[5:06] Public Comment
[31:10] Consent Agenda
[32:10] Town Manager's Report
[32:36] New Business: Town of Johnstown Public Art Plan
[48:04] New Business: Establishing a Data Center Advisory Committee
[1:17:40] Public Hearing: Whitehall Filing No. 2 Preliminary Plat and Rezone
[1:59:44] Public Hearing: Ordinance 2026-295: An Ordinance Establishing a Temporary Moratorium on Data Center Facilities in the Town of Johnstown
[2:24:11] Council Reports and Comments
[2:47:30] Mayor's Comments
[2:50:08] Executive Session

Transcript

Download: Text · SRT
SOURCE TRANSCRIPT

This transcript is downloaded from the source you provided but we haven't reviewed it for accuracy. Treat it as a starting point, not a verbatim record. You can also request an AI-transcription of the audio file with the button to the left.

[1:02:25] Yeah But we're not taking any questions
[1:02:28] on this If you continue to interrupt,
[1:02:34] you're going to be removed So respect the decorum.
[1:02:36] Please.
[1:02:37] Here I have a hearing from Well, you're
[1:02:40] welcome to move your chair up closer,
[1:02:42] but we're not interrupting the meeting.
[1:02:44] Let's let's let's respect everybody else in here.
[1:02:48] The folks are talking up here, but we're getting out of line.
[1:02:51] All right.
[1:02:52] Continue please.
[1:02:53] Chad I guess my question would be what?
[1:02:57] I mean, you want to look at this over this year time period
[1:03:02] that we're looking at.
[1:03:03] You know, to do this research So what
[1:03:07] does this time frame look like that we would compile
[1:03:10] this committee of sorts?
[1:03:14] Because as are we wanting this to be
[1:03:16] in conjunction with that year time
[1:03:19] frame that he's making reference.
[1:03:22] I don't think i wasn't suggesting that it had to be.
[1:03:25] I just, you know, we have a proposal in front of us.
[1:03:29] If it takes longer or less time, I I would
[1:03:33] I don't think that it's that it should be time certain I mean
[1:03:44] I guess I'm not saying I don't trust our staff,
[1:03:47] but how are You going to pick six people and not
[1:03:50] and have that be random unless you're going to draw names out
[1:03:53] of a hat because you're going to know if someone's
[1:03:56] for it or against it.
[1:03:57] I could pick six people right now.
[1:03:59] That'd be great with it.
[1:04:01] That's not right Because I'm pretty
[1:04:03] sure six people in this room would be against it So
[1:04:06] how do you find how are you going to keep
[1:04:09] that biased or unbiased?
[1:04:12] So when I look at it from a staff perspective,
[1:04:14] us as a council up here vote 98% at a time of staff
[1:04:18] recommendation So what's your what you're saying
[1:04:23] is you don't trust the staff is kind
[1:04:25] of what I'm getting at here.
[1:04:27] I did not say that.
[1:04:28] I didn't.
[1:04:29] That's kind of what we're in situate into.
[1:04:31] The way I look at staff not put words in my mouth.
[1:04:34] Please.
[1:04:34] I did not say, Well, you just saying,
[1:04:35] how do we trust the staff?
[1:04:37] I did not say that The staff gives
[1:04:40] us recommendation and guidance.
[1:04:42] That's not what I said If you don't
[1:04:45] want to go forward with this it would be an advisory committee.
[1:04:49] It would not take away your discretion at the end of the day
[1:04:52] to make right decisions.
[1:04:54] And regulations.
[1:04:55] We're going to need even with an advisory committee,
[1:04:58] you're going to need assistance of staff
[1:05:01] to help draft regulations.
[1:05:04] It would it would be a process just to provide recommendations
[1:05:08] and information to you.
[1:05:10] We could do our best to set out the types of folks
[1:05:15] that you might want to sit on this committee
[1:05:19] if you want them to have education or no education.
[1:05:21] I mean, that that's all within your protocol.
[1:05:24] But i just want you to know that it won't take off.
[1:05:27] At the end of the day, They're not going to be
[1:05:28] the final decision makers.
[1:05:29] They're just going to be providing education If you
[1:05:32] want to go forward with this.
[1:05:34] I think one of the other things that I heard from marin Council
[1:05:37] was if you want to create this commission
[1:05:40] or this committee, what we could actually do
[1:05:42] is probably establish some sort of survey asking people
[1:05:46] exactly what their perspective or their preferences on data
[1:05:51] centers So we do get a good cross-section
[1:05:56] of perspectives on this topic.
[1:05:59] So that we can listen and learn hopefully about what's going on
[1:06:04] and take all of that information and you know,
[1:06:08] there may there may be some other activities that
[1:06:11] that committee decides to do.
[1:06:13] But what we can do as staff is we
[1:06:16] can collect that data for them and present it to them.
[1:06:19] So that they can make the best decision or recommendation to
[1:06:24] the council for final decision.
[1:06:27] Matt, do you feel that Six would be too small or 6.
[1:06:31] A good number ?
[1:06:37] I I don't know that answer.
[1:06:40] I mean, I I ideally, you want to find
[1:06:43] somebody that really doesn't probably
[1:06:46] know much about data centers.
[1:06:48] I'd, I'd say probably a good candidate,
[1:06:50] but I'm not going to be involved in that You know
[1:06:55] But people that don't have a bias One way or another
[1:06:59] that at the end of the day, I mean as a staff,
[1:07:03] we're here to serve Right.
[1:07:05] That's why we're here We we take the opinions of the community.
[1:07:10] We take the direction of the council.
[1:07:12] And we carry that out.
[1:07:13] That's our responsibility Our responsibility is not
[1:07:16] to get emotionally involved with the decision making
[1:07:19] process of the governing body All right.
[1:07:25] Six might be the right answer Now
[1:07:28] I shudder to think that more than ten,
[1:07:31] but I think you do need a good cross-section of pro con
[1:07:37] and probably understand guided that need to take
[1:07:43] the information excuse me.
[1:07:45] Take that information and come to a conclusion
[1:07:48] to as to as to what they think is best for the community
[1:07:54] probably more more than likely.
[1:07:55] Thou art is better than even in the case
[1:08:00] that we have a split decision and probably
[1:08:05] probably if you have I do you probably
[1:08:07] want to try to keep as many undecided or unknowing
[1:08:13] individuals about the topic would be primary
[1:08:17] So then I'll reverse the question.
[1:08:18] The council does council think that the six or if we go
[1:08:21] with an odd number, 7 or 9 or something,
[1:08:23] what number feels good ?
[1:08:28] I still think it should be left up to the citizens.
[1:08:31] I do.
[1:08:32] It's their property They.
[1:08:33] They live in this town.
[1:08:35] I've lived here Not as long as Chad or Jessie.
[1:08:38] I've lived here 26 years.
[1:08:40] But even people coming in, they bought property here
[1:08:43] and they should have a right to say whether they get to hear
[1:08:47] the noise breathe, the pollution, whatever I don't even
[1:08:51] think six people whether they're four against it,
[1:08:54] how you're going to do that.
[1:08:56] And bring it back to us, for us to decide when, if we just
[1:08:59] listen to our citizens, we would we would have that answer
[1:09:03] if we listened to the citizens.
[1:09:05] Right now, you would have that answer.
[1:09:07] If you've looked online is social media at all?
[1:09:10] I have not heard very many people for it.
[1:09:13] So why are we not listening to the citizens
[1:09:15] instead of creating a committee just
[1:09:17] to kick the can down the road, to have somebody that possibly
[1:09:21] pushes those people that are on there to magically get
[1:09:25] some good news through there that somebody believes
[1:09:29] and then it's i don't know.
[1:09:31] Well, there's over 20,000 residents in this
[1:09:33] community So I think we've got to look at it
[1:09:35] from a bigger perspective.
[1:09:37] Let them vote on the ballot in 2020.
[1:09:43] But yeah, this is a tough one, right So
[1:09:56] and I'm trying to scope my brain around the agenda item, which
[1:10:00] is the committee I have definitely comments
[1:10:02] for ordinance number eight when we get to that piece
[1:10:08] But the committee itself, I've been part of a lot
[1:10:10] of committees over the years.
[1:10:12] I'm sorry, early public arts and several of them.
[1:10:15] I do agree that if we move forward with a committee,
[1:10:18] I think having an odd number is recommended
[1:10:21] and a smaller number not to exceed, say,
[1:10:25] ten just because then we get too much Where I'm hearing Diane
[1:10:30] is of the need for the committee.
[1:10:32] The need for the committee was based off
[1:10:33] the idea of ordinance number eight,
[1:10:36] which is establish a moratorium.
[1:10:38] But assured in hearing from the citizens
[1:10:40] This committee will also just like we've
[1:10:42] done in other committees, will establish communication plans
[1:10:45] with the citizens that could be you know,
[1:10:48] that could be in their charge. that could be one thing
[1:10:50] that they come up and they want to do Maybe they
[1:10:52] want to do the barbecue days or trick
[1:10:54] or treat street and get feedback directly from the citizens.
[1:10:56] That's going to be with the committee.
[1:10:58] Some of the committee decisions So it's not that we can't have
[1:11:01] 20,000 people doing it.
[1:11:04] But then again, we get all the data,
[1:11:06] we get all the information from The committee and the citizens
[1:11:10] It gets really reviewed.
[1:11:12] And again, we we don't have to make a decision The moratorium.
[1:11:15] And Abby, correct me if I'm wrong,
[1:11:16] we have moratoriums and other things They can't just
[1:11:19] come in her bill without our approval we have had more times
[1:11:29] for other things that we had a short oil and gas moratorium
[1:11:32] and we had a moratorium water dedication.
[1:11:34] Since I've been here What's your question exactly?
[1:11:40] I think that if somebody brought forth an application for a data
[1:11:43] center based on My understanding from the work session,
[1:11:46] is it would be considered under the code right now.
[1:11:49] Correct.
[1:11:49] Unless we do the moratorium would pause
[1:11:52] that for 12 months, Correct.
[1:11:53] They would not be able to get that move
[1:11:56] through because it's arbitrary.
[1:11:57] If you all choose to adopt.
[1:11:58] Correct.
[1:11:59] So I just want to clarify that.
[1:12:00] And the committee, if they say we need more time,
[1:12:03] there's more time If the committee also
[1:12:04] says it needs to go to the ballot that's the information
[1:12:07] we want to hear from the citizen.
[1:12:08] So those are the kind of, I guess,
[1:12:10] all the talking points that I'm hearing
[1:12:11] that I'm you want to make sure it's very
[1:12:14] clear to everybody tonight.
[1:12:16] We're not saying at least I'm not saying we
[1:12:18] don't hear from the citizens.
[1:12:19] It's been very light full hearing from the citizens
[1:12:23] We're not saying we're doing anything at this point.
[1:12:26] We still have a public hearing that we have to do.
[1:12:29] And we're not saying that if we do
[1:12:31] a moratorium, if we do nothing, there is
[1:12:32] a risk that they could come in.
[1:12:35] But if we do a moratorium, they can't come in.
[1:12:38] If we ban it, they can't come in So that's what we can do
[1:12:45] But again, I don't think we're there yet as far as
[1:12:46] making that final decision on.
[1:12:48] We just keep a moratorium forever
[1:12:51] and we have marijuana right now is a moratorium forever.
[1:12:53] But I mean, we haven't i mean, it's until somebody can write it
[1:12:59] well, but then that comes to a vote
[1:13:01] against it's not just they can't build something downtown
[1:13:04] So I think we have we have protections in place.
[1:13:07] We just don't have all the information in.
[1:13:10] And.
[1:13:10] That's right.
[1:13:11] One information.
[1:13:11] I think there are some smart people out here that
[1:13:13] know a lot more about this stuff than us
[1:13:16] And I'd love to hear from them both on all sides of the fence.
[1:13:19] As you said So that's why I think establishing
[1:13:22] a committee would help do it is not,
[1:13:24] I think, all inclusive to the seven people
[1:13:27] or whatever we decide Megan what would be the next opportunity
[1:13:34] if if we chose to put it to a vote
[1:13:38] We were told last week that the next opportunity
[1:13:43] after this November would be April of 2028.
[1:13:46] Is that still true?
[1:13:48] Mayor Duncan and Council member If you are looking at a tabor
[1:13:53] question, sales tax something like that, that
[1:13:56] is correct because sales tax questions
[1:13:59] can only be coordinated or put on our regular municipal ballot.
[1:14:05] If you are looking to ask a question of the community
[1:14:08] and that is not a Tabor question the council
[1:14:11] can coordinate with the counties for a November election
[1:14:16] at that time frame is very tight right now,
[1:14:19] but you could look at 2027 in November, but actually
[1:14:23] and this council also has the ability
[1:14:26] to call a special election if they choose to.
[1:14:29] And refer a measure to the public at any time,
[1:14:33] as long as it's not a Tabor question okay.
[1:14:36] Thank you.
[1:14:37] I was not aware of how that worked.
[1:14:39] And I appreciate you telling us.
[1:14:40] Thank you Again, Meghan, at what cost for that special election?
[1:14:46] Sure.
[1:14:46] So generally coordinated elections and and,
[1:14:50] you know, Weld County is very clear.
[1:14:52] Right. $2 a voter is what we pay larimer County.
[1:14:57] It's based on ballot size.
[1:14:59] How many other municipalities are coordinating And so, you
[1:15:03] know, we estimate for a coordinated election 40
[1:15:05] to 50,000 to do that election coordinated with the counties
[1:15:10] are our last election that we just did in April
[1:15:14] And that election was 35,000.
[1:15:16] The council should note that there
[1:15:18] were two two different ballots that
[1:15:21] went out because of the DDA.
[1:15:22] So that did change it a little bit in my estimation,
[1:15:26] between 25 and 30,000 at today's cost today would be what
[1:15:31] it would cost for my office to do
[1:15:35] an election for the town Yeah.
[1:15:47] So as you guys want to do 11 on the advisory board, given it
[1:15:50] that odd number or Seven good What's everybody
[1:15:59] feeling I have no preference.
[1:16:00] I'm fine with either way.
[1:16:02] Just curious what everybody else thought.
[1:16:03] Oh, Chad i would think 7 would be enough but I don't.
