]
year not by a ton we were up a lot more
in April than we were in May
[12:22]
our fuel flow is still a little higher
than it was last year in May
[12:27]
and then the painful one fuel flowage
jet A
[12:34]
dramatically down from last year. Again,
a lot of this is a function of
[12:39]
changeover of of airlines. Also,
employment's not growing quite as
[12:44]
quickly um through this. Also,
a factor that I think could be the
[12:51]
changeover of airline coming. People are
anticipating that um potentially not as
[12:56]
much advertising rolling in as maybe it
was before and promotion. So, I'm not
[13:01]
overly concerned with that being down in
May because I think it'll pick back up
[13:05]
again after we have a more stable
airline situation at the airport that
[13:11]
we're not in flux.
We'll talk about this, but I just wanted
[13:16]
this picture. Did you all get this
picture?
[13:20]
» That's up there. It's the first P as the
first aircraft to park on our new
[13:25]
concrete
>> parking apron.
[13:29]
Um,
>> Jud's going to give you a little more
[13:32]
statistical relevance to that when we
get to the construction portion, but I
[13:36]
just wanted you to see that was our it's
being used.
[13:39]
» Thought you were showing us the smoke in
the background. [laughter]
[13:41]
» Well, that too.
>> That too.
[13:46]
» So, Steve, did you get any feedback from
the firefighting aircraft? I know a lot
[13:50]
of them are flying out of the old
airport here in Moab.
[13:53]
» Some of them aren't. And some of them
are also flying out of Monaceel.
[13:57]
» Yeah. And Blanding. Yeah, they're kind
of just going they're going wherever
[14:00]
they can go
>> to get close to the fire and to get
[14:03]
close to water.
>> Okay.
[14:05]
» Um
>> yeah,
[14:06]
» you know, one of our issues is you can't
really fill anything up.
[14:09]
» Okay.
>> I'm just curious why so many at the old
[14:12]
airport versus the Canyon Lands airport.
Is it distance or is it
[14:16]
» just to place the station?
>> Is there a fuel flow charges?
[14:20]
» Typically they bring their own fuel,
>> right? So do they pay flowage at the
[14:25]
airport? No, not you mean when
>> there's no difference to them at the old
[14:29]
airport or at the
>> No, there shouldn't there shouldn't be.
[14:32]
We typically have not charged a fuel
flowage fee.
[14:35]
» Yeah. So, they're just doing it like
convenience then is closer to that.
[14:40]
» Yeah. There are other fees we we might
look at charging them, but fuel flowage
[14:44]
is not one of them.
>> Okay.
[14:46]
» Yeah. It's it's mostly convenience,
number of people, proximity to
[14:51]
other things um where they can go take a
shower and have a place to sleep.
[14:56]
» I'm sure they're probably camping out at
the airport.
[14:59]
» So, it's
>> we're just so far from like
[15:04]
» a lot a good water source right now that
I I think that is part of it.
[15:08]
» Okay.
But the ones that come out here like it.
[15:11]
They they don't like the light placement
near our new hopefully helipad. But uh
[15:19]
we'll discuss that at another time. J
and I are working through some ideas
[15:23]
about that. So we'll get there. The next
thing that you have in your packet is
[15:29]
the idea for the front entrance road.
>> You have slides on this or
[15:35]
» um I can pull them up or they're the
ones in the packet for the road.
[15:39]
get out of the pack.
>> Oh,
[15:42]
not in the in the online packet there.
So, we can we can pull it up. Um,
[15:49]
» the ones there.
>> Um, those are the ones I can
[15:53]
» that's the first one. I think we they go
past that one and it gets a little more
[15:57]
detailed.
>> Yeah. Yeah.
[15:58]
» So, we kind of show the scope of the
work and what what's going to be
[16:01]
happening. The first thing I want to
tell everybody is I just made a
[16:04]
unilateral decision that we're going to
wait and do this in July of next year.
[16:09]
Um rather than do that while we're doing
a a changeover of an airline. And uh
[16:16]
there's I think all of us at the airport
right now are uh it's a good problem to
[16:21]
have. We've got a little construction
fatigue. Um there's just so much been
[16:26]
happening um that we just think I just
think it would be better if we waited
[16:31]
and tore up our entry road after we're a
little more established and we do it at
[16:36]
a slow point
>> in the airport July rather than doing it
[16:41]
at a busy time of the airport uh in
October right when we're right when
[16:47]
we're having airlines.
>> I totally agree with you on that. Is
[16:50]
there a chance for additional funding if
we wait till next summer at all? Is that
[16:55]
part of the
>> I don't think so. In in fact, um if
[17:00]
anything, it's going to depend on what
oil prices do. The price of the project
[17:04]
could actually go up. Uh it's just it's
just a bad time, I think, for us to be
[17:10]
shutting down the airport.
And so if we lose a little bit of the
[17:16]
project,
uh we'll we'll choose the part we lose
[17:21]
judiciously. Um but hopefully we can get
the whole thing bid and and paid for in
[17:26]
July just as soon as we can here. In the
meantime, uh we're going to go ahead and
[17:30]
kind of split it, I think, is what we
decided. And the engineering for it is
[17:33]
going to be going forward so that we'll
be ready to rock. Um the intent is going
[17:39]
out to bid January. that we mean
obviously we're we've been working on
[17:44]
the intention of building it this fall
for the design aspects of it. Um we'll
[17:50]
kind of back off and reallocate
resources and basically go for getting
[17:54]
design finished by the end of the year
to go out to bid in January which is
[17:59]
always a very good time uh for bidding
project. We'll just bid it with the
[18:04]
intention of hey this is not going to be
a March 1st start date. is going to be
[18:08]
probably the June July timeline for
construction
[18:11]
» July August timeline.
>> Yeah. And this is something that can't
[18:15]
be done in the winter because of the
asphalt.
[18:18]
» So it's a seasonal correct the asphalt
plants are
[18:24]
in the while it's not set in stone
November 15th to April 1st no asphalt.
[18:32]
um they will either run it a little bit
later in the year or start a little bit
[18:37]
earlier depending upon what those
schedules look like. But generally
[18:42]
speaking, unless the contractor who has
the project is the one who's also making
[18:48]
the asphalt, they will always open up
their asphalt plants if they can get
[18:53]
work out of it, but they won't do it to
sub as much. If there's anyone that's
[18:58]
going to get early work, they're going
to do it or asphalt manufacturers, which
[19:02]
» isn't necessarily something you would
want anyway for curing and just doing it
[19:08]
when it's cold. It just doesn't cure
properly. It'll crack. It's It's not a
[19:11]
good time to do it.
>> Um, as far as Oh, I I skipped ahead to
[19:18]
entry roads. I wasn't reading our agenda
very closely. Um, so we issued our first
[19:27]
as far as I know, the first
written uh letter to someone for uh
[19:34]
violation of rules. We're not going to
bring up who it was or publicly shame
[19:39]
anyone, but just as a reminder to
everyone, when you stop, you must wait
[19:45]
for the gate to close completely
before proceeding.
