Agenda
Agenda: https://highlandca.api.civicclerk.com/v1/Meetings/GetMeetingFile(fileId=7737,plainText=false)
Full agenda packet (agenda plus every staff report and attachment): https://highlandca.api.civicclerk.com/v1/Meetings/GetMeetingFile(fileId=7736,plainText=false)
Transcript
SOURCE TRANSCRIPT
This transcript is downloaded from the source you provided but we haven't reviewed it for accuracy. Treat it as a starting point, not a verbatim record. You can also request an AI-transcription of the audio file with the button to the left.
These are YouTube's auto-generated captions, not a human transcript — expect occasional errors, especially with names and technical terms.
This transcript looks garbled at the source (not a parsing bug on our end) — treat it as approximate.
This transcript looks garbled at the source (not a parsing bug on our end) — treat it as approximate.
[0:02]
Good evening. We're going to uh call our
city council special meeting to order
[0:06]
for August uh 25th, 2026. And right now
the time is 5:30 p.m.
[0:12]
Uh we want to welcome everyone here in
the audience and and at home. Our first
[0:18]
business order of business is roll call.
[0:22]
» Councilmember Hogan?
>> Here.
[0:24]
» Councilmember Lilburn? She has an
excused absence due to a conflict of
[0:28]
interest requiring recusal from the sole
item on tonight's agenda.
[0:33]
Councilmember McMillan?
>> Here.
[0:35]
» Councilmember Saldana?
>> Here.
[0:37]
» And Councilmember Timber?
>> Present.
[0:40]
» All right. At this time, we are going to
move on to public comment and I'm going
[0:45]
to look to uh our city clerk to read us
into public comment.
[0:49]
» Thank you, Mayor Pro Tem. At this time,
we will open the public comment period.
[0:52]
Members of the public may address the
city council matters that are within the
[0:55]
city's jurisdiction and they're only
listed on the agenda. I don't see any
[1:01]
public speakers um remotely or in
person.
[1:05]
» Okay.
>> And no emailed public comments either
[1:08]
submitted by email.
>> Excellent. Thank you. Okay, we're going
[1:11]
to move on to the uh legislative item on
the agenda, actions related to the
[1:15]
Highland Senior Center HVAC systems. And
I'm going to look to Octavio for a
[1:19]
presentation.
>> Good evening, Mayor Pro Tem, city
[1:23]
council. Uh tonight we'd like to provide
an update on the Highland Senior Center
[1:26]
HVAC project and uh seek direction from
the council regarding completion of the
[1:31]
project using uh CDBG and additional
city funds.
[1:35]
Um as a reminder, uh city's awarded uh
about $180,000 in CDBG funding through
[1:42]
the county in 2024 and this is part of
um COVID relief funds and um the um
[1:51]
the purpose of that grant, the county
suggested
[1:54]
um the Highland Senior Center as a
viable candidate for for those funds. Uh
[2:00]
So, the project was intended to address
the Highland Senior Center's three
[2:04]
existing
HVAC systems, aging system.
[2:08]
This project was seen as critical given
it serves our senior community and it's
[2:13]
also one of two cooling centers in the
region.
[2:17]
Or if you know, that's open to our
Highland
[2:20]
residents.
This project facilitated by the city
[2:25]
and the grant requires that all work be
completed by September 30th
[2:30]
in order to
you know, get costs reimbursed.
[2:35]
Since the approval,
the project's encountered um
[2:40]
challenge after challenge,
unforeseen circumstances.
[2:44]
When we first started the project, it
was intended to be a
[2:48]
really a like-for-like replacement.
We took a look at the existing
[2:53]
equipment, worked with the
the vendor, the manufacturer of that
[2:58]
equipment and we asked for proposal to
really replace those units in kind. At
[3:04]
the time,
we received a proposal to replace all
[3:08]
three systems for about $120,000.
Concurrently,
[3:14]
because this this was on a
the building is owned by the state, we
[3:18]
needed approval from the state to move
forward with the project. You know, fast
[3:22]
forward after you know, a couple years
of coordination,
[3:26]
we were finally given direction to
provide engineered plans and receive
[3:32]
approval from the state fire marshal. Um
This happened roughly this past spring.
[3:39]
Because time was of the essence, so even
though I said the
[3:43]
the grant expires or the deadline for
the grant was September is September
[3:47]
30th,
at one point in time it was June 30th
[3:51]
and we were able to get an extension to
keep the project alive, keep it going
[3:54]
given the circumstance.
Um so that's one important important
[3:57]
piece there as far as timing's
concerned.