[1:16:08] I don't have an opinion.
[1:16:10] One way or the other.
[1:16:11] I do think I'd numbers better, but I don't.
[1:16:14] I don't care what number it is, the more you add,
[1:16:16] the more complex it gets for the staff as well too.
[1:16:18] Sure.
[1:16:19] So I'm thinking 7 would be a prime number for me to recommend
[1:16:24] OK And thank you, Damien, for explaining that a little better
[1:16:30] All right.
[1:16:31] Any further deliberation before I make a motion with that,
[1:16:36] I move to establish a Johnstown Data Center Advisory committee
[1:16:40] consisting of seven Johnstown residents selected
[1:16:42] through an open application process
[1:16:45] and one town staff member to provide
[1:16:48] administrative oversight.
[1:16:49] The committee should operate independently of the town
[1:16:51] council, evaluate all aspects of potential data center
[1:16:53] development including land use, infrastructure
[1:16:56] environmental impacts, public safety, potential regulations
[1:16:59] to receive public and expert input
[1:17:01] and submit a written report with recommendations including
[1:17:04] proposed regulations, development standards
[1:17:06] to the Town Council or with a date to be determined The all
[1:17:14] right, Well article in a motion by myself,
[1:17:16] seconded by Council member Bashford, we put it to electric.
[1:17:46] Preliminary plat and rezone seven Alpha Resolution number
[1:17:50] 2020 6-35 approve a preliminary plat to White House a division
[1:17:54] following number two, then seven Bravo ordinance 2020 62-29
[1:17:59] for approving rezoning a real property
[1:18:02] known as the White subdivision Finally, number two.
[1:18:07] With that, I go and ask for a staff report To
[1:18:23] and Megan will have a vote on all three of those resolutions
[1:18:26] separately.
[1:18:28] The two that are before us.
[1:18:30] Duncan Yes.
[1:18:31] OK Thank you Good evening.
[1:18:46] Mayor Duncan and council members.
[1:18:48] My name's Aubrey Flores, planner one with the town of Johnstown
[1:18:52] And I'm just trying to get my slide show on to the screen
[1:18:58] Maybe it's coming to your rescue.
[1:19:00] Thank you, Mike Okay Thank you.
[1:19:08] Thank you.
[1:19:09] Here we go.
[1:19:10] Tonight, I'll be presenting Two applications for the property
[1:19:14] known as White Hall.
[1:19:15] A preliminary plat and a reason these applicant ations
[1:19:18] were submitted and reviewed concurrently under the town's
[1:19:21] land use and development code.
[1:19:23] The subject property is approximately 163.34 acres.
[1:19:28] And as you can see on the vicinity map
[1:19:29] provided it is located north of Weld County Road 46 west
[1:19:34] of Colorado Boulevard south of the Clearview neighborhood
[1:19:37] and east of unincorporated weld County.
[1:19:40] The property was annexed into the town in 2021
[1:19:43] through the Whitehall annexation At that time,
[1:19:46] the property was zoned planned unit development,
[1:19:48] mixed use or Puti MOU.
[1:19:51] There were no zoning documents created or approved
[1:19:53] for the property at that time Also in 2021, Whitehall
[1:19:57] filing number one was approved.
[1:19:58] This subdivision created the parcel.
[1:20:00] You can see around the orange for Roosevelt High School It was
[1:20:05] constructed a few years later The current applications
[1:20:09] represent the next phase of development for the remaining
[1:20:12] Whitehall property.
[1:20:13] So the applicant tonight is requesting approval
[1:20:16] of a preliminary plot I'll be showing you the plot later
[1:20:20] in my presentation portion, but it would subdivide the property
[1:20:22] into seven tracts to outline it and the associated public
[1:20:26] right away that outlets are intended
[1:20:28] for open space drainage detention
[1:20:31] and utility infrastructure.
[1:20:33] The proposed right away establishes the future street
[1:20:35] network through the property and provides connectivity
[1:20:38] to the surrounding areas.
[1:20:40] The applicant tonight is also requesting a reason
[1:20:43] to replace the existing PD zoning with a combination
[1:20:46] of standard zoning districts found within our land
[1:20:49] use undeveloped met code.
[1:20:51] Our two mixed density neighborhood
[1:20:53] our three high density neighborhood
[1:20:55] mNC mixed use neighborhood commercial and MRC mixed
[1:20:59] use Regional commercial.
[1:21:01] The intent of the proposed zoning framework
[1:21:03] is to establish a transition of development intensity
[1:21:06] across the property with lower density residential uses
[1:21:10] to the West and increased opportunities for mixed use
[1:21:13] and commercial development Closer to Colorado Boulevard.
[1:21:16] So this proposal was reviewed for consistency
[1:21:19] with the comprehend the plan, which you can see on the screen
[1:21:23] And it was found that the proposed zoning framework aligns
[1:21:26] with the future land use designations for the property So
[1:21:29] as shown on the future land use map,
[1:21:32] the eastern portion of the property
[1:21:33] is designated medium density slash intensity,
[1:21:36] while the western portion is designated low density slash
[1:21:39] intensity The proposed zoning also supports the town
[1:21:43] goals related to the housing affordability plan
[1:21:46] by providing a wide range of housing for diverse individuals
[1:21:50] neighborhood connectivity and access to service and amenities
[1:21:54] The applications are consistent with the comprehensive plan,
[1:21:56] including goal L1,
[1:21:58] which seeks to ensure that neighborhood character
[1:22:01] and amenities contribute to the health
[1:22:02] and well-being of a diverse range of residents.
[1:22:06] So the following slide shows the existing zoning
[1:22:09] and the surrounding land uses as well,
[1:22:11] which are generally residential to the north and east
[1:22:14] and agricultural to the west and the south.
[1:22:17] The areas shown in gray are located within an incorporated
[1:22:21] Weld County, while the colored areas are properties annexed
[1:22:24] into the town of Johnstown.
[1:22:26] Given this context, the proposed zoning framework
[1:22:29] was designed to create a transition in intensity areas
[1:22:32] across the property.
[1:22:34] Moving to the proposed zoning map as you can see,
[1:22:38] the districts generally increase in intensity from west
[1:22:40] to east, allowing Colorado Boulevard to serve as a corridor
[1:22:44] for supporting the higher density development
[1:22:47] So a helpful way to think about the proposal
[1:22:50] is a progression from homes on the West to mixed use
[1:22:52] residential areas in the center that provide the neighborhood
[1:22:55] services on the East.
[1:22:58] Are two district supports a variety of housing types
[1:23:00] in a lower density neighborhood While our three dense district
[1:23:04] increases residential density near commercial areas,
[1:23:08] helping support local businesses by providing residents
[1:23:11] within walking distance of services,
[1:23:13] the M20 District provides opportunities for neighborhoods
[1:23:16] serving uses, such as restaurants, personal services
[1:23:19] and small offices, while also allowing residential uses
[1:23:22] like duplex Is and townhomes.
[1:23:25] The mRC district provides opportunities for larger
[1:23:28] community, serving uses such as recreation centers,
[1:23:31] while remaining connected to surrounding neighborhoods
[1:23:33] through sidewalks and trails OK, so a significant feature
[1:23:38] of the proposal is the planned connectivity
[1:23:40] through the property.
[1:23:41] So as you can see on the preliminary plat on this slide,
[1:23:44] it includes an east west Trail corridor, which includes a ditch
[1:23:48] realignment intended for future multi-use trail integration
[1:23:53] This connection will provide future connectivity
[1:23:55] to Roosevelt High School and surrounding neighborhoods.
[1:23:58] The Street Network is is coordinated with surrounding
[1:24:01] development and future final plat applications will refine
[1:24:04] the timing and sequencing of roadway and infrastructure
[1:24:07] improvements.
[1:24:08] Both colorado Road and County Road 46 will be required to be
[1:24:12] improved as part of the plan application A neighborhood
[1:24:16] meeting was held on May 12th at the Johnstown yMCA and this year
[1:24:21] 15 people attended it, including residents,
[1:24:24] town staff and representatives of the applicant
[1:24:27] Discussion focused primarily on road facing traffic impacts.
[1:24:31] Utility extensions feature lane uses football stadium noise
[1:24:35] at the high school housing projections
[1:24:38] and access along County Road 46.
[1:24:41] Notice of the neighborhood meeting
[1:24:42] was mailed to all property owners within 800
[1:24:44] for the property published in the Johnstown Breeze
[1:24:47] and posted on the site in Three different locations.
[1:24:50] For tonight's hearing, public notice was published
[1:24:53] in the Johnstown Breeze on June 25th, 2026,
[1:24:55] and mailed notice was again, provided to all
[1:24:57] property owners within 800ft.
[1:25:00] Stick with me.
[1:25:01] I'm going to be listing the staff findings addressing
[1:25:05] the criteria for a preliminary plat pursuant to section 17
[1:25:09] DoorDash 2-2 of the land use and development Code so that
[1:25:15] Preliminar pre plat proposes a subdivision of the 163.34 acre
[1:25:18] property into seven tracts, two out lots in Associated
[1:25:23] Round-Up right of way.
[1:25:25] So from the land use and Development code the first item.
[1:25:29] The first criteria is that the application is in accordance
[1:25:32] with the comprehensive plan and in particular,
[1:25:34] the physical development patterns and concepts of a plan.
[1:25:38] So the application complies with the comprehensive plan,
[1:25:41] particularly the development patterns and concepts related
[1:25:44] to planned residential and mixed use
[1:25:46] development transportation, connectivity
[1:25:49] and neighborhood scale design.
[1:25:50] The next criteria is that the development and infrastructure
[1:25:53] are arranged in a manner to minimize
[1:25:55] impacts on geologic hazards.
[1:25:57] Environmentally sensitive areas, wildlife, habitat or other
[1:26:00] natural features of the land.
[1:26:02] So the development and infrastructure
[1:26:04] are arranged to minimize impacts on geologic hazards,
[1:26:07] environmentally sensitive areas and other natural features.
[1:26:10] To the extent applicable to the site
[1:26:14] No significant constraints have been
[1:26:16] identified that would prevent development
[1:26:18] and the proposed configuration.
[1:26:20] The next criteria is that the arrangement and proposed design
[1:26:23] of streets open space and blocks meet the development and design
[1:26:25] standards of this code and are coordinated
[1:26:28] with the existing or potential development
[1:26:30] on adjacent property.
[1:26:32] So the arrangement and proposed design of streets, open space
[1:26:35] and box meet applicable development and design standards
[1:26:37] and are coordinated with existing and future development
[1:26:40] on adjacent properties, including
[1:26:42] connections to surrounding residential
[1:26:43] and aggregate natural areas.
[1:26:46] The next criteria is that the proposed blocks and lots are
[1:26:48] capable of meeting all development and site design
[1:26:51] standards of the applicable zoning district
[1:26:53] So the proposed blocks are capable of meaning
[1:26:55] all development and site design standards,
[1:26:58] which will be further reviewed at the time of final part.
[1:27:00] And site specific development applications Next one
[1:27:04] is that the application demonstrates
[1:27:05] preliminary feasibility of being able to meet
[1:27:08] the design, construction performance, and maintenance
[1:27:10] requirements for all required improvements in this application
[1:27:14] and demonstrates preliminary feasibility of meeting design,
[1:27:17] construction performance and maintenance requirements
[1:27:20] for required improvements, including
[1:27:22] streets, utilities, drainage and open space infrastructure.
[1:27:26] The next criteria is that phasing is clearly indicated
[1:27:29] and demonstrates a logical and coordinated approach
[1:27:31] to development and the timing, location,
[1:27:34] and construction of amenities is consistent throughout phases.
[1:27:37] So future development will continue
[1:27:39] to be refined through subsequent final plat application, which
[1:27:42] will establish timing infrastructure
[1:27:44] sequencing and amenities.
[1:27:47] The last.
[1:27:48] The next point is that any impacts identified
[1:27:50] by specific studies or technical reports
[1:27:53] are mitigated with generally accepted in sound planning,
[1:27:56] engineering, and urban design solutions
[1:27:58] Any impacts identified through technical reports,
[1:28:01] including stormwater analysis, are proposed to be mitigated
[1:28:04] through engineering review to ensure long term
[1:28:06] function of the development The next criteria
[1:28:10] part of the preliminary plat is that the design does not impede
[1:28:13] the construction of anticipated or planned
[1:28:15] future public infrastructure or other development within the
[1:28:18] area.
[1:28:19] And the design does not impede planned or anticipated
[1:28:22] public infrastructure, including transportation
[1:28:24] and trail connections.
[1:28:26] The last criteria is that the plot has addressed issues
[1:28:29] of professional staff or any other public entity or review
[1:28:32] agencies as to officially review the preliminary plat
[1:28:36] So the application has been reviewed by town staff
[1:28:38] and applicable review agencies, and revisions have been
[1:28:41] incorporated to address comments So next i'm going to be moving
[1:28:45] into the staff findings addressing the criteria
[1:28:48] for a rezoning pursuant to section
[1:28:50] 17 dash 2-3.B of the Land Use and Development Code.
[1:28:54] So staff reviewed the proposed zoning against each criteria
[1:28:58] required by the code I'm going to list the following findings
[1:29:02] demonstrating how the proposed rezoning meets
[1:29:04] the applicable required meets.
[1:29:06] Point number one is that the rezoning furthers
[1:29:08] one or more of the purposes of these
[1:29:10] regulations and 17 dash 1-3.
[1:29:13] And on any balance, any purpose that may be undermined
[1:29:16] or untrue weighed by the benefits of those purpose,
[1:29:18] it furthers.
[1:29:20] So the proposed rezoning from Puti I mean to r 2R3,
[1:29:23] I mean and C and M r c replaces a P designation that does not
[1:29:28] include specific development standards The proposed zoning
[1:29:30] districts establish clear, enforceable development
[1:29:33] regulations consistent with the land use and Development Code.
[1:29:37] Two is that the proposal is consistent with the goals
[1:29:39] and objectives of the comprehensive plan
[1:29:42] and any other plan, policy or guidance
[1:29:44] adopted pursuant to that plan.
[1:29:46] So the subject property is designated medium density
[1:29:49] and low density intensity within the comprehensive plan
[1:29:52] future Land Use map.