[19:52]
We're not a sight airport, but we do
still have to follow those rules. If we
[19:56]
were a side airport, it becomes
a pretty serious violation. Here we have
[20:02]
some escalation clauses. You blow the
gate gate once, we're going to talk to
[20:06]
you. You're going to come back in and
get retrained. You blow the gate twice,
[20:10]
you're going to come back in, get
retrained, and get a formal letter
[20:14]
written to you. And if you're employed
by someone, your employer, it's going to
[20:17]
go to me, it's going to go to, you know,
whoever needs to see it. If it happens a
[20:23]
third time, we start restricting gate
access for a period of time where if you
[20:28]
work at the airport, that can be
pretty detrimental to your career. So,
[20:34]
um we're hoping that this we can keep
this stuff under control and make sure
[20:39]
everybody's obeying these rules. So,
that was our one real incident that we
[20:43]
had um to report as far as I the board
wanted to it's sort of an incident
[20:49]
accident report. Does it have repercuss
repercussions against the company if
[20:52]
they work for somebody
>> or the
[20:54]
» well their employee can't their employee
can't get in the door
[20:57]
» right there's nothing like
>> oh because your employee did this we're
[21:00]
going to restrict your access business.
>> We don't we don't do that. It's an
[21:05]
individual issue and
everybody gets trained by the same
[21:10]
people. So, everybody should know
exactly what the rules are. And
[21:15]
[clears throat] yeah, we just had one
that was a repeat offender and we
[21:18]
actually let it go
longer than we should have before
[21:23]
writing a frontal letter. So, we've just
taken it to step two. As far as I know,
[21:26]
it's the first time we've ever had to do
that. So,
[21:30]
I think everybody's doing doing pretty
good. Usually just verbal warning and
[21:34]
retraining gets it done. Um,
so that's it. Unless unless we have some
[21:39]
questions. I'll talk some more when we
get down to the construction portion.
[21:45]
Any questions?
[21:48]
Just know that we're going to continue
to work with Sky Last um to try and make
[21:52]
this change over as smooth as we
possibly can, but there's no way to do
[21:57]
it perfectly smoothly. There's going to
there's going to be bumps in the road,
[22:00]
but I'm working closely with Mark Ragio
in DC with Sky West uh to make sure we
[22:05]
can make it as smooth as possible.
>> Hey, hey, Steve.
[22:10]
» Yes.
>> I just wanted to clarify that on Sky
[22:12]
West um web site for jobs, their career
page for their agents. It says this is a
[22:19]
part-time position starting at $16 per
hour. their agents will be will be hire
[22:25]
will be hired as part-time,
>> which is the conversation that Cody and
[22:30]
I had today. He's got to go through a
little bit of a board process before
[22:33]
they can start changing that. Um, but he
and I were on the phone together uh
[22:39]
today for about an hour and that was the
major topic of conversation was to make
[22:45]
sure that that um hourly rate is raised
to a living wage in Moab. I I need them
[22:53]
to take what they did was just took all
their EAS
[22:57]
airports and just kind of got something
out there as quickly as possible.
[23:00]
They're now going out and reviewing that
because they do need to start training
[23:04]
people. They do need to start. So, they
just kind of got something out there
[23:07]
quick. Um but yeah, I'm still talking to
him about that. Um gave him some new
[23:12]
numbers that we want him to shoot for
and I'll be talking to him again
[23:15]
tomorrow.
>> Well, yeah, that I mean that's what they
[23:17]
promised, right? Full-time positions and
and our wage.
[23:24]
And so, yeah, we're definitely going to
hold them to to what they what they said
[23:29]
they would do. Had that conversation
today
[23:34]
and we'll continue.
Any other questions?
[23:43]
Oh, okay. We're we're going to be
working also on uh what the contract
[23:48]
looks like. We've got several examples
of Sky West contracts with other EAS
[23:53]
airports. We've got several examples of
um contracts from Contour and Denver Air
[24:00]
connections with other airports. They're
all public record because these are EAS
[24:06]
federally funded. So, we're looking at
those and creating a matrix. I think you
[24:09]
guys have the matrix already. We're
we're just going to see if we can pick
[24:14]
the best parts out and make sure our
contract is good. Actually,
[24:21]
» can they add that to the contract?
>> What?
[24:26]
» Yeah,
>> if we can certainly try. It'll be it'll
[24:31]
be what
I'll
[24:36]
» You know, I'm just I'm just trying to
look out for my agents. They can't work
[24:39]
part-time at $16 an hour. That it's just
not feasible.
[24:42]
» No, I'm I totally am with you and I
understand that. And if we can get that
[24:46]
into the contract, we definitely will.
Some things some things are governed
[24:51]
more by uh the Fed and some things are
governed more by the airport and the
[24:56]
airline. So, we're still working our way
through which is which. And um we're
[25:02]
going to get everything into that
contract that we can to make sure we
[25:05]
have a solid written document.
I also think contour or iOS going to re
[25:12]
is realized pretty quickly when they
start offering people part-time work
[25:15]
that they're not going to find people to
take. No.
[25:17]
» No. Especially if you have if you have
to go home and come back for for a
[25:21]
two-flight situation when we're so far.
>> I think there are a lot of things that
[25:26]
they're that they're the person that put
it out on the web did not take into
[25:31]
account, but I'm I'm dealing with them
at the vice president level and and
[25:35]
we'll try and get those worked out. And
I've talked to a couple people that have
[25:38]
interviewed who I I asked them like,
"Did they offering you part-time or
[25:42]
full-time?" They were like, "No, it's
full time." So,
[25:45]
» um, so I think that maybe it is a
weapon.
[25:48]
» Yeah. I think I think they're got to get
that fixed as quickly as possible. But
[25:52]
yeah, just know we're working on it
[25:58]
» for your people, too, Rachel. We I I
want them to be taken care of, too. I I
[26:04]
I don't want anybody getting hurt.
over this change.
[26:12]
» That's it.
>> Okay, back to you, Bill.
[26:16]
» Do uh why don't we let Bill go first and
[26:23]
on your county?
>> Yeah, there's a lot going on in the
[26:28]
county right now. We're in the middle of
the shuttle
[26:33]
to the end of Arches process. That'll be
a big discussion tomorrow.
[26:38]
We um I know there's been some side
discussions with um Mick and the
[26:44]
liaison, which is Brian Martinez,
regarding the advertising that's coming
[26:50]
up with Sky West. So, we don't have
anything rolled out yet, but I know that
[26:56]
they're trying to um parallel some TRT
money alongside the
[27:02]
Sky West money so that we can reach a
broader group there. And I think that
[27:07]
they're also trying to pinpoint the slow
times of the year as well. So, that's
[27:13]
going on.
[27:18]
What else are we in the middle of? We
got all kinds of stuff going on, but I
[27:22]
think that's mostly airport related. You
know, I do think that um with Sky West
[27:28]
coming in here and the shuttle at the
same time, those two are both going to
[27:32]
hopefully open up some doors to the
rental business at the airport. So,
[27:38]
and and as well as the shuttle business.
So, we should see some change there. I I
[27:44]
don't know. That's probably Howard's
realm, but curious to hear how the
[27:48]
trains running and what's going on there
when we get to that point. So,
[27:54]
but that's all I got.
