Beach Road Stabilization Project Oversight Subcommittee Meeting: March 25, 2026

Belvedere, CA · · More Belvedere, CA meetings · More California meetings

Transcript

Download: Text · SRT
SOURCE TRANSCRIPT

This transcript is downloaded from the source you provided but we haven't reviewed it for accuracy. Treat it as a starting point, not a verbatim record. You can also request an AI-transcription of the audio file with the button to the left.

These are YouTube's auto-generated captions, not a human transcript — expect occasional errors, especially with names and technical terms.
This transcript looks garbled at the source (not a parsing bug on our end) — treat it as approximate.
[0:00] That's it. Great.
[0:03] All right. Okay, well, maybe I I guess I'll I'll call to order and start the
[0:07] meeting. Um first order is roll call and I'll start
[0:12] and then we can go around. John Tantum, I volunteered to be chair of this
[0:15] committee, a Cove Road resident. Go ahead, Mr. Isaacson. Sitting in for
[0:20] Larry Store. Keith Fagan, a
[0:24] town resident. Uh Peter Mark, city council member. I'm going to excuse
[0:28] myself and get a pen. This one doesn't work good.
[0:30] Okay.
[0:34] Julian Poolweiler with Stetson Engineers, uh design team for the Beach
[0:37] Road stabilization project. Adrian Formaini, both with the city
[0:41] project management team. Great.
[0:44] Tony Boyd, public works director. Um
[0:48] and uh the others I I can chime in that Robert's uh
[0:52] excused himself from from being here. He wasn't able to make it, but he is
[0:55] joining us on Zoom. So, yeah, that's city manager Robert Zadnik.
[1:00] Robert, Robert, can you hear us? Are you on audio?
[1:05] Uh yeah, hi everyone. Can you hear me? Yes.
[1:08] Yeah, can you can you hear us okay, Robert?
[1:11] Yes. Yeah, you're coming through loud and clear. Thanks.
[1:14] Great.
[1:17] And I'm Chris Berry, assistant engineer with the city of Belvedere in the public
[1:20] works department.
[1:22] Peter, were you out when when the
[1:25] when the call came around to your your seat?
[1:27] » You know I said it, Peter. Okay, thanks. Yeah, um
[1:32] All right. Okay, well, the next item is the approval of the minutes from our
[1:36] prior meeting on February 26th, uh which are in the packet here and were
[1:42] distributed earlier. Are there any comments?
[1:46] on those? Happy to make a motion to approve it.
[1:50] I'll second that. In favor? I.
[1:54] Uh the minutes were approved from the February 26th meeting.
[1:59] Um next is the the the matter at hand to
[2:04] talk about the Beach Road stabilization project and the bids and reviewing the
[2:09] bids and uh
[2:11] discussing those and hopefully come out come up with a recommendation for the
[2:15] city council. Great. So, maybe Tony, I'll let you take
[2:18] it take over. Yep, thank you. Yeah, and um thank you everybody for for being
[2:23] here once again um in your time.
[2:26] And um this uh this meeting is a follow-up from
[2:32] our last meeting which really introduced you all to the to the plans for the
[2:35] project and uh the context for it. Um this meeting is to uh present the
[2:42] selection process um
[2:44] uh to you all and uh basically um uh request a recommendation uh that the
[2:53] city council approve uh the the contract uh for the for the project and award the
[2:57] contract uh to a contractor. Um and so, what I'll be doing is I'll walk
[3:03] you through the selection process um and we are uh I think it's fairly
[3:09] informal. We can, you know, discuss and ask questions as we go. And um yeah,
[3:14] happy to fill you in on on any of the of the details.
[3:20] All right. So, um so, to start with I'd like to clarify in
[3:25] my memo um >> [clears throat]
[3:28] » uh that because I didn't point this out in the memo. Um this contract is for the
[3:34] sheet pile installation portion of the project, which is the main uh the sort
[3:38] of the meat of the project. Uh there is another um
[3:42] segment which it which has to do with the the private properties on Beach
[3:45] Road, number 16 uh to number 28 Beach Road, um where there are gangways and
[3:52] utilities on on the properties there that will need to be removed for the
[3:55] installation of the pre of the of the sheet piles.
[3:59] And that's a project in itself. Um and so, that will be a a separate contract.
[4:03] Um And there there's a little bit of
[4:07] possible confusion with with uh with the numbers that that amount was included in
[4:11] the engineer's estimates um uh
[4:14] you know, and and that's not really I I didn't really um clarify that or point
[4:18] that out in the memo. Um
[4:21] and yeah, we we can we can look at it more closely uh but uh exhibit C, the
[4:26] engineer's estimate will will show uh
[4:30] that uh where that that line was included in the total cost of of the
[4:34] estimate versus the cost of this proposal.
[4:38] Um and
[4:42] yeah, if need be um I could also it'll take me a few minutes, but at some
[4:47] point I did uh pull up uh some of these documents
[4:51] onto the screen if it's helpful. And Robert might find that
[4:55] that useful. Um okay. Um so, the RFP was posted on
[5:00] February 20th. There was a lot of interest um it seemed
[5:04] to us with uh 58 downloads of uh of the RFP materials. Um
[5:11] uh it gives some indication, I guess, of of uh all the contractors out there and
[5:15] and who are kind of perusing the sites and
[5:17] uh interested to see what what projects are
[5:20] going on. Um
[5:22] that was followed by a mandatory site meeting uh with with prospective
[5:26] contractors. Um so, any contractor who wanted to
[5:30] submit a bid would have to be at the at the site meeting.
[5:33] Uh there were 14 companies represented there.
[5:36] Um and the deadline for questions following that was March 9th. Um we
[5:42] received four questions in writing and responded to in in in an addendum.
[5:49] Um there were two adden- addenda issued. Uh the first addendum was um
[5:55] a change to the insurance requirements in the contract.
[5:58] Um so, that uh yeah, basically uh provided uh the details of that.
[6:03] Um and then addendum two um uh provided details on the on the uh
[6:08] pre-bid meeting, um the questions received, um the responses
[6:13] to those questions, and also a clarification of of some of the uh
[6:16] contractor's responsibilities uh during during the project um
[6:21] related to workflow, their workflow, and coordination.
[6:26] The deadline was March the 19th um and that was uh attended by four
[6:32] different contractors' representatives uh as well as a union representative
[6:36] representative. Um A union from local three. Operators. It's not
[6:42] uncommon that they show up knowing about this type of projects. Yeah, thank you.
[6:48] Thanks, I wouldn't have known that. Um
[6:51] and then uh yeah, so and it was fairly
[6:55] straightforward. Each uh each envelope each sealed envelope was opened and the
[7:01] bids uh bid amount was was read out loud. Um
[7:05] uh people people, you know, took notes and uh and then asked some questions. Um
[7:11] most of the questions, I think all the questions were
[7:13] » So, they they they opened up their bids amongst all the other competitors?
[7:17] Yeah, so basically we received the bids um at a table we had a little table
[7:21] stationed next to the door there. As they came in, uh they they uh handed in
[7:25] their bid um and then um at the designated time
[7:29] which was 11:30 on that day, um we declared that uh bids were now uh
[7:35] closed and then uh and then we stood up at a at a table and opened each bid
[7:39] individually, pulled out the the documents, and read out the number to
[7:43] the to the uh the contractors. Is that is that a requirement? So, is that a
[7:48] requirement? It is the It's a law. I'm sorry, I didn't mean to speak over you.
[7:51] Yeah, that's right. Yeah, that was that is the procedure for
[7:53] uh public opening. And it sort of takes away your ability to negotiate with
[7:56] anybody. It does and the law it's it's it's uh
[8:03] it's a legal requirement for for public agencies. Um
[8:07] and and the the possibility to negotiate um
[8:12] is actually extremely limited. I mean, the the the amount on the bid uh if the
[8:17] city is to accept a bid, um
[8:20] it has to justify not accepting the lowest bid, basically. Um if it's not
[8:25] going to accept the the lowest bid, um there there needs to be a reason in, you
[8:30] know, um uh that the city would would do that. I
[8:34] mean, it's very seldom that that a city would want to not [clears throat] accept
[8:37] the lowest bid. But but is there is there I'm sorry to meet you.