[1:29:54] The proposed zoning districts are consistent with the intent
[1:29:57] of these designations and support
[1:29:58] the overall land use framework established
[1:30:01] by the Comprehensive plan.
[1:30:03] So as I talked about earlier, the Eastern part of the property
[1:30:06] is medium density slash intensity.
[1:30:09] The comprehensive plan describes medium density areas
[1:30:12] as complete neighborhoods that provide a diversity of shops
[1:30:15] and services, including schools and civic facilities within
[1:30:18] a walking or biking district.
[1:30:20] Distance from residential areas.
[1:30:22] These areas are intended to provide strong walking
[1:30:25] connections multimodal trails, a range of housing options
[1:30:28] and opportunities for diverse lifestyles and income ranges.
[1:30:32] So in this doc finds that the proposed hour to hour three
[1:30:36] and C and MRC zoning framework closely
[1:30:38] relent reflects the intent of the medium density area.
[1:30:42] So rather than separating housing
[1:30:44] from services the proposed zoning creates
[1:30:46] a complete neighborhood by integrating a variety of housing
[1:30:49] types with neighborhood scale, commercial and community,
[1:30:52] serving uses that anyone see District complements
[1:30:55] these residential uses by allowing neighborhoods serving
[1:30:58] commercial uses, including small restaurants personal services
[1:31:01] and neighborhood retail These uses are intended to remain
[1:31:04] neighborhood skill and are not designed to accommodate
[1:31:07] large commercial structures with large parking lots and see also
[1:31:11] allows for senior aging facilities The MRC district
[1:31:16] provides opportunities for larger community serving
[1:31:18] commercial uses while remaining connected
[1:31:20] to nearby residential areas through sidewalks and trails.
[1:31:23] Also MMR is the only zoning district
[1:31:26] that permits recreational centers buy write directly
[1:31:29] supporting the comprehensive plans
[1:31:31] vision of complete neighborhoods where residents have
[1:31:33] convenient access to shopping services, recreation
[1:31:36] and other daily needs.
[1:31:38] The western portion of the property
[1:31:40] is designated low density.
[1:31:42] The comprehensive plan describes these areas
[1:31:44] as primarily single family neighborhoods,
[1:31:46] with opportunities for lower density
[1:31:47] attached housing, such as townhomes,
[1:31:50] duplexes and patio homes.
[1:31:52] Staff finds that the proposed R two and R three districts best
[1:31:55] implement this vision and are one district
[1:31:58] was not considered because it is limited to detached
[1:32:00] single family homes on larger lots
[1:32:03] and does not provide the flexibility
[1:32:04] to accommodate the range of housing options encouraged
[1:32:07] by the comprehensive plan.
[1:32:09] The proposed are to an three districts
[1:32:10] allow for the housing diversity envisioned by the Comprehensive
[1:32:13] plan by supporting a mix of residential building
[1:32:16] types and densities.
[1:32:17] The proposed R two district maintains the low density
[1:32:20] character and vision for this area,
[1:32:22] while providing additional housing flexibility This
[1:32:25] supports the strategic plan goal of supporting a broad range
[1:32:28] of housing options, including the greater
[1:32:30] likelihood of attainable housing The proposal supports the town's
[1:32:34] planned transportation and trail network through an East West
[1:32:37] Trail connection that will provide
[1:32:38] connectivity to Roosevelt High School
[1:32:40] and surrounding neighborhoods.
[1:32:42] So the next criteria from the code
[1:32:44] is number three, which the changes,
[1:32:46] consistent with the intent of the proposed zoning district,
[1:32:49] specifically considering the design of streets, civic space
[1:32:53] and other open space, be the pattern, scale, and format
[1:32:56] of buildings and sites and see the compatibility and transition
[1:32:59] with other complementary uses and development in the vicinity
[1:33:03] So the proposed rezoning is consistent with the intent
[1:33:06] of the park.
[1:33:07] Applicable zoning districts because it incorporates
[1:33:11] planned transportation improvements
[1:33:12] and an east west rail corridor.
[1:33:15] B The zoning framework establishes
[1:33:16] a logical progression of intensive d, the and C the
[1:33:20] proposed districts provide a appropriate transitions
[1:33:23] between Roosevelt high School, the Clearview neighborhood
[1:33:26] the Colorado Boulevard Corridor and adjacent unincorporated Weld
[1:33:29] County Lines.
[1:33:31] The next criteria is that the change is necessary for at least
[1:33:34] one of the following reasons A There has been a material change
[1:33:37] in the character of the area or in the town generally, such
[1:33:41] that the proposed reason is in the public interest.
[1:33:43] B The change will serve a community need
[1:33:45] or provide an amenity or benefit to the surrounding area.
[1:33:48] That was not anticipated at the time of the initial zoning.
[1:33:51] So since annexation and the surrounding area
[1:33:54] has experienced change including the development of Roosevelt
[1:33:56] High school, these conditions support implementation
[1:34:00] of standard zoning districts.
[1:34:02] The proposed rezone provides greater regulatory clarity
[1:34:05] and improved alignment with the comprehensive plan compared to
[1:34:08] the existing P. D designation.
[1:34:10] Five.
[1:34:11] The town or other agencies have the ability
[1:34:13] to provide services or facilities that
[1:34:15] may be necessary for anticipated uses in the proposed district
[1:34:18] So the town of Johnstown and utility providers
[1:34:21] have the ability to serve the subject property and service
[1:34:24] capacity and infrastructure have evaluated
[1:34:26] through the review process.
[1:34:29] Six Any reasonably anticipated the negative impacts
[1:34:32] on the area or adjacent property either mitigated
[1:34:34] by sound planning, design, and engineering practices
[1:34:37] or are outweighed by broader public benefits
[1:34:39] to the surrounding community So potential impacts associated
[1:34:44] with future development, including traffic and land use
[1:34:46] compatibility are addressed through zoning standards
[1:34:49] and engineering requirements.
[1:34:51] Any remaining impacts are outweighed
[1:34:53] by broader public benefits of the proposed
[1:34:56] development framework.
[1:34:57] Seven.
[1:34:58] If owner initiated at least two thirds of the subject
[1:35:00] property owners within the change of zone boundary
[1:35:03] have signed the application.
[1:35:04] So the application is owner initiated and meets
[1:35:07] the ownership requirements Eight If owner initiated the subject
[1:35:10] property has not been included in a reason
[1:35:12] action in the prior 12 months.
[1:35:14] So the subject property has not been
[1:35:16] included in a rezoning action within the previous 12 months.
[1:35:19] Nine.
[1:35:20] The recommendations of any professional staff
[1:35:22] and advisory review bodies have been considered,
[1:35:24] so the application has gone through three technical review
[1:35:27] cycles with towns, staff, referral agencies, utilities
[1:35:30] and IT companies Okay.
[1:35:33] Thanks for sticking with me through that.
[1:35:36] So the Planning and Zoning Commission held a public hearing
[1:35:40] on July 8th, 2026, following the public hearing and discussion
[1:35:43] of the proposal The Commission voted unanimously 7 to 0
[1:35:48] to recommend approval of both the zone
[1:35:51] and preliminary plat with revisions
[1:35:53] to the proposed zoning pattern.
[1:35:55] So specifically the Commission recommended
[1:35:58] changing the proposed R32R to say they're changing
[1:36:04] the proposed m r c area to Emily and see that recommendation
[1:36:10] would result in about a 107.6 acres of R two
[1:36:14] and 69.44 acres of MMM c All seven commissioners
[1:36:18] in attendance voted in favor of that recommendation
[1:36:22] and the commissioners rationale for these recommendations was
[1:36:24] that they believe the zoning districts would
[1:36:27] provide a more appropriate transition
[1:36:29] to the surrounding area.
[1:36:30] Specifically, the Commission felt
[1:36:31] more comfortable with the eminences zoning district
[1:36:34] next to Roosevelt high School and the existing
[1:36:37] residential neighborhoods as it limits commercial uses
[1:36:39] to a neighborhood scale.
[1:36:41] The Commission also recommended changing the proposed R three
[1:36:44] district to R two to provide lower
[1:36:46] density residential next to the existing residential.
[1:36:51] So in conclusion, staff finds that the Whitehall rezone
[1:36:54] and preliminary plat establish a logical and connected
[1:36:57] development framework for the property The proposal
[1:37:00] aligns with the comprehensive plan
[1:37:01] provides clear zoning standards supports future housing
[1:37:04] and commercial opportunities, and incorporate
[1:37:07] plan transportation and trail connections The proposal also
[1:37:10] meets the requirements outlined in the Land
[1:37:13] Use and Development code.
[1:37:14] The proposed zoning framework creates
[1:37:16] an appropriate transition between surrounding land uses
[1:37:18] while providing opportunities for a variety of housing types
[1:37:22] neighborhood serving commercial uses and future community
[1:37:24] amenities Staff recommends that town council
[1:37:27] approve the White House filing.
[1:37:28] Number two Preliminary plat as presented.
[1:37:31] Staff recommends approval of the rezone with the breath,
[1:37:34] a revision is recommended by Planning and Zoning Commission
[1:37:37] And thank you very much.
[1:37:39] And I'm happy to answer any questions The applicant is also
[1:37:42] here to answer any questions.
[1:37:44] Thank you for the long presentation,
[1:37:46] you did a good job One question I have.
[1:37:50] So the staff report references the East and West Trail
[1:37:52] connection Can staff explain when the trails anticipated
[1:37:56] to be construction and whether that will connect directly
[1:37:58] to the high school or whether it will
[1:38:02] connect Sorry, whether it will connect
[1:38:05] directly to the high school?
[1:38:07] I think that will be up to the applicant
[1:38:09] and will be refined through a final plat application.
[1:38:13] And for the first part of your question
[1:38:15] which was when it will be constructed,
[1:38:17] that will be determined when the development agreement is drafted
[1:38:21] for the preliminary plat.
[1:38:23] Yeah, I think if we can have something that connects
[1:38:25] to the high school because these kids need a safe place to walk
[1:38:27] and we don't currently have anything like that
[1:38:29] in the community For the kids that live close by
[1:38:32] or the parents can't afford to get them to school I mean,
[1:38:35] I think we need to applicant can take that into consideration
[1:38:38] that we can connect that to the high school
[1:38:40] to give these kids some sort of a safe trail or path
[1:38:43] to get to school because we lack those sidewalks here currently
[1:38:47] With that, I'll open it up to council
[1:38:48] for questions or comments.
[1:38:51] So I'd like to see more patio homes and some over 55 and older
[1:38:56] homes ranches versus a bunch more apartments and townhomes,
[1:39:00] which, you know, people they insurance on some
[1:39:03] of these multi roofed buildings are impossible to get insurance
[1:39:09] and they're outrageous for the resident.
[1:39:11] So I'd really press on them to really try
[1:39:14] to bring in some patio home ranch
[1:39:16] type style homes that are cottage
[1:39:19] looking and cute with backyards and areas
[1:39:23] that people can downsize a little bit
[1:39:25] Since we built here with big yards and can't afford water
[1:39:30] Be correct.
[1:39:32] Thank you.
[1:39:32] Can Council member Morris the applicant
[1:39:35] will have a presentation and they might be able to speak
[1:39:37] to some of the housing types.
[1:39:39] They're considering Thank you.
[1:39:42] Any further questions from council ?
[1:39:45] I guess so.
[1:39:45] The applicant has a presentation if they
[1:39:47] want to come forward and give the presentation
[1:40:11] Giving idea how that Perfect.
[1:40:20] Thank you.
[1:40:21] You, Mayor and council members.
[1:40:23] My name is Brian Williamson.
[1:40:24] I'm with DST Consulting Engineers.
[1:40:26] We are the planner and engineer for the project Our Aubrey did
[1:40:30] a great job presenting to you, so there's a lot of redundancy
[1:40:33] in our presentation.
[1:40:34] I'll skip over those things pretty quickly.
[1:40:36] I want to introduce our team So myself,
[1:40:38] Brian Williams and also Lee Lowery
[1:40:40] from lowery Development Group.
[1:40:42] And then I have John Sweet as well.
[1:40:44] He's the engineer on the project unit, sir.
[1:40:46] Any technical questions you have?
[1:40:48] I'm a trader.
[1:40:48] Really?
[1:40:49] For a second and then I'll be right back Good evening.
[1:40:53] Good evening.
[1:40:53] Mayor Duncan and Council members.
[1:40:55] Thank you for your time this evening.
[1:40:57] My name is Leanne Lowery, managing
[1:40:59] member of Whitehall Development Partners,
[1:41:00] as well as Lowery Group.
[1:41:01] Ryan going to have most of the nuts and bolts information
[1:41:04] for you tonight, but I just wanted this to come up and say,
[1:41:07] how happy you are to present this project to you tonight.
[1:41:11] This is one of three projects that we
[1:41:12] currently have in johnstown.
[1:41:14] We love Johnstown It's the our concentration
[1:41:17] in Northern Colorado.
[1:41:18] We love your comp plan.
[1:41:19] We follow your comp plan to implement
[1:41:21] what you what your vision is for the town We're in.
[1:41:26] All of our projects were long time stakeholders in everything
[1:41:29] that we do So in various projects
[1:41:31] we will if it's approved we will be not only property owners.
[1:41:36] But stakeholders in the in the town for decades to come.
[1:41:40] So we we really like it here.
[1:41:42] And it's just it's been a pleasure We believe
[1:41:45] that this design that we have for a while
[1:41:47] will greatly augment the school and the site
[1:41:50] that where the school is currently on I
[1:41:53] think not only does it create for the town,
[1:41:56] but we also believe it creates a community
[1:41:59] around the new high school.
[1:42:01] And just what an impressive new school that is.
[1:42:03] We've had the opportunity to tour
[1:42:04] the school with the principal and spent
[1:42:06] almost four hours there.
[1:42:07] And it's just such an impressive school.
[1:42:09] I believe this will augment that very, very well Again,
[1:42:14] I just wanted to just say a quick hello.
[1:42:16] I'll look forward to answering your questions after an hour
[1:42:19] after Brian speaks.
[1:42:20] But I just wanted to take up a quick thank you as 1 2
[1:42:22] the Planning Commission for their review and approval
[1:42:25] definitely to town staff.