[4:00]
Uh so because time was of the essence,
uh we engaged one of our on-call
[4:04]
engineering firms, WSP, who's
uh well-versed in this type of work, has
[4:09]
worked with the state getting approvals
from the State Fire Marshal office.
[4:13]
And um
uh we received we we completed those
[4:18]
those plans and we received approval
from the state. Uh but that effort alone
[4:21]
was uh roughly $43,000.
Um and um
[4:27]
once we had those plans in place, we
reached out to a carrier who had
[4:30]
provided the proposal prior. And uh we
determined that
[4:35]
uh the the cost had significantly
increased due to additional items that
[4:40]
the state required to be
uh done for the project. So it was no
[4:44]
longer a like-for-like uh you know, in
kind replacement. We had to do a bunch
[4:48]
of duct work and um
uh other uh construction-related items
[4:53]
to to meet the the state requirement. Um
uh but all hope was not lost. Um we
[4:59]
pivoted rather than focusing on three
systems like we initially planned.
[5:04]
Uh we were able to still um
you know, deliver a project and and
[5:08]
deliver two systems, uh or so we
thought.
[5:12]
Um
Once we reached out to uh Carrier uh
[5:17]
to move forward with with a new proposal
that had given us um
[5:21]
uh for the two systems,
uh
[5:24]
they let us know uh that equipment was
no longer available and it would take uh
[5:29]
about 12 weeks to actually get that
equipment. Uh that wouldn't work with
[5:33]
the timeline of the grant, so we had to
pivot once more.
[5:37]
Um
we engaged our engineer and um other
[5:41]
uh vendors to try to find an alternate
substitute for for these systems or for
[5:46]
the HVAC system.
We were able to uh
[5:49]
find that train
um would be able to provide alternate
[5:54]
units and they were, you know,
ready,
[5:58]
um available, and they could deliver it
within the grant timeline.
[6:02]
Um the the issue was um
they couldn't secure the
[6:09]
piece of equipment without a signed
purchase order. Given the experience
[6:13]
that we had had with Carrier,
uh we moved forward with signing a
[6:17]
purchase order for just one system
um because there was an unknown of of
[6:22]
labor. Uh they were concurrently
reviewing the scope
[6:27]
uh make sure that they uh
uh gave us a an accurate labor cost for
[6:32]
the installation of that unit and we
also um asked for quotes for for the
[6:36]
rest of the the systems.
Uh unfortunately, the cost of all three
[6:41]
systems, um much like before, was beyond
the budget um and uh we focused on a
[6:47]
single system.
Um
[6:50]
and um
you know, uh to our surprise, the the
[6:54]
cost of that single system had increased
significantly compared to the cost that
[6:59]
we had seen before.
Uh for that single system, just the
[7:02]
labor uh was $156,000.
So, combined with the equipment that we
[7:08]
had reserved,
uh we were looking at $191,000
[7:12]
for one of three systems.
Um
[7:16]
so, uh the the total project cost,
including engineering, permits,
[7:23]
um and a you know, we're
um
[7:28]
we're requesting a 20 uh roughly a 10%
contingency, so $20,000,
[7:33]
uh you're looking um uh
a deficit of roughly $81,000
[7:41]
um uh, to to able to complete a single
system.
[7:45]
Um, and and that's that's really where
we are right now. Um,
[7:50]
to date we've spent, uh, $55,000 on on
this project and
[7:56]
uh, one important consideration is that
uh, so not only do we have the grant
[8:00]
deadline, uh, but one piece that's, uh,
required is that we deliver the project
[8:04]
to be able to,
uh, get the, uh, the money that we've
[8:08]
already spent reimbursed.
Um,
[8:12]
when you take out the $20,000
contingency, uh, the cost of moving
[8:17]
forward with the project is $61,000.
Um, and um,
[8:24]
you know, with that, I you know, I'd
like to conclude my presentation and
[8:27]
open it up to any questions you might
have.
[8:32]
» I I
uh, Mr. Chair,
[8:34]
I'm confused.
Uh,
[8:38]
I was reading the list of, uh, of, uh,
materials and it looks like there's a
[8:43]
air conditioning unit and a heat pump.
Are they two separate units or one
[8:49]
together?
>> So, um, I'll I'll I'll provide, uh,
[8:53]
a response, but I also have Jim
Richardson here who's, uh, I call him an
[8:57]
HVAC expert and can better explain it.
Uh, but how it works, it's it's a
[9:02]
system. So, I think I probably used unit
and system interchangeably. So, you have
[9:08]
three systems and you have a combination
of
[9:13]
um, two to four units per system. It's
kind of depends on the build. Uh, so,
[9:20]
uh, in this particular case, we would
be, uh, if if the council chooses to
[9:24]
move forward, we would be completing uh,
one of the three systems. I I believe it
[9:30]
was, you know, three units, both heating
and ventilating and, uh, air
[9:33]
conditioning.