[8:41] » No, no. Just just
[8:43] couple questions. So, you went from 58 downloads, I guess, I know it's a it's a
[8:48] gross number um to 14 visits and four
[8:52] made meeting the deadline. Did anybody come in after the deadline? Um which I
[8:56] know you you need to exclude, but I'm saying anybody come in just for
[9:00] information. >> No, no, nobody came in after the
[9:02] deadline. >> normal or why would you think you'd go
[9:04] from 58 to 14? I I understand a 58 to 14, but 14 to four seems a larger jump
[9:09] than I would expect. I'll go over the bats and then I'll and then I'll let
[9:12] I'll let you Adrian chime in. He's definitely um
[9:16] kind of written a few more of these rodeos than I have. Um but
[9:19] um I think uh one of the main reasons was there was this a specific piece of
[9:24] equipment that was um specified in the RFP and and uh and that was this uh
[9:30] silent piler, this guy can machine. And there are very few uh if
[9:36] if any, I think, in Northern California um
[9:39] uh companies that that provide that. Um so,
[9:43] you know, that was another thing is that all of them had the same subcontractor
[9:47] uh to drive these piles in. Um
[9:50] and I think yeah, some of the comments at the pre-bid meeting um
[9:54] related to that. They they sort of said, well, I mean, if we're all going to have
[9:57] the same prime I mean, if we're all going to have the same sub,
[10:00] um what difference does it make to you
[10:02] guys? And so, I think a lot of people felt that they wouldn't have a
[10:06] competitive chance. So, you know, so didn't didn't want to waste their time.
[10:10] Um but yeah, Adrian Yeah. So, uh you know, it was certainly a great turnout
[10:17] at the pre-bid versus who pulled plans. And who pulled plans could be a host of
[10:21] individuals that may actually not even have any
[10:25] ultimate goal of bidding on the project. However, they are very interested
[10:28] whether it be a vendor. Uh there are several
[10:32] uh communication uh companies that will track projects
[10:37] and then, you know, post items. Um so, you usually have a very broad spectrum
[10:42] of individuals that will pull plans and and anyone's allowed to do it. So, then
[10:46] you get down to the pre-bid meeting, which is certainly a more uh fine-tuned
[10:51] group of individuals that still may consist of additional
[10:57] individuals outside of who will be bidding on the project. Myself signed in
[11:02] on the pre-bid sheet because I was an attendee.
[11:05] Um my project manager Kyle, you know, Tony. So, there were
[11:09] others at the pre-bid that necessarily weren't going to be bidding on the
[11:12] project including subcontractors to potential primes.
[11:17] So, one of the critical uh subcontractors and at that point we
[11:22] weren't sure if there was a uh a prime or a subcontracting component
[11:28] to the uh company that does retain several of these Dyken silent pilers.
[11:33] And they were, you know, there with three individuals, you know, that are
[11:36] all from Blue Iron. So, that's how your list kind of kind of kind of
[11:42] that we ended up with? Is that a successful process or would we wish we'd
[11:45] had more or what what how do we how do you evaluate that? Exactly. Yes. So,
[11:49] good question. So, because of the uh selective equipment for installation,
[11:55] these contractors all knew that Blue Iron was going to be
[12:00] involved with this contract. You can only make the case Blue Iron's you know,
[12:04] selected who they who they want to work with. Correct. So, we do know based on
[12:08] the bid results that Blue Iron so provided numbers to several contractors
[12:12] and that's great. And all of them were very close on that one particular bid
[12:16] item when we analyzed the results. >> But they're not though. But they're not
[12:20] though. I mean, unless it's embedded in these lines. I mean, there's there's
[12:22] there's quite a big of variance in the, you know, uh line five, six, seven, and
[12:26] eight. You would think you would think if it's
[12:28] the same contractor between the same The contractor is this the opinion of cost
[12:32] for the project? I'm just looking at the
[12:34] line-by-line breakdown. Must be in the bid
[12:36] Okay. Yeah, so that's a computer too. I'm sure it's in a more detailed
[12:39] tabulation. But but you know, where you would where you would expect to see
[12:44] So, I'm I'm my bad. I'm sorry. I didn't have a thought that was on the one Where
[12:47] you would expect to see some consistency among them all
[12:51] would be alignment A, alignment A, alignment B, alignment C, you know,
[12:54] where this where where the the structural steel um sheet piles are
[12:57] being driven. You know, basically line five, six, and seven.
[13:00] Um and part of I guess
[13:05] Yeah. I don't know what I'm seeing right now, but
[13:07] To jump in, I'm I I I 100% see what you're saying and it is a bit of a head
[13:11] head scratcher about why Valentine uh uh
[13:15] have 2.3 million whereas the other contractors I think are more
[13:20] closely um converged at, you know, between 1.6
[13:27] and and 1.8 million. Quick question. Are uh are
[13:31] are we we're in at this point we're not even discussing Valentine's numbers or
[13:34] do you want to discuss their I mean, they're they're they're way high. No,
[13:39] no, no, I know. I know. I know. I'm I'm I mean, well, just just with four on the
[13:42] page and I you may want to just mention why you knocked out Corcus.
[13:46] Yes. Yeah. Yeah, definitely. I was coming to that. Yeah.
[13:50] Yeah, so they knocked out Corcus. They didn't
[13:52] they didn't really follow the process. Yeah, we can we can look at the
[13:54] administrative oversight by Corcus and they just forgot to sign something or
[13:57] was it like a substantial they didn't
[14:00] complete something important? Uh it was an it was I think
[14:04] I if it was me, if it was my company, I'd be very frustrated uh because um
[14:10] it is it's it's a very minor detail when you're filling out a form,
[14:15] but in in an RFP um it's it's significant
[14:20] um and uh it basically
[14:25] um The frustration for us too is that um we
[14:29] we were aware that Corcus had downloaded those those addenda
[14:33] um and so when they when they filled in their
[14:37] form um saying that they had not they they did not acknowledge uh the the
[14:41] addenda basically. I mean, but but but in the city's defense and our in our
[14:45] broader legal defense of this is also that when and if
[14:49] they're they're not acknowledging those two addenda which we we we can't verify
[14:52] that it's in their their their budget data and and they'll perform the work
[14:54] according to the specs that you laid out. Exactly. What's your real change?
[14:58] Which is why you have to sort of eliminate that.
[15:00] There's no way to have them acknowledge the addenda after the fact. It was too
[15:06] late at that point after the envelopes have been opened. Is that right? It you
[15:10] know, it's It would have been basically, yeah. I
[15:14] think that would have resulted in protest from from the other bidders um
[15:19] basically that they didn't follow procedures and then were being given an
[15:22] allowance for you know, to to correct items in their
[15:26] in their bid. Um
[15:28] Yeah. And you know, I mean, I think ultimately um
[15:33] you know, the city attorney weighed in on it and and uh
[15:36] yeah, it it was quite clear that uh this was the only option.
[15:40] Yeah. Um Luckily for us the the next the next
[15:45] bidder was was a very close in price and they, you know, for the total.
[15:49] I mean, but on those my question was a lot of those install sheet pile. Yeah,
[15:54] you go from even if you take out Valentine, you
[15:57] know, there's a six there's a $300,000 swing on line five.
[16:03] Between between between Thompson and and Gordon Gordon Mhm. And and Thompson
[16:09] being the third. That's why they were in third place. No, no, no, but I'm saying
[16:12] but if if if the same subcontractor is providing the service, maybe there's
[16:15] more detail that that there that I'm not seeing. Because they are carrying costs
[16:18] of unforeseen to for covering a sub. So, guaranteed Thompson is a more local
[16:24] contractor from Nevada and they may or may not have worked with um um Blue Iron
[16:30] as much, but I do know that both Corcus and Gordon Ball both
[16:35] work with them quite often and that is probably that is a reflection in Gordon
[16:39] Ball's number is that they have a very good understanding and operation for
[16:44] their subcontractor which is carrying, you know, 75% of this this project
[16:50] weight here. Um that is the way I see it.
[16:54] What a really good question. Um what is the ultimate nature of our agreement
[16:59] with this contractor? Is it a guaranteed max? What factors you you mentioned that
[17:03] in your review of um uh
[17:08] references that one of the one of the things you got back about Gordon Ball in
[17:11] particular was that they were able to finish the project on time and on
[17:14] budget.
[17:17] What what are the opportunities or what are
[17:19] the negative opportunities to be off budget for us? I mean,
[17:23] if is this a guaranteed max? Is this a fixed price? What happens
[17:27] um certainly I understand client driven change orders or or or material driven
[17:30] change orders, but is that what can can can can drive this into an overage
[17:33] situation? Yes. And and it's really and and Adrian definitely please do chime in
[17:38] here, but um
[17:40] my understanding is that uh they based their
[17:44] their their estimates of of costs or their their price
[17:50] on the If if other you know, if they get out to the sites
[17:54] and and um you know, they start digging and there's something something else
[17:59] down there than other than loose sand and rock, for example, um that causes
[18:03] delays and you know, changes um then then costs can
[18:08] change. Yeah.