>> Okay, Jason.
[27:57]
» Um, so the city has has a ton of
projects that are out to bid, you know,
[28:03]
um, such as continuing sidewalks, the
ball fields, um, roads, um, and
[28:11]
some flood mitigation things. that we
have all these things that are just kind
[28:14]
of we're waiting for for it to come
back. So, I think in the next couple
[28:17]
months we're going to be super busy kind
of approving some projects, things
[28:20]
going. Um, kind of the big thing that
we've had this month was um was what to
[28:26]
do with with the fireworks situation and
the fire situation. So that was kind of
[28:31]
a big deal we've been dealing with the
last two two two and a half weeks is
[28:35]
coming up with the moratorum or whatever
you want to call it on the fireworks ban
[28:41]
within the city limits which took a lot
of work to kind of get that done with
[28:46]
with the state. So yeah got it done all
I have right now.
[28:56]
It seemed like it was pretty good. I
didn't see any major
[29:02]
issues with fireworks. Did you?
>> No. That night everybody was quite
[29:06]
respectful. Actually,
>> I talked to some firefighters who said
[29:09]
that they didn't even hear fireworks at
that idea.
[29:12]
» I didn't either. I mean, I right here.
>> Yeah. And so I thought it was great that
[29:16]
everybody kind of heated that.
>> Yeah. Me, too. Yeah.
[29:21]
» I think that was a big deal because even
last year I can remember they were going
[29:25]
all over.
>> Yeah. Now we just got to get through the
[29:29]
the 24th.
>> I know. And I think that that's kind of
[29:32]
we gota So the fire ban goes till July
30th, but it has to kind of be
[29:38]
re-evaluated by the city for a few weeks
to see if that still can hold up, you
[29:44]
know. So
>> that's it. That's all I have.
[29:49]
» All right. How um kind of a lot of pro
projects underway including a lot of
[29:54]
advertising. Obviously, we're waiting
for the SEC or the UDOT for the decision
[29:59]
to announce Sky West. Um, I do recommend
even though we don't have a board
[30:05]
meeting this month, that the travel
office gets a goes ahead and kind of
[30:08]
gets things going as you said, Bill, and
we'll go ahead and approve that next
[30:12]
month. I'm all waiting for it to happen.
Um, a report from the returns this year.
[30:18]
Obviously, the county works in a
two-month debt um behind, you know, when
[30:22]
the numbers come in, but it was the
first the first quarter of this year. I
[30:26]
heard it was the first positive quarter
of growth of the county in four years.
[30:31]
So, I'd like to say that um the role of
marketing being re-engaged as it has
[30:36]
been in the last couple years has
impacted our visitation here. also
[30:41]
caveat the fact that there was no snow
this winter and it'll be interesting to
[30:45]
see how the second quarter results come
in. But certainly transient room taxes
[30:49]
are trending way above the budgets.
Restaurant taxes on the other hand are
[30:53]
actually quite a bit in decline. They're
about 34% down. We're doing a check in
[30:57]
to see if the number reporting is
correct. It's seen as quite an anomaly.
[31:02]
So, but so far so good. Um so things
seem to be gradually coming back into
[31:06]
Moab and we're doing all we can to
continue that um progression.
[31:14]
» All right. Anybody else want to
report except Jud? You want to take your
[31:19]
you want to take do your
>> um is it possible? You should be able to
[31:24]
share a screen. Correct.
>> Did you want me to back up?
[31:28]
» Uh no. I'm sharing something else
that worked up this morning. kind of
[31:34]
family vacation pictures. Yes,
[31:40]
» you should be able to share.
>> Okay. Yeah. Um they're not.
[31:43]
[clears throat] Okay.
[31:48]
Um
really go since the road's going to be
[31:54]
pushed. But basically just what we're
looking just as a very very quick
[31:59]
preview. the road the entrance road will
be happening in phases. It will be a lot
[32:03]
of signage a lot and this is why the
complication arises is um let me zoom in
[32:10]
as much as I can.
Um you know on the first phase we have
[32:16]
no overnight parking
in front of the terminal open parking in
[32:21]
the large parking lot. No overnight
parking. The reason for that is you
[32:24]
don't want someone to get on a plane, go
for a vacation for three weeks, come
[32:28]
back and forfeit it between them and the
exit.
[32:32]
» So, um just kind of that long.
>> How far south does that extend? Does it
[32:37]
go in front of our ners or is it short?
>> Uh the project will hit all of the road,
[32:43]
not necessarily parking spots, but the
road from property line to the automatic
[32:48]
gate.
>> Right. So,
[32:50]
» so will we have no parking for a certain
period?
[32:53]
» For a certain period, so during this
first phase, no, you daily parking in
[32:58]
front of the hangers, but um long term,
the only thing would be available
[33:03]
terminal parking lot [clears throat]
for us.
[33:06]
» The second phase will be very impactful.
Um
[33:13]
the rental car area will basically be uh
in access
[33:20]
for construction. Um, again, no
overnight parking. We'll work out the
[33:23]
details, but possibly rental cars in
front of the main terminal building
[33:27]
because there the rental car parking
right now will be the main thri for
[33:32]
construction traffic. Um, and obviously
that road will be be completely torn up.
[33:38]
So, no parking there. Pedestrians will
have to access through a temporary
[33:44]
walking path for general aviation
businesses and u GA tenants um or in a
[33:53]
longer walk over to the terminal
building.
[33:56]
The third phase
uh we'll build a secondary kind of
[34:03]
temporary dirt road right at the
entrance to go around while we do the
[34:07]
main entrance portion. By this point,
we'd have access to the parking.
[34:13]
Um, but by this point, be able to drive
in all the way up through the gate.
[34:19]
» How much time is each one of those
phases? Roughly,
[34:22]
» uh, roughly right now where we're at is
25 days phase one, 10 days phase two
[34:28]
because there's some carryover. Um,
and 10 days phase three. So, 45day
[34:34]
project. on will impact the the entry
gate so we'll have another way to get
[34:40]
around um so that skydive can continue
to get people in and we'll have accesses
[34:47]
with signage telling the access but
phase one is the longest one because
[34:51]
that's the one where the hole is in the
front of u the fire building and we're
[34:56]
going to have to go deeper there's a
little more it's a little more involved
[34:59]
there
>> but it it's impossible to see on this
[35:03]
resolution but we
This is addressing pedestrians
[35:09]
u the commercial terminal or commercial
traffic vehicles of general aviation or
[35:15]
airport businesses versus rental versus
um taking into account fire access
[35:21]
taking into account EMS access for
getting care flights out uh fuel
[35:26]
deliveries um there will be a portion
would actually have to utilize boot
[35:30]
hills were most likely to escort same
way that the large asphalt trucks are
[35:34]
delivering right now um to escort fuel
trucks up there.
[35:39]
» Yeah.
>> Will we lose access to the fuel farm at
[35:42]
some point?
>> Uh
[35:46]
» no, [clears throat]
>> you might have to take you might have to
[35:50]
take a different route, but you're not
going to do it, but I can always get to
[35:54]
the tanks.