>> So,
[9:35]
so we're in essence we're replacing unit
with a heat pump,
[9:40]
which does air conditioning and heating
at the same time.
[9:43]
» Yeah, I'll I'll call Jim who can better
explain it.
[9:52]
» You got to turn the mic on.
[9:57]
» So, uh the unit that's being replaced
that is uh still in this uh
[10:04]
request is a Trane.
The outdoor unit is a Trane
[10:09]
uh condenser and the indoor part is make
made up of two
[10:15]
uh
fan coil units that are sistered
[10:18]
together
into one uh plenum
[10:22]
and it's because of the space that's in
the building is limited. So, it actually
[10:26]
takes two units inside to two five-ton
units inside
[10:32]
uh fan coil units
that are coupled with the outdoor 10-ton
[10:37]
unit.
If that makes sense.
[10:42]
» Well, I
I don't understand, but but uh I know uh
[10:47]
at AQMD, we're trying to get everyone to
use heat pumps instead of H you know,
[10:52]
air conditioning systems.
But,
[10:56]
» I can confirm that it is uh it's all
electric heat pump. It's We The existing
[11:01]
unit is gas electric and the new unit is
all electric.
[11:06]
» Okay. Okay.
Thank you.
[11:08]
Question uh for
Tish, I guess. The uh 81,000
[11:14]
is it that's coming from our general
fund?
[11:20]
» Yeah, it would come from the general
fund because we can't use special
[11:23]
revenue funds to fund a project like
this. You can only use general fund. So,
[11:28]
we'll be using our general capital
financing fund
[11:31]
technically.
If you choose to do so.
[11:34]
» Being reimbursed by community
development.
[11:36]
» We're only being reimbursed for 178,000
and some change, and the rest is what we
[11:42]
have to actually pay out of pocket as
is.
[11:44]
» And we're paying for a project that's
not in the city?
[11:46]
» Correct.
But it directly benefits our residents
[11:50]
is why we're allowed to actually even
consider it. Yeah.
[11:54]
Only from the general fund money. We
can't use any of our special revenue
[11:57]
accounts to fund it.
>> Um I have a question for Octavio and and
[12:02]
I guess Jim.
Um so you you mentioned that we were
[12:05]
initially we were going to install three
systems, and then because of time and
[12:10]
the permitting process and that, you
know,
[12:12]
uh those constraints that we narrowed it
down to one system.
[12:16]
Will that one system be sufficient to
cool off the building to to be Is it
[12:20]
adequate enough to call it a cooling
center for our seniors?
[12:26]
» Yeah, so so the
the system serve different portions of
[12:32]
uh the center.
Um
[12:35]
I mean officially, I don't I don't know
what um the requirements for a cooling
[12:40]
center would be, but
um
[12:44]
you know,
moving forward with with this would
[12:47]
provide the the adequate cooling um
within portions of of the senior center
[12:52]
and
>> And you know, it is assuming the the
[12:54]
main the general areas like where they
congregate and do some most of the
[12:58]
activities.
>> Yes, so so the
[13:02]
the systems are
functioning now, so it's serving as a
[13:07]
cooling center as is. However, there's a
lot of maintenance uh issues and uh the
[13:12]
system tends to be down pretty
frequently, so uh moving forward uh with
[13:17]
this uh may address this at least, you
know, one of the three aging systems.
[13:21]
» Okay.
Okay, any
[13:25]
Larry?
>> Uh
[13:27]
Well, I would
I would definitely support and move the
[13:31]
the project forward. However, since
we're using general fund money,
[13:36]
uh
I would like to ask the city manager as
[13:40]
part of this motion to seek
reimbursement from the state or and
[13:45]
county to replace the general fund money
since we are in essence donating to the
[13:50]
senior center.
[13:53]
» And if I may respond to that, um so we
will certainly try to do that. Um but
[13:58]
just to be clear, you know, we don't
have the time to get that approved ahead
[14:02]
of time because we have September Yeah,
so we will definitely
[14:06]
um both approach um
you know, the state and also the county
[14:12]
uh for effectively a reimbursement to
the city for the local funds we're going
[14:16]
to spend.
>> Especially the state since they're the
[14:18]
ones that causing this additional funds
to be needed.
[14:22]
» Surely.
>> Right.
[14:23]
» Yes.
>> Okay, so I've got a motion.
[14:27]
» I second.