[18:12] Yeah. Most of them Yeah, and then some of the units are are are stated you have
[18:16] you do a square foot for the sheet pile, but primarily they are either single
[18:21] units or total and or, you know, lump sum. So, each the only the square
[18:26] footage is on the the sheet pile, which is total.
[18:29] And then it's a furnish and install, so it's a completed system. I mean, Jason
[18:34] repair that was completed a few years ago. Were there many change orders
[18:36] associated with that project? Not one. And did it come in on budget? Uh well,
[18:43] that one was a little There was there it was not the same development of that
[18:48] project based on the situation because it was more of a observation that was
[18:53] made with both and Miller Pacific during and Stetson during the H and H study in
[18:58] 2019 for the shoreline resiliency for both shoreline and
[19:03] Santa Paula and Beach. Uh so, that was when it was prompted and
[19:07] the wall was showing uh significant signs of failure. So, that was what
[19:11] prompted that project. So, it certainly was in line with pricing
[19:16] um and there was no additional inflated costs due to a
[19:20] you know, expedited, you know, time frame. Blue Iron came in well under
[19:24] because they had a unique perspective on the installation of sheet with uh
[19:29] um just cutting edge tech
[19:32] you know, so they were we were able to complete the
[19:36] project faster than other companies. So And can you confirm my understanding
[19:41] as well that it's it it would go both ways as well. So, if less materials are
[19:45] used, for example, um than than anticipated calculated the
[19:50] square footage, um then then uh that's what's that is what it's
[19:56] built to the city as well as well invoiced. Yeah, I mean they're they're
[20:00] you know, this is what they were expecting and they're going to they're
[20:03] going to procure sheets like this is the first thing that has to happen. So
[20:07] » Right. So as far as the sheets go those that would be a single kind of bulk
[20:11] order I guess. >> Oh yeah, and they're going to jump on
[20:13] that as soon as possible just because of the lead time and getting into a roll
[20:17] because these sheets very well may not be on the brand yet. Okay. So it's yes
[20:22] specific to sheets yeah. Okay. I just know that I mean you know with
[20:27] paving for example if um you know for whatever reason it turns
[20:31] out that it's a few tons less than than expected. Absolutely
[20:37] and that's what's important just for keeping on track with you know that all
[20:40] those all those things. But yeah we'll certainly do that. And the good thing
[20:43] that we have going for us is the knowledge base of both Gordon and
[20:47] Blue Iron is that they're straightforward contracting that very
[20:51] they work well together. So the mere fact that they are a well-oiled machine
[20:56] is going to have you know it's going to just you know
[21:00] assist tremendously versus you know other subs that may or may not have that
[21:05] well of a communication yeah you know so. And then also yeah just to just to
[21:11] add if there is if there are complications
[21:15] you know it's it's uh the city you know through its through
[21:20] its engineer engineering team would have to
[21:24] um um
[21:25] uh basically approve any any changes like
[21:28] that any changes to the to the scope. So cost would be a part of that
[21:34] decision. So if you know if there's a if there's a huge change
[21:38] it because of you know some some unforeseen circumstance that that
[21:44] results in a big change in cost somewhere
[21:47] that would be a decision that the city would weigh
[21:49] for in terms of the project as a whole. What we do know is that we had very
[21:54] little issues whatsoever with a significant section of Beach Road
[21:58] several years ago. We saw very very bland questions from contractors.
[22:04] The bids came in without carrying costs of which we had no idea how this is
[22:09] going to go down. So that was those were all really good
[22:12] signs of a well-designed bid package from both the technical side as well as
[22:17] the opinion of cost. It was it was very it was right in line with what we you
[22:22] know we were hoping to see. We're just very excited we didn't see this as a
[22:26] huge The lowest the lowest bid it's Gordon Ball not Norman Ball right. I
[22:31] think in your memo you Yeah right sorry I for some reason I kept So I think a
[22:36] little bit of Herman Ball I don't know why it is wrong. See you the experience
[22:39] they have but we have not worked with Gordon Ball before as a city. They are a
[22:44] large contractor so there's a very good chance that they wouldn't have probably
[22:48] been worked on any They are typically a huge large scale commercial contractor
[22:54] doing anything else than that. But I I do know of that nature cuz they
[22:58] they do a lot of municipal work. >> Okay. I don't know but I don't know the
[23:01] company is that are public company or a privately held company we have I'm not
[23:05] sure and or if it's a member owned we have to you know have to look into look
[23:09] into that. One of them There was there was a level of analysis required for
[23:14] for this review. But this is this is They they
[23:18] are a large company that does many projects that's not name I've never
[23:22] heard of. No yeah. um Yeah it's I have noted them either.
[23:27] um I don't know if they're nationwide I
[23:30] don't know if they're that >> No they're not. I do know that they do a
[23:32] lot of work with PG&E. They do a lot of public utility work so they are they
[23:38] understand the public process. And I do know again that they work with Blue Iron
[23:43] quite a bit with projects. And a lot of times Gordon Ball is in prime for PG&E
[23:47] projects where Blue Iron is their sub. Yeah their their references were um
[23:53] uh were I thought I thought very good that the projects that they that they
[23:58] highlighted were very similar to this.
[24:01] They all involved installing sheet pile in in locations a lot of locations with
[24:07] with water river banks and and boat launches and and these kind of
[24:12] situations and and one of the one of the project managers that I spoke
[24:16] to from I think it was the Santa Clara Santa Clara
[24:19] water district said that they
[24:23] um that they were also in very close
[24:25] proximity to homes and that they uh you know they performed everything
[24:30] that they needed to with you know vibration monitoring and and that kind
[24:33] of equipment so they they're definitely familiar with with this this type of
[24:38] work. They were they were nearby projects here in the area in Northern
[24:42] California. >> Yes yes yeah.
[24:49] Yeah. Right well so okay
[24:56] where did I where was I? um >> [clears throat]
[25:00] » Addenda yeah okay. So
[25:05] The addenda were were required to be acknowledged and and one contractor
[25:09] didn't as we know um
[25:13] Is there and I understand that the strict nature
[25:16] of the bid process
[25:18] uh
[25:22] We're not obligated to take anything just just thing you guys have to get
[25:25] right? Correct. >> Right we can say cuz you're
[25:28] you're above what our expected cost will be we're not obligated to take anything
[25:31] on >> Yes. Yeah. Um it's still subject to city
[25:34] approval but you I mean there's there's there's a
[25:37] number of line items you know you know 10 12 and 15 for example where
[25:43] they are higher than everybody else. Uh and I know that just the it's the
[25:48] discrepancies that you guys have the uniqueness of that individual
[25:51] contracting approach and their their sensitivity to that particular line item
[25:55] I can imagine. But you can't go back to them and say you know we'd like to we'd
[25:58] like these three items to be reconsidered or looked at is does does
[26:02] this municipal process allow for that or not?
[26:05] No um yeah unfortunately not because of the
[26:09] because of the RFP process um you know everybody
[26:14] uh everybody provide you know has the same uses the same parameters for their
[26:19] for their costing and and the the final price
[26:23] um can't be changed before the before the
[26:26] contract is awarded. After the contract is awarded
[26:30] then there can be some negotiation with with the contractor. The contractor is
[26:35] awarded at that price but change orders can
[26:39] be generated by the city that change the
[26:43] scope of work. So that's often in negotiation.
[26:47] » be I mean I'm just saying cuz we have to separate decision by the city as to
[26:51] appropriate more money for this right. So that's not insignificant. um
[26:56] uh ask so it would be against this process and perhaps municipal law I
[27:02] don't know that you can't go to them and say you
[27:06] were the low bidder after we excluded one you know full
[27:10] transparency you're the low bidder but you're still above our budget we
[27:13] can't award the contract unless you were to reconsider these three line items
[27:16] which you're you're you're 10% above the competitors. Would you consider to do
[27:20] so? That's not you can't do that? We do you Yes so
[27:26] and and just so you know that we have discussed
[27:29] that angle because in a public contract
[27:32] that's kind of where you go next. You look to VE or value engineer some of
[27:37] your items and where you do not take away or
[27:42] we don't want to adjust and or go back to the design team to say we need to
[27:49] change the how we go about getting you know this design completed. It is maybe
[27:55] a reduction of overall footage and we can't you know there's a very good
[28:00] chance that the contractor is going to be willing to negotiate cuz they want
[28:03] this project that's for certain. But if you
[28:05] by your process you award the contract at this price what reason do they have
[28:09] to negotiate It's not as easy as looking why are you well you're $80,000 more
[28:14] than the competitor so why can't you do it for their cost? Because there are so
[28:17] many different moving mechanics we don't know what the other contractor may or
[28:22] may not have had or if they underbid that.
