Agenda
[1:14]
CALL TO ORDER
[1:24]
ROLL CALL
[1:27]
LAND ACKNOWLEDGEMENT
[1:57]
APPROVAL OF THE AGENDA
[2:13]
DECLARATIONS OF PECUNIARY INTEREST
[3:11]
ADOPTION OF MINUTES FROM PREVIOUS MEETING
[3:17]
July 27, 2026 - Regular
[3:37]
PUBLIC INPUT SESSION
[6:57]
PRESENTATIONS
[7:00]
Rogers Arena Project Update
[27:13]
BHP Elliot Lake - Quirke TMA Dams G1 and G2 Raise Project Update
[56:37]
DELEGATIONS
[56:40]
CONSENT AGENDA
[56:42]
INTRODUCTION AND CONSIDERATION OF CORPORATE REPORTS
[56:44]
Report from the Manager of Environmental Services
[1:03:08]
Report from the Manager of IT
[1:08:50]
Report from the Director of Public Works
[1:15:36]
Report from the Director of Recreation and Culture
[1:27:16]
Report from the Director of Finance & Treasurer
[1:34:46]
Memo from the Director of Finance & Treasurer
[1:40:01]
PRESENTATION OF COMMITTEE REPORTS
[1:40:04]
UNFINISHED BUSINESS
[1:40:07]
Report from the Museum Curator
[1:52:29]
NOTICE OF MOTION
[1:52:33]
GENERAL ANNOUNCEMENTS
[1:54:03]
ADDENDUM
[1:54:05]
INTRODUCTION AND CONSIDERATION OF BY-LAWS
[1:54:46]
By-Law 26-53
[1:55:07]
CLOSED SESSION
[2:14:39]
CONFIRMATORY BY-LAW
[2:14:44]
By-Law 26-54
[2:14:52]
ADJOURNMENT
Transcript
SOURCE TRANSCRIPT
This transcript is downloaded from the source you provided but we haven't reviewed it for accuracy. Treat it as a starting point, not a verbatim record. You can also request an AI-transcription of the audio file with the button to the left.
[1:16]
Good evening welcome to the regular meeting of the Council
[1:19]
of the Corporation of the City of Elliot Lake Monday,
[1:22]
August 24th 2026 at 7 p. m. Call to Order.
[1:28]
Roll call, all members are present. We would like to
[1:31]
begin by acknowledging that the land on which we are
[1:33]
gathered is in the traditional territories of the Anishinaab egg
[1:37]
of the Robinson here on Treaty, specifically the Serpent River,
[1:42]
Mississauga, and Sagamac First Nations. We save me Gwitsch to
[1:47]
thank Indigenous Peoples for taking care of this land from
[1:50]
time immemorial. We are all called to treat the sacred
[1:53]
land, its plants, animals, stories, and its peoples with honour
[1:59]
and respect. Approval of the agenda may have a motion
[2:04]
that the agenda be approved as presented. Mover. Councillor Saito,
[2:10]
second did councillor bull. All in favor. That's carried. Are
[2:17]
there any declarations of pecuniary interest. Councillor Bolt. Thank you,
[2:23]
your worship. I'd like to declare an indirect pecuniary interest
[2:27]
with regards to it in 11. 1, 11. 3, and
[2:32]
17. 1 as my daughter works for that corporation. Okay,
[2:40]
thank you. Are there any other conflicts. Councillor Man. Thank
[2:45]
you, worship. I'd like to declare under unfinished business, 13
[2:48]
- 1 reported from the Museum Coordinator regarding the letter
[2:53]
for the Monument installation indirect pecuniary interest as my employer
[2:59]
is supporting the installation financially. Okay, thank you. And are
[3:09]
there any further declarations. Going once. Twice. Adoption of the
[3:15]
minutes from previous meeting. May of a motion that the
[3:18]
following minutes be adopted July 27, 2026 regular meeting. A
[3:24]
mover. Councillor Morset, seconded councillor Flintoff. Are there any questions
[3:30]
or comments. Okay, all in favor. That's carried. Public input
[3:39]
session this evening, Mr. Mike Thomas would like to speak
[3:43]
to items 8. 1, 8. 2 and 11. 4. Welcome
[3:52]
Mr. Thomas. Thank you, Mr. Mayor, members of council and
[3:59]
members of staff. I'll go a little bit out of
[4:04]
order. If that's alright. Now start with 8. 2 years
[4:09]
ago, notification on council agenda that BHP had applied for
[4:17]
federal and provincial licences in the industrial waste management facility.
[4:21]
And I don't recall that information coming back to council.
[4:25]
In terms of how that ended up. And since they're
[4:29]
here tonight, I'd like to take the opportunity to ask
[4:32]
if they wouldn't mind sharing with us whether that covered
[4:35]
the entirety of their property and how many hectors or
[4:38]
acres that covers. And whether it is just the buildings
[4:42]
and facilities or whether it includes all the tailing ponds
[4:44]
as well. Thank you. Regardless to item 8. 1 and
[4:53]
11. 4. I was at the meeting where 11. 4
[4:58]
was discussed. And it's interesting that. Even though it's for
[5:04]
Parsons part, and I understand we did get some funding
[5:07]
for that. The issue of the retaining wall, I felt
[5:12]
it should really be combined with what we're hearing about
[5:16]
the Rogers Arena night. And since Mr. Perry is here.
[5:20]
And you'll probably want to hear about them both. That
[5:22]
might be a good idea. Because the retaining wall is
[5:27]
also germane to the south end of the arena. For
[5:32]
the stability of the soil and maybe of course the
[5:34]
back of the building. So I think those two issues
[5:37]
kind of go hand in hand. And then I'd be
[5:41]
remiss if I didn't bring up what I've discussed before
[5:44]
council several times. Is that we've heard that. We've got
[5:50]
the funding to satisfy the totality of the invoices that
[5:55]
we've received. But I haven't seen anything come before the
[6:01]
council or the community is to what happened to the
[6:04]
billings from the first contractor. And I don't want to
[6:07]
say his name. And I always get the letters wrong.
[6:10]
But I think it's ARD and WRD. That we had
[6:13]
the issues with. So it might be helpful. That if
[6:19]
we had the opportunity to have a review of those
[6:22]
invoices and make sure that there's no duplicates or overbuilding,
[6:28]
if there was a way, if we haven't paid all
[6:30]
of the first vendors invoices, that we could put a
[6:33]
moratorium on payment for 90 days until such time. Is
[6:38]
the director of finance and treasure could bring a report
[6:40]
back before this council or the next administration so that
[6:44]
we might look at cost recovery for that. And that
[6:47]
is the totality of my input. And I thank you
[6:49]
for your time. Okay, thank you Mr. Thomas.
[7:00]
Okay. Eight presentations. The first presentation is the Rogers Arena
[7:05]
Project Update. Chris Perry from Perry and Perry Architects. Welcome
[7:13]
back, Mr. Perry. Is that okay?
[7:23]
Thank you. Um, well I have some good news. Uh,
[7:28]
I was on the site today. And all goes well
[7:34]
starting Wednesday. We'll have blades on the ice. September 1st.
[7:41]
It's going to be tight. Uh, I had hoped for
[7:44]
a little bit more of a time contingency. Um, but
[7:47]
I'll share with you where we're at with the project
[7:50]
and how we're going to get to the finish line.
[7:52]
And the, uh, the game winning goal. The progress to
[7:57]
date that was encouraging the rink boards are 99 percent
[8:02]
installed. They are expected to be installed tonight tomorrow morning
[8:06]
at the latest. That includes the rink boards, the glass
[8:09]
and all the netting. The bleachers are going to say
[8:15]
95 percent, possibly the, uh, ice making process, uh, is
[8:23]
satisfactory for them to start the ice making as of
[8:27]
Wednesday morning. This month. Or of this week. Of this
[8:31]
month. We do have a media platform that's going to
[8:36]
be installed while the ice making process is going to
[8:40]
be, uh, happening over the next week. The dehumidification units.
[8:45]
We have both of them operational. There was a concern
[8:47]
that we only have one in time, but we've got
[8:49]
both of them in time. The mechanical trades work the
[8:53]
weekend to make sure that we can get maximize those
[8:56]
units. We want to minimize the humidity in the facility
[8:59]
while we do the ice making. Uh, we did test
[9:03]
the ice making plant. We did that on for one
[9:06]
full day. Uh, just to make sure this was done
[9:08]
a week ago because I was hoping to do it
[9:10]
last week. You could feel the rink or the facility
[9:16]
already cooled down. Uh, within that, uh, 12 hour period.
[9:20]
So it's a testament to the building envelope and the
[9:24]
new insulation and the air tightness that we have in
[9:28]
the arena. All the exterior doors, uh, are installed, including
[9:32]
the overhead door for the Zamboni room. The actual Zamboni
[9:36]
room door to its, uh, fire separated. Garage is coming
[9:41]
in tomorrow. And about as well by
[9:51]
tomorrow morning. That will allow us, uh, for a day
[9:56]
of final cleaning of the arena proper to make sure
[9:59]
that there's minimal dirt and that we have, um, minimal
[10:04]
personnel within the arena so that we can maximize the
[10:07]
ice making process. I've been advised that the ice could
[10:11]
take as quick as seven days. Which will bring us
[10:14]
to the first. I'm recommending that, uh, we wait till
[10:19]
after Labour Day weekend, uh, which would be, I believe,
[10:22]
the eighth Tuesday, at which time that I'd feel more
[10:26]
comfortable that any public use could be happening at that
[10:30]
time. Keep in mind that that public use would be
[10:32]
limited to the arena proper and the change rooms. The
[10:36]
lobby is still under construction. And it is anticipated for
[10:38]
it to be done prior to the September 25th Vikings
[10:43]
Homopenine game. Um, so that work is proceeding. We've been
[10:50]
focusing on the arena. The Vikings and the change rooms
[10:52]
to get those occupiable for the first week of September.
[10:56]
The Vikings room, uh, rubber florin is 95 percent installed
[11:01]
HVAC system is being finished as we speak. And their
[11:04]
locker stalls are coming in this week for installation. Um,
[11:07]
the rest of it is more cosmetic and is scheduled
[11:10]
to be ready for a week of September. Uh, as
[11:14]
I mentioned, the lobby, uh, we're waiting for the aluminum
[11:18]
entrance systems. Uh, the ones that create the vestibule as
[11:21]
well as the barrier between the lobby and the arena
[11:24]
proper. Those were ordered four months ago. And they're coming
[11:29]
in this week. I have been told from the contractor.
[11:34]
And once those are installed, then the tarps and the,
[11:37]
and the barricades of the front lobby will be open.
[11:40]
And you could probably drive by and see that rink
[11:43]
from the outside. Um, I'm quite excited for that, uh,
[11:47]
that moment. The, um, in addition to the, uh, lobby,
[11:53]
we have been proceeding on the, uh, the entrance lobby
[11:57]
canopy that goes from the outside into the lobby and
[12:00]
then back out into the arena. Um, that is all
[12:03]
framed. All the lights are installed. We're just waiting for
[12:06]
the, uh, the red siding material to put on, uh,
[12:09]
to finish it. And that's expected by the end of
[12:11]
this week as well. Installations should take about a week.
[12:16]
Painting's done, fluorines and all the change rooms are done.
[12:19]
Uh, we're just basically at the finishing stages at all
[12:23]
aspects. Uh, I'm not at a comfort level with that
[12:25]
lobby to provide public use until prior to the, uh,
[12:31]
September 25th date. The other big work that you're probably
[12:36]
seeing right now is the exterior site work. Um, there's
[12:41]
a complete new front entrance retaining wall access happening. We
[12:49]
have worked with in detail for accessibility with respect to
[12:55]
accessing the arena from that side of the building. We
[12:59]
have two actual areas to access it. Um, I know
[13:04]
there was some, some discussion about the self baseball field
[13:09]
retaining wall. I'm not involved with that. That's telecam engineering,
[13:14]
but I had shared with, uh, carry, um, director of
[13:18]
Recreation. Recreation and culture. Um, that we can add some
[13:23]
input on the accessibility aspects of that, um, we, we've
[13:28]
got quite a good rapport with the community and the
[13:32]
accessible team to make sure that that's, uh, that's being
[13:35]
maintained and consistent with the arena project. We actually used
[13:39]
the spec the same retaining wall stone on the front
[13:44]
was spectacked in the back. So there is again, uh,
[13:47]
I see it as a connected overall image or vision.
[13:56]
As I had mentioned, uh, well, with the exterior work,
[14:01]
uh, there's lots of work to do on the parking
[14:03]
lot side. We're getting there. It will be done and
[14:06]
ready prior to the 25th. I can't give you exact
[14:09]
dates right now because we're focusing on that ice plant
[14:13]
and the front, uh, you notice there's a big hole
[14:16]
there as well. And we're updating some of the water
[14:19]
lines at the cities right away and getting the proper
[14:23]
curb stops and vowels in place. To make sure it's
[14:28]
current and up to code. For a current and up
[14:30]
to code new building. Um, we did have some challenges.
[14:36]
We had some HydraON challenges. But turned into opportunities. It
[14:40]
allowed us to do some other activities. We were expecting
[14:43]
to have Hydro One in place, the end of July.