>> Always going to be able to fuel tank.
[35:56]
» There might be some, you know, short
crossover times where the it might be
[36:02]
» deliverable. That's the whole idea of
having this plan that we can then now
[36:06]
we'll be
>> uh teasing out over the next 12 months.
[36:11]
» Okay.
>> Yeah. Luckily, we have now plenty of
[36:13]
time to revise and look at other ways to
do it. So,
[36:17]
» yeah.
So, uh next is the uh
[36:24]
this is the apron. I just kind of wanted
to give you an overview of what what was
[36:29]
actually done out there. We're still
waiting on some test results to so we
[36:33]
can work out getting contractor paid,
making sure everything meets passes all
[36:37]
the long-term testing standards.
Obviously, not going to pay for
[36:41]
something if it's bad. Um, but you also
saw that it took significantly longer
[36:46]
than we had scheduled um due to some
problems with their paving. So the very
[36:53]
first day ate a control strip and uh
then we ripped out two/3 but
[37:02]
uh came up with different designs uh
then came back and paved another section
[37:08]
as a control strip actually passed
enabled them to start going forward. Uh
[37:12]
then did what we're looking at is it's
hard to tell but there's little dots
[37:18]
here A through K 1 through 32. Those are
those 18 by 18 foot blocks of concrete.
[37:25]
Um so started doing them in pairs.
Poured that one on our third pore. Then
[37:30]
we ripped that out.
Um
[37:35]
then had a really good I you know
thought we had a or they thought they
[37:38]
had a good solution
and did that. Uh so then they came back
[37:44]
did a smaller section made them rip that
out. When they ripped that out, they
[37:49]
also broke part of the good part behind
it.
[37:52]
» Um,
then they came back and filled in that
[37:56]
original strip from the first day. We're
now by this point in time off the
[38:02]
original schedule where they should have
been completed. Now they're getting back
[38:06]
to finally finishing day one.
Um, next time build out the end,
[38:14]
added in smaller portions, got things
paved, and I don't know if you saw this
[38:19]
kind of very small portions paid on the
end, but that enabled the asphalt to be
[38:24]
paid. So, this is all the concrete. The
asphalt is the darker gray that
[38:28]
surrounds it. by doing these last final
sections that enable them to come back
[38:33]
and do the asphalt paving
to try to get that make sure that's open
[38:39]
before the current apron job is
happening. Um then they finally finished
[38:45]
everything out. Um, when it was all said
and done,
[38:51]
uh,
they did 10,300
[38:56]
square yards of concrete and 11,000
square yards of asphalt. So, 21,000
[39:03]
square ft. Biggest parking lot in Grand
County is City Market.
[39:08]
And City Market is for just under 15,000
square yards. So, this is almost Imagine
[39:17]
all city market just being concrete
where the cars are at where the overall
[39:21]
projects 50% larger than the biggest
parking lot. And this is just that side.
[39:26]
You know, this is the new expanded
parking. So, it really was a monumental
[39:30]
project that will benefit the airport
lock.
[39:34]
So, it might have been some struggles
and some uh difficulties for the tenants
[39:40]
and recognize that. But you do have
something great at the end that will
[39:44]
last for decades.
So do you think that we need to write
[39:49]
into the specs that they batch on site
in future projects? I mean that is the
[39:54]
issue is by the time that mud gets
>> the time was one of the biggest aspects
[39:59]
and they
we can't tell them explicitly how to do
[40:06]
that work. It's
>> it's way FA works is they you just have
[40:11]
a spec. You can't tell somebody how to
meet the spec. They just have to
[40:15]
guarantee they will meet the spec. That
recommendation was made to them multiple
[40:20]
times. Um, and they didn't meet the spec
as a result.
[40:25]
» I think that if they did it again, I
think they would put the batch plant in
[40:30]
because was
monumentally unprofitable for them. this
[40:38]
project.
>> Every one of those red blocks indicated
[40:40]
an area where they paid they spent
hundreds of thousands of dollars on
[40:44]
concrete and time and materials, then
had to rip it out, then put it back in,
[40:50]
and they're only getting paid. So, they
paid
[40:52]
» they paid
20 30% of the project twice at their own
[40:58]
cost.
>> So, eventually, did they batch it out
[41:00]
there?
>> Yeah.
[41:03]
» Uh they started they changed how they
were running their trucks. So again, we
[41:08]
can't tell them exactly how uh their
batch plant runs 8 cubic yards at a
[41:13]
time. They started out with 10 cubic
yard doing 10 cubic yard loads to
[41:19]
minimize how much many trips they needed
to make out. Well, that resulted out of
[41:24]
the first 32 panels,
24 of them getting ripped out.
[41:31]
Yeah. comp test sample because just the
carryover that going try to get that
[41:37]
extra two cubic yards tacked on 10
minutes on each load 15 minutes on each
[41:41]
load. So started coming back.
>> So what we can do though Bill is we can
[41:48]
charge um damages
to people when they take too long. So if
[41:55]
this happens you can build into the
contract liquidated damage.
[41:58]
» Did we have LDS built into this?
>> Yes. And did they end up going into LDS?
[42:04]
» Uh, it comes down to the whether the
county chooses to impose. Uh, but yes,
[42:11]
yes, they did go into LDS. Um,
>> and what are the LDS daily?
[42:15]
» I I can't remember if it's 1750 or 2250.
I think on this one it was 1750 a day
[42:24]
to the tune of about 40 days.
But that's that is the only way we have
[42:29]
kind of a holding fee to fire. So
[42:34]
» that will be a discussion that we'll be
having with you
[42:38]
and then in turn with them once we get
all of the final testing data back.
[42:43]
» Do we have any projects coming up that
require concrete out at the airport in
[42:47]
the f future in the next I don't care.
>> Not in the short term. No. So it's we're
[42:53]
kind of over the hump on the concrete
for right now.
[42:56]
» Yes. Anything that would would be minor
curb and gutter type stuff.
[43:00]
» Yeah. Yeah.
>> That doesn't have to be
[43:04]
» and taxi would still be asphalt. Any
anything any of the other airport
[43:08]
pavements would be asphalt
[43:15]
» for some time. It's not a concern one or
the other.
[43:20]
And now we are fortunate I don't have
I'll stop sharing. Um
[43:26]
we I don't I only have live pictures. I
forot I don't have any on my computer
[43:32]
for the other project going.
>> You were going to bring those back.
[43:36]
» I
Yeah, I thought they were on here.
[43:42]
» So yeah, we've got the first phase is
done. Um we're waiting for the final
[43:48]
test results of that. We got the first
round of test results and we're waiting
[43:51]
for the finals. Um, they milled out the
other section today.