[28:24] But at this point with them we don't care.
[28:27] Realistically we don't care. I mean if if if if we're if we're now one to one
[28:30] with these folks and we want to award it then we don't do
[28:33] it. I I get where you're going with this. I
[28:35] I'm just I'm just saying that. We haven't added obstacle here that
[28:39] we've got to get this money from this from the city and ultimately from our
[28:41] residents. And that's not a
[28:46] you know something the city council is going to
[28:48] love to be vote on and be comfortable with and the the way you propose to do
[28:52] it is to put up other projects. You know other lanes other maintenance
[28:56] projects other other capital improvements
[28:58] or finding it in the this this this broader budget whether it's contingency
[29:01] or things like this which probably possible but
[29:05] depending on what you find out there. Yeah
[29:08] yeah no for sure. 300,000 for Belvedere's is is a big
[29:11] » Well let's let's let's shelve that aspect over for now cuz if and when we
[29:14] go there there's other things to talk about certainly. Um
[29:17] I would just say that it's a it's a competitive public bidding process and
[29:22] so you've provided all the parameters in the contract documents and these
[29:25] contractors have put their best foot forward so to speak. This is this is
[29:29] what they're proposing to do and I would say you're not really one to one with
[29:33] anybody until the contract is awarded. But they also know your estimate going
[29:38] in. I mean it's it's it's not it's not a
[29:41] it's a coming from the private you know construction world that's just lunacy
[29:45] lunacy to me. But
[29:47] Well I get it. If you if you if you're attempting to negotiate with one
[29:51] contractor before awarding a contract, all the other ones say, "Well, how come
[29:54] you didn't come to us? We We could We could do it, too." And it just, you
[29:58] know, it could sort of unravel the whole process. I get it. I get it.
[30:02] Yeah, and I I mean, to your point, you lose all your leverage if if you've
[30:06] already signed a contract with them. Um but I think I mean, in my in my
[30:10] experience, and and maybe you you guys can chime in on this, um
[30:15] you know, contractors are generally uh willing to talk. You know, they they're
[30:21] um that
[30:23] if you say, you know, "By the way, you know, we We've got everything signed,
[30:26] but um
[30:28] this is this uh you know, finances are very tight for us, and we would like to
[30:32] find ways to to reduce the costs. Um we we may want to reduce the scope
[30:37] somewhere. Um but we did notice in your in your uh bid
[30:41] that you know, these were much higher than than other people's, and Okay. are
[30:45] you able to, you know, you know, share with us what the you Cuz we can always
[30:49] say to them, "So, we're not going to either uh
[30:52] Ball, you reduce by this amount. And and we'll award it to you, otherwise we will
[30:56] award it to nobody, and we will we will we won't go forward, and we'll do
[31:00] another RFP, and we'll just we'll rebid the whole thing, and let let
[31:03] them it's a little bit of a Put that on the table then. If they say
[31:08] they won't, then we just put the RFP out again, and start the process again. I
[31:11] don't think you can Well, well, I don't think you can do that. Well, why not?
[31:14] Why Why What What Well, look, it's public I mean, I'm not a I'm not a I'm
[31:17] not a contractor. It changes the scope. It changes the scope. I mean, obviously,
[31:20] or the timing. No, no, because because basically, if if if if if we choose not
[31:24] to do this now, realistically at this point in time, even with the same scope
[31:27] in a rebid process, or modify this slightly, we missed the '26 window.
[31:31] Right. If you miss the '26 window, it's not going to get any less expensive
[31:35] knowing, you know, that >> that, for sure. And the re so the the
[31:38] re-solicitation process, what we've done is certainly has a a cost that isn't
[31:43] going to necessarily, you know, be able to be recouped as well in a lot of the
[31:47] public, you know, process has, you know, there's has to be, you know, completed
[31:51] again. But but if we don't have the money Yeah, no, I I they might say,
[31:54] "Okay, well, we'll we'll help you with that." So, I mean
[31:58] they might say, "Okay." And that's why I know that, you know,
[32:01] again, internally within you know, with James, I'll try to remember who else was
[32:05] on that call, but Stetson, we talked about at least areas identified that we
[32:10] can discuss, um and it was confident We don't have specifics, you know, but
[32:14] there were certainly some areas uh to look at that we started to discuss. You
[32:18] know, one of them would be, you know, just uh
[32:21] essentially I I think again, though in accordance
[32:25] with the public contracting, you you can't begin these negotiations until
[32:29] after a contract is awarded to to one of these. And so, I think that's probably
[32:34] what the city is looking at. You You either have to make the decision to
[32:36] award a contract Could we go to all of them and say, "This is This is our
[32:40] budget. Would you like to Uh I think that that that sort of involves
[32:44] reopening up the bidding process. I don't I can't I think once it's closed,
[32:48] you can't reopen it. You would be looking at a rebid.
[32:51] The issue with the timing is that there's an in-water work window, June
[32:55] through October. And so, to start the process over means
[32:59] we wouldn't have enough time to issue a rebid, open it all up, and receive bids
[33:04] in order to construct this year. So, re-bidding the project does mean you're
[33:08] you're you're looking at next year, 2027.
[33:14] Let's be realistic. Um
[33:17] how confident are we that with the ability to start this project?
[33:21] First question. Second question is um what I would be afraid would happen
[33:26] is that there would be a delay, there would be a uh uh
[33:29] a backlog of this particular equipment or something like that, and the
[33:31] contractor gets started under this price, and says we have to finish it
[33:34] next year, and here's the here's the cost to do so.
[33:38] Well, I think they would be under contract to um
[33:41] uh you know, to to complete it by October uh 15th, I think is what the
[33:45] contract says. But just like but just like finding a a a you know, Right.
[33:49] immovable boulder under the ground, there's a there's a there's a delay with
[33:52] Blue Hill Stetson. I apologize. Blue Iron. Blue Iron. That That can't deliver
[33:56] it. It's out of their control, and they're they're they're delayed a month,
[33:59] and they and they That's I don't for I mean, anything's possible, but I'm um
[34:03] they're they're they have agreed to perform this project by a certain date,
[34:08] and if not, there are liquidated damages daily that occur if they are not
[34:13] complete by that time frame. Do we Do we think we'll get this done in
[34:17] this time frame? I mean, can it be They need to go, yeah.
[34:20] Permit I mean, we're you know, there's Um there are there are a few factors um
[34:25] that that are outstanding. Um Yeah. What Like what? So, first of all,
[34:31] uh permitting. Uh we're waiting for a BCDC permit. Um
[34:35] and they are in a review sort of stage. Um they have a commission meeting where
[34:41] it needs to be approved. Um and which I believe it is April 29th, I think, 19th
[34:48] or 29th, so it can only be after that. Um
[34:52] uh PG&E need to complete some uh some work in on Beach Road to modify their uh
[35:00] their lines, their um utility lines, main lines through there.
[35:04] » Before we get going. Yes. Yeah. Given what we've heard from
[35:07] PG&E, is that is that likely? Uh they uh we we ask them We We meet
[35:13] with them about every 2 weeks uh to get progress and and update uh
[35:17] updates from them. Um they
[35:21] assure us that um that that it's that it's
[35:25] doable to do before before June. Um but we have no control over that or or
[35:31] over their their work. So, if these dependencies um if if Gordon and
[35:36] Company, Gordon Ball, can't get started to comfortably make the window
[35:41] this contract's void then, right? We're not, you know, cuz obviously, the prices
[35:44] probably wouldn't be held for the next year.