[14:46]
It did not happen until I believe after you had
[14:49]
a power schedule power outage. Where they came in and
[14:54]
did that work as well. August 9th, I was a
[14:56]
Sunday. We immediately got our, uh, systems connected with the
[15:03]
new power. We needed that power to get the dehumification
[15:06]
units. Operational. And it's not just plug and play. Once
[15:10]
you're plugged them in, there's controls and wiring and systems
[15:13]
that have to be coronated and set up to get
[15:15]
those mechanical systems operational. And that's where we are, um,
[15:20]
today. Uh, in terms of budget, there has been no,
[15:25]
uh, extraneous or, uh, items that have, uh, incurred any
[15:31]
additional costs. We seem to be within our original mandated
[15:36]
budget that you gave me, uh, don't foresee any at
[15:39]
this time any unforeseens that are going to, uh, uh,
[15:43]
take us beyond that. Um, we're at the finishing line.
[15:47]
We're in the third period. Minute to go. And, uh,
[15:51]
I can't wait to take that final shot. So that's
[15:55]
my report for today. Okay. Thank you very much. Um,
[16:00]
lots of exciting news in that report. Do we have
[16:03]
any questions. Councillor Marset. True, you, your worship. With all
[16:08]
the work that's being done to the building with new
[16:11]
insulation and all of that. Is there going to be
[16:14]
a possible savings to the city with the operational cost?
[16:19]
Do you think with the electricity and all that stuff.
[16:22]
In my opinion, yes. What that would be, I can't
[16:26]
answer. I don't know what your operational costs were before
[16:29]
to compare it to what they would be. But you
[16:31]
have, it's basically a, um, continuous installation wrap that we
[16:36]
put around the building. So it's, uh, very efficient way
[16:41]
of an economic way to insulate the billing and to
[16:47]
maximize your opportunity with your mechanical systems to work the
[16:50]
best they can. Okay. Another question. With the amount of
[16:58]
rain that we got recently to the building. Can you
[17:01]
share that with the public. That there is no leaks
[17:06]
happening inside the building at all? Correct. Uh, basically the
[17:11]
roofing that's on that building is the same as the
[17:13]
sky dome. And it's one of the best roofing materials.
[17:20]
It's continuous. It's welded seams. It's adhered in a very
[17:23]
unique way to make sure that any uplift or any
[17:26]
movement from wind uplift is minimized. Um, so we didn't
[17:30]
want to skimp on the roofing material, uh, after you
[17:34]
invested a lot of some money in the structural component.
[17:37]
So I've always said that where you want to put
[17:39]
your money is in the roof because it's protecting millions
[17:42]
and millions of dollars beneath it. So we're happy to
[17:45]
say that, uh, survived that wind or the wind in
[17:49]
the rain. Okay. Uh, councillor man. Thank you, worship through
[17:56]
to Mr. Perry. Having toured the facility this afternoon, I
[18:01]
think the work that's been done since our last tour,
[18:03]
which is about a month ago, um, there's been a
[18:08]
significant amount of work done. So thank you to those
[18:10]
that were on site. Um, it was posed during public
[18:14]
question period. So I will ask you now just to
[18:17]
clarify the relationship between the retaining wall on the ball
[18:20]
field site and the structure of the arena. Is there
[18:23]
a relationship. Between that retaining wall? Well, again, I'm not
[18:26]
the, uh, designer engineer of that system or what, but
[18:30]
in general, uh, you want to frost protect your footings.
[18:35]
And it's typically done by cover, whether it's done by
[18:37]
earth cover and or installation. Um, to substitute any loss
[18:43]
of cover. Um, I took a quick look at the
[18:47]
drawings. I'd have to defer to telec engineering to for
[18:50]
any contracted. But in my opinion, it appears that they're
[18:55]
maintaining that cover. Uh, against the building. And, uh, then
[19:01]
my mind that, that's compromising the structure or affecting, but
[19:06]
again, I'd have to. No, absolutely. Thank you. Councillor Flintoff.
[19:12]
Yeah. Thank your worship. Just a comment and one question.
[19:17]
Yeah. I also went on the tour and it was
[19:19]
very impressive. I was talking to one of your head
[19:21]
form. And he said there was 55 trades been in
[19:25]
there working. And they were just inside outside lobby everywhere.
[19:30]
And we're touring around. And I said, so what's your
[19:32]
opinion? And he said to me, this is probably one
[19:34]
of the safest buildings he's ever been a part of
[19:37]
the way to cement the wood, the beams, the micro
[19:41]
everything. So it's, it's looking really, really exciting. My one
[19:46]
question is once I know you're concentrating on the rink
[19:51]
and everything, will you be able to keep all amount
[19:53]
of that staffing on so we can get going like
[19:56]
little bit because the lobby looks like it still has
[19:58]
a little bit of a project in front of it.
[20:01]
Right. As mentioned, the lobby appears to be needing a
[20:06]
lot of work, but all of the mechanical electrical infrastructure
[20:10]
is in place sprinkler systems are all in place and
[20:14]
certified, uh, it's more cosmetic. Um, it's the fluorine. It's
[20:18]
the ceiling work. Um, uh, the canteen, uh, the hood
[20:23]
does not schedule to arrive until mid - September. Um,
[20:27]
that's going to involve some roofing work, but we've already
[20:30]
put in the roof curbs for that. We order that
[20:33]
in advance. And that's, so that's all it's all kind
[20:36]
of ready. It just needs the time and attention. And
[20:39]
so we have not been put in the time and
[20:42]
attention on it basically to get in that arena ready.
[20:46]
Okay. Thank you. Great work. Councillor Lefe. Thank you. Russia
[20:54]
through you to Mr. Perry. Just a question we receive
[20:57]
from the public. I know I asked you and was
[20:59]
satisfied with the question, but I'll ask it again for
[21:01]
the members of the public. Have we tested the ZM
[21:04]
boning machine? Are we sure that it works. Well, we,
[21:08]
we have, uh, weekly meetings with the project team, inclusive,
[21:12]
uh, is the city, obviously in staff. And we usually
[21:16]
brainstorm and troubleshoot all aspects of the project. And even
[21:21]
one's non - related to the construction. And I believe
[21:24]
it was in June or July where we had red
[21:27]
flagged that all of these operational requirements and equipment has
[21:31]
to be confirmed to be operational. And I believe at
[21:34]
that time, uh, the city had got, I can't remember
[21:39]
the name of the, uh, the Zamboni service, uh, we
[21:44]
asked for it to be off the site. But while
[21:46]
it's off the site, have it serviced and make sure
[21:47]
it's operational because we are going to be starting ice
[21:50]
to the end of August. Thank you, your worship. More
[21:58]
of a comment I did to or two today. And
[22:00]
I thought what I saw was amazing what you've done
[22:03]
with that building reorganised washrooms, the change rooms and everything.
[22:07]
I don't know how you got all that space in
[22:09]
there to accommodate everything. And the bleachers look great. They're
[22:12]
going to have the seating. The lighting looks good. It's
[22:16]
a totally new building. So those that, uh, thought this
[22:20]
might be a waste of money. I think you're going
[22:22]
to be pleasantly surprised when you see it. And so
[22:24]
thank the crew and thank you so. Thank you. Councillor.
[22:32]
You're good? Okay. Feel her going to all have big
[22:36]
hugs soon. No, that's very exciting news. It's been a
[22:40]
long trial to get here. Um, we had thought that
[22:45]
we had hit this mark a few times along the
[22:48]
way. But truly going through that arena, I think everybody
[22:52]
will be happy. Of course it's baby steps going in.
[23:00]
I would ask if you notice things to just notify
[23:05]
the city and maybe give a suggestion to help out
[23:10]
if there is something deficient. Got to work together and
[23:14]
make it really good. From what I've seen is, um,
[23:19]
a tremendous amount of, uh, just progress. Especially this whole
[23:25]
summer. And again, I'd like to go councillor bowl. Thank
[23:29]
all the workers that are in there. They worked really
[23:31]
hard. People have noticed. I do have a few questions.
[23:38]
Um, just concerning occupancy. Uh, where are we with that?
[23:44]
So part of our weekly meetings, uh, what we call
[23:48]
in project closeout. Phase or mode. Um, so working with,
[23:53]
uh, Chief Billing official and staff and the fire department,
[23:57]
uh, frequent site visits to make sure that we've got
[24:00]
everything in line with what's required of them, uh, in
[24:04]
addition to building code states what we need to have
[24:05]
in place and operational. Um, and we have a checklist
[24:09]
of that. It's ongoing, uh, certifications and certificates and all
[24:14]
of that. Are to be in place. And we're expecting
[24:16]
to get, uh, for the occupied spaces that cleared and
[24:20]
checked off, uh, prior to the eighth. Okay. Um, this
[24:27]
might be a question from Ms. Kluck. Is there preparation
[24:31]
for staff training? And or do we have still experienced
[24:35]
employees of the arena that are familiar with the plant.
[24:40]
And, you know, humidifying systems. That kind of stuff? Or
[24:44]
is there plan training to occur. Thank you, Thrill. So,
[24:50]
uh, we have one returning employee and the ongoing training
[24:54]
throughout the summer and in past years as well, just
[24:58]
in certifications. And I think they're as ready as they
[25:02]
can be. It's going to be some of its new
[25:05]
and a learning curve. But, um, everyone is ready and
[25:09]
looking forward to it. And there's other employees that have
[25:13]
helped in the past too in other departments that I'm
[25:16]
sure they'll lean on, if needed for expertise. But, um,
[25:20]
our main lead arena operator is ready and trained. And
[25:25]
I think a few different certifications this summer. All right.
[25:28]
Thank you. And then the final thing. So we're opening
[25:31]
the I September 8th, but the lobby is not open
[25:34]
till the 25th. What is the access to get to
[25:39]
the change rooms? And is that going to be open.
[25:43]
Yeah. So the focus was obviously knee change room if
[25:45]
you want to be using the ice. So, uh, we
[25:47]
have a clear delineation between the lobby and the change
[25:50]
rooms. So it's quite an easy, uh, separation. Um, and
[25:56]
again, we still need to work with the chief billion
[25:59]
official and the fire department to make sure that those
[26:02]
areas that are occupiable are meeting the code and that
[26:06]
we have the proper sign - offs for that, uh,
[26:08]
that section. Uh, today the red flags that are going
[26:11]
to inhibit that from happening. Okay. Any other questions.
[26:21]
No, let's have a lot of questions this time. We're
[26:25]
getting so close. I'm trying to give you the puck
[26:28]
and pasta so you can score. Let's go into the
[26:31]
third period. We're going to make the first puck market.
[26:33]
We don't want any overtime. Yeah. So that's great. The
[26:37]
next, um, I guess few steps you'll be back and
[26:41]
forth here quite a bit. Are we going to get
[26:43]
another update or are we going to wait a month.
[26:46]
Uh, well probably another update before 25th. Yeah. Yeah. Okay.
[26:53]
And I'm serious. I'm hoping to have my skates. Bring
[26:58]
your elbow packs. Elmo is up. Okay. Thank you very
[27:04]
much, Chris. Appreciate it.
[27:15]
Okay. Our second presentation is from BHP Elliott Lake. Quirk
[27:21]
TMA DAMS G1 and G2 raise project update. This evening's
[27:29]
presenters, uh, Maxime Morin. I'm assuming Darren Willems, Brittany Shirley
[27:35]
and Stacy Hannam. On virtual support.
[27:53]
The sharing of the screen, I guess. Is that what
[27:55]
you have to do? I have to. People on Zoom.
[28:00]
We're going to share the screen for your presentation. Oh,
[28:02]
okay. Britt. Your, this year able. To share the presentation.
[28:11]
Yeah. I'll go ahead and do that. Maxime is your
[28:21]
green light on still. There we go.
[28:32]
Is that okay for folks in the room there. See
[28:38]
the BHP Elliot Lake slide? Yes. Okay. Perfect.
[28:53]
Do you want to kick it off Maxim? Yeah. I'll
[28:55]
kick this off. Uh, thanks everyone for attending. Do you
[28:58]
want to maximize that maybe? Just maximize it. If you
[29:02]
can. Full screen. Let's see if I'm capable to maximize
[29:07]
that.
[29:28]
Or the top right square. I don't know. Is that
[29:33]
where it is on this one? I have no idea.
[29:35]
Apologies. My computer did an update of this software. Quite
[29:41]
literally today. Um. Looking here. I'm
[29:51]
feeling if I go a hundred percent, it's going to
[29:53]
be very unappealing. Well, that's a little better. Okay. That's
[29:59]
a little better. I apologise. Sorry. Get going. Our agenda
[30:05]
today is to discuss about the quirk TMA DAMS G1
[30:09]
and G2 raise project update. And I'll go in the
[30:14]
next slide to our agenda. We'll go through a land
[30:16]
acknowledgement. Just level high level review of our legacy assets
[30:22]
values and purpose. The history of the CURC facility. The
[30:26]
project update and to go for adoption as well as
[30:28]
the path to completion. Yeah. Just a disclaimer about this
[30:37]
presentation. And all the forward looking statements that it includes.
[30:41]
Um, so just make sure that, uh, nothing in this
[30:44]
presentation should be construed as or ran or either an
[30:49]
offer to sell or to solicitate and offer to buy
[30:53]
or sell BHP securities at any jurisdiction. It'd be treated
[30:56]
Hyrule White upon as per recommendation or advice by BHP.