>> And I second. I got a motion from
[14:30]
McAllen and a second from Hogan.
Uh all those in favor?
[14:35]
» Aye.
>> Aye.
[14:37]
» Any opposed?
>> Just to follow up on I just want to make
[14:41]
sure it's a reflect in the minutes what
Larry just discussed. I have heartburn
[14:45]
spending general fund money outside the
city even though it does probably
[14:51]
service a lot of Island citizens in a
state building which required us to put
[14:57]
increased costs into this project in
their building.
[15:02]
Government is running absolutely amok.
I mean
[15:07]
» I I agree with you, John. I
if I may share while I was out
[15:11]
canvassing for my campaign and speaking
to some of these seniors,
[15:14]
a lot of them that are on fixed budgets
don't want to run the AC system, you
[15:18]
know, they they can't afford to it and
it being 109° outside today, I can only
[15:24]
imagine what you know how they're
suffering. So, us being able to provide
[15:28]
this, even if it is a state building, us
being able to provide this for them, I
[15:31]
think, you know, it's a step in the
>> Well, I understand I approve the
[15:34]
project, but there's just heartburn that
the state's requiring us to do extra
[15:39]
things to get this project through in
their building to service citizens of
[15:45]
the county, Highland, and the state of
California. Makes absolutely no sense.
[15:50]
But,
>> Hopefully Carlos can get us that money
[15:53]
reimbursed, but okay.
>> And and then just to be clear, as part
[15:56]
of the recommendation by city council,
we do have an eighth item, and that is
[16:01]
for the city manager to seek
reimbursement from the state and/or the
[16:04]
county for the city's share. So, just
want to put that into the record.
[16:08]
» Into the record, yes.
>> Yes, thank you.
[16:10]
» Okay. Does that require a separate vote?
That's just
[16:14]
» No, that was It's all part of the same
vote that the council
[16:17]
» Okay. Um if we don't have any other
items, uh we will adjourn.
[16:21]
» Now, can I ask a question? This is not
on the agenda. It's it's off the agenda,
[16:26]
but it's we're not going to ask or make
a decision. I'd like an update
[16:31]
on the stolen cameras.
Uh makes no sense that
[16:37]
How are they stealing on a pole that's
30 or 40 ft in the air unless you've got
[16:41]
a boom truck? And can we get an update
where that's at and what do we have what
[16:47]
information we have about the theft? It
just to me is what mind-boggling.
[16:51]
» Yeah, so I'll I'll I'll be brief because
it's not an item on the agenda, but just
[16:55]
as part of my updates that I would give
to the council, I suppose I can take a
[16:59]
few minutes to cover that item. Um what
I can tell you is that we did have
[17:03]
vandalism at three separate locations. I
could tell you that Captain Dean is
[17:09]
making this a priority for him. They are
going to
[17:12]
catch the people. They No, they they
They there's there's vandalism. They're
[17:16]
cutting the poles. They're damaging the
equipment.
[17:19]
» The poles most of them are on traffic
signal poles.
[17:22]
» Actually
there are some that are not. There are
[17:25]
on poles. In fact, the one that
just to give you a point of reference,
[17:29]
there's one right there in front of the
Starbucks on Baseline at the 210 Freeway
[17:33]
and it's in the median and you can see
it. It's it's visible. It's about the
[17:38]
height of
you know a street street sign like a
[17:41]
street name sign or or a stop sign. So
it's a pole of that height. So not all
[17:47]
cameras are set up higher in elevation,
but that is something that we're looking
[17:52]
to do in order to
>> So they're basically being stolen low
[17:55]
elevated.
>> Correct. Cameras that are accessible.
[17:59]
Obviously people shouldn't be doing
that, but the fact of the matter is
[18:03]
they're there.
They are accessible. All they have to do
[18:06]
is cut the pole and they're the camera
will come down with the panel with solar
[18:11]
panel and everything. So this is an
issue.
[18:15]
And so we we are working with Flock to
get those cameras replaced, but we're
[18:20]
also working the PD is also working
>> Pole I hope.
[18:23]
» Right. We're looking at those yeah, so
that we don't necessarily
[18:27]
put them right back where it was because
obviously we need to take a different
[18:31]
approach.
>> I don't think we should continue talking
[18:34]
about where the cameras are and how high
they are.
[18:36]
» Yeah.
>> And and um since this item is not on the
[18:39]
agenda, I I would recommend that we wrap
up the discussion as well.
[18:43]
» Thank you, Marcella. Okay, with that we
will adjourn.
[18:47]
» Thanks for patience.
[18:53]
» I was just envisioning how they climb