[1:42:26] They've been great, as you can see, Ari, that was
[1:42:28] a lot of information there.
[1:42:29] But they've been great working with Aubrey and Planning
[1:42:33] Director Queen director Jennifer,
[1:42:35] and also just I can't say enough how proud we are and happy to be
[1:42:40] able to working with this.
[1:42:41] Our family, the current landowners,
[1:42:43] and to be able to bring this project
[1:42:45] forward and implement a lot of their vision,
[1:42:47] they had for the project.
[1:42:49] So we've been very honored to be able to do that in their trust
[1:42:52] in us.
[1:42:52] So i'll bring up Brian and he'll go through the nuts and bolts
[1:42:58] Thank you OK, so project location, Highway 60 Colorado
[1:43:04] Boulevard The project surrounds Rosebud High School Existing
[1:43:08] around it is agricultural use The rezoning
[1:43:11] request I'm going to kind of move
[1:43:12] through these pretty quickly.
[1:43:13] I think you guys have seen a fair amount of information here.
[1:43:17] Here's the comprehensive plan.
[1:43:18] I think I've spent a good amount of time working through that.
[1:43:20] So western to thirds, a little bit
[1:43:22] lower density, Eastern one third, a little bit higher
[1:43:24] density and intensity of uses.
[1:43:26] So the existing zoning is the PUD.
[1:43:29] When that beauty was put in place,
[1:43:30] there wasn't really any anticipated thought
[1:43:33] for the future development.
[1:43:34] It really was about getting the high school in there.
[1:43:36] So we're electing, you know, we could do one of two tracks here.
[1:43:39] We could amend the PUD and create standards
[1:43:43] We reviewed the land use code.
[1:43:44] I think the updates that have happened recently
[1:43:46] in the land use code lend itself to a lot
[1:43:48] of flexible development.
[1:43:49] So we are opting to propose street zoning out here.
[1:43:53] This is the original proposal.
[1:43:54] So our two Four acres is on the eastern side working
[1:43:59] as the intensity increases are three than the mixed
[1:44:02] use neighborhood commercial.
[1:44:03] And that mixed use regional commercial up at the top
[1:44:07] This exhibit shows the planning Commission recommendations.
[1:44:10] So swapping this tract see down here And you see my own?
[1:44:15] Yeah.
[1:44:16] OK.
[1:44:16] This tracks down here from our 3 to our two.
[1:44:19] We don't really have a concern about that Like as we work
[1:44:22] through that transition of density, you know,
[1:44:24] we envision that R two is going to be single family.
[1:44:26] Are the tracks c which was our three before,
[1:44:30] would be a mix of single fan blades attached and detached
[1:44:33] So not really kind of going to those higher R
[1:44:36] three zoning districts.
[1:44:38] I think the intent originally was to just have that transition
[1:44:41] on in the zoning, but I think we can accomplish what we
[1:44:43] want to do in the R two there.
[1:44:46] Then they change the the mixed use neighborhood
[1:44:49] commercial is is similar here.
[1:44:51] And then this piece up here, which
[1:44:53] is tracks i think they're G and F
[1:44:56] are changed from the mixed use regional commercial
[1:45:00] to the mixed use neighborhood commercial.
[1:45:03] We have a slate modification that we would like you
[1:45:04] to consider and that is moving that regional commercial down
[1:45:08] to that southeast corner of the site.
[1:45:11] The reason that we're asking for that
[1:45:13] is there's a specific use in that zoning district.
[1:45:15] And I touched on a little bit which is the indoor outdoor
[1:45:19] recreation, the mixed use neighborhood commercial has it,
[1:45:23] but it is capped at an 8,000 square foot.
[1:45:26] One of the thoughts is that as the high school developed
[1:45:30] in the towers were very instrumental in getting
[1:45:32] that project through the process and dedicating
[1:45:35] the ground for it, they were hoping to have a facility that
[1:45:38] could support full year round training that would help
[1:45:44] the high school athletes and other athletes
[1:45:46] in the in the region.
[1:45:48] We understand that there are concerns about that zoning
[1:45:51] district up against the existing residential that happens
[1:45:55] on the north side of the railroad tracks
[1:45:57] We think that moving it down here
[1:45:58] is probably a better fit for that location
[1:46:01] So we'd ask you guys to consider that option as you're approving.
[1:46:06] Hopefully approving the application
[1:46:08] to So a quick overview of the preliminary plat there.
[1:46:13] We have the tracks that are laid out.
[1:46:15] Those zoning colors match the original application.
[1:46:19] We do have zoning caps on tracks,
[1:46:21] air density caps not density, but max number
[1:46:23] of unit caps on tracks A, B and C,
[1:46:26] and you can see those there 175 units on tract A
[1:46:30] that ends up being 4.6 dwelling units.
[1:46:32] The acre maximum of 165 on track B that would be 4.9.
[1:46:37] Dwelling needs to the acre and a max of 184.
[1:46:40] That's eight dwelling units.
[1:46:41] The acre on track C tracks d E f and g.
[1:46:45] Those are a little less certain right now.
[1:46:47] So we're not proposing any standards there
[1:46:49] I think will be back in front of you
[1:46:51] for a preliminary on all of those parcels
[1:46:53] as we work through the process and kind
[1:46:55] of understand how those mixes work better in the future.
[1:46:59] Landscaping trails you guys had a question for Aubrey
[1:47:01] about that, so I'd love to talk about it a little bit
[1:47:04] So we do have complete street lights,
[1:47:07] tree lined streets there would be built in phased
[1:47:10] as the development goes So, you know,
[1:47:13] we wouldn't be building streets that
[1:47:14] are going to be empty for a substantial period of time.
[1:47:17] We want to get those streets built
[1:47:19] at the time of adjacent development
[1:47:22] But, you know, we have a pond up here in the south east corner
[1:47:26] of Tract a that would be a detention
[1:47:28] pond in a non-potable pond.
[1:47:31] So we would have a nonprofit system
[1:47:32] that would run all of the outdoor irrigation
[1:47:34] for the entire development, both serving all
[1:47:36] of the common open spaces but also serving
[1:47:39] the individual houses as well.
[1:47:42] This yellow line represents kind of the regional trail that
[1:47:46] is called out in Your Trails master plan
[1:47:48] So it doesn't necessarily directly
[1:47:49] connect to the high school, but we
[1:47:50] do have plans to kind of integrate
[1:47:52] through the track developed meant to make those connections
[1:47:55] to the high school.
[1:47:56] We do want to be kind of deliberate about how
[1:47:59] we're tying the development into the high school.
[1:48:00] We don't really want these, let's say,
[1:48:03] porous barriers between them.
[1:48:05] We want to have specific points of access
[1:48:07] So we've identified one that is right up here that would come
[1:48:11] from tract A into the the high school
[1:48:14] And then I think all the other access points are going
[1:48:16] to come from the South Really.
[1:48:18] We don't want to have you know, as kids come out,
[1:48:21] we don't want them filtering into the development.
[1:48:24] I think we just want to have like very clear points of access
[1:48:27] where the development interfaces with high school.
[1:48:30] I have a little cross section here of what the swale is.
[1:48:34] So i forget to mention that there
[1:48:36] is an existing long tail water ditch that comes
[1:48:38] through the property here.
[1:48:40] This is the existing alignment of it.
[1:48:42] We're going to really line that to kind of be a little bit more
[1:48:46] friendly to the character of the neighborhood Also, it helps.
[1:48:50] There's kind of some significant slopes that come from 46
[1:48:53] down into that drainage.
[1:48:54] So kind of moving that a little bit to the north
[1:48:56] helps even all that out.
[1:48:58] So there would be a trail corridor
[1:48:59] with the gates constructed when that ditch gets realigned.
[1:49:03] This is kind of a cross section of what that would look like.
[1:49:05] So there would be a ten foot concrete
[1:49:06] trail on the South side, trees on both sides.
[1:49:11] There's a 41ft bus bottom to that swale because it does take
[1:49:16] a substantial amount of storm drainage
[1:49:18] as well as the water that's in the in the ditch right now.
[1:49:22] If I were to draw that out, the trees would look super tiny
[1:49:26] in this cross section.
[1:49:26] So we just kind of like a abbreviated it.
[1:49:28] But you can see, you know this is
[1:49:30] about 20ft here on this bench.
[1:49:33] So ten foot of trail.
[1:49:34] And then about ten feet of landscaping that that trail is
[1:49:36] going to kind of meander through that bench
[1:49:39] So it's not just kind of like a street alignment there
[1:49:42] but that kind of gives you a sense of, you know,
[1:49:44] double that space is going to be at the bottom
[1:49:46] of that ditch intersection.
[1:49:49] We are we spent a lot of time talking about this
[1:49:50] at the neighborhood meeting so I wanted to make
[1:49:52] sure that it was included here.
[1:49:54] The Blue Stars represent right in, right
[1:49:55] out access points The Red Stars represent full movement assets,
[1:49:59] access points.
[1:50:01] I think, there's a red star on the roundabout at Roosevelt
[1:50:05] right now at the intersection of 46 and Colorado boulevard.
[1:50:10] We're anticipating there might be another either
[1:50:11] a signal or a roundabout there.
[1:50:13] We're working through that kind of as we go into final design,
[1:50:16] these intersections that are set on 46 are kind
[1:50:20] of at the standard intersection spacing
[1:50:23] So you can see that we've got 660ft
[1:50:25] to that First access point.
[1:50:26] That's going to be a right in right out your full movement
[1:50:29] intersections have to be that 13 20
[1:50:32] or a quarter of a mile separation
[1:50:33] from the major intersections.
[1:50:35] So then you can see as we go through,
[1:50:36] we're just kind of hitting that same rhythm of 13, 20
[1:50:39] plus or minus a little bit and then
[1:50:41] we will be building Roosevelt, the extension,
[1:50:43] Roosevelt over to the east.
[1:50:45] So that will be ready for future development.
[1:50:47] Is that next parcel comes through infrastructure.
[1:50:51] A water and sewer service would be provided by the town.
[1:50:54] The developer will build the infrastructure dedicate
[1:50:56] to the town just like all the other developments will have
[1:50:59] a non portable water system that serves
[1:51:00] the open space and the lots.
[1:51:03] That non-potable system is proposed
[1:51:05] to be operated by a metropolitan district
[1:51:06] just so there's some security about how that operates
[1:51:11] Neighborhood compatibility We talked a little bit about you
[1:51:14] know, what's appropriate against the existing residential.
[1:51:17] So there are 30 foot require landscape
[1:51:19] buffers from all arterials.
[1:51:21] And then there's density transitions and setbacks.
[1:51:23] So we kind of worked the density transitions through that zoning,
[1:51:26] but as well there are setbacks that are used,
[1:51:29] determined setbacks that would happen at the time
[1:51:32] of individual sightline.
[1:51:33] So between residential and commercial,
[1:51:35] between commercial and industrial,
[1:51:37] between independent uses that are conflicting,
[1:51:40] your land use code does a great job of just describe
[1:51:43] what those buffers need to be Construction and bathing.
[1:51:51] So we will phase the development.
[1:51:52] So we're not going to build everything at first.
[1:51:55] And you know but there'll be critical infrastructure
[1:51:56] that needs to be built in.
[1:51:59] We'll work we're starting to work on the final plat
[1:52:01] and construct construction drawings,
[1:52:03] and those will include the phasing.
[1:52:04] So each piece will be you know, as the first piece comes in,
[1:52:09] there'll be supporting infrastructure that that serves
[1:52:11] that everything that's required They're
[1:52:13] going to be based, developed, based
[1:52:15] on market demands and timing.
[1:52:16] So we don't have like we're not breaking ground
[1:52:18] like in a certain time And then but we do think, you know,
[1:52:23] it's possible.
[1:52:24] We would be starting construction,
[1:52:25] probably in in the summer of 2027
[1:52:29] schedule next steps we did have neighborhood
[1:52:31] meeting on May 12th.
[1:52:32] As I mentioned, we had the planning commission a couple
[1:52:35] of weeks ago on July 8th.
[1:52:36] We're here today, July 20, which is the town board hearing.
[1:52:40] And then we'll be making a final plat submittal shortly
[1:52:42] after this hearing And I'm here to answer
[1:52:47] any questions you might have about the development.
[1:52:49] Lee and John are also available if you guys have questions
[1:52:51] that I can't answer.
[1:52:54] Thank you.
[1:52:54] Covered a lot of the nuts and bolts, as Lee put it.
[1:52:57] So the answer my question to the trails
[1:52:59] because I know it's very important to the community
[1:53:02] I don't have any further questions I'll kick it over
[1:53:05] to council for any questions Do you know
[1:53:10] which plat you'll do first?
[1:53:13] It's anticipated that the single family
[1:53:16] will probably happen first.
[1:53:17] The upper left?
[1:53:19] Yeah, probably a or A or B, I mean, probably.
[1:53:23] I think a there's some things that happened
[1:53:25] with on a like the nine part system
[1:53:27] that really make that required at the beginning
[1:53:30] you could develop a nonpartisan them and not the rest of GI
[1:53:33] tract A but right now it looks like tract eight would probably
[1:53:35] be we would start kind of on the east the northeast ways
[1:53:40] and move to the west.
[1:53:40] Yeah.
[1:53:41] OK.
[1:53:41] Thank you So as far as that phasing is concerned.
[1:53:47] Then, because you said that you wouldn't necessarily
[1:53:50] make all of those improvements to roadways
[1:53:52] and you would clearly have to make that extension Are you
[1:53:59] saying you just wouldn't implement the north south roads
[1:54:04] then through cD any correct.
[1:54:08] Yeah Yeah.
[1:54:10] You know, yeah, the Roosevelt extension would have to go
[1:54:13] through right There would need to be some other second point
[1:54:15] of access that would come up to tract
[1:54:18] a whether that's an emergency access easement or a 4th Street.
[1:54:21] I think we're still working through kind of what
[1:54:23] those phasing details would look like I think that, you know,
[1:54:29] there's a possibility that there's
[1:54:30] some synergy between tract A and tract B
[1:54:32] and maybe some of that stuff gets built in kind
[1:54:35] of a consecutive phase Thanks.