[31:01]
It's a standard. Disclaimer that we have on all representations.
[31:06]
Um, for land acknowledgement, uh, we'd like to begin by
[31:10]
our meeting by acknowledging that BHP operates around the world.
[31:13]
On land and has been inhabited by indigenous people for
[31:17]
thousands of years. We honour this place and honour their
[31:23]
contributions. We acknowledge that the land where Elite Lake asset
[31:27]
is, is in a traditional territory of a shinabi people
[31:31]
and his signatories of the Robertson here on treaty. And
[31:34]
we pay our respects to the First Nations ancestors. And
[31:37]
we will also be engaged with them in the upcoming
[31:40]
weeks. Um, so who is BHP? We are a global
[31:44]
resource mining company. Aiming to bring people and resources together
[31:49]
to build a better world. Real album is a subsidiary
[31:52]
company of EHP. And we have in Elliot Lake, eight
[31:58]
decommission uranium mines. That operate, that were closed between 1990
[32:02]
and 2000. And all the sites in this area are
[32:06]
currently in long - term care and maintenance. Of the
[32:10]
mining cycle and activities are both licensed federally and provincially.
[32:16]
The values that we have for a company remain the
[32:19]
same as last time that we do that we had,
[32:21]
uh, presentation in March. Do what's right, seek better ways
[32:25]
and make a difference. Uh, the project that we're going
[32:28]
to be talking about today is fits right in within
[32:31]
our values and our purposes. Um, making sure that we're
[32:35]
doing what's right for our assets that we have. And
[32:39]
our purpose is to bring people and resources together to
[32:41]
build a better world. And just locally, our purpose is
[32:45]
to protect today and improving tomorrow. Uh, just on the
[32:50]
legacy assets, overview of North America, there's a, the, our
[32:54]
team manages or regional team manages around 23 sites. That
[32:59]
are within various stages of the mining cycle. And your
[33:02]
primary acquired through mergers and acquisitions, including illegally. Current site
[33:08]
activities include tailings management, risk mitigation, technical studies, closure and
[33:13]
road mediation projects. As well as general Karen maintenance. Now
[33:22]
just another introduction for those who don't know the facility
[33:26]
of quirk, which is just 13 kilometers north of Elyt
[33:28]
Lake. Currently there is a remediation project that we don
[33:34]
as the main dam buttress project. It's continually ongoing. This
[33:38]
is a separate engagement. Related to the G1 and G2
[33:42]
raises. Uh, but the facility itself, uh, operated in the
[33:46]
50s, mid 50s and again, from the late 60s to
[33:50]
1990 and operated between 2700 and 6400 tons per day,
[33:55]
uh, underground with the conventional acid leech milling. The facility
[34:01]
itself contains 42 million tons of neutralized tailings and formulang
[34:05]
tons of waste rock. And in 1990s, the tailings were
[34:10]
flooded by contain eight perimeter dams that you could see
[34:13]
around the facility. The quirk TMA has been partitioned into
[34:18]
five flooded cells. With four internal dikes with a two
[34:22]
to four metre water level drop between cells and overall
[34:26]
between say the upstream and downstream end. There's a 14
[34:29]
metre difference in elevation from one dam to the other.
[34:33]
Um, so tailings are maintained in a saturated state with
[34:35]
a water cover to reduce the environmental impact. So covering
[34:39]
the level. Covering the fine particles of the tailings and
[34:42]
making sure that they're not getting accedized. Um, all contact
[34:47]
water for quirk is being contained through our water treatment
[34:50]
plan and at South Right corner of the, of the
[34:55]
site, the picture there. Uh, and all contact water is
[34:58]
conveyed through that treatment plan. It passes through settling ponds
[35:02]
that are monitored for compliance and released offsite to the
[35:05]
Serpent River. Darren, if you want to talk about the.
[35:14]
I'll talk about, uh, the issues that we have with
[35:16]
the internal dykes, the main reason we're here. So we've
[35:20]
got the internal diches and we've got the perimeter dikes
[35:24]
that he showed you in the previous slide. Now the
[35:26]
internal Dykes themselves are founded on tailings. Um, tailings are
[35:31]
not necessarily a great foundation material. Um, but back in
[35:37]
the day when they were built, they were built to
[35:39]
the technology, the engineering of the day, built in good
[35:43]
faith, um, built around. Industry requirements that required, you know,
[35:48]
minimum, um, seismic events to design two things like that.
[35:52]
Well, a lot of that has changed. Um, over the
[35:54]
last couple of decades, there have been a lot of
[35:57]
damn failures in various parts of the world. And with
[36:01]
that, it's come a lot of change in the industry,
[36:05]
in the, um, uh, industry requirements around DAM. So what
[36:09]
used to be acceptable, where we designed these facilities for
[36:13]
one in a thousand year seismic events, which, you know,
[36:15]
we all know this isn't really a seismic area, but
[36:18]
you still have to design for a one in a
[36:20]
thousand year event. Since then, that criteria has changed to
[36:24]
one in 10, 000 years. So, you know, we've got
[36:26]
facilities that have been built. That have been standing for
[36:31]
30 years. But now they don't meet the new requirements.
[36:35]
So we're having to go and make some changes. Um,
[36:40]
we have perimeter DAMs around the facility. That are built
[36:45]
on solid foundation. So they're all built really well. The
[36:50]
main dam was the one exception. And that's the one
[36:51]
that we are building a buttress around, uh, now that
[36:55]
we talked about with you guys last year, the year
[36:58]
before. But the issue we have because the internal dychs
[37:01]
are founded on poor foundation material and are susceptible to
[37:04]
earthquakes. There's a potential that we could have a cascading
[37:09]
failure event. Where the upper cells fail. And each dyke
[37:14]
continuously fails. And the risk is that we will have
[37:18]
an overtopping event of G1 and G2 that he showed
[37:21]
you at the bottom of that. Image. And so what
[37:24]
we're doing is we're going to build up G1 and
[37:26]
G2 so they contain that event. And that prevents downstream
[37:31]
of risk to people on the highway to people in
[37:34]
the community. People at Quirk Lake and so on. But
[37:41]
I think important to highlight is that there is no
[37:43]
performance issues with the internal dikes. To date. It's all
[37:49]
kind of precautionary works that we're doing. Yeah, it's all
[37:52]
really work that's directed around bringing everything up to code.
[37:56]
That's probably the best way to put it. And BHP's
[38:02]
got a pretty low tolerance for. Any potential for events
[38:07]
to happen. Uh, even though we don't expect anything to
[38:10]
happen here, uh, we. Want to make sure we do
[38:14]
everything to make sure we meet current guidelines. And codes.
[38:19]
So that's, that's the driver behind this work. Brittany, if
[38:24]
you want to continue with the next slide. Prefer cool
[38:28]
for it off. For sure. Um, and just to double
[38:31]
check, uh, everyone in the room can hear me. Yes.
[38:35]
Okay. Perfect. Thank you so much. Um, and so right
[38:39]
now, um, like Darren mentioned, we've identified, um, that issue
[38:45]
and we're working through, um, how we're going to address
[38:48]
it. And like he said, um, we're going to focus
[38:51]
on rather than stabilizing the internal dichs, which has some
[38:56]
challenges in themselves. We're going to focus on raising the
[39:00]
perimeter dams around the facility. So in the low likelihood
[39:04]
of a failure, um, the downstream impact to people is
[39:12]
eliminated there. And so in order to do that, the
[39:16]
sort of four scope elements we need to look at.
[39:19]
And those scope elements are to raise DAM G1. Raise
[39:26]
DAM G2. Construct an emergency spillway. And construct a way
[39:32]
to convey water through the treatment plant. So with those
[39:38]
four options, we had brought in a multi stakeholder decision
[39:42]
group. It included, um, operations experts from Maxim's team. It
[39:47]
included folks like Darren from a technical point of view.
[39:51]
It included our construction team, our environmental. Those sorts of
[40:00]
things. And we went through in the end the conceptual
[40:06]
figure you see here is where. We landed on sort
[40:11]
of our go forward option to bring forward into detailed
[40:15]
design. The phase that we're currently in. And so the
[40:19]
interesting things out of those workshops in terms of the
[40:23]
rays of DAM - G1 and D2 is we very
[40:26]
much had to consider how Maxim's team accesses the key
[40:30]
infrastructure on site. During the construction as well as after.
[40:35]
And so a lot of the considerations and optimizations we
[40:38]
did around there were ensuring that he could have access
[40:41]
to the treatment plant and his folks could have access
[40:44]
to the different valves, the different environmental instruments, uh, the
[40:48]
different sampling points all through site. Um, so that was,
[40:51]
um, the considerations at the conceptual level, um, in terms
[40:55]
of the intake, uh, currently today, this final cell that
[41:00]
you see here, this final cell, um, has a gravity
[41:03]
fed intake and it goes into the treatment plant. That
[41:07]
won't work with the rays or the intake as it
[41:09]
is today won't work with the race. Um, and we
[41:12]
looked at a couple of different options, some more mechanically
[41:15]
complicated than others. And we've settled on our preferred intake
[41:20]
to also be, um, a gravity feed intake going forward
[41:25]
largely for, um, operational ease and minimizing maintenance. And it
[41:30]
has been proven to work very well, um, at the
[41:33]
corp facility for us. And then the last, um, option
[41:39]
or scope element, we considered in the conceptual design is
[41:42]
where the emergencies spillway will discharge. And so, um, currently
[41:48]
the court facility does have an emergency spillway. But once
[41:53]
again, as we raise those perimeter dams, we raise DAMS
[41:57]
- G - 1 - G2. We just need to
[41:58]
modify the spillway height and capacity to be appropriate for,
[42:03]
uh, what the new facility will. Look like. And we've
[42:08]
opted to put it in the location you see here
[42:11]
because from. An environmental point of view, option of sort
[42:17]
of remobilizing water that we've already treated. And this option
[42:22]
won't have that sort of residual impact. Um, this is
[42:26]
not a final design. Um, this is the scope elements
[42:30]
we're working through detail design on. So this is a
[42:33]
conceptual sketch of where we're starting in our detailed design
[42:36]
process. Um, so what is our path to getting, getting
[42:43]
through this, um, eliminating this risk. So we're currently in
[42:48]
2026. And we're looking to, uh, complete the.
[43:00]
Pelt design of the raises, the feed intake. And so
[43:04]
that includes, um, the regular. Modelling, um. And verifications. We
[43:11]
highly at Lake as well as a development of a
[43:14]
specification and issued for construction drawings that can feed both
[43:19]
the permit applications as well as our tender processes. Um,
[43:26]
so we are aiming to have our permit applications in
[43:31]
with the provincial as well as the federal regulator in
[43:36]
2027. Um, and then they'll have the opportunity to review
[43:41]
the package, um, technically and provide us any feedback clarifications
[43:47]
and challenges they might have with that package. Um, and
[43:52]
then we would look to, um, tender our material procurement
[43:57]
ahead of time. The largest portion of this project is
[44:01]
the raising of the two dams. And so that does,
[44:04]
um, require a considerable amount of granular material. Um, and
[44:09]
so we wish to tender it fairly early in the
[44:12]
process, um, so that we can spread the hauling throughout,
[44:18]
um, a longer period of time. Once we have our
[44:23]
materials secured with a vendor, we'll then look to tender
[44:27]
the main construction work packages for the earthworks as well
[44:32]
as the, uh, smaller amount of mechanical components for this
[44:36]
project. We're anticipating just based on, uh, applications we've done
[44:43]
in the past that it'll take about a year to
[44:47]
receive our regulatory approvals. So we're anticipating to receive those
[44:52]
in 2028. And if we do receive those and are
[44:57]
able to meet the conditions of them, we would look
[44:59]
to do construction, um, initiating in the spring of 2028,
[45:05]
um, taking a pause over the winter and finish the
[45:08]
last component, um, in the construction season of 2029. We,
[45:16]
one of the reasons we wish to split the construction
[45:19]
season over two seasons is to ensure our operations team
[45:24]
maintains, uh, safe and reliable access to the treatment plant.
[45:29]
So we can continue to manage the environmental, um, treatment
[45:34]
during that time. And so the really at the end
[45:41]
of the day, the most important question about this, um,
[45:47]
this is a fine project. But how do we ensure
[45:51]
that wall we are doing it, we are doing it
[45:55]
safely for people and the environment. And also leaving it
[46:01]
in its state, um, now and in the future. And
[46:04]
so the regulators will, um, provide us, I'm going to
[46:10]
say like assurance for this process. Um, all of the
[46:14]
plans I'm going to go through, um, are either submitted
[46:17]
to our federal or provincial regulator for approval. And then
[46:22]
they do frequently come to Elliot Lake to verify that
[46:25]
we are indeed doing what we say. So the key
[46:29]
plans that we have for people and environmental safety for
[46:33]
this project are a DAM safety monitoring program. Um, every
[46:38]
time you modify or impact a tailings management facility or
[46:43]
a DAM, um, there will be performance monitoring established. We'll
[46:48]
know more in detail design what the engineer recommends. It'll
[46:51]
likely be a combination of instrumentation survey and some visual
[46:57]
monitoring as well. We'll look to develop a project specific
[47:02]
construction environmental management plan. Um, this project is primarily occurring
[47:08]
on, um, disturbed or already disturbed area. And perhaps I
[47:14]
should have, um, highlighted in the last figure, but the
[47:18]
footprint print of this project is within REO ADM property.