[35:47] Well, I think there's probably room to negotiate, and and if they would like to
[35:51] keep the contract for next year um you know, they may they may be some uh some
[35:57] way to um you know, to
[36:00] to keep them on board um with some kind of uh
[36:04] you know, adjustment in price, you know, related to inflation or something. There
[36:09] There is some flexibility built into the way this is structured. There's a
[36:12] There's a The in-water work window is a 5-month period, June through October,
[36:16] but the actual construction period is only 65 days. And so, even if they don't
[36:21] necessarily have to start on June 1st, I mean, that can slide backwards, and
[36:25] there would there would still be room for them to complete this project. And
[36:28] in theory, the the out-of-water work can continue outside that window. That's
[36:31] correct. It is. Yeah. Yeah. Um
[36:35] And so, you know, that's that's the reason we did try to put this
[36:38] out to bid early, to get the bids early, to have a contractor under contract
[36:42] early so that these these scheduling and um
[36:47] the the coordination between the city, Hadley, PG&E, this can all kind of be
[36:52] worked out over the next several months until June, and when when the
[36:55] construction would actually occur. Mhm. >> [clears throat]
[37:00] » Yeah. Um The other The other factor is uh
[37:04] easements with uh temporary construction easements with the property owners on on
[37:08] Beach Road, because uh the work that would need to take place
[37:12] on their property um for this project to to go ahead. I mean, the seawall
[37:16] actually enters their property at uh you know,
[37:20] at at their property lines. Um so, it's a couple of feet in from the
[37:24] property line, so the the work and the structures would would all be on their
[37:27] on their land. Um
[37:30] and we've met we've met with them um a few times, uh described the project,
[37:35] and we've sent over the uh the easement agreements. Um
[37:40] So, at this point, we're waiting for them to
[37:42] um review those. Uh
[37:46] And we're we're ready to go for the for the April meeting for them uh to to have
[37:51] those easements um approved by City Council. Um
[37:55] And yeah, but but we do have to wait for their their signatures, basically, on
[37:58] their side. How many property owners are we talking
[38:01] about again? Uh three property owners. Um Yeah. Um
[38:05] And one of them has indicated that um he's is absolutely willing. Um he's just
[38:12] out of the country right now. Um so, he's uh seems seems like he's ready to
[38:18] sign as soon as he gets back. Uh the other two
[38:21] uh are new uh new owners of of the property. And um
[38:26] I think it seems like they're wanting to review the the language more carefully,
[38:30] and um Was it a It's three properties, but two owners,
[38:34] right? Cuz there's Yeah. Yes.
[38:37] » Hadley owns one building, and the Spruce Group owns the other two. Yes, yeah. And
[38:41] those other two are are owned, I think, on paper by two different LLCs, but it's
[38:45] the same people. Okay, so that's okay. Yeah.
[38:49] Yeah. So, from a financial perspective, I'm
[38:53] looking at this overall project budget relative to
[38:56] appropriations funding at the top. Um we're looking at that 3.475
[39:02] line of which includes two $280,000 or so,
[39:08] that's going to a separate contractor to do the utility work.
[39:13] Right? So, that's where we get the 300 So, that the the we have a $315,000
[39:17] variance on that line if we take this this this bid from Gordon and Ball,
[39:21] right? Uh yeah, it's it's
[39:26] uh without knowing it, we don't have the exact number for the contracts uh of the
[39:30] other amounts. I would assume the 279 that the way you got your 315 was the
[39:34] 279 um plus the 35 over
[39:39] this number. Correct, yeah. With a with a little bit of Yeah, yeah. flexibility
[39:43] to in case that 279 is over. >> So, I'm just writing 315 in parentheses
[39:47] next to the 3475, which means Right. on this page we're 315 over budget on that
[39:53] particular line. And you've discussed this with Helga and her and
[39:58] your recommendations with Robert as well is to handle this either within this
[40:04] $4.6 million total project expenditures
[40:08] budget, finding it somewhere, whether it's coming out of your hide
[40:13] I mean from a project manager perspective or somewhere along this line
[40:15] of our mass remediation, somewhere somewhere through here you think you
[40:19] might be able to find some money. That that's option one, right?
[40:23] Just confirming that's what that means. >> Yeah. And option two is in the broader
[40:27] public works budget. Um capital improvement projects, whether
[40:30] it's paving or whether it's a retaining wall or whether it's a lane improvement
[40:34] or something like that, finding that money in that over the next couple
[40:37] years. Yeah, and and and there are two components to that,
[40:40] too. So, there are existing CIP funds that
[40:45] that that overlap with
[40:48] with with some of the work in this project. So, paving for example, there's
[40:52] a we have a we have a CIP fund for paving.
[40:55] And that that could cover the cost of the the paving restoration
[41:00] in instead of using this this account for that for for those
[41:04] costs. >> Use that account.
[41:06] » Yeah, exactly. I get it. Um
[41:12] Yeah, exactly. And the sidewalk, yeah, exactly.
[41:14] And and we have it in we have not embedded the contingency on this budget.
[41:20] Um Well, with that
[41:24] so so with that over
[41:29] I'm just saying on paper on paper right now we're talking about that one line
[41:32] item having a a negative variance.
[41:35] But that 383 arguably still exists if we if we know we have 4.6 in our in our in
[41:43] our fund at this point. >> Yes, right. Yes. So, so yeah,
[41:46] sorry I I I took me a minute there, but yeah,
[41:49] basically that would restore that that contingency amount.
[41:52] » Yeah, yeah, absolutely. So,
[41:55] however we decide, you may want to work with Helga. I would
[41:58] suggest if this is to be recommended to the city council, I wouldn't go in with
[42:02] this to $315,000 over tier. I would I would I would front it by
[42:07] saying exactly what you've talked about before, that we're going to approach
[42:10] this if we award this contract with diligent approach to value engineer to
[42:16] to line item look at things to to recognize this is over budget and see
[42:20] where we can get some some some potential savings out of this contract.
[42:24] May yield nothing, but but that's an approach and we certainly should do
[42:26] that. I would also try to identify specifically where you think this money
[42:30] can come from. Meaning if you if you if you have known expenditures that you
[42:35] think are going to be less than what you have up here anyway,
[42:38] for example, if you know that you know, the
[42:42] the environmental mitigation costs are not
[42:45] $100,000, but they're going to be $80,000 much like we had with the repair
[42:48] over there on Beach Road. You know, you that came in less than we thought we
[42:52] were going to commit. So, I'm not saying we take that money, but I'm saying if
[42:55] you know already where we are, I identify it. You could you could
[42:59] probably say of that we know we've got $35,000 in
[43:05] city planning paving sorry, sidewalks for the next 2026 2027 we have
[43:12] $45,000 in in road paving for the 2026 and 2027 budget that we can apply to
[43:18] this. And our assessment is that that won't
[43:21] damage our overall value of our infrastructure around the
[43:26] city. So, we can apply that those small amounts of those larger budgets. We can
[43:29] also apply $200,000 of contingency to that and
[43:33] that's where we think we can make up this money and still and still retain
[43:36] the 4.630. Right.
[43:38] » Yeah, exactly. You need to present it in a fashion like that. Right. Yeah, and
[43:41] that's that's that is definitely what's what we had planned was you know, be
[43:46] able to be specific about you know, about how you know, how this is
[43:50] possible. And and there would be council approval
[43:55] for for some of those changes as well. Well, they'll have
[43:58] comments and they'll and they'll probably stress you know, we really want
[44:01] you to push the value engineering and and really you know, sharpen your pencil
[44:05] on the scope, you know, once you have the contract selected to keep within the
[44:08] the appropriate public bidding process so that we can make sure we we make this
[44:12] project as as tight and and not only timely, but also it does our our our
[44:17] base minimum needs for the for the for the for the money we're spending so we
[44:20] get as much value as we possibly can. Right. Yeah. Yeah.
[44:23] Yeah, I yeah, I I hear you and I think um
[44:28] I we all feel that way. We definitely I know I I you know, and and and I
[44:32] definitely know Robert does and everybody does.
[44:36] Yeah, I mean it's it's um it's we we all want a want a project that's
[44:41] delivered on time and under budget. You know, some of this this
[44:47] law that we have to comply with
[44:50] is is a little cumbersome and frustrating,
[44:54] but you know, from from the time that we start meeting with the with the
[44:59] contractor, there will definitely be you know, a lot
[45:02] of emphasis on on um keeping costs you know, within budget.
[45:08] Um and if I mean you know, I I to be fair, I think I think the
[45:13] contractors probably get that from from everybody that they all the cities that
[45:16] they work with. Um But yeah, and I mean you know, some of the costs, you know,
[45:21] and I can I can point to some in on here that's um
[45:24] we anticipate not not having to pay for example,
[45:29] environmental mitigation costs. BCDC
[45:33] uh may ask us to you know, mitigate for
[45:37] much more than than we are already. Um but it seems like they're not
[45:43] um in in our discussions with them so far,
[45:45] they haven't said that they that they will that they will and they've accepted
[45:49] our submission with with the mitigation that
[45:52] we've proposed. Um So, uh you know, for example there, there's
[45:56] potential for that full 100,000 to be available to be to be moved into another
[46:01] sort of road. Um Yeah. Um
[46:06] Yeah, and then you know, land surveying and mapping for
[46:09] example, that's another item that's we haven't we haven't had to Yeah, I you
[46:14] know, I I I Yeah. You understand me. Just as you prepare it, sharpen your
[46:19] pencil in because you you know, come in solution oriented to the council.