[43:57]
» And you, if you didn't go out and watch
that milling machine work, you missed it
[44:02]
now. It is It's hypnotic. It takes out
this much asphalt just as it's
[44:09]
» wow
>> driving down and dumps it into a dump
[44:11]
truck. It's
>> pretty incredible to watch. This
[44:14]
project's been going really smooth,
really well. So, and we were able to
[44:19]
with the the money we got from this is
what I wanted to point out. If we had a
[44:23]
picture with with the with the money we
were able to get from the county to do a
[44:28]
little closer to that 50ft section in
front of those buildings, we're able to
[44:32]
get the worst of it. So, the most failed
asphalt, we're able to completely mill
[44:37]
that out and replace it with 6 in of
asphalt. So, we got the worst of it
[44:42]
taken care of.
It's not the full width of the hanger,
[44:47]
but that was
>> No, it got the worst. It's the part that
[44:51]
was unraveling.
>> Yeah. Moving on.
[44:54]
» Yeah.
>> Um, that one's going well. Again, the
[44:58]
road will rework for the entrance road
and then pay for maintenance to be
[45:02]
later.
>> How we doing on time on the
[45:06]
» the current apron job? Uh, I think we're
as of today, I think we're one day ahead
[45:11]
of schedule.
Um
[45:15]
depending on because they actually not
only mil everything but they actually
[45:19]
have have to hold the uh gra the first
layer. Um it will be the similar process
[45:25]
if you were there for the first phase
where they basically take they're taking
[45:29]
the whole area that they've mil. They're
digging out 30 in deep. They will haul
[45:34]
that away for right now. Then they will
dig out the rest down to 5t. Dump it on
[45:40]
the other half of the project. get that
material worked in, move that section
[45:46]
back on, work that material in, be ready
to go.
[45:52]
» PSJ has been good to work with and uh
>> really good. It's been really some these
[45:57]
guys are on top of their game.
>> What contractor is this?
[46:01]
» TSJ.
[46:05]
» Land was their sub for paving.
They did better paving than they did
[46:12]
with the concrete, but not by much.
>> So, we'll hopefully have the we will
[46:19]
have um the final testing stuff this
week from the phase one paving.
[46:28]
» Do we want to talk about the light poles
or something?
[46:31]
» No, let's I'll talk to you about it. Um
>> yeah, because we are getting questions.
[46:36]
I know that
>> it's Yeah, we'll we'll we'll talk about
[46:42]
it online.
>> Okay.
[46:47]
» And yeah, that so that handles all of
the the past project or the current
[46:53]
project and the next few project
maintenance and value.
[47:00]
» Hey, Steve, I think it's back to you for
airport leases.
[47:03]
» A couple of things to discuss about
airport leases.
[47:06]
with the easiest ones. Um, just waiting
for Laurel to get her survey points in
[47:12]
um for her first row of hangers that she
would she would like to build. So, she's
[47:17]
got a surveyor. Um, she called me today.
I wasn't able to talk to her. Today was
[47:20]
kind of a a crazy day, but I'll get with
her tomorrow and see where we're at. So,
[47:24]
those are still moving forward, still
planned. Um, just need to get some
[47:28]
survey markers in and some policy
decisions made and we'll be moving on
[47:33]
that. One of the policy decisions is the
difference between 20 feet between
[47:38]
hangers and 30 feet between hangers. Um
30 feet between hangers lowers the cost
[47:45]
of construction
dramatically,
[47:49]
but it takes up an extra 10 ft of space
where we could be putting hangers. Um
[47:58]
I think there's two ways that we can
look at this and this will be something
[48:00]
I will write up and we can have as a
discussion item uh or a vote item at a
[48:05]
future board meeting. Uh we can say that
if we have joined hangers like
[48:11]
condominiumized hangers like T hangers
that are all in a row, we're basically
[48:15]
saving that 20 ft of space in between
each one of those if they were
[48:19]
individual hangers. So, putting 30 feet
between those and the one next to them
[48:25]
might be one way we can go with it
because if hangers are together, you're
[48:29]
saving the space that you're losing. Uh,
for single hangers, we stick with the 20
[48:33]
ft. Um, that's just one of the ideas I'm
floating as a concept. I'll have
[48:38]
something more written up for you of how
it actually impacts the space um later.
[48:45]
We're just kind of starting to look down
these things. So, that's first on
[48:48]
leases. um still have some of those
pipelines still looking at getting some
[48:54]
of those hangers done. Uh particularly
uh Skydive Moab um which
[49:00]
should be moving dirt here pretty soon
to get that one started. Uh the other
[49:05]
thing about leases is again one of these
things I'm going to have to write up for
[49:09]
you so that we can have it as a
discussion item because I'm we're not
[49:12]
ready to vote on it tonight and I don't
have the information for you but I want
[49:15]
to give you a heads up. Um, some of our
leases are very vague and some of them
[49:22]
are kind of all over the map as we go
through the leases uh as far as what
[49:25]
people are paying and what people uh
what their terms are. Um, it's kind of
[49:30]
everywhere, but the one thing every
lease has
[49:34]
um in it is they are all subordinate to
the minimum standards and to the airport
[49:41]
rules and rags. So, if we want to clean
up some of the leases, some of them are
[49:46]
very long-term. The way we can do that
is through minimum standards um made
[49:53]
statute at the county. So, these are
some discussions that we're going to
[49:57]
have to be having here in the next
little while. The other part about
[50:00]
leases as we dig into these things as we
find out that there are many sublet
[50:07]
hangers around
uh we need to decide as an airport if
[50:11]
we're okay with subleting. Right now it
looks like uh as an airport we are
[50:16]
because it's been working out for pretty
much everybody. Um, one thing I would
[50:21]
like to do, however, is make sure that
any hanger that is being sublet, we have
[50:25]
a separate sublet agreement with the
subleases.
[50:30]
One of the issues that we have is we
don't know who's in some of these
[50:33]
hangers. I mean, we don't have any way
to contact them. Um, if there was an
[50:38]
issue, we we uh don't do this. So, I
told you I came from two schools of
[50:42]
thought. Provo, we just didn't allow
subleting at all. uh Reton, we did allow
[50:47]
subleting, but the sublet agreement also
had to be signed by the airport so that
[50:53]
we knew who was in there. So, you have
to have an agreement with the person
[50:56]
you're subleting to. And we have to know
how much you're charging that person.
[51:02]
Does that person also have insurance? Do
you have hangerkeeper liability
[51:06]
insurance?
Um just some of these different things.
[51:10]
And these are things we're just going to
have to come to policy decisions on
[51:14]
where we want to go. And and when we
come to have that conversation, I'm
[51:18]
going to I'm going to give you all
information on both sides of it so that
[51:22]
we can all discuss it openly how we want
to proceed because that is something
[51:27]
we'll build into the minimum standards.
If you are going to sublet your hanger,
[51:32]
the minimum standard for being a a sasso
is what it's called, a a special air
[51:39]
service operation. Hangarkeepering is
one of those operations and there is a
[51:44]
specific set of rules that we can put in
place that you have to follow to do
[51:48]
that. One of them is insurance u and one
of them is separate sublessie
[51:54]
agreements. So, just an FYI, that's
we're a ways away from that yet. We're
[51:59]
still working our way through it. I'm
just trying to identify areas of concern
[52:03]
that we need to um start looking at
sooner rather than later. Um
[52:11]
and again, it's more of a liability
issue for me. Need to know who's who's
[52:16]
there. I know some of them, but um we
don't know all of them. We have
[52:18]
agreements for some of them, um but not
all of them. Uh so I think it would be
[52:24]
important that we that we put something
like that in place but again until I
[52:27]
have something set up to do that with um
it's just a discussion item that we can
[52:33]
have. Uh the just one question on on the
is this also going to encompass uh
[52:41]
nightly or weekly rentals?