[47:22]
That being said, um, there is still an environmental component
[47:26]
to manage particularly around, um, ensuring the continued safe treatment
[47:31]
of water. We will ensure that the final structure is
[47:37]
safe through our QA and QC program with our engineer
[47:43]
of record licensed in Ontario. And so that'll ensure that
[47:46]
the project, um, that we are delivering, um, last now
[47:53]
and well into the future. Um, we will, um, look
[47:58]
to implement a radiation protection program as we will be
[48:02]
working adjacent to the tailings management facility with the potential
[48:07]
of some excavation of the tailings. We'll need to ensure
[48:10]
that the people doing that work are safe. Um, and
[48:13]
so that'll include things like decontaminating equipment before it leaves
[48:18]
sites, um, ensuring workers are receiving, um, doses that are
[48:25]
not dangerous. Um, and ensuring we can provide the proper
[48:29]
separation between the radiation hazards and the folks working on
[48:33]
site. And then lastly, uh, one of BHP's core values
[48:40]
is health and safety and the environment. Um, we do
[48:43]
have a standard within our legacy assets group, um, and
[48:47]
so that'll be used to manage the key, um, occupational
[48:51]
health and safety risks we have on that project. Being
[48:59]
that, you know, mobile equipment, our excavates there. Um, yeah,
[49:06]
Maxim, would you like to close for us. Just thank
[49:13]
you. Uh, one answer. And we're open to any questions
[49:17]
or follow - ups. Okay. No, thank you for coming
[49:21]
to report to council every year and updating us on
[49:24]
all your projects. Are there any questions from councillor Morset?
[49:28]
True you, your worship. Does PhP work in the wintertime.
[49:35]
And are those, uh, dams monitored during the wintertime. Or
[49:40]
all year round. Um, like in terms of. Okay.
[49:50]
Um, in terms of this BHP work in the winter,
[49:53]
I'll maybe let Maxim colour that statement a little bit
[49:56]
more from an operations point of view. For projects, we,
[50:00]
um, we sometimes work in the winter, uh, we generally
[50:04]
don't do earthworks projects in the winter. It's just challenging
[50:09]
in the northern Ontario climate, uh, but we, yeah, so
[50:13]
we try to plan around the more. Uh, mild, uh,
[50:17]
summer season. And then Maxime, do you want to speak
[50:19]
a little bit more to, uh, what your team does
[50:23]
in the winter. Yeah. From the operations team, like we,
[50:28]
we don't stop all year. We're 365 days a year.
[50:31]
Uh, we have some DAM inspections that occur, uh, snow
[50:36]
free conditions and some that require at least one inspection
[50:39]
during a winter. We have some instrumentation that stays within
[50:43]
the DEMS all year long. And, uh, but yeah, it's
[50:48]
definitely part of our, uh, long - term care and
[50:50]
maintenance plan is to make sure that things are operating
[50:53]
and still, uh. In top shape during the winter as
[50:57]
well. Any other questions. Councillor flintoff. Uh, thank you. Thank
[51:05]
you. Worship through you. I think to Maxine, is there
[51:08]
hauling going on there out there right now with material.
[51:13]
Yes, hauling going on right now. And so I think
[51:18]
it was Maxim who alluded to it, um, during this
[51:23]
slide, um, there is this dam that's sort of in
[51:26]
this trapezoid shape here called MainDAM. And that's a different
[51:31]
project that is currently under construction. Um, that project is
[51:37]
to make a buttress. Because like Darren had said, uh,
[51:41]
the perimeter dams are founded on bedrock. Um, the exception
[51:46]
is main dam, uh, so currently a buttress is being
[51:49]
constructed there to improve the stability. So yes, there is
[51:53]
hauling, but it is associated with a different project. So
[51:58]
just to follow up, so the main DAM project is
[52:01]
one that you presented to us a couple of years
[52:03]
ago. That one's in the works. And this is going
[52:06]
to be a whole new project. Starting up. Okay. Thank
[52:12]
you. Yes. That's correct. Any other questions councillor CIDL. Uh,
[52:19]
thank you, you worship. Um, with your internal dykes now
[52:22]
with you raising DAM G2 and G1. Is there any
[52:28]
evidence of the internal DICE. Giving away it all where
[52:33]
we're going to be worried about the height of the
[52:35]
dam's G1 and G2? I can take care of that,
[52:40]
uh, question. Um. Yeah, so with, with the rays of
[52:44]
G1, G2, really nothing will change inside the facility. Um,
[52:48]
one thing we're doing right now, just to help construction
[52:52]
is we're reducing the amount of water that we flow
[52:55]
through the facility. So we, we add water to the
[52:58]
facility at gravel pit lake at the top end and
[53:00]
it flows through. And we're, we've cut back on that.
[53:04]
Because we don't want to have to treat as much
[53:05]
water because we've had to make some adjustments to our
[53:08]
discharge line and things like that. So we've got a
[53:10]
lot less load on our internal lakes right now because
[53:13]
the water levels are down. So, uh, if anything, the
[53:16]
situation's improved because of, because of that reducing. Okay. Thank
[53:22]
you. Any other questions. Um, so the most dangerous part
[53:30]
of this part, it sounds like you're going to be
[53:33]
digging up tailings. Um, have, have you been through that
[53:37]
sort of process at other spots before? Or is Elliot
[53:40]
Lake unique in that. Yeah. We're not really digging up
[53:43]
any. Tailing. So the tailings will all stay. Where they
[53:45]
are. Um. We're just building up. G1 and G. And.
[53:50]
Proving MaineDai. To contain everything. If it were to fail.
[53:55]
Okay. Yeah. And then in terms of just tailings, um,
[54:02]
it's just something like in terms of the plans and
[54:05]
the that we're going to develop to safely execute this
[54:08]
project just due to the locations of DAMS - G1
[54:11]
and G2. Um, there is, we just need to plan.
[54:16]
We need to plan for, um, the incidental contact of
[54:20]
the tailings to ensure that we have plans in place
[54:23]
if we do. And that's something that we have, um,
[54:28]
good baseline plans established and can retain the appropriate radiation
[54:33]
scientists, um, to plan specifically for what we could encounter
[54:37]
in those areas. Okay. Um, I'm not sure if you
[54:41]
heard public input earlier. Um, concerning your permits and applications.
[54:49]
It sounds like it's pretty laid out for this project.
[54:51]
And I'm pretty sure it was late over the last
[54:52]
one. Could you perhaps update that or did you hear
[54:56]
about you heard it? Okay. Perfect first. One. So happened
[55:02]
to come out. Thank you. Um, yeah, so I believe
[55:05]
the question was related to our waste facility operating license
[55:08]
that is currently being modernized. So an application was submitted
[55:13]
around two years ago. So our waste facility operating license
[55:17]
is actually under a previous act and legislation. So it
[55:21]
does take quite a while to modernize it to today's
[55:23]
legislative standards. So that is in the process. We've gone
[55:27]
through most of the technical reviews. It's just understanding how
[55:30]
we license going forward. And so that is still under
[55:33]
discussion with CNSC at the moment. And there was also
[55:36]
a question related to how many hectares. Are involved. And
[55:41]
I don't have that number off the top of my
[55:43]
head. So I would have to get back to you,
[55:46]
but it does involve the tailings facilities as well as
[55:49]
all of our treatment infrastructure. So all of the bounds
[55:52]
of our site. And all the land too. Correct. Yeah.
[55:57]
Okay. Well, that's it for my questions. Thank you very
[56:00]
much once again for presenting. I expect you'll present the
[56:06]
council when you have updated this current plan. Conceptualization stage
[56:11]
and then planning stages. But yeah, happy to have you
[56:14]
anytime. Thank you. Thank you. Thank you.
[56:40]
So the delegations consent agenda. Introduction and consideration of corporate
[56:46]
reports. 11. 1 report from the Manager of Environmental Services
[56:51]
regarding landfill site operation contract. 2013 - 06. Rate Adjustment
[56:59]
proposal. May have a motion that the Report of the
[57:02]
Manager Environmental Services regarding the rate adjustment proposal provided by
[57:06]
beam is construction for the landfill site operations be received.
[57:11]
And the Council approved entering into an extension agreement with
[57:15]
beamSconstruction ink for the provision of landfill site operation services
[57:19]
commencing July 1st, 2026, and ending December 31st, 2026. And
[57:28]
that council approved a rate increase of 10 percent over
[57:31]
the current annual rate effect of July 1st, 2026 through
[57:36]
December 31st, 2026, and that the appropriate bylaw be passed.
[57:43]
We have a mover. Councillor Mann, seconded councillor of faith.
[57:48]
Mr. Irving, please. Good evening, your worship. And through you
[57:52]
to members of council, the landfill site operations has been
[57:55]
provided by BeamESh Construction since August of 2013. The current
[58:00]
contract extension expired June 30th, 2026. And this extension will
[58:04]
cover the period of July 1st, 2026, and end on
[58:07]
December 31st, 2026. The extension will also grant BEMS
[58:11]
construction, 356 dollars and 57 cents plus
[58:21]
HST monthly or 292, 278 dollars and 84 cents annually.
[58:28]
The new monthly price dating back to July 1st, 2026
[58:32]
will be 26, 792
[58:35]
dollars, 64 cents annually. With the
[58:45]
current LAN fill expansion still within the approval stages with
[58:49]
a most recently requested baseline water quality assessment report completed
[58:53]
by PENSHON Limited and submitted to the Ministry of Environment
[58:56]
Conservation and PRX. There's currently a few unknown variables pertaining
[59:00]
to the expansion. This is inclusive of desired changes to
[59:04]
the operation scope of work, such as how waste is
[59:07]
managed within the landfill with development of cells and a
[59:10]
specified unloading and sorting area. Staff is recommending the execution
[59:19]
of the extension with a 10 percent increase. This will
[59:23]
age in AID and bridging the municipality to 2027 while
[59:27]
ensuring adequate landfill operational services are provided. During this time,
[59:31]
BMISH will prepare or revise proposal and staff will investigate
[59:34]
other alternatives such as the competitive process of issuing a
[59:38]
request for proposal. The length of the future RFP or
[59:41]
contract extension will be determined based on the current stage
[59:45]
of the landfill expansion. For example, should it still not
[59:48]
be completed. The contract will be for a short period
[59:50]
of time to compensate for the required scope of work
[59:53]
adjustments. And I'm open to any questions. Okay. Thank you,
[59:59]
Mr. Irving. Do I have any questions. Councillor Madden? Thank
[1:00:03]
you, worship - through to Mr. Irving. I will support
[1:00:07]
the recommendation tonight. Obviously, we're two months into this term
[1:00:10]
already. And that's the second part of my question. Will
[1:00:14]
you have sufficient time before this now. Term contract elapses
[1:00:21]
by the end of this year in order to get
[1:00:24]
a longer range plan or at least come back to
[1:00:27]
council with alternatives? Thank you. Three of your worship. I
[1:00:32]
don't expect the expansion to happen by the end of
[1:00:35]
the year. So it might just be continuous short -
[1:00:38]
term six - month extension agreements until the expansion actually
[1:00:42]
takes place. And then the whole scope of work would
[1:00:45]
adjust. That's what. Mean as well. Additional increases in January.
[1:00:56]
It could. Thank you. Councillor Flintoff. Thank you, our ship
[1:01:02]
- free to Mr. Irving. So just so I can
[1:01:04]
understand this. So there's two contracts going on. Like there's
[1:01:08]
going to be the contract for the operation of the
[1:01:11]
landfill. And then they're working on a separate contract for
[1:01:15]
the expansion or will they be combined. Three year worship.
[1:01:20]
So the expansion is actually submitted originally in 2017. And
[1:01:26]
it was to expand the whole site, essentially double the
[1:01:29]
size of the landfill. So the operations is the only
[1:01:33]
contract that's actually taking place currently. It's just with the
[1:01:38]
expansion taking place, the whole operations out there is going
[1:01:41]
to change. There's going to be designated cells out there.
[1:01:44]
There's going to be an unloading area. And there's also
[1:01:47]
going to be a sorting area. So that will change
[1:01:50]
the scope of work within the RFP from 2013. Does
[1:01:56]
that answer your question? Yeah. Yeah. So basically, as Councillor
[1:02:00]
Man had said this contract's going to go sort of
[1:02:04]
along like this, we do the expansion. Then we're going
[1:02:07]
to have to look at the whole new thing. You
[1:02:10]
are correct. Okay. Thank you. Councillor Faith. Okay, your worship
[1:02:16]
through you. So you made a comment that you don't
[1:02:18]
expect the expansion until next summer. So would it not
[1:02:21]
make more sense to extend this contract to say next
[1:02:24]
June so that we could lock in a price. For
[1:02:27]
a year rather than just six months? Three year worship.
[1:02:31]
B is just one of the to prepare six month
[1:02:33]
extension. And then look at a Revised proposal. To touch
[1:02:38]
on councillor man's comment. There's probably going to be a
[1:02:42]
price increase come January considering there was no price increase
[1:02:45]
for three years. Okay. Any other questions. Nope that sounds
[1:02:53]
okay to me too. Um, of course you'd like to
[1:02:57]
lock in longer. Cheaper rake, but got to play fair.