[46:23] » Right. Right. Yeah. Yeah, okay. Yeah, appreciate that.
[46:31] Are you guys probably I mean you've sat down with them. You've you've
[46:35] you've you've met with them. Are you comfortable with them being a partner in
[46:39] in if not that it it doesn't sound like it's a big job for them, but it's a big
[46:42] job for us. >> Yeah, no, we haven't actually met with
[46:44] them. Yeah, we we wanted to but you know, I
[46:47] actually I I spoke to Gordon Ball yesterday on the phone. Um
[46:54] And um but we had wanted to have this
[46:59] meeting before we you know, provided any kind of official
[47:03] communication to especially well, to the other contractors. Um and it's obviously
[47:08] not going to be an easy phone call with Marcus, but um
[47:12] yeah, that's So, Peter, I mean so if we make a recommendation, we're
[47:17] making a recommendation knowing it's higher than the budget, although with
[47:20] your mitigating recommendations, it may be lower, but it
[47:24] sounds like it's it's worth discussing among the city council anyway. I mean
[47:27] it's it's not so far out there. >> Absolutely. It's
[47:30] it's achievable potentially. Well, I mean
[47:33] I mean I'm sure maybe Glenn you less so than us, but we're
[47:36] we're just all reacting to that like public process is you know, I wouldn't
[47:40] bid my house with that process. You know,
[47:42] and it's just a it's just a just a it's sort of frustrating, but um
[47:47] I think you need to present it that you know, this is the process and and it's
[47:51] not it's not unusual to have our estimate be be a little bit short of the
[47:54] of of the in fact, the dynamic of the of the process to to to almost have that be
[48:00] the the norm. But there is an opportunity
[48:04] and I and I do believe it's worth the time because because we have a lot to do
[48:07] between BCDC, PG&E and the easements um which would at the end of the day if
[48:12] those if those don't come through, you know, this project's not going to go
[48:15] ahead anyway. So, work aggressively with with the selected contractor to and it's
[48:21] not like we have much of a choice. We have to choose
[48:23] the non-eliminated low low bid, right? Right. Yeah, and and I think
[48:29] if if we're choosing if we're choosing any, yeah.
[48:31] Right, yeah, exactly. And and I I think that you know, if if if there was
[48:35] another close bid for example, and and you know, there was a way to parse
[48:39] through the qualifications, um then then we might be having a different
[48:44] conversation, but I think you know, we have one apparently bidder. The the next
[48:48] one is you know, 500,000. I mean you know, higher. I
[48:52] touched on this last meeting, too, and I know this will come up in the city
[48:54] council is and it's hard it's hard to weigh this
[48:59] against known risk failure there, but is this is this something that you know, in
[49:04] a year or two might be might be better pricing?
[49:07] I'm not saying non-inflationary pricing, but just better pricing relative to the
[49:11] war, the supply chain issues, steel prices, gas petroleum prices. Good good
[49:15] question. And currently so far, we actually
[49:19] do a lot of supply chain analysis for our projects nationwide.
[49:23] So, right now I do know that most of the sheet pile is coming from US. So, no
[49:31] tariffs. So, that has not been impacted. Currently, the price of oil has not
[49:37] impacted the sheet pile pricing. And that was something that, you know, once
[49:42] we started to see what was happening in around and that's typically one of the
[49:45] first triggers is the price of oil will just start to impact everything for
[49:49] production and specifically sheet pile. So, at this
[49:54] point we don't foresee any changes and we're that close that it
[49:59] would be not a major escalation. We may have more impacts if we push the project
[50:04] and you know, without
[50:07] you know, we're talking, you know, two years down the road we're probably Even
[50:12] these folks these folks gave these bids, you know, these orders are good. The
[50:16] price associations have been two or three weeks, right? Two three and a half
[50:18] weeks. Um
[50:20] would it could or would they come back and say there's a 10% premium based on
[50:24] recent events? They I do know that there there is a
[50:28] level of like they are entitled to that, but I don't know the specifics
[50:32] personally to what that is. >> They could do that. They could come back
[50:34] with a I'm not sure to the specifics. So, it all depends on I think on the
[50:38] specifics of the contract. I'm just not fully aware they are, you know, entitled
[50:43] to that. >> [clears throat]
[50:45] » All the good scenario I mean as far as whether the contract
[50:49] Yeah, yeah, two or three two or three as as as they go lower their price they
[50:52] can ask us to raise the price. No, this is what the contract would be. Yeah.
[50:57] And that's yeah, they're they're hanging their hat on that and knowing that okay,
[51:00] well, you know, we have to we get a word once, you know, supposed
[51:04] to that we you know, move specifically on the sheets that would be the big
[51:07] thing. So, I mean if it's if it's if it's
[51:11] legitimately now a cost of theirs big it's
[51:14] choose not to take the contract, right? Or the or are they obligated to take
[51:17] this contract? Well, they're I think yeah, they have
[51:21] you Julian can speak to this as well. Again, are they obligated or that's
[51:23] where they're yeah, that's where we have a bond. Mhm. A bid bond.
[51:29] Yeah. >> [clears throat]
[51:32] » Well, so this committee we were going to make a recommendation. It sounds like
[51:36] the staff's recommendation is to to recommend city council to accept the bid
[51:41] of Gordon Ball.
[51:43] Um are we ready to decide on that with the committee? I don't know how we what
[51:48] do we further questions or discussion? I would I would
[51:54] edit that a bit in the sense that it's not this committee's decision to go
[51:59] ahead with the project. Right? From a from a broader risk
[52:02] perspective from a broader financing perspective and from a broader um
[52:06] operations perspective. But in in the event the council is clearly said to us
[52:09] at a retreat hence the formation of this committee is um
[52:14] we want this project to go forward. It should it go forward we want you to do
[52:18] the proper due diligence and proper transparency to make sure that it's done
[52:21] in a fair equitable manner and that you're getting as much value for the
[52:24] process as possible. I think we should that's what we should
[52:26] say is that given the process and given the understanding of the project and the
[52:29] scope, this is the best contract for the job
[52:32] and given the conditions that we talked about a second ago that you're going to
[52:35] post awarding of the contract value engineer and look for look look for
[52:39] potential values in the scope itself and um
[52:42] here are ways we can potentially mitigate the cost in the existing
[52:45] budgets or other budgets. Um that's the recommendation to choose Gordon Ball.
[52:51] What is it the >> Yeah, I think it should be yeah. We're
[52:53] not saying the project should go ahead with this. Ultimately,
[52:56] you know, five people up there with public comment are going to decide
[52:59] whether this is this this, you know, $4.6 million is something the city sees
[53:03] a priority for the next, you know, year and a half to
[53:06] to mitigate this risk. Yeah. Yeah. Um so it sounds like it it's um
[53:13] on the understanding that there will be you know, aggressive um
[53:18] uh what
[53:22] I don't want to say reduction in cost I mean, you know, you know the people up
[53:27] there myself and and what I mean they're going to say, you know, find a
[53:31] place, you know, figure out the 315, right? You know, we'd rather not have
[53:34] that. We'd rather we'd rather you, you know, get it out of the get it out of
[53:38] the project one way or the other, you know, either sharpen your pencil from a
[53:40] scope perspective, value engineer it or if you have to do exactly what what what
[53:45] you guys talked about is is, you know, take a portion that that's responsible
[53:49] of a paving and a sidewalk budget or other public works budgets and apply it
[53:53] to this recognizing that you're you're you're you're stealing from Peter to pay
[53:56] Paul, but but be confident that you're you're doing that in a in a in a in a
[54:01] balanced way that you're not jeopardizing Paul in that scenario.
[54:05] They're going to want to see that information. Right. Yeah. Yeah.
[54:09] And and just just be confident that you thought about it so that if you're not
[54:12] able to lower the price that we're not we don't have a, you
[54:15] know, day one $315,000 hit to this budget. You don't want to go
[54:19] through a project day one with that kind of, you know, budget deficit.
[54:23] » for sure. Um
[54:25] Yeah, absolutely. I mean, I I >> help you with the staff report too. I
[54:28] mean, like I'm don't stress about that. Between Robert, you and me and Helga we
[54:31] can figure out how to Yeah. write that up. Yeah, that that
[54:35] I really appreciate that. Um Yeah, and and I think I think part of
[54:40] the um
[54:42] you know, one of the questions that that we'd have for you is is uh whether you
[54:45] think, you know, where would be a more appropriate um place to to look for um
[54:51] savings uh and yeah, so you know, see our existing CIP funds
[54:56] versus scope of the projects and um yeah, these kind of Well, that's kind of
[55:00] a contract. I mean, I mean, yes the the city can start with, you know,
[55:06] what what what what um parks and lanes what what what broader
[55:10] public works infrastructure are you doing that one you don't think you're
[55:13] going to get to. Every year we don't get to projects, right? That happens all the
[55:16] time. So so so so figure out which are the ones we don't
[55:20] think we're going to get to and roll that into '27 '28 or '26 '27 or
[55:25] even '26 '27 '27 '28 and that's that's a that's appropriate that potentially
[55:30] could be used um for this recognizing you're just kicking a can down the road.