Is that lease subleasasing? What is
[52:45]
that?
We're going to have to talk about
[52:51]
that's that's another topic. Do we want
to allow someone to do a nightly sublet?
[52:59]
If so, then that there should be a
minimum standard built in to do that. It
[53:04]
should be addressed in our minimum
standards. You can do a nightly, but
[53:07]
here's the process that you have to
follow to do that as a business. Um,
[53:14]
» does that fall under our FBO at all?
nightly and weekly. Those short-term
[53:19]
rentals, I would say, should be done
through the FBO because that's where you
[53:23]
already have the blanket of coverage of
insurance coverage. Uh, that would come
[53:29]
all of those people would come in under
that umbrella. If we try and do nightly
[53:34]
sublets at every different hanger, it's
going to be almost impossible for us to
[53:39]
keep track of who's here, who's not, um,
in the event of any issue of liability.
[53:44]
In a sense, then you would be creating
competition for our revenue.
[53:48]
» Exactly. [clears throat]
>> True. And I don't want to do that. We
[53:52]
need to protect and that's going to be
one of the next things we're gonna talk
[53:54]
about here. Um protecting revenue
streams for the FBO. As you guys have
[53:59]
heard from me about a million times. Um
nobody comes into an airport and says,
[54:04]
"Gosh, that airport director and staff,
they're really good." They they don't
[54:07]
know we're even there if we're doing a
really good job. they they see our
[54:12]
terminal and they see our FBO. So, it's
really important to have a good strong
[54:16]
FBO. In order to have a good strong FBO,
you have to be able to protect some of
[54:19]
those revenue streams um that that
FBOs's are beholden to because your
[54:25]
minimum standards require your FBOs to
do a lot of different things for the
[54:31]
right to sell the fuel. [clears throat]
So, we require a lot of them. And if
[54:37]
we're not requiring as much of the
people who are coming in and competing
[54:42]
with them, um, that is an unfair
advantage against the FBO. So that's why
[54:48]
I want to tighten up those minimum
standards is to try to help protect some
[54:52]
of those revenue streams that
traditionally should belong to the FBO.
[54:57]
Is that making sense to everybody? There
are also some things with your FBO that
[55:01]
you should do in my opinion
um to make the FBO more profitable and
[55:06]
more able to
be strong. And one of those things is uh
[55:11]
that's the only person or the only
entity on the airfield in my opinion uh
[55:16]
that should have different lease terms
than
[55:22]
the rest of the airfield. FBO and ASO.
If you are a if you are qualified
[55:29]
minimum standard ASO, there are some of
those that we might be able to build in
[55:32]
some some favorable lease terms. One of
those is a longer lease.
[55:38]
So, if we give the FBO a little bit
longer lease, they have more ability to
[55:45]
finance their operation because as
leases expire, you know, buildings
[55:51]
» What's ASO?
>> Oh, sorry. Air service operator.
[55:54]
» Do we have any of those?
>> Oh, sure. Skydive Mand service operator.
[55:58]
» I get it.
>> Yeah. So, and there are [clears throat]
[56:02]
more that are operating that.
>> Yeah. We have the balloon people and
[56:07]
some others out there.
>> Yeah.
[56:10]
» Well, there's some others that are doing
some other things that we don't have any
[56:13]
minimum standards preventing them from
doing it. So, they're not having to meet
[56:17]
the same qualifications as the FBO.
Anyway, it's it's tricky and it's
[56:21]
complicated when you only have one FBO,
but we can't support more than one FBO
[56:26]
at the airfield. We just don't don't
sell enough fuel. Um because you want to
[56:31]
be careful
because it is a monopoly. You do have to
[56:35]
build some things into your minimum
standards to make sure that you um kind
[56:39]
of keep everything fair and above board.
And again, this is just the beginning.
[56:42]
This is the opening of this
conversation. I think I've mentioned
[56:46]
here before and Jed can back me up on
this. more airport directors have been
[56:49]
fired over rewriting the minimum
standards than almost any other topic.
[56:54]
Um, so it's a tough one. It's
>> looking to move on.
[56:58]
» It's a tough one to move into, but it's
one I think that this airport really,
[57:03]
really needs. Um, partly to protect the
FBO. Uh, in light of that, the current
[57:09]
FBO uh lease was signed in 2023
um for all of their hangers. How many
[57:17]
years is that for?
>> Well, what I'm saying is we're going to
[57:20]
make those all 50.
>> I see.
[57:23]
» From 2023 on, we're going to do 50-year
leases for the FBO. Now, what we do for
[57:29]
the rest of the of the airfield, let's
talk and let's decide what's good. What
[57:34]
we decided in Provo was 40, a 30-year to
5 years. Why? Because for tax purposes,
[57:39]
that gives you the ability to depreciate
out the entire value of building. I
[57:43]
believe that's still the case. But um so
for most people we do 40. For the FBO we
[57:50]
do 50. Now we would build that in some
of these leases that are almost unending
[57:56]
currently. We would build that in by
statute in the minimum standards and the
[58:02]
rules and regs stating
no individual airport lease can exceed
[58:09]
a period of this amount of time without
written consent from the count the
[58:15]
airport sponsor. All right. So, I'm I'm
letting you know this is the direction
[58:20]
that I'm hoping to move us and we will
have many many discussions along the
[58:25]
way, but this is uh
kind of I've been here a year now. I
[58:31]
have a pretty good feel for for what's
going on out there, for which direction
[58:35]
we're going. Um, and so we're going to
be having these these tougher
[58:42]
discussions and tougher votes over the
next coming months. And I I realize that
[58:47]
that's going to be right while we're
also prepping for an airline changeover.
[58:50]
But um we've just got to get started now
and we feel like we're in a position
[58:55]
where where we can finally we got a
stable staff and um
[59:02]
you know so we're working hard on that.
Um
[59:05]
» Sarah Sarah's been doing a great job.
>> So as you build this idea, great idea.
[59:10]
Uh we also need the financial part of
it.
[59:13]
» Yeah.
>> Uh you know the I you know the rules and
[59:17]
regs I mean you got to have this
insurance that insurance and all these
[59:19]
other insuranceances. Yeah. We need we
need to really say well what's the
[59:23]
impact of that? No. Like when the FAA
does something, they say, "Hey, when
[59:27]
they do A tob, they say, okay, it's
going to cost10 billion dollars to to do
[59:32]
that, you know, and it's going to you
need to know the effect of
[59:36]
» for sure
>> of because if you add a bunch of rules
[59:40]
and regulations, a bunch of
insuranceances, that means that
[59:43]
» well, people are going to pay more to
rent a hanger."
[59:46]
» Yeah.
>> Yeah. We need to understand the B.
[59:49]
» No. Yeah, they will. if if we had that.