[1:03:01]
So, um, any other comments. Okay. All in favor. That's
[1:03:08]
carried. 11. 2 report from Manager of IT.
[1:03:18]
Regarding card access controls, supply and installation for municipal facilities.
[1:03:23]
We have a motion that council approved entering into an
[1:03:26]
agreement with smart tech installations limited. For the supply and
[1:03:32]
installation of card access control systems for 23 doors across
[1:03:37]
nine municipal facilities in the amount of 49, 639 dollars,
[1:03:45]
and that the additional 4, 639 dollars and 54 cents
[1:03:51]
required above the 45, 000 previously approved in the 2026
[1:03:55]
capital budget. Be funded from the IT operational budget that
[1:04:00]
the appropriate bylaw be passed. Um, over. Council man, second
[1:04:06]
hit councillor bull. Uh, Mr. Deshaw. Thank you, worship. So
[1:04:12]
this report recommends council approve and agreement with smart tech
[1:04:15]
installations for CARD access control on 23 doors across nine
[1:04:19]
facilities at a cost of 49, 639 dollars plus HSD.
[1:04:25]
But right now most city buildings are on mechanical keys.
[1:04:28]
There's no record of who enters a building. A lost
[1:04:31]
key can't be turned off. And every lost key means
[1:04:34]
re - keying. City hall, the fire hall and the
[1:04:37]
airport have CARD access today. But on two separate data
[1:04:40]
systems. This project replaces all of that with one system.
[1:04:44]
Staff carry a single fob that works at the facilities.
[1:04:47]
They're authorized for access can be granted or revoked in
[1:04:50]
minutes. And every entry is logged. The financial impact, council
[1:04:54]
approved 45, 000 dollars in the 2026 capital budget. Staff
[1:04:59]
evaluated quotes from four vendors and SmartTech was the lowest
[1:05:02]
compliant bid at 49, 639 dollars. The software for this
[1:05:12]
runs on our existing servers. There are no subscription or
[1:05:15]
licensing fees. And we don't pay the contractor until each
[1:05:18]
building is installed, tested and accepted. All sites are scheduled
[1:05:22]
to be completed by the end of October of this
[1:05:24]
year. The scheduled sites are City Hall. The fire hall,
[1:05:29]
Collins Hall, the pool, public works building, the parks building,
[1:05:33]
the airport, the water treatment plant and the wastewater treatment
[1:05:36]
plant. The Heritage Centre will proceed under a separate agreement
[1:05:40]
with its own grant funding. And the arena may proceed
[1:05:43]
as a future phase. A rough estimate for the arena
[1:05:47]
for six card access doors. Is about 18, 000 dollars.
[1:05:51]
Approving the recommendation today will provide modern auditable access control
[1:05:55]
across the city's principal facilities under a written agreement with
[1:05:58]
smart tech installations limited. And I'm happy to answer any
[1:06:01]
questions. Okay. Thank you Mr. Deshaw. Any questions or comments,
[1:06:06]
councillor men. Thank you worship through you to Mr. DeJon.
[1:06:10]
Thank you very much for your report. I know this
[1:06:12]
has been something that's been in the works for a
[1:06:14]
while. So if we can minimize keys and increase our
[1:06:18]
logging ability to track usage into facilities, especially where we
[1:06:21]
have multi - use agreements with other groups and open
[1:06:25]
facilities, I think this is great. So happy to support
[1:06:27]
it tonight. Okay. Any other questions or comments. Council more
[1:06:33]
set through you, your worship. The only question I have
[1:06:36]
is what happened if there's power outage. To the city
[1:06:42]
or any of those buildings. Can they still access the
[1:06:46]
building somehow? Through your worship, the existing access with the
[1:06:50]
mechanical keys will still be there. It's just the actual
[1:06:53]
entry of the door. That you can use the mechanical
[1:06:56]
keys as a backup. And it always allows you to
[1:06:58]
exit the building in case of a power outage. So
[1:07:00]
the only access is the access in. The access out
[1:07:03]
is always open. Hope that answers your question. Mr. KF.
[1:07:12]
Generator. Are all. Close to after Billy. No, they're not,
[1:07:17]
but the actual swipe door installation have their own backup
[1:07:19]
battery panel. I don't know if it sort of brings
[1:07:27]
the question if there's keypads to get rid of mechanical
[1:07:30]
keys, but then you can still use mechanical keys. Yeah.
[1:07:37]
I understand. Are you going to collect all the mechanical
[1:07:40]
keys that you can before giving out fobs. I think
[1:07:45]
you're a worship. The existing keys that are out there,
[1:07:48]
we can't do anything about, but it will prevent us
[1:07:50]
from having to give keys to new people to enter
[1:07:52]
those buildings. Or change the logs. Yes, correct. Okay. Any
[1:08:01]
other. Sorry just for context. Um, we have had a
[1:08:05]
locksmith in and we are looking at Rekine All Building.
[1:08:08]
So that will be coming to council at a future
[1:08:09]
meeting. Sounds good. Any other questions. Le Fave.
[1:08:19]
Thank you. Your worship through you. I think you mentioned
[1:08:21]
it, but this will streamline this software for all key
[1:08:24]
access doors. Your worship. Yes. That's correct. All under one
[1:08:30]
centralized system for every facility. And we administer that on
[1:08:33]
site, correct? Yes, correct. Perfect. Okay. Any more comments. Okay.
[1:08:41]
Thank you again, Mr. Desha. Tub of a vote, all
[1:08:45]
in favor. Not carried.
[1:08:55]
Back and away. 11. 3. Report from the director of
[1:09:04]
public works regarding RDS 2026 - 01. Surface treatment 2026
[1:09:12]
tender results and additional budget authorization. We have motion that
[1:09:17]
council received the tender evaluation results for contract RDS -
[1:09:21]
2026 - 1, surface treatment 2026. And the Council Award,
[1:09:27]
the contract to Beamers Construction Inc. as the lowest compliant
[1:09:30]
bidder in the amount of 952, 795 dollars in 80
[1:09:36]
cents, excluding HST. And the council approved an additional budget
[1:09:41]
allocation of 203, 927 dollars in 80 cents, excluding HST.
[1:09:49]
To be funded from the public works reserve to fully
[1:09:52]
fund the project based on the submitted tender pricing and
[1:09:56]
that the mayor and Cleric be authorized to execute the
[1:09:58]
necessary contract documents. A mover. Councillor Flintoff, seconded councillor Morris
[1:10:06]
set. And welcome Mr. Derek Young. Our new director of
[1:10:11]
public works. Thank you, you worship. Uh, yes, this is
[1:10:15]
a tender that was issued prior to my arrival. Um,
[1:10:19]
but the closed one I arrived. And the tender results
[1:10:23]
were reviewed. For the work on Null Road and Statenrock.
[1:10:28]
It includes grading, shaping, compacting, placing upcross dashbolt and so
[1:10:31]
forth. Um, the city staff and the consultant TOLOC both
[1:10:37]
reviewed the submitted bids. And decided that the beamish one
[1:10:44]
was the most compliant. Although it was over budget by
[1:10:48]
203, 927, 080 cents, excluding HST. In order to get
[1:10:55]
the work done to mitigate any future damage to the
[1:10:58]
area and the road would recommend that this work be
[1:11:01]
carried out. Okay. Thank you very much. Any questions. Councillor
[1:11:08]
Morset. Through you your worship. Does this work start from
[1:11:12]
the highway down all the way down to DENLOP shore
[1:11:16]
to the end, which is 14 kilometers in? Or is
[1:11:20]
it certain section. Of the nubshore? Because I thought they
[1:11:23]
did some work. In the last two years with grading
[1:11:27]
there. Street year, your worship. Um, this is the first
[1:11:32]
live kilometers. I've done my Lake Road. And I believe
[1:11:35]
it's the first four kilometers of Stamrock that are going
[1:11:38]
to be redone. The score kilometers? Focal Optimus on one
[1:11:41]
and five kilometers under there. So nine o'clock is the
[1:11:43]
total. Flintoff. Thank you, worship, through you. Just a comment,
[1:11:52]
uh, the original approved amount of the 748, 000 dollars
[1:11:59]
for this, but that was all a grant money. Is
[1:12:01]
that right? Through you, uh. No, there is, uh,
[1:12:12]
grand funding for, um, part of. Most of the road.
[1:12:20]
Yes. But, uh, but, uh. Sorry. Sorry, Anna. Maybe I
[1:12:24]
shouldn't have asked. No, no, no, no, no. Could you
[1:12:27]
repeat the question one? Okay, my question is the original
[1:12:29]
748, 000 dollars that we approved. Most of that was
[1:12:34]
grant money. I know the rest isn't. That's correct. So,
[1:12:38]
so that's all from the, uh, the AMO gas tax
[1:12:41]
program. Okay. Great. And in the first report, Mr. Young,
[1:12:47]
um, it was showing, this makes more sense now that
[1:12:51]
you've said this, but it was originally showing four kilometers
[1:12:55]
for dun lobstures and four kilometers for Stanrock. So maybe
[1:12:58]
another reason we're a little bit over. It makes more
[1:13:01]
sense to do the five kilometers because of that then
[1:13:05]
not automatically pair up to the other part of the
[1:13:08]
road that's done. That's correct. Three of you, you worship.
[1:13:11]
That's correct. Okay. That's good. Great. Councillor Seidel. Uh, thank
[1:13:20]
you, worship. But between Councillor Mooret set and councillor Flint
[1:13:25]
off, all my questions are answered. Okay. So one of
[1:13:28]
the things what I wanted to make sure were the,
[1:13:31]
um, TIPN char was going to start right at the
[1:13:34]
high weight and go right to where it was. Downlop
[1:13:37]
shores wrote. So basically the first five kilometers. Well, first
[1:13:42]
five kilometers plus it were already down another four kilometers.
[1:13:45]
So basically the first 10 kilometers of Dunlop shores are
[1:13:48]
going to be tip and shared. Councillor Lefebvre. Thank you,
[1:13:58]
Grisha. 3U. So just to clarify, we're doing the 5
[1:14:02]
kilometers will join to the part that's already been asphalted.
[1:14:06]
And then so how much will be left to do
[1:14:08]
on Dunlop Shores when all of this is said and
[1:14:10]
done. Through your worship. I believe there was another 4
[1:14:14]
kilometers to be done at the end. And then Stanrock.
[1:14:22]
Will be completed or there's still some left there. Too.
[1:14:27]
You'll worship, I'm not sure on that. Gabe, you can
[1:14:29]
come back with that information, but I think there is
[1:14:31]
for sure. Any other questions? Okay. Councillor Seidel. Thank you,
[1:14:38]
your worship through you. Uh, my other question would be
[1:14:40]
for Stanrock Road. Statenrock Road is much wider than what
[1:14:44]
Dunlop Shores wrote. Will it be the whole width of
[1:14:48]
the road or will it just be, um. A set
[1:14:51]
perimeter? How wide is going to be? Three of you,
[1:14:55]
your workshop. It's too much. What's currently there? Okay. So
[1:15:00]
it'll be the whole width of the road then. Yes.
[1:15:03]
Okay. Thank you. And if we pass this this evening,
[1:15:09]
when does the construction start.
[1:15:20]
I think the ACEO. Get your contractor is ready to
[1:15:24]
go. They were looking for permission to start last week.
[1:15:27]
So they're ready to start immediately. Okay. Well, that's even
[1:15:30]
more exciting. Okay. Any other questions. All in favor. And
[1:15:37]
I just carried. Uh, 11. 4 report from the director
[1:15:41]
of Recreation and Culture regarding Parsons, Park and Rogers Arena
[1:15:45]
Retaining Wall. We have a motion that counsel approve 350,
[1:15:50]
000 dollars for the completion of the Parsons Park in
[1:15:53]
Rogers Arena Retaining Wall that the funds be drawn from
[1:15:56]
the buildings and facilities reserve. A mover. Councillor Bo seconded,
[1:16:01]
councillors Le Favre. Ms. Kluck. Thank you, your worship here
[1:16:07]
to provide an update on the Parsons Park Retaining Wall
[1:16:10]
and Bleacher Reconstruction Project and the request for the approval
[1:16:15]
of the additional funding required to move forward with this
[1:16:18]
project. So the project originated from an inspection in late
[1:16:22]
2024 when staff identified structural and safety concerns with the
[1:16:25]
retaining wall bleachers and access area between Park Baldimmond and
[1:16:30]
the south end of Rogers Arena, the area has shifted
[1:16:33]
over time. And the existing wood cribbing and seating has
[1:16:37]
deteriorated beyond lifespan. There's also concerns with fall protection accessibility
[1:16:43]
and drainage from the arena roof, which currently directs water
[1:16:46]
onto the ball diamond, which can result in unsafe plan
[1:16:49]
conditions. One of the most important considerations for this project
[1:16:52]
is that the retaining wall is not simply standalone park
[1:16:56]
structure. And it supports directly or indirectly with the Rogers
[1:17:00]
Arena, including the area containing the washrooms and the entrance
[1:17:05]
of the junior A dressing room. So as a result
[1:17:08]
addressing this infrastructure is important to protecting the arena itself
[1:17:11]
as well. This is the engaged with teleking engineering to
[1:17:14]
assess the area and their assessment confirmed the bleachers were
[1:17:18]
structurally unsound and required reconstruction or replacement. And they also
[1:17:26]
provided a design that would address the structural concerns well,
[1:17:30]
improving the accessibility, drainage, railing, step, and access to the
[1:17:34]
spectator areas on the visitor dugout side. So the project
[1:17:38]
has been brought forward to the Recreational Standing Committee in
[1:17:40]
February, 2025. And as well presented to the accessible advisory
[1:17:44]
committee, uh, in the same month for feedback. Since then,
[1:17:49]
um, because of the connection between the retaining wall and
[1:17:51]
the structure of Rogers Arena staff of engaged with Perry
[1:17:56]
and Perry to oversee this project to ensure that the
[1:17:58]
work is coordinated with the broader arena retrofit. Peri and
[1:18:04]
Perry has obtained updated pricing with the current estimate of
[1:18:08]
the project to be approximately 350, 000. So, um, this
[1:18:12]
approximately includes an approximate amount of 330 for the job
[1:18:16]
with an additional 20, 000 dollar contingency. This would include
[1:18:20]
the earthworks construction work, uh, removals, aswalt, landscaping, uh, galvanized
[1:18:26]
steel handrails and foundation work for the project. This is
[1:18:32]
also an important connection between the project and the planned
[1:18:35]
improvements for the Parsons Park through the J's care grant.