[1:54:41] What's feeding that pond?
[1:54:42] Is it a spring over there, or just does it.
[1:54:46] Keep pretty good levels of water because it's
[1:54:48] not exactly by the swale that you're mentioning?
[1:54:51] No.
[1:54:52] So that would be fed with raw water.
[1:54:55] That's currently be used for irrigation
[1:54:58] on the site so the egg water that's being used there.
[1:55:01] OK.
[1:55:02] Thank you Any further questions from Council?
[1:55:08] Mr. All right.
[1:55:10] Thank you.
[1:55:10] With that will go ahead and open up public comment for anybody
[1:55:14] who's for against the application
[1:55:16] This is your time to come up and speak
[1:55:18] Would anybody like to speak for or against the application
[1:55:22] or All right.
[1:55:25] Nothing heard.
[1:55:25] We have anything online, Megan?
[1:55:28] No comments online.
[1:55:29] Thank you Before we close out the public hearing,
[1:55:32] would Council like to take any further deliberation
[1:55:37] on these this resolution and ordinance before us
[1:55:39] tonight All right.
[1:55:42] Nothing her with that.
[1:55:44] We'll go ahead and close up.
[1:55:45] You got some yourselves, Mr. Mayor.
[1:55:46] May I make one ask one question of the applicant in case
[1:55:49] you all decide to go with their revised proposal
[1:55:53] I'm reading it just for purposes of the motion.
[1:55:55] If the council decides to go with your proposed revisions
[1:55:59] that tract G and F would change to Amu and c tract E
[1:56:05] would be new.
[1:56:06] R C and tract C would be are two.
[1:56:10] That's correct.
[1:56:11] OK.
[1:56:12] Thank you so that's the approval with conditions
[1:56:15] is what you're asking for to bring
[1:56:17] that commercial down, correct?
[1:56:19] Yeah.
[1:56:19] I think there's the initial application.
[1:56:22] There's the conditions that were set by the Planning Commission
[1:56:25] and then we kind of have given you a Third option
[1:56:35] Any further questions for we close out the public hearing
[1:56:40] All right.
[1:56:40] We're going to close out the public hearing of a I'll
[1:56:44] go ahead and ask the pleasure of the Council of resolution number
[1:56:47] 2026 dash three five Five 2952 I move to approve ordinance
[1:56:58] So I move to approve orton's 2026 DoorDash 35 for the White
[1:57:03] tail filing number to preliminary plat
[1:57:05] as presented Second motion by Councilmember
[1:57:12] Berg, seconded by Council.
[1:57:15] Merman's is going to put it to electronic vote.
[1:57:17] Please I have a motion carries with that clerk.
[1:57:25] Can I have you read the ordinance title for 70 audience
[1:57:36] number 2020 6-2 94 Approving the rezoning of real property known
[1:57:41] as White House Subdivision and filing number two located
[1:57:44] on the East have at the southwest corner and south east
[1:57:47] corner of Section 12 Township four north Range 68 west
[1:57:52] of the six principal meridian town of Johnstown county, well,
[1:57:55] state of Colorado consisting of approximately 163.39 acres from
[1:58:01] planned unit development mixed use puti at Amu to mixed density
[1:58:06] neighborhood are two high density neighborhood
[1:58:09] are three mixed use neighborhood commercial m u c and mixed use.
[1:58:15] Regional commercial m u r c And if I could just before you all
[1:58:20] deliberate and decide how to vote
[1:58:21] just for clarity of the record.
[1:58:23] So the ordinance that was presented
[1:58:25] reflects the initial application by the applicant for planning
[1:58:31] and Zoning Commission recommended
[1:58:33] a modification and the applicant can is now
[1:58:37] proposed the third alternative of which I
[1:58:39] believe is a compromise.
[1:58:40] So you may just consider that if you're going to move to approve
[1:58:47] the ordinance as presented, it's going
[1:58:48] to be the original application Or if you
[1:58:50] want that ordinance amended somehow, just let us know.
[1:58:53] And then we can Amanda for a second reading OK.
[1:59:00] You go in as opposed to council Mr. Mayor,
[1:59:05] I move to approve ordinance number 2026
[1:59:08] to 95 to White House filing.
[1:59:09] Number two, rezone with the following conditions as
[1:59:14] stated in the recommendations as presented by the developer
[1:59:17] today.
[1:59:20] Second motion by Councilmember burke,
[1:59:22] seconded by Councilmember Come, put it
[1:59:24] to vote, please Ayes have it.
[1:59:31] Motion carries with that we'll go ahead and open our next
[1:59:34] public hearing ordinance 2020 6-295 An ordinance establish
[1:59:39] a temporary moratorium on the data center facilities
[1:59:42] in the town of Johnson And I'm going
[1:59:44] to ask for a staff report Good evening, Mayor and council.
[1:59:48] Hope we're all doing well this evening.
[1:59:50] Before you do have ordinance number 2026 dash 295.
[1:59:57] The result of the work session that we conducted with the town
[2:00:02] council staff conduct with the town council
[2:00:07] to actually discuss data centers and begin
[2:00:10] the educational and informational process
[2:00:12] related there to the moratorium that is presented to you.
[2:00:17] I would establish a 12 month moratorium piggybacking
[2:00:22] on the committee that was established we would utilize
[2:00:28] the committee together for information or staff would be
[2:00:32] providing them with information to evaluate the alternatives
[2:00:36] related to a data center I would note that once a policy is
[2:00:42] established, whether that is to establish form
[2:00:45] or a full prohibition on related to data
[2:00:49] centers or something that does permit data centers at that time
[2:00:55] in the 12 month moratorium would cease to exist if, for whatever
[2:01:00] reason that committee desires to collect additional information.
[2:01:05] And that goes beyond the 12 month period,
[2:01:07] we would bring something back that would continue to extend
[2:01:10] that moratorium until a date certain or until the committee
[2:01:15] actually is completed Staff does recommend approval of Ordinance
[2:01:20] 2020 6-2 95 as presented on first reading
[2:01:27] Happy to answer any questions you
[2:01:28] might have I'm only questions.
[2:01:31] I think we've hammered is pretty hard in the working
[2:01:34] meeting and I in support of the one year moratorium.
[2:01:37] But I'll open it up to Council for deliberations or questions
[2:01:43] you may have for Matt Matt, does the year
[2:01:46] start after second reading?
[2:01:49] Yes.
[2:01:51] So actually the year would start after the effective date,
[2:01:55] which is Seven days after the second reading.
[2:02:00] So that would be roughly August 10th.
[2:02:03] Sounds about right.
[2:02:04] Thank you.
[2:02:06] You Any other council comments or questions other All right.
[2:02:18] With that, we'll go ahead and open public comment.
[2:02:21] We'll start off with Angela Swanson Good evening, Mayor.
[2:02:30] Council members and staff, Thank you for the opportunity
[2:02:33] to speak tonight.
[2:02:35] While data centers can drive economic investment,
[2:02:38] even mid-scale facilities bring profound, complex challenges
[2:02:41] that need rigorous local oversight
[2:02:44] This type of development risks straining
[2:02:46] our city's resources and land.
[2:02:48] So I believe it is in john's town's best interest
[2:02:51] to put in place a lengthy moratorium or even a ban.
[2:02:54] So our city leaders can do the work
[2:02:56] and research including following up on what's happening.
[2:02:59] And other cities that have already adopted
[2:03:01] these across the nation.
[2:03:03] While the moratorium provides necessary time for research,
[2:03:07] it could also include establishing long, robust zoning
[2:03:10] and protections to put an actual center in place
[2:03:14] So I guess my primary concern is the potential for the moratorium
[2:03:18] to end prematurely, and the public not fully be
[2:03:21] aware due to all the time that has passed specifically,
[2:03:25] I'm wondering what public notice and hearing standards
[2:03:27] will apply if that occurs.
[2:03:30] Will local hearing notification remain
[2:03:32] standard to our already set rule of ten days prior to a hearing ?
[2:03:37] Or will we make more of an effort to ensure the public has
[2:03:40] the genuine seat at the table?
[2:03:41] Obviously, some of these questions
[2:03:43] have been answered tonight because I do believe the step
[2:03:46] to form the advisory committee would be helpful,
[2:03:48] but only in gathering that large of a body of research.
[2:03:51] Because when it comes to voting, the actual decisions
[2:03:55] are made at the hearings by the governing body in place.
[2:03:58] I've been in my own neighborhood meeting
[2:04:00] where everyone in attendance was against something
[2:04:02] and the motion passed anyway I'm not insinuating that this is how
[2:04:05] it always goes, but this has been what I've experienced
[2:04:08] and it was very discouraged Judging as far
[2:04:10] as influence and advocacy goes.
[2:04:13] Ultimately I'd like to see our notification
[2:04:15] practices on larger decisions like this
[2:04:18] improved to be beyond standard.
[2:04:20] I believe current practices leave residents
[2:04:23] to be the ones to that must actively monitor how
[2:04:26] this situation unfolds especially
[2:04:28] over the period of a year A thorough review
[2:04:32] process through a moratorium is a necessary and honorable
[2:04:35] first step.
[2:04:36] But staying informed and engaged is the next and much harder
[2:04:40] step for our community at this point.
[2:04:42] I guess my message switches over to my fellow residents
[2:04:46] in that regardless of serving on tonight's proposed committee
[2:04:50] or not, we all have to stay vigilant,
[2:04:52] keep each other in the loop and i ask that we dig really, really
[2:04:56] deep when it comes to using our collective resources and skills
[2:05:00] to keep tabs on what happens next going forward So
[2:05:03] thank you Thank you.
[2:05:05] Thank you We have Suzanne and Black next, please Hello.
[2:05:18] Thank you for letting me speak.
[2:05:19] I hadn't really planned on saying anything.
[2:05:23] I've lived in Johnstone for 29 years.
[2:05:26] Lots of changes in that time.
[2:05:28] I've raised children here, but things
[2:05:32] that I've noticed in the last few years
[2:05:33] are very concerning to me.
[2:05:34] Regarding town government and most recently this issue
[2:05:40] that's at hand.
[2:05:41] But I wanted to personally ask if anybody on this committee
[2:05:46] has personally signed any NDA or any agreement,
[2:05:50] any private communication, such as meetings,
[2:05:53] phone calls, private messages, emails with any developer
[2:05:56] company landowner, land owner or representative
[2:05:59] regarding any current or potential project.
[2:06:02] The good affect the town of John's town
[2:06:04] or surrounding areas in any negative way.
[2:06:09] No Nobody going to mention anything.
[2:06:11] OK.
[2:06:12] All right.
[2:06:12] I just The mayor ran on transparency
[2:06:15] and I don't feel like that always happens.
[2:06:18] So I just wanted to make that clear
[2:06:20] that those are things that we are very concerned about.
[2:06:23] Thank you.
[2:06:24] Thank you.
[2:06:26] Next up is Dana Karcher.
[2:06:29] Rodger So, sure, if I say that correctly Mayor, Mayor Pro
[2:06:36] Tem Council members and staff.
[2:06:38] My name is Dana Karcher I live at 6 to 3.
[2:06:41] Charlotte Street in regards to the ordinance
[2:06:44] before you tonight I believe it is
[2:06:45] really disrespectful to the citizens of Johnstown.
[2:06:48] And it's timing and wording and this is something
[2:06:51] that I've witnessed before is a disrespect towards the citizens
[2:06:54] who are out here talking about something that they do not want
[2:06:59] to develop, an ordinance that would change
[2:07:00] the very face of our community based on the fact
[2:07:02] that as soon as the fact finding is done,
[2:07:05] something could be rushed through Now,
[2:07:08] this may change with this committee idea,
[2:07:10] but the fact of the matter is this is not one year,
[2:07:13] this is what gets done first.
[2:07:14] And we need to quit saying it's one year.
[2:07:16] It needs to be One year or longer.
[2:07:19] So the wording town attorney is incorrect.
[2:07:22] Also, it's very loose and we could be sued on that.
[2:07:26] Or you could be sued on that very easily.
[2:07:29] We all know that Councilman bashford has said publicly
[2:07:33] that he is against any ordinance that brings up a moratorium
[2:07:36] for anything in this community.
[2:07:38] We haven't even heard what the community thinks yet about this.
[2:07:42] So I believe it's disrespect for.
[2:07:44] I'd like to see it reworded so that it actually
[2:07:47] says one year and beyond.
[2:07:48] So that we can actually find out what this is
[2:07:51] going to do to our community.
[2:07:52] Thank you Thank you Pauline, can have you come up.
[2:08:00] I'm not going to try to say your last name
[2:08:03] because I butchered every time out of respect
[2:08:09] Pauline Emilio Migliore.
[2:08:10] 337.
[2:08:11] Granite Way I urge the Council to approve
[2:08:15] the ordinance for the moratorium and here's why.
[2:08:19] Johnstown is a distinctive community,
[2:08:21] and we, the people who call it home possess
[2:08:23] immense pride in our town.
[2:08:25] We celebrate our pride are proud to agricultural heritage.
[2:08:31] It's welcoming family friendly atmosphere and local values.
[2:08:36] Johnstown abounds with beautiful repair
[2:08:38] and areas open, spacious and vistas of the front range.
[2:08:42] It's a natural canvas that sets the town
[2:08:44] apart and invites people to slow down
[2:08:47] and take it all in open space.
[2:08:49] TrailHeads rest areas along the trails, parks
[2:08:52] create creekside areas.
[2:08:53] The johnstown Reservoir, our present natural opportunities
[2:08:58] where residents go to recharge recreate
[2:09:00] and connect with the landscape.
[2:09:02] We love.
[2:09:03] The guiding principles of community
[2:09:04] centeredness inclusivity, accessibility
[2:09:07] engagement, partnership.
[2:09:09] Collaboration and all of that good stuff
[2:09:11] is why i made Johnstown my home for the past ten years.
[2:09:16] So do these sound familiar?
[2:09:18] They're all direct quotes from the Johnstown Public Art Plain
[2:09:22] as you hear from citizens.
[2:09:24] This evening during the ordinance And yourselves.