But but we're not um look, we don't have
[59:53]
to reinvent the wheel on on this. This
has been done at a lot of other other
[59:58]
places. And frankly, it's just a rule.
If you're hangerkeepering,
[1:00:03]
the FBA wants you to have hanger keepers
liability insurance. I
[1:00:08]
» sure. for [clears throat] those that
don't have it. Now, I think what Bill's
[1:00:10]
point is we need to know is now the rent
on Bill Winfield's airplane going to go
[1:00:15]
up 100 a month or 500 a month, you know,
so that they can adjust that.
[1:00:19]
» No, I agree. I agree. That's why this is
going to be a discussion point. Minimum
[1:00:23]
standards don't get rewritten over the
course of a month.
[1:00:27]
» They they get rewritten over the course
of a year. I mean, these are discussion
[1:00:32]
points and some of them are heated. You
have public comment time. and we let
[1:00:36]
everybody at the airport um have input
uh so that we make sure that we get the
[1:00:40]
product out of it that is going to work
for the airport. All of that will be
[1:00:44]
part of it. Is um is hangerkeepers
liability insurance going to increase
[1:00:52]
the cost of that subletter? Probably if
they don't already have it.
[1:00:56]
» Yeah. the the the secondary thing the
other thing I would make sure that you
[1:01:00]
add in this is the idea of
uh are these some of these
[1:01:07]
insuranceances when we looked at this a
year or two ago
[1:01:11]
» some of the insuranceances weren't even
available you couldn't even get them
[1:01:14]
» so we don't want to write something in
you can't get
[1:01:17]
» no no no and that that's all part of it
like I said we don't have to reinvent
[1:01:20]
the wheel here it's been it's been done
at other airports so we just look at at
[1:01:26]
what they've and to find out what the
what the liability should be. I mean,
[1:01:30]
some some some people request so much
liability that you couldn't get it no
[1:01:36]
matter what. So, of course, we want it
to be reasonable. Um, and we want it to
[1:01:41]
[clears throat] be correct for our for
our airport. So,
[1:01:43]
» well, and some of the contention when
all that was going on before you arrived
[1:01:49]
was based off of trying to require
insurance that was similar to what the
[1:01:53]
FBO carried. And so there you had all
kinds of people that own Hangar, Mr.
[1:01:58]
Bird, Mr. Holly, a bunch of people like,
whoa, whoa, whoa.
[1:02:01]
» Yeah. If you require hund00 million of
single li single liability insurance,
[1:02:05]
you're pricing everybody out of the
>> out of doing it. And [clears throat]
[1:02:10]
like I said, to to require that just
means somebody didn't understand the way
[1:02:14]
airports work. Um, and didn't understand
that other airports
[1:02:20]
have kind of dialed that in where it
should be. So that's the problem you
[1:02:25]
find is as we went out and serve
surveyed airports, we found a pottery of
[1:02:30]
this and this and this and this and
this. There wasn't there wasn't an there
[1:02:34]
wasn't a standard or international
standard for the survey.
[1:02:38]
» No, you go to um you go to specific
airports. Um when I was doing Provo, I I
[1:02:43]
used Jeffco as sort of my sample because
at the time we didn't have commercial
[1:02:48]
service but we're growing um as my
sample. For us, we would use a larger
[1:02:56]
um commercial service airport and we
would look at those. We we want to
[1:02:59]
compare apples and apples.
So, but you're right, as Jud has stated
[1:03:04]
in this meeting, if you look at one
airport, you've seen one airport.
[1:03:08]
Everybody does it a little bit
different.
[1:03:10]
» Um but but there are ways to dial
within.
[1:03:14]
» Great. So I I I just wanted to as as we
start the discussion on this, I think we
[1:03:19]
just need to uh try to identify all the
issues and try to address them. That's
[1:03:24]
all it was.
>> I agree. And let me just say right now,
[1:03:26]
I don't think that anybody in particular
on the airfield is is abusing it or
[1:03:30]
doing anything particularly wrong. I
just get worried about the liability of
[1:03:34]
it. Sure.
>> And um if we're not doing our part, you
[1:03:39]
know, we need just need to do our part.
Yeah. Any questions about that?
[1:03:45]
» Yeah,
>> we're gonna have a ton. Oh, you had
[1:03:46]
something. Oh,
>> I did send an email for contacts and for
[1:03:50]
people to send in their insurance forms.
I've literally gotten two back from all
[1:03:55]
attendants at the airport. Um, so if we
can, you know, if you guys know, you
[1:04:02]
know, people talking to them that we
don't have all of this year's current
[1:04:07]
insurance paperworks for it. I mean,
there's work people that have airplanes
[1:04:11]
on the field. Um, and maybe you might
have a little bit more
[1:04:16]
maybe information or ability to push,
but yeah, I've gotten I've gotten two
[1:04:20]
back.
>> So, so remind people that we need that.
[1:04:23]
Um, yeah, we don't have contact
information for people that are actually
[1:04:27]
that have hangers, they've moved or or
uh um that as we go through these
[1:04:32]
leases, we just we just find layer upon
layer of stuff that we that we need to
[1:04:39]
dig into. and we're going to it's just
going to this isn't going to this isn't
[1:04:44]
going to be a six-month process. This is
going to take a while. So, bear with us.
[1:04:48]
But the starting point is um
find out how to contact everybody. All
[1:04:55]
right? Um it's hard for them to have
input if I can't notify them of a
[1:04:59]
meeting, for example. Um, so
anybody you know at the airport,
[1:05:06]
uh, some of you are out there more than
others, just tell them, please send
[1:05:10]
Sarah their contact info so that we can
move on with that part. We're not trying
[1:05:15]
to go after anybody. We just need to
know who's out there.
[1:05:18]
» Plus, with all the construction, I want
to make sure that everybody gets a fair
[1:05:21]
chance to know what's going on. I'd be
surprised if they show up one day like,
[1:05:25]
"Oh,
>> hey, the whole lamp's torn apart." I
[1:05:27]
mean we say we try to go okay
>> we sent out we sent out a blanket email
[1:05:33]
» or six months I think our emails are
probably fairly accurate. I think people
[1:05:38]
just haven't prioritized uh
>> moving them up. I think our emails are
[1:05:43]
accurate because we do hear back
>> from time to time from people. Um,
[1:05:49]
» oh, the other thing, the website, this
isn't about Lisa's. Sorry, I should have
[1:05:52]
brought this up during, uh,
director's report, uh, the website. We
[1:05:59]
have found out AJ was going to comment
on this, but Sarah and AJ have been kind
[1:06:03]
of working together on how we can update
our our web page, our airport web page.
[1:06:08]
Um, do you want to tell them? So
according as a map the uh Grand County
[1:06:12]
took all the I guess external websites
and have made it where they go directly
[1:06:17]
to the county website. So we cannot have
our own external website as of right
[1:06:21]
now. Um but we are kind of hand tied on
what we can put on there basically by
[1:06:28]
the way the Granite County website is
built. So, we will be getting with Matt
[1:06:33]
at some point in it to kind of like make
ours a little bit nicer and things that
[1:06:38]
we have posted on, they aren't showing
up. So, we're going to get with him and
[1:06:41]
make sure that we understand, you know,
the website well enough that we can put
[1:06:46]
more stuff on there.