[1:18:39]
So, um, the retaining wall work needs to be completed
[1:18:41]
before the fence and dugout replacements can proceed. This existing
[1:18:45]
fence will need to be removed and it'll allow the
[1:18:49]
retaining access to the retaining wall to take place. And
[1:18:51]
then once that is complete, the contractor for the fence
[1:18:55]
can then begin to, uh, work towards the other field
[1:18:58]
improvements. So, um, originally it was estimated between to be
[1:19:03]
cost between 100 and 150, 000 dollars while we were
[1:19:07]
initially working with TELIC. But at this point after receiving
[1:19:11]
cost estimates, uh, the project is estimated to be 350,
[1:19:13]
000. So ultimately the project is about safety, improving accessibility
[1:19:18]
to both sides of the field and protecting the city's
[1:19:21]
infrastructure. It allows to safely maintain access to the visitor's
[1:19:25]
dugout spectator areas and the washroom while protecting the south
[1:19:29]
end of the Rogers arena and allowing for, uh, planned
[1:19:33]
person park improvements to move forward. So staff are recommending
[1:19:37]
the approval from council for the additional funds to move
[1:19:40]
forward with this project. Okay. Thank you. Uh, any questions
[1:19:44]
or comments. Councillor Bo, thank you, your worship through you
[1:19:48]
to Ms. Kluck. Uh, I agree this work has to
[1:19:51]
be done. I'm just kind of curious how the price
[1:19:54]
jumped from 150, 000 to 200 or 350, 000. Was
[1:20:00]
there something that with Tullic missed the first time. You're
[1:20:04]
your ship. I'm not entirely sure. I think it's when
[1:20:07]
we work with telekin engaged often, it's their estimate of
[1:20:12]
projects they've been working on. And so that was what
[1:20:14]
we used for a foundational for foundation when budgeting. And
[1:20:19]
at this point after receiving the breakdown from, um, Chris
[1:20:23]
Perry, it all broke down from just the handrails itself
[1:20:27]
to being, um, close to 100, 000 dollars. It's just
[1:20:31]
everything, um, is pretty, pretty costly. So. Uh, that's the
[1:20:36]
price difference that we got. Yeah. Follow up. Uh, so
[1:20:42]
we budgeted 85, 000. Is that included in the 350
[1:20:46]
or is that on top? So are we looking at
[1:20:48]
a higher total cost? Um, three worshipped. Uh, it would
[1:20:52]
be, that's a total. So it would be the extra
[1:20:55]
additional 270, 000 or 265, 000. On. That. Okay. That's
[1:21:03]
pretty expensive handrails, I'd say. But thanks. For flintoff. Thank
[1:21:12]
you, our ship 3 to Ms. Klug. When we originally
[1:21:15]
were discussing this back a couple of years ago, if
[1:21:18]
I remember, I think it was basically the retaining wall
[1:21:22]
was only our conversation. Let's repair the retaining model. Let's
[1:21:25]
not safe. When you did your explanation, you were saying
[1:21:28]
landscaping, you know, seemed like a lot more than the
[1:21:33]
original request. So I don't think we can quite compare
[1:21:37]
apples to apples to when the original thing item came
[1:21:40]
in to what you're asking us tonight. That's sort of
[1:21:45]
the way I took it from where you had explained
[1:21:48]
it. And then the other question that I have is,
[1:21:52]
so Jay's cares grant, they will not, they won't come
[1:21:56]
in here until we get the retaining wall, all the
[1:21:59]
accessibility. Cause I don't even think that word came into
[1:22:01]
play on the original retaining wall repair. So you start
[1:22:05]
putting all that into it. It can get to 350.
[1:22:07]
I'm not. So would they wait until we get all
[1:22:09]
that done? Then they would show up after the fact.
[1:22:13]
Um, through you, your worship. So just a comment on
[1:22:15]
the first, about the retaining wall and the earth works.
[1:22:20]
Yeah. We don't want to, we make sure want to
[1:22:22]
make it done right. And that's why we engage with,
[1:22:24]
uh, Chris Perry to, to ensure that it wouldn't be
[1:22:28]
missed because we are moving earth away from, from the
[1:22:30]
facility. We want to make sure that they oversee everything,
[1:22:34]
um, it's not something we were looking at pricing of
[1:22:38]
the bricks itself directly. And we're just with the additional
[1:22:42]
handrails, which was probably one of our question marks. We
[1:22:45]
weren't sure on pricing, but, um, obviously everything did come
[1:22:49]
in at a higher price. But there's option potentially maybe
[1:22:51]
for 20, 000 dollars cheaper to go with a cheaper
[1:22:53]
steel, but then we're looking at painting it and more
[1:22:55]
maintenance throughout the year. So we, we did go with
[1:22:58]
galvanized to decrease maintenance in the air. But, um, and
[1:23:02]
then for your second comment, uh, when applying for the
[1:23:06]
JSCare, this was a big component for, uh, through the
[1:23:08]
grant application was that this will, there is a phase
[1:23:11]
one already going to, uh, improve the access to the
[1:23:14]
field and phase two would be replacing that, that fencing.
[1:23:18]
So we, we can't address the fencing until we get
[1:23:21]
that retaining wall fixed. So we have the six months,
[1:23:25]
which would put us into, we have an additional six
[1:23:29]
months after that contract, which I believe is sometime in
[1:23:31]
November to complete it. So our, our plan with Chris
[1:23:34]
Perry since to get them to do it to complete
[1:23:36]
it in September with the ongoing work that they are
[1:23:40]
doing at the arena. I'm not sure if that pushes
[1:23:42]
it. But with a, we have contractors lined up ready
[1:23:44]
to work in October and are ready to go once
[1:23:48]
we know. But it's just, uh, trying to, trying to
[1:23:50]
get this project approved so we can have more timelines
[1:23:52]
for both to complete them both. Just follow up. I
[1:23:57]
would, I would support this. It is a little more
[1:24:00]
than originally thought, but it sounds like it's a little
[1:24:02]
more of a project. And you tie all that in
[1:24:05]
with the Rogers centre and the G's. It's going to
[1:24:07]
be, it's going to look sharp. People be coming and
[1:24:11]
liking it. Thank you. Councillor Le Favre. Thank you. Where's
[1:24:17]
your two just to add to, um, Councillor Flintoffs. I
[1:24:20]
agree. I think the discussion was when we had brought
[1:24:24]
it to the accessibility committee, the grade wasn't completely accessible.
[1:24:28]
So there was changes in the design which would have
[1:24:30]
added to the additional cost. So we're now going to
[1:24:33]
have bleachers that are fully accessible that follows in line
[1:24:37]
with the entire arena. So the price is justified in
[1:24:40]
my mind. Yeah. I think that's the main thing. Um,
[1:24:47]
he discussed how the front is being done. They want
[1:24:50]
to do it similar to the back. But the slope
[1:24:55]
in the back is higher. So it requires handrails. And
[1:24:59]
it's no joke. They're still handrails. They're super expensive. But
[1:25:05]
I think this project, the way it's set up now,
[1:25:10]
the retaining wall is actually part of the structure of
[1:25:12]
the dugout and support for the fence around home base.
[1:25:20]
This will be all taken out with this project. And
[1:25:23]
then I think that adds more money for our blue
[1:25:26]
jays. Grant money to do more for the dugouts and,
[1:25:31]
and home base and behind. So it is a little
[1:25:36]
more money, but then it's got your right drainage, which
[1:25:40]
was addressed. We're brought up earlier. We wanted to put
[1:25:43]
that together with the grading of the side of the
[1:25:46]
urina. So I think this all ties in nicely. Unfortunately,
[1:25:50]
we'll cost more for the railings is the main thing.
[1:25:54]
But it's going to be great. Councillor Bowl. Oh, two
[1:25:59]
hardship. I'm not against it. I just wanted to make
[1:26:02]
that. Apparent that I think it's a great idea, but
[1:26:06]
we're still going to have, I think we discussed a
[1:26:08]
little accessibility feature. On the bottom for an access to
[1:26:14]
that area for everyone to be able to watch. Yeah.
[1:26:18]
Yeah. Through your worship. Yeah. We have the points that
[1:26:20]
were brought up from the accessibility committee and a lot
[1:26:22]
can be approach or dealt with after the install, but
[1:26:26]
it still, once we know the measurements between the fencing
[1:26:31]
and the slope of the retaining wall, we'll have a
[1:26:33]
better idea to how big of or how high in
[1:26:37]
many rows of bleachers we can also insert. So once
[1:26:41]
we can, and we'll have that integrated seating as well,
[1:26:44]
uh, down below. Okay. Thank you. And also understand that
[1:26:47]
it was going to save us a little bit of
[1:26:49]
money because we're going to be using the same people
[1:26:52]
that are doing the front. Do the back when they're
[1:26:54]
done. And I believe baseball season is done. So the
[1:27:01]
summer summer leagues are, there are some fall leagues, but,
[1:27:03]
uh, they will be based out of the burly fields
[1:27:07]
while we complete these projects. Okay. Any other questions. All
[1:27:13]
in favor that's carried. 11. 5 report from the director
[1:27:22]
of finance and treasure regarding electricity supply agreement with silver
[1:27:26]
birch power corp, uh, migration of residential rate sites to
[1:27:31]
market base pricing through NPN capital markets. We have a
[1:27:35]
motion that council authorized the director of finance and city
[1:27:38]
treasurer to enter into an electricity supply agreement with silver
[1:27:43]
birch power corp. Through the brokerage services of MPN, capital
[1:27:49]
markets to transition all city on sites currently build under
[1:27:52]
the residential electricity price plan to the Ontario electricity market
[1:27:58]
price. And that council authorized the director of finance and
[1:28:01]
city treasurer to execute the supply agreement. And any related
[1:28:04]
documents required to give effect to this recommendation on terms
[1:28:09]
and conditions satisfactory to the director of finance and city
[1:28:13]
treasurer. Mover. Councillor Flint off, seconded councillor of faith. Mr.
[1:28:20]
Alt. Thank you, Merrin. Council. You know in the era
[1:28:25]
of recession, and increasing costs, um, our department, uh, within
[1:28:32]
procurement is focused on taking, uh, operational cost increases or
[1:28:37]
operating cost pressures and transitioning them to operating cost relief
[1:28:42]
or operating cost decreases. Uh, and so, uh, we wanted
[1:28:46]
to, uh, look at, uh, within our operating, uh, budget
[1:28:52]
kind of more generally different areas where we see, have
[1:28:55]
seen some increases to date since January, obviously energy is
[1:29:00]
one of those areas. And we want to find a
[1:29:03]
way that we could save some money, uh, on, uh,
[1:29:07]
in our analysis, uh, with our new procurement department, um,
[1:29:11]
we realised that many of our sites, of course, do
[1:29:16]
have, uh, the commercial rate through hydro one, uh, but
[1:29:20]
many more, uh, do not, um, Hydra one has some
[1:29:25]
pretty strict policy on, on what qualifies as residential or
[1:29:30]
commercial. So HydraONE provides the service. And they also provide
[1:29:36]
the actual energy commodity for all of our sites to
[1:29:39]
date through the government of Mike Harris in 1999, initial
[1:29:44]
steps were taken to deregulate energy, which was completed in
[1:29:48]
2002, uh, to offer consumers, including our city, uh, more
[1:29:52]
choice when it comes to energy. And of course, more
[1:29:55]
competition lowers prices, pretty much all of the time. Uh,
[1:30:00]
in this case, we have a choice not of the
[1:30:03]
service. We still have to buy energy service through HydraONE.
[1:30:07]
But where we have choices in the commodity, the underlying
[1:30:09]
commodity. And through a review of various, uh, energy suppliers,
[1:30:15]
which are privately owned businesses. We've realised a very favorable
[1:30:20]
contract with silver birch power corporation, uh, through MPN capital
[1:30:26]
markets as the broker, uh, which is going to offer
[1:30:29]
us the commodity at the, uh, for lack of better
[1:30:33]
terms, the general rate or the commercial rate. This will
[1:30:36]
lower our amount of energy expense per year. Um, by
[1:30:42]
over 40, 000 dollars. And again, in the era of
[1:30:49]
rising energy costs, of course, indirectly contributing to that, things
[1:30:52]
like the carbon tax, things like the, uh, recessionary economic
[1:30:56]
conditions we currently are seeing is putting pressure on energy.