[55:34] It's not a savings, but but it's a new public works budget next
[55:38] year. Right. Yeah, exactly. And and if through your personal or a professional
[55:43] assessment that
[55:45] project can be deferred for that amount of time. I mean, that's got to be part
[55:49] of it as well. Yes, exactly. And I think I actually
[55:52] didn't get to that part of when I was talking about the CIPs and the and the
[55:55] paving um yeah, the It's got to be based on some assessment
[55:59] Well, exactly. Yeah, I mean, because there are as you say
[56:02] projects that roll over every year and there are also, you know, sort of
[56:07] forecast funds for for for different projects that you
[56:12] know, won't be used for one reason or another and and can be pushed off to the
[56:16] following year. Yeah. And we'll just see if there are any I
[56:19] see Patrick has joined. If there are comments from Patrick or any I don't
[56:22] know if there are any other Robert or Rob or Glenn or anyone else who might
[56:26] not have a chance to speak about this and
[56:30] Robert, Patrick, Glenn, any
[56:35] Hey, >> [clears throat]
[56:36] » I can go ahead and comment. I've just been listening to this
[56:40] well, to the whole conversation, but on this last part we we did actually meet
[56:44] Tony, myself and Helga and take a look at our 20 our current budget in terms of
[56:49] rollover and then what we're looking at for next year in terms of projects that
[56:53] have funds assigned, but not necessarily a project earmarked for those funds. So,
[56:58] I think there um you know, to Peter and and Tony to your point there is enough
[57:02] flexibility in the next, you know, this current year and next year
[57:06] we need to we we can find a way to pay for this 315. Um but but the broader
[57:10] point is let's let's work really hard and try and bring the cost down, which
[57:14] is of course what we'll present to city council.
[57:21] Yeah, and so and this is just Robbie, you've
[57:25] just reminded me of another thing that's um
[57:28] we would like to emphasize is that we have no plans to request more funds from
[57:34] from reserves uh from general fund or critical
[57:37] infrastructure reserves. Um the you know, all the all the cost
[57:41] savings would come from existing and forecast funds and from the projects
[57:46] itself. Yeah.
[57:49] That's a bit that's that's sort of splitting hairs because it's
[57:53] Well, it's just going to be it really comes
[57:55] from the city >> all all the same funds. So, it's a
[57:57] matter of Right. >> whether it's
[58:00] in an existing appropriation or not. Right. Yeah, yeah, no, absolutely. We
[58:05] can't print money. So, it's it's at the end of the day it's coming from
[58:08] something or we're not doing something. Oh, yeah, exactly. We're putting
[58:12] deferring something or yeah. But I I I think Robert said it exactly right and
[58:17] Yeah. we can we can endeavor to to make that presentation and I'll and I'll
[58:20] certainly be part of that and help explain it to
[58:23] the council as we go forward. Yeah, well, thank you. Yeah.
[58:27] Okay, well, there's no further discussion. It seems like we should try
[58:31] and bring our our committee's recommendation to our to a vote and
[58:35] I think the movement is that the sub committee
[58:39] will vote to um
[58:42] I guess that the vote along with the the staff
[58:46] has made the proper recommendation to the city council subject to the
[58:51] adjustments and sort of financing and payment. Um
[58:57] and I I I guess we're not quite endorsing that the the committee should
[59:00] do this, but the committee supports the staff's recommendation. I think you said
[59:03] it exactly right that that that we we support the recommendation of the of the
[59:07] city staff that Gordon Ball is the is is the contractor
[59:11] to select and that um
[59:14] uh we encourage the the staff in the presentation to city council to to focus
[59:18] on you know, value engineering and and and
[59:21] scope considerations and then identify where the
[59:25] surplus $315,000 can come from within existing budgets.
[59:30] I was um [clears throat] may I move into the vote on that?
[59:34] Uh second that. I can second that. And all all in favor,
[59:38] I I think it's just the three of us
[59:42] Well, thank you. Yeah, and hopefully the the speaker caught all of the
[59:46] caught all of the language in there. It's much better than the last one, I
[59:49] know that. Um so, the microphone of the speaker,
[59:52] yeah. And so, this may be the final time we'll
[59:55] have to meet, I guess maybe subject to Yeah, I don't know.
[59:59] Robert, remind me, do we think it makes sense to because because there's still
[1:00:05] as you mentioned between BCDC, Genie, and the
[1:00:08] easements and the ultimate, you know, issues of permits and getting going. Uh
[1:00:14] and and after all, this committee is designed to be the eyes and ears of
[1:00:19] the community just just just just to understand and, you know, either
[1:00:22] anecdotally or or publicly make a comment that, you know, we've been aware
[1:00:25] of what's going on. I'd suggest another in, you know,
[1:00:29] if not one or two month at monthly intervals, just to check in where you
[1:00:32] are in this process um so that the next month you presumably
[1:00:36] would have received city council approval, you presumably would have
[1:00:39] engaged in a contract with Gordon Ball, and have those initial discussions, and
[1:00:43] have a tentative timeline for the project. That would be So, in about a
[1:00:47] month's time from now That's what I think unless you think that's that's too
[1:00:50] soon. Um
[1:00:52] No, I think I think there would be uh quite a few there'd be a few updates in
[1:00:58] a month's time. Um and we can possibly, you know, change the date if
[1:01:03] if we need to if we're waiting on for some, you know, some
[1:01:06] um decision or something. Robert, that's not surpassing the the the um
[1:01:12] charter or design of this subcommittee? No, the the subcommittee is ad hoc. We
[1:01:18] can't exist forever. Um but if we have a clear ending point which may align
[1:01:23] you know, with the duration of the project and maybe at the close out uh
[1:01:27] we'll have a final report that goes back to council. I think that's still the
[1:01:31] scope. Yeah, I would agree. I think it'd be good to meet in another month.
[1:01:35] And actually maybe throughout the until the project is completed I absolutely We
[1:01:38] discussed even having maybe one committee member available for whether
[1:01:42] it be every construction meeting, but at least it's certainly up to speed whether
[1:01:47] it's even also a follow-up after our construction meeting with the
[1:01:51] contractor. I'm under the impression we'll be doing those weekly. Could be a
[1:01:54] bi-weekly check-in or something of that nature, but I think that it's very
[1:01:58] important to keep you guys in the loop throughout the process, too. You know,
[1:02:02] we'll also have the have the contract happening,
[1:02:05] it sounds like. So, you'll you'll bring this to council in April?
[1:02:08] Yes. Yeah, that is the plan. Okay. Yeah. Um
[1:02:14] Yeah, so April 13th um and
[1:02:18] yeah, unfortunately, I'm going to be out of town for a couple of weeks here, but
[1:02:21] I have the the draft staff report and um you know, uh I think the finance the
[1:02:29] fiscal impact section is is the part we need to um
[1:02:33] drill down into. Yeah. But uh
[1:02:37] yeah, that and hopefully the construction easements
[1:02:40] and maybe even a contract for the other portion of the work if that can all
[1:02:44] happen in in in April, uh that would be There's no bid
[1:02:49] requirement for that? Is that the bid threshold or something? They would
[1:02:52] typically be, yes, but there is in this case
[1:02:57] what's called a sole source justification
[1:03:00] for for this for this contract because they have specialized
[1:03:06] knowledge of that company. >> installed it.
[1:03:08] Yes, exactly. Yeah. Yeah.
[1:03:12] Yeah, and but that's, you know, these are all
[1:03:15] updates that can can come at the next meeting for sure. Yeah. Okay, so we'll
[1:03:19] plan on having a meeting probably late April after the city council meeting and
[1:03:23] after progress has been made. Um and then we'll see
[1:03:26] periodically after after that. Um would you like to pencil in a date now that we
[1:03:30] can uh
[1:03:32] or or uh Would you Yeah. prefer to to wait and
[1:03:38] have a a poll maybe further down the line? If we if we sort of have a a
[1:03:42] target date that we are, you know, can then confirm, I think um
[1:03:46] All right, for me that always seems to work work better.