[2:09:26] Ask yourselves, how can you logically square
[2:09:30] the careful work of the steering committee town staff, council,
[2:09:34] seated at the time of stakeholder interviews focus
[2:09:38] groups, community engagement, pop ups, community service
[2:09:42] steering committee workshops mapping charrette, and to town
[2:09:45] council sessions for a public arts program with a plan
[2:09:49] apparently developed outside Johnstown Charter
[2:09:52] Authority other words, help us understand
[2:09:56] why seeking community input for a public art plan
[2:10:00] requires Herculean effort.
[2:10:03] And this ordinance does not I urge you to approve
[2:10:08] the current ordinance, and I applaud the advice re committee
[2:10:12] being suggested tonight because it seems to me it's long overdue
[2:10:17] and a reaction to the feedback council
[2:10:19] has received recently rather than intentional planning.
[2:10:24] So please approve this.
[2:10:27] Get this committee seated and listen
[2:10:30] to the citizens of Johnstown.
[2:10:33] Regardless of what your preconceived desires are.
[2:10:37] Thank you.
[2:10:38] Thank you Next up is Lisa Lang Thank you for having me, Mayor.
[2:10:52] Council and staff, town attorney I have something written down,
[2:10:59] but I was thinking as I was driving to this meeting
[2:11:02] a long time ago when I got here how beautiful the land is here
[2:11:07] and how I'm driving through it is so soothing
[2:11:13] that the the farms, the ranches, the little farm homes, the small
[2:11:22] coming through town and to miles an hour,
[2:11:25] you know, just the whole feeling of slowing down and taking
[2:11:29] a breath and enjoying the beauty that most of Colorado
[2:11:34] wishes they had.
[2:11:35] And they don't What we do here in Johnstown
[2:11:40] about data centers matters.
[2:11:45] This decision is bigger than just us These decisions are
[2:11:50] for our families, our children, our grandkids
[2:11:52] And they also may have serious impacts on surrounding cities
[2:11:56] and townships in our area along the Front Range
[2:12:02] But just because big tech is in a race
[2:12:05] for dominance control and big money
[2:12:06] doesn't mean that we're in that race.
[2:12:09] It's our responsibility to make choices that are best for us
[2:12:13] here in Johnstown and for our community
[2:12:16] There's time This will not be a one time only decision
[2:12:19] but will have lasting effects that may that we may or may not
[2:12:22] get a second chance to get right I do support a one year to 18
[2:12:27] month moratorium on any data center consideration
[2:12:31] and/or for as long as it takes for us to know, understand,
[2:12:35] and decide if data centers are right for us
[2:12:42] Time to create safeguards for our residents,
[2:12:45] for the power grid for our water resources our air quality.
[2:12:49] The noise alone would make anyone
[2:12:50] think more on the subject.
[2:12:53] We want to breathe clean air.
[2:12:54] We want to drink clean water We want to look at the stars.
[2:12:57] We want to enjoy Colorado for the beautiful state that it is.
[2:13:00] Perhaps these data centers need to be tested.
[2:13:02] Reviewed.
[2:13:03] Researched.
[2:13:04] They may need to evolve into something that makes more sense
[2:13:07] or has less negative impacts on our environment.
[2:13:10] You know, flying cars don't make any
[2:13:12] more sense today than they did in The Jetsons
[2:13:14] cartoons in the 1960s.
[2:13:16] The government literally tested the atomic bomb in Alamogordo,
[2:13:20] New Mexico So that doesn't make any sense either.
[2:13:23] The point is, we do not have to rush to a decision that may take
[2:13:27] forever that may forever change the landscape of our countryside
[2:13:31] and our lifestyle.
[2:13:33] I believe such decisions should be made
[2:13:35] by the people in our community.
[2:13:37] This is not a one man show.
[2:13:39] I thought you respect the council.
[2:13:42] The mayor have been elected by this community
[2:13:44] and are expected to be representatives
[2:13:46] of all your constituents and cities represent us.
[2:13:49] Put it to a vote to the Johnstone community.
[2:13:52] Let us have a choice in our future.
[2:13:54] And I do appreciate the comments and the resolution of bringing
[2:13:59] up a committee of residents.
[2:14:02] I'm not sure how that's going to look
[2:14:06] in the future I'm not sure how you're going to select people.
[2:14:09] I don't know if that's going to weed out or weed in biases.
[2:14:14] If we say we're for or against it,
[2:14:17] does that mean, we're out or in or whatever?
[2:14:20] I think that's an issue that probably needs
[2:14:22] to be thought about before any kind of PowerPoints
[2:14:31] or talking points.
[2:14:32] Who's going to be elected or who's going to be select
[2:14:35] voted to be on that committee.
[2:14:37] And I hope that the committee is is gets along and is able to get
[2:14:46] the information that we need.
[2:14:48] I think that we need to look at the data centers that
[2:14:51] are already underway that are built and that are functioning
[2:14:57] and see what the impact of the community you know impact
[2:15:02] of the centers have on the community
[2:15:04] And you brought up earlier Councilwoman Morris
[2:15:10] about the lawsuit, that lawsuit for 233,
[2:15:15] Bill in gallons of of water from the Imperial Valley,
[2:15:21] which the imperial Valley in California
[2:15:23] only received its water from the Colorado River.
[2:15:27] So this data center is One of the largest.
[2:15:30] It will be the largest in California.
[2:15:31] And yet, if it's built in the Imperial valley,
[2:15:34] it has now filed a lawsuit demanding access
[2:15:38] to 233 million gallons of water from the Colorado River
[2:15:45] Do we want to be those townships or the cities that are being
[2:15:50] attacked and lawsuits filed against us
[2:15:53] for the same situation Thank you for your time.
[2:15:56] Thank you, Lisa All right.
[2:16:03] With that, do we have any online public comment?
[2:16:07] Milton, can you do you have one online public comment?
[2:16:12] Let me put up One moment Comment was received from Jessica frey.
[2:16:24] 132 Jennings Lane and Johnstown According to his comments
[2:16:30] on Next Door, a post about Johnstown and data
[2:16:32] centers Nick Bashford has already decided he
[2:16:35] will vote no on the moratorium.
[2:16:37] To quote him directly, I have a lot of experience
[2:16:40] in all of this, enough to advise on smart policy.
[2:16:43] I hope the rest of council and the Mayor
[2:16:45] will listen to the people of Johnstown and their concerns.
[2:16:47] First.
[2:16:48] At the work session last week, no one from the council or town
[2:16:51] staff could say whether the water needed for cooling
[2:16:54] has to be portable.
[2:16:55] When asked whether there was data on the number of gallons
[2:16:58] needed for a closed loop system, the town staff
[2:17:01] explained they could not find sources
[2:17:03] they felt were factual enough to include them
[2:17:05] in their presentation and so that information
[2:17:07] wasn't provided by them.
[2:17:09] This is likely due to the Nda's municipality is required to sign
[2:17:12] as a condition of bringing datacentres to their communities
[2:17:15] which severely limits what's publicly
[2:17:17] known about these facilities.
[2:17:18] Impact on water supplies and power
[2:17:20] grids It should concern everyone that these companies require
[2:17:23] an NDA to keep that information private and the town staff
[2:17:27] decide.
[2:17:27] Despite significant research, still could not
[2:17:30] find it for the work session.
[2:17:31] What's before you tonight is a request that the town do
[2:17:34] its due diligence and gather all available factual information
[2:17:38] before making a decision that will affect the community.
[2:17:40] Passing a moratorium.
[2:17:42] Given this body's responsibilities to
[2:17:44] the community, Fiduciary yes.
[2:17:46] But also public welfare and civic stewardship.
[2:17:48] I hope and expect that proper time will be given to ensure
[2:17:51] our community and the citizens who elected you are protected
[2:17:54] and that a quick decision isn't made without proper vetting.
[2:17:57] Thank you for your time.
[2:17:59] Thank you.
[2:18:00] With that will go and close out public comment before we
[2:18:02] close out the public hearing.
[2:18:04] This council want to deliberate further.
[2:18:08] Actually, I want to know if we can change the motion
[2:18:11] to include it to be one year.
[2:18:15] And when she said beyond So how about we say
[2:18:18] 1 to 2 years until we have the answers from the committee
[2:18:21] you suggested?
[2:18:23] Can we change that to where that's on there?
[2:18:25] If you read it carefully in Section three,
[2:18:29] what it says is 12 months, unless you adopt,
[2:18:33] decide you want to adopt standards
[2:18:35] ahead of time which you can do.
[2:18:37] If not, it's 12 months.
[2:18:38] And then it says the town council reserves the right
[2:18:41] to extend the moratorium if the town council determines
[2:18:44] at its discretion that additional time
[2:18:46] time is required to complete the regulatory process.
[2:18:50] So we could certainly change this to 18 months.
[2:18:53] If you want.
[2:18:54] But right now as it is 12 months,
[2:18:57] you will still have the opportunity in 11.5, 12 months
[2:19:01] to extend this if you want.
[2:19:02] This isn't foreclosing a longer moratorium.
[2:19:07] So you do whatever direction you all want to go Thank you.
[2:19:11] Obviously, the language already supports if we want
[2:19:13] to come back and extend it out.
[2:19:15] Perfect Anything further from council?
[2:19:19] No nothing further on this topic.
[2:19:21] I do want to bring up one of the comments,
[2:19:23] and I can only speak for myself.
[2:19:25] I was brought up.
[2:19:26] Did anybody you know, I can say emphatically no that I am not
[2:19:30] on in the contract paid supported by have anything
[2:19:35] to any developer or any business that's
[2:19:39] moving to Johnston Somebody stole the words out of my mouth.
[2:19:43] Those part of my closing comments
[2:19:45] So I go on the record to there's no NDA out there.
[2:19:48] There's no secret contract, there's no conspiracy theory,
[2:19:51] there's no application before the town.
[2:19:53] Sometimes as a leader you have to be forward thinking You know,
[2:19:56] that's kind of the hard part.
[2:19:57] Being a mayor, period.
[2:19:58] You got to look 30 years ahead.
[2:20:00] And how we're going to keep this town protected along with
[2:20:03] grow smart growth.
[2:20:05] So, you know, I want to record there's nothing before us
[2:20:08] tonight and there's no NDA that I've signed or seen or allegedly
[2:20:12] signed So you're welcome with that Anything further
[2:20:16] from council?
[2:20:17] I'll also add myself to that list.
[2:20:19] And that I have not talked to any developers
[2:20:21] about data centers at all either I'll follow up.
[2:20:26] I have not sign anything I don't get Anti Kickback for anything.
[2:20:30] Look at my bank statement.
[2:20:33] It's pretty sad.
[2:20:35] Yes yes, yes.
[2:20:37] Well, I mean, being the mayor's a tough gig.
[2:20:39] We get 185 bucks to work in meetings.
[2:20:41] So it's not a I call it my a part time full time job.
[2:20:45] You know, it takes a lot of peer to answer a lot of citizens
[2:20:47] questions And I may not get it right every time
[2:20:49] but at least try to make myself available to hear everybody
[2:20:53] out and give some kind of outlet to give you guys a voice back,
[2:20:58] you know, because when we started transpo RNC up here,
[2:21:02] you know online public comment wasn't read.
[2:21:04] You had three minutes to speak.
[2:21:06] Now you have five.
[2:21:06] An online public comment is here.
[2:21:08] And if I can answer your questions or get them answered,
[2:21:12] I'll get them answered here.
[2:21:13] I may not get it the first time here.
[2:21:14] Maybe some follow up or follow through.
[2:21:16] But hey, so minimum stay on top of me
[2:21:18] because I get a lot of emails.
[2:21:20] I answer a lot of people back and folks who mailed in that
[2:21:23] were against the data center.
[2:21:24] I took the time to email each and every one of you back,
[2:21:27] and if I missed you I apologize.
[2:21:29] But I get a lot of emails So it's a it's a tough job up here.
[2:21:34] Sometimes, but sometimes you got to be the good guy,
[2:21:36] the bad guy or the neutral guy because, you know,
[2:21:39] I'm representing 20,000 residents up here So I got
[2:21:42] to I got to work for everyone.
[2:21:44] Everyone's my boss here, whether you know it or not.
[2:21:46] So thank you, Dave.
[2:21:48] You know I worked for a lot more people than everyone,
[2:21:53] so I work for everyone You know Yeah.
[2:21:58] How about we just keep the conjecture down a little bit.
[2:22:02] And let's Let's keep it.
[2:22:04] Let's keep it even flush with everybody.
[2:22:07] I think we've respected you interrupt.
[2:22:09] You've had your cell phone back for an extended period.
[2:22:11] Well, that's fine.
[2:22:12] That's my time up here as a mayor.
[2:22:13] You're welcome to run for a city council or town council whatever
[2:22:17] you find your time to serve best up here and give your ideas
[2:22:21] and your conjecture We have elections in 2028,
[2:22:24] so you're welcome to come forward and put your put
[2:22:28] your name and face out there and tell us what you're about
[2:22:30] and represent your community.
[2:22:32] We recommend that come forward.
[2:22:35] I like to see more participants in the community step forward.
[2:22:38] Hey, when i got into this business, I never
[2:22:42] been a politician.
[2:22:43] I was a military guy for 20 years.
[2:22:44] And folks who they need a little bit of change.
[2:22:46] But you know what?
[2:22:47] I'm gonna go throw my hat in the ring
[2:22:48] and, hey, you can call it ugly.
[2:22:50] Good bad, ugly.
[2:22:52] You got to have tough skin up here.
[2:22:53] We're not going to get everything right tonight.
[2:22:56] But I think we've listened to the citizens
[2:22:58] and we got an ordinance before us to really do some research
[2:23:02] and dig into this and give you guys voice back.
[2:23:04] And I think that's what's the most important piece tonight.
[2:23:07] So with that, I'll go to ask if there's anything
[2:23:08] further from the council for I close out the public hearing
[2:23:10] on All right.
[2:23:13] Nothing further.
[2:23:14] I'm going to go ahead and close out the public hearing
[2:23:16] and I'll go ahead and make the motion to adopt ordinance number
[2:23:19] 2020 6-295 on first reading, Establishing a temporary
[2:23:24] moratorium on the data center facilities in the town
[2:23:26] of Johnstown, which prohibits the town from accepting
[2:23:29] applications, are engaging in precedent or activities for data
[2:23:32] center facilities for a period of 12 months from an effective
[2:23:35] date of the ordinance.