[1:30:59]
And this takes that bad news and converts it to
[1:31:03]
a piece of good news by, you know, allowing us
[1:31:06]
to hopefully realise some operating surplus. Uh, so, uh, I'd
[1:31:10]
be happy to answer any questions on this report that's
[1:31:13]
going to, uh, lower the expenses of the city. Well,
[1:31:16]
continuing to enable us to meet the demands, uh, of
[1:31:19]
the present state. Thank you. Thank you, Mr. Alt. Any
[1:31:23]
questions or comments, Councillor Maone. Thank you, worship through you.
[1:31:28]
Um, initially, I had some concerns about this. Typically vendors
[1:31:33]
and brokers want there. Slice as well. Um, but I
[1:31:37]
did go and speak to Mr. Realtime Friday regarding this.
[1:31:41]
And he's assured me that, um, there's definitely some savings.
[1:31:45]
What further comforted me this is there is no term.
[1:31:48]
And this can be cancelled at any point in time.
[1:31:51]
So if there are concerns within implementation that it can
[1:31:54]
be easily cancelled. So for that reason alone, I will
[1:31:57]
support it this evening. Thank you. Councillor Flintoff. Thank your
[1:32:04]
ship through you to Mr. Alt. So this is based
[1:32:06]
on the market conditions up for the price of the
[1:32:09]
electricity. Who would there be somebody from the city that
[1:32:12]
would be monitoring and say, Oh, Mr. Alt, our Hydro
[1:32:15]
bill is starting to get a lot higher than it
[1:32:17]
used to be or how would that work? So thank
[1:32:20]
you. So this is a veryte. So this basically, so
[1:32:23]
right now we have a lot of sites that don't
[1:32:25]
consume a lot of energy, right? It's because they're small
[1:32:28]
sites. So we have some that consume a lot of
[1:32:29]
energy. Like Mr. Irving's where he works in the water
[1:32:33]
treatment plant. That consumes a lot of energy. So it's
[1:32:36]
already at the commercial rate. Other facilities like here in
[1:32:40]
City Hall don't really consume that much energy. We don't
[1:32:43]
really have too many machines here. And so because of
[1:32:45]
that, we're actually built at the residential rate. And there's
[1:32:48]
about a two cent per kilowatt. Difference. And that adds
[1:32:53]
up quite substantially. So what we're saying is, well, Hydro
[1:32:56]
1 and we have tried because we don't meet the
[1:32:59]
thrust hold for energy use at this site. We're not
[1:33:02]
billed as a customer where build as 65 different customers.
[1:33:06]
Because of every site has their own account with HydraONE.
[1:33:09]
So on all the smaller sites, we don't qualify for
[1:33:12]
the cheaper rate through the monopoly of HydroNot, not as
[1:33:17]
a service, but as the commodity. So what we're saying
[1:33:20]
is, uh, with silver birch power, we negotiated them to
[1:33:24]
offer the energy to us at whatever the Ontario Energy
[1:33:27]
Market Rate is. So it is a variable rate that
[1:33:30]
will be the same as the commercial rate. So I
[1:33:33]
would move the same as our commercial sites do. We
[1:33:35]
give, I think it's two 100th of a cent per
[1:33:39]
kilowatt hour as a commission. Uh, which is outlined in
[1:33:43]
the, uh, in the report. And of course, this is
[1:33:46]
a month - to - month contract. But compared to
[1:33:48]
what we were able to do, uh, with HydroNowON directly,
[1:33:51]
there was savings. And compared to the other contracts, they
[1:33:53]
would have had us locked in at fixed rates, which
[1:33:55]
of course open us up to uncertainty. And for long
[1:33:58]
periods of time. This is a matching contract. It matches
[1:34:03]
the Ontario energy market price. And it's months to months.
[1:34:06]
So if we have any issue with customer service, we
[1:34:08]
can cancel at any time, then go back to the
[1:34:10]
way it was. Uh, but this again is making use
[1:34:13]
of the competitive forces to lower, uh, costs incurred by
[1:34:17]
the city that ultimately lowers taxes. Great. Thanks. We'll explain.
[1:34:26]
The faith. Thank you. We're ship through you. Just kudos
[1:34:30]
to the procurement team for, you know, looking at ways
[1:34:33]
to save on operational cost. So I think, you know,
[1:34:36]
I think it's job well done. Any other questions. Okay.
[1:34:44]
All in favor. That's carried. Uh, memo from the director
[1:34:51]
of finance and treasure regarding digital system analysis, ERP replacement
[1:34:56]
project. Status update and revised delivery timeline. We have a
[1:35:01]
motion that the memo from the director of finance city
[1:35:03]
treasurer regarding digital systems and analysis, ERP. Placement, project status
[1:35:09]
update and revised delivery timeline B received. Uh, move. Councillor
[1:35:14]
Bowe, seconded councillor Morset. Mr. Alt. Thank you Mayor and
[1:35:20]
council and through all of you tonight. Uh, you know,
[1:35:22]
uh, as you know, our city operates with a digital
[1:35:26]
infrastructure system, which we call an enterprise resource planning system
[1:35:30]
or ERP. This system controls pretty much everything. It has
[1:35:35]
payroll functions, procurement functions, uh, accounts payable and receivable taxes,
[1:35:40]
water, uh, pretty much all of the information that comes
[1:35:44]
in to City Hall in some way touches the ERP
[1:35:48]
system. Uh, our ERP system was a class leading ERP
[1:35:53]
system, uh, for much of its useful life. And we've
[1:35:56]
had great planes here at our city, uh, for more
[1:36:00]
than two decades. Um, obviously technology has changed rapidly, especially
[1:36:05]
in the past five years with the growth of AI
[1:36:08]
and other ways and new ways of managing information too.
[1:36:12]
So that we take, uh, take more insights from the
[1:36:15]
data. And, uh, great planes is of course at its
[1:36:19]
end of life. As we discussed in the capital budget,
[1:36:22]
we did put money in there to do a digital
[1:36:24]
systems analysis because as we move from what is an
[1:36:28]
on - prem or on - premise, uh, EOP system
[1:36:31]
to something in the cloud, uh, you know, the vendors
[1:36:34]
that all offer something very, uh, unique. And there aren't
[1:36:38]
actually many cities in Ontario that have moved to a
[1:36:41]
new system quite yet, despite the end of life date
[1:36:44]
for great planes, fast approaching. So to make sure that
[1:36:48]
we do the job and we do the job right.
[1:36:51]
We engaged MNP, which is a global, uh, firm based
[1:36:56]
in Canada. Uh, that specializes in accounting and digital, uh,
[1:37:00]
cloud financial systems. And we engaged this team, uh, experts
[1:37:06]
from, uh, on our team include people, uh, such as
[1:37:11]
Wendy, Guinez, who was the former chief technology officer of
[1:37:16]
the city of Edmonton. We have individuals also on the
[1:37:21]
team that are emerging leaders in technology that come with
[1:37:24]
backgrounds and computer science, business analytics. Um, and even finance
[1:37:29]
and accounting. And, uh, we, uh, want to make sure
[1:37:33]
that we do, uh, a job where everybody's voice at
[1:37:36]
the city is going to be heard. So in dealing
[1:37:38]
with the scope of that project, uh, we want to
[1:37:41]
make sure, uh, that there was sufficient time to understand
[1:37:44]
where the city is currently at before we start talking
[1:37:48]
about where we want to go. And so the, uh,
[1:37:52]
timeline that was ultimately agreed in this project is well
[1:37:55]
underway in interviews have already, uh, occurred. The timeline has
[1:37:59]
us ending in January. So the final report would be,
[1:38:03]
or a draft report would be ready at the end
[1:38:04]
of December. And then obviously, uh, council presentation and some
[1:38:09]
revisions and such made in January. And so with that,
[1:38:14]
we just want to update you on the timeline. Initially,
[1:38:16]
we were targeting an earlier timeline. But again, we wanted
[1:38:20]
to make sure there was sufficient understanding of the current
[1:38:23]
state and the current workflows, uh, before we start talking
[1:38:26]
about, um, the future state and the future workflows. And
[1:38:30]
this, I think, would help change management at the city.
[1:38:33]
So this is the bones of the city. It's the
[1:38:36]
backbone of the city. All information coming into city hall
[1:38:39]
rather be your water bill or tax bill or even
[1:38:41]
internal matters, um, in some way, shape or form flows
[1:38:44]
through the ERP. So we want to make sure we
[1:38:46]
do a really good job at ensuring that whatever it's
[1:38:49]
selected works, uh, with that, I just wanted to give
[1:38:53]
a memo to council, uh, and also thank our director
[1:38:57]
of information technology Robin Scott as for all of the
[1:39:01]
time and effort to also often this file. Thank you.
[1:39:04]
Okay. Thank you. Any questions or comments. Of help.
[1:39:15]
Thank you. Worship through you. Uh, thank you for this
[1:39:17]
update. This project's been something I've been keeping an eye
[1:39:20]
on. This is probably the largest IT project undertaking this
[1:39:25]
city will ever take. So we have to be very
[1:39:27]
careful that we walk slowly and not try and boil
[1:39:31]
the ocean. Um, so I'm glad to see that we're
[1:39:35]
engaging some experts from across the country that have experience
[1:39:38]
with city, uh, IT. So I would support you're not
[1:39:45]
asking for support. But I think having the additional time
[1:39:48]
to make sure that work is done properly is very
[1:39:51]
prudent. Any other questions or comments. Okay. All in favor.
[1:40:01]
Let's. Carry it. Uh, there's no presentation of committee reports
[1:40:07]
unfinished business 13. 1. Report from the Museum Creator. Cuorator.
[1:40:15]
Take a lot fast. Regarding letter monument installation location of
[1:40:20]
a motion, the council approved the updates to the project
[1:40:23]
plan for the proposed public art letter monument. And that
[1:40:27]
council approve option B is the site for the proposed
[1:40:29]
public art letter monument to be located within the green
[1:40:33]
belt adjacent. To the shoulder of how we 108 near
[1:40:37]
the intersection of Highway 108 and hillside drive north. Uh,
[1:40:42]
mover. Second did councillor ball. Mr. Mato, please. Thank you
[1:40:50]
through you your worship and good evening to you in
[1:40:52]
all of council. At the last meeting of council in
[1:40:55]
July, we presented a public art initiative on behalf of
[1:40:58]
the Arts and Culture Working Group. This project consists of
[1:41:02]
individual coloured steel letters, spelling Elliott Lake, which each with
[1:41:06]
each letter standing approximately five feet in height and the
[1:41:09]
entire structure spanning approximately 42 feet in length. The original
[1:41:13]
location proposed for this project was the hillside at the
[1:41:16]
intersection of hillside drive north and Highway 108 chosen for
[1:41:21]
its vantage point and the fact that the letters would
[1:41:23]
be legible, both driving up and down hillside drive north
[1:41:27]
as well as north on Highway 108. This location, however,
[1:41:31]
raised some safety concerns as it was anticipated people would
[1:41:33]
cross the street to access the structure for photo opportunities,
[1:41:37]
while the project itself was approved in principle. Um, staff
[1:41:40]
were directed to return to council with alternate location options
[1:41:44]
for consideration. Staff in the working group surveyed many potential
[1:41:47]
sites to see if they met the criteria that the
[1:41:50]
structure would be located on our property in a high
[1:41:53]
traffic area that it would be, I have a visually
[1:41:55]
appealing backdrop and that it would not obstruct the view
[1:41:58]
of drivers. We wanted the structure to be in proximity
[1:42:02]
of a sidewalk or pathway accessible to anyone who wanted
[1:42:05]
to take photographs as well. Due to the approximately 42
[1:42:09]
foot span of the structure, individuals would need to stand
[1:42:12]
approximately 33 feet away to capture the entire art piece
[1:42:15]
in a photo taken on any, basically any standard camera
[1:42:19]
or mobile phone. With this in mind, staff would like
[1:42:22]
to present three options to council for deliberation on the
[1:42:25]
installation site. Option A is the original proposed location on
[1:42:30]
the hillside of hillside drive north and highway 108. Well,
[1:42:33]
the elevation of this location provides high visibility. The sidewalk
[1:42:36]
is on the opposite side of the street from the
[1:42:37]
structure. So individuals would need to take photographs from further
[1:42:40]
away causing the letters to look smaller in scale, which
[1:42:43]
may not be ideal. Option B is the recommended option
[1:42:47]
of staff and the working group, which would see the
[1:42:49]
structure installed within the green belt adjacent to the shoulder
[1:42:52]
of highway 108 near the intersection of Hyway 108 and
[1:42:55]
hillside drive north, basically across from the chev wheel. Well,
[1:43:00]
with this option, the letters would only be legible from
[1:43:02]
Highway 108. And you would see the back of them
[1:43:05]
while travelling down, uh, hillside drive north. The letters would
[1:43:09]
still be highly visible and appear larger as they are
[1:43:11]
not high on the hill. This option would also allow
[1:43:14]
individuals to capture photos safely from the walkway adjacent to
[1:43:17]
highway 108, allowing closer proximity to the structure. Option C
[1:43:22]
was proposed during the public input session of the July
[1:43:25]
27th Council meeting and would see the structure installed within
[1:43:28]
the green bell to adjacent to the shoulder. By 108.