[1:03:50] So, maybe the week of the 27th? Okay.
[1:03:55] I'm gone that whole week. Are you there the week of the 20th? I'm
[1:03:59] there the 20th.
[1:04:02] I I'm here the week of the 20th. When does city council act? Uh you said
[1:04:08] it was the 13th. 13th, yeah. So, that's great.
[1:04:12] So, that's a week after the city council meeting. But you might not have made
[1:04:15] much progress with the contract. Yeah, it might be a little soon. Might shoot
[1:04:18] for beginning of May, like the week of the 4th. Early May might be better. I'm
[1:04:21] away the week of the 4th, so I can do the Monday or Tuesday.
[1:04:26] And there's always, you know, we can there's no reason this for emailing
[1:04:29] communication Personally, I could I could join a Zoom call.
[1:04:32] » Or even a remote call if that's Yeah. Yeah, I know it works for you. I guess
[1:04:35] it would do we if we're not voting on things necessarily, we don't have to all
[1:04:39] be present, correct? And I don't know what the or can we not have
[1:04:42] a meeting? It's not a Brown Act, I don't believe. Right, Robert?
[1:04:47] That is correct. I don't believe this is a Brown Act. I don't believe
[1:04:50] So, I mean If this same group is meeting Sorry, sorry. If this same group is
[1:04:55] meeting meeting the you know, the the core group that we
[1:04:58] have here today, then it is a Brown Act meeting. If it's just one person
[1:05:02] assigned to meet with staff and what's not
[1:05:06] Well, I I guess our question, Robert, is if
[1:05:09] we couldn't do this as a complete remote meeting.
[1:05:15] Right, we need to have a quorum. Then then the majority a majority of the
[1:05:18] members have to be in person. It worked out today because only one
[1:05:22] person member of that sub of the subcommittee
[1:05:25] was was connected remotely. Do we want to shoot for say Wednesday
[1:05:30] the 6th and if John can't I did do it remotely, but
[1:05:34] I'm happy to do that remotely. Yeah, sure. Let's do that. Okay. Let's May the
[1:05:39] 6th.
[1:05:43] 2 2 p.m. Or sorry, 1 p.m. Yeah, if that time works for everyone.
[1:05:51] Keep it consistent, I guess.
[1:05:55] Okay. All right, I just need to raise one
[1:05:59] point. Yes, a design point. Yeah, uh go ahead.
[1:06:03] Yeah, that's okay. So, this is addressed to Stetson.
[1:06:07] Uh has to do with the height of the sheet piling.
[1:06:11] Larry's question to you apparently was misunderstood.
[1:06:15] He's asking why not maintain the level the
[1:06:20] » [clears throat] >> same as the existing sheet piling.
[1:06:25] Oh, the 2019 sheet piling, the top of it.
[1:06:28] Um >> Maintaining that height. It was It was
[1:06:32] primarily to save cost to to not have a higher sheets and more concrete backfill
[1:06:38] and any any fill you put along the wall um requires a mitigation from the
[1:06:45] jurisdiction. So, the wall where existing sheet piling
[1:06:49] is the new sheet piling. It's It's approximately a foot lower.
[1:06:55] You're cutting it off. You're cutting off longer pieces anyway.
[1:07:00] Maybe. I mean, it depends where they where they drive it to. Well,
[1:07:04] I could drive it in and drive it in those. These aren't being driven.
[1:07:09] These aren't being driven. Yeah, they're being pressed. There's no driving.
[1:07:13] There there will be a It's that We did We did We did design it so there's a
[1:07:17] It's a It's a It'll be a gradual transition, so it's not going to be a an
[1:07:21] abrupt, you know, 90° change. It's There is going to be a
[1:07:25] transition over over a period of a horizontal
[1:07:28] distance, so >> And and the 2019
[1:07:31] repair has one as well. There's a a little slope down to two different
[1:07:35] elevations. Um but to add
[1:07:38] Julian to the reason for keep reasons to keep it keep it down, one is the
[1:07:43] permitting because permitting agencies um
[1:07:47] were happy to see that if that's the the all
[1:07:52] the pile would be kept below the the height of
[1:07:55] where the sea sea lettuce reaches because that would be colonized much
[1:08:00] more quickly by sea lettuce and barnacles and so on. So, the lower the
[1:08:03] better for them as far as habitat goes.
[1:08:07] Um then also aesthetics. Um right now from from the the homes along there or
[1:08:13] from from the water um
[1:08:16] it's it's less visible the the lower down it is.
[1:08:19] Um so, that along with the embedding the
[1:08:23] uh the gravel into the top of the concrete along there um
[1:08:27] you know, sort of the the permitting and and somewhat for aesthetics. So, we're
[1:08:31] talking about a foot. About a foot, yes. Yeah. Yeah.
[1:08:36] Yeah, so I mean, and if you look at the the 2019 piles, there's a point on the
[1:08:40] piles where the barnacles stop. And then above that is just the the metal, you
[1:08:45] know. So, the idea here was that the this would be completely below that
[1:08:49] that level of you know, habitat. Is Is there Is there
[1:08:54] inherently a you know, for the people viewing it from
[1:08:57] the water side or from the homes out there? Obviously,
[1:09:01] um I mean, there is every every aesthetic
[1:09:03] appeal to having it consistent as as much as consistent as as possible. Um
[1:09:07] but you're saying there's there's there's no structural need for it cuz
[1:09:11] that the note we got today clearly said that the the the structural requirements
[1:09:16] are really down below as opposed to above. No structural need for it. My my
[1:09:19] biggest concern is is it would add additional mitigation measures and
[1:09:23] potentially hold up the BCDC permitting process. Um you guys need to sort of
[1:09:27] give us a thumbs up and thumbs down this. I mean I see Larry's point that it
[1:09:30] might look better if it was less It was all the same. jig jaggy.
[1:09:35] But not enough to delay or or the project or to have a cost consideration
[1:09:40] or have you know, permitting issues with you
[1:09:43] know, the lead agency there. Right. Yeah. Or even if we can do it from an
[1:09:47] environmental perspective whether whether ours are are
[1:09:51] review covered that scope. But then again, we did we're we're we're we're
[1:09:55] we're we're we're we're I'm leaning on the broader
[1:09:58] review, right? So that matter that should matter. The environmental review
[1:10:01] should matter, right? No, so that it wouldn't I don't think
[1:10:05] impact the EIR if it was you know, if if what you're talking about is is the 2019
[1:10:11] sheet piles cuz I think that's probably what was kind of envisioned as
[1:10:17] the sort of a comparable Yeah, exactly. Yeah, I don't know if Julian if you have
[1:10:21] any thoughts on that. Well, it would require going back to all the agencies.
[1:10:26] It would be it would be more fill in the jurisdictional waters. So we'd have to
[1:10:29] restart or you know, renegotiate with all the agencies and there would be a
[1:10:34] cost increase. Yeah.
[1:10:38] Any answer? >> If I could chime in here too, from from
[1:10:41] what we've talked about on this project from the beginning we we always
[1:10:45] envisioned I think this aesthetic improvement that we're talking about
[1:10:49] whether that be a cap or riprap or some other kind of concealment method
[1:10:53] for hiding that you know, the steel sheet piles and the concrete. That would
[1:10:57] always be coming as kind of a phase two. And it's just a matter of when we can
[1:11:01] get that done in terms of you know, perhaps the larger project or when funds
[1:11:05] are available. But you know, the structural [clears throat] component
[1:11:09] holding up the wall and you know, keeping the cost down low was always our
[1:11:13] primary target at least in the short term.
[1:11:17] Okay, I'll tell Larry. Thank you. Yeah, he raised it last month also. And
[1:11:22] I think Yeah. You should I don't know if Larry
[1:11:25] got that note you sent around today. Um Um I I think he uh
[1:11:30] with with the response from the state and I think he must have because I think
[1:11:33] that's what what you might be referring to then for the
[1:11:37] as far as the the misunderstanding. I think that's maybe what what he was
[1:11:41] referring He brought it up last week too last month too. So he he may or may not
[1:11:45] have it well. >> Right. Yeah, and I I mean I I
[1:11:49] misunderstood it too actually cuz I thought he was talking about having a
[1:11:53] higher up you know,
[1:11:55] to support the wall. I think he just wanted it to match what was there. Yeah,
[1:11:59] I understand. And yes. And so
[1:12:03] Okay, I think we can adjourn unless there's any further comments. Thank you
[1:12:06] so much. So many thanks. Thanks. Yeah, thank you all. Thank you all so much.
[1:12:11] Thanks Robert. >> Thanks Robert.
[1:12:16] What