[2:23:36] Second motion by myself seconded by Council member Morris
[2:23:41] was go and put it to electronic.
[2:23:43] OK So in the read ordinance title, first, Thank you, Mayor.
[2:23:46] You know, to myself Ordinance number 2020 6-295.
[2:23:50] An ordinance establishing a temporary moratorium
[2:23:52] on data center facilities in the town of Johnstown.
[2:23:57] Thank you.
[2:23:57] With that, I'll go ahead and put the electronic vote
[2:24:05] I thought the ayes have it motion carries.
[2:24:07] Thank you, everybody, for coming out tonight.
[2:24:09] With that, we're going to move into council comments.
[2:24:12] I'll go and start off with council member means is
[2:24:16] i think my group chief Oglesby where are we with the weed
[2:24:28] mitigation ordinance that we passed or have we been issuing
[2:24:32] citation and No, but we have.
[2:24:41] We did turn your Mike on Sorry.
[2:24:45] That's okay.
[2:24:47] Yeah They've been working very hard on the weed situation.
[2:24:50] But I can't give you a direct number right now.
[2:24:52] OK Because obviously, with the drought weeds,
[2:24:56] weeds, love drought.
[2:24:57] I wish grass, love, drought but weeds love drought.
[2:25:01] OK I know.
[2:25:06] I'm going back to a topic that nobody wants to talk about,
[2:25:09] but have any matt or Mitzi have any of the maintenance
[2:25:16] repair items that we brought up to Dr. Coker on our 622 meeting.
[2:25:23] Been fixed or have they presented bids to repair
[2:25:29] the things that were shown?
[2:25:31] Because Dr. Coker indicated that he would look into it right away
[2:25:38] Mayor and council I'd have not received nine communication
[2:25:42] regarding that, but I will check into that this week
[2:25:45] and let me know at the end of the week Also,
[2:25:51] Mr. Levinson mentioned that the to her 2025 audit of the why
[2:25:58] was delayed due to the vacation of the auditor,
[2:26:01] and he said that it would be forthcoming after he returned
[2:26:06] from he or she returned from vacation
[2:26:09] So it's been almost a month.
[2:26:11] Do we have the audit marion Council We have not received
[2:26:17] the audit at this time.
[2:26:19] And I notice that the June financials
[2:26:22] are not in the packet.
[2:26:23] So we have not received those as well from the mayor and council.
[2:26:29] Those were received on Friday some time, maybe.
[2:26:35] I don't recall exactly what time,
[2:26:38] but the packet was already distributed on Thursday
[2:26:41] as it normally is Right.
[2:26:44] OK Councilmember Morris you have mentioned many times
[2:26:50] that your role on the board of the YMCA
[2:26:53] is to improve the communication between the town and the Y.
[2:26:57] So i would like to ask if it would be possible for you
[2:27:00] to give us a report, a monthly report from the board meetings
[2:27:05] and what's happening.
[2:27:07] And I think it's it's important that we have
[2:27:11] this line of communication, but we haven't heard from you
[2:27:16] since you've been on the board of what goes on
[2:27:19] in their meetings and Well, I have mentioned at least once,
[2:27:22] but we had some meetings that were canceled.
[2:27:25] And then I recently aligned with Brittany since she's taken over
[2:27:30] and she's going to be giving me reports
[2:27:32] every month so that I can do it.
[2:27:34] I was suggesting on the second meeting of the month,
[2:27:37] we did not have one in the last month because of barbecue days.
[2:27:42] So that is so coming.
[2:27:46] What do they what do they they meet
[2:27:48] the first Friday of every month, first Friday at 730
[2:27:51] in the morning.
[2:27:52] And so did they not meet in July either on that?
[2:27:57] Is that the one that I did not go to?
[2:27:59] Yeah, I did not go to that one.
[2:28:00] I had staff in or family in town and we were
[2:28:04] preparing for barbecue days.
[2:28:05] So I did not barbecue days is in June.
[2:28:08] I'm asking about July.
[2:28:09] Oh, June, July seven.
[2:28:12] But it just be a similar report that any other like the library
[2:28:19] board submits their meeting minutes
[2:28:21] Could we just ask that the YMCA would submit that same data?
[2:28:27] I'm fine with that.
[2:28:28] I just mean, if we are really trying
[2:28:31] to improve our communicate and I think it's important to know
[2:28:34] what the board is discussing.
[2:28:36] I mean, I come with my behavioral health.
[2:28:38] I mean, we don't meet, we meet quarterly.
[2:28:40] So it's, you know, it's not a monthly situation
[2:28:43] but I think it's important for all of us that serve on a board
[2:28:47] to bring that to council.
[2:28:50] So that we know what's happening And I just would, you know,
[2:28:54] I know the is a hot topic right now.
[2:28:57] And I think that it's important for us
[2:28:59] to keep the line of communication open
[2:29:02] and know what's going on there.
[2:29:04] And then they know what's going on here.
[2:29:06] I agree.
[2:29:07] And I've asked in the past from Pat
[2:29:10] and I think just the transition between Pat and Britney
[2:29:13] and all the time last summer that there were cancellations
[2:29:16] of meetings because of staff being on vacation
[2:29:21] and then also the whole entire topic of the why
[2:29:24] has kind of been in front of us.
[2:29:25] So I didn't think they had anything specific extra
[2:29:29] that they needed to discuss.
[2:29:30] But I have already put that in place.
[2:29:32] And she's going to be getting me a report every month.
[2:29:35] And then it'll be I'll, I'll talk
[2:29:37] about it at my council meetings on the second meeting
[2:29:40] of the month.
[2:29:41] Okay That's great.
[2:29:42] Thank you.
[2:29:43] That's all I have.
[2:29:43] Thank you, Mayor.
[2:29:45] Councilmember Burke.
[2:29:46] Nothing's reported this time Cast member Morris.
[2:29:52] So I just wanted to thank everybody for coming out
[2:29:56] and for the passion that you have for this town and the love
[2:30:00] that you have for this town and everything that you've said.
[2:30:02] I know that there was a lot of outbursts of happiness and joy
[2:30:06] for some comments and i understand that.
[2:30:09] And it it's when you really are passionate about something,
[2:30:13] it's hard to not let that out.
[2:30:15] So I do want to thank everybody and for that
[2:30:18] as well And we're going to be studying this with these folks.
[2:30:24] And hopefully learning more.
[2:30:25] All of us.
[2:30:26] And then I wanted to ask why we're
[2:30:29] here about the why I'm not sure if it's Matt that I ask you.
[2:30:33] Can you really permission for the YMCA
[2:30:36] to be able to talk to the auditor
[2:30:38] since they have agreed to pay for half of the audit.
[2:30:41] So they can discuss the numbers that were incorrect?
[2:30:45] So we can get this finalized?
[2:30:47] I know that they did meet Mitzi and the CFO
[2:30:51] and they were wanting to try to get that negotiated and there
[2:30:57] was I asked about the question, speaking of the information
[2:31:00] from the way i did end up asking him
[2:31:03] if they figured out what the number was Because if we
[2:31:06] remember correctly when they came before us marks that there
[2:31:08] was an exact number on this spreadsheet
[2:31:10] out to the dollars and cents that had
[2:31:14] to be wrong because you can't come
[2:31:15] up with that same exact number.
[2:31:17] So I think that for all intents and see that we be
[2:31:21] able to let them talk to them.
[2:31:23] So that they can question and figure out what
[2:31:25] it is that might be missing or that might be in error.
[2:31:29] So we can come to a final dollar amount.
[2:31:31] And get this put behind us Is that possible So Mayor
[2:31:37] and council the full funds of 35,000 associated
[2:31:42] with the audit have been fully expended There is no more money.
[2:31:48] So if I if they want to talk to the auditors
[2:31:53] they would need to engage contractually with i Bailey
[2:31:58] to continue that process So they're not.
[2:32:04] So they're the auditors are not allowed
[2:32:05] to talk to them about mistakes or not mistakes
[2:32:09] that they made in the audit.
[2:32:11] So so the hours allocated for that contract have been expended
[2:32:16] probably above and beyond that isn't to say that they probably
[2:32:21] couldn't talk to the auditors but they
[2:32:23] would need to go under contract themselves
[2:32:25] to actually have to pay for it.
[2:32:29] Bailey To continue services, if that was something I'd.
[2:32:32] Bailey wanted to continue forward with, OK Brittany,
[2:32:36] can you pass that information along?
[2:32:38] OK I just was curious why they cannot if they truly made
[2:32:43] a mistake you think you'd be able
[2:32:45] to ask someone about that mistake
[2:32:47] without having to pay for it?
[2:32:48] That that's just my you know, being naive about an audit.
[2:32:52] I've never been audited.
[2:32:53] So that was an exit for me.
[2:32:56] And then we also have the upcoming course of my brain
[2:33:00] just went completely blank.
[2:33:01] But upcoming neighborhood night out
[2:33:04] with the Y and tPR and the town is going to be involved in that
[2:33:09] still.
[2:33:10] What date is that ?
[2:33:12] Friday night at Nelsen Park.
[2:33:14] Thank you.
[2:33:15] You Thank you.
[2:33:18] Councilmember Morris.
[2:33:19] Councilmember Bashford I have a couple topics for tonight
[2:33:26] First, we're going to talk about the letter
[2:33:28] that never reached us Mayor, fellow council members
[2:33:31] and neighbors At our last meeting
[2:33:33] I told you nearly every concern that
[2:33:35] was raised in 2017 about our way and see a partnership
[2:33:39] has come true.
[2:33:40] And I quoted it from the record to show it tonight.
[2:33:43] I want to tell you about one document from that record
[2:33:46] that most of this council has never seen I want to tell you
[2:33:49] about it because the way it was handled then
[2:33:51] is the same problem we're living with now at 1047 on the night
[2:33:56] of March fifth, 2017 15 days before this council selected
[2:34:01] the YMCA, a detailed written warning
[2:34:04] arrived in a former council member, Gary Leib Sachs inbox.
[2:34:07] It came from former employees and members
[2:34:10] of the YMCA of Boulder Valley, and it was not a rant.
[2:34:13] It was specific It described an organization carrying roughly
[2:34:17] $800,000 in debt, talked about nepotism,
[2:34:20] and described a culture where leadership reported
[2:34:23] in their words, quote, favorable numbers while, quote,
[2:34:27] only a select few have regular eyes on the core fiscal reports
[2:34:31] Five minutes later, that same anonymous
[2:34:33] sender sent it to former council member Troy Mallon.
[2:34:37] And that's where it appears to have stopped.
[2:34:39] Two of the seven members of the council received that warning.
[2:34:42] That letter never appears in the March 20th 2017 council packet.
[2:34:47] It's never mentioned in the minutes in the files
[2:34:50] I've reviewed.
[2:34:51] There's no email.
[2:34:52] The former mayor Scott James knob forward
[2:34:54] to staff no reply, no discussion and no verification
[2:35:00] 15 days later, council voted to enter a partnership
[2:35:03] with that organization and it's possible
[2:35:06] that three of the four members casting that vote
[2:35:09] had no idea the wording existed It's important to note
[2:35:13] that former council member Loebsack voted yes,
[2:35:16] while former council member Mellen recused I want
[2:35:21] to be careful and fair here.
[2:35:22] I can't prove that no one ever mentioned
[2:35:24] it in the hallway conversation.
[2:35:26] I can only tell you what the record shows which
[2:35:29] is that a written specific firsthand warning
[2:35:31] about our partner fiscal transparency reached the council
[2:35:35] and evaporated before it could inform the decision.
[2:35:39] And I would ask you to sit with that.
[2:35:41] With what that letter predicted.
[2:35:43] Favorable numbers, few eyes.
[2:35:46] The total difference between the town YMCA
[2:35:48] and his numbers is $211,546.62.
[2:35:54] The people that wrote that letter in 2017
[2:35:56] were not making up stories They were witnesses.
[2:36:00] And here is why that is not just history The failure in 2017
[2:36:05] was not that.
[2:36:05] No one no knew Someone always knows the failure was
[2:36:10] that our institution had no way to make sure that what one
[2:36:13] member, Neil all members, Neil and colleagues
[2:36:17] I would gently ask you are we confident that
[2:36:20] has changed when fiscal discrepancies surfaced today?
[2:36:24] Does every member of this council
[2:36:26] see them at the same time in the same form
[2:36:29] in the packet on the record?
[2:36:31] Or it is critical information about this partnership
[2:36:34] Still travel person to person arriving
[2:36:36] at some desks and not others shaping
[2:36:39] some votes and not others.
[2:36:42] Tonight I have a few asks First, a standing policy
[2:36:46] that any communication to any council member concerning a town
[2:36:49] contract or a vendor or a proposed contract
[2:36:51] or a vendor, whether it arrives by email, letter or handshake
[2:36:56] is logged and distributed to the full council
[2:36:58] and included in the record before any vote
[2:37:01] regarding the contract or a vendor redacting
[2:37:03] any personal information.
[2:37:05] If the sender wishes to be anonymous Matt Naveh,
[2:37:09] could you please draft something up for council
[2:37:11] to discuss at another meeting Might ensure
[2:37:19] I'm following the direction.
[2:37:20] Are you at four for clarity?
[2:37:29] What you're asking for is every communication
[2:37:34] that we have with an outside vendor
[2:37:36] that we have a contract with that we communicate
[2:37:41] the discussions that we have with those vendors with council
[2:37:45] as well.
[2:37:46] I'm saying if it's possible something that a council member
[2:37:50] received that it shared with the rest of council,
[2:37:53] if it could have anything to do with a vote that could be
[2:37:57] upcoming, it would be difficult in the sense
[2:38:01] that you're asking staff to start going through all council
[2:38:04] member emails.
[2:38:06] I mean perhaps you will want to discuss
[2:38:08] a policy among yourselves were if you want to forward it
[2:38:13] to staff, we can distribute it Could there
[2:38:18] be some kind of maybe if it's not possible to have a policy,
[2:38:23] could it be something that the Council agrees that all of us
[2:38:26] would be, you know, willing to forward on to everybody.
[2:38:30] So that a situation like this doesn't happen again?