>> So,
[1:06:48]
» yeah, cuz right now when we change
something, it doesn't show up.
[1:06:51]
» Yeah.
>> On on the actual site. We'll make the
[1:06:54]
change exactly as told and then it
doesn't show up. We'll try and put a
[1:06:57]
picture in. Not nice.
>> It didn't show up. Yeah. not not getting
[1:07:00]
there. So, we're working our way through
that. But the one thing we know and I
[1:07:04]
understand this them bringing everything
under one umbrella makes sense. You want
[1:07:08]
to you if you want to centralize your
branding so that everybody's not all
[1:07:12]
over the map, but we've got to figure
out a way that we can that we can update
[1:07:17]
some things a little a little easier and
and AJ is the one that's been working on
[1:07:21]
that from this point. So, we appreciate
uh his help with that. So, that's it for
[1:07:26]
me. I'm long- winded.
Hey, Steve. It's Rachel.
[1:07:31]
» Um, I just wanted to say thanks for um
the work you're doing on those leases. I
[1:07:36]
think that's had to have been done a
long time. So, the time you're taking to
[1:07:41]
get everything done with those. Um, I
really appreciate it.
[1:07:45]
» Well, well, you're welcome. But let's
let's give a big thanks to Sarah as well
[1:07:50]
and Chrissy from
>> Legal.
[1:07:54]
» Yeah. because they they have uh been
working together to get a lot of this
[1:07:59]
sorted out. Uh so yeah, I appreciate
that. We're we're really trying to get
[1:08:04]
on this. I have
>> to say I have to give Jess a shout out
[1:08:07]
because I can really see where she was
putting stuff together before I came and
[1:08:13]
where she got to and she did a lot of
work on it also. So I will give her
[1:08:18]
credit for credit
>> getting everything organized. Jess was
[1:08:22]
doing very well right in the middle of
it. Um, and so luckily Sarah was able to
[1:08:26]
see exactly where that was and pick it
up and go.
[1:08:29]
» Good job, team. Way to go.
>> Thank you.
[1:08:36]
All right. Uh, on the airport entrance
sign, not a lot has happened. We found
[1:08:41]
out that there is a ordinance that
prohibits uh electronic signs in the
[1:08:47]
county.
Uh, and it's unclear. So, we're
[1:08:52]
researching what that means. Uh, it's
the city has an exemption right now. So,
[1:08:58]
they can have digital signs, but the
county can't. Uh, so we're also looking
[1:09:05]
still looking for funds and ways to go
forward. So, if anybody has any ideas,
[1:09:10]
uh, I'll leave it on the agenda and
we'll talk about it in the future. Yeah,
[1:09:14]
I would love it if there was some kind
of a way we could at least have it on
[1:09:17]
during the day. Um, but this fight has
been fought before and uh didn't didn't
[1:09:27]
» I I need to know about the fight that
fought that was
[1:09:29]
» Well, I heard that that that another
company tried to put the sign in to see
[1:09:35]
if they could get a sign and this was
years ago. This is when this ordinance
[1:09:39]
first came out.
>> How old is the ordinance?
[1:09:42]
I'm not sure how old the ordinance is.
>> You know,
[1:09:45]
» I don't
It's not It's at least two commissions
[1:09:50]
ago.
>> Oh, yeah. It's long time ago.
[1:09:52]
» It's a long time ago. And it's based on
it's based on dark sky. Uh
[1:09:57]
» and and so that when they wrote it
though, it just says no. It doesn't say
[1:10:02]
only a day or only a night.
>> And whether it's a battle we want to
[1:10:05]
find technology has improved to the
point now.
[1:10:09]
» Yeah. There's a lot of questions. So you
can get
[1:10:12]
» is that a fight?
>> Is that a fight we want to get into or
[1:10:16]
just have a nice concrete
>> sign?
[1:10:19]
» Yeah. Or do we? Yeah. So that I think
that's that.
[1:10:23]
» I would love it if we could if we could
do that where we could put more
[1:10:26]
information about flights on it and um
it would it would be great, but we'll
[1:10:32]
just have to keep going down that road
and see where it leads.
[1:10:34]
» Yeah.
Yep. All right. Uh
[1:10:42]
I think that's about it. Uh for the that
we do have an thing on here for
[1:10:48]
marketing. I think we covered that
pretty well.
[1:10:50]
» Yeah, Bill covered that really well.
>> Howard talked a little bit about that.
[1:10:54]
» I think what Bill didn't mention is that
Melissa Jeffers, our economic
[1:10:58]
development director, is also um in that
loop now with that marketing money.
[1:11:04]
she's the one uh trying to combine it
with some other money so that we can
[1:11:08]
maybe magnify it. So yeah.
>> All right. Now who who uh I did have one
[1:11:14]
question that goes to marketing and that
has to do with u
[1:11:20]
who is who is the point for if we have a
newspaper article or a a construction
[1:11:28]
project that completed successfully or
you know we want to you know do an
[1:11:33]
entrance
>> who who is the point for getting that
[1:11:36]
» from now on it's me.
>> Okay. Jeffers
[1:11:41]
» and I'll work with Melissa
and uh
[1:11:44]
» for press releases and that kind of
thing.
[1:11:46]
» Yeah. Work with Howard and you know
we'll work with all the different
[1:11:49]
entities but uh the point person will be
from now on.
[1:11:55]
» Okay. Uh so we probably ought to do
something as far as contacting all the
[1:12:01]
press and tell telling them that
>> send a press release out oh about that
[1:12:06]
that they should be contacting me
directly. Well, okay. About marketing
[1:12:12]
things, we do have a PIO at the airport
now or not the airport, but at the
[1:12:17]
county, which is Melissa Jeffers. So,
she's the point person on on news items.
[1:12:23]
I I thought you were just talking about
the direct marketing dollars. And
[1:12:27]
» no, I'm talking about the press
releases.
[1:12:29]
» Press releases. We'll go through me, but
we'll go through Melissa.
[1:12:33]
» Okay.
>> Yeah. And so I'm just saying the press
[1:12:37]
needs to know all that. I've I've seen
some
[1:12:41]
» varying articles that have actually
disinformation in some of the articles
[1:12:45]
and that's a little bit concerning that
we don't get a
[1:12:48]
» that's not the fault of
the fault. I'm not going to call out the
[1:12:53]
newspaper. I'll keep them.
>> No, that's okay. I'm just saying we need
[1:12:56]
to have a they need to know that hey the
we're going to release something they
[1:13:01]
feel what they said.
>> It should be it should be clear to
[1:13:04]
everybody at this time that our PIO is
Melissa Jeffers. At least all of the
[1:13:07]
media knows that for sure.
>> Okay.
[1:13:11]
Great.
>> Y
[1:13:15]
does everybody have anything else? Okay,
we're done. Call the meeting close at
[1:13:20]
5010.
Thanks everybody.
[1:13:26]
Wednesday.