[1:43:31]
But on the opposite side of hillside drive north across
[1:43:35]
from the minors Memorial. Staff do like this location. However,
[1:43:40]
installation would need to be a top or retaining wall,
[1:43:42]
which we do not know the longevity or the integrity
[1:43:45]
of. And the adjacent walkway is a bit too close
[1:43:47]
to the structure that you would not be able to
[1:43:49]
capture the entire structure in a photo taken with a
[1:43:52]
standard like mobile phone when you're using the walkway unless
[1:43:56]
you're taking it, um, at an angle or across the
[1:43:59]
street in the minor's Memorial parking lot. The green belt
[1:44:02]
in option B does allow us to push the structure
[1:44:05]
back a bit further to allow for better photocap string
[1:44:07]
capabilities. But the tree line in the backdrop of option
[1:44:10]
C does prevent this. It should be noted that with
[1:44:14]
all options, the closest city parking facilities to all three
[1:44:17]
proposed locations is at the minor's Memorial Park. So individuals
[1:44:21]
wanting to access the structure in closer proximity would be
[1:44:24]
required to cross the highway if they were driving and
[1:44:27]
wanted to park to visit the structure. On further note,
[1:44:30]
staff wanted to inform council of some design changes to
[1:44:33]
the project. Originally, each letter was to be decorated with
[1:44:37]
black decals, which depicted different designs celebrating Elliot Lake, like
[1:44:40]
iconic landmarks, natural landscapes, wildlife and recreational activities. These designs
[1:44:45]
were to be based off of the artwork of Linda
[1:44:48]
Finn as this art project is being completed in her
[1:44:50]
honour from funds that were donated in her memory. As
[1:44:54]
staff worked with the working group to narrowed down silhouettes,
[1:44:56]
it did become a parent that the original vision would
[1:44:59]
likely not transpose properly to the final product. With the
[1:45:02]
DECL designs looking obscure or messy from a distance. And
[1:45:05]
perhaps compromising the legibility of the letters. Another deficit of
[1:45:09]
the silhouettes is that it would pay improper homage to
[1:45:13]
Linda's work, which is so recognisable due to her techniques
[1:45:16]
colours and skills, boiling them down to just silhouettes or
[1:45:19]
line art kind of detracts from her skill and doesn't
[1:45:24]
make it identifiably Linda Finn's work. So instead, the working
[1:45:27]
group would like to install Memorial Bench in plaque accompanying
[1:45:30]
them monument to honour Linda's legacy and her contributions to
[1:45:34]
the community. These changes to the project scope do not
[1:45:37]
affect the approved budget of the project as the fees
[1:45:40]
for the bench or the decals are virtually interchangeable. In
[1:45:44]
summary, the purpose of this report is to have staff
[1:45:47]
is to have council approve these updates to the project
[1:45:49]
plan and to recommend option B as the installation location
[1:45:53]
to have it installed within the green belts adjacent to
[1:45:56]
highway 108 near the intersection of Highway 108 and Hillside
[1:45:59]
Drive North. Thank you so much for your time and
[1:46:02]
let me know if you have any questions. Okay. Thank
[1:46:04]
you very much. Any questions or comments. Councillor Morset. You
[1:46:12]
worship, I got, um, two questions. First, will the project
[1:46:17]
be done. By the fall like we wanted it to
[1:46:20]
have it done. Three of your worship to Councillor Morisset.
[1:46:25]
I can confirm that KES have already started manufacturing the
[1:46:29]
letters and our plan is still for a fall installation
[1:46:32]
if everything goes according to our timeline. And the second,
[1:46:37]
um, still going to be some potential people crossing the
[1:46:42]
highway. Could there be some kind of signage. Alerting the
[1:46:48]
people maybe to slow down or crosswalk or watch for
[1:46:52]
pedestrian type signage put up. Uh, around that area. Do
[1:47:00]
your worship. That's not something I have an answer for
[1:47:02]
immediately, but definitely something we can look into to increase
[1:47:05]
the safety of the overall project. Thank you. That's a
[1:47:10]
friend of. That. Thank you, worship more of just a
[1:47:14]
comment. I like the new location. Uh, and at the
[1:47:17]
end of the day, all three are good. But any
[1:47:21]
way you take this, you're crossing the highway. So I
[1:47:25]
think by going over there, you can save some money,
[1:47:29]
get a Memorial bench, people can sit. It seems a
[1:47:31]
little bit more out of the way. And, uh, I'd
[1:47:35]
support this. Thanks. Councillor Seido. Uh, thank you. You worship
[1:47:41]
through you. Um, I like council Flint off. I do
[1:47:44]
agree with this area. I think it's before hillside north
[1:47:49]
where you turn up. Um, a couple of questions that
[1:47:52]
I have. One would be have we got any locates
[1:47:56]
and is there any critical infrastructure underneath this. For one
[1:48:01]
question. And the second would be, how are we attaching
[1:48:04]
this as a ground? Are we, this is going to
[1:48:06]
be a hundred percent permanent. And are we going to
[1:48:09]
go down to attach these below the frost level. You're
[1:48:14]
your worship to address the first question. Locates have not
[1:48:17]
been completed at this time. But once we do select
[1:48:19]
the final location, we'll perform all the necessary assessments and
[1:48:23]
locates needed. And, uh, we're pretty sure that we'll be
[1:48:28]
able to find like a feasible location within that green
[1:48:30]
belt, even though it's not maybe directly where the conceptual
[1:48:34]
design indicates. But, um, we're hoping that we could find
[1:48:37]
a suitable area for installation. And then if not, we
[1:48:40]
would of course move to another. We would still proceed
[1:48:42]
with a project at another reasonable location. And then for
[1:48:47]
the second question, um, the letters will be installed through
[1:48:54]
Sono tubes. The idea is to have them permanently installed.
[1:48:57]
They will be fixed. We won't be removing them during
[1:49:00]
like the winter season, for example. They will be permanently
[1:49:03]
installed. However, the way that they are installed is that
[1:49:06]
there will be like welded metal rods at the base
[1:49:09]
of each letter that will connect into tubes permanently cemented
[1:49:12]
in the sono tubes and bolted in. So there is
[1:49:15]
the opportunity to remove them if for whatever reason we
[1:49:18]
have to do maintenance and whatnot. And I do believe
[1:49:22]
that they have taken into consideration the frost level. That
[1:49:26]
would be down to our installation team, which is being
[1:49:28]
done in - house, uh, through our parks department. Um,
[1:49:31]
and we'll make sure that we do all those necessary
[1:49:35]
background checks and whatnot. Okay. Thank you. Any other councillor
[1:49:41]
Lefebvre? Thank you, worship through you. I would agree with
[1:49:45]
Councillor Flintolf. I think no matter where this location is,
[1:49:49]
there will be people trying to attempt to get across
[1:49:51]
the highway. Um, I do like the better location. And
[1:49:56]
kudos to your team. I think you presented the feedback
[1:50:00]
was well received. You went and looked at alternate it
[1:50:04]
alternative options. And you presented something that we hadn't even
[1:50:07]
thought of in the past. So kudos to your team
[1:50:10]
and I liked a new location. Thank you,
[1:50:19]
yourship, through you. Uh, I think it's a good location.
[1:50:25]
And is it going to, how close it will, you're
[1:50:27]
not sure exactly where it's going to be located. It'll
[1:50:29]
be further away from the pathway. And he rough idea
[1:50:33]
how far. Through Ju Yourship approximately 33 feet is what
[1:50:39]
we're aiming for. It is dependent on, of course, locates
[1:50:43]
and where the parks deems the most suitable. Um, the
[1:50:46]
area is relatively flat. So we do have a lot
[1:50:48]
of room to play around with on that particular green
[1:50:51]
belt. And, um, we're kind of aiming for the 33
[1:50:53]
feet because that's the minimum capture distance that we've calculated.
[1:50:57]
So we'll make sure that when we're installing, we'll do
[1:51:00]
once the structure is actually completed, we'll have the very
[1:51:03]
accurate, um, total length. Right now it's estimated at approximately
[1:51:06]
42 feet. So perhaps that capture distance will be reduced
[1:51:09]
if, for example, the letters are convened installed closer together.
[1:51:13]
Um, but right now we're aiming for vote 33 feet
[1:51:16]
away from the pathway. Okay. Thank you. And have you
[1:51:19]
thought about any kind of maybe some solar lighting to
[1:51:22]
light it up at night? So maybe deter. Certain individuals.
[1:51:29]
From damaging it or? Yes. That's definitely something we've considered.
[1:51:34]
And it depends perhaps with contingency. We'll have enough room
[1:51:37]
in the budget to develop that this year. Or if
[1:51:40]
not budget for it in future years. Okay. Thank you.
[1:51:45]
Yeah. I like the, the, the B location. It sets
[1:51:49]
up well for this, but also I guess in the
[1:51:53]
future with the historical society considering having little monuments or,
[1:52:00]
um, updates of the history of LA Lake. You could
[1:52:05]
be putting on some of the silhouettes from Linda Finn
[1:52:09]
in and around the park. Like as an expansion down
[1:52:12]
the road. So there's lots of room there. When you
[1:52:15]
do your locates, check everywhere. And then, uh, but yeah,
[1:52:19]
we can start with this. I think it's good. Let's
[1:52:23]
have a vote all in favor. Not carried. Thank you.
[1:52:32]
Uh, there's no notice of motion. General announcements. Earlier this
[1:52:38]
month, we wished local athlete Tyreen Assir. Well, as she
[1:52:43]
headed off to Resent Elliot Lake and Ontario at the
[1:52:47]
special Olympics, Canada summer games in medicine, hide Alberta. And
[1:52:52]
Tyrena returned with some brand new hardware. She had an
[1:52:57]
amazing performance claiming gold in the four by 400 metre
[1:53:01]
relay. Um, she claimed bronze in both the 400 metre
[1:53:07]
and many Javelin events. And also an impressive fourth place
[1:53:13]
finish in the running long jump. So please join us
[1:53:16]
in celebrating such extraordinary hard work and dedication. Tyrena, you
[1:53:22]
competed and represented Ontario and Elliot Lake with class and
[1:53:27]
sportsmanship. And we are all proud to help you celebrate
[1:53:30]
your accomplishment. Congratulations. And Councillor Man. Thank you, Risher. Um,
[1:53:39]
just to advise, um, I was able to attend or
[1:53:44]
on behalf of ADSAP last week at the, uh, the
[1:53:47]
annual AMO conference. I was able to attend a couple
[1:53:50]
of municipal delegations with Councillor Bowe. And I just want
[1:53:54]
to acknowledge Mr. Antunes for the work he did on
[1:53:56]
the four delegations we had with ministry stuff. Thank you.
[1:54:01]
Thank you. Whether or. Announcements. Okay. There's no addendum. Introduction
[1:54:09]
and consideration bylaws. 17. 1 bylaw 26. Or dash 52.
[1:54:19]
Being a bylaw to authorize an extension agreement with beamish
[1:54:22]
construction for the landfill site operations for the period of
[1:54:25]
July 1st, 2026 to December 31st, 2026 may have a
[1:54:31]
motion, a bylaw - 26 - 52 be passed. A
[1:54:35]
mover. Councillor fave, second did councillor sidal, all in favor.
[1:54:41]
That's carried. And 17. 2 by - law - 26
[1:54:46]
- 53 being a by - law to authorize entering
[1:54:50]
into an agreement with SmartTEC installations limited for card access
[1:54:54]
controls, supply and installation. We have a motion that Bylaw
[1:55:00]
26 - 53 be passed. Mover. Council LeFab, seconded councillor
[1:55:06]
Flint off, all in favor. That's carried. Close session. There's
[1:55:12]
one item for closed session this evening. Um, memo from
[1:55:15]
the Manager of Economic Development regarding letter of intent to
[1:55:18]
purchase land on Oakland Boulevard July 2026. As this matter
[1:55:23]
deals with a proposed or pending disposition of land by
[1:55:27]
the municipality or local board may be discussed in closed
[1:55:30]
session as per provisions under section 239 2C of the
[1:55:35]
Municipal Act 2001. We have a motion, a council proceed
[1:55:40]
into closed session as per the provisions under Section 239,
[1:55:45]
the municipal act at the hour of 854 PM. Mover.
[1:55:52]
Councillors, uh, Lefebvre, seconded councillor Bo, all in favor. That's
[1:55:58]
good.
[2:14:31]
Okay, I have a motion of the council returned to
[2:14:33]
open session at the hour of 913 PM. Movert. Councillor
[2:14:38]
five, second did councillor Bowe, all in favor. It's carried.
[2:14:43]
Confirmatory bylaw, I have a motion that Bylaw 26 -
[2:14:47]
54 be passed. Mover. Councillor Marsette, second did Councillor Man,
[2:14:54]
all in favor. That's carried. Adjournment, we have a motion
[2:14:57]
that the meeting adjourned at the hour of 913 PM.
[2:15:01]
Movert. Councillor Marsette, seconded councillor flintoff, all in favor. That's
[2:15:08]
carried. Thank you very much.