[2:38:33] Do you mind if I ask a question?
[2:38:35] Sure.
[2:38:36] So i know that we've gotten letters that
[2:38:38] have went into our junk mail.
[2:38:41] I found in a letter from a resident in my junk mail.
[2:38:44] How do you know that Mayor Loebsack or Mayor Pro
[2:38:48] Tem or Troy Mullen how do you know
[2:38:52] they even got those letters?
[2:38:54] Because it was in their inbox So they at least in the it
[2:38:56] was in or in the junk they at least
[2:38:59] received it in their email Yeah, but that's what I'm saying.
[2:39:02] I've gotten we got all of the council members
[2:39:05] got a letter from a fake person and i did not
[2:39:09] see it until I was asked by someone else,
[2:39:12] Did you see the email?
[2:39:14] And I said, No, I never got it.
[2:39:16] And then i went in my junk and found it So some sometimes
[2:39:21] your junk delete stuff.
[2:39:22] If you don't go in there fast enough.
[2:39:24] Right.
[2:39:25] Isn't it set up like that So I'm just curious
[2:39:30] because I on the policy.
[2:39:31] I don't know how that works, but I know that all of council
[2:39:34] at least got that community.
[2:39:35] Jason Well, that's why it was available for all of council.
[2:39:38] People should write council at Johnstown Coker
[2:39:41] and it goes to every single person
[2:39:44] So it i don't know how to keep stuff out of the junk,
[2:39:47] but I'm just saying I don't know how you can say that.
[2:39:50] They saw it because you don't really have proof of that.
[2:39:54] And that seems and they're not here to defend themselves.
[2:39:56] I didn't I said that at least two inboxes got it.
[2:39:59] I didn't say they got it.
[2:40:00] And they that's what I meant.
[2:40:01] I didn't say that.
[2:40:01] That's what I'm asking.
[2:40:02] What if they never saw it?
[2:40:04] I mean, it's alluding to that, again,
[2:40:05] that something was not that was shady
[2:40:07] when we don't know that, again, that's
[2:40:10] okay That's all I'm saying.
[2:40:11] That's all my question was, if I could add a small point
[2:40:14] to theirs, as you all very well Now,
[2:40:16] I believe there's a difference between a quasi judicial and
[2:40:19] legislative actions and citizens are certainly
[2:40:22] allowed to reach out when it comes to more
[2:40:25] of a legislative type of decision, which this probably
[2:40:28] was at that point So I'm not sure whether that here nor there
[2:40:34] as to your request, I think if council wants
[2:40:36] to make a decision to share all their emails they certainly can.
[2:40:40] If you decide to do that rather than start replying
[2:40:44] all and the potential to create a meeting,
[2:40:48] you could for them if you got an individual email,
[2:40:51] you could forward it to Matt or Megan However, the protocol gets
[2:40:56] established and asked that that be added to a packet.
[2:40:58] If you get an individual email and you
[2:41:00] wanted that into a packet, that could be done.
[2:41:02] I would like to formally request my email be deleted completely.
[2:41:05] I don't want to go through all those emails.
[2:41:07] I'm just saying I'd rather not get any,
[2:41:12] but i put my number out there multiple times on the breeze.
[2:41:16] Add on one ad that was on there, I
[2:41:19] would rather someone call and talk to me about any issues.
[2:41:23] We got so many emails regarding this topic.
[2:41:25] It is a lot.
[2:41:26] So not that we don't read them, but to try to reply to everybody
[2:41:30] and then if things go in the junk
[2:41:32] and we don't get back to Bobby Sue,
[2:41:34] then Bobby sue thinks we ignored her.
[2:41:36] When we did not.
[2:41:36] It was in junk and it possibly got deleted.
[2:41:39] That's all I'm saying So I don't know how you're
[2:41:41] thinking this might work, but.
[2:41:42] OK, that's all.
[2:41:43] I'll bring something up at a different time than about it.
[2:41:46] I just.
[2:41:46] Let's find out.
[2:41:47] But second, I would like to ask now that the 2017 letter has
[2:41:52] surfaced that it be formally entered
[2:41:53] into the record of this council Nine years late.
[2:41:56] So that's finally where it should have been transferred
[2:41:58] Parent The people who wrote the letter signed it
[2:42:01] as former employees and members of the why,
[2:42:04] they had nothing to gain.
[2:42:05] They wrote to a small town that they had never
[2:42:07] lived in because they believed we deserved to decide
[2:42:10] with our eyes open to people possible We opened
[2:42:13] and read that email tonight.
[2:42:15] We can finally finished delivering it.
[2:42:17] And I also want to make a pledge tonight that letter surfaced
[2:42:20] online a few weeks ago.
[2:42:21] And while some dismissed it as a disgruntled employee
[2:42:25] I saw it as someone who cared enough to speak up.
[2:42:27] They chose to stay anonymous.
[2:42:29] And I understand why coming forward is never easy
[2:42:32] no matter where you work Strong organizations
[2:42:35] welcome honest feedback.
[2:42:37] That's true of the best towns, the best companies
[2:42:40] and the best partnerships.
[2:42:42] So tonight, I want anyone connected
[2:42:43] to the town of Johnstown through any of its contractors
[2:42:46] or vendors to know this.
[2:42:47] If you ever have information you believe should be heard,
[2:42:51] I'm here to listen.
[2:42:52] I will help protect your identity.
[2:42:53] If that is your concern.
[2:42:55] Speaking up in good faith should never come at a personal cost
[2:42:59] And hey, anyone out there who has already faced retaliation
[2:43:02] for speaking up, I'm sorry that happen
[2:43:05] And I know where you're coming from.
[2:43:07] Stay strong and keep up the good fight because you will prevail.
[2:43:11] And I'm glad I listened when concerns were
[2:43:13] raised about the rec center, because listening
[2:43:15] is how we get better.
[2:43:16] That is my commitment to anyone out there weighing
[2:43:19] whether to come forward.
[2:43:20] My door is open I will listen and I
[2:43:23] will help in any way I can.
[2:43:25] I'm not making a motion tonight I will be submitting it
[2:43:28] in writing and I am asking that it be placed on the August 3rd
[2:43:31] agenda under new business A motion to amend our june 22nd
[2:43:35] direction by striking the clause asking
[2:43:38] the town to work to amend the damage
[2:43:40] and reputation of the YMCA.
[2:43:43] And let me be clear about what my ask is.
[2:43:46] The partnership continues the direction to staff to negotiate
[2:43:50] continues.
[2:43:51] The 90 day cap is untouched and it does not leave a silent
[2:43:55] about how people are treated because the amendment replaces
[2:43:59] that clause with a directive that public communication
[2:44:03] regarding our operating partner be factually
[2:44:06] accurate and consistent with our audited financial reporting
[2:44:10] and that town staff and YMCA employees be
[2:44:13] treated with respect and professionalism
[2:44:16] in every public forum.
[2:44:18] What changes is one thing this council would stop officially
[2:44:22] certifying without a hearing and without a finding
[2:44:25] that the concerns raised about this partner
[2:44:27] were false because as this 2017 letter shows,
[2:44:32] concerns about the organization existed long before anyone
[2:44:35] in Johnstown ever raised them.
[2:44:37] And some of what we were told was
[2:44:39] false has since been confirmed by our own audit You will
[2:44:42] each have the full text in their packet
[2:44:45] after I send it to RB for review with time
[2:44:47] to read it before you're asked to vote.
[2:44:49] And that is the standard that i'm asking the Council to adopt
[2:44:54] And then I want to explain tonight.
[2:44:59] Why I voted no on the moratorium Everyone who has concerns
[2:45:03] tonight, they are valid concerns.
[2:45:06] However each one of those could be addressed in smart policy.
[2:45:10] Each one is measurable limits can be set with strict policies
[2:45:13] for failing to adhere to those policies.
[2:45:17] Policy can be written that protects the town.
[2:45:19] The resident and the way of life that we all
[2:45:21] enjoy Oh, my mind is not made up on what
[2:45:24] needs to exist in the policy.
[2:45:27] My mind is made only made up that we
[2:45:29] need a policy over what we have now and that is nothing.
[2:45:33] I ran on conservative beliefs.
[2:45:35] I believe in small government I believe that government should
[2:45:38] set guardrails to make sure everyone's playing fairly
[2:45:41] and that the town and resident are protected.
[2:45:43] But I am not a fan of overreaching regulations
[2:45:47] and saying, no, even pausing is government overreach no matter
[2:45:51] what the topic is I believe the council can protect
[2:45:55] the town by creating good policy and some policies
[2:45:59] need to be continuously updated Second,
[2:46:03] it's council's job to have open eyes, open ears and open hearts.
[2:46:07] Anyone who runs for council should
[2:46:08] love where they live and want what's best
[2:46:10] for our town over themselves.
[2:46:13] They should be impartial.
[2:46:14] Look at the facts and make fair judgments
[2:46:17] and absolutely explain why they voted the way they did Council
[2:46:21] only works if there is trust transparency and accountable
[2:46:25] city No one person can push something through It
[2:46:30] takes a majority vote and that's why there's seven of us.
[2:46:33] Good members of council are lifelong learners They do
[2:46:36] their homework by researching and investigating all aspects
[2:46:40] of a particular topic as best as they can Each council member
[2:46:45] represents all 22,000 residents, not just the residents that we
[2:46:49] want to represent I can't speak for everyone,
[2:46:52] but it's not always an easy job to do for myself.
[2:46:56] I read every email.
[2:46:58] I'm active on social media I give full attention
[2:47:00] to every public comment.
[2:47:02] So I'm listening I'm researching.
[2:47:04] And I spend a ton of time on this because I care.
[2:47:08] Some of us up here have kids and even grandkids and we all
[2:47:11] want to leave something great to them.
[2:47:13] The goal is to make Johnstown the place they
[2:47:14] want to live when they grow up.
[2:47:16] The ultimate goal is to make anyone who wants to live here
[2:47:20] be able to live here and truly believe
[2:47:22] that Johnstown is the community that cares nothing further.
[2:47:27] Thank you, Mayor Pro Tem.
[2:47:28] You know report tonight.
[2:47:29] Thank you Thank you.
[2:47:31] Mayor Pro tem.
[2:47:32] Yeah, I before I jump into my speech,
[2:47:35] Commissioner always be can we get with Mr. York
[2:47:37] and see how we can fix that radar
[2:47:40] problem that he brought up?
[2:47:41] And also, if we can get a, you know, a big scare crowed Mr.
[2:47:46] York, because he's a big guy.
[2:47:46] I've never seen in person before.
[2:47:48] And maybe to scare those weeds away,
[2:47:50] I think that would be great But thank you for the comments
[2:47:53] and bringing that to us tonight I really appreciate that.
[2:47:56] All right.
[2:47:56] With that, before we adjourn, I like
[2:47:58] to leave everyone with one final thought tonight
[2:48:01] We heard different perspective.
[2:48:03] And that's the very nature of a representative government
[2:48:05] government.
[2:48:06] Our responsibility as elected officials
[2:48:08] is not to chase every opinion or every moment,
[2:48:11] but to listen respectfully, deliberate, thoughtfully make
[2:48:15] decisions.
[2:48:15] We believe will best serve the long term interests of
[2:48:17] the entire johnstown community.
[2:48:19] Leadership is tested most when opinions differ,
[2:48:23] and those moments our duty is to remain steady,
[2:48:25] to uphold public trust, and to continue
[2:48:27] moving the community forward with integrity
[2:48:29] humility and purpose.
[2:48:32] Tomorrow, the work continues Our police officers will
[2:48:34] answer the calls for service.
[2:48:36] Our firefighters and first responders
[2:48:38] will stand ready Our public works crew will maintain
[2:48:41] our streets and infrastructure.
[2:48:43] Our staff will continue serving our residents
[2:48:45] with professionalism and dedication
[2:48:46] to their quiet, consistent work is what
[2:48:49] keeps this community strong.
[2:48:50] And I want to thank every town employee
[2:48:52] for their unwavering commitment an unwavering
[2:48:55] commitment to public service.
[2:48:57] Before we leave tonight, I ask that we pause and remember
[2:49:00] the 17 American service members who
[2:49:01] have given their lives for the ongoing conflict in Iran.
[2:49:05] As a retired Air Force member, I know
[2:49:06] that behind every name is a family forever changed Brothers
[2:49:10] and sisters in arms carry immeasurable loss
[2:49:14] and a nation forever indebted to their sacrifice
[2:49:17] Their courage reminds us of the freedoms we enjoy,
[2:49:19] even the freedom to gather in this chamber, to debate openly
[2:49:22] and to disagree respectfully have always come at a price.
[2:49:27] Let us honor the memory not only with our words,
[2:49:29] but with how we serve one another.
[2:49:31] May we lead with humility?
[2:49:33] Treat one another with dignity and never lose sight on the fact
[2:49:36] we are blessed to call this country our home.
[2:49:38] And this community, our own.
[2:49:40] Thank you to my fellow council members
[2:49:42] for your service to our staff, for your dedication
[2:49:45] and to every resident who took the time to participate
[2:49:48] this evening May God bless the families of those who have made
[2:49:51] the ultimate sacrifice Watch over the men and women serving
[2:49:54] around the world tonight and continue
[2:49:56] to bless the town of Johnstown, the great state of Colorado,
[2:49:59] and the United states of America.
[2:50:01] Thank you, everyone Have a safe evening.
[2:50:04] That's it for me tonight on this of closing comments With that,
[2:50:08] we'll go ahead and move into executive session an executive
[2:50:13] session to discuss the purchase of acquisition,
[2:50:15] lease transfer or sale of any real person or personnel
[2:50:20] or other property interest percent
[2:50:21] this year as 20 4-6-424 alpha.
[2:50:25] With that I'll go and I suppose you the counsel moved.
[2:50:31] I'll second it motion by Council member Burke seconded by myself.
[2:50:36] What's go and put it to voice vote.
[2:50:38] All in favor say aye.
[2:50:39] Aye Aye all oppose Ayes have it We're
[2:50:41] in executive session number I'm the way of relating All right.
[3:12:24] We're back in session No other topics were
[3:12:27] discussed or voted on tonight.
[3:12:28] We're adjourned And no decisions were made